Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Environmental Monitoring Report
Semiannual Report
Covering Jan-Jun 2016
MFF: Energy Sector Development Investment Program
(ESDIP) - Tranche 3, ADB Grant No. 0280
Gereshk Electricity Services Improvement Project Rehabilitation of Gereshk Hydro Power Plant
December 2016
Prepared by Da Afghanistan Breshna Sherkat (DABS - Electricity Utility) of Islamic Republic of
Afghanistan for the Asian Development Bank.
The Environmental Monitoring Report is a document of the Government of Afghanistan. The
views expressed herein do not necessarily represent those of ADB’s Board of Directors,
Management, or staff, and may be preliminary in nature.
Gereshk Electricity Services Improvement Project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant - 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 2 of 65
CURRENCY EQUIVALENTS
(as of December 2016)
Currency unit – AFN
AFN1.00 = $0.017
$1.00 = 66.50AFN
This semiannual environmental monitoring report is a document of the borrower. The views
expressed herein do not necessarily represent those of ADB's Board of Directors,
Management, or staff, and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any
designation of or reference to a particular territory or geographic area in this document, the
Asian Development Bank does not intend to make any judgments as to the legal or other
status of any territory or area.
Gereshk Electricity Services Improvement Project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant - 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 3 of 65
GLOSSARY
ADB : Asian Development Bank
NEPA : National Environment Protection Agency
DABS : Da Afghanistan Breshna Sherkat
DG : Diesel Generator
EA : Environmental Assessment
EHSSO : Environmental, Health & Social Safeguard Officer
EA : Environmental Assessment
EMP : Environmental Managemen t Plan
EMMP : Environmental Management and Monitoring Plan
ESA : Environmental Safeguard Asisstant
ESSO : Environmental and Social Safeguard Officer(PMO)
HPP : Hydro Power Plant
IEE : Initial Environmental Examination
kV : Kilo volt
MFF : Multitranche Financing Facility
PMC : Project Management Consultants
PMO : Program Management Office (of DABS)
PPE : Personal Protective Equipment
SHSA : Social and Health Safeguard Asisstant
SSA : Social Safeguard Asisstant (PMO)
SPS : Safeguard Policy Statement
TL : Transmission Line
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 4 of 65
Table of Contents 1. INTRODUCTION .......................................................................................................................... 7
1.1 Overview ................................................................................................................................ 7
1.2 Objective and Methodology ................................................................................................ 7
1.3 Project Scope of Works and Anticipated Environmental Framework ........................... 8
1.4 Contract for Consulting Services ....................................................................................... 9
1.5 Changes in the Project Organization and Environmental Team ................................. 10
1.6 Relationship with Contractors, Owner and Lender ....................................................... 10
1.7 Status of Work Activities during the Period Compared to Previous Period ............... 10
2. ENVIRONMENTAL MANAGEMENT PLAN/PROGRAM ..................................................... 13
2.1 Objectives ................................................................................................................................. 13
2.2 Strengthening of Environmental Safeguard Setup and Staffing ....................................... 13
2.3 Roles and Responsibilities of EMP Safeguard Set-up ....................................................... 15
3 ENVIRONMENTAL MANAGEMENT ...................................................................................... 18
3.1 Implementation Management of the EMP ...................................................................... 18
3.2 Site Specific Management of Key Environmental Issues............................................. 20
3.2.1 Constructions Materials ................................................................................................. 20
3.2.2 Construction Activities Management ............................................................................ 20
3.2.3 Soil Loss and Contamination Management ................................................................ 20
3.2.4 Water Loss and Contamination Management ............................................................ 21
3.2.5 Air Quality Impact management ................................................................................... 21
3.2.6 Noise Nuisance & Vibration Management .................................................................. 21
3.2.7 Loss of Vegetation and Crops....................................................................................... 22
3.2.8 Solid Waste Management ............................................................................................. 22
3.2.9 Health & Safety Management ....................................................................................... 22
3.3 Site Inspections and Audits .............................................................................................. 23
3.4 Non-Compliance Notices .................................................................................................. 24
3.5 Consultation and Complaints............................................................................................ 24
3.6 Corrective Action Plan ....................................................................................................... 25
4 ENVIRONMENTAL MONITORING ......................................................................................... 27
4.1 Overview .............................................................................................................................. 27
4.2 Fulfillment of Environmental Responsibilities................................................................. 27
4.3 Description of Environmental Monitoring ........................................................................ 28
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 5 of 65
4.3.1 Air Pollution/Quality Control ................................................................................................ 28
4.3.2 Noise and Vibration Control ................................................................................................ 29
4.3.3 Water Pollution and Soil Contamination/Erosion Control ............................................... 29
4.3.4 Crops and Vegetation loss Control .................................................................................... 29
4.3.5 Workers and Community Safety –Occupational Health & Safety ................................. 29
4.3.6 Public Health and First Aid Kits Provisioned .................................................................... 30
4.3.7 Waste Management, Sanitation and Muck Disposal Control ........................................ 30
4.4 Conclusions and Recommendations ............................................................................... 30
5 REFERENCES ........................................................................................................................... 31
ANNEXURE-1: Overall Environmental and Social Management Plan ...................................... 32
ANNEXURE-2: Overall Environmental and Social Monitoring Plan ........................................... 42
ANNEXURE-3: Email Issued to Strengthening EMP Setup & Establish Baselines ................. 53
ANNEXURE-3A: Non-compliance Repeated Notice for Documentations/Reports ................. 54
ANNEXURE-4: Project-Site Photo- Log ......................................................................................... 55
ANNEXURE-5: Test Results PH of Soil ........................................................................................ 61
ANNEXURE-6: Test Result PH of Water........................................................................................ 62
ANNEXURE-7: Monthly Medicine Log Sheet (June 2016) .......................................................... 63
ANNEXURE-8: Complaint Letter from Local Community ............................................................ 64
List of Tables and Figures:
Figure Title Page No.
Figure 1 Contractor’s overall Organizational Structure for the Project 14
Table Title Page No.
Table 1 Project Work Status as Compared to Previous Reporting Period 10
Table 2 Summary of Environment Management Actions during the
Reporting Period
18
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 6 of 65
PART- I INTRODUCTION
(Project Brief, Scope of works and Status)
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 7 of 65
1. INTRODUCTION
1.1 Overview
This second Bi-Annual Environmental Monitoring Report (BAEMR) for Jan-June 2016 covers the status of the rehabilitation and up-gradation process of the Gereshk hydropower plant, which is presently been carried out mainly through Asian Development Bank (ADB) funding under Tranche 3 program. The restoration program focuses on the provision of electricity services improvement with rehabilitation and up-gradation of the existing old hydropower plant, by replacement with new equipment and accessories to increase electricity generation and make available more reliable locally generated power supply to meet the local demand which is presently having electricity supply shortages. Currently only about 2,500 households have connections to the local electricity distribution system, while 5,000 households claim to await new connections. Some have their own diesel generators which are too expensive for the mass and the poor. Even for those connected to the electricity network, prolonged load shedding during both the morning and evening peak hours means that most receive only a few hours of power supply a day and the existing infrastructure does not allow continued access to reliable power supply.
The Gereshk Hydro Power Plant Rehabilitation Project is located in central Helmand Province, about 2.5km northeast of Gereshk town and about 125 km west of Kandahar with the project location coordinates as 31°49' 36.0"N Latitude and 64°35' 30.0"E Longitude at El. 826 elevation level above mean sea level. This hydropower plant, which has been operating for about 50 years now is presently under rehabilitation process for restoration and up-gradation of the power plant to 4.8MW installed capacity from its longstanding approximately 2MW generating capacity.
The Project which aims at increasing access to reliable power is in line with the energy
sector strategy under the Afghanistan National Development Strategy (ANDS), the
Government strategic platform for development during 2008-2020. The Project is in line with
the ADB's Country Partnership Strategy (2009-2013) for Afghanistan which identifies the
rehabilitation and upgrading of existing infrastructure as priority in the energy sector. It is
also consistent with ADB's Strategy 2020 and ADB Energy Policy (2009) for promoting
inclusive growth, energy security, and supporting energy efficiency and renewable energy.
1.2 Objective and Methodology
The main objective of the Environmental Monitoring is to anticipate and effectively address
environmental and social concerns associated with the Gereshk Hydropower Plant
Rehabilitation Project in line with Afghanistan Environmental legislation/standards as well as
meeting the requirement of the Safeguard Policy Statement of the ADB. The EMP identified
covering all possible foreseen environmental and social impacts from all the project
components/activities during the construction. Also the provision for the unforeseen
environmental & social impacts that may arise during the actual construction of the project
shall be monitored too and mitigated/addressed accordingly. The step by step approach
used for the purpose was as follows:
The monitoring process assess and establishes baseline environmental conditions in
the project area and documentation of the same;
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 8 of 65
The potential change in environmental parameters likely to be effected by project
related activities are identified and listed;
The assessment identified the likelihood and significance of potential impacts;
Then defining & listing of mitigation measures to reduce adverse impacts to as low as practicable are done;
These anticipated issues, identified mitigation measures, management and monitoring action plan, responsibilities with frequency/timeline and reporting action formulated and being implemented as per Annexures 1 & 2.
The main objective of the Bi-annual Environmental Monitoring Report is to provide general information on the progress of implementation of the project rehabilitation works during the reporting period. The other objective is to assess if the project construction is going-on smoothly as planned with all environmental and social precautions in place or needs some recommended action for necessary improvement. The judgments on the progress are established on weekly/monthly review meetings. The main contractor presents the project site findings along with the monitoring actions for site-specific civil repairs and other rehabilitation works of the project like access roads, peripheral walls, annex building and foundation for DG sets between January and June 2016 as these were the main components of activities carried out by the contractor during this period. Further, the contractor assured that all environmental and social issues have been taken care as required. The Environmental & Social Management and Monitoring Plan (ESMMP) report also prepared & finalized during the period and submitted for further implementation starting next reporting period.
1.3 Project Scope of Works and Anticipated Environmental Framework
The Gereshk Hydropower Plant rehabilitation Project consists of the following major
components of rehabilitation works:
a) Replacement of two turbine-generator units which are still in operational stage and
installation of a new third turbine-generator unit with other associated accessories,
switchgears and control system including step-up 3.3/20kV transformer substation;
b) Replacement and installation of various hydro-mechanical gates, trash-racks and
powerhouse gantry crane;
c) Civil repair works: (i) re-grading, filling & re-profiling to improve the overall stability
of both the banks of canal of length 150 m downstream of powerhouse; (ii) Civil
concrete works (second stage concrete) for replacing the Unit I and II of Turbine-
Generator and other associated equipment, (iii) Concreting works for installing unit
III (new turbine, generator and associated equipment), (iv) New perimeter / boundary
walls on the left and right banks, (v) Control Room for Stand-by Diesel Generator
sets, (vi) Annex Building cum store,(vii) Repair works of powerhouse, and (viii)
Temporary earthen dyke construction/removal for water isolation to enable hydro
mechanical (HM) works at the intake.
d) Upgrading of the existing access road of 9.6 km on the left bank from Intake to
Powerhouse and about 2.6 km road on the right bank.
Regarding the environmental and social issues, this project shall not be affected relating to change in the drainage pattern and water resources depletion due to dam/weir related constructions (which was also highlighted in the first bi-annual EMR of July-Dec. 2015) as no such components exist in the project. Therefore the anticipated environmental and social impacts during construction could result from:
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 9 of 65
The temporary use of land immediately adjacent to the canal, which may result in some localized scrub clearance and temporary loss of vegetation;
Extraction (can be from stone/sand quarries) and the transport of construction materials and dredged materials from the canal (causes dust generation, traffic congestion, sedimentation, temporary storage space, noise & vibration);
Dredging of 'the canal area (can cause sedimentation, dust generation, temporary storage space and noise);
Disposal of the old equipment of the HPP including the existing two turbines, associated electrical equipment and hydro-mechanical gates (require temporary storage space, dust generation, spillage of oils/lubricants, etc. noise & vibration);
Concrete works in proximity to the canal areas including concrete reinforcement of spillways and the canal banks (dust generation, water contamination, noise and vibration);
Water Quality issues during construction;
Noise and vibration associated with construction machineries, other equipment and DG set operation;
Contractors work practices and on site environmental management (can be a disaster if good practice environmental management not followed);
Worker Occupational health and safety issues including provision of PPEs;
Community /public health and security; Use of water for Project activities including workers camp’s requirements & road
sprinkling, etc.; Generation of waste by the Project activities during the construction; Construction of temporary earthen dyke and coffer dam for canal repair and
equipment erection may also have to be monitored properly;
Accordingly, the summarized list of key environmental and social impacts being tackled at the construction site with proper mitigation measures and monitoring as follows:
a) Soil Contamination (soil quality issue) b) Soil Erosion (loss of soil) c) Water Contamination (water quality issue) d) Fugitive Dust Emissions (impact on air quality) e) Vehicular and Generator Exhaust Emissions (GHG impact on air quality) f) Damage to Infrastructure due to Blasting g) Noise Nuisance and Vibration h) Siltation due to Temporary Earthen Dyke Construction/Removal at the Intake for
Water Isolation to Enable HM works i) Loss of Vegetation and Crops j) Occupational Health and Safety Issues; k) Community/Public Health Issue including Poor Sanitation & Waste Management
System and Communicable Diseases; l) Working Conditions and Management of Workforce Relationship. m) Blockade of access of local community right of way due to project construction
activities prioritization; n) Disturbances on Community Privacy/Safety and Site Security; o) Community Interactions & Conflict between Workers and locals.
