Air Leakage Test
Hydro Test
Commissioning Checkpoints
Equipments Trial Run
Refractory Dry Out
Chemical Cleaning
Boiler Safety Protection Checking
ACTIVITIES OF COMMISSIONING
Grid Air pressure Drop Study
Control Instrumentation Checking
Boiler Light up & Coal Firing
Steam Blowing
Safety Valves Floating
Steam Dumping
Synchronization
ACTIVITIES OF COMMISSIONING
Air Leakage Test
Pressure parts
The aim of air leak test is to ensure that erection
of the pressure parts is completed and no major
leaks are there.
Air leak test is conducted by introducing air into
the boiler pressure parts at a pressure of
approximately 7 - 8ksc
Air Leakage Test
Non Pressure parts
The purpose of air leak test of air, gas ducting & ESP
is to ensure leakage proof in ducts, welding joints,
flange joints to ensure efficient operation of fans,
boiler
Hydro Test
All the pressure parts of the boiler, which are
subjected to high operating pressure during
operation, should be checked to ensure that they
withstand the high pressure so hydraulic test is
conducted
Commissioning Checkpoints
Checklist have to be prepared for all equipments and
all activities.
After completion of equipments erection, check
points to be made and the trial run of equipments
shall commence
Equipments Trial Run
No-load trial & load trials of following equipments are
completed after fulfilling the commissioning checkpoints
ID fan
SA fan
Loop seal blower
PA fan
Feed pumps
Fuel feeders
Refractory Dry Out
In a boiler furnace, during the phase of erection
refractory is laid in many areas like furnace, second
pass areas, cyclones, bed ash cooler etc,
Refractory drying is to be carried out by utilizing
either light oil or gas
Chemical Cleaning
During the process of erection, there might be
entrainment of unwanted material like rust, dirt, mill
scale etc.
The internal surfaces of a boiler where demineralized
water of high purity is to be evaporated, should be
maintained free of all material which come in the way
of efficient heat transfer and thus effect generation.
The cleaning procedures aim to removal of rust, dirt,
sand and also any foreign material entrained in the
contour.
The cleaning can be achieved by an alkali boil out or
alkali flushing and acid cleaning.
Chemical Cleaning
Boiler Safety Protection Checking
Check the following equipments are having
interlocks
ID fan-I & I vs. loop seal blower
loop seal blower delivery damper open vs. loop
seal blower
IID Fan vs. SA Fan
ID Fan vs. PA Fan
Boiler Safety Protection Checking
Check the following equipments are having
interlocks
PA Fan vs. Fuel Feeders
Drum Level very LOW vs. MFT
Deaerator Level Low vs. Feed pump
Drum level Very High vs. Turbine
Furnace pressure Very high vs. MFT
Boiler Safety Protection Checking
Check the following equipments are having
interlocks
Furnace pressure Very low vs. MFT
Grid Air pressure Drop Study
Grid air pressure drop study is nothing but finding
out the pressure drop across grid nozzle at different
air flows
The pressure drop values measured in grid pressure
drop study are used to find out the bed height when
the boiler is in running condition. i.e. at a particular
air flow
Control Instrumentation Checking
Before boiler light-up, all control instruments have to
be checked i.e. to ensure whether the remote
operation of all equipments is in proper condition
Steam Blowing
The objective of steam blowing is to remove dirts, loose
material, cutting bars etc, that might have been
entrapped in Super Heaters, Steam piping, re-heaters
during manufacture, storage, erection at site.
Failure to remove the debris may result in damage to
turbine blades, valves etc
Safety Valves Floating
The objective of the Testing Schedule is to test the
safety valves by actually floating and ensuring
that safety valves lift at recommended values.
Steam Dumping
Steam dumping is nothing but allowing steam from
re-heater through MSL and by by-passing the HP
turbine the steam is send to re-heater via HRH line
and from re-heater it is send to condenser via CRH
line by by-passing IP turbine and LP turbine.
During initial commissioning steam dumping is
done to achieve steam purity.
Steam Dumping
Till achieving purity, the steam can be allowed to
drain from CEP O/L to open drain. After achieving
purity it can be taken to close circuit.
Synchronization
After completion of all activities synchronization of
the unit shall commence
Synchronization is nothing but matching the
generator frequency with grid frequency using
syncro-scope
Reliable test Run
Reliability run is Seven (7) days of Continuous
Power Plant operation at various loads in which 72
hrs at full load and 2 hrs at 110% MCR capacity to be
demonstrated.
During this period two tripping of the plant is
allowed and after tripping plant to be
synchronization within 4 hrs to be demonstrated,
Performance test Run
Boiler performance test run is conducted
For understanding the current level of performance
of the boiler,
For any trouble shooting of the boiler for
performance deviations
For proving the performance guarantees