Upload
vpmohammed
View
218
Download
0
Embed Size (px)
Citation preview
8/13/2019 Data Rates Gate Works 9
1/21
GATE / HOIST AND ALLIED WORKS
Quantity of coal tar epoxy paint for 8 sqm @ 6 sqm / ltr / coat : 5.5 ltr
As surface cleaning by sand blasting is hazardous, it is proposed to adopt chemical treatment
to remove grease, rust, scaling etc., and to form phasphate coating to prevent further rusting
before applying primer painting.
Quantity of rust cleaner / inhibitor for 8 sqm @ 8 sqm / ltr : 1 ltr
6. Requirement of other machinery :
For finishing weld joints / edges 2 hours use of grinding machine considered.
7. Requirement of work force :
Work component Foreman Helper /
Painter Cl-II
Cutting sections 20 hours 1 2 2 5
Fabricating by stitch welding 39 hours 2 5 --- 10
Run welding 116 hours 2 --- 15 15
Erection of Sill beam / Tracks / Guide 1 2 --- 4
Cleaning surface 8 sqm @ 15 sqm/day --- --- --- 0.5
Painting ( 5 x 8 ) sqm @ 15 sqm / day --- --- --- 3.5
Finishing / cleaning --- 1 --- 1
Total : 6 10 17 39
Note : a. It is assumed that all stitch welding will be done by fabricator. Hence, no separate provision
is considered for welder for stitch welding.b. Workforce for painting 1 coat primer and 4 coats finishing paint consists of 3 Painters Cl-II
at 15 sqm / day and 0.5 helper to assist painters.
8. Excise duty on supply :
Excise duty is applicable on supply of fabricated parts. The cost of materials is inclusive of all
taxes/ duties. Therefore, for purpose of rate analysis 75 percent of total cost excluding the cost
of materials ( assuming 25 % erection cost ) is considered for assessing excise duty.
9. Use rate of materials :
Cost of welding set @ Rs: 4500.00 / Each Rs: 4500.00
Life of welding set : 1000 hours
Use rate of welding set per hour ( cost / life ) Rs: 4.50
Cost of gas cutting set @ Rs: 1500.00 / Each Rs: 1500.00
Life of gas cutting set : 600 hours
Use rate of gas cutting set per hr ( cost / life ) Rs: 2.50
RATE ANALYSIS UNIT : 1.685 tonne
A. MATERIALS:
Sl No Unit Amount
in Rs.
1 Structural steel
Angles / beams / channels / bars kg 1134.00 37.95 43035.30
Plates / flats kg 523.00 40.00 20920.00
2 Stainless steel plate / flats kg 70.00 120.00 8400.003 Bolt / Nut / Washer ( MS ) kg 1.00 55.00 55.00
4 Oxygen gas cum 30.00 48.00 1440.00
5 Acetyline gas cum 10.00 258.00 2580.00
6 Welding electrodes ( general purpose ) Nos 124.00 6.00 744.00
7 Welding electrodes ( low hydrogen ) Nos 1120.00 12.00 13440.00
8 Welding electrodes ( stainless steel ) Nos 209.00 43.00 8987.00
9 Zinc rich epoxy primer ltr 1.00 594.00 594.00
10 Coal tar epoxy paint ltr 5.50 208.00 1144.00
in Rs.
Erector /
Quantity
Marker /
Perticulars
Fabricator /
Rate
Gas cutter /
Welder
160
8/13/2019 Data Rates Gate Works 9
2/21
GATE / HOIST AND ALLIED WORKS
11 Rust cleaner / inhibitor ltr 1.00 240.00 240.00
12 Use rate welding holder set Hour 155.00 4.50 697.50
13 Use rate gas cutting torch set Hour 12.00 2.50 30.00
14 Wire brush Nos 1.00 30.00 30.00
15 Sundries LS 2.00 30.00 60.00
Total Rs: 102396.80
Add for small Tools and Plants @ 1% Rs: 1023.97
Add for Contractor's Profit @ 10% Rs: 10239.68
Add for Contractor's Overheads @ 5% Rs: 5119.84
Total cost of Materials : Rs: 118780.29
B. MACHINERY:
Sl No Unit Amount
in Rs.
1 Welding transformer Hour 155.00 12.00 1860.00
Fuel / Energy charges Hour 97.00 60.00 5820.00
2 Pug cutting machine Hour 8.00 16.00 128.00
Fuel / Energy charges Hour 8.00 3.00 24.00
3 Planing machine Hour 44.00 88.00 3872.00
Fuel / Energy charges Hour 44.00 75.00 3300.00
4 Grinding machine Hour 2.00 18.00 36.00Fuel / Energy charges Hour 2.00 25.00 50.00
5 Sundries LS 2.00 30.00 60.00
Total Rs: 15150.00
Add for small Tools and Plants @ 1% Rs: 151.50
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 925.40
Add for Contractor's Overheads @ 5% Rs: 757.50
Total hire charges of Machinery : Rs: 16984.40
C. LABOUR:
Sl No Unit Amount
in Rs.
1 Crew for Planing machine Hour 44.00 73.40 3229.60
2 Crew for Grinding machine Hour 2.00 59.50 119.00
3 Foreman Day 6.00 177.00 1062.00
4 Marker / Fabricator / Erector Day 10.00 157.50 1575.00
5 Gas cutter Day 2.00 157.50 315.00
6 Welder ( General ) Day 13.00 157.50 2047.50
7 Welder ( X - ray ) Day 2.00 173.25 346.50
8 Helper fabrication / erection Day 35.00 141.50 4952.50
9 Helper for cleaning / painting Day 1.00 141.50 141.50
10 Painter Cl - II Day 3.00 141.50 424.50
11 Electrician Day 1.00 143.00 143.00
Total Rs: 14356.10Add for small Tools and Plants @ 1% Rs: 143.56
Add for Contractor's Profit @ 10% Rs: 1435.61
Add for hidden cost on Labour @ 15% Rs: 2153.42
Add for additional hidden cost on labour @ 15% Rs: 2153.42
Add for Contractor's Overheads @ 5% Rs: 717.81
Total cost of Labour : Rs: 20959.91
ABSTRACT:
in Rs.
RateQuantity
Description Quantity
in Rs.
Description
Rate
161
8/13/2019 Data Rates Gate Works 9
3/21
GATE / HOIST AND ALLIED WORKS
A. Cost of Materials Rs: 118780.29
B. Hire charges of Machinery Rs: 16984.40
C. Cost of Labour Rs: 20959.91
TOTAL Rs: 156724.59
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% Rs: 2344.96
Add for insurance charges @ 1.00% Rs: 1567.25
Add for designs and drawings @ 2.50% Rs: 3918.11
Add for zigs / supports / winches / chain-pulley @ 2.50% Rs: 3918.11
Add for power supply arrangements @ 2.00% Rs: 3134.49
Add for enabling works @ 1.40% Rs: 2194.14
Total Rs: 173801.66
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2 x 1.685 tonnes @ Rs: 129.10 / tonne Rs: 435.07
Add for transportation upto work site @ 3.00% Rs: 5214.05
Total cost for 1.685 tonne Rs: 179450.78
Rate per tonne Rs: 106500.00
Rate approved per tonne Rs: 106500.00
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2010-11 ITEM No: 34
ITEM: Design, fabrication, supply, erection, testing and commissioning of sliding type stoplog gate
elements consisting of skin plate, horizontal and vertical girders, slide blocks, stiffeners,
guide shoes, rubber seals etc., with all accessories for canal regulator vent including cost of
all materials, machinery, labour, cutting, aligning, welding, finishing, cleaning, applying one
coats of zinc rich epoxy primer and three coats of cold applied coal tar epoxy paint, seal
fixing etc., complete as per specifications and approved drawings with all leads and lifts.
