Upload
joshua-simon
View
215
Download
0
Embed Size (px)
Citation preview
Final Version
Gabe KarpatiMay 17, 2002
Micro-Arcsecond X-ray Imaging Mission, Pathfinder (MAXIM-PF)
System Overview
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
SystemPage 2
Final Version
Requirements & AssumptionsBaseline ConfigurationOptions ConsideredComments, Issues, Concerns
Outline
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
SystemPage 3
Final Version
Requirements & Assumptions Study Overview
Mission objective X-ray interferometry mission, a pathfinder to full MAXIM
Original requirements As formulated in the Prework and in K. Gendreau’s “going-in-13may02.ppt”
Original requirements modified during the study Lifetime for Phase 1: 1 yr required / 50 targets (1wk/target);
Lifetime for Phase 2: 3 yrs required / 4 yrs goal (3 wks/target)
Additional constraints, challenges 2015 launch
Primary purpose of this study Identify mission drivers and breakpoints Identify technologies required Subsystem configuration, mass and cost estimates
Length of study 5 days
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
SystemPage 4
Final Version
Requirements & Assumptions Major Driving Requirement Areas
High precision pointing Centroid image of a laser beacon for microarcsec LOS alignment Point by referencing microarcsec image of stars or use GPB-like
microarcsec grade Super-Gyro Multi s/c formation flying
Orbital dynamics: Formation acquisition and control; Orbits; Transfer to L2
Propulsion: Thrust needs to vary by several orders of magnitude ACS: Position control to microns over 100’s of m, and to cm’s over
20000 km, knowledge to microns; Retargeting issues Software
To accommodate all functions Verification
Functional and performance verification 1 g environment Thermal control
Handle two thermally very dissimilar mission Phases with one h/w Control to .1 degree to maintain optical figure “STOP” CTE effects
Communication Complex communications web: Detector to Ground; Hub to Detector;
Hub to FFs; FF to FF; Rough ranging using RF
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
SystemPage 5
Final Version
Baseline Configuration Experiment Overview
Observatory configuration One Hub spacecraft, one Detector spacecraft, six Free Flyer spacecraft Hub communicates with Detector and the Free Flyers Detector communicates with ground
Phase 1: 100 microarcsec Science 2 formation flying objects at 200 km
Phase 2: 1 microarcsec Science Hub surrounded by 6 identical Free Flyers in a circle of 200-500 m,
Detector at 20,000 km Distance from Hub to Detector: RF ranging course & time of flight for
fine ranging and control (~5m) Align Hub and Detector using Superstartracker that centroids the image
at the Detector of a LISA - like laser beacon mounted on Hub (microarcsec)
LOS pointing: reference beacon image to image of stars in background w/ Superstartracker or use GPB - like Super-Gyro (microarcsec)
HUB to FF’s distance: w/ RF ranging course; Laser interferometer fine w/ corner cubes on Hub (~10 um);
FF position: use FF startrackers (~arcsecs)looking at LED on Hub
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
SystemPage 6
Final Version
Baseline Configuration Experiment Overview
•LOS to target knowledge to ~0.1 milliarcsec (~15 microns @ 20,000 km)
FreeFlyer S/C•Pitch, Yaw control to ~1 arcsec•Pitch, Yaw Knowledge to arcsecs •Roll Control to 30 milliarcsecs
