121

EMC AT ANNUR, COIMBATORE FINAL DPRenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/13_Nov... · One of the important objectives of the NPE is to achieve a turnover of about

Embed Size (px)

Citation preview

 

 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 2 

   

 

 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 3 

   

CONTENTS LIST OF ANNEXURES ...................................................................................................................... 4

EXECUTIVE SUMMARY .................................................................................................................. 5

CHAPTER 1 .................................................................................................................................... 8

CONTEXT & BACKGROUND ...........................................................................................................

CHAPTER 2 .................................................................................................................................. 42

PROJECT OBJECTIVES ....................................................................................................................

CHAPTER 3 .................................................................................................................................. 45

TARGET BENEFICIARIES .................................................................................................................

CHAPTER 4 .................................................................................................................................. 48

PROJECT COMPONENTS ................................................................................................................

CHAPTER 5 .................................................................................................................................. 60

SUPPORT INFRASTRUCTURE .........................................................................................................

CHAPTER 6 .................................................................................................................................. 64

ENVIRONMENTAL IMPACT ASSESSMENT .....................................................................................

CHAPTER 7 .................................................................................................................................. 75

MARKETING STRATEGY .................................................................................................................

CHAPTER 8 .................................................................................................................................. 80

MANAGEMENT ARRANGEMENTS .................................................................................................

CHAPTER9 ................................................................................................................................... 93

MEANS OF FINANCE & PROJECT BUDGET ....................................................................................

CHAPTER 10 .............................................................................................................................. 102

TIME FRAME .................................................................................................................................

CHAPTER 11 .............................................................................................................................. 104

RISK ANAYSIS .................................................................................................................................

CHAPTER 12 .............................................................................................................................. 107

FINANCIAL & ECONOMIC ANALYSIS ..............................................................................................

CHAPTER 13 .............................................................................................................................. 115

SUSTAINABILITY ............................................................................................................................

CHAPTER 14 .............................................................................................................................. 119

CORPORATE SOCIAL RESPONSIBILITIES ........................................................................................

 

 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 4 

   

 

LIST OF ANNEXURES 

 

1  Annexure 1  Architectural Design Report 

2  Annexure 2  Electrical Design Report 

3  Annexure 3  Plumbing Design Report 

4  Annexure 4  MoUAIPL &GoTN 

5  Annexure 5 (a) & 5 (b) 

5(a) – Supply of Water: Copy of Communication from NTADL 

5(b) – Bore well – Copy of Communication from the President, KuppanurPanchayat 

6  Annexure 6  Copy of Application  to TNEB 

7  Annexure 7 Copy of Acknowledgement – Application for Environmental Clearance 

8  Annexure 8  Detailed cost estimate for project 

9  Annexure 9  Details of financial statement 

    

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 5 

   

EXECUTIVE SUMMARY   Proposed project   Greenfield Electronic Manufacturing Cluster (EMC) 

   

Project location  Annurtaluk  in  Coimbatore,  Tamil  Nadu.    It  is  a  part  of  the  1500  acre industrial park being developed  for which a MoU has already been  signed between  the Government  of  Tamil Nadu  (GoTN)  and  ADD  Industrial  Park (Tamil Nadu) Limited (AIPL) the Chief Promoter of the proposed EMC.   From Annur  town,  the  location  is  about  9  Kms  from  NH  209  connecting Coimbatore and Mysore and nearly 38 Kms from Coimbatore city. 

   

Scheme and nature of activities involved in the project 

To make India a global player in the field of electronics manufacturing and to offset disabilities  faced by  industries  for  reliable  infrastructure, Electronics Manufacturing  Clusters  (EMC)  Scheme  was  notified  by  the  Ministry  of Communications  and  IT,  Government  of  India  (GoI)  in  October,  2012  to provide  support  for  creation  of  world‐class  infrastructure  for  attracting investments  in the sector.   The EMCs scheme provides grant assistance  for setting  up  EMCs  across  the  country.    The  financial  assistance  under  the Scheme is in the form of grant‐in‐aid for creating infrastructure and logistics. 

As  per  the  Scheme,  a  proposal  for  development  and  promotion  of  a Greenfield EMC on 157.6 Acres of land in Annurtaluk has been submitted by M/s.  ADD‐ELCINA  Electronics  Park  Private  Limited  to  the  Department  of Electronics & IT (DeitY), Ministry of Communications and IT, GoI.  

The proposed EMC project comprises of 163 plots of various sizes designed for  sale as  independent or  combined units occupying 95+  acres.    It would endeavour to bring the entire gamut of electronic manufacturing operations under one umbrella and facilitate all stages of the value chain of electronic manufacturing.  Each plot would be connected by a road network along with all the common services  like electric connection, sewer connection, central STP, treated water supply & storm water drainage, which can be utilized by the  units within  EMC.  Further,  common  support  facilities  like  tool  room, CAD/CAM, testing, certification, R&D, administration,  training and business centres  and  support  services  viz.  employee  hostel  and  mess,  hospital, recreation  facility, crèche,  local shopping centre etc.   The EMC would be a secured gated campus.  

   

Details of special purpose vehicle (SPV) 

Name of the SPV: ADD‐ELCINA Electronics Park Private Limited, Incorporated in June 2015 with CIN U31401KA2015PTC080857 Promoters:  ADD Industrial Park (Tamil Nadu)  Limited (AIPL) – Chief Promoter Om Metals Infraprojects Limited (OMIL) Adhunik Power Transmission Limited (APTL) Electronics Industry Association of India (ELCINA) 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 6 

   

Master Plan  The master planning is aimed at optimising the layout of the industrial plots with the following pattern of utilization: Processing  Area  (industrial  plots  &  common  /  support  infrastructure)  – 86.5% Non‐processing area (common amenities) – 13.5% 

   

Processing Area  Processing area comprises of industrial plots and support infrastructure like roads,  storm  water  drains,  water  treatment  plants,  sewage  treatment plants,  electrical  substations,  warehouse,  buildings  for  administration, training,  manufacture  support  and  gate  house  etc..    The  total  area  of 5,51,802Sqm. (136.6 Acres) 

Non‐processing area  Non‐processing  area  consists  of  other  common  amenities, which  includes employee  hostels,  medical  centre,  clubhouse,  worker  welfare  and  green space with a total area of 86,050 Sqm. (21 Acres) 

   

Project Cost  Sl. No.  Name of the component  Amount (in INR Lakhs) 

1  Processing area (% area) 

a)  Basic development (36%) 6021

b)  Essential services (38%)  6282

c)  Support services (6%)  1021

d)  Manufacturing services (3%)  505

e)  Government regulatory services (3.5%)  269

  Sub‐total (86.50%)  14098

2  Non‐processing area   

a)  Welfare Services (3.4%)  2214

b)  Green area (10.1%) 322

  Sub‐total (13.50%)  2536

  Total EPC cost of the project  16634

3  Land  1215

4  Administration expenses 493

5  CSR  83

6  Interest During Construction (IDC)  1131

 

  Total Project cost including IDC 19594

   

Grant Calculation Grant Calculation 

Processing / Non‐processing 

Grant % 

Grant Amount (in INR Lakhs) 

Processing Costs   1,409,761,108  50%           7048.80Non Processing Costs   253,625,992 

20%             507.25

Adm. Costs Allowed for Grant     

3%             226.68

TOTAL GRANT                 7782.74

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 7 

   

 

   

Means of finance  Source  Amount (in INR Lakhs) 

  Grant  7783

  Debt  8268

  Equity (By Chief Promoter) 1736

  Equity (By Unit holders)  1807

  Total  19601

   

Employment generation  Once fully established and populated, the Cluster expects to employ 16,000+ workers directly and another 32,000  indirectly. This  is basedon the average capital investment of Rs. 14Crores per acre which adds up to about Rs. 1,300 Crores and an output of Rs.3,900Crores at a capital output ratio of 1:3. 

 

Sustainability  The proposed EMC would be operational  from year 2 after  receipt of  finalapproval from DeitY.   Sale of the plotsin the EMC  is  likely to take place  in a phased and gradual manner. During the first year of construction 20% of the plots are expected to be sold and another 35%  in the second year followed by 45% in the third year.   During the operation and maintenance, a steady flow of revenue is expected from the maintenance charges collected from the unit holders, charges from use  of  tool  room,  testing,  hostels,  clubhouse,  warehouse,  for  skill development services, communication service and other such income, which will  sustain  the  EMC.For  the  infrastructure  replenishment,  a  fee  will  be collected  from  the  units  of  EMC  once  in  3  years  for  upgrading  the infrastructure  of  the  EMC  which  generates  adequate  cumulative  cash reserves for the EMC.   The NPV (as per the financial analysis) of the project is Rs. 694 Lakhs, IRR of the project is @ 14.31 % and the repayment period is 7 years and hence the project is economically viable. 

 

   

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 8 

   

 

CHAPTER 1  

CONTEXT & BACKGROUND  1.1 Introduction: 

Electronics industry is one of the fastest growing manufacturing industries in the world. The demand in  the  Indian market  for Financial Year 2014‐15 stood at USD 90+ Billion and  is expected  to  reach USD400 Billion by year 2020.   At the current rate of growth domestic production can cater to only USD 100 Billion by year 2020 creating a demand supply gap of nearly USD 300 Billion which would be higher than oil imports and not sustainable.  To correct this  the Union Cabinet approved the National Policy on Electronics (NPE) in 2012 with a vision of transforming India into a global hub for electronic design and system manufacturing (ESDM)  to meet both local and global demand.  One of the important objectives of the NPE is to achieve a turnover of about USD 400 Billion by 2020 involving  investment of approximately USD 100 Billion and  increase employment  to 28 million by 2020. This also  includes achieving a  turnover of USD 55 Billion by  the  chip design and embedded software  industry and USD 80 Billion of exports  in the sector.   A major and  important target of the NPE is to set up 200 Electronic Manufacturing Clusters which would enable and drive the growth of Electronics manufacturing.   As  part  of  the  National  Policy  on  Electronics  (NPE)  for  promotion  of  Electronic  Manufacturing Clusters  (EMCs),  an  EMC  scheme  has  been  notified  by  the  government  vide  notification  no.  252 dated 22‐10‐2012 in part 1, Section 1 of the Gazette of India (Extraordinary).   The scheme provides incentives including financial assistance in terms of a grant in aid to special purposes vehicles (SPVs) created for setting up EMCs.  In  line with  the objectives of  the NPE,  to promote electronics manufacturing, ADD  Industrial Park (TN)  Ltd  (AIPL)  along with Om Metals  Infraprojects  Limited  (OMIL),  Adhunik  Power  Transmission Limited (APTL) and Electronic Industries Association of India (ELCINA) have formed an SPV to submit this final proposal for development and promotion of a Greenfield EMC on 157.6 acres of land near AnnurTaluk, Coimbatore District  in  the  state of Tamil Nadu.   This would be part of  the 1500 acre mega industrial park that is being set up by AIPL for which a memorandum of understanding (MoU) with Government of Tamil Nadu (GoTN) has been signed on the 5th of November 2012.  The detailed profiles  of Chief  Promoter  and  other  Promoters  of  the  SPV  are provided  later  in  the  Chapter on ‘Management Arrangements’. 

 

   

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 9 

   

1.2 Electronics industry – India  Electronics  is  now  a  key  input  in  all  aspects  of  human  life  and  all  sectors,  including  Telecom, IT/Computers,  Consumer  Appliances,  Automotive, Medical,  Lighting,  Energy,  Transportation  and more. Further, the share of electronics  in the  form of hardware and software  is rising by the day resulting  in  rapid growth of market  for electronics, as mentioned above. This  trend  is bound  to continue  and  gain  further momentum.  The  size  of  the  Electronics  Industry  in  comparison with other sectors is estimated as follows:  a) 4.40 times the size of Oil, Petrol and Minerals Industry b) 2.75 times the size of Chemicals and Plastics Industry  c) 2.45 times the size of Food, Beverages and Tobacco industry  d) 2.44 times the size of Transportation industry  e) 2.20 times the size of Electricity, Water and Gas industry  The birth of the Indian electronics industry can be traced to the sixties, when the Government took the  initiatives of manufacturing space and defence electronic products  for national  security. This was  followed  by  developments  in  consumer  electronics, mainly  the manufacturing  of  transistor radios, black and white TVs, calculators and other audio products. This was followed later in 1980s, with the manufacture of colour televisions, advent of computers and telecom products.  India, though still a relatively small player  in the world Electronics market,  is growing very quickly with steady growth of the Indian economy. This is supported by supportive demographic trend of a growing  and  large  middle  class  accompanied  by  rising  incomes  and  aspirations.  The  demand growth  is  led  by  telecom  products/infrastructure,  computer  &  IT  products,  auto  electronics, medical,  industrial  and  consumer  electronics.The  electronics  sector  attracted  foreign  direct investment  (FDI) worth Rs. 5,986.51  crore  (USD 1.08 Billion at 2013 Exchange  rate) during April 2000  to  June  2013,  according  to  the  data  released  by  the Department  of  Industrial  Policy  and Promotion  (DIPP), Government of  India. This FDI  is not adequate and  falls extremely short of the need  to  boost  domestic manufacturing  and  keep  pace with  demand. While  exports  from  India comprise  a  large  range of  electronic  components  and  products  for  the  following  segments,  the volumes are still quite low compared to competing countries:‐   a) Display Technologies  b) Entertainment Electronics c) Optical Storage Devises  d) Passive Components  e) Electromechanical Components  f) Telecom equipment g) Transmission & Signalling Equipment h) Semi‐Conductor designing  i) Electronic Manufacturing Services (EMS)  

   

EMC AT ANN

ADD‐ELCINA

 

1.3 Dome 

As deprojeproje20202020by imJapandemaachiewill cUSD 

 

 Anotadditelectadde

 Electrused railwavirus R&D wthreatthe ES

 

UR, COIMBATORE

A ELECTRONICS 

estic manufac

epicted belowected to growected  to rise 0. This  is base0. There is a hmports from cn and also Mand‐supply  geve this goal. cater to only 300 Billion m

ther  challengtionfocused  otronics produed and depen

ronic Hardwain  internal  says, civil aviat/ cyber‐attacwith access tot to its nationSDM sector. E

20

FY

Prod

E – FINAL DPR 

PARK PRIVATE L

cturing ‐ A st

w, in year 200w to USD 125from  the cured on domesthuge gap in tcountries leadMalaysia, Thaigap  and  the The current USD 104 Billi

making electro

ge  for  India on  last  mile ucts being medent on impo

are Manufactsecurity  and tion etc. and ck. This  is a do the IP and tnal security, bExcessive reli

 

45

Y09

duction Vs D

LIMITED

rategic issue

09, the dema5 billion by 20rrent USD 4 tic consumpthe demand ading in Electroland etc. Mancurrent  efforate of growton demand bonics the high

is  that  moassembly.  T

et by  importsorted inputs.

turing  is of videfense  as  can have sedefinite posstechnology. Tboth externaance on impo

Demand Ind

Prod

 

nd in the Ind014 and USD billion  to USDion growth aand supply wonics Manufanufacturing norts  of  the  Gth of manufaby 2020 and thest contribut

ost  of  the  dThus,  in  adds,  the manuf

ital  strategic well  as  key rious conseqibility  if one This situationl and internaorts is a threa

42

125

FY 14

ian Electronin USD Billions 

duction De

dian market st400 billion bD 15 billion bt a high CAGith about 70%acturing such needs to growGovernment cturing, it is lthere will be tor to imports

domestic  maition  to  almfacturing  that

importance civilian  domuence  in casedoes not ha makes the cl and highlighat to the econ

5

nic Market F

emand 

tood at USD by 2020. Furtby 2014 and R of 22% for % local demaas China, Taiww rapidly to cand  Industryikely that doa demand sus, even highe

anufacturing ost  70%  curt  is happenin

for  the  counains  such  ase of disruptiove  its own mountry suscehts the stratenomy and nat

104

FY 2

Y 2009‐FY 2

Page 

45 billion andther, exports USD 80 billiothe period 2

and being serwan, South Kcheck the groy  are  directiomestic produpply gap of nr than oil imp

is  of  low rrent  demanng  is  low on 

ntry as  it  is ws  telecom,  poon of servicesmanufacturingptible to a seegic importanional security

400

20

020

10 

d was were on by 2009–rviced Korea, owing on  to uction nearly ports. 

 

value d  for value 

widely ower, s or a g and erious nce of y. 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 11 

   

1.4 Overall industrysize & growth  Revised estimates of the Indian ESDM industry indicate that the market was $68.31 billion in 2012 and projected to grow between 2011 and 2015 at a Compound Annual Growth Rate (CAGR) of 9.88 percent.  The  corresponding  size  of  the market  by  2015 was  projected  to  be  $94.2  billion.  The following chart illustrates the total ESDM industry market growth. (Source: DeitY) 

 

  

The total market  (TM)  for  Indian ESDM  (comprising of electronic products, electronic components, semiconductor design and electronic manufacturing services) was estimated to be $44.81 billion  in 2012, representing a growth of 7 percent over the previous year. The TM  is expected to grow at a CAGR of 11.5 percent and reach revenues of $64.85 billion by 2015. Total domestic market (TDM) for 2012 was estimated to be $17.07 billion, representing a growth of 11 percent over 2010. Growing a CAGR  of  10.4  percent,  the  TDM  is  expected  to  scale  to  $22.66  billion  by  2015.  The  chart  below represents total market(TM) and total domestic market (TDM) for the Indian electronics market.  

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 12 

   

   1.5 Industry segments market size & growth 

 The  Indian  Electronics  industry  is  divided  into  six  sub  segments,  namely  Consumer  Electronics, Industrial Electronics, Computer Hardware, Communication and Broadcasting, Strategic Electronics and Electronic Components and their market growth rates from 2008 to 2013 are as below:‐  

 a) Consumer Electronics: Consumer electronics  include electronic equipment meant for everyday 

use  and  are  most  often  used  in  entertainment,  communications,  and  to  enhance  office productivity.  Some  of  the major  products  under  consumer  electronics  include MP3  players, audio equipment, televisions, calculators, GPS automated navigation systems, digital cameras and  playback  and  recording  of  video media  such  as DVDs,  VHSs  or  camcorders.  The  Indian Consumer Electronics  industry has experienced  rapid changes over  the  last  few years. These changes have been resultant of a booming Indian economy growing at 8% and above till end of last decade,  the changing  lifestyles, higher disposable  incomes and greater affordability have been  important  factors  in  fuelling  this  growth.  The  consumer  preference  has  also  shifted towards products and devices that come with smart technology,  innovative designs, and user friendly  and  are  also  aesthetically  designed.  This  increase  in  growth premium products, not only  in Metros but also  in  rural areas  is going  to provide  the  future growth  stimulus  for  the domestic  consumer  industry.  Figure  below  shows  the  production  growth  of  consumer electronics segment for the period 2008‐20013.  

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 13 

   

  

b) Industrial  Electronics:  The  industrial  electronics  segment  includes  critical  hardware technologies  and  systems  with  built‐in  software.  It  is  a  very  challenging  area  which  is multidisciplinary  in  nature  requiring  high  level  of  technical  skill  in  designing  systems  for applications  in  a  variety  of  industrial  sectors  of  the  economy.  Even  though  India  has  been having  significant  expertise  in  conceptualizing  such  systems  and  its  erection  and commissioning,  the  sector  is  very  largely  dependent  on  import  of  critical  hardware  and associated software. Large projects are implemented with total import of C&I (commercial and industrial) packages from abroad without any knowledge of its design. In most cases, this leads to  higher  initial  cost  and  a much  higher maintenance  cost  in  the  long  run.      The  domestic industrial  electronic  consists  of  process  control  equipment,  test  &  measuring  equipment, medical electronics, power electronics equipment,  industrial electronics and automation and analytical  instruments.  This  is  a mature  segment  but  the  incentives  announced  under  the National  Policy  on  Electronics  should  revive  this  sector.  Figure  below  shows  the  industrial electronics segment production growth for the period 2008‐2013.  

22,600 25,550 

29,000 32,000 

34,300 

41,200 

13.1%13.5%

10.3%7.2%

20.1%

2007‐08 2008‐09 2009‐10 2010‐11 2011‐12 2012‐13(E)

Consumer Electronics Production 2008‐2013in INR crores 

YoY Growth

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 14 

   

c) Computer Hardware:  The computer hardware market consists of the computers, storage, and other  devices  segments.  The  computers  segment  comprises:  desktops  and  laptops.  Storage segment  includes memory  sticks,  CD  packs,  hard  disks  and  other  data  storage  devices.  The other  devices  segment  include:  computer  peripherals,  PDAs,  organizers,  calculators  and satellite navigation systems.The growing  income as well as  levels and  increasing awareness of PC  as  an  Educational  device  seem  to have  impacted  the PC  sales over  the  years,  especially amongst  the  SECC  segment where  the  young  population  seem  to  be  driving  adoption.  The derived value of production for this segment for 2012‐13, is about Rs. 24,300 crores, as against Rs. 16,500 crore in 2011‐12, a growth of about 47%. Figure below shows the production growth of computer hardware segment for the period 2008‐2013.   

  

d) Communication &  Broadcasting  Equipment:  Communication  Technology  is  a  key  driver  for development  and  growth  of  this  segment.Telecommunications  is  one  of  the  few  sectors  in India, which has witnessed  the most  fundamental,  structural  and  institutional  reforms  since 1991. In recent times, India has emerged as one of the fastest growing telecom markets in the world. The communication technology has taken a big  leap forward and received the national recognition as the key driver for development and growth. India has the second largest wireless network in the world with nearly 750 connections. As on 31st December, 2012, the total gross telephone subscribers  in the country was 895.51 million covering total wireless subscribers of 864.72 million and wire  line  subscribers of 30.79 million  respectively. During  the period,  the overall tele‐density was 73.34 per cent overall urban and rural tele‐densities being 149.90 and 39.85 respectively. The break‐up of the Tele‐density with .respect to wire line and wireless are 2.52  and  70.82.  The  total  domestic  broadband  subscriber  communication,  navigation  and surveillance  systems,  base  were  14.98  million  in  December  2012.  This  coupled  with proliferation of handsets  (supportive equipment),  FM  stations,  set  top boxes which  are  also being  exported  makes  this  segment  an  attractive  destination.  The  estimated  value  of production for this segment for 2012‐13 is Rs. 55,000 crore as against Rs. 40,500 crore in 2011‐12,  i.e.,  a  growth  of  about  35.8%.  The  figure  below  shows  the  production  growth  of  the 

15,870 13,490 

14,970  14,970 16,500 

24,300 

‐15.0% 11.0%0.0% 10.2%

47.3%

2007‐08 2008‐09 2009‐10 2010‐11 2011‐12 2012‐13(E)

Computer Hardware Production 2008‐2013 in INR Crores 

EMC AT ANN

ADD‐ELCINA

 

c

 

 e) S

mdTffiit 

f) TdhisdiparahgeaEc

UR, COIMBATORE

A ELECTRONICS 

communicatio

Strategic Elecmarkets globadefence forceThese  requirefocusing moreforeign equitymporting thrn India as weto find a right

This is an impdefense  purphomeland  sencludes  comsystems,  satedisaster manndustry  has paramilitary  fand a Defencrevised recenand dispersedhave opened geo‐political  cequipment byabout  13.4% Electronics (Scrores  during

E – FINAL DPR 

PARK PRIVATE L

on and broad

ctronic Systeally and  likelyes. Requiremeements  are  pe and more oy participatioice as much ell as from ab fit.  

portant sectorposes  as  weecurity  and  cmunication, ellite based coagement  sysnot  been  abforces.  In thisce Procuremetly to achieved and leave a up huge oppconsiderationy 2015.Indianper  year  duE)  in India hag  2010‐11.  A

LIMITED

casting equip

ms:    Indian Ay to grow furent during 20primarily  beinon  ‘Make  in  In, JV norms, as China andbroad. Task  is

r due to criticell  as  the  emcivilian  applinavigation  aommunicatiotem  and  intble  to meet s segment, went Policy ande this purposelot of room fportunities  fons,  India  is exn defence elecuring  the  11as been growAs  per  projec

 

pment for the

Aerospace &Drther at a  fas012 to 2017 png met  throuIndia’ througetc. India is t Pakistan.This to map the 

cal technologmerging  statcations.  Thend  surveillanon, underwaternal  securitthe  bulk  of 

while preferend Defence Pre, domestic cfor investmenor DPSU’s as xpected  to bctronics indus1thplan  periodwing steadily fcted  growth 

e period from

Defence  (A&st pace due tperiod  is pegugh  imports, h offset provthe biggest ims presents a possibilities 

y requiremente‐of‐the‐art e  strategic  ence  systems, er electronic y  systems.  Tthe  requirem

nce  for domeroduction Polcapability in snt and local mwell as  locae one of  thestry has beend,  i.e.2007‐12from Rs. 5700rates  and  in

m 2008‐2013. 

D)  sector  is oo  large scale ged at over Rbut  new  po

visions, relaxamporter of debig opportunby understan

nts for the strtechnology 

electronics  seelectronic w systems, nigThe  Indian  stments  of  Indestic over  impicy have beestrategic electmanufacturingl  Large and Me  top  five man growing at a2.The  produc0 crores in 20ndustry  estim

Page 

one of  the  lamodernizatiRs. 100,000crlicy  initiativeation of normefence equipnity for compnding the sce

rategic sectorrequirementegment  interwarfare & weght vision devtrategic  electdia’s  defenceports  is  increen  formulatedtronics are limg. Defence OfMSME’s.Drivearkets  for defan average raction  of  Stra007‐08 to Rs.mates,  electr

15 

 

argest on of rores. es  are ms for ment panies enario 

r, like ts  for r  alia eapon vices, tronic e  and easing d and mited ffsets en by fence ate of ategic .9000 ronics 

EMC AT ANN

ADD‐ELCINA

 

pR

 

 g) El

mvacom 

h) Chvph5c4(c1getpce

UR, COIMBATORE

A ELECTRONICS 

production  inRs. 13,800 Cro Figure  below2008‐2013. 

lectronic  Commainly  by  groariety of comomponents, manufacturing

Components high  local  cosvalue  added pace with thehigh costs, m56,600  crorescrores (USD 140% of  the  d30%)  of  thisconsumption,12, this resultgrowth of Eleenergy  and telecommunicproduction  figcroresin 2011electronics co

E – FINAL DPR 

PARK PRIVATE L

n Defence Secores during 2

w  shows  the 

mponents:  Twth  in  consuponents fromICs)  and  is  dg capabilities 

manufacturinsts because  cmanufacturine rest of the waking  it globs  (USD 11.8 b12.5 billion) indemand  at USs  componen, which is useted in  importctronic CompTablets  (IT cations,  indgure  for  com1‐12, showingomponents in

LIMITED

ctor  in  India 013‐14 recor

production  g

he  growth  inumer  electrom the rudimedependent  onin the countr

ng  has  facedcomponents ng. Historicalworld, and wally un‐compbillion)  in 20n 2012‐13. AgSD  .99 billionnt  productioned in local equts of almost Uponents are Lproduct).Thustrial  elect

mponents  is  tg a growth of  India for the

 

reached Rs.1ding a growth

growth  of  str

n  production onics  and montary (cablesn  derived  dery.  

  serious  charequire high ly,  Indian  ele

was saddled wpetitive. Dem11‐12  and wgainst this don  and USD  5n  is  exporteuipment prodUSD 8.6 billioLED lighting,aese  are  in tronics  and to  the  tune  oabout 7%. Fige period 2008

12,000crores h of over 15%

rategic  electr

of  componeobile  sector. s, simple connemand  based

llenges due  tinvestmentsectronics  comwith outdatedand  for elect

was estimatedomestic outpu.19  billion  reed  leaving  oduction. As peon of componutomotive eladdition  toconsumer 

of  Rs.  26,500gure below sh‐2013:‐ 

during 2012‐%. 

ronics  segme

ents  industryThis  segmennectors) to ved  on  local ma

to policy defs,  technologymponents  secd technology,tronic compod  to grow  to ut has remainespectively. Anly  about  2er estimates anents. The proectronics, eno  existing  seelectronics.

