Upload
lyhanh
View
222
Download
1
Embed Size (px)
Citation preview
GABES STEG POWER PLANT
Crane Liebherr LTM 1600-8 (600 T)
Crawler crane CC2600 DEMAG (500 T)
SETTING UP OF 10 MODULES OF BOILER (240T/ PIECE)
Crane DEMAG (500T)
(SERGAZ – EL HAOURIA) VERTICAL SETTING OF EXCHANGER
Crane CC2600 DEMAG (500T)
Crane Liebherr LTM 1120 (120T)
TURBINE AND COMPRESSER REPLACEMENT
Crane CC2600 DEMAG (500T)
SETTING UP OF EXCHANGER (78 TONS) COMPRESSION STATION
OF EL HAOUAIRIA (CAP BON)
Crane DEMAG CC 2600 (500T)
CEMENT PLANT CIOK-TAJEROUINE
Replacement of two oven’s ferrules with bending (220T)
CEMENT PLANT OF ENNFIDHA
Setting of separator (110t)
Crane DEMAG CC 2600 (500T)
BRITISH GAZ GABES
Unloading and burying of five gas reservoirs (240T)
SAFETY FIRST
MAIN ACTIVITES
1. STRUCTURES FABRICATION AND ERECTION
2. MECHANICAL EQUIPMENTS ERECTION
3. PREFABRICATION AND ERECTION OF ALL KINDS OF PIPES (CS, AS, AND SS)
4. ELECTRICAL INSTALLATION
5. INSTRUMENTATION
6. PIPELINES SETTING
PRINCIPALES ACTIVITES:
1. FABRICATION & MONTAGE STRUCTURES
2. MONTAGE DES EQUIPEMENTS MECANIQUES
3. PREFABRICATIONS ET MONTAGE TOUS TYPES DE TUYAUTERIE(CS,AS ET SS)
4. INSTALLATIONS ELECTRIQUES
5. INSTRUMENTATIONS
6. POSE DE PIPE-LINE
SAFETY FIRST
PROJET ANNEE MAITRE
D’OUVRAGE
MAITRE
D’OEUVRE
CPF-WAHA PRODUCTION
FACILITIES
Travaux d’extension-PIPING
2008/200
9
PIONEER/
ETAP PIONEER
CPF OUM CHEIH
Travaux d’extension & Revamping
2007/200
8
PERENCO/
ETAP PERENCO
STATION COMPRESSION GAS
HAOUARIA
Gestion de matériel et levage
Fourniture et Montage de deux
filtres à manches Type FLS
2007 SCOGAT SAMPROGETTI
Unit GPL Gabes
Augmentation de capacité station
gaz (GPL Gabes)
2006 STEG TECHNOFRIG
O
Pipe-line GAZOUDUC TRANSTUNISIE
Gazoduc (déchargement, triage et
alimentation de l’unité de montage
tranche I & tranche II
1992
/
1993
SNAM
PROGETTI SIF ISOPIPE
Unit GPL Gabès
Station de récupération GPL. 1986 STEG LUMUS
CREST(France)
Gazoduc –NORTH TUNIS 1986 STEG STEG
Pipe line SITEP
Pose de pipe-line 1985 SITEP SITEP
CPF OUM CHEIH Maitre de l’ouvrage : PERENCO/ETAP Durée de projet : 5 mois Travaux réalisés : Equipements mécaniques montés : 700 T Structure et supports métalliques montés : 300 T
Préfabrication et montage tuyauterie : 350 T Installation électrique - Instrumentation Traitement de surface - isolation thermique
CPF-WAHA PRODUCTION FACILITIES Maitre de l’ouvrage : PIONNER/ETAP Durée de projet : 8 mois Travaux réalisés : Équipements mécaniques montés : 600 T Structure et supports métalliques montés : 300 T Préfabrication et montage tuyauterie : 550 T Installation électrique - Instrumentation Traitement de surface - Isolation thermique
STATION COMPRESSION GAS HAOUARIA Maitre de l’ouvrage : SNAMPROGETTI Travaux réalisés : Équipements mécaniques montés : 500 T Structure métallique montée : 250T Préfabrication et montage Tuyauterie : 800 tonnes Installation électrique - Instrumentation Traitement de surface- Isolation thermique
