Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
1
Final NHBRC Phase I Geotechnical Report for the
Proposed Township Development, Portion 419 of
Farm 61 in uPhongola, KwaZulu-Natal
Client: MNT Geomatics
Reference: 16-0816R01
Dated: 6 October 2016
GCS Geotechnical 63 Wessels Street
Rivonia
Cell: +27 (0)82 567 1561
www.gcs-sa.biz
Site Investigations Borrow Pits and Materials
Slope Stability Roads
Rock Mechanics Groundwater
Soil Mechanics
Foundations
NHBRC
Geotechnical Instrumentation
2
Final NHBRC Phase I Geotechnical Report for the
Proposed Township Development, Portion 419 of
Farm 61 in uPhongola, KwaZulu-Natal
Reference: 16-0816R01 Date: 6 October 2016
TABLE OF CONTENTS
1. INTRODUCTION & TERMS OF REFERENCE .............................................................. 5 2. AVAILABLE INFORMATION ........................................................................................... 5 3. SITE DESCRIPTION ............................................................................................................ 6 4. GEOLOGY ............................................................................................................................. 7 5. FIELDWORK ........................................................................................................................ 7 6. GROUNDWATER ................................................................................................................. 8 7. LABORATORY TESTING .................................................................................................. 8 8. FINAL DEVELOPMENT RECOMMENDATIONS ......................................................... 9 8.1 Trenchability and Rippability Assessment ............................................................................................. 9 8.2 Drainage .................................................................................................................................................. 9 8.3 Earthworks and Site Clearance ............................................................................................................. 10 8.4 Settlement/Heave Analysis ................................................................................................................... 11 8.5 NHBRC Site Classifications ................................................................................................................. 11 8.6 Foundation Recommendation ............................................................................................................... 11 8.7 Surface Beds ......................................................................................................................................... 12 8.8 Recommended Subgrade Treatment ..................................................................................................... 12 8.9 Pipe Bedding ......................................................................................................................................... 12 9. CONCLUSIONS & RECOMMENDATIONS .................................................................. 13
Appendix A TLB-excavated Inspection Pit Profiles
Appendix B Laboratory Test Results
Figure 1 Site Plan
Figure 2 Geological Plan
3
EXECUTIVE SUMMARY
This final NHBRC Phase I geotechnical report contains the findings and development
recommendations for the construction of the proposed township to be located on Portion
419 of Farm 61 in uPhongola.
It is considered that the conditions prevailing on site are such that the majority of the site is
considered suitable for the proposed development, provided the recommendations outlined
in this final report are adhered to. The main geotechnical constraints to the development
will be collapsible subsoils.
Six disturbed and four undisturbed samples were taken from the inspection pit excavations
for laboratory analysis. Particle size distribution (PSD), hydrometer analysis and Atterberg
limits determination are currently being carried, and the four undisturbed samples were sent
for collapse potential testing. The laboratory test results are included in Appendix B.
The site is underlain by quaternary alluvial age sediments and the bedrock is andalusite-
sericite schist and amphibole schist of the Mphushana Formation, Mozaan Group. Soft
excavation in terms of SABS 1200 D is generally anticipated to depths in excess of 2.9 m
below natural ground level over the site.
One of the more important factors in the promotion of a stable site is the control and removal
of surface water from the property. It is important that the design of the storm water
management system, allow for the drainage of accumulated surface water from the platform
and into the storm water system or natural drainage lines.
The NHBRC Site Classification is C1-C2 for majority of the site. The options for suitable
foundations are:
Modified normal with articulation joints at some internal and all external doors, or
Compaction of in-situ soils below individual footings, or
Soil or RC raft
Stiffened strip footings
Finally, it must be understood that the ground conditions described in this report refer
specifically to those encountered at the test positions on site. It is therefore possible that
conditions at variance with those discussed above may be encountered elsewhere on the
property.
In this regard it is important that GCS Geotechnical carry out periodic inspections of the
site during construction to ensure that any variation in the anticipated ground conditions
can be assessed, and revised recommendations made to avoid unnecessary delays and
expense.
