4
ITEM DESCRIPTION UNIT QUANTITY UNIT COST (SR) Unit Cost in Words TOTAL (SR) A Included - B - C Included - 1 Site administration, management, programming, reports, etc. - Included - 2 Material submittals and Shop Drawings submitted as hard copies in Auto Cad latest version. L.S. - Included - 3 Installation of Project Informatory Signs and other relevant information, i.e., detour hazard signs, warnings, and other safety barriers and signages as required by Owner. L.S. - Included - 4 Cleaning and Watching L.S. - Included - 5 As Built Drawings in the latest Revit 2019. L.S. - Included - 6 Safety Officer in charge of daily site safety measures L.S. - Included - 7 Protective Clothing (uniforms) bearing Company Name L.S. - Included - 8 Hard Hats,Safety Shoes, Fire Extinguishers, Safety Goggles for eye protection L.S. - Included - DATE : All manpower and/or staff shall be absolutely under the Contractor's sponsorship. No sub-contractors will be allowed unless required for specialized works and approved by Owner. Contractor shall adhere to the required qualifications of project Key Personnel's, to be submitted for approval of the Owner, as follows: Project Manager - min. 8 years experience in the installation of electrical equipment (Electrical Engineer) Site Engineer - min. 5 years experience in experience in the installation of Elevators or other Conveying systems (Electrical Engineer). (as required) Safety Officer - min. 5 years experience as a Safety Officer.(as required) Planner/ Scheduler - min. 5 years experience as a construction planner/ scheduler as required. Entrance of heavy equipment to be used in the project shall be coordinated with the KFSH&RC Security Department KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTRE ENGINEERING PROJECTS MANAGEMENT DIVISION BILL OF QUANTITIES Project: EDMD-1039 -REPLACEMENT OF UNINTERRUPTIBLE POWER SUPPLY (UPS) UNITS IN THE HOSPITAL BUILDINGS AND RESIDENTIAL AREAS Div. 01 - GENERAL REQUIREMENTS The following is (but not necessarily limited to) the list of preliminary items as set and described in the contract documents or required to complete the project. If the Contractor fails to price any item of the list, it shall be deemed that no charge is to be made, or the item is covered in other rates elsewhere. Workers Safety and Protective Measures, that MUST be priced by the Contractor, as follows: Total Division No. 01 (C/F to Summary) CONTRACTOR : Included

ENGINEERING PROJECTS MANAGEMENT DIVISION BILL OF QUANTITIES

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ENGINEERING PROJECTS MANAGEMENT DIVISION BILL OF QUANTITIES

ITEM DESCRIPTION UNIT QUANTITY UNIT COST (SR) Unit Cost in Words TOTAL (SR)

A Included -

B

-

C Included -

1 Site administration, management, programming, reports, etc. - Included -

2Material submittals and Shop Drawings submitted as hard copies in Auto Cad

latest version.L.S. - Included -

3

Installation of Project Informatory Signs and other relevant information, i.e., detour

hazard signs, warnings, and other safety barriers and signages as required by

Owner.

L.S. - Included -

4 Cleaning and Watching L.S. - Included -

5 As Built Drawings in the latest Revit 2019. L.S. - Included -

6 Safety Officer in charge of daily site safety measures L.S. - Included -

7 Protective Clothing (uniforms) bearing Company Name L.S. - Included -

8 Hard Hats,Safety Shoes, Fire Extinguishers, Safety Goggles for eye protection L.S. - Included -

DATE :

All manpower and/or staff shall be absolutely under the Contractor's sponsorship. No sub-contractors will

be allowed unless required for specialized works and approved by Owner.

Contractor shall adhere to the required qualifications of project Key Personnel's, to be submitted for

approval of the Owner, as follows:

Project Manager - min. 8 years experience in the installation of electrical equipment (Electrical Engineer)

Site Engineer - min. 5 years experience in experience in the installation of Elevators or other Conveying

systems (Electrical Engineer). (as required)

Safety Officer - min. 5 years experience as a Safety Officer.(as required)

Planner/ Scheduler - min. 5 years experience as a construction planner/ scheduler as required.

