20
 4X135 MW CAPTIVR POWER PLANT, DONGAMAHUA RAIGARH (DISTRICT), CHATTISGARH PROJECT IDEA SHEET JSPL owns captive mining facility at village Dongamahua in District-Raigarh. Large amount of middling and fines will be generated during process of yielding washed coal from the un-graded coal mining. Reports and analysis suggests that yield will be 18%; by the time spin-off middling and fines will be tune of 57%. Precisely, every 01 T of washed coal yield attributed for generating 03T of middling and fines. These middling & fines has lower potential and considered as unusable for power generation in general. CFBC Technology is apt for firing these low GCV coal with high combustion efficiency rate with very low emissions of Nox, Sox etc. JSPL initiated a pit-head power plant of 4x135MW Capacity eyeing multiple gains such as best utilization of the upgraded low GCV coal, negligible fuel handling cost, catering power demand of existing and upcoming plants of JSPL, Raigarh, evacuating surplus power to power starved Chattisgarh and so on. General parameters Coal Property:  ______________________ __ Proximate Analysis:  Total Moisture : 10% 14 %   Ash : 50% – 58%   Volatile matter : 15% - 21%  Fixed Carbon : 13% 20%  GCV Kcal/Kg : 2200 2700 Ultimate Analysis:  Total Moisture : 10% 14 %   Ash : 50% – 58%  Carbon (C) : 23% 28%  Hydrogen (H) : 2.3% – 3.0%  Nitrogen (N) : 0.7% 0.95%  Sulphur : 0.4% – 0.6%  Oxygen (O) by : 4.5% 6.0% difference Boiler: SN Description Unit Value at 100% BMCR Value at 100% TMCR 1 Type Natural Circulation, Single Drum, Water Tube, Balanced Draft, Uncooled type Cyclone 2 Boiler Capacity TPH 460 426 3 Pressure (at SH O/L Header) Kg/cm 2 (g) 141 135.2 4 MS Temperature at SH O/L 0  C 540+/- 5 540+/- 5 5 FW Temp at Eco I/L 0  C 249 245.5 6 MS Temp at RH O/L 0  C 540+/- 5 540+/- 5 7 Boiler Efficiency % 81.5

cfbc DCPP at a Glance

Embed Size (px)

DESCRIPTION

cfbc

Citation preview

  • 4X135 MW CAPTIVR POWER PLANT, DONGAMAHUA

    RAIGARH (DISTRICT), CHATTISGARH

    PROJECT IDEA SHEET

    JSPL owns captive mining facility at village Dongamahua in District-Raigarh. Large amount of middling and fines will

    be generated during process of yielding washed coal from the un-graded coal mining. Reports and analysis

    suggests that yield will be 18%; by the time spin-off middling and fines will be tune of 57%. Precisely, every 01 T

    of washed coal yield attributed for generating 03T of middling and fines.

    These middling & fines has lower potential and considered as unusable for power generation in general. CFBC

    Technology is apt for firing these low GCV coal with high combustion efficiency rate with very low emissions of Nox,

    Sox etc.

    JSPL initiated a pit-head power plant of 4x135MW Capacity eyeing multiple gains such as best utilization of the

    upgraded low GCV coal, negligible fuel handling cost, catering power demand of existing and upcoming plants of

    JSPL, Raigarh, evacuating surplus power to power starved Chattisgarh and so on.

    General parameters

    Coal Property:_____________________________________________________________________________

    Proximate Analysis:

    Total Moisture : 10% 14 %

    Ash : 50% 58%

    Volatile matter : 15% - 21%

    Fixed Carbon : 13% 20%

    GCV Kcal/Kg : 2200 2700

    Ultimate Analysis:

    Total Moisture : 10% 14 %

    Ash : 50% 58%

    Carbon (C) : 23% 28%

    Hydrogen (H) : 2.3% 3.0%

    Nitrogen (N) : 0.7% 0.95%

    Sulphur : 0.4% 0.6%

    Oxygen (O) by : 4.5% 6.0%

    difference

    Boiler:

    SN Description Unit Value at 100% BMCR Value at 100% TMCR

    1 Type Natural Circulation, Single Drum, Water Tube, Balanced Draft, Uncooled type Cyclone

    2 Boiler Capacity TPH 460 426

    3 Pressure (at SH O/L Header) Kg/cm2(g) 141 135.2

    4 MS Temperature at SH O/L 0 C 540+/- 5 540+/- 5

    5 FW Temp at Eco I/L 0 C 249 245.5

    6 MS Temp at RH O/L 0 C 540+/- 5 540+/- 5

    7 Boiler Efficiency % 81.5

  • Steam Turbine:

    SN Description Unit Value at 100% TMCR Value at VWO

    1 Type Tandem compound, single Re-Heat, Re-Generative, Condensing, Multi Cylinder (HP&IP, LP) Casing

    2 Electrical Power output at Generator Terminal

    MW 135 141.373 (at 3% makeup)