Furthermore it is emphasised that this report satisfies the requirements of an NHBRC Phase
I shallow geotechnical investigation for township proclamation and town planning
purposes. The final estimation of the appropriate foundation options for each erf/stand
should be determined by a NHBRC Phase 2 investigation during service trench construction.
4
Definitions and Abbreviations
Commercial:
GCS Geotechnical GCS Geotechnical (Pty.) Ltd.
Technical:
CH Chainage (metres)
mbgl metres below ground level
masl metres above sea level
NGL Natural Ground Level
FL Foundation Level
BH Borehole
SPT Standard Penetration Test
N SPT N value (blows per 300 mm)
TLB Tractor-mounted Loader Backhoe
TP Test Pit
DCP Dynamic Cone Penetrometer
EABC Estimated Allowable Bearing Capacity
G1-G10 Standard classification of natural road building materials (TRH 14)
CBR California Bearing Ratio
MDD Maximum Dry Density (kg/m3)
MADD Modified AASHTO Dry Density
OMC Optimum moisture Content (%)
PI Plasticity Index
LL Liquid Limit
LS Linear Shrinkage
RMR Rock Mass Rating
GSI Geological Strength Index
mi Hoek-Brown Constant (origin & texture dependent)
RQD Rock Quality Designation (%)
FF Fracture frequency
UCS Unconfined Compressive Strength (MPa)
C (c’) Cohesion (kPa) – total stress and (effective stress)
Φ (Φ’) Friction Angle (degrees) – total stress and (effective stress)
Kv Modulus of Subgrade Reaction (MN/mm or kPa/mm)
CFA Continuous Flight Auger (pile type)
DCI Driven Cast In situ (pile type)
Cv Coefficient of Consolidation (m2/yr)
Mv Modulus of Compressibility (m2/MN)
MC1 Moisture Content Before Test (%)
MC2 Moisture Content After Test (%)
ρ Dry Density (kg/m3)
VSR Very soft rock
SR Soft rock
MHR Medium hard rock
HR Hard rock
VHR Very hard rock
5
Final NHBRC Phase I Geotechnical Report for the
Proposed Township Development, Portion 419 of
Farm 61 in uPhongola, KwaZulu-Natal
Reference: 16-0816R01 Date: 6 October 2016
1. INTRODUCTION & TERMS OF REFERENCE
At the request of Mr. Muzi Mntambo of MNT Geomatics, GCS Geotechnical (hereafter
referred to as GCS) was asked to provide a proposal and cost estimate quotation, in an email
dated 4th July 2016, for the undertaking of a NHBRC Phase I geotechnical investigation for
the proposed township development on Portion 419 of Farm 61 in uPhongola, KwaZulu-
Natal.
2. AVAILABLE INFORMATION
The following information was drawn upon for the purposes of the investigation:
The 1:250 000 Geological Map titled “2730 Vryheid” as compiled by the South
African Geological Survey, 1986.
Google Earth historical imagery
Brink (1985) Vol. 4
SABS 1200 D – Earthworks
Two drawings showing proposed unit developments
6
Table 2-1: Summary of Available Desk Study Information
Parameter Value Reference
Development Residential MNT Geomatics
Site co-ordinates 27.35954° S / 31.58262° E
MNT Geomatics
Weinert’s N-value 2-5 Weinert (1974)
Climatic Region Moderate TRH 2 (1978)
Rainfall >1500 mm King, 2003
Temperature 20-22.5˚ C after DWAF (1986)
Evaporation 1400-1600 mm After DWAF (1986)
Water Balance Normal Schulze (1985)
Weathering Type Moderate decomposition Fookes et al (1971)
Geology Alluvium, andalusite-sericite
schist and amphibolite schist.
2730 Vryheid 1:250 000 scale
Soil Cover Colluvium, talus and alluvium Brink (1985)
Origin Discontinuous cover of fine
colluvial soils
Brink (1985)
Drainage To east Garmap SA Topo & Rec 2012.1
Drainage Region Quaternary Catchment: W44 DWAF (1999)
Hydrogeology Intergranular & fractured (0.5-2
l/s)
King, 2003
Groundwater depth 20 m King, 2003
Erodibility Index 1-15 (Moderate to high) WRC (1992)
Seismic Intensity VI (MMS) Fernandez et al (1972)
Liquefaction Marginal (50-100 cm/s²) Welland (2002)
3. SITE DESCRIPTION
The proposed township development is located approximately 5 km north-west from the
center of uPhongola, in KwaZulu-Natal. The central co-ordinates of the site are 27.35954°
S / 31.58262° E.
