4
STEEL CONSTRUCTION: FABRICATION AND ERECTION __________________________________________________________________________ 659 STEEL CONSTRUCTION: FABRICATION AND ERECTION Lecture 3.2.3: Erection III OBJECTIVE/SCOPE To give guidance on site welding and to discuss the operation of Quality Control and Safety Procedures on site. PREREQUISITES Lecture 3.2.1: Erection I Lecture 3.2.2: Erection II The following lectures might be helpful: Lectures 3.1: General Fabrication of Steel Structures Lecture 3.3: Principles of Welding Lecture 3.4: Welding Processes RELATED LECTURES Lecture 3.5: Fabrication/Erection of Buildings Lecture 15A.8: Offshore: Fabrication Lecture 15B.12: Introduction to Bridge Construction SUMMARY The lecture deals with the planning and careful preparation required for site welding; it also discusses the requirements of a Quality Control Programme and gives guidelines for improving site safety. 1. INTRODUCTION Lecture 3.2.2 discusses, in detail, the technical aspects of steelwork erection including the requirements for bolted connections. In some cases it may not be possible to use bolts and site welding may then be necessary. Where welding is used careful pre-planning is required, as outlined in Section 2 below.

Erection III

Embed Size (px)

DESCRIPTION

A detailed view design, production, and erection of steel structures according to the new European code EC 3.

Citation preview

  • STEEL CONSTRUCTION: FABRICATION AND ERECTION __________________________________________________________________________

    659

    STEEL CONSTRUCTION:

    FABRICATION AND ERECTION

    Lecture 3.2.3: Erection III

    OBJECTIVE/SCOPE

    To give guidance on site welding and to discuss the operation of Quality Control and Safety Procedures on site.

    PREREQUISITES

    Lecture 3.2.1: Erection I

    Lecture 3.2.2: Erection II

    The following lectures might be helpful:

    Lectures 3.1: General Fabrication of Steel Structures

    Lecture 3.3: Principles of Welding

    Lecture 3.4: Welding Processes

    RELATED LECTURES

    Lecture 3.5: Fabrication/Erection of Buildings

    Lecture 15A.8: Offshore: Fabrication

    Lecture 15B.12: Introduction to Bridge Construction

    SUMMARY

    The lecture deals with the planning and careful preparation required for site welding; it also discusses the requirements of a Quality Control Programme and gives guidelines for improving site safety.

    1. INTRODUCTION Lecture 3.2.2 discusses, in detail, the technical aspects of steelwork erection including the requirements for bolted connections. In some cases it may not be possible to use bolts and site welding may then be necessary. Where welding is used careful pre-planning is required, as outlined in Section 2 below.

  • STEEL CONSTRUCTION: FABRICATION AND ERECTION __________________________________________________________________________ 660

    It is always necessary to have quality control and safety procedures in force on site to ensure the successful completion of the project with minimum risk to the workforce. This lecture discusses these matters in detail, outlining the basis for a Quality Control Programme and giving guidelines on how risk to the workforce may be minimised.

    2. WELDING CONNECTIONS ON SITE It should be the aim of the designer to ensure that site connections are bolted wherever possible. There will be occasions, however, when site welding is necessary. In such cases, careful pre-planning will be required as follows:

    it will be necessary to provide for temporary alignment of the adjacent components which are to be welded together, and to hold them in position until they are welded. The methods adopted for alignment may have to be able to carry the weight of the components and in some cases a substantial load from the structure.

    safe means of access and a secure working platform must be provided for the welder and his equipment. The working platform may also have to incorporate weather protection, since wind, rain and cold can all adversely effect the quality of the weld.

    the design of the weld and the preparation of the components to be joined must take into account the position of those components in the structure; the method statement for the erection and the welding procedure for each joint must take all these factors into account.

    all the welding must be carried out by qualified welders in accordance with approved procedures.

    a detailed welding plan must be made for the more important structural joints as well as for structures to which special specifications apply.

    the earth return of the electric current must never be made through the steel frame of buildings, cranes, or through metallic parts of installations but must be directly connected to the construction part being welded.

    the surface of the zone to be welded must be clean and dry.

    3. QUALITY CONTROL

    3.1 Quality Assurance Manual

    The Quality Assurance Manual defines the appropriate procedures required to ensure that the finished product is up to specification. The staff responsible for the erection must be informed of all the variables affecting the quality of the assembly, so that they can be monitored.

    3.2 Quality Control Programme

    The Quality Control Programme is the particular programme, that has been specifically written for the job in hand.

