Engineering and Commercial Infrastructure - Transport & Drainage Monthly Review March 2019

ECI - Transport Drainage Monthly Review - March 2019 · Page 4 Engineering & Commercial Infrastructure Monthly Review > March 2019 SAFETY 1.1. Incidents and Injuries The incident

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ECI - Transport Drainage Monthly Review - March 2019 · Page 4 Engineering & Commercial Infrastructure Monthly Review > March 2019 SAFETY 1.1. Incidents and Injuries The incident

 1  [Type the document title] 

Engineering and Commercial Infrastructure -

Transport & Drainage

Monthly Review March 2019

Page 2: ECI - Transport Drainage Monthly Review - March 2019 · Page 4 Engineering & Commercial Infrastructure Monthly Review > March 2019 SAFETY 1.1. Incidents and Injuries The incident

 

 

Page 2

Engineering & Commercial Infrastructure Monthly Review > March 2019

OVERVIEW ............................................................................................................................. 3 

SAFETY ................................................................................................................................ 4 

1.1.  Incidents and Injuries .................................................................................................. 4 1.2.  Lost Time Injuries & Days Lost .................................................................................... 5 

FINANCE .............................................................................................................................. 6 

2.1.  Operational Financial Report - 1 July 2018 - 30 November 2018 ............................... 6 

MAINTENANCE ACTIVITIES ......................................................................................... 6 

3.1  Road and Drainage Maintenance Activities ................................................................ 7 3.2  Unsealed Road Maintenance Activities ....................................................................... 7 3.3  Open Drainage Maintenance ...................................................................................... 7 3.4  Bridge Management .................................................................................................... 8 3.5  Cyclone Debbie – REPA Repairs and Category D Betterment/Beach Restoration..... 8 

CLIENT SURVEYS .......................................................................................................... 11 

4.1  Requests for Maintenance Work ............................................................................... 11 

Projects ............................................................................................................................. 12 

5.1  Significant Projects .................................................................................................... 12 

 

Page 3: ECI - Transport Drainage Monthly Review - March 2019 · Page 4 Engineering & Commercial Infrastructure Monthly Review > March 2019 SAFETY 1.1. Incidents and Injuries The incident

 

 

Page 3

Engineering & Commercial Infrastructure Monthly Review > March 2019

OVERVIEW

This report is for Transport and Drainage activities during the period 1 December 2018 - 31 January 2019. Significant items in this period include:

There were no LTI’s during the month of March 2019.

Grading Teams are continuing to undertake programmed grading and gravelling works including the remaining NDRRA Restoration Works associated with TC Debbie. However, wet weather has continued to disrupt the works Program causing delays.

Special Open Drainage Maintenance has commenced with reshaping and de-silting work completed at Zamia Street Drain, and desilting at Willman’s Road Drain. Planned works are scheduled for Cabbage Tree/Aspley Way Drain and Bridge Road Drain wall instability repairs.

The geotechnical site investigation and engineering surveys of the Dalrymple Road landslips have been completed. The draft geotechnical report detailing the cause and extent of the landslips and restoration options has been completed and has been reviewed. The final report will form the basis of the Restoration Funding Submission to the Queensland Reconstruction Authority.

The Midge Point Sand Nourishment Project commenced in late February 2019 and is approximately 55% complete. The revegetation and fencing will be undertaken during April 2019.

The Lamberts Beach Sand Nourishment Project commenced in mid-February 2019 and is approximately 60% complete. The revegetation and fencing will be undertaken from April 2019 to May 2019 as each section of the sand nourishment is completed.

Director Engineering & Commercial Infrastructure  

Page 4: ECI - Transport Drainage Monthly Review - March 2019 · Page 4 Engineering & Commercial Infrastructure Monthly Review > March 2019 SAFETY 1.1. Incidents and Injuries The incident

 

 

Page 4

Engineering & Commercial Infrastructure Monthly Review > March 2019

SAFETY

1.1. Incidents and Injuries

The incident statistic details a summary of the Transport and Drainage safety incident performance. Transport and Drainage aspires to achieve zero harm with a stretch target of zero injuries.

