173
CANAL AND ALLIED WORKS FOR THE YEAR : 2014-15 CONTENTS PAGES REFERENCE DATA 1 -- 3 NOTES ON BASIC RATES 4 -- 4 DATA FOR SCHEDULE OF RATES 5 -- 167 DATA FOR ENABLING WORKS 168--170 CANAL AND ALLIED WORKS CANAL AND ALLIED WORKS CANAL AND ALLIED WORKS CANAL AND ALLIED WORKS d®¸ÀA¥À£ÀÆä® E¯ÁSÉ d®¸ÀA¥À£ÀÆä® E¯ÁSÉ d®¸ÀA¥À£ÀÆä® E¯ÁSÉ d®¸ÀA¥À£ÀÆä® E¯ÁSÉ FINILISED BY SCHEDULE OF RATES COMMITTEE CHAPTER- WRD: 3 SCHEDULE OF RATES SCHEDULE OF RATES SCHEDULE OF RATES SCHEDULE OF RATES zÀgÀ¥ÀnÖ ¸À«Äw¬ÄAzÀ ¥ÀjµÀÌj¸À®ànÖzÉ zÀgÀ¥ÀnÖ ¸À«Äw¬ÄAzÀ ¥ÀjµÀÌj¸À®ànÖzÉ zÀgÀ¥ÀnÖ ¸À«Äw¬ÄAzÀ ¥ÀjµÀÌj¸À®ànÖzÉ zÀgÀ¥ÀnÖ ¸À«Äw¬ÄAzÀ ¥ÀjµÀÌj¸À®ànÖzÉ WATER RESOURCES DEPARTMENT

Data rates-Canal Works

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Data rates-Canal Works

CANAL AND ALLIED WORKS

FOR THE YEAR : 2014-15

CONTENTS PAGES

REFERENCE DATA 1 -- 3

NOTES ON BASIC RATES 4 -- 4

DATA FOR SCHEDULE OF RATES 5 -- 167

DATA FOR ENABLING WORKS 168--170

CANAL AND ALLIED WORKSCANAL AND ALLIED WORKSCANAL AND ALLIED WORKSCANAL AND ALLIED WORKS

d®¸ÀA¥À£ÀÆä® E¯ÁSÉd®¸ÀA¥À£ÀÆä® E¯ÁSÉd®¸ÀA¥À£ÀÆä® E¯ÁSÉd®¸ÀA¥À£ÀÆä® E¯ÁSÉ

FINILISED BY SCHEDULE OF RATES COMMITTEE

CHAPTER- WRD: 3

SCHEDULE OF RATESSCHEDULE OF RATESSCHEDULE OF RATESSCHEDULE OF RATES

zÀgÀ¥ÀnÖ ¸À«Äw¬ÄAzÀ ¥ÀjµÀÌj¸À®ànÖzÉzÀgÀ¥ÀnÖ ¸À«Äw¬ÄAzÀ ¥ÀjµÀÌj¸À®ànÖzÉzÀgÀ¥ÀnÖ ¸À«Äw¬ÄAzÀ ¥ÀjµÀÌj¸À®ànÖzÉzÀgÀ¥ÀnÖ ¸À«Äw¬ÄAzÀ ¥ÀjµÀÌj¸À®ànÖzÉ

WATER RESOURCES DEPARTMENT

Page 2: Data rates-Canal Works

CANAL AND ALLIED WORKS

Page 3: Data rates-Canal Works

CANAL AND ALLIED WORKS

FOR THE YEAR: 2014-15

COST OF MATERIALS :