Optics Hub S/C• Pitch, Yaw, control
to ~ 1 arcsec, roll control to arcmins
• Pitch, Yaw, Roll Knowledge to +/- 1 arcsecond
Diagram courtesy of K. Gendreau
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
SystemPage 7
Final Version
Baseline Configuration Experiment Overview
Continuous full sun Battery required for safe Phase only
Transfer to L2 Takes up to 6 months All S/C are attached together High thrust chemical propulsion Transfer stage is jettisoned at L2
Communication web HUB to Free Flyers HUB to Detector All Space-Ground communications performed by Detector spacecraft IP, 50 Kbps; One contact day @ DSN 5 Mbps Ranging for collision avoidance
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
SystemPage 8
Final Version
Baseline Configuration Overview
LV Delta IV 4040 (4M fairing) Delta IV 4240 Delta IV 4450
C3 (km2/s2):- .7
2780kg
C3 (km2/s2):- .7 4,135kg
$97M
C3 (km2/s2):- .7 4,650kg
Orbit Orbit Type Eclipse Boresight
L2, Lissajous, 800,000 km
, ~6 months period
No eclipse. Full Sun, Avoid Moon
shadow
Anywhere within a 30 deg halfangle
cone, perpendicular to sunline
Mission Liftoff Mass Life Size Consumables
~3000 kg Ph1: 1 yr req / 50 targets
(1wk/ target);
Ph2: 3 yrs req (3 wks/ target) /
4 yrs goal
5 yrs; Phases 1 & 2 combined
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
SystemPage 9
Final Version
Baseline Configuration Overview
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
SystemPage 10
Final Version
Baseline Configuration Instrument Resources Summary
X- ray Detector System $k kg
Detector Unit 15000 50Electronics Unit 5000 50
X- ray Detector System Total 20000.0 100.0
Mirror Module (one unit) $k kg
Bench / Houing 5
2 Mirrors ttl 100
6 Actuators ttl 30
6 Mechanisms ttl 60
1 Shutter 1
Electr/ Harness 10
Thermal 1
I nstr Eng 40
S/ C level I &T .1 FTE 15
Assy Tech .2 FTE 30
One Mirror Module Total 292.0 5.0
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
SystemPage 11
Final Version
Baseline Configuration Metrology System Resources
Summary
Hub Metrology System $k kg
LI SA Laser Beacon 5000 20
Hub's LED's (6) and cornercubes (6) Total 400 5
Det Metrology System $k kg
LOS Superstartracker / Gyro Package 70000 120
FF Metrology System $k kg
FF's Ranging I nterferometers, one unit 2000 10
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
SystemPage 12
Final Version
Baseline Configuration S/c Mass Summaries
HUB TOTAL MASS [kg]
Actual Contingent
PAYLOAD TOTAL 70.0 85.3
BUS SUBSYSTEMS DRY TOTAL 198.6 238.4
Observatory Dry Mass 268.6 323.6
PROPELLANT 62.0 74.4
WET MASS (BUS + PAYLOAD) 330.64 398.0
DET TOTAL MASS [kg]
Actual Contingent
PAYLOAD TOTAL 220.0 275.0
BUS SUBSYSTEMS DRY TOTAL 288.1 345.7
Observatory Dry Mass 508.1 620.7
PROPELLANT 111.0 133.2
WET MASS (BUS + PAYLOAD) 619.08 753.9
FF ea. TOTAL MASS [kg]
Actual Contingent
PAYLOAD TOTAL 65.0 78.5
BUS SUBSYSTEMS DRY TOTAL 217.0 260.4
Observatory Dry Mass 282.0 338.9
PROPELLANT 22.0 26.4
WET MASS (BUS + PAYLOAD) 304.04 365.348
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
SystemPage 13
Final Version
Baseline Configuration Mission Mass Summary
MISSION TOTAL MASS [kg]Actual Contingent
Hub Wet 330.6 398.0
Detector Wet 619.1 753.9
Total 6 Freeflyers Wet 1824.2 2192.1
Transfer Module Wet 500.0 600.0
LIFTOFF MASS 3274.0 3944.0