DATA:Consider down stream sealing vertical lift slide gate. The stoplog gate consists of number
of inter-changeable elements having height of each element in the range of 0.9 to 1.2 m. Each
element consists of skin plate, horizontal girders, vertical end girders, stiffeners, slide blocks,
gate guide shoes, brackets, lifting pins,seals etc., with all accessories.
Consider canal escape / regulator gate for 2 m vent opening and 3.7 m depth of water.
Consider 4 elements of size 2.50 m length x 1.00 m height each.
Weight of 1 set of stoplog gate elements in tonne based on empirical formula :
= 0.0995 ( L2x H x h )
0.716
Where ( L ) is length and ( H ) is total height of gate and ( h ) is head of water in metres.
= 0.0995 ( 2.5 x 2.5 x 4.0 x 3.7 )0.716
: 2.544
The weight computed as above based on empirical formula is further checked by computing the
actual weight as per fabrication drawings of canal escape / regulator stoplog gate elements of
size provided for one of the canal escape / regulator structure.
Actual wt of 1set of stoplog elements as per data in Item : 34 of Annexure-2 : 2.534 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of canalescape / regulator stoplog gate elements provided for one of the canal escape / regulator ( for
details refer Item : 34 of Annexure-2 ).
1. Requirement of materials:
a. Structural steel conforming to IS : 2062 :
Angles/ beams/ channels/ bars with 2.5 % wastage ( 1166x1.025 ) : 1195 kg
Plates / flats with 2.5 % wastage ( 1342 x 1.025 ) : 1376 kg
b. Alluminium/ Bronze alloy components conforming to IS : 305 :
162
8/13/2019 Data Rates Gate Works 9
4/21
GATE / HOIST AND ALLIED WORKS
Bronze pads : 16.00 kg
c. Bolts / Nuts / Washers conforming to IS : 1363 :
GI bolts / nuts / washers with 2.5 % wastage ( 20 x 1.025 ) : 20.5 kg
MS bolts / nuts / washers with 2.5 % wastage ( 6 x 1.025 ) : 6 kg
d. Rubber seal conforming to IS : 11855 :
Bottom seal ( uncladed ) ( 8 x 1.025 ) : 8.2 Rm
Side seals ( uncladed ) ( 8.05 x 1.025 ) : 8.25 Rm
e. Welding electrodes ( General purpose / Low hydrogen ) :
GP / LH electrodes as per data sheet ( Item:34 Annexure-2 ) : 1588 Nos
Add for variations / wastage / misc welding @ 10 % ( 1588 x 0.1 ) : 159 Nos
Total requirement of GP / LH electrodes : 1747 Nos
for stitch weld GP electrodes @t 10 % of total ( 1747 x 0.10 ) : 175 Nos
for run welding LH electrodes @ 90 % of total ( 1747 x 0.90 ) : 1572 Nos
2. Cutting :
Total length of cutting assuming cutting for 2 sides as per data sheet : 70 Rm
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 7 Rm
Total : 77 Rm
For cutting structural steel sections to required sizes gas cutting is assumed.
Length of steel to be cut by using gas manually : 40 m
Length of steel to be cut by gas using pug cutting machine : 37 m
Time for gas cutting manually at ( av ) 2 m cutting / hour : 20 hoursTime for gas cutting by pug cutting machine at ( av ) 3 m cutting / hour : 12 hours
Acetelyne gas @ 0.6 cum / hour ( 20 + 12 ) x 0.60 : 19 cum
Oxygen gas @ 1.8 cum / hour ( 20 + 12 ) x 1.80 : 57 cum
Use of gas cutting torch with 50 min / hr working ( 20 x 60 / 50 ) : 24 hours
Use of pug cutting machine with 50 min / hr working ( 12 x 60 / 50 ) : 14 hours
3. Welding :
Length of welding as per data sheet : 216 Rm
For stich welding @ 2 hrs usage / shift & @ 15 electrodes / hr
( 175 / 15 ) x 8 / 2 : 47 hours
For run welding @ 6 hrs usage / shift & @ 15 electrodes / hr
( 1572 / 15 ) x 8 / 6 : 140 hours
Total : 187 hours
Deploy welding transformer for 187 hours.
Fuel / Energy charges @ 25 % hrs for stitch welding & @ 75 % hrs for run welding.
( 47 x 0.25 + 140 x 0.75 ) : 117 hours
4. Surface cleaning and painting :
Painting area for stoplog gate at 18 sqm / tonne ( 2.534 x 18 ) : 45 sqm
1 coat of zinc rich epoxy primer 40 micron dry film each coat.
Quantity of primer paint for 45 sqm @ 9 sqm / ltr / coat : 5 ltr
3 coats of coal tar epoxy paint 100 micron dry film each coat.
Quantity of coal tar epoxy paint for 45 sqm @ 6 sqm / ltr / coat : 23 ltr As surface cleaning by sand blasting is hazardous, it is proposed to adopt chemical treatment
to remove grease, rust, scaling etc., and to form phasphate coating to prevent further rusting
before applying primer painting.
Quantity of rust cleaner / inhibitor for 45 sqm @ 8 sqm / ltr : 6 ltr
5. Requirement of other machinery :
For handling of parts during fabrication and erection use of mobile derric crane for 2 hours and
stationery derric crane for 4 hours considered.
For drilling holes in skin plate, end girders and seal clamps use of drilling machine for 8 hours
163
8/13/2019 Data Rates Gate Works 9
5/21
GATE / HOIST AND ALLIED WORKS
considered.
For grinding and finishing weld joints in skin plate and other locations 8 hours use of grinding
machine considered.
6. Requirement of work force :
Work component Foreman Helper /
Painter Cl-II
Cutting sections 38 hours 2 5 5 10
Drilling holes 8 hours 1 1 --- 1
Fabricating by stitch welding 47 hours 3 6 --- 12
Run welding 140 hours 2 --- 18 18
Slide blocks fixing / Seal fixing 1 2 --- 2
Cleaning surface 45 sqm @ 15 sqm/day --- --- --- 3
Painting ( 4 x 45 ) sqm @ 15 sqm / day --- --- --- 15
Guide shoe fixing / Finishing / Erecting 1 1 --- 2
Total : 10 15 23 63
Note : a. It is assumed that all stitch welding will be done by fabricator. Hence, no separate provision
considered for welder for stitch welding.
b. Workforce for painting 1 coat primer and 3 coats finishing paint consists of 12 Painters Cl-II
at 15 sqm / day and 3 helpers to assist painters.