March 2019 Summary:

No. of Incidents

Mechanism of injury Injury Type

5 Vehicle Incidents Asset Damage

1 Muscular Stress Suitable Duties Injury

1 Being Hit by Moving Objects

Suitable Duties Injury

1 Psychological Near Miss

1 Bite/Sting Medical Treatment Injury

1 Muscular Stress Medical Treatment Injury

1 Vehicle Incident Member of Public

5

6

17

10

8 8

10

6

8 8

11

12

11

0 0 0 0 0

1

0 0 0 0 0 0 00 0

1 1 1

0 0

1

2

0

1

2

1

2

3

2

1

3

0

3 3

2

1

2

0

2

4

6

8

10

12

14

16

18

Total Incidents Lost Time Injuries Total Recordable Injuries All Injuries

Page 5: ECI - Transport Drainage Monthly Review - March 2019 · Page 4 Engineering & Commercial Infrastructure Monthly Review > March 2019 SAFETY 1.1. Incidents and Injuries The incident

 

 

Page 5

Engineering & Commercial Infrastructure Monthly Review > March 2019

1.2. Lost Time Injuries & Days Lost

Transport and Drainage aspires to achieve zero Lost Time Injuries by improving safety performance by developing a proactive safety culture and implementing best practice safety management across all business areas

March 2019 Summary:

11 incidents were reported during the March 2019 period. For the 2018/2019 year to date, there has been one (1) Lost Time Injury.

Department

2014-15 201516 2016-17 2017-18 2018-19

LTI Days Lost LTI Days Lost LTI Days Lost LTI Days Lost LTI Days Lost

Civil Operations 8 214 3 130 3 21 1 13Transport & Infrastructure Projects 3 19 1 11 Technical Services 1 17 Transport & Drainage 11 233 5 158 3 21 1 13

233

158

021 13

11

5

0

3

1

0

2

4

6

8

10

12

0

50

100

150

200

250

2014‐15 2015‐16 2016‐17 2017‐18 2018‐19

TADAB Total Days Lost TADAB Total LTIs

Page 6: ECI - Transport Drainage Monthly Review - March 2019 · Page 4 Engineering & Commercial Infrastructure Monthly Review > March 2019 SAFETY 1.1. Incidents and Injuries The incident

 

 

Page 6

Engineering & Commercial Infrastructure Monthly Review > March 2019

FINANCE

2.1. Operational Financial Report - 1 July 2018 - 31 March 2019

 

 

 

 

 

NTENANCE ACTIVITIES 

Financial Performance Report % YTD Variance of YTD Budget

Period Covered: 1 July 2018 to 31 March 2019 YTD Variance favourable of budget

YTD Variance unfavourable, between 0% and 5% of YTD Budget

YTD Variance unfavourable, more than 5% of YTD Budget

RevisedBudget

YTDBudget

YTDActual

YTDVariance

Comments

5.01 - Engineering Management (623,684) (756,818) (763,198) (6,379)

5.02 - Civil Operations 17,749,469 13,148,022 12,284,331 (863,691)

5.03 - Transport and Drainage Infrastructure Planning 5,941,497 3,565,778 3,191,726 (374,052)

Operating (surplus) / deficit 23,067,282 15,956,981 14,712,859 (1,244,123)

Engineering

Mainly savings against Wages & Plant Hire offset by $3K increase in discounts allowed.

Income $397K less which is comprised of $175K timing difference and $222K of RMPC income not received (to March Budget review (MBR)). Wages is $186K less than budget to be offset by overspend against NDDRA. Materials & Services including Internal Transfers are $1121K less than budget mainly due to $222K expenses to MBR to offset income from RMPC, $121K timing differences and $780K Internal Plant Hire offset by overspends in NDDRA.

Income $15K more than budget (External enquiries and Traffic Management Plans $10K, Traffic Counters sold $5K). Wages is $144K less than budget of which $48K included in MBR. Materials & Services including Internal Transfers is $215K less than budget mainly due to timing differences.

