Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
Department of Civil Engineering and Architecture
LONG-SPAN RAILWAY BRIDGE DESIGN:
EVALUATION OF ALTERNATIVE STRUCTURAL
FORMS, A CASE-STUDY OF A 170 M SINGLE-SPAN
DOUBLE-TRACK BRIDGE
PIKASILDELISTE RAUDTEESILDADE PROJEKTEERIMINE: ALTERNATIIVSETE
KONSTRUKTSIOONILAHENDUSTE TEHNILINE ANALÜÜS 170 M SILDEAVA
KORRAL
MASTER’S THESIS
Student Kees Vanamölder
Student code 144394EATM
Supervisor Professor Juhan Idnurm
Tallinn 2017
1
AUTHOR’S DECLARATION
Hereby I declare that I have written this thesis independently.
No academic degree has earlier been applied for based on this material.
All works, major viewpoints and data of the other authors used in this thesis have been
referenced.
19.05.2017
Author: ..............................
/signature /
Thesis is in accordance with terms and requirements
“.......” .................... 201….
Supervisor: ….........................
/signature/
Accepted for defence
“.......”....................201… .
Chairman of theses defence commission: .............................................................................
/name and signature/
2
Preface
Current MSc thesis has been carried out in cooperation with Republic of Estonia Technical
Regulatory Authority and Ministry of Economic Affairs and Communications in order to
analyse possible structural solutions for railway bridge of Rail Baltic over Pärnu river.
I would like to express high gratitude to my supervisor professor Juhan Idnurm for
supporting, consulting and advising me during thesis writing. I want to thank professor
emeritus Siim Idnurm for teaching and introducing me to the exciting world of bridge and
structural engineering. I appreciate highly my mentor and a great friend Vladimir Keiv for
motivating me to study bridge engineering.
Finally, I would like to thank everyone who have contributed to my pleasant time at Tallinn
University of Technology during my master studies 2014-2017, including my fellow-
students from the university and colleagues from Sweco.
3
Table of contents
Preface ...............................................................................................................................2Table of contents ................................................................................................................31 Introduction ................................................................................................................52 Literature survey and current practice in design of long-span railway bridges .............6
2.1 Classic arch bridges .............................................................................................72.2 Network arch bridges ......................................................................................... 102.3 Cable-stayed bridges .......................................................................................... 142.4 Suspension bridges ............................................................................................ 182.5 Truss bridges ..................................................................................................... 232.6 Beam and cantilever bridges .............................................................................. 25
3 Case-study: technical characteristics and ground information ................................... 303.1 Location of designed railway bridge .................................................................. 303.2 Railway track geometry on the bridge ................................................................ 323.3 Technical constraints for design and requirements of Rail Baltic ........................ 33
4 Structural design of solutions for case-study railway bridge...................................... 354.1 Structural materials ............................................................................................ 354.2 Basics of structural design.................................................................................. 36
4.2.1 Loads .......................................................................................................... 364.2.2 Ultimate limit state ..................................................................................... 394.2.3 Service limit state ....................................................................................... 414.2.4 Structural dynamics .................................................................................... 43
4.3 Structural design and FEM analysis ................................................................... 444.3.1 Basics of girder modelling .......................................................................... 454.3.2 Basics of arch modelling ............................................................................. 464.3.3 Basics of cables modelling .......................................................................... 474.3.4 Basics of truss modelling ............................................................................ 474.3.5 Supports and bridges layout ........................................................................ 47
5 Structural evaluation and description of bridge alternatives ...................................... 505.1 Deflections and displacements of structural elements ......................................... 505.2 Internal forces of structures ................................................................................ 53
4
5.3 Conclusions of structural analysis ...................................................................... 566 Quantities of structural materials .............................................................................. 577 Life cycle cost evaluation ......................................................................................... 58
7.1 Methodology and base-prices ............................................................................. 587.2 Conclusions and LCC comparison ..................................................................... 61
8 Aesthetics evaluation ................................................................................................ 648.1 Methodology...................................................................................................... 648.2 Conclusions ....................................................................................................... 64
9 Conclusions and further research .............................................................................. 679.1 Conclusions ....................................................................................................... 679.2 Main contributions ............................................................................................. 679.3 Further research ................................................................................................. 68
10 Summary .................................................................................................................. 6911 Kokkuvõte................................................................................................................ 70Bibliography .................................................................................................................... 71
5
1 Introduction
Due to constant development and upgrading of railway infrastructure around the world,
structural solutions for long-span railway bridges need to be applied around the world. Being
a technically advanced solution and requiring high investments, decision-making about cost-
effective and rational structural form is important.
Many long-span railway bridges were built during 19th or 20th century around the world.
Despite long history, bridge engineering is in constant development by new construction
materials, increased application of high strength concrete and steel and new developments
for innovative structural solutions.
For example, network arch bridge that is among the structures analysed in current study, was
developed during the second half of 20th century but found wider use in last 20 years
[Varennes 2011]. Truss bridges have been widely used during 19th and 20th century,
nowadays optimized structural forms have been developed.
The aim of current study was to analyse and compare different structural forms for 170 m
single-span railway bridge, taking into account modern structural solutions and materials
available. For comparing the structural forms, following evaluation criterions have been
defined:
- Cost-effectiveness: life-cycle cost and construction price;
- Aesthetics: architectural value of structural form of bridge.
For estimation of described criterions, conceptual design, including structural analysis and
optimization was carried out on 5 different structural forms for case-study bridge.
6
2 Literature survey and current practice in design oflong-span railway bridges
In current chapter, literature survey was carried out to determine common design and
construction practices of railway bridges similar to 170 m span that is being analysed in
current study.
Bridges with double-track railway superstructure spanning up to 170 m are considered as
exceptional solutions and should not be considered as economically reasonable solution in
case possibility for intermediate supports exist. According to investigations conducted at
Delft University of Technology, long-span solutions for double-track railway bridges solved
with arch or cable-stayed structure showed to be in average 1.7...1.9 times more expensive
than typical continuous beam or truss bridge with intermediate supports. [TU Delft: ESDEP
course]
Optimal and possible span length for different bridge structure types can be observed from
Figure 2.1. These values are based on mechanical characteristics of existing building
materials, excluding any possible new materials that could probably be available in the
future. [Melaragno 2009]
Figure 2.1. Optimal and possible range of span for different bridge structure types
0
100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
1400
1500
Concrete/steel beambridge
Steel truss bridge
Concrete/steel archbridge
Cable stay bridge
Suspension bridge
Span lenght [m]
7
As showed in Figure 2.2, all above described bridge types can be found amongst variety of
road bridges in Sweden (Trafikverket) [Safi 2012].
Figure 2.2. Structural forms of road bridges in use in Sweden with span range 100-200
m
2.1 Classic arch bridges
Arch is a typical structure of bridge for spans between 50-400 m. Philosophy of arch bridge
lies in exertion of vertical loads into compression forces in the arch cross-section and
transmitting them to ground support to be balanced by horizontal and vertical reaction
component.
Since for curved beams forming the arch, longitudinal forces are usually more economical
to resist compared to bending, arch type structure, in case if optimally designed, can be more
economical for long spans, compared to simple beam bridges.
For abutments of arch bridge, solid ground conditions are required since both vertical and
horizontal forces from the arch are transmitted to the ground by abutments. [Melaragno
1998]
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Beam/truss bridge
Arch bridge
Cable stay bridge
Suspension bridge
Number of bridges in analysed segment [pcs]
8
Arch bridges for long spans can be divided into two main categories based on configuration
of hinges presented in Figure 2.3.
Figure 2.3. Arch types divided according to number of hinges [Sundquist 2007]
For zero-hinge arches, foundation needs to absorb both the horizontal force and clamping
moment, therefore remarkably good ground conditions are required, preferably rock or other
material with internal friction. Zero-hinge arches provide the most material-economical
solution for arch. In case of poor ground conditions, two-hinge arch should be introduced.
In Figure 2.4, different bridge deck configurations are presented. Bridge types 4) and 5) use
deck plate as both tie and stiffening beam, as for bridge types 1) and 2) expansion joint have
been introduced to accommodate railway connection in the middle of the bridge. This
solution can be called bow-string arch and can be used for two-hinge arch in order to reduce
horizontal reaction forces on abutments.
9
Figure 2.4. Different solutions of bridge deck configuration for arch bridges [Sundquist
2009]
Span-to-rise ratio L/f is normally provided between 5 and 7 in order to introduce
economically reasonable solution. [Sundquist 2007]
Figure 2.5. Stäketbron in Sweden. Concrete arch bridge on Mälarbanan (Stockholm-
Västerås railway). Span lenght 130 m. Opened for traffic in 2001. Picture of author
10
Figure 2.6. Typical process for construction of concrete arch bridge with no
intermediate supports. Arch is constructed step-by-step with supporting of pieces with
cables, supported on vertical columns and anchored to soil [Осипов, Храпов, Бобриков
1988]
For conventional arch bridge both reinforced concrete and steel are considered as suitable
options for arch material. Reinforced concrete, according to world practice, can be more
suitable option when majority of internal forces are formed by bending moments. In case
of longitudinal tension is considered as the dominating type of internal forces, steel arch
would be more suitable. [Осипов, Храпов, Бобриков 1988]
In case of arch is installed on top of bridge deck, vertical hangers conventionally can be
manufactured from steel since they work for longitudinal tension.
2.2 Network arch bridges
Network arch is defined as a tied-arch bridge with inclined hangers that cross each other at
least twice. The hangers always work under tension and chords for both tension and
11
bending. Arch is usually manufactured from steel. Lower bridge deck is typically a
concrete slab. Example of network arch bridge is presented in Figure 2.7. [Varennes 2011]
Figure 2.7. Typical network arch bridge [Varennes 2011]
Figure 2.8. Network arch road bridge at Rannu-Jõesuu, Estonia. Span lenght 90 m,
opened in 2009. Photo: AS Merko Ehitus.
Network arch hangers can be wires or rods and they have strength for longitudinal tension,
they are not meant for resisting bending moments. Hangers are typically tied to each other
in order to prevent them from bumping into each other.