The management of these impacts/issues is being undertaken at the project site as planned under the table in Annexure 1.
1.4 Contract for Consulting Services
In line with the foreseen requirement of Professional consultants with all specialists qualified to perform all necessary works in high quality, DABS-PMO, employer has retained the
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 10 of 65
Project Management and Supervision Consultant. Hill International (HI) for providing such services as intended for the purpose to the employer. Accordingly the work is implemented as per Regulations of ADB, and Regulations of the Islamic Republic of Afghanistan as well as in accordance with the Special Contract Conditions and Technical Specifications which are set by the Employer. Quality Control is also an integral part of the project supervision work of the PMC.
1.5 Changes in the Project Organization and Environmental Team
There is no major change in the overall project organization. DABS with its Project Management Office (PMO) and its Director as the overall authority is the direct implementation set-up to manage the day-to day coordination, monitoring and administration activities of the Gereshk rehabilitation project. However, the process of recruitment of the proposed PMO environmental team is under process and shall be in place soon. In the meantime and till such an environmental team is in place, the PMC, HI environmental expert, who is part of the monitoring and supervision team for the project has been supporting the PMO in coordinating all environmental related issues on behalf of PMO in addition to his PMC role of overseeing environmental management and monitoring of contractor’s work, and reporting.
1.6 Relationship with Contractors, Owner and Lender
During this reporting period, DABS closely acted as a team with the PMC, Hill International in reviewing all environmental aspects of the project activities and engaged also the contractor while requesting them for proper documentation of all environmental site management monitoring activities with priority basis. The communication on the project activities from the contractor with the PMO were going directly and also via the Team Leader of the Project Management Consultant. The PMO/PMC also requested from the lender’s ADB Office in Kabul for their representations in the review meetings where fruitful suggestions and advice on many issues including environmental and social safeguard aspects were provided by the ADB representative in the interest of the project construction and completion.
1.7 Status of Work Activities during the Period Compared to Previous Period
The cumulative status and progress of works activities carried out during the reporting period (Jan-June 2016) as compared to the end of the previous reporting period (31 Dec. 2015) is as follows:
Table 1: Project Work Status as Compared to Previous Reporting Period
Sl.#
Work Activities Status (30th
June 2016) Status ( 31 Dec. 2015)
A. Civil works Status
1 Left bank road – 9.6km (total) 4km PH to Intake completed 90% of 2.8 km PH to Highway Bridge completed
About 2 km excavation works was completed. About1km ABC & DBM from intake completed
2 Annex building construction Completed 95% work completed
3 DG sets foundation Completed Excavation was completed
4 Lattice tower for DG sets Completed Excavation was completed
5 Control room - Excavation completed
6 Fuel tank chamber Completed Excavation completed
7 RB-Perimeter wall-5.6m high(56m) Completed Excavation of 56 m out of 240m completed
8 RB-Perimeter wall-3.6m high(184m) 75% Completed Site clearing/cleaning done
9 Storage area for new equipment 80% Completed Only area cleaning and grubbing was done
10 Transformer foundation 50% Completed None
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 11 of 65
11 Cofferdam fabrication Completed None
12 Rail extension (Right Bank) 43% excavation completed, 32.6% PCC C10 for all structures completed, 22% reinforcement steel completed
None
B. Status and Progress of Electromechanical Mechanical (EM) Equipment
1 Lot 1-Consignment with complete set of Turbine Generator Equipment of Unit # 3 with all auxiliaries from M/s. Hunan Allonward, China
Consignment have reached Kandahar Customs in March 2016 but due to high custom duty valuation, it is yet to be cleared from Kahandar Customs by the contractor
Manufacturing completed, factory inspection & tests done and consignment dispatched from China on 18
th Dec, 2015
2 Lot-II Consignment with the remaining Two Units # 1 and # 2 Turbines & Generator equipment and all auxiliaries from M/s. Hunan Allonward, China
Consignment dispatched from China on 22
nd Jan.
2016 and have been cleared from Karachi Port, Pakistan and waiting near Kahandar boarder to be custom cleared from Kahandar after Lot - I
Manufacturing completed, factory inspection & tests done and consignment ready to be dispatched from China.
3 Lot-III Consignment of DG Sets –5 Nos. from M/s. Sudhir Electrical, Jammu, India
Consignment dispatched from Mumbai in March 2016 & currently in Karachi Port, Pakistan and in process of port clearance.
Manufacturing completed, factory inspections and tests done and consignment ready for dispatch
C. Status and Progress of Hydro Mechanical (HM)Equipment
1 Lot-1 HM Equipment with trash rack & Crane parking shed items from M/s. Khyaati Engineering, Channai, India
Consignment have reached Kandahar Customs in March 2016 but due to high custom duty valuation, it is yet to be cleared from Kahandar Customs by the contractor
Manufacturing completed, and consignment dispatched during December 2016 from Chennai, India
2 Lot II of HM Equipment comprising HPP & Canal Intake Gates – Total 8 Sets with all Embedded Parts from M/s. Khyaati Engineering, Channai, India
Consignment reported to have been cleared from Karachi Port but due to similar problem with Kahandar custom as above, Lot II materials were returned back to near border area for safe custody
Manufacturing completed, and consignment ready for dispatch
3 Lot-III HM Equipment with Gantry Crane & rubber seals for new gates items from M/s. Khyaati Engineering, Channai, India
Consignment have been transported from Chennai Port and held near border area due the customs clearance issue of HM Equipment Lot-I.
Manufacturing completed, and consignment ready for dispatch
D. Overall progress achieved based on certifications (for payment)
61.48% 46%
NOTE: PH=Power House, ABC=Aggregate Base Course, DG=Diesel Generator, DBM=Dense Bitumen Macadam, PCC=Plain Cement Concrete, HPP=Hydro Power Plant.
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 12 of 65
PART-II ENVIRONMENTAL MANAGEMENT
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 13 of 65
2. ENVIRONMENTAL MANAGEMENT PLAN/PROGRAM
2.1 Objectives
The determination of creating an EMP is to propose appropriate mitigation measures as well
as to recommend establishment of institutions or safeguard mechanisms to manage, monitor
and ensure compliance with environmental regulations and implementation of the proposed
mitigation measures. Such a set-up would pursue to ensure continuously improving
environmental protection activities in order to prevent, reduce, or mitigate adverse impacts.
The identified potential environmental and social effects/issues for the project taking
consideration of the environmental framework described above in the introduction chapter,
section 1.3 and proposed mitigation measures per Annexure-1 to be followed at the project
site during the restoration/rehabilitation of Gereshk HPP for reducing or eliminating the
anticipated adverse impacts.
The site specific environmental and social management and monitoring plan report is
prepared during this reporting period and finalized for implementation starting next reporting
period to ensure environmental protection by reducing or eliminating the anticipated adverse
impacts during the project implementation. The schedules of activities being followed for the
environmental protection by the environmental setup of the project are highlighted under
“Annexure 1 & 2” wherein the annexure-1 summarizes & provides the details of the overall
management action plan being carried out at the project site while the Annexure-2
summarizes overall monitoring action plan. The contractor’s site specific EMP provides a
delivery mechanism and addresses all these potential environmental, health and social
impacts/issues of the project during its execution including for the reporting provision and
strengthening of environmental safeguard setup to enhance project benefits.
2.2 Strengthening of Environmental Safeguard Setup and Staffing
As compared to the previous reporting period (till end of Dec. 2015), where the activities were
limited and at the initial stages of the project civil works, like: workers camps, erecting
perimeter wall (which is on-going still), and mobilization work for upgrading of the access
road, storage area and control room. The contractor thus had only little to do in that period till
Dec 2015 and their site setup for environment management aspects was just starting.
However, it was anticipated that more civil works needed to start in addition to these above
ongoing ones for the period starting from Jan 2016 like annex building, compound walls,
foundation for Diesel Generating (DG) sets, power house (PH) building repairs, etc. These
increase in site activities also anticipated for a more robust environmental management
safeguard system to be properly established at site. Accordingly discussions held with the
project Contractor and also an email was issued to the contractor on Dec. 27, 2015 for
strengthening environmental, health and social safeguard set-up along with staffing provision
and directions provided to establish baseline references control points at the project site to be
used for future monitoring purpose (the email is provided here as Annexure-3). Thus the
Contractor’s involvement in the EMP improved and also they provided new site setup
exhibiting more responsibilities in the environment management as follows:
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 14 of 65
a) Contractor’s EMP Safeguard Set-up: The contractor has included environmental
management and monitoring set-up also in their overall organizational system for the project
and it is as provided in Fig.1 in next page.
Fig.1: Contractor’s Overall Organizational Structure for the Project
With the overall set-up, the contractor embraced a particular procedure to effectively get to
environmental health, social & safety management & monitoring including required
mitigations and regular reporting in line with the Annexure 1 & 2. The subcontractors to be
managed in all respects by the main contractor, AIPL-Hunan Allonward JV & also provide
the subcontractors’ personnel with necessary awareness training and inductions at regular
intervals and ensure compliance with such plan. The subcontractors too require appointing
an environmental safeguard representative/focal person who shall be available on the site
throughout the construction period of the respective sub-contract for the stipulated purpose.
Chief Project Manager
Quality Control & Design Manager
QCS Clerk/Submittal
officer
Design Manager
Design Engineering Staffs
Quality Control Dy. Manager
Construction Manager
Civil Construction
Engineer
Electrical Engineer(Master
Electrician)
Mechanical Engineer
Civil Engineer
Foreman (Electrical,
Mechanical, Civil)
Security & Safety
Manager
Envirmental Health & Social Safety
Officer
Site Safety & Health Officer /
Asstt.
Alternate Site Safety & Health Officer/
Asstt.
Project Coordinator
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 15 of 65
The contractor’s set-up team proposed for the implementation of environmental and social
management and monitoring is as follows:
A Security & Safety Manager (SSM) works in parallel with the Construction Manager
(CM) at site under the command & direction/advice of Chief Project Manager-CPM
from the central office and Project Coordinator from the Kabul office. A full time
Environmental, Health & Social Safeguard Officer-EHSSO dedicated for the site
specific environment and social management and monitoring of various construction
activities, works under the SSM. The EHSSO makes the daily/regular EMP after
discussions with the SSM and CM (for site construction activities and schedules) for
his daily/regular monitoring works.
The EHSSO is being further assisted at the project site for daily supervision and
monitoring of environmental & social impacts by two Environmental & Social
Safeguard Assistants as required in reducing or eliminating the adverse impacts.
In addition, the sub-contractor also deputed a dedicated safety officer/assistance
who also looks after the environmental safeguard at their construction sites.
Grievance or Complaint Redress Cell (Complain Box) is setup & operated by the
contractor with monitoring by the PMO/PMC at three (one at powerhouse / camp
site, another at intake road area, and the other nearby the community location to put
their grievances(if any) in writing in these installed complain boxes. The contractor’s
EMP-Team then collect the complaints on weekly basis and make entry of all such
complaints in a properly maintained log-register and inform the PMO/PMC for further
addressing them in an amicable way.
b) PMO/PMC (HILL) EMP Safeguard Set-up: The Director, PMO of DABS is the overall
responsibility with its PMO ensuring effective compliance with the requirements on the
environmental management and monitoring. The status of recruitment of the proposed PMO
environmental team personnel is under process. In the meantime and till this process is
completed, the PMC, HI environmental expert, who is a part of the PMC team for the
monitoring and supervision of the Greeshk HPP has been looking after and coordinating all
environmental related issues, management, monitoring and reporting on behalf of
PMC/PMO and also overseeing the environmental monitoring activities of the Contractor’s
environmental setup to ensure the environmental integrity of the project rehabilitation.
Accordingly, the overall ESMMP implementation, monitoring, operation and reporting
organizational structure of the PMO, PMC and the Contractor combined has been kept the
same as proposed in the BAEMR of June-Dec. 2016.
2.3 Roles and Responsibilities of EMP Safeguard Set-up
a) Contractor’s Roles & Responsibilities: The contractor’s environmental setup shall
initiate and activate the operation of the EMP and reporting management of the mitigation
measures and the monitoring to the PMO/PMC set-up effectively in line with Annexures 1 &
2. Some major responsibility being followed are but not limited to the following:
Ensure the implementation of the EA/EMP throughout construction works including
for the reporting period by all contractor personnel and subcontractors;
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 16 of 65
Ensure that adequate resources are available to implement the requirements of
the EMP;
Undertake required environmental monitoring, supervision, audits and reports to PMO/PMC on regular basis.
