Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
i
DRAFT ASSESSMENT REPORT ON STATUS OF
ACTIVITY IMPLEMENTATION
CONSTRUCTION INDUSTRY SKILLS COUNCIL (CISC) AND
SUDOKKHO AGREEMENT FOR 2017/18
NOVEMBER 2018
ii
TABLE OF CONTENT
1. Background ..................................................................................................................................... 1
1.1 Goal of 2nd Collaboration Agreement ..................................................................................... 1
1.2 Objective of 2nd Collaboration Agreement ............................................................................ 1
1.3 Overall support from Sudokkho to CISCs capacity building in 2nd year ................................. 1
2 Expected Outputs, Activities and Deliverables ............................................................................... 2
3 Deliverable of CISC to Sudokkho ..................................................................................................... 3
4 Assessment of the status of implementation. ................................................................................ 3
4.1 Sudokkho Team ....................................................................................................................... 4
4.2 CISC Team ............................................................................................................................... 4
4.3 Assessment Matrix .................................................................................................................. 4
5 General Observations ..................................................................................................................... 4
6 Recommendations .......................................................................................................................... 5
Appendix 1: Assessment Matrix .............................................................................................................. 6
1
1. Background
Sudokkho signed an MOU with the Construction Industry Skills Council (CISC) in January 2015 for a
period of about 4 years from 13 January 2015-31 March 2019. The MoU outlined the broad areas of
the support from Sudokkho to CISC and the obligations of the CISC in this regard.
The CISC has a governing body with representatives from ten (10) industry associations and one (01)
labour representative organization of the construction sector. The CISC has also formed four
Standing Committees: i) Skills Planning Standing Committee (SPSC), ii) Curriculum Development and
Training Support Standing Committee (CDTSSC); iii) Assessment, Moderation, Verification and
Certification Standing Committee (AMVCSC); and iv) Administration, Finance & Procurement
Standing Committee (AFPSC). Nevertheless, further to the MoU between CISC and Sudokkho, a
yearly collaboration agreement was signed in order to specify the discrete technical package offers
to CISC for implementing the planned programme activities.
Sudokkho, under its 1st collaboration agreement, supported CISC to formulate a business plan for a
three-year period which was subsequently approved and accepted by SEIP. CISC also signed a 3-year
funding agreement with SEIP to meet up its operational expenses. Additionally, Sudokkho-SEIP-CISC
has signed tripartite agreement for smooth functioning of the different areas of supports to CISC. As
per the agreement, the Skills for Employment Investment Program (SEIP) is committed to support
the CISC financially to cover its operational costs, while Sudokkho is committed to complement this
with strengthening the CISC's institutional capacity and support the implementation of its key
functions. This is mentionable that funding from SEIP to CISC is contingent to the technical supports
from Sudokkho. Sudokkho strengthens the institutional capacity and supports key functions of
Industry Skills Councils (ISC) and supports capacity building of national training consultancy service
providers (TCSP) to sustain a long-term development process. Given the above context, Sudokkho
signed its 2nd year collaboration agreement with CISC for the period 1 October 2017-30 September
2018.
1.1 Goal of 2ndCollaboration Agreement
The goal of the 2nd collaboration agreement was to contribute to the financial and technical
sustainability of the Council at the end of the agreement period.
1.2 Objective of 2nd Collaboration Agreement
The cooperation between Sudokkho for the second time running was to ensure that CISC executives
and members have technical capacities and are capable to effectively and efficiently perform
various activities of the Council to the required standards and achieve the objectives within the
stipulated time.
1.3 Overall support from Sudokkho to CISCs capacity building in 2nd year
During the implementation of activities of the 2nd agreement (October 2017 – September 2018);
Sudokkho assigned experts to liaise with CISC to coordinate interventions and support in
operational activities.
Sudokkho bore direct costs related to engagement of subject matter experts and costs relevant
to the facilitation of developing and or reviewing competency standards, curriculums, CBLMS,
2
Board meetings, standing committee meetings and annual general meetings including relevant
workshops, promotional events etc.