Delta 4040 capability to L2 2780.0 2780.0
Margin [kg] -494.0 -1164.0
Margin [%] -17.8 -41.9
Delta 4240 capability to L2 4135.0 4135.0
Margin [kg] 861.0 191.0
Margin [%] 20.8 4.6
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
SystemPage 14
Final Version
Baseline ConfigurationPayload Cost [$M]
Actual w/ Cont. Cont %
9 Mirror Modules 2.6 3.4 30%Metrology System: LI SA Laser, 6 cornercubes, 6 LEDs 5.4 7.0 30%Payload GSE incl inclPayload I &T 18.3 22.8 25%Payload Support incl incl
Payload Total 26.3 33.2
Hub s/c
Hub s/c
Actual w/ Cont. Cont %
X-ray Detector System Total 20.0 26.0 30%LOS Superstartracker / Gyro Package 70.0 100.0
Payload GSE incl incl
Payload I &T incl incl
Payload Support incl incl
Payload Total 90.0 126.0
Detector s/ c
Detector s/ c
Actual w/ Cont. Cont %
11 Mirror Modules 3.2 4.2 30%FF's Ranging I nterferometers 2.0 2.6 30%Payload GSE incl inclPayload I &T incl inclPayload Support incl incl
Payload Total 5.2 6.8
Freeflyer s/ c
Freeflyer s/ c
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
SystemPage 15
Final Version
Baseline ConfigurationHub S/c Subsystems Cost [$M]
HUB SPACECRAFT BUS SUBSYSTEMS* [$M]
Actual w/ Cont. Cont %
Mechanical Cost 0.6 0.7 20%Mechanical Labor 1.1 1.3 20%ACS Hardware 2.7 3.3 20%ACS Design, Analysis, SS I &T 5.2 6.2 20%Thermal Hardware 0.7 0.8 20%Thermal Labor 1.0 1.2 20%Propulsion Hardware 1.0 1.2 20%Propulsion Labor 2.0 2.4 20%
Power Hardware 1.5 1.8 20%
Power Labor 2.8 3.4 20%
C&DH Hardware 5.0 6.0 20%
C&DH Labor 2.0 2.4 20%RF Communication Hardware 4.5 5.4 20%RF Communication Labor (I &T, CTV test) 5.0 6.0 20%Flight Sof tware Hardware 0.2 0.2 20%Flight Sof tware Labor 10.8 12.9 20%
Spacecraft Bus Total 46.0 55.2
Hub s/c
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
SystemPage 16
Final Version
Baseline ConfigurationDetector S/c Subsystems Cost [$M]
DETECTOR SPACECRAFT BUS SUBSYSTEMS* [$M]
Actual w/ Cont. Cont %
Mechanical Cost 0.7 0.8 20%Mechanical Labor 1.7 2.0 20%ACS Hardware 2.7 3.2 20%ACS Design, Analysis, SS I &T 5.2 6.2 20%Thermal Hardware 1.1 1.3 20%Thermal Labor 2.5 3.0 20%Propulsion Hardware 2.0 2.4 20%Propulsion Labor 3.0 3.6 20%
Power Hardware 2.8 3.3 20%
Power Labor 2.0 2.4 20%
C&DH Hardware 8.0 9.6 20%
C&DH Labor 2.0 2.4 20%RF Communication Hardware 11.7 14.0 20%RF Communication Labor (I &T, CTV test) 5.0 6.0 20%Flight Sof tware Hardware 0.2 0.2 20%Flight Sof tware Labor 10.1 12.1 20%
Spacecraft Bus Total 60.5 72.6
Detector s/ c
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
SystemPage 17
Final Version
Baseline ConfigurationOne FF S/c Subsystems Cost [$M]
FREEFLYER SPACECRAFT BUS SUBSYSTEMS* [$M]
Actual w/ Cont. Cont %
Mechanical Cost 0.6 0.7 20%Mechanical Labor 1.1 1.3 20%ACS Hardware 2.7 3.2 20%ACS Design, Analysis, SS I &T 0.9 1.0 20%Thermal Hardware 0.5 0.6 20%Thermal Labor 0.4 0.5 20%Propulsion Hardware 2.0 2.4 20%Propulsion Labor 0.5 0.6 20%
Power Hardware 1.4 1.7 20%
Power Labor 1.4 1.7 20%
C&DH Hardware 4.0 4.8 20%
C&DH Labor 1.0 1.2 20%RF Communication Hardware 0.8 0.9 20%RF Communication Labor (I &T, CTV test) 0.5 0.6 20%Flight Sof tware Hardware 0.1 0.1 20%Flight Sof tware Labor 2.7 3.2 20%
Spacecraft Bus Total 20.4 24.5
Freeflyer s/ c
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
SystemPage 18
Final Version
Baseline Configuration Overall Cost Summary [$M]
TOTAL MI SSI ON COST [$M]Actual w/ Cont.
