INFORM A RIGGER — PASS THE WORD PAGE 1 __________________________________________________________________________________________________________________ Copyright © Gunnebo Johnson Corporation All rights reserved 12/2016 P/N 69749 Additionally Pile Driving and Pile Extracting are applications approved for existing Gunnebo Johnson Model "J- Block" Crane Blocks equipped with Cheek Weights secured at the base with a capscrew(s) as shown in figure 1 & 2, PROVIDED; 1) EXISTING "A" CAPSCREWS HAVE BEEN REPLACED with an appropriate "B" capscrew kit. (see Replacement Procedure below) 2) 80% of WLL given on the crane block identification tag is not exceeded and 3) Impact loading is precluded and 4) Each day before use, the crane block and its fasteners and attachments shall be inspected for damage or defects by a competent person designated by the employer with additional inspections performed during crane block use where service conditions warrant and 5) All associated equipment is operated within the crane manufacturer guidelines. Capscrew(s) replacement procedure; 1) Contact Gunnebo Johnson Customer Service with crane block serial number or other identifying information to obtain appropriate capscrew field replacement kit. 2) Remove “A”capscrew(s) and lock washer from crane block cheek weights 3) Remove any corrosion or contamination from side plate threads. 4) Assemble lock washer to “B” capscrew. 5) Apply Loctite Threadlocker #263 to the threads of “B”capscrew(s) 6) Install “B” capscrew into side plate as shown in Figure 3 and tighten to 10 -15 Ft. - Lbs. 7) Allow 24 hours for Loctite to cure before returning block to service. Gunnebo Johnson Application Advisory For Gunnebo Johnson Crane Blocks used in Pile Driving and Pile Extraction service. Pile Driving and Pile Extracting are applications approved for existing Gunnebo Johnson Model "J-Block" Crane Blocks equipped without Cheek Weights and with Cheek Weights attached by all four tie bolts and for all Gunnebo Johnson Model "QRJ" Crane Blocks equipped with or without Cheek Weights , PROVIDED; Figure 3 Existing Capscrew & Lock Washer "A" 1) 80% of WLL given on the crane block idenfication tag is not exceeded and 2) Impact loading is precluded and 3) Each day before use, the crane block and its fasteners and attachments shall be inspected for damage or defects by a competent person designated by the employer with additional inspections performed during crane block use where service conditions warrant and 4) All associated equipment is operated within the crane manufacturer guidelines. For assistance and answers to questions please contact Gunnebo Johnson customer service at 918-832-8933 or [email protected] "J-Block" Crane Block with Cast Weights Figure 1 "J-Block" Crane Block with Steel Weights Figure 2 Existing Capscrew & Lock Washer "A" Cheek Weight Replacement Capscrew & Lock Washer "B" Reduced Body Loctite Threads Side Plate No Marking No Marking Grade 5 Grade 5 Grade 8 or or

For Gunnebo Johnson Crane Blocks used in Pile Driving and ...Gunnebo Johnson Model "J- Block" Crane Blocks equipped with Cheek Weights secured at the base with a capscrew(s) as shown

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

  • INFORM A RIGGER — PASS THE WORD PAGE 1__________________________________________________________________________________________________________________

    Copyright © Gunnebo Johnson CorporationAll rights reserved

    12/2016P/N 69749

    AdditionallyPile Driving and Pile Extracting are applications approved for existingGunnebo Johnson Model "J- Block" Crane Blocks equipped with CheekWeights secured at the base with a capscrew(s) as shown in figure 1 &2, PROVIDED;

    1) EXISTING "A" CAPSCREWS HAVE BEEN REPLACED with anappropriate "B" capscrew kit. (see Replacement Procedure below)2) 80% of WLL given on the crane block identification tag is notexceeded and3) Impact loading is precluded and4) Each day before use, the crane block and its fasteners and attachmentsshall be inspected for damage or defects by a competent persondesignated by the employer with additional inspections performedduring crane block use where service conditions warrant and5) All associated equipment is operated within the crane manufacturerguidelines.

    Capscrew(s) replacement procedure;1) Contact Gunnebo Johnson Customer Service with crane block serialnumber or other identifying information to obtain appropriate capscrewfield replacement kit.2) Remove “A”capscrew(s) and lock washer from crane block cheekweights3) Remove any corrosion or contamination from side plate threads.4) Assemble lock washer to “B” capscrew.5) Apply Loctite Threadlocker #263 to the threads of “B”capscrew(s)6) Install “B” capscrew into side plate as shown in Figure 3 and tightento 10 -15 Ft. - Lbs.7) Allow 24 hours for Loctite to cure before returning block to service.

