Renovation of Lobby Area, Restaurant Staff Accommodation, Driver
Quarters, Laundry, Common Washrooms, Kitchen and supply and
installation of generator including elevated generator room at NHR
Anuradhapura.
SLTDA/RM/W/NCB/Renovation - Anuradhapura (Phase-II)/2021/06
BILL OF QUANTITIES
Chief Engineer's office(Zone 3) Department of Buildings ,
Wilgoda Road,
Kurunegala.
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 2
CONTENTS Page No.
GENERAL NOTES S07-04
PRICING PREAMBLES S07-07
PRELIMINARIES S07-20
BILL NO 1 - DEMOLITION AND OTHER
A - DEMOLITION S07-26
B - EXCAVATION AND EARTH WORK S07-31
C - CONCRETE WORK S07-34
D - MASONRY WORK S07-37
COLLECTION - SUBSTRUCTURE -Bill No. 1 S07-38
BILL NO 2 - RENOVATION AND ALTERATION
C - CONCRETE WORK S07-39
D - MASONRY WORK S07-44
E - WATER PROOFING S07-45
F- STRUCTURAL WORK S07-47
G- METALWORK S07-54
H- CARPENTRY & JOINERY S07-71
J - ROOF AND ROOF PLUMBING S07-78
K- PLUMBING S07-81
L- WALL, CEILING AND FLOOR FINISHES S07-95
M- ELECTRICAL INSTALLATION S07-104
N - PAINTING S07-118
Q - HIGH PRESSURE LAMINATED PARTITION WORK S07-121
COLLECTION - SUPERSTRUCTURE -Bill No. 2 S07-122
BILL NO 3 EXTERNAL WORK
Q - EXTERNAL DRAINAGE S07-123
R- WASTE WATER TREATMENT UNIT AND STORM WATER DISPOSAL S07-130
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 3
S - GENERATOR ROOM S07-135
COLLECTION - EXTERNAL WORK -Bill No. 3 S07-137
BILL NO 4 MISCELLANEOUS WORK
MISCELLANEOUS WORK S07-138
COLLECTION - MISCELLANEOUS WORK -Bill No. 4 S07-139
GRAND SUMMARY S07-140
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 4
GENERAL NOTES
Extent of work :-
The extent of work as provided for in this Bill of Quantities consists of :-
(a) Full repair works to main building and boundry including
(b) Water supply
(c) Sewerage work
(d) Electrical Installation
(e) All other work as specified or shown in the drawings with respect to the above job.
Trade Names ;
Where trade names , brands and / or catalogue numbers are referred to sole preference to any material or
equipment is not intended . Any other material or equipment may be used, provided that the characteristics of
type, quality, appearance, finish, method of construction and / or performance is not less than specified and
provided also that approval is first obtained.
Method of Measurement
This Bill of Quantities has been prepared generally in accordance with the principles of "Method of
Measurement of Building Works(First Revision), Sri Lanka Standard 573:1999"
Measurements :
Tenderers are to note that, the measurements are taken absolutely nett. unless or otherwise stated.
Discrepancies :
Any discrepancy in Drawings, Specifications , Bill of Quantities or any other documents shall be brought to the
notice of the employer before tendering.
Payments :
Payments shall be made on actual quantity of work carried out at the site as per contract. The quantities given
in the Bill of Quantities are approximate.
The attention of the tenderer is drawn to the requirements of the contract, the specifications and any other
particulars of the tender . It is the tenderer's responsibility to see that his prices include for complying with all
the requirements of the conditions of contract and any other documents whether specifically referred to in the
Bill of Quantities or not.
The following products have been declared by the Government as products for which the "SLS" mark is
compulsory. Contractor must strictly comply with this requirement.
01). Cement Blocks SLS 855
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 5
02). Ordinary Portland Cement SLS 107
03). Masonry Cement SLS 515
04). Blended Hydraulic Cement SLS 1247
05). Portland Limestone Cement SLS 1253
06). Plain Steel Bar Reinforcement SLS 26
07). Ribbed Steel Bar Reinforcement SLS 375
08). Mild Steel Wire for General Engineering purposes SLS 139
09). Hot Rolled Steel Round Bars for Structural & General Engineering
purposes
10). Hot Rolled Steel Squre Bars for General Engineering Purposes
11). Hot Rolled Steel Hexagonal Bars for Structural & General
Engineering purposes
12). Hot Rolled Steel Flats for Structural & General Engineering
purposes
SLS 949 Part 1
SLS 949 Part 2
SLS 949 Part 3
SLS 949 Part 5
13). Hot Rolled Structural Steel "U" Sections (Channel) SLS 907 Part 3
14). Hot Rolled Structural Steel "L" Sections (Equal or Unequal Angles)
22). Household electric plugs & socket outlets SLS948 & SLS734
23). Household electric switches SLS 1000
This requirements shall also apply to building products declared by the Government as products for which
"SLS" Mark is compulsory subsequent to 3rd of March 2012.
Timber :
Unless otherwise specified in the respective Trades / Sections , the timber for all trades shall be as specified in
Carpentry and Joinery.
SLS 907 Part 4
15). Hot Rolled Structural Steel "T" Sections (tee's) SLS 907 Part 5
16). U PVC Pipes for portable cold water SLS 147
17). U PVC Pipe joints and fittings for portable cold water SLS 695
18). Clay Roofing tiles (flat tiles) SLS 2
19). Clay Ridge tiles SLS 2
20). Electric bulbs SLS 984
21). Household electric lamp holders SLS 138
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 6
All timbers under exceptional Circumstances, any equivalent timber to the given Species may be used with the
approval of the Engineer.
(Group-1): Door, Window and Fanlight Frames
Category A
Satin Palu Milla Ketakala Tulang
Halmilla Mee Hulanhik Wewarana Valdel.
Kohomba Jak Teak Path kela Kon
Category B Microcoris Grandis
(Group-2): Door , Window and Fanlight Sashes , Cupboards, Counters and Shelving
Category A Satin Tulan Halmilla Mahogany
Kohomba Wewarana Hulanhik Sooriya mara
Category B Ginisapu
(Group-3): Roof Framework
Category A
Madan Milla Palu Wewarana Tulang Mee Valdel. Micro Kolon Etathimbiri Jak Dun Ginisapu Alastonia
Category B Domba Grandis Saligna
(Group-4): Ceiling Framework and Partitions
Category A
Satin Palu Milla Ketakala Tulang
Halmilla Mee Hulanhik Wewarana Valdel.
Kohomba Etathimbiri Teak Panakka Lunumidella
Albesia
Category B Domba Grandis Cyprus Saligna Boron treated pinus Albesia
(Group-5): Valance Board and Valley Boarding
Category A
Kolon Tulang Val Del Kohomba Mahogany Satin Hulanhik Wewarana
Sooriya mara Jak Panakka
Category B Ginisapu Grandis
(Group-6): Beadings :
Alstonia Mahogany Lunumidella
(Group-7): Special Timber
(Group-8): Beeralu
Category A Satin Kolon Mahogany Sooriyamara
Category B Saligna
(Group-9): Skirting
Category A Kolon Teak Panakka Coconut Mahogany
Category B Saligna
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 7
1. GENERAL
PRICING PREAMBLES
a. The Bidder shall read and be conversant with the full description of workmanship and materials
as described in the Particular Specification and ICTAD Specification for the respective items of
work/ trades prior to the preparation of the Bid.
b. The Bidder shall refer to the relevant Clauses of Pricing Preamble when pricing composite item
of works.
c. The rate for each item must be comprehensive and must include for complying in all respects with
the requirements of the aforesaid specifications, these Pricing Preambles, cover all the obligations
under the Contract, and all matters and things necessary for the proper construction, completion
and maintenance of the Works. No claim for additional payment shall be allowed for any error or
misunderstanding by the Contractor of the work involved.
d. The rate for each item shall also include for all the following -
i. Labour and all connected costs ;
ii. Materials and goods including all connected costs;
iii. Preparatory works and setting out of particular item ;
iv. Complying with regulations of the Municipal Council and/or any other relevant authority under
which particular item of work is to be executed unless otherwise included in the Preliminaries ;
v. Fitting and fixing materials and goods in position, including hoisting to any height or lowering to
any depth and all temporary works, equipment and small tools ;
vi. Plant and equipment unless otherwise included in Preliminaries ;
vii. Handling of materials and working in situation where there is very restricted working space or no
working space ;
viii. Square cutting and Waste of materials ;
ix. Forming of ends, angles, miters and junctions between straight and raking or curved work ;
x. Protecting and cleaning ;
xi. All other incidental works and necessary works which are not described in the B.O.Q. but
described in the aforesaid specifications and or shown in the drawings for the proper completion
of the relevant item of work ;
xii. Establishment charges and overheads( not included in preliminaries or anywhere in the Bill Of
Quantities), and profits.
e. In addition to above, the rates for items of work in Substructure shall include for the works at
depths extending below ground water table where applicable including excavation under
water,removal and disposal of mud and sand and preparation of place to a condition suitable for
proper execution of the works.
Contd.,
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 8
2. EXCAVATION AND EARTHWORK
a. All works under this section are measured net and no working space is allowed.
b. The Contractor shall be responsible for the design and execution of the excavation method which
is subject to scrutiny by the Engineer. However, scrutiny by the Engineer shall not in any way
relieve the contractor of his responsibilities and duty of care.
c. Existing ground levels shown in the Drawings have been taken at the surface of the ground, with
no particular differentiation to indicate buried foundations, pavings etc.
d. The Contractor shall note that the rate for compacted earth fill and granular fill, stone, gravel and
sand beds shall include for imported materials or materials from borrow areas.
e. Dewatering has been measured under the Items,
(i). Bill No.01 (Substructure), and
(ii). Priliminary Item Number (36), for furnishing of water pumps.
f. Rates for Excavation & Earthwork shall include for -
i. Accepting site as found and preparing to condition suitable for proper execution of the Works
ii. Excavating by whatever means are necessary including excavation done manually or by machine
in any type of ground including ground with boulders (except rock) and excavation around existing
RCC. bored piles and jet grout piles ;
iii. Trimming sides, keeping clean and consolidating bottom of basement, sumps, pits
and trenches ;
iv. Backfilling and disposal of surplus excavated materials as specified and directed ;
Any necessary additional works required due to
v.
a. Working space required by the Contractor ;
b. Earthworks supports ;
c. Formwork ;
vi. Any additional trimming or appropriate back- filling to provide specified or approved formations and
profiles necessitated by the uneven excavation of the earth, unless otherwise measured
separately ;
g. Rates for compacted earth fill, granular fill and gravel and sand beds shall include for finishing
sub-grade to slopes and falls, depositing in layers, leveling, blinding, and machine or hand-
packing to form vertical or battered or level faces, and for forming sinking where required under
floor slabs or sub-floor layers.
h. Rates for approved damp-proof membrane shall include for laps, and straight, raking and
circular cutting, and for notching around all obstructions.
Contd.,
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 9
3. CONCRETE WORK
a. Rates for concrete work shall include for -
i. Mixing as per specification, depositing, handling, hoisting and placing at any height or depth ;
ii. In case of readymix concrete, transporting, admixtures, handling, pumping/hoisting and placing
at any height or depth ;
iii. Packing and tamping around reinforcement, including vibrating ;
iv. Contractor's designed kickers, construction joints and sealents ;
v. Finishing to slopes and falls, and preparing surface ready for screeds or paving, where necessary,
including cutting to sizes and temporary supports to form necessary grooves ;
vi. Curing ;
vii. Preparation of ground surface, grading to slope and falls, if any, and machine or hand packing to
form vertical or battered or level surface and all necessary formwork to edges of blinding concrete
in case of pile caps ground slab/ramps/beams.
FORMWORK
a. Formwork for similar concrete members are measured together irrespective of the height or
depth and the shape or form.
b. Extra-over rate for a particular type of high quality formwork should be applied only for the
areas of formwork which requires such high quality type formwork as specified.
c. Formwork shall be properly designed and strictly as described in the specifications for the
particular type of concrete surface finish and it should be sufficiently strong and grout tight.
d. Faces of Jet grouting piles, masonry and concrete work which will be formed or used as
formwork shall not be measured as formwork and no payment shall be made for same.
e. Rate for formwork shall include for -
i. Fabricating setting up and erection at any height or depth ;
ii. Strutting, supporting through lower floors and supporting at any level, including additional
propping, strutting and supporting decks ;
iii. Coating with shuttering oil and or lining ;
iv. Easing, striking and removing ;
v. Cleaning, preparing for reuse ;
vi. Removal when no longer required ;
vii. Props, stays, struts, wedges, bolts, incidental items and materials such as nails, screws
anchors hooks etc ;
Contd.,
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 10
viii. All overlaps and passing at angles ;
ix. Labour at intersections and narrow widths ;
x. Rubbing down and making concrete surface good after removal of formwork ;
xi. All fillets, to form grooves, rebates and throats, splays or chamfers, raking and circular cutting,
and cutting around all pipes, sleeves, conduits, ducting, metal sections and fittings ;
xii. Providing samples as required by the Engineer of the different formed finishes specified.
REINFORCEMENT
a. i. Standard length of reinforcing bar for the purpose of measurement shall be 6.0 m.
ii. Payment for bar reinforcement shall be to be nearest 0.01 Metric Ton.
orcement shall include for -
i. Rolling margin ; (Variations not paied under BOQ quantities)
ii. Preparation of bar bending schedules ; (Counted only if not considered under Priliminary Item
No. 21)
iii. Straightening as required and cleaning of bars ;
iv. Cutting, bending and binding ;
v. Hoisting and placing in position at any height or depth ;
vi. Binding wires, and cover blocks.
vii. Necessary spacers. (inevitable laps & chairs paid separately)
viii. Aligning and supporting in position during concreting.
PRECAST CONCRETE WORKS
a. Rates for precast concrete works shall include for -
i. Moulds and for formwork with the required finish to all exposed surfaces in accordance with the
specifications, hacking surfaces to form key for rendering etc, and hoisting to any height or depth
including providing any lifting holes or other devices to the approval of the Engineer,building in,
including bedding and jointing in mortar as required, and any necessary strutting and supporting.
ii. The requirements of the Pricing Preamble clauses which refer to Concrete Work,Reinforcement
and Formwork.
iii. Loading, transporting to Site, unloading, handling and stacking.
iv. Hoisting and fixing in position at any height or depth.
Contd.,
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 11
4. MASONRY WORK
a. In the calculation of the volumes of brick wall which are not multiples of the size of standard bricks,
the thickness of such walls shall be taken as the thickness of full bricks from which they can be
cut. The same principle of calculation of volume shall be used for all brickwork of which the cross-
sectional dimensions are not multiple of brick sizes.
b. Rates for brickwork/Block work shall include for -
i. Plumbing, angles,straight cutting,forming rebates,reveals and raking out joints for plastering;
ii. Splay cutting, rough cutting, fair cutting, forming chases or grooves for slabs, partitions,staircases,
roofs and the like, bonding ends of walls, building in or cutting and pinning in and making goods
on lintels, timber and steel works ;
iii. Building at any level or height of slabs or beams, additional labour in kerbs, isolated and attached
piers, all cutting, bonding at angles and intersections, building into or against adjacent work,
wedging and pinning up to soffits;
iv. Supplying and fixing metal clamps, Galvanized, steel boundary ties, and brick reinforcement etc;
v. Necessary cutting required in walls which are not multiples of brick size ;
vi. Preparing existing walls for raising and pinning new brickwork ;
vii. Bonding new walls to concrete faces and old walls where necessary, and materials to be used for
such bonding.
b1. Rates for Damp Proof Course shall include for -
i. Necessary leveling screed and trimming top of rubble/block/brick plinth wall ;
ii. Fair edges, rounded edges, drips and arises, angle fillets ;
iii. Turning nibs of asphalt into grooves ;
iv. Cutting to line and jointing new to old asphalt.
c. STONE WORK
Generally
Stones are defined as consolidated aggregates of one or more minerals and includes all types
of rock used in the construction industry.
c1 Rubble work
Rubble Stone masonry built of stones either irregular in shape as quarried or shaved and only
hammer dressed and having comparatively thick joints.
Rates for Rubble Masonry shall include for -
i. All joggles, cramps, dowels, ties, templates ;
ii. Plumbing, angles, fair returns, setting, jointing, eaves filling, pointing and fixing in position,
hoisting to any given height or depth ;
Contd.,
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 12
iii. Bonding ends of walls, rough cutting and fair cutting ;
iv. Leveling up in walling for Damp Proof Courses, sills, thresholds, string courses, copings and
the like ;
v. Forming straight vertical joints next to dressings, panels, brickwork etc ;
vi. Forming openings and dressed margins ;
vii. Forming chases, throats, rebates, margin flutes, sinking, chamfered and rounded edges, and
all labour connected therewith.
c.2 Ashlar Stone masonry using dressed stone blocks of given dimensions having faces
perpendicular to each other and laid in courses.
Rates for stone work shall include for:-
i Extra material for curved work
ii. All rough and fair cutting
iii. Dressing
iv. Forming rough and fair grooves, throats, mortices, chases, rebates, holes, stops and mitres.
v. Raking out joints for key
vi. Labours in eaves filling
vii. Dressed margins to rubble work
viii. Leveling uncoursed work
ix. Rough and fair square cutting
x. Centering
xi. Wedging up and pinning to concrete soffits and steel work
xii. Building in frames, flashing, damp proof courses including filling hollows of corner blocks with
mortar
xiii. Building in ties, lugs, plates, lintels, pipe sleeves, inserts, switch boxes and the like. As the
work proceeds.
c.3 Stone Veneering work (Face rubble work)
i Stone lining upto 80mm along planes parallel to natural bed. The natural bed may be masonry
of brickwork or rubbel work, concrete surface.
ii. Stones cut into slabs of required thickness.
iii. Dressed to very close tolerances.
5. WATER PROOFING
a. Rates for Water Proofing shall include for ;
i. For necessary leveling and trimming top of rubble/block/brick plinth wall ;
ii. Fair edges, rounded edges, drips and arises, angle fillets ;
iii. Forming internal and external angles, bonding bricks/blocks and the like ;
iv. Turning nibs of asphalt into grooves and asphalting around brackets ;
v. Cutting to line and jointing new to old asphalt ;
vi. Temporary screeds, ground and rules.
Contd.,
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 13
6. STRUCTURAL STEELWORK
a. Rate shall include for :
All shop fabrication work, including cutting, drilling, bolting, riveting, welding, grinding,
delivering, unloading, hoisting, erecting and fixing.
7. METAL WORKS
a. Type and quality of steel to be used for metal work shall be as per drawings and relevant
specification clause and or shall conform to latest British Standards.
b. Contractor to prepare shop drawings for approval of the Engineer.
c. Rates for Metal Work shall include for anchors, screws, dissimilar metals and providing thermal
movement and the preamble clauses for Structural Steel Work where relevant and they shall
apply equally to relevant items of this section.
Aluminum component
d. Fabrication & fixing of Aluminum components shall be carried out by experienced tradesman.The
Contractor shall furnish particulars of Aluminum fabricator through the engineer for his approval.
The Contractor will be required to furnish a guarantee on material and workmanship for a period
of 8 years from the date of handing over of Works in the form required by the employer, binding
the Aluminum manufacturer and the Contractor jointly and severally
e. Rate for Aluminum doors, windows & partitions shall include for
i. Glass and glazing
ii. All necessary ironmongery (For Doors; Door Locks, Door Handles and Door Closers shall be
quorted as separate Items in the BOQ)
iii. Furnishing shop drawings (materials & workmenship should be accordance with the
specifications given under the aluminium works)
Note: This component shall ignore, if the contractor intends to quote it under Preliminaries Item
No. 21
iv. Furnishing guarantee's as required by the employer
v. Sampling and submission of test reports to the engineer as directed
Qrwh=þwklvþfrpsrqhqwþvkdooþl¡qruh/þliþwkhþfrqwudfwruþlqwhqgvþwrþtxrwhþlwþxqghuþSuholplqdulh
8. ROOF COVERING AND ROOF PLUMBING
a. Rates for roof covering and roof plumbing shall include for :
i. Hoisting, placing and fixing in position ;
ii. Straight cutting, raking cutting, circular cutting, notching, and working around obstructions and
waste ;
iii. Nails, screws and the like ;
iv. Drilling and making holes or opening and the like;
Contd.,
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 14
b. Rates for flashings shall include for the following in addition to the requirement of "a" above -
i. Bending and cutting to required shape and forming roll edges ;
ii. Angles, edges and ends ;
iii. Notching over roofing ribs or dressing into roof cover/concrete as the case may be ;
iv. Forming and dressing into or around walls at obstructions and the like ;
v. Stepping up ;
vi. Sealing with sealant materials.
9. CARPENTRY(Roof and ceiling frame)
a. Sizes of all timber given are finished sizes.
b. All timber shall be well seasoned and treated against insect and termite attack before
fixing in position
c. Rates for carpentry shall include for -
i. Any type of cutting required, sawing, notching, drilling, trimming, framing, jointing, splayed edges
and the like, hoisting and fixing in position with nails, spikes, plugs, screws, and gluing and priming
to joints and ends ;
ii. Forming splayed edge, grooves, chamfers, scribed and rounded edge, beveling,molding and the
like ;
iii. Plugging, wedging, nuts and washers with bolts,sprockets and pins and the like ;
iv. Nogging or solid bridging, cut between studs or joints for structural timber.
v. Rebating, singings, grooving, mortising ;
vi. Additional timber lengths required for carpentry jointing ;
vii. Protection and keeping clean for staining, polishing or painting where applicable ;
d. Rates for roof decking shall include for machine sanding, protecting and preparing in addition to
the requirements c above.
e. Rates for walls and ceiling lining shall include for jointing and fixing to walls/ ceiling/ eaves etc. all
cover and joint strips, in addition to the requirements c above.
f. Rates for timber paneling/wall lining shall include for cover moldings, sills, stiles and head
moldings to openings as relevant.
10. JOINERY
a. Sizes of all timber given are finished sizes.
b. All timber shall be well seasoned and treated against insect and termite attack before fixing.
c. Timber used for joinery works shall be well seasoned well treated and in one species of special
class timber recommended for the particular class of Joinery works as specified in the
Specification.
Contd.,
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 15
d. Rates for Joinery shall include for -
i. Any type of cutting required, sawing, notching, drilling, trimming, planing, forming and jointing and
the like, fixing in position complete with nails, spikes, plugs, screws and gluing and priming to
joints and ends ;
ii. Forming splayed and tongued edges, rebates mortises, grooves, chamfers, scribed and rounded
edges, beveling, moulding, margin and the like and rounded corners, sinkings ;
iii. Working to stated sizes, for all short lengths making mitres, joints and ends ;
iv. Necessary bolts, dowels metal clips, anchors, grips and fixing joinery ;
v. Glueing, dowelling, plugging, wedging pining and the like ;
vi. Punching heads and filling with approved filler if nails or pins are used for fixing ;
vii. Countersinking and filling heads with approved filler, if brass screws are used for fixing ;
viii. Painting rebates of frames before fixing glass ;
ix. Bedding in cement mortar filling and hanging to frame lining ;
x. Keeping clean for staining, polishing or painting;
xi. Painting, Laquering or Varnishing as specified.
e. Preambles for Glazing section and a, b and c under Painting and Decorating section shall equally
apply to Joinery works.
f. Ironmongary
i. All cutting, fitting, sinking, boring, mortising ;
ii. Matching screws for ironmongery
iii. Removing during decoration, refixing after decoration, leaving oil and in proper working order on
completion and supplying and labeling all keys and handing over to Employer.
