82
GEOECHNICAL ENGINEERING RECOMMENDAIONS MONEMA CON COMBINED COR SSEMS BILDING Cortez, Colorado Prepared For: Ms. Melissa Brunner, Montezuma County Project Number: 54077GE January 28, 2016

GEOTECHNICAL ENGINEERING RECOMMENDATIONS

  • Upload
    lethien

  • View
    219

  • Download
    1

Embed Size (px)

Citation preview

Page 1: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

GEOTECHNICAL ENGINEERING

RECOMMENDATIONS

MONTEZUMA COUNTY COMBINED COURT SYSTEMS

BUILDING

Cortez, Colorado

Prepared For:

Ms. Melissa Brunner, Montezuma County

Project Number: 54077GE

January 28, 2016

Page 2: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

1

1.0 REPORT INTRODUCTION ................................................................................................ 2

1.1 Scope of Project ................................................................................................................... 3

2.0 GEOTECHNICAL ENGINIEERING STUDY .................................................................. 3

2.1 Geotechnical Engineering Study Scope of Service .............................................................. 3

3.0 FIELD STUDY ....................................................................................................................... 5

3.1 Project location .................................................................................................................... 5

3.2 Site Description and Geomorphology .................................................................................. 6

3.3 Subsurface Soil and Water Conditions ................................................................................ 7

3.4 Anticipated Excavation Characteristics of the Formational Materials ................................ 9

3.5 Excavation Cut to Embankment Fill Shrink/Swell Factors ................................................ 10

3.6 Site Seismic Classification .................................................................................................. 11

4.0 LABORATORY STUDY .................................................................................................... 12

5.0 FOUNDATION RECOMMENDATIONS ........................................................................ 14

5.1 Spread Footings Supported by the Competent Formational Sandstone Material ............. 15

5.2 Spread Footings Supported by the Site Clay Soil Materials.............................................. 19

5.3 General Shallow Foundation Considerations ................................................................... 24

6.0 RETAINING STRUCTURES............................................................................................. 24

7.0 SUBSURFACE DRAIN SYSTEM ...................................................................................... 26

8.0 CONCRETE FLATWORK ................................................................................................. 28

8.1 Interior Concrete Slab-on-Grade Floors ............................................................................ 28

8.2 Exterior Concrete Flatwork Considerations ...................................................................... 30

8.3 General Concrete Flatwork Comments ............................................................................. 31

9.0 PAVEMENT SECTION THICKNESS DESIGN RECOMMENDATIONS .................. 32

9.1 Asphalt Pavement Recommendations ................................................................................. 33

9.2 Rigid Concrete Pavement Recommendations ..................................................................... 34

9.3 General Parking Area Considerations ................................................................................. 35

10.0 CONSTRUCTION CONSIDERATIONS ........................................................................ 36

10.1 Fill Placement Recommendations ..................................................................................... 36

10.1.1 Natural Soil Fill ........................................................................................................ 36

10.1.2 Granular Compacted Structural Fill ......................................................................... 37

10.2 Excavation Considerations ............................................................................................... 38

10.2.1 Excavation Cut Slopes ............................................................................................... 39

10.3 Utility Considerations ....................................................................................................... 39

10.4 Exterior Grading and Drainage Comments ..................................................................... 40

10.5 Landscaping Considerations ............................................................................................ 40

10.6 Soil Sulfate Content, Corrosion Issues ............................................................................. 42

10.7 Radon Issues ..................................................................................................................... 42

11.0 CONSTRUCTION MONITORING AND TESTING .................................................... 42

12.0 CONCLUSIONS AND CONSIDERATIONS ................................................................. 43

Page 3: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

2

1.0 REPORT INTRODUCTION

This report presents our geotechnical engineering recommendations for the Montezuma County

Combined Court System Project. This report was requested by Melissa Brunner, Montezuma

County Administrator. The field study was performed on January 7 through January 20, 2016.

The laboratory study was completed on January 25, 2016. We provided verbal recommendations

and consultation to members of the design team during the preparation of this report.

Geotechnical engineering is a discipline which provides insight into natural conditions and site

characteristics such as; subsurface soil and water conditions, soil strength, swell (expansion)

potential, consolidation (settlement) potential, and often slope stability considerations. Typically

the information provided by the geotechnical engineer is utilized by many people including the

project owner, architect or designer, structural engineer, civil engineer, the project builder and

others. The information is used to help develop a design and subsequently implement

construction strategies that are appropriate for the subsurface soil and water conditions. It is

important that the geotechnical engineer be consulted throughout the design and construction

process to verify the implementation of the geotechnical engineering recommendations provided

in this report. Generally the recommendations and technical aspects of this report are intended

for design and construction personnel who are familiar construction concepts and techniques, and

understand the terminology presented below. We should be contacted if any questions or

comments arise as a result of the information presented below.

The following outline provides a synopsis of the various portions of this report;

� Sections 1.0 and 2.0 provide an introduction and an establishment of our scope of

service.

� Sections 3.0 and 4.0 of this report present our geotechnical engineering field and

laboratory studies

� Sections 5.0 through 9.0 presents our geotechnical engineering design parameters and

recommendations which are based on our engineering analysis of the data obtained.

� Section 10.0 provides a brief discussion of construction sequencing and strategies which

may influence the geotechnical engineering characteristics of the site.

The discussion and construction recommendations presented in Section 10.0 are intended to

help develop site soil conditions that are consistent with the geotechnical engineering

recommendations presented previously in the report. Ancillary information such as some

background information regarding soil corrosion and radon considerations is presented as

general reference. The construction considerations section is not intended to address all of the

construction planning and needs for the project site, but is intended to provide an overview to

aid the owner, design team, and contractor in understanding some construction concepts that

may influence some of the geotechnical engineering aspects of the site and proposed

Page 4: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

3

development.

The data used to generate our recommendations are presented throughout this report and in the

attached figures.

1.1 Scope of Project

We understand that the proposed project will consist of constructing a pre-engineered metal-

framed building that is supported by a steel reinforced concrete foundation system. A partial

basement with a mechanical room and “sally port” will be constructed under the northern portion

of the building. A combination of concrete slab-on-grade and structurally supported floors (at

minimum over basement areas) will be used for the interior building floor system. The

development will include asphalt pavement driveway and parking areas as well as exterior

concrete flatwork.

2.0 GEOTECHNICAL ENGINIEERING STUDY

This section of the report presents our geotechnical engineer scope of services to date for the

project.

Our services include a geotechnical engineering study of the subsurface soil and water

conditions of this site for development of a foundation design and pavement section thickness

study for the proposed use.

2.1 Geotechnical Engineering Study Scope of Service

The scope of our study which was delineated in our proposal for services, and the order of

presentation of the information within this report, is outlined below.

Field Study

• We advanced eighteen (18) continuous flight auger test borings and two (2) NW wireline

core borings at the project within the areas we understand are planned for construction of

the proposed structure and parking/landscape areas.

• Select driven sleeve and bulk soil samples were obtained from the test borings and

returned to our laboratory for testing.

Page 5: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

4

Laboratory Study

• The laboratory testing and analysis of the samples obtained included;

� Moisture content and dry density,

� Direct shear strength tests, to help establish a basis for development of soil

bearing capacity and lateral earth pressure values,

� Unconfined compressive strength tests on select sections of rock core obtained

from our wireline core borings,

� Swell/consolidation tests to help assess the expansion and consolidation potential

of the support soils on this site to help estimate potential uplift associated with

expansive soils and to help estimate settlement of the foundation system,

� Plastic and liquid limit tests to determine the Plasticity Index of the soil,

� Sieve analysis tests,

� Moisture content/dry density relationship (Proctor) tests, and,

� California Bearing Ratio (CBR) tests.

Geotechnical Engineering Recommendations

• This report addresses the geotechnical engineering aspects of the site and provides

recommendations including;

Geotechnical Engineering Section(s)

� Subsurface soil and water conditions that may influence the project design

and construction considerations,

� Geotechnical engineering design parameters including;

� Viable foundation system concepts including soil bearing capacity

values,

� settlement considerations for the foundation system concepts that are

viable for this project,

� Lateral Earth Pressure values for design of retaining structures, and,

� Flexible asphalt concrete pavement thickness design considerations

� Soil support considerations for interior and exterior concrete flatwork

Construction Consideration Section

� Fill placement considerations including cursory comments regarding site

preparation and grubbing operations,

Page 6: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

5

� Considerations for excavation cut slopes,

� Natural soil preparation considerations for use as backfill on the site,

� Compaction recommendations for various types of backfill proposed at the

site,

� Utility trench comments, and,

� Cursory exterior grading considerations

• This report provides design parameters, but does not provide foundation design or

design of structure components. The project architect, designer, structural engineer or

builder may be contacted to provide a design based on the information presented in

this report.

• Our subsurface exploration, laboratory study and engineering analysis do not address

environmental or geologic hazard issues other than expansive soil conditions.

3.0 FIELD STUDY

3.1 Project location

The project site is located west of the intersection of North Park Street and East Driscoll Street,

just south of the existing Montezuma County Detention Center. Figure 3.1 shown below

obtained from Google Earth imagery indicates the location of the project site.

Page 7: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

6

Figure 3.1: Project Location

3.2 Site Description and Geomorphology

The project site is located on a previously undeveloped approximate 6.8 acre lot. The project

site is relatively barren with vegetation consisting of sparse sage brush and grass cover. The

ground surface on the project site generally slopes down to the north with slope inclinations in

the range of about fifteen to one (15:1, horizontal to vertical) or flatter. A relatively shallow

drainage feature with a gradient down to the north towards Park Street exists in the north central

portion of the lot.

The geomorphology in the vicinity of the project consists of a relatively shallow wind-blown

loess deposit consisting of fine sands and clay and silt soil materials overlying the Dakota

Sandstone Formation. The clay soil materials encountered in the vicinity of the project may

exhibit a moderate to high swell potential and moderate consolidation potential under typical

foundation loads. The Dakota Sandstone Formation consists of interbedded layers of sandstone,

claystone, and shale materials. Lignite (coal like material) is sometimes encountered within the

formational material. The claystone and shale materials encountered within the formational

material may exhibit a moderate to high swell potential.

Project Location

N

Page 8: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

7

Subsurface water is often encountered in the vicinity of the project. We suspect that the source

for this subsurface water is the relatively heavily irrigated park system and related canal systems

located to the southeast of the subject project site. Water may be encountered over the

formational sandstone material or within fractures within the formational materials.

3.3 Subsurface Soil and Water Conditions

We advanced eighteen (18) continuous flight auger test borings and two (2) NW wireline core

borings in the vicinity of the proposed structure and proposed parking/landscape areas. The

surveyed location of our test borings relatively to the approximate location of the structure are

shown on Figure 3.3 below. The surveying and development of the figure below was provided to

us by Maness and Associates. The logs of the soils encountered in our test borings are presented

in Appendix A.

Figure 3.3: Test Boring Locations

N

Page 9: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

8

The test boring locations were survey located however the location of the structure footprint

relatively to our test borings has been approximated. We understand that the building location

relative to our test boring locations should be accurate to within a few feet.

The following provides a general description of the subsurface conditions that we encountered

in our test borings. The logs of the test borings presented in Appendix A should be consulted for

more precise information.

Generally, we encountered sandy clay soil material from the ground surface to depths ranging

from about one and one-half (1½) to as deep as about eight (8) feet below the ground surface

where we encountered the Dakota Sandstone Formation. The upper approximate one (1) foot of

sandy clay soil materials were generally very moist and soft, becoming stiffer and drier with

depth. The clay soil materials encountered and tested exhibit a low to moderate swell potential,

and moderate to high consolidation potential.

The formational material was encountered at depths ranging from about one and one-half (1½)

to about eight (8) feet below the ground surface elevation. The upper portion of the formational

material was very hard. All of our auger test borings, with exception to Test Borings Four

through Seven, were advanced to refusal within about one-half (1/2) to one (1) foot of

penetration into the formational material. We were able to advance auger Test Borings Four

through Seven through the upper very hard sandstone material into more friable sandstone

material and claystone materials. The claystone materials were encountered at depths ranging

from about ten (10) to fifteen (15) feet below the ground surface. Test Borings Four through

Seven were advanced to refusal on a deeper very hard sandstone layer encountered at depths

ranging from about eighteen (18) to as deep as about thirty-eight (38) feet below the ground

surface elevation.

We advanced two (2) NW wireline core borings in the vicinity of the project (eastern area of the

proposed structure location) where we encountered shallow auger drilling refusal. We have

referred to these core borings as TB-2A and TB-10A. In TB-2A we encountered sandy clay soil

material from the ground surface to a depth of about two (2) feet below the ground surface

elevation where we encountered very hard sandstone formational material. The formational

material encountered consisted of very hard and moderately fractured sandstone to a depth of

about seven (7) feet below the ground surface. At depths ranging from about seven (7) to twelve

(12) feet below the ground surface we encountered highly fractured and more friable sandstone

material. We encountered highly fractured clayey sandstone to sandy claystone at depths ranging

from about twelve (12) feet below the ground surface to a depth of about twenty (20) feet below

the ground surface where primarily sandstone material was encountered. TB-2A was advanced

to a depth of about twenty-two (22) feet below the ground surface elevation.

Page 10: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

9

In TB-10A we encountered sandy clay soil materials from the ground surface to a depth of

approximately five (5) feet below the ground surface where we encountered hard claystone

material to a depth of about seven (7) feet below the ground surface. Very hard and moderately

fractured sandstone material was encountered at a depth of about seven (7) feet below the ground

surface elevation to the bottom of the core boring advanced to twelve (12) feet below the ground

surface elevation.