Network arch bridge is considered to be structural form where components are loaded with
more longitudinal tension and less bending moment compared to tied arch bridge. This
12
effect is especially remarkable in case if bridge is only partially loaded and not being under
constant divided load for all length. This phenomena was characterised by calculations of
Per Tveit in 1980, presented in Figure 2.9. [Tveit 2014]
Figure 2.9. Influence lines for bending moments in the lower chords [Tveit 2014]
Hangers of network arch should be configured as shown in Figure 2.10. Angles α between
arch axis and hangers should be equal.
Figure 2.10. Geometry of fastening for hangers and arch [Brunn, Schanack 2003]
13
Figure 2.11. Fehrmansundbrücke, Germany. Steel network arch bridge on railway line
Lübeck-Puttgarden, longest span 248 m. On bridge deck single-track railway and 1+1 road
is accommodated. Bridge was constructed 1960-1963. Photo: Mario Schürholz
In order to simplify constructability, arch structure for network arch bridge has typically
circular shape. It could be manufactured from I-beams (shorter spans) or box steel beams
(longer spans).
Network arch as a first alternative can be constructed on site by erecting the arch and
fastening the hangers with each other and finally constructing the lower bridge deck. Since
network arch is considered to be light structure, compared to other bridge types,
constructing it nearby and then lifting it on site with floating cranes (Brandanger bridge,
Norway) or by sliding the bridge to right place. Mentioned alternative is illustrated in
Figure 2.12. [Tveit 2014]
14
Figure 2.12. Possible construction technology proposed by Per Tveit for Straubing
bridge (span lenght 152 m), Germany, constructed in 1981 [Tveit 2014]
2.3 Cable-stayed bridges
Cable-stayed bridge consist of vertical or longitudinally tilted pylons and cables that connect
pylons to the bridge deck. Typically cable-stayed bridge consists of one medium span and
two spans on sides that in most cases are approximately two times shorter than medium span.
Beams that support the bridge deck can be trusses, plate-girders or box-girders. Cable-stayed
15
bridges are common solutions for covering long spans, also for railway bridges. Typical
configurations of a cable-stayed bridges are presented in Figure 2.13. [Осипов, Храпов,
Бобриков 1988]
Figure 2.13. Main structural types of cable-stayed bridges. Type 1) harp configuration,
type 2) fan configuration and type 3) asymmetrical system. For type 4) pylon has been tilted
in longitudinal direction in order to equalize cable forces [Sundquist 2009, Idnurm 2016]
16
Figure 2.14. Cable-stayed bridge over Po river, Milan-Bologna high-speed railway in
Italy. Main span length is 192 m, the bridge was opened in 2006. Picture: Mario Petrangeli
& Associati
Cables are typically formed of steel ropes fixed with internal plastic cover. Several
different configurations exist for configuration of cable and pylon supports. Main
configurations are presented in Figure 2.14. [Idnurm 2016]
17
Figure 2.15. Typical construction procedure of a cable-stayed bridge [Sundquist 2009]
18
Figure 2.16. Main configurations of cable fastenings and pylon supports for cable-stayed
bridge. For a) and b) cables are fastened to bridge deck and are therefore supported for
both sides. For c) cables are anchored to ground, pylon can be lighter in that case. For d)
pylons are stiffly fastened with deck plate. For railway bridges typically solution a) or b) is
applied [Idnurm 2016]
2.4 Suspension bridges
A suspension bridge is a type of bridge in which the deck (the load-bearing portion) is hung
below suspension cables on vertical suspenders. Main load-bearing components are main
cable, vertical hangers, pylons and bridge deck that also works as stiffening girder (See
Figure 2.17).
19
Suspension bridges can be classified by number of spans, continuity of stiffening girders,
types of suspenders and types of cable anchorage. Stiffening girders can be classified into
two-hinge or continuous types. In order to provide equalised distribution of internal forces,
for railway (or combined road-railway bridges) typically continual girder is preferred. [Kivi
2009]. Examples of suspension bridge classification can be found from Figures 2.18 and
2.19.
Figure 2.17. Main components of suspension bridges and typical cable ground anchorage
[Harazaki, Suzuki, Okukawa 2000]
20
Figure 2.18. Suspension bridge with continuous (a) and two-hinge (b) stiffening girders
Figure 2.19. Suspension bridge with cable anchorage to stiffening girder with side-spans
(a) and to externally anchored main cables (b) without side-spans.
Typically suspension bridges are designed with one span in the middle and two side-spans
with length 0.5 times the length of middle span. In case if the need for side-spans does not
exist, suspension bridge can be designed also with single middle-span with main cables
anchored to ground (Figure 2.18b). [Gimsing, Georgakis 2012]
Typically suspension bridges are in use in world practice for long-span solutions (300 m or
more) with road or combined road-railway bridges. Longest spans of suspension bridges
cover up to 2000 m in length.
(b)
(a)
(a)
(b)
21
World’s practice lacks of good examples about railway dedicated suspension bridges.
World’s first railway suspension bridge was opened in 1855 at Niagara Falls between USA
and Canada (Figure 2.20). Good examples exist for very long-span road and railway
combined bridges, bridges with span more than 1,0 km have been built (Figure 2.21).
Figure 2.20. Suspension bridge for single-track railway, opened in 1855 with middle span
length 251 m. The suspension bridge was replaced with arch bridge during 1890s due to
increased traffic loads.
22
Figure 2.21. Tsing Ma bridge in Hong Kong, carrying 6 lanes of road traffic and 2 railway
tracks with middle span 1377 m [Wikipedia]
Typical erection technology for suspension bridge involves firstly launching main cables
and fastening deck plate and hangers piece-by-piece to main cables and can be observed
from Figure 2.22. [Harazaki, Suzuki, Okukawa 2000]
Figure 2.22. Typical construction technology of a suspension bridge
23
2.5 Truss bridges
Truss is a load-bearing element of a structure that is formed of elements that bear only
longitudinal tension and compression, not bending moment, and are connected to each other
with pinned joints. Truss was introduced to wider use for railway bridges during 19th century.
Main types of truss configuration can be found from Figure 2.23.
Figure 2.23. Main truss types in use for bridges [Kulicki 2000]
In world practice truss has appeared as reasonable structural type for covering spans between
25 and 300 m. Examples of truss bridges can be found from Figures 2.24, 2.25 and 2.26.
24
Figure 2.24. Steel truss single-track railway bridge in Estonia over Narva river with span
150 m that was opened for traffic in 1947. Truss can be considered as double-intersection
Warren type
Figure 2.25. Ekensbergsbron in Stockholm city, light rail Warren truss bridge over
conventional railway with span 70 m that was manufactured during 2011 [promostal.pl]
25
Figure 2.26. Stockley bridge in London is a Warren truss railway bridge constructed in
2014 [crossrail.co.uk]
Warren truss has occurred as the most popular option for railway bridges during 1980s and
1990s due to high structural performance and aesthetics.
Typically truss bridges are constructed similarly compared to network arch or tied arch
bridges, i. e manufactured on ground and then lifted to place. [Kulicki 2000]
2.6 Beam and cantilever bridges
Beam and slab bridges are not frequently used for covering long spans because usually high
beam is needed for that case and that increases significantly structural height of a bridge.
Span-to-structural depth ratio is usually considered to be about 1/20 in case of concrete
bridges, so for example bridge with 170 m span would require at least 8,5 m height of beam
and slab. [Melaragno 1998] Therefore simple beam or continous beam bridges are not further
analysed in current study.
For beam cross-section, T-beams, box-girders or steel-concrete composite bridges can be
used. Two mainly preferred girder systems for long-span bridges can be followed in Figure
2.27.
26
Figure 2.27. Possible cross-sections for long-span single-track railway beam or cantilever
bridge – box girder (left) and steel-concrete composite bridge (right) [Sundquist 2009]
For long-span bridges, balanced cantilever bridges can be used that are common in world
practice with span range 100-300 m. Bridge piles support rigidly cantilevers that are usually
formed of symmetrical beams, balancing vertical loads both sides of supports. Beams are
connected to each other in the middle of a span with vertically stiff bearing in order to
equalize internal forces of structure. [Sundquist 2009] Typical cantilever bridge layout can
be seen in Figure 2.28.
Figure 2.28. Typical cantilever bridge [Sundquist 2009]
27
Figure 2.29 Voroshilov cantilever road bridge, Russia. Longest span 160 m. Photo:
Rostov-on-Don city municipality
Typical construction method for cantilever bridge construction is presented in Figures 2.29
and 2.30. Bridge is being constructed step-by-step by lifting segments into place.
Figure 2.30. Construction of Krasnopresnensk cantilever bridge from precast concrete
elementsthat are lifted into place with a crane, Russia. Span 130 m [Осипов, Храпов,
Бобриков 1988]
28
Figure 2.31. Construction of cantilever road bridge at Ihaste, Estonia. Cast-in-situ
technology is applied with movable form step-by-step. Photo: Estonian society of concrete
engineering
In order to compensate bending moment that is exerted to cantilevers in middle span, typical
cantilever bridge should have in addition to middle span, side spans with length about 0,5
middle span. Structure of cantilever bridge is being designed with an assumption that
selfweight of side span bridge deck and possible traffic load on side span compensates
bending moments exerted to structure in middle span. Therefore bridge supports are not
designed to resist great bending moments and properly designed side spans are required. In
case if side spans were to be eliminated and supports to be designed to resist bending
moments the described technical solution of a bridge would appear to become an integral
beam bridge instead of cantilever bridge. Integral beam bridges have not shown to be
technically optimal solution for span as long as 170 m. [Sundquist 2009]
As the case-study railway bridge of current thesis does not require side spans and providing
side spans would result with unreasonably long and probably economically not optimal
solution, cantilever bridge is not further analysed in this study.
29
For case-study railway bridge, cantilever bridge requires to be analysed in further
investigations in case of placement of supports into the river becomes possible or side spans
appear to be necessary due to additional roads etc.
30
3 Case-study: technical characteristics and groundinformation
In order to evaluate possible structural solutions for bridges in practical case, case-study was
performed on the basis of designed Rail Baltic bridge over Pärnu river.
