40
PROPOSED EXPAN TPM TO 15750 TP PLANT (22 MW T M/s. PHIL Survey No. 47, SH Dist: K FORM-I For ANSION OF CARBON BLACK (1 PM ) AND CO-GENERATION P TO 32 MW) IN EXISTING PREM of LLIPS CARBON BLACK LTD. H – 46, Village: Mokha, Tal: Mun Kutchh-370421, Gujarat Consultant 0 10950 POWER MISES ndra,

Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

PROPOSED EXPANSION OF

TPM TO 15750 TPM

PLANT (22 MW TO

M/s. PHILLIPS CARBON BLAC

Survey No. 47, SH

Dist: Kutch

FORM-I

For

EXPANSION OF CARBON BLACK (10950

TPM ) AND CO-GENERATION POWER

PLANT (22 MW TO 32 MW) IN EXISTING PREMISES

of

PHILLIPS CARBON BLACK LTD.

, SH – 46, Village: Mokha, Tal: Mundra

Kutchh-370421, Gujarat

Consultant

0

10950

GENERATION POWER

IN EXISTING PREMISES

Mundra,

Page 2: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

1

APPENDIX I

(See paragraph - 6)

FORM 1

(I) Basic Information

Sr.

No.

Item Details

1. Name of the project/s PHILLIPS CARBON BLACK LTD.

2. S. No. in the schedule 5 (C)

3. Proposed capacity/area/length/tonnage to be

handled/command area/lease area/number of

wells to be drilled

Carbon Black = 15750 MT/Month

Co-Generation Power Plant =32 MW

For detail Please refer Annexure – I

Phase - I Carbon Black = 13350 MT/Month

Cogeneration = 26 MW

(50 mt/hr capacity boiler will be installed in 1st

phase)

Phase - II Carbon Black = 15750 MT/Month

Cogeneration = 32 MW

4. New/Expansion/Modernization Expansion

5. Existing Capacity/Area etc. Carbon Black = 10950 MT/Month

Co-Generation Power Plant = 22 MW

6. Category of Project i.e. ‘A’ or ‘B’ ‘A’

7. Does it attract the general condition? If yes,

please specify.

No

8. Does it attract the specific condition? If yes,

please specify.

No

9. Location

Plot/Survey/Khasra No. Survey No. 47

Village Mokha

Tehsil Mundra

District Kutchh

State Gujarat

10. Nearest railway station/airport along with

distance in kms.

Mundra: 14 Km

11. Nearest Town, city, District Headquarters along

with distance in kms.

Mundra: 14 Km

12. Village Panchayats, Zilla Parishad, Municipal

Corporation, local body (complete postal

address with telephone nos. to be given)

Mokha

13. Name of the applicant PHILLIPS CARBON BLACK LTD.

14. Registered Address Duncan House

31, Netaji Subhas Road,

Post Box No. 2229,

Kolkata – 700001

West Bengal

15. Address for correspondence: Survey No. 47, SH-46, Village: Mokha, Taluka:

Mundra, Dist: Kutchh.

PIN: 370421

Gujarat

Page 3: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

2

Name Girish Singh

Designation (Owner/Partner/CEO) Chief Projects, Specialty Process & Technology

Address M/s. PHILLIPS CARBON BLACK LTD. Survey No. 47, SH-46, Village: Mokha, Taluka:

Mundra, Dist: Kutchh.

Pin Code 370421

E-mail [email protected]

Telephone No. +91 2838 619203

Fax No. +91 2838 283635

Mobile +91 9099069970

16. Details of Alternative Sites examined, if any.

Location of these sites should be shown on a

topo sheet.

NA

17. Interlinked Projects No

18. Whether separate application of interlinked

project has been submitted?

No

19. If yes, date of submission No

20. If no, reason No

21. Whether the proposal involves

approval/clearance under: if yes, details of the

same and their status to be given.

(a) The Forest (Conservation) Act, 1980?

(b) The Wildlife (Protection) Act, 1972?

I The C.R.Z. Notification, 1991?

No

22. Whether there is any Government Order/Policy

relevant/relating to the site?

No

23. Forest land involved (hectares) No

24. Whether there is any litigation pending against

the project and/or land in which the project is

propose to be set up?

(a) Name of the Court

(b) Case No.

I Orders/directions of the Court, if any and its

relevance with the proposed project.

No

Capacity corresponding to sectoral activity (such as production capacity for manufacturing, mining

lease area and production capacity for mineral production, area for mineral exploration, length for

linear transport infrastructure, generation capacity for power generation etc.,)

Page 4: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

3

(II) Activity

1. Construction, operation or decommissioning of the Project involving actions, which will cause

physical changes in the locality (topography, land use, changes in water bodies, etc.)

Sr.

No.

Information/Checklist confirmation Yes/

No

Details there of with approximate quantities

frates, wherever possible) with source of

information data

1.1 Permanent or temporary change in land

use, land cover or topography including

increase intensity of land use (with respect

to local land use plan)

No Proposed expansion is within existing unit

1.2 Clearance of existing land, vegetation and

Buildings?

No --

1.3 Creation of new land uses?

No The project site is located on level ground,

which does not require any major land filling

for area grading work.

1.4 Pre-construction investigations e.g. bore

Houses, soil testing?

No --

1.5 Construction works?

Yes For detail Please refer Annexure – II

1.6 Demolition works? No There will not be any demolition work at the

site.

1.7 Temporary sites used for construction

works or housing of construction workers?

No

1.8 Above ground buildings, structures or

earthworks including linear structures, cut

and fill or excavations

Yes For detail Please refer Annexure – II

1.9 Underground works mining or tunneling?

No

1.10 Reclamation works?

No

1.11 Dredging?

No

1.12 Off shore structures?

No

1.13 Production and manufacturing processes?

Yes For detail Please refer Annexure –III

1.14 Facilities for storage of goods or materials?

Yes Areas for storage of raw materials and

finished products will be developed for the

proposed expansion project.

1.15 Facilities for treatment or disposal of solid

waste or liquid effluents?

Yes Details of the Liquid Effluent is given as

Annexure – V and details of solid waste is

given as Annexure –VI.

1.16 Facilities for long term housing of

operational workers?

No

1.17 New road, rail or sea traffic during

Construction or Operation?

No

Page 5: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

4

1.18 New road, rail, air waterborne or other

transport infrastructure including new or

altered routes and stations, ports, airports

etc?

No

1.19 Closure or diversion of existing transport

routes or infrastructure leading to changes

in traffic movements?

No

1.20 New or diverted transmission lines or

Pipelines?

No

1.21 Impoundment, damming, culverting,

realignment or other changes to the

hydrology of watercourses or aquifers?

