38
FibeAir1500/1528 Validation & Acceptance TEST PLAN General FibeAir1500/1528 Test Plan Rev2.0

General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Embed Size (px)

DESCRIPTION

usefull for testing

Citation preview

Page 1: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

FibeAir1500/1528

Validation & Acceptance

TEST PLAN

General FibeAir1500/1528 Test Plan Rev2.0

Page 2: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

0.0 Table of Content TITLE PAGE

0.0 Table of Content 2

1.0 Purpose 4

2.0 General Test Summary 4

3.0 FibeAir Overview 4

4.0 FibeAir 1+0 Validation and Acceptance Tests 5 4.1 Test Set-Up 5 4.2 RF Tests 5 4.2.1 Test Set-Up 5 4.2.2 Transmit Power Test 6 4.2.3 Receiver Sensitivity and Overload Test 7 4.2.4 Transmit Frequency Accuracy 8 4.2.5 Automatic Transmit Power Control (ATPC) 8 4.3 SDH Tests 10 4.3.1 Synchronization 10 4.3.2 STM-1 Main Channel BER Test 11 4.3.3 E1 Wayside Channel BER Test 11 4.3.4 10BaseT Wayside Channel Test 12 4.3.5 RS232 User Channel Test 13 4.3.6 Engineering Order-Wire Test (EOW) 14 4.3.7 SDH Fault Management 15 4.3.8 Jitter Test 16 4.4 ATM Tests 17 4.4.1 STM-1 BER Test 17 4.4.2 Cell Loss Ratio Measurement (CLR) 18 4.5 Network Management Tests 19 4.5.1 General 19 4.5.2 Ethernet and Serial Connection 19 4.5.3 Inventory data 19 4.5.4 Frequency Control 20 4.5.5 Radio Parameters Control 20 4.5.6 Alarms Management 21 4.5.7 Performance Monitoring 21 4.5.8 Loopbacks Operation 22 4.5.9 External Alarm Operation 23 4.5.10 Software Reset 24 4.5.11 Software Download 24 4.6 2 x Fast Ethernet Tests 25 4.6.1 General 25 4.6.2 Fast Ethernet Traffic Test 25 4.6.3 Throughput Measurement 26 4.6.4 Dynamic Band-Width Allocation Tests 28 4.7 3 x E3 Tests 30

General FibeAir1500/1528 V&A Test Plan Page 2 of 38

Page 3: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

4.8 Fast Ethernet + E3 Tests 32

5.0 FibeAir 1+1 Validation and Acceptance Tests 34 5.1 General 34 5.2 Test Set-Up 34 5.3 STM-1 BER Test 35 5.4 Protection Switching Tests 36 5.5 1+1 Management Tests 37

General FibeAir1500/1528 V&A Test Plan Page 3 of 38

Page 4: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

1.0 Purpose The following document is Ceragon networks’ Validation and Acceptance Test Plan for the evaluation tests of Ceragon Networks FibeAir1500/1528 SDH Microwave link and its versatile network solutions. This document describes the proposed test procedures for the FibeAir1500/1528 product in 1+0 and 1+1 configurations with the different interfaces configurations. The document will include descriptions of the set-ups and procedures required to verify the products functionality according to its specs and to verify interoperability with other transmission equipment. 2.0 General Test Summary Tests described in this section will be divided to 2 categories:

1. FibeAir1500/1528 1+0 Tests RF tests, SDH tests, Network management tests, Fast Ethernet tests and E3 tests

2. FibeAir1500/1528 1+1 Tests 3.0 FibeAir Overview Providing high-capacity connectivity from 45 to 622 Mbps, Ceragon's FibeAir™ product family offers service providers the capacity and reliability of fiber without the high cost and time required to lay lines. Ceragon's FibeAir systems operate across multiple frequencies from 7.5 to 38 GHz while supporting IP, SONET/SDH and ATM network protocols and complying with North American and international standards. The IDU provides interfaces for 155 Mb/s SONET/SDH/ATM main channel, 2Mb/s Wayside channel, 64Kb/s User channel and 64 Kb/s Order Wire channel. The 155 Mb/s channel can be replaced by 2 x 100 BaseT (Fast Ethernet), 3 x E3/DS3 or a combination of 1 x 100 BaseT and 1 x E3/DS3 interfaces. The IDU multiplexes the different interfaces signals into 155 Mb/s SDH signal, transmitted over the air. The IDU modulates the 155 Mb/s payload, converts it to 350 MHz IF signal and transmits it to the ODU. In the opposite direction, IDU receives 140 MHz IF signal from the ODU, demodulates it and transmits it to the line output.

General FibeAir1500/1528 V&A Test Plan Page 4 of 38

Page 5: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

4.0 FibeAir 1+0 Validation and Acceptance Tests 4.1 Test Set-Up A complete FibeAir1500/1528 radio link, including 2 IDUs and 2 ODUs connected using a Test-Set will be used for the V&A tests: RF tests, SDH tests, and IP tests. IDUs shall be configured with STM-1 interfaces, 100BaseT interfaces or E3 interfaces according to the functionality tested (SDH/ATM, IP or TDM). Specific test set-up to be used is specified in each one of the tests. Specific test equipment required is specified in each one of the tests. Lab test set-up requires:

(a) FibeAir1500/1528 radio link. (b) –48 VDc@3Amp power supply for each terminal (IDU+ODU). (c) Coax cables between IDUs and ODUs. (d) Test-Set for the tested frequency to connect the 2 ODUs.

The Test-Set includes ODU’s plate adapter, wave-guides transitions and attenuators.

(e) PC to install the CeraView for the link’s management.

Test equipment to be used: (a) Power-meter (b) Spectrum Analyzer (c) SDH Analyzer (for BER measurement) (d) Packet Analyzer for IP traffic measurements

4.2 RF Tests 4.2.1 Test Set-Up Test Set-Up A will be used for all RF tests, described in this section. Test Set-Up A:

General FibeAir1500/1528 V&A Test Plan Page 5 of 38

Page 6: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

ODU ODU Coax Cable

Coupler

VariableAttenuatorWave-Guide

1+0 Test-Set

Fiber

SDHAnalyzer

STM-1

PowerMeter

NMS

EthernetCable

ETH

Tx Rx

SpectrumAnalyzer

4.2.2 Transmit Power Test Test Purpose To test the ODU’s transmit power accuracy compared to the specified TX power in the management. Required test-equipment

(a) Power-meter

Test Procedure (a) Connect the ODU to the IDU and start the IDU power. (b) Connect the ODU to a Power-meter using the test-plate adapter. (c) Calibrate the Power-Meter for the attenuation of the test-plate and cable

that are used. (d) Set the TX power of the ODU to the maximum (+20dBm) using the Link

Manager management. (e) Measure the TX power with the Power-meter. (f) Compare the measured TX power to the specified TX power in the

management. (g) Repeat steps (e) and (f) for Tx power as specified in the table below. (h) Repeat steps (e) and (f) for every TX power value (until the minimum is

reached). Results Summary

Step Tx Power (management)

Tx Power (Power Meter reading)

1 +20 dBm 2 +10 dBm 3 0 dBm 4 -10 dBm

General FibeAir1500/1528 V&A Test Plan Page 6 of 38

Page 7: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

4.2.3 Receiver Sensitivity and Overload Test Test Purpose To measure the radio link’s receiver sensitivity and overload threshold for certain BER level. Required test-equipment

(a) Power-meter (b) SDH Analyzer (for BER measurement)

Test Procedure (a) Use a calibrated Test-Set that its attenuation was measured and known.

