Upload
yogeshmangal1317
View
224
Download
1
Embed Size (px)
Citation preview
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
1/28
1
Case Study onFrequent tube Failure of Grid
panel in CFBC Boiler
Presented by
S. SivakumarAGM- O&M Contracts
Cethar Vessels Ltd, Trichy
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
2/28
2
CETHAR VESSELS LIMITED
Leading manufacture of AFBC , CFBC , WHRB for sponge iron kilnGas, cement kiln gas ,DG exhaust gas & supply of power plant onEPC basis for more than two decades .
Tied up with Riley Power Inc, USA for PC fired boilers of sub critical &super critical pressure. Collaboration with Riley / Siemens Benson
Technology for super critical PC boilers.
Collaboration with Siemens for Super Critical CFBC boilers.
Tied up with OJSC power machineries , Russia for turbine design andManufacturing.
Executing O & M contracts of captive power plants of any Capacitythrough Cethar energy ltd.
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
3/28
3
Major projects under execution:
2x 135 MWe IPP with CFBC Boiler - M/s.Aryan Coal Beneficiation
2 x 350 MWe PF Fired Boiler - M/s.Ind Barath energy Ltd.
2 x 300 MWe PF Fired Boiler - M/s.Meenakshi energy Ltd.
2 x 150 MWe IPP with CFBC Boiler - M/s.Shree cement
2 x 135 MWe IPP with PF Fired Boiler - M/s.Vandana vidhuyut
2 x 60 MWe CFBC Boiler - M/s.Jayprakash associates
65 Boilers are under execution for IPP, CPP & Co-gen
10 IPP & Captive power plants are under execution
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
4/28
4
Credentials
CVL had designed, manufactured, erected andcommissioned more than 1000 FBC boilers.
Based on our versatile experience duringoperation and maintenance, we have listed fewproblems faced and the causes, solution given
for the information to this elite league
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
5/28
5
Case study I :
Reported issue:
Tube failure of grid panel in CFBC boiler
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
6/28
6
BACKGROUND :
Plant capacity : 2 X 25MW CPP
Boiler capacity : 114 TPH
Type of firing : CFBC
Steam pressure : 88 Kg/cm
Steam temperature : 520 5 C
Grid tube size : 51.0 X 4.0 mm
location : 1,2,17,18,19,20,21,24,25,26th row from
combustor left side
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
7/28
7
BACKGROUND :
Approx. service temperature : 300C
Boiler commissioned on : 20.08.2009
Tube failed on : (a) Tube No : 1, 2 -23.01.10
(b) Tube No : 19, 20, 21 -12.01.10
(c) Tube No: 24, 25, 26 -12.11.2009
(d) Tube No: 16, 17 -13.11.2009.
Approx. service period : 4 Months
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
8/28
8
Observations
(A)Sample No. 17& 24 :
On inspection it is found that severe erosion withpuncture.
Transverse cracks with ID grooving were also noticed.
Transverse crack at
inner surface
Crack noticed by LPI
test
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
9/28
9
ObservationsSample No. 20, 16, 1 & 2 :
Severe puncture with erosion was noticed
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
10/28
10
ObservationsSample No. 19, 21 :
Erosion is found at 25 mm from one end.
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
11/28
11
ObservationsSample No 26:
This tube length 320 mm have no crack indication.
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
12/28
12
Failure Analysis
Dimensional Measurements :Diameter and thickness of grid panel tube sample
measured at various location and given below
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
13/28
13
Failure Analysis
Chemical Analysis :
Spectroscopically chemical analysis of failed tubesample carried out. Values are given below
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
14/28
14
Failure Analysis
Deposit analysis (24,26,19 & 21) :
F il A l i
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
15/28
15
Failure Analysis
Hardness measurement :Hardness measurement using Rockwell B scale
was done on failed tubes. The values given below
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
16/28
16
Failure Analysis
Metallographic Examination (Micro) :
Metallographical polishing is done in the region closer
& away from failure region and examined under
microscope
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
17/28
17
Reasons for Failure
(A) Sample No. 24 & 17 :
Overheating of tube around Ac1 for prolonged period.
Fluctuating load.
Thermal Cyclic variation.
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
18/28
18
Reasons for Failure
(B) Sample No. 19,20,21, 1 & 2 :
Erosion on outer surface of the tubes.
Secondary failures caused from other primary sources.
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
19/28
19
Solution
Refractory was laid on the entire grid panel tube to a thickness of100mm to withstand thermal load variation.
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
20/28
20
Conclusion
There is no grid panel tube failure till date after refractory laying.
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
21/28
21
Case study 2:
Reported issue:
Excess coal consumption
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
22/28
22
Plant design details:
Plant capacity : 1 X 8 MWe co-gen plant
Boiler capacity : 40 TPH
Type of firing : AFBC
Steam pressure : 68 ata
Steam temperature : 495 C
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
23/28
23
Design Fuel Analysis
Moisture : 13.98%GCV : 6100 kcal/kg
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
24/28
24
Plant visit was made, boiler operating data, fuel input were
collected and analyzed
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
25/28
25
Boiler data:
Boiler operating capacity : 37.5 TPH
Steam pressure : 68.007 ata
Steam temperature : 495 C
Feed water temperature : 122C
Flue gas temperature leaving APH : 132C
O2 in flue gas : 4%
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
26/28
26
Fired fuel analysis and efficiency
GCV : 3950 Kcal/kg
Moisture : 31.50%
Efficiency achieved : 81.7%
Reasons for lower Efficiency:
Excess fired fuel moisture comparing to design fuel
moisture
Lower GCV of fuel comparing to design
Loss in efficiency due to the above was 3.501%
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
27/28
27
Conclusion:
Corrected efficiency is 85.2%
Fuel moisture to be controlled for achieving theguaranteed thermal Efficiency of the boiler
Expected Fuel saving by controlling moisture is 7.6TPD
7/30/2019 Frequent Tube Failure in Grid Panel of CFBC
28/28
28
Any questions
please?
THANKSCVL