1 Air hose 25 mm dia per Rm `: 200.00

2 Air hose 50 mm dia per Rm `: 270.00

3 Asphalt 80 / 100 and 85 / 25 Gr per kg `: 52.00

4 Binding wire per kg `: 60.00

5 Cement per kg `: 7.50

6 Coarse aggregate 10-4.75 mm per cum ( at quarry ) `: 1160.00

7 Coarse aggregate 20-10 mm per cum ( at quarry ) `: 950.00

8 Coarse aggregate 40-20 mm per cum ( at quarry ) `: 740.00

9 Curing Compound per ltr `: 134.00

10 D - cord per Rm `: 9.00

11 Detonating fuse coil per Rm `: 9.00

14 Detonator delay type per No. `: 20.00

15 Detonator electric per No. `: 12.00

16 Detonator ordinary per No. `: 7.00

17 Diesel oil per ltr `: 55.00

18 Empty cement bags per No. `: 3.00

19 Explosive ANFO high strength booster per kg `: 65.00

20 Explosive ANFO per kg `: 52.00

21 Explosive small dia.( Kelvex-220 ) per kg `: 60.00

22 Extension rod with coupling sleeve per Rm `: 4190.00

23 Filter fabric 200 gsm per sqm `: 220.00

24 Filter fabric 250 gsm per sqm `: 255.00

25 Fine aggregate / Sand per cum ( Un-screened at quarry ) `: 615.00

26 Fine aggregate per cum ( Screened at quarry ) `: 730.00

27 G I pipe 50 mm dia A class per Rm `: 280.00

28 Jack hammer Drill rod 1.5 m length per No. `: 4395.00

29 LDPE sheet 500 micron thick per sqm `: 110.00

30 LDPE sheet 750 micron thick per sqm `: 180.00

31 LDPE sheet 1000 micron thick per sqm `: 215.00

32 Murum per cum ( at quarry ) `: 140.00

33 Paving Cylinder per Each `: 27800.00

34 PVC sealing strip per Rm `: 45.00

35 Reinforcement steel per kg `: 48.48

36 Rough stone 200 x 200 x 750 mm per No. ( at quarry ) `: 20.00

37 Shahabad stone slab per sqm `: 270.00

38 Shutter oil per ltr `: 35.00

39 Size stone 150 - 200 mm height per No. ( at quarry ) `: 10.00

40 Size stone 200 - 250 mm height per No. ( at quarry ) `: 11.00

41 Size stone 250 - 300 mm height per No. ( at quarry ) `: 15.00

42 Stone chips per cum ( at dump yard ) `: 385.00

43 Stone chips per cum ( at quarry ) `: 500.00

44 Structural steel angle / beam / channel / bar per kg `: 49.14

45 Structural steel plate / flat per kg `: 51.14

45 Super Plasticiser per ltr `: 105.00

47 Tarfelt jointer filler board 12 mm thick per sqm `: 400.00

48 Tarfelt jointer filler board 20 mm thick per sqm `: 650.00

1

CANAL AND ALLIED WORKS - REFERENCE DATA

Page 4: Data rates-Canal Works

CANAL AND ALLIED WORKS

49 T.C Cross bit 100 mm dia per No. `: 12185.00

50 Through stone 200 x 200 x 300 mm per No. ( at quarry ) `: 16.00

51 Through stones 250 x 250 x 450 mm per No. ( at quarry ) `: 22.00

52 Turfing sods per sqm `: 25.00

53 Un-coursed rubble stones per cum ( at dump yard ) `: 320.00

54 Un-coursed rubble stones per cum ( at quarry ) `: 400.00

55 Wire mesh 50 x 50 mm 20 guage per sqm `: 220.00

LEAD CHARGES FOR 1 km REHANDLING LEAD: Unloading

1 Earth/ Sand `: 49.50 74.90 12.80

2 Stone/ Coarse aggregates `: 70.30 88.40 44.20

3 Cement `: 55.40 81.50 81.50

4 Reinforcement steel `: 55.40 81.50 81.50

ROYALTY CHARGES: Per tonne

1 Earth / Soil / Murum `: 20.00

2 Stone / Coarse aggregate `: 60.00

3 Fine aggregate / Sand `: 60.00

HIRE CHARGES OF MACHINERY : Crew charge

1 Air compressor 8.5 cmm ( diesel ) / hour `: 223.00 851.00 121.00

2 Angle dozer 90 hp per hour `: 1273.00 582.00 128.00

3 Batching plant 15 cum / hr rated capacity `: 334.00 288.00 181.00

4 Concrete hand mixer 45 / 30 ltr per hour `: 11.00 6.00 ---

5 Concrete mixer 300 / 200 ( diesel ) / hour `: 46.00 76.00 126.00

6 Concrete mixer 600 / 400 ( diesel ) / hour `: 93.00 151.00 126.00

7 Diesel generating set 30 KVA per hour `: 66.00 605.00 75.00

8 Diesel generating set 50 KVA per hour `: 104.00 908.00 75.00

9 Diesel road roller per hour `: 252.00 681.00 121.00

10 Jack hammer per hour `: 16.00 8.00 188.00

11 Mechanical concrete paver per hour `: 311.00 28.00 241.00

12 Needle Vibrator 40 mm ( petrol ) per hour `: 9.00 18.00 90.00

13 Pump 5 hp ( diesel ) per hour `: 7.00 76.00 60.00