    3 MS Flow at I/L of HP Turbine TPH 418 447

    4 Pressure at HP Turbine I/L Bar (g) 132.4 132.4

    5 MS Temperature at HP Turbine I/L 0 C 535 535

    6 Condenser Pressure Ata 0.1186 0.1186

    7 CW I/L Temperature 0 C 33 33

    8 CW O/L Temperature 0 C 42 42

    Generator:

    SN Description Unit Value at 100% TMCR

    1 Rated O/P MW 135

    2 MVA Rating MVA 169

    3 Power Factor 0.80 Lagging

    4 Terminal Voltage KV 13.8

    5 No. of Phases 3

    6 RPM 3000

    7 Frequency HZ 50

    8 Type of Cooling (Stator winding, core and rotor) Air

    9 Type of excitation Brushless

    10 Type of AVR Digital

    Light Diesel Oil:

    SN Description Unit IS:1593

    1 Flash Point 0 C 66

    2 Viscosity at 150C max Cst 2.0-7.0

    3 Pour point 0 C 12

    4 Ash content by weight % Max 0.025

    5 Free water content by volume % Max 0.05%

    6 Sediments by weight % Max 0.1%

    7 Total Sulphur by weight % Max 1.8%

    8 Carbon residue (rams bottom) % Wt

    9 Approximate GCV Kcal/ Kg In the order of 11000

    10 Sp gravity at 150C max 0.81

    Ash:

    SN Description Abb. IS:1593

    1 Silica Silica Sio2 58-62

    2 Alumina Al2o3 23-26

    3 Iron Oxide Fe2o3 7-10

    4 Titaneum Oxide Tio2 0.15-3

    5 Calcium Oxide CaO 3-5

    6 Magnesium Oxide MgO 1.5-3

    7 Sulphuric Anhydride SO3 0.15-0.4

    8 Manganese Mn 0.02-0.04

    9 Potassium pentoxide P2O5 Traces

    10 Alkalis & undermined Remaining

  • POWER STATION BASICS

    STEAM CYCLE THEORY AND CYCLE CONSTRAINTS

    Over the years, and particularly the last three decades the size and terminal conditions of generating plants

    has continuously increased at a remarkable rate as shown in table below:-

    Steam Pressure

    Main Steam Temperature

    Reheat Steam

    Conditions

    Type Design Efficiency of Power Plant

    Size of plant

    Bar Deg C Deg C % MW

    41.4 462 27.5 30

    62.1 482 30.5 60

    103.4 566 33.7 100

    103.4 538 538 Reheat + Regeneration 35.7 120

    162 566 538 Reheat + Regeneration 37.3 200

    158.6 566 566 Reheat + Regeneration 37.7 275

    158.6 566 566 Reheat + Regeneration 38.4 550

    158.6 566 566 Reheat + Regeneration 38.4 350

    241.3 593 566 Supercritical 39.0 375

    158.6 566 566 Reheat + Regeneration 39.25 500

    The main incentive to keep striving for bigger and better plant is that one expects the thermal efficiency to improve

    with size and capital cost per MW decreases with the increase of size.

    It can be seen that steam temperatures have increased at quite a slow rate. This is because increasing steam

    temperature is intimately bound up with metallurgical advances and such advantages are painfully slow. On the

    other hand, by increasing the steam pressure, introducing reheat and rapidly increasing output it has been possible

    to reduce the cost per MW of installed plant considerably.

    Increased output is normally associated with increasing pressure and temperature conditions. This is because:-

    1. The higher cost of high temperature components is partly affected by a reduction in the number of

    components per MW.

    2. Losses become proportionately smaller in the large machine.

    3. High density steam must be associated with large flows to give reasonably sized H.P. blades.

    Rankine Cycle

    The Rankine cycle is the simplest theoretical cycle using vapour as the working medium. The basic arrangement of

    this, the simplest of all vapour cycles is shown in fig 1 (Scheme) and Fig 2 (TS Diagram).

  • Fig 1 Schematic representation of power plant

    Fig 2 Rankine cycle on T-S diagram

    Temperature Entropy Diagram (T-S Diagram)

    The temperature (T-S) diagram is probably the most useful diagram of all illustrating certain fundamental

    points about steam cycles. Ideal condition for a unit on a T-S diagram is indicated in fig-3 mentioned. The unit uses

    steam at a pressure of 100 bar absolute, temp. 566 oC (839 o K) and rejects it to the condenser at 30m bar abs.

    (saturation temp. 24.1 o C).

    At point A the condensate is at boiling temperature corresponding to the back (condenser) pressure. Heat

    (sensible) is added to this water to raise its temperature and pressure. At the point B it reaches its saturation temp.

    (310.961oC obtainable from steam table) at a pressure of 100 bar. Evaporation beings at the pt. B. Heat (latent-

    because no rise in temperature between B & C, as evident from the diagram) addition continues. At C all the water

    evaporates and superheating commences. This shown by the curve CD and at D and superheated steam

    temperature is 566oC.