Using coupler, connect Power-Meter. (b) Set the ODU for the minimum TX power (-10dBm). (c) Set the RSL to –60dBm using the attenuators. (d) Connect SDH Analyzer to the 155 Mbps channel in one direction (Tx

fiber to one IDU and Rx fiber to the second IDU). Set the SDH Analyzer to measure Bit Error Rate. Verify BER better than 10E-11.

(e) Reduce the received signal level of the tested ODU in 1 dB steps using the variable attenuator.

(f) Monitor the SDH Analyzer BER measurement until BER=10E-6. (g) Verify that the RSL value is better than the stated sensitivity threshold of

–65dBm. (h) Set the ODU for the max TX power (+15dBm). (i) Set the RSL to –25dBm using the attenuators. (j) Connect SDH Analyzer to the 155 Mbps channel in one direction. Set

the SDH Analyzer to measure Bit Error Rate. Verify BER better than 10E-11.

(k) Increase the received signal level of the tested ODU in 1 dB steps using the variable attenuator.

(l) Monitor the SDH Analyzer BER measurement until BER=10E-6. (m) Verify that the RSL value is better than the stated overload

threshold of -20dBm.

Results Summary Step Test Expected Results

Test Results

1 Receiver Sensitivity BER=10E-3 2 Receiver Sensitivity BER=10E-6 3 Receiver Overload BER=10E-3 4 Receiver Overload BER=10E-6

General FibeAir1500/1528 V&A Test Plan Page 7 of 38

Page 8: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

4.2.4 Transmit Frequency Accuracy Test Purpose To tests the ODU’s transmit frequency accuracy compared to the specified center-frequency of the channel tested. Required test-equipment

(a) Frequency counter.

Test Procedure (a) Connect the ODU to the IDU and start the IDU power. (b) Connect the ODU to a frequency counter using the test-plate adapter. (c) Set the ODU to Transmit in CW mode (use the Ceragon CW software

for this purpose). (d) Measure the transmitted frequency for at least 3 channels of the ODU

using the Frequency Counter (use the management to change the frequency).

(e) Compare the measured frequency to the specified frequency in the management and verify that the frequency accuracy is +/-5 ppm.

Results Summary Step Transmit Frequency

(management)

Transmit Frequency (Measured)

Accuracy (ppm)

1 2 3 4.2.5 Automatic Transmit Power Control (ATPC) Test Purpose To test the ATPC functionality of the radio link and to verify proper and error-free transmission of the STM-1 signal during ATPC operation. Also will be tested the ATPC upper-limit functionality that allows the user to define and limit the maximum Tx power to be transmitted. Required test-equipment

(a) SDH Analyzer (for BER measurement) Test Procedure

(a) Set up a link using the Test-Set. Set the Tx power to maximum (+15dBm) and verify that ATPC is disabled using the Link Manager management.

(b) Using the attenuators set the RSL to -30dBm. (c) Connect SDH analyzer to one IDU. Loop the Line module in the second

General FibeAir1500/1528 V&A Test Plan Page 8 of 38

Page 9: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

IDU. (d) Set the SDH Analyzer to transmission of STM-1, VC-4 bulk with 2^23

PRBS sequence (transmitter coupled to receiver). (e) Verify that there are no alarms on the SDH Analyzer and on the Link

Manager management. (f) Clear all alarm log files on the Link Manager management. (g) Run BER test on the SDH Analyzer. Verify that there are no alarms or

errors of any kind. (h) Activate ATPC and set the Reference Level to –45dBm. (i) Verify that the Received RSL has changed to –45dBm and that the

Monitored Tx Level have reduced in 20dB (~0dBm). (j) Add 15dB attenuation to the link using the Variable Attenuator and verify

that the RSL is maintained at –45dBm and the Monitored Tx Level has increased in 15dB.

(k) Decrease 25dB attenuation from the link using the Variable Attenuator and verify that the RSL is maintained at –45dBm and the Monitored Tx Level has decreased in 25dB.

(l) Verify that the SDH Analyzer did not detect any errors on the STM-1 signal during the ATPC tests.

(m) ATPC Upper-Limit Test: Disabled ATPC using the Link Manager management and set the Tx power to +5dBm at both ends of the link.

(n) Using the attenuators set the RSL to -30dBm. (o) Activate ATPC and set the Reference Level to –45dBm. (p) Verify that the Received RSL has changed to –45dBm and that the

Monitored Tx Level have reduced in 15dB (~-10dBm). (q) Add 25dB attenuation to the link using the Variable Attenuator and verify

that the Monitored Tx Level does not exceed the pre-defined Upper-Limit (+5dBm).

(r) Verify that the SDH Analyzer did not detect any errors on the STM-1 signal during the ATPC tests.

Results Summary Step ATPC

Expected Results Test Results

1 Full range ATPC Tx power changes from minimum (–10dBm) to maximum (+15dBm)

2 SDH errors No errors 3 Upper-Limit

ATPC Tx power changes from minimum (–10dBm) to defined limit (+5dBm)

4 SDH errors No errors

General FibeAir1500/1528 V&A Test Plan Page 9 of 38

Page 10: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

4.3 SDH Tests The test may be carried out in three interfaces combinations:

(a) Optical interfaces on all four IDUs. (b) Electrical interfaces on all four IDUs. (c) Optical interfaces on two IDUs of one end of the 1+1 link and Electrical

interfaces on the other end of the link. 4.3.1 Synchronization Test Purpose To tests that the traffic is not affected by a frequency-offset of +/- 20 ppm on the incoming STM-1 signal. Test Set-Up Test Set-Up B will be used for this test. Test Set-Up B:

ODU ODU Coax Cable

Coupler

VariableAttenuatorWave-Guide

1+0 Test-Set

PhysicalLoop

SDHAnalyzer

STM-1

NMS

EthernetCable

ETH

Required test-equipment

(a) SDH Analyzer (for BER measurement)

Test Procedure (a) Set up a link using the Test-Set. Set the RSL to ~-40dBm. (b) Change the frequency-offset synch according to the table and verify that

no errors are detected by the SDH Analyser on the STM-1 payload. Results Summary Step Frequency

Offset Expected Results

Test Results

1 0 ppm No errors 2 -20 ppm No errors 3 +20 ppm No errors

General FibeAir1500/1528 V&A Test Plan Page 10 of 38

Page 11: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

4.3.2 STM-1 Main Channel BER Test Test Purpose To test and verify proper and error-free operation of the 155 Mbps channel (main channel). Test Set-Up Test Set-Up B will be used for this test. Required test-equipment

(a) SDH Analyzer (for BER measurement)

Test Procedure (a) Set up a link using the Test-Set. Set the RSL to ~-40dBm. (b) Connect SDH analyzer to one IDU. Loop the Line module in the second

IDU. (c) Set the SDH Analyzer to transmission of STM-1, VC-4 bulk with 2^23

PRBS sequence (transmitter coupled to receiver). (d) Verify that there are no alarms on the SDH Analyzer and on the Link

Manager management. (e) Clear all alarm log files on the Link Manager management. (f) Run BER test on the SDH Analyzer. Verify that there are no alarms and

no errors of any kind. (g) Allow this SDH test to run at least 60 minutes. (h) Verify that no errors were detected by the SDH analyzer. (i) Verify that there were no alarms on the management.