7. Excise duty on supply :Excise duty is applicable on supply of fabricated parts. The cost of materials is inclusive of all
taxes/ duties. Therefore, for purpose of rate analysis 75 percent of total cost excluding the cost
of materials ( assuming 25 % erection cost ) is considered for assessing excise duty.
8. Use rate of materials :
Cost of welding set @ Rs: 4500.00 / Each Rs: 4500.00
Life of welding set : 1000 hours
Use rate of welding set per hour ( cost / life ) Rs: 4.50
Cost of gas cutting set @ Rs: 1500.00 / Each Rs: 1500.00
Life of gas cutting set : 600 hours
Use rate of gas cutting set per hr ( cost / life ) Rs: 2.50
RATE ANALYSIS UNIT : 2.534 tonne
A. MATERIALS:
Sl No Unit Amount
in Rs.
1 Structural steel
Angles / Channels / Beams / Bars kg 1195.00 37.95 45350.25
Plates / flats kg 1376.00 40.00 55040.00
2 Alluminium / Bronze alloy components
Bronze pads kg 16.00 635.00 10160.00
3 Bolt / Nut / Washer
GI bolts / nuts / washers kg 20.50 95.00 1947.50MS bolts / nuts / washers kg 6.00 55.00 330.00
4 Rubber seals
Bottom seal ( uncladed ) Rm 8.20 147.00 1205.40
Side seals ( uncladed ) Rm 8.25 235.00 1938.75
5 Oxygen gas cum 57.00 48.00 2736.00
6 Acetyline gas cum 19.00 258.00 4902.00
7 Welding electrodes ( general purpose ) Nos 175.00 6.00 1050.00
8 Welding electrodes ( low hydrogen ) Nos 1572.00 12.00 18864.00
Welder
Quantity
Gas cutter /
in Rs.
Rate
Fabricator /
Marker /
Erector /
Perticulars
164
8/13/2019 Data Rates Gate Works 9
6/21
GATE / HOIST AND ALLIED WORKS
9 Zinc rich epoxy primer ltr 5.00 594.00 2970.00
10 Coal tar epoxy paint ltr 23.00 208.00 4784.00
11 Rust cleaner / inhibitor ltr 6.00 240.00 1440.00
12 Use rate welding holder set Hour 187.00 4.50 841.50
13 Use rate gas cutting torch set Hour 24.00 2.50 60.00
14 Wire brush Nos 1.00 30.00 30.00
15 Sundries LS 5.00 30.00 150.00
Total Rs: 153799.40
Add for small Tools and Plants @ 1% Rs: 1537.99
Add for Contractor's Profit @ 10% Rs: 15379.94
Add for Contractor's Overheads @ 5% Rs: 7689.97
Total cost of Materials : Rs: 178407.30
B. MACHINERY:
Sl No Unit Amount
in Rs.
1 Welding transformer Hour 187.00 12.00 2244.00
Fuel / Energy charges Hour 117.00 60.00 7020.00
2 Pug cutting machine Hour 14.00 16.00 224.00
Fuel / Energy charges Hour 14.00 3.00 42.00
3 Mobile crane 8 t Hour 2.00 362.00 724.00Fuel / Energy charges Hour 2.00 495.00 990.00
4 Stationery derric crane Hour 4.00 66.00 264.00
Fuel / Energy charges Hour 4.00 9.00 36.00
Contd
B. MACHINERY ( Contd ) :
Sl No Unit Amount
in Rs.
Contd
5 Grinding machine Hour 12.00 18.00 216.00
Fuel / Energy charges Hour 12.00 25.00 300.00
6 Drilling machines Hour 8.00 18.00 144.00
Fuel / Energy charges Hour 8.00 25.00 200.00
7 Sundries LS 5.00 30.00 150.00
Total Rs: 12554.00
Add for small Tools and Plants @ 1% Rs: 125.54
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 873.80
Add for Contractor's Overheads @ 5% Rs: 627.70
Total hire charges of Machinery : Rs: 14181.04
C. LABOUR:
Sl No Unit Amount
in Rs.1 Crew for Mobile crane Hour 2.00 75.70 151.40
2 Crew for Drilling machine Hour 8.00 59.50 476.00
3 Crew for Grinding machine Hour 12.00 59.50 714.00
4 Foreman Day 10.00 177.00 1770.00
5 Marker / Fabricator / Erector Day 15.00 157.50 2362.50
6 Gas cutter Day 5.00 157.50 787.50
7 Welder ( General ) Day 16.00 157.50 2520.00
8 Welder ( X - ray grade ) Day 2.00 173.25 346.50
Description
in Rs.
in Rs.
Quantity Rate
Quantity RateDescription
Description Quantity Rate
in Rs.
165
8/13/2019 Data Rates Gate Works 9
7/21
GATE / HOIST AND ALLIED WORKS
9 Helper fabrication / erection Day 45.00 141.50 6367.50
10 Helper for cleaning / painting Day 6.00 141.50 849.00
11 Painter Cl - II Day 12.00 141.50 1698.00
12 Electrician Day 1.00 143.00 143.00
Total Rs: 18185.40
Add for small Tools and Plants @ 1% Rs: 181.85
Add for Contractor's Profit @ 10% Rs: 1818.54
Add for hidden cost on Labour @ 15% Rs: 2727.81
Add for additional hidden cost on labour @ 15% Rs: 2727.81
Add for Contractor's Overheads @ 5% Rs: 909.27
Total cost of Labour : Rs: 26550.68
ABSTRACT:
A. Cost of Materials Rs: 178407.30
B. Hire charges of Machinery Rs: 14181.04
C. Cost of Labour Rs: 26550.68
TOTAL Rs: 219139.03
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% Rs: 2517.22
Add for insurance charges @ 1.00% Rs: 2191.39
Add for designs and drawings @ 2.50% Rs: 5478.48Add for zigs / supports / winches / chain-pulley @ 2.50% Rs: 5478.48
Add for power supply arrangements @ 2.00% Rs: 4382.78
Add for enabling works @ 1.40% Rs: 3067.95
Total Rs: 242255.32
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2 x 2.534 tonnes @ Rs: 129.10 / tonne Rs: 654.28
Add for transportation upto work site @ 3.00% Rs: 7267.66
Total cost for 2.534 tonne Rs: 250177.26
Rate per tonne Rs: 98700.00
Rate approved per tonne Rs: 98700.00
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2010-11 ITEM No: 35
ITEM: Design, fabrication, supply, erection and commissioning of embedded parts consisting of
liners for trash rack grooves ( coarse and fine screens ) with all accessories for pump house
intake structureincluding cost of all materials, machinery, labour, aligning, anchoring, welding,
finishing, cleaning, applying one coat of zinc rich epoxy primer and four coats of cold applied
coal tar epoxy paint etc., complete as per specifications and approved drawings with all leads
and lifts.
DATA:Embedded parts for trash rack groove of pump house intake structure consist of groove linerswith anchors.
Weight of one set embedded parts for trash rack groove will be in the range of 100 to 125 kg / m
height of the trash rack groove for one vent.
Consider embedded parts for trash rack groove of pump house intake for 3.55 m wide and 12 m
height vent.