14 Shovel 0.85 cum per hour `: 1322.00 832.00 128.00

15 Shovel 0.50 cum per hour `: 799.00 454.00 128.00

16 Tipper 5 cum per hour `: 309.00 286.00 95.00

17 Transit mixer 2 cum per hour `: 708.00 832.00 151.00

18 Vibratory pad foot roller per hour `: 1246.00 983.00 151.00

19 Waggon drill per hour `: 239.00 14.00 150.00

20 Water tanker per hour `: 306.00 286.00 95.00

WAGES OF WORKERS Per day

1 Bar bender `: 256.73

2 Blaster ( Licensed ) `: 243.23

3 Carpentor Class II `: 244.23

4 Cartman with double bullock cart `: 278.23

5 Crowbarman `: 239.73

6 Electrician `: 241.23

7 Helper blasting `: 239.73

8 Maistry `: 241.23

Fuel charge

1 km lead

2

Loading

Hire charge

Page 5: Data rates-Canal Works

CANAL AND ALLIED WORKS

9 Mason Class I `: 256.73

10 Mason Class II `: 244.23

11 Mazdoor heavy `: 238.73

12 Mazdoor light `: 237.23

13 Mechanic / Fitter / Welder `: 254.73

14 Pipe fitter `: 249.23

15 Rollerman with bullock roller `: 278.23

16 Stone breaker `: 241.73

17 Stone chiseller Cl- I `: 244.73

18 Stone chiseller Cl- II `: 241.73

OTHER DATA :

1 Contractor's Overheads on Materials / Machinery / Labour % 5.00

2 Contractor's Profit on Materials / Fuel & Energy charges / Labour % 10.00

3 Hidden cost on Labour % 15.00

4 Rate of interest per annum % 11.00

5 Small Tools & Plant on Materials / Machinery / Labour % 1.00

6 Structural steel fabrication per kg `: 16.00

7 Sundries ( lumpsum rate for unquantified inputs ) `: 44.00

8 Cost of Other enabling works ( as per Annexure-1 at the end ) % 1.00

3

Page 6: Data rates-Canal Works

CANAL AND ALLIED WORKS

FOR THE YEAR : 2014-15

1. All notes under ' General Notes on Schedule of Rates ' and Notes on Lead, Lift, Loading and

un-loading Charges are applicable to Canal and Allied Works also to the extent they are

relevant.

2. Unless otherwise specified the basic rates are inclusive of all lifts.

3. For earth / rockfill embankment works 1 km initial lead is considered in the basic rates. As no

storing / stacking and re-handling of materials is involved for these works lead charges for

additional lead shall be worked out for total lead including initial lead of 1 km and then the

cost of first km lead shall be deducted. No loading and un-loading charges shall be added as

the additional lead does not involve re-handling of materials.

Example :

Total lead for soil from approved borrow area : 2 km

Initial lead included in the basic rate in the SR : 1 km

Additional lead charges : Lead charges for 2 km `: 59.90

Less Lead charges for 1 km `: -49.50

Additional lead charges `: 10.40

No loading and un-loading charges shall be added.

4. Cement content specified for cement concrete works in the item description is based on

theoritical design mix computations and is exclusive of wastage and requirement for any

incidentals. The actual cement content may vary based on trial mix studies. A suitable clause

shall be included in the tender for regulating payment for any upward or downward variation in

cement content.

5. A weightage of 25 percent over the rates in the SR is permissible for all items of works involved

in the modernization of canals and which are to be carried out during the canal closure period

of about 3 - 4 months and less. In the estimates for modernization, the items of work shall

appear based on the rate in SR without the permissible weightage. Below the respective items,

the weightage permissible for the item is to be included. Further, the payment of weighatage

is permissible only when the contractor completes a minimum of 90 percent of the work

entrusted in a single closure period. Failing which the contractor foregoes the advantage of

weightage. Payment of RA bills shall be made at rates excluding the weightage. It is only in

the last RA bill / final bill, payment for weightage is to be released subject to above condition.