Documentation on the boundary area in and around the Gereshk HPP project along
with baseline control points established as indicators for the monitoring purpose
during the implementation of the EMP;
Manage and monitor the environment site activities, health and social issues in line
with Annexure 1 & 2 ;
Identify the need for and recommend corrective actions;
Control undesirable social interaction between local communities and the migrant
construction workers;
Prepare daily, weekly/monthly and bi-annual reports as required and submit to the
PMO/PMC.
b) Employer/Client/PMO’s Roles and Responsibilities: With overall responsibility for the
Project, DABS/PMO shall:
Minimize any impact the “Project” may have on the environment and social issues;
Appoint and set-up an ESMMP team as proposed above for coordination,
supervision and monitoring of the environmental and social issues of the project;
Issue directives to the contractor(s) to comply with the provision of ESMMP
implementation;
Approve any changes required at site as per the site conditions during the
construction period and as per the recommendations by the PMC,
Arrange and provide the required land for the project activities (if any);
Obtain the relevant environmental permits, consents and authorizations prior to
commencing site works;
Coordinate with all relevant stakeholders of the project and in obtaining all NOCs
requirements from NEPA related to the Project.
Perform site inspection and monitoring of environmental and social issues as well as
monitors the PMC and contractor’s activities.
c) PMC-HILL’s Roles and Responsibilities: This environmental setup shall monitor the
EMP implementation and report the implementation to PMO/DABS and ADB. Some major
responsibilities includes but not limited to the following:
Assist and advise PMO for the ESMMP implementation
Monitor environmental health and social activities of the contractor
Identify the need for and recommend corrective actions
Assist the PMO in resolution of non-compliance issue of the contractor
Control undesirable social interaction between local communities and the migrant construction workers through the main contractor;
Advise and assist the contractor in conducting safety and health related training along with health staff.
Advice and assist the contractor to arrange provision for improvement of local infrastructure, i.e. portable water supply, temporary housing for workers, etc.;
Check the sanitary of the area and offer remedial measures;
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 17 of 65
Compile additional contractor’s report on progress and the status of each rehabilitation component conducted;
Liaise between DABS/PMO, ADB and the contractor;
Compile from contractor’s report/data and prepare a monthly/bi-annual reports in the required format to submit to the DABS/PMO and ADB.
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 18 of 65
3 ENVIRONMENTAL MANAGEMENT
3.1 Implementation Management of the EMP
At the project site, the environmental health, social & safety officer of the contractor is
working directly under the Security Manager with collaborative team-work support from other
technical teams like the Construction Manager and subcontractors’ environmental
designated personnel from the concerned project activity site. The Chief Project Manager
looks after the overall coordination of monitoring and supervision of the project to fulfill the
EMP. A Project Coordinator working directly under the CPM through the Kabul Contractor’s
office coordinates all the project related activities including the environmental management
between the employer, PMC and other stakeholders.
An assessment of the implementation of the environmental management according to the
norms described in the EA (IEE) report of the project (also prepared ESMMP during the
reporting period in line with the EA report and the overall ESMMP in a summarized table is
as per Annexure-1).
A site specific time-line followed for ESMMP activity-wise environment implementation management of the mitigation measures (which also depend on the technical construction schedules & activities) were as indicated below:
Table 2: Summary of Environment Management Actions during the Reporting Period
EMP Activities
Implementation Time-line
Environment Management Actions during the Period
Stakeholder consultation /
communication and
interactions with local
community
At start of the project and
regular follow-up discussions
throughout the project
construction period
Project/Civil works started after
briefing / discussions with concerned
stakeholder & their consent including
community elders
Relevant environmental
awareness trainings and
inductions
At start of the project and
regular follow-up awareness
briefings / inductions
throughout the project
construction period.
Briefings on importance of
environment protection and use of
PPEs for their own protection
provided every day before start of
work, weekly inductions on use of
PPEs, tool box training & other EMP
provided to all workers
Maintaining farmers'
access to irrigation water
if the works are
implemented during the
irrigation season;
During irrigation season
period as required
Canal not closed during this reporting
period and water provided for irrigation
all the time
Maintaining vehicle
access to the community
areas and traffic
management
Throughout the project
construction period especially
during equipment
transportation peak period
Followed as required by Annexure 1
though not many vehicles as project
equipment are on the way from the
manufacturing country and yet to
reach the site
Pollution control
(including spill prevention,
dust abatement, noise, air
and water, etc.) and
biodiversity preservation
Baseline information to be
established at start of the
project and monitor regularly
throughout the project
construction period
Baselines drawn from the EA (IEE)
report for the project and Annexures 1
& 2, which are also summarized in line
with the EA followed as required and
practiced at site
Provision of potable water Required throughout the Quality water provided / made
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 19 of 65
and washing/toilet
facilities to workers;
project period and should be
arranged at site
available as required with bore hole
constructed at the base camp area of
the project site
Provision of occupational
health and safety care to
workers and treatment for
injuries and infections
Throughout the construction
period and first aid to be
arranged at site and doctors
to be arranged from nearby
hospitals
PPEs provided to workers as required
work-wise and all treatments including
work injuries treated by contractor’s
first aid & site medical arrangements.
However there was no need during
the period for calling the doctor at site
Provision of health care
to workers including
control risk of spreading
communicable diseases
to workers and in
communities for
appropriate treatments
The Contractor to ensure that
the engaged workers are free
from such disease at the time
of initial appointment. And
provision for control and
treatment throughout the
construction period
No worker at site with communicable
disease. No communicable disease
observed at the project site and the
local communities
Mechanism for workers
and community
relationship management
for creating harmony in
the project constructions
Full project briefing at start of
the project/civil works and
regular follow-up inductions
throughout the project
construction period on the
importance of maintaining
good relationship & harmony
with local community
Though the project site is more than
one km away from the nearest village
except one house, which is about
200m from the project site, village
elders were visited and discussion
held mainly on issues like access
limitation from project site during
construction & also for safety
reasons, work relation with workers
verses communities, prevalent
diseases in the area, workforce
management by contractor in line with
Annexure1. The workers on the other
hand were provided also full briefing
during the weekly tool box induction
training on the importance of
maintaining good relations with the
local communities and the norms to
be followed by the workers on the
same
Assessing importance of,
reporting and
investigating chance
historical, cultural and
archaeological findings
during the construction
Only during the time when
such additional unexpected
environmental surprises
occur
No such new surprises have been
found during the period and as such
no action was required
Inspection and monitoring Daily and regular inspection
throughout the construction
period
Annexure2 followed and practiced at
the project site with daily and regular
supervision & inspections for
maintaining environmental integrity
The work plan for the EMP activities followed the technical construction activities of the
project. Due to some security situation at the project site during this reporting period, the
Contractor has been discussing for a more practical construction schedules with the employer
and PMC and once that is finalized, the work plan for site specific EMP activities/actions as
enumerated in the stated annexures 1&2 shall follow the technical construction schedule
activity-wise as required and environmental protection measures would follow accordingly.
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 20 of 65
3.2 Site Specific Management of Key Environmental Issues
3.2.1 Constructions Materials
The construction stone is not available around the project site and the contractor arranged
for both before and during the reporting period from outside of the project site ranging up to
5 km distance, involving local suppliers following local rules and regulations for such
supplies. Similar was the case for supply of sand for concrete works and mud/gravel
required for boundary / perimeter / HESCO walls erection. Hence the project site
environment was not affected with the construction material extraction and quarries.
3.2.2 Construction Activities Management
The workers base camps, restoration/upgrading of the access road to different project
facilities like intake & powerhouse, annex building construction, foundation / excavations of
Diesel Generating (DG) sets, control-room, fuel tank chamber, storage area preparation and
boundary / perimeter wall at right bank & also listed above under section 1.7 were the major
ongoing works continued from the previous reporting period. In addition to these on-going
activities, foundations concreting for Diesel Generating (DG) sets, DG lattice structure, fuel
tank, power house (PH) building repairs, transformer base excavation and foundation,
excavation for rail extension in front of the powerhouse were being carried out during the
reporting period. All these work activities were carried out and managed by the Contractor
engaging three local sub-contractors: (i) NLCC (Niamat Lali Construction Company), who
were mainly involved for upgrading access road, construction of perimeter walls, storage
area, and cofferdam fabrication; (ii) PGCC (Power Global Construction Company)-they were
involved in the construction of fuel tank chamber, DG sets foundation, lattice tower and
transformer foundations; (iii) FECC (First Eagle Construction Company)- they were involved
mainly for construction of base camps, annex building and crane rail extensions.
3.2.3 Soil Loss and Contamination Management
The maximum soil loss at the Gereshk HPP could have been from the excavation of different
activities like, road upgrading and foundations as highlighted above. However, the
restoration road works consisted excavation in some length and filling in other parts of the
road and thus the same excavated soil was also used for filling. Similarly the various
foundation excavated soil was also used for backfilling and leveling. Accordingly the net
soil/muck generation and soil loss was almost nil except a truck load of debris/muck created
during the total reporting period, which was then disposed at the local municipality
designated muck disposal site, about 4km away from the project site.
The constructions of the stated activities were free from soil contamination issue too. The
possible contaminants existing during the period were fuel oils/lubricants/brake oils / grease
(the solid waste management was dealt separately and will be explained below). With the
oil/fuel handling done at site at designated place with concrete base and required lining near
the base camp area, the issue of soil contamination management during the period was
satisfactorily complied. The soil PH was tested during the reporting period for three samples
around the project (near powerhouse area, intake area and road construction area). The
value of the PH test results is provided in Annexure-5 and the PH values for the three
samples of soil are 7.2, 8.3 and 8.4 indicating good soil in relation to the PH.
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 21 of 65
3.2.4 Water Loss and Contamination Management
The water extraction from the river and canal was limited to some concreting works of the
stated limited facilities only and thus the water loss from the river and canal is minimum or
negligible. The staff/ workers water consumptions have been arranged by the contractor
through bore hole at the base camp area to avoid using from the local community water
supply system. Also two water sprinkling tanker-trucks filled with borehole water were used
once in the morning and one time in the afternoon daily for dust suppression along the road
during the upgrading of the road work. Therefore, the water loss from the river system and
the project area was not much limiting to the above stated uses and did not impact on the
aquatic life and fishes.
On the water contamination issue, the project activities during the reporting period did not
cover the river intake and canal repairs and thus river/canal water contamination
management with such repairs was not necessary. The left bank road restoration and
upgrading from the powerhouse to intake & powerhouse to highway was along the water
canal but the excavated net soil generation was limited as indicated above. The limited soil
generation was not allowed to dump into the river and canal with proper supervision and
thus the water contamination issue did not arise during the reporting period. The PH tests
results provided in Annexure-6 of three water samples show that the water quality relative to
PH scale is satisfactory as follows:
Sample No. Sample Place PH Test Result (Value)
Sample 1 Base camp water 7.33
Sample 2 Social community well drinking water 7.41
Sample 3 Bagrah canal water 7.38
3.2.5 Air Quality Impact management
The dust production in the air at the project site during the reporting period was mainly with
the upgrading of the access roads. As indicated above, the roads being constructed were
water sprinkled twice a day in the morning and afternoon so that the dust generation in the
air reduced.
The other air pollution impact was from the GHG emissions from the use of construction
equipment & vehicles. However the vehicles movements at the site were limited since
project equipment could not be transported to site during the period. The limited equipment
and vehicles at site during the period were, two DG sets running for 24 hours, one roller
compactor, two water tanker-trucks, two dump trucks and one air compressor. The others
like excavators, bulldozers and pay loader were hired during the initial stage of the period.
By choosing new & fuel efficient equipment/vehicles during hiring time, minimizing
unnecessary machines idling with operator/driver awareness training and with limited
number of equipment required at site, the gaseous emissions were also limited avoiding to a
large extent the air pollution accordingly.
3.2.6 Noise Nuisance & Vibration Management
The communities are located away from the project site (the nearest community being
almost one km away) and hence the noise level and vibration for the community areas were
far below the indicated ceiling of 85 db(A) in the EA document (to follow) due to the distance
from the project site. Therefore the project staffs, operators, drivers and the workers only
needed to be taken care from the generated noise. The operators/drivers and workers
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 22 of 65
required to work/stay near the noisy equipment were provided ear muffs & plugs to reduce
the impacts of the noise accordingly.
3.2.7 Loss of Vegetation and Crops
There is not much vegetation in and around the project area and no vegetation loss occurred
during the period. Providing awareness training to the workers on use of designated
routes/access strictly from the agricultural areas and also installing fencing between the
construction site and the agricultural plots as seen in the photo-log at Annexure-4 saved loss
of the crops.
3.2.8 Solid Waste Management
Leak-proof plastic tanks being used for collection and storing of the small quantities of the
camps’ toilet/sewage wastes and disposed every month to the local municipality designated
disposal area, about four km away from the project site.
On the other types of garbage, six types of segregation being done using different colored
dust bins/drums for site collections as shown below.
Sl. # Color Color Name Color Code/Meaning (for workers to understand and follow for segregation/collection purpose)
1 Green Food Wastes - (Marked “FOOD WASTES ONLY”)
2 Yellow Paper/Cardboard - (Marked “PAPER/CARDBOARD ONLY”)
3 Light Blue Plastic/General Waste - (Marked “PLASTIC/GENERAL WASTE ONLY”)
4 Orange Medical wastes - (Marked “MEDICALWASTES ONLY”)
5 Grey Scrap Metal Pieces - (Marked “METAL PIEACES/SCRAPS ONLY”)
6 Red Oily Wastes including Filters - (Marked “OILY WASTES ONLY”)
There was no hazardous chemical waste generated during the period and if such a waste appears at any time at site in future, it would be dealt separately.