No

1.22 Stream crossings?

No

1.23 Abstraction or transfers of water form

ground or surface waters?

No

1.24 Changes in water bodies or the land

surface Affecting drainage or run-off?

No

1.25 Transport of personnel or materials for

construction, operation or

decommissioning?

Yes By road and sea

1.26 Long-term dismantling or decommissioning

or restoration works?

No

1.27 Ongoing activity during decommissioning

which could have an impact on the

environment?

No

1.28 Influx of people to an area either

temporarily or permanently?

No

1.29 Introduction of alien species? No

1.30 Loss of native species or genetic diversity? No

1.31 Any other actions? No

Page 6: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

5

2. Use of Natural resources for construction or operation of the Project (such as land, water,

materials or energy, especially any resources which are non-renewable or in short supply):

Sr.

No.

Information/checklist confirmation Yes/No Details there of (with approximate quantities

frates, wherever possible) with source of

information data

2.1 Land especially undeveloped or agricultural

land (ha)

No

2.2 Water (expected source & competing users)

unit: KLD

Yes Water requirement will be met through GWIL.

Water balance is given as Annexure – IV

2.3 Minerals (MT) No

2.4 Construction material – stone, aggregates,

and / soil (expected source – MT)

Yes Construction materials, like steel, cement,

crushed stones, sand, rubble, etc. required for

the project shall be procured from the local

market of the region.

2.5 Forests and timber (source – MT) No.

2.6 Energy including electricity and fuels (source,

competing users) Unit: fuel (MT), energy

(MW)

Yes Fuel

Existing:

LDO= 30 KL/Month (only for heating & cooling

during startup & stops)

HSD= 4 KL/Month

After Proposed Expansion:

LDO= 40 KL/Month (only for heating & cooling

during startup & stops)

HSD= 6 KL/Month

Energy :

Existing: 7 MW from own CPP

After Proposed Expansion:

Total: 9.5 MW from own CPP

Note: During start up & shut down PGVCL

power will be utilized.

2.7 Any other natural resources (use appropriate

standard units)

No

Page 7: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

6

3. Use, storage, transport, handling or production of substances or materials, which could be

harmful to human health or the environment or raise concerns about actual or perceived

risks to human health.

Sr.

No.

Information/Checklist confirmation Yes/No Details there of (with approximate

quantities/rates, wherever possible) with

source of information data

3.1 Use of substances or materials, which are

hazardous (as per MSIHC rules) to human

health or the environment (flora, fauna, and

water supplies)

No --

3.2 Changes in occurrence of disease or affect

disease vectors (e.g. insect or water borne

diseases)

No

3.3 Affect the welfare of people e.g. by changing

living conditions?

Yes Direct/Indirect employment

3.4 Vulnerable groups of people who could be

affected by the project e.g. hospital patients,

children, the elderly etc.

No

3.5 Any other causes No

4. Production of solid wastes during construction or operation or decommissioning (MT/month)

Sr.

No.

Information/Checklist confirmation Yes/No Details there of (with approximate

quantities/rates, wherever possible) with

source of information data

4.1 Spoil, overburden or mine wastes No

4.2 Municipal waste (domestic and or commercial

wastes)

No

4.3 Hazardous wastes (as per Hazardous Waste

Management Rules)

Yes Please refer Annexure –VI

4.4 Other industrial process wastes Yes Please refer Annexure –VI

4.5 Surplus product No

4.6 Sewage sludge or other sludge from effluent

treatment Yes

Please refer Annexure –VI

4.7 Construction or demolition wastes No

4.8 Redundant machinery or equipment Yes Please refer Annexure –VI

4.9 Contaminated soils or other materials No

4.10 Agricultural wastes No

4.11 Other solid wastes Yes Please refer Annexure –VI

Page 8: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

7

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)

Sr. No. Information/Checklist confirmation Yes/No Details there of (with approximate

quantities/rates, wherever possible)

with source of information data

5.1 Emissions from combustion of fossil fuels

from stationary or mobile sources

Yes Please refer as Annexure – VII

5.2 Emissions from production processes Yes Please refer as Annexure – VII

5.3 Emissions from materials handling storage or

transport

Yes Please refer as Annexure – VII

5.4 Emissions from construction activities

including plant and equipment

No

5.5 Dust or odors from handling of materials

including construction materials, sewage and

waste

No

5.6 Emissions from incineration of waste No

5.7 Emissions from burning of waste in open air

(e.g. slash materials, construction debris) No

5.8 Emissions from any other sources No

6.Generation of Noise and Vibration, and Emissions of Light and Heat:

Sr. No. Information/Checklist confirmation Yes/No Details there of (with approximate

quantities/rates, wherever possible)

with source of information data with

source of information data

6.1 From operation of equipment e.g. engines,

ventilation plant, crushers

Yes The Noise level is within the prescribed

limit. At noisy area, adequate preventive

& control measures are taken. No

significant noise, vibration or emission of

light & heat from the unit.

6.2 From industrial or similar processes Yes -do-

6.3 From construction or demolition No

6.4 From blasting or piling No

6.5 From construction or operational traffic No

6.6 From lighting or cooling systems Yes Adequate Lighting is provided in unit

and also local ventilation system is

provided.

6.7 From any other sources No

Page 9: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

8

7. Risks of contamination of land or water from releases of pollutants into the ground or into

sewers, surface waters, groundwater, coastal waters or the sea:

Sr. No. Information/Checklist confirmation Yes/No Details there of (with approximate

quantities/rates, wherever possible) with

source of information data

7.1 From handling, storage, use or spillage of

hazardous materials

Yes Please refer as Annexure – VIII

7.2 From discharge of sewage or other effluents

to water or the land (expected mode and

place of discharge)

No

7.3 By deposition of pollutants emitted to air into

the and or into water

No

7.4 From any other sources No

7.5 Is there a risk of long term build up of

pollutants in the environment from these

sources?

No

8. Risk of accidents during construction or operation of the Project, which could affect human

health or the environment

Sr. No. Information/Checklist confirmation Yes/No Details there of (with approximate

quantities/rates, wherever possible)

with source of information data

8.1 From explosions, spillages, fires etc. from

storage, handling, use or production of

hazardous substances

Yes Please refer as Annexure – VIII

8.2 From any other causes No

8.3 Could the project be affected by natural

disasters causing environmental damage

(e.g. floods, earthquakes, landslides,

cloudburst etc)?

No

9. Factors which should be considered (such as consequential development) which could lead to

environmental effects or the potential for cumulative impacts with other existing or planned

activities in the locality

Sr. No.

Information/Checklist confirmation

Yes/No

Details there of (with approximate

quantities/rates, wherever possible)

with source of information data

9.1 Lead to development of supporting. Lities, ancillary development or development stimulated by the project which could have impact on the environment e.g.