Weight of embedded parts for 12 m height in tonnes based on empirical rule :
( 12 x 112.50 ) : 1350.00 kg
The weight computed as above based on empirical rule is further checked by computing the
166
8/13/2019 Data Rates Gate Works 9
8/21
GATE / HOIST AND ALLIED WORKS
actual weight as per fabrication drawings of embedded parts for trash rack groove for one vent
of one of the pump house intake structure.
Actual weight of embedded parts as per data in Item :35 of Annexure-2 : 1.322 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of embedded
parts for one vent of trash rack groove of one of the pump house intake structure ( for details
refer Item : 35 of Annexure-2 ).
1. Requirement of materials:
a. Structural steel conforming to IS : 2062 :
Plates / flats with 2.5 % wastage ( 1322 x 1.025 ) : 1355 kg
b. Welding electrodes ( General purpose / Low hydrogen ) :
GP / LH electrodes as per data sheet ( Item:35 Annexure-2 ) : 983 Nos
Add for variations / wastage / misc welding @ 10 % ( 983 x 0.1 ) : 98 Nos
Total requirement of GP / LH electrodes : 1081 Nos
for stitch welding GP electrodes @t 10 % of total ( 1081 x 0.10 ) : 108 Nos
for run welding LH electrodes @ 90 % of total ( 1081 x 0.90 ) : 973 Nos
2. Cutting :
Total length of cutting assuming cutting for 2 sides as per data sheet : 78 Rm
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 8 Rm
Total : 86 Rm
For cutting structural steel sections to required sizes gas cutting is assumed.Length of steel to be cut by using gas manually : 10 m
Length of steel to be cut by gas using pug cutting machine : 76 m
Time for gas cutting manually at ( av ) 2 m cutting / hour : 5 hours
Time for gas cutting by pug cutting machine at ( av ) 3 m cutting / hour : 10 hours
Acetelyne gas @ 0.6 cum / hour ( 5 + 25 ) x 0.60 : 18 cum
Oxygen gas @ 1.8 cum / hour ( 5 + 25 ) x 1.80 : 54 cum
Use of gas cutting torch with 50 min / hr working ( 5 x 60 / 50 ) : 6 hours
Use of pug cutting machine with 50 min / hr working ( 25 x 60 / 50 ) : 30 hours
3. Welding :
Length of welding as per data sheet : 98.3 m
For stich welding @ 2 hrs usage / shift & @ 15 electrodes / hr
( 108 x 8 / 15 / 2 ) : 29 hours
For run welding @ 6 hrs usage / shift & @ 15 electrodes / hr
( 973 x 8 / 15 / 6 ) : 86 hours
Total : 115 hours
Deploy welding transformer for 115 hours.
Fuel / Energy charges @ 25 % hrs for stitch welding & @ 75 % hrs for run welding.
( 29 x 0.25 + 86 x 0.75 ) : 72 hours
4. Surface cleaning and painting :
Painting area for embedded parts at 12 sqm / tonne ( 1.322 x 12 ) : 16 sqm
1 coat of zinc rich epoxy primer 40 micron dry film each coat.
Quantity of primer paint for 16 sqm @ 9 sqm / ltr / coat : 1.75 ltr 4 coats of coal tar epoxy paint 100 micron dry film each coat.
Quantity of coal tar epoxy paint for 16 sqm @ 6 sqm / ltr / coat : 10.5 ltr
As surface cleaning by sand blasting is hazardous, it is proposed to adopt chemical treatment
to remove grease, rust, scaling etc., and to form phasphate coating to prevent further rusting
before applying primer painting.
Quantity of rust cleaner / inhibitor for 16 sqm @ 8 sqm / ltr : 2 ltr
5. Requirement of other machinery :
For handling parts during fabrication and erection use 8 t mobile crane for 4 hours.
167
8/13/2019 Data Rates Gate Works 9
9/21
GATE / HOIST AND ALLIED WORKS
For holding in position during erection use stationery derric for 8 hours.
For finishing weld joints / edges 4 hours use of grinding machine considered.
6. Requirement of work force :
Work component Foreman Helper /
Painter Cl-II
Cutting sections 36 hours 2 4 4 8
Fabricating by stitch welding 29 hours 2 4 --- 8
Run welding 86 hours 1 --- 11 11
Erection of liners 1 2 --- 4
Cleaning surface 16 sqm @ 15 sqm/day --- --- --- 1
Painting ( 5 x 16 ) sqm @ 15 sqm / day --- --- --- 9
Finishing / cleaning --- 1 --- 1
Total : 6 11 15 42
Note : a. It is assumed that all stitch welding will be done by fabricator. Hence, no separate provision
is considered for welder for stitch welding.
b. Workforce for painting 1 coat primer and 4 coats finishing paint consists of 6 Painters Cl-II
at 15 sqm / day and 3 helpers to assist painters.
7. Excise duty on supply :
Excise duty is applicable on supply of fabricated parts. The cost of materials is inclusive of all
taxes/ duties. Therefore, for purpose of rate analysis 75 percent of total cost excluding the costof materials ( assuming 25 % erection cost ) is considered for assessing excise duty.
8. Use rate of materials :
Cost of welding set @ Rs: 4500.00 / Each Rs: 4500.00
Life of welding set : 1000 hours
Use rate of welding set per hour ( cost / life ) Rs: 4.50
Cost of gas cutting set @ Rs: 1500.00 / Each Rs: 1500.00
Life of gas cutting set : 600 hours
Use rate of gas cutting set per hr ( cost / life ) Rs: 2.50
RATE ANALYSIS UNIT : 1.322 tonne
A. MATERIALS:
Sl No Unit Amount
in Rs.
1 Structural steel
Plates / flats kg 1355.00 40.00 54200.00
2 Oxygen gas cum 54.00 48.00 2592.00
3 Acetyline gas cum 18.00 258.00 4644.00
4 Welding electrodes ( general purpose ) Nos 108.00 6.00 648.00
5 Welding electrodes ( low hydrogen ) Nos 973.00 12.00 11676.00
6 Zinc rich epoxy primer ltr 1.75 594.00 1039.50
7 Coal tar epoxy paint ltr 10.50 208.00 2184.00
8 Rust cleaner / inhibitor ltr 2.00 240.00 480.009 Use rate welding holder set Hour 115.00 4.50 517.50
10 Use rate gas cutting torch set Hour 6.00 2.50 15.00
11 Wire brush Nos 1.00 30.00 30.00
12 Sundries LS 3.00 30.00 90.00
Total Rs: 78116.00
Add for small Tools and Plants @ 1% Rs: 781.16
Add for Contractor's Profit @ 10% Rs: 7811.60
Add for Contractor's Overheads @ 5% Rs: 3905.80
Marker /
Quantity
Erector /
Fabricator /
Perticulars Rate
Welder
in Rs.
Gas cutter /
168
8/13/2019 Data Rates Gate Works 9
10/21
GATE / HOIST AND ALLIED WORKS
Total cost of Materials : Rs: 90614.56
B. MACHINERY:
Sl No Unit Amount
in Rs.