The wastes collected under serial nos. (2), (5) and (6), which were recyclable or could be
further used like the paper, cardboard, scrap/metal pieces and plastic fuel/ oil / lubricants
jercans/cans have been handed over to scraps collector from the local area/Laskargah. The
medical wastes was nil / minimum and has not been disposed except for some paper
wrappings, which were disposed together with other general wastes. The wastes collected
under serial nos. (1) and (3) and part of (6) was about 15kg per week and disposed
separately on a weekly basis to the disposal site designated and provided by the local
municipality office about 4km away from the project site.
3.2.9 Health & Safety Management
To ensure that the workplace is safe and healthy, all health & safety control measures were
implemented in line with Annexure-1&2 to address the hazards and risks outlining the
procedures and responsibilities for preventing, eliminating and minimizing the effects of
those hazards and risks.
The contractor ensured the safety of its employees/workers at site with proper awareness and
training on the working environmental and also providing Personnel Protective Equipment (PPE)
as required at concerned work sites for various works as follows:
Type of Work Personnel Protective Equipment (PPE)
Elevated work Safety helmet, safety belt,(greater than 20 ft), footwear for elevated work.
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 23 of 65
Handling work safety Helmet, leather safety shoes, work gloves.
Welding and cutting work Eye protectors, shield and helmet, protective gloves.
Grinding work Dust respirator, earplugs, and eye protectors.
Wood working Hard hat, eye protectors, hearing protection, safety footwear, leather
gloves and dust respirator.
Blasting Hard hat, eye and hearing protection.
Concrete and masonry work Hard hat, eye protectors, hearing protection, safety footwear, leather
gloves and dust respirator.
Excavation and trenching Hard hat, safety boots, gloves,
Operation of heavy machineries
and equipment.
Qualified and certified operators, Proper condition of machineries, signal man, back alarm and suitable PPE Such as hearing Protection.
Painting Hard hat, eye protectors, hearing protection, safety footwear, leather gloves and dust respirator.
Plastering Hard hat, eye protectors, hearing protection, safety footwear, leather gloves and dust respirator.
Hot mix asphalt Fire resistive cloths, Hard hat, eye protectors, hearing protection, safety footwear, leather gloves and dust respirator.
Earth work Hard hat, eye protectors, hearing protection, safety footwear, leather gloves and dust respirator.
Electric work Hard hat, eye protectors, hearing protection, safety footwear, leather gloves.
In addition, the following safety measures were also carried out by the contractor: (i)
Installation of signboards and symbols as shown in a photo in the Annexure-4 of photo log,
to inform workers to be alert & careful; (ii) Ensuring that materials storage were all stacked,
racked, interlocked, or otherwise secured to prevent sliding, falling, or collapse; (iii)
Removing all scrap and waste material from the immediate work area as the work
progresses; (iv) “First Aid” facilities being made available at work sites and had
arrangements for doctors/hospital staff, who could be called in, from nearby towns whenever
necessary. Further the contractor proposed an overall emergency preparedness and
response plan in the ESMMP, prepared during the reporting period for dealing with
emergencies for safety control at the project site.
3.3 Site Inspections and Audits
During the period of this report, civil works rehabilitations were on-going for walls; DG set
foundation, annex building, transformer foundation, fuel tank chamber, access road
restoration works, storage area development, etc. Adequate attention has been paid to the
implementation of the mitigation measures and the environmental management. The
environmental impacts have been prevented or reduced to the minimum level possible
through the proper implementation of various mitigation measures.
Due to the security concerns at the project site, the PMO/PMC set-up could not carry out the
site checks during the reporting period and depended on the contractor’s feedbacks and
responses. The contractor’s environmental setup as described above under chapter 2
carried out the EMP site supervision and provided their feedbacks /data / information
through their Chief Project Manager to the PMO/PMC. The environmental expert at the
PMO/PMC then reviewed, verified and compiled these information and data and refined
contractor’s information and reports to submit to the employer and ADB in the required
format.
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 24 of 65
Usually environmental regulatory authorities require a quarterly or half yearly audit report for
large scale projects but the Gereshk HPP rehabilitation being a small project with less or no
severe environmental adverse impacts, an audit at the near end or just before the
completion of the rehabilitation is proposed and expected to suffice the purpose.
3.4 Non-Compliance Notices
During the reporting period, no non-compliance notices were issued to the contractor in
relation to environmental harm for the project site activities. However, on the environmental
management documentation front, it was observed that contractor was lagging behind. It
was thus highlighted by the PMC with emails/letters and also during meeting/discussions
between the PMO, PMC and the Contractor that documentation and submission on the
ESMMP activities carried out (to be carried out) at site needed more improvement and
attention from the contractor’s side. One such email notice was issued on 27 Dec.2015, a
copy of which is attached as Annexure-3. The email repeat notices for the purpose were
issued on 29 March, 2016, 28 May, 2016 and 02 June, 2016. Again a letter as Annexure3A
by PMC was issued on 03 June 2016 for the purpose. The major documentation works
discussed here are for project baselines documentation (only water & soil PH tests results
provided till date), environmental awareness training/inductions documentation and timely
progress reporting. The contractor, AIPL has been reminded again on these, and AIPL has
agreed to take the actions on priority basis.
3.5 Consultation and Complaints
The consultations among the employer, PMC and the contractor are a continuous process in the interest to the project construction and completion. Also complaint / grievance boxes installed at three locations for public/locals to submit their suggestions and grievances in writing and the Grievance Redress Mechanism (GRM) shall follow the process described below in the box:
Grievance Redress Procedure
Step 1: The aggrieved local person submits his/her grievance in writing to the Grievance
Redress Outlet Box Point established by the Project during the construction with
committee called “Grievance Redress Committee (GRC)” with members comprising of the
Project (PMO/Hill-Project Manager, Local DABS representative & Environmental Expert),
Contractor’s Environmental Health and Social Safeguard Officer, and Local
Village/Municipality and District representatives. Initially the contractors discuss with the
aggrieved person/community and try resolving the issue. If the contractors are unable to
resolve, it is put up to the GRC.
GRC deals with grievance within 15 days of receipt of complaint.
If unresolved Step-2 follows:
Step 2: The aggrieved person is not satisfied with the decision rendered by the GRC or, if
he/she does not receive a response within 15 days; he/she can approach and appeal
further to the senior management of DABS, where the concerned appeal will be studied
properly and decision provided within two months of receipt of the complaint / appeal.
Step 3: If still, the aggrieved person is not satisfied with the DABS senior management
decision, she/he can ultimately appeal to the Afghan Court of Law for final justice.
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 25 of 65
During the reporting period, two written grievances were received as per Annexure-8, from
the local community people in the second half of April 2016 through the complaint boxes.
The complaints were on the access blockade due to the construction works and the villagers
were treated badly by the contractor’s GHPP guards during the movement of locals and
transportation from the project area. However, the contractor as per the monthly progress
report (ESMMP) of June 2016 indicated that the contractor discussed on the complaint
letters with the village leaders and resolved the issue after properly briefing them.
3.6 Corrective Action Plan
No corrective actions planned on EMP during the period except the concerns and request
made to the contractor for timely submission of documentation/reporting including the EMP
monthly progress reports.
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 26 of 65
PART-III ENVIRONMENTAL MONITORING
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 27 of 65
4 ENVIRONMENTAL MONITORING
4.1 Overview
Monitoring activities were carried out by the set-up described above in chapter 2 during the
reporting period according to the monitoring program developed based on the ADB
safeguards and EMP requirements. Monitoring program for the period included regular
monitoring of construction activities for their compliance with the environmental
requirements as per specified standards, specifications and report on the implementation
& performance on measures as per Annexure-2. Some of the major monitoring activities
followed at site were:
a) Site Inspection – undertaken daily/regularly in all relevant areas of the civil work
activities mentioned above under section 1.7. The inspections were also focused on
compliance with the EMP by increasing awareness of the EMP among workers with
regular inductions on the EMP.
b) Audits - Usually environmental regulatory authorities require a quarterly or half yearly
audit report for large scale projects but the Gereshk HPP rehabilitation being a small
project with less or no severe environmental adverse impacts, an audit at the near end
or just before the completion of the rehabilitation is proposed and expected to suffice
the purpose. Therefore, no audits carried during the reporting period.
c) Non-conformances and Incidents – with the requirements of the EMP for actions,
such as spills, resulting in potential or actual environmental harm. However, there was
no requirement for non-compliance as no serious environmental harm occurred during
the reporting period except the above stated concerns made to the contractor for timely
documentation and submission of the documents/reports including the monthly
progress reports, baselines, awareness trainings/inductions.
d) Communication/Reporting/documentation – the EMP reporting and documentation of Gereshk HPP Rehabilitation Project by the contractor during the reporting period was observed to be inadequate. Accordingly the contractor has been requested with emails/letters and in weekly /monthly meetings to improve their reporting/documentation line of actions to the employer and the PMC.
With the construction activities of the project, environmental and social monitoring done to
ensure the protection of air quality, noise level, water quality, flora & fauna monitoring,
preventing soil erosion/quality, proper waste management control, to maintain good
community relationship, project site/works safety control, awareness training and regular
inductions provided, look after public health issues, risk reduction for occupational health &
workplace safety issue and GRM (Grievance Redress Mechanism) which are also
described in the following sections.
4.2 Fulfillment of Environmental Responsibilities
The environmental responsibilities outlined in the EA report in compliance with the ESMMP
developed with statuary/regulatory requirements of the country and the donor’s, ADB
guidelines (May 2003) are by and large fulfilled, albeit with delays in some environmental
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 28 of 65
documentation monitoring and reporting. The status of fulfillment of environmental
responsibilities is tabulated and summarized below:
Phase Responsible
Agencies
Environmental Responsibility Status of
Fulfillment
Preparation
& Design
PMO, Feasibility
Study Consultants
Preparation of EA (IEE) with public
consultations & indicative mitigation
measures
Fulfilled
National Environment
Protection Agency
(NEPA)
Review and approval of the EA (IEE) report Fulfilled
Tendering /
Bids
PMO, PMC and
Contractors
Major Mitigation Measures incorporated in
the bids
Fulfilled
Construction
PMO and PMC Finalize and Advise on implementation of
ESMMP in line with the EA; supervision &
monitoring of implementation of mitigation
measures
Fulfilled
Contractors Preparation of site specific ESMMP and
implementation of mitigation measures,
documentation and reporting
Fulfilled albeit delays
in some
documentation &
reporting
External Auditing and
ADB
Provision of external auditing included in
the EA as well as ESMMP to be done once
before the completion of the project
Fulfilled and would
be carried out as
planned in ESMMP.
4.3 Description of Environmental Monitoring
4.3.1 Air Pollution/Quality Control
The contractor followed the procedures enumerated in Annexure 2, also developed during
the reporting period in line with the EA (IEE) report of project design stage and also included
in the ESMMP for maintaining good air quality. Daily supervision and monitoring carried out
to reduce on the major sources of air pollution as follows:
Dusty roads in and around the project activities (near workers camps & work areas,
local community) were water sprayed daily once before lunch and once in the
afternoon to suppress dust;
The vehicles delivering sand and mud were covered with tarpaulin sheets and also
checked on overloading for preventing dusts flow in the air;
Vehicles speed were checked and controlled not to exceed 30km/hr for heavy
vehicles and 40km/hr for light vehicles in and around the project site to prevent dust
generation in the air;
Proper maintenance of vehicles and other diesel equipment, and avoidance of
unnecessary running of vehicles & equipment engines were adopted to reduce
emissions in the air;
Stock piles of sand & mud done with covers and away from the workers camps &
community areas
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 29 of 65
4.3.2 Noise and Vibration Control
Noise sensitive areas like: schools, hospitals, residential communities do not fall near the
project construction sites as they are more than one km farther away. So the noise level to
such sensitive areas was far less than the indicated upper ceiling value to be maintained as
per the EA (IEE) report. The monitoring to avoid impacts from noise & vibration carried out in
other project areas as follows:
Monitored daily that equipment with Low levels of noise were selected and engaged
near the workforce camps and other more noisy equipment engaged away from the
camp areas;
Regular monitoring done to check that PPEs like ear muff & plugs were provided for
operators and workers to work with or near the equipment. Also temporary barriers
were used to reduce noise;
Speed limits as indicated above were also monitored regularly to help reducing the
noise.
4.3.3 Water Pollution and Soil Contamination/Erosion Control
Daily/regular supervision and monitoring in line with Annexure-2 carried out at the
constructions activities to reduce on the major sources of water & soil contamination and
soil erosion as follows:
Project equipment and vehicles fueling, lubricants/oil change, and storage
checked and regularly monitored to occur at designated places developed suitably
near the base camp area with concrete lining away from the water course and to
avoid any spills directly on the soil;
Daily monitoring done to check that excavated soil, muck or the camp wastes
were not dumped near or into the water canal/courses or drains to help both water
contamination and soil erosion;
Monitored regularly to check that soil/sand stock piles were covered to avoid from
blown away by wind causing soil erosion and water contamination.