UNITE GPL GHANOUCHE Maitre de l’ouvrage : STEG
Durée de projet : 12 mois Travaux réalisés : Équipements mécaniques montés : 828 T
Structure et supports métalliques montés : 350T
Préfabrication et montage tuyauterie : 583T
Installation électrique - Instrumentation
Traitement de surface - Isolation thermique
SAFETY FIRST
PROJECT YEAR CLIENT CONTRACTOR
CPF-WAHA Production facilities
Extension works - piping 2008/2009 PIONEER/
ETAP PIONEER
CPF Oum Chiah
Extension works and revamping 2007/2008 PERENCO
/ETAP PERENCO
GAS COMPRESSION STATION HAOUARIA
Material management , lifting, supply
and erection of two handle filters type
FLS
2007 SCOGAT SAMPROGETTI
LPG UNIT GABES
Increase of capacity of the gas station
(LPG Gabes) 2006 STEG TECHNOFRIGO
Gas pipeline Transtunisie
Gas pipeline (unloading, sorting and
power supply of the erection unit part I
and part II)
1992
/
1993
SNAM
PROGETTI SIF ISOPIPE
LPG unit Gabes
LPG recovery station factory 1986 STEG
LUMUS
CREST(France)
Gas pipeline North Tunis 1986 STEG STEG
SITEP pipeline
Pipeline setting 1985 SITEP SITEP
Project: CPF-WAHA Production facilities Client: PIONEER/ETAP
Project duration: 8 months Executed works: Erection of mechanical equipments: 600T
Erection of steel structure and supports: 300T
Pipes prefabrication and erection: 550T
Electrical installation Instrumentation
Surface treatment Thermal isolation
Project: Revamping and construction works Client: PERENCO/ETAP
Project duration: 5 months Executed works: Erection of mechanical equipments: 700T
Erection of steel structure and supports: 300T
Pipes prefabrication and erection: 350T
Electrical installation Instrumentation
Surface treatment Thermal isolation
Project: Gas compression station Haouaria
Client: SNAMPROGETTI Executed works: Erection of mechanical equipments: 500T
Erection of steel structure: 250T
Pipes prefabrication and erection: 800T
Electrical installation Instrumentation
Surface treatment Thermal isolation
Project: LPG Gabes GHANNOUCH
Client: STEG
Project duration: 12 months Executed works: Erection of mechanical equipments: 828T
Erection of steel structure and supports: 350T
Pipes prefabrication and erection: 583T
Electrical installation Instrumentation
Surface treatment Thermal isolation
SAFETY FIRST
MAIN ACTIVITIES
1. FABRICATION, ERECTION OF ALL TYPES OF PYLONS
2. ERECTION OF EQUIPMENTS ON ANTENNAS (BTS, BATTERIES …)
PRINCIPALES ACTIVITES:
1. FABRICATION, MONTAGE DE TOUS TYPES DES PYLONES
2. MONTAGES DES EQUIPEMENTS SUR LES ANTENNES (BTS BATTERIE,….)
ANNEE CLIENT TYPE DE PYLONE HAUT NBRE FOURNISSEUR
PYLONE PROJET
1997 SOTETEL
ALCATEL
Carre autostable 30m 40m
50m 60m
25 - 20
15 - 2
ELFOULADH T.TELECOM GSM PHASE I
1997 ELFOULADH Carre auto stable
45m 60m
75m 100m
2 - 1
1 - 1
ELFOULADH MINISTERE DE LA DEFENCE
2000 SITE carre autostable 70m 90m 1 - 2 MITAS RESEAU M. DE L’INTERIEUR
