1
Objectives After testing the initial Norvarg discovery well (operated by Total in the Norwegian Barents Sea) the vision of the reservoir was for large channel sands having better reservoir properties than tested in the first well – the Norvarg 2 appraisal well was planned with the objective of investigating uncertainties regarding reservoir deliverability, compartmentalisation risk and the fluid contacts A particular objective was to demonstrate the contribution of other geological facies by performing a long duration pressure build-up beyond the end of the drill stem test (DST) period To minimise costs, it was a requirement for the well to be permanently abandoned at the end of the DST without any requirement for a further semi-sub based well intervention Expro Excellence Three CaTS wireless transmitting gauges were deployed externally mounted on the tailpipe below a permanent packer and above the TCP guns The DST string was stabbed into the packer and a conventional short duration well test performed At the end of the final pressure build-up (PBU) a sliding sleeve valve in the lower completion was activated to isolate the reservoir zone being monitored from the upper DST string A well kill was then performed above the packer, the DST string recovered to surface and the well plugged and abandoned by setting cement plugs in accordance with industry legislation A CaTS subsea receiver assembly featuring dual redundancy capability was deployed from the rig on drill pipe and located on the abandoned well head Value to client High quality pressure build-up data was recovered from all three gauges for a period of nine months after well plug and abandonment The subsea receiver equipment and final well head retrieval was achieved cost effectively using services deployed from a supply boat Interpretation of the PBU data identified two no-flow boundaries 130m and 280m from the wellbore that were not observed during the course of the normal DST period The vision for the large channel sands was more likely to be a channel belt with individual smaller channels having internal flow barriers, meaning that additional wells would have been required to develop the field compared to what was known prior to collecting the data Contact For further information, please contact: [email protected] www.exprogroup.com/wws / Expro Excellence Wireless Well Solutions Expro Excellence exprogroup.com Wireless Well Solutions CaTS™ wireless gauge technology detects flow barriers in the reservoir during extended post-abandonment pressure build-up monitoring Reducing uncertainty in connected volumes during Barents Sea appraisal CaTS gauges mounted on the tailpipe Test string configuration showing three CaTS gauges mounted on the tailpipe

Expro Excellence Wireless Well Solutions… · beyond the end of the drill stem test (DST) period • To minimise costs, it was a requirement for the well to be permanently abandoned

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Expro Excellence Wireless Well Solutions… · beyond the end of the drill stem test (DST) period • To minimise costs, it was a requirement for the well to be permanently abandoned

Objectives

• After testing the initial Norvarg discovery well(operated by Total in the Norwegian BarentsSea) the vision of the reservoir was for largechannel sands having better reservoirproperties than tested in the first well – theNorvarg 2 appraisal well was planned withthe objective of investigating uncertaintiesregarding reservoir deliverability,compartmentalisation risk and the fluidcontacts

• A particular objective was to demonstratethe contribution of other geological facies byperforming a long duration pressure build-upbeyond the end of the drill stem test (DST)period

• To minimise costs, it was a requirement forthe well to be permanently abandoned atthe end of the DST without any requirementfor a further semi-sub based wellintervention

Expro Excellence

• Three CaTS wireless transmitting gaugeswere deployed externally mounted on thetailpipe below a permanent packer andabove the TCP guns

• The DST string was stabbed into thepacker and a conventional short durationwell test performed

• At the end of the final pressure build-up(PBU) a sliding sleeve valve in the lowercompletion was activated to isolate thereservoir zone being monitored from theupper DST string

• A well kill was then performed above thepacker, the DST string recovered tosurface and the well plugged andabandoned by setting cement plugs inaccordance with industry legislation

• A CaTS subsea receiver assemblyfeaturing dual redundancy capability wasdeployed from the rig on drill pipe andlocated on the abandoned well head

Value to client

• High quality pressure build-up data wasrecovered from all three gauges for aperiod of nine months after well plug andabandonment

• The subsea receiver equipment and finalwell head retrieval was achieved costeffectively using services deployed from asupply boat

• Interpretation of the PBU data identifiedtwo no-flow boundaries 130m and 280mfrom the wellbore that were not observedduring the course of the normal DSTperiod

• The vision for the large channel sandswas more likely to be a channel belt withindividual smaller channels having internalflow barriers, meaning that additional wellswould have been required to develop thefield compared to what was known priorto collecting the data

ContactFor further information, please contact:

[email protected] www.exprogroup.com/wws

/ Expro ExcellenceWireless Well Solutions

Expro E x c e l l e n c e exprogroup.com Wireless Well Solutions

CaTS™ wireless gauge technology detects flow barriersin the reservoir during extended post-abandonmentpressure build-up monitoring

Reducing uncertainty in connectedvolumes during Barents Sea appraisal

CaTS gauges mounted on the tailpipe

Test string configuration showing threeCaTS gauges mounted on the tailpipe

WWSCS Norvarg Case Study_A4 16/11/2016 12:16 Page 1