72
 Environmental Monitoring Report Semestral Report July-December 2013 VIE: Mong Duong 1 Thermal Power Plant  Prepared by Electricity of Vietnam and Thermal Power Projects Management Unit 1 for the Government of Viet Nam and the Asian Development Bank.

Environmental Monitoring Report

Embed Size (px)

Citation preview

  • Environmental Monitoring Report

    Semestral Report July-December 2013

    VIE: Mong Duong 1 Thermal Power Plant

    Prepared by Electricity of Vietnam and Thermal Power Projects Management Unit 1 for the Government of Viet Nam and the Asian Development Bank.

  • EVN GENCO 3

    Thermal Power Projects Management Board 1 (TPMB1)

    MONG DUONG (2 x 500MW) THERMAL POWER PLANT PROJECT

    2nd

    SEMI-ANNUAL

    ENVIRONMENTAL MONITORING REPORT 2013

    Period 01st

    July 31st

    December 2013

    Contract No: TPMB1-EVN/ADB-2610L2MFF-Consulting-002

  • 2nd Semi-annual Environmental Monitoring Report 2013

    Mong Duong (2 x 500MW) Thermal Power Plant Project

    Page 2 of 70

    CONTENTS

    EXECUTIVE SUMMARY ........................................................................................................... 5

    1. INTRODUCTION ............................................................................................................. 10

    1.1 The project ........................................................................................................................................10

    1.2 Incorporation of Environmental Requirements into Project Contractual arrangements ...................10

    1.3 Project Implementation Progress ......................................................................................................11

    1.4 Report Purpose .................................................................................................................................13

    2. ENVIRONMENT COMPLIANCE INSPECTIONS ..................................................... 14

    2.1 Environment Compliance Inspections at the Construction Site ........................................................14

    2.2 Health, Safety & Environment (HES) Aspects .................................................................................14 2.2.1 Health, Safety & Environmental Management Plan (EMP) ......................................................15 2.2.2 HSE Management Organization (EPC Contractor Hyundai E&C) ...........................................15 2.2.3 Total Man hours of the EPC Contractor and its Subcontractors ................................................15 2.2.4 Accident Free Man hours of the EPC Contractor and its Subcontractors ..................................16 2.2.5 Health, Safety and Environmental Training ..............................................................................16 2.2.6 Health, Safety & Environment Inspection and Result ...............................................................19 2.2.7 Personal Protective Equipment (PPE) .......................................................................................21 2.2.8 Security Status ...........................................................................................................................21 2.2.9 HSE Improvement Plant ............................................................................................................22 2.2.10 Safety Award .............................................................................................................................24

    3. ENVIRONMENTAL QUALITY MONITORING ........................................................ 25

    3.1 Air quality, Noise and Vibration Monitoring....................................................................................25 3.1.1 Monitoring of Air quality ..........................................................................................................25 3.1.2 Noise Monitoring ......................................................................................................................27 3.1.3 Vibration Monitoring ................................................................................................................31 3.1.4 Overall Assessment ...................................................................................................................32

    3.2 Water Quality Monitoring ................................................................................................................33 3.2.1 Monitoring parameters and procedures .....................................................................................33 3.2.2 Inspection Activities ..................................................................................................................35 3.2.3 Monitoring result and assessment ..............................................................................................36 3.2.4 Underground water quality at existing wells .............................................................................42 3.2.5 Underground water quality from drilled wells ..........................................................................45 3.2.6 Overall assessment ....................................................................................................................48

    4. AQUACULTURE & FISHERY ....................................................................................... 50

    4.1 Overview ..........................................................................................................................................50

    4.2 Inspection Activities .........................................................................................................................50

    4.3 Overall Assessment Aquaculture and Fishery ..................................................................................51

  • 2nd Semi-annual Environmental Monitoring Report 2013

    Mong Duong (2 x 500MW) Thermal Power Plant Project

    Page 3 of 70

    5. MANGROVE REFORESTATION MONITORING ..................................................... 53

    5.1 Overview ..........................................................................................................................................53

    5.2 Inspection Activities .........................................................................................................................53

    5.3 Overall Assessment Mangrove Reforestation ...................................................................................54

    5.4 Recommendation ..............................................................................................................................55

    6. OVERALL CONCLUSIONS AND RECOMMENDATIONS ..................................... 56

    6.1 Health, Safety &Waste Disposal Management .................................................................................56

    6.2 Environmental Quality Monitoring...................................................................................................56 6.2.1 Air & Noise and Vibration Monitoring .....................................................................................57 6.2.2 Water quality Monitoring ..........................................................................................................57 6.2.3 Aquaculture and Fishery Monitoring ........................................................................................58 6.2.4 Mangrove Reforestation Monitoring .........................................................................................58

  • 2nd Semi-annual Environmental Monitoring Report 2013

    Mong Duong (2 x 500MW) Thermal Power Plant Project

    Page 4 of 70

    TABLES Table 1.1Institutional Responsibilities for EMP Implementation (extended version) ................................................. 10

    Table 2.1: Accident-free man-hour .................................................................................................................................... 16

    Table 2.2: Health, Safety & Environment Training Status .......................................................................................... 17

    Table 2.3: Health, Safety & Environment Inspection and Result ................................................................................ 20

    Table 2.4: HSE Improvement Plant ............................................................................................................................ 22

    Table 3.1: The monitoring location, monitoring parameters and monitoring equipment and analyzed methods for air

    quality monitoring ............................................................................................................................................... 25

    Table 3.2: Monitoring results of TSP and PM10 ........................................................................................................ 25

    Table 3.3: The monitoring location, monitoring parameters and monitoring equipment and analyzed methods for

    noise monitoring.................................................................................................................................................. 28

    Table 3.4: Monitoring results for Noise at residential sites ......................................................................................... 28

    Table 3.5: Monitoring result for Noise at the working site ......................................................................................... 29

    Table 3.6: The monitoring location, monitoring parameters and monitoring equipment and analyzed methods for

    vibration monitoring ............................................................................................................................................ 31

    Table 3.7: Monitoring results for vibration at residential sites .................................................................................... 31

    Table 3.8: Coordinates of surface water samples ........................................................................................................ 36

    Table 3.9: Monitoring and analyzing results of surface water .................................................................................... 37

    Table 3.10: Coordinates of coastal water samples ...................................................................................................... 39

    Table 3.11: Monitoring and analyzing results of coastal water samples ..................................................................... 40

    Table 3.12: Coordinates of underground water samples (Existing wells) ................................................................... 42

    Table 3.13: Monitoring and analyzing results of underground water (Existing wells) ................................................ 43

    Table 3.14: The coordinate of underground water (Drilling wells) samples ............................................................... 45

    Table 3.15: Monitoring and analyzing results of underground water (Drilling wells) ................................................ 46

    Table 5.1: Monitoring and analyzing results ............................................................................................................... 54

    FIGURES Figure 3.1: Water quality environmental monitoring procedure ................................................................................. 34

    Figure 3.2: Monitoring sites ........................................................................................................................................ 35

    Figure 5.1: Method for selection of sample................................................................................................................. 53

    APPENDIXS Appendix 1 Environmental Team Organization Chart ................................................................................................ 60

    Appendix 2 HSE Organization Chart .......................................................................................................................... 62

    Appendix 3 Pictures of Air quality and Noise ............................................................................................................. 63

    Appendix 4 Pictures of Water Quality ........................................................................................................................ 65

    Appendix 5 Pictures of Aquaculture and fishery......................................................................................................... 66

    Appendix 6 Pictures of Mangrove Reforestation ........................................................................................................ 67

    Appendix 7 Picture of HSE ......................................................................................................................................... 68

  • 2nd Semi-annual Environmental Monitoring Report 2013

    Mong Duong (2 x 500MW) Thermal Power Plant Project

    Page 5 of 70

    EXECUTIVE SUMMARY

    The Mong Duong 1 Thermal Power Plant project has been classified as category A1 in

    accordance with ADBs Environmental Assessment Guidelines (2003). The Project EMP was developed as an integral part of the Environmental Impact Assessment (EIA) process of the

    Project that was completed and approved by ADB in 2006.

    To ensure that negative environmental health and safety impacts are minimized and addressed

    effectively throughout the project implementation and operational phase, an environmental

    management plan (EMP) has been formulated detailing mitigation measures and a monitoring

    program during various project phases of the Mong Duong 1 Thermal Power Plant project,

    located in the northern province of Quang Ninh (Vietnam)

    The report is highlighting on the environmental monitoring tasks and quality observations

    performed by the various project entities on air & noise, vibration, water quality, aquaculture

    and fishery development and a chapter on mangrove reforestation. It is further reporting on

    health & safety issues at site as well as on social impacts on the affected communities including

    gender issues related to man and women working together on the same project and sharing

    common camp facilities.

    It covers the works implemented during the period July to December 2013 and provides a

    summary of current problems, conclusions and recommendations how to best mitigate the

    impacts on affected parties and the environment.

