Upload
lesley-robbins
View
216
Download
2
Embed Size (px)
Citation preview
Content
Provides an overview of:
ACER Framework Guidelines
ENTSOG CAM Update
Potential key GB impacts
Summary & GB Stakeholder involvement
Framework Guideline
ACER final CAM Framework Guideline published 3rd Aug
ENTSOG original Code delivery date 27thJan 12
New Commission invitation to ENTSOG to deliver a CAM Code now extended to 9th March 12
Changes from Previous Version The relevant clauses shall be amended
within nine months after entry into force of the network code(s)
The standardisation is based on a daily capacity product’s duration from 5:00 to 5:00 UTC/GMT, or any other time period harmonised across the EU as defined by European Network of Transmission System Operators for Gas
At least 10 percent of the available firm capacity at each interconnection point shall be set aside for firm capacity services with a duration of less than one quarter
These rules on mandatory bundling also apply, to the extent that they are relevant, to secondary capacity markets
Sunset Clause revised:
• Parties to agree, NRAs to mediate
• Default rule in case users to not reach agreements
• Sanctions allowed by NRAs to enforce agreements
Commission Guidelines for tariff methodologies related to cross-border trade of natural gas or in the Framework Guidelines for network codes on rules regarding harmonised transmission tariff structures
Web-based platform for primary capacity allocation and secondary capacity trading
Timetable for the implementation of a single EU-wide platform required
European Network Code Development Process
Work programme
ENTSO Agency
Frameworkguidelines
Commission
Preparation of draft Network
CodeCommission
Agency
Comitology
Legally binding Network
Code
Commission
Stakeholder workshops
Consultation
Stakeholder Consultation &
workshops
DECC
GB CodeChange process
ENTSO EU Commission ACER (ERGEG/CEER)
StakeholderConsultation
CAM CodeCurrent Phase
CAM Consultation
Capacity Allocation Mechanism (CAM)
Entsog consultation on CAM draft EU code received 56 responses
GB well represented @10 respondents + Associations
Next Steps:
Publish analysis of responses – now completed 26th Sept
Continue stakeholder dialogue on key aspects
Sunset clause ‘default’ meeting 6th Oct (Brussels)
SJWS Stakeholder meeting planned for 20th Oct (Brussels)
The final EU code is still expected to be published in Jan 2012
Commission extended Code deadline until 9th March
ENTSOG may use additional timeline to carry out a short re-consultation period?
7
Key CAM Documents
Project Plan
Launch Document
All stakeholder (SJWS) meeting material
Draft CAM network code & supporting documents
Consultation responses &
Analysis report
Available from ENTSOG @
http://www.entsog.eu/publications/index_g_cam.html
8
ENTSOG Draft CAM Network Code Overview
In principle similar to GB Entry arrangements however:
Will have impacts to current arrangements
Guidelines applicable to Interconnection Points only
GB Regime
Governance
3rd package Code development / changes
Commitology timelines may not be appropriate for changes
Lighter change process needs consideration
Handbook approach?
UNC Code change process
T&C – Code amendment timeline 9 months
Implementation?
Different rules for IPs
UNC to differentiate between IPs / Non IPs?
Separate IP Code?
GB Regime
Sunset Clause
Within 5 years of the Code coming into force Users need to agree split of contracts either side of the IP to combine (bundle) capacity
ENTSOG to provide a default rule if capacity is not bundled
Does this effect capacity bookings (as already carried out via transparent auction process)?
GB Regime
Mandatory Bundling
Primary and secondary capacity via bundled products
No opportunity to book / trade at flange
Currently capacity sold in aggregate at an ASEP
Bundling applicable to IPs only (Bacton)
Current bookings out to 2025
Licence Baselines
Implications to interconnector operators
Art.22 exemptions
GB Regime
Enduring Exit
Need changes to regime to incorporate auctions
Auction Design
Different to GB Entry auction
Available capacity only no incremental (note: CEER Workplan 2012)
Differing Stakeholders views on key draft Code principles:
LT and MT products
Volume based auction single round, ascending clock multi round, others
ENTSOG Draft CAM Network Code
Standard Products
Concept similar to Entry but differences in the detail design
For LT - Users favoured Quarterly
GB Regime
Interruptible
No obligation to bundle
Only align interruptible services
Min obligation for day ahead (where firm sold out)
CMP v CAM interaction - within day nom
GB Regime
Incentive Regime
Buy back on a bundled capacity product?
Sale of non-obligated with a bundled product?
Interoperability (CET) 05:00 – 05:00 gas day alignment
CMP
Commission undertook consultation during summer
[New CMP document to be issued soon] - tbc
[Restriction of renom rights not mandatory] – tbc
[Oversell / Buy backs & incentives] - tbc
GB Regime
Other 3rd Package Code Interaction
Tariffs
Framework Guideline – then straight to commotology
Code development step not included
Implementation Timelines
Code changes
IT systems timeline
Joint platform(s) / Separate