6. The quantities of materials including wastage, requirements for incidentals etc., for working

out additional lead charges shall be as per the statement of requirement of materials under

this section.

NOTES ON SCHEDULE OF RATES

4

CANAL AND ALLIED WORKS

Page 7: Data rates-Canal Works

CANAL AND ALLIED WORKS

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.1

ITEM: Excavation in all kinds of soil including boulders upto 0.6 m diameter ( 0.113 cum) for canal,

seating of embankment, filter drains / catch water drains etc., and placing the excavated stuff

neatly in dump area or for formation of service road / embankment as directed including

cost of all materials, machinery, labour, dressing bed and sides to required level and profile etc.,

complete with lead upto 1 km and depth of cut upto 18 m.

DATA:Capacity of shovel bucket : 0.85 cum

Capacity of shovel bucket under heaped condition : 1.00 cum

Capacity of tipper : 5.00 cum

Lead for disposal of excavated soil : Upto 1 km

Speed for loaded tipper under canal excavation condition : 15 km / hr

Speed for empty tipper under canal excavation condition : 15 km / hr

Turning and unloading time : 2.00 min

Shovel digging and loading cycle per bucket : 20 sec

1. Quantity of excavation :

In-situ quantity / bucket for 20 % bulkage on unloading ( 1 /1.20 ) : 0.83 cum

In-situ quantity per load for 20 % bulkage of soil ( 5 /1.2 ) : 4.16 cum

Number of buckets per load ( 4.16 / 0.83 ) say : 5 buckets

Corrected Quantity of in-situ soil per load ( 5 x 0.83 ) say : 4.16 cum

Ideal cycle time for loading 5 buckets ( 5 x 20 / 60 ) : 1.67 min

The ideal cycle time for shovel requires spotting of a tipper within 1.67 minutes near the shovel.

However, in practice for canal excavation the space available may not permit positioning of the

tippers on either side of the shovel. Generally, one tipper has to move after loading to position

the next tipper for loading. Assuming one cycle time extra the corrected cycle time for the

shovel will be : ( 6 x 20 / 60 ) : 2.00 min

Round trip cycle time for tipper:

Corrected cycle time of shovel for digging & loading : 2.00 min

Time for ( av ) 0.75 km haulage under load ( 0.75 x 60 / 15 ) : 3.00 min

Time for turning and un-loading : 2.00 min

Time for ( av ) 0.75 km return trip ( 0.75 x 60 / 15 ) : 3.00 min

Time for turning and spotting : 0.50 min

Total : 10.50 min

No.of tippers to match corrected cycle time of shovel ( 10.50/ 2.00 ) : 5.25 Nos

Output of tipper / hr with 50 min working / hr ( 50 x 4.16 / 10.50 ) : 19.80 cum

Output for 5 tippers per day ( 5 x 19.80 x 8 ) : 792 cum

Further, assuming about 90 percent of excavation by deploying shovel and about 10 percent

excavation mainly for trimming the canal to final profile by manual labour the daily progress of

excavation will be : ( 792 / 0.9 ) say : 880 cum

Consider 880 cum for rate analysis.

2. Requirement of materials:

No materials involved in the work.

3. Requirement of machinery :

Deploy 0.85 cum capacity shovel for 8 hours for digging and loading 792 cum insitu soil.

Deploy 5 tippers of 5 cum capacity for 8 hours for disposal of 792 cum insitu soil.

CANAL AND ALLIED WORKS - DATA RATES

5

Page 8: Data rates-Canal Works

CANAL AND ALLIED WORKS

4. Requirement of workforce ( other than machinery crew ) :

Average output of 1 heavy & 1 light mazdoor assumed at 5 cum / day for trimming and disposal.

Deploy 18 heavy and 18 light mazdoors for trimming and disposal of 88 cum soil.

Deploy 1 maistry.

RATE ANALYSIS UNIT : 880.00 cum

A. MATERIALS:

Sl No Unit Amount

in `.

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total cost of Materials : `: 0.00

B. MACHINERY:

Sl No Unit Amount

in `.