Rail Baltic is designed as new railway line between Tallinn and Poland that would connect
Baltic states with European railway network with 1435 mm track gauge. Rail Baltic is
double-track electrified railway line for mixed traffic with design speed of 240 km/h and
with overall length around 700 km. In Estonia overall length of railway route is around 210
km and railway alignment follows Tallinn (Muuga/Ülemiste), Rapla, Pärnu and Ikla.
Preliminary design of Rail Baltic will be finished during 2017-2018. Detailed design will be
carried out starting from 2018. Construction works scheduled to begin in 2019 and by 2026
new railway will be opened for traffic.
For ground information of current study, Rail Baltic preliminary design was presented to
author by agencies representing Estonian government in Rail Baltic project1 and consulting
company2 performing preliminary design.
3.1 Location of designed railway bridge
According to approved railway alignment in preliminary design, Rail Baltic intersects Pärnu
river, with a width of 150 m, inside Pärnu city. Due to environmental reasons locating bridge
supports into the river is restricted, therefore bridge spanning around 170 m needs to be
applied.
Future Rail Baltic bridge is located 20 m East from existing railway and road bridge over
Pärnu river. Location of bridge can be seen in Figures 3.1, 3.2, 3.3 and Appendix 1.
1 Republic of Estonia Ministry of Economic Affairs and Communications;Republic of Estonia Technical Regulatory Authority.2 Reaalprojekt OÜ
31
Figure 3.1. Route of Rail Baltic inside Pärnu city. With red circle case-study bridge
location is highlighted.
Figure 3.2. Proposed location of case-study bridge, view from North-East side. Future
Rail Baltic bridge will be located next to existing railway and road bridge.
32
Figure 3.3. Proposed location of case-study bridge, view from South-East side.
3.2 Railway track geometry on the bridge
On the proposed bridge a double-track railway is located with a straight track section and a
constant gradient 5‰.
Following clearances have been taken into account for bridge design:
- Vertical clearance above road at least 5,3 m;
- Vertical river clearance 7,3 m or more.
As a part of Pärnu station, railway track crossovers need to be placed on the bridge. That
requires good accessibility and possibility for turnout installation to be taken into account in
bridge design. Since, according to current design, turnouts are partly located on deformation
joints that cannot be relocated on the future bridge, solution for turnouts on the bridge will
probably need to be redesigned.
Due to railway horizontal curve near Pärnu station, design speed of railway on the Pärnu
river bridge is restricted to 120 km/h.
33
3.3 Technical constraints for design and requirements of RailBaltic
Near Pärnu river, two road bridges need to be located at:
- Km+m 5+265 that is solved with a slab frame bridge in current study, span length
8,0 m;
- Km+m 5+526 that during current study is solved with a two-span (20+24 m)
continuous beam.
Due to design restriction of one middle-span and two relatively short side spans, structural
forms that require side-spans with at least 0,5 times the length of middle-span (cantilever
bridge, typical solution of suspension or cable-stayed bridge) cannot be used or needs to be
modified to meet the requirement of having only one span.
Due to clearances, main load bearing structure cannot be accommodated under a bridge and
therefore arch, truss etc need to be located above the bridge deck.
For Rail Baltic, railway structural clearance GC is in use together with distance between
parallel railway tracks 4,2 m that can be followed in Figure 3.4. [EVS-EN 15273-
3:2013+A1:2017]
34
Figure 3.4. Typical cross-section of Rail Baltic structural clearance (GC
35
4 Structural design of solutions for case-study railwaybridge
In order to provide alternative bridge solutions on sufficient level that allows to compare
them by multi-criteria analysis and to perform technical assessment, solutions were designed
on a level of preliminary bridge design. Designed structures can be followed from
appendixes 2, 3, 4, 5 and 6.
Structural analysis were carried out using FEM (Finite element method) numerical analysis
with software Bentley STAAD.Pro. Structure elements were dimensioned on the basis of
ultimate limit state (ULS) and service limit state (SLS).
Bridge structure optimisation and structural analysis were parts of overall technical
evaluation that allowed to make conclusions about different technical characteristics of
investigated bridge solutions.
4.1 Structural materials
For structural analysis and technical evaluation, main structural materials were used that
form the basis of structures load bearing capacity. List of structural materials and their
properties is presented in Table 4.1.
36
Type of material Steel S355Reinforced concrete
C35/45
Modul of elasticity E [MPa] 210*10³ 33,5
Poisson’s ratio υ 0,3 0,2
Shear modulus G [MPa] 81*10³ 9,28*10³
Density ρ [kg/m³] 7850 2500
Yield stress f.y [MPa] 335
Tensile strength f.u [MPa] 490
Compression strength f.ck [MPa] 35
Table 4.1. List of structural materials properties used in current study [Rohusaar et al
2014, Otsmaa 2014]
Reinforced concrete was modelled with FEM as monolitic material with modul of elasticity
60 MPa for longitudinal tension. Reinforcement rate was not considered during current study
since it needs to be determined during following phases of design.
4.2 Basics of structural design4.2.1 Loads
Load models that were used as basis of structural design, are defined in standard EVS-EN
1991-2/NA:20073. Main load models for railway traffic on bridges are as follows:
- Vertical traffic loads LM71, SW/0 and SW/2, presented in figures 4.1 and 4.2;
- Centrifugal force, applied in case railway track on a bridge is located on a horizontal
curve;
- Traction and braking force;
- Derailment forces.
For vertical load definition, load models LM71 and SW/2 have been applied:
3 EVS-EN 1991-2/NA:2007. Actions on structures. Part 2: Traffic loads on bridges. Estonian National Annex
37
Figure 4.1. Load model LM71 for static influence of conventional railway traffic [EVS-
EN 1991-2]
Figure 4.2. Application scheme of load model SW/0 for static influence of conventional
railway traffic to continuous beam structure and SW/2 for influence of heavy railway traffic
[EVS-EN 1991-2]
Load model qvk [kN/m] a [m] c [m]
SW/0
SW/2
133
150
15,0
25,0
5,3
7,0
Table 4.2. Normative load values of SW/0 and SW/2 models
According to information that was available during this investigation for Rail Baltic, heavy
railway traffic load model SW/2 needs to be taken into account for dimensioning of
structures. SW/0 load model is not taken into consideration during current study since
continous beams are not in use for designed structures, it is expected that SW/2 is source of
higher loads that are governing compared to SW/0.
Vertical load models need to be multiplied with coefficient of dynamics Φ3 [EVS-EN 1991-
2/NA:2007] as following:
=2,16− 0,2
+ 0,73
has been considered as double distance between lateral beams, that according to designed
structures is 15 m. Therefore =1,32 for all structures.
38
Braking and traction forces acting on a bridge deck can be estimated according to
following rules:
- Traction force: Qlak= 33 [kN/m] La,b [m] ≤ 1000 [kN] for LM71, SW/0 and SW/2;
- Braking force: Qlbk=20 [kNm] La,b [m] ≤ 6000 [kN] for LM71 and SW/0 or Qlbk=35
[kN/m] La,b [m] for SW/2.
In order to evaluate the effect of different load models through bending moment formation
in the structure, a simple exercise has been carried out to compare load model effect on
simple beam bridge with 170 m long span. As seen from Figure 4.3, in general cases LM71
could be a source of highest bending moment in structure.
Figure 4.3. Calculated bending moments for 170 m single-span beam bridge.
Different structure types, such as suspension, cable-stayed or arch bridge could be more
sensitive to concentrated loads from load models SW/0 and SW/2. Also differences occur
depending on load exertion position on bridge deck – for example suspension bridges in
general could be more sensitive to concentrated loads on one side of the span than loads
exerted at mid-point of span.
0
50000
100000
150000
200000
250000
300000
350000
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170
Bend
ing
mom
ent[
kNm
]
x-coordinate of span [m]
LM71 SW/2 SW/2SW/0
39
Selfweight of designed structures are considered with their respective densities (see Table
4.1).
4.2.2 Ultimate limit state
Ultimate limit state (ULS) is defined as a loading state where structure is working at its limit
of load bearing capacity. Exceeding ULS would result in a collapse of the structure.
Load factors can be found from EVS-EN 1990:2002/A1:2006. Generally for railway bridge
design dead load factor = 1,35 and live load factor = 1,45. Therefore for ULS
following equations apply for total load calculations:
∑ = +
stands for dead load according to standard load models. stands for live load according
to standard load models.
For calculation of ULS, all normative load cases were analysed in combination with dead
load in order to analyse structural stress and define necessary dimensions of structural
elements.
For material strength check in ULS, permissable stress in material can be calculated as
following:
For concrete compression: =
For steel: =
According to EVS-EN 1993-2:2006 = 1,15 and = 1, 5.
Structures in current study have been dimensioned for ULS according to Eurocodes. Variety
of checks have been carried out to provide necessary structure load bearing capacity. For
example steel structures for bending and shear stresses, steel beams for buckling and
40
stability, reinforced concrete deformation, stresses, crack opening, reinforcement tension
etc.
For global design of compressed and/or bent steel structures classification of cross-sections
has been taken into use for determining safe limits for minimum flange and wall width.
According to Figure 4.4, steel elements have been dimensioned for class 1 cross-sections
[EVS-EN 1993-2:2006/AC:2009].
Figure 4.4. Drawings for determining element width t and size c and factor α for cross-
section classification [EVS-EN 1993-2:2006/AC:2009].
Cross-sections for class 1 need to be determined according to following equation [EVS-EN
1993-2:2006/AC:2009]:
In case if > 0,5, ≤
In case if ≤ 0,5, ≤
41
=235
Where – yield strenght of steel
For estimating stresses in elements that are simultaneously suffering bending moment and
longitudinal tension, following equation was used for determining stresses [EVS-EN 1993-
2:2006/AC:2009]:
, + , − , ∗ , + 3 ≤ 1
Where , – stress of longitudinal tension
, – stress of lateral tension
– shear stress
4.2.3 Service limit state
Service limit state (SLS) involves several requirements that need to be followed in order to
provide acceptable working situation for the structure. In case if SLS is not followed,
structure strength is not necessarily yet endangered, but structure working state is no longer
providing visual aesthetics or reasonable maintenance, also structure reliability could be in
danger.