  • Fig 3 Sensible, Latent and Superheat, 100 bar, 566 oC Cycle on T-S Diagram

    Steam then expands isentropically i.e. enters the turbine and rotates it, as shown by the line DEF. At point

    E there is no superheat left in the steam and so from E to F there is increasing wetness. At F and steam is at a

    pressure of 30 m bar abs. Steam is then passed out of turbine to the condenser and condensation of steam takes

    place as represented by the line FA. At point A the steam has all been condensed and condensate is at boiling

    temperature ready to begin another cycle.

    To summaries the above,

    AB Heating of feed water (i.e. sensible heat addition)

    BC evaporation of water in boiler (i.e. latent heat addition)

    CD superheating of steam (i.e. superheat addition)

    DF expansion of steam in turbine point E denotes and demarcation between superheated and wet steam.

    FA condensation of steam in the condenser

    An important basic fact to remember is that heat is product of absolute temperature and change of

    entropy. In other words the heat is represented by the area under the curve.

    Sensible heat addition

    In fig above the heat added is represented by the area AB. At A the temperature is 24.1 oC and at B it is 311oC.

    Now amount of sensible heat addition can be found as:

    Sensible heat at A = 101 kJ/Kg and Sensible heat at B = 1408 kJ/Kg (Both the values taken from the steam table)

    So, sensible heat added = B A = 1408 101 = 1307KJ/Kg

    It should be noted that increasing pressure in boiler to get more output in turbo alternator (i.e. more MW) means

    more sensible heat per kilogram. Fig 2 also presents it graphically. As maximum sensible heat is supplied in feed

    heaters and economizers, number of feed heaters or area of feed heating surface shall increases with increase of

    steam condition. Table below, shows the increase of sensible heat with corresponding pressure.

  • Absolute pressure (bar) Saturation Temperature (oC) Sensible Heat (kj/kg)

    50 100

    150 200

    221.2

    263.9 311.0

    342.1 365.7

    374.15

    1154.5 1408.0

    1611.0 1826.5

    2107.4

    Fig 4 Sensible heat at Saturation Temperature at Various Pressures

    Latent Heat addition

    As stated before almost all-sensible heat is supplied in the feed heaters and economizer. Water entering

    the boiler water wall tubes is almost at boiling temperature, fast bit of sensible heat is added to water at lower part

    of water wall tubes and thereafter latent heat addition starts taking place.

    As there is no change in temperatures (line BC in fig3 indicates so) the water/ steam mixture is about

    constant temperature from the bottom to top of the tubes. The area nBCl represents the latent heat added. It

    amounts can be calculated in the following way:

    Latent heat required = T (S2- S1)

    Where, T=temp. of boiler water at B=311degC=584.15K

    S2=Entropy at C=5.6198Kj/Kg.K

    S1=Entropy at B=1319.7Kj/Kg deg. K

    It should be noted that unlike sensible heat at amount of latent heat required to convert boiling water to dry

    saturated steam reduces with increase of pressure. At critical pressure of 221.2 bar absolute it is zero.

  • Fig 5 Latent heat at various pressures

    Table -II Latent heat at Saturation Temperature

    Absolute Pressure Saturation temp.(deg C) Latent heat(Kj/Kg)

    50 100

    150 200

    221.2

    263.9 311.0

    342.1 365.7

    374.15

    1639.7 1319.7

    1004.0 591.9

    0

    Superheat addition: -

    The curve CD shows the process of steam being superheated at a constant pressure of 100 bars from the state of

    dry saturated steam at 311 deg C to the designed stop valve temp. of 566 deg C.The area plCD represents the

    amount of superheat. The amount of heat required by deducting the total heat at C from total heat at D and is

    equal to 811.6 Kj/Kg. Quantity of heat required to superheat steam to a given temperature varies with pressure.

    Table3 Variation of superheat for different pressure (final temp 570 deg C)

    Pressure Bar absolute Superheat required KJ/Kg

    50

    100 150

    200

    800.9

    821.5 885.4

    1033.2

    Thermal Efficiency of the cycle:-

    Useful heat Thermal efficiency =

    Total heat

  • Useful heat means that part of total heat which is used in rotating the turbine i.e. when the steam expand

    adiabatically(adiabatic expansion means no heat accepted or rejected during the process; all work done by steam

    at the expense of its internal energy) in the turbine represented by line DEF fig - 6. Expansion of steam takes place

    up to a pressure of 30 m bar (24.1 deg C). The condensation takes place at a constant temp. as indicated by line

    FA, until all latent heat is removed.

    Heat removed from steam or useless heat is shown or useless heat is shown by rectangular pmAF. Amount of this

    rejected can be calculated as follows:

    FIG- 6: Basic Ideal Cycle showing useful rejected heat components

    Heat rejected = T x (S2 S1) where,

    T = Absolute temperature of FA = (24.1 + 273.15) = 297.25oK

    S2 = Entropy at F = 6.803 kJ/kg

    S1 = Entropy at A = 0.3455kJ/kgK

    So, Rejected heat = 297.25 X (6.8043 0.3544) = 1917.2kJ/kg

    Now, total heat = Sensible heat + latent heat + superheat

    = 1307 + 1319.7 + 811.6 = 3438.3kJ/kg

    Useful heat = Total heat Rejected heat

    So, Thermal Efficiency = Total heat Heat rejected

    Total heat

  • Q = 1 - Rejected Heat = 1 - 1917.2

    Total heat 3438.2

    = 0.4423 or 44.23%

    This is the highest possible efficiency for a basic Rankine Cycle with steam at 100 bar absolute, 566oC and

    backpressure is 30m bar. Ofcourse, in practice a turbine operating under this cycle will be less efficient. It can also

    be noted that how superheating of steam adds to efficiency. If steam is not superheated the total amount of heat

    in this cycle will be addition of sensible heat and latent heat only i.e.1307 + 1319.7 = 2626.7kJ/kg