The total site area comprises 19 ha and majority of the site is undeveloped with the exception
of 2 kraals. The site is bound to the north-west by an existing township and to the east, west
and south by sugar cane plantations.
Topographically, the site falls in a north easterly direction from 369 to 339 masl at a gradient
of 1:13. The site is poorly vegetated and serves as a grazing field for cattle, and hosts a
network of rudimentary pathways criss-crossing the site.
7
4. GEOLOGY
Regionally, the site is underlain by quaternary alluvial age sediments, which in turn is
underlain by andalusite-sericite schist and amphibole schist of the Mphushana Formation,
Mozaan Group. A prominent fault passes the site to the east in a north-south direction.
5. FIELDWORK
Twenty TLB-excavated inspection pits (hereafter referred to as IP’s) were opened across the
site, in order to ascertain the general geotechnical engineering properties of the subsurface
materials.
5.1 TLB-Excavated Inspection Pits
In general the soil profile showed an open-grained structure (generally indicative of collapse)
as well as instances of bioturbation, reworking and mulching. A summary of the inspection
pits can be found below in Table 5.1 below. The detailed inspection pit profiles are provided
in Appendix A. The results of the IP’s suggested refusal depths ranging between 1.2 m and
2.9 m below existing ground level, refusing on cobbles and boulders, or by simply reaching
the maximum depth of excavation with a TLB, without intercepting bedrock.
The depth to bedrock could not be confirmed in this shallow investigation, and the possibility
of encountering bedrock or boulders below the final depths of the test pits cannot be ruled
out.
Table 5.1: Summary of Test Pit Profiles
Depth
(m-m)
Description EABC
(kPa)
Kv
(kPa/mm)
E (MPa) or
C (kPa)
Notes
Colluvium
0.0-1.4 Dry to slightly moist, dark reddish
brown to dark orange brown,
FIRM TO STIFF, pin-holed and
bioturbated, slightly sandy silty
Clay.
25-200 35-65 36-144
-Pin-holed
-Ferruginized nodules
-Rootlets.
1.4-2.8 Slightly moist, dark reddish brown
to orange brown, SOFT TO FIRM,
pin-holed, slightly sandy silty Clay.
25-100 35-65 18-72
-Pin-holed
-Ferruginized nodules
-Rootlets.
Talus
0.0-1.6 Dry to slightly moist, dark brown to
dark orange brown, SOFT TO
FIRM, pinholed and bioturbated,
slightly sandy silty Clay.
25-100 35-65 18-72 -Pin-holed
1.6-2.5 Slightly moist, dark reddish brown
to dark orange brown, LOOSE TO
MEDIUM DENSE, pin-holed,
clayey silty Sand.
75-250 55-100 3-12
-Pinholed
-Abundant medium to
course rock fragments
and boulders
All the samples rated as low potential expansiveness.
8
6. GROUNDWATER
No groundwater seepage occurred in any of the inspection pit’s excavated on site although
during the rainy season perched water levels should be expected at the weathered bedrock
interface. The regional groundwater level resides at about 20 m below surface.
7. LABORATORY TESTING
Laboratory tests have been scheduled on six disturbed soil samples and four undisturbed soil
samples recovered from the site.
The following tests are being carried out:
Foundation indicator tests (PSD, hydrometer and Atterberg Limits), and
Collapse potential tests.