Subsurface free water was initially encountered at a depth of about twenty-five (25) feet below

the ground surface elevation in Test Boring Four. Subsequent measurements of the free water

elevation in Test Boring Four were at about twenty-one (21) feet below the ground surface. We

measured subsurface free water at a depth of about sixteen (16) feet below the ground surface

elevation in Test Boring/Core 2A. The free water was encountered in fractures within the

formational materials. We anticipate that the source area for this free water is from the heavily

irrigated park system and associated canals located a relatively short distance to the southeast of

the project site. Based on the subsurface information obtained we anticipate that the proposed

structure will be located above the static water elevation for the area. However we anticipate that

a periodic or seasonal water surface may develop over the formational sandstone material or

within fractures in the upper portions of the formational sandstone materials within the extent of

the structure depth during periods of high precipitation or spring snow melt. This is due to the

relatively shallow depth and impermeable nature of the formational sandstone material below

and adjacent to the project site. Our recommendations for a subsurface drain system may be

found in Section 7.0 of this report.

The logs of the subsurface soil conditions encountered in our test borings are presented in

Appendix A. The logs present our interpretation of the subsurface conditions encountered

exposed in the test borings at the time of our field work. Subsurface soil and water conditions

are often variable across relatively short distances. It is likely that variable subsurface soil and

water conditions will be encountered during construction. Laboratory soil classifications of

samples obtained may differ from field classifications.

3.4 Anticipated Excavation Characteristics of the Formational Materials

Based on our understanding of the proposed structure finished floor elevations we anticipate

that at minimum the entire basement area foundation system will be located within the

formational sandstone materials. The main level foundation system may be slightly below the

formational sandstone materials in some areas of the structure footprint.

As discussed above, the upper portions of the formational sandstone material were very hard.

We experienced auger refusal with our four (4) inch diameter solid stem auger utilizing our

approximate 12,000 pound CME-45 drilling equipment in many areas of the structure footprint

and proposed exterior landscape areas. Due to the auger refusal experienced during our initial

Page 11: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

10

field study we advanced additional NW wireline core borings in select locations of the structure

area (TB-2A and TB-10A). The upper approximate five (5) to six (6) feet of the formational

materials encountered exhibited Rock Quality Designation (RQD) values in the range of about

60% to 85%, meaning relatively competent sandstone with moderate to low fracturing. We

performed unconfined compressive strength testing of select sections of rock core obtained from

the upper portions of the formational sandstone material. The compressive strength of the rock

core tested ranged from about 4,500 pounds per square inch (psi) to over 10,000 psi. The

formational materials encountered below the upper approximate five (5) to six (6) feet of the

surface of the formation were considerably more fractured and friable with a compressive

strength in the range of about 1,000 psi.

Based on our understanding of the structure finished floor and basement floor elevations, the

structure basement foundation system will be located within the very hard sandstone materials

that exhibited moderate to low fracturing with compressive strengths ranging from about 4,500

psi to over 10,000 psi. We anticipate that blasting will be necessary to efficiently remove the

very hard sandstone formational materials in some areas of the project. Blasting must be

performed very carefully by an experienced blaster to ensure that the foundation bearing

materials are not compromised for support of the structure. Careful attention must be given to

post blasting operations to insure that the foundation support materials have not been

compromised or portions of the formational materials located behind the proposed basement

retaining walls have not been destabilized. We are available to assist with these post blasting

observations. Where possible, we recommend that alternative excavation methods be used to

more precisely excavate the foundation bearing support elevation with less potential for

disturbance to the foundation support materials.

3.5 Excavation Cut to Embankment Fill Shrink/Swell Factors

We understand that excavation cut and embankment fill construction will be used to establish

the project site grade(s). This section of the report provides estimated shrink/swell factors for

excavated material that will be placed and compacted as embankment fill. The factors provided

are applicable for the sandy clay soil materials located above the formational sandstone materials.

All embankment fill placed on the project site should be compacted to at least ninety (90)

percent of the Modified Proctor (ASTM D1557). The factor provided below is based on an

average value of the existing in-place density for the native sandy clay soil materials compacted

to ninety (90) percent of the Modified Proctor (ASTM D1557).

We obtained a number of driven Modified California Barrel liners within the native sandy clay

soil materials; however the number of samples that could be obtained was limited due to the

relatively shallow depth of the formational material underlying the project site. The dry density

and moisture content of these liner samples are tabulated in Section 4.0 below. An average dry

density of about 117 pounds per cubic foot was obtained for the liner samples obtained and tested

Page 12: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

11

from the sandy clay soil materials that overlie the formational sandstone material.

The results of the Modified Proctor test are presented in Section 4.0 below. We obtained a

maximum dry density of about 124 pounds per cubic foot at an optimum moisture content of

about 11.0 percent. Based on ninety (90) percent compaction, embankment fill material should

be compacted to about 112 pounds per cubic foot. Therefore we anticipate that it will require

between about 0.96 cubic yards of excavation cut within the site sandy clay soil materials to

produce about 1.0 cubic yard of embankment fill material. Therefore the swell factor from

excavation cut to embankment fill appears to be in the range of about 1.04. This value is not

applicable for the formational materials. We estimate a swell factor of about 1.2 from excavation

cut to embankment fill for the competent formational sandstone materials.

3.6 Site Seismic Classification

The seismic site class as defined by the 2009 International Building Code is based on some

average values of select soil characteristics such as shear wave velocity, standard penetration test

result values, undrained shear strength, and plasticity index.

Based on our standard penetration field tests and laboratory test results we feel that the

subsurface conditions for the project are consistent with the criteria for a Site Class C designation

as outlined in the 2009 International Building Code, Table 1613.5.2.

The table below presents seismic site coefficients for the project site based on a Site Class C

designation in conjunction with the mapped short period acceleration and long period

acceleration. The spectral response maps and subsequent seismic site coefficients were obtained

from the 2009 International Building Code Specifications.

Mapped Spectral

Short Period

Acceleration Ss

(Figure 1613.5(1))

Mapped Spectral

1-second

Acceleration S1

(Figure 1613.5(2))

Short Term Period Site

Coefficient Fa

(Table 1613.5.3 (1))

Long Term Period Site

Coefficient Fv

(Table 1613.5.3 (2))

0.20g

0.06g

1.2

1.7

Page 13: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

12

4.0 LABORATORY STUDY

The laboratory study included tests to estimate the strength, swell and consolidation potential of

the soils tested. We performed the following tests on select samples obtained from the test

borings.

Moisture content and dry density; the moisture content and in-situ dry density of some of the

soil samples were assessed in general accordance with ASTM D2216. The results of the

moisture content and dry density tests performed are tabulated below.

Sample Identification

and Depth

Sample Wet Density

(pcf)

Sample Moisture

Content (%)

Sample Dry Density

(PCF)

TB-3: 1.5 feet 109.8 3.3 106.3

TB-4: 13.5 feet 138.4 7.6 128.6

TB-5: 2 feet 116.4 4.8 111.1

TB-6: 4.5 feet 115.3 3.6 111.3

TB-8: 3.5 feet 118.3 2.5 115.4

TB-11: 1 foot 127.3 7.9 118.0

Atterberg Limits and Sieve Analysis; the plastic limit, liquid limit and plasticity index of some

of the soil samples was determined in general accordance with ASTM D4318. In conjunction

with the Atterberg Limits tests, sieve analysis tests were performed in general accordance with

ASTM D422 and D1140. The results of the sieve analysis and Atterberg Limits testing

performed are provided in Appendix B, Figures 4.1 through 4.6. The sandy clay soil materials

encountered and tested classify as USCS type “CL” or AASHTO type “A-6” sandy lean clay

material. The Plasticity Index of the clay soils tested range from about 9 to 16.

One Dimensional Swell-Consolidation Tests; the one dimensional swell-consolidation potential

of some of the soil samples obtained was determined. The soil sample tested is exposed to

varying loads and the addition of water. The one-dimensional swell-consolidation response of

the soil sample to the loads and/or water is represented graphically in Appendix B, Figures 4.7

through 4.12. The basic information obtained from the swell-consolidation tests performed is

tabulated below. We performed a swell pressure/ swell potential only for the test performed on

TB-2A at a sample depth of seventeen (17) feet therefore the swell/consolidation graph was not

produced for this sample. The results of the swell pressure/potential for this test are provided

below.

Page 14: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

13

Sample

Designation

Initial

Moisture

Content

Initial Dry

Density

(pcf)

Swell

Pressure

(psf)

Swell Potential

(percent)

TB-2A: 17 feet (claystone)

11.1% 127.4

(remold) 0 --

(100 psf surcharge load)

TB-3: 1.5 feet (sandy clay)

3.3% 106.3 0 -- (100 psf surcharge load)

TB-4: 13.5 feet (claystone)

7.6% 128.6 900 1.0% (100 psf surcharge load)

TB-5: 2 feet (sandy clay)

4.8% 111.1 0 --

(100 psf surcharge load)

TB-6: 4.5 feet (sandy clay)

3.6% 111.3 290 0.3%

(100 psf surcharge load)

TB-8: 3.5 feet (clayey sandstone)

2.5% 115.4 300 0.2%

(100 psf surcharge load)

TB-11: 1 foot (sandy clay)

7.9% 118.0 950 0.9%

(100 psf surcharge load)

Based on our laboratory test data the site clay soil materials and claystone materials encountered

within the formational materials exhibit a low to moderate swell potential. The sandy clay soil

materials encountered and tested that overlie the formational materials exhibited a moderate to

relatively high consolidation potential when exposed to typical spread footing foundation

pressures.

Unconfined Compressive Strength; the unconfined compressive strength of select sections of

the NWL (NQ diameter) core were tested for strength in our concrete press. The results of the

unconfined compressive strength tests are presented below.

NQ Core Boring and Depth

(feet below the ground surface)

Unit Weight

(pcf)

Ultimate Compressive Strength

(psi)

TB-2A at 2.5 feet

TB-2A at 10.0 feet

156.8

144.0

4,650

1,180

TB-10A @ 9.0 feet 157.4 10,520

Rock Quality Determination (RQD); The relative quality with regard to degree of fracturing of

the core was determined. The results of the RQD tests may be found on the NWL core logs

presented in Appendix A. The formational materials encountered in our core borings may be

generally considered as being moderately to highly fractured.

Page 15: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

14

Direct Shear Strength tests; direct shear strength tests were performed on select soil samples to

estimate the soil strength characteristics in general accordance with ASTM D3080. Based on the

test results, we used an angle of internal friction of thirty (30) degrees and cohesion of about 50

pounds per square foot for the sandy clay soil materials encountered in the upper soil strata. The

results of the direct shear strength test are shown on Figure 4.13.

Moisture content-dry density relationship (Proctor) tests; We performed laboratory moisture

content-dry density tests to assess the relationship between the soil moisture content and dry

density. The Proctor tests were performed in general accordance with ASTM D1557. We

obtained a maximum dry density of about 124.0 pounds per cubic foot at an optimum moisture

content of about 11.0% for the sandy clay soil materials encountered at the project site. The

results of the laboratory Proctor tests are presented on Figures 4.14.

California Bearing Ratio (CBR) Tests; We assessed the pavement section support

characteristics of select composite soil samples in general accordance with ASTM D1883. We

obtained a CBR value of about six (6) for the sandy clay subgrade soil materials compacted to

about ninety (90) percent of the maximum dry density as defined by the Modified Proctor test

(ASTM D1557). The results of the CBR tests are presented on Figure 4.15.

5.0 FOUNDATION RECOMMENDATIONS

Based on the subsurface conditions encountered and laboratory test data obtained, we feel that

the proposed structure may be supported by a conventional spread footing foundation system. As

discussed above, based on the data available to us at the time this report was prepared, the entire

basement/sally port corridor areas will extend into the competent formational materials. The

structure perimeter foundation system will be located on or within about two (2) feet of the

formational sandstone material for a “typical depth” bottom of footing elevation around the

southwest and majority of the southeast sides of the structure. However we anticipate that the

formational materials will be located more than two (2) feet to possibly as much as about six (6)

feet below a “typical depth” bottom of footing elevation for the northeastern area of the structure.

Section 5.1 below provides bearing capacity values and construction considerations for

extending the entire structure foundation system to bear on a layer of structural fill and/or lean

concrete fill that extends to the competent formational sandstone material. This footing support

strategy limits the potential for post construction differential settlement to occur in the

foundation system. The competent formational sandstone materials will provide a relatively

high bearing capacity value with minimal potential for post construction settlement or heave due

to expansive soil conditions. We calculated that the potential differential settlement between

Page 16: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

15

portions of the foundation system supported on the formational sandstone material versus

portions of the foundation system supported on the site clay soil materials that overlie the

formational material could be in the range of one (1) inch or greater. Therefore we do not

recommend that the structure foundation system bear on the different material types.

Section 5.2 provides bearing capacity values for supporting spread footings on the site sandy

clay soil materials. These recommendations are applicable for ancillary structures (that are not

structurally connected to the main structure) such as exterior retaining wall structures.

We are available to provide alternative foundation recommendations such as drilled caissons at

your request, however we do not feel that the use of a drilled caisson foundation system is

necessary based on the subsurface conditions encountered and laboratory test data.

The integrity and long-term performance of any foundation system is influenced by the quality

of workmanship which is implemented during construction. It is imperative that all excavation

and fill placement operations be conducted by qualified personnel using appropriate equipment

and techniques to provide suitable support conditions for the foundation system.

5.1 Spread Footings Supported by the Competent Formational Sandstone Material

The sketch provided below is intended to provide insight regarding the depth of the competent

formational sandstone material below the various areas of the structure layout. This figure is

based on the approximate location of our test borings relative to the proposed building footprint

as provided to us by Maness and Associates, the existing topography of the ground surface

around the structure area, and our understanding of the various finished floor elevations of the

structure. The actual depth of the formational sandstone material below the chosen footing

support elevation will likely vary somewhat from the approximate depths shown below. The

figure below is based on the following assumptions;

• The finished floor elevation of the main structure floor system will be at an elevation of

about 6164.5 feet. We have assumed a bottom of footing depth for the structure

perimeter footings of about 6160.5 feet. This portion of the foundation system is outlined

in the colors yellow and red in the sketch shown below.

• The finished floor elevation of the basement mechanical/electrical rooms and basement

corridor “sally port” will be at an elevation of about 6149.5 feet. We have assumed a

bottom of footing elevation for the structure basement/corridor walls of about 6148.5 feet.

This portion of the foundation system is outlined in green in the sketch below.

Page 17: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

16

The general foundation preparation strategy provided below should be followed for supporting

the entire structure foundation system on the competent formational sandstone materials.