    The following environmental aspects were looked at for environmental compliance and

    monitored for environmental quality during the reporting period

    Air and noise quality

    Water quality

    Aquaculture and fisheries status

    Mangrove reforestation

    Health, Safety and Environment (HES)

    Social impacts and Gender issues Problem areas inspected for environmental compliance and monitored for environmental quality

    during the reporting period relating to Air & Noise, Vibrations, Water quality and Aquaculture

    were more affected in the current reporting period compared to the last 6 months period, mainly

    due to the increased level of activities at the construction site or nearby locations serving the

    Mong Duong project. Air & Noise and Vibration Issues Regarding Air Quality comparing the monitoring results (dust) of affected areas between the first 6 months in 2013 and the last 6 months of 2013, it shows that the last 6 months of 2013 has a

    higher concentration of air pollutants than the 6 months before, especially in the 3 months

    September, October and December 2013 when the construction activities were very high. The

    increase is mostly due to increased traffic on the new No.18 and old No.18A road likewise

    carrying equipment and construction materials to the site

    On the new No.18 road near the entrance of Mong Duong 1 and 2 power plants, heavy vehicle

    movements are the main cause of dirt and dust. Additionally intermittent rainfalls during these

    months made the road muddy too. The contractor is trying hard to clean the road to improve the

    conditions. The appearance of construction waste in nearby vacant land (along the new No.18

  • 2nd Semi-annual Environmental Monitoring Report 2013

    Mong Duong (2 x 500MW) Thermal Power Plant Project

    Page 6 of 70

    road such as concrete from bored piles and other construction debris has improved over time

    and gives a tidy look now. Wheels of construction vehicles leaving the site are cleaned before

    entering the public road. Excavated areas and heaps of backfill on the site shall are sprayed with

    water or covered with plastic sheeting to limit dust migration to nearby residential areas.

    Through 6 monitoring times of noise quality at the working site during 2 days each in the period

    July to December 2013, the monitoring results for noise at working site in all six monitoring

    times, noise level monitored in 1 hours at boiler area is about 73,2 78,1 dB(A). If compared

    with allowable noise levels at working places, the measured values are lower than the limited

    permitted values in TCVN 3985:1999 (85 dB).

    Noticeable environmental impacts during the reporting period has not only been caused by

    construction activities, but also due to social environment changes caused by the gathering of the

    large work force in the Mong Duong precinct which causes all sort of problems including

    increased traffic, particularly in the early morning and evening time, when a large contingent of

    the labor force for both projects enter the work space and accumulation of domestic waste caused

    by the increase in people inhabiting the area.

    In order to limit the noise level at Residential areas, particularly at night time, the Contractor has

    been requested to keep heavy construction works to day times and limit vehicle movements after

    10PM to a minimum required. This has been well observed by both contractors for Md1 and

    MD2 power plants

    Through 6 monitoring times during 2 days each in the period July to December 2013,

    Monitoring results for vibration level at 2 sites during the period of 6AM 21PM are lower than the limited value in QCVN 27:2011/BTNMT National Technical Regulations on Vibration. Construction activities of Mong Duong 1 Thermal Power Plant are mainly implemented during

    the daytime, therefore no vibration is created during the nighttime, from 21PM-6AM. Water quality

    Water quality is monitored for underground water and coastal water:

    Almost all tested items of underground water at the sampling sites are within the limits of

    the National technical regulation on underground water quality QCVN09/2008/BTNMT

    except for (Cd) and (Cl-) content and content of micro-organisms (Coliform)

    Concentration of microorganisms (Coliform) beyond permissible limits of the National

    technical regulation on underground water quality were found at the sampling points of

    PW-01, PW-02, PW-03, PW-04, PW-05, PW-06, PW-08, PW-09. This is explained by

    the fact that water in existing wells are not frequently utilized, thus the water is not

    rotated thereby easily creating conditions for microbial growing.

    Concentrations of chloride (Cl-) beyond permissible limits of the National technical

    regulation on underground water quality were found at the sampling points of PW-03,

    GW-01-D, GW-08, GW-09 and GW-11. This is explained by the fact that the sampling

    sites are located in the coastal areas, thus may be lightly saline

    Impact of obstacle removal activities in coastal surface water is monitored by coastal

    surface water sampling sites. Parameters of them are all within limit in comparison with

    QCVN 10: 2008/BTNMT

  • 2nd Semi-annual Environmental Monitoring Report 2013

    Mong Duong (2 x 500MW) Thermal Power Plant Project

    Page 7 of 70

    Impact of Mong Duong river alignment activities in coastal surface water is monitored by

    coastal surface water sampling sites. Parameters of them are almost within the limit in

    comparison with QCVN 08: 2008/BTNMT

    Impact of transport activities in coastal surface water is monitored by coastal surface

    water sampling sites. Parameters of them are within limit in comparison with QCVN 10:

    2008/BTNMT

    Two of the heavy water pollution sources are water discharged from coal mining areas

    via the Mong Duong River and barges transporting coal in the nearby waterway.

    Spilled coal from barges dilutes elements and compound to coastal waters.

    In order to compensate for the two wells which were covered during the initial site fill activities,

    the contractor has been requested to drill two additional wells with a depth of 25 to 30m to

    ensure water quality sampling can be done at lower aquifers. This has since been completed by

    the Owners own contracted agency.

    Contractor must maintain all current measures to avoid pollution of surface and underground

    water resources by strict control on solid and liquid waste dumping and/or accidental spillage of

    oil and chemicals.

    To offset the problem of the polluted water discharge from coal mining activities, treatment of

    discharged water from the coal mining process and a reduction in coal smuggling activity would

    greatly improve the quality in the water way, but this may be difficult to achieve.

    Aquaculture and Fisheries

    Based on the results of the two surveys on fishing and aquaculture activities in Thac Thay, De

    Dach and Mong Duong rivers and along the coastal line of Cam Hai commune during the second

    half of 2013, it can be concluded that the construction phase of Mong Duong 1 power plant has

    minor impacts on the aquatic resources in the inspected areas. There were no fishing activities in

    De Dach and Mong Duong rivers due to heavy industrial pollution from mining and coal trading.

    Number of aquatic species and their components in these areas are very limited. Some fishing

    activities were observed in the Thac Thay River and Luong Gac areas, but there are no

    shrimp activities along Cam Hai coastal line due to loss from shrimp disease outbreak and

    flooding. Normal fishing activities and aquaculture species are observed in the Thac Thay River

    and along the coastal line of Cam Hai commune.

    To reduce impacts of pollution from mining and coal trading, Contractors are requested to

    strictly enforced the solid and liquid waste disposal management plan and prohibit dumping of

    hazardous substances into nearby rivers and coastal water.

    Mangrove Reforestation Program

    To compensate for the loss of mangrove forest taken by the Mong Duong Project, 52ha of

    mangrove has been re-planted in Dong Rui Commune, (Tien Yen district, QuangNinh province)

    Inspection result shows that mangrove quality develops well, branching off well, in the allocated

    area of 52 ha of mangrove forest which was replanted, there is 95% survival rate of plants.

  • 2nd Semi-annual Environmental Monitoring Report 2013

    Mong Duong (2 x 500MW) Thermal Power Plant Project

    Page 8 of 70

    With the current achieved results, the Mangrove planting project has met the requirement of

    ADBs EIA.

    To sustain the good results, continuous protection and feeding of the mangrove is a must to

    ensure their good development and branching off. Activities such as tree clearing, weeding and

    replanting of failed areas must also be maintained

    Dumping of waste in mangrove and forestry areas and resource extraction from mangroves and

    plantation forestry areas must be strictly prohibited.

    Mangrove reforestation in area 1 has been accepted by TPMU1 in October 2013. The area 2 has

    not been accepted due to the ratio of coverage has not meet the requirement of the contract yet

    and the areas of died trees needs to be regrown, so efforts need to be continued to achieve the

    required results

    Health & Safety and Environment

    Monitoring consists of daily observation and inspections of environmental pollution, soil

    contamination, fire hazards, labor and site safety and other health or safety hazards. This topic

    does not belong to the monitoring scheme of the assigned environmental experts of the

    Consultant, but is observed and monitored by the Owners Consultant Site supervision staff during their daily work activities and by the Consultants Occupational Health and Safety expert.

    Current results show

    Good overall performance of the EPC contractors appointed HSE team with the

    Environmental Officer (OE) appointed as per the Contractors EMP

    Good site safety management of the EPC contractor with regards to fire safety, plant and

    equipment safety, labor safety, worker training before entering working sites and access

    gate checks at site entering points.

    No fatality but 2 Lost Time accident occurred until now with the accumulated total man-

    hours of 12,386,146 as of December 2013

    No serious soil issues happened at site until now, besides some small oil spillages

    which were treated immediately as per the Contractors EMP

    Waste management follows the contractors EMP by separating waste into different

    groups and collected and disposed as per the EMP requirements.

    All required permits are in place ie. Permit To Work, Confined Space Entry Permits, Gas

    Test Certificates etc.

    First Aid service is available 24/7

    In order to maintain the good standard the EPC contractor must strictly enforce the site safety,

    warn offenders and in repeat cases dismiss them from site (some recent incidents shown in the

    attached pictures need to be corrected)

    Newly legislated and/or revised environmental laws must be carefully examined in order to

    determine whether or not they are required to be implemented during the project execution

    Contractor has to ensure at all times that it complies with the EIA and the requirements specified

    in chapter VI of the ADB environmental assessment guidelines, 2003. Contractor should once

  • 2nd Semi-annual Environmental Monitoring Report 2013

    Mong Duong (2 x 500MW) Thermal Power Plant Project

    Page 9 of 70

    every 6 months organize exercises based on likely accident scenarios at site in which the

    contractors assigned key site personnel assumes their emergency response roles and

    periodically evaluate the efficiency of the Project EMP in place.

