GOVERNMENT OF GHANA
ELLEMBELLE DISTRICT ASSEMBLY
DRAFT
MEDIUM-TERM DEVELOPMENT PLAN
UNDER THE
GHANA-SHARED GROWTH DEVELOPMENT AGENDA
(GSGDA II) 2014-2017
PREPARED BY: DISTRICT PLANNING CO-ORDINATING UNIT (DPCU)
November 2014
2
Table of Contents GOVERNMENT OF GHANA ................................................................................................................. 1
EXECUTIVE SUMMARY .................................................................................................................................. 8
INTRODUCTION ............................................................................................................................................. 8
METHODOLOGY ............................................................................................................................................ 9
SUMMARY OF KEY OBJECTIVES ................................................................................................................... 11
INDICATIVE BUDGET ................................................................................................................................... 13
EXPECTED OUTCOME OF THE 2014 – 2017 DMTDP ................................................................................... 13
PERFORMANCE REVIEW.............................................................................................................................. 15
THEMATIC AREA: INFRASTRUCTURE AND HUMAN SETTELMENT DEVELOPMENT .................................... 18
Thematic Area: Accelerated Agricultural Modernization and Sustainable Natural Resource Management
.................................................................................................................................................................... 20
Thematic Area: Transparent & Accountable Governance .......................................................................... 27
Thematic Area: Transparent & Accountable Governance .......................................................................... 31
Thematic Area: Oil and Gas Development .................................................................................................. 33
Expenditure Pattern .................................................................................................................................... 35
1.2 ANALYSIS OF PERFORMANCE REVIEW ........................................................................................... 37
1.2.1 Accelerated Agricultural Modernization and Sustainable Natural Resource Management .............. 38
1.2.2 Oil and Gas Development ........................................................................................................... 39
1.2.3 Enhancing Competitiveness of Ghana’s Private Sector .............................................................. 39
1.2.4 Infrastructure and Human Settlements ...................................................................................... 40
1.2.5 Human Development, Productivity and Employment ................................................................ 41
1.2.6 Transparent and Accountable Governance ................................................................................ 41
1.3 OTHER INTERVENTIONS .................................................................................................................... 42
1.3.1 Tandan Bamboo Biomass Project ............................................................................................... 42
1.3.2 Ghana Social Opportunities Project (GSOP) ............................................................................... 42
1.3.3 Social Protection & Vulnerability Aspect of GSOP ...................................................................... 43
1.4 Gaps / Challenges Identified in the Implementation of the DMTDP 2010-2013 ........................... 45
Lessons learnt during implementation of 2010 – 2013 DMTDP ................................................................. 46
SCORING SCALE ........................................................................................................................................... 47
1.6 SUMMARY OF KEY DEVELOPMENT PROBLEMS .............................................................................. 49
1.5 DISTRICT PROFILE /CURRENT SITUATION OF THE DISTRICT .......................................................... 50
1.5.1 Physical and Natural Environment .............................................................................................. 50
3
1.5.2 Location and Size ........................................................................................................................ 50
1.5.3 Climate ....................................................................................................................................... 50
1.5.4 Relief and Drainage ............................................................................................................................ 51
1.5.5 Vegetation .......................................................................................................................................... 52
1.5.6 Soil Type ...................................................................................................................................... 52
1.5.7 Tourism ....................................................................................................................................... 53
1.5.6 Condition of the Natural Environment ....................................................................................... 53
1.5.7 Deforestation ............................................................................................................................. 54
1.5.8 Mining and Quarrying ................................................................................................................ 54
1.5.9 Bushfires and Soil Erosion ........................................................................................................... 54
1.5.10 CULTURE...................................................................................................................................... 55
1.5.10.1 Religion and Ethnicity ................................................................................................................ 55
1.1 Traditional Set-up ................................................................................................................................ 55
1.5.11 Culture and Festivals ................................................................................................................... 55
1.5.12 SPATIAL ANALYSIS / SETTLEMENT ................................................................................................... 56
Annex 2: Scalogram..................................................................................................................................... 57
1.5.13 Agriculture .................................................................................................................................. 58
1.5.13.1 Land ......................................................................................................................................... 58
1.5.13.2 Soils ......................................................................................................................................... 58
1.5.13.3 Cropping .................................................................................................................................. 58
1.5.13.4 Coconut Sector ........................................................................................................................ 58
1.5.13.5 Rubber ..................................................................................................................................... 59
1.5.13.6 Cocoa ....................................................................................................................................... 59
1.5.13.7 Poultry and Livestock Production ........................................................................................... 59
1.5.13.8 Fishing and Fish Farming ......................................................................................................... 60
1.5.13.8 Manufacturing Industry .......................................................................................................... 60
1.5.13.8 Energy ..................................................................................................................................... 60
1.5.13.9 Tourism ................................................................................................................................... 61
1.5.14 Transport Infrastructure ............................................................................................................. 63
1.5.15 Major Town and Facilities/Activities ........................................................................................... 64
1.6 Food Security.................................................................................................................................. 65
1.7 Governance ..................................................................................................................................... 65
DISTRICT DEPARTMENTAL ORGANOGRAM ................................................................................................ 67
4
1.9 Composition of the District Assembly ............................................................................................. 68
1.11 District Sub – Structure ................................................................................................................... 68
1.12 Traditional Authority ....................................................................................................................... 69
1.13 Administration of Justice ................................................................................................................ 70
1.14 NGO/Civil Society ............................................................................................................................ 70
1.15 7PRIVATE SECTOR ............................................................................................................................. 71
5.8 Assembly Finance .................................................................................................................................. 71
Problems of Revenue Collection ................................................................................................................. 72
Expenditure Pattern .................................................................................................................................... 72
1.16 Local Economic Development ......................................................................................................... 73
1.17 ACCESSIBILITY TO SOCIAL SERVICES ................................................................................................. 73
Educational Characteristics ......................................................................................................................... 73
1.1.2 ENROLMENT by Gender (2013/2014) ............................................................................................. 75
1.1.3 TEACHER POPULATION: trained & untrained (2013/2013) ............................................................... 75
1.17 Youth and Sports ............................................................................................................................. 76
1.18 HEALTH SITUATION ......................................................................................................................... 78
1.18.1 Health Structure ....................................................................................................................... 78
1.18.2 MAIN PROBLEMS OF THE HEALTH SECTOR IN THE DISTRICT ..................................................... 80
1.18.3 KEY ACHIEVEMENTS .................................................................................................................... 80
1.18.4 OPD CASES .................................................................................................................................. 81
1.18.5 Health Financing ......................................................................................................................... 82
1.19 Water and Sanitation ...................................................................................................................... 83
1.19.1 Water Facilities ........................................................................................................................... 83
1.20 VULNERABILITY ANALYSIS ............................................................................................................... 85
1.21 HIV/AIDS .......................................................................................................................................... 86
1.22 GENDER ........................................................................................................................................... 87
1.23 INFORMATION AND COMMUNICATION TECHNOLOGY (ICT) ......................................................... 88
1.24 SECURITY ......................................................................................................................................... 88
1.25 DISASTER ......................................................................................................................................... 88
1.26 WATER SECURITY ............................................................................................................................ 89
1.27 MIGRATION (IMMIGRATION & EMIGRATION) ................................................................................ 89
2.0 CHAPTER TWO ..................................................................................................................................... 90
2.1 Prioritization of Development Issues ............................................................................................... 90
5
OUTCOME OF COMMUNITY ENGAGEMENT FOR THE MTDP (2014-2017) ................................................ 90
AREA COUNCIL: NKROFUL ........................................................................................................................... 90
KIKAM AREACOUNCIL ................................................................................................................................. 92
ASASETRE AREA COUNCIL ........................................................................................................................... 93
AWIEBO-BASEKE AREA COUNCIL. ............................................................................................................... 94
ESIAMA AREA COUNCIL .............................................................................................................................. 96
AIYINASE AREA COUNCIL ............................................................................................................................ 98
ATUABO AREA COUNCIL ........................................................................................................................... 100
2.1.1 Prioritized development issues under the MTDPF 2014-2017 ...................................................... 102
2.2 POCC ANALYSIS ............................................................................................................................. 104
2.2.1 ENHANCING COMPETIVENESS IN GHANA’s PRIVATE SECTOR ..................................................... 104
2.2.2 ACCELERATED AGRICULTURE MODERNIZATION AND SUSTAINABLE NATURAL RESOURCE
MANAGEMENT.......................................................................................................................................... 108
2.2.3 Oil and Gas Development ......................................................................................................... 111
2.3.4 INFRASTRUCTURE AND HUMAN SETTLEMENTS DEVELOPMENT ............................................. 112
2.3.5 HUMAN DEVELOPMENT, PRODUCTIVITY AND EMPLOMENT ................................................... 115
2.3.5 TRANSPARENT AND ACCOUNTABLE GOVERNANCE ................................................................. 120
3.0 CHAPTER THREE ................................................................................................................................ 123
3.1 DEVELOPMENT GOAL, OBJECTIVES AND STRATEGIES ...................................................................... 123
DEVELOPMENT FOCUS .............................................................................................................................. 123
3.2 DISTRICT DEVELOPMENT GOAL........................................................................................................ 123
GSGDA II OBJECTIVES AND STRATEGIES ................................................................................................... 124
3.3 Formulation of Development Programmes .................................................................................. 134
3.4 CROSS CUTTING DEVELOPMENT PROGRAMMES ......................................................................... 141
3.5 LOCAL ECONOMIC DEVELOPMENT ............................................................................................... 141
3.6 Rural Enterprise Project (REP)....................................................................................................... 141
3.7 International Network for Bamboo and Rattan (IMBAR) ............................................................. 141
3.8 HIV/AIDS ............................................................................................. Error! Bookmark not defined.
3.9 CLIMATE CHANGE .................................................................................... Error! Bookmark not defined.
3.10 SOCIAL PROTECTION ..................................................................................................................... 141
3.11 ENVIRONMENT AND CLIMATE CHANGE ....................................................................................... 142
3.11.1 Ghana Wildlife Society .............................................................................................................. 142
3.11.2 ........................................................................................................................................................ 142
6
Coastal Sustainable Landscapes Projects (CSLP) ....................................................................................... 143
3.11.3 GREEN ECONOMY ..................................................................................................................... 145
CHAPTER 4 ................................................................................................................................................ 147
PROGRAMME OF ACTION ......................................................................................................................... 147
4.0 THEMATIC AREA: Human Development, Productivity & Employment ......................................... 147
Education. ................................................................................................................................................. 147
4.1 THEMATIC AREA: Accelerated Agriculture Modernization And Sustainable Natural Resource
Management. ............................................................................................................................................ 162
Agriculture ................................................................................................................................................ 162
4.2 THEMATIC AREA: Human Development, Productivity & Employment ...................................... 168
HEALTH DIRECTORATE. ............................................................................................................................. 168
4.4 THEMATIC AREA: Transparent and Accountable Governance. ................................................... 174
Non-Formal Education Division. ............................................................................................................... 174
4.5 THEMATIC AREA: Transparent and Accountable Governance. ................................................. 175
Internal Audit ............................................................................................................................................ 175
National commission for civic education .................................................................................................. 177
GHANA POLICE SERVICE ............................................................................................................................ 178
4.6 THEMATIC AREA: Infrastructure and Human Settlement Development ................................. 180
Water And Sanitation................................................................................................................................ 180
4.7 THEMATIC AREA: Infrastructure and Human Settlement Development .................................. 181
Road Infrastructure ................................................................................................................................... 181
CHAPTER 5 ................................................................................................................................................ 183
5.0 ANNUAL ACTION PLAN FOR 2014 ................................................................................................. 183
5.1 ANNUAL ACTION PLAN 2015......................................................................................................... 199
5.4 ANNUAL ACTION PLAN FOR 2016 ................................................................................................. 218
5.5 ANNUAL ACTION PLAN FOR 2017 ................................................................................................. 237
5.6 INDICATIVE FINANCIAL PLAN 2014 – 2017 ................................................................................... 256
4.10.1 Financial Control Mechanism ....................................................................................................... 257
Sector Budget from 2014-2017 ................................................................................................................. 258
CHAPTER 6 ................................................................................................................................................ 270
MONITORING AND EVALUATION .............................................................................................................. 270
6.1 Monitoring and Evaluation Arrangements ................................................................................... 270
6.1.2 Monitoring Report .................................................................................................................... 270
7
6.1.3 Monitoring Framework ............................................................................................................. 270
CHAPTER 7 ................................................................................................................................................ 273
COMMUNICATION STRATEGY ................................................................................................................... 273
7.1 Introduction ...................................................................................................................................... 273
7.2 Expected Roles/Responsibilities of stakeholders in the plan implementation .................................. 274
7.2.1 Ellembelle District Assembly ............................................................................................................ 275
7.2.2 Executive Committee ....................................................................................................................... 276
7.2.3 Sub-Committee ................................................................................................................................ 276
7.2.4 Decentralized Departments/Agencies ............................................................................................. 276
7.2.5 Chiefs, Opinion Leaders and Traditional Authorities ....................................................................... 276
7.2.6 Non-Governmental Organizations (NGOs)/ Development Partners ............................................... 276
7.2.7 Communities .................................................................................................................................... 277
7.3 Strategies for promoting dialogue/management of public expectations concerning services .......... 277
7.4 Conclusion ..................................................................................................................................... 278
8
EXECUTIVE SUMMARY
INTRODUCTION The Ellembelle District Assembly (EDA) was created in December 2007 by L.I. 1918 and
inaugurated in February 2008. It was carved out of the then Nzema East District, now Nzema
East Municipal. The District has undergone the implementation of two (2) Medium Term
Development Plan namely GPRS II (2006 – 2009) and GSGDA I (2014-2017), of which the former
was an adopted plan from the erstwhile Nzema East District Assembly now a Municipality.
During the previous planning regime, the EDA strategized to leverage the implementation of
the GSGDA I within the context of the strategies, objectives, as well as overarching goal of the
Government’s Comprehensive National Medium Term Development Policy Framework (2010 –
2013), referred to as, the Ghana and Shared Growth Development Agenda (GSGDA 1).
Despite its few years in existence, the District managed and complemented the national efforts
of achieving a middle income status with interventions geared towards job creation and
increased household incomes as well as general living condition of the people. The priority
areas were improved road network, improved sanitation conditions, improved access to safe
water, enhanced social services especially health and education, improved financial support,
farm inputs for both crop farming and fishing, and Employment creation, sub-structure
development, improved literacy level, gender equality and HIV prevention as spelt out under
the seven thematic areas of Priority namely Ensuring and Sustaining macroeconomic stability,
Enhancing Competiveness in Ghana’s Private Sector, Accelerated agriculture modernization and
Sustainable Natural Resource Management, Oil and Gas Development, Infrastructure, Energy
and Human Settlement, Transparent and accountable governance and Human Development,
Productivity, productivity and Employment
9
On the backdrop that the District was implementing its first MTDP, much as it tried to
improve the lives of the people through the implementation of the programmes and
projects in 2010-2013 DMTD Plans, it was confronted with a countless number of challenges
and constraints. Significant among these are inadequate and untimely release of
Government and Donor funds, limited Human Resources, low sub structures participation,
inadequate data for planning purposes, high cost of goods and services, inadequate internal
revenue among others.
Against this background, the District Assembly in consultation with its stakeholders has re-
aligned the strategies within the context of the Ghana Shared Growth and Development
Agenda (GSGDA 1) 2010-2013 to harness all facets of resources both internal and external
to implement programmes and projects with the view of complementing government’s
growth inducing policies and programmes under the following priorities and thematic areas:
1. Ensuring and Sustaining Macroeconomic Stability;
2. Enhancing Competitiveness of Ghana’s Private Sector;
3. Accelerated Agriculture Modernization and Sustainable Natural Resource Management;
4. Oil and Gas Development;
5. Infrastructure and Human Settlements;
6. Human Development, Productivity and Employment;
7. Transparent and Accountable Governance
In preparing this Medium Term Development Plan, the Ellembelle District in strict
adherence to the guidelines from the National Development Planning Commission (NDPC),
employed a series of planning workshops, meetings and community interface involving all
key stakeholders viz. community members, opinion leaders, Assembly members, NGOs,
DPCU members, political parties and the private sector. The draft plan was presented to the
General Assembly for popular debate and adoption in compliance with the NDPC guidelines.
METHODOLOGY A participatory process was used in preparing this plan. The processes were based on the
guidelines provided by the National Development Planning Commission in the preparation
of the 2014 – 2017 MTDPs. In the plan preparation process, the DPCU adopted a multi –
stage method used in plan preparation. These steps included:
10
1. DPCU meetings to discuss the objectives of the plan and to inform members of their
respective roles in the preparation and compilation of the plan.
2. Collection of data on existing situation, problems and plans of the decentralized and
centralized departments in the district.
3. Collation of Departmental information on the performance for the 2010 – 2013 DMTDP
based on the GSGDA 1.
4. Collecting community perspectives on current needs, levels of household income and
expenditure and aspiration of the sub- districts through participatory process.
5. Data collation using secondary sources of Data in addition to Institutional Surveys and
Interviews with target populations, validation and analysis, which involved holding two
workshops at Nkroful, the District Capital
6. Preparation of the draft DMTDP (2014 – 20117) document for public hearing
7. Public hearing on both draft plan and development options (spatial plans) conducted at
Nkroful with key stakeholders like DPCU, Spatial Planning Committee (SPC) and other
key departmental heads.
8. Presentation of first Draft to the general Assembly.
9. Submission of Draft Plan to NDPC for comments and corrections
10. Finalization of the plan document after the public hearing and Public hearing for the
adoption of the Draft Plan
This plan document consists of seven (7) Chapters as contained in the NDPC guidelines and
proceeded by the executive summary. These include:
Chapter 1: Performance Review /Profile/Current Situation/Baseline
Chapter 2: Development Priorities
Chapter 3: Development Goals, Objectives and Strategies
Chapter4: Development Priorities
Chapter 5: District Annual Action Plans
Chapter6: Monitoring and Evaluation Arrangements
Chapter 7: Communication Strategies
11
MISSION
The Ellembelle District Assembly exists to ensure the total development of the District
through effective management of resources in collaboration with Ministries, Department,
Agencies and Non-Governmental Organizations in order to improve the quality of life of the
people in the District.
VISON
The vision of Ellembelle District is to improve livelihood through Equitable Growth and
Sustainable development.
SUMMARY OF KEY OBJECTIVES - To improve access to quality social services in the District
- To harness environmental sustainability in development issues.
- To increase production and productivity in all sectors of the Local Economy
- To improve private sector participation in development.
- To enhance Institutional arrangement for sectoral collaboration on poverty
reduction.
- To encourage indigenous potential resource mobilization towards Local
Economic Development.
- To ensure local Content and local participation across the oil and gas value
chain.
Against the background of the overriding goal and the key objectives, the District
Medium Term Development Plan (2014 – 2017) took cognizance of not only the
deprived nature of the District especially the northern part but also the administrative
and personnel needs confronting the administration of the District. Following the
consultation and town hall meetings held at the community and the departmental
levels, the district was able to fashion out the developmental needs of the people in the
district based on major sectors of the District’s economy. This informs the District of the
scope and directions of the projects and programmes that fed into the 2014 – 2017
DMTDP. Therefore, the scope and direction of the projects and programmes as
identified by the Ellembelle District Assembly covers health, education, water and
12
sanitation, Agriculture, roads, revenue mobilization and expenditure controls, gender
equality, ICT and HIV&AIDS prevention as well as programmes that will empower the
vulnerable and the disadvantaged in the District. Also, issues of climate change,
population, housing, electricity, telecommunication, tourism development and
establishment and strengthening the capacity of various departments and their staffs in
the district are well captured and planned for. These projects and programmes are
captured in the broad Composite of Programme of Action (page 146-180) which covers
the 4 – year planning period and stated under the thematic areas of the Medium Term
Development Policy Framework MTDPF 2014 – 2017). It is based on the prioritized set of
activities of the district and their respective cost. Annual Action plans are also provided
in details (page 181-252) and relate to the various activities, timeframe, output
indicators, annual budgets and implementation agencies.
IIId. SUMMARY OF DISTRICT STRATEGIES
To ensure the realization of the overall goal and objective, the District strategy shall
focus on the underlisted Areas:
- Facilitating support for equitable Human Resourced Development
- Increasing production and promoting sustainable livelihood
- Ensuring good governance
- Encouraging the active involvement of the Private Sector as a key-partner in the
development of the District.
- Ensuring gender equity
- Providing special programmes for the vulnerable and excluded
- Facilitating the provision of Basic Services and infrastructural development.
Also a comprehensive monitoring and evaluation plan has been developed to ensure
the effective and smooth implementation of the MTDP (2014 – 2014). By the
Monitoring and Evaluation Plan, the responsible actors are to track and assess the
action plan, the respective activities, the time frame, the personnel and materials
required and supplied and the financial flow and cost involved as well as the progress of
work and the technical details of the projects and programmes formulated in this plan.
13
INDICATIVE BUDGET The total budget for the planned activities is estimated at GH₵56,679,754.00 for the 4 –
year period of the plan. The distribution is captured in the Composite Programme of
Action of the MTDP (2014 – 2017). The implementation of the plan is expected to be
funded predominantly through Governmental sources like the DACF, (including the
District Assembly) and Non- Governmental Organizations and Agencies within and
outside the district. Specific sources of funds for the implementation of the plan will
include Internal Generated Funds (IGF), District Assembly Common Fund (DACF) and
grants from Government of Ghana, NGOs, and other Development Partners (DPs) in
and outside the District.
EXPECTED OUTCOME OF THE 2014 – 2017 DMTDP All the projects and programmes of the MTDP (2014 – 2017) are planned and
formulated based on the overarching objective of the Ellembelle District Assembly.
Therefore the expected outcome of this plan will indicate:
Improved agricultural performance
Improved road conditions
Improved telecommunication facilities
Adequate employment opportunities for local people
Improved health delivery system
Improved educational performance
Increased and improved potable water supply
Reduced spread of HIV &AIDS
Enhanced and sustainable women participation in decision making at all levels
Improved environmental and sanitary conditions
Improved electricity coverage
Improved conditions of the vulnerable and the disadvantaged in the district
Effective population management
Increased internally generated revenue (IGR)
Ensured sound financial management
Strengthened institutional collaboration between the central administration
and the Decentralized departments of the District
14
Improved judicial services delivery (rule of law adhered to)
Increased number of personnel and logistics of the District Assembly
In summary, it is expected that, the effective implementation and management of this
plan will result in poverty reduction, thereby leading to an increase in real income per
capita, greater awareness of gender equality, HIV&AIDS prevention, food security and
sustainable development as well as active community participation in the socio –
economic development of the district.
15
PERFORMANCE REVIEW
1.0 THEMATIC AREA: INFRASTRUCTURE AND HUMAN SETTELMENT DEVELOPMENT
WATER & SANITATION
PROGRAMME/ACTIVITY LOCATION POLICY OBJECTIVE INDICATORS TARGET LEVEL OF ACHIEVEMENT REMARK
2010 2011 2012 2013
Training and formation of existing and old WATSANS respectively in 8 Communities
Aiyinasi, Asasetre, Nkroful/Teleku-Bokazo, Awiebo, Kikam, Asemko, Esiama, Tandan,
Accelerate the provision of affordable and safe water
Improved performance level of WATSANs
Existence of well-motivated WATSAN committees
Train 90% of WATSANs Committees
All WATSAN Committees were trained especially in project towns
Extension of Small Water System in neighboring communities of Beneficiary project towns.
A.B.Bokazo, Alabokazo,Anwia, Tandan,Akpandue
Accelerate the provision of affordable and safe water
All Neighboring Communities to be covered.
Only 30% of the beneficiary town did extension.
Construct new pipe systems for Highly populated areas
District Wide ,,, Mostly donor funded projects
Const. of Boreholes for communities within Aiyinasi North.
Selected Communities.
Ensure efficient Management of water resources
To cover all communities
Only 10% of the Communities were covered
Construction of 10 No. borehole for communities &
Selected Communities
,,, 100% coverage by end of
100% completed.
16
Rehabilitation
planning period
Carry out mosquito control program.
District Wide Accelerate the provision and Improve Environmental Sanitation
Reduction in Sanitation related diseases.
Mosquitoes free district.
The activity is ongoing, hugely successful due to the support from AngloGold Company support during the later stage of the plan period.
Procure 5 refuse containers
Selected Communities
‘’ 100% 100% completed. But inadequate to supply the growing population
Identify suitable sites or the construction of the bays.
District wide ‘’ 80% coverage within the planning year
Carry out weekly stray animal arrest
District Wide ‘’ Largely unsuccessful due to financial commitment and weak bye laws.
17
Construction of 16 Seater Aqua privy toilet
District Wide ‘’ 100% completed.
carry out spraying of sites
Selected Communities
Ongoing activity, need a lot of financial commitment
Organize education in schools on the need to keep public places clean
District Wide Ensure the development and implementation of health education as a component of all water and sanitation program
Educate communities on the need for clean environment
Selected Communities
,, Ongoing exercise.
Prepare IDs for those screened and passed fit.
District Wide ,, Routing activity. A lot of education still needed to make it successful.
Registration of all eating houses and owners
District wide ,, Not successful especially in the hinterland.
Intensive education and screening of food vendor
District Wide ,, Routine activity.
Auctioning of arrested animals
District Wide ,, Not successful. Weak bye-laws
18
Inspection of existing slaughter houses to ascertain their state
Aiyinasi Ongoing, a routing activity.
Provide support for zoomlion service and activities
Nkroful 100% Statutory deduction
THEMATIC AREA: INFRASTRUCTURE AND HUMAN SETTELMENT DEVELOPMENT EDUCATION
PROGRAMME/ACTIVITY LOCATION POLICY OBJECTIVE INDICATORS TARGET LEVEL OF ACHIEVEMENT REMARK
2010 2011 2012 2013
Construction of 3-units classroom block.
Kumgbunli Adubriem Asomase Kwesikrom
Improve management of education service delivery
Improved learning conditions.
100% within planning period
100% completed. Inconsistency in the flow of funds.
Manufacturing of 300 dual school desk
Nkroful Increases students enrolment
100% 100% completed.
Construction of 3-unit classroom block with office, store and staff common room
Ankobra Akropong Adisekrom Esiama
100% 80% completed. Left with only Adisekrom
Construction of 1 No. 15 Unit office block.
Nkroful
100% 100% completed.
19
Construction of 1 No. 4 Unit Classroom block, office and store room.
Kikam Meth. Lower Primary, Asemko D/A Primary School, Teleku-Bokazo D/A J.H.S , Nyaneba Model J.H.S Nkroful
Improve quality of teaching and learning
100% 50% completed. Poor resources flow.
Sponsor twenty (20) pupil teachers a year to become professional teachers
District Wide Improve teaching output.
50% Few teachers were sponsored. Not quite a lucrative venture.
Promote Science, Maths & English
District Wide Increase inclusive and equitable access to, and technology at all levels
100% within planning period.
Routine exercise by both DA and Education Directorate.
Provide for educational assistance
Selected schools 100% Routine exercise by both DA and Education Directorate.
20
Thematic Area: Accelerated Agricultural Modernization and Sustainable Natural Resource Management AGRIC
ACTIVITY LOCATION POLICY OBJECTIVE INDICATORS TARGET LEVEL OF ACHIEVEMENT
REMARK
2010 2011 2012 2013
Conduct M&E Exercise District wide Improve Agricultural Productivity
Improved farming practices
70% 50% completed. Ongoing
Carry out 100 demons. On row planting for optimum yields for 5000 farmers by Dec.,2013
Selected farms Promote selected crop development for food security, export and industry
Increased farm produce.
100% 30% Farmers complained as being laborious and time wasting
Carryout 10 demons on improved practices to increase yields of vegetables by 2012.
Selected farms Improved institutional coordination for agricultural development
80% 40% High cost of fertilizers and other farm inputs hindered farmers interest
Carry out 30 demons on improved practices to increase yields of maize and cowpea
40 communities
100% 45% High cost of fertilizers and other farm inputs hindered farmers interest
21
Conduct 500 AEAS Supervision
District wide 100% 38% High cost of fuel and few AEAs
Train 100 pig farmers on improved production and management skills by Sept, 2011
10 communities
Improved expertise of farmers
42% Farmers prefer the local breeds to the exotic ones since no proper care is given as they fend for themselves
Organize 150 Field day activities
District wide 48% Lack of resources to organize field days
Organize a 2 day workshops on marketing of exportable agricultural commodities for 50 producers annually
District wide Improved expertise on marketing
100% Lack of funds to complete the activity
Conduct post-harvest training
District wide 85%300 farmers were trained in post-harvest losses in maize and cassava
Implement Inland Valley Rice Project
Kumgbunli Increased rice produce
70% 50% Project at a standstill as the contractor abandoned the earth works
Vaccinate 1,600 poultry &2000 livestock
District wide 100% 47% Few veterinary staff at
22
post
Train farmers associations
District wide 100% 62% 10 active FBOs are operating
Educate 500 cocoa farmers and Conduct disease surveillance
Selected farms 100% 85% Inputs from CODAPEC were used to train farmers
Treat 1500 clinical/Surgical cases
85% 46% Few veterinary staff
Conduct Training on Bee-keeping
Selected farms 50% Inadequate fnd to execute project
Train 20 management and field staff in ICT skills for effective extension delivery by June,2012
Menzezor 40% of total staff
Only two staff have been trained
Train 1 staff in socio-economic analysis for District Agric. Development Planning and Management
Menzezor 100% Not executed due to lack of funds
Train 1 staff on Market Information Collection
Menzezor 100%
Educate 10,000 people on public health in connection with H1N1 influenza annually
District wide 100% 65% Support was given by RADU
23
Train 10 caterers on fortification of staples during processing and linkage to school feeding program
100% Lack of resources to organize the training
Train 200 producers, processors and marketers on post-harvest handling of perishable
100% 25%, inadequate resources.
HEALTH THEMATIC AREA: INFRASTRUCTURE AND HUMAN SETTELMENT DEVELOPMENT
THEMATIC AREA ACTIVITY LOCATION OBJECTIVS INDICATOR TARGET PERFORMANCE RATE/LEVEL OF IMPLEMENTATION
REMARKS
Human resource development, productivity and employment
Community education on prevention of malnutrition, malaria, tuberculosis, HIV/AIDS and other
District wide Intensify prevention and control of communicable diseases
Community sensitizations carried out in Aiyiansi, Asasetre, Kamgbunli, Esiama, Asanta
Mothers at CWC, ANC, OPD clients, Congregations and general public
100% Activities well patronized
24
communicable diseases
Education on safe food practices
Ankobra FM Churches, clinics, markets places
Improve governance, strengthen efficiency and effectiveness in health service
2 FM education carried out on Ankobra FM, West end radio 4 education at market places at Eikwe, Aiyinasi, Esiama and Asasetre
Food vendors 100% Very effective
Formation of healthy life style clubs in schools
NASS Esiama SEC TEC
Improve access to quality maternal, neonatal, child and adolescent health
2 clubs formed Students 100% Clubs in active due to students turn overs. To be reformed
TOT for club leaders on regenerative health
Selected schools
Intensify prevention of and control of communicable and non – communicable diseases
Selected schools 20 Club leaders 0% Lack of funds
Human development, productivity and employment
Celebrate world AIDS day
Nkroful Intensify prevention and control of communicable diseases
No of World AIDS days celebrated in district
General public
50%
Inadequate funding
Provision care and support for
District wide Increase access financial
Number of PLWHAs
PLWA 10 Inadequate funding
25
people living with HIV/AIDS
accessibility to health care to protect the poor
registered with NHIS
Institute health walks in district
Sub district capitals
Intensify prevention and control of communicable diseases
No of communities/ institutions engaged in monthly health walks instituted in the district
Workers, Students and individuals
20 Esiama, Asasetre, Aiyinasi, Adamus workers etc
Implement National health promotion programs(Child health promotion weeks, NIDs, Measles immunization etc)
Communities Increase access to quality health care
% of children under five reached
Children under five
80% Activities carried out annually
Orientation of health staff on HIRD
DHMT Improve governance and strengthen efficiency and effectiveness in health service delivery
No of health workers trained
50 100% Health workers trained
Human development, productivity and
Promote Maternal and child survival
Communities Improve access to quality maternal,
No of PROMISE stakeholders meetings held
8 100% 2 stakeholders meetings held annually
26
employment Excellence (PROMISE)
neonatal, child and adolescent health services
in district
Implement adolescent health programs in schools and communities
Health facilities and senior high schools
Improve access to quality maternal, neonatal, child and adolescent health service
No of adolescent clubs formed
4 50% 2 adolescent clubs formed(NASS and Aiyinasi health center)
Strengthen disease control and surveillance
Communities and health facilities
Intensify prevention of communicable and non-communicable diseases
No of Community based surveillance volunteers trained
100 50% 50 Community based volunteers trained
Renovation of health centers and staff quaters
Aiyinasi, Aidoosuazo, Asasetre Esiama
Improve governance and strengthen efficiency and effectiveness in health care delivery
No of health centers and staff quarters renovated
3 health centers 5 staff quarters
70% Aidoosuazo H/Center and staff quarters fully renovated Esiama Health Center and staff quarters renovated, 1 staff quarters of Asasetre Health center renovated
Construction of OPD block and expansion of dispensary
Nkroful and Asasetre Health centers
Improve access to quality health service
No OPD block constructed
1 OPD block at Nkroful 1 dispensary renovated
50% OPD block of Nkroful Health Center almost completed.
27
Thematic Area: Transparent & Accountable Governance.
CENTRAL ADMINISTRATION
ACTIVITY LOCATION POLICY OBJECTIVE INDICATORS TARGET LEVEL OF ACHIEVEMENT
REMARK
2010 2011 2012 2013
Completion of school blk for Eikwe physically challenged school.
Eikwe Encourage public private partnerships in socio-economic development.
Improved sector performance
100%
completio
n by mid-
June 2012
100% completed, handed over
Construction of Science Lab.
Asanta 100% 100% completed. Funded by ENI
Renovation of dispensary at Asasetre not started.
Sustain mobile health service in he district
Communities Improve access to quality health care
No of communities reached with mobile health service
At least 50 60% Most communities are not reached
Organize annual health fairs
Nkroful, Aiyinasi
Improve access to quality health service
No of health fairs organized in a year
1 100% Health fairs organized at Esiama and Ayinasi
28
before
Fed. 2012
Foundation
Construction of ICT Center
Nkroful 100%
before
Nov. 2011
100% completed, and handed over
Construction of Doctors Quarters at Eikwe
Eikwe Improved sector performance
100%
completed
in 2011
100% completed. Handed over
Promote sport and culture
District Wide Effective implementation of the Local Government Act
Routine activity, but mostly hindered by inadequate fund
Construct staff quarters at Esiama Nursing Training
Esiama 100%
completio
n by end
of 2010
100% completed, handed over
Fencing of DCE’s Bungalow and construction of 1No. boys quarters
Nkroful 100%
completed
by end of
2010
Not executed.
Purchase of Vehicle (Pick-Up)
By end of
2012
Not executed. Due to Inadequate funds
29
Construction of 1No. Market and lorry park at Esiama.
Esiama Increased revenue
By end of
2013
Not executed.
Construct Administration Blk.
Nkroful - ongoing
Construct Low cost buildings for junior staffs
Nkroful - ongoing
Support Human Resource Training
District Wide Strengthens institution to offer support to ensure social cohesion at all levels of society
Improved productivity
- Routine activity, Mostly hindered by resources flow.
Rehabilitate Official vehicles
Nkroful Routine activity
Construction of 2-bedroom storey, semidetached quarters for staff
Nkroful 100%
completed
by end of
2010
80% completed.