Results Summary

BER Test Duration

Test Expected Results

Test Results

SDH Alarms No alarms Errors Detected No errors BER No errors detected /

10E-13

Management Alarms

No alarms

4.3.3 E1 Wayside Channel BER Test Test Purpose To test and verify proper and error-free operation of the 2 Mbps E1 channel (Wayside Channel).

General FibeAir1500/1528 V&A Test Plan Page 11 of 38

Page 12: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

Test Set-Up Test Set-Up B will be used for this test. Required test-equipment

(a) SDH Analyzer (for BER measurement)

Test Procedure (a) Set up a link using the Test-Set. Set the RSL to ~-40dBm. (b) Activate the Wayside Channel using the Link Manager management. (c) Configure the IDUs with E1 interfaces as the Wayside Channels. (d) Connect SDH analyzer to the E1 Wayside Channel of one IDU. Loop

the Wayside Channel in the second IDU. (e) Set the SDH Analyzer to transmission of E1 2 Mbps signal (transmitter

coupled to receiver). (f) Verify that there are no alarms on the SDH Analyzer. (g) Clear all alarm log files on the Link Manager management. (h) Run BER test on the SDH Analyzer. Verify that there are no alarms and

no errors of any kind. (i) Allow this SDH test to run at least 60 minutes. (j) Verify that no errors were detected by the SDH analyzer. (k) Verify that there were no alarms on the management. (l) Disable the Wayside Channel and verify that no traffic can run over the

link. Results Summary

BER Test Duration

Test Expected Results

Test Results

SDH Alarms No alarms Errors Detected No errors BER No errors detected /

10E-13

Management Alarms

No alarms

4.3.4 10BaseT Wayside Channel Test Test Purpose To test and verify functionality of the 2 Mbps 10BaseT channel (Wayside Channel). Test Set-Up Test Set-Up B will be used for this test.

General FibeAir1500/1528 V&A Test Plan Page 12 of 38

Page 13: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

Required test-equipment (a) PC

Test Procedure (a) Set up a link using the Test-Set. Set the RSL to ~-40dBm. (b) Configure the IDUs with Ethernet Bridge 10BaseT interfaces as the

Wayside Channels. (c) Activate the Wayside Channel using the Link Manager management. (d) Connect the PC to one of the 10BaseT Wayside Channel on one end of

the link. (e) Connect the second IDU’s wayside channel to the Ethernet

management port using cross-cable. (f) Send “Ping” command from one PC to the IDU on the other end of the

link and verify that reply is received. (g) Launch Link Manager software and verify you can manage the IDU. (h) Disable the Wayside Channel and verify that no traffic can run over the

link and no reply is received from the remote IDU.

Results Summary Step Wayside Channel

Mode Expected Results

Test Results

1 Activated “Ping” Received √ 2 Activated Management of remote IDU

is possible √

3 Disabled “Ping” is not received √ 4.3.5 RS232 User Channel Test Test Purpose To test and verify functionality and performance of the 64 Kbps User Channel. Test Set-Up Test Set-Up B will be used for this test. Required test-equipment

(a) RS232 analyzer

Test Procedure (a) Set up a link using the Test-Set. Set the RSL to ~-40dBm. (b) Activate the User Channel using the Link Manager management. (c) Connect the RS232 Analyzer to the user-channel port on one end the

link. (d) Loop the remote IDU using physical loop.

General FibeAir1500/1528 V&A Test Plan Page 13 of 38

Page 14: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

(e) Run BER test and verify full throughput and no errors are detected. (f) Disable the User Channel and verify that no traffic can run over the link.

Results Summary Step User Channel

Mode Expected Results

Test Results

1 Activated No errors detected, 100% throughput

2 Disabled No traffic √ 4.3.6 Engineering Order-Wire Test (EOW) Test Purpose To test the operation of the Engineering Order Wire. Test Set-Up Test Set-Up B will be used for this test. Test Procedure

(a) Set up a link using the Test-Set. Set the RSL to ~-40dBm. (b) Using the Link Manager management, verify that the EOW is enabled. (c) Press the buzzer on one IDU. Verify that the Buzzer is heard from the

opposite IDU. (d) Press the buzzer on the second IDU. Verify that the Buzzer is heard

from the opposite IDU. (e) Connect headset to each IDU. Verify proper communication between

the two IDUs. (f) Disable EOW operation. (g) Press the buzzer on one IDU. Verify that the Buzzer is not heard from

the opposite IDU. Results Summary Step EOW Mode Expected Results

Test Results

1 Activated Buzzer heard on both directions

Proper communication over the EOW

2 Disabled Buzzer not heard No communication over

the EOW

General FibeAir1500/1528 V&A Test Plan Page 14 of 38

Page 15: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

4.3.7 SDH Fault Management Test Purpose To test and verify that the fault and alarms reporting and resulting actions are generated and transmitted through the radio. Test Set-Up Test Set-Up B will be used for this test. Required test-equipment

(a) SDH Analyzer (for BER measurement)

Test Procedure (a) Set up a link using the Test-Set. Set the RSL to ~-40dBm. (b) Connect SDH analyzer to one IDU. Loop the Line module in the second

IDU. (c) Set the SDH Analyzer to transmission of STM-1, VC-4 bulk with 2^23

PRBS sequence (transmitter coupled to receiver). (d) Verify that there are no alarms on the SDH Analyzer and on the Link

Manager management. (e) Clear all alarm log files on the Link Manager management. (f) Disconnect the transmitter fiber from the SDH analyzer to the IDU. (g) Verify that the “Loss Of Signal” alarm is reported on the LED panel and

on the Link Manager management. Verify that the alarm is recorded on the Alarm Log of the Link Manager management.

(h) Verify that the SDH analyzer reports MS- AIS. Re-connect the fiber. (i) Using the Loopbacks function of the Link Manager management force

AIS to Line and then to Remote. Verify that the SDH analyzer reports the AIS.

(j) Using the Loopbacks function of the Link Manager management force RDI to Line and then to Remote. Verify that the SDH analyzer reports the RDI.

(k) Insert B1 errors from the SDH analyzer at 10E-5 level. Verify that the IDU generates “Line Signal Degrade” alarm. Verify that the radio corrects the B1 errors and no errors are detected on the SDH analyzer.