• Supporting infrastructure (roads, power

supply, waste or waste water treatment,

Yes For detail please refer Annexure – IX

Page 10: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

9

10.Environmental Sensitivity

Sr. No.

Areas Name/

Identity

Aerial distance (within 15km.)

Proposed project location boundary

1 Areas protected under international

conventions, national or local legislation for

their ecological, landscape, cultural or other

related value

- No protected area within 10 km from

the proposed expansion project site.

2 Areas which important for are or sensitive

Ecol logical reasons – Wetlands,

watercourses or other water bodies, coastal

zone, biospheres, mountains, forests

Gulf of

Kutchh

Coastal water is 10.8 Km away from

the project site.

3 Area used by protected, important or

sensitive Species of flora or fauna for

breeding, nesting, foraging, resting, over

wintering, migration

- No protected area or sensitive

species within 10 km from the

proposed expansion project site.

4 Inland, coastal, marine or underground

waters

Gulf of

Kutchh

Coastal water is 10.8 Km away from

the project site.

5 State, National boundaries

- State boundary = 235 km

National boundary = 138 km

6 Routes or facilities used by the public for

access to recreation or other tourist, pilgrim

areas

- N.A.

7 Defense installations - N.A.

8 Densely populated or built-up area Mokha Mokha is around 1.9 km from the

proposed expansion project site.

9 Area occupied by sensitive man-made land

uses Hospitals, schools, places of worship,

community facilities)

- N.A.

10 Areas containing important, high quality or

scarce resources (ground water resources,

surface resources, forestry, agriculture,

fisheries, tourism, minerals)

- N.A.

etc.)

• housing development

• extractive industry

• supply industry

• other

9.2 Lead to after-use of the site, which could

have an impact on the environment

No

9.3 Set a precedent for later developments No

9.4 Have cumulative effects due to proximity to

other existing or planned projects with

similar effects

No

Page 11: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

10

Page 12: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

11

LIST OF ANNEXURES

SR. NO. NAME OF ANNEXURE

I List of products with their production capacity

II Layout Map of the Plant

III Brief Manufacturing Process Description with Chemical and Mass Balance

IV Details of Water Consumption Wastewater Generation

V Effluent Treatment Scheme

VI Details of Hazardous /Solid Waste Generation, Handling and Disposal

VII Details of Air pollution Control System (Stack & Vent)

VIII Details of Storage of Hazardous Chemicals

IX Socio-economic Impacts

X Proposed Terms of Reference for EIA studies

Page 13: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

12

ANNEXURE – 1

LIST OF PRODUCTS WITH THEIR PRODUCTION CAPACITY

SR.

NO. PRODUCT NAME

EXISTING

CAPACITY

ADDITIONAL

CAPACITY

TOTAL

( MT/MONTH )

1 Carbon Black

10950 Phase – I: 2400

Phase – II: 2400

Phase – I: 13350

Phase – II: 15750

2 Co-generation Power

(waste gas base)

22 MW

Phase – I: 2 MW

Phase – II: 6 MW

Phase – I: 24 MW

Phase – II: 32 MW

LIST OF RAW MATERIALS

SR.

NO. RAW MATERIAL NAME

EXISTING

CAPACITY

ADDITIONAL

CAPACITY

TOTAL

( MT/MONTH )

1

CBFS 19500 Phase – I: 4286

Phase – II: 4286

Phase – I: 23786

Phase – II: 28072

2

Molasses 66.66 Phase – I: 15

Phase – II: 15

Phase – I: 81.66

Phase – II: 96.66

3

Potassium Nitrate 5.5 Phase – I: 1.0

Phase – II: 1.0

Phase – I: 6.5

Phase – II: 7.5

Page 14: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

13

ANNEXURE – 2

PLANT LAYOUT

Page 15: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

14

ANNEXURE – 3

MANUFACTURING ACTIVITIES

Manufacturing Process Details

CARBON BLACK is manufactured from highly aromatic hydrocarbon oils, which are thermally cracked

at high temperature in specially designed reactor. The heat for this endothermic thermal cracking is

supplied by either burning of partial Carbon Black feedstock oil or auxiliary fuel oil with process air

inside the reactor itself or both. Carbon Black particles formed are recovered and converted into

pellets for ease of storage, handling and transportation.

The complete manufacturing process has following sections:

Feedstock storage and pumping

Reactor section

Process Bag Collector section

Pelletization and drying section

Vapor Bag Collector section

Conveying and storage section

Packing and dispatch section

Energy Conservation Section (CPP)

Utility section

A brief description of each section is given below to understand the process in totality.

Feedstock Storage And Pumping:

Carbon Black feedstock / auxiliary fuel received from the refineries or from coal tar distillation units

in road tankers are unloaded into the feedstock or auxiliary fuel storage tanks separately. Since the

feedstock is quite viscous in nature, special type of pumps and steam heating of the fluid is required

for ease of handling and pumping.

Feedstock is stored in large CS fixed roof tanks and maintained at about 60-80oC. temp. in the tank

through external steam heating or hot feedstock return from the plant.

Feedstock or auxiliary fuel is supplied to the plant at high pressure through pumps suitable for

handling high viscosity fluids. The feedstock is filtered through a line mesh strainers / filters to

remove extraneous materials.

Feedstock header pressure is maintained by automatic controls by means of suitable control valves

and controlling stations.

Reactor Section:

Various grades of Carbon Black which are mentioned below, can be produced in the oil FURNACE

BLACK PROCESS under varying reaction conditions.

N115 N121 N134 N220 N326 N330 N339 N375 P824 P1201

N550 P435 N650 N660 N774 N762 N772 N765

Preheated feedstock of about 250-350oC. is finally atomized and sprayed inside the reactor through

specially designed nozzles made of special material. The reaction chamber which is lined with high

temperature special refractory is at a temp. of approx. 2000oC - 2500

oC. at a pressure of

0.5kg./sq.cm.

Page 16: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

15

Burning of auxiliary fuel and partial burning of feedstock oil in case of HB reactor in presence of air

inside the reactor raise the temp. to 2000 - 2500oooC and provide the endothermic heat for thermal

cracking reaction. The reaction products moving at very high velocities are quenched with water

sprays at predetermined locations inside the reactor to about 900 to 1100oC. Sufficient length of

refractory lined tunnel downstream of the reactors is provided for complete vaporization of quench

water. Energy from this hot stream is recovered by heat transfer from gases laden with carbon black

particles to cold air in a specially designed air pre heater. The hot air at 800-950oC. is used in the

reactor thereby making substantial savings in the fuel requirements in the reactor operation.

Feedstock oil is heated in SS heat exchangers for raising its temp. to 250-350 degree centigrade for

better atomization and hence increasing the process efficiency.