11. WALL,FLOOR AND CEILING FINISHES
a. i. All works under this trade shall be measured in m2 after deduction for voids,openings, doors and
windows
ii. All other small quantities/panels/narrow widths/ arises/ reveals/ angles/ ends/short lengths including
those of tiling work on door and window jambs and reveals are measured together with the
respective tiling item and labour in such work shall be included in the rate for the main finishing
item and they shall not be measured/paid separately.
b. Rates for wall, floor, ceiling finishings and wall floor screed and bedding shall include for -
i. All temporary rules, screeds, templates and supports, curing and cleaning off on completion
and exact thickness required to finish ;
ii. Caulked joints and making good and cutting around bolts, pipes conduits,sleeves, ducting,
fittings, sections, obstructions and the like ;
iii. Tamping and compacting ;
Contd.,
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 16
iv. Raking out joints of new brickwork/Block work or hacking concrete to form key, including
brushing, cleaning off and dampening ;
v. Forming internal and external angles and arises ;
vi. Any extra thickness required to finish to true levels ;
vii. Any additional dubbing out required to plastered surfaces of brickwork and to the finished
surface of concrete to obtain the requisite standard of finish ;
viii. Samples to be submitted for the approval of the Engineer.
c. Rates for tile slab or block finishing to floor and wall shall also include for the following in
addition to the above -
i. Straight raking and circular cutting ;
ii. Dubbing out or packing to concrete surface to correct deviations within specified tolerance ;
iii. Laying or finishing to falls or cross falls ;
iv. Expansion joints at perimeter and between bays where required in case of floor tile paving ;
v. Sand blasting, cleaning, waxing and appropriate floor finishings.
d. Rates for ceiling lining shall include for the following
i. Working to sides and soffits of attached or isolated beams and soffit of staircases where
relevant;
ii. Additional forming required for lighting and air-conditioning grills ;
iii. Straight, raking and circular cutting ;
iv. Neoprene sealing for air tightness around hatches if any ;
v. Matching edges where cutting occurs and for filling the heads of fixings with approved filler
vi. Painted mild steel hanging rods.
12. GLAZING
a. i. Type of Glazing shall be as specified.
ii. Thickness of glazing shall be as per the design of the approved specialist contractor who will
be engaged by the Contractor. However, the minimum thickness shall be 6mm.
b. Rates for Glazing shall include for -
i. Glazing, fixing, bedding priming and panel pins and other materials and labour for same and
cutting to size ;
ii. Templates, straight cutting, circular cutting, grinding edges or special type of edges required
and sand blasting ;
iii. Glazing beads, washlether or neoprene strip, glazing sealant, weather stripping, caulking joint
silicone joint ;
Contd.,
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 17
iv. Replacing cracked or broken glass ;
v. Making holes where necessary ;
vi. Samples to be submitted for the approval of the Engineer.
13. PAINTING AND DECORATING
Note
Colour and the quality of all paint and other painting materials shall be approved by the
Engineer prior to use.
a. Rates for painting shall include for -
i. Preparation of surfaces, cleaning down, smoothing, etc ;
ii. Submission of samples for the approval of the Engineer ;
iii. Protection of floors, walls and fittings etc ;
iv. Working to returns, painting in any colour, multi- colour works, cutting into line at junctions of
different colours at angles or plain surfaces, painting in small quantities ;
v. Cleaning down upon completion
b. Rates for work to isolated general surfaces shall include for working on door frames,
linings,window subframes (where of a differing material to the window), skirting, rails, architrave's,
bars,posts, balusters and the like.
c. Rates for work to glazed general surfaces, glazed windows and the like (measured both sides,flat
over glass, irrespective of size and panes) shall include for work to edges and glazing rebates,
returns and moldings of frames, mullions, transoms, architaves and the like.
d. Rates for work to pipes and conduits (which shall include trunking, ducting and the like) shall
include for all work on hangers, supports, brackets and the like.
14. PLUMBING
a. The rates for Plumbing shall include for :
i. Refer specifications for full description of materials and workmanship.
ii. Screws, nails, sockets, connectors, backnuts, nipples, and standard pipe fixing or supporting
clips, saddles, brackets straps, screws, nails, solder rivets connectors, flanges pipe sleeves,
brackets, made bend holder bats and the like.
iii. Short lengths, joints connections and couplers in running length.
iv. Sealing, fixing and support with holder bats or pipe clips cut and pinned built in wall or slabs.
v. Plugging screwing to walls or ceiling
vi. All laps, straight cutting and waste
vii. The fittings including bends, tees, collars, reducers elbows, valve sockets, junctions, caps and
the like for pipe less than or equal 50mm dia pipe.
viii. Jointing compound, solvent cement and incidental materials and labour.
ix. Connecting pipes to sanitary fixtures and appliances.
Contd.,
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 18
x. Standard and special pipe fixing arrangement where necessary fittings, supporting
clips,saddles,brackets, holder bats straps etc.
xi. All builders works such as chasing and forming holes through brick work/ blockwork/ foundations
and concrete slabs beams columns floor slabs manholes and like and making good all damages.
xii. Testing and disaffection after completion.
b. Rates for sanitary fittings shall include for
i. Fittings such as taps, waste water outlet, flushing cistern, internal overflows and the like and
supporting brackets, incidental materials for fixing.
ii. Assembling, jointing together, fixing components parts and jointing to pipes including necessary
coupling and for leaving perfectly clean undamaged and in perfect working order as on
completion.
c. Jointing and or connecting pipes to sanitary fittings.
Any special water supply and drainage fittings such as bends, tees, reducers etc. unless
otherwise specified separately in the Bill of Quantities, shall be deemed to have been included in
the relevant items and such items should accordingly be rated to include for such specials etc.
and for any extra work involved and the satisfactory completion of such items.
Where pipes pass through walls or slabs these shall be wrapped with a layer of inert materials.
For pipes exceeding 50 mm dia sleeve pipes shall be used for the full thickness of slabs, walls or
beams through which the pipes pass.
DRAINAGE WORK
a. The provisions and the clauses of precedence trades shall equally apply to relevant item of this
trade.
b. The rates for trench excavation for pipes shall include for depending and widening the trench as
necessary to enable the barrels of pipes of rest on firm and to facilitate jointing.
c. The rates for rock excavation in trench excavations shall include for importing selected materials
to replace any excavated rock which is unsuitable for back filling and for all additional rock
excavation and appropriate filling beyond the maximum measurable in accordance with the
specification.
d. The rates for concrete beds and surrounds to pipes shall include for flexible joints and any
necessary formwork where required by the specification.
15. ELECTRICAL INSTALLATIONS
a. The execution of Electrical Installation shall every respect comply with the current Regulations of
the Institute of Electrical Engineers, London, requirements of Ceylon Electricity Board and the
area Authority.
b. The rates for equipment and control area, distribution boards, meters, switches, fuses, etc. shall
include for connecting up, fixings and supports for the complete installation and for suitable
mounting boards, frames, supports, housings and cabinets where required.
c. The rates for cables, tape, bus-bar trunking etc. (except where included in sub circuits or electrical
points) and the like shall include for joints in the running length, all allowances for sagging snaking,
for drawings through conduits,laying in trunking of surface fixing where retired with cable
supports, clears, hangers, channels, insulators and the like.
d. i. The rates for cables and the like laid in benches shall include for drawing through conduits or ducts
where required.
ii. The rates for cable terminations shall include for all connections point boxes, insulating and jointing
materials, cable terminations glands, lock nuts, bushes and the like.
Contd.,
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 19
e.i. The rates for conduits trunking cable tray etc. (except where included in sub circuits of electrical
points) and the like shall include for all short lengths, joints and couplers in the running length,
and for all fixings and supports with approved saddles, crumpets, clips and the like cut and
pinned, built-in or plugged and screwed to walls or ceilings including chasing brick work, block
work, concrete slab beams walls columns and the like and make good.
ii. The rates for conduits and the like shall include for all bends, tees, socket and the like,cutting,
screwing, threading, jointing and providing all conduit boxes, junction boxes and the like.
f. The rates for the installation of sub main circuits, lighting points switched points, socket outlets,
fused spur outlets, isolators, etc. (other than those applicable to the distribution switch gear) shall
include where applicable, for all conduit, trunking, cable tray, cabling, terminations, fixings and
connections from the distribution
switched gear to and including the point (accessories measured separately) and shall be deemed
to include for any item mentioned in the Electrical installation Specification but not shown on the
drawings and vice-versa.
g. The rates for lighting fittings, fittings such as ceiling fans and extract fans, and for appliances such
as air- conditioning units shall include for assembly, fixing and connection from the spur outlet or
isolator to the fitting or appliance with all necessary additional wiring earthing and outlet roses
and leaving perfectly clean and undamaged on completion.
h. The rates for fixing only fittings and appliances provided by the employer should include in addition
to the foregoing for accepting delivery, storing and handling the fittings and providing any
additional materials and internal wiring.
j. The rates for connections only to fittings and appliances such as pumps, water heaters, air
conditioning units and extract fans shall include for connection from the isolator or spur outlet to
the fitting or appliance (these being measured separately) , with all necessary additional wiring,
earthing and outlet roses.
k. The rates for power outlets shall include for mounting boxes and frames.
l. The rates for power switched with remote outlets shall include for the additional outlet plates and
boxes.
m. The rates for switched socket outlets shall include for 1 No fused plug top and 4 No fuse links.
n. The preceding preambles shall apply equally to auxiliary installations such as TV installations,
telephone installations, and bell signal systems.
o. Painting of timber work and metal work.
p. If the items of electrical installation are measured as sub circuit point wiring or in electrical
points, the rates for such items shall include for :
i. The preceding clauses of this trade where relevant.
ii. Preparation of asbuilt drawings to be submitted to Employer at the handing
over/ practical completion.
iii. All items and accessories required for proper installation as per specification and
regulation up to load point and labour connected therewith.
iv. All wiring, conduiting and cables and labour connected therewith if not measured
separately.
v. Items specified in the specification but not shown in the drawings.
vi. Disconnecting and refixing of electrical fitting and appliances as required for the
convenience of other trades.
vii. Painting of timber work metal work executed under this trade.
q. Rate to include submission of Megar Test report of the building Elactrical Installation from
Charted Elactrical Engineer
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 20
PRELIMINARIES
Note 1 :The Engineer/Consultant may modify or amended any item, or
delete inappropriate item/s or add new item/s, depending the nature of
the proposed work.
Note 2 :Mode of payment are as below
Mode Of Payment Category
Reimbursement of actual cost on submission of the relevant
document acceptable to the Engineer plus 5% of the actual cost
of obtaining the Insurance Policies and Securities.
A
To be paid on signing of the formal Contract Agreement. B
60% on completion of temporary buildings or structures. 30% in
equal instalments over the contract period and balance 10% on
dismantling and removal on completion.
C
Paid on satisfactorily completion of the item. D
In equal instalments over the contract period. E
Mode of payment to be mutually agreed between Contractor and
the Employer at the commencement of contract in relation to the
programme of work.
F
On the completion of works. G
Note 3 : The above recommended percentages may be adjusted by the
Employer/ Consultant to audit the particular project.
Serial
No
Description
Mode of
payment
category
Unit
Amount
1
Insurance and Securities
Allow for providing a Performance Security
Allow for providing an Advanced Payment Security
Provisional sum for insurance of Works, Machinery &
Equipment, Plant, Materials, third party persons &
property and Employer's personnel & property at site
as per the Contract
(a ) Provisional sum for insurance against accidents
and injury to Contractor's personnel as per the
contract
( b )Provisional sum for Insurance cover for inquires
and damages to Engineer's personnel
Total Carried Forward
A
Provisional
sum 200,000.00
2 A Provisional
sum 650,000.00
3
Provisional
A sum 500,000.00
4
A Provisional
sum 300,000.00
Provisional
A sum 300,000.00
1,950,000.00
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 21
Brought forward
C
D
E
C
C
1,950,000.00
Engineer's Facilities
5 Allow lump sum for constructing, maintaining
dismantling and removal on completion of the
Works, a temporary building for Engineer's
requirements , including necessary furniture and
fittings, furnishing , sanitary facilities and other
facilities such as Item
( a ) Minimum size of the office space not less than
36 m2 ( 9m x 4m ) and to be air conditioned
throughout the project period with drinking water
facilities with hot and cold water dispenser. ( AC
units to be handed over at the end of project)
( b ) Furniture such as 3 No. tables & 6 No.chairs for
( c ) Laptop computer & Desktop computer ( I7 ) with
4 in 1 laser printer with internet facility through out
the project period. ( Items under sub item (b) & © to
be handed over at the end of project)
( d ) Allow sum for providing safety facility for the
Engineer and his staff during construction. ( Safety
helmets, Boots and other facilities )
6 Allow lump sum for providing telephone and
facsimile facilities , electricity and water services for
the engineer's site office for their use in connection
with the Works Item
7 Allow lump sum for maintenance, rental,
consumption charges etc. for telephone and
facsimile facilities , electricity and water services for
the engineer's site office for their use in connection
with the Works Item
Contactor's facilities
8 Allow lump sum for constructing, maintaining
dismantling and removal on completion of the
Works, a temporary site office of adequate size
including staff rest room and toilets and other
facilities for the contractor's site management staff in
accordance with the plans prepared by the
contractor and concurred by the Engineer. Item
9 Allow lump sum for constructing, maintaining
dismantling and removal on completion of the
Works, buildings to be used as workshops and
stores for perishable materials. Buildings shall be
constructed in accordance with the drawings
prepared by the Contractor and concurred by the
Engineer. The lump sum shall also include for
altering, modifying or dismantling and re-erecting
within the site all temporary buildings / structures if
required. Item
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 22
Brought forward
10 Allow lump sum for constructing, maintaining
dismantling and removal on completion of the Works,
temporary buildings in accordance with the plans
prepared by the Contractor and concurred by the
Engineer to accommodate the following:
C Item
1.Workers' rest room, canteen facilities, kitchen
2.Toilet and wash areas
3. Sick / First-Aid room
4. Accomodation for Contractor's staff and
workmen including sanitary facilities on site,
if applicable
Facilities to workmen shall conform to the latest
public health and industrial regulations
11 Allow lump sum for providing accommodation
including sanitary facilities and transport for
Contractors staff and workmen off site
E
Item
12 Allow lump sum for providing telephone and facsimile
facilities , electricity and water services for the
Contractor's site office for their use in connection with
the Works
D
Item
13 Allow lump sum for maintenance, rental, consumption
charges etc.. for telephone and facsimile facilities ,
electricity and water services for the Contractor's site
office for their use in connection with the Works
E
Item
14 Allow lump sum for Contractor's transport facilities at
site
E
Item
15
Construction management and supervision
Allow lump sum for employing suitably qualified and
experienced technical personnel on full time basis for
Construction Management Services at the site
E
Item
Category Qualification
Month
Salary (Rs)
Engineer
(Full time)
B.Sc. Civil
( 5 Year exp.) 120,000.00
Technical
Officer
(Full time)
NDT Civil or
Equivalent
( 7 year exp.)
60,000.00
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 23
16
Brought forward
Allow lump sum for employing supervisory staff not
listed under item 15 above, on full time basis. Listed
below are the particulars of staff to be engaged
E Item
Category Qualification Salary (Rs)
Chartered
Engineer
(Visiting)
Charter in Civil
Engineering
2,000.00
per hour, 5
hours per
week
Technical Officer
( Electrical)
NDT Electrical
or Equivalent
( 5 year exp.)
1500.00
per day
Setting Out
17 Allow lump sum for employing a licensed land
surveyor to define the building site work etc. , check
levels and carry out such other survey as may be
necessary to establish accurately the placing of forms
and pouring of concrete and all other setting out in
both vertical and horizontal plane.
F Item
18 Allow lump sum for setting out of Works in accordance
with drawings and other written information given by
the Engineer
F
Item
Quality ,Standards and Progress
19 Allow lump sum for provision of progress reports
including photographic records and other schedules
included in the ICTAD publication - Guidelines for
Effective Construction Management.
(ICTAD/CM/01), relevant to contract administration as
directed by the Engineer
E
Item
20 Allow lump sum for all cost in connection with
preparing samples for testing, making arrangements
for testing of Materials, Goods etc. as stipulated in the
specification, obtaining test reports and submitting the
same to the Engineer
E
Item
21 Allow lump sum for provision of shop drawings ,bar
schedules etc. for Engineer's approval
E
Item
22 Allow lump sum for provision of 2 sets of (hard copies
and soft copies) as - built drawings of all services , for
Engineers approval
D
Item
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 24
23
Brought forward Health Safety and Environment
Allow lump sum for engaging the service of an
adequately trained person to attend to first-aid medical
duties including a provision of a first aid box and
regular supply of medicine ,linen etc
Allow lump sum for providing and maintaining a first-
aid box and regular supply of medicine ,linen etc.
Allow lump sum for the following services throughout
the period of construction for the Engineer's office,
Contractor's site office and worker's rest room and
other facilities;
a. Employing workmen to clean and maintaining all
areas to be in good hygienic conditions including
toilets , wash areas , kitchen etc.
b. Supplying adequate drinking water , water for
washing purposes, soap, detergent, etc. throughout
the period of construction
Allow lump sum for providing all necessary safety
measures to workmen at site confirming to the latest
industrial safety regulations and as directed by the
Engineer
Allow lump sum for making adequate provisions
against air and noise pollution of surrounding areas.
Hoarding and dust screens shall be provided to control
dust escaping to surrounding areas
Allow lump sum for maintaining the site in a clean and
orderly manner at all times and during the entire
contract period
The Contractor shall take due care to prevent water
Allow lump sum for demobilization , removal of all
rubbish & debris and clearing up site on completion ,
leaving all in good order and handing over
Security and Protection
Allow lump sum for employing an adequate number of
security personnel and security systems on full time
basis throughout the period of construction, and
providing for necessary security lighting and a warning
system
Allow lump sum for providing and maintaining
necessary fencing ,hoarding and gates for
safeguarding the Works , Materials and plant as
directed by the Engineer
Total Carried Forward
E
Item
24
E Item
25
E
Item
26
E
Item
27
E
Item
28
E Item
29
G Item
30
E
Item
31
E
Item
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 25
Brought forward
32 Allow lump sum for protection of public and private
services at site. The Contractor shall take due care
to protect, water supply and drainage systems,
telephone and overhead / buried electrical cables
etc. whose locations are identified and made
available to the bidder at the time of bidding , unless
earmarked for demolition, during the execution of the
Works. The contractor is to make good any damage
due to any cause within his control at his own
expenses or pay any cost and charges in connection
therewith. E Item
Services and Facilities
33 Allow lump sum for supply of water for the Works
and paying all charges and other expenses in
connection with the supply from water mains or any
other alternative method of water supply , storage
and reticulation E Item
34 Allow lump sum for supplying temporary electricity
for the Works including connection, distribution
system for the works , internal arrangements and all
payments to the authorities for consumption E Item
35 Allow lump sum for providing hoisting equipment
and other plant for the use of the Works on site(dry F Item
36 Allow lump sum for providing small machinery and
equipment for the use of the Works at site. F Item (a ). Hammer drill.
(b ). Jack hammer.
(c ). Compressor.
(d ). water pump with necessary accessories for
working order
(e ). Welding Plant.
37 Allow lump sum for erecting and maintaining
scaffolding and/or self climbing platforms. Such
scaffolding etc. shall be removed on completion and
all Works disturbed shall be made good. F Item
Miscellaneous
38 Allow lump sum for stamp duty in accordance with
the prevailing regulations of the Government B Item
39 Allow lump sum for providing and maintaining a
name board to the specifications and/or as directed
by the Engineer C Item
40 Allow lump sum for excavation for trial pits / trial
trenches as specified or as directed by the Engineer
as for locating services etc. and reinstating the
ground and making good disturbed work to the
satisfaction of the Engineer F Item
TOTAL CARRIED TO SUMMARY ON PAGE S 07 - 140
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 26
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
BILL NO 1 - DEMOLITION AND OTHER
A- DEMOLITION
1.A.1 Disconnecting, removing existing electrical
wiring, fittings. Etc. and stacking away all
serviceable material and handing over to
Client as per Engineer's approval in
Entrance lobby, restaurant, kitchen, existing
store buildings, laundry, connecting
corridors...etc. Rate to include providing
temporary connections for other building
from existing supply mains. 1 Item
1.A.2 Disconnecting and removing existing
telephone/fax/data systems/wiring, fittings.
Etc.. where necessary and re-fixing same
after repair works completion to working
order and to the Engineer's approval.
1 Item
1.A.3 Roof removing tiles or asbestos sheets or
both and timber, stacking serviceable
materials and clearing debris away as
specified in single storied buildings. Rate to
include removing of clay tiles on existing
roof covering and disposing them and
clearing debris away from work site. 700 m2
1.A.4 Roof removing tiles or asbestos sheets or
both and timber, stacking serviceable
materials and clearing debris away as. Rate
to include removing of clay tiles on existing
roof covering, removing of Ridge tiles and
disposing them and clearing debris away
from work site. specified in two storied
buildings 830 m2
1.A.5 Removing ceiling asbestos including timber
framework, stacking serviceable materials
and clearing debris away in single storied
buildings
180 m2
1.A.6 Removing of existing roof trusses at kitchen
building 3 Nr.
1.A.7 Removing and stacking gutter from roofs of
single storied buildings 160 m Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 27
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
1.A.8 Removing and stacking gutter from roofs of
two storied buildings 155 m
1.A.9 Removing and stacking down pipe from
roof gutter of single storied buildings 100 m
1.A.10 Removing and stacking down pipe from
roof gutter of two storied buildings 80 m
1.A.11 Removing and stacking Valance, Barge
board materials and clearing debris away
in single storied building 200 m
1.A.12 Removing and stacking Valance, Barge
board materials and clearing debris away
in two storied building 155 m
1.A.13 Removing and stacking Door or Window
from existing walls including sashes. 75 Nr
1.A.14 Removing and stacking Door or Window
sash only from existing Frame. 5 Nr
1.A.15 Removing and stacking Metal grill of
window and clearing debris away. ( Max.
Area - 4m2) 20 Nr
1.A.16 Removing and stacking Metal Door or
Window from existing walls , Size
approximately - 1900 x 1900mm 2 Nr.