1 Welding transformer Hour 115.00 12.00 1380.00
Fuel / Energy charges Hour 72.00 60.00 4320.00
2 Pug cutting machine Hour 30.00 16.00 480.00
Fuel / Energy charges Hour 30.00 3.00 90.00
3 Mobile crane 8 t Hour 4.00 362.00 1448.00
Fuel / Energy charges Hour 4.00 495.00 1980.00
4 Stationery derric crane Hour 6.00 66.00 396.00
Fuel / Energy charges Hour 6.00 9.00 54.00
5 Grinding machine Hour 4.00 18.00 72.00
Fuel / Energy charges Hour 4.00 25.00 100.00
6 Sundries LS 3.00 30.00 90.00
Total Rs: 10410.00
Add for small Tools and Plants @ 1% Rs: 104.10
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 663.40
Add for Contractor's Overheads @ 5% Rs: 520.50
Total hire charges of Machinery : Rs: 11698.00
C. LABOUR:
Sl No Unit Amount
in Rs.
1 Crew for Mobile crane Hour 4.00 75.70 302.80
2 Crew for Grinding machine Hour 4.00 59.50 238.00
3 Foreman Day 6.00 177.00 1062.00
4 Marker / Fabricator / Erector Day 11.00 157.50 1732.50
5 Gas cutter Day 4.00 157.50 630.00
6 Welder ( General ) Day 11.00 157.50 1732.50
7 Helper fabrication / erection Day 32.00 141.50 4528.00
8 Helper for cleaning / painting Day 4.00 141.50 566.00
9 Painter Cl - II Day 6.00 141.50 849.00
10 Electrician Day 1.00 143.00 143.00
Total Rs: 11783.80
Add for small Tools and Plants @ 1% Rs: 117.84
Add for Contractor's Profit @ 10% Rs: 1178.38
Add for hidden cost on Labour @ 15% Rs: 1767.57
Add for additional hidden cost on labour @ 15% Rs: 1767.57
Add for Contractor's Overheads @ 5% Rs: 589.19
Total cost of Labour : Rs: 17204.35
ABSTRACT:A. Cost of Materials Rs: 90614.56
B. Hire charges of Machinery Rs: 11698.00
C. Cost of Labour Rs: 17204.35
TOTAL Rs: 119516.91
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% Rs: 1786.17
Add for insurance charges @ 1.00% Rs: 1195.17
Add for designs and drawings @ 2.50% Rs: 2987.92
Description Quantity Rate
QuantityDescription Rate
in Rs.
in Rs.
169
8/13/2019 Data Rates Gate Works 9
11/21
GATE / HOIST AND ALLIED WORKS
Add for zigs / supports / winches / chain-pulley @ 2.50% Rs: 2987.92
Add for power supply arrangements @ 2.00% Rs: 2390.34
Add for enabling works @ 1.40% Rs: 1673.24
Total Rs: 132537.66
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2 x 1.322 tonnes @ Rs: 129.10 / tonne Rs: 341.34
Add for transportation upto work site @ 3.00% Rs: 3976.13
Total cost for 1.322 tonne Rs: 136855.13
Rate per tonne Rs: 103500.00
Rate approved per tonne Rs: 103500.00
SECTION: GATE / HOIST & ALLIED WORKS. YEAR : 2010-11 ITEM No: 36
ITEM: Design, fabrication, supply, erection and commissioning of trash racks consisting of a number
of structural steel panels of suitable height with vertical trash bars at wider interval and weld
mesh frame for pump house intake structure including cost of all materials, machinery,
labour, aligning, anchoring, welding, finishing, cleaning, applying one coat of zinc rich epoxy
primer and four coats of cold applied coal tar epoxy paint etc., complete as per specifications
and approved drawings with all leads and lifts.
DATA:Tracsh rack consists of a number of panels of suitable size. Each panel consists of structural
steel frame with horizontal stiffeners at interval and vertical trash bars at closer or wider interval.
Where the trash bars are spaced at wider interval a weld mesh frame is attached to main frame.
Consider trash rack panels for pump house intake structure for 3.55 m wide vent opening.
Length of each panel : 3.75 m
Height of each panel : 2.70 m
Number of panels for one vent : 3.00 Nos
Total height of trash rack ( 3 x 2.70 ) : 8.10 m
Head of water : 7.50 m
Weight of trash rack in tonnes based on empirical formula :
= 0.0375 x ( L2x H x h )
0.716
Where ( L ) is length and ( H ) is total height and ( h ) is head of water in metres.
= 0.0375 x ( 3.75 x 3.75 x 8.1 x 7.5 )0.716
: 4.710 tonnes
The weight computed as above based on empirical formula is further checked by computing the
actual weight as per fabrication drawings of trash rack panels for 1 vent for pump house intake
structure having same vent size provided for one of the pump house.
Actual weight of embedded parts as per data in Item :36 of Annexure-2 : 4.686 tonnes
Consider actual weight for data rate analysis.
Consider details of Material / Gas cutting / Welding based on fabrication drawings of trash rack
provided for one vent of one of the pump house intake structure.
structure ( for details refer Item : 36 of Annexure-2 ).
1. Requirement of materials:
a. Structural steel conforming to IS : 2062 :Angles/ beams/ channels/ bars with 2.5% wastage ( 3246.1x1.025 ) : 3327 kg
Plates / flats with 2.5 % wastage ( 1359.3 x 1.025 ) : 1393 kg
b. Weld mesh (2 mm dia 25x25 mm opening ) ( 3.44x2.7x3x1.025 ) : 28.50 sqm
c. Bolt / Nut / Washer conforming to IS : 1363 :
GI bolts / Nuts / Washers with 2.5 % wastage ( 6.7 x 3 x 1.025 ) : 20.6 kg
d. Welding electrodes ( General purpose / Low hydrogen ) :
GP / LH electrodes as per data sheet ( Item:36 Annexure-2 ) : 1488 Nos
170
8/13/2019 Data Rates Gate Works 9
12/21
GATE / HOIST AND ALLIED WORKS
Add for variations / wastage / misc welding @ 10 % ( 1488 x 0.1 ) : 149 Nos
Total requirement of GP / LH electrodes : 1637 Nos
for stitch welding GP electrodes @t 10 % of total ( 1637 x 0.10 ) : 164 Nos
for run welding LH electrodes @ 90 % of total ( 1637 x 0.90 ) : 1473 Nos
2. Cutting :
Total length of cutting assuming cutting for 2 sides as per data sheet : 76 Rm
Add for variations ( cutting more than 2 sides / odd shape etc ) at 10 % : 8 Rm
Total : 84 Rm
For cutting structural steel sections to required sizes gas cutting is assumed.
As the work involves use angles / channels / beams cutting using cutting torch is considered.
Length of steel to be cut by using gas manually : 84 m
Time for gas cutting manually at ( av ) 2 m cutting / hour : 42 hours
Acetelyne gas @ 0.6 cum / hour ( 42 ) x 0.60 : 25 cum
Oxygen gas @ 1.8 cum / hour ( 42 ) x 1.80 : 75 cum
Use of gas cutting torch with 50 min / hr working ( 42 x 60 / 50 ) : 50 hours
3. Welding :
Length of welding as per data sheet : 149 m
For stich welding @ 2 hrs usage / shift & @ 15 electrodes / hr
( 164 x 8 / 15 / 2 ) : 44 hours
For run welding @ 6 hrs usage / shift & @ 15 electrodes / hr
( 1473 x 8 / 15 / 6 ) : 131 hours
Total : 175 hours
Deploy welding transformer for 175 hours.