The laboratory test results and analysis will determine the material quality for earthworks
and layer-works suitability, as well as foundation characteristics. The laboratory test results
are included in Appendix B with a summary in Table 7-1 below:
Table 7-1: Summary of Foundation Indicators
TP Depth
(m-m) LL PI GM
LS CBR*
(%)
Classifications
TRH14 PRA USCS
Hillwash
1 0.0-2.1 41 15 0.12 7.0 7-8 G10 A-7-6(10) CL
17 1.0-2.6 38 18 0.15 9.0 6-7 G10 A-6(11) CL
Talus
1 2.1-2.8 33 10 0.38 5.0 12-13 G10 A-4(8) SC
2 2.5-2.85 41 12 0.54 6.0 12-13 G10 A-7-6(0) ML-
O
L
5 1.8-2.3 40 16 1.53 8.0 19-20 G10 A-6(4) SC
6 2.6-2.7 34 11 2.40 5.5 45-50 G7 A-2-6(0) GC
*CBR estimated at 93-95% MADD from PI-GM relationship.
9
Table 7-2: Collapse Potential Results
TP Depth
(m-m)
MCa*
(%)
MCb**
(%)
Dry
density
(kg/m3)
e0 CP200***
(%)
Settlement
(mm)
Hillwash/colluvium
1 1.3-1.4 15.43 26.99 1500 0.720 1.6 24
5 0.6-0.7 11.27 23.90 1586 0.683 0.4 6
9 1.0-1.2 21.01 31.25 1275 1.110 7.0 84
Talus
13 1.7-1.8 26.84 40.0 1246 1.152 7.0 6 *MCa = moisture content before soaking
**MCb = moisture content after soaking
***CP200 = collapse potential at 200 kPa
8. FINAL DEVELOPMENT RECOMMENDATIONS
8.1 Trenchability and Rippability Assessment
From information gleaned from the field investigation, the excavatibility of the site in terms
of SABS 1200D can be classified as “soft excavation” from surface to depths in excess of
2.9 m below natural ground level.
8.2 Drainage
The most important factor in the promotion of a stable site is adequate drainage, both surface
and subsurface, be constructed so that no water ingress into the subsurface soils in and
around the foundation base is possible. The natural ingress of groundwater and the additional
localised inundation due to the development itself should be managed and controlled to
prevent erosion and the collapse settlement of materials.
Drainage should be such that any rainfall is diverted to the nearest stormwater drainage
system. Areas of potential pooling or damming of rainfall on site should be carefully
designed and sloped so as to remove this water from the site. Once excavations have been
opened, they are to be blinded with mass concrete as soon as possible, so as to prevent any
rainfall occurring having an impact on the founding soils.
All drainage installations should be completed prior to building construction.
8.2.1 Surface Drainage
Surface drainage of building platforms should be designed to direct water away from fill
edges, to prevent overtopping of the fill crest and erosion of fill embankment slopes. Surface
water on these platforms should be directed to, and collected in, open lined drains or piped
to the natural drainage line.
10
It is important that grassing or protection of fill embankments be carried out as soon as
possible after construction, to minimise ponding of the water on the cut platforms to reduce
slope instability and piping erosion.
Run-off from building roofs should be piped from gutters, through downpipes, and
discharged into the storm water reticulation system. In addition a suitable concrete apron
should be provided at least 1.5 m wide and shaped away from the edge of the structure to
ensure effective run-off.
Since the area to be developed is in excess of 0.8 hectares, the storm water received onto and
generated on the site will have to be managed and attenuated on site.
8.2.2 Sub-Surface Drainage
It is strongly recommended that the subsoil drains (if required) be designed according to the
specific filter criteria of the in situ soils to prevent piping of the material and subsequent
rapid erosion.
8.3 Earthworks and Site Clearance
8.3.1 Site Clearance
All vegetation should be cleared from the areas over which structures are to be built. Any
removal of surface topsoil will probably bring any groundwater seepage closer to the surface
and this should be borne in mind and made clear to the contractor.
Earthworks should commence shortly after vegetation clearing to prevent erosion runoff
along the steeply sloping western slope.
8.3.2 Earthworks
It is recommended that all earthworks be carried out in accordance with SABS 1200 D.
In general, it is recommended that cut slopes and fill embankments have a maximum
slope of 1 vertical to 2 horizontal to ensure stability. Excavation with unsupported side
walls will remain relatively stable for short periods (less than 24 hours) unless they are
destabilized by a storm or a perched groundwater seepage. The need for the subsoil drainage
both beneath and in fills will have to be assessed during the earthworks, taking into account
the height and locality of individual fills.