4.3.4 Crops and Vegetation loss Control
Regular Monitoring done to check that barricade fences were installed to block
passage for workers to enter agricultural land to avoid crops tampering;
Monitored to check that repair of irrigation trenches damaged by project construction
activities were timely repaired;
4.3.5 Workers and Community Safety –Occupational Health & Safety
Monitoring was done to check that the contractor had taken all precautionary
measures to ensure workers safety. PPEs were provided and generally used at all
times for any person, entering the construction site.
Monitoring was also carried out that for injury or illness to any worker in the project
area or in the vicinity, the contractor was fully responsible for medical care and
according to the prevailing labor law. For example –during the month of June 2016,
about ten such cases of injuries/illness occurred and the contractor treated them from
the First Aid Kits as per the annexed “Monthly Medicine Log sheet” as Annexure-7
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 30 of 65
4.3.6 Public Health and First Aid Kits Provisioned
Under the direct supervision & control of the contractor’s EHSSO, the “first aid kits”
having all necessary common medicines was installed and available at site;
Checked that emergency numbers were made available and posted at entry points
and at the site office areas;
Record log for the first aid cases on a monthly Medicine Log Sheet;
As indicated above, 10 cases of minor injury/illness were reported during June 2016,
which were handled in the base camp First Aid Kit’s room;
No major injury/illness or accident was reported at the site during the reporting
period.
Monitoring to check that workers and communities were made aware on the
communicable diseases including cleanliness and sanitation requirements.
4.3.7 Waste Management, Sanitation and Muck Disposal Control
Regular monitoring of segregation of six garbage types according to the six dust bins
provided were properly done and the dust bins emptied and disposed into
weatherproof bags on a weekly basis at the designated site about 4km away from the
Gereshk HPP.
Regular check also done for sewage waste water emptied in a leak proof plastic
tanks on a monthly basis and disposed off at designated site about 4km from the
project site.
Regular monitoring done for the prevention of discharge of any pollutant such as
cement/concrete, lime, chemicals and fuels into any water courses or on the soil
around the project site.
4.4 Conclusions and Recommendations
As an interim measure, the contractors have been following the initial project design EA
report for environmental and social protection related activities and actions at site till date.
However, the ESMMP has been prepared during the reporting period and finalized now for
further implementation starting from the coming reporting period.
During the period of this report, civil works rehabilitations is/was on-going for walls, DG set
foundation, annex building, access road restoration, transformer foundations, fuel tank
chamber, rail extension, etc. The contractor has on the whole claim fulfillment of the
environmental, social/health and safety responsibilities by putting adequate attention to the
implementation of the mitigation measures and environmental monitoring.
The documentation and submission on the ESMMP activities carried out (or required to be
carried out) at site needed more improvement and attention from the contractor’s side. The
major documentation works discussed here are for control points baselines documentation,
awareness training and inductions documentation and timely progress reporting. The
contractor has been requested to submit such requested documentations in time henceforth
on priority basis.
The conclusion at this stage is that no major environmental and social issues/impacts are
expected associated with the proposed rehabilitation works at the Gereshk Hydropower
Plant if EMP is implemented properly through the contractor as designed by the PMO/PMC.
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 31 of 65
5 REFERENCES
Bi-Annual EMR - 42094-042–emr-01 for July-December 2015 (Gereshk HPP Rehabilitation) ADB, Safeguard Policy Statement - 2009 ADB, Environmental Guidelines for Selected Industrial and Power Development Projects, 1990 ADB, Hand Book on Social Analysis, 2007 ADB, 2003, Environmental Assessment Guidelines Government of Afghanistan, 2007, Environment Law Government of Afghanistan, 2004, Law on the Protection of Historical and Cultural Properties
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 32 of 65
ANNEXURE-1: Overall Environmental and Social Management Plan
Impact Ref
(Environment /
Social Issue)
Description (Objective
for Mitigation Measures)
Mitigation / Management Measures
(Actions to meet the Objective)
Implementation
Responsibilities
Awareness /
Training (Capacity
Building)
PEI-01 Improper handling / storage
of fuel, oils/ lubricants,
grease, plastics and other
substances resistive to
biodegradation result in
spills leading to soil
contamination.
Discharge related to the
project construction and
operation phases
particularly DG-sets /
generators operation,
vehicle fueling, lubricants
change and wastewater
system can potentially
result in the contamination
of soil.
1. Storage of fuels & oils/lubricants/grease shall be done in a manner that does not allow leakage to the soil as these can readily infiltrate the soils polluting it as well as the ground and surface water;
2. Undertake regular routine preventive maintenance of motorized equipment and vehicles to
avoid any fuel leakage and spill;
3. Fueling will be carefully undertaken at designated and well maintained fuelling centers;
4. Collect and dispose all hazardous waste generated from the project activities including
plastic / polythene, and metallic wastes in accordance with local guidelines, National
Environment Law, Waste Management Regulations and international best practice;
5. The generators will be placed on impervious layer. Sufficient area around the generator
will be made impervious to contain any spill during operation & maintenance;
6. Grease traps will be installed on the site, wherever needed, to prevent flow of oily water;
7. Fuel tanks will be appropriately marked by content and will be stored in dike areas with an
extra 10% storage capacity of the fuel tank. The area will be lined with an impervious
base;
8. Spill control kit (shovels, plastic bags and absorbent materials) will be available near fuel
and of oil storage areas;
9. Emergency plan for spill management will be prepared and inducted to the staff for any
incident of spill;
10. The bottom of any soak pit or septic tank will be at least 10 m above the ground water
table on general condition. However this distance can be lowered / reduced if analyzed &
designed on soil properties;
11. All organic waste generated at labour camps such as food stuffs shall be collected and
transported by a licensed waste collection entity to designated landfills / dumping sites.
Contractor with the
directives and
supervision of the
PMO and PMC
(Hill)
Contractors shall
carry out awareness
training to all the
employees and
workers on the
importance of soil
quality & the needs
for them to know the
objective & actions
of the ESMMP and
their roles during the
construction and
operation to
safeguard the
environmental and
social aspects while
carrying out the
project activities.
( to be planned at
the beginning of the
project as well as
inductions at regular
intervals)
So
il C
onta
min
atio
n (
soil
qu
alit
y issue
)
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 33 of 65
PEI-02
Soil Erosion
Issue
Land clearing, excavation &
surface leveling, blasting
and drilling activities may
loosen the top soil in the
project area resulting in
possible acceleration of soil
erosion, especially in the
wet season. The access
road excavated areas,
workforce camp cleared
areas, muck disposal site
and quarry sites are
venerable to soil erosion
and need good attention.
12 Vegetation loss shall be minimized to the extent possible which would help soil bonding;
13 The nearby area will be sprinkled before blasting and drilling to minimize erosion;
14 Controlled blasting shall be done to minimize soil erosion;
15 For all depression, unstable slope areas for access road construction, adequate retaining
wall or breast wall to be provided in case the geology is not self-supporting;
16 Adequate vertical and horizontal drains, drainage along road sides, cross drainage will be
provided for channeling water, which otherwise may cause soil erosion;
17 Areas such as muck disposal sites, workforce camps, quarry sites, along access road
sides, etc. after the closure shall be rehabilitated by planting grass, shrubs and trees.
Contractor with the
directives and
supervision of the
PMO and PMC
(Hill )
Similar to the above
or together with the
above awareness
training, the
contractor shall
include and provide
the awareness
training on soil
erosion issues and
its importance for
protection to all the
project employees at
the beginning of the
project
PEI-03
Water
Contamination
(water quality
issue)
Water contamination due to
releases from the
construction camp, vehicles
washing area and sewage
from the power plant
facilities and possible fuel
and oil spills/leakages.
Contaminated run-off from
spill sites could adversely
affect soils and vegetation
and if it reaches the river,
would have an adverse
impact on water quality &
aquatic life.
18 Leakage of fuel & oil wastes from storage and machinery /vehicles should be avoided in
order to prevent potential contamination of canal/river water and ground water (Proper
PEI-01 implementation as proposed above will help to address this impact on water too);
19 Lining of all effluent channels at all working areas with cement will be done to prevent seepage;
20 Soak pits for kitchen waste water will be installed; 21 Septic tanks for sewage waste will be put in place;
22 Release of camp effluents to the water channels or land will be strictly prohibited;
23 All the garbage shall be segregated, collected and disposed-off adequately to the
designated disposal site;
24 Areas such as muck disposal sites, workforce camps, quarry sites, along access road
sides, etc. after the closure shall be rehabilitated with grass, shrubs and trees with local
species.
Contractor with the
directives and
supervision of the
PMO and PMC
(Hill)
Similar to the above
or together with the
above awareness
training, the
contractor shall
include and provide
the awareness
training on water
quality issues and its
importance for
protection to all the
project employees at
the start of the
project
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 34 of 65
PEI-04
Fugitive Dust
Emission
(Impact on Air
Quality)
Increased dust level in the
air with amplified particulate
matters is mainly caused
with the access road
rehabilitation/construction,
stockpiles and other civil
repair work activities, and
may temporarily hinder
visibility for workers and
local communities. The
increased vehicle
movements / traffic also
produces a lot of fugitive
dust emission and add
more adverse impact on the
air quality
25 Workforce & community awareness on potential environmental & social risks of dust
emission and all other project related environmental and social issues along with the best
practice to be followed at the project site by the workforce, drivers/operators and the local
community shall be provided;
26 All dusty project access will be continuously water sprinkled by watering trucks so that
surfaces remain damp at all times when in use during the construction period. The
Contractor will make provisions to have an adequate amount of water and appropriate
equipment to disperse water onsite at all times, Again some stretches of unpaved road
which are required to be used frequently shall be graveled ;
27 All stockpiles will be located away from sensitive receptors and covered & shielded
against wind storms where necessary to ensure protection of ambient air from dust
emission during the construction period.
28 Controlled blasting shall be carried out to minimize fugitive dust emission spreading to
wider areas;
29 All vehicle and other construction machineries movements will be subject to risk
assessment (which therefore allows for the incorporation of project-specific controls) and
all drivers/operators will be inducted in health, safety, social and environmental issues);
30 Speed limits (example: maximum 30 km/ hour for heavy vehicles and 40km for light
vehicles), defensive driving policies will be strictly implemented and monitored;
31 A grievance redress mechanism (will be further elaborated later in the following sections)
will be put in place to address grievances from local communities if they are not satisfied
on such issues;
Contractor with the
directives and
supervision of the
PMO and PMC
(Hill)
Similar to the above
or together with the
above awareness
training, the
contractor shall
include and provide
the awareness
training on dust
emission and air
quality issues and its
importance for
protection to all the
project employees at
the beginning of the
project
PEI-05
Vehicular and
Equipment/Gen
erator Exhaust
Emission
(Impact on Air
Quality)
Exhaust emissions from
generators, vehicles and
batching plant may
deteriorate the local
ambient air quality.
Operation of vehicles,
equipment and machinery
will produce exhaust
emissions, which could
impact on the ambient air
quality by GHG emission in
the air. The access road
32 Regular maintenance and servicing of vehicles and equipment will be conducted in
accordance to the manufacturers’ specifications to maintain efficiency and keep emissions in
check;
33 Efforts will be made to use new, fuel-efficient and low emissions machinery and vehicles;
34 All emission-producing equipment will be operated only when necessary and unnecessary
idling of equipment will be avoided;
35 Batching plant & other equipment shall be set up near the work site and away from
communities and also considering the wind direction so that the nearby communities are
not affected by the emissions from batching plant;
36 A grievance redress mechanism (will be further elaborated later in the following sections)
will be put in place to address grievances from local communities if they are not satisfied
on such issues;
Contractor with the
directives and
supervision of the
PMO and PMC
(Hill)
Similar to the above
or together with the
above awareness
training, the
contractor shall
include and provide
the awareness
training on air quality
issues due to
vehicular &
equipment /
generator exhaust
emissions in the air
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 35 of 65
and other civil repair works
will engage substantial
construction equipment and
vehicle like: Loader
Backhoes, Dump Trucks,
Vibrator Roller, Water
Bowser, Excavator,
Dumpers, Mechanical
Winch, Dump Trucks,
Diesel Generators,
Dewatering Pumps, Jack
Hammer, Welding Plants,
Air Compressor, Concrete
mixers, etc.
and its importance
for protection, to all
the project
employees at the
beginning of the
project and also at
regular intervals
PEI-06
Damage of
Infrastructure
due to Blasting
Blasting and drilling near
any civil structures like
houses, schools, mosques,
shrines, commercial
buildings etc. may cause
damage of the structure if
safe distances are not
maintained. Apart from that
noise and vibrations
produced from these
activities would also create
nuisance to the
surrounding communities
and wildlife.