Product gases laden with Carbon Black particles (now hereafter referred as smoke) are cooled down

to 240-260 degree centigrade in a SS ventury cooler and they enter the PBC section for separation of

Carbon Black from gaseous products (a mixture of CO, CO2, CH4, C2H2, N2, H2, Air and water

vapors).

Process Bag Collector Section:

Process Bag Collector is Pulse Jet Filter and comprises of number of modular compartments.

Compartments are housed with very special type of filter bags made of fiber glass / Huyglass /

membrane coated fiber glass. The bags have only top opening and are fixed securely to the cell

plate along with venturi.

Smoke coming from reactor section at 240-260oC. enters the process bag collectors, CB particles are

deposited outside the bags and Clean gas filters off and goes to “off gas header”.

Cleaning of filter bag is done by high pressure air pulse. The deposited CB particles out side the filter

bags drop down into the hopper.

CB material collected in hoppers is conveyed through pneumatic conveying fans and Dense Bag

Collector to a surge tank for pelletizing and drying section. Before conveying, the material passes

through a micro pulverizer, which crushes some hard carbonaceous particles to – 325 mesh.

Off gases collected in the off gas header are sent to pelleting and drying section and energy

conservation section for their 100% utilization and thus eliminate the risk of atmospheric pollution.

Pelletizing and Drying Section:

Carbon Black material collected in a large SS316 L surge tank is sent to a pelletizer at a constant rate

through a variable speed rotary valve where it is mixed with water and molasses solution to form

strong wet pellets.

Pelletizer is specially designed equipment and is equipped with a rotating shaft fixed with sharp edge

pins in a double / triple helix configuration. The close gap between the pins and the inner smooth

surface of pelletizer accompanied by the conveying and rotating action of pins converts the mixture

of CB particles and water in to wet and strong spherical pellets.

These wet pellets are fed into a long rotary SS dryer. Pellets are dried inside the hot rotating dryer

by slow tumbling, agitating and falling action without damaging the pellets. Dryer shell is enclosed in

a refractory / Ceramic lined box all along its length and the heat is supplied by burning of off gases

received from the PBC section in a specially designed refractory lined combustion furnace.

Dry pellets with moisture less than 0.5% exit at the other end of the dryer for storage in the silos.

Modern techniques and reliable electronic instruments are used in this section to give a dried

pelleted product of consistent quality at all times and make the process smooth and efficient.

Vapor Bag Collector Section:

Water evaporated due to drying of wet pellets in the dryer along with some powdered material is

removed by a Vapor Fan at the feed end of the dryer. These hot gases are sent to a cylindrical bag

Page 17: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

16

filter house called Vapor Bag Collector to remove and collect the CB particles and let out into the

atmosphere very clean, purge gases. Vapor Bag Collector is also equipped with special bags for

filtration of CB particles.

Carbon Black collected in the conical hopper is fed to the conveying line which gets mixed with the

main stream.

Conveying and Storage Section:

Dried pellets coming out at the exit end of the dryer are fed into a bucket elevator made of SS

buckets to carry the material to the top of the silos. The material can be fed into any of the silos via

SS screw conveyors located on the top of silos. These silos are made of MS but epoxy / SS lined from

inside to prevent contamination of product during storage.

Packing & Dispatch Section:

Material stored in the silos is packed in 25kg. paper bags / Bulk Bags through automatic packing

machines. The portable packing machines can be connected to any of the storage silos. Fully

automatic packing machine along with the moving roller conveyors and bag shapers make the

handling of paper bags very fast, convenient and clean. Packed bags are stacked on wooden pellets

in warehouse for storage and subsequent dispatch in trucks to the consumers.

Energy Conservation Section:

Low Btu off gases generated in the manufacturing process of CB in the reactor section and separated

from accompanying CB particles in PBC section are collected in the off gas header. In spite of their

low calorific value, these gases can be utilized to recover their calorific value in a specially designed

boiler system to generate high pressure steam and in a specially designed dryer combustor furnace

to supply the heat energy requirements in the pelletizing and drying section.

The quantum of high pressure steam which can be generated through burning of these off gases

meets the plant requirement of steam and power. Excess power generated is sent to the Grid.

So the benefit of above scheme is being fully taken care of by installing the following system:

1. High pressure boiler system

2. Turbo Generators

3. Power Export

High pressure boiler which can be run on a combination of off gases and fuel oil or Off gas alone

generates high pressure super heated steam at 85 kg./sq.cm.

This high-pressure steam is used to generate sufficient power required for plant consumption

through turbo generator system and excess power is sent to the Grid. The scheme also helps in

eliminating the atmospheric pollution problem which would have been caused had complete

utilization of off gas were not made.

Utilities Section:

Utilities section has following major systems which meet the requirement of various sections at

different locations:

a. Instrumentation Air System.

b. Compressed Air system at 7.0 kg./sq.cm. pressure.

c. Raw water

d. Fire fighting system

e. Cooling water system

f. De Minerlized water system

g. R O System

These systems are provided with necessary equipments eg. Pumps, blowers, compressors, tanks,

towers etc. as necessary.

Page 18: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

Figure is a flow diagram for a typical one tread reactor unit.

Figure is a flow diagram for a typical one tread reactor unit.

17

Page 19: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

18

There are many reactions occurring in the process after feedstock injection until the point of quenching. Note that the CO2 in the shift reaction and the consumption by CO2 reaction comes from the combustion of fuel in the combustion section of the reactor. These reactions are complicated and only a summary is listed below:

a. Dehydropenation of Oil

CXHY = X/8 C8H + (Y/2 -X/16) H2

Feedstock goes to carbon black plus hydrogen

b. Combustion of Oil

CXHY + (X/2 + Y/4) O2 = xCO + Y/2 H2O

Feedstock plus oxygen goes to carbon monoxide plus water

c. Methane Production

CXHY + (2X - Y/2) H2 = xCH4

Feedstock plus hydrogen goes to methane

d. Acetylene Production

CXHY+((X-Y)/2)H2 = X/2C2H2

Feedstock plus hydrogen goes to acetylene

e. Shift Reaction

CO2 + H2 = CO + H2O

Carbon dioxide plus hydrogen goes to carbon monoxide plus water

Carbon Black Consumption by CO2

8CO2= I6CO+I/2H2

Carbon black + carbon dioxide goes to carbon monoxide + hydrogen

g. Carbon Black Consumption by H2O

CaH + 8H2O = 8 CO + 8 1/2 H2

Carbon black + water goes to carbon monoxide plus hydrogen

h. Acetylene Consumption

4 C2H2 = CsH + 7/2 H2

Acetylene decomposes to carbon black and hydrogen

f.

