DZero Run IIb PMGJanuary 28, 2003
1
AgendaRun IIb D-Zero PMG
January 28, 2003
Overview, issues (Kotcher) Project status (O’Dell) Trigger technical status (Wood) AOB
Jon KotcherDZero Run IIb PMGJanuary 28, 2003
DZero Run IIb PMGJanuary 28, 2003
2
Run IIb Project Organization
D0 Run IIb ProjectJ. Kotcher, Project Manager
R. Partridge, Deputy; V. O’Dell, Associate; W. Freeman, Assistant
M. Johnson, Technical Coordinator C. Yoshikawa, Budget Officer; T. Erickson, Administration
WBS 1.1Silicon
M. DemarteauTBD
1.1.1 Sensors R. Demina, F. Lehner
1.1.2 Readout SystemA. Nomerotski, E. von Toerne
1.1.4 QA, Testing, & Burn-inC. Gerber, TBD
1.1.3, 1.1.5 Mechanics & Assembly
W. Cooper, K. Krempetz
1.1.6 MonitoringM. Corcoran, S. de Jong
1.1.4 ProductionJ. Fast, TBD
1.1.7 Software & Simulation F. Rizatdinova, L Shabalina
WBS 1.2Trigger
H. Evans D. Wood
1.2.3 L1 Track TriggerM. Narain
1.2.1 L1 Cal UpgradeM. Abolins, (H. Evans),
P. LeDu
1.2.4 L2UpgradeR. Hirosky
1.2.5 Silicon Track Trigger U. Heintz
WBS 1.3DAQ/Online
S. FuessP. Slattery
1.2.2 L1 Cal/Track MatchK. Johns
1.2.6 SimulationM. Hildreth, E. Perez
WBS 1.5 Installation
R. Smith
1.5.1 Silicon InstallationMechanical:H. Lubatti
Electronics: L. Bagby, R. Sidwell
1.5.2 Trigger InstallationD. Edmunds
WBS 1.4Project
Administration
1.2.7 Administration(D. Wood)
1.1.8 Administration(M. Demarteau)
1.3.3 Control SystemsF. Bartlett, G. Savage,
V. Sirotenko
1.3.1 Level 3 SystemsD. Chapin, G. Watts
1.3.4 DAQ/Online Management(P. Slattery)
1.3.2 Network & Host Systems
J. Fitzmaurice, S. Krzywdzinski
Red: Today’s speakersBlue: New silicon co-leader will be in place
Mar 1Agreement with Alice Bean was one year, ended
Aug ’02Two silicon Level 3 subsystems need co-leaders
DZero Run IIb PMGJanuary 28, 2003
3
Overview of Status Schedule “statussed” for Dec 1-31 time period (talk by O’Dell)
Second full shot since Nov 4-8 EIR Monthly effort reports being handled in straightforward manner
Work package assignments to individuals’ effort made by WBS Level 3 personnel in hour or two
Returned to Project Office, double-checked before sending to PPD Lunar report cycle:
Wk –1: Effort reports finalized Wk 1-2: Status schedule, collect monthly report information Wk 3: Integrate information, edit reports, identify change control,
discuss with project Wk 4: Report Laboratory, hand in to DOE
First monthly report drafted (bootstrapped from NuMI report) Overview of project status Milestone status & summary (includes Gantt) Narrative highlights to WBS Level 3 Variance analysis Cost reports
Tables to WBS Level 3, plots to WBS Level 2 Pending final approval, only BCWS available
DZero Run IIb PMGJanuary 28, 2003
4
Overview of Status
Have suggested COBRA/reporting meeting with all principals Want to have final machinery in place in anticipation of FY03
spending approval; many details to consider, commonality: Inclusion (or not) of R&D Handling of pass-through COBRA report output Change control/variance thresholds Timing of consultant visit Finalize form of monthly reports Tracking university costs Integration of actuals …
OPMO on board, setting it up “Office of Project Management Oversight”
First Production Readiness Review will take place Jan 30 “Purple Card” for silicon readout during testing, production Does not go in final detector, used for stand-alone testing at
SiDet Was useful test bed for PRR process, worked quite smoothly
DZero Run IIb PMGJanuary 28, 2003
5
Purple Card PRR
Review Committee: C. Gerber (UIC) J. Green (Fermilab) K. Hanagaki (Fermilab) S. Lager (Stockholm) R. Lipton (Fermilab, Chair) R. Sidwell (KSU)
DZero Run IIb PMGJanuary 28, 2003
6
Some Near-Term Silicon Milestones
Six Major Upcoming Silicon Milestones
Project Target Date
Current Forecast
Baseline Date
Comments
Silicon Prototype Mechanical Stave Built
12/16/03 12/18/03 1/6/03 Major integration milestone – was met
L2-L5 Sensors Released for Production
2/11/03 2/18/03 3/24/03 Further delays expected; characterizing sensors. Should not extend to baseline date.