N

Foundation system

located within competent

formational sandstone

materials

Foundation system

located near or about

two (2) feet above

competent formational

sandstone

Foundation system

located about two (2)

to as deep as about six

(6) feet above

competent formational

sandstone

Page 18: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

17

• The footing excavation should extend to the competent formational sandstone material.

Loose debris from the excavation (or blasting) operations must be removed to expose

competent formational sandstone material.

• We recommend a minimum structural fill depth of eight (8) inches be placed to help

achieve a uniform footing support elevation and to aid in the construction of concrete

formwork.

• For areas of the structure where the chosen footing support elevation is located within

about two and one-half (2½) feet of the competent formational material, an imported

structural fill may be placed and compacted to establish the bottom of footing elevation.

• For areas where the competent formation sandstone material is located between about two

and one-half (2½) feet or more below the chosen bottom of footing elevation we

recommend that a lean concrete fill be used to backfill the bottom of the footing

excavation to within about two (2) to two and one-half (2½) feet of the bottom of footing

elevation. An imported structural fill material may then be placed and compacted to

establish the bottom of footing elevation. The lean concrete fill material must be

adequately cured prior to placement of the compacted structural fill material.

• The structural fill material should be compacted to at least ninety (90) percent of the

maximum dry density as defined by ASTM D1557, Modified Proctor. In general we

recommend that the structural fill material consist of Colorado Department of

Transportation (CDOT) Class 6 material. Other types of structural fill material may

suitable as well. We are available to assess other material types for use as structural fill

material as the project progresses.

• The lean concrete fill material should consist of a minimum two (2) sack Portland

cement mix. A maximum lift thickness of about three (3) feet should be placed and

allowed to cure prior to placement of additional lifts of lean concrete fill. A higher

strength lean concrete fill such as a three (3) to four (4) sack mix may be used if it is

desired to speed up the strength gain curing process and/or if cold ambient air conditions

are present that would hamper the curing of lighter mixes.

• The lean concrete fill material may be placed neat within the foundation trench

excavation. The width of the lean concrete fill trench excavation should be equal to the

width of the structural fill material. The figure provided below indicates the necessary

width of structural fill material below the footing.

• Alternatively, if it is acceptable by the project structural engineer, the foundation system

may be stepped to limit the depth of fill materials under the footings.

Page 19: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

18

The compacted structural fill should be placed and compacted as discussed in the Construction

Considerations, “Fill Placement Recommendations” section of this report, below. The zone of

influence of the footing (at elevations close to the bottom of the footing) is often approximated as

being between two (2) lines subtended at 45 degree angles from each bottom corner of the

footing. The compacted structural fill should extend beyond the zone of influence of the footing

as shown in the sketch below.

A general and simple rule to apply to the geometry of the compacted structural fill blanket is

that it should extend beyond each edge of the footing a distance which is equal to the fill

thickness.

Spread footings and isolated footings may be designed using an allowable gross bearing

capacity of 4,500 pounds per square foot. The allowable gross bearing capacity may be increased

by twenty (20) percent due to transient loads. A coefficient of friction of 0.45 (based on

structural fill characteristics) may be used for lateral sliding calculations.

All footings should have a minimum depth of embedment of at least one (1) foot. The

embedment concept is shown below.

45 degrees 45 degrees

Footing

No Scale

Footing Zone of Influence Concept

Footing Zone of Influence

Page 20: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

19

We estimate that the footings designed and constructed as discussed above will have a total post

construction settlement of less than one-half (1/2) inch. Differential settlement between various

portions of the foundation system will be less than one-half (1/2) inch.

All footings should be support at an elevation deeper than the maximum depth of frost

penetration for the area. This recommendation includes exterior isolated footings and column

supports. We understand that the code frost depth for the City of Cortez is thirty-two (32) inches.

5.2 Spread Footings Supported by the Site Clay Soil Materials

This section of the report provides bearing capacity values for the site sandy clay soil materials

that overlie the formational materials. These recommendations are applicable for ancillary

structures such as exterior retaining wall footings that are not structurally attached to the main

structure.

The sandy clay soil materials encountered and tested exhibit swell pressures in the range of

about 300 to up to 900 pounds per square foot with a magnitude of swell potential up to about

one (1) percent when exposed to a 100 pound per square foot surcharge load. The site clay soil

materials encountered may be considered as having a low to perhaps moderate swell potential.

The samples tested exhibit a moderate to relatively high consolidation potential when exposed to

typical spread footing foundation pressures.

Minimum depth

of embedment Footing

Footing Embedment Concept

No Scale

Page 21: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

20

Properly designed and constructed continuous spread footings with stem walls/retaining walls

(beams) have the ability to distribute the forces associated with movement in the support soils.

The rigidity of the system helps reduce differential movement and associated damage to the

structure. Movement within the soils supporting isolated pad footings will result in direct

movement of the supported component. Damage to the structure due to this type of movement

can be severe. If possible, we recommend that isolated pad footings structurally connected to

other foundation elements be avoided and that the foundation system be designed as rigid as is

reasonably possible.

Careful preparation of the support soils, placement of granular compacted structural fill, careful

placement and compaction of stem wall backfill and positive surface drainage adjacent to the

foundation system all help reduce the influence of movement within the foundation support soils

on the performance of the spread footing foundation system.

We recommend that the footings be supported by a layer of moisture conditioned and

compacted natural soil which is overlain by a layer of compacted structural fill material. This

concept is outlined below;

• The foundation excavation should be excavated to at least one (1) foot below the

proposed footing support elevation.

• The natural soils exposed in the bottom of the excavation should be scarified to a depth of

about six (6) to eight (8) inches

• The scarified soil should be thoroughly moisture conditioned to about two (2) percent

above the laboratory determined optimum moisture content and then compacted.

• After completion of the compaction of the moisture conditioned natural soil a one (1) foot

thick layer of granular aggregate base course structural fill material should be placed,

moisture conditioned and compacted.

• The moisture conditioned natural soil material and the granular soils should be compacted

as discussed under the Compaction Recommendations portion of this report, below.

All footings should have a minimum depth of embedment of at least one (1) foot. Exterior

footings should have a minimum depth of embedment at least equal to the code frost depth. The

embedment concept is shown below.

Page 22: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

21

Spread footings located away from sloped areas may be designed using the allowable gross

bearing capacity values tabulated below.

Minimum Depth of

Embedment (Feet)

Continuous Footing Design

Capacity (psf)

Isolated Footing Design

Capacity (psf)

1 1,500 2,000

2 2,000 2,500

3 2,500 3,000

The bearing capacity values tabulated above may be increased by twenty (20) percent for

transient conditions associated with wind and seismic loads. Snow loads are not transient loads.

The bearing capacity values above are based on a continuous spread footing width in the range

of about two (2) to three (3) feet and an isolated footing width in the range of about three (3) to

four (4) feet. Larger footings and/or footings placed on deeper depth of compacted structural fill

will have a higher design soil bearing capacity. Development of the final footing design width is

usually an iterative process based on evaluation of design pressures, footing widths and the

thickness of compacted structural fill beneath the footings. We should be contacted as the design

process continues to re-evaluate the design capacities above based on the actual proposed footing

geometry.

Minimum depth

of embedment Footing

Footing Embedment Concept

No Scale

Page 23: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

22

The settlement of the spread footing foundation system will be influenced by the footing size

and the imposed loads. We estimated the total post construction settlement of the footings based

on our laboratory consolidation data, the type and size of the footing. Our analysis below

assumed that the highest bearing capacity value tabulated above was used in the design of the

footings. The amount of post construction settlement may be reduced by placing the footings on

a blanket of compacted structural fill material.

The estimated settlement for continuous footing with a nominal width of about two (2) to three

(3) feet are tabulated below

Thickness of Compacted

Structural Fill (feet)

Estimated Settlement

(inches)

B/2 1/2 -3/4

B About 1/2

B is the footing width

The estimated settlement for isolated pad footings with a nominal square dimension of about

three (3) to four (4) feet are tabulated below

Thickness of Compacted

Structural Fill (feet)

Estimated Settlement

(inches)

B/2 3/4 - 1

3B/4 1/2 - 3/4

B is the footing width

The compacted structural fill should be placed and compacted as discussed in the Construction

Considerations, “Fill Placement Recommendations” section of this report, below. The zone of

influence of the footing (at elevations close to the bottom of the footing) is often approximated as

being between two (2) lines subtended at 45 degree angles from each bottom corner of the

footing. The compacted structural fill should extend beyond the zone of influence of the footing

as shown in the sketch below.

Page 24: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

23

A general and simple rule to apply to the geometry of the compacted structural fill blanket is

that it should extend beyond each edge of the footing a distance which is equal to the fill

thickness.

All footings should be support at an elevation deeper than the maximum depth of frost

penetration for the area. This recommendation includes exterior isolated footings and column

supports. We understand that the code frost depth for the City of Cortez is thirty-two (32) inches.

The post construction differential settlement may be reduced by designing footings that will

apply relatively uniform loads on the support soils. Concentrated loads should be supported by

footings that have been designed to impose similar loads as those imposed by adjacent footings.

Under no circumstances should any footing be supported by more than three (3) feet of

compacted structural fill material unless we are contacted to review the specific conditions

supporting these footing locations.

The design concepts and parameters presented above are based on the soil conditions

encountered in our test borings. We should be contacted during the initial phases of the

foundation excavation at the site to assess the soil support conditions and to verify our

recommendations.

45 degrees 45 degrees

Footing

No Scale

Footing Zone of Influence Concept

Footing Zone of Influence

Page 25: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

24

5.3 General Shallow Foundation Considerations

Some movement and settlement of any shallow foundation system will occur after construction.

Movement associated with swelling soils also occurs occasionally. Utility line connections

through and foundation or structural component should be appropriately sleeved to reduce the

potential for damage to the utility line. Flexible utility line connections will further reduce the

potential for damage associated with movement of the structure.

6.0 RETAINING STRUCTURES

Laterally loaded walls will be constructed as part of this site development. We understand that

both interior structure retaining walls associated with the main structure as well as exterior

retaining walls will be constructed. The magnitude of the lateral earth pressure forces is partially

dependent on the soil strength characteristics, the geometry of the ground surface adjacent to the

retaining structure, the subsurface water conditions and on surcharge loads.

The retaining structures may be designed using the following un-factored equivalent fluid

pressure values tabulated below for level backfill. We are available to provide specific analysis

for retaining walls that will have sloped backfill or surcharge loads above the retained soil mass.

Lateral Earth Pressure Values

Type of Lateral Earth Pressure Level Native Sandy Clay Soil

Backfill

(pounds per cubic foot/foot)*

Level Granular Soil Backfill

(pounds per cubic foot/foot)

Active 45 35

At-rest 65 55

Passive 345 460

Allowable Coefficient of Friction 0.35 (sandy clay soils) 0.45 (imported structural fill)

The passive wedge of backfill material and retained soil materials should be compacted to at

least ninety (90) percent of the maximum dry density as defined by ASTM D1557, Modified

Proctor, in order to achieve the values tabulated above.

The table below provides estimated for the magnitude of retaining wall rotation/translation to

achieve the active and passive pressures tabulated above.

Page 26: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

25

Backfill Soil Type Displacement to achieve

active pressures

(per total unit height of wall)

Displacement to achieve

passive pressures

(per total unit height of wall)

Native sandy clay soils 0.01 0.02

Imported Granular Fill 0.001 0.002

Granular soil that is used for the retaining wall backfill may be permeable and may allow water

migration to the foundation support soils. We recommend capping the granular backfill material

with about one and one-half (1½) to two (2) feet of the site clay soil materials. A separation

geotextile may be necessary depending on the grading of the granular backfill materials. It

should be noted that if the site clay soils are used settlement may occur in the backfill mass

which will influence the performance of overlying concrete flatwork or structural components.

Utilizing a granular fill material will decrease the overall consolidation of the backfill mass. This

is discussed in more detail in Section 8.0 below.

The values tabulated above are for well drained backfill soils. The values provided above do

not include any forces due to adjacent surcharge loads or sloped soils. If the backfill soils

become saturated the imposed lateral earth pressures will be significantly higher than those

tabulated above.

The granular imported soil backfill values tabulated above are appropriate for material with an

angle of internal friction of thirty-five (35) degrees, or greater. The granular backfill must be

placed within the retaining structure zone of influence as shown below in order for the lateral

earth pressure values tabulated above for the granular material to be appropriate.

Page 27: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

26

If a granular backfill is chosen it should not extend to the ground surface. Some granular soils

allow ready water migration which may result in increased water access to the foundation soils.

The upper few feet of the backfill should be constructed using an impervious soil such as silty-

clay and clay soils from the project site.

Backfill should not be placed and compacted behind the retaining structure unless approved by

the project structural engineer. Backfill placed prior to construction of all appropriate structural

members such as floors, or prior to appropriate curing of the retaining wall concrete (if used) may

result in severe damage and/or failure of the retaining structure.

7.0 SUBSURFACE DRAIN SYSTEM

A subsurface drain system must be constructed near the base of all retaining walls. Exterior

retaining structures may be constructed with weep holes to allow subsurface water migration

through the retaining structures.

As discussed earlier in this report, we feel that it is feasible for a temporary subsurface water

condition to develop over the relatively shallow formational materials that underlie the project

site during periods of heavy precipitation or snow melt. Due to the basement areas that will be

incorporated with the structure we recommend that in addition to the basement retaining wall

drain system, a subsurface drain system be constructed adjacent to the exterior sides of the

structure. It may be possible to terminate the drain system along portions of the downslope side

of the structure such as along the north side of the structure to facilitate daylighting the drain

55 Degrees

Retaining wall zone

of influence

Retaining

Structure

Retaining Structure Zone of

Influence Concept, No Scale

Impervious soil

backfill for

upper 2 feet

Page 28: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

27

system.