1 Shovel 0.85 cum capacity Hour 8.00 1322.00 10576.00

Fuel / Energy charges Hour 8.00 832.00 6656.00

2 Tippers 5 cum capacity ( 5 ) Nos Hour 40.00 309.00 12360.00

Fuel / Energy charges Hour 40.00 286.00 11440.00

Total `: 41032.00

Add for small Tools and Plants @ 1% `: 410.32

Add for Contractor's Profit on DPOL / Energy @ 10% `: 1809.60

Add for Contractor's Overheads @ 5% `: 2051.60

Total hire charges of Machinery : `: 45303.52

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Shovel Hour 8.00 128.00 1024.00

2 Crew for Tipper Hour 40.00 95.00 3800.00

3 Maistry Day 1.00 241.23 241.23

4 Heavy mazdoor Day 18.00 238.73 4297.14

5 Light mazdoor Day 18.00 237.23 4270.14

Total `: 13632.51

Add for small Tools and Plants @ 1% `: 136.33

Add for Contractor's Profit @ 10% `: 1363.25

Add for hidden cost on Labour @ 15% `: 2044.88

Add for Contractor's Overheads @ 5% `: 681.63

Total cost of Labour : `: 17858.59

ABSTRACT:

A. Cost of Materials `: 0.00

B. Hire charges of Machinery `: 45303.52

C. Cost of Labour `: 17858.59

TOTAL `: 63162.11

Description

Description Quantity Rate

Perticulars

in `.

Quantity Rate

Rate

in `.

6

in `.

Quantity

Page 9: Data rates-Canal Works

CANAL AND ALLIED WORKS

Add for other enabling works @ 1.00% `: 631.62

Total cost for 880.00 cum `: 63793.73

Rate per cum `:`:`:`: 72.49

Rate approved per cum `:`:`:`: 72.00

Note: For depth of cut exceeding 18 m from ground level increase the basic rate by 5 percent for the

quantity of excavation beyond 18 m depth.

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.2

ITEM: Excavation in all kinds of soil including boulders upto 0.60 m diameter ( 0.113 cum ) for field

channels, seating of embankment for field channels and placing the excavated stuff neatly for

formation of service road / field channel embankment as directed including cost of all materials,

machinery, labour, dressing bed and sides to required level and profile etc., complete with

lead upto 10 m and lift upto 2 m.

DATA:Capacity of shovel bucket : 0.50 cum

Capacity of shovel bucket under heaped condition : 0.57 cum

Lead for disposal of excavated soil : Upto 10 m

In view of shallow depth of digging for field channels the cycle time for digging and disposal by

shovel is assumed at 1.5 times the cycle time considered for canal.

Shovel digging and loading cycle per bucket ( 1.5 x 20 ) : 30 sec

1. Quantity of excavation :

In-situ qty / bucket for 15 % bulkage of soil ( 0.57 / 1.15 ) : 0.50 cum

Output of shovel with 50 min./ hr working ( 50 x 60 x 0.5 / 30 ) : 50 cum / hr

Daily output of excavation ( 8 x 50 ) : 400 cum

As the excavated soil is dumped by the side of field channel within the reach of shovel boom

no tippers are considered in the rate analysis for disposal of excavated soil.

Further, assuming about 90 percent of excavation by deploying shovel and about 10 percent

excavation mainly for trimming bed and sides of channels / trenches to final profile by manual

labour, the daily output will be : ( 400 / 0.90 ) say : 445 cum

Consider 445 cum for rate analysis.

2. Requirement of materials:

No materials involved in the work.

3. Requirement of machinery :

Deploy 0.5 cum capacity shovel for 8 hours for digging and loading 400 cum.

4. Requirement of workforce ( other than machinery crew ) :

Average output of 1 heavy & 1 light mazdoor assumed at 5 cum / day for trimming and disposal.

Deploy 9 heavy and 9 light mazdoors for trimming and disposing 45 cum soil.

Deploy 1 maistry.

RATE ANALYSIS UNIT : 445.00 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Contd

Perticulars RateQuantity

in `.