    It is based on the following:

  • STEEL CONSTRUCTION: FABRICATION AND ERECTION __________________________________________________________________________

    661

    the Quality Assurance Manual. the General Contract for the Project. the general standards, applicable to the Project. the manufacturer's standards, procedures and specification.

    The Quality Control Programme will consist of:

    the site-organisation (in relation to Quality Control). the (written) procedures. the inspection programme.

    3.3 Inspection Programme

    The Inspection Programme is based on the erection plan and is complemented by written procedures and points of inspection. Its aim is to ensure good standards of workmanship.

    It may incorporate the following:

    Reference numbers for the work procedures. Revision numbers. Written procedures for:

    welding heat-treatment non-destructive testing alignment and plumbing tolerances HSFG bolting.

    4. SAFETY AT THE ERECTION-SITE By its very nature, erection of a structural frame is a process involving a certain amount of risk. The work is carried out at height and, until it has progressed to a certain point, there is nothing to which a safe working platform can be attached. In fact, it is true to say that the process of establishing a safe working platform can be as hazardous as the erection process itself; a possible solution may be to provide mobile access platforms if ground conditions permit.

    The object of a Safety Procedure is to ensure that everything possible is done to eliminate the risk of an accident. In order to achieve this objective the following procedures should be adopted:

    1. The safety procedure should be communicated to all concerned with its implementation by, for example, issuing abstracts or running courses. In practice, awareness of safety aspects can best be maintained by continually monitoring hazardous areas of the site (restricted areas, scaffolding, plant, etc.) to check that the appropriate restrictions are in force, and by informing the person in authority if potential hazards exist.

  • STEEL CONSTRUCTION: FABRICATION AND ERECTION __________________________________________________________________________ 662

    2. The necessary equipment should be made available on the site and maintained in good condition. This equipment ranges from safety helmets and belts, to ladders, working platforms and properly selected tools.

    3. The work should be organised so that as little as possible is done at height. The danger can be minimised as follows: by the use of sub-assembly techniques. by fixing ladders and working platforms onto the steelwork before it is lifted into place. by the early provision of horizontal access walkways. by the provision of temporary staircases or hoists, where appropriate.

    4. It should be ensured that all portable equipment such as gas bottles and welding plant, is firmly anchored while it is being used. Care should be taken to ensure that there are no flammable materials below on which sparks could fall.

    5. Finally, and fundamentally, the design should be done with safety in mind as follows:

    Splices should be positioned to give simple site connections, bearing in mind that these may have to be connected at height. Lifting cleats and connections for heavy and complex components should be incorporated, as far as possible, in the fabricated elements to be connected. Consideration should be given, at design stage, to incorporating cleats, brackets or holes in the fabrication to facilitate fixing of safety belts, safety nets and working platforms.

    5. CONCLUDING SUMMARY Careful pre-planning is required if site welding is necessary. A Quality Control Programme, involving inspections, should always be

    implemented. All site personnel should be made aware of the safety procedures. Safety procedures should be strictly enforced.

    6. ADDITIONAL READING 1. Arch, H., Erection, Chapters 33 - Steel Designers' Manual, Oxford, Blackwell

    Scientific Publications, 1992. 2. Thornton, W. A., "Design for Cost Effective Fabrication and Construction",

    Chapter 7.1 Constructional Steel Design, London, Elsevier Applied Science, 1992. 3. Miller, E. W., "Erection of Steel Structures", Chapter 7.2 Construction Steel

    Design, London, Elsevier Applied Science, 1992. 4. Potter, P. D., "Fast Steel Erection": Steel Fabrication Journal, No. 46, February

    1983, Australian Institute of Steel Construction. 5. The Steel Construction Industry Code of Practice for Sage Erection of Building

    Steelwork: Part 2 - Multi-storey Buildings and Structures, Australia, Australian Institute of Steel Construction, 1989.

    6. Eurocode 3: "Design of Steel Structures": ENV 1993-1-1: Part 1.1: General Rules and Rules for Buildings, CEN, 1992.

    Lecture 3.2.3: Erection IIIOBJECTIVE/SCOPEPREREQUISITESRELATED LECTURESSUMMARY1. INTRODUCTION2. WELDING CONNECTIONS ON SITE3. QUALITY CONTROL3.1 Quality Assurance Manual3.2 Quality Control Programme3.3 Inspection Programme

    4. SAFETY AT THE ERECTION-SITE5. CONCLUDING SUMMARY6. ADDITIONAL READING