    So, Thermal efficiency= 1 Rejected heat = 1 - 1917.2 Total heat 2626.7

    = 0.2701 or 27.1%

    Hence, efficiency of basic Rankine Cycle can be improved by increasing the superheat. But this scope becomes limited due to limitations of materials, which can withstand very high temperature and the cost associated

    with it.

    REHEATING To increase the heat available compared to the heat rejected is to increase the superheated steam

    temperature. Unfortunately this is only possible to a very small degree because of metallurgical limitations. Thus

    there is very little scope in this direction. Therefore the alternative is to probably expand the steam in the turbine to some suitable intermediate condition and then pass it back to the boiler to be reheated to some high temperature.

    It is then piped back to the turbine to continue expansion.

    Let us consider the same 100bar cycle, now with reheat. Fig - 7 below shows the cycle. Steam as usually starts expanding after being superheated. At the point G when the pressure had dropped to 20 bar the steam is

    taken out of turbine and reheated to 566oC as shown by the line GH. It is then fed to the LP turbine where it expands to the condenser pressure.

    The efficiency of the cycle is determined in a similar manner to the previous cases and works out to be 46.09%.

    So, reheating had improved efficiency from 44.23% to 46.23% to 46.09%. A further advantage of

    reheating is that the wetness of the exhaust steam is reduced considerably.

    Fig 7 Modified Basic Cycle to incorporate reheat

  • REGENERATIVE FEED HEATING

    Steam in a thermal cycle will normally reject heat in two ways. Firstly the heat rejected can go to waste via the

    condenser cooling water and secondly, the steam can reject heat to the feed water by means of feed heaters. In

    the second case, all the heat is kept within the cycle and not lost. The more steam which can be prevented from

    going to the condenser, the more heat will be saved from rejection to waste. Consequently, if the steam is allowed

    to expand to a certain extent in the turbine and perform useful work before it is allowed to transfer its remaining

    heat to feed water, then the quantity of work is obtained without any condenser loss and the efficiency is improved.

    In modern design of high capacity units the bled steam has been used for turbine driven feed pump and its exhaust

    used for feed water heating in addition to the conventional extractions.

    Let us see the previous 100 bar cycle, this time with regenerative feed heating (Fig 7). The steam

    expands isentropically in the turbine until the temperature is 250oC after which the steam is bled to an infinite

    number of feed heaters. The result is quantity of heat represented by area under the curve KL is transferred to the

    water side shown by the area LFpr has been given to feed water whereas before it would have been rejected in the

    condenser. The heat represented by the area LKF has also been transferred to feed water, where as formerly it

    would have done some useful work in turbine, so there is some loss of work too. Yes, but on the balance its is

    better to loss the power from the triangle LKF to save the heat represented by large rectangle LFpr that would have

    been wasted.

    Regenerative feed heating elevates the condensate temperature represented along the boiling water line to

    M and the remaining sensible heat is supplied in the economizer and boiler to point B.

    Let us find the efficiency with reheat;

    Total heat supplied = sensible heat from M to B + Latent heat + superheat

    Amount of latent heat and superheat in this cycle are same on the previous cycle with superheat and eual; to

    1319.7kJ/kg and 811.6kJ/kg respectively.

    Now, sensible heat = Total heat at B total heat at M = 322.2 kJ/kg

    So, total heat supplied = 322.2 + 1319.7 + 811.6 = 243.5 kJ/kg

    Heat rejected = Area under ALRM = 1192.2kJ/kg

    So, efficiency = 1 - Rejected Heat = 1 - 1192.2 Total Heat 2453.5

    = 0 .514 or 51.4%

    Hence you find how efficiency of Rankine cycle changes with reheating and feed heating.

    Basic efficiency (Fig 6) = 44.23%

    Reheat efficiency (Fig 7) = 46.09%

    Feed heating cycle efficiency (Fig 8) = 51.4%

  • A combination of reheating and feed heating will give higher ideal cycle efficiency.

    Fig 8 Modified Basic Cycle to incorporate feed heating

    The main factors affecting the cost of plant are:

    1) The improvement in thermal efficiency permits a reduction in the size of boiler as it has less heat input to do

    for a given load.

    2) The increased amount of steam tapped for feed heating increases the cost of the feed heaters and the steam

    piping between turbine and heaters.

    3) The increase in the total steam consumption increases the cost of the steam piping between the boiler and

    the turbine, the cost of high pressure end of the turbine and that of feed piping and feed pumps.