    Social and Gender Aspects

    Most current results show that both men and women are well informed of potential health and

    safety risks: HIV/AIDS control and prevention activities for both camp workers and offices were

    carried out by the EPC contractor to educate awareness on personal hygiene and sexually

    transmitted diseases. Drug education for construction and office workers are implemented and

    undergo test screenings every 6 months for early detection and manage health issues. Camp

    workers and construction office workers are vaccinated and regularly checked for diseases by

    healthcare provider taking care of construction workers and local villages.

    A recent audit at one of the contractors labor camp (LLM 69.1) showed excellent results. The

    rooms for women are in good condition and include bath room and toilet inside. Television and

    Air conditioner are also provided. Water supply is from underground well treated by RO system

    before using. Water is tested frequently for its safe use.

    The condition of the site toilets is good with separate toilets available for both men and women.

    Currently 76 toilets are provided at the Mong Duong 1 site for some 3,000 workers. They are

    cleaned daily. As per the EPC contractors information the percentage of female workers is

    approximately 15% split in field and office staff.

    It is suggested that the Owners Consultant will continue to perform regular audits at the contractors labor camps, especially with regards to gender issues, at the contractors offices and at the construction site itself, to ensure the good standard regarding sanitary conditions is

    maintained throughout the project construction phase.

  • 2nd Semi-annual Environmental Monitoring Report 2013

    Mong Duong (2 x 500MW) Thermal Power Plant Project

    Page 10 of 70

    1. INTRODUCTION

    1.1 The project

    The Government of Viet Nam has requested assistance from the Asian Development Bank

    (ADB) to part finance the construction of the Mong Duong 1 Thermal Power Plant (under Loan

    No.2350, and 2610). The Project is a coal-fired, thermal power electricity generation project with

    a generation capacity of 1,000 MW. The overall project comprises of two power plants on the

    same plot of land with an ultimate generation capacity of 2200 MW. The Mong Duong 1 power plant will comprise of two 500 MW generating units, and associated supporting infrastructure

    whereas the Mong Duong 2 power plant built under a BOT scheme comprises of two 600 MW

    generating units.

    The MD1 project has been classified as category A1 in accordance with ADBs Environmental Assessment Guidelines (2003). The EMP was developed as an integral part of the Environmental

    Impact Assessment (EIA) process of the Project that was completed in 2006.

    The Mong Duong 2 power plant project is not part of this report, although it may contribute to

    the overall impact on the environment as the two plants are back to back located on the same

    piece of land.

    1.2 Incorporation of Environmental Requirements into Project Contractual arrangements

    To ensure that any possible negative environmental impacts are minimized and addressed

    effectively, an environmental management plan (EMP) has been formulated detailing mitigation

    measures and a monitoring program during various project phases. The individual monitoring

    tasks and its frequencies are determined by the EIA and the approved staffing plan of the Project

    Owner of the Consultants experts conducting the monitoring tasks together with EVN appointed environmental monitoring agencies of Quang Ninh province

    Key organizations in the implementation of the EMP and their corresponding responsibilities are

    presented in Table 1.1

    Table 1.1Institutional Responsibilities for EMP Implementation (extended version)

    EMP Responsibilities

    Mong Duong 1 Responsibility

    - Submit Government EIA/EMP to MONRE - Successfully implement EMP - Provide funds for EMP implementation

    EVN/GENCO3 (Project owner)

    - Coordinate and manage overall project implementation and operation including

    guiding and supervision of EMP

    implementation during pre-construction,

    construction, and operation phases

    - Manage and coordinate environmental monitoring

    - Coordinate with other parties in relation to environmental management activities

    - Supervise civil work contractor during construction, including implementation of

    TPMB1

  • 2nd Semi-annual Environmental Monitoring Report 2013

    Mong Duong (2 x 500MW) Thermal Power Plant Project

    Page 11 of 70

    EMP Responsibilities

    Mong Duong 1 Responsibility

    environmental management activities under EMP

    - Manage EMP budget - Integrate EMP specifications in contract documents

    - Prepare detailed design activities incorporating relevant EMP requirements

    Detail design consultant

    (PECC1)

    - Implement environmental specifications detailed in the construction contract

    Construction contractor

    - Monitor EMP implementation during the construction phase

    Environmental monitoring

    consultant team

    - Conduct periodic monitoring of compliance to EIA/EMP provisions

    Quang Ninh DONRE

    1.3 Project Implementation Progress

    During the second half of 2013 of the construction phase of the Mong Duong 1 thermal power

    plant project, construction activities increased commensurately with the ongoing progress of the

    project.

    Some of the main civil construction works carried out at the construction site during this period:

    July 2013

    Concrete works for Stack #1were completed

    Concrete works for top slab of Waste water treatment pond area was completed.

    Concrete works for foundation of seal pit #1 and #2 were completed.

    Concrete works for Fly Ash foundation and pedestals were completed.

    Concrete works for WT clarifier and acid tank foundation were completed.

    Superstructure for Administration building, Common Services building, Central Control

    building and Water treatment building were completed and now undergoing architectural

    finishing works

    Fuel oil tank foundations were completed

    Top slab of Turbine pedestal #1 was completed August 2013

    Earth anchor works for CW Intake facility were completed

    Concrete works for CW Intake and pump station continued

    Excavation works for Bottom Ash silo and ID fan foundation were completed

    Backfill work for Fly Ash Silo foundation was completed

    Excavation works for WT plant outdoor equipment foundations were completed

    Excavation work for Potable tank was completed

    Piling work for Chlorination plant and CW outdoor facility was completed

    Installation for 110kV switchyard were completed

  • 2nd Semi-annual Environmental Monitoring Report 2013

    Mong Duong (2 x 500MW) Thermal Power Plant Project

    Page 12 of 70

    September 2013

    Concrete works for C.W discharge box culvert were completed Concrete works for Seal pit A, B were completed Concrete works for Generator Transformer #2 fire walls were completed Top slab of Turbine pedestal #2 was completed

    Concrete work for Bottom Ash Silos and ESP foundations were completed

    Concrete works for WT plant outdoor clarifier, potable water tank, pH adjust

    &mixing pond and pressure filter foundation were completed

    Piling work for Coal Transfer Towers & Belt Conveyors was completed

    Piling work for limestone and fuel oil unloading jetties was completed October 2013

    Concrete work for Stack #2 Windshield was completed.

    Concrete work for 2nd slab in Intake Facility (pump house) was completed.

    Concrete work for Cooling water discharge box culvert zone A was completed

    Excavation work for Discharge outfall was completed

    Concrete work Transformer #1 foundation was completed

    Concrete work Transformer #2 pedestal was completed

    Backfill work Transformer #2 was completed

    Concrete work for Main pipe rack was completed

    Concrete work for ID Fan foundation #1B was completed

    Backfill work for ID Fan #1B was completed

    Backfill work for Bottom ash silo #1B was completed

    Concrete work for cable trench in 500KV & 110KV Switchyard was completed

    Pile work for Return water pump house was completed

    Pile work for Gantry crane in Intake facility was completed

    Pile work for Return water pipe rack was completed

    November 2013

    Backfill work for C.W. Discharge Box Culvert zone A was completed

    Backfill work for Main pipe rack was completed

    Concrete work for ID fan wall 1B was completed

    Concrete work for ID fan wall 2B was completed

    Concrete work for Bottom ash silo 1A was completed

    Backfill work for Bottom ash silo 1A was completed

    Concrete work for foundation of 500KV & 110KV Switchyard was completed

    Concrete work for WWT area support foundation was completed

    Concrete work for WWT area trench was completed

    Concrete work for WWT area pump foundation was completed

    Excavation work for Heavy fuel oil dike was completed

    Excavation work for Sewage treatment system was completed

  • 2nd Semi-annual Environmental Monitoring Report 2013

    Mong Duong (2 x 500MW) Thermal Power Plant Project

    Page 13 of 70

    December 2013

    Concrete work for Outfall was completed

    Backfill work for C.W Discharge Box Culvert zone B was completed

    Backfill work for Seal pit A, B was completed

    Concrete work Transformer #1 Pedestal & Fire Wall was completed

    1.4 Report Purpose

    This report intends to describe the progress regarding implementation of the project EMP and

    compliance issues and corrective actions for the second half of 2013 of the construction phase of

    the Mong Duong 1 thermal power plant project.