Fuel / Energy charges @ 25 % hrs for stitch welding & @ 75 % hrs for run welding.
( 44 x 0.25 + 131 x 0.75 ) : 109 hours
4. Surface cleaning and painting :
Painting area for trash rack panels at 30 sqm / tonne ( 4.686 x 30 ) : 140 sqm
1 coat of zinc rich epoxy primer 40 micron dry film each coat.
Quantity of primer paint for 140 sqm @ 9 sqm / ltr / coat : 16.0 ltr
4 coats of coal tar epoxy paint 100 micron dry film each coat.
Quantity of coal tar epoxy paint for 140 sqm @ 6 sqm / ltr / coat : 94 ltr
As surface cleaning by sand blasting is hazardous, it is proposed to adopt chemical treatment
to remove grease, rust, scaling etc., and to form phasphate coating to prevent further rusting
before applying primer painting.
Quantity of rust cleaner / inhibitor for 140 sqm @ 8 sqm / ltr : 18 ltr
5. Requirement of other machinery :
For handling parts during fabrication and erection use 8 t mobile crane for 8 hours.
For drilling holes for fixing bolts use drilling machine for 8 hours.
For finishing weld joints / edges 4 hours use of grinding machine considered.
6. Requirement of work force :
Work component Foreman Helper /Painter Cl-II
Cutting sections 50 hours 1 6 6 12
Fabricating by stitch welding 39 hours 2 5 --- 10
Run welding 131 hours 2 --- 16 16
Erection of panels 1 2 --- 4
Cleaning surface 140 sqm @ 15 sqm/day --- --- --- 10
Painting ( 5 x 140 ) sqm @ 15 sqm / day --- --- --- 59
Marker /Fabricator /
Gas cutter /
Erector /
Welder
171
8/13/2019 Data Rates Gate Works 9
13/21
GATE / HOIST AND ALLIED WORKS
Finishing / cleaning --- 1 --- 1
Total : 6 14 22 112
Note : a. It is assumed that all stitch welding will be done by fabricator. Hence, no separate provision
is considered for welder for stitch welding.
b. Workforce for painting 1 coat primer and 4 coats finishing paint consists of 47 Painters Cl-II
at 15 sqm / day and 12 helpers to assist painters.
7. Excise duty on supply :
Excise duty is applicable on supply of fabricated parts. The cost of materials is inclusive of all
taxes/ duties. Therefore, for purpose of rate analysis 75 percent of total cost excluding the cost
of materials ( assuming 25 % erection cost ) is considered for assessing excise duty.
8. Use rate of materials :
Cost of welding set @ Rs: 4500.00 / Each Rs: 4500.00
Life of welding set : 1000 hours
Use rate of welding set per hour ( cost / life ) Rs: 4.50
Cost of gas cutting set @ Rs: 1500.00 / Each Rs: 1500.00
Life of gas cutting set : 600 hours
Use rate of gas cutting set per hr ( cost / life ) Rs: 2.50
RATE ANALYSIS UNIT : 4.686 tonne
A. MATERIALS:
Sl No Unit Amount
in Rs.
1 Structural steel
Angles / beams / channels / bars kg 3327.00 37.95 126259.65
Plates / flats kg 1393.00 40.00 55720.00
2 Weld mesh 25x25 mm opening sqm 28.50 150.00 4275.00
3 Bolt / Nut / Washer ( GI ) kg 20.60 95.00 1957.00
4 Oxygen gas cum 75.00 48.00 3600.00
5 Acetyline gas cum 25.00 258.00 6450.00
6 Welding electrodes ( general purpose ) Nos 164.00 6.00 984.00
7 Welding electrodes ( low hydrogen ) Nos 1473.00 12.00 17676.00
8 Zinc rich epoxy primer ltr 16.00 594.00 9504.00
9 Coal tar epoxy paint ltr 94.00 208.00 19552.00
10 Rust cleaner / inhibitor ltr 18.00 240.00 4320.00
11 Use rate welding holder set Hour 175.00 4.50 787.50
12 Use rate gas cutting torch set Hour 50.00 2.50 125.00
13 Wire brush Nos 2.00 30.00 60.00
14 Sundries LS 15.00 30.00 450.00
Total Rs: 251720.15
Add for small Tools and Plants @ 1% Rs: 2517.20
Add for Contractor's Profit @ 10% Rs: 25172.02
Add for Contractor's Overheads @ 5% Rs: 12586.01Total cost of Materials : Rs: 291995.37
B. MACHINERY:
Sl No Unit Amount
in Rs.
1 Welding transformer Hour 175.00 12.00 2100.00
Fuel / Energy charges Hour 109.00 60.00 6540.00
2 Mobile crane 8 t Hour 8.00 362.00 2896.00
Description Quantity Rate
in Rs.
RateQuantityPerticulars
in Rs.
172
8/13/2019 Data Rates Gate Works 9
14/21
GATE / HOIST AND ALLIED WORKS
Fuel / Energy charges Hour 8.00 495.00 3960.00
3 Drilling machine Hour 4.00 18.00 72.00
Fuel / Energy charges Hour 4.00 25.00 100.00
4 Grinding machine Hour 8.00 18.00 144.00
Fuel / Energy charges Hour 8.00 25.00 200.00
5 Sundries LS 15.00 30.00 450.00
Total Rs: 16462.00
Add for small Tools and Plants @ 1% Rs: 164.62
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 1125.00
Add for Contractor's Overheads @ 5% Rs: 823.10
Total hire charges of Machinery : Rs: 18574.72
C. LABOUR:
Sl No Unit Amount
in Rs.
1 Crew for Mobile crane Hour 8.00 75.70 605.60
2 Crew for Drilling machine Hour 4.00 59.50 238.00
Contd
C. LABOUR ( Contd ) :
Sl No Unit Amount
in Rs.
Contd
3 Crew for Grinding machine Hour 8.00 59.50 476.00
4 Foreman Day 6.00 177.00 1062.00
5 Marker / Fabricator / Erector Day 14.00 157.50 2205.00
6 Gas cutter Day 6.00 157.50 945.00
7 Welder ( General ) Day 16.00 157.50 2520.00
8 Helper fabrication / erection Day 43.00 141.50 6084.50
9 Helper for cleaning / painting Day 22.00 141.50 3113.00
10 Painter Cl - II Day 47.00 141.50 6650.50
11 Electrician Day 1.00 143.00 143.00
Total Rs: 24042.60
Add for small Tools and Plants @ 1% Rs: 240.43
Add for Contractor's Profit @ 10% Rs: 2404.26
Add for hidden cost on Labour @ 15% Rs: 3606.39
Add for additional hidden cost on labour @ 15% Rs: 3606.39
Add for Contractor's Overheads @ 5% Rs: 1202.13
Total cost of Labour : Rs: 35102.20
ABSTRACT:
A. Cost of Materials Rs: 291995.37
B. Hire charges of Machinery Rs: 18574.72
C. Cost of Labour Rs: 35102.20TOTAL Rs: 345672.29
Add for excise duty on 75 percent cost of
Machinery / Labour components @ 8.24% Rs: 3317.23
Add for insurance charges @ 1.00% Rs: 3456.72
Add for designs and drawings @ 2.50% Rs: 8641.81
Add for zigs / supports / winches / chain-pulley @ 2.50% Rs: 8641.81
Add for power supply arrangements @ 2.00% Rs: 6913.45
Add for enabling works @ 1.40% Rs: 4839.41
in Rs.