Results Summary Step Test Expected Results

Test Results

1 Disconnect Tx fiber AIS reported by SDH Analyzer

“Loss of Signal” alarm on the Link Manager

“Loss of Signal” alarm on the Alarm Log

2 Force AIS to Line AIS reported by SDH Analyzer

General FibeAir1500/1528 V&A Test Plan Page 15 of 38

Page 16: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

3 Force AIS to Remote AIS reported by SDH Analyzer

4 Force RDI to Line RDI reported by SDH Analyzer

5 Force RDI to Remote RDI reported by SDH Analyzer

6 Insert B1 errors “Line Signal Degrade” alarm on the Link Manager

No errors on SDH Analyzer

4.3.8 Jitter Test Test Purpose To test and measure Intrinsic Jitter, Jitter Tolerance and Jitter Transfer of the FibeAir1500/1528 radio link. Tests will be performed according G.825 and G.958. Test Set-Up Test Set-Up A will be used for this test. Required test-equipment

(a) SDH Analyzer (with Jitter measurement)

Test Procedure (a) Set up a link using the Test-Set. Set the RSL to ~-40dBm. (b) Connect SDH Analyzer to the 155 Mbps channel in one direction (Tx

fiber to one IDU and Rx fiber to the second IDU). (c) Set the SDH analyzer to transmission of STM-1, SDH payload

(transmitter coupled to receiver) in Jitter measurement mode. (d) Intrinsic Jitter: Insert clean STM-1 signal and measure the Intrinsic Jitter

generated by the radio link. (e) Jitter Tolerance: Insert Jitter to the STM-1 input of the IDU and gradually

increase its value until errors detected by the SDH Analyzer. (f) Jitter Transfer: Insert Jitter to the STM-1 input of the IDU and measure

the attenuation of the Jitter on the STM-1 output. Results Summary Step Test Expected Results

Test Results

1 Intrinsic Jitter Less than 0.15UI (pp) Acc. G.825

2 Jitter Tolerance Mask acc.G.958 3 Jitter Transfer Mask acc.G.958

General FibeAir1500/1528 V&A Test Plan Page 16 of 38

Page 17: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

4.4 ATM Tests 4.4.1 STM-1 BER Test Test Purpose To test and verify proper and error-free operation of ATM traffic over the 155Mbps main channel. The test is identical to SDH 155mbps BER test (as described in Sec. 5.3.2). Test Set-Up Test Set-Up B will be used for this test. Required test-equipment

(a) ATM Analyzer (for BER measurement)

Test Procedure (a) Set up a link using the Test-Set. Set the RSL to ~-40dBm. (b) Connect ATM analyzer to one IDU. Loop the Line module in the second

IDU. (c) Set the ATM analyzer to transmission of STM-1, ATM payload

(transmitter coupled to receiver). (d) Verify that there are no alarms on the ATM Analyzer and on the Link

Manager management. (e) Clear all alarm log files on the Link Manager management. (f) Run BER test on the ATM Analyzer. Verify that there are no alarms and

no errors of any kind. (g) Allow this ATM test to run at least 60 minutes. (h) Verify that no errors were detected by the ATM analyzer. (i) Verify that there were no alarms on the management.

Results Summary

BER Test Duration

Test Expected Results

Test Results

ATM Alarms No alarms Errors Detected No errors BER No errors detected /

10E-13

Management Alarms

No alarms

General FibeAir1500/1528 V&A Test Plan Page 17 of 38

Page 18: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

4.4.2 Cell Loss Ratio Measurement (CLR) Test Purpose The purpose of this test is to measure the Cell-Loss-Ratio of the ATM link for a given radio BER level. The test will demonstrate the performance superiority of the ATM algorithm implemented in the FibeAir product. Test Set-Up Test Set-Up A will be used for this test. Required test-equipment

(a) ATM Analyzer (for BER measurement)

Test Procedure (g) Set up a link using the Test-Set. Set the RSL to ~-40dBm. (h) Connect SDH Analyzer to the 155 Mbps channel in one direction (Tx

fiber to one IDU and Rx fiber to the second IDU). (i) Set the SDH analyzer to transmission of STM-1, SDH payload

(transmitter coupled to receiver) in BER measurement mode. (j) Gradually increase the attenuation of the link, decreasing the RSL, until

the radio BER has reached 10E-7. (k) Measure the CLR value when the ATM algorithm is activated and when

it is disabled. Use the management to activate/disable the ATM algorithm.

(l) Repeat steps (d) and (e) for BER 10E-6 to 10E-3. (m) Note that the CLR is at least 10-times better when the ATM

algorithm is activated. Results Summary Step Radio BER CLR

(ATM Disabled)

CLR (ATM Enabled)

1 10E-7 2 10E-6 3 10E-5 4 10E-4 5 10E-3

General FibeAir1500/1528 V&A Test Plan Page 18 of 38

Page 19: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

4.5 Network Management Tests 4.5.1 General The purpose of the tests in this section is to test the functionality of the Link Manager management application. The Link manager management grants the user full configuration, monitoring and maintenance control on both Local and Remote terminals while connected only to one end of the link. Test Set-Up Test Set-Up B will be used for all tests in this section.

(a) Set up a link using the Test-Set. Set the RSL to ~-40dBm. (b) Connect SDH analyzer to one IDU. Loop the Line module in the second

IDU. (c) Set the SDH Analyzer to transmission of STM-1, VC-4 bulk with 2^23

PRBS sequence (transmitter coupled to receiver). Required test-equipment

(a) SDH Analyzer (for STM-1 signal generation) (b) PC to install the Link Manager on.

4.5.2 Ethernet and Serial Connection Test Purpose To check the Serial and Ethernet connection for the management. Test Procedure

(a) Establish SLIP connection between one of the IDUs and PC via the IDU’s serial management port.

(b) Run ping command and verify you get reply. (c) Launch the Link Manager management of the IDU. (d) Establish Ethernet connection between one of the IDUs and PC via the

IDU’s Ethernet management port. (e) Run ping command and verify you get reply. (f) Launch the Link Manager management of the IDU.

4.5.3 Inventory data Test Purpose To test the inventory management of the Link Manager management.

General FibeAir1500/1528 V&A Test Plan Page 19 of 38

Page 20: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

Test Procedure

(a) Launch the Link Manager management of one of the IDUs. (b) Verify that all the inventory data in the “System Information” screen is

correct: • Radio Name • Link Manager version • IDU software version • IDU serial number • ODU serial number

4.5.4 Frequency Control Test Purpose To test the frequency set-up of the Link Manager management. The Link Manager allows the user to change the frequency transmitted on Local and Remote IDUs simultaneously when connected only to one end of the link. Test Procedure

(a) Launch the Link Manager management of one of the IDUs. (b) Change the frequency channel of the IDU. (c) Verify that the link is going down for a second and then up again with

the new frequency. 4.5.5 Radio Parameters Control Test Purpose To test the ODU’s radio parameters of Link Manager management. Test Procedure

(a) Launch the Link Manager management of one of the IDUs. (b) Change TX power. Verify that the RSL on the opposite ODU is

changed accordingly. (c) Change the attenuation of the link using the Variable Attenuator.

Verify that the RSL is changed accordingly. (d) Mute the Local transmitter. Verify that no communication to remote

can be established and “Remote Disconnect” alarm reported by the LED panel and the management application.

(e) Change the Tx power, antenna sizes and the link distance and verify that the “Unfaded RSL”is re-calculated.

General FibeAir1500/1528 V&A Test Plan Page 20 of 38

Page 21: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

4.5.6 Alarms Management Test Purpose To test the Link Manager management and reporting. Test Procedure

(a) Launch the Link Manager management of one of the IDUs. (b) Connect SDH analyzer to one IDU. Loop the Line module in the

second IDU. (c) Verify that there are no alarms on the SDH Analyzer and on the Link

Manager management. (d) Clear all alarm log files on the Link Manager management. (e) Disconnect the Rx Line input of IDU. (f) Verify that the “Loss Of Signal” alarm is reported on the LED panel

and on the Link Manager management. Verify that the alarm is recorded on the Alarm Log of the Link Manager management.