Sensitize Community members on Negative effects of HIV/AIDS
District wide Reduced HIV/AIDS coverage
Conduct training on alternative sources of livelihood
Selected communities
Mainstream the concept of local economic development into planning at the District level
30
Organize workshop for women groups on LED and how to access credit
Women groups
Enhanced living standard.
70% of
women
group to
benefit by
end of
plan
period
Few areas have been covered. Financial constraint.
Completion of 4-bedroom Guest house
Nkroful 100% by
end of
2010
100% completed
Maintenance of Street lights
District wide Improved productivity
Routing activity
Reshaping of (21Km) Akropong -Jica Bridge Feeder Roads.
Akropong 100%
completio
n by end
of 2012
100% completed
Rehabilitation of 5.8km road (GSOP)
First gate 100% completed and handed over.
31
Thematic Area: Transparent & Accountable Governance.
Community Development/ Social Welfare
ACTIVITY LOCATION POLICY OBJECTIVE INDICATOR TARGET LEVEL OF ACHIEVEMENT
REMARK
2010 2011 2012 2013
Contribution and communal labor for the provision of services and teaching community women on the management of home and child
District Wide Facilitate equitable Access to good quality and affordable social services
Series of education programmes were conducted during the year under review eg. Teleku Bokazo, Menzezor & Baseke. However the exercise should be consistent.
Educate the communities on the ownership and the management of water project concept through WATSAN
Selected Communities
Considerable number of training has been conducted especially in beneficiary communities
Disseminate information and create a two way channel of communication between the people of the government so as to promote the
District Wide Strengthen institution to offer support to ensure social cohesion at all levels of society
30% out of the total communities targeted conducted. Adequate budget
32
achievement of specific development of specific development target goals in the emerging oil era.
in needed to pursue the exercise
Alleviate vagrancy and criminality in the youth and liabilities of women in the district through the provision and transfer of employable skills towards self sufficiency
District Wide Soap making and pastries were conducted Aiyinasi. Other sources of employable skills should be explored.
Organize group meeting in all the 7 area Councils on women empowerment and capacity building
Selected Communities
Enhance women access to economic resources
Trainings were conducted at Nkroful within 2010-2013, extra resource needed
Educating selected groups in the 7 area councils on the management of income generating activity
Selected Communities
Organize site safety programs for 30 ‘Gallamsey’ operators
Nkroful
30 Galamsey operators were training within the period. Also about 250 galamsey workers benefitted from
33
safety training.
Oil & Gas Activities
Thematic Area: Oil and Gas Development
ACTIVITY LOCATION POLICY OBJECTIVE INDICATORS TARGET LEVEL OF ACHIEVEMENT
REMARK
2010 2011 2012 2013
Organize regular meeting between stakeholders especially along coastal zone to discuss issues affecting them
Coastal Communities
Ensure the development of Oil and Gas Industry
Enhanced knowledge on Oil & Gas
80%
coverage by
end of 2013
40% completed.
Conduct education on Oil and Gas activities.
Selected Communities
Convert the opportunities offered by Oil and Gas industries to create decent jobs
Increased local participation in Oil & Gas industry.
100%
coverage by
end of plan
period
70% completed. Mostly done by Oil & Gas companies.
Set up Oil & Gas Sub-Committee for the District.
Nkroful Build the relevant capacity for the Oil and Gas industy.
‘’ By end of
2010
34
1.1 Review of Assembly Finance
This section analyzes the revenue and expenditure pattern of the Assembly from 2011 –
2013. An examination of the sources of revenue indicates two main sources.
a) Internal Sources (own sources)
b) External Source
TABLE 1 Revenue Sources 2011 – 2013
Type 2011
Target
(GH₵)
2011 Actual
(GH₵)
% of
actu
al
2012
Target
(GH₵)
2012
Actual
(GH₵)
% of
actu
al
2013
Target
(GH₵)
2013
Actual
% of
actual
INTERNAL
Rate
-
5,135.26
1.4
7,450.00
48,983.36
5%
15,385.0
0
64,843.5
5
21%
Lands
-
139,627.30 39% 812,600 672,326.4
1
73% 801,400 41,160.0
0
13.1%
Fees and
Fines
- 53,920.04 15% 12,250.0
0
46,628.58 5.1% 16,250.0
0
40,456.3
0
13.1%
Licenses - 112,986.96 31% 110,115 104,804.8
2
11.4
%
97,450 162,341.
90
51.5%
Rent - 7,143.22 2% 36,870 6,701.54 1.0% 49,800. 6,443.80 2.0%
Investment - 25,360.00 7% - 82,984 9% 553,602 - -
Miscellaneo
us
-
15,626.00 4.3%
3,000.00
2,552.26
0.3% 3,000.00 - -
TOTAL - 359,798.78 100 982,285 918,352.3 100 1,506,80 315,243. 100%
35
INTERNAL % 9 %% 7 5
External
Stool Lands
-
139,627.30
5.4%
812,600
672,326.4
1
19.3
%
801,400
41,160
9.3%
DACF - 2,111,754.9
5
81% 2,144,44
6.08
930,199.2
7
27% 1,704,31
3.92
41,160.0
0
9.3%
HIPC - 50,373.93 2% 50,000 292,978.1
6
8.4% 50,000 - -
Other
Grants (VIP
CBRDP)
-
302,234.30 12%
1,163,33
0
1,063,099
.37
31% 344,982 362,381.
38
81.1%
MRF - - - 500,000 519,103.6
1
15% 250,000 - -
TOTAL
EXTERNAL
2,603,990.4
8
100
%
4,670,37
6
3,477,706
.82
100
%
3,477,70
6.82
444,701.
38
100%
Reason for any deviation regarding achievements of set targets
Actions taken to remedy the situation during the period
Expenditure Pattern
The Expenditure of the district budget has been divided into recurrent and capital
Expenditure to conform to the conventional budget structure of the local government of
Ghana. The recurrent expenditure consists of personal emoluments, Travel and Transport
36
Expenditures, General expenditure, maintenance, repairs and renewals as well as
miscellaneous. The capital expenditure consists of all expenditures made on Development
Projects and Programmes.
Table 2
EXPENDITURE HEAD 2011 % 2012 % 2013 %
Amount % Amount % Amount
Personnel
Emolument
226,169.10
18%
350,257.54
24%
107,938.26 10%
Travel and Transport 53,606.36 4.2% 38,524.64 3% 105,822.49 10%
General Expenditure 82,947.83 6.5% 100,505.51 7% 34,856.98 3%
Maintenance,
Repairs, and
Renewals
8,385.09
1%
3,578.50 0.2%
28,053.65 3%
Miscellaneous 104,240.66 8.2 79,842.91 5.4% 154,377.61 14.3%
Total Recurrent - - - - - -
Capital Development 801,928.60 63% 902,873.95 61.2% 651,029 60%
TOTAL EXPENDITURE 1,277,277.64
100% 1,475,583.05 100% 1,082,077.99 100%
Source: District Finance Department, 2013
37
1.2 ANALYSIS OF PERFORMANCE REVIEW The Ellembelle District witnessed its first Medium Term Development Plan under the Ghana
Shared Growth Development Agenda after it was separated from the erstwhile Nzema East
District Assembly in 2008. Considerable number of programmes and projects were captured
with its corresponding activities with the aim to fast-track development in the entire
District.
There was a review exercise half way through the planned period and also for the annual
action plan phased out in the Plan. However this saw only a few changes in the entire plan.
New interventions came on board after the plan has been prepared which contributed
immensely towards development. All ongoing projects from previous plan were analyzed
and captured under the new development agenda to ensure harmonized development.
In order to make informed judgment about the performance of the District viz – a – viz the
state of development in the implementation of the projects and programmes set to
enhance the quality of life of the people in relation to the goal and objectives of the Ghana
Shared Growth Development Agenda (GSGDA 1), the Assembly through its District Planning
and Co-ordinating Unit (DPCU) reviewed the programmes and projects annually through the
use of the Annual Progress Reporting format in the Monitoring and Evaluation Guidelines.
However the human resource challenges faced during the planned period cannot grossed
over. Most of the department of the Assembly had not the full complement of staff
especially during the initial implementation stage.
The review revealed that, out of the eighty-nine (97) planned activities in the District
Medium Term Development Plan (DMTDP – 2010-2013), 35 were fully implemented, 26
partially implemented and the rest of 28 projects are still on- going at various levels of
completion. The delay was basically due to inadequate funds and other logistics.
The performance of the District under the GSGDA 1 thematic areas are analyzed below as
follows;
38
1.2.1 Accelerated Agricultural Modernization and Sustainable Natural
Resource Management Under the Agricultural Sector there was increase in the yield of some staple crops, namely
Plantain, Maize, Rice, and Cocoyam, yam at a percentage of 10.0mt, 1.20, 1.5, 4.0, and 3.40
respectively for 2011. It also shut up in 2012 with 10.2mt, 1.25, 1.9, 4.2 3.40, 10, 5, 12, 2.5,
2, 0.10mt
Though there was increase it was not significant. This performance was mainly due to
irregular rainy pattern, global economic recession and low coverage of extension services.
Also must of the roads linking the forest zone to the other part of the District has poor
accessibility resulting extension services.
In the area livestock production namely Sheep, Goat, Pig, Poultry, Cattle the records stood
at, 8, 5, 8, 10, 2 for 2011. However all these products increased in 2012 without poultry, and
this was attributed to inadequate inputs supply (vaccines) to farmers.
The 2013 Annual Performance Report revealed that vegetable cultivation in the district was
generally low thus resources should be channeled into the sector for enhancement.
Also, the Fishing Industry which is among the main stays of the coastal communities saw a
drastic decline in stock from 0.14mt to 0.10mt in 2010 and 2011 respectively. This was
mainly attributed to Oil and Gas activities and bad fishing practices like light fishing.
On Sustainable Natural Resources Management, the District made some stride through the
support of development partners. The Amanzule Wetlands Conservation Area Project, Hen
Mpoanu and the CREMA project were project that contributed to sustaining the natural
resources in the District. The Hen Mpoanu Project contributed to the formation of
‘CEMACs’, committees form in coastal communities to protect biodiversity, the physical
environment and the Coast. Also the CREMAs were set up for the protection of nature
reserves in especially the forest zones. However not much has been done towards
evaluations of their operation so as to ascertain their effectiveness or otherwise.
It is however required that financial resource is pushed in the growth of Agric sector in the
area supply of farm inputs and capacity building. Also projects geared towards
environmental and resources sustainability should be regularly monitored and evaluated to
ensure value for money.
39
1.2.2 Oil and Gas Development The discoveries of oil and gas in Ghana open up a collection of opportunities to stimulate
the pace of national development. Nonetheless, the potential for oil and gas to drive the
economy positively will only be realized if this emerging industry is fully integrated into the
local economy with all associated problems tackled.
The District plays a pivotal role in the emerging oil and gas industry, with the presence
Ghana Gas Company Ltd been at the pinnacle of several other facilities currently ongoing in
the District. The Atuabo Gas Project is at its conclusion stage. Other oil and gas companies
currently on board are Lornrho Ghana, Quantum Gas, ENI Foundation and others. Majority
of these companies are close to its completion stage. Economic activities have been on the
increase within the coastal communities. Accommodation rent has shot up due to the
increased population demand.
Though the industry has boosted economic activities in the District to some extent, the
corresponding problem cannot be overemphasized. The misery behind the cause of algae
bloom in the sea at some time in the year is yet to be uncovered; however local fisherfolks
attribute it to Offshore Oil & Gas production.
1.2.3 Enhancing Competitiveness of Ghana’s Private Sector Though Government continued to implement reforms aimed at improving the
Competitiveness of Ghana’s private sector, progress remains slow. It is considered as the
engine of growth for country’s development hence the government promoting Public
Private Partnership.
The Ellembelle District within the last three years has seen a major growth in this sector
notably is the service and industrial sector, with a percentage increase to 35% and 55%
respectively for 2012. The creation of the District after 2008 brought in its wake people
developed interest at the formal sector.
Also the industrial sector rose drastically due to the Oil and Gas find, and the existence
mining companies in the District. Considerable number of people especially the youth
moved to work in the companies during the constructional stage.
40
The number of people into ‘galamsey mining’ increased in 2012, with majority of them
based in Nkroful and Teleku Bokazo. However the presence of these activities boosted
commercial activities in the Communities.
Hotel business has been on the ascendency since 2011, with majority of them been in
Nkroful and Esiama. About six (6) major were built during the plan (2010-2013). However
the general tourism industry still lacks the needed impetus to become a key revenue source
for the District, and there is the need to consider the untapped potential tourism source.
In the area of Micro, Small, and Medium Enterprise (MSME), the Business Advisory Centre
under the Rural Enterprise Project (REP) undertook training in soap making in Kumgbunli (27
females), Community training in bakery and confectionary in Aiyinasi (25 females), cassava
processing (1 male & 18 females), training in batik , tie & dye at Nkroful (29 females)
(2013 District BAC Report)
1.2.4 Infrastructure and Human Settlements Infrastructure provision has become very key in the economic growth and sustainable
poverty reduction in Ghana as it’s seeks to become a middle-income country.
Consequently, the Ellembelle District during the implementation of the GSGDA 1 had
priority attention towards expansion of existing social and economic production
infrastructure to ensure that services provided are reliable, affordable and efficient. The key
areas of policy focus for the medium-term are: transport infrastructure; energy and energy
supply to support industries and households; science, technology and innovation;
information and communication technology development; human settlements
development; water, environmental sanitation and hygiene.
On road infrastructure, with 87km target the district was able to achieve 34 km in 2013.
Road rehabilitation took place in communities like Akropong, Mantukwa, First-Gate and
Aiyinasi Nyamebekyere.
The Rural Electrification Project is currently ongoing with majority of its going into the
Northern part of the District though most of the communities are yet to be covered. In total
about 70% of the entire district is covered.
41
Out of the 19 activities under environmental sanitation and water, 8 were completed, 7
were ongoing and 4 not implemented. Most of the toilet facilities were concentrated in the
coastal zone as a strategy to reduce indiscriminate defecation.
On Education, 12 projects were completed with the additional 5 ongoing (GETfund projects).
Resources are needed to complete all outstanding projects.
1.2.5 Human Development, Productivity and Employment Human Resource Development is a critical aspect of national development which aim at
growth and social equity
Human development indicators in areas such as education and skills acquisition, health,
employment, productivity, social protection, poverty reduction are indicative of major
socio-economic challenges to most developing countries.
To address spatial imbalances, the Ellembelle District has created an access road (partially)
linking the south with the Northern part of the district. However there is the need to
properly construct the road since it will easily link the cocoa producing communities to the
market centres.
On health Sector, out of the 16 activities, 7 were completed and 9 were ongoing. Among the
standout projects undertaking by the District during the plan period was the provision of a
mobile clinic and also the provision of CHPS Compounds in selected communities like
Asanta, Kwesikrom and Nyamebekyere (Aiyinasi)
In the area of social protection, the District benefited from the Bamboo Biomass Project in
Tandan and the Ghana Social Opportunities Project (GSOP) which serves as a source of
income for rural folks especially during farming off seasons.
1.2.6 Transparent and Accountable Governance The main goal of transparent and accountable governance is to strengthen government and
non-governmental bodies to participate in the national development process and
collaborate effectively to achieve national development goals and objectives. The
collaborative process is to ensure that public resources are managed efficiently towards
development.
42
The Ellembelle District during the implementation of the GSGDA I put measures in place to
improve revenue generation. A revenue generation and management action plan was
developed to guide, however the sector saw a fluctuating growth during the period. This
was due to unrealized revenue target.
Series of social accountability fora were conducted during the planned period. Budget was
also set aside for self-help through which cement and roof sheets were supplied to
communities.
The Assembly didn’t do much in the area of sub-structure development. Currently most of
the Unit Committees and Area Councils are not functional, and it is largely due to resource
constraints.
1.3 OTHER INTERVENTIONS
1.3.1 Tandan Bamboo Biomass Project International Network for Bamboo and Rattan (IMBAR)is implementing a project ‘’Bamboo
as Sustainable Biomass Energy: Alternative for firewood and Charcoal Production in
Africa, a pro poor initiative which seeks to utilize the enormous bamboo endowment in the
community to produce charcoal and briquette as means of increasing the use of bamboo as
a source of energy for the poor in Ghana thereby providing a more sustainable,
environmentally friendly and economical option for firewood and wood charcoal.
Currently the project has been completed and handed over to the beneficiary community
but yet to be commissioned. The District Assembly is helping the community to develop a
sustainability plan. Other communities have liaised with IMBAR to ascertain the possibility
of extending the project to their catchment areas.
1.3.2 Ghana Social Opportunities Project (GSOP) Ghana Social Opportunities Project (GSOP) has the overall goal to support Ghana’s Social
Protection Strategy through:
43
Developing a labor intensive public works program as a rural safety net instrument in
target districts across the country to increase cash income for the rural poor during
Agricultural off-season and
Supporting the Government’s Livelihood Empowerment against Poverty (LEAP)
program.
The Project has five components namely: 1) Rationalization of National Social Protection
Strategy
2) Labor Intensive Public Works (LIPW) 3) Support to the Livelihood Empowerment against
Poverty (LEAP) 4) Capacity Building: and Project Management & Coordination.
There are forty (40) districts plus one (1) MMDA benefiting from this intervention, which has
Five (5) years life span, and project cost of US$89.1million.
The Total allocation for the completion of the sub-project within the five years plan period
(October 2011- December 2015) is GHc517, 426.84 for Ellembelle District.
1.3.3 Social Protection & Vulnerability Aspect of GSOP The Government of Ghana has put in place a comprehensive National Social Protection
Strategy which recognizes that affects people in different ways. The NSPS represents the
government’s vision of creating an all-inclusive and Socially-empowered society through the
provision of sustainable mechanisms for the protection of persons living in situations of
extreme poverty and related vulnerability and exclusion. The objective of the Project is to
provide targeted rural poor households with access to employment and income earning
opportunities, in particular during seasonal labour demand shortfall through rehabilitation
and maintenance of public or community infrastructure.
The Ellembelle District been a beneficiary of the project drew a comprehensive program of
Action for the implementation of the project.
Table 3 Below are components of sub project within the District:
44
COMPONENT NAME OF PROJECT AMOUNT (GH₵) STATUS
1.Social Infrastructure Construction 3-unit
Teachers quarters at
Akropong
137,000.00 100%
Completed and
handed over
2.Economic
Infrastructure
Rehabilitation of 5.8km
road at First gate juct –
First gate
332,900.00
3.Climate Change Establishment of Rubber
Plantation at Menzezor
141,670.60 14 hectares of
rubber has
been planted
45
1.4 Gaps / Challenges Identified in the Implementation of the
DMTDP 2010-2013 The implementation of the DMTDP 2010 – 2013 was confronted with several challenges.
The major ones included
Inadequate resources particularly funds – local and external resources
affected the implementation of key projects.
Delays in release of funds affected projects completion periods.
Lack of residential accommodation for the core staff including heads of
departments,
Non –availability of some key departments, public sector organizations and
service providers in the district.
High illiteracy rate among the people of the district which affected
dissemination of information, adoption of modern technology, particularly
farmers, etc.
Inadequate capacity of the staff to effectively implement the programmes of
the Assembly and the entire District.
Inadequate logistics and equipment for the staff to support the
implementation of the programmes.
High cost of M&E exercises due to undue delays in project completion
periods.
Inadequate credit facilities for local entrepreneurs.
Poor accessibility to project sites due to bad nature of roads in the district
affected proper M&E exercise.
Low income among the people and the people poor attitude towards
payment of taxes affected revenue generation in the district.
Low participation of sub-structure.
lack of adequate office space for the Central Administration and the
Decentralized Departments,
Implementation of projects outside the Plan
Absence reliable and accurate data
Poor development of Tourism sector
46
Inadequate Knowledge on Oil & Gas Sector
Lessons learnt during implementation of 2010 – 2013 DMTDP Some key lessons/ experiences were learnt during the implementation of the 2010 –
2013 DMTDP. Notably among them include the following:
Internally Generated Revenue is very critical to the over operation of the
District Assembly
Poor / inadequate basic infrastructure facilities e.g. roads, accommodation
telephone, etc badly affected the smooth implementation of the plan.
Involvement or participation of communities, Private Sector, NGOs, Donors,
Decentralized Departments and other stakeholders will enhance the
implementation process
Effective collaboration/ partnership between DA and agencies, Donors,
NGOs, CBOs, and other stakeholders in services provision contributed to
development
Low commitment/apathy among community stakeholders negatively
affected project implementation.
Targets set for certain projects were too high and unattainable during the
plan period.
The multiplier effects of some projects during the plan period were not great.
Regular M&E of projects was crucial in the successful implementation of the
plan.
Execution of project outside the Plan affected the Budget negatively.
47
SCORING SCALE
DEFINITION SCORE MEANING
Storing
relationship
2 A strong harmony of community
needs and aspirations and identified
key development problem.
Weak
relationship
1 A weak harmony of community
needs and aspirations and identified
key development issues.
No relationship 0 Calls for review of the community
needs and aspirations to identify
real problems.
These scores were added together and divided by the number of community needs and
aspirations to obtain the average score. Where the score is very high, it indicates that there
is strong harmony of community needs and aspirations and identified key development
gaps/problems/issues.
A low score indicate weak harmony while a zero score calls for review of the community
needs and aspirations, if possible, to identify real problem to be addressed.
Detailed steps towards prioritization have been attached to the annexes.
48
After analyzing the Data from the communities and conducting public for a, the following
Community Needs and Aspirations, linked to the gaps from review of previous
performances, were derived
Improvement in Education Sector
Improvement and Accessibility of Road Network
Provision of Proper Health Care
Provision of Farming Inputs and Lands
Improvement in Income Generating Activities
Provision of Potable Water
Ensuring Proper Sanitation (Solid & Liquid waste)
Provision of Drains
Extension of Electricity
Provision /Rehabilitation of Office Accommodation for Central Administration and
Lower Structures (Area Councils)
Provision of Security
Improvement in Rural Housing Conditions
Security Provision
Provision of Logistics for Monitoring & Evaluation of district Projects and
Programmes
Accessibility to Credit Facilities
Improvement in Tourism Development
Enforce of District Bye-Laws
Sensitization on Oil and Gas Issues
49
1.6 SUMMARY OF KEY DEVELOPMENT PROBLEMS Planning being basically a problem solving activity cannot be undertaken without
appreciation of the prevailing development problems and priorities of the target population.
Thus the underlisted are summary of development problems identified:
Inadequate Educational Infrastructure
Poor Road Condition
Poor Health Care Delivery
Inadequate Land and Farming Inputs
Inadequate Potable Water Coverage
Poor Environmental Sanitation
Poor Internal Revenue Generation
Low Electricity Coverage
High Illiteracy Rate
High HIV/AIDS prevalence Rate
Inadequate Credit Facilities
Inadequate Office and Residential Accommodation
Inadequate Logistics for Monitoring of Projects and Programmes
Under-developed Tourism Potentials
High Incidence of Lawlessness
Inadequate Knowledge on socio-economic importance of Oil and Gas Issues
Low Production Level
50
1.5 DISTRICT PROFILE /CURRENT SITUATION OF THE DISTRICT
1.5.1 Physical and Natural Environment The physical and natural environments are essential elements of the factors for determining
socio – economic development of the district. This stems from the fact that, apart from
being potential resources, they also serve as ingredients within which all development
activities take place. The factors that need critical analysis and their implication for
development in the district under physical and natural environment include location and
size, climate, vegetation, relief and drainage, soil and geology and minerals.
1.5.2 Location and Size The Ellembelle District being one of the Twenty two (22) Districts in the Western Region of
Ghana is located on the southern part of the region between longitudes 2º05’ W and 2º35’
W and latitude 4º40N and 5º20N.
The District shares boundaries with the Jomoro District to the West, Wassa Amenfi West
District to the North, Nzema East Municipal to the South – East, Tarkwa – Nsuaem Municipal
to the East and a 70 km stretch of sandy beaches to the south. It covers a total area of
about 1,468 Square kilometers, which constitutes about 9.8% Percent of the total land mass
of the Western Region.
The District has one constituency, the Ellembelle Constituency with a total of Seven (7) Area
Councils and 31 Electoral Areas.
1.5.3 Climate The District lies within the wet semi-equatorial climatic zone of the West African Sub-
region. The area experiences an all – year round rainfall with the highest or maximum
monthly mean of rainfall occurring around May and June.
Mean Annual rainfall figures ranges from 26.8mm to 42.6mm. The average temperature
in the District is about 29.40C with variation in mean monthly ranging between 40C to
50C throughout the year as shown in the table for 2008 and 2008 below:
51
The high rainfall pattern and the long periods of the rainfall has resulted in the presence
of many rivers like Ankobra and Mufre in the District which can, using the right
technology, easily be harnessed to provide potable water and water transport the
communities.
They can also be a good source of Inland fishing as well as for irrigation farming in order
to provide employment and improve the nutritional status of the people.
The District records high relative humidity figures ranging from 27.6% to 26.6% between
May and June and 27.3% to 27.9 during the rest of the year.
The climate of the District is suitable for the cultivation of various crops both food and
cash. However the influence of the short dry spell (harmattan) has damaging effects on
the environment and farm outputs. The heavy and prolonged rains associated with this
type of climate adversely affect cocoa harvest especially drying of the beans and
aggravate the black pod diseases that attack cocoa. In addition, all the un-tarred roads
become almost immotorable during the rainy season. The effects of this on the economy
of the district are obvious.
1.5.4 Relief and Drainage The District is endowed with a number of rivers and streams, the most important of
which is the Ankobra River with its major tributaries like the Ahama and Nwini rivers.
Others like the Ankansa and Draw River and its Tributaries drain the Northern side and
act as a boundary between the District and Wassa Amenfi, Amanzule River in the south –
western area, and some numerous minor rivers and streams which do not exceed 150m
above sea level flow throughout the year. The streams and rivers exhibit a dendritic
pattern, which forms the Ankobra basin. The relief and drainage system favour the
development of fish farming and cultivation of valley bottom rice, sugarcane and dry
season vegetables. The presence of larger Rivers like the Ankobra has induced
commercial fish farming in communities along the Ankobra basin. Due to the relatively
low level of drainage in the district, construction such as road is relatively less expensive
and easier.
52
1.5.5 Vegetation The vegetation of the District is made up of the moist semi-deciduous rain forest in the
northern part of the District, but turns into secondary forest as one move southwards
mainly due to human activities like tree felling and farming. There is about 70km
coastline which is mainly of savanna vegetation. The District has several timber species
and other non-timber forest products like rattan, bamboo, among others. It also
abounds in game and wildlife all of which offer opportunities for resources extraction
and entrepreneurial development.
There are also three forest reserves in the District. These are Shelter Forest Reserve,
Draw River Forest Reserve (the largest and located at the Northern half of the District)
and the Ndumfri Forest Reserve located in the North Eastern end of the District.
However the existence of some nature conservation areas and biodiversity restricted
areas like the Ankasa Conservation Area and the Draw River at the Northern part of the
District. The Community Resource Management Area (CREMA) concept, by Wild Life
Division of the Forestry Commission is an initiative which will help curtail the
unsustainable usage of natural resources
The district has a rich diversity of fauna and flora, which has the potential of turning the
district into a major tourist destination in the country in particular and the globe in
general, if the needed tourist infrastructure such as good roads, hotels, restaurants and
communication facilities are made available. There is therefore a great potential to
generate huge revenue from tourism in the district using the forest resources and for
this reason; the District Assembly should be supported and encouraged to develop the
tourism industry into an investment attraction as an appropriate alternative revenue
earner.
1.5.6 Soil Type The soil in the District is mainly of the ferric acrisols and dysric fluvisols type. The
ferric acrisols type of soil constitute about 98% of the entire land of the district, as
such supports the cultivation of a wide range or variety of crops including cocoa,
coffee, coconuts, oil palm, plantain and cassava. Due to this characteristic, the
53
district has a comparative advantage in agriculture especially in the area of agro –
processing and plantations.
1.5.7 Tourism The District is endowed with a huge potential for Tourism development. There are
numerous tourist attractions that, if properly developed and packaged, could attract
a lot of tourists to the District. These include Historical sites like, the first President’s
(Dr. Kwame Nkrumah) birth place and original burial tomb at Nkroful, 70kms of
sandy Beaches that boarder the south of the District, the navigable Ankobra River
that links the northern and southern parts of the District through river transport, the
Wetlands and the famous Kundum Festival celebrated by all the Chiefs and people of
the District. The presence of developed beaches like Ankobra Beach Resort serves as
tourist destination which helps boost economic activities.
The Assembly must be supported to identify and facilitate the development of these
potentials through Public Private Partnerships (PPP). This would create employment
and enhance revenue generation in the District. It will also open up the district to
investment in the hospitality industry leading to the creation of various employment
opportunities. The recent emergence of the Oil and Gas in the Western coast of
Ghana and the Operation of mining companies such as the Adamus Resource Limited
has great potentials for the development of hospitality facilities (hotels) and beach
resorts in the coastal belt communities especially in Esiama, Asanda and Bobrama.
This will greatly give a boost to economic activities. The strengthening of security is
also fundamental since the development of the hospitality industry will come with its
ramifications such as crimes in the form of theft and arm robbery.
1.5.6 Condition of the Natural Environment The natural environment in the district is confronted with various challenges some of
which are very devastating as their impact on the natural environment also causes
food insecurity and exacerbating poverty in the district. The major factors that
54
negatively impact on the natural environmental condition include Deforestation,
Mining and Quarrying, Bushfires, Soil Erosion and Natural Disasters.
1.5.7 Deforestation The Ellembelle District is endowed with large tracts of forest and economic trees.
However, the District is suffering from high incidence of deforestation due to the
high exploitation of the timber for logs and lumber by registered companies and
illegal chainsaw operators. Their activities contribute significantly to the extent of
deforestation in the district. Unchecked farming practices including cocoa farming
slash and burns among others have also compounded the situation through
encroachment on the virgin forest and forest reserves.
1.5.8 Mining and Quarrying Due to the high mineral deposit in the district, a lot of mining companies are coming
into the district to mine. Galamsey activities are also dominant in the District which
is conducted in a haphazard or uncoordinated manner. The activities of these mining
companies and the galamsey operators are causing serious destruction to the
environment and the vegetative cover. This therefore poses threat to animal, plant
and human life in the District. With the help of the central government the galamsey
menace has been put under control. So far with the collaboration and assistance of
the district assembly, a small scale mining company has been licensed to operate
within the district. This development will create employment for the youth hence
reducing unemployment in the district whiles increasing the revenue of the district.
1.5.9 Bushfires and Soil Erosion The traditional method of farming, which involves the slash and burn, coupled with
indiscriminate burning of bush by unscrupulous people during the short dry season
(harmattan) exist in the district. The resultant effects of these activities are depletion
of soil nutrients and low agricultural production among farmers in the district.
55
1.5.10 CULTURE
1.5.10.1 Religion and Ethnicity In terms of Religion, Christians constitute about 79 % of the population with Moslems
having 8%, Traditionalists3.0 % and others 10%. The predominant Ethnic grouping is Akan
89%, Ga Adangbe 3%, Ewe 4% and Mole-Dagbani 4%. The District is dominated by two main
local groups within the following corresponding dominant Areas.
Table 4
1.1 Traditional Set-up
ETHNIC GROUP DOMINANT AREA
Akonu Nkroful
Nzema Atuabo
The District has one Paramountcy, The Eastern Nzema Traditional Council, situated at
Atuabo
All the Traditional Councils, in the three (3) Districts of Nzema East, Ellembelle, Jomoro,
constitute the Nzema Manle Council (District House of Chiefs).
1.5.11 Culture and Festivals One significant feature in the District is the traditional festival of Kundum which is
celebrated in all the communities of the District between August and October each year. It
is important to note that during the celebration of the festival, a large number of people
from far and near troop into town. During the season, general economic activities
(especially buying and selling) are boosted. However, the economic boom comes with its
own social and environmental impacts on the district.
The major language spoken all over the District is Nzema with other dialects like Evalue and
Gwira, Fanti and Twi also widely spoke
56
1.5.12 SPATIAL ANALYSIS / SETTLEMENT.
Various settlements have spread through the entire district. Larger portion of the
population is concentrated in the forest zone of the District. Considerable part of the District
which is mostly occupied by cocoa farmers (Northern Aiyinasi) is not accessible. These
developments normally compel farmers to sell their produce to other neighboring districts
to the detriment of the District’s Internally Generated Fund (IGF). The District is sparsely
populated. However, the population is not evenly distributed; only a few settlements such
as Aiyinasi, Esiama, Asasetre, Asanta etc. have the bulk of the population. Teleku-Bokazo
and Nkroful are gradually becoming overpopulated due to the emergence of mining
activities. This is as a result of concentration of certain amenities like electricity
In Ellembelle District, there are specific settlements of which are classified as Urban namely
Aiyinasi, Asasetre and Esiama. This is based on settlement with the population of 5,000
people as minimum. Esiama and Aiyinasi especially have the potential to grow into bigger
towns due the emergence of new economic and commercial activities. The location of these
communities along the Takoradi-Cote D’Ivoire makes them good prospects for increased
economic activities.
57
Annex 2: Scalogram Services
Settlements
Po
pu
lati
on
Kin
der
gar
ten
Pri
mar
y
JHS
SH
SV
ov
/Tec
h
CH
PS
/Cli
nic
Hea
lth C
entr
e
Ho
spit
al
Dru
g S
tore
Bo
reho
le
Pip
e S
yst
em/S
TW
S
KV
IP/V
IP
Pu
bli
c W
C
Ref
use
Bay
/S
kip
Con
tain
er
Ele
ctri
city
Tel
epho
ne/
Mobil
e
P:o
st O
ffic
e
Ru
ral
Ban
k
Po
lice
Sta
tion
Fir
e S
tati
on
Ag
ric
Ext.
Cou
rt
Mar
ket
Dis
tric
t A
dm
in
Are
a C
ou
nci
l
To
tal
No
. o
f
Fu
nct
itio
ns
%o
f F
un
ctio
ns
To
tal
Cen
trali
ty
Lev
el o
f
Hie
rarc
hy
Weight 1 2 3 4 2 3 5 1 3 4 1 1 2 4 2 1 3 2 2 2 4 4 5 4 Nkroful 4,043 X X X X X X X X X X X X X X X X X X X X X 21 88 1,564.