PROJ ECT MANAGEMENT 17.6 22.0
PRE- LAUNCH SCIENCE TEAM SUPPORT 4.2 5.3
PAYLOAD TOTAL COST 147.6 166.0
SPACECRAFT BUS SUBSYSTEMS 231.2 277.5
MISSION SYSTEMS ENGINEERING 10.8 13.0
ATLO & MISSION READINESS 18.1 21.7
LAUNCH VEHICLE 97.0 97.0
GROUND SYSTEM DEVELOPMENT 5.6 6.7
MISSION READINESS VERIFICATION 1.0 1.3
OPERATIONS FOR 3 YEARS 14.4 18.0
MISSION TOTAL, Full Acct 547.5 628.4
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
SystemPage 19
Final Version
Additional Issues To ConsiderSmaller RSDO Busses
RSDO On-Ramp II in force RSDO On-Ramp IV selection in process
Several new buses added, to increase choice
Spectrum Astro SA 200B, Bus dry mass = 90 kg Payload Power (OAV) (EOL) / Mass Limit: 86 W / 100 kg
Orbital - Microstar, Bus dry mass = 59 kg Payload Power (OAV) (EOL) / Mass Limit: 50 W / 68 kg
Ball BCP 600, Bus dry mass = 203 kg Payload Power (OAV) (EOL) / Mass Limit: 125 W / 90 kg
Orbital - Leostar, Bus dry mass = 263 kg Payload Power (OAV) (EOL) / Mass Limit: 110 W / 101 kg
Surrey - Minisat 400, Bus dry mass = 207 kg Payload Power (OAV) (EOL) / Mass Limit: 100 W / 200 kg
TRW - T200A, Bus dry mass = 242 kg Payload Power (OAV) (EOL) / Mass Limit: 94 W / 75 kg
SA 200B
BCP 600
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
SystemPage 20
Final Version
Additional Issues To Consider Bigger RSDO Busses
Swales EO-SP (new in RSDO II catalog) Bus dry mass = 370 kg Payload Power (OAV) (EOL) / Mass : 80 W / 110kg
Spectrum Astro SA 200HP Bus dry mass = 354 kg Payload Power (OAV) (EOL) / Mass Limit: 650 W / 666 kg
Lockheed Martin - LM 900 Bus dry mass = 492 kg Payload Power (OAV) (EOL) / Mass Limit: 344 W / 470 kg
Orbital StarBus Bus dry mass = 566 kg Payload Power (OAV) (EOL) / Mass Limit: 550 W / 200 kg
Orbital – Midstar Bus dry mass = 580 kg Payload Power (OAV) (EOL) / Mass Limit: 327 W / 780 kg
Ball BCP 2000 Bus dry mass = 608 kg Payload Power (OAV) (EOL) / Mass Limit: 730 W / 380 kg
EO-1
Midstar
SA200HP -DS1
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
SystemPage 21
Final Version
Comments, Issues and Concerns I&T, Requirements Verification
Environmental verification Standard, per GEVS
Any end-to-end testing / verification of the critical subsystems is very difficult or near-impossible in a 1 g environment E-E verification of orbit maintenance and formation flying capabilities
near-impossible E-E verification of metrology system near-impossible E-E verification of X-ray beam focus and alignment is difficult
Reasonable trades must be made on verification approaches, goals, and requirements That alone is a very significant body of work
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
SystemPage 22
Final Version
Maturity, Technologies, TRL
MAXIM is feasible ! MAXIM does not factor in any unrealistic technology expectations or
technologies un-envisionable today Fairly mature and serious plans, even for the metrology
Still, a staggering amount of technology development is required: Metrology system: H/w and s/w elements
Superstartracker GPB - like Super-Gyro for pointing
Software Formation flying and “virtual-one-body” telescope control software Analysis and simulation techniques
Propulsion system Very low thrust technologies, extremely variable force thrusters
Verification approaches and technologies for FF LAI missions Simulators
Low CTE optical/structural materials General TRL Level of MAXIM key technologies today is 2-3
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
SystemPage 23
Final Version
Tall Poles
Tall Pole 1: Multi s/c formation flying ACS: Position control to microns over 100’s of m, and to cm’s over
20000 km, knowledge to microns; Retargeting issues Orbital dynamics: Formation acquisition and control; Orbits; Transfer to
L2 Metrology System: swarm sensors, interferometric range sensors,
beacon detecting attitude sensors Tall Pole 2: High precision pointing
Centroid image of a laser beacon for microarcsec LOS alignment Point by referencing microarcsec image of stars or use GPB-like
microarcsec grade Super-Gyro Tall Pole 3: Software
To accommodate all required functions Tall Pole 4: Propulsion
Continuous smooth micro-thrusters Thrusters force variable by orders of magnitude
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
SystemPage 24
Final Version
Tall Poles
Tall Pole 5: Verification science Theoretical “risk-science” assessment on feasible verification vs.