7

Page 10: Data rates-Canal Works

CANAL AND ALLIED WORKS

A. MATERIALS ( Contd ) :

Sl No Unit Amount

in `:

Contd

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total cost of Materials : `: 0.00

B. MACHINERY:

Sl No Unit Amount

in `:

1 Shovel 0.50 cum capacity Hour 8.00 799.00 6392.00

Fuel / Energy charges Hour 8.00 454.00 3632.00

Total `: 10024.00

Add for small Tools and Plants @ 1% `: 100.24

Add for Contractor's Profit on DPOL / Energy @ 10% `: 363.20

Add for Contractor's Overheads @ 5% `: 501.20

Total hire charges of Machinery : `: 10988.64

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Shovel Hour 8.00 128.00 1024.00

2 Maistry Day 1.00 241.23 241.23

3 Heavy mazdoor Day 9.00 238.73 2148.57

4 Light mazdoor Day 9.00 237.23 2135.07

Total `: 5548.87

Add for small Tools and Plants @ 1% `: 55.49

Add for Contractor's Profit @ 10% `: 554.89

Add for hidden cost on Labour @ 15% `: 832.33

Add for Contractor's Overheads @ 5% `: 277.44

Total cost of Labour : `: 7269.02

ABSTRACT:

A. Cost of Materials `: 0.00

B. Hire charges of Machinery `: 10988.64

C. Cost of Labour `: 7269.02

TOTAL `: 18257.66

Add for other enabling works @ 1.00% `: 182.58

Total cost for 445.00 cum `: 18440.24

Rate per cum `:`:`:`: 41.44

Rate approved per cum `:`:`:`: 41.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.3

ITEM: Excavation in soft rock without blasting including boulders upto 0.6 m diameter ( 0.113 cum )

for canal, seating of embankment, filter drain / catch water drains etc., and placing the

excavated soft rock neatly in dump area or for formation of service road as directed including

cost of all materials, machinery,labour, dressing bed and sides to required level and profile etc.,

Perticulars

QuantityDescription

in `.

Description Rate

Quantity

Rate

in `.

Rate

in `.

Quantity

8

Page 11: Data rates-Canal Works

CANAL AND ALLIED WORKS

complete with lead upto 1 km and depth of cut upto 18 m.

DATA:Capacity of shovel bucket : 0.85 cum

Capacity of shovel bucket under heaped condition : 1.00 cum

Capacity of tipper : 5.00 cum

Lead for disposal of excavated soft rock : Upto 1 km

Speed for loaded tipper under canal excavation condition : 15 km / hr

Speed for empty tipper under canal excavation condition : 15 km / hr

Turning and unloading time : 2.00 min

Shovel digging and loading cycle per bucket : 30 sec

1. Quantity of excavation :

In-situ qty / bucket for 30 % bulkage on unloading : 0.77 cum

In-situ quantity / load for 5 cum of soft rock ( 5 / 1.30 ) : 3.85 cum

Number of buckets per load ( 3.85 / 0.77 ) say : 5 buckets

Ideal cycle time for loading 5 buckets ( 5 x 30 / 60 ) : 2.50 min

The ideal cycle time for shovel requires spotting of a tipper within 2.50 minutes near the shovel.

However, in practice for dam or canal excavation the space available may not permit positioning

of tippers on either side of the shovel. Generally one tipper has to move after loading to position

the next tipper for loading. Assuming one cycle time extra the corrected cycle time for digging

and loading one tipper by shovel will be : ( 6 x 30 / 60 ) 3.00 min

Round trip cycle time for tipper:

Corrected cycle time of shovel for digging & loading : 3.00 min

Time for ( av ) 0.75km haulage under load ( 0.75 x 60 / 15 ) : 3.00 min

Time for turning and un-loading : 2.00 min

Time for average 0.75 km return trip ( 0.75 x 60 / 15 ) : 3.00 min

Time for turning and spotting : 0.50 min

Total : 11.50 min

No.of tippers to match corrected cycle time of shovel ( 11.50/ 3.00 ) say : 3.83 Nos

Output of tipper / hr with 50 min working / hr ( 50 x 3.85 / 11.50 ) : 16.74 cum

Output for 4 tippers per day ( 3.83 x 16.74 x 8 ) say : 513 cum

Further, assuming about 90 percent of excavation by deploying shovel and about 10 percent

excavation mainly for trimming of bed / sides to final profile by manual labour the daily output

will be : ( 513 / 0.9 ) say : 570 cum

Consider 570 cum for rate analysis.