2001 ERICSSON
WIBE
carre autoporté tubulaire 30m 42m
50m
120 - 20
20
WIBE T. TELECOM RESEAU GSM PHASE II
2001 NEC carre autoporté 30m 50m
70m
2 - 4
1
MITAS TUNISIE TELECOM
2002 ERICSSON Monopole, Pylône et BTS 30 m 13 TUNISIE TELECOM
POUR CE CHAPITRE CERI PEUT OFFRIR LES SERVICES SUIVANTS: Recherche des sites : VUE NOTRE CONNAISSANCE DU TERRAIN EN TUNISIE ET NOTRE SAVOIR FAIRE EN RÉALISATION
DES SITES GSM ET EN SE BASANT SUR NOS COMPÉTENCES LOCAUX, CERI PEUT CONTRIBUER À LA RECHERCHE, NÉGOCIATION DES SITES GSM
RÉALISATION CLÉ EN MAIN DES SITES ROOFTOP FOURNITURE & INSTALLATION DES SHELTERS (CONFORMÉMENT À LA RECOMMANDATION DU
CLIENT) FOURNITURE ET INSTALLATION DES GROUPES ÉLECTROGÈNES. FOURNITURE ET INSTALLATION DES MÂTS ROOFTOP Y COMPRIS LES SUPPORTS ANTENNES. FOURNITURE ET INSTALLATION DES COFFRETS ÉLECTRIQUES. FOURNITURE ET INSTALLATION DES SYSTÈMES PARATONNERRE ET MISE À LA TERRE. SOCLES MÉTALLIQUES POUR LES BTS OUTDOOR ET SHELTER SYSTÈME DE BALISAGE NOCTURNE. RÉALISATION CLÉ EN MAIN DES SITES GREEN FIELD. CONSTRUCTION EN DURE DES ABRIS
INFRASTRUCTURE EXTERNES DES SITES DE TÉLÉCOMMUNICATIONS
SAFETY FIRST
FOR THIS CHAPTER CERI MAY OFFER THE FOLLOWING SERVICES: Searching for sites: Due to our knowledge of the fields in Tunisia and our knowhow in the realisation
of GSM sites and based on our local competences, CERI may contribute to the searching and negociation of GSM sites
Realisation on turnkey basis of rooftop sites Supply and installation of shelters (according to client recommendations) Supply and installation of generators groups Supply and installation of rooftop masts including antenna supports Supply and installation of electrical boxes Supply and installation of lighting conductor earthling systems. Steel stands for outdoor BTS and shelter Night marking system REALIZATION on turnkey basis of green field sites Supply and installation of shelters (according to client recommendations) Construction in hard of shelters Supply and installation of generators groups
YEAR CLIENT TYPE OF PYLON HEIGHT NBRE PYLON SUPPLIER PROJECT
1997 SOTETEL
ALCATEL
Square self stable 30m 40m
50m 60m
25 - 20
15 - 2
ELFOULADH T.TELECOM GSM
PHASE I
1997 ELFOULADH Square self stable 45m 60m
75m 100m
2 - 1
1 - 1
ELFOULADH MINISTRY OF DEFENCE
2000 SITE Square self stable 70m 90m 1 - 2 MITAS NETWORK OF THE
INTERIOR
2001 ERICSSON
WIBE
Square tubular Self
supporting
30m 42m
50m
120 - 20
20
WIBE T. TELECOM GSM
NETWORK PHASE II
2001 NEC Square self
supporting
30m 50m
70m
2 - 4
1
MITAS TUNISIE TELECOM
2002 ERICSSON Pylon and BTS
monopoly
30 m 13 TUNISIE TELECOM
EXTERNAL INFRASTRUCTURE OF TELECOMMUNICATION SITES
SAFETY FIRST
MAIN ACTIVITIES
1. FABRICATION AND ERECTION OF STEEL STRUCTURES AND SUPPORTS
2. ERECTION OF MECHANICAL EQUIPMENTS
3. PREFABRICATION AND ERECTION OF ALL KINDS OF PIPES (CS, AS, AND SS)
4. ELECTRICAL INSTALLATION