available resources Functional and performance verification in 1 g environment “STOP” CTE effects
Tall Pole 6: Thermal control Control to .1 degree to maintain optical figure Handle two thermally very dissimilar mission phases with one h/w
Tall Pole 7: Communication Complex communications web: Detector to Ground; Hub to Detector;
Hub to FFs; FF to FF; Rough ranging using RF Tall Pole 8: Mirror element actuators & software
General TRL Level of key technologies today is 2-3
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
SystemPage 25
Final Version
Additional Issues To Consider
Startracker on FF opposite the Hub – Sun line would stare at Sun Since 6 FF’s are 60 degrees apart, roll entire formation, to have two FFs
closest to Hub – Sun line at equal 30 degrees This concept doesn’t work for a higher number of FF’s, unless FF startracker
FOV is sufficiently narrowed (complicates access to star-field) Structural-Optical-Thermal effects
Not fully addressed yet Thermal control to 1.5 mK required – not trivial ! Lower CTE optical/structural materials?
Structural stability between the attitude sensor and the instrument It is good practice to mount the attitude sensors and the instrument on a
common temperature controlled optical table Free Flyers station fixed
Free Flyer station clocking position in circle around Hub is constrained To change position, while keeping mirrors in alignment requires rolling the FF s/c Rolling of FF s/c is disallowed for sun / anti-sun sides must be pointed right
Mounting FF Mirror Assemblies on turntable would allow repositioning of any FF s/c to any station
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
SystemPage 26
Final Version
Additional Issues To Consider
Other mission orbits should be fully explored Earth leading/trailing drift away orbit at .1 AU/year Distant retrograde orbits Solar-libration: “kite-like” solar sail “floating” on a toroid-like pseudo-
libration surface which envelops L1 between Sun-Earth Calibration Plan
Calibration may be a major requirements driver, must be factored in early on
Communications network architecture Communications between constellation elements: much refinement is
required TDRSS at L2? Servicing at L2?
Explore synergies and joint funding possibilities w/ other LAI missions at L2
Servicability at L2 Design shouldn’t of the bat preclude future serviceability Coordinate w/ servicing planners
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
SystemPage 27
Final Version
Supporting Data
Systems spreadsheet tool: “LAI-MAXIM-PF_System_Sheets.xls” System configuration summaries Mass and cost rollups and detailed ISIS subsystem data Quick propulsion calculator Prework information
WBS template: “Generic_WBS_Template_by_GSFC_NOO.doc” Full NASA mission’s complete Work Breakdown Structure Compiled by GSFC New Opportunities Office
Useful web sites Access to Space at http://accesstospace.gsfc.nasa.gov/ provides launch
vehicle performance information and other useful design data. Rapid Spacecraft Development Office at http://rsdo.gsfc.nasa.gov/
provides spacecraft bus studies and procurement services.
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
SystemPage 28
Final Version
System Summary
GSFC Contact: Keith Gendreau Phone Number: 301/286-6188 Mission name and Acronym: MAXIM-Pathfinder Authority to Proceed (ATP) Date: Dec 2007 Mission Launch Date: 2015 Transit Cruise Time (months): n/a Mission Design Life (months): 48 Length of Spacecraft Phase C/D (months): 72 Bus Technology Readiness Level (overall): 3 S/C Bus management build: TBD Experiment Mass: 3000 kg