We suggest that the system consist of a fabric-wrapped aggregate, or a sand material (some

sands may not need fabric, we are available to discuss this with you) which surrounds a rigid

perforated pipe. We typically do not recommend use of flexible corrugated perforated pipe since

it is not readily possible to establish a uniform gradient of the flexible pipe throughout the drain

system alignment. Corrugated drain tile is perforated throughout the entire circumference of the

pipe and therefore water can escape from the perforations at undesirable locations after being

collected. The nature of the perforations of the corrugated material further decreases its

effectiveness as a subsurface drain conduit.

The drain system pipe should be graded to surface outlets if possible. In areas where this is not

possible a sump vault may be constructed. Typically a minimum gradient of about two (2)

percent is preferred for subsurface drain systems, but site geometry and topography may

influence the actual installed pipe gradient. Water must not be allowed to pool along any portion

of the subsurface drain system. An improperly constructed subsurface drain system may actually

promote water access to undesirable locations. The drain system pipe should be surrounded by

about two (2) to four (4) cubic feet per lineal foot of free draining aggregate or sand. If a sump

vault and pump are incorporated into the subsurface drain system, care should be take so that the

water pumped from the vault does not recirculate through pervious soils and obtain access to

other portions of the structure. A generalized subsurface drain system concept is shown below.

Perforated pipe surrounded by

fabric wrapped free-draining

material. Note: The elevation

of the pipe will depend on the

location in the system at which

the cross section is considered.

Impervious backfill for

upper 2 feet

Compacted backfill that

meets lateral earth pressure

design criteria.

Retaining or

foundation wall

Water proof

membrane or

similar placed on

the foundation wall

and extending

below outer face of

footing

Pervious drain board or

fabric (optional)

Footing

Subsurface Drain System Concept No Scale

Geotextile filter fabric, if appropriate

Page 29: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

28

There are often aspects of each site and structure which require some tailoring of the subsurface

drain system to meet the needs of individual projects. We are available to provide consultation

for the subsurface drain system for this project, if desired.

Water often will migrate along utility trench excavations in formational material. If the utility

trench extends from areas above the site, this trench may be a source for subsurface water to

access the structure. We suggest that the utility trench backfill be thoroughly compacted to help

reduce the amount of water migration.

8.0 CONCRETE FLATWORK

We understand that both interior and exterior concrete flatwork will be included in the project

design. Concrete flatwork is typically lightly loaded and has a limited capability to resist shear

forces associated with movement within the support soils. It is prudent for the design and

construction of concrete flatwork on this project to be able to accommodate some movement

associated with movement (likely primarily consolidation) of the support soils.

Of particular concern for this project, partially due to our understanding of the basement wall

heights, is post construction consolidation of the basement/corridor retaining wall backfill and

supported slab-on-grade floors. We anticipate that an average percent consolidation of about 1.0

percent may occur in the native sandy clay soils, and an average percent consolidation of about

0.03 percent consolidation may occur in an imported granular fill material, even if these materials

are thoroughly compacted. For example, for a fifteen (15) foot backfill height, we anticipate that

up to about 1.5 inches of settlement may occur in the retaining wall backfill if the native sandy

clay soil materials are used, and about one-half (1/2) inch of settlement may occur if a well

compacted granular fill material is used. These are estimated values. For this reason we suggest

that at minimum a granular backfill material be used for the basement/corridor retaining walls.

Since at least portions of the main level floor system will be structurally supported, it may be

prudent to explore structurally supporting the entire main floor system that will be located over

the retaining wall backfill materials.

8.1 Interior Concrete Slab-on-Grade Floors

A primary goal in the design and construction of interior concrete slab-on-grade floors is to

reduce the amount of post construction movement that may occur in concrete slab-on-grade

floors due to movement of the support soils. A parallel goal is to reduce the potential for damage

to the structure associated with any movement of the slab-on-grade which may occur. There are

limited options available to help mitigate the influence of volume changes in the support soil for

concrete slab-on-grade floors, these include;

Page 30: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

29

• Preconstruction scarification, moisture conditioning and re-compaction of the natural

soils in areas proposed for support of concrete flatwork, and/or,

• Placement and compaction of granular compacted structural fill material.

Damage associated with movement of interior concrete slab-on-grade floor can be reduced by

designing the floors as “floating” slabs. Floating concrete slabs are not structurally tied to the

foundations or the overlying structure. Interior walls or columns should not be supported on the

interior floor slabs. Movement of interior walls or columns due to movement in the floor slab

can cause severe damage throughout the structure. Interior walls may be structurally supported

from framing above the floor, or interior walls and support columns may be supported on interior

portions of the foundation system.

The only means to completely mitigate the influence of volume changes on the performance of

interior floors is to structurally support the floors. Floors that are suspended by the foundation

system will not be influenced by volume changes in the site soils. The suggestions and

recommendations presented below are intended to help reduce the influence of volume changes

in the support soils on the performance of the concrete slab-on-grade floors.

Interior concrete slab-on-grade floors may be supported by a composite fill blanket which is

composed of a six (6) inch thick lower layer of scarified, moisture conditioned natural soil that is

overlain by a twelve (12) inch thick blanket of compacted structural fill. The scarified fill

material and the compacted structural fill material should be constructed as discussed under the

Construction Considerations, “Fill Placement Considerations” section of this report below.”

Capillary and vapor moisture rise through the slab support soil may provide a source for

moisture in the concrete slab-on-grade floor. This moisture may promote development of mold

or mildew in poorly ventilated areas and may influence the performance of floor coverings and

mastic placed directly on the floor slabs. There are a few options available to help reduce the

migration of capillary moisture and vapor rise into the floor slab.

Comments for Reduction of Capillary Rise

One option to stop capillary rise through the floor slab is to place a layer of clean aggregate

material, such as washed concrete aggregate for the upper four (4) to six (6) inches of fill

material supporting the concrete slabs.

Comments for Reduction of Vapor Rise

To reduce vapor rise through the floors slab a moisture barrier such as a 6 mil (or thicker)

plastic, or similar impervious geotextile material may be placed below the floor slab. The

Page 31: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

30

American Concrete Institute (ACI) recommends that four (4) inches of “trimmable material” (not

sand) conforming to ASTM D448, No.10 grading be used between the vapor barrier and the

overlying concrete for support of concrete slab-on-grade floors. We have provided the

specifications for ASTM D48 No.10 Sand below.

Grading of ASTM D448 No. 10 Material

Sieve Size Percent Passing Each Sieve

3/8 inch 100

#4 85-100

#100 10 - 30

This type of material may not be locally available therefore we suggest that if an impervious

barrier is used that it should be placed on at two (2) to three (3) inches of fine-grained granular

material, such as crusher reject material to protect it from punctures from the underlying

substrate materials with at least four (4) inches of trimmable material closely conforming to the

D448 No. 10 grading, such as appropriately graded crusher reject material, on top of the barrier

to support the concrete floor slab. This will help reduce the influence of the barrier on the

migration of concrete bleed water and associated concrete curing conditions during construction

of the slab. There are proprietary barriers that are puncture resistant that may not need the

underlying layer of protective material. We do not recommend placement of the concrete

directly on a moisture barrier unless the concrete contractor has had previous experience with

curing of concrete placed in this manner. The project architect, designer and/or builder should be

contacted for the best capillary break for this project.

The project architect, designer and/or builder should be contacted for the best capillary break for

this project. It is not necessary, from a geotechnical engineering perspective, to install capillary

breaks under garage floors unless it is possible that future conversion of the garage into interior

rooms is planned.

The project structural engineer should be contacted to provide steel reinforcement design

considerations for the proposed floor slabs. Any steel reinforcement placed in the slab should be

placed at the appropriate elevations to allow for proper interaction of the reinforcement with

tensile stresses in the slab. Reinforcement steel that is allowed to cure at the bottom of the slab

will not provide adequate reinforcement.

8.2 Exterior Concrete Flatwork Considerations

Exterior concrete flatwork includes concrete driveway slabs, aprons, patios, and walkways. The

desired performance of exterior flatwork typically varies depending on the proposed use of the

Page 32: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

31

site and each owner’s individual expectations. As with interior flatwork, exterior flatwork is

particularly prone to movement and potential damage due to movement of the support soils. This

movement and associated damage may be reduced by following the recommendations discussed

under interior flatwork, above. Unlike interior flatwork, exterior flatwork may be exposed to

frost heave.

If some movement of exterior flatwork is acceptable, we suggest that the support areas be

prepared by scarification, moisture conditioning and re-compaction of about four (4) inches of

the natural soils followed by placement of about four (4) to six (6) inches of compacted granular

fill material. The scarified material and granular fill materials should be placed as discussed

under the Construction Considerations, “Fill Placement Recommendations” section of this

report, below.

It is important that exterior flatwork be separated from exterior column supports, masonry

veneer, finishes and siding. No support columns, for the structure or exterior decks, should be

placed on exterior concrete unless movement of the columns will not adversely affect the

supported structural components. Movement of exterior flatwork may cause damage if it is in

contact with portions of the structure exterior.

Exterior flatwork should not be placed on soils prepared for support of landscaping vegetation.

Cultivated soils will not provide suitable support for concrete flatwork.

8.3 General Concrete Flatwork Comments

It is relatively common that both interior and exterior concrete flatwork is supported by areas of

fill adjacent to either shallow foundation walls or basement retaining walls. A typical sketch of

this condition is shown below.

Page 33: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

32

Settlement of the backfill shown above will create a void and lack of soil support for the

portions of the slab over the backfill. Settlement of the fill supporting the concrete flatwork is

likely to cause damage to the slab-on-grade. Settlement and associated damage to the concrete

flatwork may occur when the backfill is relatively deep, even if the backfill is compacted.

If this condition is likely to exist on this site it may be prudent to design the slab to be

structurally supported on the retaining or foundation wall and designed to span to areas away

from the backfill area as designed by the project structural engineer. We are available to discuss

this with you.

9.0 PAVEMENT SECTION THICKNESS DESIGN RECOMMENDATIONS

We performed a California Bearing Ratio (CBR) test on a composite sample of soil obtained

from the project site. Based on the results of the CBR test we used an R-Value of 6 in our

analysis for the pavement section thickness design.

We recommend that the subgrade soils be proof-rolled prior to the scarification and processing

operations. Any soft areas observed during the proof-rolling operations should be removed and

replaced with properly processed materials and/or granular aggregate materials as part of the

subgrade preparation.

The site subgrade pavement section support soils must be scarified to a depth of six (6) inches,

moisture conditioned and compacted prior to placement of the overlying aggregate pavement

Limit of construction

excavation

Foundation or

retaining wall

Concrete Slab-on-grade

Wall backfill area

Wall Backfill and Slab Support

Sketch No Scale

Page 34: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

33

section materials. The material should be moisture conditioned to within about two (2) percent

of the optimum moisture content and compacted to at least ninety (90) percent of maximum dry

density as determined by the modified Proctor test, ASTM D1557. The surface of the subgrade

soil should be graded and contoured to be approximately parallel to the finished grade of the

pavement surface.

The aggregate materials used within the pavement section should conform to the requirements

outlined in the current Specifications for Road and Bridge Construction, Colorado Department of

Transportation (CDOT). The aggregate base material should be a three-quarter (3/4) inch minus

material that conforms to the CDOT Class 6 aggregate base course specifications and have an R-

value of at least 78. The aggregate sub-base course should conform to the CDOT specifications

for Class 2 material and should have a minimum R-value 70. Other material may be suitable for

use in the pavement section, but materials different than those listed above should be tested and

observed by us prior to inclusion in the project design or construction. Aggregate sub-base and

base-course materials should be compacted to at least ninety-five (95) percent of maximum dry

density as defined by the modified Proctor test, ASTM D1557.

Aggregate base-course and sub-base course locally available that do not meet the above

specifications may be suitable for this project. We are available to review other aggregate

gradations produced by local gravel producers to insure the suitability of the gravel products for

the project. The aggregate base course should have a minimum R-value of 72, and the aggregate

sub-base course should have a minimum R-Value of 65.

9.1 Asphalt Pavement Recommendations

We recommend that the asphalt concrete used on this project be mixed in accordance with a

design prepared by a licensed professional engineer, or an asphalt concrete specialist. We should

be contacted to review the mix design prior to placement at the project site. We recommend that

the asphalt concrete be compacted to between ninety-two (92) and ninety-six (96) percent of the

maximum theoretical density.

We have provided several pavement section design thicknesses below. The structural support

characteristics of each section are approximately equal. The project civil engineer, or contractor

can evaluate the best combination of materials for economic considerations.

We have provided pavement section thicknesses for both 50,000 (standard vehicle use section)

and 125,000 (heavy vehicle use section)- 18,000 pound equivalent single axle loads (18k ESAL).

We are available to provide additional design sections, if these are desired.

Page 35: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

34

Pavement Section Design Thickness

Light Duty Standard Passenger Car/Truck Use

50,000 18k ESAL

Pavement Section Component Alternative Thicknesses of Each Component

(inches)

Asphalt Concrete 3 3

Class 6 4 10

Class 2 8 0

Reconditioned Subgrade 6 6

Pavement Section Design Thickness

Heavy Vehicle Use

125,000 18k ESAL

Pavement Section Component Alternative Thicknesses of Each Component

(inches)

Asphalt Concrete 4 4 5

Class 6 4 10 6

Class 2 8 0 0

Reconditioned Subgrade 6 6 6

The pavement section thicknesses tabulated above are appropriate for the post-construction

traffic use associated with the fire station. Heavy construction equipment traffic will have a

significant influence on the quality, character, and design life of the pavement sections tabulated

above. If possible we recommend that the asphalt pavement not be placed until completion of

the major construction activity. We are available to discuss this with you as the project

progresses.

9.2 Rigid Concrete Pavement Recommendations

We anticipate that rigid concrete pavement will likely be used for portions of the project

including exterior aprons, and possibly exterior driveway/parking areas. The following

recommendations are based on the American Concrete Institute (ACI) Guide for Design and

Construction of Concrete Parking Lots report 330R-01, strength characteristics (CBR-value) of

the native subgrade soils, and on our experience with concrete paved parking lots in the region.

A modulus of subgrade reaction of 150 pounds per cubic inch may be used for design purposes.

Page 36: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

35

Our recommendations are as follows;

• For the proposed main parking area that will service light vehicular traffic only, a

minimum concrete mat thickness of five (5) inches should be used. This section is valid

for an average daily truck (ADTT) of less than ten (10).

