Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Kunhee (KC) Choi, Ph.D.Associate Head of the Construction Science Department
Associate Research Scientist of TTI
2007.06 TxDOT Short Course
Construction IOctober 15, 2019
Determining the Most Economical B Values of A+B Bidding: Worst and Best Use Cases
0
I. Backgrounds
II. Worst Use Case
III. Seven-Step Procedure
IV. Best Use Case
V. Discussions
Agenda
Paradigm Shift
Highway Construction Paradigm Shifts to 3R
New Paradigm in Highway Construction
From building new highways to 3R
30% of the Rehab projects in urban corridors
Created an urgent dual challenge
Increased pressure to complete project early
Ever-Increased Pressure for Early Project Completion
Rehab71%
Bridge Renewal
6%
Widening18%
New Highway
3%
New Bridge
1%
Other1%
Rehab71%
Time-Cost Tradeoff CurveExtra acceleration requires additional cost.
Time-Cost Tradeoff Curve
blocker
Innovative strategies improve cost-time performance!
OrdinarySchedule
AcceleratedSchedule
EconomicSchedule
Time-Cost Performance versus Alternative Contracting MethodsA quantitative study presented a case in which A+B projects revealed a critical performance issue!!
On-time &On-budget
Time-Cost Performance versus Alternative Contracting Methods
A+B
I/D
NEB
Lump Sum
DBB
A quantitative study presented a case in which A+B projects revealed a critical performance issue!!
Cost-plus-Time Bidding with I/D
Alternative Contracting Methods
Growing need of early project completion
Design-Build
Cost-plus-Time (aka, A+B)
Incentive/Disincentive (I/D)
A+B combined with I/D provisions
On April 29, 2007, a fully loaded gasoline tanker truck turned over.
The route is a major commuter route in the San Francisco Bay Area.
Caltrans estimated 50 days with an incentive bonus of $200,000 per each day the project was completed, with a cap of $5 million.
The winning bid was for $876,075, about one-third of the total project cost.
In the end, the contractor completed it in 25 days, and thus received the entire $5-million incentive.
Later, it was discovered that the realistic project duration and cost would have been 25 days and $1.75 million dollars.
Importance of Contract Time: I-580 Bay Area Project with I/D
I-580 Bridge Repair Project
Importance of Contract Time: I-580 Bay Area Project with I/D
“There is no justification for this project to cost more than 1.8 million
dollars, but the Department spent 5.88
million dollars, three times higher than the
realistic cost of the project.”I-580 Bridge Repair Project
I. Backgrounds
II. Worst Use Case
III. Seven-Step Procedure
IV. Best Use Case
V. Discussions
Agenda
Production Rates for Concrete Weekend Closures: Normal vs. Accelerated
Production Rates for Concrete Weekend Closures: Normal vs. AcceleratedConcrete
Scope
Weekend Closures Normal vs. Accelerated
Example: Concrete, 10 lane-mile, Long-life, Weekend
Production Rates for Concrete Weekend Closures: Normal vs. Accelerated
Schedule/Cost/Traffic Integrated Analysis
Best Practice of CTD: TxDOT IH-20 Phase I Project
IH-20 Dallas6.128mi x 3 lanes x 2 directionsFull-depth 13” CPCD55,257 AADT with 27% truckA+B+I/D with $4,000 daily I/D270 Working Days
Schedule/Cost/Traffic Integrated Analysis
Best Practice of CTD: TxDOT IH-20 Phase I Project
IH-20 Dallas6.128mi x 3 lanes x 2 directionsFull-depth 13” CPCD55,257 AADT with 27% truckA+B+I/D with $4,000 daily I/D270 Working Days
Schedule/Cost/Traffic Integrated Analysis
Best Practice of CTD: TxDOT IH-20 Phase I Project
IH-20 Dallas6.128mi x 3 lanes x 2 directionsFull-depth 13” CPCD55,257 AADT with 27% truckA+B+I/D with $4,000 daily I/D270 Working Days
Weekday
Nighttime
Schedule/Cost/Traffic Integrated Analysis
Best Practice of CTD: TxDOT IH-20 Phase I Project
IH-20 Dallas6.128mi x 3 lanes x 2 directionsFull-depth 13” CPCD55,257 AADT with 27% truckA+B+I/D with $4,000 daily I/D270 Working Days
Weekday
Nighttime
Schedule/Cost/Traffic Integrated Analysis
Best Practice of CTD: TxDOT IH-20 Phase I Project
IH-20 Dallas6.128mi x 3 lanes x 2 directionsFull-depth 13” CPCD55,257 AADT with 27% truckA+B+I/D with $4,000 daily I/D270 Working Days
Weekday
Nighttime
Schedule/Cost/Traffic Integrated Analysis
Best Practice of CTD: TxDOT IH-20 Phase I Project
IH-20 Dallas6.128mi x 3 lanes x 2 directionsFull-depth 13” CPCD55,257 AADT with 27% truckA+B+I/D with $4,000 daily I/D270 Working Days
Weekday
Nighttime
No Public Events
No Right-of-Way Issues
No Utility Conflicts
No Adjacent Business and Community Concern
Schedule/Cost/Traffic Integrated Analysis
Best Practice of CTD: TxDOT IH-20 Phase I Project
IH-20 Dallas6.128mi x 3 lanes x 2 directionsFull-depth 13” CPCD55,257 AADT with 27% truckA+B+I/D with $4,000 daily I/D270 Working Days
Weekday
Nighttime
Weekday Closure is much more favorable than Nighttime in that:
It is 77% faster and 68% saving in reduced road user delay costs.
It yields much higher production rate.
The scope of the project can be accomplished 60 days earlier: 210 vs 270.
Recommendations
Schedule/Cost/Traffic Integrated Analysis
Best Practice of CTD: TxDOT IH-20 Phase I Project
RecommendationsIncentive/Disincentive (I/D):
The estimated 270 working days by the agency appear slightly overestimated,
which can result in a $240,000 free bonus to the GC without any additional
commitment.
Agency’s estimated daily I/D amount of $4,000 is reasonable, based on the
computed daily RUC of $8,766.
Schedule/Cost/Traffic Integrated Analysis
Best Practice of CTD: TxDOT IH-20 Phase I Project
TxDOT IH-20 Phase I Project: Initial Plan Amended
THANK YOU
Slide Number 1Slide Number 2Paradigm ShiftSlide Number 4Slide Number 5Slide Number 7Slide Number 8Slide Number 9Slide Number 10Slide Number 11Slide Number 12Slide Number 13Slide Number 14Slide Number 15Slide Number 16Slide Number 17Slide Number 18Slide Number 19Slide Number 20Slide Number 21Slide Number 22Slide Number 23Slide Number 24Slide Number 25Slide Number 26Slide Number 27Slide Number 28Slide Number 29Slide Number 30Slide Number 31Slide Number 32Thank You