36
EXTERNAL MONITORING REPORT ON THE SPECIFIC PROGRAMME FOR RESEARCH AND TECHNOLOGICAL DEVELOPMENT IN THE FIELD OF NUCLEAR ENERGY FUSION

EXTERNAL MONITORING REPORT ON THE … monitoring report on the specific programme for research and technological development in the field of nuclear energy fusion

Embed Size (px)

Citation preview

EXTERNAL MONITORING REPORT

ON THE SPECIFIC PROGRAMME

FOR RESEARCH AND TECHNOLOGICAL

DEVELOPMENT

IN THE FIELD OF

NUCLEAR ENERGY FUSION

This is part of the series of the external annual monitoring reports prepared for the EC Framework Programme and the Euratom Framework Programme, and their constituent Specific Programmes, and also - as a novelty- covers the implementation of the European Research Area (ERA) related activities. The Commission has over the years been placing increasing emphasis on the evaluation of Community R&D activities. With the overall Reform of the Commission, evaluation activities are more and more placed at the heart of the decision process. In line with this continuous effort for improvement, a revised programme monitoring scheme has been introduced in 2001, based on the system launched in 1995 which involved independent experts in the monitoring activities. The new mechanism launched this year, has been built in order to better involve the experts monitoring the implementation of ERA and specific programmes, by representing them in the Framework Programme Monitoring Panel (FPMP). The timely response by the Programme management to the recommendations produced by the experts will be enhanced, providing the basis for a quick response mechanism to programme developments, as the follow up of experts recommendations will be receiving still more attention. This report is the third covering the Fifth Framework Programme; the report also highlights progress in relation to implementation of ERA and results and impact of previous Framework Programmes. The report should help reinforce establishment of best practices and identify the scope for further improvements in programme implementation.

The report consists of two parts: Part A: External monitoring report prepared by the following

independent external experts: Dr Björn Brandt Dr Joaquín Calvo Prof. Dr Günther Lehner Part B: Responses of the Programme management to the external

monitoring report.

PART A:

Report of the external Monitoring Panel

TABLE OF CONTENTS 1. EXECUTIVE SUMMARY................................................................................................................................... 1

2. PANEL METHODOLOGY ................................................................................................................................. 2

3. INTRODUCTION................................................................................................................................................. 3

4. ANALYSIS AND FINDINGS............................................................................................................................... 4

4.1 STRATEGY - OBJECTIVES .............................................................................................................................4 4.1.1 The Fast Track .......................................................................................................................................... 4 4.1.2 Progress in ERA and programmes implementation.................................................................................. 5 4.1.3 Significant results in the European and international context.................................................................. 6

4.1.3.1 Progress towards ITER........................................................................................................................................ 6 4.1.3.2 Use of the JET facilities ...................................................................................................................................... 6 4.1.3.3 Work in the Associations .................................................................................................................................... 6 4.1.3.4 Fusion Technology.............................................................................................................................................. 7 4.1.3.5 Socio-Economic, Safety and Environment Studies ............................................................................................. 7 4.1.3.6 Public Awareness and Understanding of Fusion Power...................................................................................... 8 4.1.3.7 Fusion and Industry............................................................................................................................................. 8 4.1.3.8 International Co-operation .................................................................................................................................. 9 4.1.3.9 Inertial Confinement Keep-in-Touch Activity .................................................................................................... 9 4.1.3.10 Training and Mobility ......................................................................................................................................... 9

4.1.4 Participation of candidates countries..................................................................................................... 10 4.1.5 Participation of SMEs............................................................................................................................. 10 4.1.6 Women and science................................................................................................................................. 10 4.1.7 Towards new FP: modalities of implementation .................................................................................... 10

4.2 MANAGEMENT AND PROCESSES..............................................................................................................11 4.2.1 Main management issues ........................................................................................................................ 11 4.2.2 Evaluation and Monitoring Methodology, including indicators ............................................................ 12 4.2.3 Ethical Aspects........................................................................................................................................ 12

4.3 IMPACT OF PREVIOUS RESEARCH FPS AND SPS......................................................................................13 4.4 FOLLOW UP OF PREVIOUS MONITORING AND FIVE YEAR ASSESSMENT

RECOMMENDATIONS ..................................................................................................................................13

5. CONCLUSIONS AND RECOMMENDATIONS ............................................................................................ 15

5.1 GENERAL CONCLUSIONS, MAJOR TRENDS, MAIN STRENGTHS AND WEAKNESSES ENCOUNTERED .......................15 5.2 RECOMMENDATIONS ..........................................................................................................................................15

5.2.1 Recommendations on the Specific Programme....................................................................................... 15 5.2.2 Recommendation on the Monitoring Methodology................................................................................. 16

6. ANNEXES............................................................................................................................................................ 17

6.1 CORE INDICATORS AND BUDGET FIGURES .........................................................................................................17 6.2 ABBREVIATIONS.................................................................................................................................................23 6.3 DOCUMENTS PROVIDED TO THE EXPERTS BY THE PROGRAMME MANAGEMENT .................................................24 6.4 TENTATIVE TIME SCHEDULE TOWARDS JOINT IMPLEMENTATION OF ITER..........................................................26

1

1. EXECUTIVE SUMMARY At present the European Fusion Programme is considered to be the world’s leader in its field and it also represents a well implemented and probably unique European Research Area. The panel found that the Commission’s fusion staff has managed the European Fusion Programme very well and has implemented it along the guidelines and the directives issued by the Council within the given boundary conditions.

The programme is however at a critical stage, because decisions of essential importance for its future have been delayed for years. The programme also suffers because its management has been weakened by the recent reorganisation of DG Research. With the approach of decisions on the “Next Step” (ITER) in the near future, it will need stronger management. It is also foreseen that there will be insufficient funding under the next Framework Programme, FP6, to maintain the quality and strength of the Fusion Programme.

The principal recommendations of the panel are that:

�� ITER should proceed as soon as possible and all necessary decisions should be made promptly. While ITER should preferably be achieved by an international collaboration, Europe should be ready to proceed alone if necessary.

The present European mandate of negotiations to establish an ITER Legal Entity with its international ITER partners, should be enlarged in order to address ITER site, organisational and cost sharing issues.

Europe should take the lead, including promoting European candidate sites.

�� The Fast Track proposal (aiming to demonstrate the feasibility of fusion in 20-30 years) should be studied in detail and should be realised. This could save substantial public funds and a lot of valuable time.

�� As soon as a decision is made on ITER, the current management structure should be strengthened by creating a Fusion Directorate within the Commission. An appropriate European Legal Entity should also be established under the umbrella of the Commission to represent Europe in the ITER organisation.

The panel also recommends that:

The work of the Associations and the use of the JET facilities should be continued under FP6.

The materials development activities should also be further pursued intensely under FP6.

Socio-economic, environmental and safety studies should be further strengthened under FP6 and their results used to enhance public awareness and acceptance of fusion power and its future importance.

Efforts should be made to bring in new young scientists and technicians.

The co-operation with industry, including SMEs, should be further intensified.

2

2. PANEL METHODOLOGY The external monitoring has been undertaken in accordance with the legislative requirements given in Article 5 of the Council Decision of 22 December 1998 on the 5th EC Framework Programme and on the Euratom Framework Programme, and with Article 4 of the Council Decision of 25 January 1999 adopting the Specific Programme in the field of nuclear energy (Euratom). Annexes I and II of this Council Decision specify the objectives and Research and Technological Development (RTD) priorities of the Key Action on Controlled thermonuclear Fusion [1.1]1.

The Commission has asked a panel of three independent experts to monitor the implementation of the Fusion Programme in the year 2001 along the methodological Broad Guidelines of 8 November 2001 [2.2]. It was recommended that the monitoring exercise should focus on the following main issues:

• Follow-up of the recommendations made by the monitoring panel for the year 2000,

• Contribution to implementation of the European Research Area (ERA),

• Participation by accession countries,

• Small and Medium Enterprises (SME) participation,

• Women and science,

• Impact of earlier research Framework Programmes.

Panel members were Dr. Björn Brandt (chairman), Dr. Joaquin Calvo, and Prof. Dr. Günther Lehner. In preparing this report the experts were assisted by Dr. Fiona Porter of AEA Technology plc, UK.

Having used the information provided to the experts, i.e. the documents listed in annex 6.3, and having had intensive discussions with the members of the fusion staff of DG Research (Dr. Umberto Finzi, Principal Advisor to the Director General on matters concerning fusion, Prof. Dr. Hardo Bruhns, head of Unit J.6, acting Director of Directorate J until mid-March 2002, Dr. Jean-Pierre Rager, head of Unit J.5, Dr. Douglas Bartlett, and Dr. Rosa Antidormi) the experts have met four times in the period from 8 November 2001 to 27 February 2002, on which latter day the main parts of the monitoring report were finalised). In addition, interviews were held with some members of the programme committee (CCE-FU) from Germany, Spain and Sweden. Prof. Dr. Paul Vandenplas, vice chairman of the CCE-FU, has also been interviewed by the whole panel.

1 Note: document numbers, as listed in Annex 6.3 are indicated in [].

3

3. INTRODUCTION The long term objective of the European Fusion Programme is “the joint creation of prototype reactors for power stations to meet the needs of society: operational safety, environmental compatibility, economic viability” [1.1]. The Council Decision defines three main lines of research (Next Step activities, concept improvements and long-term technology) and several additional activities as integral parts of the Key Action Controlled Thermonuclear Fusion (socio-economic studies, assessments of safety and environmental aspects, information of the public, mobility and training of researchers, and a keep-in-touch activity on inertial confinement and possible alternative concepts).

Fusion power is one of only a few options which could in principle, if successfully developed, contribute to the solution of the future energy problem, which will become very serious within the next few decades. In its recent Green Paper (“Towards a European strategy for the security of energy supply” [3.21 and 3.21a]), the Commission analyses in detail energy scenarios for the next decades. Dependence on imports of energy from external sources will increase to 70% (from its present 50%) if no measures are taken. Due to the seriousness of this problem and the time scales involved, research into reactors of the future, notably nuclear fusion, is considered to be a priority of European energy policy.

The Green Paper conclusions are shared and supported by the Scientific and Technical Committee Euratom (STC) [3.3] and the Energy Working Group (E-WOG) [3.6]. Moreover, the External Advisory Group for the Key Action “Controlled Thermonuclear Fusion” (EAG-FU) [3.5] recognises that fusion power plants have good prospects of meeting the need for economic and environmentally benign base-load electricity generation plants. It therefore recommends political decisiveness to maintain the time schedule for the development of fusion power. In summary, the EAG-FU believes that the EU should vigorously pursue its R&D activities in controlled fusion research. The EU should also do all that is possible and reasonable to site the next large fusion experiment in Europe.