The fills should be placed in layers not exceeding 200mm loose thickness, and compacted
to a minimum of 93% Modified AASHTO maximum dry density at 2% wet of optimum
moisture content. Cobbles and boulders larger than ²/3 of the layer thickness and clayey
or organic material must not be included in the fill material.
Both during and after construction, the site should be well graded to permit water to drain
away readily and to prevent ponding anywhere on the ground surface. All terraces and
earthworks in general should be sloped to a gradient of not less than 1 vertical in 50
horizontal to prevent ingress of water into the subsoils since these soils might be
11
significantly permeable. Surface drainage should be directed away from the crests of fill
embankments to prevent over-topping and erosion of fill slopes.
Backfill to service trenches must be raised slightly above the surrounding ground level and
be properly compacted to avoid the formation of a surface depression as a result of settlement
of the backfill. Such depressions will increase the ingress of stormwater runoff into the soils.
It is recommended that the number of trenches running at right angles to contours be limited
as these often become preferential drainage paths. All service trenches deeper than 1.5m
must be shored.
8.4 Settlement/Heave Analysis
Based on the laboratory test results, visual and tactile descriptions, the shallow foundation
soils (colluvium & talus) have been described as pin-holed and therefore prone to collapse
settlements ranging from 6 mm to 84 mm at an average of 30 mm (due to a collapse potential
ranging from 0.4 to 7%).
The laboratory test results show that the clayey subsoils are inert and not prone to heave.
8.5 NHBRC Site Classifications
Based on the conclusions provided in section 8.4 above, the NHBRC Site Classification for
majority of the site is C2 with minor zones of C1.
8.6 Foundation Recommendation
Under no circumstances should foundations be placed in/on untreated natural subsoils unless
it has been specifically engineered to support structural foundations.
In general, good practice requires that the in situ moisture content of the founding horizons
below the structure be maintained, and in this regard the following precautions should be
taken:
No water should be allowed to pond against or within the first meter from the external
perimeter of the structure.
Gardens located against the external perimeter of the structure are not recommended.
Leaks in plumbing and associated drainage are attended to without delay.
No large shrubs and or trees are planted closer than 0.75 x the mature height of the
tree.
Septic tanks and French drains are situated well away down gradient from any
buildings.
It is not, however, cost effective to construct foundations which totally remove the chance
of damage due to soil movements and in this light, some Category 1 damage to the structures
may be expected, i.e., fine internal cracks of widths less than 1 mm aperture. To a much
lesser extent some Category 2 damage may occasionally occur, with the formation of cracks
of less than 5 mm aperture. It is recommended that GCS Geotechnical inspect and approve
12
all foundation excavations to confirm depth of founding and bearing capacity of the
underlying founding horizons.
Given the results of the inspection pits, and the relatively low in situ moisture content (dry
to slightly moist), it is clear that the upper 2.4m of the soil profile will have a high collapse
potential. A high likelihood thus exists for collapse potential should there be a sudden ingress
of water resulting in saturation of the foundation soils. This may occur should services
adjacent to walls and foundations rupture or crack, or if water is allowed to pond against the
walls of the structure. The following foundation options should be considered:
NHBRC Site Class C1:
Modified normal with articulation joints and reinforced strip footings, or
Compaction of in-situ soils below individual footings with lightly reinforced strip
foundations and light reinforcement in masonry, or
Soil raft by removing in situ material to 1 m beyond perimeter of building to a depth
of 1.5 times widest footing and replace with inert approved (G7) material compacted
to 93% MADD. Normal construction with lightly reinforced strip footings and light
reinforcement in masonry.
NHBRC Site Class C2:
Stiffened strip footings with articulation joints or solid lightly reinforced masonry.
Bearing pressure not to exceed 50 kPa and fabric reinforcement in floor slab.
RC raft with same details as above.
Compaction of in situ soils below individual footings with lightly reinforced strip
foundations and light reinforcement in masonry.