Additionally, Sudokkho engaged international consultantsperiodically to undertake the
following organizational development tasks which were based on the business plan of CISC and
related to above mentioned support scheme:
o Intensive orientation and capacity building for the management team, the technical
members of the Standing Committees and the Board members on their roles in the
CISC,
o Support the CISC in establishing formal relationship with all key government agencies
such as the NSDC, BTEB, DTE, BMET and other relevant Ministries to understand and set
up management systems to comply with government policy, legislative and regulatory
requirements, lines of communication and reporting;
o Support the CISC in setting up and managing a process to develop a skills strategy for
the sector and the production of annual training plans.
o Support CISC to establish Labour Market Information System (LMIS) for construction
sector in collaboration with the relevant industries and business associations like BACI,
REHAB etc.
o Support CISC to develop/review and approval of skills competency standards in line
with NTVQF levels 1-4 in collaboration with BTEB.
o Support CISC to develop/review and approval of curriculum framework and align
existing curriculums developed by Sudokkho and other skills development projects with
the approved curriculum framework in collaboration with BTEB.
o Support the development of a Monitoring and Evaluation instrument to track the
performance of the CISC against agreed objectives and targets. It should also be able to
generate statistical data on training activity for purposes of reporting to the governing
body, donors, other funders and the NSDC.
o Support CISC to review and formulate career mobility path for the construction workers
in different occupations well-suited with the NTVQF levels and the industry work-
structures.
o Capacitate CISC’s payroll staff including the CEO to a level that they could deliver their
assigned tasks independently in line with the core responsibilities the CISC.
o Facilitate to develop a guideline for a sustainability plan for the CISC once the funding
from the development partners will be reduced.
2 Expected Outputs, Activities andDeliverables
The expected outputs for the implementation period were as follows:
PTPs assessed and marked as RTOs by BTEB according to the required standards Occupational skills standards developed, validated and approved for a number of
occupations on the NTVQF for levels 1-4 CBT Curricula and CBLMs developed and validated at levels 1- 4 of the NTVQF Trainer and Assessor training programme consistent with NTVQF levels Assessment and Certification of trainees conducted in line with NTVQF levels Skills Planning and Labour Market Information System in place Meeting/workshops etc, conducted.
3
Various activities were undertaken during the period to achieve the above outputs.
3 Deliverable of CISC to Sudokkho
In the implementation of the 2017/18 year activities of the agreement, was expected to provide the
following deliverables to Sudokkho .
SL #1 Deliverables Indicators/KPIs 1 Annual and quarterly reports 03 quarterly reports and 01 annual reports
highlighting progress of implementation, lessons learnt etc.
2 Bi-monthly Board and Standing Committee meetings including one AGM
Signed copies of the meeting notes/minutes
3 Competency Standards 16 approved competency standards uploaded in Sudokkho and BTEB’s websites
4 CBT Curriculums 10 approved CBT curriculum uploaded in Sudokkho and BTEB’s websites
5 CBLMs and CSLBs 10 approved CBLMs and 10 CSLBs uploaded in Sudokkho and BTEB’s websites
6 Certified Assessors Profiles of 50 certified assessors and 64 onsite supervisors uploaded in Sudokkho and BTEB’s websites
7 Certified trainees assessed through RPL system
Profile of 480 BTEB certified trainees uploaded in in Sudokkho and BTEB’s websites
8 Competency assessment instruments
10 BTEB approved assessment instruments in Sudokkho and BTEB’s websites.
9 5-year skills strategy Final skills strategy paper in Sudokkho and BTEB’s websites
10 Employers survey Final report uploaded in Sudokkho and BTEB’s websites
11 LMIS CISC LMIS starts populating and linked with Sudokkho website
12 Financial sustainability guideline Sustainability guideline uploaded in in Sudokkho and BTEB’s websites
4 Assessment of the status of implementation.
An assessment of progress against the last year work plan of collaboration agreement between
Sudokkho and CISC was undertaken to:
Review scope of cooperation agreement of Sudokkho and CISC and find out the agreed
technical assistance package planned for CISC
In collaboration with the CISC, review progress of technical assistance against the existing
workplan starting from 1st October 2017 to 30th September 2018.
The review process was a collaborative exercise between CISC and Sudokkho with facilitation by an international consultant made up of the following.
4
4.1 Sudokkho Team
Dan Baffour-Awuah International Consultant
Kabir Ahmed Training Coordinator - ISCs and Industry Based Training
S.M SM Jahangir Alam Project Officer
4.2 CISC Team
Sk Abdul Mannan Chief Executive Officer (CEO)
B. M. Mofizur Rahman Curriculum development & Training Executive
Engr. Md. Asaduzzaman Assessment & Certification Executive
Md. Mohasin LMI & Research Executive
Md. Shafikul Islam Assistant Executive (Finance & Admin)
Md. Khairul Islam Office Secretary
Six different meetings were held at CISC offices to review progress ofimplementation of the activities and deliverables as against the planned ones indicated in the agreement document.
