Upload
frederica-cannon
View
216
Download
0
Tags:
Embed Size (px)
Citation preview
DZero Run IIb PMGFebruary 25, 2003
1
Run IIb DZero PMG
Status overview, issues (Kotcher) Schedule, project status (Freeman) AOB
Jon KotcherFermilab PMG
February 25, 2003
DZero Run IIb PMGFebruary 25, 2003
2
Run IIb Project Organization
D0 Run IIb ProjectJ. Kotcher, Project Manager
R. Partridge, Deputy; V. O’Dell, Associate; W. Freeman, Assistant
M. Johnson, Technical Coordinator A. Amorn-Vichet, Budget Officer; T. Erickson, Administration
WBS 1.1Silicon
M. DemarteauG. Ginther
1.1.1 Sensors R. Demina, F. Lehner
1.1.2 Readout SystemA. Nomerotski, E. von Toerne
1.1.4 QA, Testing, & Burn-inC. Gerber
1.1.3, 1.1.5 Mechanics & Assembly
W. Cooper, K. Krempetz
1.1.6 MonitoringM. Corcoran, S. de Jong
1.1.4 ProductionJ. Fast
1.1.7 Software & Simulation F. Rizatdinova, L Shabalina
WBS 1.2Trigger
H. Evans D. Wood
1.2.3 L1 Track TriggerM. Narain
1.2.1 L1 Cal UpgradeM. Abolins, (H. Evans),
P. LeDu
1.2.4 L2UpgradeR. Hirosky
1.2.5 Silicon Track Trigger U. Heintz
WBS 1.3DAQ/Online
S. FuessP. Slattery
1.2.2 L1 Cal/Track MatchK. Johns
1.2.6 SimulationM. Hildreth, E. Perez
WBS 1.5 Installation
R. Smith
1.5.1 Silicon InstallationMechanical:H. Lubatti
Electronics: L. Bagby, R. Sidwell
1.5.2 Trigger InstallationD. Edmunds
WBS 1.4Project
Administration
1.2.7 Administration(D. Wood)
1.1.8 Administration(M. Demarteau)
1.3.3 Control SystemsF. Bartlett, G. Savage,
V. Sirotenko
1.3.1 Level 3 SystemsD. Chapin, G. Watts
1.3.4 DAQ/Online Management(P. Slattery)
1.3.2 Network & Host Systems
J. Fitzmaurice, S. Krzywdzinski
• George Ginther is new silicon co-leader• Eckhard von Toerne is new silicon
readout co-leader (replaces Bill Reay)
• Arisara Amorn-Vichet, new Budget Officer
• Kurt Krempetz, K. Hanagaki plenary speakers
DZero Run IIb PMGFebruary 25, 2003
3
WBS 1.1: Basic Silicon Design Choices
Six layer silicon tracker, divided into two radial regions Inner layers: Layers 0 and 1
Axial readout only Mounted on integrated support Assembled into one unit Designed for Vbias up to 700 V
Outer layers: Layers 2-5 Axial and stereo readout Stave support structure Designed for Vbias up to 300 V
Employ single sided silicon only, 3 sensor types
2-chip wide for Layer 0 3-chip wide for Layer 1 5-chip wide for Layers 2-5
No element supported from beampipe
DZero Run IIb PMGFebruary 25, 2003
4
Silicon Detector Elements
168 silicon staves: basic building block of outer layers
Supported in positioning bulkheads at z=0, z=610 mm
Silicon
Analogue cables
Hybrid
Layer 0 Support structure: University of Washington
Silicon Hybrid
Digital cable
Layer 0/Layer 1 mated
DZero Run IIb PMGFebruary 25, 2003
5
Silicon Layer 0 Support Structure
University of Washington First Layer 0 prototype carbon fiber support structure delivered to