37 Controlled and muffled blasting techniques will be adopted at all times when required;
38 The day, time, hour and the minute at which the actual blasting will be conducted must be communicated to all the surrounding communities. All the people surrounding the project site must know the routine of blasting;
39 As a precautionary measure, sirens must be sounded prior to blasting in order to
prepare/forewarn the community;
40 Safe distances acceptable worldwide will be maintained.
Contractor with the
directives and
supervision of the
PMO and PMC
(Hill)
Similar to the above
or together with the
above awareness
training, the
contractor shall
include and provide
the awareness
training on damages
caused by blasting
and its importance
for cautiousness, to
the employees at the
beginning of the
project and also at
regular intervals
PEI-07
Noise Nuisance
and Vibration
Noise will be generated
from project construction
activities and could become
a nuisance to the local
communities within the
vicinity of the project site
41 Adherence to national noise regulations as stipulated in the National Environmental Law
2007 and EIA Regulations (2008) will be ensured;
42 Noise monitoring will be undertaken within the project area and at nearby sensitive
receptor sites during construction and operation period of the project;
43 Noisy equipment will be sited with regard to or away from sensitive receptors whenever
possible;
Contractor with the
directives and
supervision of the
PMO and PMC
(Hill)
Similar to the above
or together with the
above awareness
training, the
contractor shall
include and provide
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 36 of 65
and at nearby human
settlements. The major
sources of noise and
vibration will be mainly from
moving vehicles, operation
of construction equipment,
blasting, drilling, batching
plant and noise generated
by the construction
workforce.
44 A proper routine and preventive maintenance procedure for project vehicles and equipment
should be set and followed with the respective manufacturers which would help prevent
noise and vibration levels;
45 Provision of proper Personal Protective Equipment (PPEs), i.e., ear muffs and plugs, will
reduce noise impact on personnel;
46 Movement of vehicles should be restricted to project area only;
47 : Idling of machinery including vehicles should be prohibited, unless necessary;
48 Blasting will be done on a scheduled basis after proper discussion with the local
communities.
the awareness
training on noise and
vibration, and its
importance for
protection, to all the
project employees at
the beginning of the
project and also at
regular intervals
PEI-08
Siltation due to
Earthen Dyke
Construction /
Removal
The construction of
temporary earthen dyke
proposed at the intake will
pollute the water with silt
downstream temporarily
during construction /
removal requiring mitigation
measures
49 Following strictly the designed dimensions, the earthen dyke shall be constructed with full
stability / safety considerations. The expected siltation due to the dyke construction /
removal shall be controlled to the minimum possible by use of silt control mesh system at
the bottom & sides of the dyke as required;
50 Material for the construction of the dyke shall be sourced considering environmental
aspects including drainage pattern, stability, vegetation and public infrastructure. The
removed dyke materials shall be disposed to the designated location.
Contractor with the
directives and
supervision of the
PMO and PMC
(Hill)
Similar to the above,
the contractor shall
include and provide
awareness training
on the siltation due
to earthen dyke & its
control measures
EEI-01
Loss of
Vegetation and
Crops
The temporary use of land
immediately adjacent to the
road restoration and land in
and around the camps and
storage areas would result
in some localized scrub
clearance and temporary
loss of scrub, weedy plants
and bushes vegetation and
may also disturb the soil
bonding causing soil
erosion
51 The site clearing exercise will be controlled and limited to only that which is required for
the project components. Workers will be prohibited from removing vegetation outside
clearing marked areas of intervention;
52 Will prevent vegetation trampling by restricting access to the site along a designated
route. Movement of equipment (vehicles, contractors and the entire construction crew)
will be limited to the designated access roads – off-road driving will be prohibited;
53 Periodic trainings of the project staff and workers will be conducted on
ecology/biodiversity conservation issues to sensitize them on the need of such scrubs,
plants and biodiversity;
54 If any private crops need to be removed or damaged, proper compensation as per the
local laws and in compliance with ADB regulation will be made to the owner after
discussing the issue with the local authorities.
Contractor with the
directives and
supervision of the
PMO and PMC
(Hill)
Similar to the above
the contractor shall
include and provide
the awareness
training on the loss
of vegetation / crops,
and its importance
for protection, to all
the project
employees at the
beginning of the
project and also at
regular intervals
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 37 of 65
SEI-01
Occupational
Health and
Safety Issues
The occupational health
and safety program will aim
to ensure that the
workplace is safe and
healthy by addressing the
hazards & accident risks
and work related
diseases/illness risks at the
workplace; outlining the
procedures and
responsibilities for
preventing, eliminating and
minimizing the effects of
those hazards and risks;
identifying the emergency
management plans for the
workplace; and, specifying
how consultation, training
and information are to be
provided to employees at
workplaces.
55 Responsible ESMMP team along with health and safety supervising personnel would be
appointed – at site to ensure all occupational health and safety matters, be responsible
for maintaining records of all accidents and all health and safety issues at each site, the
number of accidents and its cause, actions taken and remedial measures undertaken;
56 To ensure safety, install warning signboards and symbols in risky and hazardous areas,
to inform workers to be careful;
57 Ensure that materials are all stacked, racked, blocked, interlocked, or otherwise secured to prevent sliding, falling, or collapse causing harm/ accident to the workers;
58 Remove all scrap and waste material from the immediate work area as the work progresses to avoid accidents of workers with such materials;
59 Use only trained staff to construct, install and repair all electrical equipment to prevent risks of electrical shocks and electrocution;
60 Install fire extinguishers and/or other fire-fighting equipment at every work site to prepare for any accidental fire hazards;
61 Ensure the prevention of accident risks to workers by providing them with essential “Personal Protective Equipment (PPE)” like helmet, eye protector, dust masks, earplugs, safety gloves, etc. to all workers at site free of cost;
62 Will maintain a record of all accidents and injuries that occur at the work site and reviewed monthly / quarterly for any corrective actions.
63 Any casualty or injury resulting from occupational activities should be compensated by the contactor as per the law /Act of the country. Where compensation is sought by the injured party, proper procedures for documentation of the case will be followed, including a detailed report on the accident, written reports from witnesses, report of the examining doctor and his/her recommendation for treatment.
64 Establish measures to prevent risks of accidents due to site traffic including developing a code of conduct for safe driving on site, speed limit, etc.
Contractor with the
directives and
supervision of the
PMO and PMC
(Hill)
Similar to the above
or together with the
above awareness,
the contractor shall
include and provide
the awareness
training on
occupational health
and safety issues,
importance to use
PPEs, Emergency
Preparedness Plan
in case of any
accidents or
incidences, to all the
project employees at
the beginning of the
project and also at
regular intervals
SEI-02
Community/Publ
ic Health Issues
including
Impacts of Poor
Sanitation and
Waste
Management
System:
The impacts of influx of
workforce from outside may
bring & spread
communicable diseases in
their temporary camps or to
the local communities. The
main concerns with such
an influx of workers
include: (i) Risk of
communicable diseases
spreading in the local
community; (ii) Waste and
65 The site specific health and safety action plan including waste management has to be
implemented properly to ensure control of any communicable diseases and other health
related issues, emergency response at the project site. MM-02 to MM-013 are some
summarized major such safety plans;
66 Responsible ESMMP team along with health and safety supervising personnel would be
appointed – at site to ensure all community health and safety issues and also be
responsible for maintaining records of all people visiting health facility;
67 As per the procedure for hiring foreign workers, all contractors are required to make all
prospective workers undergo medical tests to screen for diseases and sicknesses, prior to
selection and employment of any foreign worker. In addition to this, the Project
Management will also undertake sudden, unannounced checks on workers to look for
diseases such as HIV, STDs, and hepatitis. This is being suggested because surprise
checks in projects are important and if such cases are detected, the contractor will be
required to immediately release the worker from the site.
Contractor with the
directives and
supervision of the
PMO and PMC
(Hill)
Similar to the above
or together with the
above awareness,
the contractor shall
include and provide
the awareness
training on
community / public
health and safety
issues including
communicable
diseases, sanitation
and domestic wastes
issues and its
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 38 of 65
sewage entering the local
environment and invite
vectors to transmit
diseases. Wastes
generated may be poorly
handled and disposed of.
Such domestic wastes that
may include food waste,
food packaging and
materials brought to site by
construction workers,
sewerage overflows among
others, will be generated
during the project
construction as well as
operational phase. If not
properly handled, they may
turn out to be a sanitation
hazard as well as attract
insects, rats, flies etc. and
may bring various
diseases. And also the
plastic wastes may affect
the health of the
ecosystem. In the
community area, plastic
wastes may also affect the
health of livestock if
ingested
68 First Aid Kits/facilities should be made available by the contractor to all the workforce camps and work sites at all times of the project period;
69 The Contractor must institutionalize procedures to deal with emergencies such as sudden illness and other health related emergencies. Ensure that workers are aware of procedures to be followed in case of illness or emergencies such as informing the focal health person who in turn will arrange the necessary emergency communication, transportation and treatment requirements appropriately according to the need of the hour;
70 The provision of communal kitchens will ensure that workers do not have to be exposed to emissions from individual kitchen and can avoid illness from the kitchen harmful emission;
71 All organic waste generated at labour campsites such as food stuffs shall be collected
and transported by the contractor to designated landfills/composting sites within the
project area;
72 Ensure that all waste will be removed from site and transported by a licensed waste carrier for proper disposal. Biodegradable and non-biodegradable wastes will be properly segregated during collection;
73 All waste generated from demolition of built up structures should be sorted
(biodegradable, non-biodegradable, Metals, Glasses) by the contractor and disposed of
appropriately at designated waste disposal sites;
74 A mobile toilet for use by the construction supervision personnel will be in place at the
construction sites and the work camps, and emptied regularly by a licensed waste
contractor;
75 Anti-vermin safeguards (such as covering bins with lids) for waste segregation will be put in place
76 During the project activities, the first priority will be to reduce, re-use and recycle waste in
preference to disposal;
77 Creation of grievance redressed mechanism (GRM) to protect rights and health of community and the project workforce.
importance to
manage, to all the
project employees at
the beginning of the
project and also at
regular intervals.
Also awareness on
emergency
preparedness plan.
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 39 of 65
SEI-03
Working Terms
& Conditions
and
Management of
Workforce
Relationship
To ensure harmony at the
project site amongst
clients, contractors,
workers and local
community is essential for
good progress of the work.
To maintain such harmony,
the contractors have to play
vital roles from long before
the start of work at site
starting with fair employees
and workforce selection
process providing
transparent site situation,
their rights and
responsibilities to be
complied with according to
local labour laws and the
standards so that the
workforce will not expect
more when they reach the
site and constructions
activities are started.
78 A proper contract document is prepared by the contractors with the workforce clearly
stating their working conditions, terms of employment at the start of their employment to
avoid future misunderstanding and complications. Also establish these employment
terms and conditions along with other general information in a suitable project site for
the employee’s as well as general reference.
79 Ensure that all the employees are adequately trained for their respective jobs and
positions;
80 Ensure that the construction workforce are provided suitable and good quality temporary
accommodation at project site;
81 Ensure policy strategy prohibiting use of child (under 18 years of age) labour or forced labour in the construction activities;
82 Ensure that workers are not prohibited or discouraged from forming or joining workers’ organizations and communicate/complain to staff on recruitment, etc.;
83 Ensure policies of non-discrimination, and equal opportunity in recruitment and promotions;
84 Ensure a workers’ grievance redress mechanism for workers to submit reasonable workplace concerns and communicate procedures to workers upon recruitment. Record all such grievances, and resolutions, and provide feedback to workers.
Contractor with the
directives and
supervision of the
PMO and PMC
(Hill)
Similar to the above
or together with the
above awareness,
the contractor shall
include and provide
the awareness
discussions on
workforce
contractual terms
and their obligations
and restrictions at
site
SEI-04
Blockade of
Access of Local
Community
Right of Way
due to Project
Construction
Activities
Prioritization
The possibility of blockade
of access for the local
community is high due to
construction work on the
project. The contractor will
assure the access by
scheduling the work or by
alternate access in
consultation with local
community during
construction period. Also
85 Arrange alternate access to the local community during the construction work;
86 Also look for the possibility to tackle the problem with work scheduling and rescheduling
of road blockade timings;
87 Ensure that the road blockade will not obstruct the local communities during emergencies
such as sudden illness and accidents in the communities;
88 Ensure proper consultation with the community focal persons on their right of way
discussion and also encourage grievance/complaints mechanism procedures from the
public.
Similar to the above
or together with the
above, the contractor
shall include and
provide the
awareness training
on the importance of
community right of
way issue and the
ways and means to
solve the issue.
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 40 of 65
such blockade sometimes
may cause trouble during
emergencies and need to
make alternate
arrangements to ensure no
long term disturbances to
be caused with the project
to the public right of way /
navigation on the
river/canal or any other
community activities.
SEI-05
Disturbances on
Community
Privacy/Safety
and Site
Security
The local communities are
living in settlements mostly
in family groups where
they, especially women
freely move around for their
daily livelihood activities.
The probably of
disturbance in the privacy
of local people near
contractor’s camp with
workforce from outside is
possible as they will not
feel comfortable. The
contractor will assure the
privacy of local people by
establishing camp at a
reasonable distance from
local settlements with
proper fencing and restrict
the mobility of labor to the
community areas and
unlawful entry into the
camps for camp safety.
