32
Kunhee (KC) Choi, Ph.D. Associate Head of the Construction Science Department Associate Research Scientist of TTI TxDOT Short Course Construction I October 15, 2019 Determining the Most Economical B Values of A+B Bidding: Worst and Best Use Cases 0

Determining the Most Economical B Values of A+B Bidding: Worst and Best … · 2019. 11. 4. · Kunhee (KC) Choi, Ph.D.Associate Head of the Construction Science Department Associate

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

  • Kunhee (KC) Choi, Ph.D.Associate Head of the Construction Science Department

    Associate Research Scientist of TTI

    2007.06 TxDOT Short Course

    Construction IOctober 15, 2019

    Determining the Most Economical B Values of A+B Bidding: Worst and Best Use Cases

    0

  • I. Backgrounds

    II. Worst Use Case

    III. Seven-Step Procedure

    IV. Best Use Case

    V. Discussions

    Agenda

  • Paradigm Shift

    Highway Construction Paradigm Shifts to 3R

    New Paradigm in Highway Construction

    From building new highways to 3R

    30% of the Rehab projects in urban corridors

    Created an urgent dual challenge

    Increased pressure to complete project early

    Ever-Increased Pressure for Early Project Completion

    Rehab71%

    Bridge Renewal

    6%

    Widening18%

    New Highway

    3%

    New Bridge

    1%

    Other1%

    Rehab71%

  • Time-Cost Tradeoff CurveExtra acceleration requires additional cost.

  • Time-Cost Tradeoff Curve

    blocker

    Innovative strategies improve cost-time performance!

    OrdinarySchedule

    AcceleratedSchedule

    EconomicSchedule

  • Time-Cost Performance versus Alternative Contracting MethodsA quantitative study presented a case in which A+B projects revealed a critical performance issue!!

    On-time &On-budget

  • Time-Cost Performance versus Alternative Contracting Methods

    A+B

    I/D

    NEB

    Lump Sum

    DBB

    A quantitative study presented a case in which A+B projects revealed a critical performance issue!!

  • Cost-plus-Time Bidding with I/D

    Alternative Contracting Methods

    Growing need of early project completion

    Design-Build

    Cost-plus-Time (aka, A+B)

    Incentive/Disincentive (I/D)

    A+B combined with I/D provisions

  • On April 29, 2007, a fully loaded gasoline tanker truck turned over.

    The route is a major commuter route in the San Francisco Bay Area.

    Caltrans estimated 50 days with an incentive bonus of $200,000 per each day the project was completed, with a cap of $5 million.

    The winning bid was for $876,075, about one-third of the total project cost.

    In the end, the contractor completed it in 25 days, and thus received the entire $5-million incentive.

    Later, it was discovered that the realistic project duration and cost would have been 25 days and $1.75 million dollars.

    Importance of Contract Time: I-580 Bay Area Project with I/D

    I-580 Bridge Repair Project

  • Importance of Contract Time: I-580 Bay Area Project with I/D

    “There is no justification for this project to cost more than 1.8 million

    dollars, but the Department spent 5.88

    million dollars, three times higher than the

    realistic cost of the project.”I-580 Bridge Repair Project

  • I. Backgrounds

    II. Worst Use Case

    III. Seven-Step Procedure

    IV. Best Use Case

    V. Discussions

    Agenda

  • Production Rates for Concrete Weekend Closures: Normal vs. Accelerated

  • Production Rates for Concrete Weekend Closures: Normal vs. AcceleratedConcrete

    Scope

    Weekend Closures Normal vs. Accelerated

    Example: Concrete, 10 lane-mile, Long-life, Weekend

  • Production Rates for Concrete Weekend Closures: Normal vs. Accelerated

  • Schedule/Cost/Traffic Integrated Analysis

    Best Practice of CTD: TxDOT IH-20 Phase I Project

    IH-20 Dallas6.128mi x 3 lanes x 2 directionsFull-depth 13” CPCD55,257 AADT with 27% truckA+B+I/D with $4,000 daily I/D270 Working Days