0  crores  as  ahows the pro

Page 

‐13 and exce

ent  for  the  p

y  has  been  dt  includes  a ery high tech arket  growth

ficiency  as wy and  requirector  had  not ,  low volumesonents crosseabout Rs. 68

ned approximA  significant  s25%  for  domavailable for 2oducts drivinergy meters, egments  suc  The  estimagainst  Rs.  24oduction grow

16 

eeded 

eriod 

 

driven wide (chip h  and 

ell  as  high kept s and ed Rs. 8,100 

mately share mestic 2011‐g the solar 

ch  as mated 4,800 wth of 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 17 

   

   1.6 Opportunities 

 

As  per  the  “Report  of  task  force  to  suggest measures  to  stimulate  growth  of  electronics manufacturing  industry”,  the  electronics industry  can  significantly  boost  India’s  GDP, generate employment, modernize processes and enable  country’s  inclusive  growth.  Domestic manufacturing companies have  the opportunity to expand their production to USD 400 billion by 2020 with a very significant contribution to GDP, at 20% for 2020, at par with other economies. 

“The  Indian  ESDM  industry  presents  a  huge opportunity and is expected to emerge as a vital contributor to the nation’s economy.  

While  we  continue  to  dominate  the  high‐end semiconductor design space, we are also seeing a major shift in focus from just design to end‐to‐end  product  conception  and manufacturing  to truly  dominate  the  global  ESDM  industry”. KapilSibal‐  former Minister  for Communications and IT. 

 a) The electronics industry can increase employment in the country significantly, since some of its 

segments, such as electronic system manufacturing, are human capital‐ intensive. The  industry was estimated to employ about 10 million currently and this could grow to 28 million in 2020. 

b) The electronics  industry has a high potential for domestic value addition, especially in some of its segments, e.g., semiconductor design and electronics system/product design. 

c) Electronics  is  driving  the  Digital  India  agenda  and  facilitates  e‐governance,  developmental schemes  and  initiatives  launched  by  the  government,  e.g.,  SarvaShikshaAbhiyaan  (SSA), Restructured‐Accelerated Power Development and Reform Program  (R‐APDRP) and Mahatma Gandhi Rural Employment Guarantee Act (MNREGA). The government’s allocation of funds for developmental  schemes and  initiatives  is  close  to USD 45 billion. However,  IT  intervention  is required to ensure the effective implementation of these schemes and initiatives. 

d) The  government  is  in  the process of  setting up Common  Service Centers  (CSC)  at  the  village level,  increasing  tele‐density,  scaling  up  broadband  access  and  power  availability.  These initiatives  aim  to modernize  and  transform  India,  enable  equitable  and  inclusive  growth  and 

9,630 12,040 

13,610 

21,800 

24,800 26,500 

25.0%13.0%

60.2%

13.8%

6.9%

2007‐08 2008‐09 2009‐10 2010‐11 2011‐12 2012‐13(E)

Electronic Components Production 2008‐2013in INR Crores

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 18 

   

make  ICT  relevant  for  everyone  in  the  country.  Although  these  schemes  require  heavy investment, they offer huge opportunities for the manufacturing and design industries to create designs for products manufactured in India. 

 The  Indian  electronics  system  design  and manufacturing  (ESDM)  industry  is  one  of  the  fastest growing  sectors  in  the  country. Witnessing  uninterrupted  growth,  the  ESDM  Sector  in  India  is globally recognised for its consumption potential. Changing global landscapes in electronics design and manufacturing capabilities, and cost structures have turned the attention of global companies towards India. Companies from around the world are looking to build local capabilities in India not just  to serve  the  resident market but also  to cater  to overseas markets. This has  resulted  in  the development  of  indigenous  capabilities  across  the  ESDM  value  chain  in  India  though  different segments such as telecom electronics, automotive electronics, consumer electronics and industrial electronics, are at different stages of ecosystem development. The focus  is currently on providing the  necessary  impetus  and  developing  the missing  links  so  as  to make  the  local  ESDM  sector globally competitive. (F&S and IESA Study excerpts)   Electronics  industry  can  play  a  big  role  in  providing  products  and  solutions  for  other  industry verticals. Such products and solutions  include  low cost devices, handheld devices, bio monitoring solutions, micro payment solutions, GIS, project monitoring solutions, and smart meters to enable various developmental  initiatives of  the  government.  The  industry has  the potential  to  leapfrog India to next generation of technology adoption and holds immense transformational potential for various industry verticals as given below:‐ 

 Industry Vertical   Present State  Future Potential  

Access No connectivity  Wireless  

Electro Mechanical Meters   Smart Meters 

Energy  Incandescent lighting  LEDs  

Energy Shortage   Green Energy/Energy Efficiency 

Healthcare   Accessibility & Cost Affordable Devices/Telemedicine

Education  Limited Reach   Digital/Virtual Classrooms 

Digitization  Analogue to Digital  Electronic society/Unique ID/Digital TV, Radio 

Security  Human dependence  Integrated surveillance systems 

Others E.g. automotive   High cost, High emission cars Low cost, Low emission cars 

 

    

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 19 

   

 1.7 Market demand for key products 

 The market demand  for various high growth products are as given below also  the Figure below represents some of them graphically:‐ 

 a) PC Tablets: According to MAIT, the apex body representing India's IT hardware industry, 

training and R&D services sectors, tablet sales  in 2012‐13 stood at 1.9 million units as against 0.36 million units in 2011‐12 witnessing a growth of 427 per cent. According to a recently  published  report  by  TechSci  Research  ‘India  Tablet  PC  Market  Forecast  & Opportunities,  2018’,  the  tablet market  in  India  is  set  to  generate  USD  2  Billion  in revenue by  the end of 2013. Also  the  revenues are expected  to grow at  the CAGR of 33% by 2018. India  is  likely to have the second‐largest user base  in the world, and the largest in terms of incremental growth, with 330 million to 370 million Internet users in 2015.  Given  current  downward  trends  in  the  costs  of  Internet  access  and  mobile devices,  India  is on  the verge of an  Internet boom.  In an evolution pattern unique  to India,  users  who  access  the  Internet  only  through  a  mobile  or  tablet  device  will constitute around 75 percent of new users and 55 percent of the aggregate user base in 2015,  leading  to  increasing demand  for  content  that  is optimized  for  a  small  screen‐(McKinsey report).  

 b) LED Products: By 2020 the LED products market  is expected to grow to USD 34 Billion 

from a base of USD 1 Billion in 2010.Growing population and rise in income provides an impetus to the growth of the LED market in India. Demand from consumer electronics is expected  to  emerge  as  a major  growth  driver  for  the  Indian  LED market.  Increasing usage  in  street  lighting,  public  places  and  growing  indoor  lighting  applications  is expected to boost the growth prospects of the LED market in India.  

c) DTH: Digitisation will drive growth in DTH market. By 2020 the number of subscribers is expected to grow to 200 Million. The government announced the digitisation of cable television  in  India  in  four phases, which would be completed by the end of 2014. The digitisation  of  cable  television  has  led  to  increased  demand  for  set‐top  boxes,  dish, cables, and other electronic components. The DTH market is expected to see its annual revenue grow to more than Rs. 28,500 crore (USD 5 billion) by 2020. Consumer demand for media‐rich  home  entertainment  services  is  driving  innovations  and  new  revenue opportunities  in  the  STB  industry. Next‐generation  STBs will  become  hybrid  devices, integrating the video content from multiple signal sources such as broadcast television, premium VoD, and  Internet‐based over‐the‐top  (OTT) video  services, providing value‐added capabilities like time shifting, and allowing content to be distributed to a variety of  viewing  devices  including multi‐room  TV  networks,  personal  computers,  portable media players, and other mobile devices.  STB manufacturers are  looking  to decrease 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 20 

   

the bill of materials  (BOM) cost by using  in‐house CAS solutions and  low‐cost system‐on‐a‐chip  (SoC) optimized with  lower‐powered CPUs  that  support HD  video, but only simpler graphical user interfaces.  

d) Semi‐Conductor Design: Rising demand and availability of talent to boost growth in the semiconductor  design market.  By  2020,  the  semiconductor  design market  in  India  is expected  to  increase  to  USD70  billion  from  USD9.9  billion  in  2012.Solid  State Technology in Metering and Lighting induce Growth in Semiconductor Revenues. 

 e) TVs:  India  is the world’s third  largest TV market. The Market  is slated to grow to USD 

17.7 Billion by 2017.   

f) Telecom  Equipment:  Rising  tele‐density  in  the  country  is  fuelling  high  demand  for telecom equipment. By 2020 the market is estimated to grow to USD 34 Billion. This is fuelled by rapid mobile phone penetration in the country. Demand for mobile handsets in India, the world’s second largest telecom market after China, will reach 350 million a year by 2020, and 505 million handsets will be made  in  India  that year(Federation of Indian  Chambers  of  Commerce  and  Industry  and  professional  services  firm  Ernst  & Young). The  report  titled  “Mobile Handsets: Providing Mobility  to Every  Indian,”  also stated  that  the  average  selling  price  of  handsets  in  India  will  rise  to  $60  by  2020, compared  with  $47  in  2010.  The  study  recommends  that  there  is  need  to  set  up handset manufacturing cluster parks that would enable a sustainable ecosystem for the manufacture of mobile handsets in the country. One of the primary drivers of the sector is  an  increase  in  average household  communication expenditure. The untapped  rural market is expected to provide handset players the next phase of growth. The number of 3G  subscribers  is  expected  to  cross  300 million  by  2020,  fuelling  the  growth  of  3G enabled handsets.Further, buoyant SIM Growth and Massive Social Sector  Investment will grow the market for Smart Cards and related products.   

g) Flash Drives: The market growth is driven by massive Flash Adoption in Digital Cameras USB Flash Drives, A/V Players, Gaming & Navigators, Mobile Phones, Tablets, Solid State Drives,  Internet Enabled TV and Set Top Boxes. Storage Growth  to 34GB average per Device By 2016 is expected as per SanDisk estimates and Gartner forecast. 

 h) Smart Meters: The Smart Electrical Meter provides numerous advanced  functions  for 

recording and checking electrical energy parameters for monitoring and billing purposes and  for accurately assessing demand and supply, plugging power pilferage, preventing overdraws etc.Some  smart meters also  contain a  chip, which  can be used  to provide voice connectivity to user. The model can communicate with each and every household when  there  is  a  power  crisis  and  can  process  any  request  to  restrict  the  load.The futuristic  technology also has  small‐time micro power producers  (houses and offices) 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 21 

   

using solar panel or wind which will contribute to surplus power to the grid and hence help  consumers  gets  a  rebate  in  their bills.  The  consumers  can  remotely  control  the power consumed by home appliances like air conditioners, washing machines or ovens to save energy and cost. All these gadgets can be remote‐controlled through the web or a mobile phone. The smart meter also has a display system that shows real‐time power usage  by  geysers,  air‐conditioners,  sump  systems,  and  other  gadgets.    As  per  an asianpower.com  report,  while  there  are  significant  infrastructural  development  and capacity building issues, India  is estimated to  install 130 million smart meters by 2021. Unlike developed countries however, India has not introduced smart metering in a large scale until now. The government  is also going to finalize these eight projects of worth Rs.  500  crores  (USD  9.69  million)  on  smart  grid  implementation,  which  uses  a combination of smart metering and various technologies to improve the efficiency and reliability power system for sustainable growth. This however remains as a high growth opportunity across the next decade.  

i) Surveillance  Cameras:  Presently  in  India  security  solutions  are  still  dependent  on personnel security guards manning sensitive premises or even common commercial and residential  locations.  However,  this  is  changing  as  seen  in  developed  countries  and security options aided by electronics devices are gaining firm ground, such as biometric (finger  print  readers,  voice  and  iris  scan),  CCTV  and  control  room  monitor  alarms.  According  to  a  recent  analysis  by  ASSOCHAM,  the  video  and  surveillance  and  CCTV market in India is gaining at a CAGR of 30% a year and is likely to cross Rs. 2200 crores by 2015. The Indian CCTV market is currently poised at Rs. 1300 cores and accounts for about 40% of the Rs. 3250 crores worth total electronics security market in India.  

 j) Medical  Electronics: Medical  electronics  too  is  growing  rapidly  in  India  and  is  set  to 

witness  a  critical  mass  effect.  Electronic  components,  devices,  and  products  are increasingly gaining  importance  in  the healthcare sector.   The medical electronics has reinforced the existing healthcare infrastructure in various ways, from digitizing medical test,  diagnostics,  and  therapeutic  procedures  to  enhancing  the  reach  of  healthcare through telemedicine and health IT. The medical electronics market is viewed as a sub‐segment of the medical devices market. The medical devices market may be classified into  two  major  categories  ‐  devices  that  require  external  energy  source  to  be operational  (powered)  and  those  that  do  not  require  any  external  energy  source. Powered devices may be divided  into three product categories  ‐ equipment,  implants, and disposables. Equipment accounts for the largest pie of the total market followed by medical  implants and disposable  segments,  respectively.  It  is also  the  fastest growing segment  and  is  largely  dependent  on  imports.  This  can  be  further  segmented  into surgical  equipment,  diagnostics,  and  life  support  equipment.  The medical  electronics industry has witnessed double‐digit growth in the past couple of years and this growth trajectory  is expected to continue. According to a Deloitte FICCI report  Indian Medical 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 22 

   

Electronics  Industry Outlook 2020,  the  Indian medical electronics  industry constituted sales of Rs. 5000  crores  (USD 1 billion)  in 2010  and  is projected  to  reach Rs. 32,500 crores (USD 6.5 billion) by 2020, at a CAGR of 17 percent.  

k) Automotive  Electronics:  Automotive  Electronics  is  gaining  share  in  the  BOM  of  an automobile.   Beginning with  the  requirement of providing  enhanced engine  control, the  current breed of automobiles has become more and more  reliant on electronics, enabling  them  in  going  faster,  even while  providing  highest  levels  of  safety.  Today's contemporary  cars  have  evolved  into  electronic  machines,  with  more  and  more operations  being  controlled  with  electronic  control  units  (ECUs).  For  instance,  a premium  segment  car  can  comprise  up  to  150  such  ECUs  for  controlling  virtually  all vehicle‐related aspects. These can  include an engine control unit  for managing a car's efficiency, a steering and surround view system  for preventing accidents, a  telemetric system offering  information  related  to  local hot  spots, an electronic  stability/traction control for maintaining appropriate steering control, and sensors for deploying airbags in the event of a collision. The major trends driving demand for increased penetration of electronics in automobiles include regulatory mandates for improving fuel economy and stringent  emission  standards  as  well  as  requirements  for  advanced  safety  systems, consumer  demand  for  safety  &  security  and  comfort  &  convenience  features,  and growth  of  hybrid  and  electric  vehicles.  Environmental  issues  and  highly  stringent government regulations have been forcing auto OEMs to accord greater importance to fuel efficiency. The global market  for Automotive Electronics, estimated at USD 191.3 billion in 2013 and forecast to be USD 204.6 billion in 2014, is further projected to reach USD  314.4  billion  by  2020,  thereby maintaining  a  CAGR  of  7.3%  between  2012  and 2020. OEM Automotive Electronics accounted for a share of 86.3% in 2013 equating to USD 165.2 billion  in the overall Automotive Electronics market. This  is forecast at USD 177.2  billion  in  2014  and  expected  to  register  a  2012‐2020  CAGR  of  7.6%  to  reach projected  USD  277.1  billion  by  2020.TE  Connectivity  in  a  study  on  “Electronics Manufacturing  in  India,  in  Pursuit  of Greater  Localization”  found  out  that  the  Indian automobile industry has experienced significant growth in the last decade.The share of electronics  in automobiles  is estimated  to grow  from USD 9 billion  in 2013  to USD 26 billion by 2020. Electronic components used  in the automotive  industry are estimated at 10 percent of the total bill of materials, and this is expected to increase by about 10 percent annually over the next ten years.  

    

   

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 23 

   

 

  

  

  

 Source: IBEF 

9.9

70

2012 2020 E

Semiconductor Design Market Growth IndiaUSD Billions

27.8%CAGR 7.7

17.7

2012 2017 E

TV Market India USD Billions

18.1%CAGR

11

34

2012 2020 E

Telecom Equipmet Market Growth India 

USD Billions 

11%CAGR

1

6.5

2010 2020 E

Medical Electronics Market Growth India USD Billions 

17%CAGR

11

34

2012 2020 E

Telecom Equipmet Market Growth India 

USD Billions 

11%CAGR

1

6.5

2010 2020 E

Medical Electronics Market Growth India 

USD Billions 

17%CAGR

162.5

314.4

2013 2020 E

Global Automotive ELectronics Market

USD Billions 

7.6%CAGR

9

21

2013 2020 E

Share of Electronics in Automobiles India 

USD Billions 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 24 

   

 1.8 Top 25 products 

 Top  25  products  (as  by  F&S,  IESA  Study)  that  account  for  80  percent  of  the  overall electronics Total Market  (domestic and  imports) revenues  for 2012 are  listed  in the chart below:‐ 

 

Top 20 Products that account for 80% of Market 

1. Mobile Phones  14. Printers and MFD

2. Flat Panel Display (FPD) TV 15. Routers and Switches 

3. Notebooks  16. Car Radio

4. Desktops  17. CFL

5. Digital Cameras  18. Energy Meters

6. Inverters and UPS  19. Digital Instrument Clusters 

7. Memory Cards and USB Drives 20. Smart Cards

8. 4W EMS  21. PON, GPON ONT

9. LCD Monitors  22. Tablets

10. Servers  23. LED Lighting

11. Base Stations  24. Payment Terminals 

12. Power Supplies  25. 2W Ignition

13. Set Top Box 

The IESA‐ Frost & Sullivan report  

1.9 Government policy support & initiatives  

 The Government of India is increasing its focus on ESDM sector and aims to transform the country from a consumption‐driven market to the one that has manufacturing capability to meet  local  and  export  related  demand while  simultaneously  focusing  on  producing  high value add electronic products. This section describes various schemes the Government has launched to give a boost to manufacturing of electronics  in the country as well create an entire electronics ecosystem.    These  schemes are gradually being understood and utilised by  the  industry  for obtaining their benefits for enhancing competitiveness and business growth.   

1.10 National policy on electronics (NPE) 

 The Cabinet on 25th October, 2012  approved  a National of  Electronic Policy  (NPE) 2012 covering a comprehensive set of schemes for promotion of Electronics System Design and Manufacturing  (ESDM). The key objectives of  this policy are achieving a  turnover of USD 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 25 

   

400  Billion  by  2020  involving  investment  of  about  USD  100  Billion  and  generate approximately  28  million  jobs.  Key  incentives  announced  under  this  scheme  were  the Electronics Manufacturing Cluster Scheme  (EMC),  the Modified Special  Incentive Package Scheme  (M‐SIPS)  and  Preference  to  domestically  manufactured  electronics  goods (Preferred Market Access [PMA]). The other focus areas of the policy are Human Resource Development, Promotion of exports, Cyber Security, Strategic Electronics, R&D, Handling E Waste  and  setting  up of  Semiconductor  Fab  in  India. Approvals have been  accorded  for setting  up  of  two  semiconductor  fabrication  units  in  the  country,  entailing  combined investment of USD 8.6 billion, one led by Israel's Tower Semiconductor Ltd. (in partnership with  IBM)  and  the  other  by  Franco‐Italian  STMicroelectronics  N.V.  (in  partnership with Hindustan Semiconductor).  

Some of the key initiatives under NPE are as below:‐  a) EMC Scheme:  In October 2012, the Government notified its Electronics Manufacturing Cluster 

(EMC)  scheme  to  provide  world‐class  infrastructure  to  attract  investments  in  India’s  ESDM sector.  According  to  the  scheme,  the  Government  will  offer  financial  support  for implementation  of  EMCs  that  will  help  development  of  entrepreneurial  ecosystem  in  the country,  drive  innovation  and  catalyse  its  economic  growth  by  increasing  employment opportunities and tax revenues.   Key features of the scheme:  

 I. The proposed EMCs scheme supports setting up of both Greenfield and expanding or 

modernising  Brownfield  EMCs.  Upto  50%  subsidy  is  available  for  infrastructure development in a Greenfield Cluster and upto 75% for any modernisation and Common Facility  Centre  in  a  Brownfield  Centre.  The  Government  has  approved  a  number  of proposals for setting up EMCs and for M‐SIPS incentives to units located in these EMC’s.  

II. The Government would support a Special Purpose Vehicle (SPV), which should be a legal entity  that  is duly  registered  for  this  purpose.  The  SPV may be promoted by private companies,  industry associations,  financial  institutions, R&D  institutions, state or  local governments or their agencies and units within the EMC. 

 III. The  SPV  will  develop,  operate  and  maintain  infrastructure,  amenities  and  other 

common facilities created in EMCs.   

IV. The SPV should consider  including an academic or research  institution as part of  it for suitable academic‐industry linkages.  

 V. EMCs  will  use  existing  Information  Technology  Investment  Region  (ITIR)  wherever 

available.   

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 26 

   

b) Modified Special  IncentivePackage Scheme (MSIPS): This Scheme provides  fiscal  incentives as part of a  special  incentive package  to promote  large‐scale manufacturing  in  the ESDM  sector under its Modified Special Incentive Package Scheme (MSIPS). The objective of the scheme is to remove  impediments  in manufacture of electronic products, e.g.,  the high cost of power and finance, high transactional costs and poor base of supply chain, and create a  level‐playing field for the development of an indigenous electronics‐manufacturing eco‐system in the country. The scheme has been extended by 5 years w.e.f. August 2015 and is now available till August 2020.  These incentives offset, past disadvantages such as high tax, cost of power, finance and freight, high transaction costs etc. to a great extent. Comprehensive details of the scheme are available on DeitY website.   

i. Capital subsidy up to 20‐25% for 10 years on Capex. ii. Reimbursement of CVD/excise for capital equipment in non‐SEZ units. iii. Reimbursement of  central  taxes and duties  for 10  years  in  select high  tech units  like 

fabs and ATMPs. iv. Available for the entire value chain of identified electronics products, manufacturing of 

equipment for electronic production and select raw materials.  v. Production  subsidy  at  10%  of  production  turn  over  (ex‐factory)  for  fabrication  and 

ATMP of analogue mixed  semi‐conductor  chips, power  semi‐conductors OLEDs, PCB’s etc. (introduced in revised MSIPS on 3rd Aug 15). 

vi. Incentives available for 10 years from the date of approval.  

c) Preferential Market Access: The Government has notified  its policy of preferring domestically manufactured electronic products  for procurement by all government ministries/departments (except Defense). The policy is applicable for goods purchased for the Government’s own use as well  as  for  PPP  projects  and  PSU’s.  The  definition  of  domestically manufactured  electronic products requires that such products are manufactured by companies that are established and registered in India (including contract manufacturers but excluding traders).   

d) The benefits of National Manufacturing Policy and National Investment & Manufacturing Zones to be available to EMCs.  

India has entered  into Free Trade Agreement  (FTA)  / Preferential Trading Agreement  (PTA) with a number  of  countries  /  trading  blocs  (Thailand,  Singapore,  ASEAN,  Korea,  SAFTA,  etc.)  and more Agreements  are under negotiation, wherein  import of  electronics hardware  from  these  countries shall be allowed at preferential rate of import duty, which is lower than the normal tariff rate.  100% Foreign Direct  Investment  (FDI)  is allowed under the automatic route  in the ESDM sector.  In case  of  electronics  items  for  defense,  FDI  up  to  49%  is  allowed  under  the  government  approval route, whereas anything above 49%  is allowed  through  the approval of  the cabinet committee on security.  Two  government‐driven  initiatives  to  drive  demand  –  National  Knowledge  Network  &  National Optical  Fibre  Network.  Large  demand  generated  due  to  government  schemes  like  the  National 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 27 

   

Knowledge Network, National Optical Fibre Network, tablets for the Education sector, a digitization policy and various other broadband schemes.  Venture funds with a strong focus on electronics planned include the Electronics Development Fund, Walden India Fund, KITVEN Fund and the SIDBI Fund.  Electronic Sector Skills Council and Telecom Sector Skills Council have been set up for establishing an effective and efficient ecosystem for developing and imparting outcome‐oriented skills for the ESDM sector. A  total of  90,000  people  are  to be  supported under  the  Skill Development  Scheme  in  six different states. 

 1.11 Financial support 

 Additional  financial  incentives are being offered by  the Central Government  to promote ESDM  in the  country  and  these have been  introduced  in  the  last Union Budget.  These  include  correction /reduction  in Customs Duties on specific  inputs to correct  inverted duties and also to reduce costs of Manufacturing.   

SAD has been reduced to address the problem of CENVAT credit accumulation. On all goods except populated PCBs,  falling under  any Chapter of  the Customs  Tariff,  for use  in manufacture of  ITA bound goods; SAD has been reduced from 4% to Nil.  

  

1.11.1 Excise  duty  structure  on  certain  goods  is  being  restructured  of which  some  items  are  as follows 

 1) Wafers  for use  in the manufacture of  integrated circuit  (IC) modules  for smart cards  from 

12% to 6%. 2) Inputs for use in the manufacture of LED drivers and MCPCB for LED lights, fixtures and LED 

lamps from 12% to 6%. 3) Mobiles  handsets,  including  cellular  phones  from  1% without  CENVAT  credit  or  6% with 

CENVAT credit to 1% without CENVAT credit or 12.5% with CENVAT credit. NCCD of 1% on mobile handsets including cellular phones remains unchanged. 

4) Tablet computers from 12% to 2% without CENVAT credit or 12.5% with CENVAT credit. 5) Specified raw materials [battery, titanium, palladium wire, eutectic wire, silicone resins and 

rubbers, solder paste, reed switch, diodes, transistors, capacitors, controllers, coils  (steel), tubing  (silicone)]  for use  in  the manufacture of pacemakers  to Nil.  There  are more  such items listed in the relevant Union Budget notification. 

 1.11.2  In order to provide a further fillip to companies engaged in manufacturing, benefit through an 

Investment  Allowance  in  the  form  of  an  additional  deduction  of  15%  of  cost  of  new  P&M, exceeding  INR  250  Million  that  is  acquired  and  installed  during  any  previous  year,  until 31.3.2017. Under  the  existing provisions of  Section 35 AD of  the Act,  investment‐  linked  tax incentive is available by way of allowing deduction of the whole of any expenditure of a capital 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 28 

   

nature  (other  than  expenditure  on  land,  goodwill  and  financial  investments)  incurred wholly and exclusively for purposes of the “specified business” during the previous year in which such expenditure is incurred. 

 1.11.3 Export  Incentives:Focus  product  scheme  –  2%  duty  credit  scrip,  Special  focus  product 

scheme – 5% duty credit scrip.  