It is important to keep the discussions on the energy problem on a pragmatic level. Last year’s Specific Framework Monitoring Panel, therefore stressed: “It should be appreciated that a decision to go forward with ITER is not a decision to use fusion. It is a decision to provide future generations with the knowledge necessary to make informed decisions on the use of fusion” [2.3].

This is the background against which the present panel has to judge the achievements of the management in the implementation of the European Fusion Programme, taking into account the guidelines and directives given by the Council in its decisions [1.1, 1.2 and 1.3]. The panel’s main findings are that political indecisiveness has delayed the progress of the programme for many years and that the strong management structure necessary for such a task does not at present exist.

4

4. ANALYSIS AND FINDINGS

4.1 STRATEGY - OBJECTIVES

The long-term objective is “the joint creation of prototype reactors for power stations to meet the needs of society: operational safety, environmental compatibility, economic viability”. Within that context, the aim of the Key Action on Controlled Thermonuclear Fusion is “to further develop the necessary basis for the possible construction of an experimental reactor (the "Next Step"), with the objective of demonstrating the scientific and technological feasibility of fusion power production as well as its potential safety and environmental benefits”.

The Fusion Programme currently has three main themes: Next Step Activities (which are supposed to lead to the construction and operation of the “Next Step”, hopefully by the international ITER co-operation), Concept Improvements (to be applied in a later device, DEMO, following ITER and followed by a prototype commercial fusion reactor, PROTO), and Long-Term Technology (for use in DEMO and commercial reactors). The future Fusion Programme for 2002 and FP6 will be pursued along the same main lines and no significant changes to the programme are foreseen. The present major task of the Commission Services is the preparation of FP6. In particular, the Commission will represent the Community in the negotiations on an international ITER legal entity, which is necessary for the realisation of ITER and for the decision on an ITER site, hopefully at the end of 2002. The Commission will also prepare the restructuring of the European Fusion Programme which is necessary if and when a decision to proceed with ITER is taken. The CCE-FU has established a Special Working Group (SWG) to develop concepts and proposals for the structure needed in case of a positive ITER decision. The preliminary recommendations and views of the SWG include:

�� ITER must have first priority and should be constructed in Europe.

�� An appropriate programme in physics and technology including fusion materials is required, also to train young European scientists and engineers and to retain fusion competence in Europe.

�� The time schedule for ITER is a very critical issue.

The panel strongly supports these views.

4.1.1 The Fast Track

According to current plans, about 50 years will be necessary to realise the first commercial fusion reactor (PROTO), following intermediate generations Next Step and DEMO. This is a rather long time, especially if, as the Green Paper concludes, (Section 3), there will be difficulties for European energy supplies within 20 to 30 years from now. It would certainly be very useful and may even be necessary to reduce the 50 years by accelerating the programme.

The UK Department of Trade and Industry, being aware of these facts, saw convincing reasons for a significant role for fusion and in October 2001 proposed an examination of the feasibility of demonstrating fusion power within 20 to 30 years.

5

On the initiative of the Belgian Presidency, the EU Research Council took up the matter and established a Fast Track Working Group. This Group, chaired by Prof. David King, Chief Scientific Advisor to the UK Government, met on 27 November 2001. The report produced by the Group (the “King Paper”) for the EU Research Council, gives a positive and very interesting first assessment of the British proposal. Some of its conclusions are:

�� “The ITER project is the essential step towards energy production on a fast track”

�� “…in a fast track approach, the DEMO and PROTO generations could be combined in a single step that should be designed as a credible prototype for a power producing fusion reactor”.

�� This combined device “would depend strongly on the development of adequate materials”.

�� The design of the International Fusion Materials Irradiation Facility IFMIF, necessary for fusion materials research, should be completed in FP6.

�� International collaboration should be expanded. A clear European position would probably generate a positive response from both existing and potential new ITER partners.

The Monitoring Panel welcomes the British initiative and the prompt reaction of the EU Research Council. It also supports the conclusions of the Fast Track Working Group. To combine DEMO and PROTO in a single step appears to be a very interesting idea. The whole Fast Track scenario should be seriously investigated in detail with all its consequences. Its realisation would have the essential advantages of allowing some of the time lost by delayed decisions to be recovered and of strongly reducing the required public funding for the whole project if one generation of fusion devices is saved (though more funding would be needed in the early stages). Finally the earlier availability of power from commercial fusion reactors could facilitate the solution of severe energy supply problems.

4.1.2 Progress in ERA and programmes implementation

As observed by several bodies and panels the European fusion programme already provides an excellent example of a very successful and well-implemented European Research Area (ERA). It has reached its present standing because of decades of dedicated work by the fusion staff of DG Research and of associated national institutes, which together form an integrated network of excellence in the field of fusion. This reputation has arisen from the success of the Joint European Torus (JET) and of many successful theoretical, experimental and technical results obtained in the Associations (cf. conclusions of the recent FiveYear Assessment -Airaghi Panel [2.4] , of EAG-FU [3.5] and E-WOG [3.6]). The panel supports the well-founded views expressed in these references. It must stress, however, that such a successful European Research Area could only be realised through the enthusiasm of all people involved at all levels and their dedication to a large and challenging highly motivating joint aim.

After JET the next aim of the ERA of Fusion is the “Next Step" (ITER). However, essential ITER decisions are overdue. Further delays risk demotivation of the personnel involved and a rapid disintegration of the cohesive forces of this ERA. Previous Fusion Monitoring Panels have been concerned about this problem and recommended that ITER decisions should be made as soon as possible. Unfortunately these recommendations have not been acted upon.

The fusion programme is based on a completely integrated European programme. The instruments for its creation have been developed and optimised over a long time. Projects are carried out in a framework of cost-sharing research and technological development, implemented in accordance with the procedures laid down in the contracts of the Euratom-Associations and in the European Fusion Development Agreement (EFDA). There is a hierarchy of strong financial instruments

6

based on different financial contributions, about 25% for the normal expenditure of the Associations, 45% for specifically specified priority projects, 75% for special activities as for instance the operation of the JET facilities, and 100% for procurements and services which can only be provided by industry.

4.1.3 Significant results in the European and international context

4.1.3.1 Progress towards ITER

The year 2001 has seen some important progress towards ITER, though it is still suffering from the lack of political decisions already mentioned. A detailed and mature design, which meets the cost requirements set in 1998, has been completed [3.4,3.4a, 3.4b, 14c]. A large-scale model of a toroidal field coil has been successfully tested. Canada has officially offered Clarington, Ontario, as an ITER site [3.8]. Given that an official French offer is expected in the near future, a detailed technical investigation of Cadarache as an ITER site has been carried out and came to the conclusion that it fulfils all the technical requirements [3.9]. There may also be other proposals from Europe: the Spanish Ministry of research has asked CIEMAT (the Spanish fusion Association) to examine the technical aspects of several sites, and if the outcome is favourable they have indicated a willingness to propose one of these as a possible European site.

Formal negotiations on the joint implementation of ITER have been started among EURATOM, Canada, Japan and Russia. They are based on a limited mandate, which needs to be generalised to include cost and siting issues. In addition, a European legal entity under the Commission’s umbrella, representing Europe in its relation to the international legal ITER entity is also urgently needed. The time schedule for the necessary decisions and negotiations along the path to ITER, (annex 6.4) is extremely tight. To avoid further unacceptable delays, ITER must become an essential part of FP6.

There is currently a growing interest in the United States to consider participation in ITER again. The present ITER parties would certainly welcome them coming back and this would give extra momentum to the negotiations.

4.1.3.2 Use of the JET facilities

JET is the largest and most important European fusion device and an indispensable part of the European fusion programme as long as ITER is not operating. Due to the long delay of ITER decisions it will take a long time until ITER can start operation. Consequently JET should be used for as long as possible to minimise the time gap between the end of its operation and the beginning of ITER operation. JET can produce many further results relevant to ITER. It is also important to train scientists and engineers for ITER, as they could lose competence if not able to do experiments with large fusion devices.

The use of' the JET facilities under the auspices of EFDA has continued very successfully in 2001 by experimental campaigns, prepared and performed by scientists from the Associations. At present the machine is shut down for upgrading. Larger planned upgrading, (the JET Enhanced Performance (JET-EP)), is however being reviewed in the light of the possible budgetary limitations in FP6.

4.1.3.3 Work in the Associations

7

In 2001 the Associations have continued to produce a wealth of results for all parts of the European Fusion Programme. This included “Next Step" activities in support of ITER, preparing and performing experimental JET campaigns, investigating concept improvements, developing long term technology and performing socio-economic, environmental and safety studies. Particular highlights were the accomplishment, by the Associations Euratom-Suisse, FZK and CEA of a 1 MW 140 GHz gyrotron with energy recovery capable of steady state operation; the successful testing of a poloidal field model coil for ITER yielding the highest current (80 kA) in a superconductor ever achieved; the identification of high confinement operation in a Stellarator island divertor (Association Euratom-IPP). Important new results have been obtained at JET, pointing the way towards possible operation of ITER in so-called “advanced regimes” of increased performance. A more extensive review of the achievements of the Associations is given in document 2.1 (“Self-Assessment for Key Action Fusion”).

There has been an enhancement of the activities that promote public awareness and acceptance of fusion power as a possible future energy option. Through the Associations’ contacts and co-operation with universities they play an important role in bringing young scientists into the field of fusion and training them for the challenging future developments.

An important task for the Associations in the near future is to prepare themselves for the programme changes needed when ITER will be built. This is a difficult task, which will also involve a reallocation of funds.

4.1.3.4 Fusion Technology

There are two types of activity in the field of fusion technology: technology in support of the “Next Step” (ITER), and Long Term Technology in preparation for a prototype demonstration reactor, (DEMO), to follow the “Next Step”. Areas being investigated include breeding blankets, materials development and the design of a fusion materials test facility. The aim of materials research is to develop and to qualify low activation structural materials. Radiation testing of these materials is an essential part of the Long Term Technology activities. It will require an appropriate 14 MeV neutron source which is being considered by an international consortium under the IEA, the International Fusion Materials Irradiation Facility, IFMIF. At present the issues related to the IFMIF are investigated in the “Key Element Phase”, KEP. These activities are proceeding as expected. They should be continued under FP6.

A particular highlight in fusion technology has been the successful test of ITER Toroidal Field Model Coils at the TOSKA facility at the Association Euratom-FZK (Karlsruhe). This is a first-of-a-kind in the field of superconducting magnet technology and the test confirmed the expected behaviour of the superconductor and joint resistance and gave preliminary but important confirmation that the design of ITER poloidal field model coil is viable.

The above mentioned “Fast Track” approach would also require an acceleration of fusion technology activities, which would have to be carried out in parallel to ITER construction and operation at full power. An increase of funding would be necessary, although only for a limited period: the total investment needed to produce a prototype power station would be reduced. In any case, the indecisiveness characterising recent years is a less economic way to execute the programme.