89 Contractor’s camps to maintain a reasonable distance from local population;
90 Restrictions on the mobility of workers to the community areas;
91 Ensure constructions of appropriate fencing around the camps and storage areas which will prevent unlawful access to and from the project site;
92 Ensure to hire security responsible personnel with proper gate and entry system for the security of the site with control of un-authorized entrance into the project site;
93 Ensure proper signboards are erected with proper instructions on the entry and leaving
the sites
Contractor with the
directives and
supervision of the
PMO and PMC
(Hill)
Similar to the above
or together with the
above, the
contractor shall
include and provide
the awareness
training on the
importance of
community privacy
and safety and
security of the
project site and the
ways and means to
tackle the situation
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 41 of 65
SEI – 06
Community
Interactions and
Conflicts
between the
Workers and the
Locals to
Increase
With interactions with the
community due to influx of
outside workforce, the
chances of conflicts and
tensions between workers
and locals are high as the
local people would not like
the mobility of the workers
in the community. The
contractor will make sure a
harmony between workers
and local community
through a permanent
liaison with community
elders and by maintaining a
reasonable distance of the
camp site from the local
population.
94 Contractor’s camps to maintain a reasonable distance from local population;
95 Restrictions on the mobility of workers to the community areas;
96 Ensure job priority for the local people with expertise required by the project;
97 Ensure regular liaison and discussion with community elders by the contractors to avoid any conflict and unrest;
98 Ensure a community grievance redress mechanism is in place to enable the local community to voice their complaint and concerns from the project activities. A community communication plan to guide these discussions shall be prepared by the contractor.
Contractor with the
directives and
supervision of the
PMO and PMC
(Hill)
Similar to the above
or together with the
above, the
contractor shall
include and provide
the awareness
training on the
importance of project
site harmony without
conflicts and
tensions with the
local community and
the ways and means
to tackle the situation
including workforce
restrictions and
limitations.
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 42 of 65
ANNEXURE-2: Overall Environmental and Social Monitoring Plan
ENVIRONMENTAL &
SOCIAL ISSUES
Monitoring Objective Key Performance indicators for
Monitoring Action
Proposed Monitoring
(Type of Monitoring
Action)
Frequency Monitoring
Responsibility
and Records
Reporting and
Responsibility
ESMP Objective
(Impact Ref)
General Issues Ensure Contractor's site
preparedness for
ESMMP implementation
Site ESMMP set-up & ESMMP team in
place with required tools / equipment and
various site plans, awareness training to all
employees, community discussions/briefing
Contractor to submit to
PMO the set-up team &
tools / equipment list,
site plans
At start of
construction
Hill/PMO to verify
and log in
Register / file
Contractor &
PMO/Hill to
indicate in monthly
report
Baseline Issue Establish baseline
information for future
monitoring purpose
Soil quality/properties, air quality, water
quality, noise level
Contractor to carry out
tests and provide the
baseline test results to
PMO/Hill
At start of
construction
Hill/PMO to check
and log the results
for reporting
Contractor &
PMO/Hill to
include in monthly
report
Soil Contamination (Soil Quality Issue)
Ensure strict
management on
site to reduce
risks on soil
contamination as
identified in ESMP
for the identified
potential impact
PEI-01
Ensure the
implementation on site
the best practice
mitigation measures
identified for the impact
PEI-01
1. Fuel storage area are with proper lining
and cement base not to allow fuel
seepage / penetrate into the soil;
2. Checking the preventive maintenance
records of motorized equipment &
vehicles to avoid fuel / oil leakage and
spills;
3. Checking spills and determining fueling
methods of the equipment and vehicles;
4. Checking site generated hazardous
wastes are disposed properly at
designated sites;
5. Generator to be installed on an
impervious floor with sufficient area
around for O&M;
6. Grease and fuel traps are provided on
site for containing the spills and also on
emergencies;
7. Check evidences of signboards for fuel
tanks and tanks and type of fuel, etc.;
8. Check evidence of spill control kits
Visual check by going
around the site and also
record/log checking of
the contractors records
At start of
the fuel/oil
storage and
regular
interval – at-
least weekly
to see if any
spill
incidents,
occur etc.
By contractor’s
ESMMP team and
verified by
PMO/Hill team
Contractor &
PMO/Hill to
include in monthly
report
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 43 of 65
ENVIRONMENTAL &
SOCIAL ISSUES
Monitoring Objective Key Performance indicators for
Monitoring Action
Proposed Monitoring
(Type of Monitoring
Action)
Frequency Monitoring
Responsibility
and Records
Reporting and
Responsibility
ESMP Objective
(Impact Ref)
availability at site near the fuel storage
areas;
9. Check on the spill emergency plan and
number of staff trained for any such
incidents;
10. Check the adequacy of soak pits and
septic tanks and their conditions;
11. Check evidence of waste segregation
bins installed at site, cleanliness of the
camp areas and find how these wastes
are being disposed-off.
Soil Erosion Issue
Ensure strict
management on
site to reduce
risks on soil
erosion as
identified in ESMP
for the identified
potential impact
PEI-02
Ensure the
implementation on site
the best practice
mitigation measures
identified for the impact
PEI-02
12. Check site evidence that the vegetation /
scrubs are present at both sides of the
restored access road, around storage
area and camps as per the baselines;
13. Evidence and record of water sprinkled
along the access road and around
blasting sites.
14. Evidence and record of controlled
blasting;
15. Evidence of some retaining / breast walls
for unstable areas of the access road,
etc.
16. Evidence of drains constructed to avoid
soil erosion, etc.
17. Evidences of renewed areas with re-
vegetation like quarry sites, muck
disposal sites, and along roadsides, etc.
after closure of the work.
Visual inspections by
going around the site and
also record/log checking
of the contractors
records
At start of
the project
construction
and regular
interval – at-
least weekly
to see if
lapses and
soil erosion
occurred.
And at end
of each
activity for
sl.no.17.
By contractor’s
ESMMP team
and verified by
PMO/Hill team
Contractor &
PMO/Hill to include
in monthly report
Water Contamination (Water Quality Issue)
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 44 of 65
ENVIRONMENTAL &
SOCIAL ISSUES
Monitoring Objective Key Performance indicators for
Monitoring Action
Proposed Monitoring
(Type of Monitoring
Action)
Frequency Monitoring
Responsibility
and Records
Reporting and
Responsibility
ESMP Objective
(Impact Ref)
Ensure strict
management on
site to reduce
risks on water
contamination
(both surface &
underground) as
identified in ESMP
for the identified
potential impact
PEI-03
Ensure the
implementation on site
the best practice
mitigation measures
identified for the impact
PEI-03
18. Proper monitoring with evidences and
checking from sl. no. 1 to 17 above while
managing for the reduction of identified
impacts PEI-01 and PEI-02, the
monitoring for impact reduction on water
quality (both surface and underground)
will also be taken care adequately
covering mitigation measures from 18 to
24 under ESMP table of Annexure-1.
Visual inspections by
going around the site and
also record/log checking
of the contractors
records
Similar to
the above as
for the soil
contaminatio
n and
erosion
issue.
By contractor’s
ESMMP team
and verified by
PMO/Hill team
Contractor &
PMO/Hill to include
in monthly report
Impact on Air Quality
Ensure strict
management on
site to reduce
risks on fugitive
dust generation
which causes air
pollution as
identified in ESMP
for the identified
potential impact
PEI-04
Ensure the
implementation on site
the best practice
mitigation measures to
reduce dust generation
from construction
related activities,
harmful gaseous
emissions from project
vehicles movements
and equipment
operation as identified
for the impact PEI-04
and PEI-05.
19. Evidence of awareness training to
workforce, drivers, operators and
community members on importance of air
quality and how they could help avoiding
dust generation, harmful gaseous
emissions into the air, etc.
20. Check - evidence/record of proper
prevention and suppression measures
and procedures available to avoid air
pollution on site, some of which were
identified as mitigation measures listed in
the ESMP under sl. no. 26 to 36 and
include the following:
Stockpile covers,
Speed limits signboards,
Water sprays and water sprinkle
trucks,
Gravel and hard road surfaces
Wheel washers,
1. Regular Monitoring:
Visual inspections by
going around the site
and also record/log
checking from the
contractor’s
maintained records
throughout the
construction phase.
2. Auditing by an
independent agency
at the end of
construction and
mainly compared in
respect with the
baseline information
and test results
At start of
the project
construction
and regular
interval – at-
least weekly
to check if
lapses for air
pollution
occurred.
And auditing
towards the
end of the
construction
By contractor’s
ESMMP team
and verified by
PMO/Hill team
Contractor &
PMO/Hill to include
in monthly report.
Special Audit report
at the end of the
construction.
Also safeguard
with stringent
measures the
vehicular and
equipment /
generator exhaust
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 45 of 65
ENVIRONMENTAL &
SOCIAL ISSUES
Monitoring Objective Key Performance indicators for
Monitoring Action
Proposed Monitoring
(Type of Monitoring
Action)
Frequency Monitoring
Responsibility
and Records
Reporting and
Responsibility
ESMP Objective
(Impact Ref)
emission, which
causes air
pollution as
identified in
ESMP for the
potential impact
PEI-05.
Equipment and vehicles conditions and
their maintenance records
Equipment operation timing and
engine switch-off records
Quarry locations and conditions
Dredging process and dredged
materials quality.
Grievance redress mechanism records
The dredging of
canal and sand
removal will need
to be carefully
done to avoid
sand and dust
blown away in the
air to cause air
pollution
Damage of Infrastructure due to Blasting
Ensure with strict
measures to
restrict damages
of infrastructure
and pollution to
be caused by
blasting as
identified in
ESMP for the
potential impact
PEI-06.
Ensure the
implementation on site
the best practice
mitigation measures by
proper monitoring for
identified impact PEI-06
21 Evidence of controlled & muffled
undertaken by the contractor;
22 Evidence of the routine of blasting and
information notice shared with the
community for the timing of the blasting;
23 Signboards and sirens setup evidences;
24 Signboards evidences for safe distance
and not to make entry beyond that point
for people to follow
Visual inspections by
going around the site and
checking all the
infrastructures nearby
the project site and also
record/log checking from
the contractors records
Visual check
& inspection
to be carried
out short
after the
blasting and
also
regularly on
a weekly
basis for
cracks
By contractor’s
ESMMP team
and verified by
PMO/Hill team
Contractor &
PMO/Hill to include
in monthly report
Noise Nuisance and Vibration
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 46 of 65
ENVIRONMENTAL &
SOCIAL ISSUES
Monitoring Objective Key Performance indicators for
Monitoring Action
Proposed Monitoring
(Type of Monitoring
Action)
Frequency Monitoring
Responsibility
and Records
Reporting and
Responsibility
ESMP Objective
(Impact Ref)
Ensure with strict
measures to
restrict noise
generation by on-
site project
activities and the
workforce, and
determine if the
identified
mitigation
measures in
ESMP are
appropriate for
the potential
impact PEI-07.
Monitor to ensure the
implementation on site
the best practice
mitigation measures for
identified impact PEI-07
25 Check on evidence of discussions with
local community members on the
project activities awareness on impacts
like noise nuisance and vibration and re-
scheduling work activities requirements
for community to plan accordingly;
26 Check from local community complaints
on workforce noisy disturbances and
use of horns, vehicle traffic entering the
community areas outside the
construction sites, through grievance
redress mechanism (GRM) records;
27 Monitor regularly (quarterly/half yearly)
the noise level at sensitive areas and
compare in reference to Afghan
National Environmental laws and
regulations;
28 Check that only scheduled & controlled
blasting being undertaken;
29 Check evidence on provision of
appropriate PPEs for the workforce to
prevent from noise and nuisance
vibration;
30 Evidence of vehicles and equipment
idling and /or operated for unnecessary
purpose;
31 Monitor if routine and preventive
maintenance of project vehicles,
equipment and plants are being
undertaken to reduce unnecessary
noise generated from them.
Visual inspections by
going around the site and
checking also record/log
from the contractor’s
records. Also check on
the regular noise level
tests results.
At start of
the project
construction.
Daily
inspections
and also at
regular
interval like
quarterly to
check if
lapses for
noise level
tests. And
auditing by
an
independent
agency at
end of the
construction,
which will be
the baseline
for
operational
phase.
By contractor’s
ESMMP team
and verified by
PMO/Hill team
Contractor &
PMO/Hill to include
in monthly report
Also ensure
strictly on site
appropriate
measures to limit
noise nuisance by
construction
traffic as identified
in ESMP for
potential impact
PEI-07
Determine strictly
on site
appropriate
measures to
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 47 of 65
ENVIRONMENTAL &
SOCIAL ISSUES
Monitoring Objective Key Performance indicators for
Monitoring Action
Proposed Monitoring
(Type of Monitoring
Action)
Frequency Monitoring
Responsibility
and Records
Reporting and
Responsibility
ESMP Objective
(Impact Ref)
reduce noise
nuisance and
vibration caused
by project
equipment and
site plants
identified in
ESMP for
potential impact
PEI-07
Siltation Issue due to Temporary Earthen Dyke Construction / Removal at the Intake
Ensure strict
management on
site to reduce
siltation risks
downstream due
to earthen dyke
construction /
removal as
identified in ESMP
for the potential
impact PEI-08
Monitor to ensure the
implementation on site
the best practice
mitigation measures
identified for the impact
PEI-08
32 Check site evidence that the silt mesh
system is placed properly and silt in the
downstream water flow is minimum or
free of silt.