  • Schedule/Cost/Traffic Integrated Analysis

    Best Practice of CTD: TxDOT IH-20 Phase I Project

    IH-20 Dallas6.128mi x 3 lanes x 2 directionsFull-depth 13” CPCD55,257 AADT with 27% truckA+B+I/D with $4,000 daily I/D270 Working Days

  • Schedule/Cost/Traffic Integrated Analysis

    Best Practice of CTD: TxDOT IH-20 Phase I Project

    IH-20 Dallas6.128mi x 3 lanes x 2 directionsFull-depth 13” CPCD55,257 AADT with 27% truckA+B+I/D with $4,000 daily I/D270 Working Days

    Weekday

    Nighttime

  • Schedule/Cost/Traffic Integrated Analysis

    Best Practice of CTD: TxDOT IH-20 Phase I Project

    IH-20 Dallas6.128mi x 3 lanes x 2 directionsFull-depth 13” CPCD55,257 AADT with 27% truckA+B+I/D with $4,000 daily I/D270 Working Days

    Weekday

    Nighttime

  • Schedule/Cost/Traffic Integrated Analysis

    Best Practice of CTD: TxDOT IH-20 Phase I Project

    IH-20 Dallas6.128mi x 3 lanes x 2 directionsFull-depth 13” CPCD55,257 AADT with 27% truckA+B+I/D with $4,000 daily I/D270 Working Days

    Weekday

    Nighttime

  • Schedule/Cost/Traffic Integrated Analysis

    Best Practice of CTD: TxDOT IH-20 Phase I Project

    IH-20 Dallas6.128mi x 3 lanes x 2 directionsFull-depth 13” CPCD55,257 AADT with 27% truckA+B+I/D with $4,000 daily I/D270 Working Days

    Weekday

    Nighttime

    No Public Events

    No Right-of-Way Issues

    No Utility Conflicts

    No Adjacent Business and Community Concern

  • Schedule/Cost/Traffic Integrated Analysis

    Best Practice of CTD: TxDOT IH-20 Phase I Project

    IH-20 Dallas6.128mi x 3 lanes x 2 directionsFull-depth 13” CPCD55,257 AADT with 27% truckA+B+I/D with $4,000 daily I/D270 Working Days

    Weekday

    Nighttime

  • Weekday Closure is much more favorable than Nighttime in that:

    It is 77% faster and 68% saving in reduced road user delay costs.

    It yields much higher production rate.

    The scope of the project can be accomplished 60 days earlier: 210 vs 270.

    Recommendations

    Schedule/Cost/Traffic Integrated Analysis

    Best Practice of CTD: TxDOT IH-20 Phase I Project

  • RecommendationsIncentive/Disincentive (I/D):

    The estimated 270 working days by the agency appear slightly overestimated,

    which can result in a $240,000 free bonus to the GC without any additional

    commitment.

    Agency’s estimated daily I/D amount of $4,000 is reasonable, based on the

    computed daily RUC of $8,766.

    Schedule/Cost/Traffic Integrated Analysis

    Best Practice of CTD: TxDOT IH-20 Phase I Project

  • TxDOT IH-20 Phase I Project: Initial Plan Amended

  • THANK YOU

    Slide Number 1Slide Number 2Paradigm ShiftSlide Number 4Slide Number 5Slide Number 7Slide Number 8Slide Number 9Slide Number 10Slide Number 11Slide Number 12Slide Number 13Slide Number 14Slide Number 15Slide Number 16Slide Number 17Slide Number 18Slide Number 19Slide Number 20Slide Number 21Slide Number 22Slide Number 23Slide Number 24Slide Number 25Slide Number 26Slide Number 27Slide Number 28Slide Number 29Slide Number 30Slide Number 31Slide Number 32Thank You