4.1.3.5 Socio-Economic, Safety and Environment Studies

Progress has been made on Socio-Economic, Safety and Environment Studies in 2001. The “Socio-Economic Research on Fusion”, SERF 1, launched in 1997, has been continued by SERF 2

8

in 1999-2000 and by SERF 3 in 2001 [3.12]. One of the conclusions was that fusion power can become cost-effective if the external costs (in particular the need to stabilise the CO2 content of the atmosphere) are properly taken into account.

Safety studies, originally started in 1995 via “Safety and Environment Aspects of Fusion Power”, SEAFP, have been continued by further studies, SEAFP 2, SEAFP 99 and “Safety and Environmental Aspects Long Term”, SEAL. In 2001 another Study, “Safety and, Environmental Impact of Fusion”, SEIF, has been concluded [3.13]. It integrates all previous work. It shows for instance that fusion reactors can be inherently safe and in particular power excursions are self-limited. A “Power Plant Conceptual Study”, PPCS, has been launched in 2000, to assist the assessment of the status of fusion energy and establish coherence and priorities for the EU fusion programme. Stage I developed draft objectives for fusion power plant designs. The work of Stage II was encapsulated in a further draft of the General Design Requirements Document, and Stage III will comprise the conceptual design of several models of commercial fusion power plants, including their safety, environmental impact and economics. These studies should also be continued under FP6.

4.1.3.6 Public Awareness and Understanding of Fusion Power

The efforts to improve public awareness and understanding of fusion have been expanded appreciably in 2001. A travelling exhibition “Fusion Expo” has been shown in Switzerland (Yverdon and CERN), Germany (Berlin), Spain (Madrid), the Netherlands (Amsterdam) and Argentina (Buenos Aires). An exhibition prepared by the EFDA Close Support Unit, CSU, and by the Associations, has been shown at the UN Conference on Climate Change at the Hague. EFDA also provides a website and regularly appearing newsletters. The international Solar Energy Society, ISES, has published an EFDA paper on the merits of fusion. The Associations generate a great deal of information for use within their own countries (brochures, CD-ROMs, websites etc.). The Commission also distributes information and has developed an “Energy Research” website. The Commission has contributed to a number of summer schools and workshops, devoted to fusion research.

The European Fusion Programme needs a high degree of public acceptance, support and an understanding of the possible role of fusion for the solution of the serious future energy problem. This is an extremely difficult, but unavoidable task, which should be continued vigorously under FP6.

4.1.3.7 Fusion and Industry

The involvement of industry in the fusion programme is, as a result of Europe wide calls for tender, quite intensive. The involvement of industry would be further intensified by ITER construction, inasmuch as 80 % of its budget would go to manufacturers. Utilities are the prospective users of fusion technology and they will show interest in ITER construction and operation to be able to assume a relevant role in the project of the future demonstration power plant. In preparation of a possible positive ITER decision, the CCE-FU has requested the Committee on Fusion-Industry, CFI, to prepare a paper on the preferred EU contributions to ITER construction.

There are immediate benefits from the involvement of industry in the current fusion programme, for instance by spin-offs, when companies (including SMEs) develop or improve products under contract to Associations and then find additional markets for these products. Another possible advantage for these companies is a transfer of expertise in high-tech fields. In May 2001 the CFI organised a workshop on spin-offs and transfer of technology from fusion R&D to industry at IPP-

9

Garching, Germany. A wide variety of spin-offs were presented, and the ways in which technology transfer and generation of spin-offs could be enhanced were discussed, with particular reference to SMEs higher involvement in EU programmes [3.11]. The UKAEA has well developed activities on promotion and development of fusion spin-offs. There are many examples of spin-offs, such as numerical modelling of complex systems (e.g. financial systems), superconducting magnet technology (e.g. medical scanners), high power lasers with industrial applications, bonding techniques for advanced materials etc.

4.1.3.8 International Co-operation

In addition to participation of the candidate countries and the multilateral international ITER co-operation, international co-operation has been extended through signing new agreements with the United States in May 2001 and with Russia in October 2001. The preparation of collaborations based on these agreements is in progress. Similar agreements with the Ukraine and with Kazakhstan are in the final stages of conclusion. There is also a bilateral agreement with Japan.

Implementing Agreements in the IEA framework are quite numerous. Topics of cooperation include environmental and safety issues, fusion materials, nuclear technology of fusion reactors, plasma wall interaction (in connection with Textor, KFA Jülich), reversed field pinches, Stellarators, large Tokamaks, and toroidal physics (in connection with Asdex Upgrade, IPP Garching). The countries involved are Australia, Canada, China, Japan, Russia, Switzerland, Turkey, and the United States of America.

4.1.3.9 Inertial Confinement Keep-in-Touch Activity

In principle there are two possible methods of confining fusion plasmas, magnetic confinement and inertial confinement. Magnetic confinement has established itself as the preferred route to fusion power stations. The national research programs (US, F, UK) on inertial fusion are mainly motivated by defence (military) research. The Commission has established a keep-in-touch activity to observe the progress of inertial confinement research via the Inertial Fusion Energy Coordinating Committee-Technical Group (IFECC-TG), which held its last meeting on 19 November 2001. So far there is no reason to reconsider the fusion programme. The Council Decision also mentions “possible alternative concepts”. One such a concept is µ-mesonic fusion, which at present is of purely academic interest.

4.1.3.10 Training and Mobility

The Mobility Agreement is very effective in supporting the exchange of scientists in fusion research. It is essential for the execution of JET campaigns by the Associations, for the co-operation on activities related to ITER, for collaboration among Associations and “clusters” of Associations, allowing for instance smaller Associations to perform collaborative experiments on large devices. Estimates for 2001 are of about 500 individual exchanges and a total of about 650 professional person-months. Of this the exchange of scientists from the Candidate Countries amounts to about 50 professional visits and 90 person-months.

10

4.1.4 Participation of candidates countries

Participation of the candidate countries has progressed. So far there are Associations in Romania (Association Euratom-NASTI), in the Czech Republic, (Association Euratom-IPP.CR), and in Hungary (Association Euratom-HAS). A contract of Association between Euratom and the University of Latvia has recently been concluded. Bulgaria, Slovakia and Slovenia presently participate through cost-sharing actions based on contracts of limited duration. There is no co-operation in the field of fusion with Poland, the largest among all candidate countries, because like Estonia and Lithuania it has chosen not to associate with the Euratom Framework Programme.

The candidate countries have developed good starting levels of activity. Their introduction in the overall programme should however further grow. This situation could be developed further if the scientific workshops involving all or several associations are held in candidate countries with the additional purpose of establishing improved mutual relations between researchers from these countries and the other associations.

4.1.5 Participation of SMEs

Much of the work in the construction of fusion devices requires expertise in large-scale, complex technologies, which in most cases requires the resources of large companies. However, SMEs also participate, through the supply of specialist high-tech services and the development of smaller-scale auxiliary systems. There are immediate and tangible (although difficult to quantify) benefits that result from the involvement of industry in the fusion programme. These consist of direct spin-offs (as mentioned in section 4.1.3.7 above), where companies (often SMEs) develop or improve products under contract to fusion laboratories and then find other markets for them, plus a more general development and transfer of expertise in a variety of high-tech areas. Examples of this process abound, ranging from development of high power solid-state electronic systems to industrial-scale application of innovative techniques for material bonding and fabrication of superconducting strands.

4.1.6 Women and science

In common with other areas of the physical sciences and engineering, the representation of female professionals in the fusion programme is well below 50%. A survey of the staff lists of several of the Associations (including large, medium and small, NAS states and long-standing members) shows an average of about 10% women among professional staff, with substantial variations between the various Associations. An alternative indication of the role of women can be obtained from the statistics on the participation of women in the experimental campaigns on JET. For example, of the 216 experimental proposals for the 2002 campaigns, 26% had female scientists as principal proposers and 26% of the 354 scientific co-ordinators who will execute these experiments are women.

The Commission has a policy of equal opportunity, with recruitment based solely on merit. On a recent reserve list for possible recruitment in fusion, 32% of candidates were women.

4.1.7 Towards new FP: modalities of implementation

The continuation of the European Fusion Programme beyond FP 5 depends on the decisions on FP 6. It has been mentioned several times already, how important timely decisions are for the future of the programme. The Commission has prepared a proposal for FP6, including the European Fusion Programme. Decisions have not yet been taken, however.

11

There is a Commission proposal for the “Council Decision concerning the Sixth Framework Programme of the European Atomic Energy Community (EURATOM) for research and training activities, also contributing to the creation of the European Research Area (2002-2006)”. The level of funding foreseen for fusion during FP6 in this draft (750 million Euro) will compromise the capability of fusion associations to vigorously support ITER R&D. This could slow down the progress of the programme and therefore would risk being uneconomic in the long term. The Commission should try to increase the funds by all reasonable means before the final decision on the draft.

The Framework programmes aim to make Europe the most dynamic knowledge-based economy in the world. The integration of European research would greatly benefit from one large joint project in Europe that could be a flagship of world energy research. This would attract the participation of other countries and demonstrate the dedication and strength of a united Europe. At present there is nothing under the European Union umbrella of this grandeur.

The continuing exploitation of JET and support for the construction of ITER would be consistent with the emphasis by the Commission in FP6 on joint projects.

4.2 MANAGEMENT AND PROCESSES

4.2.1 Main management issues

The management procedures that are the subject of the present monitoring exercise are quite different from the ones of other Community Programmes. There is only one large project, the aim of which, as is defined in the Council Decision [1.1], is the joint creation of operationally safe, environmentally compatible and economically viable fusion reactors. During the fifth Framework Programme the subtasks were the so called “Next Step” activities, concept improvements, long term technology, socio-economic aspects of fusion energy, safety and environmental studies, information of the public to increase its awareness and understanding of fusion power, mobility and training of scientists and technicians in the field of fusion. Based on many discussions with the members of the Commission’s Services and on many documents, listed in annex 6.3, the panel comes to the conclusion that the fusion staff has, within the limits of its possibilities, managed the European Fusion Programme excellently and much better than was to be expected under the difficult conditions given.

It must, however be said, that the programme has been in a critical stage for some time. There are two essential managerial issues, which have been under discussion for a long time and which the present panel has to stress once more.

�� There is no longer a Fusion Directorate with appropriate power and responsibility for the whole programme. This has weakened the managerial ability to organise the fusion programme. Recommendations to strengthen the administrative structure have not been acted upon and not even been seriously answered. Indeed, a stronger management structure than before is necessary in view of “Next Step”.

The successful planning and implementation of the programme was due much more to the good will of these officials than to an appropriate hierarchical organisation.

�� The necessary political decisions have been substantially delayed. The Green Paper concluded that the energy problem will lead to difficulties for Europe within 20 to 30 years. In this context, the recommendations of a “Fast Track” approach to fusion are particularly timely, focussing on demonstrating the technical feasibility of fusion power on a 20-30 year timescale. It is therefore very important that the whole fusion programme including “Next Step” becomes an essential and sufficiently financed part of FP6 as proposed by the Commission. The need to save money now is not a good argument against this, as insufficient funds will appreciably increase the final

12

total cost of the programme. The necessary decisions have to be taken by the competent political bodies.