5. INSTRUMENTATION
PRINCIPALES ACTIVITES:
1. FABRICATION & MONTAGE DE STRUCTURES ET SUPPORT METALIQUE
2. MONTAGE DES EQUIPEMENTS MECANIQUES
3. PREFABRICATION ET MONTAGE TOUS TYPE DE TUYAUTERIE (CS,AS, ET SS)
4. INSTALLATIONS ELECTRIQUES
5. INSTRUMENTATIONS
SAFETY FIRST
PROJET ANNEE MAITRE
D’OUVRAGE
MAITRE
D’OEUVRE
KCHABTA METLINE PHASE II
CENTRALE EOLIENNE 70MW
CONSTRUCTION DE 52 TOURS EOLIENNES DE 1,32
MW
2012/2013 STEG GAMESA
GHANOUCHE GABES
Construction de la centrale électrique cycle combiné
500 MW
2009/
2010 STEG ALSTOM
KCHABTA METLINE PHASE 1
Centrale éolienne 120 MW
Construction de 91 tours éoliennes de 1.32 MW
2009/
2010 STEG GAMESA
SIDI DAOUD PHASE III
MONTAGE DE 26 TOURS EOLIENNES DE 1.32 MW
2006/
2007 STEG
MADE
TUNISIE
SIDI DAOUD PHASE II
Montage de tours éoliennes
2002 /
2003 STEG
MADE
TUNISIE
Centrale cycle combine RADES II
Montage deux chaudières
Montage deux cheminées by Bass
Montage deux cheminées de finition
2001 SITE (USA) ALSTHOM
CENTRALE THERMIQUE DE RADES
Montage chaudière
Montage des équipement mécaniques
Montage de deux condenseurs
Montage de deux stations de pompage
1996
/
1998
STEG ANSALDO
ENERGIA
CENTRALE À CYCLE COMBINÉ (SOUSSE)
Montage de deux chaudières . 1994 STEG
GEC
ALSTHOM
GHANOUCHE GABES
Construction de la Centrale électrique cycle combiné
500 MW
2009
/
2010
STEG ALSTOM
KCHABTA METLINE
Station Eoliennes
Montage des Eoliennes
2009
/
2010
GAMESA MMI
SAFETY FIRST
PROJECT YEAR CONTRACTOR CLIENT
KCHABTA METLINE PHASE II
Wind turbine plant 70MW construction of 52
wind turbine towers of 1,32MW
2012/2013 STEG GAMESA
GHANOUCHE GABES
construction of the combined cycle electrical
plant 500MW
2009/
2010 STEG ALSTOM
KCHABTA METLINE PHASE 1
Wind turbine plant 120MW construction of 91
wind turbine towers of 1,32MW
2009
/
2010
STEG GAMESA
SIDI DAOUD PHASE III
Erection of 26 wind turbine towers of 1.32MW
2006
/
2007
STEG MADE TUNISIA
SIDI DAOUD PHASE II
Erection of wind turbine towers
2002 /
2003 STEG MADE TUNISIA
COMBINED CYCLE PLANT OF RADES II
Erection of two furnaces
Erection of two by pass smokestacks
Erection of two finishing stage smokestacks
2001 SITE (USA) ALSTHOM
THERMAL PLANT OF RADES
Erection of two furnaces
Erection of mechanical equipments
Erection of two condensing unit
Erection of two pumping stations
1996
/
1998
STEG ANSALDO
ENERGIA
COMBINED CYCLE PLANT (SOUSSE)
Erection of two furnaces 1994 STEG GEC ALSTHOM
GHANOUCHE GABES
Construction of the combined cycle electrical
plant 500 MW
2009/
2010 STEG ALSTOM
KCHABTA METLINE
Wind turbine station
Wind turbine station
2009
/
2010
GAMESA MMI
CENTRAL GHANOUCHE STEG –TUNISIE 420 MW
SAFETY FIRST
KCHABTA METLINE PHASE II Maitre de l’ouvrage : STEG/ GAMESA
Durée de projet : 18 mois Travaux réalisés : Montage de 91 tours éoliennes de 1.32 MW Equipements Mécaniques : 7280 T
Structure et support Métalliques : 9646 T
travaux de terrassement, excavation génie civil.