5
1
Teleku-Bokazo 4229 X X X X X X X X X X X 11 46 154.9 4 Anwia 1846 X X X X X X X X 8 33 59.6 5 Salman 2436 X X X X X X X X X X X 9 38 148.4 4 Aluku 904 X X X X X X X X X 9 38 36 5 Esiama 8,681 X X X X X X X X X X X X X X X X X X 18 75 531.2 2 Kumbunli 3,168 X X X X X X X X X X X X 11 46 308.6 3 Azuleloanu 1,346 X X X X X X X X 8 33 112.6 5 Ampain 1590 X X X X X X X X 8 33 59.6 5 A.B.Bokazo 1,407 X X X X X X X X X 9 38 59.6 5 Alabokazo 1,030 X X X X X X 6 29 44.5 5 Apkandue 1,131 X X X X X X X X X 9 38 119.6 5 Edwakpole 779 X X X X X X X X X 6 25 92.9 5 Awiebo 3,846 X X X X X X X X X X X X X 13 54 293.2 3 Baseke 3,097 X X X X X X X X X 9 33 92.9 5 Asasetre 4,763 X X X X X X X X X X X X X 13 54 272.2 3 Tandan 2,248 X X X X X X X X 8 33 59.6 5 Bomoakpole 1,219 X X X X X X X 8 33 77.8 5 Aiyinasi 10,585 X X X X X X X X X X X X X X X X 18 75 397.5 2 Menzezor 2, 221 X X X X X X X X X X X 11 46 252.9 3 Akoto 998 X X X X X X X X X 9 38 92.9 5 Kikam 3,839 X X X X X X X X X X X 10 42 216.9 4 Asanta 3, 753 X X X X X X X X X X X 11 46 219.9 4 Ankobra 1,758 X X X X X X X X 8 33 59.6 5 Atuabo 1,785 X X X X X X X X X X X X 10 42 250.2 4 Eikwe 2,349 X X X X X X X X X X X X X 11 46 655.2 3 Ngalekyi 1,247 X X X X X X X X 6 25 88.9 5 Krisan 1,098 X X X X X X X X X 8 33 92.9 5 Baku 1,019 X X X X X X X X X 6 25 92.9 5 Comm. With Serv. 30 29 27 6 5 5 1 24 30 12 26 4 7 30 30 3 3 3 1 2 1 12 1 7 Weight 100 100 10
0
10
0
10
0
10
0
100 10
0
10
0
10
0
10
0
10
0
10
0
10
0
10
0
10
0
10
0
10
0
10
0
10
0
10
0
10
0 10
0
10
0
Weighted
Centrality
3.3 7 11.
1
67 60 60 500 4.2 10 33.
3
4 25 29 13 7 33.
3
10
0
67 20
0
10
0
40
0
33.
3 50
0
57
58
1.5.13 Agriculture It is estimated that over 65% of the economically active population are engaged in
agriculture (including fishing) and agro-processing.
1.5.13.1 Land Most parts of the land in the district are undulating, therefore very unsuitable for
mechanized farming (use of tractors for land preparation). Share – cropping (Abusa) is the
common land tenure system.
1.5.13.2 Soils These are acidic and low in nutrient due to high leaching. Leaching is the result of the high
rainfall in the District. This makes it very difficult to cultivate some staple crops and
vegetables.
1.5.13.3 Cropping The average farm size is estimated at 4 hectares. Slash and burn is the common practice of
land preparation in the district. The major tree crops grown are coconut oil palm, rubber
and cocoa with cassava and plantain being the major food crops. Vegetables such as garden
eggs, pepper and tomatoes are also cultivated among other crops. Rice cultivation is
currently very low and is grown in some low-lying areas like Asanta, Kikam, and Kamgbunli.
Food crops such as cassava, maize, rice, cocoyam and plantain are grown extensively both
for subsistence and for cash. However, due to the absence of any efficient processing and
storage facilities, post-harvest losses are high and farmers income very low.
1.5.13.4 Coconut Sector Coconut is grown extensively in the district especially in the southern part. It is processed
into coconut oil and exported mainly to Accra, Kumasi, Tarkwa and Obuasi, and also farmers
export some of the produce called ‘Copra’ to nearby countries like Nigeria. In recent years,
the lethal yellowing disease of coconut locally called Cape St. Paul’s Wilt Disease (CSPWD)
has devastated about half of the coconut plantations along the southeastern coast of the
district. This has seriously affected the economic livelihood of the people in these areas,
59
leading to low incomes and increased unemployment. The dwindling production base of
the local coconut industry has also adversely affected the internal revenue base of the
Assembly.
Replanting of hybrid coconut seedlings for farmers in the district started in the year 2000.
So far estimated acres of farms have been replanted. However the report from farmers
suggest that its resistance it not strong to withstand the spread of the disease.
1.5.13.5 Rubber Rubber plantation is the new farming sector which is most people is resulting into. Due to
the presence of Ghana Rubber Estate Limited most farmers are able to learn technologies
which improve their outputs through the Out-grower Project. This development has given
some hope to farmers whose coconuts have been perished by the dreaded Cape & Paul
Disease.
1.5.13.6 Cocoa Cocoa is grown mostly in the northern part of the district, which is a forest area. This has
over the past years attracted in influx of cocoa farmers into these parts of the district. Crop
yield per acre for cocoa in these areas are comparatively lower. It is estimated that there
are over 70,000 acres of land under cocoa plantation in the district.
Capside infestation and the Black Pod disease are major problems of this crop. Productivity
has also been affected by lack of information on soil suitability. Efforts and new measures
have been put in place, especially the spraying of the farms, help improve the yield and
price of cocoa.
1.5.13.7 Poultry and Livestock Production Local poultry, especially chicken is reared throughout the district in almost every home.
However the local chicken population remains low because of annual outbreaks of
Newcastle Disease that results in high mortality among these birds. Commercial poultry
keeping is only undertaken by a handful of entrepreneurs whose major problem is marking
of their produce.
60
Pig production is the most popular livestock activity in the district, apart from sheep and
goat, especially among the youth and women. The availability of by-product from coconut
oil processing as a major cheap source of feed for pigs is the reason for their high population
in the district. In spite of the immense potential on piggery, farmers still use traditional
methods of husbandry and therefore cannot improve production to earn more income.
Intermittently the deadly swine-flu disease hit considerable number of flock and causes a
great loss to farmers. Pig production would be vigorously promoted to create alternative
employment opportunities through introduction of improved husbandry, processing and
marketing to improve farmers’ earnings.
1.5.13.8 Fishing and Fish Farming The District ranks among the major contributors in the area of marine fishing in the country.
Fishermen are located in communities like Ankobra, Asanta, Esiama and the whole of the
Atuabo Area Council. Though this venture is major source of income in the district, it is still
bedeviled by crude and outmoded method of operations like ‘Light fishing’ and the use of
harmful chemical have hindered the growth of the industry. In recent times the fishermen
has complained about dwindling level of fish-catch and attributed to Oil and Gas activities.
There is the need for revive this industry strongly through laid down measure to which will
ensure sustainable marine fishing, and also fisherfolks should embark on aqua-culture to
supplement the marine stock hence improve their income.
1.5.13.8 Manufacturing Industry The District though has experience some upward change in the area of industrialization,
same cannot be said in the aspect of manufacturing. The few manufacturing is still executed
through crude method and on a very small scale. Coconut Oil and Cassava dough
productions exist in communities like Asasetre, Tandan and Adubrim which helps to boost
the revenue generation base of these communities. However the industry is challenged
both logistically and financially and there is the urgent need of injecting the requisite
support into the industry to enhance local economic growth.
1.5.13.8 Energy The main sources of energy for domestic, commercial and industrial needs are electricity,
fuel-wood, charcoal (including bamboo, kerosene, and LPG). About 70% of the entire district
61
is connected to the national grid, with Majority of the Communities in the Northern part of
the district are yet to be connected. This situation has affected operation of basic services
like health care with facilities resulting to solar panels as an alternative.
1.5.13.9 Tourism Like most of the Coastal District in the western Region, tourism is a key source of revenue
generation. The Kundum festival is celebrated among all the Nzema’s to remember their
heritage. Traditional dance and other activities are performed during the celebration.
62
Kwame Nkrumah Mausoleum represents the original birth place and other historical
monuments of the First President of Ghana. Also the Bakanta Estuary has a nice scenery
which is been developed boat riding navigation. It forms part of the Greater Amanzure of
which series biodiversity studies has been conducted. Apart from fishing transportation the
Ankobra River has not been fully tapped.
Also the Gas Processing Plant at Atuabo is the first of its kind in the Country hence could be
a destination for educational tours and excursion.
63
1.5.14 Transport Infrastructure Majority of the road network that links the subdistricts to the District capital are tarred.
While the road network in the northern part of the district, that is, the New Aiyinase
Subdistrict is bad and unmotorable throughout the year and becoming more deplorable
especially during the rainy season. The roads that link the communities to the subdistricts
are also mostly untarred with some of them being bad and hard to reach hence creating
transportation problems for farmers.
The main means of transportation is by road and few communities along the Ankobra River
are accessed by boat. In total, the District has 233km of trunk road of which 66.1km are
tarred representing 28%, whilst 167.6 km is graveled or feeder road representing 72%. This
is hugely inadequate and affects development negatively.
The Assembly however has created an access road to link the North and Southern part of
the district but require the Feeder Roads Department to complete it. The absence of bridges
and culverts along some feeder roads also render some of the major food producing areas
inaccessible. There is therefore the urgent need to link up these areas to the marketing
centres through the provision of bridges and culverts.
64
1.5.15 Major Town and Facilities/Activities The District comprise of eighty- seven (85) communities. Few of these communities has
majority of the population and key infrastructural facilities.
Table 5: Major town and Facilities
Major Towns Main Facilities/Activities
Aiyinasi Market, Banks, Sachet water producers, Marine Police,
Esiama Banks, Market, Gas Transmission Terminal, Schools, Fishing, Hotels
Nkroful District Capital, Mining, Dr. Kwame Nkrumah’s birth place,
Kikam Fishing, Trading, Recreational centres
Atuabo Fishing, Gas Processing Plant
Teleku-Bokazo Mining, Trading, Market
65
The existence of these facilities enhances the general growth and development of the entire
district.
1.6 Food Security About 65% of the populations in the District are farmers (fish and crop farmers). In previous
years prices for food staff and other commodities were cheaper as compared to many
towns and cities. In recent times the mining activities and the oil and gas explorations have
changed situations over the past years. The above activities have affected farm lands
coupled with high influx of immigrants into the district; demand tends to outweigh supply
hence price hike in food especially fish and general consumables. Crop farming is done
throughout the year in places like Adubrim, Asomase and Akropong. The Assembly generate
considerable amount of revenue from market tolls from places like Aiyinasi and Asasetre.
1.7 Governance Administrative and Institutional Arrangements for Local Governance and
Management of Resources
The Structure of the District Assembly
The various legal frameworks for Local development in Ghana include, the Civil Service Law,
1993 (PNDC Law 327), the National Development Planning (System) Law, 1994 (Acts 480),
the Local Government Law, 1993 (Act 462) and the Local Government Service Act 656. All of
these legal enactments place the District Assembly in the center to reinforce the
government’s decentralization process and participatory development.
Thus the Assembly, by law is the highest administrative and political body in the District. It
is composed of 45 members of which two-thirds are elected while the remaining is
appointed. The one Member of Parliament is ex-officio member.
The Ellembelle District has an executive committee made up of chairmen and secretaries of
all sub committees and key heads of departments. They formulate and execute policies of
the Assembly. The District Chief Executive represents the Central Government and chairs
the committee. It operates through the following sub-committees of the Assembly
1) Finance and Administration Sub-Committee
2) Social Service Sub-Committee
66
3) Development Planning Sub-Committee
4) Works Sub-Committee
5) Justice and Security Sub-Committee
6) Health and Sanitation Sub-Committee
The sub-committees principally deliberate on specific issues and make commendations to
the Executive Committee. The Executive Committee in turn presents them to the Assembly
for ratification and adoption.
The Executive Committee co-ordinate plans and programmes of sub-committees and
oversees the smooth operation of the administration. It also has the power to recommend
the appointment or replacement of officials in the District. The District Assembly as
authority is responsible for the overall development of the District. There is a District
Planning Coordinating Unit, which provides Advisory services to the Executive Committee in
its planning functions.
Area Councils and Unit Committees are pivotal in local level development as they ferry the
Assembly and local community and act as the supreme points of development at the local
levels. There are seven (7) area councilsl.
The District Chief Executive heads the office of the District Assembly. There are 11
Decentralized Departments under the Office of the Assembly. The activities of these
Departments are coordinated by the District Co-ordinating Director.
67
DISTRICT DEPARTMENTAL ORGANOGRAM
DCE
Internal Audit
DCD
DPCU (DPO = Secretary)
Social Sector Infrastructure Sector
Financial Sector Environmental Sector Economic Sector
Education, Youth &
Sports Dept.
SW & CD
Dept.
District Health Dept.
Works Dept.
Physical Planning
Dept.
Trade, Industry & Tourism
Dept.
Agric Dept.
Disaster Prevention
Dept.
Natural Resources
Conservation
Treasury Revenue Mobilization
Education Section
Sports Section
SW Section
CD Section
DMOH Section
R. Birth & Death
Section
Building section
(Works & R. Housing)
Water Section
Feeder Roads
Section
T&CP Section
P&G Section
Coop Section
Industry Section
Fire Section
NADMO Section
Refugee Section
Game &
Wildlife Section
Forestry Section
Animal Health and Production
Section
Crop Services Section
Agric Extension
Section
Agric Engineering
Section
Fisheries Section
Youth Section
Basic Education
Unit
Non-Formal
Education Unit
Library section
Finance Dept.
Levies
Internal Disaster
Environ Health
Central Administration Dept.
Records
68
1.9 Composition of the District Assembly The Ellembelle District Assembly in consonance with the Local Government Act 1993 (Act
462) is composed of the District Chief Executive who is appointed by Government and
approved by 2/3 majority of the members of the Assembly, the one member of Parliament
from the one constituency of the District Assembly members. 54 Members both elected
and appointees form the General Assembly, of which 12 are appointed by government in
consultation with the Traditional Authority and other interest groups. The Presiding
Member is elected by 2/3 majority of all the members of the Assembly. There are 7 Area
Councils in all.
The adequacy of skilled Personnel and Logistics for the Decentralized Departments will have
serious repercussion on the Assembly’s capacity to implement, monitor and evaluate the
MTDP and undertake further participatory development planning. With the recent
increased in personnel for the DPCU, its work has seen some effectiveness, however,
logistics and resources must be provided for efficient operation.
1.11 District Sub – Structure There are seven (7) Area Councils under the Assembly, which are functioning effectively.
Out of all the Unit committees, less than a quarter are operational. Although, the Assembly
recruited and staffed all the Area Councils, its inability to pay their remuneration had
resulted in vacation of post and low morale among staff of the Area Councils. The lack of
Logistics and suitable offices has also resulted in low performance of the councils. Lack of
motivation on the part of Unit Committee members had led to loss of interest in the work of
the committees. Both Assembly members and the sub-structures play very crucial roles at
all levels of legislation and planning. As prescribed under Act 462 and L.I. 1589, the
functions of the Assembly through the Area Councils and Unit Committees make these sub-
structures pivotal links between the Assembly and the grassroots. However, the seeming
apathy at the sub-structure level has broken the chain of plan implementation making it
difficult to mobilize local persons for development. Capacity of the substructure is also not
up to task.
69
The Assembly should build their capacities to enable them collect and collate the views and
aspirations of the people they represent from interventions. This would ensure community
participation as an integral part of the planning process.
1.12 Traditional Authority The Ellembelle District has one paramountcy under the Nzema Manle Traditional Council
with its headquarters at Esiama. Under this paramountcy are Divisional Chiefs and below
them are Odikros. These Traditional Authorities command the respect of large numbers of
their people and communities particularly in the rural areas. They are dedicated to the
development of their traditional areas and the education and enlightenment of their
people. They have a part to play in facilitating government policies and mobilizing their
70
people for development, of particular importance is the role of the traditional authorities in
support of the vulnerable and excluded. This offers positive contribution to economic and
social transformation.
Traditional Authority can therefore be regarded as part of the decentralization process. The
District Assembly would therefore strengthen its partnership with Traditional Authority to
provide a mechanism for consultation and co-operation.
Although Traditional Authority plays a very important role in the development of the
District, the existence of one paramountcy within the Ellembelle District alone poses a big
challenge for consensus building. The presence of numerous chieftaincy disputes and land
litigations have adversely affected the pace of the District’s development. Efforts would be
made to minimize these disputes and promote consensus building.
1.13 Administration of Justice The District has a magistrate court with a magistrate in attendance. There are three (3)
Police Stations with the headquarters at Esiama. The Commission for Human Rights and
Administrative Justice (CHRAJ) adjudicates on human rights infringements whereas the
Public Relations and Complaints Units under the Chairmanship of the Presiding Member of
the District Assembly hears complaints against Assembly members and Public Officers in the
performance of their duties. The magistrate court currently has no permanent
accommodation which affects it duties. The assembly has initiated the process to construct
a court complex to foster administration of justice.
The institutions especially CHRAJ need to be strengthened and resourced to protect the
rights of the people and ensure justice and accountability. The District needs a permanent
structure well-resourced to accommodate the magistrate court. This will go a long way to
facilitate justice.
1.14 NGO/Civil Society Civil Society plays a very important role in the development of Ellembelle District.
Participation by other stakeholders is manifested at the levels of information sharing,
consultation, collaboration and empowerment. To ensure public ownership of the
Assembly’s development agenda, it is necessary that avenues be created for stakeholders
71
and other parties with contributions to get involved in the whole process. This is the
effective way to generate true sustainability and public support for the development
process.
The District Assembly has instituted channels for consultations with stakeholders at the
District, Area Council and Community levels. These include Public fora and information
dissemination and Public education by I.S.D and NCCE. A number of initiatives have been
undertaken to promote participation of other stakeholders especially NGO’s, CBO’s, and the
Private Sector in the development process of the district.
1.15 7PRIVATE SECTOR The Private Sector is not well developed in the district. It is predominantly micro and small-
scale Processors, Artisans and Service Providers. Although the District has enormous
potential for tourism and agro-industry, the lack of Infrastructure and basic utilities
increases cost of doing business. There is no platform for public-private interface
Public-Private Partnership needs to be promoted. The Assembly would create the necessary
enabling environment for the growth of the private sector. Inadequate logistics and poor
accessibility have cut off a significant number of people in the district from active
participation in governance and access to information.
There is therefore an urgent need for a mass communication network e.g. F.M. with wide
coverage to facilitate information dissemination and public education in the district in order
to reach a wider section of the people especially the unreached deprived communities. The
Assembly’s has made useful strides to make the planning process participatory to promote
transparency in the Assembly decisions and ensure accountability from both public and
private sectors. More collaboration, consultation and information sharing would be
promoted with Traditional Authority, Civil Society of Ellembelle District as well as the
Western Regional Network of NGO’s (WERENGO) and other relevant private sector
organizations
5.8 Assembly Finance
Internal Sources (own sources)
External Source
72
2011 2012 2013 TOTAL
DACF 2,239,676.78 886,981.61 1,108,177.82 4,234,836.21
IGF 359,798.78 881,915.02 315,245.55 1,556,959.35
HIPC FUNDS 40,311.00 292,978.16 - 333,289.3
GOG GRANTS 161,858.05 - 227,878.3 389,736.35
DONOR GRANTS
302,234.30 457,592.27 636,378.38 1,396,204.95
TOTAL REVENUE
3,103,878.91 2,519,467.06 2,287,580.05 7,910,926.02
Source: District Assembly Annual Trial Balance (2012-2013)
Internal revenues are those collected by the Assembly using its own Revenue Collectors and
existing collection machinery. External sources on the other hand are mostly grants from
Central Governments, Royalties, and other External Agencies like NGO’s and Donor Agencies
like the World Bank, IDA, JICA, EU, DFID etc. The trend, typical of most Assemblies in the
country, depicts the over reliance of the Ellembelle District on the DACF as the main source
of revenue and funding of development projects and other programmes.
Problems of Revenue Collection The major problems confronting revenue collections in the district include:
Inadequate skilled personnel
Lack of logistics especially transportation to revenue collection centers
Poor supervision and monitoring of revenue collectors
Inefficient revenue collection systems
Inadequate motivation for revenue staff.
Expenditure Pattern The Expenditure of the district budget has been divided into recurrent and capital
Expenditure to conform to the conventional budget structure of the local government of
Ghana. The recurrent expenditure consists of personal emoluments, Travel and Transport
Expenditures, General expenditure, maintenance, repairs and renewals as well as
73
miscellaneous. The capital expenditure consists of all expenditures made on Development
Projects and Programmes.
Challenges
A whole lot of deductions are made of funds sent thus making disbursement very
difficult as funds become inadequate to disburse according to the prepared.
Lack of flexibility in the usage of DACF affects disbursement
NOTE: A table depicting a summary of expenditure within the plan period has been
captured at performance review stage.
1.16 Local Economic Development The District in terms of Local Economic Development performed fairly during the
implementation of the GSGDA I. The Assembly in its efforts of encourage local initiative
through the transfer of skills has trained some community members in Kumgbunli, Eikwe
and Nkroful in batik making, beads making and soap making.
Also IMBAR has undertaken a bamboo development project ‘Bamboo as biomass for
charcoal production, for Tandan Community. This initiative in the long would improve the
living standard of the beneficiary community and its adjourning communities.
However, some development potentials likes presence of Wetland, Forest Reserves, Rivers,
vast bamboo resource and cultural practices like Kundum festival can be developed as
tourist destination which would generate income for the local economy.
Also coconut producers should be trained on the various uses of Coconut husk, doormat,
interior designs etc. through the Business Advisory Center (BAC). These initiatives would
help generate employment.
1.17 ACCESSIBILITY TO SOCIAL SERVICES
Educational Characteristics Educational Facilities and Enrolment Levels (2013/2014)
Table 6 Education Facility
74
NO. FACILITY NO. IN DISTRICT
1 Pre-school 108
2 Primary school 96
3 JHS 68
4 SHS 5
5 Technical/Vocational 2
6 Special school (Eikwe) 1
Source: GES, Ellembelle Directorate, 2013
The chart above depicts a considerable number of facilities at the Primary and JHS level that
is 34% and 24% respectively. However it reduces drastically to 2% at the SHS level. This
situation has contributed to the low human resource base of the District, therefore the need
for conscious effort to increase facilities at the higher levels especially at SHS.
39%
34%
24%
2% 1% 0%
BREAKDOWN OF EDUCATIONAL FACILITIES
Pre-school Primary school JHS
SHS Technical/Vocational Special school (Eikwe)
75
1.1.2 ENROLMENT by Gender (2013/2014) NO CATEGORY OF SCHOOL ENROLMENT
BOYS GIRLS TOTAL
1 Pre-school 4004 3993 7997
2 Primary 8564 7986 16550
3 JHS 3024 2754 5778
1.1.3 TEACHER POPULATION: trained & untrained (2013/2013)
CATEGORY OF
SCHOOL
TRAINED TEACHERS UNTRAINED
NO MALE FEMALE TOTAL MALE FEMALE TOTAL
1 Pre-school 2 47 49 18 179 197
2 Primary 287 62 349 277 128 405
3 JHS 200 25 225 159 18 177
TOTAL 489 134 623 454 325 779
It is worthy of note that majority of Teachers in the District are untrained. Of the total
number of 1402 teachers teaching at all levels in the District, only 44.44% (623) are trained.
56.56% (779) are untrained. Those trained and untrained for primary are 349 and 405.
Junior High School, 225 and 177 for trained and untrained respectively.
This situation does not auger well for the development of education in the District and
conscious efforts must be made to address underlying cause of the problem in order to
attract qualified teachers to the district.
76
1.17 Youth and Sports With a dynamic youthful population of about 62%, there is the urgent need for the District
to create a conducive and enabling environment for the youth to channel their energies and
not dissipate it in wasteful ventures.
Sports development has been identified as a major tool for recreation and well-being as well
as economic development. The District has a number of Football and Volley ball teams but
woefully lacks basic sports infrastructure. There is virtually no standard football field as well
as facilities for other sports like basketball, volley ball, badminton, table tennis among
others. These need to be addressed in collaboration with the private sector to promote
sports. The District Assembly would have to facilitate development of sports to promote
employment and tourism and enhance health and also as a tool for and JSS in particular
might portray the picture that teachers are underutilized in the District. It again goes to
buttress the earlier fact that school participation rate is low in the District,
Below is the educational map of Ellembelle District
77
78
1.18 HEALTH SITUATION HEALTH FACILITIES AND DISTRIBUTION
The District has the following Health Facilities
Hospitals - 1
Health Centers - 4
Clinic - 8
CHPS Compound - 11
Health Training Institutions - 2
Total - 26
1.18.1 Health Structure Health facilities in the district according to location, ownership and officer in charge
No Facility Location Ownership Personnel In
Charge
1 St. Martin de Porres
Hospital
Eikwe Catholic Church(CHAG) Medical Doctor
2 Aiyinasi Health Centre Aiyinasi Ghana Health Service Principal Medical
Assistant
3 Esiama Health Centre Esiama Ghana Health Service Deputy chief
Medical Assistant.
4 Nkroful Health Centre Nkroful Ghana health service Principal
Midwifery officer
5 Asasetre Health Centre Asasetre Ghana Health Service Senior Midwife
6 AlhajiNuhu CHPS
Compound
Kamgbunli Ghana Health Service Community health
Officer
7 Aidoosuazo CHPS
compound
Aidoosuazo Ghana Health Service Community Health
Officer
8 Kwesikrom CHPS
compound
Kwesikrom Ghana Health Service Community Health
Officer
9 Asomase CHPS compound Asomase Ghana Health S CHO
79
10 Adom Clinic Awiebo Private Principal Nursing
Officer
11 A.B. Bokazo community
clinic
A.B. Bokazo Private Principal Nursing
Officer
12 Nana Benie Memorial
Clinic
Menzezor Private Medical Doctor
13 Refugee Clinic Krisan Refugee
Camp
UNHCR Nurse
14 Word Alive Community
Health Nursing School
Esiama Ministry Of Health Deputy Director of
Health service
15 Health Assistant Training
School
Asenda Seven Day Adventist
Church
Principal Nursing
Officer
16 Ellembelle Mobile clinic Esiama Ghana Health Service Medical Assistant
17 NASS School Clinic Nkroful Ghana Health Service CHN
18 Ananekrom CHPS Ananekrom Ghana Health Service CHO
19 AwulaeBlay II CHPS Atuabo Ghana Health Service CHO
20 Asanta CHPS Asanta Ghana Health Service CHO
21 Salman CHPS Salman Ghana Health Service CHO
22 Refugee Clinic Ampain
Refugee Camp
UNHCR Nurse
23 WARA Clinic Adamus Site West Africa Resource
Associate (WARA)
Nurse
24 Akropong CHPS Akropong Ghana Health Service CHN
25 Nyamebekyere CHPS Nyamebekyere Ghana Health Service CHN
26 Sanzuley CHPS Sanzuley Ghana Health Service CHN
80
1.18.2 MAIN PROBLEMS OF THE HEALTH SECTOR IN THE
DISTRICT
The key problems of the health sector in the district include the following
1. Poor access to communities in the northern part of the district as a result of
inaccessible road network making some communities hard to reach.
2. Aged vehicle which needs major repairs.
3. Inadequate residential accommodation for DHA staff.
4. No permanent administrative block for the directorate.
5. Inadequacy of basic equipment in some facilities.
1.18.3 KEY ACHIEVEMENTS
The activities undertaken contributed significantly in achieving the following:
• The district managed to train 10 Maternal Health Volunteers in Esiama Sub district
and they are providing FP services in Cycle beads.
• The district also recorded a Significant increase in ANC 4th visits and average visit in
the year as against that of the previous years
• Implementation of IRS for malaria control with the support of AGA mal in progress
• There has also been relative improvement in NHIS coverage among patients in the
district during the period.
• Opening of three new CHPS compound during the period.
• A strong collaboration with the District Assembly resulted in a new DHMT block
provided by the Assembly, though very congested with associate problem of flooding
during heavy rains.
• Two motorbikes have been procured for New Aiyinase sub district.
• The frequently broken down refrigerator at Esiama have also been repaired during
the year.
• Construction of OPD block at Nkroful Health Centre by the Chief and the people of
Nkroful.
81
1.18.4 OPD CASES.
Malaria continues to remain the number one cause of outpatient morbidity. It accounted
for 37% out of the total new cases 360721 recorded by all the facilities in the district in the
year 2013.
It is always the number one cause of OPD attendance in all the health facilities and among
all age groups due to poor sanitation and frequent rainfall. It also accounts for most of the
admissions and deaths especially among children at the only hospital in the district, St
Martin de Pores at Eikwe.
Ten Top diseases of OPD attendants for 2013
No Conditions Number Percentage
1 Malaria 132984 37.0
2 Acute Respiratory Infections 45085 12.0
3 Rheu. & Other Joint Pains 22831 6
4 Skin Diseases & Ulcer 22444 6
5 Diarrhea Diseases 19222 5
6 Intestinal Worms 12710 4
7 Gynaecological conditions 10735 3
8 Anaemia 6220 2
9 Acute UTI 4714 1
10 Acute Eye Infection 3873 1
ALL OTHER DISEASES 79903 22
TOTAL 360721 100
Source: GHS, Nkroful
82
1.18.5 Health Financing With the introduction of the Mutual Health Insurance Scheme in all Districts throughout the
Country, Medical Services are affordable to the majority of the people in the District. This is
reflected in the attendance rate at most Medical Facilities in the District which has improved
tremendously. For example Eikwe Hospital recorded Average daily OPD Attendance 320
patients in 2013 which shows an improvement over the 2012 figure of 258. Still a greater
number of people, especially those in the Rural Areas, continue to rely on alternative Health
Care Systems or delayed till the situation gets complicated. This is evidenced by the trend
of Malaria, a preventable and curable disease always topping not only the cause of
morbidity and admissions but also deaths.
Graph depicting NHIS coverage among OPD attendance (2011-2013
The poor drainage coupled with excessive rainfall and other human practices have resulted
in extensive erosion and flooding within the built environment. Communities would be
encouraged to undertake erosion prevention activities like tree planting, landscaping and
the de-silting of drains. The Assembly would also explore innovative low cost appropriate
technologies for housing delivery and pilot these through a Rural Housing Scheme.
Below is the map of Health facilities coverage in the District.
71
66
69
63
64
65
66
67
68
69
70
71
72
2011 2012 2013
83
1.19 Water and Sanitation
1.19.1 Water Facilities The water situation in the District has seen some improvement over the years with an
increase in the number of facilities and coverage.
At the end of the plan period the District aim at providing Small Town Water systems for
communities like Asanda and Ankobra and borehole facilities for all communities at the
Aiyinasi North (2014 - 2017).The current water overage is……. With these facilities made up
of 22 pipe systems, 134 boreholes, and 8 hand-dug wells, and 79 kvip, 1,040 vips and 369
84
WCs. The details of these facilities are depicted in the matrix in the tables below. This gives
a through picture of the current coverage of the population which then assisted in the
selecting the communities that need specific water facilities in the district.
Existing Water & Sanitation Facilities in the District.
AREA COUNCIL No. OF BOREHOLE
No of HAND DUG-WELL
No. of PIPE SYSTEM
Asasetre 17 1 5
Atuabo 23 3 6
Kikam 16 - 2
Esiama 16 - 1
Nkroful 27 4 2
Aiyinasi 18 - 3
Awiebo 17 - 3
TOTAL 134 8 22
85
1.20 VULNERABILITY ANALYSIS Vulnerability Analysis is the process of assessing the ability of an individual or group to
withstand shocks or manage risks, the probability of becoming poor or poorer. This could
come as a result of the following factors- political, social, environment, economic, or
physical.
The continuous migration of the economic class to Takoradi, Tarkwa and Cote D’voire is a
trend which should be curtailed. Also due to the seasonal nature of fishing activities at the
coast compel people to travel to cocoa producing area to engage in economic activities.
The fast growing of the social class system also contribute to the fast migration trend in the
District. Social problems such as child labour, child trafficking, Streetism and disability occur
86
as a result of the abuse. Child poverty is also rife in the district. Child neglect due to single
parenting, divorce or both is also common. Most often than not resulting in social vices
such as theft, drug abuses, teenage pregnancy among several others are on the rise. This
has serious implications for the district development, since its future productive capacity is
at risk. The district will forge cutting edge social interventions to address the menace. In
recent times the economy of the district is threaten by increased cost of living due to influx
of foreigners and national alike in to the district resulting from the gold mining as well as the
oil and gas exploration.
1.21 HIV/AIDS The table below illustrates the current trend of HIV/AIDS cases diagnosed at the St Martin
de Porres Hospital at Eikwe 2012 to 2013 and confirmed at the Regional Public Health
Reference Laboratory. H
HIV/AIDS CASES recorded at Jan-Dec. 2013
Category No. Tested No. Positive Percentage Positive
PATIENTS 1965 472 24
Blood Donors 2043 123 6
VCT 12 0 0
PMTCT 2071 63 3
Total 6091 658 10.8
The HIV/AIDS Prevalence rate of 10.8% among hospital attendants and 0.76% for the entire
district shows an improvement over the previous years. It is however worth noting that
these are only the reported cases at the Hospitals. With the limited access to medical
facilities coupled with the high illiteracy rate and the fear of stigmatization, the real
magnitude of the problem may be under estimated.
87
The plight of the District is worsened by its close proximity to La Cote D’ Ivoire, a high
prevalence area, and the regular interactions between their peoples. The seasonal influx of
migrant fishermen and farm Labourers into the District further compounds issues.
Efforts at addressing the problem have so far been limited to publicity campaigns, fora,
seminars to sensitize various target groups on responsible behavior and safe sex. The
District has a District Population Advocacy Team which undertakes advocacy on Population
and Development issues including HIV/AIDS. There is also a District Aids Committee under
the District Response Initiative which co-ordinates HIV/AIDS Programmes and activities in
the District. The activities of NGOs like Ransom Foundation and End-Time Restoration
Ministry, Life Relief Foundation have improved HIV/AIDS awareness through Voluntary and
Counseling Test. (VCT)
Lack of funding for HIV/AIDS Programmes in the District has constrained efforts at
addressing the challenge. Nonetheless, as the problem has now assumed the dimension of
a development issue, the District would solicit for assistance from its Development Partners
and other Agencies in confronting the issue. Advantage would also be taken of the
establishment of the GARFUND to provide additional funding to combat the HIV/AIDS
menace in the District.
1.22 GENDER The District has its most economically active population been the youth, both male and
female who are not discriminated upon in terms of various roles and responsibilities.
Both women and men have equal opportunities in relation to working at within the formal
sector. However people acquire employment opportunities based on their expertise.
Holistic approaches of community participation (old, young, male & female) are deployed as
part of development processes.
Few numbers of women (both old and young) earn their living through petty trader at
‘galamsey sites’. Traditionally women plays significant role in governance system with some
communities having Queen mothers as part of their governance system. It is also important
to acknowledge the fact that there no enough women representation in the General
Assembly of the district assembly.
88
1.23 INFORMATION AND COMMUNICATION TECHNOLOGY (ICT) ICT until recent times were is in a very poor state. The recent inclusion of ICT in schools that
is Junior High School and Senior High School has improved. The sprung up of internet cafes
and computer schools has boosted peoples interest in information technology.
Esiama and Aiyinasi are two larger communities who are benefiting from government
commercial ICT Centre. The Aiyinasi Community Information Centre (CIC) is a UNDP Funded
facility which students in the District benefits from. Nkroful has also benefited from an ICT
project. Eikwe and Ngalekyi have not also be left out.
With the emergence ‘white-color’ jobs like mining and recently Oil companies’ activities is,
most people are ready to upgrade their knowledge in Information Technology.
However about 70% of the total population does not have access to Computer, with
majority of these people living in the forest areas.
The extension of electricity to the most of communities would propel people to invest in
Information and Communication Technology (ICT) thus improving IT knowledge in the long-
run
1.24 SECURITY Until 2014, the Ellembelle district was under Nzema East district when it comes to security
(Police). It is obvious that with the emergence of oil and gas activities and gold mining in the
district, the tendency for increased criminal activities cannot be overemphasized. Social
vices such as theft, teenage pregnancy, drug trade among several others are on the rise. It
is against this backdrop that the district fought for its own police command. The District
currently has a police command, headquartered at Esiama. This development has helped
curtail or reduced crime and criminal activities which hither to was on the ascendency.
Conducive environment has been created for investment as well as protection of lives and
property. The assembly is has also initiated a move to get a fire station, immigration and
other security agencies into the district.