1.12 Make in india initiative 

 This  is a major national programme designed  to  facilitate  investment,  foster  innovation, enhance skill development, protect intellectual property and build best‐in class manufacturing infrastructure. The government has undertaken a number of initiatives to facilitate setting up business in India and this is a key focus area of the current government. Driven by the Prime Minister’s Office, large scale promotional measures are being taken by the Government for ‘Make in India’. 

 1.13 Tamil Nadu: electronics industry & investment attractiveness 

 Chennai, the capital of the state has emerged as the largest electronic hardware manufacturing hub in India.  Tamil Nadu ranks first in the country in electronic hardware manufacturing (20‐25 per cent of national production).   The  state has  the advantage of abundant skilled manpower at  relatively lower wages coupled with harmonious and peaceful industrial relations.  Tamil Nadu houses major multinationals, including Motorola, Dell Computers, Samsung, Sanmina‐ SCI, Flextronics and Nokia‐Siemens, besides more than 30 components suppliers.  Chennai  is  the  hub  of  electronic  manufacturing  in  Tamil  Nadu  and  hosts  a  large  number  of companies especially at Sriperumbudur and Oragadam. Among the recent developments is Lenovo’s announcement that  it will resume the Motorola facility near Chennai and produce six million units of Lenovo and Motorola phones  in a year. Sony, too, has announced  it will start manufacturing TV sets in the state, while Videocon's consumer durables factory is set to go on stream soon. Dell, too, has reportedly held talks to expand capacity. A list of the major companies and their activities are as shown in table below:‐  

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 29 

   

Company  Products Investments in Rs 

crores 

Flextronics  Electronics  Hardware  and  mobile  phone components 

450 

Samsung   Consumer Electronics   450 Motorola   Mobile Handsets   135 Dell   Computers   280 Sanmina   Electronics Hardware  225 Moser Baer  PV Panels 200 Signet Solar   PV Panels  2000 TAPPI Semiconductor   Semiconductor testing & packaging   1000 

Nokia Siemens  Mobile  handsets  and  Communication networks 

300 

BYD China   Mobile handsets components   350 Salcomp Finland   Mobile handsets components  120 Perlos Finland  Mobile handsets components  124 Wintek Taiwan   Mobile handsets   161 Jabil,USA   Mobile handsets 310 Laird Tech USA   Mobile handsets 310 Polymatech Japan   Keypads for mobile handsets   82 Shinetsu Japan   Keypads for mobile handsets  47 TVS Electronics   Computer Peripherals  100 Dixon tech   Color TV   37 Natronics   Semi Conductor Packaging  65  

 1.14 Vision 2023 at a glance 

 The State of Tamil Nadu has always been  in the forefront of economic growth  in the country. The State  has made  impressive  strides  over  the  years  to  carve  out  a  niche  for  itself  in  the  fields  of engineering,  automobiles,  textiles,  leather,  Information  Technology,  electronic  hardware  and  hi‐technology  industries and  the Gross State Domestic Product  (GSDP) stood at Rs.4,51,313 crore at constant prices in 2012‐13.  

 a) The industrial GSDP of Tamil Nadu grew at an impressive rate of 9.60% from the year 2005‐06 to 

2012‐13 at constant prices.  

b)  The Vision 2023 Tamil Nadu document envisages Tamil Nadu  to be the most prosperous and progressive  State  with  no  poverty  by  the  year  2023.  Towards  achieving  this  major  goal, manufacturing sector is assigned the key role of energizing the economy and creating a virtuous circle  of  enhanced  competitiveness,  efficiency  and  vibrancy  in  all  sectors  and  galvanize  the citizen and other stake holders towards reaching the targets in unison. Under this strategy, one of  the  10  thrust  areas  identified  in  the  document  is  acceleration  in  the  economy  and achievement of long term goals by increasing the share of manufacturing in the State economy at the annual rate of 14% ultimately reaching the target of 22% by 2023.  

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 30 

   

 c)  To maintain  its position as a progressive State,  the Government has  recently  taken proactive 

steps  like  the  release  of  Vision  2023  Tamil  Nadu  document,  formulation  of  Tamil  Nadu Infrastructure Development Act, Rules and Regulations, along with Tamil Nadu Transparency in Tenders (Public Private Partnership and Procurement) Act and Rules. The United Nations Report on  Probity  in  Public  Procurement  has  recognised  Tamil  Nadu  as  the  first  State  to  have  a legislative  frame work  to  deal with  Public  Private  Partnership  procurement.  Recognising  the importance of quality  infrastructure, the Tamil Nadu  Infrastructure Development Fund (TNIDF) and a Project Preparation Fund  (PPF) have also been set up and  in 2013‐2014; Rs.2000 crores has been provided for the Tamil Nadu  Infrastructure Development Fund and Rs.200 crores for the Project Preparation Fund. 

 1.15 Achievements & attractiveness  

a) Traditionally, Tamil Nadu has been in the vanguard of industrialization among the Indian States.  The State has had a strong presence  in  textiles, engineering, automobile production and auto components manufacture and recently  in  Information and Bio Technology sectors. Tamil Nadu has always been a safe haven for the investors owing to a favourable business climate, excellent infrastructure  for  trade  and  investment,  outstanding  law  and  order  maintenance,  peaceful industrial relations and healthy socio‐economic reforms.  

b) Among the Indian States, Tamil Nadu is now  ranked: i. First in the number of factories  ii. First in the number of workers employed in the factories sector iii. Third in Gross Industrial Output and  iv. Third in Net Value Addition 

 c) More  than  3000  foreign  JVs  and  100%  foreign  subsidiaries  including  Ford,  Hyundai,  Saint 

Gobain,  Nokia,  Motorola,  Dell,  Renault‐Nissan,  and  Daimler,  in  addition  to  major  local manufacturers like Ashok Leyland, TVS group, Titan, Murugappa group, cement companies etc.,  have manufacturing bases  in Tamil Nadu with a Foreign Direct  Investment  (FDI) of over USD 10.0 billion.  Tamil Nadu is increasingly becoming the choice of destination for foreign investors, which provides them with a global reach.  Ranked among the top three Indian States in terms of Purchasing Power Parity  (PPP), Tamil Nadu  is a haven  for all  those  looking  for a  rich  cultural heritage, a highly productive work force, excellent infrastructure and cost‐effective operations.  Each of these facts is substantiated by an enviable track record.  

d) Tamil  Nadu  is  to‐date  the  only  State  to  attract  seven  automobile  giants‐Ford,  Hyundai, Mitsubishi, Daimler, Nissan, Renault and BMW. As on date, Chennai, the capital of Tamil Nadu and the Detroit of South Asia, has an installed capacity to produce 13, 80,000 cars and about 3, 50,000 commercial vehicles each year. 

 e) Caterpillar,  USA  and  Komatsu,  Japan  chose  Chennai  to  establish  their  large  earth  moving 

equipment manufacturing  plants.    Chennai  is  now  emerging  as  one  of  the  “Top  10” Global 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 31 

   

Automobile manufacturing centres.   The State  is also  the preferred choice  for over 350  large auto  component manufacturers  accounting  for more  than  35%  of  India’s  auto  components production. 

 f) A comparison of the total operating costs across various investment destinations in India would 

place  Tamil  Nadu  ahead  of  the  rest  and  in  a  very  favourable  position  to  offer  investors opportunities  they  would  find  hard  to  resist.    Chennai  serves  as  the  most  cost  effective production base for export markets by many MNCs.   

 g) Tamil Nadu is known as a major exporter of Leather and Leather Goods, Textiles and Garments, 

Automobiles  and  Components,  Engineering  Goods,  Castings,  Pharmaceuticals,  Spices,  Agro‐Products, Marine Products, Electronic Hardware and, of course, Software. 

 h) Tamil Nadu offers an abundance of relevant skills, robust  IT  infrastructure and easily available 

real estate.   Chennai  is  the  choice of  international  finance majors  as well  ‐  Stanchart, World Bank, Citibank and ABN‐AMRO Bank have set up their back office operations  in the city.   BPOs and off‐shore operations have also preferred to operate from Chennai.   With more than 1,780 IT / IT Enabled Services (ITES) companies, over 3, 75, 000 professionals and annual IT exports of Rs.50, 000 crore, Chennai, with its IT Bay Area, towers over other major cities as an IT and ITES powerhouse. 

 i) Tamil  Nadu  has  an  enrolment  of  over  1,82,000  graduate  engineers  from  553  engineering 

colleges, 1,20,000 diploma holders  from 501 polytechnic  institutes, 9,05,000  science and arts graduates, and over 35,000 software engineers.  

 j) Tamil  Nadu  has  an  enrolment  of  over  1,82,000  graduate  engineers  from  553  engineering 

colleges, 1,20,000 diploma holders  from 501 polytechnic  institutes, 9,05,000  science and arts graduates, and over 35,000 software engineers. The State is blessed with a talent pool of keen minds, well‐honed expertise and  specialized educational  institutions  like Anna University  (the World’s  largest  engineering  university),      Indian      Institute      of        Technology, Madras,  the National Institute of Technology, Trichy and the Madras Institute of Technology and many other private institutions that serve as alma mater to some of the sharpest brains in the country, from where a legion of top notch engineers gear up to take on the world. The Government has set up the Indian Institute of Information Technology at Srirangam near Tiruchirapalli recently to take higher technical education to the next level for the coming decades. 

 k) The State also complements its skilled manpower with salubrious working conditions, a peaceful 

industrial  climate,  committed  workforce  and  extremely  competitive  wage  rates  that  offer substantial  cost  savings.    In  short,  when  it  comes  to  human  resources,  Tamil  Nadu  is  the “Number 1” in skilled manpower availability. 

 l) The installed capacity of conventional energy sources in Tamil Nadu is 11,415 MW.  Tamil Nadu 

is the undisputed Leader in wind power generation with an installed capacity of 7,145 MW.  The renewable energy  capacity of  the Tamil Nadu  is 30% of  the  total  installed  renewable energy 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 32 

   

capacity in the country. The State has unveiled the Solar Policy proposing to add 3000 MW solar power. 

 m) With  the  second  largest  coastline  in  the  country of around 1076 Kms,  a network of 3 major 

ports and 23 minor ports4 that  includes India’s most efficient container port at Chennai, Tamil Nadu  has  effectively  harnessed  the might  of  the  oceans  to  provide  the  perfect  gateway  for investors to reach out to the world.  Its climate favours year‐round port operations. 

 n) Travelling within Tamil Nadu or to any other part of the world  from the State has been made 

extremely  convenient,  through  extensive  connectivity  in  the  skies,  on  land  and  across  the waters.   650 plus direct  international  flights a week and passenger traffic of over 4.50 million per  year  make  Chennai’s  international  airport  the  perfect  launch  pad,  with  excellent connectivity to Europe, USA, the Gulf and East Asia. 

 o) Be it apparel or leather, food or textile processing, biotechnology or IT, the State Government of 

Tamil  Nadu  has  developed  industry‐specific  parks  that  help  promote  products  from  each industry.    In  the  Private  Public  Partnership  (PPP) mode,  the Government  of  Tamil Nadu  has promoted the Mahindra World City, a modern self‐contained industrial park, on the outskirts of Chennai.   This  is  India’s  first operational Special Economic Zone (SEZ) created with world class infrastructure, offering Plug and Play facilities.   

 1.16 State government incentives as per industrial policy 2014 

 While a state electronic policy  is being developed the following are the  incentives announced vide state industrial policy of 2014.  a) Tamil  Nadu  has  an  incentives  package  structured  to  encourage  Value‐addition  and  local 

sourcing and provides support for projects depending on investment size. GoTN provides quality and  reliable  infrastructure support  including Power and Water supply,  roads, communication, waste disposal, etc. The state also ensures a Single Window Facilitation & In‐principle composite approval  on  a  fast‐track  mode  within  30  days.  The  state  is  on  the  verge  of  declaring  an Electronic Hardware Policy.  

b) Power supply to Industries: All units with demand of more than 10 MVA will be provided with reliable  supply  at  110  KV  or  230  KV  level  depending  on  the  eligibility. Uninterrupted  power supply will be given to the projects if the same is covered by MoU or Government Order (non‐MoU).  

c) Inclusion of Investment made in captive power plants: Captive power plants will be treated as eligible  fixed assets  for  the purpose of  the structured package of assistance.   “Captive Power Plant”  for  this  purpose means  a  power  plant  set  up  to  generate  electricity primarily  for  the units’ own use.  

d) VAT refund on Capital Goods for establishing captive power plants: Refund of 50% of the VAT 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 33 

   

paid  on  purchase  of  capital  goods  exclusively  for  captive  power  generation  within  the construction period, provided they are manufactured in Tamil Nadu.  

e) Promotion of desalination plants and waste water treatment and recycling plants: Developers of Industrial parks/ SEZs/  Industry clusters, etc. will be provided  incentives to set up desalination plants/  waste  water  treatment  and  recycling  plants.    Also,  the  Government  will  encourage industries to undertake  large waste water treatment and recycling plants on the Public Private Partnership (PPP) mode for treating urban sewage to industrial grade water.  The industries will be encouraged to adopt measures for rainwater harvesting system to recharge the aquifers  in the industrial area. 

 f) Cluster level skill development: This Initiative will focus on specific existing clusters in the auto, 

leather,  textiles,  and  electronic  hardware  sectors.    A  Cluster  Human  Resources  (HR)  Skills Development  Committee will  be  established  in  each major  cluster with  the membership  of engineering  colleges,  polytechnics,  ITIs,  arts  and  science  colleges  in  the  vicinity  and  the participating  industries  to set  targets  for  training and  the  revision of course content of  these institutions. 

 g) Subsidy for quality certification / Patent registration: The Government will reimburse 50% of 

the expenditure incurred by the industrial units subject to a maximum of Rs.1.00 lakh, in getting the  BIS,  ISO  9000  /  14000  or  any  other  national  or  international  certification  or  patent registration. 

 h) Promotion of R & D: In order to encourage Research and Development in manufacturing sector, 

companies  investing  in  R &  D  facilities will  be  incentivised.  For  capital  goods  to  be  used  in setting up hi‐technology R & D centres VAT would be zero rated.  Such capital goods shall not be used for commercial production and be used exclusively for R & D. 

 i) Flexibility  in  labour  laws will  be  adopted without  compromising  labour welfare.    Subject  to 

applicable  labour  laws  and  within  the  parameters  of  the  Industrial  Employment  (Standing Orders)  Act,  1946  (Central  Act  20  of  1946),  flexibility  in  employment  conditions  including flexible working  hours  for women  and  shorter  and  longer  duration  of working  hours,    24x7 operations (3 shifts), employment of women  in the night shifts and flexibility in hiring contract labour will be permitted. 

 j) To  avoid  procedural  delays  in  getting  statutory  clearances  from  various  authorities,  the 

Government of Tamil Nadu has established a Single Window facilitation mechanism under the Guidance Bureau  to accord  in‐principle  composite approval  for pre‐ project clearances at  the State Government level.  A Committee headed by the Chief Secretary will monitor the progress of final approvals of all such cases. 

 k) Electricity  tax exemption  is also available depending on  investment amount and employment 

generated. For example an investment of Rs 5 to 50 crores in fixed assets and generation of 100 direct  jobs, Rs 0.30  crores will be  given  as  capital  subsidy  and electricity  tax exemption of 2 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 34 

   

years will be provided.   1.17 Coimbatore industry & investment attraction  

 Traditionally, Coimbatore has a recall as a strong industrial base predominantly in the automotive components,  textiles,  and  pump  sets  businesses.  The  trade  in  Coimbatore  accounts  for  a  total annual  turnover  of  Rs.  16000  crores.Coimbatore  has  a  thriving  market  in  the  automotive components market. The market share of Coimbatore in automotive components is around 25% ‐30% out of the total  Indian automotive component business. The Small and Medium Enterprises caters to supply requirements of Indian automotive OEMs such as MUL and TATA. Coimbatore also is home to pump set manufacturers. About 60 % of the water pumps and 40 % of the motors used in India are made in Coimbatore. The  Coimbatore  region  is  home  to  more  than  fifty  thousand  large,  medium  and  small  scale enterprises doing  thriving business over  the years. When  it  comes  to  the  leading manufacturing and  industrial  hubs  in  south  India,  Coimbatore  takes  pride  of  place.  Coimbatore  is  the  Second largest  industrial  region  in  Tamil  Nadu  with  a  successful  entrepreneurial  and  disciplined  work culture. It is the highest revenue yielding district in the state even ahead of Chennai, thus making it one of the fastest‐growing second‐tier metro cities in India. 

 1.17.1 Evolving businesses 

 The earliest form of enterprise in Coimbatore was the evolution of a well irrigated system. The irrigation  innovation was necessitated by  the droughts  that  the  region underwent  in extreme climates. The  soil conditions were and are  still extremely palpable  for cotton cultivation. The textile  trade witnessed  a  healthy  growth with  an  entry  into  the  international markets.  The developments  led  to  the  establishment  of  the  Coimbatore  spinning  and  weaving  mils consequently. This was among  the  first  step  from  the  transformation of an agriculture‐based business  to an  industrial based business. Envisioning  the growing  role of  cotton weaving and spinning mills, the farming community moved up the vertical chain to undertake processing of cotton yarn into spun yarn where an attractive export market existed. These pioneering efforts gave way  to  textile  capital  goods  business  that  offered  a  captive market  for  growth.   What began as a  focused center  for the manufacture of textile motors  in the early 1900s has today become a multi – disciplinary entity that  is capable of catering to voluminous demands  in the international  market.  Tooling  Divisions  were  incepted  primarily  as  captive  units  for manufacturing houses and have become a major engineering activity in the region today. With time,  many  tooling  divisions  became  profit  centers  of  their  own,  owing  to  the  consistent investment  in  technology.  Today  several  corporate houses offer precision  tooling  services  to global  industries.  The  light  engineering  industry  in  the  Coimbatore  region  also  specializes  in offering  customized  engineering  solutions  for  diverse  requirements.  This  expertise  could  be translated  into  potential  new  business  opportunities.  How  the  businesses  evolved  in Coimbatore is as per Figure below:‐ 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 35 

   

 The city is the second largest software producer in Tamil Nadu, next only to Chennai. IT and BPO industry in the city has grown greatly with the launch of TIDEL Park and other planned IT parks in and around  the  city.  It  is  ranked 17th among  the global outsourcing  cities. Companies  like Aditi Technologies, Cognizant Technology Solutions, Wipro,  Infosys, Robert Bosch GmbH,  IBM, Tata Consultancy Services, Tata Elxsi, Dell, CSS Corp and KGISL having a presence in the city.   

1.17.2 Electronic manufacturing  There  are  a  number  of  small/micro  sized  companies  in  Coimbatore  engaged  in  various electronics  related manufacturing and marketing activities. A  sample  list of micro/small  sized companies  is as per Table below. As  seen  from  the  table  the  strength of  the area  is  towards existing  industries  like  automotive  components,  textiles  and  pump  sets.  The  engineering industry base  in Coimbatore has not been  fully  leveraged and  forms an attractive proposition for setting up an EMC in the region. 

   

Cotton Farming

Spinning Mills  Export Opportunities 

Farm Based Machine Tools

Machine Tools  Automotive Engineering 

IT/ITES

EMC

1800

Pioneering Local Communities initialising farming 

1920

Local Communities identify export opportunity during 

1900

British ushered in the Industrial Era by setting up the Coimbatore Cotton and weaving Mills association

193‐40

Burgeoning demand for cotton from the region lead to mechanisation of textile mills

1920‐30

Cotton Industry paved way for farm related industrial equipment 

1930 onwards Diversification into auto components 

opened new market for entry

Today

Traditional businesses are converting IT/ITES into new business 

Today

Location favours 

electronics 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 36 

   

Company  Activity 

Indus Electronics India Pvt Ltd  Electronic electrical instruments and textile machinery spare parts 

Electronics & Controls Corporation 

Control Engineers and System Designers

Mighty Electronics Equipment Corporation 

Mfg:‐ Electronics lab equipment

Applied Electronics Corporation  Stamping for Motors Pumps, Sheet Metal Boxes 

Lakshmi Electro ‐Tech Industries  Mfg :‐ Electrical & Electronics, Electrical Control Panels Servo Voltage Stabilizers 

B.J. Electronics Pvt Ltd  M PP Plastic Film Capacitors 

Electronics Signals & Controls  Switch Boards & Control Panels 

Getech Electronics Pvt Ltd  Fabrication of Switch Boards & Control Panels 

Abirami Electronics Pvt Ltd  Computer / printer components 

Statex Electronics  Textile Testing instruments 

Salzer Electronics Ltd  Mfg: ‐ Rotary Switches & its allied switch gear products 

Accurate Electronics Mfrs. & Assembling of Electronic Weighing Scales 

Balaji Electronics  Electronic motor run capacitors & mosquito swatter bat 

Able Electronic Services  Mfrs of Servo Stabilizer , UPS , CVT , Auto Transformer & Batteries 

Textro Electronics  AC/DC Drives, Electronic Equipment& Controls, Electrical Control Panels 

Ashwin Electronics  Mfg: ‐ Electronic Fair Metres 

Techno Electronics & Instruments 

Textile Testing Instruments for Cotton, Yarn & Fabric, Moisture tester 

Renson Electronics  Voltage Stabilizers Battery Chargers, UPS Powder Coating ‐Job Work 

Cat ‐ Cam Electronics  Thermal over load protector

Textek Electronics Private Limited  

 Automotive Electronic Instruments Manufacturer 

Edison Semiconductor Pvt Ltd  Electric vehicle technology 

Universal Circuits   Electric and Electronic Circuit Board Manufacturer 

Arvey Sales Company   Electronic Weighing Machine and Sales Manufacturer 

The Everest Scales Company  Electronic Weighing Machine Manufacturer 

BJ Electronic Private Limited   Companies, Electronic Component Manufacturer 

Micro‐V Electronic Instruments  Electronic Tester Manufacturer 

Gowri Electronics   Electromagnetic Relay Manufacturer

Power Electronics  Dish Antenna Manufacturer 

Abirami Electronics Private Limited  

Sheet Metal Components Manufacturer 

Sinic Electronics Private Limited   Money Count Machine Manufacturer 

    

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 37 

   

1.17.3 Talent availability  Coimbatore  is  home  to  five  Universities,  a  large  number  of  Engineering  colleges,  85  Arts, Science and Commerce colleges. Apart from an exciting business environment, Coimbatore has a substantial pool of manpower resources well qualified for engineering and computer software related professions. Coimbatore is an educational hub of Tamil Nadu. There are 40 Engineering Colleges within 40 Kms from Annur (proposed project location) which offers courses related to electronics.  This  is  over  and  above  other  Engineering  colleges  in  the  region  and  proves  that there is adequate skilled manpower available.  

 1.17.4 EMCs near Coimbatore 

 Kanchipuram  District  and  Vellore  in  Tamil  Nadu  are  already  a  notified  Brownfield  clusters. Bangalore and Mysore in Karnataka are also already notified as Brownfield Clusters. There are a total of 5 electronic hardware SEZs being developed around Chennai. 

   

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 38 

   

 1.17.5 Connectivity to the proposed site at Annur 

 a) Distance to Major Cities: The major cities close to Annur and the distance and driving time to these are given in table  below:‐  

City & State  Approximate Distance  Approximate Driving Time  

Coimbatore  30 Kms  45 minutes 

Coonoor (TN)  63 Kms  1.5 Hours  

Erode (TN)  87 Kms 2 Hours  

Salem (TN)  152 Kms  2.5 Hours  

Mysore(Karnataka)  182 Kms  3.5 Hours  

Kozhikode ( Kerala)  216 Kms  4.5 Hours  

Madurai(TN)  223 Kms 4.5 Hours  

Cochin ( Kerala)  238 Kms 4.5 Hours  

Bangalore(Karnataka)  299 Kms  6 Hours  

Hosur (TN)  309 Kms  6 Hours  

Pondicherry (TN)  367 Kms  6.5 Hours  

Vellore(TN)  378 Kms 6.5 Hours  

Mangalore (Karnataka)  437 Kms  8 Hours  

Kanchipuram (TN)  444 Kms  7 Hours  

Sriperumbudur (TN)  472 Kms  7 Hours  

Chennai (TN)  486 Kms 7 Hours  

Sri City (AP)   549 Kms  8 Hours  

 b) Roads & Transportation: Locally the villages are connected through smaller roads and the villagers have access to the site. Annur lies on the junction of three important roads, NH 209 (Coimbatore‐Mysore), Annur  ‐ Avinashi road and Annur  ‐ Mettupalayam road to north east of Coimbatore city. Bus service  is available  to Coimbatore City almost once  in 10 minutes.  It has adequate road links and takes only less than an hour to reach Coimbatore or the nearby towns Avinashi,  Mettupalayam,  Sathyamangalam,  Tirupur  etc.  Commitment  is  made  by  GoTN  for widening nearby roads as per of MoU signed with GoTN.  c) Railways:  The  nearest  Railway  Station  to  Annur  is  at Mettupalayam  at  22  Kms,  but Coimbatore is also close by at 32 Kms. Coimbatore Junction, also known as Coimbatore Main, is the primary  railway  station  serving  the metropolis of Coimbatore.  It  is one of  the major  rail junctions in South India and the third busiest and revenue yielding railway station in Tamil Nadu after Chennai Central  railway  station and Chennai Egmore  railway station.  It  is one of  the A1 graded  station  in  the  Southern  Railway.  This  station  comes  under  the  jurisdiction  of  Salem division of Southern Railways. It  is one of the top booking stations  in  India according to Indian Railways. The trains provide excellent connectivity to Chennai, Bangalore, Cochin, Mumbai and Delhi.  

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 39 

   

Air Connectivity: As per airport authorities, the annual passenger traffic at Coimbatore (embarking and disembarking) is in the region of 108 million passengers every year with around 40 million embarking, 40 million disembarking and another 28 million by means of transit. Coimbatore has direct flights to all metro cities. It is the 18th largest airport in India in terms of total passenger movement and 13th largest airport in terms of cargo handled. Airlines that fly to Coimbatore are Air India, Jet Lite, Spice Jet, Indigo, Air Arabia and Silk Air. Dedicated Customs set up for Export Cargo, Import Cargo is available and Unaccompanied Baggage clearance is available for six days. A warehouse with one time holding capacity of 100 tons and cold rooms and strong rooms are also available. Though it is an international airport only a few flights are available to Sharjah, though Cargo airlines fly to Sharjah and Bangkok 

 

Name of the Airport  Distance from the Airport 

Salem  157 Kms 

Calicut  170 Kms 

Kochi  170 Kms 

Tiruchirappalli  206 Kms 

Madurai  230 Kms 

Bangalore  294 Kms 

Chennai  395 Kms 

 e) Sea Ports: The nearest sea port is at Cochin and is approx. 240 Kms from the site. . The nearest sea ports and distance to the seaports are given in Table below:‐   

Port  Approximate Distance 

Krishanpatnam Port, Nellore, AP  624 Kms 

Chennai Port   499 Kms 

Mangalore Port   441 Kms 

Tuticorin  404 Kms 

Cochin Port  240 Kms 

  1.17.6 Communication 

In Coimbatore, VSNL has  its  international gateway at PSG STEP Software Park  in Coimbatore. The Earth station  is backed up with a  fibre optic cable  link  to Chennai. VSNL offers both  IPLC (International  Private  Leased  Circuit)  and  Internet  both  in multiples  of  64kbps.  STPIs  Earth station is also located at Coimbatore at Saravanampatti in the KGISL complex. It also offers both IPLC  and  Internet  leased  lines  both  in  multiples  of  64  Kbps.  Both  the  earth  stations  are seamlessly expandable and by virtue of Coimbatore’s  locational advantages can get hooked to the wide band width  submarine  fibre optic  cable at Chennai or Kochi  for mission  critical and delay  sensitive  applications. With other  ISPs having been  given  license  to put up  their  earth stations or gateways, many of them would be able to provide reliable & redundant connectivity. This will reduce telecom and connectivity costs  in Coimbatore. This will also  induce companies to set up operations  there  to  take advantage of  the cost benefits  involved. The current earth station in PSG STEP provides a bandwidth of 14 mbps through optic fibre channels and satellite connectivity to Cochin. 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 40 

   

 1.17.7 Cost comparison 

 An  analysis  by  PricewaterhouseCoopers  shows  the  cost  comparison  of  nearby  cities  with Coimbatore  for  IT  services  in  a  scenario where billing  is being done  for  IT  services provided. Table  below  provides  profitability  scenarios  across  cities  at  billing  rates  of  USD  10/  hr. Coimbatore has a clear advantage when  it comes to manpower and real estate costs and  is at par only with Cochin. This is indicates that for electronics manufacturing too the manpower and real estate costs would be favourable compared to other cities nearby. 