Service limit state is stated in Eurocode EVS-EN 1990:2002/A1:2006 and main
requirements are following:
- Vertical accelerations of bridge deck must be limited in order to maintain contact
between rail and rolling stock wheel. For ballasted railway track acceleration is
limited to 3,5 m/s² and for slab track 5,0 m/s².
- Twist of bridge deck is limited in order to avoid risk of rolling stock derailment. For
railway tracks with design speed 120 km/h or less bridge deck is allowed to be
twisted up to 1,5‰.
42
- Deflection of every specific bridge span is limited in order to provide general
stiffness of structure and to ensure required minimum vertical radius for passenger
comfort. Required L/δ (span/deflection) ratios can be observed from Figure 4.4. L/δ
ratio overall must not exceed 600. That results in maximum 283 mm deflection of
bridge deck at any point for 170 m span.
- Horizontal displacement of bridge deck upper level at span end is limited in order to
provide sufficient working conditions for deformation joints.
- Bridge deck horizontal rotation around its bearing at span edge is limited in order to
maintain required level of railway track geometry.
- Lateral deflection of bridge deck is limited in order to avoid additional forces in rail
fastenings and rail longitudinal tension.
Figure 4.4. Minimum span/deflection values stated in Eurocode for bridge with 3 or more
spans. For single-span bridge L/δ should be multiplied with 0,7. [EVS-EN
1990:2002/A1:2006]
During FEM simulation of current study, bridge deck deformations are observed and further
discussed in chapter 5.
It is assumed that bridge deck deflections only need to be calculated with traffic loads since
deformations from selfweight are compensated during construction process and deflection
of a bridge suffering only selfweight and no traffic loads is zero.
43
4.2.4 Structural dynamics
According to Eurocodes [EVS-EN 1991:2004+NA:2007] requirements whether a static only
or also a dynamic analysis is needed, are presented on Figure 4.5.
Figure 4.5. Flow chart for determining whether a dynamic analysis is needed [EVS-EN
1991:2004+NA:2007]
44
Where V – maximum line speed at site [km/h];
L – span length [m];
n0 – first natural bending frequency of the bridge loaded by permanent actions
[Hz]
nT – first natural torsional frequency of the bridge loaded by permanent
actions [Hz]
v – maximum nominal speed [m/s]
According to Eurocodes, dynamic analysis is not needed for case-study railway bridge.
Therefore dynamic analysis are not included in this study and the results are valid only for
bridges that do not require dynamic analysis.
4.3 Structural design and FEM analysis
In order to analyse structural differences of bridges for load bearing capacity and to
determine dimensions of structural elements, structural analysis with FEM software Bentley
STAAD.Pro was carried out during this study. Bridge structures were analysed with traffic
loads and self-weight according to EVS-EN 1991-2/NA:2007.
Ultimate limit state (ULS) was evaluated according to EVS-EN 1990:2002/A1:2006 and
EVS-EN 1993-2:2006 and therefore bridge structures were dimensioned with sufficient load
bearing capacity. As a result of the study, major requirements that define structure
dimensions for ULS and has the most effect on overall design of the bridge from ULS point
of view are stresses in bridge elements (arch, pylons, cables and deck plate) due to tension,
compression and bending.
Service limit state (SLS) was determined according to requirements in EVS-EN
1990:2002/A1:2006, therefore bridges were dimensioned according to different
requirements stated for SLS.
As a result of the study, major requirement that defines structure dimensions for SLS and
has the most effect on overall design of the bridge from SLS point of view is vertical
deflection of bridge deck. Other requirements such as twisting of bridge deck or horizontal
deflection of elements can easily be avoided with increase of dimensions and moment of
45
inertia for single specific element. Therefore these requirements have no effect on general
structure of the bridge.
4.3.1 Basics of girder modelling
Designed bridge deck is typically a box girder of reinforced concrete, carrying two tracks of
ballasted or ballastless railway. Deck width has been selected according to required
structural clearances of railway and fixed distance between track centrelines. Typical cross-
section is presented in Figure 4.6.
Figure 4.6. Typical bridge deck for designed alternatives.
Girder has been modelled in STAAD.Pro as 4 parallel longitudinal beams consisting of
following:
- Two edge beams, forming edge of deckplate and fastening of cables and hangers;
- Two main beams, forming together box gross-section, including walls, upper and
lower flanges.
For load distribution between girders, lateral beams were designed, typically with 10 m step
between longitudinal girders. Typical girder modelled in STAAD.Pro is presented in Figure
4.7.
46
Figure 4.7. Analysed deck plate in STAAD.Pro. Longitudinal girders are displayed red,
lateral beams are painted blue and edge beams green.
Deck plate was analysed as a beam element, working for bending, tension and compression.
4.3.2 Basics of arch modelling
For arch bridge, reinforced concrete arch was taken into use and modelled in STAAD.Pro as
beam element, working for bending, tension and compression. Box beams were used as arch
with cross-section 2.0*2.5 m. Arch was formed from different straight beams that were
connected to each other at hanger position.
For network arch bridge, steel box beam is used as arch with dimensions 0.75*1.0 m. Cross-
sections of steel and reinforced concrete arch are shown in Figure 4.8.
47
Figure 4.8. Cross-sections of reinforced concrete (left) and steel arch analysed in current
study
4.3.3 Basics of cables modelling
Cables and hangers of all bridge types were modelled from steel with a condition that they
can only bear longitudinal tension, not to resist bending moment or compression (truss
element). Therefore realistic working conditions were possible to simulate.
4.3.4 Basics of truss modelling
Truss was modelled similar to cables and hangers, they were programmed to bear only
longitudinal forces: tension and compression.
Box steel beams were used as members for truss bridge with selected cross-section 0.7*0.7
m for main horizontal rod and 0.5*0.5 m for diagonal rods.
4.3.5 Supports and bridges layout
For analysis of bridge structures, bridges with 170 m long main span were considered
separately from short-spans at North side of the bridge. For deck plate, simple beam instead
of continuous beam was used (for arch bridge, continuous beam with intermediate supports
to arch through hangers) in order to avoid interaction of long-span bridge structure with side-
span on North side of the bridge and therefore to avoid unequal force and displacement
distribution in the main span.
48
Pylons were modelled with stiff fastening to ground as they could be reinforced in stiff
connection with foundation.
Layouts of alternative bridges 1, 2, 3, 4 and 5 are presented in Figure 4.9. With black, beams
and truss members are presented. With red, cables and hangers are presented.
FEM models made with Bentley STAAD.Pro can be found from Figure 4.8.
49
Figure 4.9. Layouts of tied-arch bridge (alternative 1, a), network arch bridge (alternative
2, b), suspension bridge (alternative 3, c), cable-stayed bridge (alternative 4, d) and truss
bridge (alternative 5, e). Tied-arch bridge deck is formed of continous beam, supported at
ends and by arch. For other alternatives bridge deck is formed of simple beam
(b)
(a)
(c)
(d)
(e)
50
5 Structural evaluation and description of bridgealternatives
5.1 Deflections and displacements of structural elements
Deflection of bridge deck under traffic loads is important parameter that should be followed
during structural design of a railway bridge. Deflection is limited according to Eurocode
service limit state requirements and therefore forms one of the main criterions for
dimensioning of general bridge structural elements, such as arch, hangers, truss, deck plate
etc. Deflection characterizes an overall bending stiffness of bridge structural form.
During current study was estimated that deflection of structure selfweight could be
compensated during construction and therefore only deflection from traffic loads needs to
be taken into account. Deflection of bridge deck of compared structural forms can be
followed from Figures 5.1, 5.2 and 5.3. Overall deformations can be followed from Figure
5.4.
Figure 5.1. Bridge deck deflection caused by traffic load LM71.
-250
-200
-150
-100
-50
0
50
0 10 20 30 40 50 60 70 80 90 100
110
120
130
140
150
160
170
Defle
ctio
nof
brid
gede
ck[m
m]
x-coordinate [m]
Arch
Network arch
Suspension
Cable stay
Truss
51
Figure 5.2. Bridge deck deflection caused by traffic load SW/2 that has been located to
the middle of span.
Figure 5.3. Bridge deck deflection caused by traffic load SW/2 that has been located to
the edge of span.
-300
-250
-200
-150
-100
-50
0
50
0 10 20 30 40 50 60 70 80 90 100
110
120
130
140
150
160
170
Defle
ctio
nof
brid
gede
ck[m
m]
x-coordinate [m]
Arch
Network arch
Suspension
Cable stay
Truss
-300
-200
-100
0
100
200
300
0 10 20 30 40 50 60 70 80 90 100
110
120
130
140
150
160
170
Defle
ctio
nof
brid
gede
ck[m
m]
x-coordinate [m]
Arch
Network arch
Suspension
Cable stay
Truss
52
Figure 5.4. Deformations caused by LM71 traffic load exaggerated 100 times for arch
(a), network arch (b), suspension (c), cable-stayed (d) and truss bridge (e)
a)
b)
c)
d)
e)
53
According to analysis of deflections of different structural forms of bridges, following
conclusions can be formed:
- Conventional arch bridge can be considered as a relatively stiff structure for loads
that are located to middle of span. In case if load is located only to one side of the
span, deflections occure higher due to low bending stiffness of bridge deck and
displacement of arch;
- Network arch bridge can be considered as relatively stiff structure that results in
low deformations. Bridge deck deflection for equally distributed load is higher than
for concentrated load in the middle of the span. High structural stiffness means that
the structure should be dimensioned for ultimate limit state instead of service limit
state;
- Truss bridge can be considered as relatively stiff for loads that are exerted to one
side of the span, but relatively flexible for loads that are equally distributed to the
whole length of the span;
- Suspension and cable-stayed bridges have the least stiffness for concentrated loads
that are exerted to only one side of the span due to low bending stiffness of bridge
deck and flexible structural form. High flexibility of structural form causes high
dimensions of structural elements that need to be dimensioned according to service
limit state and therefore have high amount of reserve for ultimate limit state.