Entrance of heavy equipment to be used in the project shall be coordinated with the KFSH&RC Security

Department

KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTREENGINEERING PROJECTS MANAGEMENT DIVISION

BILL OF QUANTITIES Project: EDMD-1039 -REPLACEMENT OF UNINTERRUPTIBLE POWER SUPPLY (UPS) UNITS IN THE HOSPITAL BUILDINGS AND

RESIDENTIAL AREAS

Div. 01 - GENERAL REQUIREMENTS

The following is (but not necessarily limited to) the list of preliminary items as set and described in the contract documents or required to complete the project. If the

Contractor fails to price any item of the list, it shall be deemed that no charge is to be made, or the item is covered in other rates elsewhere.

Workers Safety and Protective Measures, that MUST be priced by the Contractor, as follows:

Total Division No. 01 (C/F to Summary)

CONTRACTOR :

Included

Page 2: ENGINEERING PROJECTS MANAGEMENT DIVISION BILL OF QUANTITIES

Bill of QuantitiesREPLACEMENT OF UNINTERRUPTIBLE POWER SUPPLY (UPS) UNITS IN THE HOSPITAL BUILDINGS AND RESIDENTIAL AREAS

ITEM DESCRIPTION UNIT QUANTITY UNIT COST (SR) Unit Cost in Words TOTAL (SR)

1

2

3

4

5

6

7

8

DATE :

Contractor shall prepare and submit detailed shop drawings, samples, technical reports and other submittals as required per the Tech Spec requirements for approval prior to

implementation.

Structures,surfaces and or services outside the limits of construction damaged or affected by the construction activities shall be restored by the contractor without additional cost

against the KFSHRC.

All works shall comply with applicable building codes and regulations and Hospital and Infection Control building requirements.

The Contractor shall investigate the site to assess all obstructions and/or existing buildings and structures, installations and works that may affect the work.

It is the responsibility of the Contractor to determine the precise location of all existing utilities and under ground services within the project limit and to protect them from any

damage during his work.

Contractor shall assure that all works will be executed with minimal interruption / shut-down of service utilities on all affected areas.

The Contractor shall check all existing site conditions himself and compare it with the new drawings and requirements. It shall be deemed that the Contractor has included in

his prices the cost of removal and demolition and modifications of all obstructions even for those that might not be specifically indicated under the item description in the B.O.Q.

DIVISION 02 - EXISTING CONDITIONS

All existing service utilities interfacing with the affected structures and installations shall be safely disconnected by the Contractor at the points decided by the Owner before the

commencement of any works and shall be appropriately terminated and capped. All existing structures and equipment that are not demolished adjacent or within the work site

shall be properly protected for the duration of the work.

The costs shall include all labor, equipment, tools, construction barriers, etc. used, disposal of debris from site,capping-off all affected utility services and

patch up/ restoration of affected adjacent surfaces as required. In addition, the following shall be considered in the cost:

GENERAL NOTES:

CONTRACTOR :

13 Sept 20212 of 2

Page 3: ENGINEERING PROJECTS MANAGEMENT DIVISION BILL OF QUANTITIES

Replacement of UPS Units in Hospital Bldg and Residential Areas

ITEMSPECS

DIVISION No.SECTION

ETIMAD

ITEM CODEDESCRIPTION UNIT QUANTITY UNIT COST (SR) TOTAL (SR)

1 26 263353 2084UPS 60KVA, 3PH - 480V, 3Ph, 60Hz input voltage, 220-127V, 3Ph, 60 Hz, output

voltage with 30 minutes battery autonomy , (MH-PABX, LEV-0)No. 2

2 26 263353 2084

Replacement of the existing battery units for HITA UPS system, 2V, 400AH

Batteries,SLA type, including installation and re-connection of existing battery

cables. Works to include removal and disposal of the old batteries. HITA

UPS RM, LEV-1).