Soil raft as above
8.7 Surface Beds
The upper soils would likely be considered adequate as subgrade materials after compaction.
The design value for the modulus of subgrade reaction (k) for floor slab design would
normally be between 35 and 65 kPa/mm provided the subgrade beneath surface beds or floor
slabs can be ripped to a depth of 300mm and re-compacted to 93% Mod AASHTO dry
density.
8.8 Recommended Subgrade Treatment
Transported materials tend to be highly variable in thickness and composition, and would
likely appear as sandy silty clay. However, these materials can be potentially collapsible and
therefore it is suggested that the upper 300mm be ripped, wetted to +2% of OMC and
compacted to 93% MADD.
8.9 Pipe Bedding
It is unlikely that the situ materials occurring on site would meet the strict bedding
specifications, according to the requirements of SABS 1200LB and therefore this
commodity should be allowed for in the tender documents.
13
9. CONCLUSIONS & RECOMMENDATIONS
This final NHBRC Phase I geotechnical report contains the findings and development
recommendations for the construction of the proposed township development on portion
419 of Farm 61 Phongola, KwaZulu-Natal.
It is considered that the conditions prevailing on site during the site investigation are
such that the majority of the site is considered suitable for the proposed development,
provided that the recommendations outlined in this report are adhered to. The main
geotechnical constraints to the development will be collapsible subsoils.
Six disturbed and four undisturbed samples were taken from the inspection pit
excavations for laboratory analysis. The six disturbed samples were sent for particle size
distribution, hydrometer analysis and Atterberg limits determination, and the four
undisturbed samples were sent for consolidometer testing. A summary of the results are
provided.
The site is underlain by transported fine colluvial material, which is underlain by coarse-
grained talus and andalusite-sericite schist and amphibole schist.
Soft excavation in terms of SABS 1200D is generally anticipated from surface to depths
in excess of 2.9 m below natural ground level.
Final recommendations for earthworks and drainage to promote stable development are
given.
Due to the collapse potential of the underlying colluvium, the NHBRC Site Classification
ranges from C1 to C2.
Due to the predominantly dry to slightly moist moisture condition, pin-holed structure
and loose to medium dense consistency of the clayey sands and firm to stiff consistencies
of the silty clays to depths in excess of 2.9 m, it is advised that the most appropriate
foundations options are modified normal strip footings, RC rafts or a compacted soil raft.
One of the more important factors in the promotion of a stable site is the control and
removal of surface water from the property. It is important that the design of the storm
water management system, allow for the drainage of accumulated surface water from the
platform and into the municipal storm water system or natural drainage lines.
Finally, it must be understood that the ground conditions described in this report refer
specifically to those encountered at the inspection positions on site. It is therefore
possible that conditions at variance with those discussed above may be encountered
elsewhere on the property.
In this regard it is important that GCS Geotechnical carry out periodic inspections of the
site during construction to ensure that any variation in the anticipated ground conditions
can be assessed, and revised recommendations made to avoid unnecessary delays and
expense. This constitutes the require NHBRC Phase II investigation which will entail the
14
mapping of individual service trench excavations to provide a more accurate NHBRC
Site Classification for each erf/stand after these have been pegged.