1.25 DISASTER The assembly is located in a forest area hence it records almost all year round rainfall. This
situation causes occasional flooding especially at the peak of the raining season between
89
April and July. During this season there are economic downturns since farmers especially are
unable to access their farms and fishing activities also slow down. It is important to mention
that the district has NADMO officials who are the point of call in disaster situations.
1.26 WATER SECURITY Access to potable water has improved drastically over the years. Most people in the
southern part of the district have unfettered access to water. There are a lot of small town
water systems in the district as well as boreholes. With the exception of the Nkroful water
which is of poor quality due to high iron content, almost all other water sources are
acceptable and of high quality. Notwithstanding this, the northern part of the district faces
serious challenges when it comes to potable due to inaccessible roads, which hinder drilling
vehicles to reach that part of the district. This development affects the health of the
residents of the northern part of the district with occasional OPD cases of water borne
disease. Generally speaking the district is about 90% covered in terms of potable water
access. This situation has help eradicate all curtail water borne disease in the district and
has improved the economic and social lives of the people.
1.27 MIGRATION (IMMIGRATION & EMIGRATION) The district in recent times has seen an increase in population due to influx of large number
of people. The strategic location of the district coupled with its richness in mineral deposits
has seen large number of foreigners and nationals move in to settle. At the peak of this
population increase was the era of the ‘Galamsey’ (illegal mining) activities which also saw
the population of the district doubled. There are also large portions of the people who are
settled in the neighboring Cote D’Ivoire who come home occasionally, especially during
festive occasions.
90
2.0 CHAPTER TWO
2.1 Prioritization of Development Issues The preparation of the District Medium Term Development Plan makes it vital to have a
group of some of the development gaps of the district for the issues to be addressed.
The Chapter Two highlights the harmonization of community needs and aspirations as
captured in the planning guidelines (GSGDA II 2014-2017) with identified development gaps
in the performance review of the GSGDA I The output therefore would be would be linking
of priorities to the thematic areas of the GSGDA II 2014-2017 MTDPF.
The District Development Priorities were selected taken into consideration the District
limited financial and human resource as well as the Plan Implementation Period
The selection was done through a stakeholder consultation guided by the following criteria
in the guidelines for the preparation of the DMTDP under the GSGDA II (2010-2013)
Impact on a large proportion of the citizens especially the poor and the vulnerable.
Significant linkage effect on meeting basic human needs/rights.
Significant multiplier effect on the local economy.
Spatial location.
Opportunity for promotion of cross-cutting issues.
OUTCOME OF COMMUNITY ENGAGEMENT FOR THE MTDP (2014-
2017)
AREA COUNCIL: NKROFUL EDUCATION.
S/NO ISSUE LOCATION/COMMUNITY
1. Construction of drainage facility at the entrance of cluster of schools at Tema
Nkroful
2. Need to create aware on the need for vocational education.
Nkroful
3. Provision of library facilities for basic school at Nkroful Nkroful
4. Provision of science laboratories for basic schools at Nkroful
Nkroful
5. Provision of teachers quarters at Nkroful Nkroful
91
6. Construction of additional school block for Salman. The existing school is overcrowded.
Salman
7. Construction of SHS for Salman and its environs Salman
8. Salman community library has not books hence the need to stock the library with learning materials
Salman
9. Construction of KG and Primary block at Obengkrom. Students trek long distance to attend school at Salman
Obengkrom
10. Construction of Primary and JHS at Aluku Aluku
HEALTH
1. Provision of antenatal and maternity services for Salman electoral areas. Surrounding communities in Salman electoral areas have no access to such service. Women in labour have to be carried on motorbikes to access maternity services at Salman.
Obengkrom, Aluku, Angagyale, Angloga success, Tombusolo, Nsiah-Krom
2. There is the need to provide Traditional Birth Attendant (TBA) in communities around Salman.
Obengkrom, Aluku, Angagyale, Angloga success, Tombusolo, Nsiah-Krom
3. Salman Health Center needs additional staff (nurses) Salman
4. Intensify education on preventable diseases Nkroful
ROAD INFRASTRUCTURE
1. Construction of road (access routes) for all communities within Salman electoral area. The major problem within these communities is access and these affect all other activities.
Obengkrom, Aluku, Angagyale, Angloga success, Tombusolo, Nsiah-Krom
2. Rehabilitation of Salman-Teleku Bokazo road Salman
3. Rehabilitation of Nkroful town roads Nkroful
AGRICULTURE
1. Supply of agro chemical for farmers within Salman electoral area. Farmers to have no access agro-chemical and this affect their productivity.
Salman, Obengkrom, Aluku, Angagyale, Angloga success, Tombusolo, Nsiah-Krom
2. Intensify education of farmers on improved systems of farming
Nkroful
3. Steps must be taken to help salvage the red maize specie which faces extinction in the district.
Nkroful
4. Need to encourage the youth to go into farming. Nkroful
WATER & SANITATION.
1. Refuse management/disposal is a big challenge to the community. There are no refuse collection containers as well as a final disposal site.
Salman
2. The communities in Salman electoral area have no access to potable water
Obengkrom, Aluku, Angagyale, Angloga success, Tombusolo, Nsiah-
92
Krom
3. Provision of additional refuse containers at Nkroful Nkroful
4. Measures must be taken to build communal spirit to deal with sanitation.
Nkroful
5. Construction of drainage system in Nkroful community
Nkroful
6. The Nkroful water quality should be improved upon Nkroful
SOCIO-ECONOMIC
1. Teenage pregnancy is on the ascendancy. Most children of school going age get pregnant and the laws do not deal with such culprits.
Salman
2. The Salman community market has been abandoned since its construction. The assembly should assist in its commissioning or opening.
Salman
3. Construction of a community library for Nkroful Nkroful
4. Construction of a community centre at Nkroful Nkroful
5. Involvement of community in planning and celebration of founders’ day (Osagyefo Day)
Nkroful
6. Provision of a modern market centre for Nkroful Nkroful
7. Opening of Ghana Commercial Bank branch at Nkroful Nkroful
KIKAM AREACOUNCIL.
EDUCATION. (PRIROITY 1)
1. Rehabilitation of catholic JHS/KG at Asanta and SDA Primary school
Asanta
2. Completion of computer laboratory at catholic school. Asanta
3. Rehabilitation of Bobrama KG block Bobrama
4. Provision of furniture (desk) for all schools Bobrama, Asanta , Ankobra
5. Renovation of Ankobra primary school Ankobra
6. Rehabilitation of Asemko primary school Asemko
7. Completion of community library for Asemko Asemko
8. Construction of storm drain from SDA school to Methodist school
Kikam
HEALTH (PRIORITY 2)
1. Provision of pavilion for Asanta CHPS Asanta
2. Construction of nurses staff quarters Asanta
3. Rehabilitation of existing structure to be used as CHPS compound
Kikam
AGRICULTURE (PRIORITY 3)
1. Revamping of Aiyinase and Esiama oil mills Esiama, Aiyinase
2. Supply of improved and resistant coconut seedlings District wide
3. DA should be proactive in solving coastal/ fishing problems. Involvement of key stakeholders to solve problems.
District wide
4. Supply of farm inputs for poultry farmers District wide
5. Provision of agro-chemicals for farmers district wide
93
6. Streamlining of premix fuel supply
WATER AND SANITATION. (PRIRORITY 5)
1 Construction of sea defense along the Esiama-Ankobra beaches
Esiama, Ankobra, Bobrama, Asanta
2. Construction of toilet facility an Ankobra Ankobra
ROAD INFRASTRUCTURE (PRIRORITY 6)
1. Construction of culvert along the main road Asanta, Ankobra, Bobrama
2. Construction of speed ramps/Passover at Asanta Asanta
3. Reshaping of Asanta north/extension of road ASANTA
SOCIO-ECONOMIC (PRIORITY 4)
1 Education on teenage pregnancy Asanta, Bobrama, Ankobra
2 Provision of vocational and technical training education especially for school drop outs.
Bobrama. Ankobra, Asanta
3. Provision of alternative sources of livelihood. Bobrama, Asanta, Ankobra
4. Construction of market shed for Asemko community Asemko
5. Construction of town roads Kikam
ASASETRE AREA COUNCIL
EDUCATION.
1 Extension of school feeding programme to cover all communities with the Asasetre area council.
Asasetre area council.
2 Construction of teacher quarters at Adubrim Adubrim
3 Completion of Adubrim school (GETFUND) project for Primary, JHS and KG
Adubrim
4 Institute school feeding programme at Ngabawie Ngabawie
5 Construction of school block at Ngabawie Ngabawie
6 Construction of teachers quarters for Mempeasem Mempeasem
7 Institute incentives for teachers at Adubrim Adubrim
8 Revamping the ICT center at Asasetre Asasetre
9 Supply of teaching and learning materials for school within the area council
Asasetre area council.
ROAD INFRASTRUCTURE
1. Construction of road from Aiyinase to Beposo Aiyinase, Beposo
2. Construction of access road at Ngabawie, Ayawora and Mempeasem
Mempeasem, Ngabawie, Ayawora.
WATER AND SANITATION
1. Provision of boreholes for all communities Asasetre electoral area
2. Construction of toilet for other communities. Mempeasem, Ngabawie, Ayawora
3. Provision of potable water for Mempeasem, Ayawora and Ngabawie
94
4. Construction of toilet facility for Adubrim and other communities
Adubrim electoral area
5. Public education on the need to observe proper sanitation especially among food vendors
District wide
5. Stray animals should be arrested Adubrim electoral area.
AGRICULTURE
1. Supply of agro-chemicals (fertilizers, weedicides, pesticides etc)
Adubrim electoral area
2. Capacity building on improved farming systems Adubrim electoral area
3. Construction of bridge on Nreni river
SOCIO-ECONOMIC
1. Extension of electricity to New Sanfo New Sanfo
2. The need to intensify education on teenage pregnancy Asasetre electoral area
3. Construction of market shed
4 Extension of electricity coverage to Adubrim zone Adubrim and environs
AWIEBO-BASEKE AREA COUNCIL.
EDUCATION (PRIORITY 2)
S/NO. ISSUES LOCATION/COMMUNITY
1. Provision of additional KG and primary block and renovation of existing one at Baseke
Baseke
2. Construction of Methodist JHS block at Awiebo. Awiebo
3. Renovation of Roman Catholic Primary school at Awiebo
Awiebo
4. Construction of teachers quarters at Awiebo Awiebo
5. Construction of Bungalow and security wall at BOKASS
Awiebo
6. Completion of classroom block at BOKASS Awiebo
7. Completion of Awiebo Roman Catholic KG block Awiebo
8. Construction of new school block for Mantukwa Bibianiha and Domeabra
Mantukwa Bibianiha and Domeabra
9. Construction of JHS block for Baseke Baseke
10. Construction of teachers quarters for communities Mantukwa, Ebi and Awiebo
11. Construction of library for Baseke and Awiebo Awiebo, Baseke
12. Construction of school block for KG and Primary school at Edwakpole
Edwakpole
13. Completion of KG block at Akpandue and renovation of primary school
Akpandue
14. Construction of teachers quarters for A.B Bokazo and toilet facilities for school
A.B Bokazo
15. Construction of ICT facility for A.B Bokazo A.B Bokazo
16. Construction of JHS, teachers quarters and toilet facilities at Alla Bokazo
Alla Bokazo
HEALTH (PRIORITY 3)
1. Construction of CHPS for Mantukwa electoral area Mantukwa , Domeabra
95
and Domeabra
2. Construction of health facilities in communities Baseke, Awiebo, Ebi
3. Upgrade CHPS compounds to health centers Awiebo, A.B Bokazo
WATER AND SANITATION (PRIORITY 4)
1. Supply of refuse containers for Awiebo and Baseke Baseke, Awiebo
2. Construction of toilet facility and construction of additional two at Baseke
Baseke
3. Construction of toilet facility at Ekenyamzo and Awiebo junction
Ekenyamzo, Awiebo junction.
4. Construction of borehole at Ekenyamzo Ekenyamzo
5. Provision of potable water (hand dug well at Mantukwa
Mantukwa
6. Provision of hand-washing basin for Awiebo zone Awiebo electoral area.
7. Provision of potable water at Edwakpole Edwakpole
8. Provision of toilet facility at Alla Bokazo Alla Bokazo
9. Create environment for toilet and water privatization.
District wide
10. Provision of storm drains at Edwakpole Edwakpole
ROAD (PRIORITY 1)
1. Construction of access road from Ebi junction to Mactrime
Ebi , Mactrime
2. Construction of road from Fist-Gate-Domeabra-Bibianiha-Sanfo
First Gate, Domeabra, Sanfo
3. Construction of bridge at Mantukwa Mantukwa
4. Construction for farm tracks
5. Reshaping of A.B Bokazo electoral area roads A.B Bokazo
6. Provision of drainage for A.B Bokazo A.B Bokazo
AGRICULTURE (PRIORITY 5)
1. Agric extension services for Awiebo zone Awiebo
2. Streamlining the supply of fertilizer
3. Create easy access to farm inputs and agro-chemicals
4. Farm tracks for A.B Bokazo A.B Bokazo
5. Mass spraying exercise not ongoing at Awiebo area council
SOCIO-ECONOMIC (PRIRORITY 6)
1. Construction of communication center at Awiebo Awiebo
2. Completion of night market at Awiebo Awiebo
3. Provision of bus at Melewu Melewu
4. Construction of market at Baseke Baseke
5. Construction of market shed at Bibianiha Bibianiha
96
ESIAMA AREA COUNCIL
EDUCATION (PRIORITY 1)
S/NO. ISSUES LOCATION/COMMUNITY
1. Provision of additional block for Kamgbunli KG, teaching and learning materials and furniture
Kamgbunli
2. Renovation of Kamgbunli Islamic Primary school and construction of additional block for ‘C’
Kamgbunli
3. Provision of borehole for Kamgbunli cluster of schools Kamgbunli
4. Construction of additional classroom for school ‘B’ Kamgbunli
5. Construction of toilet facility for Primary ‘B’ and JHS ‘B’
Kamgbunli
6. Provision of canteen for cluster of schools Kamgbunli
7. Provision of computer laboratory library block for cluster of schools
Kamgbunli
8. School electrification Kamgbunli
9. Extension of playing field for cluster of schools Kamgbunli
10. Construction of assembly hall for Kamgbunli SHS Kamgbunli
11. Provision of additional staff accommodation for staff of SHS
Kamgbunli
12. Provision of duty or administrative vehicle for SHS Kamgbunli
13. Provision of boy and girls hostels for SHS Kamgbunli
14. Construction of Library block for SHS Kamgbunli
15. Revamp existing school part for SHS Kamgbunli
16. Provision of access road for SHS and entire community roads
Kamgbunli
17. All schools in the Esiama community should be fenced. Most of the schools have become a hub for criminal activities (drug trade).
Esiama
18. Creation of access bridges to link the cluster of schools at Mozukro
Esiama
19. Construction of staff quarters for teachers at Esiama especially Esiama Sec. Tech. SHS and Azulenoanu
Esiama, Azulenoanu
20. Provision of potable water for schools at Azulenoanu Azulenoanu
22. School feeding programme is conducted under unhygienic conditions. Students share common eatries and bowls
Esiama
23. School electrification exercise Esiama electoral area
24. Provision of libraries for schools in the Esiama electoral area
Esiama, Azulenoanu
HEALTH (PRIORITY 4)
1. Upgrade existing CHPS to health center Kamgbunli
2. Provision of staff quarters for health workers Kamgbunli
3. Upgrade Esiama health centre Esiama
4. Construction of a permanent facility for Azulenoanu CHPS compound. The current structure is rented
Azulenoanu
WATER AND SANITATION (PRIORITY 5)
1. Supply of refuse containers Kamgbunli. Azulenoanu
97
2. Construction of drains within town Kamgbunli
3. Provision of toilet facilities for Kamgbunli Kamgbunli
4. Construction of additional toilet facility at Esiamakpole
Esiama
5. Timely and regular cutting of refuse Esiama
6. Provision of dustbin at Esiama placed at vantage points
Esiama
7. Construction of toilet facility at Azulenoanu Azulenoanu
8. Poor drainage system at Esiama Esiama
AGRICULTURE (PRIORITY 2)
1. Revamp Kamgbunli rice irrigation project Kamgbunli
2. Create ready market for farm produce especially tomatoes
Kamgbunli
3. Provision of technical expertise for aqua-culture and credit facilities for framers
Kamgbunli
4. Provision for aqua-culture-oil and gas companies should assist fisher folks to acquire skills in alternative sources of livelihood
Esiama, Azulenoanu
5. Revamp Esiama oil mill Esiama
6. Agriculture diversification Esiama, Azulenoanu
7. Research should be done in the area of coconut extinction (coconut disease) to ascertain a solution.
Esiama, Azulenoanu
ROAD INFRASTRUCTURE (PRIORITY 3)
1. Reshaping of Kamgbunli new site road Kamgbunli
2. Reshaping of Kamgbunli town roads Kamgbunli
3. Second phase of Esiama town roads should be completed
Esiama
4. Building should be streamlined to avoid encroachment on streets and roads at Esiama new site.
Esiama
SOCIO-ECONOMIC (PRIORITY 6)
1. Construction of public library Kamgbunli
2. Construction of market shed at Kamgbunli Kamgbunli
3. Provision of community center for Kamgbunli Kamgbunli
4. Esiama market is not used Esiama
7. Rising cost of living as a result of gold mining and oil and gas activities
Esiama
8. Increased in social vices (drug trade along the Esiama beaches, theft etc)
Esiama
9. The need to construct fire service station in the district.
Esiama
98
AIYINASE AREA COUNCIL.
EDUACTION (PRIOTITY 2)
S/NO. ISSUES LOCATION/COMMUNITY
1. Construction of school block for Kwasikrom (KG, Primary and JHS)
Kwasikrom
2. Construction of teachers quarters for Kwasikrom Kwasikrom
3. Provision of furniture for Kwasikrom schools (desk) Kwasikrom
4. Supply of trained. This Kwasikrom school is understaffed
Kwasikrom
5. Construction of KG block for Asomase Asomase
6. Construction of school block for Sendaso Sendaso
7. Inadequate teachers at Bonsukrom and Asomase Bonsukrom, Asomase
8. Construction of staff quarters for Aiyinase North Schools
Aiyinase North
9. Extent coverage of School feeding programme to Aiyinase North
Aiyinase North
10. Construction of teachers quarters Akoto, Alloakpoke, Awiaso
11. Rehabilitation of Aiyinase Catholic Primary School Block
Aiyinase
12. Provision of JHS Block for Aiyinase Catholic School. Aiyinase
13. Completion of Aiyinase Methodist KG started by PTA
Aiyinase
14. Provision of trained teachers for Aiyinase Catholic school
Aiyinase
15. Provision of teachers quarters for Aiyinase community
Aiyinase
16 Construction of KG block and teachers quarters at Fiasolo
Fiasolo
17 Constriction of teachers quarters and KG block at Kanokware
Kanokware
18 Construction of teachers quarters and completion of teachers quarters at Nyamebekyere
Nyamebekyere
19 Completion of KG block at New Sanfo New Sanfo
20 Construction of KG and Primary blocks at Atababo Atababo
HEALTH (PRIORITY 3)
1. Expansion of Kwasikrom CHPS compound. Kwasikrom
2 Supply of drug and other hospital equipments to Kwasikrom CHPS
Kwasikrom
3 Construction of CHPS at Werekokrom Werekokrom
4. Supply of mid-wife for Kwasikrom CHPS and general staff. The CHPS is under staffed
Kwasikrom
5. Construction of CHPS at Sendaso Sendaso
6. Expansion of Asomase CHPS Asomase
7. Provision of mid-wives for asomase CHPS compound Asomase
8. Construction of CHPS Akoto, Alloakpoke, Awiaso
9. Upgrading of facilities at Aiyinase Health Centre (laboratory, standby generator, Ambulance etc)
Aiyinase
99
10. Provision of means of transport for Nyamebekyere CHPS
Nyamebekyere
11. Completion of existing CHPS at Nyamebekyere Nyamebekyere
ROAD INFRASTRUCTURE (PRIORITY 1)
1. All roads networks at Aiyinase North are in deplorable condition and virtually immotorable. This affects all aspects of their life. In short accessibility is single most important. When this problem is resolved, it will have rippling effects on all sectors.
Aiyinase North
2. Rehabilitation of Aiyinase-Ayawora Road Aiyinase
3. Rehabilitation of Akoto-Alloakpoke road Akoto-Alloakpoke
4. Rehabilitation of Awiaso road Awiaso
5. Rehabilitation of Fiasolo road Fiasolo
WATER AND SANITATION (PRIORITY 4)
1. Rehabilitation of non-functioning boreholes and poor quality of ground water
Aiyinase north
2. Construction of additional boreholes at Kwasikrom
3. No clean drinking water at Asomase and its surrounding communities. In the interim hand dug well could be provided due to poor road network making it difficult for drilling machines to access the area
Asomase
3. Construction of toilet facility at Awiaso Awiaso
4. Extension of existing water facilities to Aiyinase New site
Aiyinase
AGRICULTURE (PRIORITY 6)
1. Post-harvest losses due mainly to poor road network and non-existing storage facilities
Aiyinase North Communities
2. Supply of farm inputs( agro-chemicals cutlasses, protective wears etc) to farmers
Aiyinase North
3. Agric extension services Aiyinase North
4. Supply of improved cocoa seedlings Aiyinase North
5. Credit support for farmers Aiyinase North
6. Rehabilitation of roads Alloakpoke, Awiaso, Akoto
SOCIO-ECONOMIC (PRIORITY 5)
1. Construction of community centre for Kwasikrom and Asomase
Kwasikrom, Asomase
2. Construction of market shed for Kwasikrom and Asomase
Asomase, Kwasikrom
3. Completion of electrification project at Kwasikrom Kwasikrom
4. Extent telecommunication coverage to Aiyinase North
Aiyinase North
5. Provision of police Station for Aiyinase North Aiyinase North
6. Teenage pregnancy is on the rise at Aiyinase North Aiyinase North
7. Extension of electricity to Alloakpoke Alloakpoke
8. Upgrading of existing market Aiyinase
9. Extension of electricity to new sites Aiyinase
100
ATUABO AREA COUNCIL
EDUACTION (PRIOTITY 2)
S/NO. ISSUES LOCATION/COMMUNITY
1. Provision of trained teachers for Eikwe schools as well as the provision of ancillary facilities (toilet/urinal). There are inadequate teachers and this affect teaching and learning.
Eikwe
2. The Eikwe community JHS block’s roof has been ripped off, hence the need to provide roofing sheet for re-roofing.
Eikwe
3. Provision of accommodation (staff quarters) for teachers within the catchment area.
Eikwe electoral area
4. Construction of JHS block for New Bakanta. New Bakanta
5. Construction of Nursery block for Sanzule-Krisan Primary school.
Krisan, Sanzule
6. Provision of primary and KG block for Ngalekpole Ngalekpole.
7. Institution of a scholarship scheme for communities within the oil and gas catchment zone
Atuabo electoral area.
8. Construction of primary school for Atuabo. Atuabo
9. Provision of KG block for Asemdasuazo Asemdasuazo
10. Construction of teachers quarters for Asemdasuazo Asemdasuazo
11. Construction of additional KG block for Atuabo Atuabo
HEALTH (PRIORITY 5)
1. The need to train community based health volunteers on the provision of first aid in emergency cases.
Eikwe electoral area
2. Construction of a mortuary block for the St. Martins de Porres Hospital
Eikwe
3. Expansion of Atuabo CHPS compound to health centre
Atuabo
4. Construction of nurses’ quarters at Atuabo Atuabo.
WATER & SANITATION. (PRIORITY 2)
1. Provision of waste containers and the construction of a final disposal site. The existing disposal site is full and the assembly should assist to refill with lancrete.
Eikwe
2. There are inadequate potable water at New Bakanta, Sanzule, Old Bakanta and Krisan.
Krisan, New Bakanta, Old Bakanta, Sanzule and Krisan
3. Construction of additional toilet facility at Ngalekpole Ngalekpole
4. There is the need to clean the beaches along the coast whiles establishing Sanitation Inspectors.
District wide
5. Asemdasuazo needs additional toilet facility Asemdasuazo
6. Provision of refuse collection containers. Atuabo, Asemdasuazo
AGRICUTURE. (PRIORITY 4)
1. Unapproved method of fishing (light fishing) is District wide
101
affecting catch.
2. Provision for aqua-culture. Fisher folks should be trained and given support to go into fish rearing.
Eikwe electoral area
3. Farmers have no access to credit facilities District wide
4. Agriculture produce preservation is a big challenge. The need for storage facility
Eikwe
5. Farmers have no access to agric extension services District wide.
6. Supply of agro-chemical and farm inputs to farmers Atuabo
7. Train farmers on alternative sources of livelihood District wide
SOCIO-ECONIMIC (PRIORITY 3)
1. There is the need to enhance vocational training in the district
Eikwe
2. Eikwe community needs market sheds Eikwe
3. Electricity coverage should be extended to areas without electricity.
Atuabo electoral area.
ROAD INFRASTRUCTURE (PRIORITY 6)
1. The need to train drivers and commuters of roads on road safety
Eikwe
2. Proper drainage systems should be constructed for communities along the road from A.B Bokazo to Atuabo
Eikwe electoral area
3. Construction of town roads for Eikwe and Atuabo Eikwe, Atuabo
4. Rehabilitation of Atuabo-Asemdasuazo road. Asemdasuazo
102
Below are the thematic areas of GSGDA 1) 2010-2013 and the harmonized district development
issues.
2.1.1 Prioritized development issues under the MTDPF 2014-2017
No. Thematic areas of MTDPF
2010-2013
Prioritized development issues
1. Infrastructure and Human
Settlements.
Poor road condition
Inadequate Potable water coverage
Inadequate planning layout and lack
of education on land issues
Low electricity Coverage
2. Accelerated agriculture
modernization and sustainable
Natural Resource Management.
Inadequate capital and Farming
inputs
Poor development of fishing Industry
Negative impact of Algae bloom on
Sea fishing
Inadequate Agro-processing Industry
3. Enhancing Competitiveness in
Ghana’s private sector
Under-developed Tourism potentials
Low production level
Inadequate Credit facility
103
4. Human Development, Productivity
and Employment.
Poor infrastructural base( Education &
Health)
Poor Environmental Sanitation
Poor Housing Condition
Inadequate Office and Residential
accommodation
High HIV/AIDS prevalence rate
High incidence of malaria
Inadequate teachers at basic school
level
5. Transparent and Accountable
Governance.
High illiteracy rate
High incidence of lawlessness
Inadequate Logistics for Monitoring of
projects and Programmes
Low participation of sub-structures
Poor Internal Revenue Generation
6. Oil and Gas Development Inadequate Knowledge on socio-
economic importance of Oil and Gas
Inadequate local involvement in Oil &
Gas Industry
104
2.2 POCC ANALYSIS
2.2.1 ENHANCING COMPETIVENESS IN GHANA’s PRIVATE SECTOR
PIRORITIZED
DEVELOPMENT
ISSUE
POTENTIALS OPPORTUNITIES CONSTRAINTS CHALLENGES
Underdeveloped
tourism
potentials
Presence of
hotels and
resorts in the
District Eg. Kikam
Beach Beach
Resort.
Influx of private
developers into the
District.
Support from
Ghana Tourist
Board.
Hotels in
neighboring
Districts
Existence of a
tourism
development
Inadequate funds
and logistics (DA)
Inadequate
infrastructure. Eg
Roads, electricity.
Un updated tourism
development plan.
Tourism potentials
Low private
sector interest to
invest.
Inadequate funds
from central
government to
support tourism
development.
105
plan eg. SNV. not well marketed.
Conclusion: Underdeveloped tourism potentials can be solved. Existing tourism development plan should be updated and marketed well
and, presence of hotels would help improve the situation, while low private sector interest to invest in tourism and inadequate
infrastructure could be tackled through support of Ghana Tourism Board and private developers respectively.
Low Production
Level
Presence of
increasing
economic
activities in the
communities e.g.
Esiama and
Aiyinasi due to
Mining activities
Increasing
number of
interventions
due Oil and Gas
eg.ICFG &
Amanzule
Project will help
boost fishing
Absence of
Comprehensive
Local Economic (LED)
Development Plan.
Inadequate
commitment
from central
government
toward LED.
106
stock
Conclusion: Low Production Level can be solved. Inadequate commitment from central government towards LED would be tackled by
interventions due to Oil and Gas, while absence LED Development Plan can be solved by increasing economic activities in communities.
Poor Internal Revenue
Generation
Increasing
number of
economic
activities in
larger
communities
Availability of
ratable
properties and
services
Existence of
Intervention to
improve revenue
generation e.g.
LOGODEP
Existence of DDF
as a source of
supplementary
Fund.
Inadequate number and
Capacity of Revenue
Collectors
Apathy and unwillingness of
communities members to
pay rates
Declining coconut industry
High
unemployment
rate
107
Conclusion: Poor Internal Revenue Generation can be solved. High unemployment rate would be curtailed by increasing economic
activities in larger communities, and inadequate number and capacity of revenue collectors would be solved by the existence of
intervention to improve revenue generation.
Inadequate
Credit Facilities
Possibility of
more financial
institutions
locating to the
district due to oil
and mining
activities
Presence of Rural
Banks and other
financial
institution
Availability
financial support
for the
formation of co-
operatives from
GOG and Donor
agencies
Inadequate interest
in banking
Inadequate GOG
funds towards
the development
of banking
industry
Conclusion: Inadequate Credit Facilities can be solved. Inadequate interest in banking is constraint which can be solved by the possible
sprung up of financial institution due to Oil & Gas, and inadequate GOG funds toward development of banking Industry can be curtailed
108
by availability support for the formation of co-operatives as an opportunity.
2.2.2 ACCELERATED AGRICULTURE MODERNIZATION AND SUSTAINABLE NATURAL RESOURCE MANAGEMENT
PRIORITIZED
DEVELOPMENT
ISSUE
POTENTIALS OPPORTUNITIES CONSTRAINTS CHALLENGES
Inadequate
land farming
inputs
Presence of Agric
Department in
the District.
Formation of
farmer’s
cooperatives to
access existing
support
programmes.
Central
government
interventions
(Eg. Cocoa
spraying
programmes.)
Government
subsidies on
farming inputs
Eg. Fertilizer.
Non availability of
ready markets due to
poor road network.
Inadequate funds at
the Assembly level.
Low income levels of
farmers.
Inadequate
extension officers.
Inadequate funds
from central
government.
109
Conclusion: Inadequate land farming inputs can be tackled. Inadequate fund from Central gov’t would be solved through Subsidies of
farm inputs from Central gov’t and intervention like Cocoa Spraying Programmes, while low income levels of farmers and inadequate
extension officers would be tackled by the presence of Agric.Dept, and formation of farmers’ cooperatives in accessing support
programme.
Poor
development
of fishing
industry
Presence of Agric
Department in
the District.
Inland fishing
development due
to enough water
bodies.eg
Influx of NGOs
into the district
(Eg. Coastal
Resources
Center and
Friends of the
Nation) to
support the
industry.
Absence of fisheries
department.
Ineffective fishing
policies.
Conclusion: Poor development of fishing industry. Ineffective fishing policies and absence Fisheries Dept. would be solved be the
presence of development partners eg. Coastal Resource Centre would solve the problem of Poor development of fishing Industry.
Negative
impact of algae
bloom on sea
fishing
Existing of
research
institutions.
Inadequate funds
and logistics.
Lack of technical
capacity to handle
Inaction on the
part of
government.
110
situation.
Conclusion: Negative impact of algae bloom on sea fishing, would need a lot of commitment from the gov’t since the District does not
have any potential to curtail the situation, however has the existence of research institutes as opportunities. Lack of technical capacity
and inaction on the part of government, thus the need for muti-sectoral commitment.
Inadequate Agro-
Based Industry
Availability of
Land for the
construction of
industry
Presence Land
Use Map
Central
Government
intervention
Availability of
development
partners eg.
USAID.
Inadequate Funds
from Central
Government
Inadequate Fund
from Central
Government
Conclusion: Inadequate Agro-Based Industry can be solved. Presence of Land Use Map and availability of development partners can help
can help curtail the challenge of government’s problem of inadequate Fund, there improving Agro-Based Industry.
111
2.2.3 Oil and Gas Development
PRIORITIZED
DEVELOPMENT
ISSUE
POTENTIALS OPPORTUNITIES CONSTRAINTS CHALLENGES
Inadequate
Knowledge on socio-
economic importance
of Oil and Gas
Constituting of Oil and
Gas Sub-committee to
deliberate on issues
Intervention from
NGO’s to educate
populace on the Socio-
economic impact of Oil
and Gas e.g. FoN.
Over expectation of local
people on Oil and Gas
benefit
Inadequate Training
Institution for Oil & Gas
Development.
Conclusion: Poor Knowledge on Oil and Gas can be solved. Constraints like over expectation of locals on Oil & Gas can be solved by the
Constitution of Oil & Gas Committees, while inadequate Training Institution can be tackled by intervention from NGOs to educate
locals on impact of Oil & Gas.
Inadequate local
involvement in Oil &
Gas Industry
Existence of Oil and Gas
facilities in the District.
Eg Ghana Gas Comp.
Ltd.
Availability of local
expertise
Willingness of
government to
improve Oil & Gas
industry
Existence Oil & Gas
Educational
Institutions
Inadequate educational
background of local people
to tap into Oil industries
Inadequate Funds for
Capacity building
Exercise from Oil & Gas
Companies.
112
Conclusion: Inadequate local involvement in Oil and Gas Industry. Inadequate educational background of local people would be solved
by the existence Oil & Gas Educational Institutions, while inadequate funds for capacity building exercise on Oil & Gas would be solved
by government’s willingness to improve Oil & Gas.
2.3.4 INFRASTRUCTURE AND HUMAN SETTLEMENTS DEVELOPMENT
PIRORITIZED
DEVELOPMENT
ISSUE
POTENTIALS OPPORTUNITIES CONSTRAINTS CHALLENGES
Poor road
condition
Presence of
Feeder Roads
Dept. in the
District
Acquisition of
grader by the DA.
Central
government
interventions.
Supplementary
resources from
dev’t partners.
Presence of heavy
duty trucks can affect
roads.
High rainfall affects
roads.
Inadequate funds
and logistics.
Inadequate funds
and logistics.(
Central
government)
Conclusion: Poor Road Conditions can be curtailed partially since substantial potentials and opportunities exist. The challenges can be
addressed through lobbying, and with the status of newly created district. Constraint can be tackled by constructing drains along roads,
and also revenue from road charges and presence of grader can be used to dress bad road.
Inadequate Ability to expand Support from Increase in Revenues for
113
potable water
coverage
existing EU and
IDA (CWSA) water
facilities.
High rainfall
pattern good for
rainwater
harvesting.
Existence of
reliable water
bodies.
Existence of
WATSAN&WSDB
development
partners (Eg.EU)
in the provision
of potable water
population as a result
of mining and oil
activities might put
pressure on existing
water facilities.
Reluctance of
communities to pay
user charges that can
be used for
expansion of water
facilities.
expansion might
be used for other
purposes. (Eg. As
contract fees.)
Conclusion: Inadequate potable water coverage can be solved by the presence of the District potentials. Increased pressure on existing
water facilities and non-payment of user charges by communities can be curtailed through expansion of both EU & IDA Small Town
Water System s and Sensitization of communities through WATSANs and WSDBs.
114
Inadequate
planning layout
and lack of
education on
land issues
Presence of Town
and Country
Planning
Department.