Page 20: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

19

Material Balance - Line-3

Description Unit Value

LINE CAPACITY Mt/d 160.00

CBFS (Primary Feed Stock) Mt/Mt CB 1.56

SFS (Secondary Feed Stock) Mt/Mt CB 0.21

Reactor Stage

Inputs

CBFS (Primary Feed Stock) Mt/d 249.60

SFS (Secondary Feed Stock) Mt/d 33.60

Air NM3/h 25000

NM3/d 600000

Mt/d 776.79

Atomizing Steam (Optional) Mt/d 14.40

Quench Water (DM / RO)) m3/d 200.00

Additive KNO3 mt/d 0.08

Atomizing Air Nm3/h 800

Nm3/day 19200

Mt/d 24.86

1274.47

Output

Carbon Black mt/d 160.00

Off Gas mt/d 1114.47

1274.47

Venturi Cooler Stage

Input

Carbon Black mt/d 160.00

Offgas mt/d 1114.47

Quench Water m3/d 72.00

1346.47

Output

Carbon Black mt/d 160.00

Offgas mt/d 1186.47

1346.47

PBC Stage

Input

Carbon Black mt/d 160.00

Offgas mt/d 1186.47

1346.47

Output

Carbon Black mt/d 160.00

Page 21: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

20

Offgas to Dryer Comb. mt/d 189.84

Offgas to Boiler mt/d 996.64

1346.47

Dryer Comb. Stage

Input

Offgas mt/d 189.84

Air (100 % of offgas ) mt/d 243.53

433.36

Output

Flue Gas mt/d 433.36

Pelleting Stage

Input

Carbon Black mt/d 168.00

Water mt/d 167.20

Molasses mt/d 0.80

336.00

Output

Wet Carbon Black 336.00

Rotary Dryer

Input

Wet Carbon Black mt/d 336.00

Flue Gas mt/d 433.36

769.36

Output

Dry Carbon Black Pellets mt/d 160.00

Flow To VBC mt/d 262.67

To dryer Stack mt/d 346.69

769.36

Boiler

Input

Off Gas in mt/d 996.64

Air (100 % of offgas ) mt/d 1278.51

2275.15

Output

Flue Gas to Stack mt/d 2275.15

*****************************************************************************

Page 22: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

21

ANNEXURE - IV

WATER CONSUMPTION AND WASTEWATER GENERATION

EXISTING:

ADDITIONAL PROPOSED:

TOTAL AFTER PROPOSED EXPANSION:

SR.

NO.

EXISTING (m3/day)

WATER

CONSUMPTION

WASTE WATER

GENERATION

1. Domestic 50 45

2. Process 604 Nil

3. Boiler 183 50

4. Cooling & Chilling 227 116

5. Washing 100 100

6. Gardening 36 Nil

Total 1200 311

SR.

NO.

PROPOSED SECTION (m3/day)

WATER

CONSUMPTION

WASTE WATER

GENERATION

1. Domestic 10 8

2. Process 500 Nil

3. Boiler 115 44

4. Cooling & Chilling 150 8

5. Washing 20 20

6. Gardening 34 Nil

Total 829 80

SR.

NO.

PROPOSED SECTION (m3/day)

WATER

CONSUMPTION

WASTE WATER

GENERATION

1. Domestic 60 53

2. Process 1104 Nil

3. Boiler 298 94

4. Cooling & Chilling 377 124

5. Washing 120 120

6. Gardening 70 Nil

Total 2029 391

Page 23: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

22

WATER BALANCE DIAGRAM:

Total Water: 2029 KL/Day (Fresh: 1691 KL/Day +

Recycled: 338 KL/Day )

Process:

1104

KL/Day Cooling & Chilling:

377 KL/Day

(268 KL/Day

Recycled + 109

KL/Day Fresh)

Boiler (DM,

RO etc):

298 KL/Day

Washing:

120 KL/Day

Gardening:

70 KL/Day

(Recycled:

70 KL/Day)

Domestic

: 60

KL/Day

124

KL/Day

94

KL/Day 120 KL/Day

53 KL/Day: Septic

tank & Soak Pit 338 KL/Day � ETP

338 KL/Day

268

KL/Day

70

KL/Day

120

KL/Day

1104

KL/Day

109

KL/Day

298

KL/Day

0

KL/Day

60

KL/Day

253 KL/Day

Drift &

Evap loss

Page 24: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

23

ANNEXURE - V

EFFLUENT TREATMENT PLANT

M/s. Phillips Carbon Black Ltd. shall have an Effluent treatment plant consisting of primary

and tertiary treatment units in existing and proposed ETP. The details of ETP are as follows.

� Effluent Treatment Plant (Line-1):

(A) Effluent Treatment Plant Units

Unit

no. Unit name Unit size

1 Equalization Tank 4.0 MX 3.0 M X (2.5 S.W.D + 0.75 /L + 0.5 F.B.)M

2 Oil & Grease Trap 2.0 M X 1.25 M X (1.7 S.W.D + 0.3 F.B.) M

3 Live Flash Mixer 0.75M X 0.75 M X (0.75 S.W.D + 0.25 F.B.) M

4 Alum Flash Mixer 0.75 M X 0.75 M X (0.75 S.W.D + 0.25 F.B.) M

5 Flocculator Chamber 1.5 M X 1.25 M X (1.5 S.W.D + 0.5 F.B.) M

6 Lamella Tube Settler 1.5 M X 1.25 M X (2.2 S.W.D + 0.3 F.B.) M

7 Cont Liver Platform 2.5 M+1.5 M

8 Intermediate Collection Tank 3.0 MX 3.0 M X (3.25 S.W.D + 0.5 F.B.) M

9 Filter Foundation 3.0 M X 1.5 MX 0.5 M

10 Sludge Drying Bed ( 4 Nos.) 2.0 M X 2.0 M X (1.2 S.W.D + 0.3 F.B.) M

11 Multi Grade Pressure Sand Filter 0.75M DIA X 2.0 M HT

12 Activated Carbon Filter 0.6 M DIA X 2.0 M HT

13 Raw Material Store 3.0 M X 4.0 MX 3.0 M

14 Hazardous Material Storage Room 3.0 MX4.0 MX 3.0 M

(B) Effluent Treatment Scheme:

We have installed Effluent Treatment Plant for the treatment of the wastewater generated

from the Industrial unit. Waste water is treated into Effluent Treatment Plant and around

Page 25: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

24

70% treated effluent is recycled for cooling tower, compressors, blowers and remaining is

utilized for gardening and plantation purpose. Details of the same are as under.

Based on the fact that the generated wastewater mainly contains the oil and grease, the

following treatment scheme is given in ETP:

Based on quality of wastewater, we have installed only physiochemical treatment process,

in which the raw effluent is treated with chemicals like lime, alum and polyelectrolyte.