1.A.17 Removing and stacking partitions and
clearing debris away including making good
to walls and floors
90 m2
1.A.18 Removing damaged pantry cupboard and
Kitchen appliances and clearing debris
away. 1 Item
1.A.19 Removing timber handrail and guard rail of
stair and stacking away all serviceable
material and handing over to Client as per
Engineer's approval and clearing debris
away as specified by the Engineer. 20 m
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 28
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
1.A.20 Demolishing brickwork in cement stacking
brick and clearing debris away
35
m3
1.A.21 Demolishing Reinforced Cement Concrete /
mass concrete / floor concrete…etc. and
clearing debris away from work site in
floors, or beams or columns 8 m3
1.A.22 Removing of bathroom fittings including
wash basins, Closed Coupled Water
Closets/squatting pan, Bidets, shower
roses, tap wares, mirrors, soap trays…etc.
in functioning toilets/bathrooms and in
restaurant area (male, female, staff and
workers and restaurant ...etc.) and stacking
away the material without making any
damage and to the Engineers approval.
Rate to include plugging sewer connections
and water connections and floor made good
for repair works.
1 Item
1.A.23 Removing of Kitchen Sink with fittings and
stacking away the serviceable material
without making any damage and to the
Engineers approval. Rate to include
plugging waste water connections and
water connections and floor made good for
repair works. 4 Nr
Removing / Demolishing of floor tiles
including tile bed and cart away debris to
the Engineers approval.
1.A.24 Ground Floor - Staff Accommodation,
Dormitory & drivers, Laundry & bathroom 255 m2
1.A.25 Removing/Demolishing of wall tiles
including tile bed and cart away debris to
the Engineers approval.
160 m2
Chipping floor rendering, cement, and
clearing debris away floors
1.A.26 Ground Floor - Staff Accommodation,
Service area ,Corridor & veranda
355
m2
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 29
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
m2
m2
m2
m2
m2
m2
m2
m2
1.A.27 First Floor - Staff Accommodation,
Service area ,Corridor & veranda 15
Chipping floor rendering, cement, and
clearing debris away from concrete floors
1.A.28 At First Floor Kitchen
120
1.A.29 Demolishing floors brick paved, and
clearing debris away 20
Chipping internal plaster/ external plaster
with skirting, and clearing debris away from
brick wall / block walls
1.A.30 In Staff accommodation, laundry &
Dormitory. 635
1.A.31 In First floor Kitchen , Store & Entrance
building 385
1.A.32 Chipping internal plaster/ external plaster
and clearing debris away from Isolated
columns, mouldings and Beams
300
1.A.33 Chipping Cement plastering , and clearing
debris away from soffit of slab 35
1.A.34 Cutting new openings or cutting edges of
existing opening to insert Door /window in
existing Brick wall .Rate to include for
making the edges good and clearing
debris away. (Lintel concrete, reveal
plastering measured separately ). 65
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 30
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
1.A.35 Removing / Demolishing of existing
Manholes . Rate to include for Removing
and stacking existing interlocks paving ,
removing of all unserviceable material ,
carting away the debris and filling the voids
to match with existing Ground. 8 Nr.
1.A.36 Removing / Demolishing of existing septic
tank including removal of sludge using gully
bowser . Rate shall include for Removing
and stacking existing interlocks paving,
removing of all debris and unserviceable
material carting away from the site , filling
the voids to match with existing Ground
(Filling of pit will be measured separately)
2 Nr.
1.A.37 Removing / Demolishing of existing
soakage pit . Rate shall include for
Removing and stacking existing interlocks
paving, removing of all debris and
unserviceable material carting away from
the site , filling the voids to match with
existing Ground (Filling of pit will be
measured separately) 2 Nr.
1.A.38 Demolition/removing of existing curb wall
and clearing debris away. 50 m
1.A.39 Demolishing drains and clearing debris
away. Rate shall include for removing and
stacking existing interlock paving and
clearing debris away. 200 m
1.A.40 Transporting debris cleared away from site
by tractor (app 20 miles away). Rate to
include loading & unloading 10 Load
1.A.41 Transporting debris cleared away with in
site by tractor . Rate to include loading &
unloading 5 Days
1.A.42 Removing of Timber column as specified by
the Engineer 5 Nr
TOTAL CARRIED TO COLLECTION ON PAGE NO S07- 38
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 31
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
B - SITE CLEARING, EXCAVATION &
EARTH WORK
1.B.1 Clearing site including grubbing out and
clearing of any existing footings ,disused
drains, pipe serviceable or any other
matters not carried out by prior demolition
including removal of roots and growth of
every description, up to 1000 mm beyond
the outer edge of the proposed Ramp and
carting away the waste material from the
site where directed by Engineer. (Approx.
400 m2 ) 400 m2
1.B.2 Removing top soil to a depth not exceeding
150mm & depositing as directed within site 400 m2
1.B.3 Cutting and removing of roots without
damaging structures and tree where the
roots can cause severe cracking in
structures of existing building and carting
away the waste material from the site where
directed and levelling site as per Engineers
instruction and working order. Rate shall
include for necessary excavation, filling the
voids to match with existing Ground. (1 Nr
of quantity considered for roots of 1 No
Tree) 5 Nr
1.B.4 Removing trees and stumps size of girth
varies beyond 1.2 m and up to 2.4 m and
girths are measured at 1.0 m height above
ground level including cutting of trunks and
branches, grubbing up roots…etc. and
clearing site and levelling the ground with
necessary fillings. 5 Nr
1.B.5 Removing coconut trees and stumps
approx. height varies beyond 3 m and up to
6 m including cutting of branches, grubbing
up roots…etc. and clearing site and
levelling the ground with necessary fillings.
3 Nr
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 32
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
1.B.6
Brought forward
Excavation & Earth work
Excavation commencing from existing
ground level, not exceeding 1.00 m deep in
any materials except rock requiring blasting,
part return fill in ram and surplus disposed
as directed.
For column footings for connecting slab
For wall trenches
For curb wall trenches
For ramp foundation
For pavement
For waste water treatment plant
Excavation commencing from existing
ground level, exceeding 1.0 M but not
exceeding 2.0 M deep in any material except
rock requiring blasting, backfilling and
disposal of surplus earth as directed.
For waste water treatment plant
Filling under floors & backfilling
Filling under floors including levelling,
watering & compacting (well rammed and
consolidated) in 150mm layers with
imported, selected earth.
Filling under floors including levelling,
watering & compacting (well rammed and
consolidated) in 150mm layers with
available, selected earth.
Backfilling & compacting pits and trenches
(well rammed and consolidated) in 150mm
layers with available, selected earth.
Total Carried Forward
10.20
m3
1.B.7 8.20 m3
1.B.8 4.00 m3
1.B.9 5.00 m3
1.B.10 30.00 m3
1.B.11 8.5 m3
1.B.12
8.5
m3
1.B.13
30.00
m3
1.B.14
15.00
m3
1.B.15
15.00
m3
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 33
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
Dewatering
1.B.16 Allow for dewatering, in the manner
approved by the engineer to keep all
excavation dry until all works in substructure
are completed. furnishing of water pumps
are considered under Preliminary Item
Number (36) . (payment will be made only
for the actually execution the order of the
engineer )
1.00
item
Anti Termite Treatment
1.B.17 Allow for anti termite treatment for barrier
and colony elimination at post construction
stage.(600-1000mm spacing in floor shall be
drilled in both ways and chemical to be
applied as per specification & in pressurized
manner) The service provider should hold a
valid license for termite treatment issued
from Department of Agriculture. Rate to
include for a complete treatment with
1.Treatment before placing the foundation.
2. Treatment after placing floor concrete
3. Treatment along the periphery of the
building. The service provider should give
minimum 10 years warranty against termite
treatment. the service provider should
submit the list of Termiticide intended to use
for Engineer's approval. the following
minimum requirements to be maintained.
1.Application rate 5l/m2
2.Termiticide Concentration : 12.5ml/L
3. Termite pump pressure rate : 250 psi (
Approx. area 1000 m2)
1000.00
m2
TOTAL CARRIED TO COLLECTION ON PAGE NO S07- 38
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 34
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
C - CONCRETE WORK
Mass / Lean Concrete
Mass / Lean, screed concrete in
foundations, work inclusive of, pouring,
ramming and levelling in pits or trenches.
75mm thick lean concrete Grade' C - 15 ' in
the following ;
1.C.1 Under column footings 12.00 m2
Mass Concrete
Mass Concrete Grade 'C - 15 ' in the following.
1.C.2 150mm thick under wall foundations 15.00 m2
1.C.3 Supply & Laying 1000 gauge Polythene
membrane. 15.00
m2
Mass Concrete
Mass Concrete Grade 'C - 20 ' in the following.
1.C.4
75 mm thick ground floor concrete with
one layer
Ground Floor - Staff Accommodation
,Dormitory , Laundry, Store & corridor
Ground Floor - Connecting Corridor
Reinforced Concrete
Reinforced cement concrete Grade 'C -
25 ' in the following
In column footings
In column footings
In plinth beams
Total Carried Forward
410.00
m2
1.C.5 115.00 m2
1.C.6
2.50
m3
1.C.7 0.75 m3
1.C.8 0.50 m3
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 35
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
Expansion joint
1.C.9 25mm thick expansion joints in ground floor,
the 1st , 3/4 of depth filled with bituminous fill
& final top 1/4 of depth filled
with mastic compound. ( bitumen sealing
compound)
60.00
m
Formwork
Note :Refer pricing preambles
Formwork is measured as the net contact
surface measurement between concrete
and formwork Form work for columns and
beams is given as a girth measurement.
Refer section 5.2 in specification for full
description of materials and workmen ship.
Formwork shall provide a finish to concrete
surface to receive plaster as per section
5.4.8.11 in Specification.
Form work as described to ;
1.C.10 Vertical sides of column footings
<300mm high
48.00
m
1.C.11 Vertical sides of column footings 5.00 m2
1.C.12 Vertical sides of plinth beam 5.00 m2
Reinforcement
Note: Refer Pricing Preambles
No allowance have been made for rolling
margin in taking off quantities.
Tor steel rod reinforcement including
bends, hooks, tying wire, distance blocks
and ordinary spacers ( Inevitable laps and
chairs included in BOQ Quantities) fy = 460
N/mm2
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 36
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
12mm dia
1.C.13 In column shaft 85.00 Kg
10mm dia
1.C.14 In column footings 95.00 Kg
In Plinth beam
1.C.15 12mm dia. 18.00 Kg
Mild Steel Rod Reinforcement (fy=250N/mm2)
1.C.16 6mm dia as links in column shaft 5.00 Kg
1.C.17 6mm dia as stirrups in plinth beams 6.00 Kg
1.C.18 Allow inevitable laps and chairs for all types
of reinforcement bars as per the Engineers
instructions.
10.00
Kg
TOTAL CARRIED TO COLLECTION ON PAGE NO S07- 38
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 37
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
D - MASONRY
Refer Pricing Preambles
Rubble Work
Note:
Rubble shall be free from soft rock and shall
be sharp and angular shape. No vandully
large for small stone shall be used in the
rubble masonry work. The rubble shall be
obtained from and approved quarry by the
Engineer.
1.D.1 Random rubble masonry in cement and
sand 1:5 in wall foundation.(300 mm thick)
for connecting roof slab
4.50
m3
Damp proof course
12mm thick horizontal damp proof course in
cement and sand 1:2 mix and minimum of
two application of hot tar blinded with sand
1.D.2 300 mm wide 30.00 m
TOTAL CARRIED TO COLLECTION ON PAGE NO S07- 38
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 38
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
BILL NO 1 - DEMOLITION AND OTHER
COLLECTION
A- DEMOLITION (From Page 30) Rs.
B - EXCAVATION AND EARTH WORK (From Page 33) Rs.
C - CONCRETE WORK (From Page 36) Rs.
D - MASONRY (From Page 37) Rs.
TOTAL CARRIED TO SUMMARY ON PAGE S 07 - 140 Rs.
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 39
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
BILL NO 2 - RENOVATION AND ALTERATION
C - CONCRETE WORK
Note :Refer Pricing Preambles
Mass Concrete
Mass Concrete Grade 'C - 15 ' in the
following.
2.C.1 Mass concrete fill 1.50 m3
Reinforced Concrete
Reinforced cement concrete Grade 'C- 25'
in the following ;
2.C.2 In column shafts 1.90 m3
2.C.3 In circular column shafts 2.50 m3
2.C.4 In stiffener column shafts 0.40 m3
2.C.5 In Roof beams - First floor level 9.50 m3
2.C.6 At Roof Beams - Linking corridor 6.50 m3
2.C.7 In Roof beams - Second floor level 4.50 m3
In 125mm thick suspended slab
2.C.8 At first floor level - Linking corridor 150.00 m2
2.C.9 Encasing defected column of two story
building as follows : Removing plaster of
concrete column surface , remove loose
aggregates without damaging Rebars, wire
brushing reinforcement and cleaning,
applying anticorrosive coating (EMACO S40
ZR or equivalent ) and after preparation
work, column shall be encased by
Reinforced cement concrete in Grade C-25
as per Engineers approval. Rate shall
include for 5Y12 & R6@150 c/c
reinforcement work & form work .
1.00 Item
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 40
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
Form work
Refer Pricing Preamble
Refer section 5.2 in specification for full
description of materials & workmanship
Form work shall provide a finish to concrete
surface to receive plaster as per section
5.3.8.11 in Specification. Form work for
columns and beams is given as a girth
measurement.
Form work as described to ;
Vertical sides of circular column shafts
2.C.10 From ground floor level to first floor level 35.00 m2
Vertical sides of stiffener column shafts
2.C.11 From ground floor level to first floor level 5.00 m2
2.C.12 From First floor level to first floor level 5.00 m2
Vertical sides of stiffener column shafts
2.C.13 From ground floor level to first floor level 0.00 m2
2.C.14 From First floor level to first floor level 0.00 m2
Sides and soffit of beams, roof beams…etc.
2.C.15 In Roof beams - First floor level 85.00 m2
2.C.16 At Roof Beams - Linking corridor 90.00 m2
2.C.17 In Roof beams - Second floor level 40.00 m2
Soffit of suspended slab
2.C.18 Soffit of Slab - First Floor level 135.00 m2
125mm high to edge of floor slabs
2.C.19 At first floor lintel level 110.00 m
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 41
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
Reinforcement
Note: Refer Pricing Preambles
No allowance have been made for rolling
margin in taking off quantities.
Tor steel rod reinforcement including
bends, hooks, tying wire, distance blocks
and ordinary spacers ( Inevitable laps and
chairs paid separately) fy = 460 N/mm2
12 mm dia. in columns
2.C.20 From ground floor level to first floor level 0.04 MT
2.C.21 From ground floor level to first floor level 0.04 MT
10 mm dia. in stiffener columns
2.C.22 From ground floor level to first floor level 0.01 MT
2.C.23 From ground floor level to first floor level 0.01 MT
12mm dia In beams of connecting corridor
2.C.24
At first floor level
0.50
MT
10 mm dia. in roof beams
2.C.25 At first floor level 0.45 MT
2.C.26 At second floor level 0.25 MT
10mm dia in suspended floor slab
2.C.27 At first floor level 2.15 MT
Mild Steel (fy = 250N/mm2) rod
reinforcement as follows
6mm dia. links in column shafts
2.C.28 From ground level to first floor level 0.05 MT
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 42
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
6mm dia. links in stiffener column shafts
2.C.29
From ground floor level to first floor level
0.01
MT
6mm dia. stirrups in beams
2.C.30 At first floor level 0.41 MT
2.C.31 At second floor level 0.20 MT
2.C.32 Allow inevitable laps and chairs for all types
of reinforcement bars as per the Engineers
instructions. 0.01 MT
Note: The following items are measured
including reinforcement & formwork.
225x150 mm high lintel beams including 02
nos. 10 mm dia T/S bars and 6mm dia mild
steel stirrups @ 100c/c with necessary
formwork and concreting in Grade 20
2.C.33
At ground floor lintel level
10.00
m
112.5x150 mm high lintel beams including
02 nos. 10 mm dia T/S bars and 6mm dia
mild steel stirrups @ 100c/c with necessary
formwork and concreting in Grade 20
2.C.34
At ground floor lintel level
10.00
m
75mm thick R.C.C. work top (C 25)
including necessary reinforcements and
formwork, complete with 20m thick
polished granite finish with bull nose edge
including for necessary side skirting with
same granite work. Total granite area will
be measured under this item. Granite will
be selected by project Architect
2.C.35 At First Floor pantry & Kitchen (Counter top) 10.50
m2
2.C.36 At Restaurant hand washing, male and
female bathroom (Vanity of toilet )
4.20
m2
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 43
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.C.37
Brought forward
Extending of existing columns by 600mm-
1000(approx.). Rate to include necessary
demolishing of concrete for lapping of
reinforcements as specified by the Engineer.
Work may in first floor level or second
floor level. Rate to include necessary form
work, Reinforcements and concrete (Gr25)
and completing the work as per Engineer's
approval.
5.50
m3
TOTAL CARRIED TO COLLECTION ON PAGE S 07 - 122
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 44
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.D.1
2.D.2
2.D.3
2.D.4
2.D.5
2.D.6
2.D.7
2.D.8
2.D.9
D - MASONRY
Refer Pricing Preambles
Brick Work
Half brick thick (112.5 mm) walls
From ground floor level to first floor level.
From first floor level to second floor level
One brick thick (225mm) walls
From ground floor level to first floor level
From first floor level to second floor level
Brick step
1.5 - 2.0 m wide(Approx. ) brick steps at
restaurant to Corridor and Corridor to New
Accommodation Building in first floor level ,
consisting of steps with 300mm wide thread
and 150mm high risers complete with 12mm
thick cement and sand 1:2 rendering
finished smooth with neat cement floating.
Filling Existing Door / Window opening /
Recesses with Brick work with standard
bricks and making good in cement and sand
1:5 mortar.
Half brick thick (112.5 mm) walls
From ground floor level to first floor level
From first floor level to second floor level
One brick thick (225mm) walls
From ground floor level to first floor level
From first floor level to second floor level
65.00
5.00
270.00
50.00
1.00
10.00
5.00
40.00
15.00
m2
m2
m2
m2
Item
m2
m2
m2
m2
TOTAL CARRIED TO COLLECTION ON PAGE S 07 - 122
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 45
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
E - WATER PROOFING
Water proofing system, shall consist of two
(2) coats of water proofing concrete slurry
coats.
Surface preparation,mixing,application &
curing shall be strictly in accordance with the
manufacture's instructions.
The Contractor may use any system of
waterproofing concrete by crystallization,
with the prior approval of the Engineer.
Rate shall include for chipping, removing &
cleaning all loose materials on the surfaces
to be water proof.
Rate shall include for sealing around gullies,
pipe protrusions with non shrink high
strength cementation grout Master flow 98 or
equivalent
Rate shall include for forming 1:3 cement
and sand 25 x 25mm angle fillets at all right
angled edges and mixing, laying of
plastering (1:5) up to 300mm in toilet area
and 1500mm high from finished floor level in
shower area
Supplying and laying of Glass fibre
reinforcement strip, Glascote 60 or
equivalent to vertical/ horizontal
intersections as per manufacture instruction
& working order.
Waterproofing treatment in Bathroom / toilet
area by using flexible polymer cement slurry
according to Manufacturers specification's.
("Master seal
540"(Barralastic) or equivalent approved
product
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 46
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.E.1
2.E.2
2.E.3
2.E.4
2.E.5
2.E.6
2.E.7
Brought forward
Water proofing to Floor and walls of toilets
up to a height of 1800mm of wall including
10 years warranty with all materials.
In ground floor female toilet
In ground floor male toilet
In ground floor dormitory toilet
In ground floor staff G1 toilet
In ground floor common staff toilet
Water proofing to walls of toilets up to a
height of 1800mm including 10 years
warranty with all materials.
Water proofing to be used approved product
such as" Xypex "or equivalent
Water proofing to top of concrete slab
In 1st floor level - corridor slab
In 1st floor level - kitchen
40.00
36.00
77.00
35.00
52.00
150.00
0.00
m2
m2
m2
m2
m2
m2
m2
Deleted
TOTAL CARRIED TO COLLECTION ON PAGE S 07 - 122
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 47
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
F- STRUCTURAL STEEL WORK
All steel used in the work shall comply with
the relevant British Standards and to the
specifications
All steel shall be new & each member shall
be free from any built - weld or other forms
of splice for the full length between joints
shown in or indicated in the drawings unless
such splice shall have been shown in the
approved drawings.
The Bidder shall submit the specification for
the steel which he proposed to use & obtain
prior approval from the Engineer before
commencement of ordering of steel and
fabrication
Drawings
Before any steel work is fabricated the
contractor shall obtain the Engineer's
approval of the proposed details of
fabrications. For this purpose , two copies of
shop drawings shall be submitted to the
Engineer not less than 14 days before
commencement of fabrication.
Inspections
All steel work shall be subjected for
inspection by the Engineer. The steel works
shall not be moved from the place of
fabrication nor primed or painted until the
approval of the Engineer has been obtained
for the fabrication of steel work
Welding
No welding shall be done until approval of
the prepared surface has been obtained. All
welding shall be carried out under the
supervision of qualified persons.
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 48
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.F.1
Brought forward
Base plate, Sole plate, gussets plate, splice
etc. have not been measured separately but
the weights of such attachments have been
included in weight of respective items
indicated in item description.
Refer drawings for fabrication and fixing
details of trusses, purlin etc.
Rate shall include for all necessary cuttings,
drillings, bolting, reverting, welding, grinding,
delivering, unloading, hoisting, erecting and
fixing in position, levelling, plumbing and
submission and getting approval of all shop
drawings.
All steel works should be applied two coats
of coloured anticorrosive paints (two
different colours for two coats) and one coat
of Enamel paint (paint approved by
engineer)
Roof supports
Prop-A
Roof supports ( Prop - 'A' ), consisting of 2
Nos of approx. size 75x150mm in size &
minimum thickness of 5mm steel box bars
(approx. 3.4 m length each) fixed to same
size steel box bar joist (approx. 1.9 m
length) with 6mm thick bent to shape mild
steel plates welded as per detailed drawings.
Steel prop shall fixed with 12mm in dia. steel
nut and bolts at free end of joist & bottom end
of props with 10mm thick gusset plate to
existing Column. Here nut & bolts shall be
fixed as passed through the column or with
use of anchor bolts as specified by the
Engineer with existing site conditions. Rate
shall include for all necessary related
matters and completing the item as per
Drawings, Specifications & to the Engineers
approval
Total Carried Forward
10.00
Nr
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 49
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.F.2
2.F.3
Brought forward
Prop-B
Roof supports ( Prop - 'B'), consisting of
approx. size 75 x 150mm & minimum 5mm
thickness steel box bars (approx. 2.3m
length each) fixed as prop. Steel prop
shall fixed with 10mm thick base plate &
sole plate with 12 mm dia. anchor bolts at
bottom end to existing slab or beam at outer
side of building and top end fixed to Timber
purling with 10mm welded plate using
10mm in Dia. " U " shape nut and Bolts
passed through the steel plate. Rate shall
include for all necessary related matters
and completing the item as per Drawings,
Specifications & to the Engineers approval.