    4) The decrease in the amount of steam flowing through the low-pressure end of the turbine and the amount of

    steam to be condensed. It decreases the cost of low-pressure end of the turbine and the cost of condensing

    plant, C.W. culverts, etc.

    5) The higher feed temperature consequent upon the use of extensive regenerative feed heating would cause

    the flue gases to leave the boiler economizer at a higher temperature, thus inevitably reducing the boiler

    efficiency to an extent which could largely counter balance the increase in turbine thermal efficiency. For this

    reason it is necessary to employ a further regenerator in the form of an air heater in which the heat of the

    flue gases is transferred to the combustion air supplied to the furnace.

  • Another consideration with respect to boiler design is that the feed temperature at the economizer inlet must be

    higher than the due point of the boiler flue gases, but not high enough to cause steaming in the economizer also,

    the temperature of feed water in the economizer outlet must be less than the saturation temperature of water at

    that particular pressure, normally difference shall be 20oC.

    Familiarization of Boiler and Turbine system at DCPP

    Boiler:

    Shanghai Boiler Works Ltd. (SEC/SBWL) has supplied JINDAL STEEL & POWER LIMITED four sets of 460TPH CFB

    boiler. The boiler mainly consists of drum, membrane water wall furnace, thermal insulation cyclone separator, U -

    type seal pot and back-pass convective heating surface.

    1. Steam and water system: The steam and water system consists of economizer, drum, evaporative

    heating surface (furnace water wall and evaporate panels), superheater panels, back-pass superheater, final

    superheater and re-heater.

    The feed water enters low temperature economizer from one side of the pack-pass and then high temperature

    economizer. The heated water then enters the drum through 2 connecting pipes. The water in the drum flows

    to the furnace water wall through 4 large diameter downcomers, and 02 to the evaporate panels through

    downcomers. Then the saturated steam is lead to the drum through link tubes.

    The saturated steam is lead to back-pass superheater from drum through 2 connecting pipes. The superheat

    steam flows through back-pass superheater, low temperature superheater panels, first-stage de-superheater,

    high temperature superheater panels, secondary-stage de-superheater and final superheater.

    2. Gas and air system: The boiler is of balanced draft. Zero pressure point is set at the inlet duct of cyclone

    separator. The air is send into the air pre-heater by fans (include primary air fan and secondary air fan). The

    hot primary air enters wind box arranged under the furnace and flows through the nozzles on the grate and

    fluidizes the materials inside the furnace. The hot secondary air is send into the furnace through secondary

    nozzles. The high pressure fluidizing air is used as greasing air of seal pot and fluidizing air of ash cooler.

    3. Coal & Ash circulation system: Fuel, sorbent and bed materials are fluidized in the furnace by the primary

    air. Fuel particles, high temperature materials and sorbent particles are mixed sufficiently. Combustion process

    is completed in the dense-phase area, however small particles are carried out by the gas, which are separated

    in the cyclone as the heavy particles drop down and the light fly ash are carried by the gas to the back-pass.

    Two thermal insulation cyclone separators are arranged between furnace and back-pass. A U type seal pot is

    arranged under each separator. Fluidizing nozzles are arranged at the bottom of the seal pot, which fluidizes

    the material and send it back to the furnace.

    4. Ash drain system: Ash generation will be tune of 50% of the coal firing rate, in which, Fly ash and bed ash

    ration is 55:45. Bottom ash is drained from the furnace bottom. The temperature of bed ash is about 800 Deg

    C. The bottom ash will drag to ash coolers that will be cooled to as low as 120 Deg. Fly ash is drained from the

    back-pass and ESP.

  • Details of Coal Bunker, feeder, fans & motors:

    Coal bunker Capacity:

    No Item Unit Value

    1 No of coal bunkers for each boiler Set 2

    2 Volume per bunker m3 1150

    3 Effective volume m3 977.5

    4 Bulk Density T/ m3 0.85

    5 Effective Stacking capacity Tons 830

    6 Plant operation time without filling coal Hrs 12 (6 Hrs x 2 Bunkers)

    Gravimetric Coal Feeder

    No Item Unit Value

    1 Type - Gravimetric

    2 Max O/P TPH 60

    3 No. per Boiler Set 6

    Primary Air Fan

    No Item Unit Value

    1 Type - Centrifugal

    2 Inlet air capacity 0C 27

    3 Capacity m3/ Hr 165486

    4 Static pressure rising mmwc 2345

    5 Flow control device - IGV

    6 Motor rated power KW 1200

    7 Voltage V 6600

    8 No for each boiler Set 2

    Secondary Air Fan

    No Item Unit Value

    1 Type - Centrifugal

    2 Inlet air capacity 0C 27

    3 Capacity m3/ Hr 135505

    4 Static pressure rising mmwc 1567

    5 Flow control device - IGV

    6 Motor rated power KW 800

    7 Voltage V 6600

    8 No for each boiler Set 2

  • Induced Draft Fan

    No Item Unit Value

    1 Type - Double suction inlet

    Centrifugal

    2 Inlet air capacity 0C 139.5

    3 Capacity m3/ Hr 604337

    4 Static pressure rising mmwc 854

    5 Flow control device - Hyd Coupling

    6 Motor rated power KW 1700

    7 Voltage V 6600

    8 No for each boiler Set 2

    High Pressure Blower

    No Item Unit Value

    1 Type - Constant volume

    (displacement type)