Introduction of
Spatial Planning
and Land scaping
by LOGODEP
Commitment of Gov’t
through Existence of
Intervention.eg. LAP.
Inadequate funds
and logistics
Inadequate
personnel.
Absence of planning
schemes.
Failure to apply for
building permit.
(Developers)
Absence of Assembly
bye – law.
Poor or
ineffective land
policies.
Conclusion: Inadequate planning layout and lack of education on land issues can be partially minimize. The Absence of planning
schemes and
Failure to apply for building permit. (Developers) would be solve by Introduction of Spatial Planning and Landscaping by LOGODEP and
the existence of Town & Country Dept, and Poor or ineffective land policies can be solved by government commitment towards
implementation of intervention.
However there is the need for other opportunities to curtail problem fully.
Low electricity
coverage
Presence of ECG
in the district
Central
Government
support
Inadequate funds
and logistics.(DA)
Inadequate funds
and
logistics.(Central
115
Self-help projects. programmes (Eg.
Rural
Electrification
project)
government)
Conclusion: Low electricity coverage would be solved through the existence ECG and Central government support for Rural Electricity
Project
2.3.5 HUMAN DEVELOPMENT, PRODUCTIVITY AND EMPLOMENT
PRIORITIZED
DEVELOPMENT
ISSUE
POTENTIALS OPPORTUNITIES CONSTRAINTS CHALLENGES
Poor
infrastructural
base (Education
& Health)
Presence of
mining and oil
companies.
Central government
support programmes.
(Eg. Schools under trees
programme)
Inadequate
funds.
Lack of support
from traditional
authorities.
Lack of support
from community
members and
local authorities.
Inadequate
funds from
central
government.
Conclusion: Poor infrastructural base (Education & Health) can be solved. Inadequate funds from Central government is a challenge
116
which can be solved by support from central government like GETfund Schools under Trees initiative, and Constraints like Inadequate
funds and lack of support from local communities can be solved by presence of mining companies.
Poor
Environmental
Sanitation
Presence of
Env. Health
Office and
officers
Presence of
mining and oil
companies
Support of
traditional
authorities
Enactment and
enforcement of
DA bye – law
Influx of NGOs to
support sanitation
Development partners
and private sector
ready to invest in
sanitation
Central governments
support for
sanitation(Governments
Dev. Policy)
Low communal
spirit
Inadequate funds
and logistics
Low level
education on
sanitation
Inadequate
personnel
Absence of
Assembly bye –
law
Apathy on the
part of
community
members.
Inadequate
funds and
logistics
Lack of political
will
Inadequate
data on
sanitation
Conclusion: Poor Environmental Sanitation can be solved. Absence of Assembly bye – law Apathy on the part of community members
and inadequate personnel can be tackled by enactment and enforcement of DA Bye-laws and presence of Environmental Health Office,
117
while Lack of political will and inadequate Funds and Logistics can be solved by Central Government support for sanitation (Sanitation
Policy)
Poor housing
condition
Abundant local
materials
Support from Central
Government (Housing
schemes Eg. STX)
Low levels of
income.
Poor national
housing policy.
Conclusion: Poor housing condition can be solved. Low levels of income and Poor national housing policy can be curtailed by Potential
like abundant local materials and challenges like support from Central Government (Housing Schemes eg. (STX)
Inadequate
office &
residential
accommodation
Availability of
land for
construction.
Support from
oil and mining
companies.
Increase in IGF.
Possible government
interventions.
Inadequate
funds.
Lack of
provision for
newly created
districts.
118
Conclusion: Inadequate office & residential accommodation can be solved. Lack of provision for newly created districts is a challenge
which can be tackled by opportunity presence of government intervention, while inadequate funds can be solved by potential like
support from Oil and Mining Companies.
High HIV / AIDS
prevalence
rate.
Presence of
district Health
Admin.
Existence of
District Aids
Committee
(DAC)
Support from Ghana
Aids commission.
Presence of NGOs in the
district.
Ignorance of Local
people of on the health
and Socio-economic
effect of HIV/AIDS.
Influx of people
into the district
due to mining
activities.
Low levels of
education.
Inadequate funds
from DAs to
combat HIV/AIDS.
Inadequate donor
support.
Conclusion: High HIV / AIDS prevalence rate can be solved. Influx of people into the district due to mining activities and Low levels of
education can be solved by the presence of District Health Administration and the existence of District Aids Committee (DAC)
119
High incidence
of malaria
Presence of
District Health
Administration
and
Environmental
Health Unit
Support from
local authorities
Presence of
mining
company
Influx of Health related
NGOs into the District
Other government
interventions
Existence of
Marshy and
Wetlands.
Low level of
education.
Inadequate funds
and logistics.
Poor sanitation
conditions.
Inadequate
infrastructure.
Inadequate Heath
Training Institution.
Conclusion: High incidence of malaria can be solved. Inadequate Heath Training Institution can be solved by Influx of Health related
NGOs into the District, while constraints like low level of education and poor sanitation conditions can be solved by Presence of District
Health Administration and Environmental Health Unit and support from local authorities.
Inadequate
teachers at
basic school
level
District
scholarship
schemes.
Central government
support programmes
(Eg.NYEP Education
module
Inadequate funds
to provide
enough
infrastructures at
the basic Sch.
level.
120
Conclusion: Inadequate teachers at basic school level can be solved. Inadequate funds to provide enough infrastructures at the basic
Sch. Level are a constraint which can be solved by potential like District Scholarship Scheme.
2.3.5 TRANSPARENT AND ACCOUNTABLE GOVERNANCE
PRIORITIZED
DEVELOPMENT
ISSUE
POTENTIALS OPPORTUNITIES CONSTRAINTS CHALLENGES
High illiteracy
rate
Presence of
District Education
Directorate.
District
scholarship
Schemes for both
teacher trainees
and students.
Government
support
programmes (Eg.
Schools under
trees project)
Inadequate funds.
Unwillingness of
parents to support
wards in school.
Inadequate trained
teachers.
Inadequate
classroom blocks
Inadequate funds
from central
government.
Conclusion: High illiteracy rate can be solved. Inadequate funds from central government is a challenge which can be solved by
programmes like schools Under Trees by GETfund, while Unwillingness of parents to support wards in school can be curtailed by
potential like District scholarship
Schemes for both teacher trainees and students.
121
High incidence
of lawlessness
Presence of NCCE
for education at
various levels eg.
Radio programs.
Presence of basic
structures for
the police
Support from
other central
government
interventions
(Eg. CBRDP
training on
Social
Accountability)
Inadequate police
personnel
Inadequate
infrastructure
Inadequate funds
and logistics
Inadequate funds
and logistics for
capacity building
from Gov’t
Inadequate
personnel
Conclusion: High incidence of lawlessness can be solved. Inadequate police personnel and inadequate funds and logistics can be solved
by presence of NCCE and presence of presence of existing police structures, while Inadequate funds and logistics for capacity building
from Gov’t can be tackled by interventions like CBRDP eg. Social Accountability training.
Inadequate
logistics for
monitoring of
projects and
programmes
Financial
commitment
toward
monitoring and
evaluation
through Annual
Budgeting
Existence of
interventions like DDF
and LOGODEP to help
build DAs Capacity for
Revenue generation.
Inadequate IGF to
support recurrent
expenditures
including M&E
Skewness of
DACF towards
other sectors to
the detriment of
M&E
Conclusion: Inadequate logistics for monitoring of projects and programmes can be solved. Challenge like skewed nature of DACF
towards other sectors would be tackled by existence of DDF and LOGODEP would help build capacity to improve revenue generation.
122
Low
participation of
sub - structures
Presence of NCCE
in the district for
education
Support of local
authorities
Policy change in
the constitution
of the sub-
structures
Lack of motivation
Apathy on the part of
elected members
Large numbers of
elected members
Lack of logistical
support
Conclusion: Low participation of sub – structures can be solved. Apathy on the part of elected members and lack of motivation can be
tackled by presence of NCCE in the District, and large numbers of elected members would be solved by policy changed in sub-structures
formation.
123
3.0 CHAPTER THREE
3.1 DEVELOPMENT GOAL, OBJECTIVES AND STRATEGIES
DEVELOPMENT FOCUS The Development Focus of the Ellembelle District Assembly based on analysis of the
community aspirations, departmental plans, and NGO’s and development partners’ visions
is to ensure that all the inhabitants of the District have the following:
1) Bridging development gap between well-endowed communities and deprived ones.
2) Security from crime and other social unrest
3) Access to basic social services such as Health, Education, Potable water and clean
environment.
4) Empowerment of local people in environmental sustainability
5) Adequate incentives to improve production
3.2 DISTRICT DEVELOPMENT GOAL Based upon the problems, needs, potentials, opportunities, constraints and priorities
identified, the overall Goal of the Ellembelle District in line with the thematic areas of the
MTDPF 2010-2013 and the National Goal is: To co-ordinate social services and
environmental sustainability, improve security and develop accessibility to production
areas and strengthen local institution for equitable growth and sustainable development.
124
GSGDA II OBJECTIVES AND STRATEGIES
THEMATIC AREA OBJECTIVES STRATEGIES
Infrastructure and
Human Settlements
Development
Create and sustain an efficient and effective transport system that meets user needs
Establish Ghana as a transportation hub for the West African sub-region
Improve accessibility to key centres of population, production and tourism
Introduce an integrated truck staging and management systems
Prioritize the maintenance of existing road infrastructure to reduce vehicle operating costs (VOC) and future rehabilitation costs
Improve accessibility to key centres of population, production and tourism
Improve and develop the physical infrastructure across all modes for transport
Introduce an integrated truck staging and management systems
Accelerate the provision of adequate, safe and affordable water
Improve management of water resources
Support relevant state agencies, MMDAs and local communities to undertake reforestation programmes for the protection of water sheds)
Identify and assess ground water resources to enhance water availability
Facilitate on-going institutional, technological and legal reforms in support of land use planning
Strengthen the human andinstitutional capacities for effective land use planning
Integrate land use planning into the Medium-Term Development Plans at all levels
Implement relevant planning models, simplified operational procedures and planning standards for land use
125
Accelerate the enactment of coherent legal framework for land-use planning
Provide adequate, reliable and affordable energy to meet the national needs and for export
Promote the conversion of waste to energy
Expand power generation capacity
Increase access to energy by the poor and vulnerable
Improve efficiency in power generation, transmission and distribution
Improve management of water resources
Ensure the development and implementation of health and hygiene education as a component of all water and sanitation programmes
Accelerate the provision of improved environmental sanitation facilities
Adopt a sector-wide approach to water and environmental sanitation delivery
Incorporate hygiene education in all water and sanitation delivery programmes
Support Public-Private Partnership in solid waste management.
Provide modern toilet and sanitary facilities in all basic schools.
Scale-up the Community Led Total Sanitation (CLTS) for the
Review, gazette and enforce MMDAs bye-laws on sanitation
Promote behavioral change (hand washing with soap, household water treatment and safe storage, safe excreta disposal) to curtail open defecation in communities
126
Increase access to adequate,
safe, secure and affordable
shelter
Improve and accelerate
housing delivery in the rural
areas
Accelerate the implementation of the national housing policy
Provide support for private sector involvement in the delivery of rental housing
Promote the transformation of the rural economy to encourage the growth of quality settlements
Encourage the MMDAs to use a portion of their Common Fund to embark on the construction of social housing units
Accelerated Agriculture
modernization and
Sustainable Natural
Resource Management.
Promote Agriculture
Mechanization.
Improve science, technology
and innovation application
Strengthen collaboration with the private sector to build capacity to manufacture appropriate agriculture machinery, tools, and other equipment locally
Apply appropriate agriculture research and technology to introduce economies of scale in agriculture production
Enhance fish production and
productivity
Promote the collection of scientific and socio-economic data for fisheries management
Improve existing fishing land site and develop related infrastructure for storage, processing and exports.
127
Establish and strengthen co-management mechanisms with local communities for fisheries resource management
Enhance fish production and productivity
Ensure compliance with maximum allowable fish catches to promote resource regeneration
Strengthen monitoring controls and surveillance systems and ensure compliance with laws and regulations on fisheries resources
Increased Agric. Competitiveness and enhanced integration into domestic and international markets.
Strengthen collaboration between public and private sector institutions to promote agro processing.
Develop effective post-harvest management strategies, particularly storage facilities, at individual and community levels.
Enhancing
Competitiveness in
Ghana’s private Sector
Diversify and expand the tourism industry for economic development
Promote sustainable tourism to preserve historical, cultural and natural heritage
Strengthen collaboration and coordination among key stakeholders to develop the tourism sector
Encourage the expansion of tourist event attractions
Promote Public Private Partnerships for investment in the sector
Ensure tourism planning
128
in District Development plans to promote tourism development
Improve efficiency and competitiveness of MSMEs
Facilitate the provision of
training and business
development services
Support the promotion of
cost effective technology
to remove value chain
constraints
Provide opportunities for
MSMEs to participate in
all Public Private
Partnerships (PPPs) and
local content
arrangements
Develop a financial sector which is
more efficient and responsive to
private sector needs
Deepen and expand the scope of financial services, products and payment Systems
Expand the space for private sector investment and participation
Human Development Productivity and Employment.
Improve quality of teaching and learning.
Increase inclusive and equitable access to, and participation in education at all levels
Ensure adequate supply of teaching and learning materials
Bridge the gender gap and access to education at all levels
Remove the physical, financial and social barriers and constraints to access to education at all levels
Improve management of education service delivery
129
Improve management of education service delivery
Strengthen capacity for education management
Ensure efficient development, deployment and supervision of teachers
Develop and implement health sector response to the national decentralization program
Improve efficiency in governance and management of the health system
Enhance national capacity for the attainment of the health related MDGs and sustain the gains
Strengthen capacity for Monitoring and Evaluation in the health sector
Scale-up the implementation of national malaria, TB, HIV/AIDs control strategic plans
Accelerate the implementation of the Millennium Acceleration Framework (MAF)
Intensify and sustain Expanded Programme on Immunizations (EPI)
Ensure the reduction of new HIV and AIDS/STIs infections, especially among the vulnerable groups
Improve HIV and AIDS/STIs case management
Develop and implement a programme to deepen public awareness and management of STIs
Establish sustainable financing arrangement for the delivery of HIV and AIDS/STIs services
Ensure the implementation of the GAC resource mobilization
130
strategy
Bridge the equity gaps in
geographical access to health
services
Strengthen the district and sub-district health systems as the bed-rock of the
national primary health care strategy
Accelerate implementation of CHPS strategy in under-served areas
Increase coverage of NHIS especially for the poor
Formulate and implement health sector capital investment policy and plan
Promote the teaching and learning of science, mathematics and technology at all level
Expand infrastructure and facilities in tertiary institutions to absorb the increasing number of qualified students
Adopt clear policy for tertiary education
Review policies to meet
emerging demands in
education at all levels
especially at the tertiary
level
Expand infrastructure and
facilities in tertiary
institutions to absorb the
increasing number of
qualified students
Transparent and
Accountable
Governance.
Improve the capacity of security agencies to provide internal security for human
Sensitize the public on the existing legislative provisions including
131
safe and protection sanctions and the dangers of drug use and small arms
Monitor private sector involvement in the provision of internal security
Ensure strict compliance of immigration laws
Ensure effective implementation of the decentralization policy and programmes
Implement the National Decentralization Action Plan Review and consolidate legislation on local governance
Ensure effective implementation of the decentralisation policy and programmes
Review and implement the National Decentralization policy and Strategic plan
Promote Public Private Partnerships (PPPs) arrangements for infrastructural development for the newly created districts and ILGS
Enforce compliance of LI. 1967
Improve fiscal revenue mobilization and Management.
Develop the capacity of MMDAs towards effective revenue mobilization.
Formulate a comprehensive and clearly articulated policy framework to provide effective sources of revenue mobilization and financial management
Review District Demarcations
132
Strengthen mechanisms for accountability
Ensure efficient internal revenue generation and transparency in local resource management.
Develop an intergovernmental fiscal framework (IGFF).
Strengthen collection and dissemination of information on major investment expenditure items including contracts to the public and other stakeholders
Develop a financial management guidelines and manuals
Oil and Gas Development
Ensure accelerated and integrated development of the oil and gas industry
Strengthen institutional capacity of national agencies to take leadership role in managing Ghana’s oil and gas resources
Expand the national oil and gas upstream, midstream and downstream infrastructure in collaboration with the private sector within the PPP framework
Ensure local content and local
participation across the oil and gas
value chain
Leverage the opportunities offered by
the oil and gas industry to create
decent jobs
Expand and strengthen the capacity of Ghanaians for
participation in all segments of the oil and gas industry
Ensure effective implementation of the local content policy as it relates to employment in
133
the oil and gas industry
Ensure that companies comply with regulations in labour recruitment
134
3.3 Formulation of Development Programmes
1.
THEMATIC AREA ISSUES ACTIVITIES
Infrastructure and Human Settlements Development
Poor road condition
Construct access road and rehabilitate all existing roads
Reshape all new site & town road
Construct Access Bridges
Construct Farm tracks
Inadequate Potable
water
Expand potable water coverage
Train all WSMTs & WATSANs
Construct Small Town Water System in larger town
Prepare DWSP
Inadequate planning
layout and lack of
education on land
issues
Conduct education on physical development on local FM Stations
Organize monthly radio show on renewal of development permits
Form land Management task force
Task ECG to conscientize people by using sinages.
Validate data on existing facilities and
135
Low electricity
coverage.
embark on expansion.
Conduct survey and education on the
importance of energy saving appliance
Poor Environmental Sanitation.
Construct modern final waste disposal site for effective waste management
Construct Toilet and other sanitation facilities eg. Aqua privy
Construct proper drainage system
Inform communities on the healthy environment through Local FMs
Provide final disposal sites for liquid and solid waste.
Supply refuse containers for larger communities.
Increase and improve capacities of Sanitation Department
Poor Housing
Condition
Train Commt. members on modern building technology
Sensitize commt.members radio talk shows every quarter.
Prosecute haphazard developers through fines.
136
Inadequate office and
Residential
accommodation
Budget for official accommodation
Rehabilitate existing office and residential accommodation
2 Accelerated
Agriculture
modernization and
Sustainable Natural
Resource
Management.
Inadequate capital and
farming inputs
Poor development of
fishing Industry eg.
landing site & storage
facilities
Facilitate the supply of agro-chemical and farm inputs to farmers
Disseminate information via radio (F.M) station to educate farmers on new technologies and social agricultural issues quarterly every year
Carry out diseases surveillance and monitoring visits quarterly
Train Officials of Fisheries department and
other key stakeholder on data collection.
Lobby fisheries commission to upgrade
land.
Train 100 fishermen on improved culture
on fisheries technology by 2016.
Negative impact of Algae bloom sea fishing
Educate fisherfols on the modern method of fishing and aqua culture
Educate farmers on aqua culture/fish rearing
Set by-laws to curtail unlawful fishing
Low agro based industry
Educate 50 farmers and farmer groups on safe use and handling of agro-chemicals
Provide f agric. extension services
Train farmers on alternative sources of livelihood.
Organize Farmer Day Annually
137
3 Enhancing Competitiveness in Ghana’s private Sector
Under-developed tourism potentials
Form Tourism Steering Committee
Carry out Education on the importance of the formation of association.
Include tourism in cultural activites through concensus build
Set Budget for tourism related activities.
Review Tourism Development Plan
Low production Level
Educate local entrepreneurs modern ways to grow businesses
Conscientize SMEs to adopt LED initiatives e.g. beads and soap making
Promote training of Business management e.g. SNV Netherlands Development Org.
Low availability of credit facility for entrepreneurship
Training companies in acquisition of loans from Micro finance schemes
Conscientize local entrepreneurs on
modern trend of business
4 Human Development Productivity and Employment.
Poor infrastructural base (Education & Health)
Provide teaching and learning materials especially science for basic schools
Subsidize the supply of learning materials
Conduct regular school inspection and disseminate report
Provide Scholarship package for brilliant
but needy students
138
Establish time table for student to attend Community Information Center
Extend school feeding programme to cover all communities.
Construct standard CHPS compounds.
Provide basic service delivery equipment to health facilities.
Establishment of national ambulance service in district.
Registration of aged and other vulnerable on NHIS.
Provide antenatal and maternity services for communities.
Provide accommodation for health workers
High HIV/AIDS
prevalent rate
Implement National TB, HIV/AIDS and malaria programs.
Sensitization of communities on common endemic disease (TB, Malaria, HIV/AIDs etc).
Monitor and evaluate activities of NGOs handling AIDS activities
Embark on community advocacy programmes on HIV/AIDS.
High Incidence of
Malaria
Organize routine immunization programs
Identify and train community of based surveillance volunteers.
Embark on malaria prevention talk show
Promote the use of treated nets.
Monitor monthly morbidity and mortality analysis of malaria
139
High Illiteracy rate Conduct training for pre-school (KG) teachers
Provide incentive package for teachers in deprived areas
Provide learning material for basic schools.
Renovate and construct additional school blocks
Construct additional blocks for rural school
Ensure full participation of SMCs in school management
5. Transparent and Accountable Governance.
High Incidence of
Lawlessness
Apply for Information van from Information ministry
Form complaint c’ttee at various communities
Review existing bye-laws and Gazette
Charge community members non-participation in communal labour.
Supply security agencies with the requisite logistics
Inadequate logistics for Monitoring of projects and programmes
Furnish decentralized department with office equipment
Build capacity of DA staff and sub structures
Introduce incentive packages for staff
Low participation of sub-structures
Provide in-service training and refresher courses for area councils and unit committees
Construct an office each for seven Area Councils
Introduce the local people to the advantages of LED.
Poor Internal Revenue Generation
Implement revenue management action
140
Revalue properties in the District
Train zonal revenue officers in area councils.
Institute a task force team to monitor activities of retailer
Construct and rehabilitate roads linking farming areas to the south.
Inadequate credit facility
Collate all socio economic data and list of businesses
Train local entrepreneurs in business proposal writing.
Facilitate the formation of entrepreneurial association eg. Garages and Pig farmers association.
Intensify revenue and financial management training.
6. Oil and Gas Development
Inadequate Knowledge on socio-economic importance of Oil and Gas
Sensitize local populace on the socio-economic importance of Oil and Gas
Organize regular meeting between stakeholders especially along coastal zones to discuss issues affect them.
Inadequate Local involvement in Oil & Gas Industry
Organize public fora for communities.
Lobby Oil & Gas Companies to increase Scholarship scheme for local students.
141
3.4 CROSS CUTTING DEVELOPMENT PROGRAMMES
3.5 LOCAL ECONOMIC DEVELOPMENT The National Decentralization Policy 2011-2015 defines local economic development (LED) as ‘ the
process by which local government, local businesses and other actors joins forces and resource to
enter into new partnership agreements with each other or other stakeholders to create new jobs and
stimulate economic activity in municipalities, towns and villages. (Cited in Mainstreaming Gender at
the Sub-National Government level, 2012).
3.6 Rural Enterprise Project (REP) The Ellembelle District however in its effort to promote LED has continuously promoted gainfully
employment skill through the Rural Enterprise Project (REP). Annual Workplan has been developed to
roll on programme like soap making, Batik & tie-dye, bead making etc., to the rural parts of the District
to improve living standard.
3.7 International Network for Bamboo and Rattan (IMBAR) IMBAR has executed a project dubbed ’Bamboo as Sustainable Biomass Energy: Alternative for
firewood and Charcoal Production in Tandan Community, a pro poor initiative which seeks to utilize
the enormous bamboo endowment in the community to produce charcoal and briquette as means of
increasing the use of bamboo as a source of energy for the poor in Ghana thereby providing a more
sustainable, environmentally friendly and economical option for firewood and wood charcoal.
The Assembly has developed a consultative workplan to expand the current level of production.
Quarterly meetings will be held to review and improve the performance of the facility.
3.10 SOCIAL PROTECTION Ghana Social Opportunities Project (GSOP)
Ghana Social Opportunities Project (GSOP) has the overall goal to support Ghana’s Social Protection
Strategy through:
142
Developing a labor intensive public works program as a rural safety net instrument in target
districts across the country to increase cash income for the rural poor during Agricultural off-
season and
Supporting the Government’s Livelihood Empowerment against Poverty (LEAP) program.
The objective of the Project is to provide targeted rural poor households with access to employment
and income earning opportunities, in particular during seasonal labour demand shortfall through
rehabilitation and maintenance of public or community infrastructure.
The Ellembelle District has executed the Construction of 3-Unit Teachers at Akropong and
Rehabilitated 5.8 km road from First Gate Junct. – First Gate, whilst the Establishment of 30 hectares
rubber plantation (Climate Change) is ongoing.
Currently the District has selected two (2) sub projects that are ‘Rehabilitation of degraded land and
Rehabilitation of 3.4 km road’.
3.11 ENVIRONMENT AND CLIMATE CHANGE
3.11.1 Ghana Wildlife Society
Environment and biodiversity issues are increasingly becoming key as far as Climate Change is concern.
The impact of climate change affects ecosystems in a variety of ways. It does not only affects
ecosystems and species directly; it also interacts with other human stressors such as development and
industrial footprints. At the global level, human activities have caused and will continue to cause loss
of biodiversity through land-use and land-cover change; soil, air and water pollution and forest
degradation.
The Ellembelle District is endowed with significant and unique environmental features which include
high forests such as Shelter forest reserve, Draw River Forest Reserve, Ndumfri forest reserve; coastal
wetlands such as Amanzule wetlands which is an Important Birds and Biodiversity Area based on
Birdlife International’s criteria; and sandy beaches and marine biodiversity.
143
Despite the benefits obtained from these unique ecosystems, population growth and associated
uncoordinated developments as well as threats of the environmental footprints of mining, the
emerging Oil and Gas industry and climate change may comprise the sustainability of these resources.
Considering the critical nature of the above assertion, the Wildlife Society of Ghana is implementing a
project in Ellembelle District dubbed “Enhance the knowledge and awareness of the ecological
importance of the Amanzule wetland catchment area, and the associated livelihoods” under the ‘STAR
Ghana’ pooled fund initiative. The project seeks to strengthen environmental awareness amongst
local stakeholders and equip them with skills to monitor and detect changes in ecologically sensitive
areas, increase knowledge on how to engage environmental compliance enforcement agencies and
development proponents during Environmental Impact Assessment (EIA) process as well as strengthen
available structures for effective communication and feedback.
The project has mapped ecologically sensitive sites in the Amanzule area and it is using a community
based ecological monitoring approach to implement a simple but robust biodiversity monitoring
protocol that has been developed using the Important Birds and Biodiversity Areas global monitoring
framework to enhance local level environmental monitoring in the district.
3.11.2
Coastal Sustainable Landscapes Projects (CSLP) The above project is USAID sponsored is focused on climate change mitigation and adaption. The
objective is to strengthen capacity for low emission development through improved coastal forest
landscape management.
The projects have several interventions which among others are; the implementation of agroforestry
and forestry practices, Short and medium term livelihood improvement activities like
Bee-keeping expansion
Increased Vegetable Production
Woodlots for Charcoal Production
Also assistance with management of greening areas as designated in spatial plans by Town and
Country Planning Units. Establishment of trees in open areas and schools to promote urban greeneries.
144
Other intervention are Community Management of coastal zone and wetlands area (restore/replant
degraded mangroves sites, working with community based natural resource management groups eg.
CREMAs) and facilitation of the establishment of Village Savings and Loans Association VSLA (to help
promote local livelihood activities)
Initial Beneficiary Communities in the District
District Community Initial Intervention
Ellembelle Ayawora, Adubrim, Fiasolo &
Sendu
Agrofoestry, Bee keeping, VSLA
145
3.11.3 GREEN ECONOMY
SUB SECTOR RECOMMENDED POLICY SOCIO ECONOMIC BENEFIT ENVIRONMENTAL BENEFITS
Coastal Issue Replanting of Mangroves
tress and other coastal
plant to avoid depletion
Ecosystem research and
development
Improved food security through protection of water bodies
Decline in Green House emission.
Expansion in total coastal forest.
Increase in water availability in the long term.
Road
Bye-law to regulate cutting of virgin land
Establish national road data
Enhance nature conservation
Improve economic activities
Reduced GHG emission
Improve ecosystem.
Illegal Mining
Sustainable management of natural resources
Law to regulate illegal mining.
Increase revenue
Increase job opportunities
Ensures environmental sustainability in the long run.
Reduced GHG emission
Waste
Waste minimization
Waste-to-energy
Creation of jobs
Increased access to bio-energy
• Reduced GHG emission
Fishing
Regulate fishing activities
Fish stock regeneration and increase in availability
Increase employment in the long run
Increased resource base
Increased fish stock regeneration
146
through aquaculture
Oil & Gas
Enforce local content in industry.
Guidelines for usage of oil & gas revenue.
Increase employment
Increase revenue
Eco-tourism
Ensure Sustainable forest management (SFM) and expansion of forest
Regeneration of nature reserves
Increase revenue
Creation of jobs
Ensures environmental sustainability in the long run.
Improve ecosystem.
Reduced GHG emission
Transportation
Electricity
• Laws to ensure efficient
energy sources and
technologies
•
• Increased employment
opportunities in the long-
term
• Enhances the creation of
indirect jobs
• Speeds up universal access
to modern energy services
Reduced GHG emission
Cocoa
• Intensification of the use of
organic fertiliser,
• Agricultural research and
development
• Enhance post-harvesting
technologies
• Increased in employment in
the long term
• Improvement in nutrition
and food security
• Improved soil quality
• Enhanced biological
diversity within the soil
• Decline in GHG
emissions
147
CHAPTER 4
PROGRAMME OF ACTION.
4.0 THEMATIC AREA: Human Development, Productivity & Employment
Education. ACTIVITIES LOCATION TIME FRAME INDICATIVE
BUDGET (GH₵)
OUPUT INDICATOR
S
SOURCES OF FUNDING IMPLEMENTING DEPARTMENT OF THE
DA
2014 2015 2016 2017 IGF GOG DONOR LEAD COLLABORATING
Organize sensitization in communities
District Wide
20,001.50 Sensitization organized.
IGF GOG GES DA
Provide material support to needy pupils in schools
All School
13,002.00 Material support provided
IGF GES MOE
Rehabilitate KG school block
Selected area
1,466,000 KG school rehabilitated
GoG DA, Works Dept.
GES
Construction of 3-Unit KG block with ancillary facilities
Selected area
1,980,400 Three –Unit KG block constructed
DACF GETFUND
DA, Works Dept.
Build 6- unit Primary School Buildings &
Selected area
200,000 Six - unit primary school built
GOG DA, Works Dept.
MOE
148
Accessories
Construction of 3-unit JHS block with ancillary facilities
Selected area
500,000 Three –Unit JHS block constructed
GOG DA, Works Dept.
MOE
Completion of 6-unit classroom block
Selected area
- 300,000 Six-Unit bock constructed
DACF DA, Works Dept.
MOE
Provide facilities for water harvesting in schools (tanks)
Selected schools
20,000 Facilities for water harvesting provided
DACF DA
Organize health talk in schools and communities
District wide
10,000 Health talk organized
GOG MOH GES
Provide gender friendly sanitary facilities in schools
Selected schools
300,000 Gender friendly sanitary facilities provided
GOG DA GES
Formation of girls clubs in schools
10,000 Girls clubs formed
GOG MOE
Provide guidance and counseling services in JHS
District wide
10,000 Guidance and counseling service provided
GOG MOE GES
Organize literacy and Arts
District wide
20,000 Literacy and art
GOG MOE GES
149
competition in upper primary
competition organized
Undertake BECAS, SEA & NEA
District wide
25,000 BECAS,SEA &NEA undertaken
GOG MOE GES
Organize INSET for teachers professional development
District wide
IGF MOE GES
Provide teaching and learning materials especially science for basic schools
District wide
400,000 Teaching and learning materials provided
GOG MOE GES
Organize mock examination for JHS students
District wide
200,000 Mock examination organized
IGF MOE GES
Conduct training for pre-school (KG) teachers
District wide
30,000 Training conducted
DACF
GES MOE
Provides material support to trained teachers on UTDBE
District wide
20,000 Material support provided
IGF GOG MOE GES
Implement best teacher award scheme
District wide
Best teacher award scheme implemented
GETFUND
MOE GES
150
Provide incentive package for teachers in deprived areas
Selected areas
50,000 Incentive package provided
GETFUND
MOE GES
Conduct regular school inspection and disseminate report
District wide
40,000 Regular school inspection conducted
GOG MOE GES
Ensure full participation of SMCs in school management
District wide
30,000 Participation of SMCs ensured
GETFUND
GES MOE
Conduct programme to educate and disseminate information in areas in the value of education and community involvement.
Selected areas
5,000 Programme to educate and disseminate information conducted
DACF
DA MOE
Encourage the use of gender clubs and promote the use of role models within school communities
District wide
10,000 Use of gender clubs and use of role models encouraged
GETFUND
DA MOE
Support girls in life skills support programmes
District wide
30,000 Girls in life skills supported
GETFUND
DA MOE
Provides INSET for Selected 10,000 INSET for IGF DA GES
151
professional development in science, mathematics and technical in schools
schools professional development in science, mathematics and technical in schools provided
Provide office building
Selected Dept.
200,000 Office building provided
GOG DA
Conduct regular inspection and ensure proper functioning of SMCs and PTAs
District wide
40,000 Regular inspection conducted
GOG MOE GES
Monitor government interventions
District wide
30,000 Government interventions monitored
GOG DA GES
Train statistics officers in information management
District 10,000 Statistics officers trained
GOG DA GES
Organize sensitization programmes
District wide
40,000 Sensitization programmes organized
IGF DA MOE
152
Construction of Primary School Block
Aluku 200,000.00 School Block constructed
GoG DA, Works Dept.
MOE
Construction of KG and Primary block.
Obeng-krom
200,000.00 KG and Primary block constructed
GoG DA, Works Dept.
GES,MOE
Construction of Community SHS.
Salman 1,000,000.00
Community SHS constructed
GOG DA, Works Dept.
MOE
Construction of additional school block.
Salman 250,000.00 Additional school block constructed
GOG DA, Works Dept.
GES
Stocking of Salman community library
Salman 100,000.00 Community library stocked
IGF GOG Donor DA, Works Dept.
GES
Construction of drainage facility at the entrance of cluster of schools at Tema.
Nkroful 250,000.00 Drainage facility constructed
IGF GOG DA, Works Dept.
Dept. of Feeder roads
Roofing of dilapidated school blks.
District Wide
8,000.00 Eikwe community JHS roofed
IGF DA, Works Dept.
GES
Provision of accommodation (staff quarters) for
Eikwe Sanzule, Krisan
500,000.00 Accommodation (staff quarters)
GOG GES DA, Works Dept.
153
teachers. for teachers provided
Construction of JHS block
New Bakanta
200,000.00 JHS block constructed
GoG GES DA, Works Dept.
Construction of Nursery block for Sanzule-Krisan Primary school.
Sanzule-Krisan
100,000.00 Nursery block constructed
GOG GES DA, Works Dept.
Construction of primary school block for Ngalekpole
Ngalekpole
200,000.00 Primary school block constructed
GoG DA, Works Dept.
MOE
Institution of a scholarship scheme for communities within the oil and gas catchment zone.
District wide
2,000,000.00
Scholarship scheme for communities instituted
IGF Donor DA, Works Dept.
m
Construct primary school
Atuabo 250,000.00 Primary school block constructed
GOG DA, Works Dept.
MOE
Construction of KG block for Asemdasuazo
Asemdasuazo
100,000.00 KG block constructed
GOG DA, Works Dept.