Prop-B-1 at corners
Roof supports ( Prop - 'B-1'), consisting of
approx. size 75 x 150mm & minimum 5mm
thickness steel box bars (approx. 2.5m
length each) fixed as prop. Steel prop
shall fixed with 10mm thick base plate &
sole plate with 12 mm dia. anchor bolts at
bottom end to existing slab or beam at outer
side of building and top end fixed to Timber
purling with 10mm welded plate using
10mm in Dia. " U " shape nut and Bolts
passed through the steel plate. Rate shall
include for all necessary related matters
and completing the item as per Drawings,
Specifications & to the Engineers approval.
Total Carried Forward
31.00
4.00
Nr
Nr
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 50
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.F.4
2.F.5
2.F.6
Brought forward
Supply and installation of Structural " I "
beam 1 having approx. 6.3 m in Span
(Centre to centre of span Approx. 6.3 m)
Structural steel roof beam Having size
178mm x 102mm x 19kg/m Universal " I "
beam supported with beam / wall, fabricated,
hoisted and fixed at a height of 3000 mm
above ground level. rate to includes
necessary 10 mm thick Base plates,16mm
dia rag/anchor bolts, etc...as per
specification and Engineers approval
( Approx. weight of each truss 0.15 MT).
In Laundry Room
Supply and installation of structural " I "
beam 2 approx. 4350mm in Span (approx.
5.05m in length) & Structural steel hip truss
Having size 127mm x 76mm x 13kg/m
Universal " I " beam , fabricated, hoisted
and fixed at a height of 4000 mm
above ground level. rate to includes
necessary 10 mm thick Base plates, 10mm
thick sole plates. 10mm thick gusset plates,
16mm dia bolts, Nuts,washers,cleats,rivets
etc...as per specification and Engineers
approval ( Approx. weight of each truss
0.09MT)
In Dormitory/Drivers Room
Supply and installation of truss 1 having
approx. 3250mm in Span (approx. 3.8m in
length) & Structural steel hip truss Having
size 127mm x 76mm x 13kg/m Universal " I
" beam , fabricated, hoisted and fixed at a
height of 4000 mm above ground level. rate
to includes necessary 10 mm thick Base
plates, 10mm thick sole plates. 10mm thick
gusset plates, 16mm dia bolts,
Nuts,washers,cleats,rivets etc...as per
specification and Engineers approval (
Approx. weight of each truss 0.08MT)
In Staff accommodation living room
Total Carried Forward
2
1
1
Nr
Nr
Nr
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 51
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.F.7
2.F.8
2.F.9
Brought forward
Steel Roof structure-Kitchen
Structural steel roof truss type T1-a - with
203 x 133 x 30kg/m Steel I section &
9150mm centre to centre of
supports(Approx.) , hoisted and fixed at a
height of 6500mm above ground level ,two
end of eaves extended up to 1000 mm and
fixed with rag bolts including all gusset
plates, rag bolts, nuts, washers ect.all as per
detail (Approx. weight of each truss 0.46MT)
Structural steel roof truss type T1-b - with
203 x 133 x 30kg/m Steel I section &
9150mm centre to centre of
supports(Approx.) , hoisted and fixed at a
height of 6500mm above ground level ,two
end of eaves extended up to 1000 mm and
fixed with rag bolts including all gusset
plates, rag bolts, nuts, washers ect.all as per
detail (Approx. weight of each truss 0.45MT)
Supply and installation of truss T2-A having
approx. 8075mm in Span (approx.
9280mm in length) & Structural steel
hip truss Having size 127mm x 76mm x
13kg/m Universal " I " beam and eaves
extended up to 1000mm, fabricated,
hoisted and fixed at a height of
6500 mm above ground level. rate
to includes necessary Base plates, sole
plates. gusset plates, bolts,
Nuts,washers,cleats,rivets etc...as per
specification and Engineers approval (
Approx. weight of each truss 0.16MT)
Total Carried Forward
1
1
4
Nr
Nr
Nr
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 52
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.F.10
2.F.11
2.F.12
Brought forward
Supply and installation of truss T2-B having
approx. 4150 mm in Span (approx.
4770mm in length) & Structural steel
truss Having size 127mm x 76mm x 13kg/m
Universal " I " beam and eaves
extended up to 1000mm, fabricated,
hoisted and fixed at a height of
6500 mm above ground level. rate
to includes necessary Base plates, sole
plates. gusset plates, bolts,
Nuts,washers,cleats,rivets etc...as per
specification and Engineers approval (
Approx. weight of each truss 0.09MT)
Supply and installation of truss T2-C having
approx. 5450 mm in Span (approx. 6250
mm in length) & Structural steel truss
Having size 127mm x 76mm x 13kg/m
Universal " I " beam and eaves
extended up to 1000mm, fabricated,
hoisted and fixed at a height of
6500 mm above ground level. rate
to includes necessary Base plates, sole
plates. gusset plates, bolts,
Nuts,washers,cleats,rivets etc...as per
specification and Engineers approval (
Approx. weight of each truss 0.11MT)
Supply and installation of truss T2-D having
approx. 2750 mm in Span (approx. 3160 mm
in length) & Structural steel truss Having size
127mm x 76mm x 13kg/m Universal " I "
beam and eaves extended up to 1000mm,
fabricated, hoisted and fixed at a height
of 6500 mm above ground level. rate
to includes necessary Base plates, sole
plates. gusset plates, bolts,
Nuts,washers,cleats,rivets etc...as per
specification and Engineers approval (
Approx. weight of each truss 0.07MT)
Total Carried Forward
4
2
2
Nr
Nr
Nr
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 53
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.F.13
2.F.14
2.F.15
2.F.16
Brought forward
Supplying & Fixing High tensile Galvanized
Steel "C" channel purlins, having the
member thickness of 2.0mm (Tensile
strength 450 N/mm2) standards complying
with JISG 3302. Each Purlins connected
with 75mmx75mmx6mm L-Iron cleats on
roof truss together with 10mm dia. Bolt and
nuts. Necessary painting to be done for
cleats and purlins at wall to be fixed with
concrete pad.
LIP channel with the sectional dimensions of
channel , 100mmx50mmx12mm roof level
Supply and fixing of 50 x 50x 5mm equal
angle iron on steel framed roof structure.
Tempered Glass fixing frame for
FG1,FG2,FG4&FG5
Supplying and fixing of 75x150mm in size &
minimum 5mm thick GI box bar as a column
or beam to support tempered glass work GI
box bar shall be fixed to existing floor, RCC
beams or another GI column with necessary
base plate, gusset plate…etc
Supplying, fabricating and fixing of GI box
bar roof frame work having pitch of 30
degrees for security rooms having sizes of
approx. 2.4 x 2.4m(Size may vary at site).
Rate to be included for providing of 40 x 40
mm in size (Square section) and 3.0mm in
wall thickness GI box bar wall plates
mounted to existing wall and 50 x 25 mm in
size (rectangle section) and 3.0mm in wall
thickness GI box bars for hip rafters and
other rafters where necessary (Max. rafter
spacing is 1.2m) and 25 x 25 mm in
size(Square section) with 2.0mm in wall
thickness purlins in 1.0 intervals. Rate shall
be included for all work related matters and
completing the roof structure in working
order and to the Engineer's approval.
185.00
75
32
2
m
m
m
Nr
TOTAL CARRIED TO COLLECTION ON PAGE S 07 - 122
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 54
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
G- METAL WORK
Refer Pricing Preambles
Aluminium Panels
Material
All Aluminium sections shall be fully treated
extruded Aluminium alloy sections in
accordance with BS 1470,1471, 1473, 1474
or latest relevant EN stranded
All Aluminium sections to be locally
manufactured ( "Alumex" or similar products
of equivalent technical parameters)
All Aluminium sections shall present clear,
straight and sharply defined lines. They shall
be free from defects impairing strength,
appearance and durability.
Finish
All members shall be finished either by
( a ) Anodizing or
( b ) Powder coating ( What ever specified
in Aluminium Items )
Anodizing -Exposed surface of all members
shall be anodized using two steps.
Anodizing process to an anodic thickness of
not less than 10-15 microns and shall be free
of any defects.
Powder coating - Powder coating shall be
carried out using polyester coating with
proper and appropriate pre- treatment to a
thickness of not less than 60-80 microns,
measured on all significant surfaces.
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 55
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
Screws and Hardware Items
Concealed screws, nuts, bolts, rivets and
other fastening devices shall be of
Aluminium, non-magnetic stainless steel or
other approved corrosive resistant materials.
If visible, they shall blend with the finish of
the framing Aluminium sections.
Hardware items such as Hinges, Handles,
Catches, fixtures etc., shall be minimum of
grade 304 stainless steel.
Glass
Glazing shall be minimum of 5mm thick clear
float glass. Glass shall be secured at all
edges with compression gaskets and
glazing beads. When fixing glass, all glazing
sealant shall be carefully applied and
cleaned off properly.
Workmanship
The fabrication and installation of all
Aluminium work must be carried out by
specialist tradesmen.
All dimensions shown on the drawings and
the shop drawings must be verified by actual
site measurement before fabrication and
installation. Any cutting to enlarge the size of
openings and approved practical method to
fill the excess void behind frames required
after installation shall be executed by the
Contractor at his own expense.
All Aluminium members shall be factory
fabricated to the best standard of
workmanship under experienced factory
supervision and control.
Materials, method of fabrication, assembly,
installation, fastenings, supports, braces,
operating parts and the like shall be in
accordance with the approved shop
drawings.
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 56
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
All joints in frames at corners, junctions and
intersections shall be mechanically jointed
and be such that when assembled they are
as strong and rigid as adjoining sections.
Due care must be taken to ensure that all
joints are water tight and leak-proof. Joint
lines should not be visible.
Provisions must be made for expansion and
contraction in horizontal and vertical
members which are exposed to the weather
or environments. Any distortion of members
or any glass cracked or broken as a result of
inadequate provisions must be rectified by
the Contractor at his own expenses.
All works shall be securely installed and
anchored in position, set plumb, square and
level in accurate alignment with other work,
all in accordance with the approved shop
drawings to the Engineer's satisfaction.( The
allowable tolerance in terms of specified
dimensions shall be plus/minus 1.5mm.)
Submissions
The Contractor shall submit shop
drawings showing the following
information where appropriate to the item ;
layout (Sectional plan and elevation) of
complete assembly
- full size sections of members
- methods of assembly
- methods of glazing
- methods of installation, including
fixings caulking, flashing
- provisions for vertical and horizontal
expansion
- junctions and trim to adjoining surfaces
- fittings and accessories
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 57
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
The Contractor shall submit certificates
from the Aluminium manufacture and/or an
approved testing laboratory which attest
that the coating thickness offered is as
specified.
Doors & Windows
Frame and /or sash sections shall be of
extruded EN-AW 6063-T5 Aluminium Alloy
having a normal thickness of 1.5mm (
Accepted commercial tolerance of tolerance
of ± 0.15mm shall apply )
Aluminium Louvers
Fixed louvers shall be of the weather proof
type, suitable for overcoming water carried-
over by wind and the fixed louvers shall have
free areas of not less than 50%
The Contractor shall provide a guarantee in
respect of the weatherproof properties of the
fixed louvers.
All powder coatings shall match the
windows. Panels shall be so constructed as
to be completely weather proof at junctions
with adjoin structures .
Louver members shall be minimum 1.2mm
thick .
Partitions
The frames shall be properly machined no
permit easy assembly and to form weather-
tight joints when caulked.
Partition members shall be 76mm in depth
and the thickness of 1.2mm.
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 58
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
Following dimensions are applied for the
frame members of each assembly units
As sembly
Unit
Minim um
member
depth(mm)
Minimum
member
thickness
(mm)
Door 100 1.5
Sliding
door/
Window
80
1.5
Cesement
Window,
Fanlight
70
1.5
Fixed glass
window 100 1.5
Rates shall include for all necessary hinges,
screws, rubber beadings, skeleton bolts,
Aluminium louvers, pinhead stickers.(
Locks,Handles,Door closers paid separately
for doors or sliding doors)
Locks- (Union or equivalent )
Mortice lock -
Without handle- 5065/= ( excluding VAT )
With powder coated handle (Black/ White)
7050/= (excluding VAT)
Hinges-(Union or equivalent )
102 x76 x 2mm 2185/= per pair
102 x76 x 3mm 3075/=( excluding VAT)
Handle-Grade 304 stainless steel
3255/= per pair( excluding VAT)
Door closer
60kg-80kg [Yale -7300/= (excluding VAT)]
60kg-80kg [Union-7400/=(excluding VAT)]
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 59
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
Doors, Windows & Fanlights
Double Sash door
Supplying, Fabricating and Fixing Doubled
sashed glass and board Aluminium door
type D3 1200 x 2100+300-mm high overall
1.6mm thick & 45.0mmx100mm (deep)
Timber colour matt finished Powder coated
aluminium frame and aluminium door
sashes with 300mm high ,1.2mm thick
aluminium louvers with Sliding Glass on top
including 4mm thick double side cladded
approved colour aluminium composite panel
at Bottom and 5mm thick float Glass at Top,
all complete as per drawing and Engineers
approval. (Door
closers,handles,door locks paid separately,
effective area of each unit approx. 3 m2).
rate to include for supply & fixing of flush
bolt.
2.G.1
In ground floor
1
Nr.
2.G.2 In First floor Kitchen 1 Nr.
Supplying, Fabricating and Fixing Doubled
sashed glass and board Aluminium door
type D4 1200 x 2100 mm high overall 1.6mm
thick & 45.0mmx100mm (deep) Timber
colour matt finished Powder coated
aluminium frame and aluminium door
sashes including 4mm thick double side
cladded approved colour aluminium
composite panel at Bottom and 5mm thick
float Glass at Top, all complete as per
drawing and Engineers approval. (Door
closers,handles,door locks paid separately,
effective area of each unit approx.2.52 m2).
rate to include for supply & fixing of flush
bolt.
2.G.3
In ground floor
2
Nr.
2.G.4 In Ground Floor Office 1 Nr.
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 60
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
Single sash door
Supplying, Fabricating and Fixing Single
sashed fully composite panelled
Aluminium door type D1 900 x 2100+300-
mm high overall 1.6mm thick &
45.0mmx100mm (deep) Timber colour matt
finished Powder coated aluminium frame
and aluminium sashes with 300mm high
,1.2mm thick aluminium louvers with Sliding
Glass on top including 4mm thick double
side cladded approved colour aluminium
composite panel at top & Bottom, all
complete as per drawing and Engineers
approval. (Door
closers,handles,door locks paid separately,
effective area of each unit approx.2.16 m2)
2.G.5
In ground floor
5
Nr.
Supplying, Fabricating and Fixing Single
sashed glass and board Aluminium door
type D1-a 900 x 2100+300-mm high overall
1.6mm thick & 45.0mmx100mm (deep)
Timber colour matt finished Powder coated
aluminium frame and aluminium sashes with
300mm high ,1.2mm thick aluminium louvers
with Sliding Glass on top including 4mm
thick double side cladded approved colour
aluminium composite panel at Bottom &
5mm thick float Glass with sand blast sticker
sticker at top, all complete as per drawing
and Engineers approval. (Door
closers,handles,door locks paid separately,
effective area of each unit approx.2.16 m2)
2.G.6
In ground floor
2
Nr.
2.G.7 In ground floor ( at Security Room) 2 Nr.
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 61
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
Supplying, Fabricating and Fixing Single
sashed fully composite panelled
Aluminium door type D2 900 x 2100-mm
high overall 1.6mm thick & 45.0mmx100mm
(deep) Timber colour matt finished Powder
coated aluminium frame and aluminium
sashes including 4mm thick double side
cladded approved colour aluminium
composite panel at top & Bottom, all
complete as per drawing and Engineers
approval. (Door
closers,handles,door locks paid separately,
effective area of each unit approx.1.89 m2)
2.G.8
In ground floor
10
Nr.
2.G.9 In ground floor Lobby &Reception 4 Nr.
Supplying, Fabricating and Fixing Single
sashed glass and board Aluminium door
type D2-a 900 x 2100-mm high overall
1.6mm thick & 45.0mmx100mm (deep)
Timber colour matt finished Powder coated
aluminium frame and aluminium sashes
including 4mm thick double side cladded
approved colour aluminium composite panel
at Bottom & 5mm thick float Glass with sand
blast sticker sticker at top, all complete as
per drawing and Engineers approval.. (Door
closers,handles,door locks paid separately,
effective area of each unit approx.1.89 m2)
2.G.10
In First Floor Pantry & Chef Room
2
Nr.
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 62
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
Supplying, Fabricating and Fixing Single
sashed fully composite panelled Aluminium
door type D5 750 x 2100-mm high overall
1.6mm thick & 45.0mmx100mm (deep)
Timber colour matt finished Powder coated
aluminium frame and aluminium sashes
including 4mm thick double side cladded
approved colour aluminium composite panel
at top & Bottom, all complete as per drawing
and Engineers approval. (Door
closers,handles,door locks paid separately,
effective area of each unit approx.1.58 m2)
2.G.11
In ground floor
9
Nr.
Windows
Supplying, Fabricating and Fixing of
Aluminium Casement Window type W2
1200 x 1200 high overall with 1.5mm thick
70mm sections, approved colour matt
finished timber colour powder coated
aluminium frame and 2 No. of glazed
aluminium window sashes including 5mm
thick clear glass panes , all complete as per
drawing and Engineers approval.(Rates to
include necessary rubber beadings, locks,
hinges...etc. Effective area of each window
approx.1.44m² )
2.G.12
In ground floor Stores area
7
Nr.
2.G.13 In First Floor Kitchen 12 Nr.
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 63
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
Supplying, Fabricating and Fixing of
Aluminium Casement Window typeW2-a
Approx. Size -1200 x 1500 high overall with
1.5mm thick 70mm sections, approved
colour matt finished timber colour powder
coated aluminium frame and 2 No. of glazed
aluminium window sashes including 5mm
thick clear glass panes , all complete as per
drawing and Engineers approval.(Rates to
include necessary rubber beadings, locks,
hinges...etc. Effective area of each window
approx.1.62m² )
2.G.14 In ground floor Stores area 1 Nr.
Supplying, Fabricating and Fixing of
Aluminium Casement Window type W3
1200 x 1200+300 high overall with 1.5mm
thick 70mm sections, approved colour
timber colour matt finished powder coated
aluminium frame and 2No. of glazed
aluminium window sashes including 5mm
thick clear glass panes with 300mm high
,1.2mm thick aluminium louvers with Sliding
Glass on top , all complete as per drawing
and Engineers approval.(Rates to include
necessary rubber beadings, locks,
hinges...etc. Effective area of each window
approx.1.8 m² )
2.G.15
In ground floor
15
Nr.
2.G.16 In ground floor (at Security Room) 2 Nr.
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 64
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
-
Supplying, Fabricating and Fixing of
Aluminium Casement Window type W4
1800 x 1200+300 high overall with 1.5mm
thick 70mm sections, approved colour
timber colour matt finished powder coated
aluminium frame and 3 Nos of glazed
aluminium window sashes including 5mm
thick clear glass panes with 300mm high
,1.2mm thick aluminium louvers with Sliding
Glass on top , all complete as per drawing
and Engineers approval.(Rates to include
necessary rubber beadings, locks,
hinges...etc. Effective area of each window
approx.1.8 m² )
2.G.17
In ground floor (at Security Room)
6
Nr.
Supplying, Fabricating and Fixing of 2 sash
Aluminium louver window for gas room (
type W4 ) Approximate size of each sash is
600 x 1200mm high overall with 1.2mm thick
and 76mm deep Aluminium extrusions with
approved colour timber colour matt finished
powder coated aluminium frame & sash to
be completed with same colour powder
coated 52.5mm high 34.6mm width louver
blades - Alumex DG01 or equivalent as per
given drawings and to the Engineer's
approval. (Rates to include necessary
rubber beadings, locks, hinges...etc
complete the item in working order.
2.G.18
For Gas Room
1.00
Nr
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 65
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
Supplying, Fabricating and Fixing Fanlight
type F1 , 600X900mm high overall with
1.5mm thick 70mm Timber colour matt
finished Powder coated aluminium frame
and top hung fully glazed aluminium fanlight
sash , including 450mm high louvers on top
, all complete as per Drawing and Engineers
approval. (Rates to include necessary
accessories. Effective area of
each fanlight approx0.63 m2)
-
2.G.19
In ground floor
11
Nr.
Supplying, Fabricating and Fixing 1.2mm
thick 34.5mm high 28.5mm wide
symmetrical "Y" type Louver blades (Alumex
DG 04 or equivalent) to 17.0 X 31.0mm
louver frame (Alumex DG 103 or equivalent)
and fix to existing door, window or partition
frame work including all accessories.
2.G.20 Fixing of Louver panels in size with 600mm
wide & 1200 mm in high
3.00
Nr
Door Locks
2.G.21 Supplying & Fixing lock ( Union or
equivalent) for Aluminium casement door
with necessary accessories to working
order. (Range of prime cost is Rs. 5000 -
6000 excluding VAT) Door locks to be
matched for door type of single sash or
double sash.
37
Nr.
Door Closers
2.G.22 Supplying & Fixing door closer (Union or
Yale or equivalent ) for Aluminium Casement
door with necessary accessories to working
order.(Range of prime cost is Rs. 7000 -
7800 excluding VAT)
42 Nr.
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 66
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
Door Handles
2.G.23 Supplying & Fixing stainless Steel (Grade
304) door handles for Aluminium door with
necessary accessories to working
order.(Range of prime cost is Rs. 1500 -
1800 excluding VAT)
85
Nr
Tempered glass work
Specification;
i) 12mm thick tempered glass fixed with
spider.
ii) All glass material shall be accordance
with the following standards.
Air permeability - EN 1026:2000
Water tightness - EN 1027:2000
Wind load resistance - EN 12211:2000
U - factor not exceeding 0.53 Btu/ hr.sq.ft F
Average visible light transmittance of 23-
35%
Solar heat gain coefficient not to exceed
0.35
The reflective coating shall meat ASTM C
1367-03
Supply and fixing Laminated Tempered
glass Double sashed Door type D3 , Size -
1200 x 2100mm high consists of 2 No.
12mm thick 600 x 2100mm tempered glass
door sashes with stainless steel door
handles fixed to tempered glass partition.
Rate shall include for stainless steel plates,
top & bottom patches, locks, hinges and all
necessary accessories as per drawing,
specification and Engineers approval (each
unit 2.52 m2)
2.G.24 In Restaurant 3 Nr.
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 67
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
Supply and fixing Laminated Tempered
glass double sashed casement Window
type W1 , Size - 1000 x 1800mm high
consists of 2 No. 10mm thick 350 x
1800mm tempered glass sashes with
stainless steel window handles fixed to
tempered glass partition. Rate shall include
for all necessary accessories as per
drawing, specification and Engineers
approval (each unit 1.26 m2 & two floor
hinges may required for 1 no sash)
2.G.25 In Restaurant 9 Nr.
