Upload
dodiep
View
217
Download
0
Embed Size (px)
Citation preview
1
International Atomic Energy Agency
Decommissioning PlanningDecommissioning PlanningIngemar Lund - Swedish Radiation Protection Authority,
SSI, SwedenIAEA Regional Workshop: Legal and Regulatory Aspects
of Decommissioning of Research ReactorsManila, Philippines, 26 -30 June 2006
International Atomic Energy Agency
Discuss • the decommissioning planning process,• the key points of the planning process, and• the importance of early planning
Work breakdown structures
ObjectiveObjective
2
International Atomic Energy Agency
Decommissioning PlanningDecommissioning PlanningThe operator should prepare a comprehensive Decommissioning Plan, DP, with purpose to document & display how decommissioning activities can be safely performed• Successful decommissioning depends on
careful and organized planning, consistent with regulatory requirements• Ideally decommissioning planning should start
already at the facility design stage and not after shutdown – one plan for each facility!
International Atomic Energy Agency
General PlanningGeneral Planning
• The extent, content and detail of the DP depends on the complexity and hazard potential of the installation• Adequate financial resources should be
available to ensure decommissioning of any nuclear facility• Relevant facility records are critical in the
development of the decommissioning plan
3
International Atomic Energy Agency
Decommissioning Planning Decommissioning Planning -- Key ElementsKey Elements• Review of decommissioning strategies• Specific studies to support selected strategy�Feasibility/ Cost-Benefit analyses
• Cost estimate for the work at the actual site• Schedule for performing the work at the site• Technical scope of the decommissioning effort• Proper staffing and training �Technical / Management
Technical issues are often less critical than good management and planning
Safety and Radiation Protection are prime!
International Atomic Energy Agency
Decommissioning PlanningDecommissioning PlanningThree stages of planning are usually recognized:• Initial Planning• On-going Planning• Final Planning�Degree of detail will vary from facility to facility and
increases from initial to final decommissioning plan (DP)�Access to relevant facility records is a critical issue
when planning for decommissioning• Planning is an ‘evolutionary process’. The DP is a ‘living
document’� The planning successively becomes more detailed, refined and definitive
4
International Atomic Energy Agency
STRATEGY IMPLEMENTATIONSTRATEGY IMPLEMENTATION
The overall decommissioning strategy to be adopted The overall decommissioning strategy to be adopted should be identified as early as possible in the should be identified as early as possible in the
planning processplanning process
International Atomic Energy Agency
Initial PlanningInitial Planning• An initial Decommissioning Plan should be
prepared and submitted for each construction application for a new facility• This plan would contain a lower level of detail
than that which would be contained in a final DP• Operating facilities without an initial
decommissioning plan should have one prepared without undue delay
5
International Atomic Energy Agency
Ongoing PlanningOngoing Planning• During facility operations, the decommissioning
plan should be regularly reviewed, updated and made more substantial with respect to:�Facility changes, incidents/abnormal
operating events�Regulations and government policy�Technological advances�Cost estimates and financial provisions
• Also to be included into the DP are safety considerations and experience from refurbishment activities
International Atomic Energy Agency
Final PlanningFinal Planning• At final shutdown of the facility, the operating
organization should initiate detailed studies and finalise planning for decommissioning• The operating organization should submit an
application for decommissioning including a final DP for review and approval by the regulatory body• The DP may be amended or refined as the
decommissioning proceeds
6
International Atomic Energy Agency
Final PlanningFinal Planning• If phased decommissioning - the operator
should supply the regulatory body with a description of:�The proposed surveillance and maintenance program�The existing or new systems or programs necessary for
facility maintenance�The systems to be installed to perform deferred
dismantling�The proposed frequency for review of the above items�The number of staff required and their qualifications
during the deferral period
International Atomic Energy Agency
Decommissioning PlanningDecommissioning Planning• The final DP should be formulated as the first
step in the decommissioning process by a dedicated and complete project team• Adequate financial resources should be
available to ensure decommissioning of any nuclear facility• For deferred decommissioning, special
attention should be given to periodic adjustments for inflation, technological advances, waste costs and regulatory changes
7
International Atomic Energy Agency
Decommissioning PlanningDecommissioning PlanningTypical contents of DP - I• Facility description and operational history• Legal and regulatory requirements• Radioactive and toxic material inventory• Assessment and selection of decommissioning
strategy (safety, wastes, doses, costs, funding, justification)• Project management (including organization,
monitoring, review, training, reporting, records)• Decommissioning activities (phases, work
packages, decontamination, dismantling, waste management, surveillance & maintenance)
International Atomic Energy Agency
Decommissioning PlanningDecommissioning PlanningTypical contents of DP - II• Safety assessment (doses, ALARA; monitoring, …
protection and emergency systems; physical security & material control; risk analysis �safety management & functions, justification)• Radiation protection and Safety programme • Waste Management (important!)• Release criteria measurement/verification methods• Environmental impact assessment• Quality assurance programme