MOE
Construction of teachers’ quarters
Asemdasuazo
200,000.00 Teachers’ quarters
GOG DA, Works
MOE
154
at b Asemdasuazo constructed
Dept.
Construction of KG block and teachers quarters at Fiasolo
Fiasolo 400,000.00 KG block and teachers quarters constructed
GoG DA, Works Dept.
MOE
Construction of teachers quarters and KG block at Kanokware
Kanokware
400,000.00 Teachers quarters and KG block constructed
GoG DA, Works Dept.
MOE
Completion of teachers quarters at Nyamebekyere
Nyamebekyere
200,000.00 Teachers quarters completed
IGF GOG DA, Works Dept.
MOE
Construction of additional teachers’ quarters.
Nyamebekyere
250,000.00 Additional teachers’ quarters constructed.
GoG DA, Works Dept.
MOE
Construction of KG block at New Sanfo
Sanfo 100,000.00 KG block constructed
GoG DA, Works Dept.
MOE
Extension of school feeding programme to cover all communities with the Asasetre area council.
Asasetre Area Council
50,000.00 School feeding programme extended
GOG MOE GES
155
Construction of teacher quarters at Adubrim.
Adubrim 200,000.00 Teachers quarters constructed
GoG MOE DA, Works Dept.
Construction of school block at Ngabawie
Ngabawie 250,000.00 School block constructed
GOG MOE GES
Construction of teachers quarters for Mempeasem.
Mempeasem
250,000.00 Teachers quarters constructed
GoG MOE GES
Institute incentives for teachers at Adubrim
Adubrim 250000.00 IGF Donor DA GES
Revamping the ICT center at Asasetre
Asasetre 200,000.00 ICT center revamped
IGF Donor DA, Works Dept.
GES
Supply of teaching and learning materials for school.
Asasetre 2000,000.00 Teaching and learning materials supplied
IGF GOG Donor DA, Works Dept.
GES
Rehabilitation of catholic JHS/KG at Asanta and SDA Primary school.
Asanta 200,000.00 Catholic JHS/KG rehabilitated
GoG DA, Works Dept.
GES
Completion of computer laboratory at catholic school.
Asanta 100,000.00 Computer laboratory completed
GoG DA, Works Dept.
GES
156
Rehabilitation of Bobrama KG block
Bobrama 100,000.00 KG block rehabilitated
GoG DA, Works Dept.
GES
Provision of furniture (desk) for all schools.
Bobrama, Asanta , Ankobra
50,000.00 Furniture provided
GoG DA, Works Dept.
GES
Renovation of Ankobra primary school
Ankobra 100,000.00 Ankobra primary school renovated
GoG DA, Works Dept.
GES
Rehabilitation of Asemko primary school
Asemko 100,000.00 Primary school rehabilitated
GoG DA, Works Dept.
GES
Completion of community library for Asemko.
Asemko 150,000.00 Community library completed
GoG DA, Works Dept.
GES
Provision of additional KG and primary block and renovation of existing one at Baseke.
Baseke 900,000.00 Additional KG and primary block provided and renovated respectively
GoG MOE DA, Works Dept.
Construction of school block for Awiebo Methodist JHS
Awiebo 200,000.00 School block constructed
GoG MOE GES
Renovation of Roman Catholic
Awiebo 100,000.00 Roman Catholic
GoG MOE DA, Works Dept.
157
Primary school at Awiebo.
Primary school renovated
Construction of teachers quarters at Awiebo
Awiebo 200,000.00 Teachers quarters
GoG MOE DA, Works Dept.
Construction of Bungalow and security wall at BOKASS.
Awiebo 400,000.00 Bungalow and security wall constructed
GoG MOE DA, Works Dept.
Completion of classroom block at BOKASS.
Awiebo 150,000.00 Classroom block completed
GoG MOE DA, Works Dept.
Completion of Awiebo Roman Catholic KG block.
Awiebo 150,000.00 KG block constructed
GoG MOE DA, Works Dept.
Construction of new school block for Mantukwa Bibianiha and Domeabra
Mantukwa Bibianiha and Domeabra
600,000.00 School block constructed
GoG MOE DA, Works Dept.
Construction of JHS block for Baseke
Baseke 250,00.00 JHS block constructed
GoG
Construction of teachers quarters for communities
Mantukwa Ebi and Awiebo
750,00.00 Teachers quarters constructed
GoG MOE DA, Works Dept.
Construction of library for Baseke
Awiebo 600,000.00 Library constructe
GoG MOE DA, Works Dept.
158
and Awiebo d
Construction of school block for KG and Primary schools at Edwakpole
Edwakpole
50,000.00 School block constructed
GoG MOE DA, Works Dept.
Construction of teachers quarters for A.B Bokazo
A.B Bokazo
250,000.00 Teachers quarters constructed
GoG MOE DA, Works Dept.
Construction of toilet facilities for schools at A.B Bokazo
A.B Bokazo
500,000.00 Toilet facilities constructed
GoG MOE DA, Works Dept.
Construction of ICT facility for A.B Bokazo
A.B Bokazo
300,000.00 ICT facility constructed
GoG MOE DA, Works Dept.
Construction of JHS Block at Alla Bokazo.
Alla Bokazo
JAN
250,000.00 JHS block constructed
GoG MOE DA, Works Dept.
Construction of teachers’ quarters at Alla Bokazo
Alla Bokazo
250,000.00 Teachers quarters constructed
GoG MOE DA, Works Dept.
Construction of toilet facility for school at Alla Bokazo
Alla Bokazo
500,000.00 Toilet facility constructed
GoG MOE DA, Works Dept.
Provision of additional block for Kamgbunli KG, teaching and
Kamgbunli Additional block for Kamgbunli KG,
GoG GES DA, Works Dept.
159
learning materials and furniture.
teaching and learning materials and furniture provided.
Renovation of Kamgbunli Islamic Primary school and construction of additional block for ‘C’.
Kamgbunli 150,000.00 Kamgbunli Islamic Primary school renovated and additional block constructed
GoG MOE DA, Works Dept.
Provision of borehole for Kamgbunli cluster of schools
Kamgbunli 150,000.00 Borehole provided
GoG MOE DA, Works Dept.
Construction of toilet facility for Primary ‘B’ and JHS ‘B’
Kamgbunli 90,000.00 Toilet facility constructed
GoG MOE DA, Works Dept.
Provision of canteen for cluster of schools
Kamgbunli 8,000.00 canteen for cluster of schools provided
GoG MOE DA, Works Dept.
Provision of computer laboratory library
Kamgbunli 250,000.00 Computer laboratory library
GoG MOE DA, Works Dept.
160
block for cluster of schools
block provided
Construction of assembly hall for Kamgbunli SHS.
Kamgbunli 100,000.00 Assembly hall constructed
GoG MOE DA, Works Dept.
Provision of additional staff accommodation for staff of SHS.
Kamgbunli 200,000.00 Additional staff accommodation provided
GoG MOE DA, Works Dept.
Provision of duty or administrative vehicle for SHS.
Kamgbunli 80,000.00 Duty or Administrative vehicle provided
GoG MOE DA, Works Dept.
Provision of boy and girls hostels for SHS.
Kamgbunli 100,000.00 Boys and Girls hostels provided
GoG MOE DA, Works Dept.
Construction of Library block for SHS.
Kamgbunli 150,000.00 Library block constructed
GoG MOE DA, Works Dept.
Construction of school block for Kwasikrom (KG, Primary and JHS)
Kwasikrom
1,000,000.00
School block constructed
GoG MOE DA, Works Dept.
Construction of teachers quarters at Kwasikrom
Kwasikrom
250000.00 Teachers quarters constructed
GoG MOE GES,DA, Works Dept.
Provision of Kwasikro 10,000.00 Furniture IGF GoG GES DA
161
furniture for Kwasikrom schools (desk)
m provided
Supply of teachers for Kwasikrom
Kwasikrom
5,000.00 Teachers supplied
GoG GES MOE
Construction of KG block for Asomase
Asomase 1,00,000.00 KG block constructed
GoG MOE GES,DA, Works Dept.
Construction of school block for Sendaso
Sendaso 200,000.00 School block constructed
GoG MOE GES,DA, Works Dept.
Supply of teachers to Bonsukrom and Asomase communities
Bonsukrom and Asomase
5,000.00 Teachers supplied
GoG MOE GES,DA, Works Dept.
Construction of staff quarters for Aiyinase North Schools.
Aiyinase North
500,000.00 Staff quarters constructed
GoG MOE GES,DA, Works Dept.
Extent coverage of School feeding programme to Aiyinase North.
Aiyinase North
50,000.00 Coverage of school feeding programme extended
GoG MOE GES,DA, Works Dept.
Construction of teachers quarters
Akoto, Alloakpoke, Awiaso
750,000.00 Teachers quarters constructed
GoG MOE, DA, Works Dept. ,GES
162
4.1 THEMATIC AREA: Accelerated Agriculture Modernization And Sustainable Natural Resource Management.
Agriculture ACTIVITY LOCATION TIME FRAME INDICATIVE
BUDGET (GH₵)
INDICATOR SOURCES OF FUNDING IMPLEMENTING DEPARTMENT OF THE DA
2014 2015 2016 2017
Conduct 4000 farmers/farmer group visits by December annually by 10 AEAS
District wide
7,200.00 4000 farmers/farmers group conducted
IGF GoG Agric. Dept.
DA
Conduct 250 field days for 500 farmers and FBOs annually
District wide
5,000.00 250 field days for 500 farmers conducted
IGF GOG Agric.Dept.
DA
Conduct 500 supervisory visits by four (4) supervisors to backstop AEAS annually
District wide
5,760.00 500 supervisory visits conducted
IGF GOG Agric.Dept
DA
Treat 1000 clinical/surgical cases involving pigs, cattle sheep, goats by December
District wide
2,000.00 1000 clinical/surgical cases combated
IGF GOG Agric.Dept
DA
163
De-worm 20000 poultry and 200 livestock annually
District wide
1,000.00 20000 poultry and 200 livestock de-wormed
IGF GOG Agric.Dept
DA
Conduct ante/post mortem examination on slaughtered animals annually
District wide
1,000.00 Ante/post-mortem examination conducted
IGF GOG Agric.Dept
DA
Vaccinate 20000 poultry and 300 livestock and pets against rabies and other zoonotic diseases
District wide
2,000.00 20000 poultry and300 livestock vaccinated
IGF GOG Agric.Dept
DA
Carry out diseases surveillance and monitoring visits quarterly
District wide
500.00 Diseases surveillance and monitoring executed
IGF GOG Agric.Dept
DA
Organize two days’ workshop each for 40 farmers on beekeeping, snail rearing and mushroom production by December 2015
Nkroful 3,700.00 Two days’ workshop organized
IGF GOG Donor Agric.Dept
DA
Assist 10 FBO District 4,000.00 10 FBO IGF GOG MoFA DA
164
with leadership training on credit management
wide with leadership training on credit management assisted
Disseminate information via radio (F.M) station to educate farmers on new technologies and social agricultural issues quarterly every year
Esiama & Ankobra
800.00 Information via radio(F.M) disserminated
IGF MoFA
Organize 3 educational talks via radio on the effect of child labour in agriculture
Esiama 300.00 3 educational talks organized
IGF MoFA Dept of co-operative & social welfare
Hold two (2) days planning sessions with stakeholders annually
Aiyinase 7,000.00 Two days planning sessions performed
IGF GOG MoFA RADU/CSIR
Organize 2-days workshop for 60 pigs farmers on bio security measures to contain African Swine Fever in
Baku, Ngalekyi Ngalekpole Anokyi
3,000.00 Two days workshop organized
IGF GOG MoFA RADU
165
four (4) communities
Organize one (1) district farmers’ day celebration annually
Various 50,000.00 One district farmers day celebration organized
IGF GOG DONOR Agric.Dept
DA
Service one official car monthly
office 10,000.00 One official car serviced
IGF Agric.Dept
DA
Educate 50 farmers and farmer groups on safe use and handling of agro-chemicals
Aiyinase 1,500.00 50 farmers and farmer groups educated
Agric.Dept
RADU
Procure 5 motorbikes for official use by
Office 15,000.00 Five motorbikes procured
GOG Agric.Dept
DA
Procure one (1) set of stationery for office use annually
Office 2000.00 One set of stationery procured
IGF Agric.Dept
DA
Running cost of official vehicle annually
office 14,400.00 Cost of official vehicle operated
IGF Agric.Dept
DA
Facilitate the supply of agro-chemical and farm inputs to farmers
District wide
10,000 Supply of agro-chemical and farm
IGF GOG Agric.Dept
DA
166
inputs to farmers facilitated
Educate farmers on aqua culture/fish rearing
District wide
7,000 Farmers on aqua culture/fish rearing educated
IGF GOG Agric.Dept
DA
Train farmers on alternative sources of livelihood.
District wide
8,000 Farmers on alternative sources of livelihood trained.
IGF GOG Agric.Dept
DA
Revamp Aiyinase and Esiama oil mill
Esiama, Aiyinase
20,000 Aiyinase and Esiama oil mill revamped
IGF GoG Agric.Dept
DA, MOFA
Provision of agric extension services
District wide
10,000 Agric. extension services provided
GoG MoFA DA, Agric dept
Revamping of Kamgbunli rice irrigation project
Kamgbunli 50,000 Kamgbunli rice irrigation project revamped
IGF GoG Agric.Dept
DA
Encouraging agric diversification
District wide
5,000 Agric. Diversification encouraged
IGF GoG Donor Agric.Dept
DA
Conducting District 30,000 Research IGF GoG Donor Agric.D DA
167
research into the cocoa diseases
wide into the cocoa diseases conducted
ept
Supply of improved cocoa seedlings
Aiyinase north
40,000 Improved cocoa seedlings supplied
IGF Agric.Dept
DA
168
4.2 THEMATIC AREA: Human Development, Productivity & Employment
HEALTH DIRECTORATE. ACTIVITY LOCATION TIME FRAME INDICATIVE
BUDGET (GH₵)
INDICATOR SOURCES OF FUNDING IMPLEMENTING DEPARTMENT OF THE DA
2014 2015 2016 2017 IGF GoG DONOR
Construction of standardized CHPS compounds.
Kwesikrom Basake Aluku Anwia
1000,000.00 4 standardized CHPS compounds constructed
GoG Donors GHS DA, Works Dept.
Procurement of motorbikes to CHPS compounds.
All CHPS Zones
1000,000.00 Motorbikes procured for service delivery
IGF GoG Donor GHS MOH, DA
Procurement of essential service delivery equipment for CHPS.
All CHPS compounds.
All CHPS compounds provided essential equipment.
IGF GoG Donor GHS MOH, DA
Procure a robust 4 WD vehicle for mobile health care.
District 120,000.00 Mobile health services expanded to rural remote
GoG Donor GHS DA, MOH
169
communities.
Liaise with Adamus to release structure for mental health and eye care
Teleku Bokazo
200,000.00 Specialized health care established in the district.
IGF Donor GHS DA
Training of Assembly members, CHMCs and CHVs in new CHPS concept.
All CHPS/Electoral zones.
10,000.00 No of Assembly members, CHMCs and CHVs trained
IGF Donor GHS DA
Training of sub district health teams in health system management including CHPS.
Sub district management teams.
8,000.00 No of sub district health management teams trained.
IGF Donor GHS DA
Formation and training of Sub district health management committees.
Stakeholders at sub district levels.
10,000.00 No of sub district health committees formed; trained and functional.
IGF GoG Donor GHS DA
Provide quality motorbikes to CHPS compounds for service delivery.
CHPS zones.
300,000.00 No of CHPS compounds with quality motorbikes
IGF GoG Donor GHS MOH, DA
Provide basic All service 100,000.00 No of IGF GoG Donor GHS MOH, DA
170
service delivery equipment to health facilities.
delivery facilities.
facilities with adequate basic service delivery equipment.
Organize blood donation campaigns
Schools and communities.
15,000.00 No of blood donation campaigns in a year.
IGF Donor GHS MOH, DA
Construction of mother’s hostel.
Eikwe 45,000 No of mother’s hostel constructed.
IGF Donor GHS MOH, DA,
Establishment of national ambulance service in district.
Esiama/Aiyinasi.
50,000.00 No of ambulance.
IGF GHS MOH, DA
Identify and train community of based surveillance volunteers.
All communities in the district.
20,000.00 No of community based volunteers identified and trained.
IGF GHS MOH, DA
Organize routine immunization programs
All outreach points.
DEC.
15,000.00 IGF GoG GHS MOH, DA
171
Implement special national health promotion programs (NIDs, Measles immunization, MDDs, Bed net Distribution etc.).
All communities
20,000.00 No of children immunized.
IGF GoG GHS MOH, DA
Sensitization of communities on common endemic disease (TB, Malaria, HIV/AIDs etc).
All communities
20,000.00 No of people reached per program
IGF GoG Donor GHS MOH, DA
Conduct half yearly health screenings
Esiama, Nkroful, Aiyinasi Eikwe
2,000.00 No of screening activities carried out in a year.
IGF GHS MOH, DA
Implement National TB, HIV/AIDS and malaria programs.
All communities
10,000.00 % of cases detected and effectively managed.
GoG Donors GHS MOH, DA
Sensitization of communities on household latrines and safe environmental health practices.
All communities.
5,000.00 No of community sensitizations carried out.
IGF GoG GHS MOH, DA
Train service providers in
All GHS Facilities
10,000.00 Increase in IGF
IGF GHS MOH, DA
172
financial management.
generation by facilities.
Institute internal claims vetting and management at the DHMT
District wide
10,000.00 Reduction in NHIS claims deductions
GoG Donor GHS MOH, DA
Institute internal facility auditing mechanism
Facilities 15,000.000 Reduction in financial mismanagement.
IGF GoG GHS MOH, DA
Registration of aged and other vulnerable on NHIS.
District wide
50,000.00 No of vulnerable registered under NHIS.
IGF GoG GHS MOH, DA
Renovation of staff bungalow.
Aiyinasi health Center.
30,000.00 No of health centers upgraded to polyclinic in the district.
IGF Works Dept.
GHS, DA
Paint staff quarters.
Asasetre Health Center
3,000.00 No of nurses quarters painted
IGF Works Dept.
GHS
Complete of abandoned structure for maternity
Esiama Health Center
20,000.00 Completed structure being used for
GoG Donor Works Dept.
GHS, DA, MOH,
173
services. maternity services.
Construct toilet facility
Asasetre Health Center.
25,000.00 Toilet facility constructed
IGF GoG Donor Works Dept.
GHS, DA, MOH,
Provide antenatal and maternity services for communities.
District wide
100,000.00 IGF Donor GHS DA, MOH
Provide accommodation for health workers
District wide
600,000.00 Accommodation provided
IGF GoG Donor GHS DA, MOH
Upgrade CHPS to health centers
District wide
200,000.00 Centers upgraded
IGF GoG Donor GHS DA, MOH
Construct additional CHPS zones
Selected Commt
500,000.00 CHPS Constructed
GoG Donor GHS DA, MOH, Works Dept.
174
4.4 THEMATIC AREA: Transparent and Accountable Governance.
Non-Formal Education Division. ACTIVITY LOCATION TIME FRAME INDICATIVE
BUDGET (GH₵)
INDICATOR SOURCES OF FUNDING IMPLEMENTING DEPARTMENT OF THE DA
2014 2015 2016 2017 IGF GoG DONOR LEAD COLLAB.
Consult with district opinion leaders
District wide
5,000.00 Stake holders participation
IGF GoG Donor Non-Formal Edt. Unit
DA, NCCE
Conduct Land identification towards Construction of fish ponds
District wide
100,000.00 Fish ponds constructed
IGF Donor Non-Formal Edt. Unit
T&CPD, Works Dept.
Stock fish pond with fingerlings
District wide
5,000.00 Fish pond stocked
IGF Donors Non-Formal Edt. Unit
Agric. Dept.
Cultivate rice. Selected Commt
10,000.00 Rice cultivated
GoG Donor Non-Formal Edt. Unit
Agric. unit
175
4.5 THEMATIC AREA: Transparent and Accountable Governance.
Internal Audit ACTIVITY LOCATION TIME FRAME INDICATIVE
BUDGET (GH₵)
INCATOR SOURCES OF FUNDING IMPLEMENTING DEPARTMENT OF THE DA
2014 2015 2016 2017 IGF GoG Donor LEAD COLLAB.
Conduct Revenue and cash management
Nkroful n 3,000.00 Revenue and Cash managed
IGF Internal Audit Unit
DA, Finance Unit, Budget Unit
Implement Procurement management
Nkroful 2,000.00 Procurement activities managed
IGF Internal Audit Unit
Procurement Unit
Conduct special investigation
District Wide
3,000.00 Investigation conducted
IGF Internal Audit Unit
DISEC,
Conduct Stores and transport management
District wide
1,500.00 Stores and transport managed
IGF Internal Audit Unit
Transport Unit, Stores
Institute Pay roll management
District wide
2,000.00 Payroll management instituted
IGF Internal Audit Unit
DA, Finance Unit, Budget Unit
Institute Liability management
District wide
1,000.00 Liability managed
IGF Internal Audit Unit
Conduct Follow-up District 2,000.00 Follow ups IGF Internal DA, Finance
176
on audit recommendation
wide conducted Audit Unit
Unit
Institute Fixed asset management
District wide
1,000.00 Fix asset manage
IGF Internal Audit Unit
Estate Unit
Conduct IA external training
Nkroful 2,000.00 Training conducted
IGF Donors Internal Audit Unit
DA
Institute External audit liaison
Nkroful 1,000.00 External Audit liaison instituted
IGF Audit Unit
DA
Conduct Corporate governance
District wide
3,000.00 IGF Donors Internal Audit Unit
HR Dept.
Implement Accounting systems
Nkroful 1,000.00 Accounting systems implemented
IGF GoG Donors Internal Audit Unit
DA, Finance Unit
Institute Operational management reporting
Nkroful 1,500.00 Operational management reporting instituted
IGF GoG Internal Audit Unit
DA
Introduce Pre-payment vouching
District wide
Pre-payment vouching introduce
IGF Internal Audit Unit
Finance Unit
Introduce Budget cycle
District wide
Internal Audit Unit
Budget Unit
177
Sanitation District wide
National commission for civic education
Activities
Location Time frame Indicative budget(GH₵)
Output indicator Source of funding Implementing department of the DA
2014 2015 2016 2017 IGF GOG DONORS
LEAD
COLLABORATING
Sensitization on district level education
District wide
1,500.00 To increase the number of Assembly women from 5 to 10
GOG NCCE
EC,DA
Training of the newly elected Assembly/ unit committee members
Two area councils
3,000.00 To improve their performance in revenue mobilization
GOG NCCE
DA
Citizenship week celebration
District wide
1,600.00 To inculcate a civic culture
GOG NCCE
GES
Education on revenue mobilization(Duties of a
District wide
1,600.00 To raise awareness of citizens tax obligation and improve revenue
GOG NCCE
DA
178
citizen) mobilization
Education and pre-marital sex among teenagers in the district
All basic schools
2,500.00 Reduce the of teenage pregnancies and number of sexual engagement
GOG NCCE
GES
Education on Ebola Pandemic and Cholera outbreak
District wide
1,600.00 Improve awareness on Ebola Pandemic and Cholera Outbreak
GOG NCCE
EC, POLITICAL PARTIES, DA, GES ECT.
Improving sanitation conditions in the district
District wide
1,600.00 Improve sanitation to eradicate cholera
GOG NCCE
GHS, ENVIRONMENTAL HEALTH, DA, GES ECT.
GHANA POLICE SERVICE
ACTIVITIES LOCATION TIME FRAME INDICATIVE BUDGET(GH₵)
OUPUT INDICATORS
SOURCE OF FUNDING IMPLEMENTING DEPARTMENT OF DA
2014 2015 2016 2017 IGF GOG DONORS
LEAD COLLABORATING
Provide accommodation for 30
District police headquart
45,000.00 Accommodation for 30 personnel
GOG DA DA-WKS DEPT.
179
personnel ers Esiama
Provide 2 vehicles for patrols and official work
District police headquarters Esiama
70,000.00 2 vehicles for patrols and official work
GOG DA DA-WKS DEPT
Provide office equipment;2 printers and 1 photocopier
District police headquarters Esiama
20,000.00 Office equipment;2 printers and 1 photocopier
GOG DA DA-WKS DEPT
Provide accommodation for 3 personnel
District police headquarters Esiama
30,000.00 Accommodation for 3 personnel
GOG DA DA-WKS DEPT
Provide logistics and medical equipment
District police headquarters Esiama
40,000.00 Logistics and medical equipment
GOG DA DA-WKS DEPT
180
4.6 THEMATIC AREA: Infrastructure and Human Settlement Development
Water and Sanitation
ACTIVITY
LOCATION TIME FRAME INDICATIVE BUDGET
(GH₵)
INDICATOR SOURCES OF FUNDING IMPLEMENTING DEPARTMENT OF THE DA
2014 2015 2016 2017
IGF GoG Donor LEAD COLLAB.
Construction of modern final waste disposal site for effective waste management
District Wide
200,000.00 Waste management site constructed
IGF Donor Env. Health, DWST
DA
Expand potable water coverage
District wide
80,000.00 Potable water coverage expanded
GoG Donor DWST, Works Dept.
DA
Provide waste containers
Selected Commts.
200,000.00 Waste containers provided
IGF GoG Env. Health, Zoomlion
DA
Construct toilet facilities. (Aqua privy)
District wide
700,000.00 Aqua privy constructed
IGF GoG Env. Health, works Dept.
DA
Construct toilet facilities. (W/Cs)
District wide
800,000.00 W/Cs constructed
IGF GoG Env. Health, works Dept.
DA
181
Construct proper drainage systems
Kamgbunli, Esiama, Eikwe, Aiyinasi
50,000.00 IGF GoG Donor Works dept.
DA
Train all WSMTs & WATSANs
District Wide
50,000.00 WSMs & WATSANs trained
GoG Donors DWST DA
Prepare a new DWSP
Nkroful 7,000.00 DWSP prepared
IGF Donors DWST DA, CWSA
Construct Small Town Water System in larger town
Asanta, Ankobra
Water system
GoG Donors CWSA DWST, DA
4.7 THEMATIC AREA: Infrastructure and Human Settlement Development
Road Infrastructure ACTIVITY LOCATION TIME FRAME INDICATIVE
BUDGET (GH₵)
OUTPUT INDICATOR
SOURCES OF FUNDING IMPLEMENTING DEPARTMENT OF THE DA
2014 2015 2016 2017 IGF GoG DONOR LEAD COLLAB.
Construct access road and rehabilitate all existing roads
Aiyinase North
1,000,000.00
Aiyinsi North roads rehabilitated.
IGF Donor Feeder Road Dept.
DA
Construct access road for all communities.
Salman electoral area
800,000.00 Access roads constructe
GoG Donors Feeder Road Dept.
DA
182
d
Rehabilitate Access Road
Akoto-Alloakpoke, Ayawora, Awiaso, Fiasolo
1,000,000 Roads rehabilitated
GoG Donors Feeder Road Dept.
DA
Reshape all new site & town road
District Wide
700,000.00 All road reshaped
IGF GoG Donors Feeder Road Dept.
DA
Construct access Bridge
Mantukwa
400,000.00 Bridge Constructed
IGF GoG Feeder Road Dept.
DA
Construct farm tracks
District Wide
183
CHAPTER 5
5.0 ANNUAL ACTION PLAN FOR 2014 ACTIVIVITIES LOCATION OUTPUT
INDICATOR TIME SCHUDULE ANNUAL BUDGET
IMPLEMENTING AGENCIES
1st 2nd 3rd 4th Local External Lead Collaborating
Organize sensitization in communities
District wide
Sensitization organized
10,000 10,00150
GES DA
Provide material support to needy pupils in schools
All school Material support provided
13,002.00
MOE GES.
Renovation of Kamgbunli Islamic Primary school and construction of additional block for ‘C’.
Kamgbunli
Kamgbunli Islamic Primary school renovated and additional block constructed
150,000.00
MOE DA, Works Dept.
Provision of borehole for Kamgbunli cluster of schools
Kamgbunli
Borehole provided
150,000.00
MOE DA, Works Dept.
Construction of additional teachers’ quarters.
Nyamebekyere
Additional teachers’ quarters constructed
250,000.00
DA, Works Dept.
MOE
Completion of Awiebo Classroom block 150,000. MOE DA, Works
184
classroom block at BOKASS.
completed
00
Dept.
Construction of additional classroom for school ‘B’.
Kamgbunli
Additional classroom constructed
150,000.00
MOE DA, Works Dept.
Provision of furniture for Kwasikrom schools (desk)
Kwasikrom
Furniture provided
5,000.00
5,000.00 GES DA
Supply of teachers for Kwasikrom
Kwasikrom
Teachers supplied
5,000.00 GES MOE
Construction of KG block for Asomase
Asomase
KG block constructed
1,00,000.00
MOE GES, DA, Works Dept.
Supply of teachers to Bonsukrom and Asomase communities
Bonsukrom and
Asomase
Teachers supplied
5,000.00
MOE GES, DA, Works Dept.
Construction of teachers quarters for A.B Bokazo
A.B Bokazo
Teachers quarters constructed
250,000.00
MOE DA, Works Dept.
Completion of KG block at Akpandue and renovation of
Akpandue
KG block and primary school completed and
350,000.00
MOE DA, Works Dept.
185
primary school.
renovated respectively
Encourage the use of gender clubs and promote the use of role models within school communities
District wide
Use of gender clubs and use of role models encouraged
10,000
DA MOE
Conduct programme to educate and disseminate information in areas in the value of education and community involvement.
Selected areas
Programme to educate and disseminate information conducted
5,000
DA MOE
Ensure full participation of SMCs in school
District wide
Participation for SMCs ensured
30,000 GES MOE
Conduct 4000 farmers/farmer group visits by December annually by 10 AEAS
District wide
4000 farmers/farmers group conducted
3,600.00
3,600.00 Agric. Dept.
DA
Conduct 500 supervisory visits by four (4) supervisors to backstop AEAS annually
District wide
500 supervisory visits conducted
2880.00
2880.00 Agric.Dept
DA
186
Training of sub district health teams in health system management including CHPS.
Sub district management teams
No of sub district health management teams trained.
4,000.00
4,000.00 GHS DA.
Provide basic service delivery equipment to health facilities
All service delivery facilities
Basic service delivery health facilities provided
50,000.00
50,000.00
GHS MOH,DA
Conduct Revenue and cash management
Nkroful
Revenue and Cash managed
1,000.00
2,000.00 Internal Audit Unit
DA, Finance Unit, Budget Unit
Implement Procurement
Nkroful
Procurement implemented
2,000.00
Internal Audit Unit
Procurement unit
Consult with district opinion leaders
District wide
Stake holders participation
2,000.00
3,000.00 Non-Formal Edt. Unit
DA, NCCE
Expand potable water coverage
District wide
Potable water coverage expanded
80,000.00
DWST, Work
DA
187
s Dept.
Provide waste containers
Selected Commts.
Waste containers provided
50,000.00
150,000.00
Env. Health, Zoomlion
DA
Reshape all new site & town road
District Wide
All road reshaped
300,000.00
400,000.00
Feeder Road Dept
DA
Construction of toilet facility for Primary ‘B’ and JHS ‘B’
Kamgbunli
Toilet facility constructed
90,000.00
MOE
DA, Works Dept.
Provision of canteen for cluster of schools
Kamgbunli canteen for cluster of schools provided
8,000.00
MOE DA, Works Dept
Provision of computer laboratory library block for cluster of schools
Kamgbunli Computer laboratory library block provided
250,000.00
MOE DA, Works Dept
Completion of community library for Asemko.
Asemko
Community library completed
150,000.00
DA, Works Dept.
GES
Provision of furniture (desk) for all schools
Bobrama, Asanta , Ankobra
Furniture provided
50,000.00
DA, Works
GES
188
Dept.
Completion of computer laboratory at catholic school.
Asanta
Computer laboratory completed
100,000.00
DA, Works Dept
GES
Institute incentives for teachers at Adubrim
Adubrim
Incentives for teachers instituted
100,000.00
150,000.00
DA GES
Construction of additional KG block for Atuabo
Atuabo
Additional KG block constructed
100,000.00
DA, Works Dept.
MOE
Roofing of Eikwe community JHS
Eikwe
Eikwe community JHS roofed
8,000.00
DA, Works Dept
GES
Provision of accommodation (staff quarters) for teachers
Eikwe Sanzule, Krisan
Accommodation (staff quarters) for teachers provided
500,000.00
GES DA, Works Dept
Construction of Primary School Block
Aluku
School Block constructed
200,000.00
DA, Works Dept.
MOE
Monitor government interventions
District wide
Government interventions monitored
30,000
DA GES
189
Organize INSET for four frontline Deputy/A.Ds and management
District
INSET for four frontline Deputy/A.Ds and management organized
30,000
DA GES
District inspection and ensure proper functioning of SMCs and PTAs
District wide
Regular inspection conducted
40,000
MOE GES
Conduct regular school inspection and disseminate report
District wide
Regular school inspection conducted
40,000
MOE GES
Provide incentive package for teachers in deprived areas
Selected areas
Incentive package provided
50,000
MOE GES
Conduct training for pre-school (KG) teachers
District wide
Training conducted
30,000
GES MOE
Organize mock examination for JHS students
District wide
Mock examination organized
200,000
MOE GES
Provide teaching and District Teaching and 400,000 MOE GES
190
learning materials especially science for basic schools
wide
learning materials provided
Organize INSET for teachers professional
District wide
INSET for teachers professional organized
50,000 MOE GES
Organize literacy and Arts competition in upper primary
District wide
Guidance and counseling service provided
10,000
MOE GES
Formation of girls clubs in schools
District wide
Girls clubs formed
10,000
MOE GES
Organize health talk in schools and communities
District wide
Health talk organized
10,000
MOH GES
Rehabilitate KG school block
Selected areas
KG school rehabilitated
1,466,000
DA, Works Dept.
GES
Treat 1000 clinical/surgical cases involving pigs, cattle sheep, goats by December
District wide
1000 clinical/surgical cases combated
1,000.00
1,000.00 Agric.Dept
DA
191
De-worm 20000 poultry and 200 livestock annually
District wide
20000 poultry and 200 livestock
500.00 500.00 Agric.Dept
DA
Conduct ante/post mortem examination on slaughtered animals annually
District wide
Ante/post-mortem examination conducted
500.00 500.00 Agric.Dept
DA
Vaccinate 20000 poultry and 300 livestock and pets against rabies and other zoonotic diseases
District wide
20000 poultry and300 livestock vaccinated
1000.00
1000.00 Agric.Dept
DA
Carry out diseases surveillance and monitoring visits quarterly
District wide
Diseases surveillance and monitoring executed
250.00 250.00 Agric.Dept
DA
Organize two days’ workshop each for 40 farmers on beekeeping, snail rearing and mushroom production by December 2015
Nkroful
Two days’ workshop organized
2000.00
1700.00 Agric.Dep
DA
Disseminate information via radio (F.M) station to
Esiama & Ankobra
Information via radio(F.M) disseminated
800.00 MoFA
DA
192
educate farmers on new technologies and social agricultural issues quarterly every year
Hold two (2) days planning sessions with stakeholders annually
Aiyinase
Two days planning sessions performed
3500.00
3500.00 MoFA
RADU/CSIR
Organize 2-days workshop for 60 pigs farmers on bio security measures to contain African Swine Fever in four (4) communities
Baku, Ngalekyi Ngalekpole Anokyi
Two days’ workshop organized
1500.00
1500.00 MoFA
RADU
Organize one (1) district farmers’ day celebration annually
Various
One district farmers day celebration organized
20,000.00
30,000.00
Agric.Dept
DA
Service one official car monthly
office
One official car serviced
10,000.00
RADU
DA
Educate 50 farmers and farmer groups on safe use and handling
Aiyinase
50 farmers and farmer groups educated
1,500.00
Agric.Dept
RADU
193
of agro-chemicals
Procure one (1) set of stationery for office use annually
Office
One set of stationery procured
2000.00
Agric.Dept
DA
Running cost of official vehicle annually
office
Cost of official vehicle operated
14,400.00
Agric.Dept
DA
Facilitate the supply of agro-chemical and farm inputs to farmers
District wide
Supply of agro-chemical and farm inputs to farmers facilitated
5,000.00
5,000.00 Agric.Dept
DA
Educate farmers on aqua culture/fish rearing
District wide
Farmers on aqua culture/fish rearing educated
3,500.00
3,500.00 Agric.Dept
DA
Provision of agric extension services
District wide
Agric. extension services provided
10,000
MoFA
DA, Agric dept
Conducting research into the cocoa diseases
District wide
Research into the cocoa diseases conducted
5,000 25,000 Agric.Dept
DA
Supply of improved Aiyinase Improved cocoa 40,000 Agric. DA
194
cocoa seedlings
north
seedlings supplied
Dept
Organize blood donation campaigns
Schools and communities
No of blood donation campaigns in a year
7,500.00
7,500.00 GHS MOH,DA
Identify and train community of based surveillance volunteers
All communities in the district.
