STARTUP MEETING MINUTES QATAR NATIONAL LIBRARY
Form Ref : CMM 17, Dec 2009
Page 1 of 2
1.0 General
ISSUE ACTION RESP. DUE
DATE REVISED
DUE DATE
1.1 Attendance All to complete the Attendance Register before leaving.
ALL Note
1.2 Organisational Structure Have been included in the approved pre-qualification
SC Note
2.0 Commercial
ISSUE ACTION RESP. DUE
DATE REVISED
DUE DATE
2.1 Performance Bond Subcontractor is to submit a bond no later than 7 days after the sighing of Contract;
SC Note
2.2 Advance Payment Bond Subcontract forwarded to Electra for sign off
SC
SUBJECT: ELECTRA STARTUP MEETING
DATE: 23rd of January at 2 30pm at BMMG QNL Site Office
Mayyad Bader
Amiel Rosendo
Ilyas.M.S (Electra)
Muralee Dharan (Electra)
MB
AR
IS
MD
MINUTES BY: Mayyad Bader
DISTRIBUTION:
APOLOGIES:
NEXT MEETING:
All above and David Miller, Pedro J. Duarte, Jeremy Skues
Wednesday 30th of January 2013 at 2 30pm at BMMG QNL Site Office
STARTUP MEETING MINUTES QATAR NATIONAL LIBRARY
Form Ref : CMM 17, Dec 2009
Page 2 of 2
3.0 Design
ISSUE ACTION RESP. DUE
DATE REVISED
DUE DATE
3.1 Drawings Subcontractor to submit Drawing Submittal Register, i.e a list of drawings to be approved for review and approval. Format included in subcontractor start-up package.
SC 09.01.13 30.01.13
3.2 Materials Subcontractor to submit Material Submittal Register, i.e. a list of materials to be approved / procured for review and approval. Format included in subcontractor start-up package.
SC 09.01.13 30.01.13
3.3 Mock up BMMG requested from Electra to provide extra samples of panels and pedestal in order to create three separate mock ups for the timber flooring with the raised floor
SC 30.01.13
4.0 Construction
ISSUE ACTION RESP. DUE
DATE REVISED
DUE DATE
4.1 Programme BMMG to issue the Clause 8.3 programme. Subcontractor is to submit detailed programme within 10 days thereafter.
BMMG TBA
4.2 Construction Methodology List of required method statements to be submitted.
SC 09.01.13 30.01.13
5.0 Health and Safety, Quality, Environment
ISSUE ACTION RESP. DUE
DATE REVISED
DUE DATE
5.1 Quality Plan Subcontractor is to submit and obtain approval for their Quality Plan prior to commencement of works onsite.
SC 28.01.13
6.0 Other Business
ISSUE ACTION RESP. DUE
DATE REVISED
DUE DATE
6.1 Next Meeting Please note that the next meeting is scheduled for the 30th of January 2013
SC 30.01.13