Fermilab for tests in January Integrated grounding – kapton/copper mesh Performs very well under deflection tests – major technical
achievement
Silicon
Analogue cables
Hybrid
CMM headMounted
L0 structure
Mounted L0
structure, ground mesh
Clamps to inner
carbon shell
Balls for deflection
measurements
DZero Run IIb PMGFebruary 25, 2003
6
Prototype Mechanical Stave
Prototype mechanical stave being thermally tested at SiDet
Dec 18 ’02 integration milestone met
Al-ceramic hybrid
(dummy)
Stereo silicon,
axial mounted
underneath
Input cooling channel
10/10 (upper)20/20 (lower)
mechanical modules,
concatenated
DZero Run IIb PMGFebruary 25, 2003
7
Outer Layer Silicon Module Prototypes
20/20 axial module
Silicon sensors
20/20 stereo hybrid
SVX4 readout chip
20/20 axial hybrid
First outer layer electrical-grade (“20/20”) prototypes fabricated
Two types: axial & stereo readout
Each are 12 sensors long, ~100 mm in length
Stereo angle obtained by rotating sensors
Testing underway
Digital cable
DZero Run IIb PMGFebruary 25, 2003
8
Module Test Results
Electrical tests of 20/20 axial module (10 chips)
Charge injection
Pedestal
Unbonded chip
Total/ random noise
Bonded to single (dual)
sensors
DZero Run IIb PMGFebruary 25, 2003
9
Silicon Status
Ordered Delivered Ordered Delivered
ELMA
HPK
ELMA
HPK
L2 Sensors HPK
Analogue Cable Dycx
L0 Hybr id Amitr .
L1 Hybr id CPT
CPT
Amitr .
L2S Hybr id CPT
Honey
Basic
J unction Card
Twisted Pr . Cable
Adapter Card
Purple Card
Test Stand Elctr .
L0 Sensors
L1 Sensors
Digital Cable
L2A Hybr id
First Prototype Second Prototype
Component Vendor Design
DZero Run IIb PMGFebruary 25, 2003
10
WBS 1.2: Trigger Upgrades
Level 1 projects underway Level 1 Calorimeter Level 1 Cal-track
matching Level 1 Tracking Trigger simulations
Level 2 projects (not discussed here)
L2 Beta upgrade & STT upgrade
Later start in schedule VTM’s procured for STT
(part of larger order)
WBS 1.2: Trigger UpgradeH. Evans (Columbia), D. Wood (Northeastern)
WBS 1.2.1: Level 1 CalorimeterM.Abolins(MSU),
H.Evans(Columbia), P.LeDu (Saclay)
WBS 1.2.2: Level 1 Cal-track matchK. Johns (Arizona)
WBS 1.2.3: Level 1 TrackingM. Narain (Boston)
WBS 1.2.4: Level 2 Beta upgradeR. Hirosky (Virginia)
WBS 1.2.5: Level 2 STT upgradeU. Heintz (Boston)
WBS 1.2.6: Trigger SimulationM. Hildreth (ND), E. Perez
(Saclay)
DZero Run IIb PMGFebruary 25, 2003
11
WBS 1.2.1: Calorimeter Trigger Upgrade
Saclay ADC+Digital Filter
(ADF) ADF timing
distribution board Analog splitter (for
in-situ tests) ADF
Crate/backplane
Nevis Trigger algorithm
board (TAB) Global Algorithm
Board (GAB) Crates for TAB/GAB Test system for
ADF-to-GAB cables
BLS
2 EM + 2 H
EM
H
ADC + Digital-Filter (ADF)
Trig Algo’s (TAB)
Global +
Control (GAB)
ADF Timing Fanout
Existing BLS Cards:
2560 TT 0.2x0.2
TT Signal Processing
8-bit TT Et
16 EM 16 H
x 80 Sliding
Windows
x 8
clusters
sums
Global Sums
x 1
Framework Interfaces