• For areas that will be exposed to heavy truck traffic on a regular basis a minimum

concrete mat thickness of six (6) inches should be used.

The concrete mat should be supported by a minimum thickness of six (6) inches of three-quarter

(3/4) inch minus aggregate base course material that meets the specifications tabulated in section

9.1 above. We are available to review aggregate gradations produced by local gravel producers

to insure the suitability of the gravel products for the project. The aggregate materials should be

compacted to at least ninety-five (95) percent of maximum dry density as defined by AASHTO

T-180 or ASTM D 1557, Modified Proctor test. The upper six (6) inches of subgrade support

soils should be scarified and compacted to at least ninety (90) percent of maximum dry density as

defined by AASHTO T-180 or ASTM D1557, Modified Proctor test prior to placement of the

aggregate base course.

A concrete with a minimum twenty-eight (28) day compressive strength of 4,500 pounds per

square inch (psi) should be used. Joint spacing should not exceed twelve and one-half (12½) feet

for a slab thickness of five (5) inches and should not exceed fifteen (15) feet for a slab thickness

of six (6) inches. The recommendations for minimum concrete strength presented here are based

on the ACI recommendations. The site specific structural engineering design recommendations

should take precedent over those listed in this report. The project structural engineer should be

contacted for steel reinforcement design. We are available to discuss our recommendations with

the project structural engineer as needed.

9.3 General Parking Area Considerations

Water intrusion into the pavement section support materials will negatively influence the

performance of the parking lot surface. Water from irrigation, water from natural sources that

migrates into the soils beneath landscapes surface and water from any source that gains access to

the support materials can all decrease the life of the parking lot surface. Care should be taken

along curbs and any edge of the parking lot to develop an interface between the material that will

reduce subsurface and surface water migration into the support soil and pavement section

materials. Landscape islands and other irrigated features often promote water migration since no

surface flow from these features typically occurs. The same can occur along perimeter cub areas.

Page 37: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

36

Water will often migrate along the interface of concrete curbs and gutter areas early in the life

of any parking area. The tendency for this type of migration often decreases with time, but can

be reduced by compaction of materials along the outside base of curb areas adjacent to the

interface of the concrete curb and the underlying soil prior to placement of landscaping soil

above this interface.

10.0 CONSTRUCTION CONSIDERATIONS

This section of the report provides comments, considerations and recommendations for aspects

of the site construction which may influence, or be influenced by the geotechnical engineering

considerations discussed above. The information presented below is not intended to discuss all

aspects of the site construction conditions and considerations that may be encountered as the

project progresses. If any questions arise as a result of our recommendations presented above, or

if unexpected subsurface conditions are encountered during construction we should be contacted

immediately.

10.1 Fill Placement Recommendations

There are several references throughout this report regarding both natural soil and compacted

structural fill recommendations. The recommendations presented below are appropriate for the

fill placement considerations discussed throughout the report above.

All areas to receive fill, structural components, or other site improvements should be properly

prepared and grubbed at the initiation of the project construction. The grubbing operations

should include scarification and removal of organic material and soil. No fill material or

concrete should be placed in areas where existing vegetation or fill material exist.

10.1.1 Natural Soil Fill

Any natural soil used for any fill purpose should be free of all deleterious material, such as

organic material and construction debris. Natural soil fill includes excavated and replaced

material or in-place scarified material.

The natural soils should be moisture conditioned, either by addition of water to dry soils, or by

processing to allow drying of wet soils. The proposed fill materials should be moisture

conditioned to between about optimum and about two (2) percent above optimum soil moisture

content. This moisture content can be estimated in the field by squeezing a sample of the soil in

the palm of the hand. If the material easily makes a cast of soil which remains in-tact, and a

minor amount of surface moisture develops on the cast, the material is close to the desired

Page 38: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

37

moisture content. Material testing during construction is the best means to assess the soil

moisture content.

Moisture conditioning of clay or silt soils may require many hours of processing. If possible,

water should be added and thoroughly mixed into fine grained soil such as clay or silt the day

prior to use of the material. This technique will allow for development of a more uniform

moisture content and will allow for better compaction of the moisture conditioned materials.

The moisture conditioned soil should be placed in lifts that do not exceed the capabilities of the

compaction equipment used and compacted to at least ninety (90) percent of maximum dry

density as defined by ASTM D1557, modified Proctor test. We typically recommend a

maximum fill lift thickness of six (6) inches for hand operated equipment and eight (8) to ten

(10) inches for larger equipment. Care should be exercised in placement of utility trench backfill

so that the compaction operations do not damage the underlying utilities.

Typically the maximum lift thickness is about six (6) to eight (8) inches, therefore the

maximum allowable rock size for natural soil fill is about six (6) inches. If smaller compaction

equipment is being used, such as walk behind compactors in trenches, the maximum rock size

should be less than about three (3) inches.

10.1.2 Granular Compacted Structural Fill

Granular compacted structural fill is referenced in numerous locations throughout the text of

this report. Granular compacted structural fill should be constructed using an imported

commercially produced rock product such as aggregate road base. Many products other than

road base, such as clean aggregate or select crusher fines may be suitable, depending on the

intended use. If a specification is needed by the design professional for development of project

specifications, a material conforming to the Colorado Department of Transportation (CDOT)

“Class 6” aggregate road base material can be specified. This specification can include an option

for testing and approval in the event the contractor’s desired material does not conform to the

Class 6 aggregate specifications. We have provided the CDOT Specifications for Class 6

material below

Grading of CDOT Class 6 Aggregate Base-Course Material

Sieve Size Percent Passing Each Sieve

¾ inch 100

#4 30 – 65

#8 25 – 55

#200 3 – 12

Liquid Limit less than 30

Page 39: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

38

All compacted structural fill should be moisture conditioned and compacted to at least ninety

(90) percent of maximum dry density as defined by ASTM D1557, modified Proctor test. Areas

where the structural fill will support traffic loads under concrete slabs or asphalt concrete should

be compacted to at least ninety-five (95) percent of maximum dry density as defined by ASTM

D1557, modified Proctor test.

Although clean-screened or washed aggregate may be suitable for use as structural fill on sites

with sand or non-expansive silt soils, or on sites where shallow subsurface water is present, clean

aggregate materials must not be used on any site where expansive soils exist due to the potential

for water to accumulate in the voids of the clean aggregate materials.

Clean aggregate fill, if appropriate for the site soil conditions, must not be placed in lifts

exceeding eight (8) inches and each lift should be thoroughly vibrated, preferably with a plate-

type vibratory compactor prior to placing overlying lifts of material or structural components.

We should be contacted prior to the use of clean aggregate fill materials to evaluate their

suitability for use on this project.

10.2 Excavation Considerations

Unless a specific classification is performed, the site soils should be considered as an

Occupational Safety and Health Administration (OSHA) Type C soil and should be sloped and/or

benched according to the current OSHA regulations. Excavations should be sloped and benched

to prevent wall collapse. Any soil can release suddenly and cave unexpectedly from excavation

walls, particularly if the soils is very moist, or if fractures within the soil are present. Daily

observations of the excavations should be conducted by OSHA competent site personnel to

assess safety considerations.

We did not encounter free subsurface water in our test borings at the depths that we anticipate

the project excavation will extend. If water is encountered during construction, it may be

necessary to dewater excavations to provide for suitable working conditions.

We encountered formational material in our test borings. We suspect that it may be difficult to

excavate this material using conventional techniques. If blasting is planned it must be conducted

strategically to reduce the affect of the blasting on the support characteristics of the site materials

and the stability of adjacent slopes. We typically recommend that where possible blasting be

avoided, however blasting is often needed to aid in the excavation of the site to develop the

desired footing support elevations. It is typical to have about two (2) to three (3) feet of loose

angular clasts of rock, commonly called “shot-rock” below the desired bottom of excavation

elevations. This material is not suitable for support of structural components and should be

removed and replaced with compacted structural fill in areas proposed for support of structural

Page 40: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

39

components.

If possible excavations should be constructed to allow for water flow from the excavation the

event of precipitation during construction. If this is not possible it may be necessary to remove

water from snowmelt or precipitation from the foundation excavations to help reduce the

influence of this water on the soil support conditions and the site construction characteristics.

10.2.1 Excavation Cut Slopes

We anticipate that some permanent excavation cut slopes may be included in the site

development. Temporary cut slopes should not exceed five (5) feet in height and should not be

steeper than about one to one (1:1, horizontal to vertical) for most soils. Permanent cut slopes of

greater than five (5) feet or steeper than two and one-half to one (2½:1, h:v) must be analyzed on

a site specific basis.

10.3 Utility Considerations

Subsurface utility trenches will be constructed as part of the site development. Utility line

backfill often becomes a conduit for post construction water migration. If utility line trenches

approach the proposed project site from above, water migrating along the utility line and/or

backfill may have direct access to the portions of the proposed structure where the utility line

penetrations are made through the foundation system. The foundation soils in the vicinity of the

utility line penetration may be influenced by the additional subsurface water. There are a few

options to help mitigate water migration along utility line backfill. Backfill bulkheads

constructed with high clay content soils and/or placement of subsurface drains to promote utility

line water discharge through the foundation drain system.

Some movement of all structural components is normal and expected. The amount of

movement may be greater on sites with problematic soil conditions. Utility line penetrations

through any walls or floor slabs should be sleeved so that movement of the walls or slabs does

not induce movement or stress in the utility line. Utility connections should be flexible to allow

for some movement of the floor slab.

If utility line trenches are excavated using blasting techniques it is relatively common for

surface and subsurface water to migrate along the fractures in the rock that may be created by

blasting. If this water gains access to a utility line trench that has a gradient down toward the

structure the water may gain access to the foundation support materials and/or subsurface

portions of the proposed structure. Provisions should be made in the project construction plans

to create an impervious barrier to prevent water from migrating into undesirable locations.

Page 41: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

40

10.4 Exterior Grading and Drainage Comments

The ground surface adjacent to the structure should be sloped to promote water flow away from

the foundation system and flatwork. Snow storage areas should not be located in areas which

will allow for snowmelt water access to support soils for the foundation system or flatwork.

Water flow from the roof of the structure should be captured and directed away from the

structure. If the roof water is collected in an eave gutter system, or similar, the discharge points

of the system must be located away from areas where the water will have access to the

foundation backfill or any structure support soils. If downspouts are used, provisions should be

made to either collect or direct the water away from the structure.

The project civil engineering consultant or builder should develop a drainage scheme for the

site. We typically suggest a minimum fall of about eight (8) to ten (10) percent away from the

structure, in the absence of design criteria from others. Care should be taken to not direct water

onto adjacent property or to areas that would negatively influence existing structures or

improvements.

10.5 Landscaping Considerations

We recommend against construction of landscaping which requires excessive irrigation.

Generally landscaping which uses abundant water requires that the landscaping contractor install

topsoil which will retain moisture. The topsoil is often placed in flattened areas near the

structure to further trap water and reduce water migration from away from the landscaped areas.

Unfortunately almost all aspects of landscape construction and development of lush vegetation

are contrary to the establishment of a relatively dry area adjacent to the foundation walls. Excess

water from landscaped areas near the structure can migrate to the foundation system or flatwork

support soils, which can result in volume changes in these soils.

A relatively common concept used to collect and subsequently reduce the amount of excess

irrigation water is to glue or attach an impermeable geotextile fabric or heavy mill plastic to the

foundation wall and extend it below the topsoil which is used to establish the landscape

vegetation. A thin layer of sand can be placed on top of the geotextile material to both protect

the geotextile from punctures and to serve as a medium to promote water migration to the

collection trench and perforated pipe. The landscape architect or contractor should be contacted

for additional information regarding specific construction considerations for this concept which

is shown in the sketch below.

Page 42: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

41

Shallow Landscaping Drain Concept No Scale

Foundation Wall

Approximate

limit

foundation

excavation

backfill

Impermeable geotextile

material, lapped and

glued to the foundation

wall above grade

Perforated pipe

surrounded by free-

draining material

Filter Fabric

Page 43: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

42

A free draining aggregate or sand may be placed in the collection trench around the perforated

pipe. The perforated pipe should be graded to allow for positive flow of excess irrigation water

away from the structure or other area where additional subsurface water is undesired. Preferably

the geotextile material should extend at least ten (10) or more feet from the foundation system.

Care should be taken to not place exterior flatwork such as sidewalks or driveways on soils that

have been tilled and prepared for landscaping. Tilled soils will settle which can cause damage to

the overlying flatwork. Tilled soils placed on sloped areas often “creep” down-slope. Any

structure or structural component placed on this material will move down-slope with the tilled

soil and may become damaged.

10.6 Soil Sulfate Content, Corrosion Issues

The requested scope of our services did not include assessment of the chemical constituents of

corrosion potential of the site soils. Most soils in southwest Colorado are not typically corrosive

to concrete. There has not been a history of damage to concrete due to sulfate corrosion in the

area.

We are available to perform soluble sulfate content tests to assess the corrosion potential of the

soils on concrete if desired.

10.7 Radon Issues

The requested scope of service of this report did not include assessment of the site soils for

radon production. Many soils and formational materials in western Colorado produce Radon gas.

The structure should be appropriately ventilated to reduce the accumulation of Radon gas in the

structure. Several Federal Government agencies including the Environmental Protection Agency

(EPA) have information and guidelines available for Radon considerations and home

construction. If a radon survey of the site soils is desired, please contact us.

11.0 CONSTRUCTION MONITORING AND TESTING

Construction monitoring including engineering observations and materials testing during

construction is a critical aspect of the geotechnical engineering contribution to any project.

Unexpected subsurface conditions are often encountered during construction. The site foundation

excavation should be observed by the geotechnical engineer or a representative during the early

stages of the site construction to verify that the actual subsurface soil and water conditions were

properly characterized as part of field exploration, laboratory testing and engineering analysis. If

Page 44: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

43

the subsurface conditions encountered during construction are different than those that were the

basis of the geotechnical engineering report then modifications to the design may be

implemented prior to placement of fill materials or foundation concrete.