-

5,000,000

10,000,000

15,000,000

20,000,000

25,000,000

July August September October November December January February March April May June

Operating (Surplus) / Deficit

YTD Budget YTD Actual

Page 7: ECI - Transport Drainage Monthly Review - March 2019 · Page 4 Engineering & Commercial Infrastructure Monthly Review > March 2019 SAFETY 1.1. Incidents and Injuries The incident

 

 

Page 7

Engineering & Commercial Infrastructure Monthly Review > March 2019

3.1 Road and Drainage Maintenance Activities

The following chart details maintenance activities completed during the period as recorded in our Maintenance Management System, DeltaS, in comparison with the monthly average.

A high volume of maintenance activities has been delivered in response to client requests and defects identified during inspections.

3.2 Unsealed Road Maintenance Activities

Grading Teams are continuing to undertake programmed grading and gravelling works including the remaining NDRRA Restoration Works associated with TC Debbie. However, wet weather has continued to disrupt the Works Program causing delays. Also, emergent works associated with the declared Monsoon Trough event are being undertaken by Grading and Minor Works Crews.

An additional internal crew has been mobilised to undertake unsealed roads work in the Southern area; eight crews are now undertaking grading and gravelling works.

0

20

40

60

80

100

120

140

160

180

200

Completed Maintenance Activities

Completed Works Orders March 2019 Monthly Average

Page 8: ECI - Transport Drainage Monthly Review - March 2019 · Page 4 Engineering & Commercial Infrastructure Monthly Review > March 2019 SAFETY 1.1. Incidents and Injuries The incident

 

 

Page 8

Engineering & Commercial Infrastructure Monthly Review > March 2019

3.3 Open Drainage Maintenance

Special Open Drainage Maintenance has re-commenced with works on both Zamia Street Drain and Wallman's Road Drain completed. Works are planned on Bridge Road Drain and Cabbage Tree/Apsley Way Drain to undertake scour repairs and de-silting.

The Open Drains Crews are working extra hours to address the backlog of mowing and vegetation control as a result of delays associated with the wet weather.

3.4 Bridge Management

The Bridge Crew and Technical Officer are scheduled to attend a 3-day intensive Timber Bridge Maintenance and Restoration Training Course, being delivered by an external consultant, to upskill and increase knowledge and capability.  

3.5 Cyclone Debbie and NQ & FNQ Monsoon Trough Works

Cyclone Debbie - Road Works (Category B & D)

Repairs to landslips on Chelmans Road and Dalrymple Road are progressing with completion due at the end of April 2019.

Grading and gravelling of the damaged sections of the Unsealed Road Network was undertaken in February 2019 with approximately 90% of the works completed to date. These works are being undertaken by day labour and contractor grading crews in conjunction with normal maintenance and Works for Queensland works. Other restoration works are progressing. All restoration works will be completed by mid-June 2019.

The construction of the Clews Road Floodway has been halted by ongoing high creek flows. It is planned to recommence work mid-April 2019. The associated fish ladder will be built in May 2019 when the creek flows are low.

0

12

34

56

78

9

10

NDRRA REPARepairs

Heavy FormationGrading

MediumFormationGrading

W4Q2 Gradingand Gravelling

RoadsideDrainage

Shoulder Grading

KM of Road

 Maintained

March Unsealed Road Maintenance

Unsealed Road Mainenance March 2019

 

Page 9: ECI - Transport Drainage Monthly Review - March 2019 · Page 4 Engineering & Commercial Infrastructure Monthly Review > March 2019 SAFETY 1.1. Incidents and Injuries The incident

 

 

Page 9

Engineering & Commercial Infrastructure Monthly Review > March 2019

Cyclone Debbie - Beach Restoration (Category D & Resilience)

The Midge Point Sand Nourishment Project commenced in late February 2019 and is approximately 55% complete. The revegetation and fencing will be undertaken during April 2019.

The Lamberts Beach Sand Nourishment Project commenced in mid-February 2019 and is approximately 60% complete. The revegetation and fencing will be undertaken from April 2019 to May 2019 as each section of the sand nourishment is completed.

The detailed design of the St Helens Beach Groyne Project ($0.24M) and the necessary Permit Application have been prepared. The design has been reviewed and is being finalised. Once the design is finalised the Prescribed Tidal Works Permit will be lodged. It is anticipated that works will be undertaken in June/July 2019.