No. 770

3 26 263353 2084UPS 5KVA, 1PH - 220V, 1Ph, 60Hz input voltage, 220-127V, 3Ph, 60 Hz, output

voltage with 30 minutes battery autonomy, (Complex-E)No. 1

4 26 263353 2084UPS 60KVA, 3PH - 480V, 3Ph, 60Hz input voltage, 220-127V, 3Ph, 60 Hz, output

voltage with 30 minutes battery autonomy, (MH-PABX, LEV-0)No. 1

5 26 263353 2084UPS 10KVA, 3PH - 220V, 3Ph, 60Hz input voltage, 220-127V, 3Ph, 60 Hz, output

voltage with 30 minutes battery autonomy, (WC-SS#15-LEV-1)No. 1

6 26 263353 2084UPS 20KVA, 3PH - 220V, 3Ph, 60Hz input voltage, 220-127V, 3Ph, 60 Hz, output

voltage with 30 minutes battery autonomy, (MCV-PABX, LEV-1)No. 1

7 26 263353 2084UPS 60KVA, 3PH - 380-400V, 3Ph, 60Hz input voltage, 220-127V, 3Ph, 60 Hz, output

voltage with 30 minutes battery autonomy, ( NT-PABX,LEV-0)No. 1

8 26 263353 2084UPS 30KVA, 3PH - 220V, 3Ph, 60Hz input voltage, 220-127V, 3Ph, 60 Hz, output

voltage with 30 minutes battery autonomy, ( OPB,D2-LEV-2)No. 1

9 26 263353 2084UPS 15KVA, 3PH - 220V, 3Ph, 60Hz input voltage, 220-127V, 3Ph, 60 Hz, output

voltage with 30 minutes battery autonomy, ( MH-OR-LEV-2)No. 1

10 26 263353 2084UPS 40KVA, 3PH - 380-400V, 3Ph, 60Hz input voltage, 380-400V, 3Ph, 60 Hz, output

voltage with 30 minutes battery autonomy, ( ANGIO-HE-LEV-2)No. 1

11 26 263353 2084UPS 10KVA, 3PH - 220V, 3Ph, 60Hz input voltage, 220-127V, 3Ph, 60 Hz, output

voltage with 30 minutes battery autonomy, (OPB-OR-LEV-4)No. 1

12 26 263353 2084UPS 200KVA, 3PH - 380-400V, 3Ph, 60Hz input voltage, 380-400V, 3Ph, 60 Hz,

output voltage with 30 minutes battery autonomy, ( TOXICOLOGY-HE-LEV-1)No. 1

13 26 263353 2084

Supply, Testing & Commissioning of new Neutral Grounding Resistor(NGR) 400A,

System Voltage 4160Vac, L-N 2400 Vac, 6-ohms type ANG, for the MV/MV power

transformer of Chiller No-6. Works to include disconnection and removal of the

temporary NGR and re-insttallation of the NGR in the power transformer of Chiller

No.4 located at Powerhouse Transformer Room, (Powerhorhouse-Chiller #6)

Job 1

15% VAT

IN NUMBERS (SAR)

TOTAL BID COST

CONTRACTOR

STAMP AND SIGNATURE

DIV DESCRIPTION TOTAL BID IN WORDS

26 ELECTRICAL

SUMMARY

KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTREENGINEERING PROJECTS MANAGEMENT DIVISION

BILL OF QUANTITIES

EDMD-1039 -REPLACEMENT OF UNINTERRUPTIBLE POWER SUPPLY (UPS) UNITS IN THE

HOSPITAL BUILDINGS AND RESIDENTIAL AREAS

UNINTERRUPTIBLE POWER SUPPLY (UPS) : Supply, testing and commissioning of Static Uninterruptible Power

Supply (UPS) System including batteries, battery rack, conduits, cables and circuit breakers. Supply & installation

of DC cables and termination between UPS-BCB-Batteries, installation and termination of input/output cables,

extension and jointing of the existing power cables as needed, and all other required components for a complete

and functional UPS System. Retermination of existing BMS general/common fault alarm for the new UPS. Works

shall include disconnection and removal of the the old UPS units and accessories and handover to the hospital

maintenance department.