    The following environmental aspects were inspected for environmental compliance and

    monitored for environmental quality:

    Air, noise quality and vibration

    Water quality

    Health Safety and Environment (HES) aspects

    Aquaculture and fisheries

    Mangrove reforestation

    1.5 Vietnamese Environmental law/regulation and Project Environment documents

  • 2nd Semi-annual Environmental Monitoring Report 2013

    Mong Duong (2 x 500MW) Thermal Power Plant Project

    Page 14 of 70

    2. ENVIRONMENT COMPLIANCE INSPECTIONS

    2.1 Environment Compliance Inspections at the Construction Site

    - Air quality impact:

    + Dust resulting from the removal of vegetation and heavy earthmoving activities

    + The large number of construction equipment and heavy vehicles cause considerable dust emissions

    - Mitigation measures: - Constructors have applied the following measures

    + Spraying bare soil and heaps of excavation materials with water to minimize dust generation during dry periods

    + Minimizing disturbance to vegetation and terrain features and providing cleared areas and stockpiles with vegetative cover to serve as buffers between the Project and the population

    + Fencing off construction areas to contain dust,

    + Covering trucks during transport of materials and impose speed limits

    + Avoid burning of domestic wastes

    + Contractors will be required to properly maintain equipment to minimize emissions

    + Ensuring the commitment of contractors and/or suppliers to undertake applicable measures above

    + All trucks before leaving the construction site are required to clean the wheels

    - Noise and ground vibration:

    + Noise impact and ground vibration during construction can disturb nearby communities

    - Mitigation measures:

    + Construction schedules must optimize daytime working hours and scale down activities at night.

    + Extensive earthmoving and movement of heavy equipment should be conducted only during regular working hours

    2.2 Health, Safety & Environment (HES) Aspects

    The following Health & Safety and Environment (HES) aspects were inspected / monitored

    during the reporting period for compliance

    Site safety issues Site waste disposal management Pollutants Spillage

    Worker Camp and Sanitation issues Social impacts and Gender issues Health aspects

  • 2nd Semi-annual Environmental Monitoring Report 2013

    Mong Duong (2 x 500MW) Thermal Power Plant Project

    Page 15 of 70

    2.2.1 Health, Safety & Environmental Management Plan (EMP)

    The EPC contractors Environmental Management Plan (Rev B) was issued to the Project Owner on 30thNov 2012 under Doc No. MD1-0-T-070-01-00021 and approved as such.

    The policy shall be communicated to all employees and those working for and on behalf of

    HDEC through the induction course and be displayed at the site working area and in prominent

    positions on site.

    2.2.2 HSE Management Organization (EPC Contractor Hyundai E&C)

    The EPC contractors HSE organization structure is in line with their own EMP (refer to Appendix 1 update 25th December 2013)

    Safety Engineers/Officers have Certificate of OHS and show good working experience. Contractors Environmental Officer (OE) is appointed as per the EMP and portrays

    excellent knowledge of the environmental management system (EMS) as well as the

    applicable approved environmental impact assessment report (EIA).

    2.2.3 Total Man hours of the EPC Contractor and its Subcontractors

    Table 2.1 shows the accident hours against cumulative total man-hours during the period of

    July and December, 2013

  • Page 16 of 70

    2nd Semi-annual Environmental Monitoring Report 2013

    Mong Duong (2 x 500MW) Thermal Power Plant Project

    Table 2.1: Accident-free man-hour

    DESCRIPTION Total (Cumulative)

    MONTH Jul Aug Sept Oct Nov Dec

    Cumulative total man-hours

    6,007,761

    7,132,820

    8,818,228

    9,635,789

    10,988,975

    12,386,146

    Cumulative since last LTI

    892,351

    1,125,059

    1,047,408

    1,455,561

    2,222,311

    3,619,483

    Fatalities - - - - - -

    Accum. Lost time incidents (LTI)

    -

    -

    1

    2

    2

    2

    Restricted Work Day Case

    -

    -

    -

    -

    -

    -

    Accum. Medical Treatment Case

    1

    1

    1

    1

    1

    1

    Accum. Non- injurious incidents

    8

    10

    12

    12

    14

    15

    Accum. First aid cases

    99

    106

    115

    127

    134

    141

    Accum. Near Miss Incidents

    4

    5

    5

    5

    7

    8

    LTIFR* - - - 0.208 0.182 0.161

    * LTIFR (Lost Time Injury Frequency Rate)

    Fatality a+ a =

    kg as , 0, 0

    2.2.4 Accident Free Man hours of the EPC Contractor and Subcontractors

    Until 1st

    January 2014, there has been no fatality with total accumulated man hours reaching

    12386146. Unfortunately, 2 lost time incidents occurred on 15/9/2013 [Appendix 2] and on 12/10/2013 [Appendix 3] and one Fire incident on 4/12/2013 [Appendix 4]

    2.2.5 Health, Safety and Environmental Training

    The training records and site inspection results related to safety and environmental aspects are

    presented in Table 2.2.

  • 2nd Semi-annual Environmental Monitoring Report 2013

    Mong Duong (2 x 500MW) Thermal Power Plant Project

    Page 17 of 70

    Table 2.2: Health, Safety & Environment Training Status

    Item

    No. o

    July

    f

    No. of

    No.

    August

    of N

    o. of

    September

    No. of No. of

    No.

    October

    of No. of

    November

    No. of No. of

    December

    No. of No. of

    Trainer Description Training People training People training People training People training People training People

    T.B.M. Safety Engineer

    Daily T.B.M. before

    starting work

    Daily

    77,266

    Daily

    99,979

    Daily

    97,818

    Daily

    128,280

    Daily

    121,924

    Daily

    121,924

    Induction

    Training

    Safety

    Engineer

    Induction Training

    for

    Safety/Environment

    30

    1,175

    23

    1,183

    23

    1,315

    22

    1,343

    22 873 22 800

    Rigger Safety

    Officer Lifting, Rigging,

    Signal man

    2

    39

    1

    12

    1

    10

    Working at

    Height Safety

    Engineer For people who

    work at height

    5

    152

    6

    242

    7

    340

    2

    70 5 370 7 298

    Refreshment

    Training

    Safety

    Officer

    PTW, Lifting,

    Working at height,

    Accident case

    21

    1,780

    21

    1,647

    Confined Space

    Training

    Safety

    Officer

    How to work in

    confined space

    1

    26

    4

    152

    3

    87

    2

    243 2 243 2 95

    Special

    Training Safety

    Officer Electrical Safety for

    Licogi Corp.

    1

    60

    Special

    Training Safety

    Officer

    Rigger for YooA

    1

    33

    Special

    Training Safety

    Manager

    PTW Procedure

    2

    110

    Special

    Training

    Safety

    Officer

    Crane operator for BDCC and Lilama

    45.1

    1

    46

    Fire-fighting

    Training Safety

    Engineer How to prevent fire

    from the site

    30

    1,175

    23

    1,183

    23

    1,315

    22

    1,343

    22 873 22 800

  • 2nd Semi-annual Environmental Monitoring Report 2013

    Mong Duong (2 x 500MW) Thermal Power Plant Project

    Page 18 of 70

    Item

    Trainer

    Description

    July

    August

    September

    October

    November

    December

    No. of

    Training

    No. of

    People

    No. of

    training

    No. of

    People

    No. of

    training

    No. of

    People

    No. of

    training

    No. of

    People

    No. of

    training

    No. of

    People

    No. of

    training

    No. of

    People

    Operation

    Training

    Safety

    Officer

    For crane operator,

    fork lift operator

    1

    120

    PTW

    Training

    Safety

    Officer

    Permit to work

    procedure

    22 873

    Refreshment

    Training

    Safety

    officer

    For Locogi Corp, Lilama 69.1 after

    near miss

    2 133

    Special

    Training

    Safety

    Office

    Safety Supervisor

    training for Licogi

    Corp Engineers

    1 6

    Refreshment

    Training

    Safety

    Office

    Lilama 69.1 after

    near miss incident

    1 53

  • 2nd Semi-annual Environmental Monitoring Report 2013

    Mong Duong (2 x 500MW) Thermal Power Plant Project

    Training methodology

    Power Point presentation for site safety training in both languages English and Vietnamese are

    available and taught at Hyundais Site Safety office on a daily bases

    All new employees/visitors need to pass the safety training before admission to site. In case of an incidence occurrence, the involved persons are sent back to repeat training to

    avoid future incidents of a similar nature

    2.2.6 Health, Safety & Environment Inspection and Result

    Table 2.3 shows HSE inspections and results during the observed period of July and

    December, 2013

    Page 19 of 70

  • 2nd Semi-annual Environmental Monitoring Report 2013

    Mong Duong (2 x 500MW) Thermal Power Plant Project

    Table 2.3: Health, Safety & Environment Inspection and Result

    Location Inspector Jul Aug Sep Oct Nov Dec Description

    Boiler

    Safety

    Engineer/Officer

    Daily

    Daily

    Daily

    Daily

    Daily

    Daily

    Working at height, Lifting Activities, (October and November: A Lilama 69.1 worker was injured by

    Pipe spool)

    Admin

    Building

    Safety

    Engineer/Officer

    Daily

    Daily

    Daily

    Daily

    Daily

    Working at height, Scaffolding Condition, Access etc. (September: One person (Licogi 18) was injured while

    dismantling of hoist was ongoing)

    Whole

    area

    Workshop/Safety

    Engineer

    Weekly

    Weekly

    Weekly

    Weekly

    Weekly

    Weekly

    Visual inspection of all cranes (September: Temporary electric

    cable and electric pole located in GRP Block B (belonging to MD

    2) were damaged by dump truck) Field

    Tank Safety

    Engineer/Officer

    Daily

    Daily

    Daily

    Daily

    Daily Electric Condition (Welding and Panel Board), Scaffolding

    Condition, Confined Space Condition

    STB

    Safety

    Engineer/Officer

    Daily

    Daily

    Daily

    Daily

    Daily

    Daily

    Working at height, Scaffolding Condition, Access etc.