5.2 Internal forces of structures
In order to characterize distribution of loads in structure, peculiarities of every studied
structural form are described in current chapter.
As described in previous chapters, arch structures are dedicated to work under compressive
internal forces and the amount of bending moment should be as small as possible. Internal
bending moments for arch and network arch bridge are presented in Figure 5.5.
54
Figure 5.5. Internal bending moments for conventional arch and network arch bridges
formed by SW2 load model and selfweight
As visible from Figure 5.5, arch is suffering higher amount of bending moments in case of
classic arch bridge compared to network arch since hangers that are configured in diagonal
direction compensate bending moment which therefore results in required lower bending
stiffness of arch. Bending moment in deck plate is distributed more equally in case of classic
arch bridge compared to network arch.
Axial force diagrams of designed structures are presented in Figure 5.6.
55
Figure 5.6. Deformations caused by SW2 traffic load and selfweight for arch (a),
network arch (b), suspension (c), cable-stayed (d) and truss bridge (e). Tension is presented
with red, compression with blue color
a)
b)
c)
d)
e)
56
According to Figures 5.1-5.6, following conclusions can be made:
- For classic arch bridge, load bearing capacity of the structure is formed mainly by
bending of bridge deck and arch and compression of arch. For non-tied arch bridge,
deck is working for tension only with longitudinal, but not with vertical traffic loads.
Due to high compression forces in the arch, geotechnical conditions of ground ought
to be sufficient for anchorage;
- For network arch bridge, load bearing capacity of the structure is formed mainly
by compression of arch and tension and bending of bridge deck;
- For steel truss bridge, load bearing capacity of the structure is formed mainly by
longitudinal tension and compression of rods and bending of bridge deck;
- For suspension and cable-stayed bridges, structural load bearing capacity is formed
by tension of cables, compression of pylons and bending of deck plate. Due to high
tension in anchored cables, geotechnical conditions of ground ought to be sufficient
for anchorage.
5.3 Conclusions of structural analysis
In order to satisfy the criterions for ULS (ultimate limit state) and SLS (service limit state)
structural design for different structural forms, bridge alternatives were designed and
analysed. ULS was main criterion for global design of structure for network arch and truss
bridges. Therefore these two structural forms are over-dimensioned for SLS.
SLS was main criterion for global design of structure for suspension, arch and cable-stayed
bridges. Due to high requirements for railway bridges SLS (including deflection), suspension
and cable-stayed bridges need to have relatively massive structure with high longitudinal
stiffness of cables.
57
6 Quantities of structural materials
According to designed and optimised structures, quantities of structural materials have been
calculated for designed bridge alternatives. More detailed list of quantities can be found in
Appendix 7. Quantities of requiered reinforced concrete and structural steel are presented in
Figures 6.1 and 6.2.
Figure 6.1. Volume of reinforced concrete for bridge alternatives
Figure 6.2. Volume of structural steel for bridge alternatives.
1461 1512
3584
1998 1833855
380
1197
1197
380
2016
0
1000
2000
3000
4000
5000
6000
Arch bridge Network archbridge
Suspensionbridge
Cable-stayedbridge
Truss bridge
Volu
me
ofre
info
rced
conc
rete
[m³]
Deck plate Substructure and pylons Arch and truss
159278
2063
5791083
0
500
1000
1500
2000
2500
Arch bridge Network archbridge
Suspensionbridge
Cable-stayedbridge
Truss bridge
Volu
me
ofst
ruct
ural
stee
l[m
³]
Cables and hangers Arch and truss
58
7 Life cycle cost evaluation
In order to evaluate possible alternative structural solutions, life-cycle cost for designed
alternatives was calculated.
7.1 Methodology and base-prices
Life-cycle cost analysed in current study consists of following components:
- Construction cost;
- Maintenance cost.
In order to simplify calculation, construction and maintenance costs were calculated with
base-year 2016.
Construction cost was calculated according to structural quantities and unit prices. Unit price
estimation by Estonian Road Administration statistics for year 2016 tenders for bridge
construction was used. In order to more accurately consider various structural peculiarities,
recommendations from unbiased construction experts were included in order to estimate the
unit prices. Overview and detailed construction price calculation results can be found in
Appendix 7.
Maintenance cost was estimated according to following basis:
- Maintenance work list and intervals are partly based on Russian Federation
requirements on railway bridges and culverts maintenance4. Experience and practice
of Estonian Road Administration (Maanteeamet) and Estonian Railways Ltd (AS
Eesti Raudtee) for bridge maintenance has been taken into account. Therefore a
typical maintenance worklist and intervals have been determined for a railway bridge
located in Estonia. Detailed maintenance worklist can be found from Appendix 8.
- Base-prices of maintenance work were determined on basis of Estonian Road
Administration tender statistics 2016.
4 Инструкция по содержанию искусственных сооружений. МПС России. Москва: Транспорт. 1999.
59
Maintenance cost was calculated with estimation of total bridge life cycle 70 years. For
discounting maintenance prices, NPV (net present value) was used:
= (1 + )
Where i – discount rate, as estimated 0,04
C2016 – cost of specific maintenance work during 2016 [EUR],
t – number of years, counted from 2016 when a specific maintenance work
will be carried out
N – total number of maintenance procedures following same algorithm
To implement annual increase in bridge maintenance prices, average coefficient of price
change was calculated on the basis of analysis of construction price index during the years
of 2002-2017. Average increase in bridge maintenance was selected as im=1,03. Similar
coefficient (1,04) is also recommended in Estonian Road Administration roadworks unit
price prognosis5.
Unit prices for maintenance works for years 2016-2086 have been calculated according to
following formula:
( ) = (1 + )
5 Teetööde ühikhinnad ja nende prognoos aastani 2022. Tallinn: Tallinna Tehnikaülikool 2013.
60
Figure 7.1. Construction price index according to Statistics Estonia [http://www.stat.ee].
Price index is calculated on the basis of 1997 year to be equal to 100.
Maintenance worklist, intervals and unit prices can be observed in detail in Appendix 8.
0
50
100
150
200
250
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
Cons
truc
tion
pric
ein
dex
year
61
7.2 Conclusions and LCC comparison
For characterisation of construction prices and LCC of designed bridge alternatives Figures
7.2, 7.3 and 7.4 can be observed.
Figure 7.2. Construction costs of analysed bridge alternatives in 2016 prices,
percentage of different structural elements in total construction cost is presented
Figure 7.3. Maintenance cost of analysed bridge alternatives, cost by specific structural
element type in total maintenance cost is presented
1069 121 1098 8012346 761 1382 782 1292 561
525 468 258 134
2453 4122453 412
258 134412 851 722 488
5851 6275363 291
0
2016 400 1591 350
0
0
2166 428
51 398 34 767
93 003
93 003
34 767
0
2000 000
4000 000
6000 000
8000 000
10000 000
12000 000
Arch bridge Network archbridge
Suspension bridge Cable-stayedbridge
Truss bridgeCons
truc
tion
cost
[EU
R]
Deck plate Bridge substructure and cable ground anchorage
Cables and hangers Arch and truss
Groundworks
612 975 633 712
1406 102
813 128612 975
41 014 31 043
42 144
42 39328 55717 216 57 386
247 908
377 417
022 351 90 115
0
0
312 04116 923
16 923
16 923
16 923
16 923
0200 000400 000600 000800 000
1000 0001200 0001400 0001600 0001800 000
Arch bridge Network archbridge
Suspension bridge Cable-stayedbridge
Truss bridge
Tota
lmai
nten
ance
cost
durin
gLC
[EU
R]
Deck plate Bridge substructure and cable ground anchorage
Cables and hangers Arch and truss
Groundworks
62
Figure 7.4. Total LCC cost of analysed bridge alternatives, calculated with base year
2016, percentage of construction and maintenance cost in total LCC is presented
As seen from Figures 7.2, 7.3, 7.4 and Appendixes 8 and 9 following conclusions about LCC
can be formed:
- Network arch bridge can be considered among the most economical solutions for
170 m single-span configuration. Since the optimisation of a bridge results in
relatively stiff and slender structure, amount of structural materials (reinforced
concrete and structural steel) are relatively small;
- Truss bridge, having approximately 2% higher life cycle cost compared to network
arch bridge can be considered among the most economical solutions for 170 m
single-span configuration.
- Arch bridge with reinforced concrete arch is 7% more expensive compared to
network arch bridge according to LCC, therefore it can be considered among the
most economical solutions. The main difference in construction price of arch bridge
compared to network arch or truss bridge is caused by higher price of the arch and
arch ground anchorage;
- Cable-stayed bridge is 2.3 times more expensive compared to the cheapest
alternative network arch. Increase in cost is caused mainly by cables and pylons.
Cable dimensions have been selected according to limited deflections of bridge deck
4075 238 3705 540
10744 8039292 488
3751 890
710 479 829 180
1713 077
1249 861
970 497
0
2000 000
4000 000
6000 000
8000 000
10000 000
12000 000
14000 000
Arch bridge Network archbridge
Suspension bridge Cable-stayedbridge
Truss bridge
Tota
lLCC
[EU
R]
Construction Maintenance and overhaul
63
under traffic loads, therefore the estimation of cost is considered to be exact and
future optimisation might not be possible in large scale;
- Suspension bridge is the most expensive alternative for 170 m single-span solution.
Being altogether 2.8 times more expensive compared to network arch bridge, the
difference is mainly caused in high amount of structural materials required to provide
necessary structural stiffness, including cables and pylons. Similarly to cable-stayed
bridge, cost of suspension bridge is considered to be exact and future optimisation
might not be possible in large scale.
64
8 Aesthetics evaluation
8.1 Methodology
In order to evaluate visual aesthetics of bridge alternatives, evaluation was carried out with
4 experts of architecture. Each architect was asked to evaluate all 5 bridge alternatives from
the aesthetical point of view and determine a grade in 10 points scale. Following aspects
were taken into account for evaluation:
- Bridge aesthetical and artistic value;
- Bridge dignity and solemnity;
- Consistency with existing city environment;
- Consistency with Estonian architecture.
Therefore for any bridge alternative points between 0 and 40 could be obtained.