 

Overheads   Chennai  Bangalore   Hyderabad   Cochin  Coimbatore 

Manpower   26% 27% 26% 21%  20%

Real Estate   8% 9% 5% 3%  3%

Power   1% 2% 1% 1%  1%

Connectivity   2% 2% 2% 1%  1%

Marketing  10% 10% 10% 10%  10%

Miscellaneous   2% 2% 2% 2%  2%

PBDIT   51% 48% 54% 62%  63%

    

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 41 

   

1.17.8 SCOT  The strength, opportunity, challenges and threat analysis that emerges out of the above clearly indicates  that  Coimbatore  is  a  very  favourable  location  to  establish  an  EMC.  The  proposed location at Annur  is  just 30 Kms from the heart of the city and  is well connected and  land has already been procured for the EMC.  AnMoU has been signed by AIPL with the Tamil Nadu state government to establish an Industrial park in an area of 1500 acres. The EMC will benefit greatly with synergies with the common facilities available at the Industrial Park too. The SCOT analysis is given in the table below. 

 Strengths 

1) Talented Manpower Availability  2) Enterprising Community 3) Thriving  IT,  Engineering  and 

Manufacturing  Sector‐design  strength combined  with  expertise  in  tooling  , many foundry and machine shops  

4) Synergies  with  Sriperumbudur  and Oragadam and other clusters nearby. 

5) Excellent  Connectivity  by  land,  air  and sea  (Cochin  Port)  and  availability  of communication facilities.  

6) Land Availability  7) Comparative  Favourable  Costs 

(Manpower & Real Estate)  8) Salubrious Climate  9) MoU  already  signed  with  the  state 

Government for setting up and industrial park  of  1500  acres  in  the  proposed location.  

Opportunities 1) Extension  to  Electronics  manufacturing 

focus  relatively  unexplored.  Tremendous scope  for  automotive  electronics  (nearly 350 auto component manufacturers in the state, PCBs and Medical Electronics which is a relatively un‐ explored area.   

2)  Captive Electronics Components/products for local industries  

3) Ability to Leverage Design Capabilities   

ChallengesManpower may require extensive training.  

 

Threats None Envisaged 

  

    

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 42 

   

 

CHAPTER 2  

PROJECT OBJECTIVES  2.1. Brief Description of the Project  

The proposed project envisages developing a model and state of the art EMC; spread over 157.6 acres of  land. The project would provide  facilities  that match world‐class EMCs and would be an ideal place  for  investors to establish their manufacturing facilities with ease and without hurdles. The  SPV  will  develop  the  infrastructure  facilities  and  support  investors  who  want  to  set  up individual units within the cluster.  

 A total of 163 plots of various sizes have been designed for sale as independent or combined units occupying  95+  acres.  The  Cluster would  also  endeavour  to bring  the  entire  gamut of  electronic manufacturing  operations  under  one  umbrella  and  facilitate  all  stages  of  the  value  chain  of electronic manufacturing.  The  project  is  expected  to  be  completed  in  a  single  phase  across  18 months  from  start  date.  It  is  expected  that  the  Cluster  would  house  approximately  95 manufacturing units if each such unit is about an acre. 

 2.2. Development Objectives   

a) Local Community:  Provide State of the Art Industrial Infrastructure to enhance competitiveness and  efficiency  of  Electronics Manufacturers who  are  competing  globally with manufacturers operating  in  lower  cost  economies  with  highly  efficient  eco‐systems.  High  value  added manufacturing  in  electronics  sector  in  India  typically  suffers  8‐10%  cost  disability making  it difficult for  local manufacturers to be competitive  in global markets.   Further, most electronic products are subject to zero Customs Duty thereby compelling  India to  import more than 70% of its domestic demand. A key objective of this Cluster is to provide a supportive manufacturing environment, which would reduce manufacturing costs by at least 5%. 

 b) Attract investments for setting up Manufacturing Units by reputed companies which are looking 

to be competitive in the global market. The infrastructure and support services would make the Cluster a preferred location for ESDM Sector. 

 c) Enable  all  investing manufacturer members  to  avail  benefits  under  the  various  Schemes  of 

National  Policy  for  Electronics.  These  include  MSIPS,  Preferred  Market  Access  (PMA)  and encouraging R&D  through Venture Funds  financed  through  the Electronic Development Fund (EDF). The Cluster SPV would also provide information and support to enable members to avail benefits under the State Industrial and IT/Electronics Policies. These expert support facilities for obtaining government policy support would strengthen the competitiveness of manufacturers in the Cluster. 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 43 

   

d) The  development  of  a  large  industrial  park  at  Annur,  Coimbatore within which  the  EMC  is proposed would create the environment for manufacturing and would help to facilitate mutual growth of electronics and other industries at the same place. 

 e) The  Project  aims  to  create  significant  employment  and  investment  opportunities. Once  fully 

established and populated the Cluster expects to employ 16,000+ workers directly and another 30,000  indirectly.  This  is based on a conservative assumption of average capital  investment of Rs. 14 Crores per acre which adds up to about Rs 1300 Crores and an output of Rs. 3,900 Crores at a capital output ratio of 1:3. 

 f) The Government of Tamil Nadu has  attached prime  importance  to  the growth of electronics 

industry  in the state.   The proposed EMC  is also  in  line with the ambitious programme of the state government, which would significantly boost the socio‐economic growth of the region of Coimbatore and Tamil Nadu state in general. 

 g) The proposed EMC  is envisaged  as  a  green  campus  coupled with  smart  city  concepts, which 

would  facilitate  the  establishment  of  manufacturing  units  with  a  view  to  creating  an environmental friendly, sustainable and efficient manufacturing eco‐system.   

 h) Other key objectives of the Project are to provide Skill Development facilities to develop trained 

and  efficient manpower  for  ESDM  Sector.  A  Skill Development  Centre would  be  established which would operate under the guidelines and occupational Standards of the Electronics Sector Skills council.  

 i) The project has progressive CSR Objectives including providing health and education facilities to 

the community living around the project. The CSR activities would also include women’s welfare projects,  girl  child  development  activities  and  low  cost  or  free  medical  facilities  for  lower income homes. 

 Location:  The  proposed  site  (approx  157.6  acres  area)  for  the  Greenfield  EMC  is  located  at AnnurTaluk, Coimbatore District  in  the state of Tamil Nadu. The site  is  located near  the Town of Annur about 9 Km from NH 209 connecting Coimbatore and Mysore. The exact  location  is to the West of OthiMalai Road connecting Annur to OthiMalai temple. The site area was procured from the surrounding Vadkkalaur village to the South West, Akkaraisengapally village to the North West and Kuppanur village to the South. The turn to the site on the OthiMalai Road is about 9 Km from Annur and  the  site  lies approximately 1.8 Km  to  the West  from  the OthiMalai Road.   The  site  is approximately 38 Km from Coimbatore City and 36 Km from the Coimbatore International Airport (Reference  Figure  below).  Location  coordinates  (in  latitude  and  longitude)  demarcating  the proposed EMC area are 11o 18’ 5.4” N / 77o 5’ 11.7” E.  

   

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 44 

   

Proposed

Annur

To Coimbatore City  

9

OthiMalai

157 Acres

1.8

  

  

     

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 45 

   

 

CHAPTER 3  

TARGET BENEFICIARIES 

 3.1. Key Stake Holders  

The key Stakeholders and beneficiaries in the project are:‐  a) Local Community of AnnurTaluk and other areas nearby  b) Electronics Industry  c) Government of India‐ DeitY d) State of Tamil Nadu  e) ELCINA f) ADD Industrial Park ( Tamil Nadu) Ltd and other consortium members  g) Financial Investors and Lenders 

 3.1.1. Local Community: 

 The maximum  benefit  of  establishing  an  EMC  at  Annur  will  go  to  local  community.    The economy  of  the  area  primarily  depends  on  textiles  spinning.  The  proposed  EMC  would generate both direct and  indirect employment to the people of the area.   Further the allied infrastructure would be  required  to  cater  for  the proposed EMC and  this would enable  the overall development of the area.  There are CSR activities being planned for the benefit of the local community and allocation has already been made in the project budget.  Urban forestry development, drinking water provision, health care educational aids and medical facilities etc will be provided the local community.  

 3.1.2. Electronics Industry  

a) This  is a great opportunity  for companies  investing  in  the cluster  to participate  in  the several  schemes under National Electronics Policy,  like MSIPS, PMA etc  to offset  cost disadvantages  faced  by  these  companies.  They  would  also  be  able  to  benefit  from various state schemes.  

b) The cluster  is also expected to promote the startup ecosystem in the industry, through venture  funds,  since  the  Government  has  announced  a  number  of  implementation policies on Electronics Development Fund.  

c) Being part of a large industrial park allows these companies to take not only advantage of  common  facilities  of  the  park  like  social  infrastructure,  convention  centre,  golf course, knowledge city etc but also find synergies with other sector units investing into the industrial park.  

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 46 

   

d) A well‐developed  cluster  can  give  a  unit  located  in  it,  a  cost  advantage  because  of various  reasons  such  as,  increased  supply  chain  responsiveness,  consolidation  of suppliers, decreased time‐to‐market, superior common infrastructure andlower logistics costs.  

e) Assured, good quality and value for money infrastructure & services. f) Hassle  free operating environment and a single point  interface  for all  infrastructure & 

services. g) Synergies from co‐opting companies within EMC. 

 3.1.3. Government of India‐ DeitY:  If India achieves 25‐30% annual growth in electronics production 

over  the  12th  Plan  period,  it  will  create  millions  of  direct  and  indirect  employment opportunities,  contribute  to meeting  inclusive  growth  objectives,  Reduce  Foreign  Exchange outgo and  add to government revenues while improving the quality of life and empowerment of our people:‐ 

 a) Supports the NPE vision and strategy of setting up 200 clusters. b) Help  reduce  fiscal  deficit  as  the  EMC will  contribute  to  narrowing  the  gap  between 

domestic demand and production. c) Possible FDI & increase in Local investments. d) Social Benefits in terms of development of the area and employment generation 

 3.1.4. State of Tamil Nadu: TheCoimbatore Cluster will benefit Tamil Nadu in that:‐  

a) This further strengthens the States initiative on Electronics manufacturing. b) This cluster is an electronics manufacturing gateway to Bangalore and Cochin due to its 

proximity  to  these cities and  is  likely  to attract  investments  from outside  the state as well. 

c) This would assist in development of the local area. d) This  would  generate  employment  and  up‐skill  a  fair  portion  of  the  local  working 

population.   

3.1.5. ELCINA  

a) This cluster is yet another feather in ELCINA’s cap and a significant milestone in realizing ELCINA’s Cluster Vision. 

b) ELCINA  represents  the  industry  and  would  be  in  a  position  to  facilitate  further investments in the sector.  

c) Being able to develop and promote a number of clusters will enhance the credibility of ELCINA and will enable it to represents the Indian Electronics Industry more strongly on various platforms including Department of Electronics & IT (DeitY) Government of India. 

 3.1.6. ADD Industrial Park ( Tamil Nadu) Ltd and other Consortium members   

a) Recovery of investment in the land acquired which is being transferred to the SPV. 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 47 

   

b) Participate in the potential benefits of EMC through equity stake (either through equity or premium for the land). 

c) Enable these companies to contribute to the development of Annur region. d) Positions these companies as a significant players contributing to the national strategy 

to boost electronics manufacturing and infrastructure development. e) Participate in Nation Building. 

 3.1.7. Financial Investors and Lenders  

a) Reduces the risks in the project through commitment from DeitY& Government of TN. b) Bankable revenue streams and adequate cove. c) Credit enhancing mechanisms. d) Reducing the execution risk by selecting investors with a good track record. 

 3.2. Employment Generation 

 Employment Generation: At 163 saleable plots of approx ½ acres each and at an average of 100 employees per unit of ½ acre, 16300 direct  jobs are estimated to be created.  Indirect  jobs  in the electronics  industry  can  be  thumb  ruled  at  about  2  times  the  direct  employment.  The  total employment generated is expected to be 48900 jobs.  

Employment Generated  Per ½ acre Assumption Total Direct Jobs   100 16300 Indirect Jobs  200 32600     

3.3. Total Expected Investments by Units   The EMC has 163 saleable units of 1/2 acre each  for sale  in an area of 95 acres.  In   an acre  it  is possible to set up an unit and the total cost of machinery for a full manufacturing  line (  including 30000CPH   SMT  line) would be   USD 3 Million ( Rs 19 Croresapprox).    Including  land and building the total cost would be around Rs 22 Crores for a full‐fledged manufacturing unit. It is possible that some units would build vertically and include more SMT lines and other P&M. However all units are not  likely  to  set  up  a  complete  manufacturing  line  as  some  are  going  to  be  supporting manufacturing units and some supporting services. The following is assumed.  

Item description No of Units   Investment/Unit Total Investment /INR Crores 

Full Line Manufacturing Units   30  22  660 

Support manufacturing Units   45  12  540 

Supporting Services   20 8 160 

Total   95  1360 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 48 

   

 

CHAPTER 4  

PROJECT COMPONENTS  

4.1. Broad project outline:  

A Greenfield EMC  (Electronics Manufacturing Cluster)  is proposed to be developed on an area of 157.6 acresatAnnurtaluk, Coimbatore District in the state of Tamil Nadu.  The main objective of the project  is to provide a state‐of‐the‐art manufacturing facility for electronics  industry with support from  Government  of  India  under  the  Electronics Manufacturing  Cluster  (EMC)  Scheme  of  the National Policy on Electronics 2012.  The EMC  shall have world  class  facilities and utilities akin  to a SMART CITY  in order  to  facilitate efficient manufacturing.  The project mainly comprises of saleable industrial plots of approximately 2000sqm  each,  which  can  be  combined  to  form  larger  plots  as  per  the  requirement  of  the manufacturer.    Strong  emphasis  has  been  provided  on  easy  accessibility,  efficient  transport network, greenery, worker welfare services and recreational services within the project to attract manufacturers.  GREEN  INITIATIVES  like “Zero‐Discharge”  campus,  solar  lighting,  storm water  recharge  through a natural  water  reservoir,  design  suiting  the  natural  land  contours,  energy  efficient  electrical distribution system make this campus a very attractive and sustainable manufacturing destination.  Broad outline of the project components is:   PLOT AREA = 157.6acres = 637852sqm.  a) Industrial Plots saleable (163 Nos.)= 385714sqm. = 60.5% of the total plot area. b) Services Areas = 12537sqm = 2% of the total plot area. c) Roads = 116232sqm. = 18.2% of the total plot area. d) Parking / Truck holding area = 21099sqm= 3.3% of the total plot area. e) Common Amenity Buildings = 37755sqm with built up area of 16750sqm = 5.9% plot area of 

the total plot area. f) Green area = 64515sqm= 10.1% of the total plot area. 

 4.2. Masterplan: Planning concept  

The total site area  is 157.6 acres and the entire area  is proposed for setting up of the Electronics Manufacturing Cluster.    The Master planning  is  aimed  at optimising  the  layout of  the  industrial plots,  planning  of  infrastructure  (utilities  and  amenities)  and  determining  the  inter  and  intra circulation  after  incorporating  the  detailed  analysis  of  the  site,  assessment  of  immediate 

EMC AT ANN

ADD‐ELCINA

 

surroMan

 The opointin tecentrmaxithe  rInteginnovinfracons Key p

 a) M

aarss 

    

UR, COIMBATORE

A ELECTRONICS 

oundings  anufacturingind

original site ists within the rraces and crral  green  ridmising the naroads,  drainagration  of  aevation with  vstructure,  deideration. 

planning conc

Master plan and constrainareas offeringridge road, wsecondary roaserene ambie

E – FINAL DPR 

PARK PRIVATE L

d  understandustrypropose

s a contouredsite. Thenatureate beautifdge  road  hasatural featureage  and  layoesthetics,  envarious  attribesign,  green 

cepts: 

design: The nts of the siteg unhinderedhich will havads going pernce on the m

LIMITED

nding  the  reed within the

d land with a ural contoursful and  functis  been  planne.  The naturut  of  the  plovironmental butes  of  planbuilding  feat

master plan e. The highestd  views of  the landscapingrpendicular tomain ridge roa

 

equirement e park.  

level differens of the land oional vistas tned  connectial slope of thots  so  that  thconcerns,  fu

nning  like  lantures,  buildin

has been cot areas of thehe entire parkg on either sio the main ridad since no in

of  various 

nce of 33m beoffer an oppohereby rendeng  the  two he land has bhere  is minimunctional  reqnd  use  distribng  guidelines

nceptualized e park have bk.  These  areaide. The  indudge road, thudustrial plot o

 

verticals  of

etween the hortunity to deering an Archhigh‐points een considermum  land  dequirements  abution,  zonins  &  regulatio

considering been made inas  are  conneustrial plots as creating a vopens directl

Page 4

f  the  Electr

highest and loevelop the prhitectural treaof  the  site red while planevelopment wand  technolong,  transportaons  are  given

the opportuto common gected by  the re planned overy attractivey onto this ro

49 

ronics 

owest roject at.   A again nning work.  ogical ation, n  due 

nities green main n the e and oad. 

EMC AT ANN

ADD‐ELCINA

 

       

 b

c)

d

UR, COIMBATORE

A ELECTRONICS 

) State‐of‐thinfrastructroad  netwbuilding  wThere  is a laboratorycentre, emAll  these aelectrical, policy guid 

) Accessibilinetwork abeen  takecomponenroad so th 

) Natural wproposed and replenproposed 

E – FINAL DPR 

PARK PRIVATE L

he‐art  amenture desirablework,  securedwith  businessmanufacturi

y within  the mployee hostamenities wilplumbing,  d

delines issued

ity &  transpre  the basis en  to  ensurents are accessat a shuttle s

water reservoas a water renish the groualong  the  ro

LIMITED

nities:The  clue to  facilitated  gated  cams  centre,  traing support bcluster.  The tel, worker wll be connectrainage  &  Od by DeitY.  

ort:  Provisionof a successfe  clear  transsed by clean wervice can be

ir for groundeservoir, whiund water taboad  leading  to

 

uster  is  enve electronic mmpus,  truck ining  centre building with welfare  ame

welfare  centreted by  the beOFC  communi

n  of  continuful master plsportation  rowide roads ae run within th

d water rechach will be usble  in the areo  the water 

 

visaged  to manufacturingparking  areaand  auditortesting centr

enities woulde and  local  sest available ication  netwo

ous  and  cleaan of an  indoute  to  all  pnd bus stopshe cluster for

arge: The  lowsed to collectea. There  is areservoir  fro

have  all  theg. The  facilitias,  warehousium  to  showre, tool room  include  a  clhopping &  cosustainable ork  and  in  li

ar  access  roaustrial clusteplots  within  have been pr public transp

west area  in t all the storma very aesthem  the main 

Page 5

e  amenities es  include a se,  administrwcase  the  clum, R&D centreubhouse, meommunity  ceand  self‐suffine with  the 

ads  and  tranr.   Great carethe  cluster.

provided alonport.  

the park has m water dischetic water charidge  road, w

50 

and good ration uster.  e and edical entre.  icient EMC 

sport e has     All g the 

been harge annel which 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 51 

   

collects water  from  various parts of  the  site  and  joins  the  reservoir.   This  is achieved by carefully planning the layout as per the natural contours of the site. 

 e) Sustainable& self‐sufficient servicesnetwork: The utilities have been planned to provide an 

energy efficient, sustainable and pragmatic network within the cluster.  The site is serviced by  three  substations  &  three  water  works  area  to  achieve  an  efficient  network.    Solar Streetlights  have  been  planned  along  the  roads  in  the  entire  campus  along  with underground water  supply  lines,  storm water drainage,  sewage network,  communication network, electricity distribution  lines.    Sewage Treatment Plants  (STPs)  at  three different locations have been planned within the cluster to optimise the sewage system.  

f) Flexibility:The planning of the Park has been kept flexible so as to be adaptive to the rapidly evolving  business  landscape.  The  Master  Plan  allows  programmed  or  functional  re‐arrangement  and  re‐distribution  of  plot  sizes,  infrastructure  network  and  open  space distribution  enabling  the  units  to  have  plots  of  variable  sizes with  a  provision  of  future expansion.    The  typical  plot  size  is  approximately  2000sqm,  but  the  design  offers  the flexibility to combine plots as per the needs of the manufacturer.  

g) Compliance: The Master Plan  also  complies with  the guidelines  issued by Department of Town  and  Country  Planning,  GoTNandthe Ministry  of  Environment,  Forests  and  Climate Change  (MEFCC), Government of  India  (GoI).Provisions of  the National Building Code and prudent engineering practices have been followed in preparing the Master Plan. The Master Plan  follows the zoning concept  for meeting the statutory norms of planning, to minimise the  impact of pollution,  if any, on  the  resident population  in and around  the Park and  to attain  the  economics  of  design  by  consolidating  scarce  and  costly  resources  for  shared access.

 

 

4.3.Final Masterplan  

The detailed master planalong with the entire architectural features is attached as Annexure 1 (Architecture Design Report).  

   

 

4.4. Project components: 

The cluster has been envisaged as a self‐sustainable and efficient manufacturing hub complete with all modern amenities and a green and  clean environment  conducive  for electronic manufacturing. The key components of the EMC are listed below:  

OUTLINE AREA CHART 

S. No. 

Particulars  UnitPlot Area 

Building Area 

% Area   % Area  

         sqm  sqm  Processing Non‐

Processing 

   TOTAL PLOT AREA (157.6 ACRES)  sqm 637852          

1  INDUSTRIAL PLOTS  ‐ Total 163 plots  sqm 385714     60.5    

SERVICES AREA: ESSENTIAL SERVICES ‐ Electric / water works / recharge water body & other services for servicing the industrial plots. 

sqm 12537  1250  2.0    

a  Electrical Network: Sub‐station‐1, 2 & 3.  sqm 8337  500.0 

b Plumbing Network ‐ STP, WTP, Pumpingsystem. 

sqm 4200  750.0    

3 ROADS: BASIC DEVELOPMENT ‐ Area under roads and truck handling parking area for connecting industrial plots. 

sqm 116232     18.2    

             

4 TRUCK HOLDING (PARKING) ‐Area under truck handling / parking area. 

sqm 21099     3.3    

5 COMMON AMENITIES: MANUFACTURING SUPPORT & WELFARE SERVICES 

sqm 37755  15500  2.5  3.4 

  Building‐1: Gatehouse  sqm 1573 750 0.2 

 Building‐2 : Support Services: Admin & Training Building  

sqm 5936  3500  0.9 

 Building‐3 : Manufacturing support building 

sqm 2964  2200  0.5 

  Building‐4: Employee hostel & mess  sqm 4097  3000  0.6 

  Building‐5: Clubhouse   sqm 4392  1500  0.7 

  Building‐6a, 6b & 6c: Worker welfare  sqm 2829  2550  0.4 

  Building‐7: Ware house  sqm 5746 1400 0.9 

  Building‐8: Medical centre  sqm 3025  600  0.5 

  Building‐9: Community Hall  sqm 3596  future  0.6 

  Building‐10: Shopping Complex  sqm 3596  future  0.6 

 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 54 

   

 GREEN AREA ‐Total area under landscaping / Greenery 

sqm 64515        10.1 

 

   TOTAL     637852  16750  86.5  13.5 

 

4.4.1 Industrial plots:  A  total of 163 plots have been planned  for  setting up of manufacturing units by  the SPV.   The typical  size of  the plots  is  approximately 2000sqm  and  they  can be  combined  to  set up  larger manufacturing facilities. The total saleable area under these plots is 385714sqm.  Each plot would be  connected  by  the  road  network  along with  all  the  services  like  electric  connection,  sewer connection,  central  STP,  treated  water  supply  &  storm  water  drainage.    Further,  each manufacturing  unit  can  use  the  common  amenities  being  provided  in  the  cluster.    The  entire campus is a secured gated campus. 

 4.4.2 Services area: Essential services 

 All modern services have been planned for the project. 

 a. Electrical network:   All  electrical  power  requirements,  communication,  security  systems  are  brought  under  this category. The maximum electrical demand  load of  the complex  is worked out as 30 MW. Each manufacturing unit of approximately 2000sqm size shall be provided with a 150 KW electric load supply.   TheTamil Nadu Electricity Board  (TNEB) will provide power at 110 KV, 3 Phase, 50 Hz connection.   This will be connected  to a Gas  Insulated Switchgear  (GIS) and  subsequently  to 3 outgoing power transformers of 10 MVA  (5x2 MVA) each.   From here onwards, a 33 kV supply line will be  taken  through  an underground  cable  (UGC)  to  the  three 33  kV/11  kV  substations. Power shall be received through a Ring Main Unit  (RMU) via metering at  the substation of  the complex. Each manufacturing unit will be supplied power through individual cable from the 11 kV substations as per the respective load required.  The detailed electrical description and the design calculations are mentioned in the Annexure 2: Electrical design report. 

 b. Plumbing network:   The campus has been planned as a ZERO‐DISCHARGE self‐sustainable campus. The campus shall provide uninterrupted treated water to all the manufacturing units and common amenities.  The campus  shall  receive water  from  the GoTN appointed agency as well as back‐up water  supply from the bore wells plannedwithin the cluster.   7200 KLD  is the total water requirement of the campus, which  is met  through 2400 KLD  fresh water & 4800 KLD STP water  recirculation.   The entire campus is divided into three zones with their own water treatment plant (WTP) and pump house for water supply.  The drainage network is very elaborate with separate sewer and storm 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 55 

   

water drainage connecting all the units. All three zones will have their  individual 1800 KLD STP units.  Thus,  a  total  of  5400  KLD  capacity  STP  shall  be  set  up.  Total  STP  water  generated  is 4800KLD & STP water utilised is 4800KLD. Thus, we achieve a ZERO discharge industrial park.  The detailed distribution description and design calculations are mentioned  in  the Annexure 3: Plumbing design report.  