Subtotal

Grandtotal

13 Sept 2021 Page 1 of 1

Page 4: ENGINEERING PROJECTS MANAGEMENT DIVISION BILL OF QUANTITIES

ي مبنى المستشفى والمناطق السكنيةى

.استبدال وحدات إمداد الطاقة اللامنقطعة ف

القسمقسم المواصفات رقمالبندكود البند في

منصة اعتماد(ريال سعودي)التكلفة الإجمالية (س.ر)التكلفة الإفرادية الكميةالوحدةالبيان

1262633532084 60 مراحل، ذات جهد كهربائي داخل 3 فولت، 480- مراحل3 كيلو فولت أمبير، 60وحدة إمداد الطاقة اللامنقطعة

دقيقة، 30 هيرتز وبطارية ذات مدة تشغيل تصل إلى 60 مراحل، ذات جهد كهربائي خارج 3 فولت، 127-220هيرتز،

(MH-PABX, LEV-0)

2عدد

2262633532084

أمبير من نوع 400 فولت وبطارية 2استبدال وحدات البطاريات الحالية لنظام إمداد الطاقة اللامنقطعة بقوة

SLAالعمل على إزالة البطاريات القديمة . ، بما في ذلك، تركيب كابلات البطاريات القائمة وإعادة تركيبها

.(1)المستوى / نظام إمداد الطاقة اللامنقطعة. والتخلص منها

770عدد

3262633532084 60 مرحلة، ذات جهد كهربائي داخل 1 فولت، 220- مرحلة1 كيلو فولت أمبير، 5وحدة إمداد الطاقة اللامنقطعة

30 هيرتز وبطارية ذات مدة تشغيل تصل إلى 60 مراحل، وذات جهد كهربائي خارج 3 فولت، 127-220هيرتز،

(هـ- المجمع)دقيقة،

1عدد

4262633532084 60 مراحل، ذات جهد كهربائي داخل 3 فولت، 480- مراحل3 كيلو فولت أمبير، 60وحدة إمداد الطاقة اللامنقطعة

30 هيرتز وبطارية ذات مدة تشغيل تصل إلى 60 مراحل، وذات جهد كهربائي خارج 3 فولت، 127-220هيرتز،

(MH-PABX, LEV-0)دقيقة،

1عدد

5262633532084 60 مراحل، ذات جهد كهربائي داخل 3 فولت، 220- مراحل3 كيلو فولت أمبير، 10وحدة إمداد الطاقة اللامنقطعة

30 هيرتز وبطارية ذات مدة تشغيل تصل إلى 60 مراحل، وذات جهد كهربائي خارج 3 فولت، 127-220هيرتز،

(WC-SS#15-LEV-1)دقيقة،

1عدد

6262633532084 60 مراحل، ذات جهد كهربائي داخل 3 فولت، 220- مراحل3 كيلو فولت أمبير، 20وحدة إمداد الطاقة اللامنقطعة

30 هيرتز وبطارية ذات مدة تشغيل تصل إلى 60 مراحل، وذات جهد كهربائي خارج 3 فولت، 127-220هيرتز،

(MCV-PABX, LEV-1)دقيقة،

1عدد

7262633532084 60 مراحل، ذات جهد كهربائي داخل 3 فولت، 400-380- مراحل3 كيلو فولت أمبير،60وحدة إمداد الطاقة اللامنقطعة

30 هيرتز وبطارية ذات مدة تشغيل تصل إلى 60 مراحل، وذات جهد كهربائي خارج 3 فولت، 127-220هيرتز،

(NT-PABX,LEV-0 )دقيقة،

1عدد

8262633532084 60 مراحل، ذات جهد كهربي داخل 3 فولت، 220- مراحل 3 كيلو فولت أمبير، 30وحدة إمداد الطاقة اللامنقطعة

30 هيرتز وبطارية ذات مدة تشغيل تصل إلى 60 مراحل، وذات جهد كهربائي خارج 3 فولت، 127-220هيرتز،

(OPB,D2-LEV-2 )دقيقة،

1عدد

9262633532084 60 مراحل، وذات جهد كهربائي داخل 3 فولت، 220- مراحل 3 كيلو فولت أمبير، 15وحدة إمداد الطاقة اللامنقطعة