Timing (SCL) L2 & L3 Control (TCC)
F r a me w o r k
Jets
EM
Tau
Et,Mpt
timing/ctrl timing/ctrl
Cal-Trk Match
encoded clusters
Signals from L1 Track
Michigan State Interfacing to
existing system, framework
Infrastructure
L1 Cal/Track Match:
University of Arizona
DZero Run IIb PMGFebruary 25, 2003
12
Level 1 Trigger Highlights
Prototype design phase concluded for three major boards in Level 1 trigger upgrade:
Level 1 Calorimeter Trigger ADC-Digital Filter Board (ADF) - Saclay Trigger Algorithm Board (TAB) – Columbia University 2/3 of the PCBs required for L1 Cal
– Remaining Global Algorithm Boards (GAB) being completed
Level 1 Calorimeter/Track Match Flavor Board (MTFB)
Layouts begun Analog splitter installed during January shutdown in Level
1 Cal rack at DZero Assembly Building, Movable Counting House
Picks off in-situ signals from four trigger towers Data will be taken, analyzed during next few months Preparation for tests of full L1 Cal prototype chain (ADF,
TAB, GAB), beginning this summer
DZero Run IIb PMGFebruary 25, 2003
13
Analog Splitter: Saclay & MSU
Analog splitter: allows in-situ test of digital filtering with real signals
Designed and tested at Saclay
Shipped to MSU Dec 20th: tested there
Installed in DØ L1Cal trigger (Run IIa) during current shutdown
Noise tests in progress
Tests with beam (w/ splitter vs. w/o splitter) to follow
DZero Run IIb PMGFebruary 25, 2003
14
WBS 1.2.2: Cal-Trk Match: Arizona
Uses “L1mu” electronics, apart from specialized “flavor board”
Flavor board (MTFB) prototype design >90% complete
Some procurements anticipated for next month
Approval was essential for keeping this on track
Run IIa MTFB(scint flavor)
DZero Run IIb PMGFebruary 25, 2003
15
L1 CTT: Boston Univ.
Firmware design for target algorithm began in Nov
“front end” and “back end” code from Run IIa rewritten – latency reduced
Ongoing work on maps of single fibers
DZero Run IIb PMGFebruary 25, 2003
16
Trigger Simulation Progress
Studies of effects of trigger tower thresholds on L1 Cal global sums (missing ET)
L1 Cal tau algorithm included in trigger simulation
Output of Run IIb L1 Cal interfaced to standard DZero framework simulation package
Simulation of Cal-Track matching progressing Central Track Trigger (CTT) as-built geometry
and beam offsets incorporated into simulation Beam offsets up to ~1 mm do not effect efficiency of
Run IIb equations
DZero Run IIb PMGFebruary 25, 2003
17
Production Readiness Reviews (PRR)
First review: “Purple Card” - sequencer/hybrid interface PC card – held 1/30/03. Committee:
C. Gerber (UIC), J. Green (Fermilab), K. Hanagaki (Fermilab), S. Lager (Stockholm), R. Lipton (Fermilab, Chair), R. Sidwell (KSU)
Report submitted – ready to go
Next review: Outer layer silicon sensors, 3/6/03. Committee: N. Bacchetta (PISA), B. Gobbi (NWestern), J. Ellison (UCR, Chair), R.