8.2 Conclusions
Scores obtained by different bridge alternatives could be followed from Table 8.1 and
Figure 8.1.
Archbridge
Networkarch
bridge
Suspensionbridge
Cable-stayedbridge
Trussbridge
Number ofpoints
18 32 16 35 14
Table 8.1. Scores obtained during aesthetics evaluation by different bridge alternatives
65
Figure 8.1. Scores obtained during aesthetics evaluation by different bridge alternatives
As a result of aesthetics evaluation, following conclusions were made during the discussion
with experts:
- Arch bridge can be considered as clumsy architectural solution for current case. Due
to long span and railway loads, structure is too massive to be aesthetically valuable.
The bridge is architecturally very similar to a landmark of Tartu town (Kaarsild),
therefore it is not forming any separate architectural value.
- Network arch bridge is architecturally innovative and solemn solution, value is
formed of structure slenderness and uniqueness for Estonia. Additional possibilities
exist for making the bridge aesthetically more interesting and eye-catching –
connecting two arches on top of the bridge, reconfiguring hangers etc.
- Suspension bridge is a majestic and elegant, but also formal and archaic structure.
Architectural value is decreased by massive and high pylons. Configuration of cables
allows passenger of train to have undisturbed view to the river whilst the train is in
the middle of the span.
- Cable-stayed bridge can be considered as architecturally the most valuable solution.
The structure is slender, bridge is majestic and innovative. Tilted pylons create
dynamic impression of the bridge. Similar to suspension bridge, cable configuration
allows passengers to have undisturbed view in the middle of the river.
- Truss bridge has the least value from architectural viewpoint due to clumsiness and
massive structure. Since the bridge is similar to typical bridges that were built during
first half of 20th century, the overall impression is conventional and archaic. The
18
32
16
35
14
0
5
10
15
20
25
30
35
40
Arch bridge Network archbridge
Suspensionbridge
Cable staybridge
Truss bridge
Scor
eob
tain
edby
alte
rnat
ive
[poi
nts]
66
keyword for characterising aesthetical performance is rather industrial, not
architectural.
67
9 Conclusions and further research
9.1 Conclusions
On the basis of structural evaluation, LCC calculation and aesthetics evaluation, following
conclusions that apply for 170 m single-span railway bridge can be formed:
- Arch, network arch and truss bridges can be considered as relatively stiff structures
for analysed span and loads, therefore they can be designed with slender cross-
sections of main structural elements;
- Suspension and cable-stayed structures lack stiffness that is required for service limit
state for railway bridges, therefore the design of structure results in relatively massive
and expensive elements.
- Life-cycle cost of arch, network arch and truss bridges is similar, therefore they can
be considered as appropriate structural forms for analysed span;
- Cable-stayed and suspension bridge are approximately 2-3 times more expensive by
means of LCC, therefore cable structures cannot be considered as economically
rational options;
- Network arch and cable-stayed bridges are among structural forms with the highest
architectural and aesthetical value compared to other structural forms.
According to described results, the main conclusion of the current study is that network arch
bridge should be considered as preferred structural form for 170 m single-span double-track
railway bridge due to low LCC and high architectural value.
9.2 Main contributions
The main contribution of this study to modern bridge engineering is that first time network
arch double-track railway bridge was included for equal comparison with other structural
forms of long-span bridges according to Eurocode load models and requirements for
structural design.
68
9.3 Further research
In order to perform further research on comparison of the different structural forms of long-
span railway bridges, possible additional investigations that could be performed on the field
would be following:
- Environmental impact and life-cycle assessment of different structural forms of long-
span railway bridges;
- Comparison of different structural forms for long-span railway bridges with included
analysis of structural dynamics. Due to additional requirements for stiffness,
eigenfrequencies and oscillation modes of structure, structural elements of bridges
for high-speed railways need to be dimensioned in different way that could result in
increased mass of structure that influences the conclusions.
69
10 Summary
The aim of current MSc thesis was to investigate and compare different structural forms for
long-span railway bridges. The study focuses on double-track single-span railway bridge
with span 170 m. Case study was performed on the basis of Rail Baltic bridge over Pärnu
river in Estonia. Five different structural forms were included in the analysis:
- Classic-arch bridge with non-tied deck;
- Network arch tied bridge;
- Single-span suspension bridge with ground-anchored main cables;
- Cable-stayed bridge with ground-anchored cables;
- Steel truss bridge.
Analysed structural forms were evaluated and compared from following perspectives:
- Technical peculiarities of bridge structures;
- Life-cycle cost;
- Architecture and aesthetics.
Bridges with five defined structural forms were designed in preliminary phase on the basis
of case-study conditions. LCC was determined, structural peculiarities were analysed and an
architectural value was determined with help of experts.
The conclusion was made that since LCC of arch, network arch and truss bridges occurred
to be similar, these structural forms can be considered as the most suitable for span 170 m
from the financial point of view. LCC of suspension and cable-stayed bridges are
approximately 2-3 times higher compared to previously mentioned structural forms,
therefore cable structures cannot be considered as economically rational options. High
architectural and aesthetical value is obtained by network arch and cable-stayed bridges.
According to described results, the main conclusion of the current study is that network arch
bridge should be considered as preferred structural form for 170 m single-span double-track
railway bridge due to low LCC and high architectural value.
70
11 Kokkuvõte
Käesoleva magistritöö eesmärgiks oli võrrelda omavahel erinevate pikasildeliste
raudteesildade konstruktsioonilahendusi. Töös kasutati võrdlusena kaheteelist ühesildelist
raudteesilda avaga 170 m. Uuringu tarbeks defineeritud baas-raudteesilla projekteerimise
tehnilised tingimused määrati lähtuvalt Pärnu jõele projekteeritavast Rail Baltic
raudteesillast. Süvitsi analüüsiti viite erinevat konstruktsioonilahendust:
- Betoonkaarsild, kus silladekk ei tööta tõmbina;
- Võrkkaarsild;
- Rippsild maasse ankurdatud peakaablitega;
- Vantsild püloone tasakaalustavate ankurdatud kaablitega;
- Terassõrestiksild.
Erinevaid sillakonstruktsioone võrreldi järgnevatest parameetritest lähtuvalt:
- Sillakonstruktsioonide tehnilised eripärad;
- Elukaarekulud;
- Arhitektuur ning sillakonstruktsiooni esteetika.
Magistritöö tarbeks projekteeriti ning arvutati 5 eelpoolmainitud konstruktsioonilahendust
Rail Baltic sillana üle Pärnu jõe eskiisprojekti tasemel ning seejärel leiti elukaarekulud,
analüüsiti sillakonstruktsioonide eripära ning ekspertide abiga hinnati arhitektuurset
lahendust.
Töö järeldustena leiti, et betoonkaarsilla, võrkkaarsilla ning terassõrestiksilla
elukaaremaksumused on sarnased, mistõttu võib majanduslikult pidada neid antud sildele
ning tehnilistele tingimustele sobivateks variantideks. Ripp- ja vantsilla elukaarekulud on 2-
3 korda suuremad, kui eelpoolmainitud variantidel, seega ei ole need 170 m sildega
raudteesillana majanduslikult otstarbekad. Suurimat arhitektuurset väärtust omavad
analüüsitud sillatüüpidest võrkkaarsild ning vantsild.
Lähtuvalt eelpoolkirjeldatud tulemustest on käesoleva töö soovituseks 170 m pikkuse
sildega kaherajaliste raudteesildade projekteerimisel rakendada üldjuhul võrkkaarsilda, kuna
see on majanduslikult otstarbekas ning arhitektuurselt väärtuslik.
71
Bibliography
Atsushi, O., Suzuki, S., Harazaki, I. 2000. Suspension bridges. Bridge engineering
handbook. London, New York, Washington DC: CRC Press
Kulicki, J. M. 2000. Highway truss bridges. Bridge engineering handbook. London, New
York, Washington DC: CRC Press
Idnurm, Juhan. 2016. Lecture materials of course: Advanced design of bridges. Tallinn:
TUT.
Melaragno, Michele. 1998. Preliminary design of bridges for architects and engineers. New
York: Marcel Dekker, Inc.
Otsmaa, Vello. 2014. Betoonkonstruktsioonide arvutamine. Tallinn: TUT
Rohusaar, J., Mägi, R., Masso, T., Talvik, I., Jaaniso, V., Otsmaa, V., Loorits, K.,
Peipman, T., Pukk, O., Voltri, V., Õiger, K., Just, E., Just, A., Hartšuk, V. 2014.
Ehituskonstruktori käsiraamat. Tallinn: Ehitame
Safi, Mohammed. 2009. Bridge life cycle cost optimization. Analysis, evaluation &
implementation. Stockholm: KTH.
Safi, Mohammed. 2012. LCC applications for bridges and integration with BMS. Licenciate
thesis in structural engineering and bridges. Stockholm: KTH.
Sundquist, Håkan. 2009. Infrastructure structures. Stockholm: KTH.
Sundquist, Håkan. 2007. Arch structures. Stockholm: KTH.
Sundquist, Håkan. 2008. Prestressed concrete structures. Stockholm: KTH.
Tveit, Per. 2014. The network arch.
Varennes, Maxime. 2011. Design of a single-track railway network arch bridge. Stockholm:
KTH.
Крыльцов, Е. И., Попов, О. А., Файнштейн. 1974. Современные железобетонные
мосты. Москва: Транспорт.
Осипов, В. О., Храпов, В. Г., Бобриков, Б. В. 1988. Мосты и тоннели на железных
дорогах. Москва: Транспорт.
Content of TU Delft course: Steel construction: Economic & commercial factors.
72
http://fgg-web.fgg.uni-lj.si/~/pmoze/ESDEP/master/wg01a/toc.htm
Teetööde ühikhinnad ja nende prognoos aastani 2022. Tallinn: Tallinna Tehnikaülikool
2013.
Инструкция по содержанию искусственных сооружений. 1999. Москва: МПС России.
EVS-EN 1990:2002/A1:2006/AC:2010. Eurocode – Basis of structural design
EVS-EN 1990:2002/A1:2006 (+NA:2009). Eurocode - Basis of structural design.