    2 Inlet air capacity 0C 27

    3 Capacity m3/ Hr 19118

    4 Static pressure rising mmwc 7608

    5 Motor rated power KW 400

    6 Voltage V 6600

    7 No for each boiler Set 2

    Electrostatic Precipitator

    No Item Unit Value

    1 Type - Double chambers and

    eight fields

    2 Inlet flue gas temperature 0C 154.6

    3 Flow of gas m3/ Hr 962280

    4 Flow area m2 333

    5 Pressure drop mmwc 99.97

    7 Dust emission at ESP Outlet Mg/ m3

  • Reheat Condensing Steam Turbine

    Shanghai Turbine Co. Ltd. (SEC/STC) has manufactured more than 200 turbine units of 135MW capacity so far.

    Their brand-new D151 type turbine unit is developed on basis of MHIs technique. This steam turbine is a super

    high-pressure reheat unit of reaction condensing type with double exhaust arrangement. Its features are combined

    HP and IP cylinder and inverted flow path arrangement, as main steam flow and reheated inlet flow are gathered at

    the middle part of HP-IP cylinder. The LP cylinder is radial diffusing type with double exhausts, reducing axial

    length of turbine and lowering exhaust resistance by the greatest extend.

    The HP-IP cylinder is a single-shell casing, with a single-row control stage and 13 pressure stages in the HP section.

    The reheated steam enters the combined reheat valve which is controlled by 2 oil-relays in left-right arrangement

    via two pipes, and then goes into the IP section via two rigid admission pipes. The IP section has 13 pressure

    stages. The upper half of IP exhaust section is designed upright to lead the exhaust steam into the LP cylinder via

    two flexible IP and LP crossover pipes. The LP cylinder is double-flow and double-exhaust type.

    Performance evaluation of Power Station

    Evaluation of power station performance shall be pronounced as performance of boiler and TG as boiler receives

    energy from outside so as to produce steam while Turbine attributed to electricity generation.

    Power station output or capacity mentioned in terms of MW in general. Kilo-Watt-Hour or KWh is the basic unit of

    electricity.

    Heat rate:

    Heat rate is a significant indicator of power station performance. Heat rate defined as Heat Input (Kcal or KJ) per

    Unit electricity generation (KWh). Lower the heat rate, higher the plant efficiency.

    1. Turbine Heat Rate: Turbine heat rate is defined as heat input to turbine (in Kcal) per unit generation. At

    DCPP, guaranteed turbine heat rate is 2042 Kcal/ KWh.

    2. Unit heat rate: Turbine heat rate divided by boiler efficiency leads unit heat rate. For DCPP, guaranteed

    boiler efficiency is 82.7% and their by unit heat rate will be 2469 Kcal/ KWhr. (NB: 2042/.827= 2469)

    3. Station / Plant heat rate: Auxiliary power consumption of Thermal power plant is considered at 10% of

    the plant total capacity. So, the power output can be calculated as 90% of total generation and the station

    heat rate will be 2743 Kcal/ KWhr.(NB:2469/.90=2743)

    Boiler efficiency:

    Efficiency of boiler can be calculated in two ways viz; direct method and indirect method.

    Direst method: Direct method is simple Output / Input method.

    Efficiency: Main Steam Flow (TPH) X 1000 X (hs- hf) + RH Flow (hhrhs hcrhs)

    Coal fired / Hr in Kg x GCV of coal in Kcal/ Kg

  • Indirect method: Indirect method counts various losses and their by considered as more accurate than

    direct method of finding efficiency. However, blow down loss is omitted in indirect method. There are

    reference standards for Boiler testing at site using indirect method namely British Standard BS 845: 1987

    and US standard ASME PTC-4-1 Power test code steam generating units. Indirect method is also called

    heat loss method, covers various losses such as

    Heat loss due to dry flue gas

    Heat loss due to moisture in fuel

    Heat loss due to moisture in combustion air

    Heat loss due to hydrogen in fuel

    Heat loss due to radiation

    Heat loss due to Unburnt in fly ash

    Heat loss due to Unburnt in bed ash

    Station costing model (tentatively given for understanding concepts)

    Estimated project Cost of 4 x 135 MW Captive Power Plant is Rs.2259.00 Crores. The CPP will cater to ever

    increasing power demand of not only the existing but also the upcoming Steel complex at Raigarh.

    The Project is financed in two phases.