ITER construction will need a strong unified management at a European level. This should be achieved by creating a European Legal Entity under the umbrella of the Commission. In order to support this legal entity, the Commission should have a Fusion Directorate within the Commissions DG Research. The legal entity would also represent Europe in its relation to international bodies, such as the international ITER Legal Entity. Negotiations on this international ITER Legal Entity have been initiated. The panel hopes and recommends this will proceed as fast as possible. Progress is also important for the ERA in the field of fusion. Further indecisiveness could destroy its coherence. It would also make it more and more difficult to recruit new young scientists and technicians for the field of fusion, because they could not see a stable and rewarding professional future.

Since the reorganisation of DG Research, the management of the European Fusion Programme has been carried out by the Principal Advisor to the Director General on Fusion Matters (Dr. U. Finzi) and by the staff in several units of Directorate J, mainly Unit J.5 (headed by Dr. Jean-Pierre Rager), Unit J.6 (headed by Prof. Dr. Hardo Bruhns), and Unit J.7 (headed by Hans Spoor).

The committee structure for the programme is complex and ought to be improved. The present system leads to unnecessary duplication of work both for Commission staff and for Member States and Association representatives in Committees. Moreover, there is some overlapping in the roles played by various committees. A simplification of the committee structure is being considered in the preparations for the next phase of the programme.

4.2.2 Evaluation and Monitoring Methodology, including indicators

The monitoring methodology has been revised by the Commission. The panel feels that the monitoring has been improved by some of the new features and the monitoring efficiency will probably be increased by the fact that the FPMP now consists of representatives (chairpersons) of the Specific Programme Monitoring Panels (SPMPs). Past FPMPs seem to have had little interest in and insufficient understanding of the SPMPs findings and concerns. For instance the 2000 Annual Monitoring Report of the FPMP contains the Executive Summary of the 2000 SPMP report on Fusion, but the panel’s serious concerns have not been mentioned anywhere else in the report, though they have been reported to the FPMP in detail and though it had been asked to take them into account. Another improvement is the self-assessment submitted to the panel by the Commission Services [2.1]. The panel acknowledges the fact that this self-assessment was excellent and very helpful, providing a lot of clear and detailed information. The panel feels that these new features should be maintained for future monitoring exercises.

The Core Indicators relevant to the Fusion Programme provided to the panel by the Fusion Programme Management are contained in annex 6.1. Part of the data has however been produced too late to have any impact on the work of the panel.

4.2.3 Ethical Aspects

The Commission increasingly emphasises the ethical aspects of research which it supports. It demands, for instance, that fundamental ethical principles are respected in all FP6 research activities, including the fusion programme. With respect to the development of fusion power stations, environmental compatibility, operational safety and public acceptance are the main ethical issues. Efforts and studies in these fields have been carried out hitherto and will be continued under FP6 (as mentioned in sections 4.1.3.5 and 4.1.3.6 above).

13

4.3 IMPACT OF PREVIOUS RESEARCH FPS AND SPS

The present world-wide high reputation of the European Fusion Programme is the consequence of a long period of development through all the past FPs including FP5. The European Added Value of the Euratom support for fusion research has been consistently recognised by the External Monitoring panels: the programme maximises efficiency by co-ordinating and integrating the efforts of all the players in Europe, as well as permitting large-scale projects such as JET which would not have been accomplished by any member state acting alone. This achievement is underlined by Europe’s acknowledged leadership in this field of research. The valuable leading position and the reputation of the Community in the field of fusion must not be lost and should be vigorously defended.

4.4 FOLLOW UP OF PREVIOUS MONITORING AND FIVE YEAR ASSESSMENT RECOMMENDATIONS

The 2000 SPMP put forward 11 recommendations. The 2001 panel acknowledges the significant progress achieved with respect to almost all these recommendations, except one, recommendation 3. However, fusion being a long term project, the recommendations remain valid for the future. The tasks have not been finished and could not be finished in 2001. Here we briefly summarise our observations on last year's recommendations:

1. The panel welcomes the progress achieved on ITER in 2001, which is however not at all sufficient. The time schedule is now even narrower than it was a year ago. The essential, overdue, political decisions have as yet not been taken.

2. The investigation of Cadarache as an ITER site is an important step forward in the search for a European site. An official French offer has not yet been obtained, however.

3. It is extremely disappointing to realise that strong unified management is still lacking and that the recommendation on this matter made by previous panels has been completely neglected.

4. The panel is satisfied by the continued use of JET and by the well advanced planning of JET operation for 2002 and beyond.

5. The panel is also satisfied by many really remarkable experimental, theoretical and technical results achieved by the Associations. It welcomes the creation of a Special Working Group, SWG, of the CCE-FU, to examine the future role of the Associations in support of ITER, as this is an extremely important exercise.

6. The materials development activities are proceeding as expected. They will remain very important for a long time and so they are a part of the Commission’s proposal for FP6.

7. The Key Element Phase, KEP, for the International Fusion Materials Irradiation Facility, IFMIF, has not yet been completed. It is in progress, however, and has to be continued under FP6.

8. Activities to enhance public awareness and acceptance of fusion power have been intensified considerably. They are very important and need further intensification.

9. The socio-economic, environmental and safety aspects of fusion power have been studied in detail with interesting and encouraging results. These efforts will be continued and are taken into account in the Commission’s proposal for FP6.

10. There are efforts to bring young scientists into the field of fusion. The situation seems to remain unchanged, however. Probably only essential decisions on the future of fusion, i.e. on the “Next Step”, can change the situation by creating attractive scientific and technical professional careers for young scientists and engineers.

14

11. The co-operation with industry, including small enterprises, has been improved and will further be improved. Spin-offs gain increasing importance.

The panel has also been asked to follow up the 10 recommendations of the 2000 FiveYear Assessment panel (i.e. the Airaghi-Panel, mentioned above [2.4]). They have, as expected, identified the same strengths and weaknesses as observed above. We have therefore restricted ourselves to some comments on recommendations 1 and 7:

1. The European Fusion Programme has helped to place European science, technology and industry at the leading edge of development in this sector and this advantage should be defended and possibly increased.

The present panel entirely agrees with this recommendation. Europe’s leading position can only be defended by determinedly proceeding with ITER in due time. Not to proceed with ITER would risk the fragmentation of the European fusion programme, so that it would no longer be a model ERA.

7. Following a positive decision on the construction of the Next Step, a refocusing of the European Programme will be required. For this purpose a critical assessment of the different European machines and their funding should be undertaken.

This recommendation is similar to recommendation 5 of the 2000 SPMP: “The Associations continue to prepare themselves for the strongest possible support needed for a successful construction and operation of ITER....”. It is, however, stronger in that it recommends a critical assessment of funding, following a positive decision on the Next Step. After the positive decision this will certainly be necessary. The Associations must, however, remain strong enough to support ITER all the time during its construction and operation. The measures then to be taken should also be prepared by the Special Working Group (SWG) of the CCE-FU, which is examining the future role of the Associations in support of ITER.

15

5. CONCLUSIONS AND RECOMMENDATIONS

5.1 GENERAL CONCLUSIONS, MAJOR TRENDS, MAIN STRENGTHS AND WEAKNESSES ENCOUNTERED

Briefly summarising its findings the panel concludes: �� The European Fusion Programme is the world leader in its field and is an outstanding example

of a completely integrated European Research Area.

�� Adopting the Fast Track approach would give a strong impetus to fusion research.

�� The Commission’s fusion staff has managed the whole European Fusion Programme excellently within the given boundary conditions.

�� The programme is, however, suffering from the fact that essential decisions on its future (mainly concerning the “Next Step” and issues related to it) have not been taken in due time.

�� The programme is also suffering because DG Research has been reorganised so that the initially strong management structure is now too weak for a project of this size and importance.

�� The funding foreseen for fusion under FP6 is not sufficient to maintain the present quality and strength of the Fusion Programme.

�� These three weaknesses could endanger the present high standing and the future development of the Fusion Programme.

5.2 RECOMMENDATIONS

5.2.1 Recommendations on the Specific Programme

The panel recommends that:

1. ITER should proceed as soon as possible and all necessary decisions should be made promptly, on the time-scales indicated in annex 6.4. While ITER should preferably be achieved by an international collaboration, Europe should be ready to proceed alone if necessary, in view of the importance of the future energy problem. It has the abilities and resources to build a Next Step device on its own if necessary.

2. The present European mandate of negotiations with its international ITER partners in order to establish an ITER Legal Entity should be enlarged in order to address ITER site, organisational and cost sharing issues, as necessary steps for ITER construction.

3. Europe should take the lead, promoting European sites, supporting the on-going international negotiations, funding its percentage of the financial requirements for ITER construction and operation. This clear lead from Europe could be expected to generate a positive response from both existing and potential partners.

4. The panel supports the Fast Track proposal, in the report of the King Group, which was also positively received by the Council of Ministers. It recommends that it should be studied in detail and should be realised. This could save substantial public funds and a lot of valuable time.

5. The reorganisation of DG Research has weakened the management structure of the Fusion Programme. A strong unified management and organisational structure will be necessary as soon as a decision is made on ITER. At that time, the current structure should be strengthened by creating a Fusion Directorate within the Commission. The panel also recommends an appropriate

16

European Legal Entity be established under the umbrella of the Commission to represent Europe in ITER. EFDA could, for instance, be transformed into such a legal entity.

6. The use of the JET facilities should be continued as far as possible under FP 6 in order to obtain further results relevant for ITER and reduce the time gap between the end of JET operation and the start of ITER operation. This is important to retain the present coherence of the programme and of the ERA of fusion.

7. The role of the Associations is essential for all aspects of the programme. Associations should continue working in plasma physics and alternative designs in order to support the European scientific leadership.

8. The materials development activities should also be further pursued intensely under FP6, since they are necessary for the long-term success of fusion reactors. The design of the International Fusion Materials Irradiation Facility (IFMIF) should be completed under FP6, since it is urgently needed for testing fusion materials for DEMO.

9. For fusion to be adopted successfully, society needs to be assured of its safety, feasibility and economic viability. It is therefore important that socio-economic, environmental and safety studies be further strengthened under FP6. The results of these activities should be used to enhance public awareness and acceptance of fusion power and its future importance.

10.In view of the age profile of the professionals currently active in the programme, efforts should be made to bring in new young scientists and technicians, and to develop their expertise. This also requires timely decisions on the future programme towards the “Next Step”, to create enthusiasm and to open attractive professional careers.

11.The co-operation with industry, which has developed considerably in recent years, should be further intensified. The involvement of SMEs and the exploitation of spin-offs should be supported.