    August: A hook did a free fall due to operators mistake from approx. 5m at STB #2 and hit one workers left leg. He sustained slight injury (First Aid Case)

    September: Small fire happened in the GRP Block C, it was

    extinguished immediately.

    Chimney Safety

    Engineer/Officer

    Daily Checking slip form, working at height, lifting activities.

    WWT

    Building

    Safety

    Engineer/Officer

    Daily

    Daily

    Daily

    Daily

    Daily

    Lifting activities, working at height, scaffolding condition, Access etc.

    July: Falling material (Non-injury accident) took place when roof

    lifting was ongoing by YOOA contractor

    Coal

    Yard

    Safety

    Engineer/Officer

    Daily

    Daily

    Daily

    Daily

    Working at height, Lifting activities August: A fire happened in the electric panel board. It was

    extinguished completely by the Fire Watch Man

    Intake Safety

    Engineer/Officer

    Daily Working at height, Scaffolding Condition, Lifting activities, Hot Work, and etc

    BOP Safety

    Engineer/Officer

    Daily Lifting activities, Hot work, electric condition, and etc

    Environment Compliance Inspection Reports were issued in August, September, October, November and December 2013 by HDEC.

    Page 20 of 70

  • Page 21 of 70

    2.2.7 Personal Protective Equipment (PPE)

    All employees of the EPC contractor and all its subcontractors, or anyone visiting the work

    area, are required to wear hard hat (with exception of office, cafeteria, and

    accommodation), safety shoes, high visibility vest and fluorescent gathers covering ankles

    above the safety shoes. The use of a safety harness is compulsory when working at heights

    greater than 2 meters above ground. Safety [harnesses are to be of the double clip type so

    the wearer is secure at all times

    2.2.8 Security Status

    EPC contractor has placed security guards 24/7 at all the access gates. (Main gate,

    cooling water intake and material laydown area)

    All gates implement inspections for workers and vehicles to prevent theft.

    EPC contractor has prepared PPE for visitors at the main gate and check all workers and

    vehicles if they have valid IDs and/or vehicle cards

    There are 4 security cameras at the Main gate.

    However, there were still some occurrence of thefts reported by the contractor

    Time & Date: 03-Sep-2013 at night time

    Location: Barge, temporary jetty

    Discovered by: Vietranstimex Supervisor

    Material Stolen: 1'' C/S pipe (4.2 m long) 466 pieces

    4'' Horizontal Bracing (2.8 m long) 39 pieces

    4'' Horizontal Bracing (2.3 m long) 20 pieces

    4'' Horizontal Bracing (1.2 m long) 22 pieces

  • Page 22 of 70

    Time & Date: 25-Sep-2013 at night time

    Location: The North of Boiler 1B

    Discovered by: HDEC Security Supervisor

    Material Stolen: 1 ton of steel scrap

    This material hadn't moved out the site

    Time & Date: 07-Oct-2013 18.15PM

    Location: Main gate

    Description: Two SeJong workers tried to bring copper wire to out of

    the site. However, these workers were caught by HDEC Security

    Guard, and this material hadn't moved out the site

    Material Stolen: - 20 Ground Cable (01 m) x 1

    - 40 Copper wire (20 cm) x 4

    Time & Date: 20-Oct-2013 18.00PM

    Location: Main gate

    Description: Two SeJong workers tried to bring copper wire to out of

    the site. However, these workers were caught by HDEC Security

    Guard, and this material hadn't moved out the site

    Material Stolen: - 15 Ground Cable (70 cm) x 2 - 30 Copper wire (25 cm) x 2

    2.2.9 HSE Improvement Seminar

    Table 2.4: HSE Improvement Seminar

    Month Seminar topics Implementation Time Description

    July Special training for driver and

    operator

    Safety

    Engineer/Officer

    August 2013

    How to operate crane, forklift and

    excavator

    July Reinforce PTW Implement

    HSE Department

    From August

    All works need PTW to implement

    August Apply new

    penalty system

    HSE Department

    September

    2013

    Money deducted from Subcontractor

    salary will be spent for Safety Award and

    Safety Facilities. August Make man

    basket for

    emergency case

    HSE Department

    September

    2013

    For lowing injury person at restricted area

    (Turbine, Transformer, etc).

    September Refreshment training

    HSE Department Sep-Oct

    2013 PTW, Lifting, Working at height, Accident cases

    September Fire Fighting drill

    HSE Department

    Oct 2013 Fire watch man and safety staff operate fire water truck periodically

    October Enhance environmental

    management

    HSE Department

    Nov 2013

    Hazardous waste management

    October Fire-fighting drill

    HSE Department

    Nov 2013 Fire watch man and safety staff operate fire water truck periodically

    November Zero incident strategy

    HSE Department Nov 2013 to

    Dec 2013 Prevention all accident until end of this year

  • Page 23 of 70

    Month Seminar topics

    Implementation Time Description

    November Fire-fighting drill

    HSE Department

    Dec 2013 Fire watch man and safety staff operate

    fire water truck periodically December Zero incident

    strategy

    HSE Department Nov 2013 to

    Dec 2013 Prevention all accident until end of this year

    December Environment management

    Whole of the site

    Dec 2013 Hazardous waste management according

    to procedure

  • Page 24 of 70

    2.2.10 Safety Award

    Some 20-50 workers received Safety Awards each month during the reporting period. HDEC give out these safety award certificates and 100.000 VND on each first day of a month.

  • Page 25 of 70

    3. ENVIRONMENTAL QUALITY MONITORING

    3.1 Air quality, Noise and Vibration Monitoring

    3.1.1 Monitoring of Air quality

    The monitoring location, monitoring parameters, monitoring equipment and analyzed methods

    for air quality monitoring are presented in Table 3.1

    Table 3.1: The monitoring location, monitoring parameters and monitoring equipment and analyzed

    methods for air quality monitoring

    Monitoring

    Location

    Monitoring

    parameter

    Equipment for

    monitoring

    Monitoring and Analyzed

    Method

    At two

    residential sites

    selected in EMP.

    Sampling and

    analysis for:

    + TSP (1 hr and 24

    hrs)

    + PM10 (1 hr and

    24 hrs)

    Compared to QCVN

    05:2013/BTNMT National technical

    Regulations on

    Ambient Air

    Quality.

    + Air Sampler SL-20

    SIBATA/Japan

    + Air Sampler SL-

    15P SIBATA/Japan

    + Air Sampler

    MinivolTM

    TAS Metrics/ USA

    - Follow the validity Viet Nam

    Standard for environment in

    TCVN 5067:1995 Air quality Weigh Method for determination of suspended

    dusts content.

    Monitoring results on air quality and analysis are presented in Table 3.2

    Table 3.2: Monitoring results of TSP and PM10

    Monitored Points

    Results (unit: g/m3)

    TSP 1hr

    (17h0018h00)

    TSP 24hr PM10 1hr

    (17h00 18h00)

    PM10 24hr

    The 7th mobilization: from 10th to 11th July 2013:

    KK1

    437

    288

    213

    171

    KK2

    405

    272

    187

    155

    The 8th

    mobilization: from 15th

    to 16th

    August 2013:

    KK1

    491

    297

    231

    193

    KK2

    442

    281

    217

    175

    The 9th

    mobilization: from 13th

    to 14th

    September 2013:

    KK1

    335

    249

    197

    168

    KK2

    317

    223

    178

    159

    The 10th

    mobilization: from 25th

    to 26th

    October 2013:

    KK1

    443

    298

    184

    162

  • Page 26 of 70

    Monitored Points

    Results (unit: g/m3)

    TSP 1hr

    (17h0018h00)

    TSP 24hr PM10 1hr

    (17h00 18h00)

    PM10 24hr

    KK2

    451

    315

    192

    178

    The 11th

    mobilization: from 21st

    to 22nd

    November 2013:

    KK1

    289

    229

    157

    145

    KK2

    273

    214

    168

    127

    The 12th

    mobilization: from 19th

    to 20th

    December 2013:

    KK1

    296

    231

    177

    151

    KK2

    281

    222

    176

    137

    QCVN

    05:2013/BTNMT

    300 200 - 150

    Figure 3.1 compares results of 6 monitoring times.

    g/m3

    600

    500

    400

    300

    200

    100

    KK1 KK2

    350

    300

    250

    200

    QCVN 05:2013/BTNMT

    150

    100

    50

    KK1 KK2

    0

    The 7th The 8th The 9th The 10th The 11th The 12th

    0

    The 7th The 8th The 9th The 10th The 11th The 12th

    TSP 1hr (17h00-18h00) TSP 24hr

    250

    200

    KK1 KK2

    QCVN 05:2013/BTNMT

    250

    200

    KK1 KK2

    150

    150 QCVN 05:2013/BTNMT

    100 100

    50 50

    0

    The 7th The 8th The 9th The 10th The 11th The 12th 0

    The 7th The 8th The 9th The 10th The 11th The 12th

    PM10 1hr (17h00-18h00) PM1024hr

  • Page 27 of 70

    Figure 3.1 The results of 6 monitoring times.