Supplying and Fixing 12 mm thick fixed
laminated Tempered glass partition with 25
x25x 25mm stainless steel (3mm thick) U
channel frame where necessary. Sand
blast sticker affixed as per architectural
Drawing. All fixing arrangement as per
manufacturer's specifications, Drawing and
Engineer's approval. Rate shall include for
all Necessary accessories and related
matters.
2.G.26
For Door Type D3(FG2&FG3)
30.00
m2
2.G.27 For partition Type FG1& FG4 35.00 m2
Supplying and Fixing 10 mm thick fixed
laminated Tempered glass partition with 25
x25x 25mm stainless steel (3mm thick) U
channel frame where necessary. All fixing
arrangement as per manufacturer's
specifications, Drawing and Engineer's
approval. Rate shall include for all
Necessary accessories and related matters.
2.G.28
For Window Type W1
19.00
m2
2.G.29 Fixed glass Type FG 50.00 m2
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 68
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.G.30
Brought forward
G.I. Box Guard rail
Fabricating and Fixing of 900 mm high
balustrade, consisting of 50 x 50mm & 2mm
thick G.I box section pipe at 1200mm
centres & 18.75mm x 18.75mm &
1.8 or 2mm thick G.I pipe balusters at 80mm
centres internally and 6mm thick 50 x 50mm
mild steel plate welded to vertical main
baluster bottom end and embedded in floor
slab. 37.5 x 5mm flat iron section welded
horizontally to G.I balusters at top and 37.5
x 37.5 mm and 2 mm thick box section
welded to internal blusters at 100 mm in
above to finished floor level in horizontally
and timber hand rail(Teak) to be fixed at top
on flat iron member with water based
finished and sizes match to existing hand
rails in other buildings and all complete as
per drawings and Engineer's approval. rate
including preparation of surface and
application of two coats of enamel paint for
steel member.
At First Floor Restaurant
Total Carried Forward
60.00
m
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 69
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.G.31
2.G.32
Brought forward
Stair Hand rail
Fabricating and fixing of 900mm high
balustrade, consisting of 2 nos 18.75mm x
18.75mm & 2mm thick G.I box section pipe
balusters. Each twin vertical baluster shall
be fixed at centre of stair tread and twin
vertical member shall be in 80mm in C/C and
all vertical members shall fixed to Floor with
6mm thick 50x50mm mild steel plate welded
to vertical member's bottom end of baluster
and embedded in every steps .
37.5 x 5mm flat iron section welded
horizontally to G.I balusters at top and timber
hand rail(Teak) to be fixed at top on flat iron
member with water based finished and sizes
match to existing hand rails in other
buildings and all complete as per drawings
and Engineer's approval. rate including
preparation of surface and application of two
coats of enamel paint.
At First Floor Restaurant
Supplying, Fabricating and Fixing Iron grill
for Windows (Fixed). Consisting of 25 x 6
mm flat iron frame and horizontal bracing as
specified in drawing (not exceeding 1200mm
in each spacing ) and 8mm dia MS rods
welded in frame in 80mm C/C in vertically
and passed through the Horizontal bracings.
all as per drawing and Engineer's approval.
Rate shall include for two coats of anti
corrosive paints and two coats of enamel
paint.
Total Carried Forward
8.50
60
m
m2
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 70
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.G.33
Brought forward
GI Box bar grill work
Fabricating and fixing of Steel box bar grill
work frame work, consisting of 3 Nos 37.5 x
37.5mm & 2mm thick horizontal GI box bars
welded in equal spacing as per Drawings
and 50 x 50 mm and 2mm thick GI box bars
welded vertically in equal spacing as per
drawing (my vertical member spacing are
1200mm) and internal members shall be
18.75 x 18.75mm and 2mm thick GI box bars
welded to Horizontal members in 100mm
C/C. Rate to include for all work related
matters and work to be complete as per
Drawings, Specification & Engineers
approval.
20
m2
TOTAL CARRIED TO COLLECTION ON PAGE S 07 - 122
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 71
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.H.1
2.H.2
H - CARPENTRY & JOINERY
Note : Refer Pricing preambles
Carpentry
Timber used for roof and ceiling framing and
other structural work shall conform to the
requirements stipulated in Chapter 8.0 wood
work (ICTAD specification SCA/4 Vol.1)
And the timber Species for roof & ceiling
framing shall be (category A) of respective
group as listed under General notes.
All timber finished sizes to be matched as
following described sizes in items.
Maximum deviation in size specified shall
not exceed the tolerances for dimension
stated in S.L.S. 263 (1974) Clause - 3.
Timber beams, Purling, wall plate, in contact
with concrete or masonry Work shall be
properly treated with a bituminous wood
preservative.
Roof Timber Frame
Upper roof for restaurant Building
Rate for Following items shall not include for
water based paint
Supply and fixing Battens 45mm x 20mm
section
Struts 95mm x95mm section
Total Carried Forward
780.00
2.00
m
m
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 72
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.H.3
2.H.4
2.H.5
2.H.6
2.H.7
2.H.8
2.H.9
2.H.10
2.H.11
2.H.12
2.H.13
Brought forward
Following Timber members' rate shall
include for applying of two coats of water
based stain and two coats of water based
top coat (Jat or equivalent) where necessary
and specified by the Engineer.
Supply and fixing Ridge Plate 70 mm x
170mm section.
Supply and fixing Wall Plate 70mm x
95mm section.
Supply and fixing Hip & Valley Rafters
45mm x170mm section.
Supply and fixing Rafters 45mm x 95mm
section.
Supply and fixing Purlins 95mm x145mm
section.
Supply and fixing Struts 70mm x95mm
section
Lower roof for Dormitory & veranda
Following items are not exposed under
ceiling and rate shall not include for water
based paint
Supply and fixing Battens 45mm x 20mm
section
Following Timber members shall include for
applying of two coats of water based stain
and two coats of water based top coat (Jat
or equivalent) where necessary and
specified by the Engineer.
Supply and fixing Ridge Plate 45mm x
170mm section fixed to Brick wall with 12mm
dia. 4 nos nut and bolts pass through in Brick
wall in 600mm spacings with necessary
washers, plate…etc
Supply and fixing Ridge Plate 70mm x
170mm section.
Supply and fixing Wall Plate 70mm x
95mm section.
Supply and fixing Hip & Valley Rafters
45mm x170mm section.
Total Carried Forward
25.00
90.00
63.00
840.00
127.00
6.00
355.00
22.00
12.00
55.00
0.00
m
m
m
m
m
m
m
m
m
m
m
Deleted
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 73
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.H.14
2.H.15
2.H.16
2.H.17
2.H.18
2.H.19
2.H.20
2.H.21
2.H.22
2.H.23
Brought forward
Supply and fixing Rafters 45mm x 120 mm
section.
Supply and fixing Rafters 45mm x 95mm
section.
Supply and fixing Purlins 95mm x145mm
section.
Supply and fixing Struts 70mm x90mm
section
Lower roof for Laundry & Staff
accommodation
Following items are not exposed under
ceiling and rate shall not include for water
based paint
Supply and fixing Ridge Plate 70 mm x
170mm section.
Supply and fixing Rafters 45mm x 120 mm
section.
Supply and fixing Rafters 45mm x 95mm
section)
Supply and fixing Battens 45mm x 20mm
section
Following Timber members' rate shall
include for applying of two coats of water
based stain and two coats of water based
top coat (Jat or equivalent) where necessary
and specified by the Engineer.
Supply and fixing Ridge Plate 90mm x
170mm section.
Supply and fixing Wall Plate 70mm x
95mm section.
Total Carried Forward
175.00
220.00
0.00
0.00
10.00
80.00
45.00
590.00
30.00
90.00
m
m
m
m
m
m
m
m
m
m
Deleted
Deleted
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 74
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.H.24
2.H.25
2.H.26
2.H.27
2.H.28
2.H.29
Brought forward
Supply and fixing Hip & Valley Rafters
45mm x170mm section.
Supply and fixing Rafters 45mm x 120 mm
section.
Supply and fixing Rafters 45mm x 95mm
section.
Supply and fixing Purlins 95mm x145mm
section.
Repairing Timber Hand rail at Kitchen
Repair work of Timber Handrail as
follows : Removing old painting with grinder
or manually from existing timber handrail,
Replace the timber if decayed and the
preparing surface and two coat of
polyurethane varnish-Matt. Rate including
prepare the surface and sanding.
For Stair hand rail at store area
Roof Connection Making
Repairing for the Roof where the roof
connected to RCC concrete corridor slab as
follows; Cutting, trimming & aligning existing
timber members and making good the edge
with fixing Barge board and work to be
completed as per Engineers approval. Rate
shall include for All necessary related
matters and painting.
Total Carried Forward
27.00
5.00
505.00
30.00
7.00
0
m
m
m
m
m
m2
Deleted
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 75
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.H.30
2.H.31
Brought forward
Cupboards
Lower & upper cupboard unit
Supplying / fabricating & fixing
approximately 3750mm long upper and
lower cupboard unit, Size of lower cupboard
- 600mm wide x725 high (approx.
size)(+825mm to granite finished level from
FFL) fixed under the granite work top and
upper cupboard - 450mm x 725mm high
(Approx. Size) consisting of Category A
timber frame work (Ref. General Notes),
door handle and 18mm thick timber planks,
to be completed with magnetic lock, plastic
knobs, self closing hinges, stainless steel
door handle and necessary accessories . as
per drawing, specification and Engineers
approval. Stainless steel sink, Brick work,
Wall tile lining/Backsplash and granite work
top measured separately. Rate shall include
for applying of two coats of water based stain
and two coats of water based top coat (Jat
or equivalent)
At First Floor Pantry
Supplying / fabricating & fixing
approximately 3000mm long upper and
lower open rack unit, Size of lower rack -
600mm wide x725 high (approx.
size)(+825mm to granite finished level from
FFL) fixed under the granite work top and
upper rack - 450mm x 725mm high (Approx.
Size) consisting of Category A timber frame
work (Ref. General Notes), with 18mm thick
timber planks and necessary accessories .
as per drawing, specification and Engineers
approval. Stainless steel sink, Brick work,
Wall tile lining/Backsplash and granite work
top measured separately. Rate shall include
for applying of two coats of water based
stain and two coats of water based top coat
(Jat or equivalent)
At First Floor kitchen
Total Carried Forward
3.80
3.00
m
m
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 76
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.H.32
Brought forward
Supplying / fabricating & fixing
approximately 5700mm long upper and
lower cupboard unit, Size of lower cupboard
- 600mm wide x725 high (approx.
size)(+825mm to granite finished level from
FFL) fixed under the granite work top and
upper cupboard -450mm x 725mm high
(Approx. Size) consisting of Category A
timber frame work (Ref. General Notes),
door handle and 18mm thick timber planks,
to be completed with magnetic lock, plastic
knobs, self closing hinges, stainless steel
door handle and necessary accessories . as
per drawing, specification and Engineers
approval. (Stainless steel sink, Brick work,
Wall tile lining/Backsplash and granite work
top measured separately).Rate shall include
for applying of two coats of water based stain
and two coats of water based top coat (Jat
or equivalent)
At First Floor Kitchen
Total Carried Forward
5.70
m
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 77
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.H.33
Brought forward
Decorative Timber Panel Wall
Supplying, Fabricating & fixing of decorated
timber panel wall as follows; Wall to be
completely prepared and to be painted with
red (approved colour) colour Emulsion paint.
Timber work shall be with 75 mm wide and
15mm thick fully prepared and approved
colour water based painted Teak Timber
strips fixed in 12.5mm spacing to same size
vertical timber members (max. Vertical
member spacings is 1200 mm) and Timber
work shall be fixed to wall using vertical
timber members and vertical timber
members shall embedded to wall plaster.
Rate shall include for all fabrication related
matters and work to be completed as per
drawings , specifications to the Engineers
approval.
14.00
m2
TOTAL CARRIED TO BILL NO. 2 COLLECTION ON PAGE S 07- 122
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 78
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.J.1
2.J.2
2.J.3
2.J.4
2.J.5
2.J.6
2.J.7
2.J.8
2.J.9
J- ROOF COVERING AND ROOF
PLUMBING
Note-Refer Pricing Preambles
Roof timber to be Group-3,Category A
Note- 2 Zink Aluminium roof sheet gauge
0.47,Hi-tensile Grade 550 colour(Rhino
Supermet or Equivalent)
Note-3Refer frame work under Trade 'F'
0.47 mm thick Zink Aluminium colour bond
tile profile roofing sheets laid on prepared
frame work, fixed as per manufacture's
specification. Roof frame work measures
separately.
For Restaurant
For Kitchen
For Dormitory and Staff accommodation
For security room
12mm thick heat insulation sheet or Bubble
Bubble foil reflective insulation sheet laying
on 75 x75 mm GI mesh on existing steel
purling and fixing with binding as per
manufacturer's specifications
For Restaurant
For Kitchen
For Dormitory and Staff accommodation
For security room
Zink Aluminium sheet ridge and hip covering
( width 914mm) fixed to roofing sheets with
necessary hooks , bolts nuts, etc.. all
complete as per Drawing and Engineers
approval.
For Restaurant
Total Carried Forward
500.00
205.00
565.00
28.00
500.00
205.00
565.00
28.00
65.00
m2
m2
m2
m2
m2
m2
m2
m2
m
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 79
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.J.10
2.J.11
2.J.12
2.J.13
2.J.14
2.J.15
2.J.16
2.J.17
Brought forward
For Kitchen
For Dormitory and Staff accommodation
Roof Plumbing
Note:
All zinc / aluminium down pipes and fittings
shall comply with the latest BSS for Zinc /
Aluminium gutters down pipes and fittings
Supplying and fixing 0.47 mm thick zinc /
Aluminium high tensile (Grade 550 ) 457mm
girth eaves Box gutter with brackets and
specials fixed complete as per
manufacture's specification.
For Restaurant
For Kitchen
For Dormitory and Staff accommodation
Supplying and fixing 0.47 mm thick zinc /
Aluminium high tensile (Grade 550 ) 914mm
girth eaves Box gutter with brackets and
specials fixed complete as per
manufacture's specification.
For Dormitory and Laundry
Supplying and fixing 300 mm High Zinc
Aluminium high tensile valance board with
brackets (with GI box bar frame work) fixed
complete as per manufacture's specification.
Rate shall include for frame painting with two
coats of anticorrosive paints and complete
the work as specified by the Engineer.
For Restaurant
For Dormitory and Staff accommodation
Total Carried Forward
43.00
55.00
92.00
52.00
90.00
9.00
92.00
90.00
m
m
m
m
m
m
m
m
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 80
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.J.18
2.J.19
2.J.20
2.J.21
2.J.22
2.J.23
2.J.24
2.J.25
2.J.26
2.J.27
2.J.28
Brought forward
Supplying and fixing (approx. height 450
mm- 600mm High) Zinc Aluminium high
tensile valance board with brackets (with GI
box bar frame work) fixed complete as per
manufacture's specification. Rate shall
include for frame painting with two coats of
anticorrosive paints and complete the work
as specified by the Engineer.
For Kitchen
Supplying and fixing Zinc Aluminium sheet
valley gutter (0.47mm) thick ,width 457mm
and fixing to roof with self trapping screws.
(Excluding timber boarding) Hi-tensile
(Grade-550)
For Restaurant
For Kitchen
For Dormitory and Staff accommodation Extra over Zinc / Aluminium down pipes and
52.00
7.00
7.00
20.00
33
10
12
5
15
40
12
m
m
m
m
Nr.
Nr.
Nr.
Nr.
Nr.
m
m
gutters for the following
Nozzle
Gutter end cap
PVC coated steel chain 8 nos fixed to each
down Zn/Al Nozzle as per detailed drawing
& Engineer's Approval.
For Restaurant (Approx. height is 5.8m)
For Kitchen (Approx. height is 5.8m)
For Dormitory area & staff accommodation
(Approx. height is 3 m)
Supplying and fixing 0.47 mm thick (
10x100mm square) zinc / Aluminium high
tensile down pipe with brackets fixed
complete as per manufacture's specification.
For Kitchen
For Dormitory area & staff accommodation
TOTAL CARRIED TO COLLECTION ON PAGE S 07 - 122
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 81
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.K.1
2.K.2
2.K.3
K - PLUMBING
Note 1 :- Refer Pricing Preambles
Sanitary fittings and fixtures
Note 2 :-
Unless otherwise stated all sanitary fittings
and fixtures shall be of(Rocell Bath ware or
equivalent:) Imported Manufacture, such as
American standard, or alternate makes. prior
written approval to be granted by the
engineer for quality & performance of
fittings. ( Specification & samples to be
produced by the contractor, whenever
requested )
Note 3 :-
All wash basins, Sinks and Urinals to be
provided with bottle traps, accordance with
BS 3943.
Supply & fixing vanity type above counter,
600 x 430 mm overall size wash basin (
Brands as specified under Note 2 above).
40 mm dia. rubber plug with chromium
plated chain. Rate to include for fixing basin
to wall , water supply and waste water
connections respectively. All complete to
Working order. (tap & bottle trap measured
separately.)(Make:Rocell ,model ECLIPSE
or equivalent ) ( Range of prime cost is Rs.
23000.00 - 27000.00 Excluding VAT)
In Male & Female Toilet
Supply & fixing Wash basin 610 x 480 mm
overall size white vitreous china (Brands as
specified under Note 2 above). 32mm dia.
rubber plug with chromium plated chain.
Rate to include for fixing basin to wall, water
supply and waste water connections
respectively. All complete to working order.
(Pillar tap & bottle trap measured
separately.)(Range of prime cost is Rs.
14000.00 - 16000.00 excluding VAT)
In Dormitory Bathroom
In Staff accommodation Bathroom
Total Carried Forward
2
3
3
Nr.
Nr.
Nr.
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 82
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.K.4
2.K.5
2.K.6
2.K.7
Brought forward
Supply & fixing corner wash basin , 400 x
300 mm overall size vitreous china wash
basin ( Brands as specified under Note 2
above).. Rate to include for fixing basin to
wall , water supply and waste water
connections respectively. All complete to
Working order. (tap & bottle trap measured
separately.)(Make:Rocell ,model Aqua or
equivalent ) ( Range of prime cost is Rs.
9000.00 - 11000.00 Excluding VAT)
In Male & Female Toilet
In Staff accommodation Bathroom
Supply and fixing Vitreous China floor
standing close coupled water closet (toilet)
suit with wash down 6/3 litre dual flushing.
Has a horizontal outlet and cistern with water
inlet from bottom.Complet with seat, seat
cover and concealed trap etc. comprising
closet with "P" or "S" trap as directed and
rate to include for fixing closet to floor with
necessary screws, fixing cistern with water
supply and outlet connection, all complete to
working order. (Make:Rocell
,model AQUA + or equivalent )(Range of
prime cost is Rs.51000.00 - 57000.00
excluding VAT)
In Male & Female Toilet
Supply and fixing Vitreous China floor
standing close coupled water closet (toilet)
suit with wash down 6/3 litre dual flushing.
Has a horizontal outlet and cistern with water
inlet from bottom.Complet with seat, seat
cover and concealed trap etc. comprising
closet with "P" or "S" trap as directed and
rate to include for fixing closet to floor with
necessary screws, fixing cistern with water
supply and outlet connection, all complete to
working order. (Make:Rocell
,model DUNE or equivalent )(Range of
prime cost is Rs.32000.00 - 35000.00
excluding VAT)
In Dormitory Bathroom
Total Carried Forward
2
1
4
1
Nr.
Nr.
Nr.
Nr.
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 83
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.K.8
2.K.9
2.K.10
2.K.11
2.K.12
2.K.13
Brought forward
In Staff accommodation Bathroom
Supply and fixing Ceramic squatting pan
with foot rest overall white vitreous china
with ' P' or ' S ' trap as directed, 9 litre
capacity white high level cistern with
supporting brackets screwed to tapered
buried in wall, P.V.C. flush pipe, water
supply and outlet connection all complete to
working order.(Make:Rocell or equivalent)
(Range of prime cost for squatting pan with
cistern Rs. 9500.00 - 10500.00 excluding
VAT)
In Dormitory Bathroom
In Staff accommodation Bathroom
Supplying and fixing Vitreous china wall
mounted Urinal with back inlet water
connection, modelled to be used with a
sensor flush valve with brackets (Brands as
specified under Note 2 above). Rate to
include for fixing urinal to wall with
necessary screws, fixing urinal flush valve
with water supply and outlet connection, all
complete to working order. (Range of prime
cost is Rs. 34000.00 - 41000.00 excluding
VAT & sensor model)
In Dormitory Bathroom
In Staff accommodation Bathroom
Supplying and fixing Urinal separator with
brackets (High pressure laminated compact
board Besco or Equivalent ). Rate to include
for fixing urinal separator to wall with
necessary screws.
In Staff accommodation Bathroom
Total Carried Forward
3
2
1
2
1
2
Nr.
Nr.
Nr.
Nr.
Nr.
Nr.
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 84
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.K.14
2.K.15
2.K.16
2.K.17
2.K.18
2.K.19
Brought forward
Supply and fixing Plate glass Mirror shall be
superior quality plate glass bevelled
rectangular mirror free from ripples and all
blemishes mounted on fibre glass frame with
chromium plated brass screws.
Mirror Size-600 x 750 mm ; in Male toilet
Mirror Size-1800 x 750 mm ; in Female
toilet
Supplying & fixing 600 x 450mm , 5mm
thickness bevelled rectangular mirror, to wall
with Rawl plugs, chromium plated fittings
…etc.
Supply & fixing Stainless steel towel rail( G
304) 10 mm dia. and 600mm long fixed to
wall with fibre plugs and chromium plated
brass screws. (Prime cost is Rs. 5000.00 -
7000.00 excluding VAT)
In Staff accommodation Bathroom
Supplying and fixing stainless steel (G 304)
soap tray fixed to wall with fibre
plugs.(Brands as specified under Note 2
above) (prime cost is Rs. 4000.00 - 5000.00
excluding VAT)
In ground floor
Supply & fixing Brush holder fixed to wall
with fibre plugs (prime cost is Rs. 1700.00 -
2000.00 excluding VAT)
In ground floor shower
Total Carried Forward
1
1
7
6
10
6
Nr.
Nr.
Nr.
Nr.
Nr.
Nr.
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 85
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.K.20
2.K.21
2.K.22
2.K.23
2.K.24
Brought forward
Supplying and fixing stainless steel(G304)
toilet paper holder fixed to wall with fibre
plugs at 600mm above finished floor level.
(Brands as specified under Note.2
above)(prime cost is Rs. 5000.00 - 6000.00
excluding VAT)
In ground floor
Double robe/cloth hook fixed to wall with
fibre plugs at 1200mm high above
floor(Rocell or equivalent)(Range of prime
cost is Rs. 2400.00 - 2600.00 excluding
In ground floor
Supply and fixing stainless steel rain shower
and 400mm length shower arm ;
(Make:Momali or equivalent ) ( Range of
prime cost is Rs. 4000.00 - 5000.00
Excluding VAT)
In Staff accommodation Gr-2 & 3 Bathroom
& Dormitory Bathroom
Supply and fixing 20mm dia stainless steel
concealed valve for shower ; (Make:Rocell
or equivalent ) ( Range of prime cost is Rs.