Compaction testing of fill material should be performed throughout the project construction so

that the engineer and contractor may monitor the quality of the fill placement techniques being

used at the site. Generally we recommend that compaction testing be performed for any fill

material that is placed as part of the site development. Compaction tests should be performed on

each lift of material placed in areas proposed for support of structural components. In addition to

compaction testing we recommend that the grain size distribution, clay content and swell

potential be evaluated for any imported materials that are planned for use on the site. Concrete

tests should be performed on foundation concrete and flatwork. If asphaltic concrete is placed

for driveways or aprons near the structure we are available to provide testing of these materials

during placement. We are available to develop a testing program for soil, aggregate materials,

concrete and asphaltic concrete for this project.

12.0 CONCLUSIONS AND CONSIDERATIONS

The information presented in this report is based on our understanding of the proposed

construction that was provided to us and on the data obtained from our field and laboratory

studies. We recommend that we be contacted during the design and construction phase of this

project to aid in the implementation of our recommendations. Please contact us immediately if

you have any questions, or if any of the information presented above is not appropriate for the

proposed site construction.

The recommendations presented above are intended to be used only for this project site and the

proposed construction which was provided to us. The recommendations presented above are not

suitable for adjacent project sites, or for proposed construction that is different than that outlined

for this study.

Our recommendations are based on limited field and laboratory sampling and testing.

Unexpected subsurface conditions encountered during construction may alter our

recommendations. We should be contacted during construction to observe the exposed

subsurface soil conditions to provide comments and verification of our recommendations.

We are available to review and tailor our recommendations as the project progresses and

additional information which may influence our recommendations becomes available.

Page 45: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

44

Please contact us if you have any questions, or if we may be of additional service.

Respectfully submitted,

TRAUTNER GEOTECH

Jonathan P. Butler, P.E.

Staff Geotechnical Engineer

Page 46: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

APPENDIX A

Logs of Test Borings

Page 47: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Field Engineer : J. Butler

Hole Diameter : 4" Solid

Drilling Method : Continuous Flight Auger

Sampling Method : Bag Sample

Date Drilled : 01/07/2016

Total Depth (approx.) : 2.5 feet

Location : See Figure 1 in Report

LOG OF BORING TB - 1

PN:54077GE

109 W Main Street, Room 302Montezuma County Commissioners

Combined Court BuildingMontezuma County

Depthin

feet

0

1

2

3

4

5

DESCRIPTION

Sample Type

Mod. California Sampler

Bag Sample

Standard Split Spoon

Water Level

Water Level During Drilling

Water Level After Drilling

CLAY, sandy, soft to medium stiff, very moist, red

FORMATIONAL MATERIAL at two (2) feet, sandstone, very hard, tan, Dakota Sandstone and Burro Canyon Formation

Auger refusal at two and one-half (2.5) feet

US

CS

CL

GR

AP

HIC

Sam

ples

Blo

w C

ount

Wat

er L

evel

REMARKS

Page 48: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Field Engineer : J. Butler

Hole Diameter : 4" Solid

Drilling Method : Continuous Flight Auger

Sampling Method : Standard Split Spoon

Date Drilled : 01/07/2016

Total Depth (approx.) : 5 feet

Location : See Figure 1 in Report

LOG OF BORING TB - 2

PN:54077GE

109 W Main Street, Room 302Montezuma County Commissioners

Combined Court BuildingMontezuma County

Depthin

feet

0

1

2

3

4

5

6

DESCRIPTION

Sample Type

Mod. California Sampler

Bag Sample

Standard Split Spoon

Water Level

Water Level During Drilling

Water Level After Drilling

CLAY, sandy, stiff, very moist, red

CLAY, sandy, stiff, moist, tan

FORMATIONAL MATERIAL at three (3) feet, sandstone, hard to very hard, tan, Dakota Sandstone and Burro Canyon Formation

Auger refusal at five (5) feet

US

CS

CL

CL

GR

AP

HIC

Sam

ples

Blo

w C

ount

Wat

er L

evel

REMARKS

50/1

Page 49: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Field Engineer : J. Butler

Hole Diameter : NQ

Drilling Method : Wireline Core

Sampling Method : NQ Core

Date Drilled : 1/20/2016

Total Depth : 22 feet

Location : See Figure in Report

LOG OF BORING TC-2A

PN:54077GE

108 W Main Street, Room 302Montezuma County Commissioners

Combined Court BuildingMontezuma County

Depthin

feet

0

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

DESCRIPTION

NQ Core

US

CS

GR

AP

HIC

Run

dep

th

Recovery and R.Q.D.

Top of First Run at two and one-half (2.5) feet

Recovery= 94% R.Q.D= 60%

Bottom of First Run at seven (7) feetTop of Second Run at seven (7) feet

Recovery= 100%R.Q.D.= 14%

Bottom of Second Run at twelve (12) feet Top of Third Run at twelve (12) feet

Recovery= 97%R.Q.D.= 29%

Bottom of Third Run at seventeen (17) feetTop of Fourth Run at seventeen (17) feet

Recovery=100%R.Q.D.= 40%

Bottom of Fourth Run at twenty-two (22) feet

CLAY, sandy, medium stiff, moist, red

FORMATIONAL MATERIAL at two (2) feet, Dakota Sandstone and Burro Canyon Formation, sandstone, very hard, slightly moist, tan, Auger refusal at two and one-half (2.5) feet, moderately fractured sandstone, very hard, tan to white

Highly fractured sandstone, tan, Dakota Sandstone and Burro Canyon Formation

Clayey sandstone, highly fractured, tan to brown, Dakota Sandstone and Burro Canyon Formation

SUBSURFACE WATER ENCOUNTERED IN FRACTURE AT 16 FEET

Claystone and shale, highly fractured, brown to gray, Dakota Sandstone and Burro Canyon Formation

Sandstone, highly fractured, tan, Dakota Sandstone and Burro Canyon Formation

Bottom of test core at twenty-two (22) feet

CL

Page 50: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

LOG OF BORING TB - 3

PN:54077GE

109 W Main Street, Room 302Montezuma County Commissioners

Combined Court BuildingMontezuma County

Depthin

feet

0

1

2

3

4

5

DESCRIPTION

Sample Type

Mod. California Sampler

Bag Sample

Standard Split Spoon

Water Level

Water Level During Drilling

Water Level After Drilling

CLAY, sandy, medium stiff, moist, red

FORMATIONAL MATERIAL at one and one-half (1.5) feet, sandstone, upper one (1) foot is weathered then became very hard, tan, Dakota Sandstone and Burro Canyon Formation

Auger refusal at three (3) feet

US

CS

CL

GR

AP

HIC

Sam

ples

Blo

w C

ount

Wat

er L

evel

REMARKS

Field Engineer : J. Butler

Hole Diameter : 4" Solid

Drilling Method : Continuous Flight Auger

Sampling Method : Mod. California Sampler

Date Drilled : 01/07/2016

Total Depth (approx.) : 3 feet

Location : See Figure 1 in Report

40/6

50/5

Page 51: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Field Engineer : J. Butler

Hole Diameter : 4" Solid

Drilling Method : Continuous Flight Auger

Sampling Method : No Sampling

Date Drilled : 01/20/2016

Total Depth (approx.) : 2.5 feet

Location : See Figure 1 in Report

LOG OF BORING TB - 3A

PN:54077GE

109 W Main Street, Room 302Montezuma County Commissioners

Combined Court BuildingMontezuma County

Depthin

feet

0

1

2

3

4

5

DESCRIPTION

Sample Type

Mod. California Sampler

Bag Sample

Standard Split Spoon

Water Level

Water Level During Drilling

Water Level After Drilling

CLAY, sandy, soft to medium stiff, moist to very moist, red

FORMATIONAL MATERIAL at two (2) feet, sandstone, very hard, slightly moist, tan, Dakota Sandstone and Burro Canyon Formation

Auger refusal at two and one-half (2.5) feet

US

CS

CL

GR

AP

HIC

Sam

ples

Blo

w C

ount

Wat

er L

evel

REMARKS

Page 52: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Field Engineer : J. Butler

Hole Diameter : 4" Solid

Drilling Method : Continuous Flight Auger

Sampling Method : Mod. California Sampler

Date Drilled : 01/07/2016

Total Depth (approx.) : 38.5 feet

Location : See Figure 1 in Report

LOG OF BORING TB - 4

PN:54077GE

109 W Main Street, Room 302Montezuma County Commissioners

Combined Court BuildingMontezuma County

Depthin

feet

0

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

34

35

36

37

38

39

40

DESCRIPTION

Sample Type

Mod. California Sampler

Bag Sample

Standard Split Spoon

Water Level

Water Level During Drilling

Water Level After Drilling

CLAY, sandy, soft to medium dense, moist to very moist, red

FORMATIONAL MATERIAL at three (3) feet, sandstone caprock for one (1) foot, very hard, tan, Dakota Sandstone and Burro Canyon Formation

Sandstone with interbedded claystone layers, very hard, tan, Dakota Sandstone and Burro Canyon Formation

Claystone at ten (10) feet, hard/very stiff, moist, brown, Dakota Sandstone and Burro Canyon Formation

Interbedded sandstone and claystone, very hard, tan to brown

Bottom of test boring at thirty-eight (38) feet

US

CS

CL

GR

AP

HIC

Sam

ples

Blo

w C

ount

50/1

50/3

25/650/6

15/625/635/6

50/1

Wat

er L

evel

REMARKS

Page 53: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Field Engineer : J. Butler

Hole Diameter : 4" Solid

Drilling Method : Continuous Flight Auger

Sampling Method : Mod. California Sampler

Date Drilled : 01/07/2016

Total Depth (approx.) : 18 feet

Location : See Figure 1 in Report

LOG OF BORING TB - 5

PN:54077GE

109 W Main Street, Room 302Montezuma County Commissioners

Combined Court BuildingMontezuma County

Depthin

feet

0

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

DESCRIPTION

Sample Type

Mod. California Sampler

Bag Sample

Standard Split Spoon

Water Level

Water Level During Drilling

Water Level After Drilling

CLAY, sandy, soft, moist, red

CLAY, SAND, white chemical cementing, hard, slightly moist, tan to white

FORMATIONAL MATERIAL at eight (8) feet, sandstone, very hard, slightly moist, tan to brown, Dakota Sandstone and Burro Canyon Formation

Sandy claystone, very hard, moist, brown, Dakota Sandstone and Burro Canyon Formation

Auger refusal at eighteen (18) feet

US

CS

CL

CL-SCG

RA

PH

IC

Sam

ples

Blo

w C

ount

25/6

30/6

25/6

50/5

50/6

50/6

Wat

er L

evel

REMARKS

Page 54: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Field Engineer : J. Butler

Hole Diameter : 4" Solid

Drilling Method : Continuous Flight Auger

Sampling Method : Mod. California Sampler

Date Drilled : 01/07/2016

Total Depth (approx.) : 24 feet

Location : See Figure 1 in Report

LOG OF BORING TB - 6

PN:54077GE

109 W Main Street, Room 302Montezuma County Commissioners

Combined Court BuildingMontezuma County

Depthin

feet

0

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

DESCRIPTION

Sample Type

Mod. California Sampler

Bag Sample

Standard Split Spoon

Water Level

Water Level During Drilling

Water Level After Drilling

CLAY, sandy, soft, very moist, red

CLAY, SAND, some white chemical deposits, very stiff/very dense, slightly moist, red and tan

FORMATIONAL MATERIAL at eight and one-half (8.5) feet, sandstone, very hard, slightly moist, tan, Dakota Sandstone and Burro Canyon Formation

Clayey sandstone, to sandy claystone, hard to very hard, moist, brown to tan, Dakota Sandstone and Burro Canyon Formation

Claystone at twenty (20) feet, hard, moist, brown, Dakota Sandstone and Burro Canyon Formation

Sandstone at twenty-three and one-half (23.5) feet, very hard, Dakota Sandstone and Burro Canyon Formation

Auger refusal at twenty-four (24) feet

US

CS

CL

CL-SC

GR

AP

HIC

Sam

ples

Blo

w C

ount

Wat

er L

evel

REMARKS

18/630/6

50/3

40/650/5

Page 55: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Field Engineer : J. Butler

Hole Diameter : 4" Solid

Drilling Method : Continuous Flight Auger

Sampling Method : Mod. California Sampler

Date Drilled : 01/07/2016

Total Depth (approx.) : 22.5 feet

Location : See Figure 1 in Report

LOG OF BORING TB - 7

PN:54077GE

109 W Main Street, Room 302Montezuma County Commissioners

Combined Court BuildingMontezuma County

Depthin

feet

0

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

DESCRIPTION

Sample Type

Mod. California Sampler

Bag Sample

Standard Split Spoon

Water Level

Water Level During Drilling

Water Level After Drilling

CLAY, sandy, soft, very moist, red

CLAY, SAND, dense, slightly moist, red and tan

FORMATIONAL MATERIAL at three and one-half (3.5) feet, sandstone, very hard, slightly moist, tan, Dakota Sandstone and Burro Canyon Formation

Clayey sandstone, very hard, moist, brown to tan, Dakota Sandstone and Burro Canyon Formation

Sandy Claystone, very hard, moist, brown to tan, Dakota Sandstone and Burro Canyon Formation

Sandstone at twenty-one (21) feet, very hard, Dakota Sandstone and Burro Canyon Formation

Auger refusal at twenty two and one-half (22.5) feet

US

CS

CL

CL

GR

AP

HIC

Sam

ples

Blo

w C

ount

Wat

er L

evel

REMARKS

35/650/2

30/650/2

80/6

Page 56: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Field Engineer : J. Butler

Hole Diameter : 4" Solid

Drilling Method : Continuous Flight Auger

Sampling Method : Mod. California Sampler

Date Drilled : 01/07/2016

Total Depth (approx.) : 5 feet

Location : See Figure 1 in Report

LOG OF BORING TB - 8

PN:54077GE

109 W Main Street, Room 302Montezuma County Commissioners

Combined Court BuildingMontezuma County

Depthin

feet

0

1

2

3

4

5

6

DESCRIPTION

Sample Type

Mod. California Sampler

Bag Sample

Standard Split Spoon

Water Level

Water Level During Drilling

Water Level After Drilling

CLAY, sandy, soft to medium stiff, very moist, red

CLAY, sandy, stiff, slightly moist, tan

FORMATIONAL MATERIAL at three (3) feet, sandstone, hard to very hard, slightly moist, tan, Dakota Sandstone and Burro Canyon Formation