____________________ 6 October 2016
For GCS Geotechnical
www.gcs-sa.biz
Appendix A
TLB-Excavated Inspection Pit Profiles
Appendix B
Laboratory Test Results
Project: Farm 61 - 21887Client.: Soilco Hole/Block: TP 1Date: 30-09-2016 Depth (m): 1.3 - 1.4Sample No.: 09025 Consol No.: 5Sample Description: - Ring Dial. (mm): 76.75
Gauge Divs.(mm): 0.002 Specific Gravity: 2.58
Container No.: 23 Moisture content before testing (%): 15.43Mass of container (g): 81.81 Moisture content after testing (%): 26.99Mass of wet sample + container before testing (g): 234.02 Dry density before testing (kg/m3): 1500Mass of wet sample + container after testing (g): 249.26 Bulk density before testing (kg/m3): 1732Mass of dry sample + container (g): 213.67 Percentage saturation before test (%): 55.30
Percentage saturation after test (%): 108.10
Applied Dial Void Modulus of Compressibility MvPressure Reading Ratio Stress Mv Stress Mv(KPa) (divs) Range(kPa) (kPa-1) Range(kPa) (kPa-1)
1 5000 0.72025 4903 0.704 1 - 25 3.95E-04 1 - 25 3.95E-0450 4849 0.695 25 - 50 2.09E-04 1 - 50 2.99E-04
100 4789 0.685 50 - 100 1.11E-04 1 - 100 2.03E-04200 4699 0.672 100 - 200 8.27E-05 1 - 200 1.42E-04200 4548 0.644 200 - 200 #DIV/0! 1 - 200 2.22E-04NA NA NA NA NA NANA NA NA NA NA NA NANA NA NA NA NA NA NANA NA NA NA NA NA NANA NA NA NA NA NA NANA NA NA NA NA NA NA
Graph DataPrint PlotX Y
1 0.720062825 0.7037734450 0.69488727
100 0.68547286200 0.67153496200 0.64419737200 0.64419737200 0.64419737200 0.64419737200 0.64419737200 0.64419737200 0.64419737
Reference no.: 8228 Drennan Maud and Partners
Fig. no. -
Collapse Potential (%)
1.62
0.6
0.62
0.64
0.66
0.68
0.7
0.72
0.74
1 10 100 1000
Vo
id R
atio
(e)
Pressure (kPa)
Void Ratio (e) vs Log Pressure
Collapse Potential
Project: Farm 61 - 21887Client.: Soilco Hole/Block: TP 5Date: 30-09-2016 Depth (m): 0.6 - 0.7Sample No.: 09026 Consol No.: 6Sample Description: - Ring Dial. (mm): 76.35
Gauge Divs.(mm): 0.002 Specific Gravity: 2.67
Container No.: 24 Moisture content before testing (%): 11.27Mass of container (g): 81.95 Moisture content after testing (%): 23.90Mass of wet sample + container before testing (g): 235.5 Dry density before testing (kg/m3): 1586Mass of wet sample + container after testing (g): 252.93 Bulk density before testing (kg/m3): 1765Mass of dry sample + container (g): 219.95 Percentage saturation before test (%): 44.04
Percentage saturation after test (%): 99.24
Applied Dial Void Modulus of Compressibility MvPressure Reading Ratio Stress Mv Stress Mv(KPa) (divs) Range(kPa) (kPa-1) Range(kPa) (kPa-1)
1 5000 0.68325 4919 0.670 1 - 25 3.24E-04 1 - 25 3.24E-0450 4876 0.663 25 - 50 1.62E-04 1 - 50 2.41E-04
100 4836 0.658 50 - 100 6.82E-05 1 - 100 1.53E-04200 4775 0.649 100 - 200 5.13E-05 1 - 200 1.02E-04200 4740 0.643 200 - 200 #DIV/0! 1 - 200 1.20E-04NA NA NA NA NA NANA NA NA NA NA NA NANA NA NA NA NA NA NANA NA NA NA NA NA NANA NA NA NA NA NA NANA NA NA NA NA NA NA
Graph DataPrint PlotX Y
1 0.6831823125 0.6700768150 0.66332995
100 0.65766063200 0.64915927200 0.64295861200 0.64295861200 0.64295861200 0.64295861200 0.64295861200 0.64295861200 0.64295861
Reference no.: 8228 Drennan Maud and Partners
Fig. no. -
Collapse Potential (%)
0.36
0.6
0.61
0.62
0.63
0.64
0.65
0.66
0.67
0.68
0.69
0.7
1 10 100 1000
Vo
id R
atio