5.2.2 Recommendation on the Monitoring Methodology

The panel recommends the changes made in the monitoring methodology for the year 2001 be maintained in future years, i.e. that the FPMP consist of representatives of the SPMP and the self-assessments be submitted to the panels. The introduction of interviews with member state representatives in the programme has contributed to an improvement in the quality of the monitoring.

17

6. ANNEXES

6.1 CORE INDICATORS AND BUDGET FIGURES

“Core” Indicators relevant to the Fusion Programme

Important features distinguish the Fusion Programme from the other specific programmes. With regards to its implementation, the Fusion Programme does not proceed by means of “calls for proposals”; therefore many of the standardised “core” indicators do not apply.

1. SELECTION PROCEDURES: not applicable 2. MANAGEMENT OF PROGRAMME

2.i. Analysis of time taken from closing date of calls for proposals up to first contracts: not applicable

2.ii. Comparison between total funds requested and awarded : not applicable 2.iii. Running and completed contracts

Framework programmes Number of shared cost

actions

Number of training

fellowships

Number of accompanying

measures

Financial contribution (Mio€)*

FP5 Nr ongoing contracts at 5/10/2001 321 2 0 243,449,160 Nr contracts completed during 2001 166 0 0 96,859,984

FP4 Nr ongoing contracts at 5/10/2001 0 0 0 Nr contracts completed during 2001 3 2 0 1,475,100

FP3 Nr ongoing contracts at 5/10/2001 0 0 0 Nr contracts completed during 2001 0 0 0

*Including EFDA and MOB payments, financial contribution for Jet Operation Contract (JOC) MOB : Agreement for personnel mobility in the field of Thermonuclear Energy EFDA : European Fusion Development Agreement

19

3. GENERAL CHARACTERISTICS OF PROJECTS

3.i. to 3.iii. not applicable 3.iv. Participation from "Objective 1 " regions to 5 October 2001

Objective 1 regions

Total number of participations 3

Total EC-contribution ( € ) 67,650

4. QUANTITATIVE OUTPUT DATA

4.i. Cumulative quantitative data on results from FP5:

N° of scientific and technological publications c. 2000 N° of Marie Curie Individual Fellowships a) being awarded b) currently operating

0 2

N° of individual Mobility Actions (missions / secondments) 441 contracts = 662 PPM

5. DISSEMINATION / UTILISATION OF RESULTS

5.i. Qualitative information on dissemination/utilization plans of projects in 2000 at project level: The most important conferences at which results from the Euratom fusion programme have been presented are: �� 18th IAEA Fusion Energy Conference, Sorrento, Italy �� 27th European Physical Society Conference on Controlled Fusion and Plasma Physics, Budapest,

Hungary �� 13th Topical Conference on High-Temperature Plasma Diagnostics, Tucson, USA �� 21st Symposium on Fusion Technology (SOFT), Madrid, Spain �� 42nd APS Division of Plasma Physics Annual Meeting, Quebec, Canada �� 8th European Fusion Physics Workshop, Leysin, Switzerland

Proceedings of these conferences are or will be published.

5.ii. Dissemination activities at programme level under FP5:

�� Most of the Association laboratories organise “Open-Days” for the general public on a regular basis. �� During 2000, the itinerant fusion exhibition has been shown in Turin (Italy), Greifswald (Germany),

Lisbon (Portugal), and Seoul (South Korea), with a smaller version at the SOFT Conference (Madrid) and the IAEA Conference (Sorrento). A multi-lingual CD-ROM which accompanies the exhibition has been widely distributed (including being given away as a “cover-mounted” disc on several popular scientific/technical magazines).

�� During the Climate Change Conference at The Hague in November 2000, a stand with information about fusion was provided by EFDA, and manned by staff from EFDA and the Associations.

�� A four page brochure about fusion, aimed at the general public, was produced by DG RTD. EFDA also produces various newsletters and brochures about fusion, as do the Association laboratories.

20

II. Data specific to the Fusion Programme 1. EUROPEAN EXPENDITURE ON FUSION RESEARCH IN 2000

The breakdown of expenditure for 2000 is under different headings compared to 1999 and previous years because of the changes in organisation of the fusion programme, notably the end of the JET Joint Undertaking and the starting of EFDA activities. The estimates for 2000 are:

European Expenditure on Fusion Research in 2000 Expenditure

Mio EUR Community share.

Mio EUR Community share.

% (1) Associations (2) EFDA (3) & JET J.U. JOC Other Expenditure

360.1

24.5

51.6

32.0

98.9

10.2

38.7

32.0

27

42

75

100

Total

468.2

179.8

38

Notes: (1) (2)

(3)

The Community share includes the participation of Switzerland and the Newly Associated States in the financing of the Community Fusion Programme. Against the heading “Associations” is included expenditure of about 0.191 Mio EUR (Commission share of 0.052 Mio EUR), which took place under cost-sharing contracts in Member States that had no Association in 2000. Expenditure in the frame of the EFDA Agreement, amounting to about 67.661 Mio EUR in 2000, is included partly under the heading “Associations” and partly under “Other Expenditure”.

2. EUROPEAN EXPENDITURE ON FUSION RESEARCH IN 2001

Expenditure MioECU

Community Share MioECU

Community Share %

Associations 384,3 104,3 27 EFDA, inc hosting of JET and ITER

22,1 11,7 53

Joint Operating Contract for JET

57,0 42,8 75

Other Expenditure 42,3 42,3 100 Total 505,7 201,1 40

21

3. FU

SION

PRO

GRAM

ME –

ASSO

CIAT

IONS

’ EXP

ENDI

TURE

IN 20

00

in

Euro

E

xpen

ditu

re 2

000

Ass

ocia

tion

EU

R/

Gen

eral

Sup

port

actio

ns 2

5%

Tech

nolo

gy ta

sks

25%

La

rge

devi

ces

45%

EF

DA

- ho

stin

g, o

rder

s &

secm

nt's,

JET

J.U.

Tot

al E

stim

ated

E

xpen

ditu

re

Phys

ics p

riorit

y ac

tions

at +

20%

Te

chno

logy

prio

rity

actio

ns a

t +20

%

IPP

(D)

74,8

88,9

79

0 24

,329

,218

6,

700,

216

105,

918,

413

0 0

EN

EA

(I)

53,7

67,5

58

11,9

14,3

19

79,0

06

2,13

1,39

2 67

,892

,275

68

3,03

1 1,

076,

894

CE

A (F

) 44

,871

,162

11

,186

,911

2,

763,

188

1,81

0,55

4 60

,631

,815

0

552,

299

FZK

(D)

9,92

7,97

9 15

,055

,636

2,

443,

307

1,39

3,79

1 28

,820

,713

0

1,01

8,30

5 FZ

J (D

) 19

,278

,476

34

8,34

8 0

540,

162

20,1

66,9

86

2,60

2,26

0 60

9,09

8 U

KA

EA

(UK

) 19

,989

,417

1,

370,

335

0 53

,812

,764

75

,172

,515

0

0 Sw

iss C

onfe

d 12

,614

,966

1,

714,

667

333,

821

1,64

9,30

5 16

,312

,759

0

150,

558

FOM

(NL

) 8,

808,

752

2,66

7,28

9 0

637,

024

12,1

13,0

65

277,

070

1,79

4,67

2 C

IEM

AT

(E)

7,31

9,72

8 88

4,80

3 1,

855,

740

126,

060

10,1

86,3

31

0 18

4,70

0 V

R

6,29

2,25

4 1,

226,

518

0 80

1,22

1 8,

319,

993

0 0

Bel

gium

Sta

te

4,67

9,00

6 2,

221,

433

0 23

4,98

8 7,

135,

427

0 78

9,37

5 Ö

AW

(A)

2,66

4,32

8 1,

974,

397

0 15

1,71

5 4,

790,

441

0 67

8,39

6 IS

T (P

) 3,

904,

054

486,

315

0 33

5,63

3 4,

726,

002

0 0

TE

KE

S (F

IN)

1,14

9,79

5 1,

642,

235

0 31

2,84

2 3,

104,

872

0 38

8,76

7 R

ISØ

(DK

) 1,

598,

219

540,

642

0 0

2,13

8,86

2 0

148,

275

DC

U (I

RL

) 1,

181,

484

0 0

0 1,

181,

484

0 0

Hel

leni

c R

epub

lic

600,

110

271,

803

0 0

871,

913

0 90

,728

IPP.

CR

(CZ)

45

9,75

6 15

,029

0

0 47

4,78

5 0

0 N

AST

I (R

) 88

,639

14

0,38

4 0

0 22

9,02

3 0

10,8

82

HA

S (H

) 21

5,75

6 77

,178

0

0 29

2,93

4 0

28,4

61

Lux

embo

urg

0 29

,162

0

0 29

,162

0

25,6

62

27

4,30

0,41

7 53

,767

,404

31

,804

,281

70

,637

,668

43

0,50

9,77

0 3,

562,

361

7,54

7,07

4

Not

es :

(1) T

he a

bove

tabl

e is

con

stru

cted

on

the

basi

s of p

aym

ents

reco

rded

in th

e As

soci

atio

ns' e

stim

ates

for 1

999,

con

vert

ed in

to E

uro

at th

e av

erag

e

exch

ange

rate

of t

he y

ear.

(2

) The

Com

mun

ity sh

are

in th

e to

tal e

xpen

ditu

re is

abo

ut 1

01.2

13 M

ioEu

ro

(3

) In

addi

tion,

exp

endi

ture

of a

bout

0.0

59 M

io E

uro

(Com

mun

ity p

artic

ipat

ion

abou

t 0.0

15 M

ioEu

ro) t

ook

plac

e un

der c

ost s

hari

ng c

ontr

acts

in

M

embe

r Sta

tes t

hat h

ad n

o co

ntra

ct o

f Ass

ocia

tion.