(g) Bring the link down by powering off the opposite IDU. Verify that the following alarms appear on the “Alarms Status” screen:

• Loss of Frame on the radio side • RX level out of range • Remote disconnect

(h) Verify that the above alarms appear also on the “Alarms Log” screen. Power on the IDU.

(i) Disconnect the IDU-ODU coax cable and verify the following alarms appear on the “Alarms Status” screen:

• Loss of Frame on the radio side • Cable Open • Internal Communication Failure • Remote disconnect

(j) Verify that the above alarms appear also on the “Alarms Log” screen. Re-connect the cable.

(k) Reduce the RSL of the link using the attenuator until errors are detected by the SDH Analyzer.

(l) Verify that “Signal Degrade on the Radio side” and Excessive Errors on the Radio side” alarms appear on the “Alarms Status” screen according to the defined alarm thresholds.

4.5.7 Performance Monitoring Test Purpose To test and demonstrate the performance monitoring capabilities of the Link Manager management. Test Procedure

(a) Launch the Link Manager management of one of the IDUs. (b) Connect SDH analyzer to one IDU. Loop the Line module in the

General FibeAir1500/1528 V&A Test Plan Page 21 of 38

Page 22: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

second IDU. (c) Verify that there are no alarms on the SDH Analyzer and on the Link

Manager management. (d) Clear all alarm log files on the Link Manager management. (e) Run BER test for 60 minutes. (f) Verify that during the test no alarms were reported by the SDH

Analyzer or the Link Manager. (g) Check the RSL Performance Monitoring screen to verify that no

changes of the RSL were recorded. Verify the data on the graph and the history table corresponds the measured RSL.

(h) Check the SDH Performance Monitoring screen to verify that no errors or un-availability were recorded on the graph or the history tables.

(i) Reduce the RSL of the ODUs using the Variable Attenuator until errors (BER=10E-5) are reported by the SDH Analyzer.

(j) Run the BER test for 60 minutes. (k) Verify that during the test the SDH Analyzer reported the errors. (l) Check the SDH Performance Monitoring screen for the errors or un-

availability on the radio transmission caused by the low RSL. Verify the errors recorded on the graph or the history tables.

(m) Increase the RSL until no errors are reported by the SDH Analyzer.

(n) Run BER test for 60 minutes. (o) During the test, change the attenuation of the link using the Variable

Attenuator several times. (p) Check the RSL Performance Monitoring screen to verify that the

changes in the RSL were recorded. Verify the data on the graph and the history table corresponds the measured RSL.

4.5.8 Loopbacks Operation Test Purpose To test the maintenance loopbacks operation of the Link Manager management. Test Procedure

(a) Launch the Link Manager management of one of the IDUs. (b) Connect SDH analyzer to the Local IDU. Loop the Line module on the

remote IDU. (c) Verify that there are no alarms on the SDH Analyzer. (d) Disconnect the physical loop on the remote IDU. (e) Verify the SDH Analyzer reports MS-AIS. (f) Activate Main Channel loopback. Verify the Loopback Alarm is

reported by the LED panel and the management. (g) Verify the MS-AIS is cleared. (h) Run BER test and verify no errors are detected. Clear the loopback

and verify MS-AIS is reported.

General FibeAir1500/1528 V&A Test Plan Page 22 of 38

Page 23: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

(i) Activate Local To IDU And Back loopback. Verify the Loopback Alarm is reported by the LED panel and the management.

(j) Verify the MS-AIS is cleared. (k) Run BER test and verify no errors are detected. Clear the loopback

and verify MS-AIS is reported. (l) Activate Local To Remote And Back loopback. Verify the Loopback

Alarm is reported by the LED panel and the management. (m) Verify the MS-AIS is cleared. (n) Run BER test and verify no errors are detected. Clear the loopback

and verify MS-AIS is reported. (o) Connect the Link Manager management to the Remote IDU. (p) From the Remote IDU, activate Remote Main Channel loopback.

Verify the Loopback Alarm is reported by the LED panel and the management.

(q) Verify the MS-AIS is cleared. (r) Run BER test and verify no errors are detected. Clear the loopback

and verify MS-AIS is reported. (s) From the Remote IDU, activate Remote To Local And Back loopback.

Verify the Loopback Alarm is reported by the LED panel and the management.

(t) Verify the MS-AIS is cleared. (u) Run BER test and verify no errors are detected. Clear the loopback

and verify MS-AIS is reported. (v) The test may be repeated for the E1 Wayside Channel.

4.5.9 External Alarm Operation Test Purpose To test the functionality of the external alarms of the IDU. The FibeAir1500/1528 has 8 external inputs (dry contacts) and 5 external outputs (“C” relays). Test Procedure

(a) Launch the Link Manager management of one of the IDUs. (b) Short the pins of External Input #1. (c) Verify that “External Input #1” alarm is reported by the Link Manager. (d) On the link manager change the name and severity of External Input

#1. (e) Short the pins of External Input #1. (f) Verify that alarm is reported by the Link Manager with the name and

severity as defined. (g) Repeat steps (b) to (f) for external inputs 2-8. (h) Define External Output Alarms fro different alarms. (i) Generate an alarm and test with DVM open-circuit and short-circuit of

the relays, according to the pin-outs.

General FibeAir1500/1528 V&A Test Plan Page 23 of 38

Page 24: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

4.5.10 Software Reset Test Purpose To test the operation of Software Reset from the Link Manager management. Test Procedure

(a) Launch the Link Manager management of one of the IDUs. (b) Activate software reset using the Link Manager. (c) Verify that the IDU resets.

4.5.11 Software Download Test Purpose To test and demonstrate the Remote Download Application of the FibeAir1500/1528. The RDA, based on TFTP, allows to download software to many terminals (IDUs and ODUs, Local and Remote), reset the terminals and to schedule the download and reset to times the network has less traffic. Alternatively, software download can be tested using the Hyper-Terminal software download tool. The software download can be performed on 1+0, 1+1 or 2+0 configurations. Test Procedure

(a) Configure the SNMPc to monitor all IDUs. (b) Ping the IP Address of each IDU and verify you get a reply from the

IDU. (c) Launch Link Manager management session for each IDU and verify you

can manage each IDU. (d) Launch the Remote Download Application. (e) Specify the IP addresses of the IDU you want to download software to. (f) Specify the software versions to be downloaded. (g) Specify the reset time for the IDUs. (h) Start the download. Monitor its progress and verify no errors are

reported. (i) After the download completed the IDUs resets, verify that the links are

up aging and the software versions were updated.