SVX4 Released for Production
7/10/03 8/19/03 10/20/03 Excellent performance of initial prototype
Successful Fabrication of Electrical-Grade Pre-Production Silicon Stave*
7/17/03 7/24/03 10/10/03 Major integration milestone
Successful Readout of Full Silicon Stave
10/10/03 10/17/03 1/29/04 Major integration milestone
Silicon Module Production Begun
2/16/04 2/16/04 5/17/04 Remains on track* Not a DOE L2/Director’s
MilestoneForecasts remain
well ahead of baseline dates
DZero Run IIb PMGJanuary 28, 2003
7
Some Near-Term Level 1 Trigger Milestones
Five Major Upcoming Silicon Milestones
Project Target Date
Current Forecast
Baseline Date
Comments
L1 ADF shipped to Fermilab 5/2/03 6/23/03 7/11/03 Saclay designing, fabricating L1 cal front-end
L1 Calorimeter Trigger TAB/GAB Prototype Complete
7/16/03 7/15/03 9/29/03 Columbia/Nevis
ADF+TAB Prototype Integration
7/17/03 7/16/03 9/30/03 Major integration milestone: in-situ integration summer ’03
L1 CTT Algorithm Firmware Coded & Simulated with FPGA Simulation Tools
7/17/03 7/11/03 9/15/03 First major L1 CTT milestone
Fabrication & assembly of L1 Trigger Cal-TRK Match MTCM complete
10/20/03 10/20/03 11/10/03 Completion of production; based on current muon trigger cardsForecasts remain
well ahead of baseline dates
Level 2 trigger, online begin later
DZero Run IIb PMGJanuary 28, 2003
8
Run IIb Labor
Request for full-time electronics technician for silicon made at last PMG (Dec 10) Commissioning and maintenance of existing
testing, burn-in stands Cecil Needles joining us, first introductory tour
scheduled for this week
Other technical needs covered at the moment Project Office continually asking project to
anticipate their manpower requirements Collaboration help as well as FNAL technical staff Lead times can be unwieldy
DZero Run IIb PMGJanuary 28, 2003
9
Labor Cost Extracted from Schedule vs. Actuals (R&D)
FNAL Technical LaborAll Funding Sources
FY02 & FY03
$0
$20,000
$40,000
$60,000
$80,000
$100,000
$120,000
$140,000
$160,000
$180,000
$200,000Oct-01
Nov-01
Dec-01
Jan-02
Feb-02
Mar-02
Apr-02
May-02
Jun-02
Jul-0
2
Aug
-02
Sep-02
Oct-02
Nov-02
Dec-02
Jan-03
Feb-03
Mar-03
Apr-03
May-03
Jun-03
Jul-03
Aug-03
Sep-03
Calendar Month
Co
st (
FY
02
$)
WirebonderSF
MechTechSF
MechTechF
MechEngF
ElecTechSF
ElecTechF
ElecEngF
DesignerF
CompProfF
CMMProgrammerSF
CMMOperatorSF
AdminAsstF
Actuals: Oct = $168.5k, Nov = $132.8k (FY03 k$)No contingency or G&A in schedule prediction
Agreement quite good, but earned value is real measure (actuals, COBRA)
Actuals in FY02 k$
Scheduled labor in FY02 k$
Updated for Dec/Jan as soon as
information from PPD is available
DZero Run IIb PMGJanuary 28, 2003
10
Comments Significant Lab-wide parallel efforts (shutdown) never come
for free, but impact on Run IIb not as serious as initially thought
Loss of IIb SiDet personnel to Beams Division ameliorated by extra effort from other project principals
Experts within DZero redirected to Collision Hall work, but for reasonably short amount of time
Inter-cryostat gaps photographed, mapped out – required for further Run IIb design work
We have no argument whatsoever with the priorities!!! I am going to begin assuming that accelerator will run only at
396 nsec Studies & document outlining utility of SIFT upgrade for physics
at 396 nsec being completed (Bross, Hildreth, et al.) In event SIFT is deemed to be unnecessary, personnel on SIFT
project should be redirected within DZero Have particular interest in integrating P. Rubinov into group of
Run II(b) electronics experts – sore and obvious need Formal statement on 132 from Lab would be useful Will discuss privately with Mont, et al.
DZero Run IIb PMGJanuary 28, 2003
11
Comments
Jan 18-23 trip to France to discuss terms of Saclay involvement in Level 1 Calorimeter Trigger very productive
Responsible for front-end (ADF) trigger boards – ADC/Digital Filtering
LHC commitments might compete with proper Run IIb completion
Saclay has agreed to seek extension of their involvement beyond initially proposed 2005 time scale
Things like: Delays in obtaining FY03 spending approval Further bottoms-up evaluations of Run IIb project
…send very powerful message. Make it increasingly difficult to maintain committed core of upgrade groups and personnel.
DZero Run IIb PMGJanuary 28, 2003
12
Conclusions
Project making steady, solid technical progress No change control thresholds yet encountered, but
SVX4 is on (schedule) cusp Project tracking machinery being continually
developed & shaken out
COBRA and its implementation an important ingredient to nail down now
Lead time associated with labor requests might grow into a concern as project heats up
Will try on our end to make our requests as early on, and as well-defined, as possible
Cultural stasis exhibited by all entities poses a continuous difficulty – schedule drives these projects!