22

FUSI

ON P

ROGR

AMME

– AS

SOCI

ATIO

NS’ E

XPEN

DITU

RE IN

2001

– BA

SED

ON E

STIM

ATES

all a

mou

nts

in E

uro

Est

imat

es 2

000

Ass

ocia

tion

EU

R/

Gen

eral

Sup

port

actio

ns 2

5%

Tech

nolo

gy ta

sks

25%

La

rge

devi

ces

45%

EF

DA

, ITE

R

and

JET

Tot

al e

stim

ated

ex

pend

iture

Ph

ysic

s prio

rity

actio

ns a

t +20

%

Tech

nolo

gy p

riorit

y ac

tions

at +

20%

IP

P 87

,511

,000

53

,000

23

,993

,000

3,

965,

000

115,

522,

000

0 0

CE

A

45,3

93,9

82

11,7

53,6

67

1,74

3,71

2 6,

799,

074

65,6

90,4

34

0 1,

311,

062

EN

EA

55

,679

,000

12

,395

,000

11

5,00

0 3,

120,

000

71,3

09,0

00

321,

000

775,

000

FZJ

18,4

03,0

00

500,

000

0 52

2,00

0 19

,425

,000

37

,185

0

FZK

10

,141

,875

16

,860

,000

3,

492,

000

1,02

5,00

0 31

,518

,875

0

510,

000

Swis

s Con

fed

13,8

63,4

36

2,02

1,13

1 0

1,02

6,77

4 16

,911

,341

0

370,

486

UK

AE

A

21,4

12,0

20

1,48

3,29

7 0

59,8

48,6

83

82,7

43,9

99

0 11

6,08

4 FO

M

7,72

0,00

0 3,

370,

000

0 29

2,00

0 11

,382

,000

71

9,00

0 2,

150,

000

CIE

MA

T

9,75

2,84

2 1,

395,

105

1,79

1,08

8 24

5,31

3 13

,184

,348

15

,000

0

NFR

5,

959,

205

1,86

0,22

4 0

535,

355

8,35

4,78

4 0

767,

883

Bel

gium

Sta

te

5,17

5,99

1 2,

265,

000

0 55

2,90

1 7,

993,

892

0 20

0,00

0 Ö

AW

2,

538,

187

1,74

0,70

9 0

175,

832

4,45

4,72

8 0

IS

T

4,23

9,88

6 42

5,29

1 0

437,

657

5,10

2,83

3 0

0 R

ISØ

1,

622,

098

457,

259

0 0

2,07

9,35

6 0

61,6

06

TE

KE

S 1,

450,

191

1,22

9,72

1 0

568,

387

3,24

8,29

9 0

280,

514

Gre

ece

767,

603

314,

951

0 0

1,08

2,55

5 0

328,

903

IPP.

CR

66

9,80

7 31

5,29

9 0

0 98

5,10

6 0

0 N

AST

I 10

6,18

3 24

4,72

2 0

0 35

0,90

5 0

23,6

06

HA

S 34

1,20

9 18

0,45

0 0

18,3

26

539,

985

0 90

,900

D

CU

1,

285,

225

0 0

0 1,

285,

225

0 0

Uni

v. o

f Lat

via

0 0

0 0

0 0

0 L

uxem

bour

g 0

30,0

00

0 0

30,0

00

29

4,03

2,74

0 58

,894

,824

31

,134

,799

79

,132

,301

46

3,19

4,66

5 1,

092,

185

6,98

6,04

4

Not

es :

(1) T

he a

bove

tabl

e is

con

stru

cted

on

the

basi

s of p

aym

ents

reco

rded

in th

e As

soci

atio

ns' a

ccou

nts f

or 2

001,

con

vert

ed in

to E

uro'

s at t

he a

vera

ge

exch

ange

rate

of t

he y

ear.

(2) T

he C

omm

unity

shar

e in

the

tota

l exp

endi

ture

is a

bout

158

.7 M

ioEu

ro

23

6.2 ABBREVIATIONS ASDEX Axis-Symmetric Divertor EXperiment CCE-FU Consultative Committee Euratom-Fusion CEA Commissariat à l’Energie Atomique (France) CFI Committee on Fusion-Industry CIEMAT Centro de Investigaciones Energéticas, Medioambientales y Tecnológicas (Spain) DEMO DEMOnstration reactor EFDA European Fusion Development Agreement ERA European Research Area EURATOM EURopean ATOMic energy community FP Framework Programme FPMP Framework Programme Monitoring Panel FZK Forschung Zentrum Karlsruhe (Germany) IEA International Energy Agency IFE Inertial Fusion Energy IFMIF International Fusion Material Irradiation Facility IPP Institut für Plasmaphysik (Germany) ITER International Thermonuclear Experimental Reactor JET Joint European Torus JET-EP JET Enhanced Performance KEP Key Element Phase PROTO PROTOtype reactor RTD Research and Technological Development SEAFP Safety & Environmental Aspects of Fusion Power SEAL Safety & Environmental Assessment of fusion power Long term: follows

on from SEAFP and has a broader scope SERF Socio-Economic Research on Fusion SPMP Specific Programme Monitoring Panel SWG Special Working Group TAC Technical Advisory Committee

24

6.3 DOCUMENTS PROVIDED TO THE EXPERTS BY THE PROGRAMME MANAGEMENT

FUSION PROGRAMME MONITORING FOR 2001

1. Legal documents

1.1. Council Decision of 22 December 1998 concerning the Fifth Framework Programme of the European Atomic Energy Community (Euratom) for research and training activities (1998 to 2002).

1.2. Council Decision of 22 December 1998 concerning the rules for the participation of undertakings, research centres and universities in the implementation of the Fifth Framework Programme of the European Atomic Energy Community (Euratom) (1998 to 2002).

1.3. Council Decision of 25 January 1999 adopting a research and training programme (Euratom) in the field of nuclear energy (1998 to 2002).

1.4. Commission proposal for next Framework Programme. 1.5. Commission proposal for specific programme Euratom in the next Framework

Programme. 1.6. Opinion of the Committee on Industry, Trade, Research and Energy (ITRE) of the

European Parliament on the Commission’s proposal for the next Framework Programme (EURATOM).

1.7. DRAFT Council Decision concerning FP6 Euratom (12 December 2001) 2. Background documents

2.1. Self-assessment of the Key Action Fusion by the Commission Services 2.2. Broad Guidelines for the 2001 External Monitoring of the Framework

Programmes and Specific Programmes, November 2001. 2.3. 2000 External Monitoring Report on the Specific Programme for Research and

Technological Development. 2.4. Five-Year Assessment Report related to the Specific Programme: Nuclear Energy

covering the period 1995 – 1999, June 2000. 2.4a Comments by the Programme Management on the 5-year Assessment. 2.5. 2000 Annual Monitoring Report on the RTD activities conducted under the EC

and Euratom Framework Programmes. 2.6. Self-assessment of the Framework Programme by the Commission Services. 2.7. Note on “pre-draft issues” paper from the Specific Programmes (28 November

2001)

3. Specific documents – core data

3.1. Minutes of CCE-FU meetings of February, April and July 2001 (CCE-FU 9/SM – 11/SM) and Summary of decisions and recommendations of CCE-FU meeting of October 2001 (CCE-FU 12/SDR).

3.2. Fusion R&D in the European Fusion Associations (Overview chapter from document in preparation).

25

3.3. View of the Scientific and Technical Committee Euratom (STC) on the Commission’s Green Paper, “Towards a European strategy for the security of energy supply”.

3.4. ITER-FEAT – Final Design Report (Executive Summary), plus EU Domestic Assessment and Opinion of the CCE-FU.

3.4a EU Domestic Assessment of the ITER-FEAT Final Design Report. 3.4b Opinion of the CCE-FU on the ITER-FEAT Final Design Report. 3.4c ITER Council Document: “Final Report of the ITER EDA” (August 2001). 3.5. Opinion of the External Advisory Group for the Key Action Fusion 1998-2000. 3.6. Working Paper of the Energy Working Group (E-WOG) on “Sustainable and

affordable energy for the future - priorities for EU energy R&D”, EUR 19790 (January 2001).

3.7. Summary Record of the 7th Meeting of the IFE Co-ordinating Committee – Technical Group, IFECC-TG, (November 2001)

3.8. ITER Canada – Official offer to host ITER (June 2001) 3.9. ITER Site study for Cadarache (Exec Summary) 3.10. EFDA European Fusion Development Agreement – Workplan 1999-2002

(Revision April 2001). 3.11. Report on the CFI Workshop on Spin-off and Transfer of Technology (May 2001) 3.11a Selected Annexes (slides of presentations) from the Spin-off Workshop. 3.12. Socio-Economic Research on Fusion, Summary of EU research 1997-2000 (July

2001) 3.13. Safety and Environmental Impact of Fusion (April 2001) 3.14. Copy of transparencies presented at the meeting of the Panel on 28 November

2001 3.15. Copies of various public information brochures and publications produced during

2001 3.16. List of bilateral and multilateral agreements concerning fusion 3.17. cancelled 3.18. Core indicators (with budgetary information) 3.19. “Gender in Research”, Gender Impact Assessment of the specific programmes of

the Fifth Framework Programme (Energy sub-programme), EUR 20018. 3.20. Workprogramme for the new Contract of Association between Euratom and the

University of Latvia. 3.21. Towards a European strategy for the security of energy supply (Commission

Green Paper, November 2000). 3.21a Energy Supply Green Paper - Annexes. 3.22. Commission paper on materials R&D in Europe. 3.23. Background paper on fusion materials by H Bolt (IPP) #1. 3.24. Background paper on fusion materials by H Bolt (IPP) #2. 3.25. Conclusions of the Fast Track Experts Meeting (27 November 2001) 3.26. “How to maintain nuclear competence in Europe” by the CCE-Fission (EUR

19787)

26

6.4 TENTATIVE TIME SCHEDULE TOWARDS JOINT IMPLEMENTATION OF ITER

OutlineDesignReport

* Engineering DesignActivities

† Construction, Operation, Exploitationand Decommissioning Activities

Co-ordinated TechnicalActivities

FinalDesignReport

SiteOffers

Ratification

Signing ofCOEDA Agreement

EDA*Establishment of ITER Legal Entity

COEDA †

Negotiations

FP5 FP61999 20032000 2001 2002 20052004

ITER Legal Frame

FinalReport

27

PART B:

Responses of the Programme Management to the external Monitoring Report

28

Res

pons

es o

f the

Pro

gram

me

Man

agem

ent t

o th

e re

com

men

datio

ns o

f the

200

1 Fu

sion

Mon

itori

ng P

anel

Th

ese

resp

onse

s hav

e be

en p

repa

red

by o

ffic

ials

in th

e fu

sion

pro

gram

me

and

repr

esen

t the

ir pe

rson

al v

iew

s on

the

reco

mm

enda

tions

of t

he a

nnua

l m

onito

ring

repo

rt. T

hese

vie

ws h

ave

not b

een

adop

ted

or in

any

way

app

rove

d by

the

Com

mis

sion

and

shou

ld n

ot b

e re

lied

upon

as a

stat

emen

t of t

he

view

s of t

he C

omm

issi

on o

r DG

Res

earc

h.

Rec

omm

enda

tion

Com

mis

sion

Ser

vice

s’ R

espo

nse

Tim

e po

int /

indi

cato

r fo

r im

plem

enta

tion

1 IT

ER

shou

ld p

roce

ed a

s soo

n as

pos

sibl

e an

d al

l nec

essa

ry d

ecis

ions

shou

ld b

e m

ade

prom

ptly

, on

the

time-

scal

es in

dica

ted

in a

nnex

6.4

of t

he

mon

itorin

g re

port.