General FibeAir1500/1528 V&A Test Plan Page 24 of 38

Page 25: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

4.6 2 x Fast Ethernet Tests 4.6.1 General To test and demonstrate the Fast Ethernet configuration of the FibeAir1500/1528 radio link. For Ethernet applications, the FibeAir provides a full IP solution, creating virtual networks for LAN users (VLANs). The FibeAir provides two Fast Ethernet connections over 155 Mbps. Fast Ethernet tests include:

1. Fast Ethernet traffic test 2. Throughput measurement 3. Dynamic bandwidth allocation functionality

Test Set-Up For the test the two IDUs has to be configured with 2 x Fast Ethernet interfaces. Test Set-up C will be used for the Fast Ethernet Tests. Test Set-Up C:

PacketAnalyzer

FibeAir IDU FibeAir ODU FibeAir IDUFibeAir ODUTest-Kit

Right Port

Left Port

Right Port

Left Port

Port 1

Port 2

Port 3

Port 4

Test Equipment

(a) Packet Analyzer (for Fast Ethernet measurements)

4.6.2 Fast Ethernet Traffic Test Test Purpose The purpose of this test is to assure the proper and error-free operation of the 100BaseT IP link. Test Procedure

(a) Set up a link using the Test-Set. Set the RSL to ~-40dBm. (b) Set the IDUs to Auto-Negotiation Enabled and Dynamic Bandwidth

Allocation Enabled. (c) Connect the Packet Analyzer to the 100 BaseT left ports of the IDUs.

Verify that the “Link” LED of the 100 BaseT interface is green. (d) Set the Packet Analyzer to transmit and receive full duplex 100 Mb/s,

Auto-Negotiation enabled. Set the Packet Analyzer to transmit in 100%

General FibeAir1500/1528 V&A Test Plan Page 25 of 38

Page 26: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

utility and with random packet size. (e) Clear all logs of the Packet Analyzer and of the management. (f) Start transmit/receive packets. Allow this test to run for at least 15

minutes. Longer (or shorter) test period can be used. (g) Stop the transmit/receive on the Packet Analyzer. Verify that the number

of packets sent matches the number of packets received and that there are no collisions and packet-loss.

(h) Verify that there were no alarms on the Link Management. (i) Repeat steps (c) to (h) for the right ports of the IDUs.

Results Summary

Step BER Test Duration

Test Expected Results

Test Results

Lost Packets No lost packets (Bytes Sent = Bytes Received)

Collisions No collisions

Left Ports

Management Alarms No alarms Lost Packets No lost packets

(Bytes Sent = Bytes Received)

Collisions No collisions

Left Ports

Management Alarms No alarms 4.6.3 Throughput Measurement Test Purpose The purpose of this test is to verify actual throughput of the Fast-Ethernet ports of the FibeAir radio link Test Procedure

(a) Set up a link using the Test-Set. Set the RSL to ~-40dBm. (b) Set the IDUs to Auto-Negotiation Enabled and Dynamic Bandwidth

Allocation Enabled. (c) Connect the Packet Analyzer to the 100 BaseT left ports of the IDUs.

Verify that the “Link” LED of the 100 BaseT interface is green. (d) Set the Packet Analyzer to transmit and receive full duplex 100 Mb/s,

Auto-Negotiation enabled. Set the Packet Analyzer to transmit in 100% utility and with the maximal packet size packet size (1518 bytes/packet).

(e) Clear all logs of the Packet Analyzer and of the management. (f) Start transmit/receive packets. Allow this test to run for at least 5

minutes. Longer (or shorter) test period can be used.

General FibeAir1500/1528 V&A Test Plan Page 26 of 38

Page 27: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

(g) Stop the transmit/receive on the Packet Analyzer. Record the received packet’s rate (per second) and calculate the achieved throughput*. Verify that the throughput is 100Mbps.

(h) Repeat steps (d) to (g) also for 64 bytes/packet (the minimum allowed) and 512 bytes/packet.

(i) Repeat steps (c) to (h) for the right ports of the IDUs. Results Summary Step BER

Test Duration

Transmitted Packet Size

(bytes)

Expected Received Bit rate

(bits/sec)

Measured Received Packet

Rate (per sec)

Calculated Received Bit

Rate (Bits/sec)

1518 100Mbps 512 100Mbps

Left Ports

64 100Mbps 1518 100Mbps 512 100Mbps

Left Ports

64 100Mbps * In order to calculate the received Bit rate (throughput): Packet Size (Bytes)

Packet Size (Bits)

Preamble + Inner Packet Gap (Bits)

Overall Packet Size (Bits)

Received Packet Rate (per sec)

Received Bits Rate (Bits/sec)

64 512 160 672 148,810 100 M 512 4,096 160 4,256 23,497 100 M 1518 12,144 160 12,304 8,127 100 M Agenda: 1. Packet Size (Bytes) – Set. Configurable by the packet Analyzer. 2. Packet Size (Bits) – calculated. Packet Size (Bytes) x 8 (Bits/Byte). 3. Preamble + Inner packet Gap (bits) –

Preamble – fixed by the IXIA to 64 Bits (8 Bytes) Inner Packet Gap–the minimum available by the IXIA is 960 nsec (960E-9 sec), equivalent to 96 Bits at rate of 100Mbits/sec: 1 Bit = 1 / 100Mbits/sec = 10 nsec

960 nsec / 10 nsec/Bit = 96 Bits. 4. Overall Packet Size (Bits) – Packet Size (Bits) + Preamble + Inner Packet Gap (Bits) 5. Received Packets Rate – measured result from the IXIA. 6. Received Bits Rate – Overall Packet Size x Received Packet Rate.

General FibeAir1500/1528 V&A Test Plan Page 27 of 38

Page 28: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

4.6.4 Dynamic Band-Width Allocation Tests Test Purpose The purpose of this test is to verify actual throughput of the Fast-Ethernet ports of the FibeAir radio link in Dynamic Bandwidth Allocation (DWA) different modes. The DBW allocation feature enables the user to select between several BW allocation options of the two Fast Ethernet ports. Test Procedure

(a) Set up a link using the Test-Set. Set the RSL to ~-40dBm. (b) Set the IDUs to Auto-Negotiation Enabled and Dynamic Bandwidth

Allocation Not Active. (c) Connect the Packet Analyzer to the two 100 BaseT ports of the IDUs.

Verify that the “Link” LED of the 100 BaseT interface is green. (d) Set the Packet Analyzer to transmit and receive full duplex 100 Mb/s,

Auto-Negotiation enabled. Set the Packet Analyzer to transmit in 100% utility and with the maximal packet size packet size (1518 bytes/packet).

(e) Clear all logs of the Packet Analyzer and of the management. (f) Start transmit/receive packets on both ports of the IDUs. Allow this test

to run for at least 10 minutes. Longer (or shorter) test period can be used.

(g) Stop the transmit/receive on the Packet Analyzer. Record the received packet’s rate (per second) and calculate the achieved throughput of each port.

(h) Verify that the throughput of the left interface is 100Mbps and the right interface is 50Mbps.

(i) Set the Packet Analyzer to transmit in 80% utility and with the maximal packet size packet size (1518 bytes/packet).

(j) Repeat steps (e) to (g). (k) Verify that the throughput of the left interface is 80Mbps and the right

interface is 50Mbps. (l) Set the IDUs to Auto-Negotiation Enabled and Dynamic Bandwidth

Allocation Left Preferred. (m) Set the Packet Analyzer to transmit in 100% utility and with the

maximal packet size packet size (1518 bytes/packet). (n) Clear all logs of the Packet Analyzer and of the management. (o) Start transmit/receive packets on both ports of the IDUs. Allow this test

to run for at least 10 minutes. Longer (or shorter) test period can be used.

(p) Stop the transmit/receive on the Packet Analyzer. Record the received packet’s rate (per second) and calculate the achieved throughput of each port.