Amendment A1 - Annex A2: Application for bridges
EVS-EN 1993-2:2006/AC:2009. Eurocode 3 - Design of steel structures - Part 2: Steel
Bridges
EVS-EN 1991-2/NA:2007. Actions on structures. Part 2: Traffic loads on bridges. Estonian
National Annex
EVS-EN 1992-2:2005/AC:2008. Eurocode 2 - Design of concrete structures - Concrete
bridges - Design and detailing rules
EVS-EN 15273-3:2013+A1:2017. Railway applications - Gauges - Part 3: Structure gauges
4.5
1
4.7
1
3.90
4.0
1
5.7
0
7.33
8.98
vana nılvakindlustus
9.14
2.1
5 2.1
2
2.1
4
3.1
6
3.0
5
2.8
3
2.6
2
2.3
5
7.7
2
7.6
1
2.7
3
1.6
8 1.6
9
0.5
3
1.4
2
1.6
9 1.2
8
2.2
4
2.5
3
2.5
3
9.24
mulla
hunnik
ud
Kr
Kr
Kr
A
A
Kr
KrKr
1.52
1.3
7
1.3
1
1.0
7 1.2
5
1.7
1
2.3
3
1.8
8
2.3
4
1.6
3
1.65
1.7
3
1.7
2
1.6
9
1.7
0
1.5
7
1.6
1
1.3
9 0.11
1.7
8
2.0
8
2.16
1.78
1.77
2.16
2.16
2.29
2.2
4
2.1
1
2.3
2
2.2
6
2.8
7 2.7
4
2.7
5
2.7
6 2.9
0
2.6
7 2.4
9
2.5
4
2.5
9
2.7
2 2.5
8
2.9
0 2.6
5
2.6
0
2.9
5
2.9
7 2.7
4
2.7
3
2.8
0
2.6
8 2.5
6
2.9
1
2.5
4
2.7
2
3.7
9
2.75 2.6
4
3.48 8.88
3.9
7
3.92
3.9
4
3.30
2.72 2.87
3.55 3.12
8.61
8.68
8.79
6.34
8.42
8.50
8.82
8.51
9.15
9.14
8.99
8.62
8.27
8.77
8.94
8.36
9.07
9.04
8.85
8.24
8.08
8.54
8.83 8.98 8.93
8.77
8.25
8.06
6.69
4.73
2.74
2.80 2.72
2.87
2.79
2.83
2.94
2.91
3.2
2
3.8
9
3.2
9
3.60
3.57
3.57
3.9
3
4.12
4.07
4.01
4.07 3.99
2.1
4
9.43 9.53 9.72
3.4
9
3.0
0
1.6
3
2.3
2
2.4
6
2.6
4
3.0
5 3.0
2
3.1
7
2.7
6 2.9
4
3.4
3
3.3
9 3.2
0
7.97 7.97
3.9
2
8.99
9.30
9.30
8.67
-
0.0
2
-0.0
4
-
0.0
2
-
0.0
3
-
0.16
0.2
4
1.3
8
1.6
1
1.5
7
0.0
9
-
0.0
3
2.2
5
0.3
4 -
0.0
2
0.1
3
2.2
6
1.31
1.9
4
2.0
1
2.0
0
1.8
4
2.0
8
2.1
9
2.0
6
2.2
2
2.0
6
2.1
4
1.51
0.6
0
1.7
4
2.0
3
2.0
0 1.9
8
1.8
9
9.82
9.99
10.00
9.57 9.53
9.84
9.64
9.52
9.85
9.51
9.43 9.52
9.71
9.70
9.33
3.19
3.23
3.1
3
2.17
2.65
2.25
2.77
3.01
3.05 3.03
2.70
9.62
9.62 9.43
9.30
9.31
2.74
3.11
5.12
4.4
2
4.1
7
2.73
2.74
2.67
2.47 2.67 3.76
2.85
7.10
8.65
8.81
8.59
8.00
7.00
8.00 8.47
8.26
8.36
8.11
8.19
8.2
3
8.85
9.16
8.83
8.15 8.34 9.02
4.7
5
TP
3.7
9 3.9
4
9.2
2
Kill
A
A
Kr
A
A
Kr
4.6
1
4.4
7 4.1
8 4.1
6
4.2
0 4.2
5
4.3
1
5.1
0 4.2
2
4.1
5
4.0
3
4.0
6
3.9
4
3.9
3
3.8
6
3.4
1
2.3
4
1.9
7
1.2
3
0.2
4
4.5
2
4.0
6
4.1
8 4.2
5
4.2
9
4.1
3
3.9
4
3.9
3 3.9
2
3.9
1
3.9
0 3.5
3
2.8
5
0.5
9
0.2
7
1.0
6
0.1
8
2.65
2.47
0.1
3
2.1
6
0.2
0
4.4
3
2.7
5
3.98
4.0
3 3.8
7
4.4
6 4.6
4
4.2
1
4.2
5
4.3
0
4.3
4
4.2
7
4.1
6
4.1
2
4.1
1
4.0
8 4.0
6
3.7
1
3.2
8
2.8
1
0.1
8
2.5
7
0.0
1
3.4
1
2.9
7
4.0
0
4.0
5
4.6
7
4.5
2
4.6
3
4.3
7
1.4
5
1.1
6
-
0.1
7
-
0.2
1
-
0.1
9
-
0.1
9
2.16-1.9
64.0
4
kaev-0.7
92.8
7.5
0
8.1
0
8.8
8 8.9
2
9.0
5
8.5
6 8.8
0
8.4
4
7.6
8
7.6
5
bet
bet
6.2
7 6.4
7
8.2
7
9.2
2
10.62
TP
kaev-2.5
9
10.16
10.24
10.42
5.6
9
10.20
10.25
10.26
10.55 10.73 10.73
10.56
8.79 8.89
10.25
6.44
6.83
7.71
6.3
7 7.4
3
6.19
9.43
10.36
10.03
7.47
7.7
7
7.6
6
7.4
4
7.7
3
8.0
3
7.6
2
8.2
8 7.6
4
8.20
8.52
10.15
10.65 10.66
9.79
10.05
10.12
10.3
1 8.2
1
10.46
6.5
5
10.56
9.64
9.66 9.57
9.55 9.49
9.52
9.4
3 9.4
3
9.5
7 9.3
4
Platvorm
Platvorm
9.73
9.72 9.92 10.09
10.09
9.73 9.68
10.83
10.84
10.45
10.62
10.64
10.54 10.50
10.59
10.68 10.85 10.85
10.60
11.14
10.56
10.55
10.82
10.82
10.52
10.50
10.48
10.52
10.61 10.77
10.78
10.43 10.37
1.7
1
0.8
0 1.0
2 1.8
5
1.7
9
1.3
7
10.74 10.74
10.37
10.43
10.46 10.29
10.43
10.61
10.62
10.31 10.26
10.28
10.27 10.16
10.18 10.37 10.52
10.52
10.18 10.15
10.10
10.04
10.38
10.38
10.02
10.03
9.95
9.97
10.16 10.30
10.30
9.91 9.93
9.86 9.88
9.82
9.82 9.96 10.15 10.15
9.76
9.81
9.84 9.99 10.04 9.85 10.10 10.13
10.26
10.36
10.36 10.40
10.50
A
ASB 2xo10
2WASB 3x 10 2W+1WW
2v
2v
6 kaablit ASB 2x 10
kaugsid
e
2 kaablit
2 kaab
lit
2 kaablit
2v
4v
3.0
4
3.1
1
2.6
0
2.8
3
2.6
1
2.2
8
1.9
9
1.9
6
1.6
9
1.7
6
3.0
4
3.1
2
2.1
0
2.0
5
2.1
2
2.1
2
1.7
3
2.0
4 1.9
4
1.9
2
-
0.1
6
-
0.0
3
-
0.0
4
0.3
0
2.8
4
2.8
5
2.5
8
2.5
0
2.2
0
betpl
8.13
8.22
8.25
8.35 8.51 8.36
8.20
7.9
6 8.09
8.05
8.30
8.44
8.33
8.38
8.54
8.43 8.56
8.64
8.52
8.53 8.37
8.70
8.54
8.66
8.66 8.77
8.84
8.74
8.79
8.66
8.8
9 8.9
1 8.9
7
1.1
4
2.27
2.19
1.71 1.99
2.54 2.62
2.62 2.60
2.06 1.82 0.3
4
9.7
2
9.8
6
9.9
3
10.0
5
10.1
9
10.2
4
10.3
3
10.4
9
3.9
5
4.0
4
4.1
2
4.2
0
4.1
2
4.0
4
4.8
7
8.05 8.22 8.21
8.30 8.29 8.13
2.8
5
2.84
2.8
9
2.7
0
2.4
4
-
0.1
7
-
0.1
9
2.0
7
2.0
0
2.0
5
1.95
2.01
0.2
7 1.6
2
2.8
9
2.6
5
2.1
9
2.2
7
1.7
6
1.9
6
3.8
4
3.9
2
4.0
2
4.1
1
4.0
1
4.4
5
4.5
2 4.5
4
8.8
0
9.6
5
8.2
8
8.7
9
7.6
2
7.4
6
10.22
6.1
4
Kr
Kr
4.7
2 4.3
7
2.3
4
1.8
0
2.75
3.0
0
3.1
0
0.1
5
0.1
5 -
0.0
2
0.89
2.3
1
A
A
X= 6471150
Y= 532600
X= 6470800
Y= 532550
A
A
Papiniidu tänav
T15
62514:177:0082
Ehitajate tee
T11
62517:064:0072
Papiniidu tänav
T12
62514:177:0081
7118
7118
5+200 5+300 5+400 5+500 5+600
+50+50 +50 +50 +50
II1/12 1/18.5
1/18.51/18.5
1/18.5
I
1+646 K
M
DR
L 1
0.4
7
Nr. 3
Nr. 1Nr. 7
Nr. 5Nr. 9
0+0000+100
+50
W
S
N
E
Rail Baltic bridge
Existing railway bridge
Existing road bridge
<- Riga
14.57
3.35
4.20 4.20
12.50
Tallinn ->
Kees Vanamölder
SUPERVISOR Professor Juhan Idnurm
STUDENT
NAME OF THESIS
LOCATION LAYOUT OF CASE-STUDY BRIDGE DESIGN
NAME OF APPENDIX
DRAWING
APPENDIX 1
DATE
29.05.2017
BRIDGE
CASE-STUDY ON 170 M SINGLE-SPAN DOUBLE TRACK
OF ALTERNATIVE STRUCTURAL SOLUTIONS,
LONG-SPAN RAILWAY BRIDGE DESIGN: EVALUATION
DEPARTMENT OF CIVIL ENGINEERING AND ARCHITECTURE
SCALE
1:400
4,20
2,10 2,10
1,75
4,65
2,5
0
2,00
2,0
0
2,4
8
A-A 1:250
P˜RNU RIVER
ROAD
5+300
5+400
5+500
5+600
20,0020,0020,0020,0020,0020,0020,0020,0015,00
28,5
0
A
A
182,50
ROAD
24,0028,30
RIGATALLINN
SIDE VIEW 1:400
D=0,3m
ROAD 8,7
0
5,3
3
Kees Vanamölder
SUPERVISOR Professor Juhan Idnurm
STUDENT
NAME OF THESIS
NAME OF APPENDIX
DRAWING
APPENDIX 2
DATE
29.05.2017
BRIDGE
CASE-STUDY ON 170 M SINGLE-SPAN DOUBLE TRACK
OF ALTERNATIVE STRUCTURAL SOLUTIONS,
LONG-SPAN RAILWAY BRIDGE DESIGN: EVALUATION
DEPARTMENT OF CIVIL ENGINEERING AND ARCHITECTURE