4500.00 - 5500.00 Excluding VAT)
In Staff accommodation Gr-2 & 3 Bathroom
& Dormitory Bathroom
Supply and fixing 20mm dia stainless steel
Single Lever shower mixer ; (Make:Rocell or
equivalent ) ( Range of prime cost is Rs.
12000.00 - 16000.00 Excluding VAT)
In Staff accommodation Gr-3 Bathroom &
Dormitory Bathroom
Total Carried Forward
8
11
6.00
5.00
1.00
Nr.
Nr.
Nr.
Nr.
Nr.
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 86
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.K.25
2.K.26
2.K.27
2.K.28
2.K.29
Brought forward
Supply and fixing 20mm dia stainless steel
Hand shower set consisting of Slide rail set
with hand shower and flexible hose ;
(Make:Rocell or equivalent ) ( Range of
prime cost is Rs. 13000.00 - 15000.00
Excluding VAT)
In Staff accommodation Gr-3 Bathroom &
Dormitory Bathroom
Supply and fixing 600mm long stainless
steel linear floor drainer ; (Make:Rocell or
equivalent ) ( Range of prime cost is Rs.
6,000.00- 10,000.00 Excluding VAT)
In kitchen pot washing area
Supply & fixing 20mm dia bidet spray tap
with flexible coupling. (Brand - rocell or
equivalent) (Range of prime cost is Rs.
4500.00 - 5500.00 excluding VAT)
In ground floor
Supply & fixing 20mm dia chromium plated
bib tap.( Rocell or equivalent )(Range of
prime cost is Rs. 3000.00 - 4000.00
excluding VAT)
In ground floor
Supply & fixing 20mm dia brass stop cock (
Pegler or equivalent)(Range of prime cost is
Rs. 2700.00 excluding VAT)
In ground floor
Total Carried Forward
1.00
1.00
8
10
6
Nr.
Nr.
Nr.
Nr.
Nr.
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 87
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.K.30
2.K.31
2.K.32
2.K.33
2.K.34
2.K.35
Brought forward
Supplying & fixing 20mm dia chromium
plated angle valve. ( Rocell or Momali or
equivalent )(Range of prime cost is Rs.
1750.00 - 2250.00 excluding VAT)
In Male & female toilet
In Dormitory Bathroom & Staff bathroom
Supplying & fixing 12mm dia. Chromium
plated swan neck tap for Kitchen sinks with
necessary specials. (Brands - Dura life
Plumber or equivalent) (Range of prime cost
is Rs. 6000.00- 7500.00 excluding VAT)
In Ground Floor
Supplying & fixing 32mm dia. Chromium
plated bottle trap (Brands as specified under
Note.2 above)(Prime cost of bottle trap is
Rs. 4000.00 - 4500.00)
In ground floor
Supplying & fixing 12mm dia chrome
finished, High spout, Single lever basin
mixer for wash basins. (Brands as specified
under Note.2 above)(Range of prime cost is
Rs. 13000.00 - 15000.00 excluding VAT)
In ground floor - restaurant
Supplying & fixing 12mm dia chrome
finished, High spout, Single lever basin tap
for wash basins. (Brands as specified under
Note.2 above)(Range of prime cost is Rs.
5000.00 - 7000.00 excluding VAT)
In ground floor
Total Carried Forward
12
15
2
11
2
11
Nr.
Nr.
Nr.
Nr.
Nr.
Nr.
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 88
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.K.36
2.K.37
2.K.38
Brought forward
Supply & fixing Stainless steel kitchen sink
(Rocell - Artisan or equivalent) of an
approved make with single bowl and single
draining board, with 38mm dia. rubber plug
and chromium plated chain . Rate to include
for fixing kitchen sink on work top with water
supply and waste water connections, all
complete to working order. ( tap & bottle trap
& tapware measured separately. ) (Range of
prime cost is Rs.24000.00 - 30000.00)
In ground floor Pantry
Supply & fixing Stainless steel wall mounted
(with stand - four legs) deep sink - Industrial
kitchen sink of an approved make with two
no's of bowl (300mm deep) with draining
board (1000mm long) and 02 nos of heavy
duty Swan neck taps with necessary rubber
plug, bottle traps, drain waste collecting
buckets, and chromium plated chain . Rate
to include for fixing kitchen sink to wall, water
supply and waste water connections, all
complete to working order. (Range of prime
cost is Rs.100,0000.00 - 125,000.00)
In ground floor
Supply and fixing of 600mm long flexible
hose ( Rocell or equivalent)(prime cost is
Rs.1300)
Sanitary Plumbing
Water Supply Pipes
Note
All water supply pipe work shall be in PVC
type PNT11 to SLS 147:1993 and PVC
fittings to SLS 659:1993
All pipe work with less than 600mm of
ground cover and all pipe work under
roadways with less than 900mm of ground
cover are to be encased in concrete
Total Carried Forward
2
1
30
Nr.
Nr.
Nr.
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 89
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.K.39
2.K.40
2.K.41
2.K.42
2.K.43
2.K.44
2.K.45
2.K.46
2.K.47
2.K.48
2.K.49
Brought forward
Piping under 50mm dia. include for all
necessary elbows, bends, tees, Junctions,
inspection openings and similar fixtures.
32 mm dia (1'') water supply incoming pipe;
from water meter to sump laid under ground.
50mm dia (1 1/2 '') water supply incoming
pipe from sump & pump house to over head
tank laid under ground or fixed to wall as
directed.
63 mm dia (2'') Distribution pipe line from
water tank to delivery pipes fixed to wall or
buried in floor or screed as directed.
32 mm dia distribution pipe laid under
ground or buried in floor screed as directed.
25mm dia distribution pipe laid under ground
or buried in floor screed as directed.
20mm dia distribution pipe as connection to
sanitary fittings fixed to wall or buried in floor
screed as directed.
40 mm dia distribution pipe laid under
ground or buried in floor screed as directed.
Extra over for above UPVC pipes in the
following;
63mm dia bend
63 x 63 x 50mm dia unequal tee
63 x 50mm dia reducing socket
63 mm dia stop valve (Water Tek
equivalent)
Total Carried Forward
25.00
45.00
25.00
170.00
110.00
70.00
5.00
4.00
4.00
4.00
1.00
m
m
m
m
m
m
m
Nr.
Nr.
Nr.
Nr.
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 90
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.K.50
2.K.51
2.K.52
2.K.53
2.K.54
2.K.55
2.K.56
2.K.57
2.K.58
2.K.59
2.K.60
2.K.61
2.K.62
Brought forward
63 mm dia Elbow (Water tek equivalent)
63 mm dia Elbow with cleaning eye (Water
tek equivalent)
63 mm dia T with cleaning eye (Water tek
equivalent)
50 mm dia stop valve (Water tech
equivalent)
25 mm dia brass gate valve (Pegler or
equivalent)
20 mm dia brass gate valve (Pegler or
equivalent)
Waste water pipes
Note:
All underground drainage pipe work shall be
in UPVC (Class 4.0) to BS 4660
63mm dia. waste water pipe buried in floor
screed or chased to wall or laid as directed
by the Engineer
50 mm dia. waste water pipe buried in floor
screed or chased to wall or laid as directed
by the Engineer
63mm dia vertical vent pipe carried 450mm
above roof level fixed to wall with rawl plugs,
clips and screws as directed.
110mm dia. waste water pipes extended
from trap gulley to the nearest waste water
manhole with average invert depth not
exceeding 900mm including excavation and
back filling , bedding on a layer of cement
concrete Grade C-15-1:3:6 (25 mm) 100mm
thick and 100mm wide on each side of the
pipe and subsequently encasing with the
same concrete after inspection of the pipe
Extra over UPVC pipes for the following;
63mm dia bend
63mm dia bend with cleaning eye
63mm dia tee
Total Carried Forward
1.00
Nr.
1.00 Nr.
1.00 Nr.
1.00
6.00
1.00
100.00
30.00
20.00
25.00
10
10
4
Nr.
Nr.
Nr.
m
m
m
m
Nr.
Nr.
Nr.
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 91
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.K.63
2.K.64
2.K.65
2.K.66
2.K.67
2.K.68
2.K.69
2.K.70
Brought forward
63 x 63 x 50mm dia unequal tee
110mm dia Tee with cleaning eye
110mm dia Y
63 mm dia Y
Supply and fixing of 63 mm dia "P" trap in
externally with cleaning eye.
Drain at Laundry Room
RCC drain for laundry room, 250 mm wide
and 200 mm starting depth internally built to
slope in RCC concrete Grade C20 (1:2:4) in
75 mm thick base and 75mm thick side walls
covered with mild steel grating cover ( R10
mild steel bars welded in 25mm spacings c/c
to 25 x 25 mm and 3mm thick equal angle
frames, each frame will be in length of
1000mm) , complete with 12mm thick
cement and sand 1:3 rendering, finished
smooth with neat cement floating to all
exposed surfaces . Rate to include for
demolishing brick paving, necessary
excavation work, Reinforcement, Formwork
& all necessary related work....etc and
completing the item as per the Engineers'
approval.
Soil and vent pipes
Note ;All above ground soil & waste pipe
work shall be in PVC (Class 4.0) to BS 4514
and BS 5255
110mm dia. soil pipe extended from closets
to the nearest manhole with average invert
depth not exceeding 900mm including
excavation and back filling , bedding on a
layer of cement concrete 1:4:8(38mm)
100mm thick and 100mm wide on each side
of the pipe and subsequently encasing with
the same concrete after inspection of the
pipe
110mm dia. soil pipe buried in floor screed
or laid as directed by Engineer
Total Carried Forward
1
2
1
1
10.00
35.00
120.00
5.00
Nr.
Nr.
Nr.
Nr.
Nr.
m
m
m
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 92
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.K.71
2.K.72
2.K.73
2.K.74
2.K.75
2.K.76
2.K.77
2.K.78
Brought forward
110mm dia vertical soil stack carried
450mm above roof level as vent fixed to
wall with rawl plugs, clips and screws as
directed.
Extra over UPVC pipes for the following;
110mm dia tee with cleaning eye
110 mm dia bend with cleaning eye
110 mm dia Y
Accessories
Supplying and installing Single phase
pressure pump(Jinasena or equivalent) to
be installed on the pump house. Rate to be
inclusive of valves, sockets and necessary
fittings and fixtures including rubber joints
and work to be completed as per
specification and Engineers Approval.
Trapped floor gully to be UPVC
(150X150X118). Trapped floor gully to be
connected to waste water line with solvent
cement & unconnected opening to be sealed
with end caps with solvent cements.
Supplying and fixing of stainless steel gully
cover (rocell or equivalent , Prime cost is
RS 3800.00 - 4500.00 Without VAT)
Collecting box 150 x 150 x 150 mm deep
internally, built in 75mm thick cement
concrete 1:2:4 ( 20mm ) sides and bottom
including 12mm thick cement and sand 1:2
rendering finished smooth with neat cement
floating to all exposed faces and cast iron
grating on top, complete with inlet and outlet
connections in ground floor
Total Carried Forward
25.00
4
12.00
2.00
2
16
16.00
2
m
Nr.
Nr.
Nr.
Nr
Nr.
Nr.
Nr.
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 93
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.K.79
2.K.80
2.K.81
2.K.82
Brought forward
Electric water Heater
Supplying and fixing 50 Litre Electric water
Heater with flexible hose (Ariston or equi) on
a wall and connected to the hot water supply
system as per Engineers' approval (hot
water piping system paid separately).
(Range of Prime Cost of, Water heater 50 lit.
is Rs.28000.00 - 32000.00 )
For Kitchen
Supplying and fixing 30 Litre Electric water
Heater with flexible hose (Ariston or equi) on
a wall and connected to the hot water supply
system as per Engineers' approval (hot
water piping system paid separately).
(Range of Prime Cost of, Water heater 50 lit.
is Rs.25000.00 - 29000.00 )
For Restaurant
For Staff Grade 1 bathroom
hot water piping system
Hot water supply pipe & fittings shall be in
CPVC type SDR11
All Pipes should have high anti-corrosive
properties and will stand firm in high
temperatures and harsh application
conditions
Rate shall include for all necessary elbows,
bends, tees, Junctions, inspection openings
,similar fixtures. and for cutting walls and
making good the wall after installation.
20mm dia (1/2'') distribution pipe as
connection to sanitary fittings fixed to wall or
buried in floor screed as directed.
Total Carried Forward
1.00
1.00
1.00
60.00
Nr.
Nr.
Nr.
m
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 94
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.K.83
2.K.84
Brought forward
25 mm dia (3/4'') distribution pipe laid under
ground or buried in floor screed as directed.
Supplying and fixing of swan neck type hot
and cold water mixture tap for kitchen sink
with flexible hose water dispenser shower.
Brand Rocell or Equivalent & prime cost is
Rs. 10000.00 - 12500.00)
10.00
2.00
m
Nr
TOTAL CARRIED TO COLLECTION ON PAGE S 07 - 122
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 95
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.L.1
2.L.2
2.L.3
2.L.4
2.L.5
2.L.6
L - WALL, FLOOR AND CEILING
FINISHES
Note-Refer Pricing Preambles
Plinth plaster
15mm thick plaster in cement and sand in
1:3 finished smooth with coloured cement
floating to plinth including forming arises
Finishes on External walls
Plaster 15mm thick in cement and sand (1:5)
finished semi rough including forming arises
(Externally.)
On brick walls, attached columns
In Staff accommodation, laundry &
Dormitory.
In Kitchen, Store & Entrance building
Plaster 12mm thick in cement and sand (1:3)
finished semi rough including forming arises
(Externally.)
Reveals not exceeding 150mm wide
At Ground Floor and First Floor
Moulding not exceeding 150 mm wide
At Ground Floor and First Floor
Plaster 12mm thick in cement and sand 1:3
finished semi-rough including forming arises
(Externally)
On Isolated columns
In Ground Floor
Total Carried Forward
85.00
295.00
200.00
235.00
120.00
25.00
m2
m2
m2
m
m
m2
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 96
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.L.7
2.L.8
2.L.9
2.L.10
2.L.11
2.L.12
2.L.13
Brought forward
Plaster 12mm thick in cement and sand (1:3)
finished smooth with lime putty including
forming arises (Internally.)
In suspended floor slab
Soffit of First floor slab of connecting slab
Sides of First floor slab of connecting slab
Finishes on Internal walls
Plaster 15mm thick in cement and sand
(1:5) finished smooth with joint compound
including forming arises (Internally.)
On brick walls, attached columns
In Staff accommodation, laundry &
Dormitory.
In Kitchen, Store & Entrance building
Plaster 12mm thick in cement and sand (1:3)
finished smooth with joint compound
including forming arises (Internally.)
Reveals not exceeding 150mm wide
From ground floor level to lower roof level
Moulding not exceeding 150 mm wide
At Ground Floor and First Floor
On isolated column
At ground floor level - Entrance Building
Plaster 12mm thick in cement and sand (1:3)
finished smooth with lime putty including
forming arises (Internally.)
Total Carried Forward
150.00
110.00
985.00
295.00
300.00
40.00
125.00
m2
m
m2
m2
m
m
m2
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 97
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.L.14
2.L.15
2.L.16
2.L.17
2.L.18
2.L.19
2.L.20
2.L.21
Brought forward
In suspended floor slab
Soffit of First floor slab of Entrance Building
In isolated beams
Side & soffit of First floor slab of Entrance
Building
Wall tiles
Tiles should be fixed to wall using a
recommended Tile Adhesive(Brand Swiss tek
or equivalent). As per Specification and
Engineers Approval.
Supply and laying 300 x 600mm glazed
ceramic wall tiles lining up to a height of 1500
mm from finished floor level of approved
colour set in 10mm thick cement and sand
(1:3) screed backing and joints pointed with
tile grout to match the colour of tiles in toilets
(Prime cost Rs. 550.00
-850.00 per tile with out VAT )
In ground Floor Dormitory Bathroom & Staff
Bathroom
In ground Floor Male&Female Bathroom
In ground Floor Laundry
In First Floor Kitchen
Floor Finishes
Cement Rendering on Floors
Rendering, 12 mm thick in cement and sand
(1:3) , and finished with floating coat, using
neat Cement and finished smooth with
Colour pigments.
For Store room , Gas room
For Pavement Ramp
Total Carried Forward
35.00
22.00
120.00
55.00
42.00
82.00
32.00
210.00
m2
m2
m2
m2
m2
m2
m2
m2
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 98
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.L.22
2.L.23
2.L.24
2.L.25
Brought forward
Floor Finishes
Floor Tiles
Note 1: Refer pricing Preambles
Note 2: Paving of tiles should be on 10mm
thick cement and sand (1:3) rough cement
rendering, and the joints pointed with tile
grout to match the colour of tiles in all floor
area.
Tiles should be fixed to floor/wall using a
recommended Tile Adhesive(Brand Swiss
TEK or equivalent). As per Specification
and Engineers Approval
Tiles should be fixed on existing tile using a
recommended Tile Adhesive (Brand Swiss
TEK- Ultra Grip tile mortar or equivalent).
As per Specification and Engineers Approval
Tile on Floor
Supply and laying 600 x 600 mm non slippery
coloured semi glazed porcelain
homogeneous floor tiles paving to floor in
approved colour and design laying as
specified above ( Refer Note 2 )(Prime cost
Rs. 1100.00-1500.00 per tile with out Vat )
For Staff Accommodation
For Dormitory & Laundry room
For Store & Gas room
For Kitchen & pantry
Total Carried Forward
92.00
152.00
106.00
108.00
m2
m2
m2
m2
Deleted
Deleted
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 99
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.L.26
2.L.27
2.L.28
2.L.29
2.L.30
2.L.31
Brought forward
Supply and laying 600 x 600 mm non slippery
coloured full body porcelain mat finished floor
tiles paving in approved colour and design
laying as specified above ( Refer Note 2
)(Prime cost Rs. 1300.00
-1700.00 per tile with out Vat )
For Ground floor corridor and veranda
For Ground floor Connecting corridor
For First Floor Connecting corridor
Supply and laying 600 x 600mm non slippery
coloured mat finish porcelain homogeneous
heavy duty floor tiles paving in approved
colour and design laying as specified above (
Refer Note 2 ) (Prime cost Rs.1300.00 -
1700.00 per tile with out Vat )
In ground floor Bathroom & toilet
Tile on Existing Tile Surface
Supply and laying 600 x 600 mm non
slippery coloured semi glazed porcelain
homogeneous floor tiles paving on existing
tile surface in approved colour and design
laying as specified above ( Refer Note
2 )(Prime cost Rs. 1100.00 - 1500.00 per
tile with out Vat )
For Ground Floor Lobby, office & reception
For First floor restaurant
Total Carried Forward
86.00
130.00
160.00
65.00
185.00
214.00
m2
m2
m2
m2
m2
m2
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 100
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.L.32
2.L.33
2.L.34
2.L.35
2.L.36
2.L.37
Brought forward
Tile skirting
100mm high tile skirting laid on and including
10mm thick cement and sand (1:3) screed
backing and the joints pointed with tile grout
to match the colour of tiles. (Prime cost Rs.
1100.00 - 1500.00 per 600 x 600mm tile with
out Vat )
at Ground floor rooms
100mm high tile skirting laid on and
including 10mm thick cement and sand
(1:3) screed backing and the joints pointed
with tile grout to match the colour of tiles.
(Prime cost Rs. 1300.00 - 1700.00 per tile
600 x 600 mm with out Vat )
at Ground floor corridor and veranda
at First floor Connecting Corridor
Stair Tile on Existing Tile Surface
Supply and laying 600 x 600 mm non
slippery coloured semi glazed porcelain
homogeneous floor tiles paving on existing
tile surface in approved colour and design
laying as specified above ( Refer Note 2
)(Prime cost Rs. 1450-1750 per tile with out
Vat )
Stair case landing at restaurant area
300mm wide treads at Restaurant
155mm-200 mm wide treads at Restaurant
Total Carried Forward
500.00
50.00
105.00
5.40
52.00
52.00
m
m
m
m2
m
m
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 101
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.L.38
2.L.39
Brought forward
Ceiling finishes
Cement fibre board ceiling
Supplying & fixing of 600x600 & 3.5 mm
thick Cement fibre ceiling boards lay on hot
dip GI pre engineered interlocking ceiling
frame work.
The frame members for suspended ceiling
are in a standard kit (CKM or equivalent).
Main runners (38mmx24mmx3660mm) are
fixed at 1220 centres securely suspended
using 4mm dia adjustable GI hanging rod
with spring clips to the structural soffit or
existing roof structure, using an appropriate
suspension at 1220mm intervals along each
Main runners.
Cross Tees (27mmx24mmx1220mm) of
1220mm length to be fixed between the
main runners at 610mm centres and another
cross tees (27mmx24mmx610mm) fixed at
mid span between 610mm to form a grid
structure of 610mmx 610mm in size. wall
angles (24mmx24mmx3050mm) are fixed at
wall edges.
In Ground Floor Laundry Area, Linen room &
Gas room ( Eaves ceiling shall be Timber
ceiling and Measured Separately )
In First Floor Kitchen , Chef room & pantry (
Eaves ceiling shall be Timber ceiling and
Measured Separately )
Total Carried Forward
68.00
120.00
m2
m2
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 102
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.L.40
2.L.41
2.L.42
2.L.43
2.L.44
2.L.45
Brought forward
Timber Ceiling finishes
Timber used for ceiling shall conform to the
requirements stipulated in Chapter 8.0 wood
work (ICTAD specification SCA/4
And the timber Species for ceiling framing
shall be (category A) of respective group as
listed under General notes.
Note 1:-Ceiling planks ( one side only )
painted with two coats of water based stain
and two coats of water based top coat (Jat
or equivalent) where necessary and
specified by the Engineer.
Timber Sloped, exposed rafter ceiling with
20 mm thick Lunumedella tongued and
grooved timber planks fixed as per detail
Drg.and Engineer's approval
In Ground Floor Dormitory
In Ground Floor Staff accommodation &
veranda
In First Floor Restaurant
Eave Ceiling
Timber Sloped, exposed rafter ceiling with
18 mm thick Lunumedella tongued and
grooved timber planks fixed as per detail
Drg.and Engineer's approval
In Ground Floor Dormitory
In Ground Floor Staff accommodation &
veranda
In First Floor Restaurant
Total Carried Forward
146.00
210.00
275.00
37.00
70.00
225.00
m2
m2
m2
m2
m2
m2
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 103
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.L.46
2.L.47
Brought forward
Timber sloped exposed rafter Eve Ceiling
with 18mm thick Lunumudella tongued and
grooved timber planks, fixed on Timber
rafter, one end of Timber rafter shall be
hanged on Steel frame work and other end
fixed to wall with angle iron cleat mounted
to wall with 10mm in dia. anchor bolt. This
shall be matched with other eve ceiling.
Rate to be include for water based painting
in approved colour and completing item with
all related matters considering.