Rate
in Rs.
Description Quantity
QuantityDescription Rate
173
8/13/2019 Data Rates Gate Works 9
15/21
GATE / HOIST AND ALLIED WORKS
Total Rs: 381482.72
Add for 2 rehandling leads for 1 km including loading and unloading :
Fabricated parts 2 x 4.686 tonnes @ Rs: 129.10 / tonne Rs: 1209.93
Add for transportation upto work site @ 3.00% Rs: 11444.48
Total cost for 4.686 tonne Rs: 394137.13
Rate per tonne Rs: 84100.00
Rate approved per tonne Rs: 84100.00
174
8/13/2019 Data Rates Gate Works 9
16/21
GATE / HOIST AND ALLIED WORKS
ANNEXURE-1
DATA FOR PERCENTAGE PROVISIONS
FOR
ENABLING WORKS
175
8/13/2019 Data Rates Gate Works 9
17/21
GATE / HOIST AND ALLIED WORKS
176
8/13/2019 Data Rates Gate Works 9
18/21
GATE / HOIST AND ALLIED WORKS
SECTION: GATE / HOIST & ALLIED WORKS. YEAR: 2010-11 Annexure-1.a
ITEM: Provision for Electric sub-station / Demand charges / Lighting fabrication & work areas:
DATA:Generally, contracts provide for arranging HT / LT electric power line within about 1 km distance
from work site by the department. From the departmental bulk supply point laying of further
transmission lines, erection of sub-station, erecting distribution lines and other arrangements
for power supply to various installations will be the responsibility of the contractors requiring
electric power for their works.
For gate / hoist works, generally, cutting / bending / welding operations for most of the parts
are carried out at the contractor's central fabrication yard and fabrcated parts along with the
bought out parts are transported to site of work. Fabrication of some matching parts and minor
modifications to shop fabricated parts / erection / field welding / commissioning are carried out
at specified work site. Therefore, electric power supply arrangements are necessary both at
central fabrication place and erection / commissioning place for gate / hoist works.
Estimation of electric power load for sub-station for gate / hoist works:
Erection
place ( in hp )Plate shearing machine 20.00 ---
Bending machine 15.00 15.00
Pug cutting machine 4.00 2.00
Planing machine 15.00 ---
Drilling machine 5.00 5.00
Grinding machine 5.00 5.00
Welding transformers 120.00 120.00
Work shop equipments / miscellaneous 20.00 20.00
Total : 204.00 167.00
Requirement of power in Kw 152.184 124.58
Add for lighting fabrication area & trial running etc @ 5 % 7.61 ---
Add for lighting erection areas & trial running etc @ 10 % --- 12.46
Add for lighting & domestic use for camp @ 5 % 0.00 6.23
Add for reserve capacity @ 5 % 7.61 6.23
Total : 167.40 149.50
Capacity of sub-station required hp / 0.85 196.94 175.88
200 kVA 175 kVA
For working out demand charges sanctioned power requirement is assumed to vary from
100 KVA to 200 kVA ( average 150 kVA ) for fabrication place and from 75 kVA to 175 kVA
( average 125 kVA ) for erection site.
Av. demand for electric power is considered for 2 years each for fabrication and erection sites.
Consider 1 Transformer of 250 KVA at each place.
Capital cost of other sub-station equipments & distribution lines:( for each place )
HT / LT Circuit breaker 3 Nos @ Rs: 30000.00 / Each Rs: 90000.00
Poles with fixtures 10 Nos @ Rs: 4200.00 / Each Rs: 42000.00
HT / LT Line conductor 2 km @ Rs: 27000.00 / km Rs: 54000.00
Other accessories / controls / junctions LS Rs: 36000.00Total Rs: 222000.00
Life of sub-station equipments ( average ) : 20 years
Salvage value : 10 percent
Maintenance & Repairs as % of Capital cost : 25 percent
Miscellaneous charges as % of Repair charges : 10 percent
Fabrication
place ( in hp )
say :
177
8/13/2019 Data Rates Gate Works 9
19/21
GATE / HOIST AND ALLIED WORKS
Interest on av. capital cost per annum : 11.00%
Insurance charges as % of av. capital cost per annum : 1%
Average capital cost 222000 x ( 20+1 ) / 40 Rs: 116550.00
Hire charges of sub-station equipments / year :
Depreciation per year 222000 x 0.9 / 20 Rs: 9990.00
Interest on av. Capital cost per year 116550 x 0.11 Rs: 12820.50
Maintenance & repairs per year 222000 x 0.25 / 20 Rs: 2775.00
Miscellaneous charges per year 2775.00 x 0.1 Rs: 277.50
Insurance charges per year 116550 x 0.01 Rs: 1165.50
Total hire charges / year Rs: 27028.50
Total cost of sub-station equipments :
Transformers 1 Nos @ Rs: 297000 / Each Rs: 297000.00
Other sub-station equipments Rs: 222000.00
Total Rs: 519000.00
Cables & Fittings: ( for fabrication place and erection place ) :
PVC cable 70 sqmm 200 m @ Rs: 250.00 / Rm Rs: 50000.00
PVC cable 25 sqmm 200 m @ Rs: 100.00 / Rm Rs: 20000.00PVC cable 16 sqmm 500 m @ Rs: 58.00 / Rm Rs: 29000.00
PVC cable 10 sqmm & below 1000 m Rs: 48.00 / Rm Rs: 48000.00
Miscellaneous fittings / switches etc LS Rs: 200.00
Total Rs: 147200.00
Assume use of cables for 10 years with 10 percent salvage value.
Use rate of cables per year with 10 % salvage value Rs: 13248.00
Data for cost of Lighting : ( for fabrication place and erection place ) :
Lighting facilities are to be provided for plants and work areas during night time.
Provision of flood lights near work areas and tube lights at other locations is assumed.
No. of tube lights for fabrication and erection areas assumed: : (10+10) Nos.
No. of hours of use and energy requirement for 2 years
No. of hours of usage ( 20 x 12 x 300 x 2 ) : 144000.00
Energy requirement in Kwhr ( 20x 12x 300x 2x 40 / 1000) : 5760.00
No. of flood lights for fabrication / erection areas assumed: : (10+10) Nos
No. of hours of use and energy requirement for 2 years
No. of hours of usage ( 20 x 12 x 300 x 2 ) : 144000.00
Energy requirement in Kwhr (20x 12x 300x2x 500/ 1000 ) : 72000.00
Flood / Tube light fittings:
Flood light sets 20 Nos @ Rs: 1200.00 / set Rs: 24000.00
Tube light sets (plant area) 20 Nos @ Rs: 190.00 / set Rs: 3800.00
Accessories for light fittings / repairs / replacements etc LS Rs: 1500.00
Total Rs: 29300.00
Assume use of light fittings for 10 years with 50 percent salvage value.