No of community based volunteers identified
20,000.00
GHS MOH,DA
Sensitization of communities on common endemic disease (TB, Malaria, HIV/AIDs etc).
All communities
No of people reached per program
5,000.00
15,000.00
GHS MOH,DA
Conduct half yearly health screenings
Esiama, Nkroful, Aiyinasi Eikwe
No of screening activities carried out in a year
2,000.00
GHS MOH,DA
Implement National TB, HIV/AIDS and malaria programs.
All communities
% of cases detected and effectively managed.
5,000.00
5,000.00 GHS MOH,DA
Institute internal claims vetting and management at the DHMT
District wide
Reduction in NHIS claims deductions
5,000.00
5,000.00 GHS MOH,DA
195
Institute internal facility auditing mechanism
Facilities
Reduction in financial mismanagement.
7,500.00
7,500.00 GHS MOH,DA
Provide antenatal and maternity services for communities
District wide
antenatal and maternity service provided
50,000.00
50,000.00
GHS DA,MOH
Construct additional CHPS zones
Selected Commt
CHPS Constructed
500,000.00
GHS DA, MOH, Works Dept
Conduct special investigation
District Wide
Stores and transport managed
1,500.00
Internal Audit Unit
Transport Unit, Stores
Institute Pay roll management
District wide
Payroll management instituted
2,000.00
Internal Audit Unit
DA, Finance Unit, Budget Unit
Institute Liability management
District wide
Liability managed
1,000.00
Internal Audit Unit
DA, Finance Unit, Budget Unit
Conduct Follow-up on District Follow ups 2,000.0 Inter DA,
196
audit recommendation
wide
conducted
0
nal Audit Unit
Finance Unit
Institute Fixed asset management
District wide
Fix asset managed
1,000.00
Internal Audit Unit
Estate Unit
Conduct IA external training
Nkroful
Training conducted
1,000.00
1,000.00 Internal Audit Unit
DA
Institute External audit liaison
Nkroful
External Audit liaison instituted
1,000.00
Audit Unit
DA
Conduct Corporate governance
District wide
Corporate governance conducted
1,500.00
1,500.00 Internal Audit Unit
HR Dept.
Institute Operational management reporting
Nkroful
Operational management reporting instituted
1,000.00
500.00 Internal Audit Unit
DA
Introduce Pre-payment vouching
District wide
Pre-payment vouching introduce
10,000.00
Internal Audit Unit
Finance Unit
197
Introduce Budget cycle
District wide
Budget cycle introduced
5,000.00
Internal Audit Unit
Budget Unit
Construct toilet facilities. (Aqua privy
District wide
Aqua privy constructed
350,000.00
350,000.00
Env. Health, works Dept.
DA
Construct toilet facilities. (W/Cs)
District wide
W/Cs constructed
400,000.00
400,000.00
Env. Health, works Dept.
DA
Train all WSMTs & WATSANs
District Wide
WSMs & WATSANs trained
50,000.00
DWST
DA
Sensitization on district level education
District wide
To increase the number of Assembly women from 5 to 10
1,500.00 NCCE EC,DA
Citizenship week celebration
District wide
To inculcate a civic culture
1,600.00 NCCE DA
Education on revenue mobilization(Duties of a citizen)
District wide
To raise awareness of citizens tax obligation and improve revenue
1,600.00 NCCE DA
198
mobilization
Education and pre-marital sex among teenagers in the district
All basic schools
Reduce the of teenage pregnancies and number of sexual engagement
2,500.00 NCCE GES
Education on Ebola Pandemic and Cholera outbreak
District wide
Improve awareness on Ebola Pandemic and Cholera Outbreak
1,600.00 NCCE EC, POLITICAL PARTIES, DA, GES ECT.
Improving sanitation conditions in the district
District wide
Improve sanitation to eradicate cholera
1,600.00 NCCE GHS, ENVIRONMENTAL HEALTH, DA, GES ECT.
Provide accommodation for 3 personnel
District police headquarters Esiama
Accommodation for 3 personnel provided
30,000.00
DA DA-WKS DEPT
199
5.1 ANNUAL ACTION PLAN 2015
Activities Location Output indicators
Time frame Annual budget Implementing agencies
1st 2nd 3rd 4th Local External Lead Collaborating
Construction of teachers quarters at Kwasikrom
Kwasikrom
Teachers quarters constructed
250000.00
MOE
DA, Works Dept. ,GES
Construction of school block for Kwasikrom
Kwasikrom
School block constructed
1,000,000.00
MOE
DA, Works Dept
Construction of staff quarters for Aiyinase North Schools.
Aiyinase North
Staff quarters constructed
500,000.00
MOE
GES, DA, Works Dept.
Construction of school block for Sendaso
Sendaso
School block constructed
200,000.00
MOE
GES,DA, Works Dept
Renovation of Roman Catholic Primary school at Awiebo.
Awiebo
Roman Catholic Primary school renovated
100,000.00
MOE
DA, Works Dept.
Construction of toilet facilities for schools at A.B Bokazo
A.B Bokazo
Toilet facilities constructed
500,000.00
MOE
DA, Works Dept.
200
Construction of JHS block for Baseke
Baseke
JHS block constructed
250,00.00
MOE
DA, Works Dept
Construction of ICT facility for A.B Bokazo
A.B Bokazo
ICT facility constructed
300,000.00
MOE DA, Works Dept
Construction of JHS Block at Alla Bokazo
Alla Bokazo
JHS block constructed
250,000.00
MOE DA, Works Dept
Construction of teachers’ quarters at Alla Bokazo
Alla Bokazo
Teachers quarters constructed
250,000.00
MOE DA, Works Dept
Construction of toilet facility for school at Alla Bokazo
Alla Bokazo
Toilet facility constructed
500,000.00
MOE DA, Works Dept
Provision of additional block for Kamgbunli KG, teaching and learning materials and furniture.
Kamgbunli
Additional block for Kamgbunli KG, teaching and learning materials and furniture provided
200,000.00
GES DA, Works Dept
Provision of boy and girls hostels for SHS
Kamgbunli
Boys and Girls hostels provided
100,000.00
MOE DA, Works Dept
Construction of Library block for SHS
Kamgbunli
Library block constructed
150,000.00
MOE DA, Works Dept
201
Provision of access road for SHS and entire community roads
Kamgbunli
Access road provided
300,000.00
MOE DA, Works Dept
Construction of school block for Kwasikrom
Kwasikrom
School block constructed
1,000,000.00
MOE DA, Works Dept
Supply of teaching and learning materials for school.
Asasetre
Teaching and learning materials supplied
200,000.00
DA, Works Dept
GES
Institute incentives for teachers at Adubrim
Adubrim
incentives for teachers instituted
150,000.00
100,000.00
DA GES
Completion of Adubrim school (GETFUND) project for Primary, JHS and KG.
Adubrim
Adubrim school project completed
50,000.00
MOE GES
Construction of KG block at New Sanfo
Sanfo
KG block constructed
100,000.00
DA, Works Dept
MOE
Construction of teachers quarters and KG block at Kanokware
Kanokware
Teachers quarters and KG block constructed
400,000.00
DA, Works Dept
MOE
202
Institution of a scholarship scheme for communities within the oil and gas catchment zone.
District wide
Scholarship scheme for communities instituted
1,000,000.00
1,000,000.00
DA
MOE
Stocking of Salman community library
Salman
Community library stocked
100,000.00
150,000.00
DA GES
Organize sensitization programmes
District wide
Sensitization programmes organized
40,000
DA MOE
Train statistics officers in information management
District
Statistics officers trained
10,000
DA GES
Monitor government interventions
District wide
Government interventions monitored
30,000
DA GES
Conduct regular inspection and ensure proper functioning of SMCs and PTAs
District wide
Regular inspection conducted
40,000
MOE GES
Provides science consumables
Selected schools
Science consumables provided
20,000
DA MOE
203
Ensure full participation of SMCs in school
District wide
Participation of SMCs ensured
30,000
GES MOE
Conduct regular school inspection and disseminate report
District wide
Regular school inspection conducted
40,000
MOE GES
Provide incentive package for teachers in deprived areas
Selected areas
Incentive package provided
50,000
MOE GES
Conduct training for pre-school (KG) teachers
District wide
Training conducted
30,000
GES MOE
Organize mock examination for JHS students
District wide
Mock examination organized
200,000
MOE GES
Organize INSET for teachers professional
District wide
INSET for teachers organized
10,000.00
MOE GES
Organize literacy and Arts competition in upper primary
District wide
Literacy and art competition organized
20,000
MOE GES
Provide guidance and counseling services in JHS
District wide
Guidance and counseling service provided
10,000
MOE GES
204
Provide gender friendly sanitary facilities in schools
Selected schools
Gender friendly sanitary facilities provided
300,000
DA GES
Organize health talk in schools and communities
District wide
Health talk organized
10,000
MOH GES
Provide material support to needy pupils in schools
All School
Material support provided
13,002.00
GES MOE
Organize sensitization in communities
Sensitization organized
10,0150.00
10,00.00 GES DA
Conduct 4000 farmers/farmer group visits by December annually by 10 AEAS
District wide
4000 farmers/farmers group conducted
3,000.00
4,200.00 Agric. Dept
DA
Conduct 250 field days for 500 farmers and FBOs annually
District wide
250 field days for 500 farmers conducted
2,500.00
2,500.00 Agric. Dept.
DA
Conduct 500 supervisory visits by four (4) supervisors to backstop AEAS
District wide
500 supervisory visits conducted
3,000.00
2,760.00 Agric. Dept.
DA
205
annually
Treat 1000 clinical/surgical cases involving pigs, cattle sheep, goats by December
District wide
1000 clinical/surgical cases combated
1000.00
1000.00 Agric. Dept.
DA
De-worm 20000 poultry and 200 livestock annually
District wide
20000 poultry
and 200 livestock
de-wormed
500.00 5000.00 Agric. Dept.
DA.
Conduct ante/post mortem examination on slaughtered animals annually
District wide
Ante/post-mortem examination conducted
500.00 500.00 Agric. Dept.
DA
Vaccinate 20000 poultry and 300 livestock and pets against rabies and other zoonotic diseases
District wide
20000 poultry and300 livestock vaccinated
1,000.00
1,000.00 Agric. Dept.
DA
Carry out diseases surveillance and monitoring visits quarterly
District wide
Diseases surveillance and monitoring executed
250.00 250.00 Agric. Dept.
DA
206
Assist 10 FBO with leadership training on credit management
District wide
10 FBO with leadership training on credit management assisted
2,000.00
2,000.00 MoFA
DA
Disseminate information via radio (F.M) station to educate farmers on new technologies and social agricultural issues quarterly every yea
Esiama & Ankobra
Information via radio(F.M) disseminated
800.00 MoFA
DA
Hold two (2) days planning sessions with stakeholders annually
Aiyinase
Two days planning sessions performed
3,500.00
3,500.00 MoFA
RADU/CSIR
Organize one (1) district farmers’ day celebration annually
Various location
One district farmers day celebration organized
20,000.00
30,000.00
Agric. Dept.
DA
Service one official car monthly
office
One official car serviced
10,000.00
Agric. Dept.
DA
Procure one (1) set of stationery for
Office
One set of stationery
2000.00
Agric. Dept.
DA
207
office use annually
procured
Running cost of official vehicle annually
office
Cost of official vehicle operated
14,400.00
Agric. Dept.
DA
Facilitate the supply of agro-chemical and farm inputs to farmers
District wide
Supply of agro-chemical and farm inputs to farmers facilitated
5,000.00
5,000.00 Agric. Dept.
DA
Train farmers on alternative sources of livelihood.
District wide
Farmers on alternative sources of livelihood trained
4,000.00
4,000.00 Agric. Dept.
DA
Provision of agric extension services
District wide
Agric. extension services provided
10,000
MoFA
DA, Agric dept
Encouraging agric diversification
District wide
Agric. Diversification encouraged
2,000.00
3,000.00 Agric. Dept.
DA
Conducting research into the cocoa diseases
District wide
Research into the cocoa diseases conducted
10,000.00
20,000.00
Agric. Dept.
DA
Supply of improved cocoa
Aiyinase north
Improved cocoa seedlings
40,000
Agric. Dept.
DA
208
seedlings
supplied
Construction of standardized CHPS compounds
Kwesikrom Basake Aluku Anwia
4 standardized CHPS compounds constructed
1000,000.00
GHS DA, Works Dept.
Procurement of motorbikes to CHPS compounds
All CHPS Zones
Motorbikes procured for service delivery
300,000.00
700,000.00
GHS MOH,DA
Procurement of essential service delivery equipment for CHPS.
All CHPS compounds
All CHPS compounds provided essential equipment
30,000.00
70,000.00
GHS MOH,DA
Liaise with Adamus to release structure for mental health and eye care
Teleku Bokazo
Specialized health care established in the district.
100,000.00
100,000.00
GHS DA
Training of Assembly members, CHMCs and CHVs in new CHPS concept.
All CHPS/Electoral zones
No of Assembly members, CHMCs and CHVs trained
5,000.00
5,000.00 GHS DA
Training of sub district health teams in health system management including CHPS.
Sub district management teams
No of sub district health management teams trained
4,000.00
4,000.00 GHS DA
209
Formation and training of Sub district health management committees
Stakeholders at sub district levels
No of sub district health committees formed; trained and functional
3,000.00
7,000.00 GHS DA
Provide quality motorbikes to CHPS Compounds for service delivery.
CHPS zones
No of CHPS compounds with quality motorbikes compounds with quality motorbikes
100,000.00
200,000.00
GHS MOH,DA
Provide basic service delivery equipment to health facilities.
All service delivery facilities.
No of facilities with adequate basic service delivery equipment.
30,000.00
70,000.00
GHS
MOH, DA
Organize blood donation campaigns
Schools and communities.
No of blood donation campaigns in a year.
10,000.00
5,000.00 GHS
MOH, DA
Establishment of national ambulance service in district.
Esiama/Aiyinasi.
No of ambulance.
50,000.00
GHS
MOH, DA
210
Identify and train community of based surveillance volunteers
All communities in the district.
No of community based volunteers identified and trained.
20,000.00
GHS
MOH, DA
Organize routine immunization programs
All outreach points.
Routine immunization organized
10,000.00
5000,00.00
GHS
MOH, DA
Implement special national health promotion programs (NIDs, Measles immunization, MDDs, Bed net Distribution etc.).
All communities
No of children immunized.
10,000.00
10,00.00 GHS
MOH, DA
Sensitization of communities on common endemic disease (TB, Malaria, HIV/AIDs etc).
All communities
No of people reached per program
5,000.00
15,000.00
GHS
MOH, DA
Conduct half yearly health screenings
Esiama, Nkroful, Aiyinasi Eikwe
No of screening activities carried out in a year.
2,000.00
GHS
MOH, DA
Implement National TB, HIV/AIDS and
All communities
% of cases detected and
10,000.00
GHS MOH, DA
211
malaria programs.
effectively
Sensitization of communities on household latrines and safe environmental health practices
All communities.
No of community sensitizations carried out.
2,000.00
3,000.00 GHS MOH, DA
Train service providers in financial management
All GHS Facilities
Increase in IGF generation by facilities
10,000.00
GHS MOH, DA
Institute internal claims vetting and management at the DHMT
District wide
Reduction in NHIS claims deductions
10,000.00
GHS MOH, DA
Institute internal facility auditing mechanism
Facilities
Reduction in financial mismanagement
8,000.00
7,000.00 GHS MOH, DA
Paint staff quarters
Asasetre Health Center
No of nurses quarters painted
3,000.00
Works Dept.
GHS
Construct toilet facility
Asasetre Health Center.
Toilet facility constructed
10,000.00
15,000.00
Works Dept
GHS, DA, MOH
Provide antenatal and maternity
District wide
Antenatal and maternity
70,000.00
30,000.00
GHS DA, MOH
212
services for communities
services provided
Provide accommodation for health workers
District wide
Accommodation provided
200,000.00
400,000.00
GHS DA, MOH
Upgrade CHPS to health centers
District wide
Centers upgraded
50,000.00
150,000,00
GHS DA, MOH
Construct additional CHPS zones
Selected Commt
CHPS Constructed
500,000.00
GHS DA, MOH, Works Dept
Consult with district opinion leaders
District wide
Stake holders participation
2,000.00
3,000.00 Non-Formal Edt. Unit
DA, NCCE
Cultivate rice.
Selected Commt
Rice cultivated
10,000.00
Non-Formal Edt. Unit
Agric. unit
Conduct Revenue and cash management
Nkroful
Revenue and Cash managed
3,000.00
Internal Audit Unit
DA, Finance Unit, Budget Unit
Implement Procurement
Nkroful
Procurement activities
2,000.00
Internal Audit
Procurement unit
213
management
managed
Unit
Conduct special investigation
District Wide
Investigation conducted
3,000.00
Internal Audit Unit
DISEC,
Conduct Stores and transport management
District wide
Stores and transport managed
1,500.00
Internal Audit Unit
Transport Unit, Stores
Institute Pay roll management
District wide
Payroll management instituted
2,000.00
Internal Audit Unit
DA, Finance Unit, Budget Unit
Institute Liability management
District wide
Liability managed
1,000.00
Internal Audit Unit
DA, Finance Unit, Budget Unit
Conduct Follow-up on audit recommendation
District wide
Follow ups conducted
2,000.00
Internal Audit Unit
DA, Finance Unit
Institute Fixed asset management
District wide
Fix asset manage
1,000.00
Internal Audit Unit
Estate Unit
214
Conduct IA external training
Nkroful
Training conducted
2,000.00
Internal Audit Unit
DA
Institute External audit liaison
Nkroful
External Audit liaison instituted
1,000.00
Internal Audit Unit
DA
Conduct Corporate governance
District wide
Corporate governance conducted
3,000.00
Internal Audit unit
HR Dept.
Implement Accounting systems
Nkroful
Accounting systems implemented
300.00 700.00 Internal Audit Unit
DA, Finance Unit
Institute Operational management reporting
Nkroful
Operational management reporting instituted
500.00 1,000.00 Internal Audit Unit
DA
Introduce Pre-payment vouching
District wide
Pre-payment vouching introduce
1,000.00
Internal Audit Unit
Finance Unit
Introduce Budget cycle
District wide
Budget cycle introduced
1,000.00
Internal Audit Unit
Budget Unit
Expand potable water coverage
District wide
Potable water coverage
80,000.00
DWST, Works
DA
215
expanded
Dept
Provide waste containers
Selected Commts
Waste containers provided
100,000.00
100,000.00
Env. Health, Zoomlion
DA
Construct toilet facilities. (Aqua privy)
District wide
Aqua privy constructed
350,000.00
350,000.00
Env. Health, works Dept
DA
Construct toilet facilities. (W/Cs)
District wide
W/Cs constructed
400,000.00
400,000.00
Env. Health, works Dept
DA
Construct proper drainage systems
Kamgbunli, Esiama, Eikwe, Aiyinasi
Proper drainage systems constructed
20,000.00
30,000.00
Works dept
DA
Train all WSMTs & WATSANs
District Wide
WSMs & WATSANs trained
50,000.00
DWST
DA
Prepare a new DWSP
Nkroful
DWSP prepared
5,000.00
2,000.00 DWST
DA, CWSA
Construct access road and the rehabilitate all existing roads
Aiyinase North
Aiyinsi North roads rehabilitated
500,000.00
500,000.00
Feeder Road Dept
DA
Rehabilitate Access Road
Akoto-Alloakpoke, Ayawora, Awiaso, Fiasolo
Roads rehabilitated
1,000,000
Feeder Road Dept
DA
216
Reshape all new site & town road
District Wide
All road reshaped
300,000.00
400,000.00
Feeder Road Dept
DA
Construct access Bridge
Mantukwa
Bridge Constructed
200,000.00
200,000.00
Feeder Road Dept
DA
Sensitization on district level education
District wide To increase the number of Assembly women from 5 to 10
1,500.00 NCCE EC,DA
Training of the newly elected Assembly/ unit committee members
Two area councils To improve their performance in revenue mobilization
3,000.00 NCCE DA
Citizenship week celebration
District wide To inculcate a civic culture
1,600.00 NCCE GES
Education on revenue mobilization(Duties of a citizen)
District wide To raise awareness of citizens tax obligation and improve revenue mobilization
1,600.00 NCCE DA
Education and pre-marital sex among teenagers in the district
All basic schools Reduce the of teenage pregnancies and number of sexual engagement
2,500.00 NCCE GES
Education on Ebola Pandemic and
District wide Improve awareness on
1,600.00 NCCE EC, POLITICAL
217
Cholera outbreak Ebola Pandemic and Cholera Outbreak
PARTIES, DA, GES ECT.
Improving sanitation conditions in the district
District wide Improve sanitation to eradicate cholera
1,600.00 NCCE GHS, ENVIRONMENTAL HEALTH, DA, GES ECT.
Provide office equipment;2 printers and 1 photocopier
District police headquarters Esiama
Office equipment;2 printers and 1 photocopier provided
20,000.00
DA DA-WKS DEPT
Provide logistics and medical equipment
District police headquarters Esiama
Logistics and medical equipment provided
40,000.00
DA DA-WKS DEPT
218
5.4 ANNUAL ACTION PLAN FOR 2016
ACTIVITIES
LOCATION
OUTPUT INDICATORS
TIME FRAME ANNUAL BUDGET IMPLEMENTING AGENCIES
1st 2nd 3rd 4th Local External Lead Collaborating
Organize sensitization in communities
District Wide
Sensitization organized
10,000.00
10,0150.00
GES DA
Provide material support to needy pupils in schools
All School
Material support provided
13,002.00
GES MOE
Construction of 3-Unit KG block with ancillary facilities
Selected area
Three –Unit KG block constructed
1,980,400
DA, Works Dept.
GES
Completion of 6-unit classroom block
Selected area
Six-Unit bock constructed
300,000
DA, Works Dept.
MOE
Organize health talk in schools and communities
District wide
Health talk organized
10,000
MOH GES
Provide guidance and counseling services in JHS
District wide
Guidance and counseling service provided
10,000
MOE GES
Organize literacy and Arts competition in upper primary
District wide
Literacy and art competition organized
20,000
MOE GES
219
Organize INSET for teachers professional development
District wide
INSET for teachers professional development organized
10,000.00
MOE GES
Organize mock examination for JHS students
District wide
Mock examination organized
200,000
MOE GES
Conduct training for pre-school (KG) teachers
District wide
Training conducted
30,000
GES MOE
Provide incentive package for teachers in deprived areas
Selected areas
Incentive package provided
50,000
MOE GES
Conduct regular school inspection and disseminate report
District wide
Regular school inspection conducted
40,000
MOE GES
Ensure full participation of SMCs in school management
District wide
Participation of SMCs ensured
30,000
GES MOE
Provides INSET for professional development in
Selected schools
INSET for professional development in
10,000
DA GES
220
science, mathematics and technical in schools
science, mathematics and technical in schools provided
Conduct regular inspection and ensure proper functioning of SMCs and PTAs
District wide
Regular inspection conducted
40,000
MOE GES
Monitor government interventions
District wide
Government interventions monitored
30,000
DA GES
Procure office stationery
Selected Dept.
Office stationery procured
50,000
DA GES
Construction of Community SHS
Salman
Community SHS constructed
1,000,000.00
DA, Works Dept
MOE
Construction of drainage facility at the entrance of cluster of schools at Tema.
Nkroful
Drainage facility constructed
150,000.00
100,000.00
DA, Works Dept
Dept. of Feeder roads
Construction of Nursery block for Sanzule-Krisan
Sanzule-Krisan
Nursery block constructed
100,000.00
GES DA, Works Dept.
221
Primary school
Construction primary school block for Atuabo
Atuabo
Primary school block constructed
250,000.00
DA, Works Dept
MOE
Construction of teachers’ quarters at b Asemdasuazo
Asemdasuazo
Teachers’ quarters constructed
200,000.00
DA, Works Dept
MOE
Extension of school feeding programme to cover all communities with the Asasetre area council
Asasetre Area Council
School feeding programme extended
50,000.00
MOE GES
Construction of school block at Ngabawie
Ngabawie
School block constructed
250,000.00
MOE GES
Institute incentives for teachers at Adubrim
Adubrim
Incentives for teachers instituted
150,000.00
100,000.00
DA GES
Revamping the ICT center at Asasetre
Asasetre
ICT center revamped
150,000.00
50,000.00 DA, Works Dept.
GES
Rehabilitation of Bobrama KG block
Bobrama
KG block rehabilitated
100,000.00
DA, Works Dept.
GES
222
Renovation of Ankobra primary school
Ankobra
Ankobra primary school
100,000.00
DA, Works Dept.
GES
Construction of storm drain from SDA school to Methodist school
Asemko
Storm drain constructed
100,00.00
DA, Works Dept
GES
Provision of additional KG and primary block and renovation of existing one at Baseke
Baseke
Additional KG and primary block provided and renovated respectively
900,000.00
MOE DA, Works Dept
School electrification
Kamgbunli
School electrification provided
10,000.00
MOE DA, Works Dept.
Extension of playing field for cluster of schools
Kamgbunli
Playing field extended
5,000.00
MOE DA, Works Dept.
Construction of assembly hall for Kamgbunli SHS.
Kamgbunli
Assembly hall constructed
100,000.00
MOE DA, Works Dept
Provision of additional staff
Kamgbunli
Additional staff accommodation
200,000.00
MOE DA, Works Dept
223
accommodation for staff of SHS.
provided
Provision of duty or administrative vehicle for SHS.
Kamgbunli
Duty or Administrative vehicle provided
80,000.00
MOE DA, Works Dept.
Extent coverage of School feeding programme to Aiyinase North.
Aiyinase North
Coverage of school feeding programme extended
50,000.00
MOE GES,DA, Works Dept
Conduct 4000 farmers/farmer group visits by December annually by 10 AEAS
District wide
4000 farmers/farmers group conducted
3,700.00 3,500.00 Agric. Dept.
DA
Conduct 250 field days for 500 farmers and FBOs annually
District wide
250 field days for 500 farmers conducted
2,500.00 2,500.00 Agric. Dept
DA
Conduct 500 supervisory visits by four (4) supervisors to backstop AEAS annually
District wide
500 supervisory visits conducted
3,000.00 2,760.00 Agric. Dept
DA
Treat 1000 clinical/surgical cases involving pigs, cattle sheep, goats by
District wide
1000 clinical/surgical cases combated
1,000.00 1,000.00 Agric. Dept.
DA
224
December
De-worm 20000 poultry and 200 livestock annually
District wide
20000 poultry and 200 livestock de-wormed
500.00 500.00 Agric. Dept.
DA
Conduct ante/post mortem examination on slaughtered animals annually
District wide
Ante/post-mortem examination conducted
500.00 500.00 Agric. Dept.
DA
Vaccinate 20000 poultry and 300 livestock and pets against rabies and other zoonotic diseases
District wide
20000 poultry and300 livestock vaccinated
1000.00 1000.00 Agric. Dept.
DA
Carry out diseases surveillance and monitoring visits quarterly
District wide
Diseases surveillance and monitoring executed
250.00 250.00 Agric. Dept.
DA
Disseminate information
via radio (F.M) station to educate
farmers on new technologies and
Esiama & Ankobra
Information via radio(F.M) disseminated
800.00 MoFA
DA
225
social agricultural issues quarterly
every year
Organize 3 educational talks via radio on the effect of child labour in agriculture
Esiama
3 educational talks organized
300.00 MoFA
Dept of co-operative & social welfare
Hold two (2) days planning sessions with stakeholders annually
Aiyinase
Two days planning sessions performed
3,500.00 3,500.00 MoFA
Organize one (1) district farmers’ day celebration annually
Various
One district farmers day celebration organized
20,000.00
30,000.00 Agric. Dept.
DA
Service one official car monthly
office
One official car serviced
10,000.00
Agric. Dept.
DA
Procure one (1) set of stationery for office use annually
Office
One set of stationery procured
2000.00
Agric. Dept.
DA
Running cost of official vehicle annually
office
Cost of official vehicle operated
14,400.00
Agric. Dept.
DA
Facilitate the supply District wide Supply of agro- 5,000.00 5,000.00 Agric. DA
226
of agro-chemical and farm inputs to farmers
chemical and farm inputs to farmers facilitated
Dept.
Educate farmers on aqua culture/fish rearing
District wide
Farmers on aqua culture/fish rearing educated
3,500.00 3,500,00 Agric. Dept.
DA
Provision of agric extension services
District wide
Agric. extension services provided
10,000
MoFA
DA, Agric. Dept.
Revamping of Kamgbunli rice
irrigation project
Kamgbunli
Kamgbunli rice irrigation project revamped
25,000.00
25,000.00 Agric. Dept.
DA
Conducting research into the cocoa diseases
District wide
Research into the cocoa diseases conducted
10,000.00
20,000.00 Agric. Dept.
DA
Supply of improved cocoa seedlings
Aiyinase north
Improved cocoa seedlings supplied
40,000
Agric. Dept.
DA
Construction of standardized CHPS compounds
Kwesikrom Basake Aluku Anwia
4 standardized CHPS compounds constructed
1000,000.00
GHS DA, Works Dept
Procurement of All CHPS Zones Motorbikes 300,000. 700,000.0 GHS MOH,DA
227
motorbikes to CHPS compounds
procured for service delivery
00 0
Procurement of essential service delivery equipment for CHPS
All CHPS compounds
All CHPS compounds provided essential equipment
10,000.00
20,000.00 GHS MOH,DA
Procure a robust 4 WD vehicle for mobile health care
District
Mobile health services expanded to rural remote communities
120,000.00
GHS DA,MOH
Training of Assembly members, CHMCs and CHVs in new CHPS concept.
All CHPS/Electoral zones
No of Assembly members, CHMCs and CHVs trained
5,000.00 5,000.00 GHS DA
Training of sub district health teams in health system management including CHPS
Sub district management teams
No of sub district health management teams trained.
4,000.00 4,000.00 GHS DA
Provide quality motorbikes to CHPS compounds for service delivery
CHPS zones.
No of CHPS compounds with quality motorbikes
100,000.00
200,000.00
GHS MOH,DA
228
Provide basic service delivery equipment to health facilities
All service delivery facilities.
No of facilities with adequate basic service delivery equipment
30,000.00
70,000.00 GHS MOH,DA
Organize blood donation campaigns
Schools and communities.
No of blood donation campaigns in a year
500.OO 1,000.00 GHS MOH,DA
Construction of mother’s hostel
Eikwe
No of mother’s hostel constructed
20,000.00
25,000.00 GHS MOH,DA
Identify and train community of based surveillance volunteers
All communities in the district.
. No of community based volunteers identified and trained
20,000.00
GHS MOH,DA
Organize routine immunization programs
All outreach points
Routine immunization organized
7,500.00 7,500.00 GHS MOH,DA
Implement special national health promotion programs
All communities
No of children immunized
10,000.00
10,000.00 GHS MOH,DA
229
(NIDs, Measles immunization, MDDs, Bed net Distribution etc.).
Sensitization of communities on common endemic disease (TB, Malaria, HIV/AIDs etc).
All communities
No of people reached per program
10,000.00
10,000.00 GHS MOH,DA
Conduct half yearly health screenings
Esiama, Nkroful, Aiyinasi Eikwe
No of screening activities carried out in a year
2,000.00
GHS MOH,DA
Implement National TB, HIV/AIDS and malaria programs
All communities
% of cases detected and effectively managed
10,000.00
GHS MOH,DA
Sensitization of communities on household latrines and safe environmental health practices
All communities.
No of community sensitizations carried out.
2,500.00 2,500.00 GHS MOH,DA
Train service providers in financial management
All GHS Facilities
Increase in IGF generation by facilities
10,000.00
GHS MOH,DA
230
Institute internal facility auditing mechanism
Facilities
Reduction in financial mismanagement
7,500.00 7,500.00 GHS MOH,DA
Registration of aged and other
vulnerable on NHIS
District wide
No of vulnerable registered under NHIS.
25,000.00
25,000.00 GHS MOH,DA
Renovation of staff bungalow
Aiyinasi health Center
No of health centers upgraded to polyclinic in the district
30,000.00
Works Dept.
GHS,DA
Paint staff quarters
Asasetre Health Center
No of nurses quarters painted
3,000.00
Works Dept.
GHS
Complete of abandoned structure for maternity services.
Esiama Health Center
Completed structure being used for maternity services
20,000.00
Works Dept.
GHS,DA,MOH
Provide antenatal and maternity services for communities
District wide
Antenatal and maternity services provided
50,000.00
50,000.00 GHS DA,MOH
Provide accommodation for health workers
District wide
Accommodation provided
200,000.00
400,000.00
GHS DA,MOH
231
Upgrade CHPS to health centers
District wide
Centers upgraded
1000,000.00
1000,000.00
GHS DA,MOH
Construct additional CHPS zones
Selected Commt
CHPS Constructed
500,000.00
GHS DA, MOH, Works Dept
Consult with district opinion leaders
District wide
Stake holders participation
2,500.00 2,500.00 Non-Formal Edt. Unit
DA,NCCE
Conduct Land identification towards Construction of fish ponds
District wide
Fish ponds constructed
50,000.00
50,000.00 Non-Formal Edt. Unit
T&CPD, Works Dept.
Stock fish pond with fingerlings
District wide
Fish pond stocked
2,500.00 2,500.00 Non-Formal Edt. Unit
Agric. Dept.
Cultivate rice.
