12
Hg System Status V.B. Graves P.T. Spampinato Muon Collaboration Friday Meeting October 20, 2006

Hg System Status V.B. Graves P.T. Spampinato Muon Collaboration Friday Meeting October 20, 2006

  • View
    215

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Hg System Status V.B. Graves P.T. Spampinato Muon Collaboration Friday Meeting October 20, 2006

Hg System Status

V.B. Graves

P.T. Spampinato

Muon Collaboration Friday Meeting

October 20, 2006

Page 2: Hg System Status V.B. Graves P.T. Spampinato Muon Collaboration Friday Meeting October 20, 2006

2MC Friday Meeting 20 Oct 2006

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

Initial Water Testing Setup

A primary containment has been mocked up to allow initial water tests to be performed

Will be used to debug Labview control software and test some of the sensors

Remainder of syringe hardware scheduled for delivery week of Oct 23

Page 3: Hg System Status V.B. Graves P.T. Spampinato Muon Collaboration Friday Meeting October 20, 2006

3MC Friday Meeting 20 Oct 2006

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

Control System Connections

Most internal Labview wiring completed

Temporary wiring for sensors required for testing

Remainder to be completed upon delivery of wiring pkg from Princeton

At last review

Current wiring

Page 4: Hg System Status V.B. Graves P.T. Spampinato Muon Collaboration Friday Meeting October 20, 2006

4MC Friday Meeting 20 Oct 2006

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

Syringe Pump Performance Testing

Control system development complete based on water tests Minor modifications may be required after switch to Hg, but none are

expected Data logging incorporated

System can produce a 20m/s, 1cm-dia water jet Water test nozzle configuration approximately matches one of the two Hg

nozzles My opinion: jet quality looks good for a no-field condition. Holds together for

better than ~1/2m

Page 5: Hg System Status V.B. Graves P.T. Spampinato Muon Collaboration Friday Meeting October 20, 2006

5MC Friday Meeting 20 Oct 2006

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

Water Test 20m/s Screenshot

Page 6: Hg System Status V.B. Graves P.T. Spampinato Muon Collaboration Friday Meeting October 20, 2006

6MC Friday Meeting 20 Oct 2006

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

Load Testing of Common Baseplate & Target Cart

CERN Safety Commission voiced concerns regarding analysis performed on common baseplate design

Load test performed on structures to verify strength and test adjusting mechanisms

Estimated component weights Magnet: 12000 lbs (5440 kg) Hg system (with 23liters Hg): 4000 lbs (1810 kg)

Test weights Magnet: 13600 lbs (6170 kg) = 113% estimated weight Hg system: 4500 lbs (2040 kg) = 113% estimated weight

Page 7: Hg System Status V.B. Graves P.T. Spampinato Muon Collaboration Friday Meeting October 20, 2006

7MC Friday Meeting 20 Oct 2006

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

In Nominal Test Position Baseplate tilt ~ 66mrad

Elevation matches CAD models

Page 8: Hg System Status V.B. Graves P.T. Spampinato Muon Collaboration Friday Meeting October 20, 2006

8MC Friday Meeting 20 Oct 2006

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

Operational Testing

Lifting jacks and lateral position adjustment mechanisms tested

Page 9: Hg System Status V.B. Graves P.T. Spampinato Muon Collaboration Friday Meeting October 20, 2006

9MC Friday Meeting 20 Oct 2006

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

Roller Testing

Loaded baseplate pushed with pallet jack while on three Hilman rollers

Page 10: Hg System Status V.B. Graves P.T. Spampinato Muon Collaboration Friday Meeting October 20, 2006

10MC Friday Meeting 20 Oct 2006

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

Leveling Jack Testing

Baseplate adequately supported by four leveling jacks

Page 11: Hg System Status V.B. Graves P.T. Spampinato Muon Collaboration Friday Meeting October 20, 2006

11MC Friday Meeting 20 Oct 2006

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

Conclusions

Syringe pump control system development completed

System can produce 20m/s water jet within pump's performance limits No reason to think Hg will be different

MERIT common baseplate has been successfully tested with 113% expected loading

Final assembly and optics integration to commence shortly

Switch to Hg will be made once all operational aspects of system have been tested with water

Page 12: Hg System Status V.B. Graves P.T. Spampinato Muon Collaboration Friday Meeting October 20, 2006

12MC Friday Meeting 20 Oct 2006

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

Conclusions

Manual control of syringe demonstrated

Hydraulic system fill and drain procedures developed

Hg control system wiring is underway, water tests to start afterwards

Ready for Hg testing after conclusion of water tests and when remainder of fabricated components available