4.3 Assessment Matrix
The assessment of progress is indicated in Appendix 1 attached. It includes achievement as against planned, deviation, challenges and recommendations
5 General Observations
The following general observations were made
Out of the 21 planned activities 6 (representing 28.6 %) of them were fully achieved, with
one activity exceeding the target by over 200%.Nine (9) of the activities (representing 42.8%)
have been initiated and reached various levels of completion. While six (6) representing
28.6% planned activities were not initiated at all.
The existence and activities of CSIC are not known to the general public
CISC and Sudokkho had cordial working relationship and worked as a team
CISC relied mainly on Sudokkho staff to lead the implementation of the activities, thus in the
absence of Sudokkho staff (especially the passing away of Engr. Md. Belayet Hossain)the
implementation of most of the activities have been delayed.
The CISC team (paid staff) for implementation of the planned activities, comprising of the
CEO and three technical staff are very committed in performance of their duties butneeded
enhanced technical and management capacities to fully carry out the planned activities
successfully.
Some of the planned activities were ambitious, while some of them required third party
support to achieve the set targets.
Some of the activities were not properly planned in terms of the usage of technical
expertise, sequencing and alignment of implementation.
CISC did not take up ownership of the activities and had no exist strategy for sustainability
after the support of Sudokkho comes to an end.
5
6 Future Outlook
The following recommendations are made based on discussions on the assessment of activities and
mainly looking at the future performance and sustainability of the Council.
Sudokkho is encouraged to renew the technical agreement for another year and focus on
the under-listed areas for the cooperation agreement.
o Capacity building for CISC office staff and members
o Teaching and Learning material development and validation
o Embankment on advocacy activities to bring the existence and activities of CISC to
the public domain
o Development of partnership with public and private institutions
Activities that were initiated in the previous year’s agreement but have not been completed
should be fast-tracked for completion.
The staff of CISC should be in the driving seat in all activities and only request for technical
support from Sudokkho
Looking beyond the support from Sudokkho, CISC should intensify their internally generated
funds (IGF) activities as indicated the sustainability document.
They also need to be pro-active and do not have to wait for Sudokkho to initiate activities
There should be lot of team work, delegation and proper coordination of activity
implementation.
6
Appendix 1: Assessment Matrix
SL # Activities Deliverables STATUS/EVIDENCE DEVIATION CHALLENGES RECOMMENDATION
Training Institutions
1 Identify and assess capacity of 30 private training providers working in construction sector to align with the BTEB requirements for RTO to run certified CBT courses
Capacity of 20 PTPs assessed
Capacity of 5# PTPs assessed and marked as RTOs by BTEB
#15 under processing
Have to comply with the requirement of BTEB
Direct Sudokkho implementation
Occupational Skills Standards
2 Develop and validate competency standards (CS) for new occupations including accreditation documents (number of standards are equivalent to NTVQ levels).
