1
Objectives In late 2012, General Electric (GE) challenged Expro’s subsea product line with delivering a complex deepwater (up to 1,700 meters) electro-hydraulic subsea safety system to be used in their West African operations, Block 15/06 – part of a contract with Eni Expro Excellence Production of a system satisfying design requirements and delivery in time for subsea operations commencing in 2014, delivered by a multinational team split over two locations – Aberdeen and Luanda Building a highly skilled operational team with an in depth knowledge of electro- hydraulic systems Reacting to an exceptional scenario when a complete landing string was lost overboard during severe Atlantic storms - Expro replaced the lost system in record time preventing any delay in the well completion program Final equipment testing coincided with the final commissioning of our new facility in Luanda, which required detailed planning to ensure the delivery of equipment and facilities were not compromised In June 2014 the subsea safety system was delivered on schedule and successfully completed a comprehensive set of acceptance tests before going operational Operations were conducted in an efficient manner optimising rig up time and efficiency Value to client Delivery of a complex, deepwater, electro- hydraulic subsea safety system with water depths of up to 1,700 meters, overcoming unique challenges Expro delivered the equipment on time, equipment running time exceeded targeted efficiency, and avoidance of non-productive time (NPT) during the execution of the work ENI has now started production of first oil from Block 15, with the field currently producing 45,000 barrels of oil per day, with an expected daily production of up to 100,000 forecast Block 15 discoveries were developed in an industry-leading timescale of only 44 months from the Declaration of Commercial Discovery Contact For further information, please contact: Colin Mackenzie Product Line Director, Subsea [email protected] www.exprogroup.com/subsea Expro overcame numerous challenges and mitigated risk with rapid deployment of original solutions including: Sourcing and securing fleet assets to deliver a replacement back-up landing string when the original was lost as the result of an extreme storm during shipment to Angola - Expro managed through rapid reallocation and procurement of resources without impacting other operational requirements An Expro first; the vertical testing of the back-up landing string as part of a system integration test alongside third-party equipment had never been done before at Expro’s Luanda facility, resulting in the implementation of new health and safety processes and procedures to ensure incident-free equipment verification Liaising with Eni and Saipem to implement/incorporate 40 critical actions required on the Scarabeo 9 rig prior to the Expro system being utilised offshore The expansion of our facilities and capability in Luanda to ensure first class service support during the full field development Subsea / Expro Excellence Expro’s subsea expertise delivers industry-leading deepwater electro-hydraulic subsea safety system in West Africa Subsea Expro Excellence exprogroup.com Exceeding our customers’ expectations was fundamental in our approach from concept to completion, reinforcing Expro’s high performance reputation. Even with a track record of over 30 successful completions prior to this project, the team overcame new challenges by implementing unique solutions, unparalleled engineering design, efficient testing schedules, and the expansion and redevelopment of Expro’s Angola facility. Colin Mackenzie Product Line Director Subsea ’’

Expro Excellence Subsea… · 2016. 7. 19. · engineering design, efficient testing schedules, and the expansion and redevelopment of Expro’s Angola facility. Colin Mackenzie

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

  • Objectives

    • In late 2012, General Electric (GE)challenged Expro’s subsea product line withdelivering a complex deepwater (up to1,700 meters) electro-hydraulic subseasafety system to be used in their WestAfrican operations, Block 15/06 – part of acontract with Eni

    Expro Excellence

    • Production of a system satisfying designrequirements and delivery in time forsubsea operations commencing in 2014,delivered by a multinational team split overtwo locations – Aberdeen and Luanda

    • Building a highly skilled operational teamwith an in depth knowledge of electro-hydraulic systems

    • Reacting to an exceptional scenario when acomplete landing string was lost overboardduring severe Atlantic storms - Exproreplaced the lost system in record timepreventing any delay in the well completionprogram

    • Final equipment testing coincided with thefinal commissioning of our new facility inLuanda, which required detailed planning to

    ensure the delivery of equipment andfacilities were not compromised

    • In June 2014 the subsea safety system wasdelivered on schedule and successfullycompleted a comprehensive set ofacceptance tests before going operational

    • Operations were conducted in an efficientmanner optimising rig up time and efficiency

    Value to client

    • Delivery of a complex, deepwater, electro-hydraulic subsea safety system with waterdepths of up to 1,700 meters, overcomingunique challenges

    • Expro delivered the equipment on time,equipment running time exceeded targetedefficiency, and avoidance of non-productivetime (NPT) during the execution of the work

    • ENI has now started production of first oilfrom Block 15, with the field currentlyproducing 45,000 barrels of oil per day, withan expected daily production of up to100,000 forecast

    • Block 15 discoveries were developed in anindustry-leading timescale of only 44months from the Declaration of CommercialDiscovery

    ContactFor further information, please contact:

    Colin MackenzieProduct Line Director, [email protected]/subsea

    Expro overcame numerous challenges and mitigated risk with rapid deployment of originalsolutions including:

    • Sourcing and securing fleet assets to deliver a replacement back-up landing string whenthe original was lost as the result of an extreme storm during shipment to Angola - Expromanaged through rapid reallocation and procurement of resources without impacting otheroperational requirements

    • An Expro first; the vertical testing of the back-up landing string as part of a systemintegration test alongside third-party equipment had never been done before at Expro’sLuanda facility, resulting in the implementation of new health and safety processes andprocedures to ensure incident-free equipment verification

    • Liaising with Eni and Saipem to implement/incorporate 40 critical actions required on theScarabeo 9 rig prior to the Expro system being utilised offshore

    • The expansion of our facilities and capability in Luanda to ensure first class service supportduring the full field development

    Subsea

    / Expro Excellence

    Expro’s subsea expertise deliversindustry-leading deepwater electro-hydraulicsubsea safety system in West Africa

    Subsea

    Expro Exce l lence exprogroup.com

    Exceeding our customers’expectations wasfundamental in ourapproach from concept tocompletion, reinforcingExpro’s high performancereputation. Even with atrack record of over 30successful completionsprior to this project, theteam overcame newchallenges byimplementing uniquesolutions, unparalleledengineering design,efficient testing schedules,and the expansion andredevelopment of Expro’sAngola facility.Colin Mackenzie Product Line DirectorSubsea ’’

    GE and Eni Case Study_A4 16/03/2015 08:30 Page 1