SIDI DAOUED STATION EOLIENNES Maitre de l’ouvrage : STEG/MADE Durée de projet : 8 mois Travaux réalisés : Montage de 26 tours éoliennes de 1,32 MW Equipements Mécaniques : 2000 T
Structure et support Métalliques :4000 T
Project: CONSTRUCTION DE CENTRALE ELECTRIQUE DE GANOUCHE GABES ALSTOM
Maitre de l’ouvrage : STEG Durée de projet : 12 Mois Travaux réalisés : mécaniques 4500 T
Structure métalliques : 400 T
Préfabrication et montage tuyauterie : 600 T
Installation électrique
Instrumentation
Traitement de surface
Isolation thermique
Project: CONSTRUCTION DE CENTRALE ELECTRIQUE DE SOUSSE Maitre de l’ouvrage : GEC ALSTOM
Travaux réalisés : Equipements Mécaniques : 3500 T
Structure Métallique : 2800 T Préfabrication et montage tuyauterie :500 T
SAFETY FIRST
Project: KCHABTA and METLINE (Towers erection) Client: STEG/GAMESA
Project duration: 18 months Executed works: Erection of 91 wind turbine towers of 1.32MW Erection of mechanical equipments: 7280T
Erection of steel structure and supports: 9646T
Leveling works, excavation and civil works of 91 towers
Project: SIDI DAOUED wind turbine station Client: STEG/MADE
Project duration: 8 months Executed works: Erection of 26 wind turbine towers of 1.32MW
Erection of mechanical equipments: 2000T
Erection of steel structure and supports: 4000T
Project: CONSTRUCTION OF ELECTRICAL POWER PLANT AT GANOUCHE GABES ALSTOM Client: STEG
Project duration: 12 months Executed works: Erection of mechanical equipments: 4500T
Erection of steel structure and supports: 400T
Pipes prefabrication and erection: 600T
Electrical installation
Instrumentation
Surface treatment Thermal isolation
Project: Construction of combined cycle electrical power plant at Sousse
Client: GEC ALSTOM
Executed works: Erection of mechanical equipments: 3500T
Erection of steel structure and supports: 2800T
Pipes prefabrication and erection: 500T
SAFETY FIRST
MATERIEL DE LEVAGE Notre parc d’engins est constamment renouvelé : Plus de 50 grues , de capacités allant jusqu’à 600 tonnes, nous permet d’assurer une grande variété d’opérations de montage, de levage et de transport. Des moyens de transport (semi-remorques, portes chars télescopique, camions, moyens de transport du personnels, Chariots éleveurs de capacité allant jusqu’à 30 Tonnes La formation continue de notre personnels et les outils informatiques mise en place permettent à notre société d’apporter un service satisfaisant à nos clients en développant des solutions techniques innovantes : La simulation et la cinématique pour chaque opération de
manutention, La Conception de dispositifs particuliers, La Création d’outillages spécifiques.
NACELLES TÉLESCOPIQUES La mise à disposition des nacelles de hauteur de plus de 40 m en remplacement des échafaudages, dans certains cas, permet à nos équipes de montage de travailler en sécurité et leurs faciliter les travaux en hauteur, d’économiser et maitriser le temps.
SAFETY FIRST
Lifting materials
Our engine fleet is constantly renewed:
More than 50 cranes of a capacity up to 600 Tons, allow us to insure a wide variety of erection, lifting and transport operations
Transportation means (tractor trailers, telescopic floats, trucks, personal transportation means)Forklifts of a capacity going to 30 tons
The continuous training of our personnel and the IT equipments put in place allow our company to provide satisfying services to our clients by developing innovative technical solutions.
The simulation and the kinematic for each operation of handling,
The Conception of special measures
The Creation of specific tools
Telescopic cherry picker
Making available of cherry pickers of a height of more than 40m in replacement of scaffolding in some cases allow to our erection teams to work safely and make easier the work at height which leads to save and control time
SAFETY FIRST
OUTILLAGE SPÉCIAL
Soudure
Pour couvrir tous les domaines, CERI développe des solutions concrètes grâce à la mise en place de moyens matériels et humains adéquats.
CERI dispose de soudeurs hautement qualifiés, conformément aux normes américaine ASME et
Européenne dans les principaux procédés suivants:
GTAW - GAS TUNGSTEN ARC WELDING
SMAW - SHIELDED METAL ARC WELDING
GMAW - GAS METAL ARC WELDING
SAW - SUBMERGED ARC WELDING
TRAITEMENT THERMIQUE ET PRÉCHAUFFAGE Nos machines de traitement thermiques à six canaux, équipées d’automates qui gèrent quatre thermo-contrôles par canal, nous donnent plus de flexibilités pour respecter les besoins les plus difficiles de nos clients.
MACHINE DE COUPE ET CHAUFREIN Découpage et chanfreinage des tuyauteries à froid: Pour la mise en œuvre des différentes nuances des aciers (acier à carbone, acier inox et surtout les aciers alliées) nous nous sommes équipés des moyens de coupe et de chanfreinage mécanique tube pour tous les diamètres : de 4¨ jusqu’à 24¨
MACHINE DE SOUDURE AUTOMATIQUE DC 1000)
SERRAGE Clé Hydraulique (couple de
serrage de 2000 NM à 40.000 NM)
Clé dynamométrique (couple de serrage de 100 NM à 2500.000 NM)
GRUES A TOUR Grues à tour de hauteur allant de
20 m jusqu’à 120 M longueur de flèche max 60 M
SAFETY FIRST
Special tools Welding In order to cover all the fields, CERI develops clear solutions by mean of the availability of material and human means CERI disposes of welders highly qualified, according to European and American (ASME) standard in the following main methods: GTAW - GAS TUNGSTEN ARC WELDING SMAW - SHIELDED METAL ARC WELDING GMAW - GAS METAL ARC WELDING SAW - SUBMERGED ARC WELDING
Thermal treatment and preheating
Our machines of thermal treatment of six canals, equipped by automatons which manage four thermal-controls by each canal, give us more flexibility to respect the hardest needs of our clients.