30 هيرتز وبطارية ذات مدة تشغيل تصل إلى 60 مراحل، وذات جهد كهربائي خارج 3 فولت، 127-220هيرتز،

(MH-OR-LEV-2 )دقيقة،

1عدد

10262633532084 مراحل، وذات جهد كهربائي داخل 3 فولت، 400-380- مراحل3 كيلو فولت أمبير، 40وحدة إمداد الطاقة اللامنقطعة

30 هيرتز وبطارية ذات مدة تشغيل تصل إلى 60 مراحل، وذات جهد كهربائي خارج 3 فولت، 400-380 هيرتز، 60

(ANGIO-HE-LEV-2 )دقيقة،

1عدد

11262633532084 60 مراحل، وذات جهد كهربي داخل 3 فولت، 220- مراحل3 كيلو فولت أمبير، 10وحدة إمداد الطاقة اللامنقطعة

30 هيرتز وبطارية ذات مدة تشغيل تصل إلى 60 مراحل، وذات جهد كهربائي خارج 3 فولت، 127-220هيرتز،

(OPB-OR-LEV-4 )دقيقة،

1عدد

12262633532084 60 مراحل، ذات جهد كهربائي داخل 3، 400-380- مراحل 3 كيلو فولت أمبير، 200وحدة إمداد الطاقة اللامنقطعة

30 هيرتز وبطارية ذات مدة تشغيل تصل إلى 60 مراحل، وذات جهد كهربائي خارج 3 فولت، 400-380هيرتز،

(TOXICOLOGY-HE-LEV-1 )دقيقة،

1عدد

13262633532084

L-N 2400 فولت للتيار المتردد، و 4160 أمبير وجهد النظام 400توريد واختبار وتشغيل مقاوم التأريض المحايد

العمل على تضمين فصل وإزالة مقاوم . 6 للجهد المتوسط ومحول الطاقة للتبريد رقم ANG أوم للنوع 6للتيار المتردد، و

الطاقة ) الموجود في غرفة محول الطاقة الكهربائية 4التأريض المؤقت وإعادة تركيبه في محول الطاقة للتبريد رقم

(6الكهربائية للتبريد رقم

1المهمة

ضريبة القيمة المضافة15%

(الريال السعودي)بالأرقام

إجمالي قيمة العرض

المتعاقد

الختم والتوقيع

إجمالي قيمة العرض بالحروفالبيانالقسم

الأعمال الكهربائية26

الملخص

مستشفى الملك فيصل التخصصي ومركز الأبحاثقسم إدارة المشاريع الهندسية

جدول الكميات

EDMD-1039 - استبدال وحدات إمداد الطاقة اللامنقطعة في مبنى المستشفى والمناطق السكنية.

توريد واختبار وبدء تشغيل نظام إمداد الطاقة اللامنقطعة الاستاتيكي بما يشمل البطاريات وحامل البطارية وقنوات الأسلاك والكابلات :وحدة إمداد الطاقة اللامنقطعة

توريد وتركيب كابل التيار المباشر وتوصيل أطراف بطاريات وحدة إمداد الطاقة اللامنقطعة وقاطع الدائرة الكهربائية للبطارية وتركيب .وقواطع الدائرة الكهربية

الخارجية، وتمديد وتوصيل كابلات الطاقة، حسب الاقتضاء، وجميع المكونات المطلوبة لعمل نظام إمداد الطاقة اللامنقطعة بشكل / وتوصيل أطراف الكابلات الداخلية

تتضمن الأعمال .شائع في نظام إدارة البطارية من أجل وحدة إمداد الطاقة اللامنقطعة الجديدة/ إعادة توصيل أطراف الإنذار الخاص بوجود خلل عام .كامل وفعال

.فصل وإزالة وحدة إمداد الطاقة اللامنقطعة القديمة وملحقاتها وتسليمها إلى قسم الصيانة بالمستشفى

الإجمالي الفرعي

الإجمالي الكلي

13 Sept 20211 من 1صفحة