In First Floor Kitchen
Construction of 25mm x 25mm weather
guard at sunshades 1:3 cement & sand
mortar
55.00
100.00
m2
m
TOTAL CARRIED TO COLLECTION ON PAGE S 07 - 122
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 104
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
M - ELECTRICAL INSTALLATION
Refer Drawing No:
Refer Pricing Preambles
Electrical items are to be of the following
makes:
(a) Electrical switches and socket outlets :
Krypton, Legrand, Clipsal, Kevilton, Orange
or equivalent
(b) Distribution boards: Consumer unit flush
mount type or as specified
(c) Fans:
K.D.K., National-Japanese origins
(d) Exhaust Fans:
K.D.K., National-Japanese origins
(e) Switch Gear - MCCB'S
Schneider ,ABB, Siemens, Hager, LS
Brand or approved equivalent
[f] RCCB , MCB'S
Schneider, Siemens, Hager, ETN Brand or
approved equivalent
[g] LED/ Tube Fittings :
The light should be good quality, Philips or
equivalent. Minimum efficacy at scotopic
condition should be above 100 lumen/w.
correlate colour temperature (CCT) should
be above 4000k, (cool white). colour
rendering index (CRI) should be above 80.
rated life time should be above 50,000 hrs.
[h] Energy saving Bulbs CFL/LED bulbs
should be 4 stars or above.
[i] Distribution sub panels: Shall be in
surface mount plastic enclosure or metal
enclosure fabricated with zinc coated sheet
metal of gauge not less than 1.8mm total
enclosed, with hinged door with protective
cover plate for terminals. Finished with
powder coating of approval colour and
components as specified in the BOQ
[j] Cable : ACL , Kelani or equivalent.
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 105
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.M.1
2.M.2
2.M.3
2.M.4
2.M.5
2.M.6
Brought forward
[kj] Energy saving bulbs : 4 Star rated.
Wiring type in concealed conduit, floor
conduit, metal or PVC trunking
All panel boards and consumer units should
have wire numbering and a laminated circuit
diagram should be pasted on the inside
surface of the door.
All types of fittings, materials, painting and
finishes shall be approved by the Electrical
Engineer prior to installation.
[L] hot water piping
hot water piping shall be insulated using
fibre glass blankets of not less than 25mm
thickness valves, pumps and strainers shall
be neatly boxed in .hot water system must
have an 20A separate MCB and hot water
system must contain internal ELCB and Test
switch in it.
Wiring of light points
Wiring of a light point includes supply of
required cables, conduits, ceiling rose,
junction boxes, flush switch & all other
required materials .
Wiring of a light point , from respective
Consumer unit using 2 x 1mm2 , CU / PVC/
PVC cable + 2.5mm2 Cu/PVC Earth cable
drawn through securely fixed concealed
PVC conduit , Controlled by a 10A flush
switch .
At Store and other area - ground floor
At upper floor - Kitchen
At Restaurant - Upper floor
At Restaurant - Ground floor-main lobby
At Generator room (two sides to be covered)
At Corridor
Total Carried Forward
92
46
15
23
2
8
Nr
Nr
Nr
Nr
Nr
Nr
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 106
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.M.7
2.M.8
2.M.9
2.M.10
2.M.11
2.M.12
2.M.13
2.M.14
2.M.15
2.M.16
Brought forward
Nr
Nr
Nr
Nr
Nr
Deleted
Wiring of 13A Socket outlets flush mounted.
Wiring (including supply of all material
required ) of 13A socket outlets flush
mounted using 2.5 mm2 Cu/PVC/PVC, 2C
cable & 2.5 mm2 earth cable drawn through
securely fixed concealed PVC conduit.
At Store and other area - ground floor 39
At upper floor - Kitchen 15
At Restaurant - Upper floor 10
Ground floor main lobby 7
At Generator room (two sides to be covered) 2
Wiring of 3 pin 16A industrial Socket outlets flush mounted.
Wiring (including supply of all material
required ) & installation and commissioning
of 30 kW DC EV Car charging point with 10
inch Display and complete to working order
(GoEV EX30 or Equivalent)
Ground floor (for car charging)
Ceiling fan Point Wiring
Wiring (including supply of all material, earth
wire, fan hook, regulator & switch) of the
ceiling fans using 2 x 1mm2
Cu/PVC/PVC + 2.5 mm2 earth wire drawn
through securely fixed concealed PVC
conduits.
At Store and other area - ground floor
At upper floor - Kitchen
At Restaurant - Upper floor
Ground floor main lobby
Total Carried Forward
0
20
6
8
5
Nr
Nr
Nr
Nr
Nr
Deleted
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 107
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.M.17
2.M.18
2.M.19
2.M.20
2.M.21
2.M.22
2.M.23
Brought forward
Exhaust fan Point Wiring
Wiring (including supply of all material, earth
wire, fan hook, regulator & switch) of the
exhaust fans using 2 x 2.5mm2
Cu/PVC/PVC + 2.5 mm2 earth wire drawn
through securely fixed concealed PVC
conduits including 13A socket outlet close to
the fan.
At Store and other area - ground floor
At upper floor - Kitchen
Hand drier Point Wiring
Wiring (including supply of all material, earth
wire & switch) of the Hand driers using 2x
2.5mm2, Cu/PVC/PVC + 2.5
mm2 earth wire drawn through securely fixed
concealed PVC conduits including 13A
socket outlet close to the Hand driers.
At Main lobby visitors bathroom
At Restaurant :- Upper floor
Hot Water point wiring
hot water point (including supply of all
material of earth wire and the switch) must
be wired using 2X2.5mm2,Cu/PVC/PVC +
2.5mm2 earth wire drawn through securely
fixed concealed PVC Conduits including 13A
Socket outlets close to hot water
system(IP65).must be distributed by isolated
cable from the DB to 13A switch through 20A
breaker.
At upper floor - Kitchen
At Restaurant
At staff room
Total Carried Forward
6
3
2
1
1
1
1
Nr
Nr
Nr
Nr
Nr
Nr
Nr
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 108
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.M.24
2.M.25
2.M.26
2.M.27
2.M.28
2.M.29
2.M.30
2.M.31
2.M.32
2.M.33
2.M.34
2.M.35
Brought forward
Luminaire's and fixtures
Supply & install of following light fittings.
Light fittings shall be of high quality & shall
be subject to the approval of the Electrical
Engineer prior to the installation.
Supply & installation of wall mounted twin
box led weather proof ip66 6w up down
light.
At ground floor
At upper floor- Kitchen
At Restaurant
Supply & installation of pendant lamp C/W
250mm dia, conical plastic shade and 10W
LED bulb(P5)
At ground floor
At upper floor
Supply & installation of ceiling pendant lamp
C/W 200mmdia glass globe 10W LED Bulb
At ground floor
At upper floor
At Generator room
Supply & installation of ceiling 1200mm
suspension type T8 LED rub light complete
with 1x18W tube(Industrial type)(L6)
At ground floor
At upper floor
Supply & installation of recessed type
1200mm T8 LED tube light 1X18W fitting .
At ground floor
At upper floor
Total Carried Forward
27
8
12
12
5
3
2
2
18
2
19
1
Nr
Nr
Nr
Nr
Nr
Nr
Nr
Nr
Nr
Nr
Nr
Nr
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 109
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.M.36
2.M.37
2.M.38
2.M.39
2.M.40
2.M.41
2.M.42
2.M.43
2.M.44
2.M.45
2.M.46
2.M.47
Brought forward
Supply & installation of Square type
(210x210mm) surface mounted light fitting
weather proof type C/W 12W LED bulb.(C4)
At ground floor
Supply & installation of Ceiling lamp Surface
Mounted 15W(C1)
At ground floor
Supply & installation of 450mm dia Industrial
Exhaust fan with shutter (KDK or equivalent)
Supply & installation of 450mm dia Industrial
(High pressure) Exhaust fan with shutter
(KDK or equivalent)
Supply & installation of 300mm dia. Exhaust
fan with auto shutter(IP65)
At ground floor
Supply & installation of spot light indoor.
(SPt)(IP66)(15W)
At ground floor
At upper floor(restaurant area)
Supply & installation of wall fans 65W
At ground floor
Supply & installation of hand dryer. (HD)
At Restaurant :- Upper floor
At Main lobby :- Ground floor
Supply & installation of ceiling fan 1400mm
dia controlled by 5 speed fan regulator &
10A switch (F)
At ground floor
At upper floor
Total Carried Forward
7
6
2
1
6
1
16
2
1
2
23
6
Nr
Nr
Nr
Nr
Nr
Nr
Nr
Nr
Nr
Nr
Nr
Nr
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 110
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.M.48
2.M.49
2.M.50
2.M.51
2.M.52
2.M.53
2.M.54
2.M.55
Brought forward
Supplying & installation of Decorating ceiling
fan (KDK black) (Prime cost Rs.14000.00 -
15000.00)
Supply & installation of surge arrestor for
the total electrical system
At ground floor
Supply & installation of 400mm in size
Industrial type exhaust fan wired through a
13A socket outlet at high level.(EF) (KDK or
equivalent) (Prime cost Rs.43000.00 -
48500.00)
At upper floor- Kitchen
Supplying, installation and fixing of
Decorative Pendant type lobby light fitting
(Candle light)(prime cost Rs. 50000.00 -
60000.00)
At main building
At Restaurant - Upper floor
Supplying, installation fixing and
Commissioning of Decorative Pendant type
Spot light fitting (Edison bulb or LED
Filament bulb)(track bar hanging type)
(Prime cost Rs. 25000.00 - 28000.00)
At Restaurant
Supply installation fixing and
Commissioning of Decorative Ceiling
mounted light fitting (Prime cost Rs.
6750.00 - 7500.00)
At Restaurant
Supply installation fixing and Commissioning
of Decorative bell type pendant light
fitting(Led or round tube light minimum
dimension 250 mm-300mm in dia and
450mm in high )(Prime cost:- Rs 12500.00)
At Restaurant :- Ground floor
Total Carried Forward
11
1
0
3
3
1
14
8
Nr
P.Su
m.
Nr
Nr
Nr
Nr
Nr
Nr
200,000.00
Deleted
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 111
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.M.56
2.M.57
2.M.58
2.M.59
2.M.60
Brought forward
Supply installation fixing and
Commissioning of Decorative Bell type
Pendant light fitting (Edison bulb or LED
Filament bulb)(Prime cost Rs. 4500.00 -
6000.00)
At Restaurant :- Upper floor
Supplying installation & fixing and
commissioning of 150 KVA Diesel Generator
along with sound proofing including all
necessary equipment's with ATS(Cummings
or equivalent)
At generator room
SP - lobby wiring recessed type wall
mounted plastic enclosure as specified
complete with following switch gears to be
supplied and installed to working order.
1 No 30A 2P MCB
1 No. 40A 2P RCD (30 mA sensitive) )
3 Nos 6A 1P MCB
3 Nos 20A 1P MCB
DB-2 (upper floor) in recessed type wall
mounted plastic enclosure as specified
complete with following switch gears to be
supplied and installed to working order.
1 No. 30A 2P MCB
1 No. 40A 2P RCD (30 mA sensitive) )
2 Nos. 20A 1P MCB
4 Nos. 6A 1P MCB
A/C - Switch - With 20A 2P MCB in plastic
enclosure to be supplied and installed to
working order.
Total Carried Forward
3
1
1
1
2
Nr
PS
Nr
Nr
Nr
7,200,000.00
7,200,000.00
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 112
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.M.61
2.M.62
2.M.63
2.M.64
Brought forward
DB-3 (kitchen) in recessed type wall
mounted plastic enclosure as specified
complete with following switch gears to be
supplied and installed to working order.
1 No. 30A 2P MCB
1 No. 40A 2P RCD (30 mA sensitive) )
4 Nos. 20A 1P MCB
2 Nos. 6A 1P MCB
DB - Driver in recessed type wall mounted
plastic enclosure as specified complete with
following switch gears to be supplied and
installed to working order.
1 No.30A 2P MCB
1 No.40A 2P RCD
4 No .20A 1P MCB
2 No.6A 1P MCB
DB-Stores Supplying and installation of wall
mounted (MSB-Panel) ,Recessed Enclosure
made electro Zinc coated sheet steel with
thickness not less than 1.5 mm -
2.00 mm and powder coated in Ivory grey
textured finish , should meet IP 54 Protection
level. Internal wiring , should be comply with
BS 7671:2008. Following items should as
follows;
1 No.100A 4P MCCB
4 No.30A 2P MCB
3 No. Indication lights
1 No.40A 30MA 2P RCCB
1 No 20A 1P MCB
2 No 6A 1P MCB
DB-Laundry in recessed type wall mounted
plastic enclosure as specified complete with
following switch gears to be supplied and
installed to working order.
1 No 30A 2P MCB
1 No 40A 2P 30mA RCCB
4 No 20A 1P MCB
Total Carried Forward
1
1
1
1
Nr
Nr
Nr
Nr
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 113
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.M.65
2.M.66
2.M.67
2.M.68
Brought forward
DB-Staff in recessed type wall mounted
plastic enclosure as specified complete
with following switch gears to be supplied
and installed to working order.
1 No 30A 2P MCB
1 No 40A 2P 30mA RCCB
2 No 6A 1P MCB
2No 20A 1P MCB
DB-Toilet in recessed type wall mounted
plastic enclosure as specified complete with
following switch gears to be supplied and
installed to working order.
1 No 30A 2P MCB
1 No 40A 2P 30mA RCCB
2 No 6A 1P MCB
2 No 20A 1P MCB
DB-SGR2 in recessed type wall mounted
plastic enclosure as specified complete with
following switch gears to be supplied and
installed to working order.
1 No 30A 2P MCB
1No 40A 2P 30mA RCCB
2 No 6A 1P MCB
2 No 20A 1P MCB
Main Switch Board (MSB) (In Panel room)
Upgrading of wall mounted (MSB- Panel) as
per given electrical drawing with replacing of
1 Nos of 160A 4P MCCB
Total Carried Forward
1
1
1
1.00
Nr
Nr
Nr
Nr
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 114
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.M.69
2.M.70
Brought forward
ATS Panel (Generator Room) - Supplying
fixing and commissioning of wall mounted
Enclosure made electro Zinc coated sheet
steel with dimensions of
1000mmx750mmx250mm thickness not
less than 1.5 mm -2.00 mm and powder
coated in Ivory grey textured finish , should
meet IP 54 Protection level. Internal wiring ,
should be comply with BS 7671:2008.
Following items should as follows;
6 Nos of indicator lamps along with 2 fuses
3 Nos of 250A 4P MCCB
1 Nos of 250A 4P ATS
Sub panel 01 (Ground floor lobby)
Supplying fixing and commissioning of wall
mounted Enclosure made electro Zinc
coated sheet steel with dimensions of
1000mmx750mmx250mm thickness not
less than 1.5 mm -2.00 mm and powder
coated in Ivory grey textured finish , should
meet IP 54 Protection level. Internal wiring ,
should be comply with BS 7671:2008.
Following items should as follows;
3 Nos of indicators with fuse
1 Nos 160A 4P MCCB
1 set of 200A 4P Bus bar with earth bar
1 Nos 100A 4P MCCB
1 Nos 60A 4P MCCB
1 Nos 30A 3P MCB
6 Nos 30A 2P MCB
1 Nos 20A 4P MCB
1 Nos 40A 2P RCD(30mA)
3 Nos 20A 1P MCB
5 Nos 6A 1P MCB
Total Carried Forward
1.00
1.00
PS
Item
520,000.00
520,000.00
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 115
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.M.71
2.M.72
2.M.73
2.M.74
Brought forward
AC Panel (From Sub panel 01)Supplying
fixing and commissioning of wall mounted
metal Enclosure made electro Zinc coated
sheet steel with dimensions of
500mmx450mmx250mm thickness not less
than 1.5 mm -2.00 mm and powder coated
in Ivory grey textured finish , should meet IP
54 Protection level. Internal wiring , should
be comply with BS 7671:2008. Following
items should as follows;
6 Nos 20A 4P MCB
6 Nos 40A 4P RCD
1 Nos 100A 4P MCCB
Sub Panel -02 (In panel room)Supplying
fixing and commissioning of wall mounted
metal Enclosure made electro Zinc coated
sheet steel with dimensions of
1000mmx750mmx250mm thickness not
less than 1.5 mm -2.00 mm and powder
coated in Ivory grey textured finish , should
meet IP 54 Protection level. Internal wiring ,
should be comply with BS 7671:2008.
Following items should as follows;
1 Nos 125A 4P MCCB
1 Set 150A 4P Bus Bar with earth bar
5 Nos 60A 4P MCCB
1 Nos 30A 4P MCB
Commissioning and supply wires
4C 150mm2 Cu/XLPE/PVC/SWA/PVC UG
Cable
4C 70mm2 Cu/XLPE/PVC/SWA/PVC UG
Cable
4x50mm2 Cu/PVC/PVC Cable + 25mm2
CU/PVC Earth
Total Carried Forward
1.00
120.00
47.00
12.00
Item
Item
m
m
m
Deleted
Deleted
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 116
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.M.75
2.M.76
2.M.77
2.M.78
2.M.79
2.M.80
2.M.81
2.M.82
2.M.83
2.M.84
Brought forward
4x35mm2 Cu/PVC/PVC Cable + 16mm2
CU/PVC Earth
4x25mm2 Cu/PVC/PVC Cable + 16mm2
CU/PVC Earth
4x10mm2 Cu/PVC/PVC Cable + 10mm2
CU/PVC Earth
4x4mm2 Cu/PVC/PVC Cable + 4mm2
CU/PVC Earth
2x16mm2 Cu//PVC/PVC Cable + 16mm2
CU/PVC Earth
2x6mm2 Cu//PVC/PVC Cable + 6mm2
CU/PVC Earth
2 x 2.5mm2 Cu/PVC/PVC Cable + 2.5mm2
Cu/PVC Earth cable.
2 x 1mm2 Cu/PVC/PVC Cable + 2.5mm2
16mm2 Cu/PVC Earth cable.
Supply & installation of GI pipe as earth
electrode with 50mm dia. & earth cable
should be fixed with proper nut & bolts.
Total Carried Forward
10.00
60.00
65.00
190.00
150.00
90.00
115.00
115.00
10.00
4.00
m
m
m
m
m
m
m
m
m
Nr
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 117
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.M.85
2.M.86
2.M.87
2.M.88
2.M.89
Brought forward
5W Decorative lights for Managers
Quarters and Generator entrance gate
posts with IP67 or higher and to the
Engineer's Approval(Prime cost of the
fittings Rs. 2500.00 - 2800.00)
Kitchen Hood
Supplying and fixing of 900mm stainless
steel kitchen hood for gas burners. Rate to
include all related matters excluding wiring
point.
Air Conditioning Units
Supplying and fixing of air conditioning units
to Manager's Office area, and Grade 1
Staff rooms…etc
Inspection & Testing
Testing the installation & rectify any defect &
submit a certificate by a chartered Electrical
Engineer.
Drawings
Provide three sets of "As Build Drawings"
(A3 size) to cover all the systems under
electrical works binded as a book.
4
3
1
1
1
Nr
Nr
P.
Sum
item
item
750,000.00
750,000.00
TOTAL CARRIED TO COLLECTION ON PAGE S 07 - 122
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 118
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.N.1
2.N.2
2.N.3
2.N.4
2.N.5
N- PAINTING
Refer Pricing Preambles
External Painting
Plinth painting ; Prepare and apply two
coats of approved colour C.I.C / Nippon
weather shield paint range or equivalent to
plinth including preparing surface of old work
to receive paint as per Specification and
Engineers approval
Painting to old work : Preparing the
surface of old painting work of External faces
of walls, scraped to original plaster, patching
up cracks and defects with Acrylic wall putty,
sand papering and preparation of surface
for application of paint. Prepared surface to
be Painted with two coats of approved colour
(C.I.C / Nippon weather shield paint range or
equivalent ) weather shied paint.
On brick walls ,columns , sides and soffit of
weather shades & mouldings
From ground floor level to lower roof level
From ground floor level to upper roof level
Isolated columns
Between Ground floor and First floor
Sides and Soffits of Suspended Slab &
Beam
In first floor slab
Total Carried Forward
90.00
125.00
210.00
15.00
15.00
m2
m2
m2
m2
m2
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 119
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.N.6
2.N.7
2.N.8
2.N.9
2.N.10
2.N.11
2.N.12
Brought forward
Painting to New plaster: Prepare and apply
one coat of wall primer and two coats of
approved colour C.I.C / Nippon weather
shield paint range or equivalent including
preparing surface of of plaster to receive
paint (paint approved by engineer)
From ground floor level to lower roof level
From ground floor level to upper roof level
Isolated columns
Between Ground floor and First floor
Sides and Soffits of Suspended Slab &
Beam
In Linking Corridor
Internal Paint
Painting to old work : Preparing the
surface of old painting work of Internal faces
of walls, scraped to original plaster, patching
up cracks and defects with Acrylic wall putty,
sand papering and preparation of surface
for application of paint. Prepared surface to
be Painted with two coats of approved colour
(C.I.C / Nippon paint range or equivalent )
interior emulsion paint.
On brick walls ,columns & mouldings
For Staff accommodation, Laundry, Store &
Dormitory area
For Kitchen , Entrance lobby & Restaurant
Isolated columns & Beams
At First Floor
Total Carried Forward
260.00
250.00
25.00
200.00
400.00
305.00
150.00
m2
m2
m2
m2
m2
m2
m2
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 120
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.N.13
2.N.14
2.N.15
2.N.16
2.N.17
2.N.18
Brought forward
Sides and Soffits of Suspended Slab &
Beam
In first floor slab
Painting to New plaster: Prepare and apply
one coat of wall primer and two coats of
approved colour C.I.C / Nippon Emulsion
paint range or equivalent including preparing
surface of of plaster to receive paint (paint
approved by engineer)
On brick walls ,columns & mouldings
For Staff accommodation, Laundry, Store &
Dormitory area
For Kitchen , Entrance lobby & Restaurant
area
Isolated columns & Beams
Between Ground floor and First floor
Sides and Soffits of Suspended Slab &
Beam
In first floor slab
Painting Steel Truss
Removing old paint from the Metal surface
of truss using cup brush and preparation of
surface for application of paint. Prepared
surface to be Painted with two coats of
anticorrosive paint and one coat of Enamel
paint as per Specification and Engineers
approval. (Approximate Span of Truss 9.3
m)
30.00
1050.00
355.00
150.00
295.00
0.00
m2
m2
m2
m2
m2
Item
Deleted
TOTAL CARRIED TO COLLECTION ON PAGE S 07 - -
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 121
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
2.Q.1
2.Q.2
Q - HIGH PRESSURE LAMINATED PARTITION & OTHER WORK
High pressure laminated compacted board
door (Besco or equivalent), consist of an
inward swinging door total height 2100 mm
inclusive of 125mm high adjustable stainless
steel hook door knob, thumb turn indicator
lock and set off gravity hinges partition would
be set into existing walls with powder coated
aluminium extrusion frame. All complete as
per drawings and Engineer's approval
and/or High pressure laminated panel 12mm
tk. Typical toilet partition with minimum two
stainless steel adjustable legs, 125mm in
height total partition height from floor set off
gravity hinges partition would be set into
existing walls with powder coated aluminium
extrusion frame. All complete as per detail
drawing and Engineer's approval and/or
Supplying and fixing High pressure
laminated panel 12mm thick urinal separator
would consist of one separating panel
600mm in height with brackets. Rate to
include for fixing urinal separator to wall with
necessary screws. All complete as per
drawing and Engineer's approval.
