STARTUP MEETING MINUTES QATAR NATIONAL LIBRARY Form Ref : CMM 17, Dec 2009 Page 1 of 2 1.0 General ISSUE ACTION RESP. DUE DATE REVISED DUE DATE 1.1 Attendance All to complete the Attendance Register before leaving. ALL Note 1.2 Organisational Structure Have been included in the approved pre-qualification SC Note 2.0 Commercial ISSUE ACTION RESP. DUE DATE REVISED DUE DATE 2.1 Performance Bond Subcontractor is to submit a bond no later than 7 days after the sighing of Contract; SC Note 2.2 Advance Payment Bond Subcontract forwarded to Electra for sign off SC SUBJECT: ELECTRA STARTUP MEETING DATE: 23 rd of January at 2 30pm at BMMG QNL Site Office Mayyad Bader Amiel Rosendo Ilyas.M.S (Electra) Muralee Dharan (Electra) MB AR IS MD MINUTES BY: Mayyad Bader DISTRIBUTION: APOLOGIES: NEXT MEETING: All above and David Miller, Pedro J. Duarte, Jeremy Skues Wednesday 30 th of January 2013 at 2 30pm at BMMG QNL Site Office

Electra Weekly Progress Meeting Minutes 002

Embed Size (px)

DESCRIPTION

Minutes

Citation preview

  • STARTUP MEETING MINUTES QATAR NATIONAL LIBRARY

    Form Ref : CMM 17, Dec 2009

    Page 1 of 2

    1.0 General

    ISSUE ACTION RESP. DUE

    DATE REVISED

    DUE DATE

    1.1 Attendance All to complete the Attendance Register before leaving.

    ALL Note

    1.2 Organisational Structure Have been included in the approved pre-qualification

    SC Note

    2.0 Commercial

    ISSUE ACTION RESP. DUE

    DATE REVISED

    DUE DATE

    2.1 Performance Bond Subcontractor is to submit a bond no later than 7 days after the sighing of Contract;

    SC Note

    2.2 Advance Payment Bond Subcontract forwarded to Electra for sign off

    SC

    SUBJECT: ELECTRA STARTUP MEETING

    DATE: 23rd of January at 2 30pm at BMMG QNL Site Office

    Mayyad Bader

    Amiel Rosendo

    Ilyas.M.S (Electra)

    Muralee Dharan (Electra)

    MB

    AR

    IS

    MD

    MINUTES BY: Mayyad Bader

    DISTRIBUTION:

    APOLOGIES:

    NEXT MEETING:

    All above and David Miller, Pedro J. Duarte, Jeremy Skues

    Wednesday 30th of January 2013 at 2 30pm at BMMG QNL Site Office

  • STARTUP MEETING MINUTES QATAR NATIONAL LIBRARY

    Form Ref : CMM 17, Dec 2009

    Page 2 of 2

    3.0 Design

    ISSUE ACTION RESP. DUE

    DATE REVISED

    DUE DATE

    3.1 Drawings Subcontractor to submit Drawing Submittal Register, i.e a list of drawings to be approved for review and approval. Format included in subcontractor start-up package.

    SC 09.01.13 30.01.13

    3.2 Materials Subcontractor to submit Material Submittal Register, i.e. a list of materials to be approved / procured for review and approval. Format included in subcontractor start-up package.

    SC 09.01.13 30.01.13

    3.3 Mock up BMMG requested from Electra to provide extra samples of panels and pedestal in order to create three separate mock ups for the timber flooring with the raised floor

    SC 30.01.13

    4.0 Construction

    ISSUE ACTION RESP. DUE

    DATE REVISED

    DUE DATE

    4.1 Programme BMMG to issue the Clause 8.3 programme. Subcontractor is to submit detailed programme within 10 days thereafter.

    BMMG TBA

    4.2 Construction Methodology List of required method statements to be submitted.

    SC 09.01.13 30.01.13

    5.0 Health and Safety, Quality, Environment

    ISSUE ACTION RESP. DUE

    DATE REVISED

    DUE DATE

    5.1 Quality Plan Subcontractor is to submit and obtain approval for their Quality Plan prior to commencement of works onsite.

    SC 28.01.13

    6.0 Other Business

    ISSUE ACTION RESP. DUE

    DATE REVISED

    DUE DATE

    6.1 Next Meeting Please note that the next meeting is scheduled for the 30th of January 2013

    SC 30.01.13