    Assessment of the monitoring results:

    Through 6 monitoring times during 2 days each in July, August, September, October, November,

    December 2013, the results show that:

    - The monitoring results for average 1 hr TSP at 2 monitoring points KK1 and KK2 in the

    all four monitoring times (July, August, September and October) are higher than the

    limited value in QCVN05:2013/BTNMT National Technical Regulations on Ambient

    Air Quality(higher than 1,05 1,63 times). Especially the 15th of August monitoring

    times, the monitoring results for average 1 hr TSP at 2 monitoring points KK1 and KK2

    are higher than the limited value in QCVN05:2013/BTNMT National Technical

    Regulations on Ambient Air Quality (higher than 1,47 1,63 times).

    - The monitoring results for average 24 hr TSP at 2 monitoring points KK1 and KK2 in all

    six mobilizations are higher than the limited value in QCVN05:2013/BTNMT National

    Technical Regulations on Ambient Air Quality (higher than 1,07 1,57 times). Especially

    the 25th of October monitoring times , the monitoring results for average 24 hr TSP at 01

    monitoring point KK2 are higher than the limited value (1,57 times).

    - The monitoring results for average 24 hr PM10 at monitoring points KK1 and KK2 in all

    six mobilizations are approximations and higher than the limited value in

    QCVN05:2013/BTNMT National Technical Regulations on Ambient Air Quality (higher

    than 0,91 1,28 times).

    - Comparison of monitoring results between KK1and KK2 shows that KK1 has higher

    concentrations of air pollutants than those at KK2, because the population density and

    roads in coal mines at KK1 is higher than that at KK2.

    - The time that concentrations of average 1 hr TSP and average 1 hr PM10 at 2 monitoring

    points reach maximum is the rush hour when traffic activities are the highest (17h00

    18h00).

    - The weather in Mong Duong: During the 2 monitoring times in 2013 (September and

    November) is rain, in the 4 monitoring times remaining ( July, August, October and

    December) is sunny, dry.

    3.1.2 Noise Monitoring

    The monitoring location, monitoring parameters, monitoring equipment and analyzed methods

    for noise monitoring are presented in Table 3.3

  • Page 28 of 70

    Table 3.3: The monitoring location, monitoring parameters and monitoring equipment and analyzed

    methods for noise monitoring

    Monitoring

    Location

    Monitoring

    parameter

    Equipment for

    monitoring

    Monitoring and

    Analysist

    Method

    At two

    residential sites

    selected in EMP.

    Compared with

    Equivalent acoustic

    level A, LeqdBA.

    Integrating-

    Averaging Sound

    level meter, Type

    6226 ACO/Japan.

    Follow the Viet Nam

    Standard for environment

    TCVN 7878-1: 2008 (ISO

    1996-1: 2003); TCVN

    7878-2: 2010 (ISO 1996-

    QCVN 2: 2003).

    26:2010/BTNMT National technical Regulations on Noise.

    + At 01 construction site where workers are impacted

    Monitoring results for Noise level are presented Table 3.4

    Table 3.4: Monitoring results for Noise at residential sites

    Monitored Points

    Results LAeq (1h) (dBA)

    7h 8h 17h 18h 22h 23h

    The 7th mobilization: from 10th to 11thJuly 2013:

    KK1 69,7 70,8 63,7

    KK2 59,8 61,2 56,4

    The 8th mobilization: from 15th to 16thAugust 2013:

    KK1 69,5 72,4 66,1

    KK2 57,6 59,4 53,7

    The 9th mobilization: from 13th to 14thSeptember 2013:

    KK1 68,7 70,8 66,9

    KK2 62,7 64,1 57,1

    The 10th mobilization: from 25th to 26th October 2013:

    KK1 69,1 70,3 65,8

    KK2 63,1 64,5 58,2

    The 11th mobilization: from 21st to 22nd November 2013:

    KK1 62,5 68,7 59,6

    KK2 60,7 65,9 57,3

  • Page 29 of 70

    Monitored Points

    Results LAeq (1h) (dBA)

    7h 8h 17h 18h 22h 23h

    The 12th mobilization: from 19th to 20th December 2013:

    KK1 63,1 69,3 60,1

    KK2 62,2 66,4 58,1

    QCVN

    26:2010/BTNMT

    70 70 55

    Figure 3.2 compare results of 6 monitoring times

    dBA 80

    70

    60

    50

    40

    30

    20

    10

    0

    80 KK1(7h-8h) KK2(7h-8h) KK1(17h-18h) KK2(17h-18h)

    QCVN 26:2010/BTNMT 70

    60

    50

    40

    30

    20

    10

    0

    KK1 KK2

    QCVN 26:2010/BTNMT

    The 7th The 8th The 9th The 10th The 11th The 12th The 7th The 8th The 9th The 10th The 11th The 12th

  • Page 30 of 70

    LAeq1hr (7h-8h) v (17h-18h) LAeq1hr (22h-23h)

    Figure 3.2 The results of 6 monitoring times

    Monitoring results for Noise at working site are presented Table 3.5

    Table 3.5: Monitoring result for Noise at the working site

    Monitored Points

    Results LAeq (1h) dB(A)

    9h 10h

    The 7th

    mobilization: from 10th

    to 11th

    July 2013:

    KK3

    73,7

    The 8th

    mobilization: from 15th

    to 16th

    August 2013:

    KK3

    73,2

    The 9th

    mobilization: from 13th

    to 14th

    September 2013:

    KK3

    78,1

    The 10th

    mobilization: from 25th

    to 26th

    October 2013:

    KK3

    77,6

    The 11th

    mobilization: from 21st

    to 22nd

    November 2013:

    Monitored Points

    Results LAeq (1h) dB(A)

    9h 10h

    KK3

    75,8

    The 12th

    mobilization: from 19th

    to 20th

    December 2013:

    KK3

    76,4

    Figure 3.3 compares results of 6 noise monitoring times at working sites .

    dBA 79

    78

    77

    76

    75

    74

    73

    72

    71

    70

    The 7th The 8th The 9th The 10th The 11th The 12th

  • Page 31 of 70

    LAeq1hr (9h-10h)

    Figure 3.3 The results of 6 monitoring times

    Assessment of noise monitoring results:

    Through 6 monitoring times during 2 days each in July, August, September, October, November,

    December 2013, the results show that:

    - The monitoring results for noise in the daytime of 7h - 8h during the period of 6h - 21h at KK1 and KK2 are lower than the limited value in QCVN 26:2010/BTNMT National Technical Regulations on Noise; of 17h - 18h during the period of 6h - 21h at KK1 are

    approximate and higher than (about 0,72,6 dBA) the limited value in QCVN 26:2010/BTNMT,at KK2 are lower than the limited value in QCVN 26:2010/BTNMT .

    - The monitoring results for noise in the nighttime of 22h 23h during the period of 21h-

    6h, at KK1, monitored point about 7m from the road are higher than (about 4,6-11,9 dBA) the

    limited value in QCVN 26:2010/BTNMT National Technical Regulations on Noise; at KK2,

    monitored point about 20 m from the road, are approximate and higher than (about 1,4 - 3,2

    dBA) the limited value in QCVN 26:2010/BTNMT National Technical Regulations on Noise.

    Caused by transport activities increased on the old 18A road at night such as: carrying coal,

    materials.

    At the working site: Through 6 monitoring times during 2 days each July, August, September, October, November, December 2013, the results show that:

    - The monitoring results for noise at working site in all six monitoring times, noise level monitored in 1 hours at boiler area is about 73,2 78,1 dB(A). If compare with allowable noise level at working place the lower than the limited value in TCVN 3985:1999 (85 dB).

    3.1.3 Vibration Monitoring

    The monitoring location, monitoring parameters, monitoring equipment and analyzed methods

    for vibration are presented in Table 3.6

    Table 3.6: The monitoring location, monitoring parameters and monitoring equipment and analyzed

    methods for vibration monitoring

    Monitoring

    Location

    Monitoring

    parameter

    Equipment for

    monitoring

    Monitoring and Analyst Method

    At two

    residential sites

    selected in

    EMP.

    Vibration

    Acceleration (dB).

    Compared with

    QCVN

    27:2010/BTNMT National technical

    Regulations on

    Vibration.

    Vibration meter

    TYPE 3233 ACO/Japan.

    Follow the validity Viet Nam

    Standard for environment in TCVN

    6963:2001 Vibration and shock Vibration emitted by construction

    works and factories Method of measurement.

    Monitoring for vibration level was conducted at the same time with noise monitoring at

    monitoring points. Vibration is monitored with 3 directions and the highest result is used to

    compare with the regulation.