    The total project cost and financing plan for Phase I & II is as under:-

    Sl. Description Project cost

    Phase I Phase II

    1 Total Project Cost Rs.1179.00 Crores Rs.1080.00

    Cost calculation sheet (combined for Phase I & II)

    Generation

    Item Unit Quantity Remark

    Turbine Maximum Continuous rating (TMCR) MW 135.00 Per Hour generation in Million Units

    Maximum Generation per day MU 3.24

    Average achievable generation per day MU 2.92 at 90% PLF

    Auxiliary power consumption per day MU 0.29 at 10% of generation

    Net saleable units per day MU 2.62 Average generation - Aux Power

    Per day revenue (Rs in Crores) Rs in Cr 1.14 at Rs 4.35 / Unit (i.e. KWhr)

    Monthly Generation MU 78.73

    Monthly revenue Rs in Cr 34.25

    Yearly generation MU 944.78 Considering 12 months

    Yearly achievable generation MU 866.05 considering 01 Month S/D

    Unit Yearly Revenue Rs in Cr 376.73 From one Unit

    Plant yearly Revenue Rs in Cr 1506.93 From 04 Units

  • Coal

    Item Unit Quantity Remark

    Max Coal Consumption per hour BMCR Tones 162 for 460 TPH, 2300 Kcal/ Kg GCV coal

    Max Coal Consumption per hour TMCR Tones 145 For 435 TPH, 2042 Kcal/ Kg heat

    rate, Boiler efficiency at 82.7%

    Avg. Coal consumption per Day Tones 130 At 90% PLF

    Coal consumption per day Tones 3120

    Specific coal consumption T/MW 1.075

    Cost of coal per day Rs in Cr 0.28 at Rs 900/ T of Middling

    Cost of coal per month Rs in Cr 8.42

    Cost of coal per annum per unit Rs in Cr 92.66 Considered 01 month S/D

    Cost of fuel per annum for 04 units Rs in Cr 370.66

    Fuel Oil

    Item Unit Quantity Remark

    LDO Consumption (Per light up) T 32.00 Cold startup

    LDO Consumption (Per light up) T 12.00 Hot Startup

    Total consumption / annum T 336.00 06 cold startup & 12 hot startup

    Fuel cost Rs/T 30000.00

    Fuel cost per annum Rs in Cr 1.01 One unit

    Fuel cost for 04 Units Rs in Cr 4.03

    Miscellaneous costs

    Item Unit Quantity Remark

    Maintenance cost and other Misc cost such as

    Manpower (staff & operators), Ash transportation,

    chemicals, DM Water etc

    Rs in Cr 113 5% of capital cost of 2259 Crores

    Calculation sheet

    Item Unit Quantity Remark

    Total revenue per annum Rs in Cr 1506.93 From 04 units

    Expenditure Rs in Cr 487.69

    Net Savings Rs in Cr 1019.24

    Simple payback period:-

    This is the simplest technique that can be used to appraise a project proposal. The Simple Payback Period can be

    defined as the length of the time required for the running total of net saving before depreciation to equal the

    capital cost of the project. Shorter the payback period, more attractive the project becomes.

    Simple payback period (SPP) : Capital cost of the projects / Net annual saving. SPP (of DCPP) : 2259 / 1019

    : 2.21, to say 2 years 03 months

    Discounted cash flow methods:-

    Even though, SPP is a simplest technique for a quick evaluation, it has a number of major weaknesses as below:

    SPP does not consider savings that are accrues after the payback period is finished.

    SPP does not consider either interest, inflation etc. Other way, time value for money is not been considered

    in SPP Method.

  • Net present value: NPV method calculates the present value of the all yearly cash flows (i.e. capital costs and

    net savings) incurred or accrued throughout the life of a project, and summates them. Costs are represented as

    negative value and savings as positive. The sum of all the present value termed as NPV. The higher the NPV, the

    more attractive the proposed project.

    PV = S x DF; DF = (1+IR/100)-n

    PV is the Present Value of S in n years time, S is the value of cash flow in n years time, DF is the discount

    factor or simply interest on capital.

    Profitability Index: Profitability index termed as sum of the discounted net savings per capital cost.

    Net Present Value and Profitability Index for a 10 Year span

    Discount factor is nothing but accrues figure of interest, depreciation and inflation. Here, we have considered 10% interest, 10% depreciation and 4% inflation

    Net Present Value and Profitability Index for a 10 Year span

    Year Discount at 16% (Interest,

    inflation and Depreciation)