Whi

le IT

ER sh

ould

pre

fera

bly

be a

chie

ved

by a

n in

tern

atio

nal c

olla

bora

tion,

Eu

rope

shou

ld b

e re

ady

to p

roce

ed a

lone

if

nece

ssar

y, in

vie

w o

f the

impo

rtanc

e of

the

futu

re

ener

gy p

robl

em. I

t has

the

abili

ties a

nd re

sour

ces

to b

uild

a N

ext S

tep

devi

ce o

n its

ow

n if

nece

ssar

y.

The

Com

mis

sion

’s p

ropo

sal f

or th

e Sp

ecifi

c Pr

ogra

mm

e (E

urat

om) f

or F

P6 fo

rese

es th

at a

dec

isio

n on

the

join

t im

plem

enta

tion

of IT

ER c

ould

be

soug

ht in

the

perio

d 20

03-2

004,

so

that

con

stru

ctio

n co

uld

effe

ctiv

ely

star

t dur

ing

the

perio

d 20

05-

2006

.

A d

ecis

ion

to p

roce

ed

with

ITER

is

antic

ipat

ed a

nd th

e co

nstru

ctio

n co

uld

star

t du

ring

the

perio

d 20

05-

2006

.

2 Th

e pr

esen

t Eur

opea

n m

anda

te o

f neg

otia

tions

w

ith it

s int

erna

tiona

l ITE

R p

artn

ers i

n or

der t

o es

tabl

ish

an IT

ER L

egal

Ent

ity sh

ould

be

enla

rged

in o

rder

to a

ddre

ss IT

ER si

te,

orga

nisa

tiona

l and

cos

t sha

ring

issu

es, a

s ne

cess

ary

step

s for

ITER

con

stru

ctio

n.

The

Com

mis

sion

form

ally

requ

este

d an

ext

ensi

on o

f its

ne

gotia

ting

man

date

at t

he m

eetin

g of

the

Cou

ncil

of M

inis

ters

on

11 M

arch

200

2. T

his e

xten

sion

was

gra

nted

by

the

Cou

ncil

on 2

7 M

ay 2

002,

and

ena

bles

the

Com

mis

sion

to n

egot

iate

with

the

othe

r IT

ER p

artn

ers o

n si

ting

and

cost

issu

es.

The

exte

nded

man

date

w

as g

rant

ed in

May

20

02.

29

R

ecom

men

datio

n C

omm

issi

on S

ervi

ces’

Res

pons

e T

ime

poin

t / in

dica

tor

for

impl

emen

tatio

n

3 E

urop

e sh

ould

take

the

lead

, pro

mot

ing

Euro

pean

site

s, su

ppor

ting

the

on-g

oing

in

tern

atio

nal n

egot

iatio

ns, f

undi

ng it

s per

cent

age

of th

e fin

anci

al re

quire

men

ts fo

r ITE

R

cons

truct

ion

and

oper

atio

n. T

his c

lear

lead

from

Eu

rope

cou

ld b

e ex

pect

ed to

gen

erat

e a

posi

tive

resp

onse

from

bot

h ex

istin

g an

d po

tent

ial

partn

ers.

The

Euro

pean

neg

otia

tors

hav

e pl

ayed

a le

adin

g ro

le in

the

nego

tiatio

ns w

hich

hav

e si

gnifi

cant

ly p

rogr

esse

d to

war

ds a

n ag

reem

ent o

n th

e co

nditi

ons f

or th

e jo

int i

mpl

emen

tatio

n of

ITER

. In

Janu

ary

2002

, the

Fre

nch

Min

iste

r for

Res

earc

h as

ked

the

EU

that

the

Fren

ch p

ropo

sal t

o re

alis

e IT

ER in

Cad

arac

he b

e ta

ken

into

acc

ount

, and

requ

este

d th

at th

e co

nditi

ons u

nder

whi

ch a

Eu

rope

an si

te c

ould

be

prop

osed

for I

TER

con

stru

ctio

n be

def

ined

. Te

chni

cal w

ork

on C

adar

ache

as a

pos

sibl

e si

te h

as p

rogr

esse

d co

nsid

erab

ly a

nd h

as le

d to

the

laun

ch o

f the

lice

nsin

g pr

oced

ure

with

the

Fren

ch a

utho

ritie

s. Th

e ca

se fo

r a E

urop

ean

site

for I

TER

ha

s bee

n fu

rther

stre

ngth

ened

by

the

notif

icat

ion

of a

dec

isio

n by

th

e Sp

anis

h G

over

nmen

t to

offe

r a c

andi

datu

re fo

r the

Eur

opea

n si

ting

of IT

ER a

t Van

delló

s, ne

ar B

arce

lona

. Th

e le

vel a

nd n

atur

e of

EU

par

ticip

atio

n in

ITER

fund

ing

will

de

pend

on

the

outc

ome

of th

e ne

gotia

tions

with

the

inte

rnat

iona

l pa

rtner

s, an

d on

the

loca

tion

of th

e IT

ER si

te. I

f ITE

R w

as lo

cate

d in

Eur

ope,

the

EU p

artic

ipat

ion

wou

ld a

lso

incl

ude

cont

ribut

ion

to

the

cost

s to

be b

orne

by

Euro

pe a

s a H

ost P

arty

. Th

e ro

le o

f the

Eur

opea

n de

lega

tion

in th

e ne

gotia

tion

proc

ess h

as

been

stre

ngth

ened

by

the

exte

nsio

n of

the

nego

tiatio

n m

anda

te.

The

Com

mis

sion

is su

ppor

ting

the

tech

nica

l stu

dies

for p

ossi

ble

Span

ish

and

Fren

ch si

tes.

The

ITER

neg

otia

tions

ar

e ta

king

pla

ce

regu

larly

and

as

plan

ned.

Th

e C

omm

issi

on

actio

ns h

ave

had

a st

rong

impa

ct in

ad

vanc

ing

prog

ress

in

thes

e ne

gotia

tions

.

4 Th

e pa

nel s

uppo

rts th

e Fa

st T

rack

pro

posa

l, in

th

e re

port

of th

e K

ing

Gro

up, w

hich

was

als

o po

sitiv

ely

rece

ived

by

the

Cou

ncil

of M

inis

ters

. It

reco

mm

ends

that

it sh

ould

be

stud

ied

in d

etai

l an

d sh

ould

be

real

ised

. Thi

s cou

ld sa

ve

subs

tant

ial p

ublic

fund

s and

a lo

t of v

alua

ble

time.

The

supp

ort f

or a

fast

trac

k to

fusi

on p

ower

pro

duct

ion

is

wel

com

ed b

y th

e C

omm

issi

on S

ervi

ces.

In p

artic

ular

, the

C

omm

issi

on is

bei

ng w

orki

ng to

impl

emen

t the

firs

t of t

he

impo

rtant

reco

mm

enda

tion

of th

e K

ing

Gro

up e

mph

asis

ing

the

prom

pt re

alis

atio

n of

ITER

. The

pos

sibi

lity

of im

plem

entin

g so

me

or a

ll of

the

othe

r rec

omm

enda

tions

in th

e re

cent

(D

ecem

ber

2001

) rep

ort o

f the

Fus

ion

Fast

Tra

ck E

xper

ts G

roup

will

dep

end

on d

ecis

ions

to b

e m

ade

abou

t ITE

R, a

nd o

n av

aila

bilit

y of

fund

s.

The

activ

ities

pre

sent

ly b

eing

car

ried

out o

n IT

ER a

nd th

e pl

anne

d ac

tiviti

es o

n m

ater

ials

, inc

ludi

ng IF

MIF

, are

con

sist

ent w

ith th

e

Not

app

licab

le a

t sho

rt te

rm.

30

R

ecom

men

datio

n C

omm

issi

on S

ervi

ces’

Res

pons

e T

ime

poin

t / in

dica

tor

for

impl

emen

tatio

n

fast

trac

k ap

proa

ch.

5 Th

e re

orga

nisa

tion

of D

G R

esea

rch

has

wea

kene

d th

e m

anag

emen

t stru

ctur

e of

the

Fusi

on P

rogr

amm

e. A

stro

ng u

nifie

d m

anag

emen

t and

org

anis

atio

nal s

truc

ture

will

be

nec

essa

ry a

s soo

n as

a d

ecis

ion

is m

ade

on

ITER

. At t

hat t

ime,

the

curr

ent s

truct

ure

shou

ld

be st

reng

then

ed b

y cr

eatin

g a

Fusi

on D

irect

orat

e w

ithin

the

Com

mis

sion

. The

pan

el a

lso

reco

mm

ends

an

appr

opria

te E

urop

ean

Lega

l En

tity

be e

stab

lishe

d un

der t

he u

mbr

ella

of t

he

Com

mis

sion

to re

pres

ent E

urop

e in

ITER

. EFD

A

coul

d, fo

r ins

tanc

e, b

e tra

nsfo

rmed

into

such

a

lega

l ent

ity.

The

nego

tiatio

ns c

urre

ntly

taki

ng p

lace

bet

wee

n th

e IT

ER p

artn

ers

conc

ern

the

jurid

ical

and

inst

itutio

nal c

ondi

tions

of t

he

esta

blis

hmen

t of a

n IT

ER L

egal

Ent

ity a

nd n

egot

iatio

ns fo

r its

jo

int i

mpl

emen

tatio

n. T

he C

omm

issi

on w

ill d

eter

min

e th

e m

ost

appr

opria

te fo

rm fo

r a E

urop

ean

Lega

l Ent

ity w

hich

will

hav

e re

spon

sibi

lity

for t

he E

urop

ean

cont

ribut

ion.

Suc

h an

ent

ity w

ill

need

a st

rong

uni

fied

man

agem

ent a

nd o

rgan

isat

iona

l stru

ctur

e.

The

man

agem

ent s

truct

ure

with

in th

e C

omm

issi

on w

ill b

e co

nsid

ered

in th

e co

ntex

t of t

he o

vera

ll m

anag

emen

t of E

RA

ac

tiviti

es a

nd th

e sp

ecifi

c IT

ER n

eeds

. The

pro

spec

t of

impl

emen

ting

a fa

st tr

ack

appr

oach

will

be

take

n in

to a

ccou

nt,

subj

ect t

o th

e bu

dget

in fu

ture

Fra

mew

ork

Prog

ram

mes

.

The

Com

mis

sion

will

en

sure

a u

nifie

d an

d st

rong

man

agem

ent o

f th

e fu

sion

pro

gram

me

at a

ll tim

es.

6 Th

e us

e of

the

JET

faci

litie

s sho

uld

be

cont

inue

d as

far a

s pos

sibl

e un

der F

P6 in

ord

er to

ob

tain

furth

er re

sults

rele

vant

for I

TER

and

re

duce

the

time

gap

betw

een

the

end

of JE

T op

erat

ion

and

the

star

t of I

TER

ope

ratio

n. T

his i

s im

porta

nt to

reta

in th

e pr

esen

t coh

eren

ce o

f the

pr

ogra

mm

e an

d of

the

ERA

of f

usio

n.