  • Page 32 of 70

    Table 3.7: Monitoring results for vibration at residential sites

    Monitored Points

    Results, dB (1h)

    7h 8h 17h 18h 22h 23h

    The 7th

    mobilization: from 10th

    to 11thJuly 2013:

    KK1 58,1 50,5 41,7

    KK2 48,3 43,4 37,6

    The 8th

    mobilization: from 15th

    to 16th

    August 2013:

    KK1 48,3 49,1 46,8

    KK2 40,4 41,2 38,2

    The 9th

    mobilization: from 13th

    to 14th

    September 2013:

    KK1 46,7 48,3 40,4

    KK2 40,1 45,6 36,8

    The 10th

    mobilization: from 25th

    to 26th

    October 2013:

    KK1 47,1 48,5 41,2

    KK2 41,3 43,2 37,6

    The 11th

    mobilization: from 21st

    to 22nd

    November 2013:

    KK1 42,3 44,7 40,8

  • Page 33 of 70

    50

    Results, dB (1h)

    Monitored Points 7h 8h

    17h 18h

    22h 23h KK2 39,5 41,3 36,8

    The 12th

    mobilization: from 19th

    to 20th

    December 2013:

    KK1 42,8 45,6 41,1

    KK2 40,8 41,9 38,5

    QCVN 27:2010/BTNMT

    (6h 22h)

    75

    -

    Figure 3.5 compares results of 6 monitoring times

    70

    dB KK1(7h-8h) KK2(7h-8h) KK1(17h-18h) KK2(17h-18h)

    60 45 40

    50 35

    40 30

    25

    30 20

    20 15

    10 10

    5

    0 0

    The 7th The 8th The 9th The 10th The 11th The 12th

    KK1 KK2

    The 7th The 8th The 9th The 10th The 11th The 12th

    Vibration 1hr (7h-8h) v (17h-18h) Vibration 1hr (22h-23h)

    Figure 3.5 The results of 6 vibration monitoring times

    Assessment of the vibration monitoring results: Through 6 monitoring times during 2 days each in July, August, September, October, November, December 2013, the results show

    that:

    - Monitoring results for vibration level at 2 sites during the period of 6h 21h are lower than the limited value in QCVN 27:2011/BTNMT National Technical Regulations on Vibration.

    - Construction activities of Mong Duong 1 Thermal Power Plant are implemented during the day time, therefore no vibration is created during the nighttime, from 21h-6h.

    3.1.4 Overall Assessment

    Implementation of Environmental Management Measures by the Construction contractor has

    followed the guidelines under the EMP

    Problems Identified and Actions Recommended

    During the second 6 months in 2013, construction activities at the site of Mong Duong 1

    were more intense than during previous monitoring sessions due to construction activities

    now overlapping with erection activities. Therefore, during this period, overall construction

    activities had an impact on the air environment (dust) and noise to the nearby residential

    areas.

  • Page 34 of 70

    02 monitoring stations KK1 and KK2 located at residential areas selected in EMP are not

    impacted during the construction phase of Mong Duong 1 Thermal Power Plant, but may

    have an impact during the operation phase, particularly from the high pollution sources

    (boiler, stack etc.).

    Air pollution sources (mainly dust) towards the more dense populated residential areas of

    Mong Duong Ward which is near the 2 sides of the old No.18A road are due to transport

    activities (carrying coal and materials, cars, motorcycles sorting out coal plant (near KK2),

    coal discharge area (especially when the wind blows from south-east direction). However,

    better quality of the old No.18A road and community awareness of Mong Duong ward

    residents was higher so the level of air pollution mitigation was better ( the old 18A road is

    cleaned and watered regularly by local people).

    Comparison monitoring results (dust) between the first 6 months of 2013 and the second 6

    months of construction phase in 2013 shows that the second 6 months of 2013 had a higher

    concentration of air pollutants than the 6 months previous. This is mainly caused by

    increased transport activities on the new and old No.18 road which influence the resident

    area of Mong Duong, especially when the weather in Mong Duong is sunny, hot and dry.

    The social environment due to the gathering of large work force at Mong Duong precinct,

    which cause the problems regarding to services, food provision etc need to be further

    observed

    3.2 Water Quality Monitoring

    Monitoring is implemented inside and outside of Mong Duong 1 Thermal Power Plant project

    within 5km radius

    The report on the actual state of the water environment at Mong Duong 1 Thermal Power Plant

    project has been prepared with the following purposes:

    Domestic sewage water, grey water and subsequence discharge that would impact on ambient

    surface water. Thus, during the pre-construction process, samples of 16 sensitive surface water

    sites and 20 sensitive underground water sites were selected. The results of the original samples

    were carefully recorded (as baseline data) to assess possible changes of the water quality during

    construction. The data collected during the preconstruction phase will be compared to the data

    obtained during construction and operation to establish sources of pollution and recommend

    solutions to reduce possible impacts.

    3.2.1 Monitoring parameters and procedures Monitoring parameters:

    Ambient surface water: Temperature, pH, TSS, DO, COD, BOD5, Cl-, NH4+, heavy metal (As, Cr, Cd, Cu, Pb, Zn, Ni, Hg, Fe, Mn, Se), oil and grease, Coliform, T-N, T-P.

    Underground water: Temperature, pH, TSS, COD, Cl-, NH4+, NO3-, SO42-, heavy metals (As, Cr, Cd, Cu, Pb, Zn, Ni, Hg, Fe, Mn, Se), VOC, SVOC, TPH, oil and grease

    and Coliform.

    Monitoring procedure

  • Page 35 of 70

    Sampling, analyzing in

    Laboratory

    Collecting information relating to the project. Analyzing samples in the laboratory Summarize and handling analytical data. Assessing monitoring results. Prepare evaluation report of water conditions

    Propose treatment measures to minimize water environment pollutants (Figure 3.1)

    Figure 3.1: Water quality environmental monitoring procedure

    Water Environment

    monitoring

    Measures at Site

    Synthesize and Handle

    Data

    Assess monitoring results

    Propose treatment measures to

    minimize pollutants.

    Preparing report

  • Page 36 of 70

    3.2.2 Inspection Activities

    Monitoring sites

    Monitoring site is described in Figure 3.7 below and co-ordinates of sensitive areas are

    shown in the Annex

    Figure 3.2: Monitoring Sites

    Environmental condition at Monitoring times

    No rain

    No significant events at coastal water sampling times

    No significant events at underground water sampling times

    Drilling Well Nos. 1, 2, 3, 4, 6, 8 were available for water sample monitoring

  • Page 37 of 70

    3.2.3 Monitoring results and Assessment

    Surface water quality

    Water samples were collected from surface water bodies at the project site and its

    surrounding area based on Mong Duong and De Dach River to establish the baseline database for

    the surface water quality. Eight water samples were collected at the selected locations. The

    locations of the surface water sampling points are shown in the Figure 3.7. The coordinates of

    the surface water sample points are shown in Table 3.8

    Table 3.8: Coordinates of surface water samples

    No.

    Item

    Co-ordinate

    Description X Y

    Surface water

    1

    SW-01 10702100 E 2100410 N

    Mong Duong river

    2

    SW-02 10702101 E 2100429 N

    Mong Duong river

    3

    SW-03a 10702108 E 2100408 N

    Mong Duong river

    4

    SW-06 10702125 E 2100512 N

    De Dach river

    5

    SW-07 10702147 E 2100504 N

    De Dach river

    6

    MD-1 107020.170 E 21

    003.800 N

    Mong Duong river

    7

    DD-1 107020.934 E 21

    004.273 N

    De Dach river

    8

    DD-4 107022.013 E 21

    005.147 N

    De Dach river

  • Page 38 of 70

    The surface freshwater resources in the areas affected by the Mong Duong power plant project

    development, consist of the lower reaches of the western Mong Duong River which discharges at

    the plant site, the lower estuary of the small De Dach River to the north, and the distant Thac

    Thay River to the north of Cam Hai commune. Mong Duong River drains a small, sparsely

    populated basin from the west that is dominated by an active open pit coal mine The River

    passes through Mong Duong town just before discharging into the Luong Gac channel at the

    plant site. The analytical results of samples are summarized in the Table 3.9

    Table 3.9: Monitoring and analyzing results of surface water

    P

    ara

    met

    er

    Sampling site

    QCVN

    08:2008

    BTNMT

    (B2)

    Unit

    SW-

    01

    SW-

    02

    SW-

    03a

    SW-

    06

    SW-

    07

    MD-

    01

    DD-1

    DD-4

    On-site monitoring results

    Temp. 0C

    28.37

    28.04

    27.79

    27.96

    27.07

    29.49

    28.15

    29.14

    -

    pH

    -

    7.00

    7.35

    6.72

    6.73

    7.05

    6.13

    5.72

    6.90

    5.5-9

    DO

    mg/l

    4.7

    5.3

    5.1

    4.3

    5.1

    3.9

    4.3

    4.8

    2

    Laboratory monitoring results

    TSS

    mg/l

    28.25

    19.44

    15.21

    20.95

    18.00

    38.69

    22.60

    19.76

    100

    COD

    mg/l

    9.8

    9.8

    8.9

    11.5

    10.2

    16.8

    12.0

    10.7

    50

    BOD

    mg/l

    6.05

    5.62

    7.05

    7.18

    7.50

    8.53

    7.63

    6.79

    25

    Cl-

    mg/l

    254.34

    344.05

    587.45

    644.36

    795.82

    169.96

    287.09

    372.91

    -

    NH4+

    mg/l

    0.358

    0.283

    0.260

    0.280

    0.234

    0.306

    0.287

    0.262

    1

    As

    mg/l

    0.0034

    0.0050

    0.0036

    0.0028

    0.0038

    0.0038

    0.0036

    0.0030

    0.1

    Cr

    mg/l

    0.0025

    0.0020

    0.0018

    0.0028

    0.0019

    0.0031

    0.0029

    0.0027

    -

    Cd

    mg/l

    0.0006

    0.0009

    0.0004

    0.0008

    0.0005

    0.0015

    0.0006

    0.0004

    0.01

    Cu

    mg/l

    0.0044

    0.0044

    0.0048

    0.0138

    0.0084

    0.0263

    0.0149

    0.0098

    1

    Pb

    mg/l

    0.0072

    0.0053

    0.0051

    0.0067

    0.0066

    0.0073

    0.0056

    0.0059

    0.05

    Zn

    mg/l

    0.0485

    0.0533

    0.0471

    0.0580

    0.0527

    0.0740

    0.0715

    0.0592

    2

    Ni

    mg/l

    0.0027

    0.0025

    0.0017

    0.0021

    0.0015

    0.0024

    0.0020

    0.0014

    0,1

    Hg

    mg/l

    0.0004

    0.0003

    0.0003

    0.0007

    0.0005

    0.0008

    0.0005

    0.0003

    0.002

    Fe

    mg/l

    0.1817

    0.1529

    0.0970

    0.1307

    0.1212

    0.3172

    0.1605

    0.1082

    2

  • Page 39 of 70

    P

    ara

    met

    er

    Unit

    Sampling site

    QCVN

    08:2008

    BTNMT

    (B2)