Use rate of light fittings / year with 50 % salvage value Rs: 1465.00
( 29300.00 x 0.5 / 10 )
Cost of flood lights 500 W Rs: 650.00 / Each Rs: 650.00
Life of flood light in hours : 1500.00Use rate of flood lights per hour 650.00 / 1500 Rs: 0.43
Cost of tube lights 40 W Rs: 50.00 / Each Rs: 50.00
Life of fluorescent tube light in hours : 1500.00
Use rate of tube lights per hour 50.00 / 1500 Rs: 0.03
178
8/13/2019 Data Rates Gate Works 9
20/21
GATE / HOIST AND ALLIED WORKS
Running 50 KVA DG set is assumed for 1 hour daily for fabrication place and 2 hours daily for
erection site to ensure minimum power supply for lighting and works during break down of main
power supply from grid.
RATE ANALYSIS UNIT: 1.00 No.
A. MATERIALS:( fabrication & erection sites combined )
Sl No Perticulars Unit Amount
in Rs.
1 Use rate of cables Year 2.00 13248.00 26496.00
2 Anchors / supports for cables / lights LS 200.00 30.00 6000.00
3 Use rate of flood/ tube light sets Year 2.00 1465.00 2930.00
4 Use rate of flood lights Hour 0.43 62400.00
Energy charges Kwhr 72000.00 5.60 403200.00
5 Use rate of fluorescent tubes Hour 0.03 4800.00
Energy charges Kwhr 5760.00 5.60 32256.00
6 Sundries ( tapes & consumeables ) LS 200.00 30.00 6000.00
Total Rs: 544082.00
Add for small Tools and Plants @ 1% Rs: 5440.82
Add for Contractor's Profit @ 10% Rs: 54408.20
Add for Contractor's Overheads @ 5% Rs: 27204.10Total cost of Materials : Rs: 631135.12
B. MACHINERY: ( fabrication & erection site combined ) :
Sl No Unit Amount
in Rs.
1 Sub-station at fabrication place Year 2.00 54057.00
Sub-station at erection place Year 2.00 54057.00
2 Transformer 250 KVA 1 No.( fabrication ) Month 24.00 3523.00 84552.00
Transformer 250 KVA 1 No. ( erection ) Month 24.00 3523.00 84552.00
3 Demand charges for 2 years: 150 KVA
at 85 % PF ( 150x2x12x0.85 ) KVA 3060.00 190.00 581400.00
Demand charges for 2 years: 125 KVA
at 85 % PF ( 125x2x12x0.85 ) KVA 2550.00 190.00 484500.00
4 DG set 50 KVA at fabrication place Hour 600.00 94.00 56400.00
Fuel / Energy charges Hour 600.00 660.00 396000.00
DG set 50 KVA at erection place Hour 1200.00 94.00 112800.00
Fuel / Energy charges Hour 1200.00 660.00 792000.00
5 Sundries LS 200.00 30.00 6000.00
Total Rs: 2706318.00
Add for small Tools and Plants @ 1% Rs: 27063.18
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 225990.00
Add for Contractor's Overheads @ 5% Rs: 135315.90
Total hire charges of Machinery : Rs: 3094687.08
C. LABOUR: ( fabrication & erection sites combined ) :
Sl No Unit Amount
in Rs.1 Crew for DG set at fabrication place Hour 600.00 45.10 27060.00
Crew for DG set at erection place Hour 1200.00 45.10 54120.00
Contd
Description
Description
Quantity Rate
in Rs.
Quantity
Quantity
144000.00
144000.00
27028.50
in Rs.
Rate
in Rs.
Rate
27028.50
179
8/13/2019 Data Rates Gate Works 9
21/21
GATE / HOIST AND ALLIED WORKS
C. LABOUR( Contd ) : ( fabrication & erection sites combined ) :
Sl No Unit Amount
in Rs.
Contd
2 Electrician 1 No. x 2 x 12 x 26 days Day 624.00 143.00 89232.00
Electrician 1 No. x 2 x 12 x 26 days Day 624.00 143.00 89232.00
3 Heavy mazdoor 1 No x 2 x 12 x 26 days Day 624.00 132.00 82368.00
Heavy mazdoor 1 No x 2 x 12 x 26 days Day 624.00 132.00 82368.00
Total Rs: 424380.00
Add for small Tools and Plants @ 1% Rs: 4243.80
Add for Contractor's Profit @ 10% Rs: 42438.00
Add for hidden cost on Labour @ 15% Rs: 63657.00
Add for additional hidden cost on labour @ 15% Rs: 63657.00
Add for Contractor's Overheads @ 5% Rs: 21219.00
Total cost of Labour : Rs: 619594.80
D. ENABLING WORKS AT ERECTION SITE :
1 Shed for DG set & office 50 sqm @ Rs: 4500.00 / sqm Rs: 225000.00
2 Fensing for sub-station 100 Rm @ Rs: 750.00 / Rm Rs: 150000.00
3 Civil works for foundations / pedastals / duct etc LS Rs: 60000.00
Total Rs: 435000.00Add interest for ( 1 + 1 ) years @ 11% Rs: 95700.00
Add for transportation / erection / dismantling cost @ 12% Rs: 62280.00
Deduct salvage value on shed & fensing @ 25% ( - ) Rs: -93750.00
Total Rs: 499230.00
ABSTRACT:
A. Cost of Materials Rs: 631135.12
B. Hire charges of Machinery Rs: 3094687.08
C. Cost of Labour Rs: 619594.80
D. Cost of enabling works Rs: 499230.00
TOTAL Rs: 4844647.00
Less requirement for camp use at site @ 5% ( - ) Rs: -242232.35
Total cost for work 1.00 No. Rs: 4602414.65
Approximate quantity of gate / hoist work is assumed at 2000 tonnes.
As radial gates are major components of work, the basic unit rates worked out for radial gate
and hoist are considered for estimating the approximate cost of gate / hoist works.
The quantity distribution for embedded parts / gate / hoist is assumed as under:
Embedded parts with all accessories : 260 tonnes
Gates with all accessories : 1460 tonnes
Hoists with all accessories : 280 tonnes
Total : 2000 tonnes
Basic cost of embedded parts / tonne Rs: 1270647 / 14.334 ( Item-1) Rs: 88645.66
Basic cost of radial gate / tonne Rs: 6384227 / 57.457 ( Item-2) Rs: 111113.13
Basic cost of radial gate hoist / tonne Rs: 2477887 / 15.440 ( Item-3) Rs: 160484.92
Total cost of embedded parts / gates / hoists:
Total cost of embedded parts x 260 Rs: 23047871
Total cost of gates x 1460 Rs: 162225168Total cost of hoists x 280 Rs: 44935779
Total Rs: 230208819
Cost of power supply arrangements including lighting and demand charges as percentage of
Description Quantity Rate
88645.66
111113.13
in Rs.
160484.92