Midge Point Sand Nourishment Project  

Page 10: ECI - Transport Drainage Monthly Review - March 2019 · Page 4 Engineering & Commercial Infrastructure Monthly Review > March 2019 SAFETY 1.1. Incidents and Injuries The incident

 

 

Page 10

Engineering & Commercial Infrastructure Monthly Review > March 2019

NQ & FNQ Monsoon Trough – Road Restoration Works

Emergency repair works are being undertaken as necessary on damaged sections of the road network. These works need to be completed in the first 90 days following the event.

The geotechnical site investigation and engineering surveys of the Dalrymple Road landslips have been completed. The draft geotechnical report detailing the cause and extent of the landslips and restoration options has been completed and has been reviewed. The final report will form the basis of the Restoration Funding Submission to the Queensland Reconstruction Authority.

A preliminary design for the reconstruction of the Boundary Creek Causeway is being prepared. The design will need to address fish passage requirements as the creek is a major impact waterway and it will need a Development Application for a Waterway Barrier Permit. Once the preliminary design is finalised the Restoration Funding Submission will be lodged.

Lamberts Beach Sand Nourishment 

Project  

Page 11: ECI - Transport Drainage Monthly Review - March 2019 · Page 4 Engineering & Commercial Infrastructure Monthly Review > March 2019 SAFETY 1.1. Incidents and Injuries The incident

 

 

Page 11

Engineering & Commercial Infrastructure Monthly Review > March 2019

4.1 Requests for Maintenance Work

Results of Customer Survey (January / February 2019)

Representative Comments Trends A great crew, respectful and very courteous No one replied back to tell me they will send someone out

to fix it. Council staff attended to maintenance within 48 hours A nice neat finish just a patch, it will come up again in the next big storm Not started, let alone completed. The corrected sign is as good as new. I was surprised how

quickly the job was completed because of the nature of the repair I thought it would have taken longer.

If all Council employees are as competent, efficient and friendly as this crew, my rates are being well spent

Excellent. Was 4.45pm when I made the initial call. The lady was helpful and not fazed about getting the information. Was easy and fast considering the time of day and the weather situation.

Timely.

Page 12: ECI - Transport Drainage Monthly Review - March 2019 · Page 4 Engineering & Commercial Infrastructure Monthly Review > March 2019 SAFETY 1.1. Incidents and Injuries The incident

 

 

Page 12

Engineering & Commercial Infrastructure Monthly Review > March 2019

PROJECTS

5.1 Significant Projects

Significant Projects are assessed considering the Project Cost, the Project Risk and/or Community Interest. The following information was current as of 26 November 2018.

Council Project Management Phases

1. Planning (Plan) 2. Design (Des) 3. Procurement (Proc) 4. Construction (Con)

Indicators

On Track Potential Issue Definite Issue

PROJECT  PHASE PHASE % 

COMPLETE INDICATORS 

ORIGINAL 

BUDGET DETAILS COMMENTS 

Land Acquisition and Drain Construction Ferris Gully

Con 97%

Schedule

Scheduled Completion Date:

January 2019

Original Budget:

$6.7M (over multiple years)

Final planting has been delayed again due to weather creating issues with access. Practical Completion now expected end of April 2019.

Budget

Other Issues/

Risk

Casey Avenue Upgrade –

Con 98%

Schedule

Scheduled Completion Date:

Dec 2018

Original Budget: $1,700,000

Site works completed. As-Cons to be finalised. Budget

Other

Issues/

Risk

Fourways Drainage Design 100%

Schedule Scheduled

Completion Date:

March 2019

Original Budget:

$2.48M

Amended Budget:

$2.48M

Project deferred.

Budget

Other Issues/

Risk

Cod Hole Con 100% Schedule Scheduled

Completion Date:

Complete

Budget

Page 13: ECI - Transport Drainage Monthly Review - March 2019 · Page 4 Engineering & Commercial Infrastructure Monthly Review > March 2019 SAFETY 1.1. Incidents and Injuries The incident

 

 

Page 13

Engineering & Commercial Infrastructure Monthly Review > March 2019

PROJECT  PHASE PHASE % 

COMPLETE INDICATORS 

ORIGINAL 

BUDGET DETAILS COMMENTS 

Other Issues/

Risk

November 2018

Original Budget:

$3.2M

Amended Budget:

$3.2M