The

Com

mis

sion

reco

gnis

es th

e pi

onee

ring

role

of J

ET a

s an

exam

ple

of a

maj

or jo

int p

roje

ct, a

nd th

e m

odel

it p

rovi

des o

f how

a

devi

ce li

ke IT

ER c

ould

be

oper

ated

. The

Com

mis

sion

pro

posa

l fo

r FP6

incl

udes

the

cont

inui

ng e

xplo

itatio

n of

the

JET

faci

litie

s in

the

fram

ewor

k of

the

Euro

pean

Fus

ion

Dev

elop

men

t Agr

eem

ent

(EFD

A),

in v

iew

of c

ompl

etin

g th

e ex

ploi

tatio

n of

the

enha

ncem

ents

cur

rent

ly u

nder

way

. The

use

of t

he JE

T fa

cilit

ies

will

hav

e to

be

susp

ende

d at

an

appr

opria

te ti

me

to e

nabl

e th

e co

rres

pond

ing

reso

urce

s to

be re

dire

cted

to th

e N

ext S

tep

/ ITE

R.

The

pres

ent p

lann

ing

for F

P6 fo

rese

es e

xplo

itatio

n of

the

JET

faci

litie

s as l

ong

as is

com

patib

le w

ith th

e re

sour

ces r

equi

red

for

ITER

.

Dec

isio

n on

pos

sibl

e fu

rther

ope

ratio

n to

be

take

n in

200

4.

31

R

ecom

men

datio

n C

omm

issi

on S

ervi

ces’

Res

pons

e T

ime

poin

t / in

dica

tor

for

impl

emen

tatio

n

7 Th

e ro

le o

f the

Ass

ocia

tions

is e

ssen

tial f

or a

ll as

pect

s of t

he p

rogr

amm

e. A

ssoc

iatio

ns sh

ould

co

ntin

ue w

orki

ng in

pla

sma

phys

ics a

nd

alte

rnat

ive

desi

gns i

n or

der t

o su

ppor

t the

Eu

rope

an sc

ient

ific

lead

ersh

ip.

The

esse

ntia

l rol

e of

the

Ass

ocia

tions

is re

cogn

ised

in th

e pr

opos

als f

or F

P6, w

hich

cal

l upo

n th

em to

con

tinue

thei

r wor

k in

fu

sion

phy

sics

and

pla

sma

engi

neer

ing,

fusi

on te

chno

logy

, and

in

vest

igat

ion

of so

cio-

econ

omic

asp

ects

of f

usio

n.

The

Com

mis

sion

’s p

ropo

sal f

or F

P6 st

ates

that

the

Ass

ocia

tions

w

ill e

xecu

te th

e ac

com

pany

ing

prog

ram

me

esse

ntia

l to

ITER

.

Not

app

licab

le

8 Th

e m

ater

ials

dev

elop

men

t act

iviti

es sh

ould

al

so b

e fu

rther

pur

sued

inte

nsel

y un

der F

P6,

sinc

e th

ey a

re n

eces

sary

for t

he lo

ng-te

rm

succ

ess o

f fus

ion

reac

tors

. The

des

ign

of th

e In

tern

atio

nal F

usio

n M

ater

ials

Irra

diat

ion

Faci

lity

(IFM

IF) s

houl

d be

com

plet

ed u

nder

FP6

, sin

ce it

is

urg

ently

nee

ded

for t

estin

g fu

sion

mat

eria

ls fo

r D

EMO

.

A p

hase

of E

ngin

eerin

g V

alid

atio

n an

d En

gine

erin

g D

esig

n A

ctiv

ities

(EV

EDA

) for

IFM

IF d

urin

g FP

6 is

und

er d

iscu

ssio

n w

ith o

ther

Par

ties p

artic

ipat

ing

to th

e IE

A Im

plem

entin

g A

gree

men

t on

Fusi

on M

ater

ials

. The

EU

con

tribu

tion

wou

ld b

e im

plem

ente

d in

Ass

ocia

tions

and

indu

stry

und

er E

urop

ean

Fusi

on

Dev

elop

men

t Agr

eem

ent (

EFD

A).

This

nex

t pha

se w

ould

focu

s on

the

deve

lopm

ent o

f a re

fere

nce

desi

gn a

nd o

n fa

bric

atio

n m

etho

ds;

fabr

icat

ion

and

test

of p

roto

type

s; c

ost e

stim

ates

with

the

invo

lvem

ent o

f ind

ustry

; and

the

prep

arat

ion

of th

e lic

ensi

ng

proc

ess f

or th

e co

nstru

ctio

n.

Afte

r a tr

ansi

tion

perio

d fo

llow

ing

the

Key

Ele

men

t Pha

se fo

r IF

MIF

, the

EV

EDA

pha

se is

pla

nned

to st

art i

n 20

04.

The

eval

uatio

n of

the

optio

ns fo

r mat

eria

ls

test

ing

will

be

com

plet

ed b

y th

e en

d of

20

02. I

n 20

04, t

he n

ext

desi

gn p

hase

of I

FMIF

w

ill b

egin

.

9 Fo

r fus

ion

to b

e ad

opte

d su

cces

sful

ly, s

ocie

ty

need

s to

be a

ssur

ed o

f its

safe

ty, f

easi

bilit

y an

d ec

onom

ic v

iabi

lity.

It is

ther

efor

e im

porta

nt th

at

soci

o-ec

onom

ic, e

nvir

onm

enta

l and

safe

ty

stud

ies b

e fu

rther

stre

ngth

ened

und

er F

P6. T

he

resu

lts o

f the

se a

ctiv

ities

shou

ld b

e us

ed to

en

hanc

e pu

blic

aw

aren

ess a

nd a

ccep

tanc

e of

fu

sion

pow

er a

nd it

s fut

ure

impo

rtanc

e.

An

impo

rtant

ele

men

t com

plem

entin

g th

e A

ssoc

iatio

ns’ s

cien

tific

an

d te

chni

cal w

ork

in F

P6 w

ill b

e in

vest

igat

ions

of s

ocio

-ec

onom

ic a

spec

ts, f

ocus

ing

on e

valu

atio

n of

eco

nom

ic c

osts

and

so

cial

acc

epta

bilit

y of

fusi

on e

nerg

y, in

add

ition

to fu

rther

stud

ies

on sa

fety

and

env

ironm

enta

l asp

ects

. Th

e C

omm

issi

on S

ervi

ces f

ully

supp

ort t

he v

iew

that

pub

lic

awar

enes

s and

acc

epta

nce

of fu

sion

pow

er is

an

impo

rtant

are

a of

ac

tivity

. Fur

ther

stre

ngth

enin

g of

act

ions

in th

is a

rea,

par

ticul

arly

w

ithin

the

fram

ewor

k of

EFD

A a

nd th

e A

ssoc

iatio

ns, i

s for

esee

n.

The

Com

mis

sion

Ser

vice

s will

und

erta

ke th

ese

activ

ities

dur

ing

FP6.

Furth

er st

udie

s on

soci

o-ec

onom

ics b

ased

on

the

resu

lts o

f the

ex

istin

g Po

wer

Pla

nt

Con

cept

ual S

tudi

es w

ill

star

t in

2003

.

32

R

ecom

men

datio

n C

omm

issi

on S

ervi

ces’

Res

pons

e T

ime

poin

t / in

dica

tor

for

impl

emen

tatio

n

10

In v

iew

of t

he a

ge p

rofil

e of

the

prof

essi

onal

s cu

rren

tly a

ctiv

e in

the

prog

ram

me,

eff

orts

shou

ld

be m

ade

to b

ring

in n

ew y

oung

scie

ntis

ts a

nd

tech

nici

ans,

and

to d

evel

op th

eir e

xper

tise.

Thi

s al

so re

quire

s tim

ely

deci

sion

s on

the

futu

re

prog

ram

me

tow

ards

the

“Nex

t Ste

p”, t

o cr

eate

en

thus

iasm

and

to o

pen

attra

ctiv

e pr

ofes

sion

al

care

ers.

The

Com

mis

sion

enc

oura

ges t

he A

ssoc

iatio

ns to

mak

e pr

opos

als

for M

arie

Cur

ie g

rant

s whi

ch p

rovi

de a

n ef

ficie

nt m

eans

to a

ttrac

t, yo

ung

rese

arch

ers i

nto

the

fusi

on c

omm

unity

.

One

of t

he st

rong

poi

nts o

f the

fusi

on M

obili

ty S

chem

e is

that

it

prov

ides

a m

echa

nism

by

whi

ch re

sear

cher

s fro

m th

e al

l A

ssoc

iatio

ns (p

artic

ular

ly a

lso

thos

e in

the

new

ly a

ssoc

iate

d st

ates

) ca

n w

ork

on th

e la

rge

expe

rimen

ts a

nd fa

cilit

ies o

f the

fusi

on

prog

ram

me.

Thi

s is e

spec

ially

val

uabl

e in

pro

mot

ing

the

expe

rtise

of

you

nger

rese

arch

ers.

The

real

isat

ion

of a

pro

ject

like

ITER

wou

ld a

ttrac

t bril

liant

, you

ng

phys

icis

ts a

nd e

ngin

eers

. Th

is is

link

ed to

a d

ecis

ion

on IT

ER c

onst

ruct

ion.

This

is a

n on

goin

g ac

tivity

.

11

The

co-

oper

atio

n w

ith in

dust

ry, w

hich

has

de

velo

ped

cons

ider

ably

in re

cent

yea

rs, s

houl

d be

furth

er in

tens

ified

. The

invo

lvem

ent o

f SM

Es

and

the

expl

oita

tion

of sp

in-o

ffs s

houl

d be

su

ppor

ted.

The

Com

mis

sion

, in

conj

unct

ion

with

the

actio

ns o

f the

C

omm

ittee

on

Fusi

on In

dust

ry (C

FI),

has p

rogr

esse

d in

pro

vidi

ng

info

rmat

ion

to in

dust

rial p

artn

ers f

or th

e la

rge

scal

e in

volv

emen

t w

hich

will

be

need

ed in

the

cons

truct

ion

of IT

ER. T

he c

o-op

erat

ion

with

indu

stry

has

bee

n es

sent

ial:

cost

est

imat

es fo

r sy

stem

s tha

t mig

ht b

e co

nstru

cted

for I

TER

are

bas

ed o

n ev

alua

tion

stud

ies m

ade

by in

dust

ry. P

artic

ipat

ion

of S

MEs

in

ITER

con

stru

ctio

n w

ill b

e pr

omot

ed th

roug

h ne

twor

king

/clu

ster

ing

with

the

Ass

ocia

tions

. Fur

ther

inte

nsifi

catio

n of

indu

stria

l in

volv

emen

t in

fusi

on w

ill fo

llow

any

dec

isio

n to

pro

ceed

with

IT

ER c

onst

ruct

ion.

This

is a

n on

goin

g ac

tivity

.