Lipton (Fermilab), H. Sadrozinski (UCSC), S. Worm (Rutgers) $1.5M order with Hamamatsu – procurement ready to move upon
receiving nod from Committee. Costed in four lots. Placement of order was second Run IIb DOE milestone (March 24)
Project target date: Feb 18 PRR report due March 14, procurement immediately thereafter Project is learning from such experiences
DZero Run IIb PMGFebruary 25, 2003
18
Labor Cost Extracted from Schedule vs. Actuals (R&D)
FNAL Technical LaborAll Funding Sources
FY02 & FY03
$0
$20,000
$40,000
$60,000
$80,000
$100,000
$120,000
$140,000
$160,000
$180,000
$200,000O
ct-0
1
Nov
-01
De
c-01
Jan-
02
Fe
b-02
Mar
-02
Apr
-02
Ma
y-02
Jun-
02
Jul-0
2
Aug
-02
Sep
-02
Oct
-02
Nov
-02
Dec
-02
Jan
-03
Feb
-03
Mar
-03
Apr
-03
May
-03
Jun-
03
Jul-0
3
Aug
-03
Se
p-03
Calendar Month
Co
st (
FY
02
$)
W irebonderSF
MechTechSF
MechTechF
MechEngF
ElecTechSF
ElecTechF
ElecEngF
DesignerF
CompProfF
CMMProgrammerSF
CMMOperatorSF
AdminAsstF
Dec + Jan (predicted) ~ Dec + Jan (observed)
Actuals in FY02 k$
Scheduled labor in FY02 k$
DZero Run IIb PMGFebruary 25, 2003
19
Current Conclusions on Labor from 1st Quarter
We are using very different flavors of people than the schedule predicted
Rates for given flavor consistent with average rates used as input to project cost
<DesF> actual pay ~ <DesF> as used in schedule
Using more labor than we thought 10% high in hours and cost
Actual cost within 1% of predicted Above all very good…but even though we are
using more labor, we are not keeping up with aggressive schedule in all cases
Comments to follow…
DZero Run IIb PMGFebruary 25, 2003
20
Costs Loaded Into COBRA
DZero Run IIb Upgrade Cost and ContingencyWBS Name COBRA Base Contingency Total Cost Cont %
1.1 Silicon $15,762,834 $5,127,166 $20,890,000 33%1.2 Trigger $3,061,564 $1,430,436 $4,492,000 47%1.3 Online $1,050,759 $342,241 $1,393,000 33%1.4 Project Administration $1,497,798 $331,202 $1,829,000 22%
TOTAL PROJECT $21,372,955 $7,231,045 $28,604,000 34%
WBS Name EIR Base EIR Cont EIR Cost
1.1 Silicon $15,986,000 $4,904,000 $20,890,0001.2 Trigger $3,276,000 $1,216,000 $4,492,0001.3 Online $1,062,000 $332,000 $1,393,0001.4 Project Administration $1,463,000 $366,000 $1,829,000
TOTAL PROJECT $21,787,000 $6,818,000 $28,604,000
Differences (EIR-COBRA)WBS Name Base Contingency
1.1 Silicon $223,166 ($223,166)1.2 Trigger $214,436 ($214,436)1.3 Online $11,241 ($10,241)1.4 Project Administration ($34,798) $34,798
TOTAL PROJECT $414,045 ($413,045)
COBRA ready to go
(see monthly report)
Thanks to Rissa, Dale,
Colleen, Dean
DZero Run IIb PMGFebruary 25, 2003
21
Adhering to Schedule
Creating, maintaining a schedule and using it to monitoring progress is only initial step
Essential that next step be taken: extract lessons learned from slippages, implement corrective actions where possible. Anticipate project needs well in advance.
Project has begun to turn this corner Schedule being taken with increasing
seriousness, attentiveness by all principals This is a major step, will continue until we’ve
finished
DZero Run IIb PMGFebruary 25, 2003
22
Miscellany, Conclusions
MoU/SoWs being generated project-wide Overhead-free MoUs for silicon MRI in place
for some time First formal agreement just completed, Run
IIb PO being generated (Louisiana Tech) COBRA loaded, ready to use
Report on equipment costs only Technical progress continues to be
excellent Beginning to truly manage to aggressive
schedule – positive and important step No change controls on horizon
DZero Run IIb PMGFebruary 25, 2003
23
Keeping Run II(b) on the Map: Next Six Months
Experiments now directly participating in BD planning. Comes with a price: Reviews (both sides of table), associated preparation quite extensive
Above demonstrates impact of current climate, + compressed schedule Heavy emphasis on project management at all levels
Feb Mar
Apr May
Jun Jul Aug
Accelerator
Advisory Committe
eBD Long-
Range Plan for
Run II due to DOE
Director’s Review of BD Long-
Range Plan
P5 Review of Run IIb
Director’s Review
of Run IIb
DOE (Lehman) Review of
Run IIb (CD-3b)
DOE Review of Accelerator
All information required by DOE
for long-term assessment in hand at this
pointDOE
Review of FNAL
Program
Monthly PMGs:
Long-Range BD, Run IIb
Green = Beams Div (BD)Brick = Run IIb Detector ProjectsDates shown are latest est
PAC