� The raw wastewater is entered into the oil and grease chamber which is provided with

baffle wall to remove oil and grease.

� Then after wastewater is collected into underground equalization tank, which is equipped

with air purging system to keep the particulate matter in suspension.

� An Effluent Transfer Pump is transferred the effluent from Equalization Tank to Flash Mixer

where simultaneously lime dosing takes place.

� From the Flash mixture the effluent is then transferred to the flocculation chamber where

gradual dosing of alum and polyelectrolyte is done. This Mixture is then transferred to

Primary Settling Tank.

� The sludge from Primary Settling Tank is transferred to the Sludge Drying Beds through

sludge sump. The sludge after drying is disposed off to secured Landfill site.

� Leachate from the Sludge Drying Beds is collected and directed to equalization tank for

further treatment.

Page 26: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

25

.

.

Oil & Grease

Trap

Equalization

Tank Live fresh mixer Flocculation

chamber

lime Alum

Primary settling

Tank

Sludge Pump

Sludge Drying

beds.

Multi Grade

Pressure Sand

Filter

Activated Carbon

FilterTreated Water

Collection Tank

Reuse in Gardening and

Process

Treated Water Collection Tank

Leachate

Leachate

(C) Schematic Flow Diagram of Effluent Treatment Scheme:

Page 27: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

26

Effluent Treatment Plant (Line-2):

(A) Effluent Treatment Plant Units

Sr.

No. Unit Qty.

Hydraulic

Volume,

(m3)

Overall Size

(m)

1. Oil & Grease Trap 1 12.0 4.0 x 2.0 x1.5 SWD+1.5 FB

2. Collection cum

Equalization Tank 2

48.0

(Each) 4.0 x 4.0 x3.0 SWD+1.5 FB

3. Chemical Solution Tanks 3 1.0

(Each) 1.0 x 1.0 x1.0 SWD+0.5 FB

4. Flash Mixing Tank 1 3.0 1.8 x 1.5 x1.1 SWD+0.4 FB

5. Flocculation Tank 1 10.0 2.25 x 2.25 x2.0 SWD+0.4 FB

6. Primary Clarifier 1 126.0 8.0 Φ x 2.5 SWD+0.3 FB+0.6 SD

7. Sludge collection tank 1 9.0 3.0 x 2.0 x 1.5 SWD+0.5 FB

8. Primary Treated effluent

collection tank 1 48.0 4.0 x 4.0 x 3.0 SWD+0.5 FB

9. Final Treated Effluent

Collection Tank 1 48.0 4.0 x 4.0 x 3.0 SWD+0.5 FB

10. Sludge Drying Beds 8 4.5 (Each) 3.0 x3.0 x 1.5

11. Leachate collection tank 1 2.4 1.2 x 2.0 x 1.0 SWD+1.5 FB

(B) Effluent Treatment Scheme:

Effluent Treatment Plant consists of primary with physico-chemical treatment followed by

sludge settling and tertiary treatment to achieve the discharge norms prescribed by GPCB

for the treated effluent. The detailed effluent treatment scheme is given hereunder.

� OIL AND GREASE TRAP

The wastewater generated from various processes is first passed through oil & Grease

chamber where emulsified oil, grease and other floating matter is removed/skimmed off

manually.

� COLLECTION CUM EQUALIZATION TANK

After removal of oil and floating matter, effluent is collected in collection cum equalization

tank through network of pipe by means of gravity. The effluent is thoroughly mixed by

Page 28: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

27

supplying compressed air through aeration grid placed at the bottom of the tank. Lime is

added to the effluent as a coagulant in this tank. The effluent is then pumped to the Flash

Mixing Tank.

� CHEMICAL DOSING TANKS

The chemical dosing tanks are provided for the preparation of chemical solution required

for the primary treatment such as hydrated lime, alum and polyelectrolyte.

� FLASH MIXING TANK

Alum solution is added to the effluent in the flash mixer. Here coagulants are properly

mixed with the effluent by means of stirrer. Effluent is then flow by gravity into the

Flocculator.

� FLOCCULATOR

Polyelectrolyte solution is added as a flocculent in this tank. It helps to form large and dense

flocs of settlable solids which can easily settle. From here all the mass is taken by gravity

into the primary clarifier.

� PRIMARY CLARIFIER

The effluent from flocculation tank is flow by gravity to Primary clarifier. Here the effluent is

retained for certain period in a relatively quiescent state. Thus, chemical flocs are settled

down at the tank bottom. The settled sludge from bottom is drained to the sludge drying

bed.

� PRIMARY TREATED WATER COLLECTION TANK

The clear supernatant effluent from clarifier tank overflow is collected here for further

polishing tertiary treatment. From this tank, effluent is pumped to the Pressure Sand Filter

by means of high pressure pump.

� PRESSURE SAND FILTER

Pressure Sand Filter consists of graded quartz free sand supported on gravel and pebble

bed. This acts as a packing material and also protect the under drainage system. Here

remaining suspended solids are removed from the effluent. Pressure sand filter needs to be

cleaned periodically to remove accumulated solids. This is done by backwashing the filter

Page 29: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

28

using fresh water in reverse flow sequence. The backwash water flows back to collection

cum equalization tank for treatment.

� ACTIVATED CARBON FILTER

Activated Carbon Filter consists of bed made of coconut shell based activated carbon. The

carbon bed is provided over the sand bed and is supported on gravel and pebble bed. This

acts as a packing material and protect the under drainage system. The effluent from the

outlet of pressure sand filter is passed through activated carbon filter where final polishing

of the effluent is done to remove the suspended solids, color, odour and other organic

impurities. Activated carbon filter needs to be cleaned periodically to remove accumulated

solids. This is done by backwashing the filter using fresh water in reverse flow sequence. The

backwash water flows back to collection cum equalization tank for treatment.

� FINAL TREATED WATER COLLECTION TANK

Treated effluent from tertiary treatment is collected in this tank and is utilized for land

irrigation within premises.

� SLUDGE DRYING BEDS

The settled sludge at the bottom of primary clarifier tank is drained into Sludge drying beds.

Here water from the sludge is filtered through the bed and filtrate is taken back to the

collection cum equalization tank for further treatment. The sludge after drying is collected

and stored in to hazardous water storage area and ultimately disposed of at hazardous

waste disposal site.