4.4.3 Roads: Basic development  

Bitumen surface roads as per the Ministry of Road Transport & Highways (MoRTH) specifications with footpaths and green area have been planned for the entire campus.  A total of approximately 7 Km  length of roads shall be  laid, which shall consist of 30m wide road (350m) at the entrance; 18m wide  road  (1750m) as  the main  ridge  road; 15m wide  road  (400m) with  the central storm water channel & 13m wide road (4300m) servicing the plots.  All road sections have been carefully planned  to maximise  accessibility  and  provide  aesthetic  value  to  the  campus  by  incorporating water  channels,  footpaths,  street  lighting,  service  ducts &  greenery.    The  natural  slope  of  the original  land  has  been maintained  to  a  large  extent  in  designing  the  roads.    A  typical  section through the road is as follows:  

 

 

            Owing to the naturally sloping terrain, there shall be basic land development required for cutting & filling  the  land  in  order  to  develop  terraces  to  suit  the master  plan.    The  cost  of  basic  land development, which  includes  the  cutting  /  filling  of  land  to  establish  the  suitable  gradient  and terracing of the land has not been included in the detailed cost estimate as per the requirement of DeitY.  This  cost has been  factored  in  the  land  cost, which  is not  considered  for  the purpose of evaluation.     

4.4.4      Truck holding area:  

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 56 

   

Proper care has been  taken  to plan  the  truck holding areas  for  the parking of  trucks. An area of approximately  21100sqm  is  planned  as  a  bitumen  surface  for  this  purpose.    Worker  welfare buildings are also planned adjacent to the truck holding areas. 

 4.4.5 Common amenities:  

 Efficient and  functional  common  amenity buildings are proposed  to  facilitate  the manufacturing units as prescribed in the DeitY guidelines.  The detailed description & layout of all the buildings are depicted  in  the Annexure  1: Architecture Design  Report.  The  common  amenity  buildings  are  as follows:  

 Building‐1: Gatehouse:  Government regulatory services building:   The building shall be the entry point of the cluster campus and shall house the time office, security personnel and government support office.    It shall be a 2 floor building comprising of a signature gate signifying an  institutional entrance  to  the campus.    It  is planned on a 1573 sqm plot with a built up area of 750 sqm at an estimated cost of approximately Rs. 2.70 Crores.   Building‐2: Support services: Admin & Training building:  This building is the heart of the campus and showcases the cluster.  It is planned as an institutional building consisting of a grand reception area and a cluster administration office. There shall be a business  centre  with  a  200  seat  auditorium,  2  Nos.  of  30  seat  conference  rooms  with  video conference facility and an office space, which can be used by the manufacturers.  The building shall also  house  2  training  rooms  for  40  people  each  for  conducting  industry  specific  skill  training programs for the employees of the manufacturing companies. The maintenance office along with a store and IT / telecommunication hub shall also be planned in this building.  It is planned on a 5936 sqm plot with a built up area of 3500 sqm at an estimated cost of approximately Rs. 10.2 Crores.  Building‐3: Manufacturing support building:   This  building  shall  house  the  central  manufacturing  support  facilities  for  the  aid  of  the manufacturers.  It is a 2 floor building with space for testing / certification, tool room, CAD design, R&D centre as per  the needs of  the cluster.   Some basic  testing machines shall be placed  in  this building so that the manufacturers do not have to invest in setting up such cost intensive facilities in their units.   This building  is planned on a 2964 sqm plot with a built up area of 2200 sqm at an estimated cost of approximately Rs. 5.05 Crores.    Building‐4: Employee hostel& mess:  Welfare services:  This  is  a  facility provided  for  temporary  stay of employees  / guests within  the  cluster.    It has  a common dining area, multipurpose hall and gaming area along with accommodation for 103 guests consisting of 11 single rooms, 11 double rooms and 14 five‐bed dormitories. It is a 5 storey building 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 57 

   

planned on a 4097sqm plot with a built up area of 3000 sqm at an estimated cost of approximately Rs. 10.50 Crores.  Building‐5: Clubhouse: Welfare services:  This  is  the  recreational  building  planned  for  the  employees  of  the  cluster, which  consists  of  a restaurant, swimming pool, gaming area & multipurpose hall.  It is a 2 storey building planned on a 4392  sqm plot with a built up area of 1500  sqm at an estimated  cost of approximately Rs. 4.40 Crores.    Building‐6a, 6b & 6c: Worker welfare buildings (3 Nos.): Welfare services:   This building has been proposed at 3  locations within  the  campus  and houses  the basic welfare amenities for the workers in the cluster. Each building will have a convenience shop, ATM, creche, first aid centre, cafeteria and a worker orientation space.   There shall be 3 buildings of 850 sqm built‐up area each at 3 locations within the cluster at an estimated total cost of approximately Rs. 4.77 Crores.  Building‐7: Warehouse: Essential services:  A central warehouse has been planned  for the benefit of the manufacturers.    It  is a single storey prefab  shed building with  loading  / unloading dock planned on a 5746  sqm plot with 1400  sqm 

built‐up area at an estimated cost of approximately Rs. 3 Crores.  Building‐8: Medical Centre: Hospital & ESIC building:  A  basic  medical  centre  with  first  aid  and  preliminary  medical  facility,  emergency  ward  and chambers for doctors have been proposed.  It is a single storey building planned on a 3025 sqm plot 

with 600 sqm built up area at an estimated cost of approximately Rs. 2.30 Crores.  Building‐9: Community Hall building: Welfare services:  A 3596 sqm plot has been reserved for the development of a community hall building in future. It has been planned near the water reservoir so that it becomes a recreational area.  

Building‐10: Local Shopping Centre building: Welfare Services: 

 A 3596  sqm plot has been  reserved  for  the development of  a  local  shopping  centre building  in future.  It has been planned near the water reservoir so that it becomes a recreational area.     

4.4.6 Green Area 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 58 

   

 Green areas are  the  lifeline of any development and enable a healthy, clean environment within the cluster. The  location of  the green areas has been planned very strategically  so  that  they are easily accessible  from all parts of the cluster.   The site has two elevated points, which have been reserved  for natural  landscaped green areas to enable uninterrupted views of the entire campus. The main ridge road has a continuous green belt on either side along with other scattered green areas located in the campus.  

4.5. “GREEN” campus features: 

 The design  ideology of  the  cluster has been evolved with a  keen  thrust of  incorporating GREEN technologies. We plan to get a GREEN CERTIFICATION RATING for the project so that we can attract the best manufacturers in the industry.  

 The key features incorporated in the project are:  4.5.1. Site  selection &  planning:  The  entire  campus  has  been  planned  keeping  in  view  the 

natural contours of  the  land  so as  to be  least  invasive. The natural  slopes are used  for water drainage and a reservoir  is planned at the  lowest point to recharge groundwater. The natural features are retained as much as possible. Electrical distribution is planned so as to minimise the distribution losses.  

 4.5.2. Health & well‐being:A green campus  results  in happy, committed and efficient working 

professionals. The  central  ridge provides a peaceful,  calm and green getaway  from  the hectic  activity  in  the  industrial  plots.  The  ridge  has  all  the  common  amenities  and  is flanked by the two natural green high points providing beautiful vistas of the campus. The entire  campus  shall be  a  tobacco  free  campus. Noise  levels  shall be  kept  in  control by careful  planning  of  accessibility  and  transport  routes,  segregated  truck  handling  areas interspersed with green belts and trees. 

 4.5.3 Building planning & construction: The emphasis has been on sensitive building design & 

construction.  All  local  and  low  energy  consuming  materials  with  high  recycle  value content shall be used in the construction. Solar streetlights have been used in the campus to demonstrate the commitment to alternate renewable energy. The planning compliance with all national & international standards has been done in order to create a truly holistic manufacturing campus.   

 4.5.4 Recycle,  reuse &  recharge:  zero  discharge  campus:The  entire  campus  pledges  not  to 

discharge any waste water. Rather the entire waste water produced is processed through the  central  STP and  then  consumed entirely within  the  system,  thus, achieving a ZERO DISCHARGE  CAMPUS.  Total  STP  water  generated  is  4800KLD  &  STP  water  utilised  is 4800KLD.  

 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 59 

   

4.5.5 Building  operation  &  maintenance:Since  Green  buildings  have  energy  efficient  and effective  building  solutions,  the  operation  and maintenance  is  both  cost  effective  and simple. All systems are self‐sustainable with a very low payback period. 

 4.5.6 Benefits of green buildings:The project will reap both tangible and intangible benefits by 

going for a “green” campus, such as:  

Reduced operating cost  Enhanced productivity of occupants  Green Corporate image  Demonstration of the commitment to Green in order to attract international investment into the campus. 

   

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 60 

   

 

CHAPTER 5  

SUPPORT INFRASTRUCTURE  

The proposed Electronics Manufacturing Cluster (EMC) shall have the most advanced electrical, plumbing (water supply, drainage, sewerage), security & communications network in order to facilitate a hassle free manufacturing campus. It is envisaged that all the  infrastructure services shall be laid below ground along with the road network so that they are not visible and also easily serviceable since they do not cross any private territory.  A schematic layout of the services is as follows:  

 

 

5.1.Water Requirement: 

The water  requirement  for  the campus has been worked out considering  that 5L/sqm  (assuming 50 litres per person consumption & 200 people shall be employed on a 2000 sqm plot) domestic water consumption & 10L/sqm for the process water requirement. The total  industrial requirement for the manufacturing units is estimated to be 5786KLD, out of which 3729KLD will besupplied by STP and the balance 2057KLD shall be fresh water.  The  total  domestic  requirement  of water  for  Common  Amenities,  Roads,  Park&  External  Areas  is estimated as 1350KLD, out of which 1030KLD will be supplied by  the Sewage Treatment Plant  (STP) and balance 320KLD shall be fresh water.  The plumbing design report is attached as Annexure 3. The  source  of  fresh water will  be  from  the New  Tiruppur  Area  Development  Corporation  Limited (NTADCL) where adequate water  is available for which action has been  initiated by AEEPPL based on the MoU signed between AIPL (the Chief Promoter) and GoTN for the development of industrial park at Annur, Coimbatore within which the EMC is proposed to be established.  A copy of MoU is attached as Annexure 4. A copy of the communication received from NTADCL confirming the supply of water for 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 61 

   

the  industrial  park, which  houses  the  EMC  is  attached  as  Annexure  5  (a).    In  the meantime,  the President,  KuppanurPanchayat  (which  is  the  authority  concerned)  has  issued  a  No  Objection Certificate (NOC)for drawing water from the existing and new bore wells proposed within the EMC, a copy of which is shown as Annexure 5 (b). 

 

 

 

5.2. Electricity Requirement: 

The total electrical power requirement for the EMC  is estimated as 30 MW, which  is proposed to be met by establishing 3 substations each consisting of 2 Nos. of 5MVA transformers each. Each unit shall be provided with a 150 kW electric  load supply. TheTamil Nadu Electricity Board  (TNEB) will provide power at 110 kV, 3 Phase, 50 Hz connection. The power from the  grid will be at 110 kV, which will be connected to a Gas Insulated Switchgear (GIS) and  subsequently to 3 outgoing power transformers of 10 MVA (5x2 MVA) each. From here onwards 33 kV supply line will be taken through an underground cable  (UGC)  to 33  kV/11  kV 3 Nos.  substations.  Supply  shall be  received  through  a Ring Main Unit (R.M.U) via metering at the substation of the EMC.  From 11 kV substations each unit will be supplied with individual cable as per the load required. 

The  total power  required  for common area  (i.e. non‐processing area)  is 1605 kW demand, which  is shown  in the table below.  The power requirement for processing area  is shown  in the report on the electrical system design, which is attached as Annexure 2.   

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 62 

   

ITEM Substation1 

(Connected load in kW) 

Substation 2 (Connected load in 

kW) 

Substation 3 (Connected load in 

kW) 

Transformers   2 No 5 MVA 2 No 5 MVA   2 No 5 MVA

Welfare Building (6a)(Approximately)  70 70 70

Gatehouse (Approximately)  50

Administrative Building (Approximately)  237    

Hostel (Approximately)  168    

Ware House (Approximately)  80

Medical Centre (Approximately)  60    

Plumbing (Approximately)  200 200 200

Community Hall (Approximately)    100  

Shopping Complex (Approximately)    100  

 Common Area (Approximately)  865 470 270

Total for Common Areas (non – processing area)  1595

 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 63 

   

 

Based on the MoU signed between AIPL (the Chief Promoter) and GoTN for the development of industrial park at Annur, Coimbatore within which the EMC is proposed to be established, the Tamil Nadu Electricity Board  (TNEB)  has  been  requested  for  supplying  the  required  power  for  the  EMC.    The matter  is  being processed  by  TNEB,  GoTN.    The  copy  of  the  application  submitted  to  TNEB  in  this  regard  isattached herewith as Annexures 6.  

5.3: Security & Communications Network  

Security considerations are paramount in the campus. The entire campus  is a secured, gated campus to ensure the security of every  individual. All areas shall be adequately  lit and the access points duly manned by security personnel. Smoke / heat detection system is provided in all buildings.  Communication  systems  are  the  backbone  of  any  manufacturing  cluster.  All  the  leading telecommunication brands have expressed  their  interest  in  setting up  their network. As part of our infrastructure we shall be  laying an Optic Fibre Communication network  in the entire campus. Kindly refer to Annexure 2: Electric Design report for the detailed report on the electric network. 

 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 64 

   

CHAPTER 6  

ENVIRONMENTAL IMPACT ASSESSMENT  

6.1 Introduction  

The campus  is proposed  to be a sustainable and “green” campus with all state‐of‐art  facilities.   The environmental  impact assessment  (EIA)  is extremely  important  to minimise  the  impact of  industrial development on the environment.  Apart from being a mandatory approval required for the EMC, the EIA will help in developing a sustainable cluster.  The summary of the project is as per the table below:  

 Proposed project  Greenfield Electronic Manufacturing Cluster 

   

Category  8(b), “B2”   

Project location  Kuppanur village   Survey No. 70, 71, 72, 207, 208, 209, 210/1A, 210/1B, 210/2, 239, 240, 

241, 242, 243, 244, 313      Akkaraisengapalli village   Survey No. 556, 558, 559, 560, 561, 562, 563, 564, 565/2, 567/3      Vadkalur village   Survey No. 304, 313/2, 314   AnnurTaluk, Coimbatore district, Tamil Nadu   

Total plot area  Land area:‐ 63.79 Ha / 157.6 Acre

   

Total built‐up area  21,169 sq. M 

   

Environmental setting  Site co‐ordinates 

    Latitude  Latitude 

    11o19.087’N  77o3.671’N 

    11o18.713’N 77o3.781’N 

    11o18.632’N  77o4.359’N 

    11o18.214’N  77o4.875’N 

    11o18.131’N 77o5.113’N 

    11o18.178’N  77o5.601’N 

    11o16.975’N  77o5.671’N 

       

Elevation  394 m AMSL

  

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 65 

   

   River     

   R.Bhavani    5.21 Km, West 

   Waterbodies     

   Annur Lake    5.0 Km, SE 

   Vadkalur Lake    1.8 Km, SE 

   MasakkaananKuttai    3.0 Km, SE 

   Reservoir     

   BhavaniSagar reservoir    9.6 Km, NNW 

   Reserve Forests     

   Odunthurai R.F    9.0 Km, WNW 

   MedurPethikuttai Forest    5.4 Km, NNW 

 

   Mountain       Mount Sirumugai 2.1 Km, North   Mount Othimalai   6.13 Km, North

   Densely populated area        Annur    5.66 Km, SSE           Nearest major habitation   Mannur ‐ 0.2 Km, West.            Proposed facilities  Electronic Manufacturing Cluster     Total occupancy  6379 Persons (Including visitors)     Parking details  21,099 Sqr. Mtrs.      Water requirement  Total water requirement    72,00 KLD 

   Total fresh water requirement   24,00 KLD   Source   of   fresh   water:   New   Tiruppur  Area   Development    Corporation Limited (NTADCL) and bore well / tube well     

   Treated water from STP – 48,00 KLD    

 Water supply Source New Tiruppur Area Development Corporation Limited& bore well /  tube well 

     Sanitation details  Proposed sewage treatment plant (STP) capacity of 54,00 KLD.     

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 66 

   

Solid‐waste management  The  solid      wastes  will  be  collected      and      segregated.  Thebiodegradable&non‐biodegradable waste will be given to authorized recyclers. 

    Power requirement  Power demand: 30 MW

  Source:  TANGEDCO  will be supplying the power through the nearest TNEB substation for which the MoU has been signed with GoTN 

      Emergency Back‐up  DG Sets ‐ Used for Common areas, External lighting and Lifts.   Fuel Requirement: Ultrapure low sulphur content diesel 

  Back‐up:

 DG Set 2 Nos. Of 500 kVA; 2 Nos. of 200 kVA; 3 Nos. of 100 kVA and 1 No. of 82.5 kVA.

  LS‐Diesel‐ 100 Litres/Hr

  Individual lessee will be managing their power back up facility based upon their requirements  

 Air Pollution/Noisegeneration Sources 

DG  Sets  will  be  provided  with  stack  height  of  3m  above  thebuilding height. Also provided with suitable acoustic enclosurestominimize noise.  

      Total investment of the project/activity 

Estimated  total  project  cost  for  infrastructure  development  under  thisproject is Rs. 196/‐ Crores  

  Funds allocated for EMP    Capital cost: Rs. 195 Lakhs  Recurring cost: Rs. 56.5 Lakhs/Annum    Name of the Environmental Consultant involved 

M/s. VIMTA LABS LIMITED  Branch office:  No. 8 – Azad Road  R. S. Puram,  Coimbatore – 641002

  Regd. office:  142, IDA, Phase‐II,  Cherlapally, Hyderabad‐500 051    QCI/NABET Accredited  EIA Consultancy Organization,   NABL     Accredited,  ISO  17025   Certified   and   MoEF   Recognized     Laboratory           

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 67 

   

 

 

LANDUSE SPLIT‐UP  

  Sl. No. 

 Land Use 

 Area 

(in Sqr.Mtr)

 Area (ha)  Area (%) Usage Type        

     

  1    Industrial Plots    385714 38.57 60.5 Processing area 

  2    Services Area    12536    1.25  2  Processing area 

  3    Roads    116232    11.62  18.2  Processing area 

  4    Parking Area    21099    2.11  3.3  Processing area 

 5 

 Common amenities    37755    3.78  5.9 

Processing area (2.5) + Non processing area (3.4) 

                  

  6    Greenbelt    64516 6.45 10.1 Non‐processing area

      Total    637852 63.79 100

  Kuppanur Village             SF.No. 70, 71, 72, 207, 208, 209, 210/1A, 210/1B, 210/2, 239, 240, 241, 242, 243, 244, 313 

  Akkaraisengapalli village            SF.No. 556, 558, 559, 560, 561, 562, 563, 564, 565/2, 567/3

  Vadkalur Village             SF.No. 304, 313/2, 314         

  AnnurTaluk, Coimbatore district, Tamil Nadu     

  

I. Water and wastewater management   

The total water required for the project  is 7,200 KLD. The fresh water requirement of (2,400 KLD) will be met from New Tiruppur Area Development Corporation Limited / Bore well and 4,800 KLD from STP as treated water.  

 The  total  wastewater  generation  of  the  area  development  will  be  about  5,323  KLD.  The generated wastewater will be treated in the STP (90% efficiency) of 5400 KLD and the treated wastewater will be utilized for process, domestic requirement and in common amenities  

 Surface  run‐off  collected  from  the  terrace  floor  run‐off  will  be  diverted  to  the  rainwater recharging structures.   

II. Greenbelt / landscaping  

The  project  will  be  developed  with  6.45  ha  green  cover.  In  the  upcoming  future developments more green belt area will be developed covering 35% of the total area. 

 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 68 

   

III. Solid waste management  

The  total waste  generated  from  the  entire  project  amounts  to  around  0.32  TPD. Out  of which biodegradable will be about 0.19 TPD (i.e. 60%) and non‐biodegradable will be about 0.13 TPD (i.e. 40%). The solid wastes will be collected and segregated. The biodegradable & non‐biodegradable waste will be given to authorized recyclers. STP sludge generated  from the STP will be used as manure for garden. 

 SOLID WASTE GENERATION DETAILS 

 

Sl.  No. 

Source No. of Persons 

Per capita Considered (in TPD) 

Total Solid Waste (TPD) 

1  General Garbage       

  Industrial Plots  6379  0.05  0.32 

  Total Garbage       

2  STP sludge  ‐‐‐  ‐‐‐  0.88 

  

SOLID WASTE MANAGEMENT  

Sl. No. 

Description of waste 

Quantity

Mode ofCollection 

Mode of Disposal Organic (60%) 

Inorganic (40%) 

1  General Garbage  0.19 TPD Manual Authorized waste collectors        

0.13 TPD  Manual          

2  STP sludge    0.88  Manual  On own land for Gardening

  IV. Fire safety measures adopted  

 Firefighting  system  to  the  Industrial plots  is designed based on  the  recommendations of NBC 2005. Following safety measures are envisaged.  

 o An exclusive UG Sump at the ground level & OHT on the stair case core of each block at 

the terrace level will be adopted.   

o An electrical driven fire pump and one diesel pump shall be provided.   

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 69 

   

o One no. of Sprinkler pump exclusively for sprinkler system.   

o One no. of wet riser will be provided.   

o FHC is envisaged with hydrant valve and hose reel at each staircase landing level.   

o Separate pump riser & distribution network is proposed for sprinkler system.   

o Portable fire extinguishers are proposed to be placed at strategic locations.   

o Fire brigade inlet connection for external pumping arrangement is envisaged   

o A yard hydrant of building peripheral length is provided   

o Installation control valve is envisaged for sprinkler system   

o Automatic sprinkler system is envisaged for entire building  

The above safety requirements are same for all the blocks  6.2 Indicative environmental & social impact  6.2.1  Environmental  impact:  The  environmental  impacts  due  to  the  development  of  the  EMC  are  pre‐dominantly  likely  to be  in  term of air, water and noise pollution. However no major  impact  is expected during  construction  and  operational  stage.  The  operating  units  will  have  to  obtain  pollution  control clearance  from  state  authorities  at  an  individual  level  and  adhere  to  the  norms  laid  down  by  the authorities.  Necessary  control measures will  be  undertaken  at  the  design  stage  to meet  the  statutory requirements and towards minimizing environmental impacts. 

 6.2.2 Air quality during Construction: Cutting and levelling activity would be required for providing roads, sewage network, storm water system, administrative buildings for proposed project. The potential source of air quality  impact arising  from  the establishment/construction of  the proposed project  is  fugitive dust generation. The dust, measurable as Particulate Matter (PM<2.5μ, PM 10μ), Sulphur dioxide (SO2) oxides of  nitrogen  (NOx),  would  be  generated  as  a  result  of  construction  activities.  During  construction,  the existing  houses  nearby  may  be  subjected  to  the  potential  dust  impacts.  The  potential  dust  sources associated with the constructional activities are  loading and unloading of the materials, top soil removal, vehicular movement over unpaved roads, and wind erosion, etc. The possible constructional activities that contribute to the environmental impacts broadly given below:  

 a) Dust Generation during leveling of earth  b) Dust generation due to the movement of vehicles on unpaved roads  c) Emission of pollutants from vehicular exhaust  d) Unloading of raw materials and removal of unwanted waste material  e) Accumulation of excavated earth material 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 70 

   

 6.2.3 Air quality mitigation measures: For the proposed development, levelling and grading will be carried 

out; where ever possible  the natural elevations will be maintained and not be disturbed. Levelling activity will  be  carried  out  for  providing  roads,  sewage network,  storm water  system,  and  places required for providing buildings for administrative, production/manufacturing plant and other utility erections. According to the engineering assessment; most of the excavated material shall be reused within the proposed development. Most of the construction dust will be generated by the movement of carrying vehicles on unpaved roads. Unloading and  loading of constructional materials shall also act as a potential source for dust nuisance. Given the implementation of proper control measures for dust suppression, no adverse  impacts are expected. The control measures proposed to be taken up are given below:‐ 

 a) Water  sprinkling  on main  haul  roads  in  the  proposed  development  will  be  done,  this 

activity will be carried out at least twice a day, if need arises frequency will be increased on windy days,  in this way around 50% reduction on the dust contribution from the exposed surface will be achieved.  

b) The duration of stockpiling will be as short as possible as most of the material will be used as backfill material for the open cut trenches for road development.  

c) Temporary tin sheets of sufficient height (3m) will be erected around the proposed site for the development of as barrier for dust control.  

d) Tree plantations around the boundary will be initiated at the early stages by plantation of 2 to 3 years old samplings using drip irrigation so that the area will be moist for most part of the day.  

e) All  the  vehicles  carrying  raw  materials  will  be  covered  with  tarpaulin  /  plastic  sheet, unloading and loading activity will be stopped during windy period.  

f) To reduce the dust movement from civil construction site to the neighborhood the external part of the building will be covered by plastic sheets. 

g) During  Operation  DG  set  stacks  and  other  process  emissions  are  passed  through appropriated  air  pollution  control  units/treatment  systems  and  vented  through  stack meeting the TNSPCB standards 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 71 

   

6.2.4 Water quality mitigation measures: During the development necessary precautions will be taken, so that the runoff water from the proposed site gets collected to working pit and if any over flow is, will be  diverted  to  nearby  greenbelt  /  plantation  area.  At  the  time  of  construction  in  the  proposed development,  all  the  equipments  washed  water  will  be  diverted  to  working  pit  to  arrest  the suspended  solids  if  any  and  the  settled water will be  reused  for  constructional purposes,  and  for sprinkling on roads to control the dust emission, etc. The waste generated from the proposed project site work  , will be segregated  like used oil,  lubricants, etc and disposed to authorized recyclers the waste  like soiled cotton, paper, etc will be disposed to municipal bins or sold out to the authorized agencies. The domestic wastewater generated from temporary toilets used by the work force will be treated through sewage treatment plant and reused. Therefore,  impact on water qualitydue to the proposed development would be insignificant. 

 6.2.5 Noise mitigation measures: Noise generating equipment will be used during day  time during brief 

period of  its  requirement. Proper enclosures will be used  for reduction  in noise  levels, where ever possible  the noise generation equipment will be kept away  from human habitation. Temporary tin sheets of sufficient height will be erected around the noise generating activity or all around the area of construction as a barrier for noise travelling outside construction area. Therefore, impact of noise on environment would be considerably  insignificant. All vehicles entering  the site would adhere to proposed  speed  limits  and  not  blow  horns  unless  absolutely  necessary.  Personal  protective equipment  like  ear muffs  helmets  covering  ears  will  be  provided  to  the  workers  and  it  will  be ensured that the workers wear them regularly.  

 6.2.6  Solid waste mitigation measures:  The  solid  waste  generated  during  constructional  period  being 

predominantly  inert  in nature, construction and demolition waste does not create any chemical or biochemical pollution. However maximum effort would be made to reduce, reuse and recycle them. Most of the solid waste material will be used for filing/ levelling of low‐lying areas. All attempts will be made to stick to the following measures:‐ 

 a) All construction waste shall be stored within the proposed site  itself. A proper screen will be 

provided so that the waste does not get scattered.  b) Attempts will be made to keep the waste segregated into different heaps as far as possible so 

that their further gradation and reuse is facilitated.  c) Materials, which can be reused for purpose of construction, leveling, making roads/ pavement 

will also be kept in separate heaps from those which are to be sold or land filled.  d) The  local body or a private company may be arranged to provide appropriate number of skip 

containers/ trolleys on hire.   