(q) Verify that the throughput of the left interface is 100Mbps and the right interface is 50Mbps.

(r) Set the Packet Analyzer to transmit in 80% utility and with the maximal packet size packet size (1518 bytes/packet).

(s) Repeat steps (e) to (g).

General FibeAir1500/1528 V&A Test Plan Page 28 of 38

Page 29: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

(t) Verify that the throughput of the left interface is 80Mbps and the right interface is 70Mbps.

(u) Set the IDUs to Auto-Negotiation Enabled and Dynamic Bandwidth Allocation Enabled.

(v) Set the Packet Analyzer to transmit in 100% utility and with the maximal packet size packet size (1518 bytes/packet).

(w) Clear all logs of the Packet Analyzer and of the management. (x) Start transmit/receive packets on both ports of the IDUs. Allow this test

to run for at least 10 minutes. Longer (or shorter) test period can be used.

(y) Stop the transmit/receive on the Packet Analyzer. Record the received packet’s rate (per second) and calculate the achieved throughput of each port.

(z) Verify that the throughput of each interface is 75Mbps. Results Summary

Left Interface Right Interface Step Dynamic BW Allocation

Mode CalculatedReceived Bit Rate

(Bits/sec)

Expected Received Bit Rate

(Bits/sec)

Calculated Received Bit Rate

(Bits/sec)

Expected Received Bit Rate

(Bits/sec)

1 Not Active 100% utility

100Mbps 50Mbps

2 Not Active 80% utility

80Mbps 50Mbps

3 Left Preferred 100% utility

100Mbps 50Mbps

4 Left Preferred 80% utility

80Mbps 70Mbps

5 Enabled 75Mbps 75Mbps

General FibeAir1500/1528 V&A Test Plan Page 29 of 38

Page 30: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

4.7 3 x E3 Tests Test Purpose To test and demonstrate the 3 x E3 configuration of the FibeAir1500/1528 radio link. The FibeAir radio link provides three channels of E3 (or DS3) over 155 Mbps. Test Set-Up For the test the two IDUs has to be configured with 3 x E3 interfaces. Test Set-up D will be used for the E3 Tests. Test Set-Up D:

SDHAnalyzer

FibeAir ODU FibeAir ODUTest-KitE3#1

FibeAir IDU

E3#2 E3#3 E3#1

FibeAir IDU

E3#2 E3#3

Test Equipment

(a) SDH Analyzer (for E3 BER measurement)

Test Procedure (a) Set up a link using the Test-Set. Set the RSL to ~-40dBm. (b) Connect SDH analyzer to E3 Port #1 of one IDU. Loop E3 Port #1

module in the second IDU. (c) Set the SDH Analyzer to transmission of E3 34Mbps signal (transmitter

coupled to receiver). (d) Verify that there are no alarms on the SDH Analyzer and on the Link

Manager management. (e) Clear all alarm log files on the Link Manager management. (f) Run BER test on the SDH Analyzer. Verify that there are no alarms and

no errors of any kind. (g) Allow this SDH test to run at least 15 minutes. (h) Verify that no errors were detected by the SDH analyzer. (i) Verify that there were no alarms on the management. (j) Repeat steps (c) to (i) for E3 Port #2 and E3 Port #3.

General FibeAir1500/1528 V&A Test Plan Page 30 of 38

Page 31: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

Results Summary E3 Port BER

Test Duration

Test Expected Results

Test Results

SDH Alarms No alarms Errors Detected No errors BER No errors detected /

10E-13

Port #1

Management Alarms No alarms SDH Alarms No alarms Errors Detected No errors BER No errors detected /

10E-13

Port #2

Management Alarms No alarms SDH Alarms No alarms Errors Detected No errors BER No errors detected /

10E-13

Port #3

Management Alarms No alarms

General FibeAir1500/1528 V&A Test Plan Page 31 of 38

Page 32: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

4.8 Fast Ethernet + E3 Tests Test Purpose To test and demonstrate the Fast Ethernet and E3 configuration of the FibeAir1500/1528 radio link. The FibeAir radio link provides a unique solution supporting IP and TDM applications. Test Set-Up For the test the two IDUs have to be configured with Fast Ethernet + E3 interfaces. Test Set-up E will be used for the Fast Ethernet and E3 Tests. Test Set-Up E:

SDHAnalyzer

FibeAir ODU FibeAir ODUTest-KitFE

FibeAir IDU

E3#3

FibeAir IDU

E3#3

PacketAnalyzer

Port 1

Port 2

FE

Test Equipment

(a) SDH Analyzer (for E3 BER measurement)

Test Procedure (a) Set up a link using the Test-Set. Set the RSL to ~-40dBm. (b) Set the IDUs to Auto-Negotiation Enabled. (c) Connect the Packet Analyzer to the 100 BaseT left ports of the IDUs.

Verify that the “Link” LED of the 100 BaseT interface is green. (d) Set the Packet Analyzer to transmit and receive full duplex 100 Mb/s,

Auto-Negotiation enabled. Set the Packet Analyzer to transmit in 100% utility and with 1518 bytes/packet packet size.

(e) Clear all logs of the Packet Analyzer and of the management. (f) Start transmit/receive packets. Allow this test to run for at least 15

minutes. Longer (or shorter) test period can be used. (g) Stop the transmit/receive on the Packet Analyzer. Verify that the number

of packets sent matches the number of packets received and that there are no collisions or packet-loss.

(j) Record the received packet’s rate (per second) and calculate the achieved throughput. Verify that the throughput is 100Mbps.

(h) Connect SDH analyzer to E3 Port #3 of one IDU. Loop E3 Port #3

General FibeAir1500/1528 V&A Test Plan Page 32 of 38

Page 33: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

module in the second IDU. (i) Set the SDH Analyzer to transmission of E3 34Mbps signal (transmitter

coupled to receiver). (j) Verify that there are no alarms on the SDH Analyzer and on the Link

Manager management. (k) Clear all alarm log files on the Link Manager management. (l) Run BER test on the SDH Analyzer. Verify that there are no alarms and

no errors of any kind. (m) Allow this SDH test to run at least 15 minutes. (n) Verify that no errors were detected by the SDH analyzer. (o) Verify that there were no alarms on the management.

Results Summary

Test Test Duration

Test Expected Results

Test Results

Lost Packets No lost packets (Bytes Sent = Bytes Received)

Collisions No collisions Management Alarms No alarms

Fast Ethernet

Throughput 100Mbps SDH Alarms No alarms Errors Detected No errors BER No errors detected /

10E-13

E3

Management Alarms No alarms

General FibeAir1500/1528 V&A Test Plan Page 33 of 38

Page 34: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

5.0 FibeAir 1+1 Validation and Acceptance Tests 5.1 General Ceragon Networks 1+1 Hot StandBy solution is based on the same components (IDUs and ODUs) used in a 1+0 link. The same units can operate as a 1+0, 1+1 and 2+0 configurations. This section will cover additional V&A tests specific to 1+1 configuration. All tests discussed above regarding “FibeAir1500/1528 1+0 Validation and Acceptance Tests” can be performed on 1+1 configuration as well. The test may be carried out in three interfaces combinations:

(d) Optical interfaces on all four IDUs. (e) Electrical interfaces on all four IDUs. (f) Optical interfaces on two IDUs of one end of the 1+1 link and Electrical

interfaces on the other end of the link. 5.2 Test Set-Up FibeAir1500/1528 1+1 link is composed from two 1+0 links, including 4 IDUs and 4 ODUs. The two links are connected using a Test-Set that will be used during the V&A functionality tests. The tests will be performed using Test Set-Up E. Lab test set-up requires:

(a) Two FibeAir1500/1528 radio link. (b) –48 VDc@3Amp power supply for each terminal (IDU+ODU). (f) Coax cables between IDUs and ODUs. (g) Test-Set for the tested frequency (38GHz). (h) Protection cable to connect the two IDUs. (i) Protection Kits for splitting the traffic interfaces. (j) PC to install the Link Manager for the link’s management.