In Male and Female Toilet 25.00 m2
Repairing of the roof end of corridors where
the corridor connects at T junctions with
one side of corridor with timber framed roof
structure and other side corridor with RCC
slab roof structure. The repair works will
includes finishing the end of timber framed
roof in proper manner with necessary frame
work, barge boards, ceiling...etc and rate
shall include for all necessary cutting,
fabricating and finishing work with all related
materials and completing the item in
acceptable manner to Engineer's approval.
3.00 Item
TOTAL CARRIED TO COLLECTION ON PAGE S 07 - 122
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 122
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
BILL NO 2 - RENOVATION AND ALTERATION
COLLECTION
C - CONCRETE WORK Rs.
D - MASONRY WORK Rs.
E - WATER PROOFING Rs.
F - STRUCTURAL STEEL WORK Rs.
G- METAL WORK Rs.
H- CARPENTRY & JOINERY Rs.
J- ROOF AND ROOF PLUMBING Rs.
K - PLUMBING Rs.
L- WALL, CEILING AND FLOOR FINISHES Rs.
M- ELECTRICAL INSTALLATIONS Rs.
N- PAINTING Rs.
Q - HIGH PRESSURE LAMINATED PARTITION WORK Rs.
TOTAL CARRIED TO SUMMARY ON PAGE S 07 - 140 Rs.
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 123
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
BILL NO 3 - EXTERNAL WORK
m
m
All External work to be executed
according to the available drawings and
as per Engineer's approval.
Q- EXTERNAL DRAINAGE
3.Q.1 RCC drain with cover slab : Storm water
Drain 300 mm wide and 250 mm starting
depth (or more as per site conditions)
internally built to slope in RCC concrete
Grade C20 (1:2:4) in 100 mm thick base
and 75mm thick side walls, complete with
12mm thick cement and sand 1:3
rendering, finished smooth with neat
cement floating to all exposed surfaces
and covered with 450 x 600 mm in size
and 100 thick perforated RCC cover slabs.
Rate to include for necessary site clearing,
excavation, backfilling, Reinforcement
(R6@150mm c/c & b/w), Formwork & all
necessary related work....etc and
completing the item as per the Engineers' approval.
100.00
3.Q.2 RCC drain only : Strom water drain
450mm internally wide and 250mm
starting depth (or more as per site
conditions) internally built to slope in
cement concrete 1:2:4 ( 20mm ) in 100
mm thick base and 100mm thick side
walls, complete with 12mm thick cement
and sand 1:3 rendering, finished smooth
with neat cement floating to all exposed
surfaces and covered with steel grating.
Rate to include for necessary r/f
(R6@150mm c/c & b/w), excavation and
expansion joints around the building and
connected to road drain.(steel grating
measured separately)
40.00
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 124
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
m
m
m3
3.Q.3 Supplying and fixing of steel fabricated
grating cover for Drainage; approx. with
(internally) - 450 mm , consisting of 40 mm
wide & 5mm thick equal angle iron welded
to make a frame, 40mm wide & 5 mm thick
flat iron welded to frame vertically in
25mm C/C spacings. Additionally, 12 mm
Dia. Steel bar to be welded horizontally at
each flat iron member which goes through
each flat iron member in centre(Pass
through) & it will be welded to frame at
both ends & as specified by Engineer and
work to be completed as per drawing,
specification and Engineers approval.
Rate shall include for all related matters,
painting with one coat of anticorrosive
paint and two coat of enamel paint etc...
40 -
3.Q.4 110mm dia. Soil pipe between all type of
manholes and pipes extended from
manhole up to the septic tank and
soakage pit laid to necessary falls with
average invert depth not exceeding
900mm including excavation and back
filling , bedding on a layer of cement
concrete 1:4:8(38mm) 100mm thick and
100mm wide on each side of the pipe and
subsequently encasing with the same
concrete after inspection of the pipe
203.00
Grease trap (Quantity for 2 No)
Drawing No :- 2016-TP-WSS03
Excavation & Earth work
3.Q.5 Excavation for grease trap pit,
commencing from existing ground level,
not exceeding 1.0 M deep in any material
except rock requiring blasting, backfilling
and disposal of surplus earth as directed.
2.00
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 125
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
3.Q.6 Excavation for grease trap pit,
commencing from existing ground level,
exceeding 1.0 M but not exceeding 2.0
M deep in any material except rock
requiring blasting, backfilling and
disposal of surplus earth as directed. 0.40
m3
Earth work supports
3.Q.7 Earthwork supports, (Planking &
Strutting) total depth of excavation not
exceeding 2.0m and distance between
vertical sides (opposing faces) not
exceeding 2.0m, (Payment will be made
only for actually executed Quantities on
the order of the Engineer) 3.00
m2
Dewatering
3.Q.8 Allow for dewatering, in the manner
approved by the engineer to keep all
excavation dry until all works in
substructure are completed (payment will
be made only if actually executed on the Pro.
order of the engineer ) 1 Sum 15,000.00 15,000.00
Concrete work
Lean Concrete
3.Q.9 75mm thick lean concrete ' C - 15 ' in the
under base slab
2.00 m2
Reinforced Concrete
Reinforced cement concrete Grade ' C -
20 ' in the following
3.Q.10 In 150mm thick base slab
0.30 m3
3.Q.11 In 125mm thick wall 1.20 m3
3.Q.12 In 75mm thick wall 0.18 m3
3.Q.13 In 50mm thick wall 0.02 m3
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 126
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
Formwork
Note :Refer pricing preambles
Formwork is measured as the net contact
surface measurement between concrete
and formwork From work for columns and
beams is given as a girth measurement.
Refer section 5.2 in specification for full
description of materials and workmen
ship. Formwork shall provide a finish to
concrete surface to receive plaster as per
section 5.4.8.11 in Specification.
Formwork as described to
3.Q.14 Vertical sides of wall 34.00 m2
Reinforcements
Refer pricing Preambles
Tor Steel Rod Reinforcement
(fy=460N/mm2)
3.Q.15
10mm dia. in wall & base
0.10
MT
Mild Steel Rod Reinforcement
(fy=250N/mm2)
3.Q.16 6mm dia. In wall 12.00 Kg
Accessories
3.Q.17 Supply and fixing 10mm thick chequered
plate cover in two pieces with lifting
handles
2
Nr
3.Q.18 Supply and fixing 110mm dia. PVC pipe.
2 m
3.Q.19 Supply and fixing 63mm dia. PVC vent
pipe.
4
Nr
3.Q.20 Supply and fixing 110mm dia. PVC equal
tee
4
Nr
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 127
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
Manhole type A- 475 x 625mm
internally
RCC Manhole type A, Internal
dimensions 475 x 625 mm (Depth up to
450mm) wall thickness 100 mm & base
Slab thickness 150 mm.Rate to include
100mm thick cover slab cover Slab with
lifting handle, Inlet and outlet connections
as per Engineer's' approval.
3.Q.21
Waste water manhole
3
Nr
3.Q.22 Sewerage Manhole 1 Nr
RCC Manhole type A, Internal
dimensions 475 x 625 mm (Depth is
greater than 450mm & up to 600mm)
wall thickness 100 mm & base Slab
thickness 150 mm.Rate to include
100mm thick cover slab cover Slab with
lifting handle, Inlet and outlet connections
as per Engineer's' approval.
3.Q.23
Waste water manhole
5
Nr
3.Q.24 Sewerage Manhole 2 Nr
RCC Manhole type A, Internal
dimensions 475 x 625 mm (Depth is
greater than 600mm & up to 750mm)
wall thickness 100 mm & base Slab
thickness 150 mm.Rate to include
100mm thick cover slab cover Slab with
lifting handle, Inlet and outlet connections
as per Engineer's' approval.
3.Q.25
Waste water manhole
3
Nr
3.Q.26 Sewerage Manhole 1 Nr
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 128
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
RCC Manhole type A, Internal
dimensions 475 x 625 mm (Depth is
greater than 750mm & up to 1000mm)
wall thickness 100 mm & base Slab
thickness 150 mm.Rate to include
100mm thick cover slab cover Slab with
lifting handle, Inlet and outlet connections
as per Engineer's' approval.
3.Q.27 Waste water manhole 1 Nr
3.Q.28 Sewerage Manhole 3 Nr
Manhole type B- 475 x 750mm
internally
RCC Manhole type B, Internal
dimensions 475 x 750 mm (Depth up to
450mm) wall thickness 100 mm & base
Slab thickness 150 mm.Rate to include
100mm thick cover slab cover Slab with
lifting handle, Inlet and outlet connections
as per Engineer's' approval.
3.Q.29
Sewerage Manhole
1
Nr
RCC Manhole type B, Internal
dimensions 475 x 750 mm (Depth is
greater than 450mm & up to 600mm)
wall thickness 100 mm & base Slab
thickness 150 mm.Rate to include
100mm thick cover slab cover Slab with
lifting handle, Inlet and outlet connections
as per Engineer's' approval.
3.Q.30 Waste water manhole 1 Nr
3.Q.31 Sewerage Manhole 1 Nr RCC Manhole type B, Internal
dimensions 475 x 750 mm (Depth is
greater than 600mm & up to 750mm)
wall thickness 100 mm & base Slab
thickness 150 mm.Rate to include
100mm thick cover slab cover Slab with
lifting handle, Inlet and outlet connections
as per Engineer's' approval.
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 129
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward Nr
Nr
Nr
Nr
Nr
Nr
Nr.
3.Q.32 Sewerage Manhole 1 RCC Manhole type B, Internal
dimensions 475 x 750 mm (Depth is
greater than 750mm & up to 1000mm)
wall thickness 100 mm & base Slab
thickness 150 mm.Rate to include
100mm thick cover slab cover Slab with
lifting handle, Inlet and outlet connections
as per Engineer's' approval.
3.Q.33
Waste water manhole
2
3.Q.34 Sewerage Manhole 1
Manhole type C- 475 x 1050mm
internally
RCC Manhole type C, Internal
dimensions 475 x 1050 mm (Depth up
to 450mm) wall thickness 100 mm &
base Slab thickness 150 mm.Rate to
incliude 100mm thick cover slab cover
Slab with lifting handle, Inlet and outlet
connections as per Engineer's' approval.
3.Q.35 Waste water manhole 1
RCC Manhole type C, Internal
dimensions 475 x 1050 mm (Depth is
greater than 750mm & up to 1000mm)
wall thickness 100 mm & base Slab
thickness 150 mm.Rate to include
100mm thick cover slab cover Slab with
lifting handle, Inlet and outlet connections
as per Engineer's' approval.
3.Q.36 Waste water manhole 2
3.Q.37 Sewerage Manhole 1
3.Q.38 Water collecting pot - 600 x 600mm as
per drawing with invert depth not
exceeding 900mm including 100mm
square G.I. mesh fixed to drain under the
concrete pot and 25 x 75mm rough
plaster band, all complete to approval. 26
TOTAL CARRIED TO COLLECTION ON PAGE S 07 - 137
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 130
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
R- WASTE WATER TREATMENT UNIT
AND STORM WATER DISPOSAL
3.R.1 Supply and installation of Johkasou
technology(Japanese) waste water
treatment Tank as per approved
manufacturer's Standards and Engineers
approval. The work includes Excavation &
Temporary work, Dewatering, temporary
support, Levelling the base with sand, 150
mm Base concrete, Filling Water,
Backfilling, Piping and Electrical Work
(Prime cost for 5000 lIter capacity is Rs.
1,700,000.00 excluding VAT)
1.00 Nr.
3.R.2 Sump and pump room construction for
Pumping out the treated water from tank
including earth work, concrete work,
accessories, pump, ground sump(1000L)
& fittings and all necessary works.
1.00 Item
Storm water disposal
3.R.3 110mm dia. PVC pipe type PNT7 laid to
necessary falls with average invert depth
not exceeding 900mm including
excavation and back filling, bedding on a
layer of cement concrete 1:3:6 (40mm)
100mm thick and 110mm wide on each
side of the pipe and subsequently
encasing with the same concrete after
inspection of the pipe.
30.00
m
3.R.4 160 mm dia. PVC pipe type PNT 7 from
drainage extended up to the discharge
point laid to necessary falls with average
invert depth not exceeding 900mm
including excavation and back filling,
bedding on a layer of cement concrete
1:4:8(38mm) 100mm thick and 110mm
wide on each side of the pipe and
subsequently encasing with the same
concrete after inspection of the pipe.
20.00 m
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 131
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
RCC storm Water catch Pit
3.R.5 Construction of RCC Storm Water catch
pit; Internal Size 900 x 900mm (depth not
exceeding 1000 mm) , Consisting of
100 mm thick Wall and 150 mm thick Base
in Grade C-20(1:2:4) concrete and
rendered with 1:2 cement sand rendering
. Rate shall include for all necessary
related work such as Removal of existing
interlock paving, Excavation, Form work,
Reinforcement and Expansion joint. Etc
and all work to be done as per
specification and Engineer's approval. (
Mild steel grating Measured separately )
2.00 Nr
3.R.6 Supplying and fixing of steel fabricated
grating cover for catch pit ; Size - 900 x
900 mm internally, consisting of 40 mm
wide & 6mm thick Flat iron welded to make
a Square frame, 40mm wide & 5 mm thick
flat iron welded with frame horizontally to
one side of flat iron frame at 150 mm C/C
spacing. Additionally, 16 mm Dia Tor Steel
bar welded horizontally to other side of flat
iron frame at 150mm C/C spacing as
specified by Engineer and work to be
completed as per drawing, specification
and Engineers approval. Rate shall
include for all related matters, painting
with one coat of anticorrosive paint and
two coat of
2.00
Nr
TOTAL CARRIED TO COLLECTION ON PAGE S 07 - 137
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 132
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
S - GENERATOR ROOM
3.S.1 Allow for clearing site of all growth
roots and cutting top soil up to a depth
of 150mm extended up to 3.0m beyond
outer walls of proposed Sump & Pump
house pit and carting away the waste
material from the site where directed.
(Approx. 125.00m2 ) 1.00 Item
Excavation commencing from existing
ground level, not exceeding 1.00 m deep
in any materials except rock requiring
blasting, part return fill in ram and surplus
disposed as directed. Rate shall include
for compacting after excavation (well
rammed and consolidated).
3.S.2 For Footing
7.50 m3
Concrete Work
Mass concrete Grade' C - 25 ' in the
following ;
3.S.3 For mass concrete footing ( Depth - 1800
mm)
44.00
m3
3.S.4 Supply & Laying 1000 gauge Polythene
membrane.
37.00
m2
Reinforced cement concrete Grade 'C -
25 ' in the following
3.S.5 In staircase footing 0.13 m3
3.S.6 In staircase shaft 0.14 m3
3.S.7 In steps and waist of staircase 0.83 m3
Formwork
Form work as described to ;
3.S.8 Vertical sides of mass concrete footing 28.50 m2
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 133
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
3.S.9 Vertical sides of staircase footings
<300mm high 4.00 m
3.S.10 Vertical sides of staircase shaft 1.62 m2
3.S.11 Sides of steps and waist of staircase 1.25 m2
3.S.12 Sloping soffit of staircase 3.75 m2
Reinforcement
Tor steel rod reinforcement including
bends, hooks, tying wire, distance blocks
and ordinary spacers ( Inevitable laps and
chairs included in BOQ Quantities) fy =
460 N/mm2
10mm dia.
3.S.13 In mass concrete footing 50.00 Kg
3.S.14 In staircase footing and shaft 23.00 Kg
3.S.15 In waist and landing of staircase 132.00 Kg
Mild Steel Rod Reinforcement
(fy=250N/mm2)
3.S.16 6mm dia as stirrups 28.00 Kg
STRUCTURAL STEEL WORK
3.S.17 Supplying and Fixing of Structural Steel
Portal Frame Consisting of
180x94x24.13kg/m Section as column
and rafter including necessary 10 mm
thick mild steel End plates, necessary
eaves hauch and apex haunch cut from
180x94x24.13 "I" sections and ,
necessary Nut & bolt. Approx. weight of
each portal frame - 0.42 MT ).Work to be
completed as per Specification and
Engineers Approval 3.00 Nr
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 134
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
3.S.18 Supplying and Fixing of Structural Steel
eaves beam fixed to portal frame a eaves
Consisting of 126x74x14.223kg/m
Section including necessary 10 mm thick
mild steel End plates, necessary eaves
and necessary Nut & bolt. Approx.
weight of each beam - 0.03 MT ) .Work
to be completed as per Specification and
Engineers Approval
6.00 Nr
3.S.19 Supplying & Fixing High tensile
Galvanized Steel 100 x 50 x 12mm Lip
channel purlins, having the member
thickness of 2.0mm (Tensile strength
450 N/mm2) standards complying with
JISG 3302. Each Purlins connected with
10mm M.S plate welded to Rafter beam
fixed with 10mm dia. Nut and Bolts. Rate
shall include for painting with two coat of
anticorrosive paint and one coat of
enamel paint M.S plate.
88 m
3.S.20 Supplying and Fixing of 10mm steel rods
with turn buckles, welded with gusset
plate and fixed between portal frame
and all work to be completed as per
Drawing, specification and Engineer's
Approval. 28.00 kg
Metal work
3.S.21 Fabricating and fixing of MS grills with
25mm x 6mm thick flat iron frame and
6mm dia.MS. rods welded to diamond
shape 75mm centres both ways.
43.00 m2
3.S.22 fabricating and fixing removable opening
type with 25mm x 6mm thick flat iron
frame and 6mm dia M.S rods fixed to
frame, all as per drawing and Engineer's
approval. Rate shall include for all related
maters and Nut & bolts 28.30
m2
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 135
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
3.S.23 Supplying and welding 25mm x 25mm x
6mm MS angle iron horizontal bracing to
existing GI pipe posts. Rate to include for
painting one coat of anticorrosive paint
and two coats of enamel paint. 45.00 m
3.S.24 Fabricating and fixing of 900 mm high,
heavy duty GI. Pipe Guard railing,
consisting of 40 mm dia.Vertical pipe
(Balusters) raised at 600 mm intervals &
firmly fixed to Concrete floor at bottom &
welded to 50 mm dia.heavy duty
Horizontal GI. pipe top rail. one rows of
25mm dia. heavy duty GI pipe bracings
welded to Vertical pipes horizontally at
bottom. Rate shall include for painting
with two coat of anticorrosive paint and
one coat of enamel paint 6.00 m
Roof covering & plumbing
3.S.25 0.47 mm thick Zink Aluminium colour
bond tile profile roofing sheets laid on
prepared frame work, fixed as per
manufacture's specification. Roof frame
work measures separately.
97.00 m2
3.S.26 12mm thick heat insulation sheet (
Bubble Bubble foil reflective insulation
sheet) laying on 75 x75 mm GI mesh on
existing steel purling and fixing with
binding as per manufacturer's
specifications
97.00
m2
3.S.27 Zink Aluminium sheet ridge covering
fixed to roofing sheets with necessary
hooks , bolts nuts, etc.. all complete as
per Drawing and Engineers approval. 11.00 m
Total Carried Forward
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 136
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward
3.S.28 Supplying and fixing 300 mm High Zinc
Aluminium high tensile valance board and
barge board with brackets (with GI box bar
frame work) fixed complete as per
manufacture's specification. Rate shall
include for frame painting with two coats
of anticorrosive paints and complete the
work as specified by the Engineer.
41.50
m
3.S.29 Supplying and fixing 0.47 mm thick zinc /
Aluminium high tensile (Grade 550 )
457mm girth eaves Box gutter with
brackets and specials fixed complete as
per manufacture's specification.
21.50
m
3.S.30 Supplying and fixing 0.47 mm thick (
457mm girth) zinc / Aluminium high tensile
down pipe with brackets fixed complete as
per manufacture's
24.00
m
Finishes
Rendering, 12mm thick in cement and
sand (1:3) , and finished with floating coat,
using neat Cement and finished smooth.
3.S.31 For floor & plinth of foundation 55.00 m2
3.S.32 For stair case steps and waist 10.00 m2
TOTAL CARRIED TO COLLECTION ON PAGE S 07 - 137
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 137
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
BILL NO 3 - EXTERNAL WORKS
COLLECTION
Q- EXTERNAL DRAINAGE Rs.
R- WASTE WATER TREATMENT UNIT
AND STORM WATER DISPOSAL
Rs.
S - GENERATOR ROOM Rs.
TOTAL CARRIED TO SUMMARY ON PAGE S 07 - 140
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07-138
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
4.T.1
BILL NO 4 - MISCELLANEOUS WORK
LP Gas Line Installation
Supplying, Installation and Commissioning
of LP gas line for kitchen from LP gas
cylinder storage room at ground floor. Rate
to include all necessary items related to work
including safety measures such as gas leak
detectors, auto shut off valves, fire
extinguishers...etc. Work shall be completed
in relevant standards (CIDA Fire
Regulations) and work shall be completed to
working order and to the Engineer's
approval.
1.00
PS
400,000.00
TOTAL CARRIED TO COLLECTION ON PAGE S 07 - 139 400,000.00
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07-139
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
BILL NO 4 - MISCELLANEOUS WORK
COLLECTION
S - MISCELLANEOUS WORK
Rs.
400,000.00
TOTAL CARRIED TO SUMMARY ON PAGE S 07 - 140 400,000.00
RENOVATION AND ALTERATION TO EXISTING MAIN BUILDING SURROUNDEING AT NATIONAL HOLIDAY RESORT AT ANURADHAPURA.
S07 - 140
GRAND SUMMARY
ITEM AMOUNT
PRELIMINARIES (S07-25) Rs:
BILL NO : 1 - DEMOLITION AND OTHER (S07-38) Rs:
BILL NO : 2 - RENOVATION & ALTERATION (S07-122) Rs:
BILL NO : 3 - EXTERNAL WORKS (S07-137) Rs:
BILL NO : 4 - MISCELLANEOUS WORK (S07-139) Rs:
SUB TOTAL ( 1 )
Rs:
Less
Provisional Sums
Rs:
11,035,000.00
SUB TOTAL ( 2 ) Rs:
Less Discount --------- (% )( if any) Rs:
Add
Provisional Sums
Rs:
11,035,000.00
GRAND TOTAL Rs:
Bid Sum carried over to Form of Bid on Page No. S4 -02
VAT Registration Number ………………………
……………………………………………………………………………………………….
Signature of Bidder
Date :……………………………………………….
Witness : (1) : ………………………………………………….
Address : …………………………………………………………..
Witness : (2) : ………………………………………………….