3
420 atw Vol. 58 (2013) Issue 7 | July Decommissioning Estimated decommissioning cost for the 23 operating nuclear power reactors in Korea Joo Hyun Moon, Gyeongju, Gyeongbuk/Rep. of Korea Address of the author: Professor Joo Hyun Moon, Ph. D Dept. of Nuclear & Energy System Engineering 707, Seokjang-dong, Gyeongju, Gyeongbuk, Rep. of Korea, 780-714 Introduction Nuclear power reactor need to be decom- missioned when they reach the end of its design life. Decommissioning is part of the final shutdown of a nuclear power reactor and starts with the removal of high radio- active spent fuel and may end with the clean-up of the entire facility or site includ- ing contaminated soil and groundwater in some rare cases [1]. The decommissioning process involves the demolition of build- ings and other structures, including the parts near the reactor core that might have become radioactive, as well as the on-site handling of construction materials (mostly steel and concrete) and the packaging and transport of these materials for safe stor- age and disposal. [2] As of December 2012, Korea has 23 op- erating nuclear power reactors, which are listed in Table 1. The operation license of Kori 1, which was the first commercial power nuclear reactor in Korea, was re- newed for 10 years in 2007. Currently, the application for an operation license renew- al of Wolsong 1 is under safety review. If Wolsong 1 does not pass the safety review, its operation will cease permanently and the decommissioning process will com- mence. Although 2 small nuclear research reactors were decommissioned early in 2000s, no commercial nuclear power reac- tor has been decommissioned in Korea. To prepare for the safe and efficient decom- missioning of nuclear power reactors, the Korean government has developed a relat- ed regulation system and advanced core technologies. The decommissioning of nuclear power reactors requires considerable funds and is performed over a long period. Conse- quently, the regulatory body requires the licensee of an operating nuclear power re- actor to provide reasonable assurance that the funds will be available for the decom- missioning process. This paper estimates the annual costs for decommissioning the 23 nuclear power plants in Korea be- tween 2014 and 2083 to forecast the total decommissioning funds needed by the li- censee as well as provide a basis for indus- trial strategy and decommissioning activi- ty planning. Tab. 1. Summary of the 23 nuclear power reactors in operation in Korea.

Decommissioning Estimated decommissioning Although 2 cost ... · Annual decommissioning cost estimates in Korea for Scenario 1. 422 atw Vol. 58 (2013) Issue 7 July Decommissioning

  • Upload
    others

  • View
    8

  • Download
    0

Embed Size (px)

Citation preview

  • 420 atw Vol. 58 (2013) Issue 7 | July

    Decommissioning

    Estimated decommissioning cost for the 23 operating nuclear power reactors in KoreaJoo Hyun Moon, Gyeongju, Gyeongbuk/Rep. of Korea

    Address of the author:Professor Joo Hyun Moon, Ph. D

    Dept. of Nuclear & Energy System Engineering707, Seokjang-dong, Gyeongju,

    Gyeongbuk, Rep. of Korea, 780-714

    Introduction

    Nuclear power reactor need to be decom-missioned when they reach the end of its design life. Decommissioning is part of the final shutdown of a nuclear power reactor and starts with the removal of high radio-active spent fuel and may end with the clean-up of the entire facility or site includ-ing contaminated soil and groundwater in some rare cases [1]. The decommissioning process involves the demolition of build-ings and other structures, including the parts near the reactor core that might have become radioactive, as well as the on-site handling of construction materials (mostly steel and concrete) and the packaging and transport of these materials for safe stor-age and disposal. [2]

    As of December 2012, Korea has 23 op-erating nuclear power reactors, which are listed in Table 1. The operation license of Kori 1, which was the first commercial power nuclear reactor in Korea, was re-newed for 10 years in 2007. Currently, the application for an operation license renew-al of Wolsong 1 is under safety review. If Wolsong 1 does not pass the safety review, its operation will cease permanently and the decommissioning process will com-

    mence. Although 2 small nuclear research reactors were decommissioned early in 2000s, no commercial nuclear power reac-tor has been decommissioned in Korea. To prepare for the safe and efficient decom-missioning of nuclear power reactors, the Korean government has developed a relat-ed regulation system and advanced core technologies.

