Gower Facility PlansDecember 18, 2012

Page 2: Gower facility plans final

Gower Middle Improvements

• 3 Science Classrooms—Grades 6, 7, & 8

• New Gym, Locker Rooms, Weight/Fitness Room

• Industrial Technology, Family & Consumer Sciences, and Art

• Lighting and Ceiling Tiles Updates

• Cafeteria Remodeled

• Athletic Fields

• Classroom Casework (cabinets and shelving)

• Entrance Vestibules at East and West Doors

• Improved Parking and Traffic Flow

Page 3: Gower facility plans final

Gower Middle: 2013 - 2014

Page 4: Gower facility plans final

Gower Middle Athletic Fields

Page 5: Gower facility plans final

Entrances

Page 6: Gower facility plans final

Gymnasium

Page 7: Gower facility plans final

Locker Rooms

Page 8: Gower facility plans final

Weight/Fitness Room

Page 9: Gower facility plans final

Science Classrooms

Page 10: Gower facility plans final

Industrial Technology

Page 11: Gower facility plans final

Industrial Technology

Page 12: Gower facility plans final

Family & Consumer Science

Page 13: Gower facility plans final

Family & Consumer Science

Page 14: Gower facility plans final

Art Classroom

Page 15: Gower facility plans final

Art Classroom

Page 16: Gower facility plans final

Gower West Improvement

• 2 Early Childhood Classrooms

• Removal of Asbestos Tile in East Classrooms

• Replacement of Flooring in East Classrooms

• Pavement Replaced on West Playground

• Fencing Added to West Playground

• Art Room Storage and Shelving

• Lighting and Ceiling Tile as Needed

Page 17: Gower facility plans final

Gower West 2013- 2014

Page 18: Gower facility plans final

Early Childhood Classroom

Page 19: Gower facility plans final

Early Childhood Classroom

Page 20: Gower facility plans final

Timeline

• January 14 Bid Invitations Published

• February 19 Bid Approval

• March 1 Excavation for GM Gym and Addition Begins

• March 25 Asbestos Abatement at GM

• June 3 Interior Work at GW & GM Begins

• September 1 Substantial Completion at GW & GM