2. Requirement of materials:

No materials involved in the work.

3. Requirement of machinery :

Deploy 0.85 cum capacity shovel for 8 hours for digging and loading 513 cum.

Deploy 4 tippers of 5 cum capacity for disposal of 513 cum.

4. Requirement of workforce ( other than machinery crew ) :

Output of 1crowbarman, 1 heavy and 1 light mazdoor assumed at 5 cum per day for trimming.

Deploy 11 heavy and 11 light mazdoors for trimming and disposal of 57 cum soft rock.

Deploy 11 crowbarman for trimming.

Deploy 1 maistry.

9

Page 12: Data rates-Canal Works

CANAL AND ALLIED WORKS

RATE ANALYSIS UNIT : 570.00 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total cost of Materials : `: 0.00

B. MACHINERY:

Sl No Unit Amount

in `:

1 Shovel 0.85 cum capacity Hour 8.00 1322.00 10576.00

Fuel / Energy charges Hour 8.00 832.00 6656.00

2 Tippers 5 cum capacity ( 4 ) Nos Hour 32.00 309.00 9888.00

Fuel / Energy charges Hour 32.00 286.00 9152.00

Total `: 36272.00

Add for small Tools and Plants @ 1% `: 362.72

Add for Contractor's Profit on DPOL / Energy @ 10% `: 1580.80

Add for Contractor's Overheads @ 5% `: 1813.60

Total hire charges of Machinery : `: 40029.12

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Shovel Hour 8.00 128.00 1024.00

2 Crew for Tipper Hour 32.00 95.00 3040.00

3 Maistry Day 1.00 241.23 241.23

4 Crowbarman Day 11.00 239.73 2637.03

5 Heavy mazdoor Day 11.00 238.73 2626.03

6 Light mazdoor Day 11.00 237.23 2609.53

Total `: 12177.82

Add for small Tools and Plants @ 1% `: 121.78

Add for Contractor's Profit @ 10% `: 1217.78

Add for hidden cost on Labour @ 15% `: 1826.67

Add for Contractor's Overheads @ 5% `: 608.89

Total cost of Labour : `: 15952.94

ABSTRACT:

A. Cost of Materials `: 0.00

B. Hire charges of Machinery `: 40029.12

C. Cost of Labour `: 15952.94

TOTAL `: 55982.06

Add for other enabling works @ 1.00% `: 559.82

Total cost for 570.00 cum `: 56541.88

Rate per cum `:`:`:`: 99.20

Rate approved per cum `:`:`:`: 99.00

Perticulars

Description

Rate

Rate

in `.

in `.

Rate

in `.

Description

Quantity

Quantity

Quantity

10

Page 13: Data rates-Canal Works

CANAL AND ALLIED WORKS

Note: For depth of cut exceeding 18 m from ground level increase the basic rate by 5 percent for the

quantity of excavation beyond 18 m depth.

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.4

ITEM: Excavation in soft rock without blasting including boulders upto 0..6 m diameter ( 0..113 cum)

for field channels, seating of embankment for field channels etc., and placing the excavated

soft rock neatly for formation of service road as directed including cost of all materials,

machinery, labour, dressing bed and sides to required level and profile etc., complete with

lead upto 10 m and lift upto 2 m.

DATA:Capacity of shovel bucket : 0.50 cum

Capacity of shovel bucket under heaped condition : 0.57 cum

Lead for disposal of excavated soil : Upto 10 m

In view of shallow depth of digging for field channels the cycle time for digging and disposal by

shovel is assumed at 1.5 times the cycle time considered for canal.

Shovel digging and loading cycle per bucket ( 1.5 x 30 ) : 45 sec

1. Quantity of excavation :

In-situ qty per bucket for 25 % bulkage of soil ( 0.57 / 1.25 ) : 0.45 cum

Output of shovel with 50 min./ hr working ( 50 x 60 x 0.45 / 45 ) : 30 cum / hr

Daily output of excavation ( 8 x 30 ) say : 240 cum

Further, assuming about 90 percent of excavation by deploying shovel and about 10 percent

excavation mainly for trimming the canal to final profile by manual labour, the daily progress of

excavation in soft rock will be : ( 240 / 0.9 ) say : 265 cum

Consider 265 cum for rate analysis.