Test equipment to be used: (a) SDH Analyzer (for BER measurement)

General FibeAir1500/1528 V&A Test Plan Page 34 of 38

Page 35: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

Test Set-Up E:

ODU ODU

ODU ODU1+1 Test-Set

SplitterHigh-Frequency

Coax Cable

ElectricalSplitters

Fibers

SDHAnalyzer

STM-1 Physical Loop

TxRxNMS

ETH

HUB

EthernetCable

ProtectionCable

OpticalSplitters

Coaxcables

5.3 STM-1 BER Test Test Purpose To test and verify proper and error-free operation of the 155 Mbps channel of a 1+1 link in all four operation options. Required test-equipment

(a) SDH Analyzer (for BER measurement)

Test Procedure (a) Set up a links using the Test-Set. Set the RSL to ~-40dBm. (b) Verify that the link is in 1+1 mode: on each side, one of the ODUs is

muted. (c) Connect SDH analyzer to the optical splitters on one end o the link.

Loop the electrical splitters on the other end of the links. (d) Set the SDH Analyzer to transmission of STM-1, VC-4 bulk with 2^23

PRBS sequence (transmitter coupled to receiver). (e) Verify that there are no alarms on the SDH Analyzer and on the Link

Manager management. (f) Clear all alarm log files on the Link Manager management. (g) Run BER test on the SDH Analyzer. Verify that there are no alarms and

no errors of any kind. (h) Force switch on each IDU (by disconnecting the Line input of the Master

IDU) on each end of the link. (i) Verify that after the SDH Analyzer is restarted (after each switch), the

SDH Analyzer does not report any errors or alarms. (j) Activate ATPC and change the attenuation of the link. Verify that the

General FibeAir1500/1528 V&A Test Plan Page 35 of 38

Page 36: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

ATPC maintains the RSL according to the Reference Level and no alarms/errors are generated during ATPC operation.

Results Summary Step Test Expected Results

Test Results

1 IDU 1 Local IDU 1 Remote No alarms/errors 2 IDU 2 Local IDU 1 Remote No alarms/errors 3 IDU 1 Local IDU 2 Remote No alarms/errors 4 IDU 2 Local IDU 2 Remote No alarms/errors 5 ATPC RSL = Reference

Level No alarms/errors

5.4 Protection Switching Tests Test Purpose To test and verify proper functionality of the protection triggers of the 1+1 link: Automatic switch, Manual switch, BER switch, External Input switch. Required test-equipment

(a) SDH Analyzer (for BER measurement)

Test Procedure (a) Set up a links using the Test-Set. Set the RSL to ~-40dBm. (b) Verify that the link is in 1+1 mode: on each side, one of the ODUs is

muted. (c) Connect SDH analyzer to the optical splitters on one end o the link.

Loop the electrical splitters on the other end of the links. (d) Set the SDH Analyzer to transmission of STM-1, VC-4 bulk with 2^23

PRBS sequence (transmitter coupled to receiver). (e) Verify that there are no alarms on the SDH Analyzer and on the Link

Manager management. (f) Clear all alarm log files on the Link Manager management. (g) Run BER test on the SDH Analyzer. Verify that there are no alarms and

no errors of any kind. (h) Force Automatic Switch on the Master IDU: disconnect the Line input,

disconnect the radio link, disconnect the IDU-ODU coax cable, reset the IDU and power off the IDU.

(i) Verify that after the SDH Analyzer is restarted (after each switch), the SDH Analyzer does not report any errors or alarms.

(j) Force Manual switch using the Link Manager management. (k) Verify that after the SDH Analyzer is restarted (after each switch), the

SDH Analyzer does not report any errors or alarms.

General FibeAir1500/1528 V&A Test Plan Page 36 of 38

Page 37: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

(l) Set the Radio Excessive Errors Threshold to 10E-5 using the Link Manager and enable BER switching.

(m) Reduce the RSL of the Master ODU until radio BER reaches 10E-5 and verify that the link switched to the Standby unit.

(n) Verify that after the SDH Analyzer is restarted (after each switch), the SDH Analyzer does not report any errors or alarms.

(o) Enable External Switch on the link. Insert external input alarm and verify that the link switches.

(p) Verify that after the SDH Analyzer is restarted (after each switch), the SDH Analyzer does not report any errors or alarms.

Results Summary Step Switching Triggers Expected Results

Test Results

1 Disconnect Line input Link Switched, No alarms/errors on link

2 Disconnect radio link Link Switched, No alarms/errors on link

3 Disconnect IDU-ODU cable Link Switched, No alarms/errors on link

4 IDU reset Link Switched, No alarms/errors on link

5 IDU power-off Link Switched, No alarms/errors on link

6 Manual Switch Link Switched, No alarms/errors on link

7 BER Switch Link Switched, No alarms/errors on link

8 External Input Switch Link Switched, No alarms/errors on link

5.5 1+1 Management Tests Test Purpose To test and verify the management of 1+1 link via the In-Band Management and the receipt of SNMP Traps on the Network Management Station. Required test-equipment

(a) SDH Analyzer (for BER measurement) (b) SNMPc Network Node Manager

Test Procedure (a) Set up a links using the Test-Set. Set the RSL to ~-40dBm. (b) Verify that the link is in 1+1 mode: on each side, one of the ODUs is

muted.

General FibeAir1500/1528 V&A Test Plan Page 37 of 38

Page 38: General FibeAir1500,1528 v&a Test Plan (Rev2.0)

Proprietary and Confidential

(c) Connect SDH analyzer to the optical splitters on one end of the link. Loop the electrical splitters on the other end of the links.

(d) Configure the SNMPc to monitor all four IDUs. (e) Ping the IP Address of each IDU and verify you get a reply from the

IDU. (f) Launch Link Manager management session for each IDU and verify you

can manage each IDU. (g) Generate a SNMP Trap on each one of the IDUs (disconnect the Line

input) and verify that the trap is received and reported by the SNMPc NMS.

(h) Force a switch to one of the Master IDUs using the Link Manager and verify the trap is received and reported by the SNMPc NMS.

(i) Power off one of the Master IDUs and verify that you can still manage the three remaining IDUs.

Results Summary Step Test Expected Results

Test Results

1 Ping each IDU Ping reply 2 Management of each IDU IDU can be

managed

3 SNMP Trap generation Trap received and reported

4 Force switch to the link Traps received and reported

5 Power off Master Remaining IDUs can be managed

General FibeAir1500/1528 V&A Test Plan Page 38 of 38