Auger refusal at five (5) feet

US

CS

CL

CL

GR

AP

HIC

Sam

ples

Blo

w C

ount

30/6

50/1

Wat

er L

evel

REMARKS

Page 57: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Field Engineer : J. Butler

Hole Diameter : 4" Solid

Drilling Method : Continuous Flight Auger

Sampling Method : Mod. California Sampler

Date Drilled : 01/07/2016

Total Depth (approx.) : 5.5 feet

Location : See Figure 1 in Report

LOG OF BORING TB - 9

PN:54077GE

109 W Main Street, Room 302Montezuma County Commissioners

Combined Court BuildingMontezuma County

Depthin

feet

0

1

2

3

4

5

6

DESCRIPTION

Sample Type

Mod. California Sampler

Bag Sample

Standard Split Spoon

Water Level

Water Level During Drilling

Water Level After Drilling

CLAY, sandy, medium stiff, moist, red

CLAY, sandy, stiff, moist, tan

FORMATIONAL MATERIAL at three and one-half (3.5) feet, sandstone, very hard, slightly moist, tan, Dakota Sandstone and Burro Canyon Formation

Auger refusal at five and one-half (5.5) feet

US

CS

CL

CL

GR

AP

HIC

Sam

ples

Blo

w C

ount

30/6

50/1

Wat

er L

evel

REMARKS

Page 58: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Field Engineer : J. Butler

Hole Diameter : 4" Solid

Drilling Method : Continuous Flight Auger

Sampling Method : Mod. California Sampler

Date Drilled : 01/07/2016

Total Depth (approx.) : 7.5 feet

Location : See Figure 1 in Report

LOG OF BORING TB - 10

PN:54077GE

109 W Main Street, Room 302Montezuma County Commissioners

Combined Court BuildingMontezuma County

Depthin

feet

0

1

2

3

4

5

6

7

8

DESCRIPTION

Sample Type

Mod. California Sampler

Bag Sample

Standard Split Spoon

Water Level

Water Level During Drilling

Water Level After Drilling

CLAY, sandy, medium stiff, moist, red

CLAY, sandy, stiff, slightly moist, red and tan

FORMATIONAL MATERIAL at three and one-half (3.5) feet, sandstone, very hard, slightly moist, tan, Dakota Sandstone and Burro Canyon Formation

Auger refusal at seven and one-half (7.5) feet

US

CS

CL

CL

GR

AP

HIC

Sam

ples

Blo

w C

ount

Wat

er L

evel

REMARKS

13/6

6/6

3/6

10/6

20/6

15/6

50/6

50/2

Page 59: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Field Engineer : J. Butler

Hole Diameter : NQ

Drilling Method : Wireline Core

Sampling Method : NQ Core

Date Drilled : 1/20/2016

Total Depth : 12 feet

Location : See Figure in Report

LOG OF BORING TC-10A

PN:54077GE

108 W Main Street, Room 302Montezuma County Commissioners

Combined Court BuildingMontezuma County

Depthin

feet

0

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

DESCRIPTION

NQ Core

CLAY, sandy, medium stiff, moist, red

CLAY, sandy, stiff, slightly moist, tan

WEATHERED FORMATIONAL MATERIAL at five and one-half (5.5) feet, Dakota Sandstone and Burro Canyon Formation, sandy claystone, hard, moist, tan

Sandstone, moderately fractured, tan to white, Dakota Sandstone and Burro Canyon Formation

Bottom of test core at twelve (12) feet

US

CS

CL

CL

GR

AP

HIC

Run

dep

th

Recovery and R.Q.D.

Top of First Run at five and one-half (5.5) feet

Recovery= 100% R.Q.D= 0%

Bottom of First Run at seven (7) feetTop of Second Run at seven (7) feet

Recovery= 100%R.Q.D.= 85%

Bottom of Second Run at twelve (12) feet

Page 60: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Field Engineer : J. Butler

Hole Diameter : 4" Solid

Drilling Method : Continuous Flight Auger

Sampling Method : Mod. California Sampler

Date Drilled : 01/07/2016

Total Depth (approx.) : 9.5 feet

Location : See Figure 1 in Report

LOG OF BORING TB - 11

PN:54077GE

109 W Main Street, Room 302Montezuma County Commissioners

Combined Court BuildingMontezuma County

Depthin

feet

0

1

2

3

4

5

6

7

8

9

10

DESCRIPTION

Sample Type

Mod. California Sampler

Bag Sample

Standard Split Spoon

Water Level

Water Level During Drilling

Water Level After Drilling

CLAY, sandy, soft, moist, red

CLAY and SAND, white chemical deposits, very stiff, very dense, slightly moist, red and tan

FORMATIONAL MATERIAL at seven (7) feet, sandstone, hard to very hard, slightly moist, tan, Dakota Sandstone and Burro Canyon Formation

Auger refusal at nine and one-half (9.5) feet

US

CS

CL

CL-SC

GR

AP

HIC

Sam

ples

Blo

w C

ount

Wat

er L

evel

REMARKS

15/6

40/6

Page 61: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Field Engineer : J. Butler

Hole Diameter : 4" Solid

Drilling Method : Continuous Flight Auger

Sampling Method : Mod. California Sampler

Date Drilled : 01/07/2016

Total Depth (approx.) : 6.5 feet

Location : See Figure 1 in Report

LOG OF BORING TB - 12

PN:54077GE

109 W Main Street, Room 302Montezuma County Commissioners

Combined Court BuildingMontezuma County

Depthin

feet

0

1

2

3

4

5

6

7

DESCRIPTION

Sample Type

Mod. California Sampler

Bag Sample

Standard Split Spoon

Water Level

Water Level During Drilling

Water Level After Drilling

CLAY, sandy, soft, moist, red

CLAY and SAND, some chemical deposits, very dense, slightly moist, red and tan

FORMATIONAL MATERIAL at four (4) feet, sandstone, hard to very hard, slightly moist, tan, Dakota Sandstone and Burro Canyon Formation

Auger refusal at six and one-half (6.5) feet

US

CS

CL

CL-SC

GR

AP

HIC

Sam

ples

Blo

w C

ount

Wat

er L

evel

REMARKS

Page 62: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Field Engineer : J. Butler

Hole Diameter : 4" Solid

Drilling Method : Continuous Flight Auger

Sampling Method : Mod. California Sampler

Date Drilled : 01/07/2016

Total Depth (approx.) : 7.5 feet

Location : See Figure 1 in Report

LOG OF BORING TB - 13

PN:54077GE

109 W Main Street, Room 302Montezuma County Commissioners

Combined Court BuildingMontezuma County

Depthin

feet

0

1

2

3

4

5

6

7

8

DESCRIPTION

Sample Type

Mod. California Sampler

Bag Sample

Standard Split Spoon

Water Level

Water Level During Drilling

Water Level After Drilling

CLAY, sandy, soft, very moist, red

CLAY and SAND, chemical deposits, stiff to very stiff, slightly moist, red and tan

FORMATIONAL MATERIAL at seven (7) feet, sandstone, very hard, slightly moist, tan, Dakota Sandstone and Burro Canyon Formation

Auger refusal at seven and one-half (7.5) feet

US

CS

CL

CL-SC

GR

AP

HIC

Sam

ples

Blo

w C

ount

13/6

13/6

50/1

Wat

er L

evel

REMARKS

Page 63: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Field Engineer : J. Butler

Hole Diameter : 4" Solid

Drilling Method : Continuous Flight Auger

Sampling Method : Mod. California Sampler

Date Drilled : 01/07/2016

Total Depth (approx.) : 9.5 feet

Location : See Figure 1 in Report

LOG OF BORING TB - 14

PN:54077GE

109 W Main Street, Room 302Montezuma County Commissioners

Combined Court BuildingMontezuma County

Depthin

feet

0

1

2

3

4

5

6

7

8

9

10

DESCRIPTION

Sample Type

Mod. California Sampler

Bag Sample

Standard Split Spoon

Water Level

Water Level During Drilling

Water Level After Drilling

CLAY, sandy, medium stiff, moist, red

CLAY and SAND, chemical deposits and cemented soils, stiff, dense, slightly moist, red and tan

Auger Refusal on FORMATIONAL MATERIAL at nine and one-half (9.5) feet, sandstone, very hard, slightly moist, tan, Dakota Sandstone and Burro Canyon Formation

US

CS

CL

CL-SC

GR

AP

HIC

Sam

ples

Blo

w C

ount

Wat

er L

evel

REMARKS

20/6

2/6

50/6

Page 64: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Field Engineer : J. Butler

Hole Diameter : 4" Solid

Drilling Method : Continuous Flight Auger

Sampling Method : Mod. California Sampler

Date Drilled : 01/07/2016

Total Depth (approx.) : 2.75 feet

Location : See Figure 1 in Report

LOG OF BORING TB - 15

PN:54077GE

109 W Main Street, Room 302Montezuma County Commissioners

Combined Court BuildingMontezuma County

Depthin

feet

0

1

2

3

DESCRIPTION

Sample Type

Mod. California Sampler

Bag Sample

Standard Split Spoon

Water Level

Water Level During Drilling

Water Level After Drilling

US

CS

GR

AP

HIC

Sam

ples

Blo

w C

ount

Wat

er L

evel

REMARKS

CLAY, sandy, soft, very moist, red

CLAY, sandy, stiff,slightly moist, red

WEATHERED FORMATION, sandstone with claystone, hard

Auger Refusal on FORMATIONAL MATERIAL at two and three-quarter (2.75) feet, sandstone, very hard, slightly moist, tan, Dakota Sandstone and Burro Canyon Formation

CL

CL

Page 65: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Field Engineer : J. Butler

Hole Diameter : 4" Solid

Drilling Method : Continuous Flight Auger

Sampling Method : Mod. California Sampler

Date Drilled : 01/07/2016

Total Depth (approx.) : 5.5 feet

Location : See Figure 1 in Report

LOG OF BORING TB - 16

PN:54077GE

109 W Main Street, Room 302Montezuma County Commissioners

Combined Court BuildingMontezuma County

Depthin

feet

0

1

2

3

4

5

6

DESCRIPTION

Sample Type

Mod. California Sampler

Bag Sample

Standard Split Spoon

Water Level

Water Level During Drilling

Water Level After Drilling

US

CS

GR

AP

HIC

Sam

ples

Blo

w C

ount

Wat

er L

evel

REMARKS

CLAY, sandy, soft, very moist, red

CLAY and SAND, some chemical deposits, stiff to very hard, slightly moist, red and tan

FORMATIONAL MATERIAL at four and one-half feet, sandstone, very hard, slightly moist, tan, Dakota Sandstone and Burro Canyon Formation

Auger Refusal at five and one-half (5.5) feet

CL

CL-SC

Page 66: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

LOG OF BORING TB - 17

PN:54077GE

109 W Main Street, Room 302Montezuma County Commissioners

Combined Court BuildingMontezuma County

Depthin

feet

0

1

2

3

4

5

6

7

8

DESCRIPTION

Sample Type

Mod. California Sampler

Bag Sample

Standard Split Spoon

Water Level

Water Level During Drilling

Water Level After Drilling

US

CS

GR

AP

HIC

Sam

ples

Blo

w C

ount

Wat

er L

evel

REMARKS

Field Engineer : J. Butler

Hole Diameter : 4" Solid

Drilling Method : Continuous Flight Auger

Sampling Method : Mod. California Sampler

Date Drilled : 01/07/2016

Total Depth (approx.) : 7 feet

Location : See Figure 1 in Report

CLAY, sandy, soft, very moist, red

CLAY and SAND, chemical deposits, stiff to very stiff, slightly moist, red and tan

WEATHERED FORMATION, sandstone, hard to very hard, tan

Auger Refusal at seven (7) feet

CL

CL-SC

Page 67: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PN: 54077GE

January 28, 2016

APPENDIX B

Laboratory Test Results

Page 68: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Tested By: Checked By:

4.1

(no specification provided)*

PL= LL= PI=

USCS (D 2487)= AASHTO (M 145)=

D90= D85= D60=D50= D30= D15=D10= Cu= Cc=

Remarks

CL - Lean clay with sand

.50.375#4

#10#40#200

10010010010010082

16 28 12

CL A-6(8)

0.1393 0.0925

1-8-16 1-21-16

J. Center

R. Barrett

Engineer Tech.

1-8-16

Montezuma County Commissioners

Montezuma County Combined Courts Building

54077GE

Material Description

Atterberg Limits (ASTM D 4318)

Classification

Coefficients

Date Received: Date Tested:

Tested By:

Checked By:

Title:

Date Sampled:Location: Test Boring 4Sample Number: 11702-D Depth: 0-3 1/2'

Client:

Project:

Project No: Figure

TEST RESULTS

Opening Percent Spec.* Pass?

Size Finer (Percent) (X=Fail)

PE

RC

EN

T F

INE

R

0

10

20

30

40

50

60

70

80

90

100

GRAIN SIZE - mm.

0.0010.010.1110100

% +3" % GravelCoarse

% Sand

Fine Silt

% Fines

Clay

0 0 0 18 82

6 in.

3 in.

2 in.

in.

1 in.

¾ in.

½ in.

3/8

in.

#4

#10

#20

#30

#40

#60

#100

#140

#200

Particle Size Distribution Report

Page 69: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Tested By: Checked By:

4.2

(no specification provided)*

PL= LL= PI=

USCS (D 2487)= AASHTO (M 145)=

D90= D85= D60=D50= D30= D15=D10= Cu= Cc=

Remarks

CL Sandy lean clay

.50.375#4

#10#40#200

1001001001009967

14 27 13

CL A-6(6)

0.2145 0.1660

1-8-16 1-12-16

J. Townsend

R. Barrett

Engineer Tech.

