-DowntimeTotal Parts / # of Identical Parts * CC / 60 - Minutes Worked = Downtime
-Hourly (If you forget to check your hourly product count, you can calculate it with this formula)(60 - Downtime) * 60 / Cycle time = The number of shots produced for that hour
-Total parts is the total number of GOOD pieces and SCRAP pieces.
-Cycle time is the ACTUAL time, not the book time.
-Minutes worked is the entirety of the time you were working on those pieces. Regardless of down time.