The use of  the construction material basically depends on  their separation and conditions of  the separated material. A majority of these materials are durable and therefore, have a high potential for  reuse.  It would, however, be desirable  to have quality  standards  for  the  recycled materials. Construction waste can be used in the following manner:  a) Reuse  of  bricks,  tiles,  stone  slabs,  timber,  piping  railings  etc.  to  the  extent  possible  and 

depending upon their conditions. 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 72 

   

b) Sale/ auction of materials which cannot be used at the proposed due to design constraint. c) Plastics, broken glass,  scrap metal, used cement bags; etc can be  sold out  to  the authorized 

agencies.  d) Rubble/ brick bats can be used for building activity, such as leveling, under coat of lanes where 

the traffic does not constitute heavy moving loads.  e)  Larger unusable pieces can be sent for filing up low lying areas.  f)  Fine material such as sand, dust, etc can be used as cover material  g) The unearthed soil can be used for leveling as well as for lawn development  h) The broken pieces of  the  flooring material can be used  for  leveling  in  the building or can be 

disposed off  i) The unused or remaining paints/varnishes/wood can either be reused or can be disposed off to 

the authorized agencies.  6.2.7 Ecological aspects: No major vegetation  is present and hence there will not be any negative  impact 

on  the  existing  plantation. However,  the  proponent  is  going  for  plantation  along  the  boundary during  construction activity. A  comprehensive green belt programme will  improve  the ecological condition of the region. 

 6.2.8 Site security: Adequate security arrangement would be made to ensure that the local inhabitants and 

the stray cattle are not exposed to the potential hazards of construction activities.  6.2.9 E‐waste disposal: E waste would be disposed off through a third party authorised vendor. Provision 

for storage of e waste may be made in the warehouse.   6.2.10  STP:  Common  Sewage  Treatment  Plants  (STP)  has  been  conceptualized  and  recommended  for 

effective treatment and disposal of wastes water from the proposed development.   6.2.11 Social impact: The proposed area is devoid of any major habitation. Despite that there will positive 

impacts on the socio – economic status of the surrounding areas  

a) More employment opportunities will be generated  b) Physical infrastructure development such as improvement to roads, UGD lines, street lights etc will take place  

 6.2.11 Environmental clearance: A detailed EIA has been prepared by expert consultants and submitted to 

the authorities for clearance. The application/acknowledgement from the authorities is attached as Annexure 7. 

    

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 73 

   

6.3. Conclusion  

The  establishment  of  the  Electronic  Manufacturing  Cluster  by  M/s.  ADD‐ELCINAElectronics  Park Private  Limited  at  Kuppanur,  Akkaraisengappali&Vadkalurvillages,  Annurtaluk,  Coimbatore  district Tamil Nadu,  is best suited with the kind of climate. The project would cater to the people working  in this area.  

6.3.1 Ground water point of view The project  consumes about 2400 KLD of  fresh water  in a day which will be  sourced  from New Tiruppur Area Development Corporation Limited (NTADCL)& bore well. The generated sewage from the  project  will  be  treated  and  used  for  green  belt  maintenance.  Efficient  recharge  system replenishes the depleted ground water. Hence, there won’t be any impact on ground water quality / quantity. 

 6.3.2 Soil quality point of view  

The soil analysis was already carried out, and was found to be good. There are no chances of soil contamination and no discharge of wastewater  from unit operations which may contaminate the ground water table. 

 6.3.3 Air quality point of view  

Air emissions will be only from DG Sets, for which stacks are provided with a height of 3m above building height for all DG Sets. Added to this, the fuel used is Ultrapure low sulphur content diesel and thus the emissions will be lowest. 

 6.3.4 Noise quality point of view  

The generation of noise from project is negligible, as the only noise generating equipment are the DG Sets which comes with an inbuilt acoustic enclosure which has noise levels <75 dB. 

 6.3.5 Floral & Faunal diversity point of view  

No kind of Floral & Faunal destruction is envisaged for the current project. As a matter of fact, the project  is going to add further to the existing situation as  landscape development  is proposed for about 6.45 Ha. More area will be developed for green belt during future development. 

 6.3.6 Hazardous waste point of view  

The project will generate any hazardous waste in the form of e‐waste. However, the authorization of  the  Tamil  Nadu  Pollution  Control  Board  will  be  obtained  as  per  the  norms  of  the  E‐waste management and Hazardous Waste Management Rules. The waste oil from the DG Sets will not be discarded in any open area. Hence there is no threat to the soil and the neighbouring area due to waste oil. 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 74 

   

 Final conclusion  The  project  would  development  have  very  less  negative  impact  on  the  surrounding  area  or  on  the environment. The project would indeed help the economy and socio economic condition of the area and it is very highly recommended for the establishment of the project to favour exports and imports. The project would not have any negative impact on the soil, water, air or noise environment. 

     

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 75 

   

 

CHAPTER 7 

MARKETING STRATEGY  7.1 Marketing efforts:  

The objective of the special purpose vehicle, ADD‐ELCINA Electronics Park Private Limited (AEEPPL)  is to promote  sustainable electronics manufacturing, gainfully utilize  the human  resources  to  improve the standard of  living and quality of  life and conserve the environment of Coimbatore  in general and Annur in particular, thereby ensuring a balanced industrial development.  Amongst  other  strategic  players,  M/s.  Electronics  Association  of  India  (ELCINA)  is  one  of  the partnersand  the  key  driver  behind  the  project.Thespecial  purpose  vehicle  (SPV) will  utilize  ELCINA branding and will be promoted by ELCINA on national and international forums. ELCINA networks with national and international  institutions and business promotion bodies to create awareness about this cluster and motivating investors to invest in the cluster.   M/s.  Tea  Stall  Studio,  Gurgaonhas  been  appointed  as  the  branding  and  advertising  agency  to strategically place the proposed EMC in the digital market orbit of electronics. They have created and designed the web page  for EMC, which can be reached at www.prime641.com.  In this web site, one can  view  the  details  of  EMC,  the  facilities  being  offered, master  plan,  industrial  plots  available  for setting up electronic manufacturing units besides its location, connectivity and other details by clicking on this URL address.   Prospective  investors / manufacturers can send their requirement of  industrial space to the email address mentioned therein.  Besides EMC,information of other clusters and major components within the proposed industrial park has been mentioned in this web page. The brand logo for the cluster is as shown below:‐ 

 

  Promotional activities are also being carried out  through some of  the other  top elite associations of electronics of  India which  include  India Electronic Semiconductor Association  (IESA), Manufacturer’s Association  of  Information  Technology  (MAIT)  and  Bangalore  Chamber  of  Industry  and  Commerce (BCIC)  through  its  members.    Further,  correspondence  and  discussions  with  some  of  the  major prospective players are under way, which include M/s. Alstom Transport, France, M/s. Blue Star India Ltd.,  Chennai,  M/s.  Assetz  Property  Group,  Bengaluru  &  M/s.  Maxworth  Consumer  Products, Hyderabad to name a few.  

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 76 

   

Discussions are also under way with M/s. Ernst & Young (E&Y), the global market facilitators  for the promotion & propagation of our EMC. E&Y  through  their dedicated  international desks  are able  to connect with the strategic investors in the international platforms.  The SPV is participating in most of the Electronics exhibition shows in the country and in international level through ELCINA. 

  7.2 Marketing strategy:  

The strategy–from conceptualization to implementation    

a. Macro Mapping of EMC and SWOT analysis of the location  b. Market Assessment and  Demand Analysis for various electronic products locally & globally c. Marketing  Strategy&  Development  of  Collaterals  (including  Website,  Flash  Presentation, 

Brochure & Annexure, Exhibition Display Graphics and Site Displays Press Kit) d. Media and Public Relations e. Expo, Road‐shows and other Events f. Sales Process Management  g. Customer Relationship Management  

 As a first step, AEEPPL commenced its informal marketing of the EMC upon receipt of the “In‐principle” approval for the project from DeitY.  While aggressive marketing activityhas been envisaged only after the final approvalof the EMC by DeitY; participation of AEEPPL at several conferences and exhibitions hasevoked tremendous interest among the industry players to associate in the project.  Based on the understanding of the various key products of electronics and analyzing the requirements of  the potential  investors and other  tenants and users, AEEPPL has evolved a marketing  strategy  to achieve the desired sales and objectives.   Principally, the marketing strategy has been categorized as follows:  

a. Identification of targeted industries b. Collection of primary database of identified industries c. Brand Establishment d. Positioning of product e. Right pricing f. Marketing collaterals g. Creation of serene, sustainable and industrial atmosphere  

A  great  thrust  has  been  put  on  branding  the  company,  for which  the  following  actions  have  been identified:  

a. A website has been developed. b. The main brand logo and sub‐logo are finalized. 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 77 

   

c. E‐mailers and flyers have been prepared. d. A comprehensive brochure for the EMC has been finalized. e. Power Point Presentation (PPT) for national and international investors is under way. f. Aggressive PR exerciseis being planned. 

 7.3 Industrial park advantage:‐ 

 A mega industrial park, which encompasses the proposed EMC, is being developed in an area of about 1500 acres, which comprises of various other  industrial clusters  for MSME, auto components, textile, food processing and pharmaceuticals amongst others.   The park would also comprise of a knowledge city, centre for skill development, golf course, social and recreational infrastructure, shopping complex, hotels etc.Therefore, the units coming up in the EMC may be able to utilize and leverage the facilities, infrastructure  and  advantage of  the  park  and other  clusters  besides  appreciation of  land  value  and greater standard of living. As such, the cluster mix of various verticals for the industrial park has been aimed to systematically include various products and services which would enhance the concept values and achieve optimum synergies.  The following segments have been identified for the proposed industrial park:  

a. Separate clusters for MSME, food processing, textile, health etc. b. Knowledge city c. Biotech/Life Sciences d. Convention centre e. Logistics and warehouses f. Mall/Multiplex, Value retail and 3/4/5 Star Hotels g. Social infrastructure viz. housing, community centre etc. h. Recreational facilities, Golf course etc. 

 This development mix will generate good demand for housing and other social infrastructure, which is being developed in the proposed industrial park. This perfect blend of the development mix also avoids risks of major  failure  in  the event of poor  response  to any  segment and  keeps on  the possibility of modifying the plan and marketing strategy to a large extent.  A significant boost to the proposed EMC is quite obvious with the development of industrial park.  

7.4 Marketing initiatives:  

With a view to promoting the EMC and attracting  industries  for setting up their manufacturing units, various  marketing  plans  have  been  initiated  through  various  platforms  &  media,  which  include participation at B2B meets, seminars, setting up stalls  in various exhibitions, approaching association bodies  since  June’15  onwards.Some  of  the  platforms/  forums  in  which  the  proposed  EMC  was presented in association with ELCINA are: 

   

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 78 

   

1. Electronics Show at Shanghai (Kunshan), China: ‐   a) A  large  electronics  show  was  conducted  at  Kunshanin  Shanghai,  China  from  30.06.15  to 

03.07.15 organised by TEEMA of Taiwan in which the proposed EMC was exhibited.  b) The  show  was  represented  by  ELCINA  wherein  several  Taiwanese  and  Chinese  electronic 

manufacturerswere met and persuaded  to set up  their electronic manufacturing units  in  the proposed EMC at Coimbatore.  

 2. Strategic Electronics Summit (SES), Bengaluru: ‐   

a) The  6th  Strategic  Electronic  Summit  (SES),  which  was  a  two  day  (30.07.15  &  31.07.15) conference and exhibition  for  strategic electronic  sector of  Indian Defence was organized by ELCINA and supported by Department of Electronics & IT (DeitY), DRDO & BSF.  

b) A  stall  was  set  up  at  this  event  showcasing  the  features  of  EMC,  its  location  and  other advantages of establishing units within it.  Brochuresand fliers were distributed.  

c) Several  prospective  investors  were  approached  with  a  view  to  wooing  prospective manufacturers to set up units within the EMC.  

d) Such prospective investors are being contacted by way of business letters, telephone calls and meeting them personally.  Notable are BDO i2i, Bengaluru, SLN Technologies, Bengaluru etc. 

 3. Global Investors Meet (GIM) 2015, Tamil Nadu  

a) This was a two day mega global event organized by the Government of Tamil Nadu attended by about 5000 delegates including 1000 from abroad on 10.09.15 & 11.09.15, wherein the state of Tamil Nadu was showcased as a top investment destination. 

b) At this event, several B2B meetingswere held with prospective strategic investors and financial institutions.    Some  of  them  are:M/s.  Ampree  Compressors  Private  Limited,  Coimbatore, Citibank,  Attivo,  Kolkata,  SunEdison  Energy  India  Private  Limited,  Stellar  Energy,  Welspun Renewable  Energy  Private  Limited,  Canada  Development  Council&  Australian  Trade Commission. 

 4. IT Asia, Hyderabad  

a) This  conference  cumexhibition was  heldfrom  24.09.15  to  26.09.15, which was  organized  by Manufacturers Association for Information Technology (MAIT). 

b) A  stall  to promote  the  EMC was  set up  at  the  event  and  brochures were  presented  to  the visitors.  

c) Had  detailed  discussions  with MAIT  and  discussed  ways  and means  to  promote  the  EMC through its members.   

d) Some of  the  companies contacted are DELL, HP, Lenovo, Acer, RDP and other medium  scale manufacturers.   Many of  them have evinced  to  look at  the EMC as next option during  their expansion stage.  

 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 79 

   

As  part  of  the marketing  efforts,  several  countries  through  its  embassies,  consulates  and  industrial associations have been approached to disseminate  information of the proposed EMC to  its electronic manufacturers.   An  exhaustive/detailed  questionnaire/enquiry  form  has  been  prepared  and  being  forwarded  to  the prospective investors to understand their capabilities and requirement to set up their units in the EMC. 

   

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 80 

   

 

CHAPTER 8  

MANAGEMENT ARRANGEMENTS  

8.1 Development of the project  

The EMC project is a partnership between ADD Industrial Park (Tamil Nadu) Limited (AIPL), Electronics Industries Association of  India  (ELCINA), Om Metals  Infraprojects Limited  (OMIL) and Adhunik Power Transmission Limited  (APTL).   With AIPL as  the Chief Promoter, an SPV has been  incorporated  in  the name of ADD‐ELCINA Electronics Park Private  Limited  (AEEPPL) exclusively  for  the development  and management of the proposed EMC.  More members will be inducted into the SPV as per the guidelines of DeitY  in  due  course  of  time.    The  project  is  envisaged  to  be  completed  under  one  single  phase comprising of the stages mentioned below upon the receipt of ‘in‐principle’ approval from DeitY, which has been obtained in May 2015: 

 a) Submission of final application and DPR to DeitY and receipt of final approval. b) Pre‐construction stage  

i. Finalization of architectural and engineering designs  ii. Floating tenders and finalization of contracts iii. Preparation of detailed working drawings iv. Mobilization and start of construction 

c) Construction stage i. External road development ii. Boundary wall and gate‐house iii. Construction of internal roads and common amenities iv. Construction of buildings and other infrastructure 

d) Post construction stage  e) Operation and Maintenance (O&M) stage 

   

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 81 

   

    PROJECT DEVELOPMENT STAGES 

 

Submission of final 

application / DPR and receipt of 

final approval 

Pre‐construction  Construction  Post Construction  O&M 

Duration   2‐3 months  3 months   18 ‐ 21 months    4 months  Upon commissioning and continuous  

Funding   SPV (AEEPPL)  SPV (AEEPPL) SPV (AEEPPL) +  DeitY+ Members+ +Bank 

SPV (AEEPPL) +DeitY+ Members+ Bank 

Generated by SPV (AEEPPL) + Members contribution 

KRAs  to proceed to next stage 

Final Approval of DeitY 

Sign off with DeitY. Finalisation ofengineering designs, reports and contractors.  

Construction and monitoring by SPV 

Completion of infrastructure development and commencement of operation of units 

  

  8.2 Management structure:   

For the efficient  implementation and running of the EMC as per the guidelines of DeitY, the roles and responsibilities of different entities are to be drawn up for which a management structure has to  be  in  place.    Such  a  management  structure  needs  to  give  due  consideration  to  the interests/concerns of all  the stakeholders  for  the smooth  implementation and sustenance of  the project.    As  a  starting  point  in  defining  the  project  structure,  the  Chief  Promoter  and  other members of the SPV would initiate the preparation and submission of application and final DPR and during the process of evaluation by DeitY till final approval of the EMC project.  Subsequently, upon approval  to  the  project,  the  SPV  would  appoint  a  Project Management  Consultant  (PMC)  for assistance  in  the development of  land and  infrastructure  for  the project.   With  the assistance of PMC, the SPV would undertake the construction of the project through contractors and would be the implementing agency for the project.  The management structure of the project is as shown in Figure below.  

  

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 82 

   

  8.3 Roles & responsibilities:   

a) Chief promoter (AIPL) and other members of SPV:    i. Manage  the process of  final application and DPR with DeitY  for  final approval of  the project 

and  financial  assistance;  preparing  the  DPR  and  offering  clarifications  to  DeitY  and  its consultants on the application, layout, project components, implementation aspects, financial model etc. 

ii. Ensure that the lease deeds for transfer of land by the Chief Promoter and its affiliates to the SPV are in place upon receipt of final approval of the project by DeitY. 

iii. Facilitate theinclusion of new members (constituent manufacturing units) into the SPV. iv. Undertake the implementation of the project and ensure its successful completion. v. Provide funds and raise finance as and when required for the project implementation.  vi. The  Chief  Promoter  and  other members would  use  its  vast  experience  in  construction  and 

project management would act as development partners to implement the project as per best industry practices and at arm’s length.  

vii. As  directors  of  the  board  of  SPV,  use  their  experience,  business  acumen  and  network  of relationships to ensure that SPV is run efficiently and profitable during all the stages and as per the guidelines of DeitY.  

 b) ELCINA:  

i. Will  act  as  the  knowledge  partner  and  guiding  force  in  the  SPV  towards  successful management of the EMC. 

ELECTRONIC MANUFACTURING STRUCTURE

PMC

SPV (AEEPPL) WIITH ITS CONSTITUENT MEMBERS

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 83 

   

ii. Will  identify gaps  in  the manufacturing  facilities  in  India and help  identify companies, which could be invited to set up units in the EMC.  

iii. ELCINA will actively promote the EMC and work towards increasing manufacturing capability in the cluster.  It will endeavour to achieve at least 80% occupation in the EMC within 2 years of commencement of development of project. 

iv. ELCINA shall  license  its trademark ELCINA to the SPV and pass on the associated reputational benefits to the SPV. 

v. ELCINA will actively assist  in enlisting members who are desirous of  investing and setting up common facilities within the EMC. 

vi. ELCINA will  assist  the  SPV  in  drafting  common  policies with  regards  to  usage,  pricing  and maintenance of such common facilities. 

vii. ELCINA will coordinate and represent  issues relating to the park with Government and other authorities and bodies. 

 c) SPV (AEEPPL) 

 i. Manage  the process of  final application and DPR with DeitY  for  final approval of  the project 

and financial assistance; appoint consultants for preparing the DPR and offering clarifications to DeitY and its consultants on the application for obtaining final approval to the EMC project. 

ii. Appoint the Project Management Consultant (PMC). iii. Obtain financial assistance (grant) for the EMC from DeitY and monitor its proper utilization. iv. Lay  down  policies  and  procedures  that  ensure  fair,  transparent  and  ethical  practices  are 

followed  in  conduct of  its business  as well  as  to  comply with  the guidelines of DeitY under which the grant would be received. 

v. Device allotment policy  for allotting developed plots  to  the prospective EMC units  in  joining the EMC.   Allotment policy shall  include,  inter alia, the applicant screening process to ensure compliance with the cluster eligibility criteria, quantum of land to be allotted, pricing structure and payment terms and entry and exit policies.   

vi. Manage the execution of the EMC project and ensure  its completion as per the project plan within the defined cost and time estimates. 

vii. Manage the cash flow during all stages of the project implementation. viii. Devise policies and procedures for operations, maintenance, security and other related issues 

of the EMC.  ix. Appointing staff and managing the day to day operations of the SPV. x. Ensure  collection of  fees and  charges  from  the  constituent members  for  smooth  running of 

common facilities within the EMC xi. Take up common  issues pertaining  to  the constituent units and EMC with  the Governments 

and other agencies / bodies.  xii. Any other roles and / or responsibilities stipulated in the guidelines of DeitY. 

   

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 84 

   

d) The PMC  i. Preparation of Project Plan including setting the standards for infrastructure development. ii. Structure and appraise the project and submit the same for consideration of SPV. iii. Assist  the  SPV  in  selection  of  agencies  /  contractors  for  preparation  of  bid  documents, 

construction and maintenance of facilities for the EMC project. iv. Assist the SPV in achieving financial closure where required. v. Monitor the implementation and submit periodical progress reports to the SPV. vi. Any other roles prescribed by DeitY in its guidelines. 

 8.4 Management of the SPV:   

a) The SPV will be managed by its board of directors.   b) The board of directors will be supported by the Chief promoter (AIPL) to fulfill various tasks.  c) The Board of SPV shall appoint a CEO / COO on terms it deems fit. 

 8.5 Board of Directors of the SPV:  

a) During Pre‐construction stage: Currently  the SPV consists of  two directors, one  representing  the Chief Promoter and the other director from one of the other promoters’ viz. OMIL.  This status will remain till approval of the final application by DeitY and during the pre construction stage.  

b) Construction  stage: During  this  stage,  the  board  of  directors  of  SPV will  have  a minimum  of  7 directors of which 4 shall be from the Chief Promoters and other Promoters other than ELCINA and 1 shall be nominated by ELCINA and 2 from constituent members.  Efforts will be made to ensure that  the  Board  of  SPV  will  have  12  directors  with  7  from  constituent  units,  4  from  the  Chief Promoters and other Promoters other than ELCINA and 1 from ELCINA. 

c) O&M  stage: When  the  EMC  is  fully  operational,  the  board  of  SPV  shall  again  be  as mentioned above, comprising of 12 directors of which 7 shall be the nominees of constituent units within EMC, 4 representing the Chief Promoter and other Promoters other than ELCINA and 1 from ELCINA.  

8.6 Shareholding in SPV:  

a) During  Pre‐construction  stage:  The  current  shareholding,  which  will  continue  during  the  Pre‐construction stage is as follows:‐  

   

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 85 

   

 

Company  No of shares  

Value INR/Share 

Total Value   % 

ADD Industrial Park (TN) Ltd. 

51,000  1  51,000  51% 

ELCINA   10,000  1 10,000 10% 

Om Metals Infraprojects Ltd.  

26,000  1  26,000  26% 

Adhunik Power Transmission Ltd.  

13,000  1  13,000  13% 

Total   100,000  100,000 100% 

 b) O&M Stage: During this stage, the constituent units within the EMC will hold equity of 51% while 

the Chief Promoters and other Promoters will continue to hold 49% in the SPV.    8.7 Management of the SPV during O&M stage:   

The SPV will continue to govern and administer the development, management and operations of the EMC during all the stages. For the day to day functioning of the SPV,there will be a team constituted upon receipt of final approval for the EMC from DeitY, as given in the table below: ‐ 

  

CEO / COO  1 

Manager  2 

Accountants  1

Clerks  2 

Technical staff  3 

Security  40 

Housekeeping  40

IT  2 

Office Support Staff  20 

  8.8 Promoters  8.8.1 ADD Industrial Park (Tamil Nadu) Limited (AIPL) is a flagship company under ADD Group involved in 

infrastructure  development  in water & waste water  treatment,  solid waste management,  power, technologies, real estate and development of industrial parks. In association with the Government of Tamil  Nadu  (GoTN),  AIPL  is  in  the  process  of  establishing  a mega  industrial  park  at  Annur  near Coimbatore in Tamil Nadu.  Spread out in an area of 1500 acres, the park would cater to a wide range of  industries, which  include manufacturing of engineering goods, textiles, electronics hardware, IT / ITES, educational  institutions, R&D centers, housing and other social  infrastructure.   It would be an economic phenomenon  in which many businesses simultaneously compete and collaborate to gain different  economic  advantages.  As  part  of  the  policy  of  Government  of  India  (GoI)  to  promote 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 86 

   

electronic manufacturing  in  the country, a national policy on electronics  (NPE) has been drawn up and one of the objectives of the policy is to establish electronic manufacturing clusters (EMC) in the country.  In  line with the policy, AIPL has embarked on a project to establish a state‐of‐the art EMC within  the  industrial park  in an area of about 157 acres.  For details about  the proposed  industrial park and EMC at Coimbatore, please visit www.prime641.com.    

8.8.2 Electronic  Industries  Association  of  India,  formerly  known  as  ELCINA  Electronic  Industries Association of  India was established  in 1967 as the  first  industry association supporting electronics hardware, when India’s Electronics  industry was still  in  its  infancy.   Since then, Electronic  Industries Association  of  India  (ELCINA)  has  established  itself  as  an  interactive  forum  for  electronics  and  IT manufacturers.  ELCINA actively interacts with the government and advises it on policy and business environment  issues.    It networks with  technical  institutions  and business  support organizations  in India  and  abroad  to  enable  business  expansion  and  information  dissemination  on  technical developments. With  greater  liberalization,  ELCINA’s  focus  has  shifted  to  professional  and  value‐added services to the Electronics Community. 

 While ELCINA’s focus was originally on promotion of manufacturing components ‐ the building blocks of the  industry has widened  its horizons and broadened  its activities to  include the development of entire Electronics and IT Hardware.  ELCINA now focuses on promoting manufacture of:  a) Electronic Components b) Industrial / professional electronics c) Defense / strategic electronics d) Electronic Manufacturing Services e) Other expanding areas in electronics such as Medical, Automobile, Electronic Design, Embedded 

Systems and more  

ELCINA’s  focus  is to support the value chain  for Consumer Electronics, Telecom and Computers /  IT correlating  their  common  interest with  that  of  equipment, material  and machinery  producers  for expansion of manufacturing. 

 ELCINA  believes  that  the  Government  and  the  industry  need  to  work  together  to  stimulate manufacturing  and  catalyse  an  IT  /  Electronics  boom  that  can  contribute  significantly  to  the development of India.   ELCINA persistently works to facilitate changes that would strengthen India’s electronics and IT manufacturing base to make it a leader on the world electronics map.  

8.8.3 Om Metals  Infraprojects  Limited  (OMIL)  is  a  conglomerate  having  diverse  business  activities  and interests  related  to  hydro  mechanical  equipment,  turnkey  solutions  for  steel  fabrication,  hydro power development, real estate, leasing, finance, entertainment centres, hotels and tourism.  It is a leading ISO 9002 company established  in 1971 and a pioneer in the field of turnkey execution from Design,  Detailed  Engineering,  Manufacture,  Supply,  Installation,  Testing  &  Commissioning  of complete range of Hydro mechanical equipment for Hydroelectric Power & Irrigation projects, PHED, PWD & various Corporations.   

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 87 

   

OMIL has to  its credentials more than 40 projects completed all over  India and Abroad  for Design, Manufacture,  Supply,  Erection,  Testing  and  Commissioning  of  Hydro‐Mechanical  Equipment.  Employing more  than  400 managerial,  technical,  skilled  and  semi‐skilled manpower, OMIL  is  fully capable and resourceful to execute the projects of any magnitude timely and confidently.  It has key and critical plants, tools, equipment and manpower required to execute turnkey contracts for small, medium and large hydroelectric power projects.  

OMIL is well acquainted with modernized methods of fabrication and erection and have successfully completed the works in remote areas, difficult climate & natural site conditions, logistics bottlenecks, difficult roads and great distances.  