    The decommissioning of nuclear power reactors requires considerable funds and is performed over a long period. Conse-quently, the regulatory body requires the licensee of an operating nuclear power re-actor to provide reasonable assurance that the funds will be available for the decom-missioning process. This paper estimates the annual costs for decommissioning the 23 nuclear power plants in Korea be-tween 2014 and 2083 to forecast the total decommissioning funds needed by the li-censee as well as provide a basis for indus-trial strategy and decommissioning activi-ty planning.

    Tab. 1. Summary of the 23 nuclear power reactors in operation in Korea.

  • 421atw Vol. 58 (2013) Issue 7 | July

    Decommissioning

    Estimation of the annual expected cost

    Only the 23 operating nuclear power reac-tors were considered when estimating the decommissioning costs. The original 2008 national basic energy plan intended that a total of 40 reactors would be operating by 2030. The plan was suspended due to the nuclear power plant accident in Japan on 11 March 2011 but may be continued.

    The unit decommissioning cost is need-ed to make an estimation of the total de-commissioning cost of a nuclear power re-actor. Therefore, the worldwide decom-missioning experience data for PWRs (Pressurized Water Reactors) and PHWRs (Pressurized Heavy Water Reactor) [3] was used. According to reference [3], the mean decommissioning cost for PWRs was  estimated to be approximately 320  US$/kWe in July 1st 2001 with a standard deviation of approximately 195 US$/kWe. The decommissioning cost esti-mates for PHWR were reported to range from 270 to 435 US$/kWe with a mean value of approximately 360 USD/kWe and standard deviation of less than 70 US$/kWe. All the cost estimates in US$ of 1st July 2002.

    Using the unit decommissioning cost in US$ of 2002 1st July and electrical pow-er  of each nuclear power reactor, the to-tal decommissioning costs of the 23 reac-tors were estimated without considering in-flation. For this estimation, the following assump-tions were made:[1] The first decommissioning of a nucle-

    ar power reactor will not be initiated until 2024 because the interim storage facility, where the spent nuclear fuel at the nuclear reactor to be decommis-sioned will be transferred, will not be secured until at that time. Therefore, if they fail to pass the safety review for a license renewal process, the decom-missioning of Wolsong 1 and Kori 1 will need to be delayed until the inter-im storage facility for nuclear spent fu-el is available.

    [2] The decommissioning of a nuclear power reactor will be performed over 3 consecutive phases including a pre-decommissioning phase (4 years), de-commissioning phase (9 years) and post-decommissioning phase (2 years). A. The pre-decommissioning phase

    consists of activities for permanent shut-down and decommissioning planning of a reactor.

    B. The decommissioning phase con-sists of engineering and licensing activities, dismantlement of the re-actor and waste management.

    C. The post-decommissioning phases consist of activities for completing the decommissioning process.

    [3] The decommissioning cost will be dif-ferent at each decommissioning phase, i.e. 15 % of the total decommis-sioning at pre-decommissioning phase, 75 % at decommissioning phase, and 10 % at post-decommis-sioning phase. Nevertheless, the cost will be spread evenly over the period of each phase.

    [4] The life of each reactor can be extend-ed by 10 years through the appropri-ate license renewal process. On the other hand, the number of license re-newals will be limited to 2 at most.

    Based on the above assumptions, the fol-lowing 4 scenarios for decommissioning the 23 nuclear power reactors were devel-oped because a national decommissioning policy for power reactors is yet to be made. Scenario 1: Wolsong 1 fails to pass the safety review of the license renewal appli-cation for a 10 year life extension. The op-eration of Wolsong 1 will cease and be un-der safe storage until 2024 when the inter-im storage facility of spent nuclear fuel can be secured and its decommissioning can be initiated. In this period, only the activities related to those in the pre-decommission-ing phase will be permitted. Kori 1, which was permitted to operate for a further 10 years in 2007, will also fail to additional li-cense renewal at 2017. The initiation of the decommissioning of Kori 1 will also be de-layed until 2024. The other 21 nuclear re-actors are assumed to obtain license re-newal for 10 more years after their design life is reached. Scenario 2: The 21 nuclear power reactors excluding Wolsong 1 and Kori 1 are as-sumed to obtain license renewal for 20 years after each design life. The other

    assumptions are the same as those in Sce-nario 1.Scenario 3: All 23 nuclear power reactors, including Wolsong 1 obtain one additional license renewal for 10 years. Kori 1 would not attempt to renew a second operation li-cense, and will enter the permanent shut-down phase. On the other hand, The initia-tion of the decommissioning of Kori 1 will also be delayed until 2024.Scenario 4: All 23 nuclear power reactors, including Wolsong 1 will obtain 2 addition-al license renewals for 20 years.