SCALE
1:400
ALTERNATIVE 1: ARCH BRIDGE
4,20
2,10 2,10
1,75
4,85
2,4
8
A-A 1:250
1,00
0,75
ROAD
P˜RNU RIVER
ROAD
5+300
5+400
5+500
5+600
26,5
0
A
A
176,00
ROAD
24,0020,00
TALLINNRIGA
SIDE VIEW 1:400
D=0,15m
5,3
3
8,6
3
Kees Vanamölder
SUPERVISOR Professor Juhan Idnurm
STUDENT
NAME OF THESIS
NAME OF APPENDIX
DRAWING
APPENDIX 3
DATE
29.05.2017
BRIDGE
CASE-STUDY ON 170 M SINGLE-SPAN DOUBLE TRACK
OF ALTERNATIVE STRUCTURAL SOLUTIONS,
LONG-SPAN RAILWAY BRIDGE DESIGN: EVALUATION
DEPARTMENT OF CIVIL ENGINEERING AND ARCHITECTURE
SCALE
1:400
ALTERNATIVE 2: NETWORK ARCH BRIDGE
0,9
6
4,20
2,10 2,10
3,10
5,15
15,70
3,8
3
A-A 1:250
P˜RNU RIVER
ROAD
5+300
5+400
5+500
5+600
A
A
176,00
ROAD
24,0020,00
32,5
0
5,50
TALLINNRIGA
D=0,6m
D=0,6m
SIDE VIEW 1:400
D=0,3m
ROAD
5,3
3
7,2
8
Kees Vanamölder
SUPERVISOR Professor Juhan Idnurm
STUDENT
NAME OF THESIS
NAME OF APPENDIX
DRAWING
APPENDIX 4
DATE
29.05.2017
BRIDGE
CASE-STUDY ON 170 M SINGLE-SPAN DOUBLE TRACK
OF ALTERNATIVE STRUCTURAL SOLUTIONS,
LONG-SPAN RAILWAY BRIDGE DESIGN: EVALUATION
DEPARTMENT OF CIVIL ENGINEERING AND ARCHITECTURE
SCALE
1:400
ALTERNATIVE 3: SUSPENSION BRIDGE
ROADP˜RNU RIVER
5+300
5+400
5+500
5+600
A
A
169,00
TALLINNRIGA
10,00
SIDE VIEW 1:400
ROAD ROAD
24,0020,00
15°
27,8
3
D=0,43m
D=0,25m D=0,25m
5,3
3
8,4
5
A-A 1:250
0,9
6
4,20
2,10 2,10
1,75
5,15
15,70
2,4
8
Kees Vanamölder
SUPERVISOR Professor Juhan Idnurm
STUDENT
NAME OF THESIS
NAME OF APPENDIX
DRAWING
APPENDIX 5
DATE
29.05.2017
BRIDGE
CASE-STUDY ON 170 M SINGLE-SPAN DOUBLE TRACK
OF ALTERNATIVE STRUCTURAL SOLUTIONS,
LONG-SPAN RAILWAY BRIDGE DESIGN: EVALUATION
DEPARTMENT OF CIVIL ENGINEERING AND ARCHITECTURE
SCALE
1:400
ALTERNATIVE 4: CABLE-STAYED BRIDGE
A-A 1:250
4,20
2,10 2,10
1,75
4,95
0,7
0
0,70
0,5
0
0,70 0,70
ROAD
P˜RNU RIVER
ROAD
5+300
5+400
5+500
5+600
25,2
0
A
A
176,00
ROAD
24,0020,00
TALLINNRIGA
SIDE VIEW 1:400
5,3
3
8,6
3
t=0,07 m
0,7*0,7 m
t=0,05 m
0,5*0,5 m
Kees Vanamölder
SUPERVISOR Professor Juhan Idnurm
STUDENT
NAME OF THESIS
NAME OF APPENDIX
DRAWING
APPENDIX 6
DATE
29.05.2017
BRIDGE
CASE-STUDY ON 170 M SINGLE-SPAN DOUBLE TRACK
OF ALTERNATIVE STRUCTURAL SOLUTIONS,
LONG-SPAN RAILWAY BRIDGE DESIGN: EVALUATION
DEPARTMENT OF CIVIL ENGINEERING AND ARCHITECTURE
SCALE
1:400
ALTERNATIVE 5: TRUSS BRIDGE
Arch bridge Network archbridge
Suspensionbridge
Cable-stayedbridge
Truss bridge
20101 Site preparation 150000 1 1 1 1 1
60409 Concreteing with reinforcement [m³] 600 1 461 1 512 3 584 1 998 1 83360801 Water isolation layer [m²] 40 1 592 1 549 1 717 1 649 1 59260404 Surface protection layer [m²] 8 1 592 1 549 1 717 1 649 1 59261002 Steel barriers [m] 255 386 374 374 340 38661601 Expansion joints [m] 950 19 23 19 19 19
1 069 121 1 098 801 2 346 761 1 382 782 1 292 561
60408Reinforced concrete for supports and wingwalls[m³]
420 265 226 438 438 226
60408 Reinforced concrete for pylons [m³] 900 2 105 2 10560406 Reinforced concrete for slab foundation [m³] 350 557 123 728 728 12360302 Concrete piles, including driving [pcs] 2500 68 36 36 36 3661609 Elastomeric bearings [pcs] 2380 16 8 8 8 860411 Reinforced concrete transition plate [m³] 400 28 28 28 28 28
525 468 258 134 2 453 412 2 453 412 258 134
60602 Steel cables and hangers [t] 2600 159 278 2 251 2 063412 851 722 488 5 851 627 5 363 291 0
60403 Reinforced concrete and assembly [m³] 1000 2 01660602 Steel arch and assembly [t] 2750 57960602 Steel truss and assembly [t] 2000 1 083
2 016 400 1 591 350 0 0 2 166 428
60202 Ground excavation for structure [m³] 5 2 058 720 4 776 4 776 72060206 Cavity fill [m³] 11 1 501 597 4 048 4 048 59761202 Slope protection of cone [m²] 50 492 492 492 492 492
51 398 34 767 93 003 93 003 34 767
4 075 238 3 705 540 10 744 803 9 292 488 3 751 890Total construction cost of alternative [EUR]
Construction price for deck plate [EUR]
Construction price for substructure and cable
Construction price for cables and hangers [EUR]
Construction price for arch [EUR]
Construction price for groundworks [EUR]
Bridge substructure and cable ground anchorage
Cables and hangers
Arch and truss
Groundworks
Price per unit[EUR]
Name of quantityQuantities
Deck plate
Preparation works
Appendix 7Specification of materials and construction worklist
Arch bridgeNetwork
arch bridgeSuspension
bridgeCable-stayed
Truss bridge
60505 Concrete surface repairs 15% [m²] 20 57 725 802 822 725 72560409 Overhaul of bridge deck [m³] 50 600 1 461 1 512 3 584 1 998 1 46160801 Renewal of water isolation layer [m²] 20 40 1 592 1 549 1 717 1 649 1 592
612 975 633 712 1 406 102 813 128 612 975
60505 Concrete surface repairs 35% [m²] 20 57 39 39 385 385 3960901/60902
Repairs or replacement of drainagesystem 30% [pcs]
20 335 12 12 12 12 12
Replacement of bearings [pcs] 30 2380 16 8 8 8 861601 Replacement of expansion joints [m] 30 950 19 23 19 19 19
41 014 31 043 42 144 42 393 28 557
60602Cleaning, repainting and corrosionprotection of steel surface [m²]
8 80 283 942 4 072 6 198
17 216 57 386 247 908 377 417 0
60505 Concrete surface repairs 15% [m²] 20 57 570
60602Cleaning, repainting and corrosionprotection of steel surface [m²]
8 80 1 480 5 125
22 351 90 115 0 0 312 041
61203Repairs of slope protection of cone 20%[m²]
20 50 492 492 492 492 492
16 923 16 923 16 923 16 923 16 923
710 479 829 180 1 713 077 1 249 861 970 497
Quantities
Deck plate
Bridge substructure and cable ground anchorage
Interval[years]
Maintenance price of cables and hangers during LC [EUR]
Maintenance price of arch during LC [EUR]
Maintenance price of deck plate during LC [EUR]
Maintenance price of substructure and cable during LC [EUR]
Name of quantityPrice per
unit [EUR]
Cables and hangers
Arch and truss
Groundworks
Total maintenance cost of alternative [EUR]
Maintenance price of cone and slopes during LC [EUR]
Appendix 8Maintenance worklist