8.8.4 Adhunik  Power  Transmission  Limited  (APTL)  offers  electrical  power  transmission  services.    The company was  founded  in 1991 and  is based out of Kolkata, West Bengal.   A  subsidiary of Deepak Cables  India  Limited,  ATPL  is  in  the  business  of manufacturing  and  selling  transmission  lines  and tower components.  It was  formerly known as Unistar Galvanisers & Fabricators Limited.   ATPL has been approved by  the Power Grid Corporation  Limited of  India and various other  state electricity boards for manufacturing transmission  line towers and sub‐station structures.    Its products  include tower accessories  (clamps, anti‐climbing devices, bird guards, U bolts, hangers etc.), ground‐based and rooftop galvanised telecom towers, galvanised cable trays, perforated trays (and accessories like coupler  plates,  bends,  fasteners  etc), welded  structures  and masts  for  the  railways  and  lightning masts, pipe structures, foundation bolts and accessories utilised in power and telecommunication.  It was a wholly owned subsidiary of AdhunikMetaliks. 

  8.9 Profiles of key personnel  The following are the profiles of the key personnel currently involved in the development of the proposed EMC project are as shown below:   They represent the Chief Promoter (AIPL), other Promoter (OMIL) and ELCINA.    

EMC AT ANNUR, COIMBATORE – DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page88 

   

Anil Sethi Chairman ADD Industrial Park (Tamil Nadu) Limited and ADD Group of Companies      Mr. Anil Sethi, with over 30 years of engineering and infrastructure development experience is credited as a  leader and spokesperson of the fast growing  Infrastructure  Industry of  India.    In his business and domain pursuits, Mr. Sethi has travelled across geographies and interacted with international business, industry and political  leaders; he has been  invited to several  leading  international forums as a speaker and advisor, apart from being an integral and lead member of eminent industry bodies and institutions such as: a) World Economic Forum b) Confederation of Indian Industry (CII) c) Federation of Indian Chambers of Commerce & Industry (FICCI) d) Steering Committees of Panels on Water Management and Urban Infrastructure  He  is  currently  the Chairman Emeritus of  SPML  Infra  Limited.   As Director  / Chairman of  SPML  Infra Limited, Mr.  Sethi’s  extraordinary  entrepreneurial  acumen  has  been  an  inspiration  in  building  the organization  into a multi‐faceted conglomerate with EPC contracting experience  in Water, Power and Infrastructure.  His achievements during his leadership in SPML Infra Limited: a) Ensured Year‐on‐year growth of over 50% Annual Turnover b) The organization has consistently been a profit making enterprise since inception c) Conceptualized and ushered in IT as an enabler within the organization d) Under his supervision, SPML was Ranked 1‐ Fastest Growing Company in the Large  

a. Category – (Source: Construction World & NICMAR – year 2009)   As  the  Chairman,  ADD Group  of  Companies, Mr.  Sethi  is  currently  focusing  on  development  of  the Group having several focus areas: a) Industrial Parks  b) Real Estate and Infrastructure Development  c) Information Technology  Mr.  Sethi  has  been  the  recipient  of  several  national  and  international  accolades  for  his  strides  and accomplishments in the industry.  Notable are: a) Nominated / Empanelled as Eminent Citizen with the NREGA  b) Outstanding  Entrepreneur  Award  for  his  contribution  as  a  Business  Leader  Par  Excellence  –  by 

Enterprise Asia – 2009 (An international panel / jury for Entrepreneurship) Award c) The Pride of India Gold Star Award and The Vikas Jyothi  

EMC AT ANNUR, COIMBATORE – DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page89 

   

Rajoo Goel Secretary General, Electronic IndustriesAssociationofIndia (ELCINA)        

Mr. Rajoo Goel has varied experience in supporting electronics  industry through his association with ELCINA, in manufacturing as a co‐founder of an auto components company and in services sector while working  for  International  Data  Management  Pvt.  Ltd.  Mumbai,  a  Software  and  Data  Processing company, which was an off shoot of IBM in India.  Since 2003 he has been serving the Electronics Manufacturing Industry in India as the Secretary General of ELCINA and has been interacting with the government for guiding policy formulation for the industry as well as with international organizations supporting electronics hardware and business development. He has worked in coordination with industry towards creating a favourable environment for the growth of the Electronics Hardware industry.  As an entrepreneur during 1986‐2003, Mr. Goel, has hands‐on  industry experience managing an auto components  company  manufacturing  auto  instruments  in  the  services  sector,  he  has  worked  on computer  systems  analysis  and programming  at  IDM, Mumbai  and General  Electric, Meter Business Division, USA. He  has worked  for  a  short  duration  in USA  and  has  travelled widely  to many  Asian countries, USA  and  Europe  developing  substantial  experience  in  international  business. He  has  also received professional  training  from CBI Netherlands, as a Trainer  for Export Promotion Strategies  for SME’s and has considerable exposure to environmental management subjects such as RoHS, eco‐design and e‐waste related issues.  Mr.  Goel  graduated  in  Economics  from  Shri  Ram  College  of  Commerce,  Delhi  University,  earned  a  Certificate  in  Software  Technology  and  Computing  Techniques  from  Tata  Institute  of  Fundamental Research, Mumbai and an MBA from the University of New Hampshire, USA.  

 

EMC AT ANNUR, COIMBATORE – DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page90 

   

 VIKAS KOTHARI,  Director ‐ Business Development  Om Metals Infraprojects Limited      

 

  Om  Metals  Infraprojects  Limited  (OMIL)  is  a  Public  Listed  conglomerate  having  diverse  business activities and interests in Engineering Construction, Hydro Mechanical Equipment, Turnkey solutions for Steel  Fabrication, Wind  Power  and  Solar  Power  Development,  Sea  Port &  SEZ  Development,  Roads Development,  Real  Estate  Development,  Automobile  Dealership,  Finance,  Entertainment  Centers& Hotels.  Mr. Kothari is responsible for all the Joint Ventures and technical collaborations in the Company (Foreign & Domestic) for various projects.  He was  instrumental  in raising USD 30 Million  for OMIL through a Qualified  Institutional Placement  in year 2007.   Mr. Kothari currently oversees all the New Business Development and Marketing activities for the Group.    

EMC AT ANNUR, COIMBATORE – DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page91 

   

Ganapathi Hegde  Chief Executive Officer  ADD Industrial Park (Tamil Nadu) Limited 

 

 Mr. Ganapathi Hegde  is  a  self‐structured  and multi‐talented person who has  a Bachelor’s degree  in Commerce &  Business  Administration.    He  joined  the  Group  in  the  year  1996  as  Accounts Officer.  However, he has handled multiple tasks and assignments apart from not being restricted to Accounting section.  Hence he has grown up to the level of being a ‘Chief Executive Officer’ of the Organization.  His  experience  lies  in  Accounting,  Commercial,  Auditing,  handling  project  activities,  Real  Estate management and Corporate Governance.   His area of  responsibilities  includes and not  limited  to  the following:‐  - Accounting: All financial transactions relating to branch up to finalization of balance sheet. - Commercial activities: Key person in charge of budgets, taxation and administration. - Real Estate: Handing complete marketing and sales activities of major properties. - Corporate  Governance:  Ensure  high  standards  of  business  integrity,  ethical  values  and 

professionalism in all its activities.  He  is  a  person  who  strives  to  maximize  the  shareholder  value  while  ensuring  fairness  to  every stakeholder – customers, employees, investors, vendors, partners, government and the community.    

EMC AT ANNUR, COIMBATORE – DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page92 

   

   Dr. Jayakumar Project Advisor ADD Industrial Park (Tamil Nadu) Limited        A thorough engineering professional, Dr. Jayakumar has more than 25 years of extensive experience in planning, development, construction and management of  infrastructure projects  in  India and abroad.  An astute civil engineer with an M Tech and PhD both from IIT, Madras, he has served the government and  private  sectors  at  various  engineering  and  management  levels.    He  was  the  founder  CEO  of Vizhinjam  International  Seaport  Limited,  which  is  responsible  for  the  development  of  India’s mega container transhipment terminal project at the southern‐most tip of  India  in Thiruvananthapuram and was also the Adviser (Ports) to Government of Kerala.    Dr. Jayakumar was the Advisor (Projects) in Westport Malaysia and has extensively travelled to several countries  including  USA,  UK,  Germany,  France,  South  Africa,  Singapore,  China,  Australia  etc.    He currently serves as the CEO of Pondicherry Port Limited.  Dr. Jayakumar has to his credit several papers in  International  Journals  and  Conference  Proceedings  and  recipient  of  several  awards  including  the Indian Achievers Award presented at the Indo‐Gulf Conference held in Dubai, UAE.   

   

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 93 

   

 

 CHAPTER 9 

 

MEANS OF FINANCE & PROJECT BUDGET  

9.1. PROJECT BUDGET:   9.1.1. Land Cost 

 a) Total Area to be developed under the scheme is 157.69 Acres  b) Total Area has been divided into two Categories, i.e. 

 i. Area for Development of Common Infrastructure and Amenities ii. Area for Saleable Purposes for setting of Electronic Manufacturing Units. 

 c) Following is the breakup of Total Area assumed  

       

d) Total Land required for Development of Scheme,  i.e., 157.69 acre to be purchased @ Rs 20 Lakhs per acre, therefore following is the breakup of cost of Land required for Development of Scheme:  

       

   

Area for Development of Common Infrastructure and Amenities  62.33 Acres 

Area for Saleable Purposes for setting of Electronic Manufacturing Units 

95.36 Acre 

Total Area  157.69 Acre 

Area for Development of Common Infrastructure and Amenities 

62.33 Acres Rs. 12,46,66,600 

Area  for  Saleable  Purposes  for  setting  of Electronic Manufacturing Units 

95.36 Acre Rs. 19,07,11,400 

Total Area  157.69 Acre Rs. 31,53,78,000 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 94 

   

9.1.2. Cost for Development of Common Infrastructure and Amenities  

9.1.2.1. The total Cost for Development of Common  Infrastructure and Amenities works out to be Rs 166.33 Crores.  

         

 

 

 

9.1.2.2. Following is the Summary of Cost for Development of Common Infrastructure and Amenities:  

Summary  ofCost  for  Development  of Common Infrastructure and Amenities: 

Amount (in Rs. Lakhs) 

% of Total 

Processing & Non Processing 

Basic Development  6021 36%  Processing 

Essential Services  6282 38%  Processing 

Welfare Services  2214 13%  Non Processing 

Support Services  1021 6%  Processing 

Manufacturing Support  505 3%  Processing 

Government Regulatory support/services 

269 2%  Processing 

Landscaping (Green area)  323 2%  Non Processing 

Total  16634 100%  

 

Further the total Cost for Development of Common Infrastructure and Amenities has been divided  into two  categories  as  per  DeitY  Guidelines,  i.e., Processing and Non Processing Cost. Following is the Breakup  of  Cost  for  Development  of  Common Infrastructure  and  Amenities  into  Processing  and Non Processing Cost:Total Processing project cost 

Rs. 1,40,97,61,108  

Total Non‐ Processing project cost  Rs. 25,36,25,992  

Total  Cost  for  Development  of  Common Infrastructure and Amenities 

Rs. 166,33,87,100  

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 95 

   

9.1.2.3. Following  is  the  Cost  break‐up  details  for  Development  of  Common  Infrastructure  and Amenities. The detailed cost estimates are attached as Annexure 8.  

 

Sl. No. 

Description of Items as per Annexure‐2 : EMC 

policy 

Items / Areas considered / Item as per detailed estimate document 

Amount  Cost Break Up 

Category (Processing/ Non‐

processing)

1  2  3  4  5  6 

1  Basic Development 

Boundary  wall,  internal roads,  street  lighting, external  storm  water drainage. 

     

a Boundary  wall  & internal  roads  &  Truck Holding area 

Infrastructure development ‐ Civil work 

50,57,85,377 

60,20,54,349 

Processing 

b  Street lighting Streetlighting  ‐  Electrical Infrastructure 

4,73,07,685  Processing 

c  Storm water drainage  Plumbing infrastructure  4,89,61,287  Processing 

2  Essential Services 

Government support office, water  treatment  plant, sewage  lines  /  treatment, waste  disposal  /  recycling/ water harvesting, Electricity substation/distribution, backup  power  plant, warehousing 

     

a1 

Water Treatment Plant (WTP)  including  Bore wells  &  water  supply lines 

Plumbing infrastructure  5,21,89,461 

38,36,44,581 

Processing 

a2 

To  be  paid  to Government  of  Tamil Nadu  /  its  nominated agencies  for conveyance  of  water system 

Plumbing infrastructure  14,50,00,000  Processing 

b Civil work  for plumbing pump house 

Civil work  11,22,72,645  Processing 

c  Sewage line with STP  Plumbing infrastructure 7,41,82,475 Processing

d Electric  Substation  & distribution 

Electrical infrastructure  19,05,75,911  21,38,04,888  Processing 

1  2  3  4  5  6 

e  Civil  work  for  electric  Civil work  2,32,28,977  Processing 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 96 

   

substation 

f Warehousing  ‐ Building‐7 

Civil work of Warehouse  2,97,90,944 3,07,87,022  Processing Internal  electrical  work 

for warehouse 9,96,078 

3  Welfare Services 

Employee hostel & mess, hospital,  recreation facility,  crèche,  local shopping  center, restaurant 

     

a Employee  hostel  & Mess ‐ building 4 

Civil  Work  of  Employee hostel & mess 

9,08,17,996 

10,56,07,446 Non‐

processing 

Internal  Plumbing  work of  Employee  hostel  & mess 

18,31,669 

HVAC  works  for Employee Hostel & Mess 

79,59,285 

Internal electrical work of Employee hostel & mess 

49,98,496 

b Hospital  &  ESIC  ‐ building‐8 

Civil  work  ‐  Building‐8  ‐ medical center 

2,17,81,076 

2,36,87,436 Non‐

processing Internal  Plumbing  work of medical center 

7,94,170 

Internal electrical work of medical center 

11,12,191 

c  Clubhouse ‐ building‐5 

Civil  work  ‐  Building‐5  : Clubhouse 

3,75,61,878 

4,43,40,882 Non‐

processing 

Internal  Plumbing  work of clubhouse 

8,50,828 

Internal  HVAC  work  of clubhouse 

40,02,633 

Internal electrical work of clubhouse 

19,25,543 

d Worker  welfare building  ‐  building‐6‐ 3nos 

civil  work  ‐  building  6  : worker welfare X 3 

4,10,77,315 

4,77,32,727 Non‐

processing Internal  Plumbing  work of worker welfare x 3 

17,44,391 

Internal electrical work of worker welfare x 3 

49,11,021 

 

   

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 97 

   

 1  2  3  4  5  6 

4  Support Services 

R&D,  training, auditorium,  video conference,  IT  ,  business center‐ Admin & Training building 

     

a Building‐2  :  Support Services:  Admin  & Training Building 

Civil  work  ‐ Building‐2  ‐admin & Training building 

8,57,05,530 

10,21,04,671  Processing 

Internal  Plumbing  work of  admin  &  training building 

14,55,429 

Internal electrical work of admin & training building 

49,09,933 

HVAC works  for Admin & Training building 

1,00,33,779 

5  Manufacturing Support tool  room,  CAD/CAM, testing, certification       

a Building‐3  : Manufacturing  support building 

Civil  work  ‐ Building‐3‐Manufacturing  support building 

4,19,12,506 

5,05,14,742  Processing 

Internal  Plumbing  work of manufacturing support building 

7,36,762 

Internal electrical work of manufacturing  support building 

12,64,943 

HVAC  works  for manufacturing  support building 

66,00,531 

 

   

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 98 

   

1  2  3  4  5  6 

6 Government Regulatory support/services 

Entry/  exit,  Security  , time office & government support offices 

     

a  Building‐1 : Gatehouse 

Civil  work  ‐  building‐1  ‐ Main  gatehouse  building having  the  timeoffice  & government  support building 

2,41,22,980 

2,68,50,855  Processing Internal  Plumbing  work of Gatehouse building 

2,47,029 

HVAC  works  for manufacturing  support building 

11,99,720 

Internal electrical work of Gatehouse building 

12,81,126 

7 Landscaping  (green area) 

green  area  development @ Rs.500/sqm 

3,22,57,500  3,22,57,500 Non‐

processing 

 Total project cost 

 166,33,87,10

0     

 Total  Processing project cost   

1,40,97,61,108  

Processing 

 Total  Non‐  Processing project cost   

25,36,25,992  

Non‐processing 

     

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 99 

   

 9.2. Grant calculation: As per DeitY guidelines, it has been assumed 50% of Total Processing Cost, 20% 

of Non‐Processing Cost and 3% of Total of Processing & Non Processing Cost as Administrative cost, Grant will be provided. According  to  this total Grant assumed  to be Rs 77.83 Cr. Following  is  the Calculation for Grant: 

 

Grant Calculation Processing/Non‐

processing Grant (in %) 

Grant Amount (Rs. Lakhs) 

Processing Costs   1,40,97,61,108  50%  70,48,80,554 

Non Processing Costs   25,36,25,992  20%  5,07,25,198 

Administration Costs Allowed for Grant  

  3%  2,26,68,173 

  

TOTAL GRANT      77,82,73,925 

  9.3. Means of finance: 

 Total Funding needs to be arranged by SPV  a) It  is  assumed  that  SPV  needs  to  arrange  for  the  Total  Cost  for  Development  of  Common 

Infrastructure and Amenities Less Grant of  its own,  i.e.,            (Rs 166.33 Cr  ‐ Rs 77.82 Cr)= Rs 88.51 Cr 

b) In  addition  to  the  above,  i.e.,  Total  Cost  for  Development  of  Common  Infrastructure  and Amenities, SPV needs to arrange funds for the following: 

 i. Land Cost ‐ Rs. 31,53,78,000 ii. Administration Expenses ‐ 3% of Total of Processing & Non Processing Cost iii. CSR Development Activities  to be  carried out  at  0.5% of  Total  of  Processing & Non 

Processing Cost and land for common area  

c) To  finance  the  additional  funding  required  it  has  been  assumed  that  the  SPV will  go  for Project Finance route. For the Project Financing of Land Cost  is being divided  into  following two Categories: 

 i. Area  for  Development  of  Common  Infrastructure  and  Amenities  –  Rs.  12.47  Cr, will  be 

financed through Project Financing Route. ii. Area  for Saleable Purposes  for setting of Electronic Manufacturing Units costingRs. 19.07 

Crores will be financed through Bridge Loan (Short Term Loan) @ 13% Interest and will be repaid  immediately  in Single  Instalment  in Second Year of Development once the SPV will have Cash Inflow from Sale of Plots cum Units. 

   

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 100 

   

9.4. Project Finance – Based on the above following will form part of Project Finance which needs to be arranged by SPV: 

 

Summary of Cost  to Arranged by  SPV  and  funded  through Project  Finance Mechanism 

Rs. In Lakhs 

Area for development of common infrastructure and Amenities  1,247

Total Cost for Development of Common Infrastructure and Amenities Less Grant 

8,851

Administrative expenses (3% of Total of Processing & Non Processing Cost)  499

CSR development Activities (0.5% of Total of Processing & Non Processing Cost and land cost) 

83

Total  10686

 i. Total Cost to Arranged by SPV will be financed through Debt: Equity of 70:30 ii. Under Project Financing,  Interest During Construction  for  the Debt utilized will also  form 

part of Project Financing, which will financed through Debt: Equity proportionately    iii. Debt  is  assumed  to  be  raised  under  Project  Financing  at  13%  Interest  Rate  and will  be 

repaid  in  5  years  after  the  Construction  Completion  and with  the  following  Repayment Mechanism:  

 

Year  Year 3 Year 4 Year 5 Year 6 Year 7  Year 8

Repayment Installment 

30%  30%  8.00%  8.00%  8.00%  8.00% 

 iv. Repayment Mechanism has been  assumed  to  ensure  that debt  is  repaid  immediately  as 

soon  as  SPV  has  sufficient  funds  and  there  is  not  much  of  Interest  Liability  and  thus increases Project Viability. 

v. 30%  Equity  will  be  brought  in  by  SPV,  wherein  49%  will  be  contributed  by  the  Chief Promoter and 51% will be contributed by the Unit Holders. 

   

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 101 

   

  

9.5. Summary  

Description Amount 

(in Rs. Lakhs) 

Total Cost for Development of Common Infrastructure and Amenities  16,634

Less Grant  7,783

Total Cost for Development of Common Infrastructure and Amenities Excluding Grant 

8,851

Land for Development of Common Infrastructure and Amenities Excluding Grant 

1,247

Administrative Expenses (3% of Total of Processing & Non Processing Cost) 

499

CSR Development Activities (0.5% of Total of Processing & Non Processing Cost& land for common amenities) 

89

Interest During Construction  1,132

Total to be Funded through Debt & Equity  11,818

 

Means of Finance  INR Lakhs

Grant  7,783

Debt  8,273

Equity ‐ Contribution by Chief Promoter   1,737

Equity ‐ Contribution by Unit Holders  1,807

Total  19,601

 

Funds to Arranged by SPV through Bridge Loan (Short term Loan) 1,907 Lakhs

 

The details of the financial statement are attached in Annexure 9. 

   

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 102 

   

CHAPTER 10  

TIME FRAME  Time  is of utmost essence  for any  successful project.    It  is estimated  that  the project will be completed within 24 months of the final approval received from Deity.  The key stages of the project are as follows:  10.1 Pre‐construction activity  

This refers to the time required to undertake the detailed design and engineering for the project and finalization of the contractor for execution of the project on site.   Detailed project planning & project management scheduling shall also be undertaken during this time period.  3 months shall be required for this activity. 

 10.2 Construction activity 

 The  construction  of  the  project  including  development  of  the  common  infrastructure,  amenity buildings, water and drainage network along with the electric, IT and communication utilities shall be done during  this phase.  It  is estimated  that a  total of 18 months  shall be  required  to  complete  this activity.  

 10.3 Post construction activity 

 This refers to the time required for commissioning, testing and checking of all the work in the project. 3 months are required for this activity.  

 The detailed timeline along with the bar chart is attached below. 

    

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 103 

   

DETAILED PROJECT TIMELINE ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED at AnnurTaluk, Coimbatore, Tamil Nadu 

   

Sl. No. 

Category / Component Month 

1  2  3  4  5  6  7  8  9  10  11  12  13  14  15  16  17  18  19  20  21  22  23  24 

        

A  PRE‐CONSTRUCTION                                                                        

        B  CONSTRUCTION                                                                                 1  Basic Development          

a Boundary wall & internal roads & Truck Holding area 

  

b  Street lighting   

c  Storm water drainage   

2  Essential Services          

a Water Treatment Plant (WTP) including Bore wells & water supply lines 

  

b  Sewage line with STP   

c Electric Substation & distribution 

  

d  Warehousing ‐ Building‐7    

 

EMC AT ANNUR, COIMBATORE – FINAL DPR   

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 104 

   

Sl. No. 

Category / Component  Month 

1  2  3  4  5  6  7  8  9  10  11  12  13  14  15  16  17  18  19  20  21  22  23  24 

3  Welfare Services                                                                        

a Employee hostel & Mess ‐ building 4 

  

b Hospital & ESIC ‐ building‐8 

  

c  Clubhouse ‐ building‐5   

d Worker welfare building ‐ building‐6 (3 Nos.) 

  

4  Support Services                                                                         

a Building‐2 : Support Services: Admin & Training Building  

  

5  Manufacturing Support                                                                         

a Building‐3 : Manufacturing support building 

  

6 Government Regulatory support/services                                                                         

a  Building‐1 : Gatehouse   

7  Landscaping (Green area)        

        

C  POST CONSTRUCTION                                                            

           

 

EMC AT ANNUR, COIMBATORE – FINAL DPR 

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 104 

   

CHAPTER 11  

RISK ANAYSIS  

11.1.Risks can be classified as below:‐  

a) Firm specific risks:  Firm‐specific risks, also known as micro risks, are those political risks that affect the project level locally up to State Government level. 

 b) Country specific risks:  Country specific risks,also known as macro risks, are those political risks that 

also affect the project level but originate at the country level.  c) Global  specific  risks:   Global‐specific  risks  are  those political  risks  that  affect  the project  at  the 

project or corporate level but originate at the global level.  

11.1.1. Firm specific risks   

a) Governance  risks:    There  is  no  governance  risk  involved  with  the  EMC  project.    During  pre‐operational stage the governance will be carried out by the consortium members as agreed by the MoU signed between them. The consortium members are experienced  in establishing  large scale projects.  Once he EMC is established there will be 12 Board of directors out of which seven will be from  the constituent units, one  from Electronic  Industries Association of  India and  four  from  the consortium members ensuring that the constituent units have majority in the decision making.   

b) Conflict with State Governmentrisks:   The State Government  is  fully supportive of the project as establishing  the EMC  is  in  line with  the State’s  initiatives  in promoting Electronic Manufacturing.   The  State  has  given  a  letter  in  support  of  the  project which was  handed  over  to  DeitY  during preliminary application.   Also MoU has been signed in advance with the state for development of the Industrial Park, within which the EMC will be located.  

c) Political risks:The current ruling party is likely to continue. Even in the case of a change in political leadership,  since  the  EMC  is  contributing  to  the  State’s  economy,  employment  generation  and development of the local area, no risks are envisaged.   

d) Labourunionrisk: Tamil Nadu  ranks  first among  the  states  in  the Country  in  terms of number of factories and  industrial workers.   The workers are hardworking and not prone to unrests.   Rather entrepreneurs from neighboring states invest and establish manufacturing units in Tamil Nadu.  

 e) Revenue risk:     Sensitivity analysis shows that even when revenue  is reduced by 15%, returns on 

the project  are  viable.   Current  IRR  is  calculated  at 14.21%  for  the project  and  at  a  scenario,  if revenues fall by 15% than assumed, the IRR is still attractive at 12.45%.At the pre‐operational stage which is in the first two years, no revenue is being assumed from constituent units other than sale of plots.  Sale of plots is spaced across 3 years and only 20% of the plots are assumed to be sold in 

EMC AT ANNUR, COIMBATORE – FINAL DPR 

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 105 

   

Year  1  and  another  35%  in  Year  2.      Post  operational  stage  revenues  are  pre‐agreed  between constituent units and vendors while signing the investor agreement.  

 f) Completion risk:  The project is being managed by a highly experienced team who has experience 

in  large scale project management.   Only a reputed agency will be engaged for  implementing the project.  Clear project performance parameters and time lines for each phase will be laid down.   A monitoring  team  will  be  set  up  by  the  management  team  and  the  project  would  be  closely monitored  for performance  parameters.  Penalty  clauses  for  time overruns will  be  added  in  the agreements with implementation agency and contractor.  

 g) Cost  overrun  risk:  Sensitivity  analysis  shows  that  even when  the  project  cost  increases  by  15% 

returns on  the project are viable.   Contingencies  for  cost overruns have been  catered  for  in  the project budget. In a scenario where cost overruns by 15% of the calculated project cost, the IRR is still viable at 10.26%.   Cost overruns will be controlled through prudent project management and budgeting.  The project monitoring committee will work closely with the implementing agency and monitor expenses.  

 h) Operating risk(Infrastructure failures): For common facilities and infrastructure DG sets have been 

catered for as back up. Street  lights are being powered by solar energy. For water bore wells are available  for  emergency  supply.    Dedicated  communication  lines  are  planned.  Periodic maintenance  is  planned  and  an  efficient  agency will  be  engaged with  clear  penalty  clauses  for failure.  

 i) Force majeure  risk:   There have been no major natural calamities  in  the area where  the EMC  is 

proposed.   No major  calamity  is envisaged  in  the  future. A  comprehensive emergency  response management policy will be framed along with roles identified and actions to be taken.  

 j) Environmental risk:  The EMC is planned as a “green” campus. An Environment Impact Assessment 

report has been carried out by an expert consulting agency and submitted to State Environmental Impact  Assessment  Authority  (SEIAA).    There  is  no  significant  impact  on  the  Environment  from development  activities.  Post  operation  each  constituent  unit  will  establish  their  own  effluent treatment plant. The EMC will obtain a green certification rating. 