1-8-16

Montezuma County Commissioners

Montezuma County Combined Courts Building

54077GE

Material Description

Atterberg Limits (ASTM D 4318)

Classification

Coefficients

Date Received: Date Tested:

Tested By:

Checked By:

Title:

Date Sampled:Location: Test Boring 6Sample Number: 11702-EE Depth: 4 1/2'- 9 1/2'

Client:

Project:

Project No: Figure

TEST RESULTS

Opening Percent Spec.* Pass?

Size Finer (Percent) (X=Fail)

PE

RC

EN

T F

INE

R

0

10

20

30

40

50

60

70

80

90

100

GRAIN SIZE - mm.

0.0010.010.1110100

% +3" % GravelCoarse

% Sand

Fine Silt

% Fines

Clay

0 0 1 32 67

6 in.

3 in.

2 in.

in.

1 in.

¾ in.

½ in.

3/8

in.

#4

#10

#20

#30

#40

#60

#100

#140

#200

Particle Size Distribution Report

Page 70: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Tested By: Checked By:

4.3

(no specification provided)*

PL= LL= PI=

USCS (D 2487)= AASHTO (M 145)=

D90= D85= D60=D50= D30= D15=D10= Cu= Cc=

Remarks

CL - Sandy lean clay

.50.375#4

#10#40#200

1001001001009963

14 30 16

CL A-6(7)

0.2259 0.1780

1-8-16 1-14-16

J. Center

R. Barrett

Engineer Tech.

1-8-16

Montezuma County Commissioners

Montezuma County Combined Courts Building

54077GE

Material Description

Atterberg Limits (ASTM D 4318)

Classification

Coefficients

Date Received: Date Tested:

Tested By:

Checked By:

Title:

Date Sampled:Location: Test Boring 7Sample Number: 11702-II Depth: 0-3'

Client:

Project:

Project No: Figure

TEST RESULTS

Opening Percent Spec.* Pass?

Size Finer (Percent) (X=Fail)

PE

RC

EN

T F

INE

R

0

10

20

30

40

50

60

70

80

90

100

GRAIN SIZE - mm.

0.0010.010.1110100

% +3" % GravelCoarse

% Sand

Fine Silt

% Fines

Clay

0 0 1 36 63

6 in.

3 in.

2 in.

in.

1 in.

¾ in.

½ in.

3/8

in.

#4

#10

#20

#30

#40

#60

#100

#140

#200

Particle Size Distribution Report

Page 71: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Tested By: Checked By:

4.4

(no specification provided)*

PL= LL= PI=

USCS (D 2487)= AASHTO (M 145)=

D90= D85= D60=D50= D30= D15=D10= Cu= Cc=

Remarks

CL - Lean clay with sand

.50.375#4

#10#40#200

1001001001009974

16 32 16

CL A-6(10)

0.1897 0.1392

1-8-16 1-14-16

J. Center

R. Barrett

Engineer Tech.

1-8-16

Montezuma County Commissioners

Montezuma County Combined Courts Building

54077GE

Material Description

Atterberg Limits (ASTM D 4318)

Classification

Coefficients

Date Received: Date Tested:

Tested By:

Checked By:

Title:

Date Sampled:Location: Test Boring 8Sample Number: 11702-O Depth: 0-3'

Client:

Project:

Project No: Figure

TEST RESULTS

Opening Percent Spec.* Pass?

Size Finer (Percent) (X=Fail)

PE

RC

EN

T F

INE

R

0

10

20

30

40

50

60

70

80

90

100

GRAIN SIZE - mm.

0.0010.010.1110100

% +3" % GravelCoarse

% Sand

Fine Silt

% Fines

Clay

0 0 1 25 74

6 in.

3 in.

2 in.

in.

1 in.

¾ in.

½ in.

3/8

in.

#4

#10

#20

#30

#40

#60

#100

#140

#200

Particle Size Distribution Report

Page 72: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Tested By: Checked By:

4.5

(no specification provided)*

PL= LL= PI=

USCS (D 2487)= AASHTO (M 145)=

D90= D85= D60=D50= D30= D15=D10= Cu= Cc=

Remarks

CL - Sandy lean clay

.50.375#4

#10#40#200

10010010010010052

14 23 9

CL A-4(2)

0.2499 0.2054 0.0931

1-8-16 1-14-16

J. Center

R. Barrett

Engineer Tech.

1-8-16

Montezuma County Commissioners

Montezuma County Combined Courts Building

54077GE

Material Description

Atterberg Limits (ASTM D 4318)

Classification

Coefficients

Date Received: Date Tested:

Tested By:

Checked By:

Title:

Date Sampled:Location: Test Boring 14Sample Number: 11702-U Depth: 5'-9'

Client:

Project:

Project No: Figure

TEST RESULTS

Opening Percent Spec.* Pass?

Size Finer (Percent) (X=Fail)

PE

RC

EN

T F

INE

R

0

10

20

30

40

50

60

70

80

90

100

GRAIN SIZE - mm.

0.0010.010.1110100

% +3" % GravelCoarse

% Sand

Fine Silt

% Fines

Clay

0 0 0 48 52

6 in.

3 in.

2 in.

in.

1 in.

¾ in.

½ in.

3/8

in.

#4

#10

#20

#30

#40

#60

#100

#140

#200

Particle Size Distribution Report

Page 73: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Tested By: Checked By:

4.6

(no specification provided)*

PL= LL= PI=

USCS (D 2487)= AASHTO (M 145)=

D90= D85= D60=D50= D30= D15=D10= Cu= Cc=

Remarks

CL - Sandy lean clay

.50.375#4

#10#40#200

1001001001009960

15 26 11

CL A-6(4)

0.2409 0.1915 0.0754

1-8-16 1-13-16

J. Townsend

R. Barrett

Engineer Tech.

1-8-16

Montezuma County Commissioners

Montezuma County Combined Courts Building

54077GE

Material Description

Atterberg Limits (ASTM D 4318)

Classification

Coefficients

Date Received: Date Tested:

Tested By:

Checked By:

Title:

Date Sampled:Location: BulkSample Number: 11702-X

Client:

Project:

Project No: Figure

TEST RESULTS

Opening Percent Spec.* Pass?

Size Finer (Percent) (X=Fail)

PE

RC

EN

T F

INE

R

0

10

20

30

40

50

60

70

80

90

100

GRAIN SIZE - mm.

0.0010.010.1110100

% +3" % GravelCoarse

% Sand

Fine Silt

% Fines

Clay

0 0 1 39 60

6 in.

3 in.

2 in.

in.

1 in.

¾ in.

½ in.

3/8

in.

#4

#10

#20

#30

#40

#60

#100

#140

#200

Particle Size Distribution Report

Page 74: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Sample Source

Soil Description

Swell Pressure (P.S.F)

Initial Final

Moisture Content (%) 3.3 18.4

Dry Density (P.C.F) 106.3 115.0

Height (in.) 1.000 0.950

Diameter (in.) 1.94 1.94

Project Number

Date

Figure

SWELL - CONSOLIDATION TEST

SUMMARY OF TEST RESULTS

TB-3 at 1.5 feet

4.7

Sandy Clay (CL)

0

54077GE

January 12, 2016

-6

-5

-4

-3

-2

-1

0

10 100 1000 10000

Co

ns

oli

da

tio

n %

Sw

ell

Pressure (Pounds per Square Foot)

Swell/Consolidation due to wetting under constant load

Water added tosample

Page 75: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Sample Source

Soil Description

Swell Pressure (P.S.F)

Initial Final

Moisture Content (%) 7.6 13.3

Dry Density (P.C.F) 128.6 128.3

Height (in.) 1.000 0.979

Diameter (in.) 1.94 1.94

Project Number

Date

Figure

SWELL - CONSOLIDATION TEST

SUMMARY OF TEST RESULTS

TB-4 at 13.5 feet

4.8

Claystone

900

54077GE

January 11, 2016

-2.5

-2

-1.5

-1

-0.5

0

0.5

1

1.5

10 100 1000 10000

Co

ns

oli

da

tio

n %

Sw

ell

Pressure (Pounds per Square Foot)

Swell/Consolidation due to wetting under constant load

Water added tosample

Page 76: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Sample Source

Soil Description

Swell Pressure (P.S.F)

Initial Final

Moisture Content (%) 4.8 16.2

Dry Density (P.C.F) 111.1 120.7

Height (in.) 1.000 0.910

Diameter (in.) 1.94 1.94

Project Number

Date

Figure

SWELL - CONSOLIDATION TEST

SUMMARY OF TEST RESULTS

TB-5 at 2 feet

4.9

Sandy Clay

0

54077GE

January 14, 2016

-10

-9

-8

-7

-6

-5

-4

-3

-2

-1

0

10 100 1000 10000

Co

ns

oli

da

tio

n %

Sw

ell

Pressure (Pounds per Square Foot)

Swell/Consolidation due to wetting under constant load

Water added tosample

Page 77: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Sample Source

Soil Description

Swell Pressure (P.S.F)

Initial Final

Moisture Content (%) 3.6 17.3

Dry Density (P.C.F) 111.4 121.6

Height (in.) 1.000 0.910

Diameter (in.) 1.94 1.94

Project Number

Date

Figure 4.10

SWELL - CONSOLIDATION TEST

SUMMARY OF TEST RESULTS

TB-6 at 4.5 feet

Sandy Clay

290

54077GE

January 12, 2016

-10

-9

-8

-7

-6

-5

-4

-3

-2

-1

0

10 100 1000 10000

Co

ns

oli

da

tio

n %

Sw

ell

Pressure (Pounds per Square Foot)

Swell/Consolidation due to wetting under constant load

Water added tosample

Page 78: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Sample Source

Soil Description

Swell Pressure (P.S.F)

Initial Final

Moisture Content (%) 2.5 16.3

Dry Density (P.C.F) 115.4 120.3

Height (in.) 1.000 0.938

Diameter (in.) 1.94 1.94

Project Number

Date

Figure 4.11

SWELL - CONSOLIDATION TEST

SUMMARY OF TEST RESULTS

TB-8 at 3.5 feet

Sandy Clay

300

54077GE

January 12, 2016

-7

-6

-5

-4

-3

-2

-1

0

10 100 1000 10000

Co

ns

oli

da

tio

n %

Sw

ell

Pressure (Pounds per Square Foot)

Swell/Consolidation due to wetting under constant load

Water added tosample

Page 79: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Sample Source

Soil Description

Swell Pressure (P.S.F)

Initial Final

Moisture Content (%) 7.9 16.3

Dry Density (P.C.F) 118.0 121.0

Height (in.) 1.000 0.962

Diameter (in.) 1.94 1.94

Project Number

Date

Figure 4.12

SWELL - CONSOLIDATION TEST

SUMMARY OF TEST RESULTS

TB-11 at 1 foot

Sandy Clay

950

54077GE

January 12, 2016

-4.5

-4

-3.5

-3

-2.5

-2

-1.5

-1

-0.5

0

0.5

1

10 100 1000 10000

Co

ns

oli

da

tio

n %

Sw

ell

Pressure (Pounds per Square Foot)

Swell/Consolidation due to wetting under constant load

Water added tosample

Page 80: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Direct Shear Test Results ASTM D3080-90

Project: Montezuma County Courts Visual Soil Description: Sandy Clay

Type of Specimen: Remolded

Laboratory Number: 11702AA Diameter 1.946 in.

Date: 1/15/2016 Thickness 2.0 in

Project Technician: RB Sample Source: TB-5: 3'-8'

Summary of Sample Data:Initial Moisture Content (%) 6.8

Intial Dry Density (P.C.F) 124.3

Final Moisture Content (%) 12.9

Final Dry Density (P.C.F) 124.3

Residual Direct Shear Test Results:Normal Stress (P.S.I) 2.04 4.07 8.15

Max. Shear Stress (P.S.I) 1.73 2.81 5.84

ESTIMATED STRENGTH PARAMETERS

Angle of Internal Friction, phi 32

Cohesion, P.S.F. 50

Figure 4.13

Project Number: 54077GE

0

2

4

6

8

0 2 4 6 8 10

Sh

ear

Str

ess, P

.S.I

.

Normal Stress, P.S.I.

0

1

2

3

4

5

6

7

8

9

10

0.00 0.05 0.10 0.15 0.20

Sh

ear

Ste

ss, P

.S.I

.

Horizontal Deformation, inches

Page 81: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

Project No. :

Figure: 4.14

Date:

DR

Y D

EN

SIT

Y (PC

F)

MOISTURE CONTENT (%)

0 5 10 15 20 25 30 3580

85

90

95

100

105

110

115

120

130

135

140

145

2.6

2.7

2.8Zero Air Voids forSpecific Gravity

Project:

Sample Source:

Sample Description:

Test Method:

Maximum Dry Density:

Optimum Moisture Content:

Laboratory Number:

Montezuma County Combined Courts Facility

Bulk

ASTM D1557 Method A

124.1 pcf

11.0%

11702-X

54077GE

1-8-16

125

Sandy Clay (CL)

Page 82: GEOTECHNICAL ENGINEERING RECOMMENDATIONS

PROJ NO: 54077GE DATE: 1/8/2016

TECHNICIAN: J.Townsend

LAB NO: 17702-X

1557A Condition: soaked Sample Source: Bulk Subgrade

124.1 PCF Surcharge: 15 Lbs

11.0%

Relative

Compaction Swell (%)

104.4 10.9 84 102.0 20.8 1.7 1.5

110.0 10.9 89 107.4 18.7 1.8 5.4

116.3 10.9 94 112.5 17.5 1.6 9.3

Figure:

Dry

Density

(PCF)

Moisture

Content (%)

Dry Density

(PCF)

Moisture

Content of

Top One (1)

Inch (%)

Pre-Soak After 72 hour Soak

PROJECT NAME: Montezuma Co. Combined Courts Facility

4.15

Optimum Moisure

Content*:

California Bearing Ratio Test Results

ASTM D1883

Proctor Method*:

Max Dry Density*:

CBR (0.100"

penetration)

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

9.0

10.0

102.0 104.0 106.0 108.0 110.0 112.0 114.0 116.0 118.0

Cali

forn

io B

eari

ng

Rati

o (

CB

R)

Dry Density (PCF)