Page 30: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

29

ETP FLOW DIAGRAM

Page 31: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

30

Characteristics of Effluent

Date of Sampling : 24/06/2015

Sr. No Parameters Result of Phase-I

Plant

Result of Phase-II Plant GPCB Norms

Raw

Inlet

Treated

Outlet

Raw

Inlet

Treated

Outlet

1. pH 6.67 7.32 7.1 7.34 6.5 to 8.5

2. Temperature, °C 32 32 32 32 40

3. Color, Pt.Co. Scale 1 1 1 1 100

4. Suspended Solids, mg/L 172 90 233.2 85 100

5. Total Dissolve Solids, mg/L 1744.25 2080.4 2530 2030 2100

6. COD, mg/L 144.312 94.312 268.088 88.624 100

7. BOD3, mg/L 45.20 25.42 40.49 22.29 30

8. Chlorides, mg/L 1408.358 587.106 1462.525 592.52 600

9. Sulphates, mg/L 268.875 236.61 243.063 162.4005 1000

10. Oil & Grease, mg/L 8.0 2.0 7.2 1.0 10

11. Ammonical Nitrogen, mg/L 50.4 10.08 42.56 12.88 50

12. Total Chromium, mg/L BDL BDL BDL BDL 0.2

13. Hexavelent Chromium,

mg/L

BDL BDL BDL BDL 0.1

14. Copper, mg/L BDL BDL BDL BDL 1.0

15. Iron, mg/L BDL BDL BDL BDL 1.0

16. Phenolic compounds,

mg/L 1.2 0.7 1 0.54

1.0

17. Sodium Absorption Ratio 22.71 19.34 29.87 19.2 26

18. % Na 58.28 55.88 57.36 52.01 60 %

Page 32: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

31

ANNEXURE-VI

DETAILS OF HAZARDOUS & SOLID WASTE GENERATION & DISPOSAL

SR.

NO.

NAME OF

WASTE

WASTE

CATEGORY

EXISTING QTY.

MT/YEAR

ADDITIONAL

QTY.

MT/YEAR

TOTAL MODE OF DISPOSAL

1 Used Oil I-5.1 1.56 0.64 2.20 Collection, Storage,

Transportation, reuse

in process/sent to

GPCB registered

recycler

2 Spent Acid from

Batteries

I-36.3 0.024 0.00 0.024 Collection, Storage,

Transportation,

Disposal by Authorized

way

3 Chemical Sludge

from Waste water

treatment

I-34.3 27.00 8 35 Collection, Storage,

Transportation,

Disposal at TSDF site

of SEPPL.

4 Oily Sludge

Emulsion

I-4.1 6.0 0 6 Collection, Storage,

Transportation,

Disposal at Common

Incineration site of

SEPPL – Bhachau

5 Used Batteries 17 0.1

(CCA

Amendment

Applied)

0 0.1 Collection, Storage,

Transportation, and

Disposal as per lead

batteries rules.

6 Discarded Drum /

Barrels/

Containers / Bags/

Liners

33.3 8

(CCA

Amendment

Applied)

4 12 Collection, Storage,

Transportation, sent to

GPCB Approved

recycler

Page 33: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

32

7 Plastic Waste X-9 0.5

(CCA

Amendment

Applied)

0.5 1 Collection, Storage,

Transportation, sent to

GPCB Approved

recycler.

8 Spent Ion

Exchange Resin

34.2 0.4

(CCA

Amendment

Applied)

0.2 0.6 Collection, Storage,

Transportation,

Disposal at TSDF site.

9 Oily Cotton Waste

/Leather Hand

Gloves / Cotton

Hand Gloves

33.2 0.4

(CCA

Amendment

Applied)

0.1 0.5 Collection, Storage,

Transportation, and

Disposal by

incineration at SEPPL –

Bhachau.

10 E-Waste 18.5 0.5

(CCA

Amendment

Applied)

0.2 0.7 Collection, Storage,

Transportation, sent to

GPCB Approved

Recycler

11 Waste Insulation

Material

- 1

(CCA

Amendment

Applied)

0.5 1.5 Collection, Storage,

Transportation, and

Disposal by

incineration at SEPPL –

Bhachau

Page 34: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

33

ANNEXURE-VII

DETAILS OF AIR POLLUTION CONTROL SYSTEM

1) Flue Gas Stack (Existing)

Note: Process Flare Stack is used only in case of emergency.

2) Process Stack (Existing)

SR.

NO.

PROCESS STACK

ATTACHED TO

HEIGHT FROM

GROUND (m)

DIAMETER

(m)

AIR POLLUTION

CONTROL SYSTEM

EXPECTED

POLLUTANTS

1 VBC- 1 50 1.0 Bag Filter SPM,SOx, NOx

2 VBC- 2 50 1.0 Bag Filter SPM, SOx, NOx

3 Dryer -1 50 1.1 Bag Filter SPM, SOx, NOx

4 Dryer -2 50 1.1 Bag Filter SPM, SOX, NOx

3. Flue Gas Stack (Proposed):

4. Process Stack (Proposed)

SR.

NO.

PROCESS

STACK

ATTACHED TO

HEIGHT

FROM

GROUND (m)

DIAMETER

(m)

AIR

POLLUTION

CONTROL

SYSTEM

EXPECTED

POLLUTANTS

1 VBC- 3 50 1.0 Bag Filter SPM, SOX, NOx

2 Dryer -3 50 1.1 Bag Filter SPM, SOx, NOx

SR.

NO. STACKS ATTACHED TO

HEIGHT FROM

GROUND LEVEL (m)

CONSUMPTION

OF FUEL

(KL/hr)

DIAMETER

(m)

EXPECTED

POLLUTANTS

1 Process Plant –Flare stack 50 NIL 1.0 SPM, SOx, NOx

2 CPP 16MW–Boiler Chimney 80 Nil 2.5 SPM, SOx, NOx

3 CPP 6MW–Boiler Chimney 80 Nil 1.8 SPM, SOx, NOx

SR.

NO. STACKS ATTACHED TO

HEIGHT FROM

GROUND LEVEL (m)

CONSUMPTION

OF FUEL

(KL/hr)

DIAMETER

(m)

EXPECTED

POLLUTANTS

1 Process Plant –Flare stack 50 Nil 1.5 SPM, SOx, NOx

2 CPP 8 MW–Boiler Chimney 80 Nil 1.8 SPM, SOx, NOx

Page 35: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

34

Total:

1) Flue Gas Stack

2) Process Stack

SR.

NO.

PROCESS STACK

ATTACHED TO

HEIGHT FROM

GROUND (m)

DIAMETER

(m)

AIR POLLUTION

CONTROL SYSTEM

EXPECTED

POLLUTANTS

1 VBC- 1 (Existing) 50 1.0 Bag Filter SPM, SOx, Nox

2 VBC- 2 (Existing) 50 1.0 Bag Filter SPM, SOx, Nox

3 Dryer -1 (Existing) 50 1.1 Bag Filter SPM, SOx, Nox

4 Dryer -2 (Existing) 50 1.1 Bag Filter SPM, SOx, Nox

5 VBC- 3 (Proposed) 50 1.0 Bag Filter SPM, SOx, Nox

6 Dryer -3 (Proposed) 50 1.1 Bag Filter SPM, SOx, Nox

SR.