 11.1.2. Country specific risks  

a) Money transfer risks:  No money is being transferred from abroad for the project.  b) Cultural &  institutional risks:   Cultural and ownership  issues are not considered as  they have no 

impact  on  establishing  the  EMC.    The  SPV will  be  constituted  as  per  SPV  guidelines notified  by Deity. 

 c) Conflict with  the Government  risks:    The Government of  India  is  the biggest proponent of  the 

Electronics Industry and establishing the EMC is in line with the National Policy on Electronics.   d) Political  risks:    The  current Government  still  has  4 more  years  to  govern  the  Country  before  a 

change is envisaged.   

11.1.3.Global‐specific Risks: 

EMC AT ANNUR, COIMBATORE – FINAL DPR 

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 106 

   

 a) Terrorism:  The EMC campus will be adequately guarded 24X7, though there  is no specific reason 

for terrorist attack on campus.   b) Cyber‐attacks:  Adequate cyber security measures will be taken at the IT center of the EMC and a 

policy on Cyber security will be developed and implemented.     

EMC AT ANNUR, COIMBATORE – FINAL DPR 

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 107 

   

 

CHAPTER 12  

FINANCIAL & ECONOMIC ANALYSIS  

12.1 Key revenue assumptions  

The major revenue streams for the cluster are as follows:‐  a) Sale of Land b) Maintenance Charges c) Fresh Water Charges  d) Recycled water Charges  e) Infrastructure Renewal Charges  f) Tool Room Charges  g) Testing Centre Charges  h) Hostel Charges  i) Rental Income  j) Warehouse Rent k) Skill Development Charges  l) IT & Telecom Facility Charges   

12.1.1 Commonassumptions  

a) Capacity utilization: It is expected that the occupancy of units in EMC would be 40% in the 3rd year, 75%  in the 4th year, 85%  in the 5thyear and 95% thereafter for financial calculation.  Occupancy of EMC by units, Tool room, Testing Centre and Hostel Utilization is as shown in the Table below: 

 

Capacity Utilization –Facility    Year 3  4  5  6  7  8  9  10  11  12 

Occupancy of EMC by Units   40% 75% 85% 95% 95% 95% 95%  95%  95% 95%

Tool Room   40% 60% 75% 80% 80% 85% 90%  90%  90% 90%

Testing and Measurement   40% 60% 75% 80% 80% 85% 90%  90%  90% 90%

Capacity Utilization –Hostel   50% 60% 70% 80% 80% 80% 90%  90%  90% 90%

 b) All common facilities charges are expected to increase at 5% YoY other than mentioned specifically.  

 12.1.2 Sale of land: The saleable area of land is 95.36 acres. This land is to be sold to units wanting to set 

up manufacturing  facilities  and  service  facilities  in  the  cluster.  The  land  is  expected  to  be  sold across 3 years  from the date of approval of the DPR. The price of  land  is expected to escalate at 15%  in  year 2  and 20%  in  year 4.   The  assumptions on  the quantity of  land  to be  sold  and per square metre price across 3 years are as per the Table given below:‐ 

   

EMC AT ANNUR, COIMBATORE – FINAL DPR 

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 108 

   

 

   1stYear 2nd Year 3rd year 

% of Area Sold  20%  35%  45% 

Increase in Selling Price  15%  20% 

Selling Price/SqMtrs.in Rs.  2373 2729 3275 

 The expected revenue from land across first 3 years is as given below:   

Time Schedule  Year1 Year 2 Year 3 

Revenues from Sale of Plots  (In Rs. Lakhs ) 

1831 3685 5685 

  12.1.3  Maintenance charges:   This is a revenue stream to be contributed by the units which have bought 

plots in the cluster. Each unit will be charged Rs 240 / Sqr. Mtrs. /year of total area held by them. This is for maintenance of individual plots. This revenue is expected to increase by 7% YoY. 

 12.1.4 Fresh  water  charges:The  total  requirement  of  fresh  water  for  manufacturing  units  has  been 

assessed at 2057 KLD. This will be charged at Rs 100/‐ per KL. This revenue is expected to increase by 7% YoY. 

 12.1.5 Recycled water charges: The total water supplied by the STP will be 3729 KLD. This will be charged 

at Rs 50/‐ per KL. This revenue is expected to increase by 7% YoY.  12.1.6 Infrastructure renewal charges:This  is a revenue stream contributed by the constituent members 

of the cluster. This  is  for maintenance asset  replenishment of common  infrastructure and will be charged once in 3 years after the cluster becomes operational.  This revenue is assumed to increase at 7% YoY. This will be charged at Rs 125/‐ per square metre of land held by units owning plots  in the cluster. 

 12.1.7 Tool room &testing centre charges:The tool room and testing centre will be an outsourced activity. 

It  is  assumed  that  since  the  SPV  will  be  providing  facilitates  and  business  opportunity  and  a complete eco system free of charge, SPV's revenue share will be 20%. The total revenue from tool room and  testing centre are as per  table below. The SPV will be earning 20% of  these  revenues depending on occupancy per year. 

   

EMC AT ANNUR, COIMBATORE – FINAL DPR 

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 109 

   

 

Tool room 

Revenue/ year  at 100% installed capacity     

Total tool room investment  200

Revenue estimated %  20%

Total revenues per year at 100 % installed capacity (Rs.  Lakhs)  40

Testing centre     

Revenue at 100% installed capacity     

No. of machines  10

Average rate per hour  500

Machine usage (Hrs/ day)  8

No. of days  300

Total revenue at 100% installed  capacity (Rs. Lakhs) 120

 12.1.8 Hostel charges:  The revenue assumptions for hostel charges are as given in the Table below:‐  

 

Employee hostel & mess 

No. of beds  103

Charge per bed per night  150

No. of days  300

Revenue at 100% installed capacity (Rs. Lakhs)  46.35

Expected usage when cluster 100% occupied  90%

Total revenues when cluster at 100% occupancy  41.715

 12.1.9 Rental income: The workers welfare building consisting of bank, local shopping, first aid, cafeteria 

etc,  the medical  centre  and  club  house  are  expected  to  be  rented  out.  The  total  built  up  area available for rent  is 3102 square metres and the rent assumed  is Rs350/square metres per month as per the table below.  

 

Rental income  Size Rent P.M. 

Rent P.A. 

Sqr. Mtrs.  Rs.  Rs. Lakhs 

Employee worker welfare building  1832 350  77

Clubhouse  & restaurant  1270 350  53

 12.1.10 Warehouse rent:   A warehouse of 1400 Square metre  is being set up  in the cluster. This will be 

rented out to units at Rs 250/ square metre  12.1.11 Skill development: The SPV will carry out skill development programmes for member units. The 

cluster has 95 acres of saleable plots and The expected revenue from skill development is as per the Table below:‐ 

   

EMC AT ANNUR, COIMBATORE – FINAL DPR 

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 110 

   

 

Assumed no of units in the EMC  95

Employees per  unit  350

Total employees in cluster  33250

Employees trained per annum  15%

Training fees per person  3000

Annual training revenues at  (Rs. Lakhs)  149.625

 12.1.12 IT & telecom facility charges: The SPV will provide IT & Telecom facilities to member units. On an 

average each unit  is expected to use service worth Rs 1 Lac per year for usage of these facilities including video conferencing.  

 12.2 Key expense assumptions 

 The major operating expenses for the cluster are as follows:  a) O&M charges for infrastructure  b) Fresh &recycled water production  c) Direct expenses for Tool Room, Testing Centre, Skill Development & Hostel d) Electricity  e) Water  f) Communication & Video Conferencing  g) Warehouse h) IT Infrastructure  i) Employee Expenses  j) Insurance  k) Marketing  l) Land Cost m) CSR n) Maintenance cost on infrastructure   

12.2.1 Common assumption: All costs increase 5% YoY.  

12.2.2 O&M charges for infrastructure:   For day to day operations and maintenance of infrastructure the following costs as a % of Capex for each sub‐component as given below in the table are assumed.  

 

Basic Development  3%

Essential Services  5%

Government Regulatory support/services  3%

Landscaping (green area)  8%

   12.2.3 Fresh & recycled water production:  The cost for fresh and recycled water production charges per 

KL are assumed as per the Table given below:‐  

EMC AT ANNUR, COIMBATORE – FINAL DPR 

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 111 

   

Fresh Water Production Charges  60 

Recycled Water Production Charges  20 

 12.2.4 Direct expenses : The direct expenses for tool room, testing center, skill development ,hostel IT & 

Telecom and warehouse as a % of revenue are as below:‐  

Tool Room Direct Expense as a % of Revenues  80.0% 

Testing Direct Expense as a % of Revenues  80.0% 

Training & Skill Development Direct Expense as a % of Revenues 60.0% 

Employee Hostel   10.0% 

IT & Telecom  40.0% 

Warehouse  10.0% 

 12.2.5 Electricity:   The electricity consumption for common facilities  is calculated at 800 units  (kiloWatt‐

Hours). Assuming that electricity would be used for 8 hours per day and for 300 working days the cost of electricity for common facilities is calculated as per the Table  below:‐  

 

Max units consumed per hour  800 

Hours/ day  8 

Units Consumed by SPV per day 6400 

No of working days  300 

Load Factor %  75% 

Cost Rs. per unit INR  7 

Annual Electricity Cost  (Rs Lakhs) at Maximum Load usage  101 

 12.2.6 Water  production  charges:  A  total  of  2407  KLD  of water will  be  required  for Maintenance  of 

Common Facilities once it is operational. The water production costs are assumed as per the Table below:‐ 

 

Water Expenses 

Daily water usage(in KLD)  2407 

No of days  300 

Cost per Litre INR  0.01 

Annual Cost of Water INR Lakhs 72.21 

  12.2.7 Communication& Videoconferencing Expenses: This is assumed at Rs 12 Lakhs per annum.    

EMC AT ANNUR, COIMBATORE – FINAL DPR 

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 112 

   

 12.2.8 Employee Expenses: For smooth day to day operations of the cluster the following employees are 

required. Security and Housekeeping may be out sourced. The employee expenses are as given  in the Table below:‐ 

Employee Type  Number

MonthlySalary INR 

Annual Salary 

INR Lakhs

Annual Benefits INR Lakhs 

Annual Total CTC INR Lakhs 

COO  1  125000 15.0 3.0  18.0

Manager  2  60000 14.4 2.9  17.3

Accountants  1 30000 3.6 0.7  4.3

Clerks  2  12000 2.9 0.6  3.5

Technical staff  3  25000 9.0 1.8  10.8

Security  40  10000 48.0 9.6  57.6

Housekeeping  40 10000 48.0 9.6  57.6

IT  2  40000 9.6 1.9  11.5

Office Support Staff  20  12000 28.8 5.8  34.6

Annual Manpower Cost  111 179.3 35.9  215.1

Annual  Benefits  ‐  (%  of Salary) 

20%  

Attrition  5%  10.8

Annual  Employee  Cost  (incl. attrition)   

       226

 12.2.9 Insurance: Insurance costs are assumed at 0.25% of the total project cost.  12.2.10 Marketing: Marketing  expenses  are  assumed  for  first  3  years.  This  is  the  cost  associated with 

marketing activities for the cluster and brokerage for sale of land (revenue from sale of plot). This is assumed at 5% of the land value. 

 12.2.11 Land value: This is the cost incurred in purchase of the land by SPV.  12.2.12 CSR:   Corporate Social Responsibility programmes are planned and  initially during  construction 

0.50% of  the project  cost and after  the cluster becomes operational 0.50% of  the PAT  is being allocated for these activities. 

 12.2.13 Maintenance cost on infrastructure: This is the cost incurred on asset replenishment and general 

maintenance of the infrastructure.  This is expected to be 5% of the Capex once in every 5 years after the cluster becomes operational.  

    

EMC AT ANNUR, COIMBATORE – FINAL DPR 

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 113 

   

 12.3 Financial highlights  

 12.3.1 The project IRR is 13.27% across 20 years and the Equity IRR is 15.31%. The Project NPV is Rs 140 

Lakhs and Equity NPV is 703 Lakhs, both at a discounted rate of 13%.   

Key Output

Average DSCR  1.53 

Project IRR  14.31% 

Equity IRR  17.11% 

Project NPV INR Lakhs  13% 694

Equity NPV INR Lakhs   13% 1,258 

  

12.3.2 Sensitivity analysis: Effect of change in project cost on Equity IRR and Project IRR. Following are the different scenarios and how Equity and Project IRR is affected due to change in Project Cost:‐  

 

Change in Project Cost 

   Project IRR  Equity IRR

   14.31% 17.11%

‐15%  20.93% 34.55%

‐10%  18.26% 25.85%

‐5%  16.09% 20.66%

0%  14.31% 17.11%

5%  12.79% 14.44%

10%  11.48% 12.33%

15%  10.34% 10.61%

 12.3.3 Effect of Change in Sale Price of Land on Equity IRR and Project IRR.  Following are the different 

scenarios and how Equity and Project IRR are affected due to change in Sale Price of Land:‐   

Change in Sale Price

Project IRR  Equity IRR 

14.31% 17.11%

‐15%  12.54% 13.81%

‐10%  13.10% 14.78%

‐5%  13.69% 15.86%

0%  14.31% 17.11%

5%  14.96% 18.55%

10%  15.66% 20.27%

15%  16.39% 22.38%

   

EMC AT ANNUR, COIMBATORE – FINAL DPR 

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 114 

   

12.3.4 Following are the different scenarios and how Project IRR are affected due to change in Sale Price of Land and change in Project Cost simultaneously:‐  

 

      Change in Sale Price 

   14.31%  ‐15% ‐10% ‐5% 0% 5%  10%  15%

Change in 

Project Cost 

‐15%  17.92% 18.85% 19.85% 20.93% 22.10%  23.36%  24.72%

‐10%  15.79% 16.56% 17.38% 18.26% 19.20%  20.20%  21.28%

‐5%  14.03% 14.68% 15.37% 16.09% 16.87%  17.70%  18.58%

0%  12.54% 13.10% 13.69% 14.31% 14.96%  15.66%  16.39%

5%  11.25% 11.74% 12.25% 12.79% 13.35%  13.95%  14.58%

10%  10.13% 10.56% 11.01% 11.48% 11.97%  12.49%  13.03%

15%  9.13% 9.52% 9.92% 10.34% 10.77%  11.23%  11.70%

       

EMC AT ANNUR, COIMBATORE – FINAL DPR 

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 115 

   

 

CHAPTER 13  

SUSTAINABILITY  

The success and sustainability of any project hinges around the following components:‐  

a) Stake Holder Commitment b) Economic Viability & Operational Sustainability  c) Social Impact & Support d) Environmental Sustainability  e) Energy Conservation 

 13.1 Stakeholder commitment 

The key stake holders of the project are:‐ a) Local Population b) Consortium Members c) Managing Team d) Constituent Units  e) Government of Tamil Nadu f) Government of India  

 13.1.1 Local  population:    The  local  population  benefits  hugely  in  terms  of  employment  generation  for 

both  unskilled  and  skilled  section.    The  EMC  would  also  enable many  to  upgrade  their  skills, improve quality of life and enhance opportunity for local vendors. The EMC is part of an integrated industrial  park  with  other  clusters  for  food  processing,  textiles, MSME,  IT  /  ITES,  health  care, Knowledge Park amongst other components, which would provide  immense opportunities for the local population to enhance their socio‐economic status.  The external support infrastructure would improve  considerably  and  improve  transportation  in  the  area.    Considerable  corporate  social responsibility  programmes  are  planned  for  the  local  area,  which  includes  urban  forestry, educational aids, health care, medical infrastructure and free drinking water facilities. A number of outreach programmes are being planned to sensitize/inform the local population of the advantages of the EMC. The local population is fully supportive of for setting up the park and is in anticipation of  its completion as per stakeholder meetings conducted with  them.   The Tahsildar has given no objection certificate to upgrade the area to an industrial one.   

13.1.2 Consortium members:  The consortium members are fully committed to developing and managing the EMC.   They bring their vast experience  in governing, managing and establishing complex  large scale  projects  and  are  anxious  to  start  the  development.    The  consortium members  have  fully agreed to raise the capital  for development as per financial closure.   The MoU  is already  in place binding  the common objectives and  roles.   The debt component of  the  financial closure  is being made  available  through  the  good  will  of  the  consortium  members.    The  consortium  is  also committing  upfront  of  the  2.5%  of  development  cost  that  needs  to  be  collected  from  the constituent units.  The land has already been procured by the Chief Promoter and its affiliate.  Once 

EMC AT ANNUR, COIMBATORE – FINAL DPR 

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 116 

   

the DPR  is  approved,  governing  policies  for  the  EMC would  be  laid  down which would  include sustainable development, social upliftment, energy conservation, water usage,  land use planning, waste managementetc.   One of the consortium members is the Electronic Industries Association of India  (ELCINA), an  industry association dedicated  to development of Electronic  Industry  in  India.  The association is also on the board of SPV and is the guiding force in the proposed EMC.   

13.1.3 Managing  team:      The managing  team  consists  of  highly  qualified  and  eminent  people whose experience  would  be  of  great  benefit  to  the  park  and  are  committed  professionals with  large project experience.  Write up on the management team is available under Chapter 8, Management Arrangements.     At  this  stage  itself,  the  following actions have been  taken even before  the  final approval  of  this DPR which  reflects  the  commitment of  both  the  consortium members  and  the managing team:‐ 

a) A reputed branding agency has already been hired and is on the job of creating a brand for  the EMC. The website www.prime641.com has been uploaded and a  logo  for  the Industrial Park has been created.  

b) The  Management  team  is  already  in  discussions  with  leading  companies  like  E&Y, KPMG, ASIPAC etc. for the promotion of the EMC.   

c) Some of the major prospective players have been contacted for setting up units in the EMC    include Alstom Transport  , France, Blue Star  India Ltd, Chennai, Assetz Property Group,  Bengaluru  & M/s. Maxworth  Consumer  Products,  Hyderabad.    The  team  is already in the lookout for a reputed implementation agency for the development of the project.   Only contractors of repute will be employed. A monitoring committee is being set up by the Chief Promoter to monitor the project.  

d) Marketing activities carried out are mentioned in Chapter 7, Ongoing Initiatives.   

13.1.4 Constituent units:  Post development of the EMC (being considered at the construction stage), the board of the SPV will have 7 members out of a total of 12 members decided as per the Consortium MoU, from the constituent units.  Along with the Electronic Industries Association of India, they will have  an  absolute  majority  in  the  running  of  the  EMC.  These  members  would  represent  the constituent  units  and will  strive  to  leverage  the  synergies  available  in  the  EMC.    They will  also promote  and  support  policies  on  business  improvement,  social  development,  environmental conservation and energy conservation.  

13.1.5 Government  of  Tamil  Nadu:      The  Government  of  Tamil  Nadu  has  undertaken  Electronics Manufacturing  as  a  core  sector  to  be  developed.    This  EMC  supports  the  State’s  initiates  in developing the electronic manufacturing eco system.   The State  is  in the process of developing an electronics policy to support the  industry.     The State  is already committed to this  Industrial Park vide the MoU signed with the Chief Promoter.     Moreover the State’s commitment to the project has  been  confirmed  vide  a  letter  issued  by  the  State  and  submitted  to DeitY  during  the  initial application.  

 13.1.6 Government of  India:   The Government of  India has  launched a number of Policy  initiatives and   

Strategies to promote Electronics Manufacturing in the country, which includes creation of National Policy on Electronics and under  it the EMC Scheme, the MSIPS scheme and     PMA and  in addition various  fiscal  incentives, as mentioned  in Chapter 1, Context/Background to this report.   This  is a 

EMC AT ANNUR, COIMBATORE – FINAL DPR 

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 117 

   

priority sector for the Government, in principal approval has been granted by the Government for this EMC which reflects its commitment.   

13.2 Economic viability & operational sustainability  

13.2.1 Economic viability: The project IRR is 14.21% and the Equity IRR is 16.94%. The NPV is Rs 644 Lakhs and Equity NPV is 1208 Lakhs. IRR for the project remains attractive at a number of scenarios which includes change in project cost and change in revenues up to 15% up or down. The details are given in Chapter 12, Financial & Economic Analysis.  

13.2.2 Operational sustainability:   Operations and Maintenance of the  infrastructure  is planned through the following revenue streams:‐ 

 a) Operations & Maintenance of Common  Infrastructure:   The operations and maintenance of 

common  infrastructure  is being carried out by charging the constituent units a % of Capex as shown in the Table below:‐  

 

Basic Development  Boundary wall, internal roads, street lighting, external storm water drainage.  3%

Essential Services  Government support office, water treatment plant, sewage lines / treatment, waste disposal / recycling/ water harvesting, Electricity substation/distribution, backup power plant, warehousing   5%

Government Regulatory support/services 

Entry/ exit, Security , time office & government support offices  3%

Landscaping (green area) 

green area development @ Rs.500/sqmtr 8%

  

b) Long  term  maintenance  &  replenishment:    For  replenishing  and  major  maintenance  of infrastructure Rs 125/square meter of occupied area per constituent unit is being charged once in every 3 years starting from operational year of the EMC. 

 c) Both the above conditions will be  incorporated  in the  initial agreement between the SPV and 

the constituent units.     

EMC AT ANNUR, COIMBATORE – FINAL DPR 

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 118 

   

 13.3 Social impact & support:  

 The  impact  on  local  population  is  very  positive  and  there  is  complete  support  from  the  local population  for  the  project.Apart  from  employment  generation  and  local  infrastructure development a number of corporate social responsibility initiatives have been planned.  

 13.4 Environmental sustainability:   

A detailed  environment  impact  assessment has been  carried out  for  submission  to  the  relevant authorities.   A number of  initiatives have been built  into  the master plan asmentioned below  to ensure environmental sustainability:  a) The Master  Plan  complies with  the  guidelines  issued  by  Department  of  Town  and  Country 

Planning, GoTN and the Ministry of Environment and Forests, Government of India. b) Provisions of the National Building Code and prudent engineering practices have been followed 

in  preparing  the Master  Plan.  The Master  Plan  follows  the  zoning  concept  for meeting  the statutory norms of planning, to minimise the impact of pollution. 

c) The EMC has been planned as a ZERO‐DISCHARGE self‐sustainable one. d) The EMC will obtain a ‘green certification’.  e) STPs and ETP are planned in the EMC for treatment of waste water and effluents.  f) A green bin system to segregate waste is proposed.  g) Details of green initiatives are given in Chapter 4, Project Components, Para 4.5.  

13.5 Energy conservation:   a) During construction, local and low energy consuming materials with high recycle value content 

shall be used. b) Only energy efficient transformers will be installed.  c) The streetlights along the roads in the entire campus will be powered by solar energy.  

    

EMC AT ANNUR, COIMBATORE – FINAL DPR 

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 119 

   

 

CHAPTER 14  

CORPORATE SOCIAL RESPONSIBILITIES  

14.1 Introduction  

Corporate Social Responsibility  is a management concept whereby companies  integrate  social and environmental concerns in their business operations and interactions with their stakeholders. CSR is generally understood as being the way  through which a company achieves a balance of economic, environmental  and  social  imperatives  while  at  the  same  time  addressing  the  expectations  of shareholders and stakeholders. In this sense it is important to draw a distinction between CSR, which can be a  strategic business management concept, and charity,  sponsorships or philanthropy. Even though the  latter can also make a valuable contribution to poverty reduction, will directly enhance the  reputation  of  a  company  and  strengthen  its  brand,  the  concept  of  CSR  clearly  goes  beyond that.Promoting the uptake of CSR amongst infrastructure and industrial projects requires approaches that  fit  the  respective  needs  and  capacities  of  these  businesses,  and  do  not  adversely  affect  the economic viability.  A properly  implemented CSR concept can bring along a variety of competitive advantages, such as enhanced exposure to  industries and markets,  increased sales and profits, operational cost savings, improved  productivity  and  quality,  efficient  human  resource  base,  improved  brand  image  and reputation, enhanced customer loyalty, better decision making and risk management processes. 

 14.1 Vision  

AEEPPL’s  vision  is  to move beyond  compliance  and engage  in  actions  that  appear  to  foster  social good, beyond  the  interests of  the company and by not  just satisfying  law requirement. To actively bestow to the social and economic development of the communities surrounding the EMC, thereby aiding in building a better, sustainable way of life for the economically weaker sections of society and contribute to the betterment of the climate. 

 14.2 On‐going activities carried out by Chief Promoter:‐  

KESHRI CHAND PUNAM CHAND SETHI CHARITABLE TRUST has been established, which is a family and private charitable  trust  registered  in Guwahati, Assam.    Initiated by  the Chief Promoter under  the visionaries;  the  Late Shri.PunamChandSethi, Founder and Mathrushree Smt. MainadeviSethi, Chief Patron,  various  social welfare works  are  being  conducted  towardsproviding  free medical  support todisadvantaged communities in India. 

   

EMC AT ANNUR, COIMBATORE – FINAL DPR 

ADD‐ELCINA ELECTRONICS PARK PRIVATE LIMITED  Page 120 

   

14.3 Milestones achieved:‐  

Over the years, the above trust have contributed to many worthy causes, be it an artificial limbs camp, eye  camp, providing  educational  assistance  to poor  girls  and providing help  to  the underprivileged sections of the society, to name a few. 

 14.4 CSR initiativesin EMC  

Besides the above‐mentioned CSR activities, AEEPPL proposes to carry out the following:‐  14.4.1. Urban  forestry:‐  In order  to combat  the climate change, AEEPPL proposes  to plant about 1 Lakh 

tree saplings during the construction period  in the areas surrounding the EMC by employing  local personnel  as  public  relation  officers  who  will  be  equipped  with  all  the  infrastructure  for coordinating and maintaining the trees for next 3‐4 years. 

 14.4.2. Educational aids:‐ AEEPPL proposes to adopt a school each in the Panchayat limits of Kuppanur and 

Akkarisengapalli village adjacent and support the school children by providing uniforms, books and providing financial assistance to the economically weaker sections and as Swatch Bharat initiative, toilets and wash rooms will be constructedin schools apart  from compound walls and class room flooring. 

 14.4.3. Healthcare camps:  ‐ Regular healthcare camps will be set up  in and around the area surrounding 

EMC  for  the  betterment  of  locals  by  engaging  panel  of  doctors  including  eye,  ENT  and  general physicians & surgeons with mobile clinic.   Food and water will be supplied during the camp along with medicine in such camps. 

 14.4.4. Medical  infrastructure:  ‐ AEPPL would provide 2 ambulance vans each with  ICU  facilities on  the 

wheel for 3 hospitals in the Kuppanur and Akkarisengapalli villages adjacent to EMC for emergency purpose. 

 14.4.5. Drinking  water  facilities:‐  AEEPPL  proposes  to  set  up  2  RO  plants  each  in  Kuppanur  and 

Akkarisengapalli village to cater to the need  of pure drinking water to the locals, free of cost.  14.5 Budget allocation  

In order to meet the expenditure of the proposed CSR activities, AEEPPL has made a provision of about Rs.  83  lakhs  in  the  project  cost  estimate  of  EMC  during  the  construction  period  of  EMC  and subsequently  adequate  amount will  be  set  aside  towards  CSR  activities  during  the  operation  and maintenance of the EMC.