    Gunnebo Johnson Application AdvisoryFor

    Gunnebo Johnson Crane Blocks used in Pile Driving and Pile Extraction service.

    Pile Driving and Pile Extracting are applications approved for existing Gunnebo Johnson Model "J-Block" Crane Blocksequipped without Cheek Weights and with Cheek Weights attached by all four tie bolts and for all Gunnebo Johnson Model"QRJ" Crane Blocks equipped with or without Cheek Weights , PROVIDED;

    Figure 3

    ExistingCapscrew &Lock Washer

    "A"

    1) 80% of WLL given on the crane block idenfication tag is notexceeded and2) Impact loading is precluded and3) Each day before use, the crane block and its fasteners and attachmentsshall be inspected for damage or defects by a competent persondesignated by the employer with additional inspections performedduring crane block use where service conditions warrant and4) All associated equipment is operated within the crane manufacturerguidelines.

    For assistance and answers to questions pleasecontact Gunnebo Johnson customer service at918-832-8933 or [email protected]

    "J-Block"Crane Block

    with CastWeights

    Figure 1

    "J-Block"Crane Blockwith SteelWeights

    Figure 2

    ExistingCapscrew &Lock Washer

    "A"

    Cheek Weight

    ReplacementCapscrew &Lock Washer

    "B"

    Reduced Body

    LoctiteThreads

    Side Plate

    NoMarking

    NoMarking

    Grade5

    Grade5

    Grade8

    or

    or

    INFORM A RIGGER — PASS THE WORD

    PAGE 1

    __________________________________________________________________________________________________________________

    Copyright © Gunnebo  Johnson Corporation

    All rights reserved

    12/2016

    P/N 69749 

    Additionally

    Pile Driving and Pile Extracting are applications approved for existing Gunnebo Johnson Model "J- Block" Crane Blocks equipped with Cheek Weights secured at the base with a capscrew(s) as shown in figure 1 & 2, PROVIDED; 

     

    1) EXISTING "A" CAPSCREWS  HAVE BEEN REPLACED with an appropriate "B" capscrew  kit. (see Replacement Procedure below)

    2) 80% of WLL given on the crane block identification tag is not  exceeded and

    3) Impact loading is precluded and

    4) Each day before use, the crane block and its fasteners and attachments shall be inspected for damage or defects by a competent person designated by the employer with additional inspections performed during crane block use where service conditions warrant and

    5) All associated equipment is operated within the crane manufacturer guidelines. 

     

     

     

     

     

     

     

     

     

    Capscrew(s) replacement procedure; 

    1) Contact Gunnebo Johnson Customer Service with crane block serial number or other identifying information to obtain appropriate capscrew

    field replacement kit.

    2)  Remove  “A”capscrew(s)  and lock washer from crane block cheek weights

    3)  Remove any corrosion or contamination from side plate threads.

    4)  Assemble lock washer to  “B” capscrew. 

    5)  Apply Loctite Threadlocker #263 to the threads of  “B”capscrew(s) 

    6)  Install “B” capscrew into side plate as shown in Figure 3 and tighten to 10 -15 Ft. - Lbs.

    7)  Allow 24 hours for Loctite to cure before returning block to service. 

     

    Gunnebo Johnson Application Advisory 

    For

    Gunnebo Johnson Crane Blocks used in Pile Driving and Pile Extraction service.  

     

    Pile Driving and Pile Extracting are applications approved for existing Gunnebo Johnson Model "J-Block" Crane Blocks equipped without Cheek Weights and with Cheek Weights attached by all four tie bolts and for all Gunnebo Johnson Model "QRJ" Crane Blocks equipped with or without Cheek Weights , PROVIDED; 

     

     

     

     

     

     

     

                                                 

     

     

     

     

     

     

     

     

     

    Figure 3

    Existing

    Capscrew &

    Lock Washer

    "A"

    1) 80% of WLL given on the crane block idenfication tag is not exceeded and

    2) Impact loading is precluded and

    3) Each day before use, the crane block and its fasteners and attachments shall be inspected for damage or defects by a competent person designated by the employer with additional inspections performed during crane block use where service conditions warrant and

    4) All associated equipment is operated within the crane manufacturer guidelines. 

    For assistance and answers to questions please contact Gunnebo Johnson customer service at 918-832-8933 or [email protected]

    "J-Block"

    Crane Block

    with Cast Weights

    Figure 1

    "J-Block"

    Crane Block

    with Steel Weights

    Figure 2

    Existing

    Capscrew &

    Lock Washer

    "A"

    Cheek Weight

    Replacement

    Capscrew &

    Lock Washer

    "B"

    Reduced Body

    Loctite

    Threads

    Side Plate

    No

    Marking

    No

    Marking

    Grade

    Grade

    Grade 

    8