Frequent Tube Failure in Grid Panel of CFBC

Embed Size (px)

Citation preview

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    1/28

    1

    Case Study onFrequent tube Failure of Grid

    panel in CFBC Boiler

    Presented by

    S. SivakumarAGM- O&M Contracts

    Cethar Vessels Ltd, Trichy

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    2/28

    2

    CETHAR VESSELS LIMITED

    Leading manufacture of AFBC , CFBC , WHRB for sponge iron kilnGas, cement kiln gas ,DG exhaust gas & supply of power plant onEPC basis for more than two decades .

    Tied up with Riley Power Inc, USA for PC fired boilers of sub critical &super critical pressure. Collaboration with Riley / Siemens Benson

    Technology for super critical PC boilers.

    Collaboration with Siemens for Super Critical CFBC boilers.

    Tied up with OJSC power machineries , Russia for turbine design andManufacturing.

    Executing O & M contracts of captive power plants of any Capacitythrough Cethar energy ltd.

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    3/28

    3

    Major projects under execution:

    2x 135 MWe IPP with CFBC Boiler - M/s.Aryan Coal Beneficiation

    2 x 350 MWe PF Fired Boiler - M/s.Ind Barath energy Ltd.

    2 x 300 MWe PF Fired Boiler - M/s.Meenakshi energy Ltd.

    2 x 150 MWe IPP with CFBC Boiler - M/s.Shree cement

    2 x 135 MWe IPP with PF Fired Boiler - M/s.Vandana vidhuyut

    2 x 60 MWe CFBC Boiler - M/s.Jayprakash associates

    65 Boilers are under execution for IPP, CPP & Co-gen

    10 IPP & Captive power plants are under execution

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    4/28

    4

    Credentials

    CVL had designed, manufactured, erected andcommissioned more than 1000 FBC boilers.

    Based on our versatile experience duringoperation and maintenance, we have listed fewproblems faced and the causes, solution given

    for the information to this elite league

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    5/28

    5

    Case study I :

    Reported issue:

    Tube failure of grid panel in CFBC boiler

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    6/28

    6

    BACKGROUND :

    Plant capacity : 2 X 25MW CPP

    Boiler capacity : 114 TPH

    Type of firing : CFBC

    Steam pressure : 88 Kg/cm

    Steam temperature : 520 5 C

    Grid tube size : 51.0 X 4.0 mm

    location : 1,2,17,18,19,20,21,24,25,26th row from

    combustor left side

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    7/28

    7

    BACKGROUND :

    Approx. service temperature : 300C

    Boiler commissioned on : 20.08.2009

    Tube failed on : (a) Tube No : 1, 2 -23.01.10

    (b) Tube No : 19, 20, 21 -12.01.10

    (c) Tube No: 24, 25, 26 -12.11.2009

    (d) Tube No: 16, 17 -13.11.2009.

    Approx. service period : 4 Months

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    8/28

    8

    Observations

    (A)Sample No. 17& 24 :

    On inspection it is found that severe erosion withpuncture.

    Transverse cracks with ID grooving were also noticed.

    Transverse crack at

    inner surface

    Crack noticed by LPI

    test

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    9/28

    9

    ObservationsSample No. 20, 16, 1 & 2 :

    Severe puncture with erosion was noticed

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    10/28

    10

    ObservationsSample No. 19, 21 :

    Erosion is found at 25 mm from one end.

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    11/28

    11

    ObservationsSample No 26:

    This tube length 320 mm have no crack indication.

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    12/28

    12

    Failure Analysis

    Dimensional Measurements :Diameter and thickness of grid panel tube sample

    measured at various location and given below

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    13/28

    13

    Failure Analysis

    Chemical Analysis :

    Spectroscopically chemical analysis of failed tubesample carried out. Values are given below

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    14/28

    14

    Failure Analysis

    Deposit analysis (24,26,19 & 21) :

    F il A l i

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    15/28

    15

    Failure Analysis

    Hardness measurement :Hardness measurement using Rockwell B scale

    was done on failed tubes. The values given below

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    16/28

    16

    Failure Analysis

    Metallographic Examination (Micro) :

    Metallographical polishing is done in the region closer

    & away from failure region and examined under

    microscope

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    17/28

    17

    Reasons for Failure

    (A) Sample No. 24 & 17 :

    Overheating of tube around Ac1 for prolonged period.

    Fluctuating load.

    Thermal Cyclic variation.

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    18/28

    18

    Reasons for Failure

    (B) Sample No. 19,20,21, 1 & 2 :

    Erosion on outer surface of the tubes.

    Secondary failures caused from other primary sources.

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    19/28

    19

    Solution

    Refractory was laid on the entire grid panel tube to a thickness of100mm to withstand thermal load variation.

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    20/28

    20

    Conclusion

    There is no grid panel tube failure till date after refractory laying.

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    21/28

    21

    Case study 2:

    Reported issue:

    Excess coal consumption

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    22/28

    22

    Plant design details:

    Plant capacity : 1 X 8 MWe co-gen plant

    Boiler capacity : 40 TPH

    Type of firing : AFBC

    Steam pressure : 68 ata

    Steam temperature : 495 C

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    23/28

    23

    Design Fuel Analysis

    Moisture : 13.98%GCV : 6100 kcal/kg

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    24/28

    24

    Plant visit was made, boiler operating data, fuel input were

    collected and analyzed

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    25/28

    25

    Boiler data:

    Boiler operating capacity : 37.5 TPH

    Steam pressure : 68.007 ata

    Steam temperature : 495 C

    Feed water temperature : 122C

    Flue gas temperature leaving APH : 132C

    O2 in flue gas : 4%

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    26/28

    26

    Fired fuel analysis and efficiency

    GCV : 3950 Kcal/kg

    Moisture : 31.50%

    Efficiency achieved : 81.7%

    Reasons for lower Efficiency:

    Excess fired fuel moisture comparing to design fuel

    moisture

    Lower GCV of fuel comparing to design

    Loss in efficiency due to the above was 3.501%

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    27/28

    27

    Conclusion:

    Corrected efficiency is 85.2%

    Fuel moisture to be controlled for achieving theguaranteed thermal Efficiency of the boiler

    Expected Fuel saving by controlling moisture is 7.6TPD

  • 7/30/2019 Frequent Tube Failure in Grid Panel of CFBC

    28/28

    28

    Any questions

    please?

    THANKSCVL