(e)
Pressure (kPa)
Void Ratio (e) vs Log Pressure
Collapse Potential
Project: Farm 61 - 21887Client.: Soilco Hole/Block: TP 9Date: 30-09-2016 Depth (m): 1.0 - 1.20Sample No.: 09027 Consol No.: 7Sample Description: - Ring Dial. (mm): 76.15
Gauge Divs.(mm): 0.002 Specific Gravity: 2.69
Container No.: 27 Moisture content before testing (%): 21.01Mass of container (g): 81.06 Moisture content after testing (%): 31.25Mass of wet sample + container before testing (g): 214.56 Dry density before testing (kg/m3): 1275Mass of wet sample + container after testing (g): 225.85 Bulk density before testing (kg/m3): 1543Mass of dry sample + container (g): 191.38 Percentage saturation before test (%): 50.91
Percentage saturation after test (%): 93.57
Applied Dial Void Modulus of Compressibility MvPressure Reading Ratio Stress Mv Stress Mv(KPa) (divs) Range(kPa) (kPa-1) Range(kPa) (kPa-1)
1 5000 1.11025 4919 1.094 1 - 25 3.24E-04 1 - 25 3.24E-0450 4854 1.080 25 - 50 2.55E-04 1 - 50 2.88E-04
100 4794 1.069 50 - 100 1.11E-04 1 - 100 1.98E-04200 4680 1.046 100 - 200 1.08E-04 1 - 200 1.52E-04200 4013 0.898 200 - 200 #DIV/0! 1 - 200 5.05E-04NA NA NA NA NA NANA NA NA NA NA NA NANA NA NA NA NA NA NANA NA NA NA NA NA NANA NA NA NA NA NA NANA NA NA NA NA NA NA
Graph DataPrint PlotX Y
1 1.1101763125 1.0937461750 1.08040144
100 1.06885182200 1.04642227200 0.89827845200 0.89827845200 0.89827845200 0.89827845200 0.89827845200 0.89827845200 0.89827845
Reference no.: 8228 Drennan Maud and Partners
Fig. no. -
Collapse Potential (%)
7.01
0.8
0.85
0.9
0.95
1
1.05
1.1
1.15
1.2
1 10 100 1000
Vo
id R
atio
(e)
Pressure (kPa)
Void Ratio (e) vs Log Pressure
Collapse Potential
Project: Farm 61 - 21887Client.: Soilco Hole/Block: TP 13Date: 30-09-2016 Depth (m): 1.7 - 1.8Sample No.: 09028 Consol No.: 4Sample Description: - Ring Dial. (mm): 76.45
Gauge Divs.(mm): 0.002 Specific Gravity: 2.68
Container No.: 25 Moisture content before testing (%): 26.84Mass of container (g): 83.62 Moisture content after testing (%): 40.00Mass of wet sample + container before testing (g): 221.41 Dry density before testing (kg/m3): 1246Mass of wet sample + container after testing (g): 235.7 Bulk density before testing (kg/m3): 1580Mass of dry sample + container (g): 192.25 Percentage saturation before test (%): 62.45
Percentage saturation after test (%): 114.55
Applied Dial Void Modulus of Compressibility MvPressure Reading Ratio Stress Mv Stress Mv(KPa) (divs) Range(kPa) (kPa-1) Range(kPa) (kPa-1)
1 5000 1.15225 4917 1.135 1 - 25 3.33E-04 1 - 25 3.33E-0450 4854 1.122 25 - 50 2.47E-04 1 - 50 2.88E-04
100 4794 1.110 50 - 100 1.11E-04 1 - 100 1.98E-04200 4680 1.087 100 - 200 1.08E-04 1 - 200 1.52E-04200 4013 0.936 200 - 200 #DIV/0! 1 - 200 5.05E-04NA NA NA NA NA NANA NA NA NA NA NA NANA NA NA NA NA NA NANA NA NA NA NA NA NANA NA NA NA NA NA NANA NA NA NA NA NA NA
Graph DataPrint PlotX Y
1 1.151894125 1.1346861550 1.12153059
100 1.10975264200 1.08687966200 0.93580706200 0.93580706200 0.93580706200 0.93580706200 0.93580706200 0.93580706200 0.93580706
Reference no.: 8228 Drennan Maud and Partners
Fig. no. -
Collapse Potential (%)
7.02
0.9
0.95
1
1.05
1.1
1.15
1.2
1 10 100 1000
Vo
id R
atio
(e)
Pressure (kPa)
Void Ratio (e) vs Log Pressure
Collapse Potential
Figure 1
Site Plan
Figure 2
Geological Plan