Selected Commt
Rice cultivated
10,000.00
Non-Formal Edt. Unit
Agric. unit
Conduct Revenue and cash management
Nkroful
Revenue and Cash managed
3,000.00 Internal Audit Unit
DA, Finance Unit, Budget Unit
Implement Procurement management
Nkroful
Procurement activities managed
2,000.00
Internal Audit Unit
Procurement unit
232
Conduct special investigation
District Wide
Investigation conducted
3,000.00
Internal Audit Unit
DISEC
Conduct Stores and transport management
District wide
Stores and transport managed
1,500.00
Internal Audit Unit
Transport Unit, Stores
Institute Pay roll management
District wide
Payroll management instituted
2,000.00
Internal Audit Unit
DA, Finance Unit, Budget Unit
Institute Liability management
District wide
Liability managed
1,000.00
Internal Audit Unit
DA, Finance Unit, Budget Unit
Conduct Follow-up on audit recommendation
District wide
Follow ups conducted
2,000.00
Internal Audit Unit
DA, Finance Unit
Institute Fixed asset management
District wide
Fix asset manage
1,000.00
Internal Audit Unit
Estate Unit
Conduct IA external training
Nkroful
Training conducted
1,000.00 1,000.00 Internal Audit Unit
DA
Institute External audit liaison
Nkroful
External Audit liaison instituted
1,000.00
Audit Unit
DA
233
Conduct Corporate governance
District wide
Corporate governance conducted
2,000.00 1,000.00 Internal Audit Unit
HR Dept.
Institute Operational management reporting
Nkroful
Operational management reporting instituted
750.00 750.00 Internal Audit Unit
DA
Introduce Pre-payment vouching
District wide
Pre-payment vouching introduce
1,000.00 Internal Audit Unit
Finance Unit
Introduce Budget cycle
District wide
Budget cycle introcuced
1,000.00 Internal Audit Unit
Budget Unit
Construction of modern final waste disposal site for effective waste management
District Wide
Waste management site constructed
100,000.00
100,000.00
Env. Health, DWST
DA
Expand potable water coverage
District wide
Potable water coverage expanded
80,000.00
DWST, Works Dept.
DA
Provide waste containers
Selected Commts
Waste containers provided
100,000.00
100,000.00
Env. Health, Zoomlion
DA
234
Construct toilet facilities.(Aqua privy)
District wide
Aqua privy constructed
350,000.00
350,000.00
Env. Health, works Dept
DA
Construct toilet facilities. (W/Cs)
District wide
W/Cs constructed
400,000.00
400,000.00
Env. Health, works Dept
DA
Construct proper drainage systems
Kamgbunli, Esiama, Eikwe, Aiyinasi
Proper drainage systems constructed
20,000.00
30,000.00 Works dept.
DA
Train all WSMTs & WATSANs
District Wide
WSMs & WATSANs trained
50,000.00
DWST
DA
Construct Small Town Water System in larger town
Asanta, Ankobra
Water system constructed
200,000.00
CWSA
DWST, DA
Construct access road for all communities
Salman electoral area
Access roads constructed
800,000.00
Feeder Road Dept.
DA
Rehabilitate Access Road
Akoto-Alloakpoke,
Ayawora, Awiaso, Fiasolo
Roads rehabilitated
1,000,000
Feeder Road Dept.
DA
235
Reshape all new site & town road
District Wide
All road reshaped
300,000.00
400,000.00
Feeder Road Dept.
DA
Training of the newly elected Assembly/ unit committee members
Two area councils
To increase the number of Assembly women from 5 to 10
1,500.00 NCCE
EC,DA
Citizenship week celebration
District wide To inculcate a civic culture
1,600.00 NCCE GES
Education on revenue mobilization(Duties of a citizen)
District wide To raise awareness of citizens tax obligation and improve revenue mobilization
1,600.00 NCCE DA
Education and pre-marital sex among teenagers in the district
All basic schools
Reduce the of teenage pregnancies and number of sexual engagement
2,500.00 NCCE DA
Education on Ebola Pandemic and Cholera outbreak
District wide Improve awareness on Ebola Pandemic and Cholera Outbreak
1,600.00 NCCE EC, POLITICAL PARTIES, DA, GES ECT.
Improving sanitation conditions in the district
District wide Improve sanitation to eradicate cholera
1,600.00 NCCE GHS, ENVIRONMENTAL HEALTH, DA, GES ECT.
Provide District police Accommodation 45,000.00 DA DA-WKS DEPT
236
accommodation for 30 personnel
headquarters Esiama
for 30 personnel provided
237
5.5 ANNUAL ACTION PLAN FOR 2017
ACTIVITIES LOCATION OUTPUT INDICATOR
TIME FRAME ANNUAL BUDGET IMPLEMENTING AGENCIES
1st 2nd 3rd 4th Local External Lead Collaborating
Organize sensitization in communities
District Wide
Sensitization organized
10,000.00 10,0150.00 GES DA
Provide material support to needy pupils in schools
All School
Material support provided
13,002.00
GES MOE
Build 6- unit Primary School Buildings & Accessories
Selected area
Six - unit primary school built
200,000
DA, Works Dept.
MOE
Construction of 3-unit JHS block with ancillary facilities
Selected area
Three –Unit JHS block constructed
500,000
DA, Works Dept.
MOE
Provide facilities for water
Selected schools
Facilities for water harvesting
20,000
DA GES
238
harvesting in schools (tanks)
provided
Organize health talk in schools and communities
District wide
Health talk organized
10,000
MOH GES
Provide guidance and counseling services in JHS
District wide
Guidance and counseling service provided
10,000
MOE GES
Organize literacy and Arts competition in upper primary
District wide
Literacy and art competition organized
20,000
MOE GES
Undertake BECAS, SEA & NEA
District wide
BECAS,SEA &NEA undertaken
25,000
MOE GES
Organize INSET for teachers professional development
District wide
INSET for teachers organized
10,000.00 MOE GES
Provide teaching and learning materials especially science for basic
District wide
Teaching and learning materials provided
400,000
MOE GES
239
schools
Organize mock examination for JHS students
District wide
Mock examination organized
200,000
MOE GES
Conduct training for pre-school (KG)
teachers
District wide
Training conducted
30,000
GES MOE
Provides material support to trained teachers on UTDBE
District wide
Material support provided
10,000.00 10,000.00 MOE GES
Provide incentive package for teachers in deprived areas
Selected areas
Incentive package provided
50,000
MOE GES
Conduct regular school inspection and disseminate report
District wide
Regular school inspection conducted
40,000
MOE GES
Ensure full participation of SMCs in school management
District wide
Participation of SMCs ensured
30,000
GES MOE
Support girls in life skills support Programmes
District wide
Girls in life skills supported
30,000
GES MOE
240
Conduct regular inspection and ensure proper
functioning of SMCs and PTAs
District wide
Regular inspection conducted
40,000
MOE GES
Monitor government interventions
District wide
Government interventions monitored
30,000
DA GES
Provide office equipment
Selected Dept.
Office equipment’s provided
5,000
DA GES
Organize sensitization programmes
District wide
Sensitization programmes organized
40,000
DA MOE
Construction of KG and Primary block.
Obeng-krom
KG and Primary block constructed
200,000.00
DA, Works Dept.
GES,MOE
Construction of additional school block
Salman
Additional school block constructed
250,000.00
DA, Works Dept.
GES
Construction of JHS New JHS block 200,000.00 GES DA, Works
241
block for New Bakanta
Bakanta
constructed
Dept.
Construction of primary school block for Ngalekpole
Ngalekpole
Primary school block constructed
200,000.00
DA, Works Dept.
MOE
Construction of KG block for Asemdasuazo
Asemdasuazo
KG block constructed
100,000.00
DA, Works Dept.
MOE
Construction of KG block and teachers quarters at Fiasolo
Fiasolo
KG block and teachers quarters constructed
400,000.00
DA, Works Dept
MOE
completion of teachers quarters at Nyamebekyere
Nyamebekyere
Teachers quarters completed
100,000.00 100,000.00 DA, Works Dept.
MOE
Extension of school feeding programme to cover all communities with the Asasetre area council
Asasetre Area Council
School feeding programme extended
50,000.00
MOE GES
Construction of teacher quarters at
Adubrim
Adubrim
Teachers quarters constructed
200,000.00
MOE DA, Works Dept.
Construction of Mempease Teachers 250,000.00 MOE GES
242
teachers quarters for Mempeasem
m
quarters constructed
Institute incentives for teachers at Adubrim
Adubrim
Incentives for teachers instituted
150,000.00 100,000.00 DA GES
Rehabilitation of catholic JHS/KG at Asanta and SDA Primary school
Asanta
Catholic JHS/KG rehabilitated
200,000.00
DA, Works Dept.
GES
Rehabilitation of Asemko primary school
Asemko
Primary school rehabilitated
100,000.00
DA, Works Dept.
GES
Construction of school block for
Awiebo Methodist JHS
Awiebo
School block constructed
200,000.00
MOE GES
Construction of teachers quarters at Awiebo
Awiebo
Teachers quarters constructed
200,000.00
MOE DA, Works Dept.
Construction of Bungalow and security wall at
BOKASS
Awiebo
Bungalow and security wall constructed
400,000.00
MOE DA, Works Dept.
Completion of Awiebo KG block 150,000.00 MOE DA, Works
243
Awiebo Roman Catholic KG block.
constructed
Dept.
Construction of new school block for
Mantukwa Bibianiha and Domeabra
Mantukwa Bibianiha and Domeabra
School block constructed
600,000.00
MOE DA, Works Dept.
Construction of teachers quarters for communities
Mantukwa Ebi and Awiebo
Teachers quarters constructed
750,00.00
MOE DA, Works Dept.
Construction of library for Baseke and Awiebo
Awiebo
Library constructed
600,000.00
MOE DA, Works Dept.
Construction of school block for KG and Primary schools at Edwakpole
Edwakpole
School block constructed
50,000.00
MOE DA, Works Dept.
Construction of teachers quarters
Akoto, Alloakpoke, Awiaso
Teachers quarters constructed
750,000.00
MOE DA, Works Dept. ,GES
Conduct 4000 farmers/farmer group visits by December annually by 10 AEAS
District wide
4000 farmers/farmers group conducted
3,200.00 4,000.00 Agric.Dept.
DA
Conduct 250 field District 250 field 2,500.00 2,500.00 Agric. DA
244
days for 500 farmers and FBOs annually
wide
days for 500 farmers conducted
Dept.
Conduct 500 supervisory visits by four (4) supervisors to backstop AEAS annually
District wide
500 supervisory visits conducted
3,000.00 2,700.00 Agric. Dep.
DA
Treat 1000 clinical/surgical cases involving pigs, cattle sheep, goats by December
District wide
1000 clinical/surgical cases combated
1,000.00 1,000.00 Agric. Dept.
DA
De-worm 20000 poultry and 200 livestock annually
District wide
20000 poultry and 200 livestock de-wormed
500.00 500.00 Agric. Dept.
DA
Conduct ante/post mortem examination on slaughtered animals annually
District wide
Ante/post-mortem examination conducted
500.00 500.00 Agric. Dept.
DA
Vaccinate 20000 poultry and 300 livestock and pets
District wide
20000 poultry and300
1,000.00 1,000.00 Agric. Dept.
DA
245
against rabies and other zoonotic diseases
livestock vaccinated
Carry out diseases surveillance and monitoring visits
quarterly
District wide
Diseases surveillance and monitoring executed
250.00 250.00 Agric. Dept.
DA
Disseminate information
via radio (F.M) station to educate
farmers on new technologies and social agricultural issues quarterly
every year
Esiama & Ankobra
Information via radio(F.M) disseminated
800.00 Agric. Dept.
DA
Hold two (2) days planning sessions with stakeholders annually
Aiyinase
Two days planning sessions performed
3,500.00 3,500.00 MoFA
RADU/CSIR
Organize one (1) district farmers’ day celebration annually
Various
One district farmers day celebration organized
20,000.00 30,000.00 Agric. Dept.
DA
Service one official office One official 10,000.00 Agric. DA
246
car monthly
car serviced
Dept.
Procure 5 motorbikes for official use by
Office
Five motorbikes procured
15,000.00
Agric. Dept.
DA
Procure one (1) set of stationery for office use annually
Office
One set of stationery procured
2000.00
Agric. Dept.
DA
Running cost of official vehicle annually
office
Cost of official vehicle operated
14,400.00
Agric. Dept.
DA
Facilitate the supply of agro-chemical and farm inputs to farmers
District wide
Supply of agro-chemical and farm inputs to farmers facilitated
5,000.00 5,000.00 Agric. Dept.
DA
Train farmers on alternative sources of livelihood.
District wide
Farmers on alternative sources of livelihood trained.
4,000.00 4,000.00 Agric. Dept.
DA
Revamp Aiyinase and Esiama oil mill
Esiama, Aiyinase
Aiyinase and Esiama oil mill
10,000.00 10,000.00 Agric. Dept.
DA
247
revamped
Provision of agric extension services
District wide
Agric. extension services provided
10,000
MoFA
DA, Agric. dept.
Encouraging agric diversification
Agric. Diversification encouraged
Agric. Diversification encouraged
2,500.00 2,500.00 Agric. Dept.
DA
Conducting research into the cocoa diseases
District wide
Research into the cocoa diseases conducted
10,000.00 20,000.00 Agric. Dept.
DA
Supply of improved cocoa seedlings
Aiyinase north
Improved cocoa seedlings supplied
40,000
Agric. Dept.
DA
Construction of standardized CHPS compounds
Kwesikrom Basake Aluku Anwia
4 standardized CHPS compounds constructed
1000,000.00
GHS DA, Works Dept.
Procurement of All CHPS Motorbikes 400,000.00 600,000.00 GHS MOH,DA
248
motorbikes to CHPS compounds
Zones
procured for service delivery
Procurement of essential service delivery equipment for CHPS
All CHPS compounds
All CHPS compounds provided essential equipment
100,000.00 100,000.00 GHS MOH,DA
Training of sub district health teams in health system management including CHPS
Sub district management teams
No of sub district health management teams trained.
4,000.00 4,000.00 GHS DA
Provide quality motorbikes to CHPS Compounds for service delivery.
CHPS zones.
No of CHPS compounds with quality motorbikes
100,000.00 200,000.00 GHS MOH,DA
Provide basic service delivery equipment to health facilities
All service delivery facilities
No of facilities with adequate basic service delivery equipment
400,000.00 600,000.00 GHS MOH,DA
249
Organize blood donation campaigns
Schools and communities.
No of blood donation campaigns in a year.
10,000.00 5,000.00 GHS MOH,DA
Identify and train community of based surveillance volunteers.
All communities in the district.
No of community based volunteers identified and trained
20,000.00
GHS MOH,DA
Organize routine immunization programs
All outreach points
Routine immunization programs organized
7,500.00 7,500.00 GHS MOH,DA
Implement special national health promotion programs (NIDs, Measles immunization, MDDs, Bed net Distribution etc.).
All communities
No of children immunized
10,000.00 10,000.00 GHS MOH,DA
Sensitization of communities on common endemic disease (TB, Malaria, HIV/AIDs etc).
All communities
No of people reached per program
10,000.00 10,000.00 MOH,DA
Conduct half Esiama, No of 2,000.00 GHS MOH,DA
250
yearly health screenings
Nkroful, Aiyinasi Eikwe
screening activities carried out in a year
Implement National TB, HIV/AIDS and malaria programs
All communities
% of cases detected and effectively managed
10,000.00
GHS MOH,DA
Registration of aged and other vulnerable on NHIS.
District wide
No of vulnerable registered under NHIS.
25,000.00 25,000.00 GHS MOH,DA
Paint staff quarters
Asasetre Health Center
No of nurses quarters painted
3,000.00
Works Dept.
GHS
Provide antenatal and maternity services for communities.
District wide
Antenatal and maternity services provided
60,000.00 40,000.00 GHS DA,MOH
Construct a mortuary.
Eikwe
Mortuary constructed
100,000.00 200,000.00 GHS DA,MOH
Upgrade CHPS to health centers
District wide
Centers upgraded
100,000.00 100,000.00 GHS DA,MOH
251
Construct additional CHPS zones
Selected Commt
CHPS Constructed
500,000.00
GHS DA, MOH, Works Dept.
Consult with district opinion leaders
District wide
Stake holders participation
2,500.00 2,500.00 Non-Formal Edt. Unit
DA,NCCE
Stock fish pond with fingerlings
District wide
Fish pond stocked
2,500.00 2,500.00 Non-Formal Edt. Unit
Agric. Dept.
Conduct Revenue and cash management
Nkroful
Revenue and Cash managed
3,000.00 Internal Audit Unit
DA, Finance Unit, Budget Unit
Implement Procurement management
Nkroful
Procurement activities managed
2,000.00 Internal Audit Unit
Procurement unit
Conduct special investigation
District Wide
Investigation conducted
3,000.00
Internal Audit Unit
DISEC,
Conduct Stores and transport management
District wide
Stores and transport managed
1,500.00
Internal Audit Unit
Transport Unit, Stores
252
Institute Pay roll management
District wide
Payroll management instituted
2,000.00
Internal Audit Unit
DA, Finance Unit, Budget Unit
Institute Liability management
District wide
Liability managed
1,000.00
Internal Audit Unit
DA, Finance Unit, Budget Unit
Conduct Follow-up on audit recommendation
District wide
Follow ups conducted
1,000.00
1,000.00 Internal Audit Unit
DA, Finance Unit
Institute Fixed asset management
District wide
Fix asset manage
1,000.00
Internal Audit Unit
Estate Unit
Conduct IA external training
Nkroful
External Audit liaison instituted
1,000.00
Internal Audit Unit
DA
Institute External audit liaison
Nkroful
External Audit liaison instituted
1,000.00
Audit Unit
DA
Conduct Corporate governance
District wide
Corporate governance conducted
1,500.00 1,500.00 Internal Audit Unit
HR Dept.
Institute Nkroful Operational 1,000.00 500.00 Internal DA
253
Operational management reporting
management reporting instituted
Audit Unit
Introduce Pre-payment vouching
District wide
Pre-payment vouching introduce
1,000.00 Internal Audit Unit
Finance Unit
Introduce Budget cycle
District wide
Budget cycle introduced
1,000.00 Internal Audit Unit
Budget Unit
Construction of modern final waste disposal site for effective waste management
District Wide
Waste management site constructed
100,000.00 100,000.00 Env. Health, DWST
DA
Expand potable water coverage
District wide
Potable water coverage expanded
80,000.00
DWST, Works Dept
DA
Provide waste containers
Selected Commts
Waste containers provided
100,000.00 100,000.00 Env. Health, Zoomlion
DA
Construct toilet facilities. (Aqua privy)
District wide
Aqua privy constructed
350,000.00 350,000.00 Env. Health, works Dept.
DA
254
Construct toilet facilities. (W/Cs)
District wide
W/Cs constructed
400,000.00 400,000.00 Env. Health, works Dept
DA
Train all WSMTs & WATSANs
District Wide
WSMs & WATSANs trained
50,000.00
DWST
DA
Reshape all new site & town road
District Wide
All road reshaped
300,000.00 400,000.00 Feeder Road Dept.
DA
Citizenship week celebration
District wide
To inculcate a civic culture
1,600.00 NCCE GES
Education on revenue mobilization(Duties of a citizen)
District wide
To raise awareness of citizens tax obligation and improve revenue mobilization
1,600.00 NCCE DA
Education and pre-marital sex among teenagers in the district
All basic schools
Reduce the of teenage pregnancies and number of sexual engagement
2,500.00 NCCE GES
Education on Ebola Pandemic and
District wide
Improve awareness
1,600.00 NCCE EC, POLITICAL
255
Cholera outbreak on Ebola Pandemic and Cholera Outbreak
PARTIES, DA, GES ECT.
Improving sanitation conditions in the district
District wide
Improve sanitation to eradicate cholera
1,600.00 NCCE
GHS, ENVIRONMENTAL HEALTH, DA, GES ECT.
Provide 2 vehicles for patrols and official work
District police headquarters Esiama
2 vehicles for patrols and official work provided
70,000.00 DA DA-WKS DEPT
256
5.6 INDICATIVE FINANCIAL PLAN 2014 – 2017
The Strategic Plans and Programmes well phased out by the District Planning Co-ordination
Unit (DPCU) within the Four (4) years plan period to alleviate poverty would not be realized
without planning on resource mobilization both locally and externally to implement the
MTDP.
The indicative financial plan entails strategies to adopt to mobilize financial resource through
revenue generation within the District, from Central Government and other donor support.
The strategies for the revenue generation are listed below:
Undertake Revaluation Exercise for immovable properties in the District
Introduce a composite billing system that incorporates basic rate and special levy for
development.
Intensify Pay your levy campaign using information vans and information centers
Engage the service of local consultants in household property mobilization
Sanction developers who build without permit
Gazette fee fixing annually
Intensify building inspection for timely identification of defaulters
Revamp the District Revenue task force to assist Area Councils in revenue collection
Build market sheds and stalls in major market centers of the district
The activities to be implemented are clearly spelled out in the Proramme of Action (PoA)
and also .It indicate the activities, location, time frame ,output Indicators, local and
external source of budget and implementing agency.
257
4.10.1 Financial Control Mechanism
Comprehensive financial control mechanisms have been put in place to efficient usage of
funds, and avoid misapplication and misappropriation of fund, thus ensure sustainable
development. This will help win the trust of donor agencies.
Revenue:
Money should be daily into the Assembly’s account after collection
Value books are manage by the District Finance Officer
All relevant income generating bodies of the Assembly should have GCR
Stock Register for the issuing of the Value Books to the Revenue Superintendent.
Supervision of revenue collector by internal auditor
Socio-economic data for revenue collection should be made available to the Revenue
Superintendent
Payment:
Trial Balance and Monthly Reconciliation statement to be submitted to relevant offices
All Memos for expenditure should be endorsed by the District Co-ordinating Director.
Payment vouchers are to be pre-auditored before cheques are issued
Payment Vouchers are prepared based on the Budget Line.
All cheques are counter signed by the District Finance Officer (DFOs) and District Co-
ordinating Director (DCD).
Financial reports are prepared and submitted to Regional Co-ordinating Council, Controller
and Accountant General and Ministry of Local Government and Rural Development
Signed checques are registered before issue to payee.
Proper Books of accounts are kept and all transactions are recorded dairy
258
Sector Budget from 2014-2017 The expenditure for implementation of programmes, activities and projects in the
Thematic Areas is presented below.
2014
EDUCATION
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
3,873,000.00 9,000.00 782,002.3334 391,001.1667
TOTAL=5,055003.5
HEALTH DIRECTORATE
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
330,000.00 40,000.00 230,000.00 60,000.00 100,000.00 40,000.00
TOTAL=800,000.00
AGRICULTURE
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
2,000.00 43,480.00 139,480.00 27,900.00
TOTAL=212,860.00
259
NON-FORMAL EDUCATION
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
2,000.00 1,500.00 1,500.00
TOTAL=5,000.00
NATIONAL COMMISSION FOR CIVIC DEDUCATION
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
10,400.00
TOTAL=10,400.00
INTERNAL AUDIT
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECT
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
1,000.00 24,000.00 2,000.00
TOTAL=27,000.00
260
GHANA POLICE SERVICE
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
30,000.00
TOTAL=30,000.00
WATER AND SANITATION
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
930,000.00 850,000.00 30,000.00 20,000.00
TOTAL=1,830,000.00
ROAD INFRASTRUCTURE
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
350,000.00 250,000.00 100,000.00
TOTAL=700,000.00
261
2015
AGRICULTURE
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
2,000.00 91,830.00 91,830.00 30,000.00
TOTAL=215,660.00
HEALTH DIRECTORATE
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
1,764,000.00 1,714,000.00 800,000.00 198,000.00 190,000.00 100,000.00
TOTAL=4,766,000.00
EDUCATION
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
5,150,000.00 1,737,667.833 1,737,667.833 1,737,667.833
TOTAL=10,363,003.5
262
NON-FORMAL EDUCATION
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
6,000.00 4,000.00 2,000.00 1,500.00 1,500.00
TOTAL=15,000.00
INTERNAL AUDIT
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECT
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
2,500.00 20,000.00 2,500.00
TOTAL=25,000.00
NATIONAL COMMISSION FOR CIVIC EDUCATION
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECT
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
13,400.00
TOTAL=13,400.00
263
GHANA POLICE SERVICE
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECT
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
60,000.00
TOTAL=60,000.00
WATER AND SANITATION
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
830,000.00 600,000.00 400,000.00 30,000.00 4,000.00 23,000.00
TOTAL=1,887,000.00
ROAD INFRASTRUCTURE
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
1,150,000.00 1,150,000.00 800,000.00
TOTAL=3,100,000.00
264
2016
EDUCATION
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
1,700,000.00 1,300,000.00 930,000.00 463,003.5 300,000.00
TOTAL=4,693,003.5
AGRICULTURE
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
106,980.00 76,980.00 20,000.00 27,000.00 25,000.00
TOTAL=255,960.00
HEALTH DIRECTORATE
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
1,759,000.00 1,759,000.00 1,000,000.00 80,000.00 70,000.00 50,000.00
TOTAL=4,718,000.00
265
NON-FORMAL EDUCATION
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
5,000.00 60,000.00 50,000.00 2,000.00 1,500.00 1,500.00
TOTAL=120,000.00
INTERNAL AUDIT
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
3,000.00 20,000.00 4,000.00
TOTAL=27,000.00
NATIONAL COMMISSION FOR CIVIC EDUCATION
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
11,900.00
TOTAL=11,900.00
GHANA POLICE SERVICE
SOURCE OF FUND
266
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
45,000.00
TOTAL=45,000.00
WATER AND SANITATION
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
1,000,000.00 1,000,000.00 130,000.00 30,000.00 20,000.00
TOTAL=2,180,000.00
ROAD INFRASTRUCTURE
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
1,200,000.00 400,000.00 900,000.00
TOTAL=2,500,000.00
267
2017
EDUCATION
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
3,000,000.00 3,000,000.00 770,000.00 800,000.00 318,003.5 150,000.00
T0TAL=8,038,003.5
AGRICULTURE
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
50,000.00 35,000.00 100,000.00 55,830.00 55,830.00
TOTAL=296,660.00
HEALTH DIRECTORATE
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
1,000,000.00 2,000,000.00 703,000.00 70,000.000 50,000.00 40,000.00
TOTAL=3,863,000.00
268
NON-FORMAL EDUCATION
SOURCE OF FUNDING
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
2,500.00 2,500.00 2,000.00 1,500.00 1,500.00
TOTAL=10,000.00
INTERNAL AUDIT
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
4,000.00 20,000.00 3,000.00
TOTAL=27,000.00
NATIONAL COMMISSION FOR CIVIC EDUCATION
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
8,900.00
TOTAL=8,900.00
269
GHANA POLICE SERVICE
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
70,000.00
TOTAL=70,000.00
WATER AND SANITATION
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
980,000.00 700,000.00 300,000.00 30,000.00 20,000.00
TOTAL=2,030,000.00
ROAD INFRASTRUCTURE
SOURCE OF FUND
PHYSICAL PROJECTS NON-PHYSICAL PROJECTS
DACF IGF DDF/OTHER
DONORS
DACF IGF DDF/OTHER
DONORS
250,000.00 250,000.00 200,000.00
T0TAL=700,000.00
GRAND TOTAL = GH₵56,679,754.00
270
CHAPTER 6
MONITORING AND EVALUATION
6.1 Monitoring and Evaluation Arrangements The monitoring and Evaluation will be done by the District Assembly through the District Planning and
Coordinating Unit – DPCU and Sectoral Departments as indicated in the Annual Action Plan.
Unforeseen changes in the Socio-Economic and Government Policies will affect the Plan. As a result
there is the need for continuous monitoring and evaluation to enable the necessary adjustment and
revision to be done.
6.1.2 Monitoring Report Monitoring starts with the implementation of the projects. It is aimed at making sure that the Project
progresses according to laid down procedures, Bill of Quantities, and scheduled as well as maintaining
high quality standards. The District Monitoring Team will be responsible for the overall supervision of
the Programmes and Projects in the Annual Plan.
A monitoring record will be kept during the implementation, which will form the basis of writing
monthly monitoring report to the District Chief Executive and also to correct mistakes.
6.1.3 Monitoring Framework The Monitoring Framework outlines the mechanisms and indicators for the monitoring of the
development programmes and projects and this is shown in the table below:
271
MONITORING FRAMEWORK
WHEN RESPONSIBILITY TOOLS INDICATORS RESULTS FEEDBACK
Daily DPO/Engineer Observation
Project visits
Project Reports
Interviews
Performance
output-quality
and quantity
Inputs – quality
and quantity (Bill
of Quantities
Designs/
Drawings
Time
Identify problems,
defects and constraints
inhibiting work and
progress and is
packaged in a
monitoring Report
Solutions and
measures to
solve problems
defects and
constraints
provided
Weekly DPO/Engineer
DCD/DCE
“ “ Identify problems,
defects and constraints
inhibiting work and
progress and is
packaged in a
monitoring report
Solutions and
measures to
solve problems
defects and
constraints
provided
Monthly District Monitoring
Team
Works Sub-
Committee
DCD/DCE
“
“
“
“
Identify problems,
defects and constraints
inhibiting work and
progress and is
packaged in a
monitoring Report
Solutions and
measures to
solve problems
defects and
constraints
provided
Quarterly District Monitoring
Team
“
“
Identify problems,
defects and constraints
inhibiting work
progress and this is
Solutions and
measures to
solve problems
defects and
272
Works Sub
Committee
DPCU
DCE/DCD
“
“
“
“
packaged in a
monitoring report
constraints are
provided
273
CHAPTER 7
COMMUNICATION STRATEGY
7.1 Introduction This chapter deals with how to disseminate the content of the Ellembelle District Medium
Term Development Plans (DMTDP). It also discusses the expected responsibilities of
stakeholders and other principal action agents as well as all the collaborating agencies in the
implementation of the District plans. Strategies for promoting dialogue to generate feedback
from the public regarding the provision of socio-economic infrastructure and related services
are also discussed.
Dissemination of DMTDP and Annual Progress Report of Implementation
To solicit for support for funding, logistic, and human resources for effective implementation
of the DMTDP, the Assembly will disseminate the plans to all stakeholders at the following
levels:
District Assembly Level
The development goal, objectives, and strategies stated in the medium term development
plans would be known to all Assembly Members, decentralised departments and agencies as
well as the staff of the Assembly for implementation.
Town/ Area Council/ Unit Committee Level
All stakeholders at the Area Council and Unit Committee levels, specifically the leaders need
to be enlightened on the content of the 2014-2017 medium term development plans to
enable them carry the message to their people. This will be done through the following:
1. The chiefs, community based/youth associations, market-women, non-
governmental organizations, the GPRTU, and other members of the private
274
sector about their roles/responsibilities and benefits to themselves and the
entire society at large.
2. Durbars, seminars, community workshops etc. would be organized on the plans
to sensitized all stakeholders
3. Investment opportunities in the district would be promoted to enable the
private sector and development partners to be attracted to the plan
Regional and National Organizations/Institutions
It is important to disseminate the plans beyond the borders of the district so as to serve as a
means of informing the public/private institutions, and the general public on the potentials
that exist in the district. This approach will also serve as a means of soliciting for financial and
material supports for the plan implementation. This will also involve the members of
parliament in the district.
International Organizations
The District Assembly would also promote the plans through workshops and seminars to
attract financial agencies in addressing people’s need. The plans would be summarized into
brochures and leaflets whilst a Website is also created for the wider international community.
7.2 Expected Roles/Responsibilities of stakeholders in the plan
implementation The role of all key stakeholders in the implementation on the plans is very important. Hence,
the anticipated role that each stakeholder will play is highlighted as follows:
275
7.2.1 Ellembelle District Assembly The decentralization policy coupled with the Local Government Act 462 designates District
Assemblies as planning Authorities and not responsible for the preparation/ formulation of
plans but also their implementation, monitoring and evaluation. This implies that the
Ellembelle District Assembly in collaboration with departments and agencies as well as other
non-governmental organizations are responsible for the day to day running of the district and
the assessment of projects after implementation. To, implement these projects/programmes;
it is necessary that the district assembly mobilizes funds both from within and outside the
district. The Local revenue base needs to be fully assessed and restructured to give the
assembly a sound financial footing for projects implementation.
The District Assembly is charged with the overall responsibility for the process of
implementation, monitoring and evaluation of the development projects/programmes. This
role can best be performed by tapping the available human and technical resources of the
Expanded District Planning Co-ordinating Unit, Departments and Agencies, Sub-Committees,
Executive Committee, NGOs and development partners
The technical skills of the assembly/departments/agencies need to be tapped for the
performance of the following functions:
Generation and provision of funds for implementation of programmes/projects
Setting up of terms of reference and framework for co-ordination and collaboration
among institutions involved in the implementation of the development plans
Identification and due response to implementation issues such as legal, administrative
and traditional bottlenecks
Identification and invitation/attraction of potentials investors in the district
Periodic revision of plan implementation, procedure and effective adjustments in the
response to the changing circumstances
276
7.2.2 Executive Committee The Executives Committee would have to play the leading role of informing the Assembly
members about the content of the plans, status of projects implementation and problems
being encountered during the implementation to enable the electorates understand issues
7.2.3 Sub-Committee The various sub-committees need to be strengthened with the requisite personnel; skills
knowledge and experience to enable the members participate actively in the implementation
of the development plans.
7.2.4 Decentralized Departments/Agencies There are major actors in the process of implementation, monitoring and evaluation. The
departments/agencies will provide technical guidance and facilitate the implementation of
desirable projects/programmes.
7.2.5 Chiefs, Opinion Leaders and Traditional Authorities The chiefs, Opinion Leaders and Traditional Authorities and owners need to be part of the
process of the plan implementation to enable them have informed decisions on their
responsibilities in implementing the programmes/projects designed in the plan
7.2.6 Non-Governmental Organizations (NGOs)/ Development Partners The District is mindful of the crucial roles played by Non-Governmental Organizations in
support of various projects/programmes in the district. The role of NGOs and other
development partners has been very crucial for the successful implementation of planned
programmes/projects. It is hoped that the development partners will bite into the plan to
enhance the overall development of the district.
277
7.2.7 Communities Communities offer a lot of support starting from project identification, design and
implementation, monitoring and evaluation. They also play important roles by providing
counterpart funds towards projects implementation. This is to enhance the principle of
community ownership and management for sustainability. In this direction, communities
provide labour, land, local expertise, counterpart funds, etc for projects implementation.
It is hoped that communities would continue to offer their best through project identification,
implementation, and evaluation for sustainability.
7.3 Strategies for promoting dialogue/management of public
expectations concerning services The District Assembly has adopted several strategies for promoting dialogue and eliciting
information from the public regarding the implementation of planned programmes and
projects in the plan. Stakeholders meetings would be held periodically at the Town/Area
Council level to update the people on progress of work.
Also, the Assembly would hold meeting with identified civil society organisation, Artisans,
Religious Groups, etc to discuss the implementation of the plan and receive feedback.
The District Assembly would to a large extent involve the people in the monitoring and
evaluation of programmes and projects to quickly respond to the concern and expectation of
the people during the implementation of the plan. Progress reports on plan implementation
would be discussed at sub-committee meetings and quarterly review meetings would also be
held to address people’s concern in the process of implementation. Furthermore, the Public
Relations and Complaint Committee of the Assembly would provide a platform for the hearing
of issues regarding the implementation of the programmes/projects in the District.
278
7.4 Conclusion The consultative participatory nature of the plan preparation process will mean that all
relevant stakeholders and development partners will be very keen and show commitment in
the implementation of the plan. The document should be seen as the Manifesto, all
stakeholders should ensure that all planned strategies or interventions are strictly
implemented. This will help improve the quality of lives of the people by ensuring wealth
creation and improving the living standards of the people in the District.
To achieve the set objectives of the MTDP of Ellembelle District, adequate resources must be
mobilized both internally and externally to fund the planned activities between 2014 – 2017.
The SEA tools reveal the importance of mainstreaming environmental issues in the DMDTP.
This will afford the District to achieve sustainable development.
Lastly, it is expected that funds would be released on timely bases to support planned
activities in order to achieve the objectives set in the DMTDP, 2014 – 2017 for Ellembelle
District Assembly.