8
International Atomic Energy Agency
Decommissioning PlanningDecommissioning PlanningTypical contents of DP - III• Details of the estimated costs and source of
funding• Continued surveillance and maintenance (deferral)• Future decommissioning activities (deferral) • Final radiation survey proposal• Outline of final decommissioning report
International Atomic Energy Agency
Waste Treatment is importantWaste Treatment is important• The waste management plan is an integral part (or
an associated document) of the overall decommissioning plan.• Various treatment systems may be required• Solidification, Removal of water• Immobilization of the contaminants• Preparation for subsequent treatment• Reduction of waste volume• Purification of water for reuse/discharge• Separation of a contaminant from a bulk matrix
9
International Atomic Energy Agency
Other supporting DocumentsOther supporting Documents• Characterization Plan• Characterization Report• Public Relations Plan• Final Survey Plan• Final Survey Report• Final Report for the Decommissioning Project
International Atomic Energy Agency
Records Records –– The Planning Basis IThe Planning Basis I• Records guide the decommissioning process from
the start of planning, through decommissioning and then serve as a record of the decommissioning• Records are also critical for• Accidents and liability issues• Institutional records• Provide lessons learned• Facilitate information exchange
• Various equipment and systems for records management and control are available
10
International Atomic Energy Agency
Records Records –– The Planning Basis IIThe Planning Basis II• Never too early for compiling key decommissioning
records• Loss or lack of records (institutional knowledge) is
precarious to the decommissioning process• Inability to access records due to changes in
records storage technology (long term issue)• Keep duplicate records in two separate secure
locations
International Atomic Energy Agency
Some Common ProblemsSome Common Problems• Different �fabrication technique & materials of
construction�radiological conditions and/or other hazards
• Inaccurate drawings• Accessibility• Procedure deficiencies• Operator ‘workarounds’• ‘Temporary modifications’
11
International Atomic Energy Agency
Unexpected occurrences or accidentsUnexpected occurrences or accidentsRemoval of fuel (loss of cooling, dropped elements, criticality)Survey of Radiation (high radiation field, malfunctioning of
equipment & monitoring instruments)Decontamination (fire in solvent, rupture of vacuum filter bag,
spillages, loss of essential services)Dismantling & removal of concrete (loss of containment,
cutting accidents, inadequate mechanical supports, equipment failure, dropped loads, combustible waste fire, explosions of oxyacetylene)
Prepare for the unexpected!Error Error reductionreduction
International Atomic Energy Agency
IAEA Safety Guide WS-G-2.2DECOMMISSIONING OF MEDICAL, INDUSTRIAL AND RESEARCH FACILITIES
12
International Atomic Energy Agency
IAEA Safety Guide WS-G-2.2 DECOMMISSIONING OF MEDICAL, INDUSTRIAL AND RESEARCH FACILITIES
International Atomic Energy Agency
Example Work Breakdown StructureExample Work Breakdown Structure
DecommissioningPlans
Regulatorydocumentation
SafetyCase
Safetydocumentation
Buildingmodifications
Maintenancesite prepared
Baselinesite survey
Preparation forcare and surveillance
PreparatoryActivities
Monitoringregime
Buildingmaintenance regime
Care andsurveillance
Decommissioningstart up activities
Set up wastemanagement systems
Set updismantling systems
Dismantle facility
Waste treatment,packaging and storage
End pointActivities
DismantlingActivities
ReactorDecommissioning Plan
M T Cross, RWE NUKEM
13
International Atomic Energy Agency
ATSR - Argonne Thermal Source Reactor
International Atomic Energy Agency
TFTR Decommissioning TFTR Decommissioning –– WBS ExampleWBS Example
Oversight & Planning (1.1)
Area Preparations (1.2)
Non-Tokamak Removals (1.3)
Tokamak Removal Engineering (1.4)
Engineering(1.0)
Oversight & Support (2.1)
Area Preparations (2.2)
Non-Tokamak Removals (2.3)
Tokamak Removals (2.4)
Field Operations (2.0)
Project Office (3.1)
Work Control Center (3.2)
Configuration and DocumentControl (3.3)
Project Management (3.0)
Health Physics Oversight (4.1)
Safety Oversight (4.2)
Health Physics & Safety (4.0)
Radwaste Management (5.1)
Containers and Supplies (5.2)
Transportation and Disposal (5.3)
Mixed Waste Management (5.4)
Radioactive Waste Operations (5.0)
TFTR Decommissioning ProjectPPPL Site, NJ
Source: Lawrence E. Boing, ANL
14
International Atomic Energy Agency
from JAPCO/Tokai-1 NPP Decom. Web site
International Atomic Energy Agency
Cost Elements Cost Elements
• 01 Pre-decommissioning actions• 02 Facility shutdown activities• 03 Procurement of general equipment and material• 04 Dismantling activities• 05 Waste processing, storage and disposal• 06 Site security, surveillance and maintenance• 07 Site restoration, cleanup and landscaping• 08 Project management, engineering and site support• 09 Research and development• 10 Fuel and nuclear material• 11 Other costsalso…Labour, Capital Equipment and Material, Expenses, and Contingency.http://www.nea.fr/html/rwm/reports/1999/costlist.pdf
Standardised List of Cost Elements (NEA / EC / IAEA)
15
International Atomic Energy Agency
ReferencesReferences• IAEA Safety Guide WS-G-2.1• IAEA Safety Guide WS-G-2.2• IAEA Safety Guide WS-G-2.4
• IAEA Technical Reports Series #351• IAEA Technical Reports Series #375• IAEA Technical Reports Series #399 • IAEA Technical Reports Series #411
International Atomic Energy Agency
SummarySummary• Planning for decommissioning should be an on-
going process, not a feared process• The entire decommissioning process should be
well planned and the roles of various parties should be clearly defined• Numerous useful IAEA reference documents are
available – use them!Early and good planning makes dividend later!