Upload
aakashtrivedi
View
67
Download
11
Tags:
Embed Size (px)
DESCRIPTION
Understanding of HAZOP method
Citation preview
Periodic Hazard Review as an essential part of your PSM system
Gerry Brennan, Lead Principal Consultant, ABB Consulting / Piper 25 Conference June 18-20 2013
Periodic Hazard Review as an essential part of your PSM system
Contents
Process Safety Management
Need for periodic hazard review
Techniques: HAZOP vs HAZID
Learning points from experience of periodic hazard review
Process Safety versus Personal Safety
Major
Accident
Hazards
Slips, trips
and falls
Very
Unlikely
Possible
Process
Safety
Personal
Safety
What is Process Safety?
“The prevention of unplanned & uncontrolled loss of
containment from plant and process equipment that
might cause harm to people or the environment”.
Process Safety Management
Commit to Process Safety
Process safety culture
Compliance with standards
Process safety competency
Workforce Involvement
Stakeholder Outreach
Understand Hazards and Risk
Process knowledge management
Hazard Identification and Risk Analysis
Manage Risk
Operating Procedures
Safe work practices
Asset integrity and Reliability
Contractor Management
Training and Performance Assurance
Management of Change
Operational Readiness
Conduct of operations
Emergency Management
Learn from Experience
Incident Investigation
Measurement and Metrics
Auditing ▪ Management Review and Continuous Improvement Guidelines for Risk Based Process Safety, CCPS 2007
Learning
phase
Hardware wearout
Loss of corporate memory
Change in people
Creeping Changes in plant
Why is periodic hazard identification and risk analysis needed?
HAZOP Ongoing risk assessment?
Accident
Life of Plant
Plant
Safety
Performance
Objective for Periodic Hazard Review
Evaluate controls for the hazards of the process as they
are currently understood
because
Process changes have introduced new hazards
New knowledge on hazard consequences is available
Recent incidents have revealed new scenarios
Barriers previously credited have changed
HAZOP or HAZID?
Loss of
Containment
FAULT TREE EVENT TREE
HAZID
CA
US
ES
CO
NS
EQ
UE
NC
ES
Mitigation
Measures
Prevention/Control
Measures
HAZOP
Methodology
1. Split process into sections;
HAZOP node is a process line
HAZID node is unit operation, typically 1 or more P&ID’s
2. Describe design intent for node;
operating parameters
key aspects of process control system
protective systems, trips/relief's/bunds
3. Apply guidewords - can it happen?
4. Assess consequences - does it matter?
5. Assess design safeguards - are they adequate?
6. Agree actions required to reduce risk
HAZOP Guidewords (IChemE)
No (not, none)
More (more of, higher)
Less (less of, lower)
As well as (more than)
Part of
Reverse
Other than
Earlier/later than
With appropriate process parameter
Flow
Pressure
Temperature
Level
Concentration
Mixing
Etc.
Look for deviations from intent
HAZID Guidewords
Burst
Internal Explosion
Overpressure
Runaway Reaction
Puncture
Impact
Weakening
Corrosion
Wear
Temperature extreme
Openings
Vent/Drain
Overflow
Flange/Seal Look for causes of Loss of Containment
Comparison application to offshore installations
Re-HAZOP of UK and overseas platforms during 2010-
2013
Hazard Study Equivalent days per platform: 90-150
Recommendations for improvement: ~500
HAZID of UK Platforms during 2011-13
Hazard Study Equivalent days per platform: 15
Recommendations for improvement: ~100
Learning Points from experience of periodic hazard review
1. Write down clear Terms of Reference
Scope of review; what is included/excluded
Timescale; duration of commitment;
Team leader; competence
Hazard study team; essential disciplines
Method; guidewords, recording detail, recording tool;
stipulations about safeguards
Time required; hours of work; how many days per week?
Meeting room; lighting; space; projection; away from the
installation
Data Gathering; up to date PIDs, process information;
2. Specify the right team
Leader
Operations Manager Operator or Supervisor
Process,
Engineering /
Maintenance
Independent
Team Member
Other specialists as required
3. Choose process node carefully
HAZOP: line or vessel HAZID: system by system
4. Correct level of detail in records
Example of poor recording
GW Cause Consequence Safeguard Recommendation
No Flow Valve closed , etc Overpressure of Vessel XXXX Alarm and trip Consider pressure relief on
Vessel xxxx
Individual causes should be
detailed. Manual valve HVxxx
closed through human error, OR
Flow control failure FICxx, OR spurious closure
XV xxx
Sequence should be determined – Tell the ‘Hazard story’. No flow causing
build up in pressure – this will be slow as
feed is low at y m3/min.
Overpressure maximum up to 4x design, but as slow rate of pressure rise line leakage at 2 to 3x design. Release
of flammable substance into local process area. 1 to 2 fatalities if ignited – normal occupancy.
Separate safeguards.
Alarm response
detailed. Trip tags and actions.
“Consider” should be avoided. Should
detail HAZOP team concern – Normal design practice to
have pressure relief. Should be a review to determine if relief is required against
design requirements and protection
required to avoid fatality
consequences.
5. Recording: Can Link Hazop to bow tie
GW Cause Hazard Consequence Sev
erity
Safeguard L R Recommendation
6. Hazard Study Recommendations
Need to carefully word to avoid confusion
Person given action may not have been at the meeting
Use “what – where – why” format
“Add instructions for securing of double block and bleed isolations on the fuel gas supply line XYZ123 to the Burner 1-B-07 prior to maintenance into plant operating instruction 23, in order to protect against the flow of fuel into the burner and risk of explosion at start-up”
Limit the number of actions generated
Complete simple design checks before report is issued
Keep a separate list of observations for project team
7. Hazard study followed by LOPA
Hazard study provides the list of initial failures
and the risk screening to pick out significant
hazard scenarios
Layer of Protection Analysis (LOPA) provides
a more detailed risk estimate
Increasingly applied where there is a
significant consequence or a Safety
Instrumented Function
7 Cont: But there some points to bear in mind…..
Scope of LOPA: Only those with a SIF? Which severity level?
If HAZOP records are sketchy, lengthy discussion in LOPA is likely
Failure sequence not quantifiable: Must be an equipment or human failure
Poor: ‘Operator error’
Good: ‘Block valves HV1 and HV2 left closed after maintenance’
Poor logic in HAZOP: e.g. failure of a safeguard as ‘cause’
Failure to determine ultimate consequence and hence all safeguards
SIF can’t be identified as no tag number on HAZOP record
Also other safeguards, e.g. alarms, procedures, relief systems
LOPA is top down from hazardous event, HAZOP is bottom up from cause
Need to cross reference all causes in HAZOP record
8. “Evergreen Records” and revalidation programmes
Goals:
Accurate, current, detailed description of hazards and
safeguards available for reference in ORAs, MOCs
Reduce resources demanded for periodic process
hazard review
Method:
Update the periodic review record with
Recommendations Closures and risk assessment
results (such as LOPA);
Revalidate the periodic review of hazards, every 5
years
8 Cont.: Revalidation Method
Select first node
Ask the following questions
Have all the recommendations been completed?
Have the changes since the baseline Hazard Study been fully assessed?
Have there been any relevant process safety incidents, has the learning
from these been acted upon?
Are there any current concerns?
Is there any new knowledge or relevant good practice applicable to this
node?
In view of the above, does the hazard study need repeating?
Repeat over all nodes
Table updated and new recommendations in the revalidation report
© ABB Group June 19, 2013 | Slide 24
© ABB Group June 19, 2013 | Slide 24
QUESTIONS?