    Figures 1 to 4 present the annual de-commissioning cost estimates in US$ of Ju-ly 1st 2001 for the 4 scenarios.

    For Scenario 1, the real decommission-ing of Kori 1 and Wolsong 1 will be initiated in 2024. The annual decommissioning cost, in other word, the decommissioning market size between 2024 and 2034, will be incurred mainly by the first 2 reac-tors. In 2033, the pre-decommissioning phase of Kori 2 will be initiated. After that,  the decommissioning market size will  grow gradually, reaching a maxi-mum size of 249.4 MUS$ in 2046 due to the successive decommissioning of nuclear power reactors. The decommissioning market size will then decrease gradually until 2076 when decommissioning of the Shin Kori 2 and Shin Wolsong 1 are com-plete.

    For Scenario 2, decommissioning cost will be incurred from 2013 due to the start of pre-decommissioning phase of Wol-song 1. The annual market size from 2013 to 2032 will be the same as that of Scenar-io 1 because only 2 power reactors, Wolsong 1 and Kori 1, will be decommis-sioned. The main difference from Scenario 1 is that no  decommissioning will occur from 2036 to 2042. The pre-decommis-sioning phase of Kori 2 will not be started

    Fig. 1. Annual decommissioning cost estimates in Korea for Scenario 1.

  • 422 atw Vol. 58 (2013) Issue 7 | July

    Decommissioning

    until 2043. Compared to Scenario 1, the peak in the market size will be shifted to 2059 from 2046, and the decommission-ing of shin Wolsung 1 will be completed in 2086.

    For Scenario 3, the pre-decommission-ing phase of Kori 1 will start in 2017. After that, the annual decommissioning market size will grow gradually and reach a peak in 2046. Between 2047 and 2068, the an-nual decommissioning market will fluctu-ate. From 2017 to 2076, only the decom-missioning of Shin Kori 1 and Shin Wol-song 1 will be undertaken.

    For Scenario 4, the initiation of the pre-decommissioning phase of the first power reactor will be delayed by 10 years com-pared to that in Scenario 3. In addition, the peak in the annual decommissioning market will occur in 2055. The period dur-ing which power reactors are decommis-sioned will be prolonged by 10 years, and decommissioning of the Shin Kori 2 and Shin Wolsong 1 nuclear reactors will be completed in 2086.

    Conclusion

    This paper estimated the annual cost for decommissioning the 23 nuclear power plants in Korea between 2014 and 2083 to  forecast the total decommissioning funds that need to be secured by the licen-see as well as to provide a basis for an in-dustrial strategy and decommissioning ac-tivity planning. For this estimation, 4 sce-narios for decommissioning the 23 nucle-ar  power reactors were developed and evaluated. The estimations showed that the real decommissioning of the nu-clear power reactors could be initiated from 2024, whereas the operations of Ko-ri 1 and Wolsong 1 could be stopped sever-al years before 2024 because the interim storage facility of spent nuclear fuel would be secured. The large decommissioning market of more 100 million US$ of July 1st 2001 will be developed between 2038 and 2077.

    References

    [1] IAEA: Status of the decommissioning of nuclear facilities around the world. http://www-pub.iaea.org/MTCD/publi-cations/PDF/Pub1201_web.pdf, 2004.

    [2] Samseth, J., Banford, A., Batandjieva-Metcalf, B., Cantone M. C., Lietava, P., Peimani H., Szilagyi, A.: Closing and De-commissioning Nuclear Power Reactors: Another look following the Fukushima accident, UNEP Year Book 2012, 2012.

    [3] OECD/NEA: Decommissioning Nuclear Power Plants: Policies, Strategies and Costs, 2003.

    Fig. 2. Annual decommissioning cost estimates in Korea for Scenario 2.

    Fig. 3. Annual decommissioning cost estimates in Korea for Scenario 3.

    Fig. 4. Annual decommissioning cost estimates in Korea for Scenario 4.