8 # CSs (NTVQ level 1-4)
6 # CSs (NTVQ level 1-4)
#2 CSs under processing
Availability of industry experts, national consultants
Proper planning required to meet targets
3 Review and validate existing standards (registered by BTEB) or developed by SEIP or other projects) including accreditation documents
8# CSs (level 1-4)
None completed All 8 outstanding
SEIP did not give approval until Aug 2018 when #2 was approved for validation
CISC have to be pro-active and follow up on request
Curricula and Training Materials
4 Development of career path/skills mobility plans for number of trades
10 # occupations None completed All 10 CISC had no capacity in this activity
Capacity of CISC has to be built with hand holding session
5 Develop curriculum framework and curricula and verify training courses are aligned with new competency standards
# CBT Curriculum Framework # CBT curricula at NTVQ Level -1 for 10 occupations
6# completed based on the number of CS completed
4# still outstanding
The CFs have to be developed on completion of the development of the CSs
Proper planning required to meet targets. Realistic targets have to be set
6 Develop Competency Based Learning Materials (CBLM) Competency Standards
# CBLM at NTVQ Level -1 for 10 occupations
None completed All outstanding Development depends on completion of CSs and related curriculum
Proper planning required to meet targets. Realistic targets have to be
7
set
7 Develop Competency Skills Log Book (CSLB) aligned with NTVQ levels (Apprenticeship)
# CSLB at NTVQ Level -1 for 10 Occupations
None developed 10# outstanding (6# in progress for developed CSs
Depends on completion of CSs and curriculum
Proper planning required to meet targets. Realistic targets have to be set
Trainer and Assessor Training
8.a Build capacity of instructors for development of competency standards for CBLM
30# trainers to be trained on CBT&A at level 5
No training was organized
All sub activities still outstanding
Only 5# training institutes accredited. There are limited number of qualified trainers
CISC to be pro-active and take the initiative as soon as possible
8.b Conduct ToT on occupational skills 50# trainers trained on occupational skills
No training was organized
All sub activities still outstanding
No agreement with CISC & Sudokkho in last year
CISC to be pro-active and take the initiative as soon as possible
8.c Conduct ToT on pedagogical skills 50# trainers trained on pedagogical skills
No training was organized
All sub activities still outstanding
No agreement with CISC & Sudokkho in last year
CISC to be pro-active and take the initiative as soon as possible
8.d Conduct apprenticeship training for new employees (Group training)
30 trainers trained on apprenticeship delivery (15 trainers per group)
No training was organized
All sub activities still outstanding
Contingent to CSLB CISC to be pro-active and take the initiative as soon as possible
9 Build the capacity of onsite supervisors who have completed a short skills training course as trainer/mentor
64 # of onsite supervisors
No training was organized
All sub activities still outstanding
Only 5# training institutes accredited. There are limited number of qualified trainers
CISC to be pro-active and take the initiative as soon as possible
8
10 Develop workplace assessors aligned with BTEB-certified CBT&A training at NVQF Level 4
60 certified assessor by BTEB
250 assessed and 121 certified as assessors by BTEB
Achieved beyond target
The activity has the potential to achieve more assessors which are needed
11 Number of trainees assessed and certified by BTEB-certified assessor
600 # of assessed and 480 certified
None has been assessed for certification
All paper work completed & started within November
Modalities for implementation was delayed
The assessment training to be conducted as per the CS
Assessment and Certification
12 Development of Assessment policies and guideline manual
01# Policies Document is available at BTEB
Policies Document is available at BTEB
CISC to take initiative as soon as possible if need further review
13 Development of Assessment instruments for each occupation
Assessment instruments for 10 occupations at NTVQ Level -1
None was developed
Tools development Workshop will be start from 12 November 2018
Non availability of resource persons. Activity depends on completion of development of CSs
CISC to take initiative as soon as possible
Skills Planning and Labour Market Information
14 Development of a 5-year skills development strategy for the construction sector
One final Skills strategy for Construction Sector
Completed in July 2018
Have to be disseminated to stakeholders
15 Employer survey on skills demand (skills shortages and skills gaps)
A report on employer survey
Completed in September 2018
Have to be disseminated to stakeholders
16 Development of an annual skills training plan
A comprehensive annual plan for CISC
Not developed The process is yet to take off
CISC did not have the capacity to undertake the activity
There is a need to the activity and have to be discussed with Sudokkho
17 Develop and Populate Labour Market Information System (LMIS)
01 # of ready to populate LMIS
01# LMIS ready Yet to be populated
Need more time for the data to be populated
9
18 Upgrading CISC website along with additional bandwidth
01# of CISC’s updated website
01# of CISC website update but yet to be functional
19 Registration of CBT curricula 12# will be registered
6# completed based on the number of CS completed
6# still outstanding
Proper planning required to meet targets. Realistic targets have to be set
20 Develop guidelines for a sustainability financial plan for CISC
01# sustainability guideline/ manual
01# financial sustainability plan completed
Conscious efforts need for implementation
Meeting/workshop
21 Annual General Meeting 01 # of AGM held with quorum members
01# AGM held with 40 participants
22 Board of Directors (BOD) meeting 06 # of BOD meetings held
06# BoD meetings held
Honorarium for Directors need to arranged
23 Standing Committee 18# technical standing SC and 03 Admin and finance SC meetings
5 technical meetings and 2 sub- committee meetings were held
13 technical and 1 sub committed meetings outstanding
Technical meetings are held on demand
Activities to be planned well for sub-committee meetings
24 Contribution to CISC launching 1 # launching programme held
Launch was not held
There was insufficient funding
Funding to be discussed with Sudokkho
TOTAL