Machine of cutting and weld groove Cold cutting and weld groove of pipes For the implementation of the different steel grades (carbon steel, stainless steel, and specially the alloyed steels) we have been equipped by the means of tube mechanical chamfer cutting for all the diameters : from 4¨ until 24¨
Machine of automatic welding DC 1000
Hydraulic chucking Hydraulic wrench (Torque from 2000
NM to 40.000 NM)
Torque Wrench (Torque from 100 NM to 2500.000 NM)
Tower crane Tower crane of a height from 20 up to 120 M
Maximum crane beam length 60 M
SAFETY FIRST
Une pluridisciplinarité de compétences compose les services Montage, Ingénierie, Management de projet, Commercial, Administratif, Financier et Qualité. Notre effectif permet d'intervenir à tous les niveaux. Ainsi notre force est de pouvoir adapter les différents intervenants pour chacun des projets réalisés. Nos effectifs ont évolué pendant la dernière décennie de 400 personnes en 2002 à 800 personnes en 2012 avec des pics de plus de 2000 personnes en 2010. BUREAU TECHNIQUE : Notre bureau technique permet la conception, le développement et le suivi de projets grâce, entre autres, à l’utilisation des logiciels pour la planification, le design (MS PROJECT, PREMAVERA, AUTOCAD, CADWORKS PLAN, TEKLASTRUCTURE …). SERVICE MONTAGE : Plus que la mise en place de ressources matérielles, notre société tient à mettre les moyens humains nécessaires en qualification et en nombre pour apporter un service satisfaisant à nos clients. Un noyau de Personnel clé permanent de 240 personnes permet le pilotage des chantiers et la coordination entre la direction et les divers chantiers et de veiller à la réalisation des projets dans les délais.
An underdesciplinarity of competences make up our erection, engineering, project management, commercial, administrative, financial and quality departments. Our staff allows intervening in all the levels. Thus our force is to be able to adapt the different stakeholders for each realized project. Our staff improved during the last ten years from 400 persons in 2002 to 800 persons in 2012 with a peak of more than 2000 persons in 2010. TECHNICAL OFFICE: Our technical office allow the conception, the development and the following up of the projects thanks to ,among others, the use of software for planning, design (MS-project, PREMAVERA, AUTOCAD, CADWORKS PLAN, TEKLASTRUCTURE …). ERECTION DEPARTMENT: In addition to the putting in place of the material resources, our company cares for putting the necessary human means in sufficient qualification and number to bring a satisfying service to our clients. A permanent kernel of key staff of 240 persons allows the following up of sites and the coordination between the management department and the different sites and insures the realization of the projects within the deadlines.
SAFETY FIRST
CERI S.A 1983
SIEGE SOCIAL: RUE 8600 N°82 Z.I. CHARGUIA I
BP 58 TUNIS CEDEX 1080
Tél : + 216 71 894 107 -
+216 71 807 729
Fax : + 216 7 1 806 441
Email: [email protected]
Site Web:
www.ceritunisie.com
CERI ALGERIE SARL 2006
SIEGE: HYDRA IMMB: ISSAFA WA MARWA
BLOC C-ALGER
Mail: [email protected]
****************************
CERI MAURITANI 2005 SIEGE : 15 SOCOGIM PLAGE-
NOUAKCHOT MAURITANIE
Mail: [email protected]
***************************
CERI CONGO 2008 SIEGE :
ENCEINTE HOTEL LEDGER PLAZA MAYA- MAYA
Avenue Auxence ICKONGA BRAZZAVILLE, REPUBLIQUE DU CONGO
Mail: [email protected] ********************************
CERI LYBIE SIEGE :
21325 JANZOUR TRIPOLI
LYBIE Mail: [email protected] **********************