33 Check the constructed dyke is stable /
safe and no scouring occurs;
34 Evidence of awareness training records
to workforce on siltation due to earthen
dyke construction/removal and its
control measures.
Visual inspections by
going around the site and
also record/log checking
of the contractors.
During the
construction
of the dyke
and regular
checks on
scouring for
dyke stability
and safety
after the
construction
By contractor’s
ESMMP team
and verified by
PMO/Hill team
Contractor &
PMO/Hill to include
in monthly report
Loss of Vegetation and Crops
Ensure strict
management on
site to reduce
risks on loss of
vegetation & crops
as identified in
Monitor to ensure the
implementation on site
the best practice
mitigation measures
identified for the impact
EEI-01
35 Check site evidence that the vegetation
/ scrubs are present at both sides of the
restored access road, around storage
area and camps as per the baselines.
Check on evidence of re-vegetation;
36 Evidence of awareness training records
to workforce & community on avoiding
Visual inspections by
going around the site and
also record/log checking
of the contractors
records
At start of
project and
regular
interval – at-
least weekly
to see if
lapses on
By contractor’s
ESMMP team
and verified by
PMO/Hill team
Contractor &
PMO/Hill to include
in monthly report
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 48 of 65
ENVIRONMENTAL &
SOCIAL ISSUES
Monitoring Objective Key Performance indicators for
Monitoring Action
Proposed Monitoring
(Type of Monitoring
Action)
Frequency Monitoring
Responsibility
and Records
Reporting and
Responsibility
ESMP Objective
(Impact Ref)
ESMP for the
identified potential
impact EEI-01
vegetation / crops tempering / clearing,
off-road driving outside of the project
activity boundary and also on the
importance of ecology / biodiversity
conservation;
37 Evidence of private crops compensation
if any crops damage to be checked from
local complaint record of GRM.
scrubs
removal is
done outside
of the project
boundary.
And at end
of each
activity for
re-
vegetation.
Occupational Health and Safety Issues
Ensure strict
management on
site to the
occupational
health & safety
mechanism and
preparedness to
reduce risks on
work related
accidents and
illness to project
workforce, local
communities and
visitors as
identified in ESMP
for the identified
potential impact
SEI-01
Monitor to ensure the
implementation on site
the best practice
mitigation measures
identified for the impact
SEI-01 and also
determine if the listed
mitigation measures are
appropriate for the
reduction of all the
impacts.
38 Check on evidence of record/log
keeping system established in place at
site with dedicated trained personnel for
the proper occupational health and
safety (OHS) concerns covering:
OHS plan including risk assessment
Accident including traffic/illness
logging system
List of “First Aid” facility
Accident & emergency plan
Awareness /training to workforce /
community members materials
records
39 Evidence of warning signboards
indicating risky and hazardous areas;
40 Evidence of safety followed at site in
stacking construction materials to avoid
accidents to workers and locals/ visitors;
41 Evidence of cleaner work sites without
scarps and waste at the work vicinity;
42 Evidence of trained contractor’s staff for
Visual inspections by
going around the site and
also record/log checking
of the contractors
records
At start of
the project
construction
and regular
interval – at-
least weekly
to see if
lapses on
OHS
concern.
By contractor’s
ESMMP team
and verified by
PMO/Hill team
Contractor &
PMO/Hill to include
in monthly report
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 49 of 65
ENVIRONMENTAL &
SOCIAL ISSUES
Monitoring Objective Key Performance indicators for
Monitoring Action
Proposed Monitoring
(Type of Monitoring
Action)
Frequency Monitoring
Responsibility
and Records
Reporting and
Responsibility
ESMP Objective
(Impact Ref)
erection and installation of all electro-
mechanical equipment to avoid
accidents with electrical shocks &
electrocution;
43 Evidence for fire safety preparedness
on all sites with firefighting equipment
installed;
44 Check the evidence of essential PPEs
list provided to the workers at site to
avoid work possible accidents;
45 Existence of workforce temporary but
secure camps /shelters and suitable
safety fencings.
Community/Public Health Issues including Impacts of Poor Sanitation and Waste Management System
Ensure strict
management on
site to reduce the
risk of community
health issues with
the influx of
project workforce
and project
activities as
identified in the
ESMP for the
identified potential
impact SEI-02
To ensure the
implementation on site
the best practice
mitigation measures
identified for the impact
SEI-02 and also
determine if the listed
mitigation measures are
appropriate.
46 Check from evidence of record/log
keeping system established in place at
site on dedicated trained health person
for the comprehensive ‘community
health and safety’ (CHS) issues
covering:
CHS & waste management plans
including emergency preparedness
List of “First Aid” facility
Workers medical screening records
prior to selection for the project work
Common communicable diseases
prevalent & treatment records
Awareness /training to workforce /
community members materials
records including emergency
preparedness provision
47 Evidence checklist on the site readiness
Visual inspections by
going around the site and
also record/log checking
of the contractors
records. Sudden
unannounced checks at
site during the
construction. Community
health and safety audit
once.
At start of
the project
construction
and regular
interval – at-
least weekly
to see if
lapses on
CHS occur.
Audits once
towards the
end of the
construction
By contractor’s
ESMMP team
and verified by
PMO/Hill team
Contractor &
PMO/Hill to include
in monthly report
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 50 of 65
ENVIRONMENTAL &
SOCIAL ISSUES
Monitoring Objective Key Performance indicators for
Monitoring Action
Proposed Monitoring
(Type of Monitoring
Action)
Frequency Monitoring
Responsibility
and Records
Reporting and
Responsibility
ESMP Objective
(Impact Ref)
for waste management system
including:
Provision of safe and healthy
workforce camps / shelters in place
Communal kitchen provision
Waste collection & segregation
system with suitable bins in place for
different types of generated wastes
including hazardous wastes
Designated waste disposal sites and
suitable disposal system to remove all
waste from the sites including waste
disposal contractors for hazardous
waste removal
Existence of mobile toilet in place
Existence of GRM in place.
Working Terms & Conditions and Management of Workforce Relationship
Ensure strict
management on
site for good
workforce and
contractors’
relationship to
help proper
management of
project workforce
and project
activities as
identified in the
ESMP for the
identified potential
To ensure the
implementation on site
the best practice
mitigation measures
identified for the impact
SEI-03 and also
determine if the listed
mitigation measures are
appropriate to suitably
handle the identified site
situation.
48 Evidence of employment contracts
between contractors and workforce;
49 Evidence of skills and training provided
to various works as per work
requirements
50 Check for evidence of good and
secured temporary site
accommodations
51 Evidence on:
Transparency on employment
selection process
Anti-discrimination policy in place and
also put into practice for recruitment
Contractor’s system to provide
general information to all employees
Visual inspections by
going around the site and
also record/log checking
of the contractors
records. Interacting and
discussing with
contractor, workers and
the local community.
At start of
the project
construction
and regular
interval – at-
least
monthly to
see if lapses
occur.
By contractor’s
ESMMP team
and verified by
PMO/Hill team
Contractor &
PMO/Hill to include
in monthly report
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 51 of 65
ENVIRONMENTAL &
SOCIAL ISSUES
Monitoring Objective Key Performance indicators for
Monitoring Action
Proposed Monitoring
(Type of Monitoring
Action)
Frequency Monitoring
Responsibility
and Records
Reporting and
Responsibility
ESMP Objective
(Impact Ref)
impact SEI-03 Employees’ training /qualifications
Anti-child and forced labour
employment
GRM in place for both employee and
employer
Workers are not prohibited or
discouraged from forming / joining
organization and make complaints.
Contractor’s regular interactions and
meetings with the workforce and the
community members and other
stakeholders.
Blockade of Access of Local Community Right of Way due to Project Construction Activities Prioritization
Ensure strict
management on
site to minimize
project impacts on
local community
with access and
right of way
blockade as
identified in the
ESMP for the
identified potential
impact SEI-04.
To ensure the
implementation on site
the best practice
mitigation measures
identified for the impact
SEI-04 and also
determine if the listed
mitigation measures are
appropriate to minimize
the impacts.
52 Evidence of access blockade and
alternative access for the local
community;
53 Evidence of contractor’s discussions
with community members for work
rescheduling and timing change for road
access blockade;
54 Evidence for emergency plan if
emergency occurred in the community
during such access blockade;
55 Evidence of GRM in place for the
community
Visual inspections by
going around the site and
also record/log checking
of the contractors
records.
At start of
the project
construction
and regular
interval – at-
least weekly
to see if
lapses
occur.
By contractor’s
ESMMP team
and verified by
PMO/Hill team
Contractor &
PMO/Hill to include
in monthly report
Disturbances on Community Privacy/Safety and Site Security
Ensure strict
management on
site to minimize
project
To ensure the
implementation on site
the best practice
mitigation measures
identified for the impact
56 Evidence of location of workforce camps
at a reasonable distance away from the
community
57 Evidence of restriction notice to the
workforce to the community areas;
Visual inspections by
going around the site and
also record/log checking
of the contractors
records.
At start of
the project
construction
and regular
interval – at-
By contractor’s
ESMMP team
and verified by
PMO/Hill team
Contractor &
PMO/Hill to include
in monthly report
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 52 of 65
ENVIRONMENTAL &
SOCIAL ISSUES
Monitoring Objective Key Performance indicators for
Monitoring Action
Proposed Monitoring
(Type of Monitoring
Action)
Frequency Monitoring
Responsibility
and Records
Reporting and
Responsibility
ESMP Objective
(Impact Ref)
disturbances on
community privacy
as well as site
security as
identified in the
ESMP for the
identified potential
impact SEI-05.
SEI-05 and also
determine if the listed
mitigation measures are
appropriate to minimize
the impacts.
58 Evidence of fencing around the
camps/sites with proper gates and
security persons at the gate for
restrictions of in and out movements of
workers as well as visitors;
59 Evidence of appropriate signboard
installed
60 Evidence of GRM in place
least weekly
to see if
lapses
occur.
Community Interactions and Conflicts between the Workers and the Locals to Increase
Ensure strict
management on
site to restrict
conflicts between
the project
workers and the
local community
as identified in the
ESMP for the
identified potential
impact SEI-06.
To ensure the
implementation on site
the best practice
mitigation measures
identified for the impact
SEI-06 and also
determine if the listed
mitigation measures are
appropriate for the
purpose.
61 Evidence of location of workforce camps
at a reasonable distance away from the
community
62 Evidence of restriction notice to the
workforce to the community areas;
63 Evidence of local people priority for
recruitment as per the skill
requirements;
64 Evidence of regular liaison by contractor
with the local community elders to avoid
conflicts and unrest;
65 Evidence of GRM in place.
Visual inspections by
going around the site and
also record/log checking
of the contractors
records.
At start of
the project
construction
and regular
interval – at-
least weekly
to see if
lapses
occur.
By contractor’s
ESMMP team
and verified by
PMO/Hill team
Contractor &
PMO/Hill to include
in monthly report
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 53 of 65
ANNEXURE-3: Email Issued to Strengthening EMP Setup & Establish Baselines
Email issued to contractor for strengthening environmental, health and social safeguard
set-up & directions to establish baseline references control points at the project site:
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 54 of 65
ANNEXURE-3A: Non-compliance Repeated Notice for Documentations/Reports
Letter issued to contractor for environmental documentations and reports submission on
environmental baselines, awareness trainings/inductions and progress report
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 55 of 65
ANNEXURE-4: Project-Site Photo- Log
Some Site Photos Related to ESMMP Implementation
Complaints Boxes Installed for GRM Initiatives
Initiatives of First Aid Kit Provision at Site
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 56 of 65
Waste Bins Implementation at Site
Implementation on use of PPEs at Site and Weekly Tool Box/PPEs Induction /Training
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 57 of 65
Implementation of Safety and Information Signboards at Site
Main Entrance to Base Camp and Powerhouse Complex
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 58 of 65
Downstream Right Bank of Powerhouse-Proposed Retaining Wall & Slope Protection
Downstream left Bank of Powerhouse – Proposed Retaining Wall for Slope Protection
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 59 of 65
Base Camp Containers and Bore-hole/well location for Camp Water Supply
Peripheral Wall for Safety and Security Reasons of Powerhouse and Base Camp
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 60 of 65
Fencing done to Restrict Workers’ Movement to Agricultural Land
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 61 of 65
ANNEXURE-5: Test Results PH of Soil
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 62 of 65
ANNEXURE-6: Test Result PH of Water
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 63 of 65
ANNEXURE-7: Monthly Medicine Log Sheet (June 2016)
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 64 of 65
ANNEXURE-8: Complaint Letter from Local Community
Complaint Letter 1
Gereshk Electricity Services Improvement project (Rehabilitation of Gereshk Hydropower Plant) ESDIP Tranche 3, ADB Grant 0280
Bi-annual Environmental Monitoring Report, January-June 2016, PMO / PMC (HILL) Page 65 of 65
Complaint Letter-2