    Capital investment (In

    Crores) Net Savings Present Value

    0 1 -2259 0 -2259

    1 0.862 0 1019 878

    2 0.743 0 1019 757

    3 0.641 0 1019 653

    4 0.552 0 1019 562

    5 0.476 0 1019 485

    6 0.41 0 1019 418

    7 0.354 0 1019 361

    8 0.305 0 1019 311

    9 0.263 0 1019 268

    10 0.227 0 1019 231

    NPV 2666

    Profitability index 1.18

  • VARIOUS PACKAGES ALONGWITH VENDORS & THEIR OWNERSHIP

    S.N. PACKAGE NAME VENDOR FOR PH-II VENDOR FOR PH-II Owner

    1 BTG PACKAGE Shanghai Electric

    Company (SEC), China

    Shanghai Electric

    Company (SEC), China

    Boiler: Mr Aravindaran

    Turbine: Mr U K Ghosh

    2 MAKE-UP WATER

    SYSTEM "RAUNAQ International

    Ltd "RAUNAQ & Jindal Saw

    Pipes Mr Balamurugan / Mr T V

    Gopi

    3 PTDM Plant TRIVENI TRIVENI Mr Sunil Porwal

    4 COOLING TOWER (2

    Nos.) "PAHARPUR COOLING

    TOWERS LTD." "PAHARPUR COOLING

    TOWERS LTD." Mr Sunil Porwal

    5 EOT CRANE "CSD,RAIGARH" "CSD,RAIGARH" Mr U K Ghosh

    6 CHIMNEY SIMPLEX Infrastructure

    Ltd GDC Mr A Kar/ Mr U K Ghosh

    7 CIVIL & STRUCTURAL

    WORK

    SIMPLEX Infrastructure

    Ltd GDC Mr A Kar/ Mr U K Ghosh

    8 CW & ACW PUMP "WPIL LTD." "WPIL LTD." Mr Sunil Porwal

    9 SWITCH YARD (For

    10Bay) "Siemens" "Siemens" Mr S K Garai

    10 POWER/GENERATOR

    TRANSFORMER

    "AREVA" T&D LTD.

    "AREVA" T&D LTD. Mr S K Garai

    11 ST & UAT "T & R ltd." "T & R ltd." Mr S K Garai

    12 Service Transformer "Crompton Greaves

    Ltd."

    "Crompton Greaves

    Ltd." Mr S K Garai

    13 CHP Enviro abrasion

    Resistant Ltd.

    Enviro abrasion

    Resistant Ltd. Mr R Verma

    14 AHP "Mecawber Beekay

    Ltd." "Mecawber Beekay Ltd." Mr Vinay Krishan

    15 BTG Erection &

    Commissioning EDAC Engineering Ltd Sunil Hi-Tech

    Boiler: Mr Aravindaran

    Turbine: Mr U K Ghosh

    16 HT Switchgear Siemens Mr S K Garai

    17 MISCELLANEOUS PUMPS "WPIL LTD." "WPIL LTD." Mr Sunil Porwal

    18 COMPRESSED AIR

    SYSTEM "Atlas Copco LTD." Mr Vipin Chaudhary

    19 HT POWER CABLE "KEI LTD" Mr S K Garai

    20

    CW & ACW PIPING

    "LLOYD LTD."

    Mr Balamurugan / Mr T V Gopi

    FUEL OIL SYSTEM Mr Balamurugan / Mr T V

    Gopi

    21 BATTERY & BATTERY

    CHARGER "HBL LTD." "HBL LTD." Mr S K Garai

    22 RE JOINT "CORI ENGINEERING

    LTD." "CORI ENGINEERING

    LTD." Mr U K Ghosh

    23 BF VALVE "TYCO VALVE LTD." "TYCO VALVE LTD." Mr Balamurugan / Mr T V

    Gopi

    24 BUSDUCT "CONTROL &

    SWITCHGEAR LTD." "CONTROL &

    SWITCHGEAR LTD." Mr S K Garai

    25 C & I M/s YOKOGAWA LTD. M/s YOKOGAWA LTD. Mr J Kole

    26 FIRE detection and protection system

    Tyko fire Tyko fire Mr Sarkar

    27 STOP LOG GATES &

    SCREENS M/s Macmet India Ltd M/s Macmet India Ltd

    Mr Balamurugan / Mr T V Gopi

  • 28 LP PIPING M/s Unitech Machines

    Ltd.

    M/s Unitech Machines

    Ltd. Mr Sarkar

    29 BOP ELELCTRICAL M/s UB ENGINEERING

    LTD. Mr S K Garai

    30 DG SETS M/s STERLING & WILSON Mr Vipin Chaudhary

    31 LT switch gear M/s Schneider Electric

    India Pvt. Ltd.

    M/s Schneider Electric

    India Pvt. Ltd. Mr S K Garai

    32 Air conditioning M/S VOLTAS LTD Mr Vipin Chaudhary

    33 Ventilation M/S SK SYSTEM Mr Vipin Chaudhary

    34 Misc crane and hoist M/s Century Crane

    Engineers Pvt ltd

    M/s Century Crane

    Engineers Pvt ltd Mr Sunil Porwal

    35 Elevator M/S OMEGA

    ELEVATORS

    M/S OMEGA

    ELEVATORS Mr Aravindaran

    36 LT Power Cable M/S KEI Mr S K Garai

    37 220 KV Transmission

    Line M/s Nirmala Constructions Mr S K Garai

    38 Logistics M/s Ruby infra logistic TRANSPORT LTD.

    39 Plate type Heat

    Exchanger M/s Tranter India Ltd Mr Balamurugan

    40 Third Party Inspection in

    china M/s Lloyd register Asia ltd.

    41 O&M Contract M/s SEC

    42 Supervision of

    Refractory Application &

    Furnace drying

    M/s SEC Mr Ravindrakumar

    43 33 kV Switchyard M/s Siemens Mr S K Garai

    44 33 kV Transformers "AREVA" T&D LTD. Mr S K Garai

    45 SCADA Mr S K Garai

    46 Effluent Treatment Mr Sunil Porwal

    47 Public Address System Mr J Kole

    UntitledUntitledUntitled