NO. STACKS ATTACHED TO

HEIGHT FROM

GROUND LEVEL (m)

CONSUMPTION

OF FUEL

(KL/hr)

DIAMETER

(m)

EXPECTED

POLLUTANTS

1 Process Plant –Flare stack

(Existing)

50 Nil 1.0 SPM, SOx, NOx

1 Process Plant –Flare stack

(Proposed)

50 Nil 1.5 SPM, SOx, NOx

3 CPP 16 MW–Boiler Chimney

(Existing)

80 Nil 2.5 SPM, SOx, Nox

4 CPP 6 MW–Boiler Chimney

(Existing)

80 Nil 1.8 SPM, SOx, Nox

5 CPP 8 MW–Boiler Chimney

(Proposed)

80 Nil 1.8 SPM, SOx, Nox

Page 36: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

35

Flue Gas/Process Stack Analysis Report

1st

Analysis Results

Sr. No.

Parameters GPCB limit Results

Flare Stack Boiler

(6 MW)

Boiler

(16MW)

D.G. Set

1. Particulate Matter 150 mg/NM3 127 141 79 121

2. SO2 100 ppm 19.87 25.56 38.35 4.56

3. NOx 50 ppm 11.3 12.64 10.87 3.35

2nd

Analysis Results

Sr. No.

Parameters GPCB limit Results

Drier 1

Drier 2

VBC 1

VBC 2

1. Particulate Matter 150 mg/NM3 140 79 85 77

2. SO2 100 ppm 42 47 57 50

3. NOx 50 ppm 8.9 7.8 9.7 8.1

Page 37: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

36

ANNEXURE – VIII

DETAILS OF HAZARDOUS CHEMICALS (EXISTING + PROPOSED)

Sr.

No

.

Name of

the

Material

Type of

Hazard

Kind of

Storage

Max.

quantity

to be

stored

(MT)

Storage

condition

i.e. temp.,

pressure

Tank

Dimensions in

(m)

Dyke

Dimensions

(m)

1 Caustic

Soda

Health

Hazard

Horizontal

cylindrical

Tank

17 Ambient &

Atmospheric

2.4 mtr dia x 3.77

mtr lenght

6.25 x 3.27 x 0.23

2 Hydrochlo

ric Acid

Health

Hazard

Horizontal

cylindrical

Tank

13 Ambient &

Atmospheric

2 mtr dia x 4.15

mtr lenght

6.51 x 6.35 x 0.23

3 CBSF OIL Fire

Hazard

Fixed Roof

Cylindrical

32400 80 &

Atmospheric

1. 9000 KL

x2 = dia

25 x ht

18 mtr

2. 2300

KLx6 =

dia 13 x

ht 18

mtr

3. 600 kl x1

= dia 8.0

x ht 11

mtr

90 x 90 x 1.2 mtr

4 LDO Fire

Hazard

Fixed Roof

Cylindrical

136 Ambient &

Atmospheric

dia 5.4 x

ht 6.0

mtr

5 HSD Fire

Hazard

Fixed Roof

Cylindrical

35 Ambient &

Atmospheric

dia 3.0 x

ht 5.0

mtr

Page 38: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

37

ANNEXURE – IX

SOCIO - ECONOMIC IMPACTS

1) Employment Opportunities

The manpower requirement for the proposed project is being expected to generate some

permanent jobs and secondary jobs for the operation and maintenance of plant. This will increase

direct / indirect employment opportunities and ancillary business development to some extent for

the local population.

This phase is expected to create a beneficial impact on the local socio-economic environment.

2) Industries

Required raw materials and skilled and unskilled laborers will be utilized maximum from the local

area. The increasing industrial activity will boost the commercial and economical status of the

locality, to some extent.

3) Public Health

The company regularly examines, inspects and tests its emission from sources to make sure that the

emission is below the permissible limit. Hence, there will not be any significant change in the status

of sanitation and the community health of the area, as sufficient measures have been taken and

proposed under the EMP.

4) Transportation and Communication

Since the existing factory is having proper linkage for the transport and communication, the

development of this project will not cause any additional impact. In brief, as a result of the

expansion there will be no adverse impact on sanitation, communication and community health, as

sufficient measures have been proposed to be taken under the EMP. The proposed expansion is not

expected to make any significant change in the existing status of the socio - economic environment

of this region.

Page 39: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

38

ANNEXURE-X

______________________________________________________________________

PROPOSED TERMS OF REFERENCE FOR EIA STUDIES

1. Project Description

• Justification of project.

• Promoters and their back ground

• Project site location along with site map of 5 km area and site details providing various industries,

surface water bodies, forests etc.

• Project cost

• Project location and Plant layout.

• Water source and utilization including proposed water balance.

• Product spectrum (proposed products along with production capacity) and process

• List of hazardous chemicals.

• Mass balance of each product

• Storage and Transportation of raw materials and products.

2. Description of the Environment and Baseline Data Collection

• Micrometeorological data for wind speed, direction, temperature, humidity and rainfall in 5 km

area.

• Existing environmental status Vis a Vis air, water, noise, soil in 5 km area from the project site. For

SPM, RSPM, SO2, NOx.

• Ground water quality at 5 locations within 5 km.

• Complete water balance

3. Socio Economic Data

• Existing socio-economic status, land use pattern and infrastructure facilities available in the study

area were surveyed.

4. Impacts Identification And Mitigatory Measures

• Identification of impacting activities from the proposed project during construction and

operational phase.

• Impact on air and mitigation measures including green belt

• Impact on water environment and mitigation measures

• Soil pollution source and mitigation measures

• Noise generation and control.

• Solid waste quantification and disposal.

5. Environmental Management Plan

• Details of pollution control measures

• Environment management team

• Proposed schedule for environmental monitoring including post project

6. Risk Assessment

• Objectives and methodology of risk assessment

• Details on storage facilities

• Process safety, transportation, fire fighting systems, safety features and emergency capabilities to

be adopted.

• Identification of hazards

• Consequence analysis through occurrence & evaluation of incidents

• Disaster Management Plan.

Page 40: Form-I. 02.08.2016 - 1docxenvironmentclearance.nic.in/writereaddata/Online/TOR/04...3 (II) Activity 1. Construction, operation or decommissioning of the Project involving actions,

39

7. Information for Control of Fugitive Emissions

8. Post Project Monitoring Plan for Air, Water, Soil and Noise.

9. Information on Rain Water Harvesting

10. Green Belt Development plan