    SW-

    01

    SW-

    02

    SW-

    03a

    SW-

    06

    SW-

    07

    MD-

    01

    DD-1

    DD-4

    Mn

    mg/l

    0.2546

    0.2164

    0.1456

    0.2524

    0.1895

    0.6253

    0.3362

    0.1614

    -

    Se

    mg/l

    0.0009

    0.0006

    0.0007

    0.0006

    0.0072

    0.0006

    0.0008

    0.0003

    -

    Oil and

    Grease

    mg/l

    0.286

    0.127

    0.053

    0.148

    0.086

    0.269

    0.152

    0.074

    0.3

    Coliform

    MPN/100ml

    587

    462

    570

    680

    586

    820

    690

    561

    10000

    T-N

    mg/l

    1.61

    0.82

    0.55

    2.13

    0.19

    3.23

    1.72

    1.35

    -

    T-P

    mg/l

    0.355

    0.324

    0.281

    0.473

    0.408

    0.378

    0.374

    0.347

    -

    Analytical results for collected surface water samples show:

    a. pH value of almost samples are within limits permitted by QCVN 08:

    2008/BTNMT (B2);

    b. NH4+

    concentration at sampling sites are within limit permitted by QCVN

    10:2008/BTNMT.

    c. Heavy metal such as As, Hg, Cd, Pb are harmful to humans and other living organisms.

    However, concentrations of metals in the samples are very low, there is not much in

    Cd, Hg; measured values are within the limits permitted by QCVN10:2008/BTNMT

    (others column).

    d. Fe concentrations of 8 stations are lower than QCVN 10:2008/BTNMT.

    e. All of oil and grease concentration at surface water sampling sites are within limits

    when compared with QCVN 08:2008/BTNMT (B2 column), those concentrations

    are not much when comparing with QCVN 08:2008/BTNMT (B2 column)

    f. Coliform concentrations of 8 surface water samplings are within limits when

    compared with QCVN 08:2008/BTNMT (B2 column).

    Coastal water quality

    The Mong Duong 1 thermal power plant is situated in the northwest of Bai Tu Long in northern

    Vietnam. The coastal zone in this area is typical of Vietnam, which is dominated by vast sandy

    sediment deposits that extend from well above the high water mark to beyond 5km offshore.

    Coastal water samples were collected at four zones that potentially could be affected in different

    ways by the power plan development: (1) near-shore area of Cam Hai commune; (2) at the ash

    pond; (3) in the Van Don district (island group) about 1km east of the project site and (4) in the

    Luong Gac channel from Cam Hai commune south to Cua Ong.

  • Page 40 of 70

    At the three points (LG-1; LG-3; LG-4) impact assessment of transportation activities to coastal

    water environment is performed. Eight coastal water samples were collected at selected

    locations. The locations of coastal water sampling are shown in the Figure 3.2. The coordinates

    of the coastal water samples are shown in Table 3.10

    Table 3.10: Coordinates of coastal water samples

    No.

    Item

    Co-ordinate

    Description X Y

    Coastal water samples

    1 SW-3b 10702127 E 2100422 N Mng Dng River

    2 SW-04 10702150 E 2100420 N Mng Dng River

    3 SW-05a 10702111 E 2100456 N D Dch River

    4 SW-05b 10702139 E 2100434 N Mng Dng River

    5 SW-08 10702119 E 2100539 N Cam Hai Coastal zone

    6 LG-1 107022.595 E 21

    005.110 N Luong Gac

    7 LG-3 107021.275 E 21

    004.611 N Luong Gac

    8 LG-4 107022.201 E 21003.855 N Luong Gac

    The lower reaches of the river starting at Mong Duong town are brackish and strongly influenced

    by the tidal cycle of Luong Gac and Bai Tu Long. The delta at the mouth of the river below

    Mong Duong town experiences annual flooding resulting from the combination of high runoff

    during the rainy season and spring (full moon) tides. Turbidity and suspended sediment loads in

    the river are high, which is caused by land erosion from human activity (open-pit coal mining)

    and the natural sandy soils of the region. The monitoring and analyzing results of coastal water

    samples are presented in Table 3.11.

  • 2nd Semi-annual Environmental Monitoring Report

    Mong Duong (2 x 500MW) Thermal Power Plant Project

    Table 3.11: Monitoring and analyzing results of coastal water samples

    N

    o.

    P

    ara

    met

    er

    Unit

    Sampling site

    QCV

    N

    10:20

    08/

    BTN

    MT

    (Othe

    r)

    SW-

    3b

    SW-

    04

    SW-

    05a

    SW-

    05b

    SW-

    08

    LG-1

    LG-3

    LG-4

    On-site monitoring result

    Temp. 0C

    27.33

    27.36

    27.22

    27.64

    27.07

    26.77

    27.21

    27.50

    -

    pH

    -

    8.17

    8.13

    7.91

    8.32

    8.04

    8.43

    8.13

    8.06

    6.5-

    8.5

    DO

    mg/l

    5.3

    5.6

    5.1

    5.4

    5.8

    5.4

    6.4

    5.6

    -

    Laboratory result assessment of coastal water

    TSS

    mg/l

    10.99

    8.50

    10.27

    9.90

    8.94

    8.75

    8.40

    12.32

    -

    COD

    mg/l

    7.7

    7.8

    8.9

    8.1

    6.2

    7.5

    7.4

    9.2

    -

    BOD

    mg/l

    5.98

    5.43

    5.58

    6.67

    3.94

    4.80

    7.03

    5.86

    -

    Cl-

    mg/l

    1156.

    20

    1223.

    87

    1250.

    37

    12113.

    00

    1267.

    13

    1215.

    70

    1204.

    28

    1223.

    10

    -

    NH4

    +

    mg/l

    0.217

    0.202

    0.189

    0.169

    0.180

    0.175

    0.146

    0.172

    0.5

    As

    mg/l

    0.003

    8

    0.003

    0

    0.003

    4

    0.0041

    0.003

    2

    0.003

    9

    0.003

    5

    0.002

    6

    0.05

    Cr

    mg/l

    0.001

    9

    0.001

    6

    0.002

    0

    0.0016

    0.002

    0

    0.002

    1

    0.001

    7

    0.001

    6

    -

    Cd

    mg/l

    0.000

    4

    0.000

    6

    0.000

    2

    0.0006

    0.000

    3

    0.000

    5

    0.000

    2

    0.000

    4

    0.005

    Cu

    mg/l

    0.003

    8

    0.004

    8

    0.002

    9

    0.0032

    0.004

    7

    0.005

    7

    0.004

    4

    0.004

    3

    1

    Pb

    mg/l

    0.005

    9

    0.005

    7

    0.004

    2

    0.0042

    0.006

    1

    0.005

    2

    0.005

    1

    0.006

    6

    0.1

    Zn

    mg/l

    0.044

    9

    0.047

    1

    0.037

    7

    0.0423

    0.047

    9

    0.039

    0

    0.047

    7

    0.037

    5

    2

    Ni

    mg/l

    0.001

    4

    ND

    0.001

    8

    ND

    ND

    ND

    ND

    ND

    -

    Hg

    mg/l

    0.000

    3

    0.000

    2

    0.000

    5

    0.0006

    0.000

    3

    0.000

    2

    0.000

    3

    0.000

    2

    0.005

    Page 40 of 70

  • 2nd Semi-annual Environmental Monitoring Report 2013

    Mong Duong (2 x 500MW) Thermal Power Plant Project

    Page 41 of 70

    N

    o.

    P

    ara

    met

    er

    Unit

    Sampling site

    QCV

    N

    10:20

    08/

    BTN

    MT

    (Othe

    r)

    SW-

    3b

    SW-

    04

    SW-

    05a

    SW-

    05b

    SW-

    08

    LG-1

    LG-3

    LG-4

    Fe

    mg/l

    0.091

    1

    0.079

    2

    0.079

    6

    0.0739

    0.071

    1

    0.101

    9

    0.097

    4

    0.081

    1

    0.3

    Mn

    mg/l

    0.165

    7

    0.092

    2

    0.077

    0

    0.0627

    0.052

    2

    0.024

    4

    0.021

    1

    0.022

    2

    0.1

    Se

    mg/l

    0.000

    5

    0.000

    6

    0.000

    7