Upload
amira-cottle
View
216
Download
0
Embed Size (px)
Citation preview
DRMS “Bringing Our Service To The Customer”
Presentedto:
Lorna B. Estep, SES, Deputy Director for Supply, Directorate of Logistics, Headquarters Air Force Materiel Command
Steven G. Schmidt, SES, Deputy Center Director, NASA Dryden Research Center, Edwards ARB
November 2007
SR-71, Disposal Operations
Multi-Service, Agency & Contractor Involvement
Air Force Materiel
Command
Edwards Air Force
Base
Marine Corp
Logistics Base
NASADefense Logistics Agency
Defense Reut & Mktg
Service
Scrap Venture
Tri-Rinse Shredder
Hw Contractor
NASA Drain/Purge
Contract
SV Roll-Off Contractor
AFMC Roll-Off Contract
Tri-Rinse Fuel
Contractor
DEMAN Contractor
APCD/DTSC
permits
DRMS SR-71 Team
Coordinating Disposition
Efforts
MCLB Security
MCLB Safety
MCLB Environment
al
AFMC Support
Team
May 07 Jul 07 Aug 07 Dec 07Oct 07
SR-71, Disposal Plan In Progress
Jun 07 Sep 07 Nov 07
AFMC/A4SM (SR-71 Project officer) and DRMS Program Manager conducted a preliminary site visit 21 May – 21 June. AFMC/DRMS teamed to initiate disposal action for NON Sensitive “H” conditioned support equipment. DRMS contractor mutilated on site, witnessed by DRMS and removed 192,000 lbs of residue.
AFMC/DRMS staff on site segregating SR-71 parts by disposal method/process Continue improving disposal process
Identified, segregated and consolidate electronic equipment, components, test sets, and circuit cards for shipment on DEMAN task orders. Successfully shipped 132,760 lbs to date. Final DEMAN task order for approx. 25,000 lbs scheduled for shipment Nov 10th
AFMC/DRMS/SV workforce on site to uncrate, segregate and stage property eligible for shredding
Tri-Rinse Shredding start date Sept 29th Identified asbestos containing property, segregated and place on disposal contract for ultimate destruction (burial)
A total of 229,520 lbs of asbestos shipped in (44) Roll-off containers. Receipt, off-load & actual burial witnessed and Certified/Verified by CORs
Identified end items with hazardous constituents, i.e. gas cylinders, support equipment containing fluids. AFMC funded NASA contractor to drain/purge on site.
Utilized Tri-Rinse shear and shredding process to dispose of end items as scrap
SR-71, Disposal Plan Mutilation Process In Action
Shear with 17K lbs pressure Large shredder crane feed
Small shredder manually feed All (3) operating simultaneously
SR-71, Asbestos Disposal Plan Complete
Asbestos loaded for departure
Certified/verified destruction by burialCORs Witness Burial Process
CORs observed receipt/off-load
SR-71, Disposal Plan Challenge & Solution
• Challenge - During the first hour of full operations the main shredder experienced a hydraulic leak
• The loss of hydraulic pressure immediately shut down the entire system.
• One of the hydraulic hoses separated from the coupling and resulted in the release of approx 10-15 gallons of hydraulic fluid
• Solution - The spill was immediately isolated, contained, and cleaned up by the Tri-Rinse staff in accordance with the provisions of their contract
• The spilled hydraulic fluid was contained on the rubber containment mats under the shredder and with the addition of absorbent and absorbent pillows
• The contaminated absorbent was place on a DRMS HW disposal contract & removed
SR-71, Disposal Plan Challenge & Solution
• Challenge - During the shredding process we experienced a fire that was caused by hot metal mixed with the shredded wooden boxes, crates & packing materials
• Smoke was immediately detected by the operator and a DRMS employee monitoring the operation
• Attempts by the SR-71 team to distinguish the smoldering content with fire extinguishers failed
• The Fire Department was immediately called and extinguished the fire
• Solution – We placed a spotter with a water hose to observe the shredding process and continuously wet down the content as it enters the roll-off