2. Requirement of materials:

No materials involved in the work.

3. Requirement of machinery :

Deploy 0.85 cum capacity shovel for 8 hours for digging and loading 240 cum.

4. Requirement of workforce ( other than machinery crew ) :

Output of 1 crowbarman, 1 heavy & 1 light mazdoor assumed at 5 cum per day.

Deploy 5 crowbarman, 5 heavy and 5 light mazdoors for trimming and disposal of 25 cum.

RATE ANALYSIS UNIT : 265.00 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total cost of Materials : `: 0.00

Rate

in `.

11

Perticulars Quantity

Page 14: Data rates-Canal Works

CANAL AND ALLIED WORKS

B. MACHINERY:

Sl No Unit Amount

in `:

1 Shovel 0.50 cum capacity Hour 8.00 799.00 6392.00

Fuel / Energy charges Hour 8.00 454.00 3632.00

Total `: 10024.00

Add for small Tools and Plants @ 1% `: 100.24

Add for Contractor's Profit on DPOL / Energy @ 10% `: 363.20

Add for Contractor's Overheads @ 5% `: 501.20

Total hire charges of Machinery : `: 10988.64

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Shovel Hour 8.00 128.00 1024.00

2 Maistry Day 1.00 241.23 241.23

3 Crowbarman Day 5.00 239.73 1198.65

4 Heavy mazdoor Day 5.00 238.73 1193.65

5 Light mazdoor Day 5.00 237.23 1186.15

Total `: 4843.68

Add for small Tools and Plants @ 1% `: 48.44

Add for Contractor's Profit @ 10% `: 484.37

Add for hidden cost on Labour @ 15% `: 726.55

Add for Contractor's Overheads @ 5% `: 242.18

Total cost of Labour : `: 6345.22

ABSTRACT:

A. Cost of Materials `: 0.00

B. Hire charges of Machinery `: 10988.64

C. Cost of Labour `: 6345.22

TOTAL `: 17333.86

Add for other enabling works @ 1.00% `: 173.34

Total cost for 265.00 cum `: 17507.20

Rate per cum `:`:`:`: 66.06

Rate approved per cum `:`:`:`: 66.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.5

ITEM: Excavation in soft rock requiring blasting including boulders above 0.6 m upto 1..2 m dia.

for canal, seating of embankment, filter drain / catch water drains etc., and placing the

excavated rock in dump area or for formation of service road as directed including cost of all

materials, machinery, labour, dressing bed and sides to required level and profile etc.,complete

with lead upto 1 km and depth of cut upto 18 m.

DATA:Capacity of shovel bucket : 0.85 cum

Capacity of shovel bucket under heaped condition : 1.00 cum

Capacity of tipper : 5.00 cum

Lead for disposal of excavated soft rock : Upto 1 km

Speed for loaded tipper under canal excavation condition : 15 km / hr

Speed for empty tipper under canal excavation condition : 15 km / hr

12

Description

Description

in `.

in `.

Rate

RateQuantity

Quantity

Page 15: Data rates-Canal Works

CANAL AND ALLIED WORKS

Turning and unloading time : 2.00 min

Shovel digging and loading cycle per bucket : 40 sec

1. Quantity of excavation :

In-situ qty / bucket for 35 % bulkage on unloading ( 1 / 1.35 ) : 0.74 cum

In-situ quantity / load for 5 cum of soft rock ( 5 / 1.35 ) : 3.70 cum

Number of buckets per load ( 3.70 / 0.74 ) say : 5 buckets

Ideal cycle time for loading 5 buckets ( 5 x 40 / 60 ) : 3.33 min

The ideal cycle time for shovel requires spotting of a tipper within 3.33 minutes near the shovel.

However, in practice for dam or canal excavation the space available may not permit positioning

of tippers on either side of the shovel. Generally one tipper has to move after loading to position

the next tipper for loading. Assuming one cycle time extra the corrected cycle time for digging

and loading one tipper by shovel will be : ( 6 x 40 / 60 ) : 4.00 min

Round trip cycle time for tipper:

Corrected cycle time of shovel for digging & loading : 4.00 min

Time for ( av ) 0.75 km haulage under load ( 0.75 x 60 / 15 ) : 3.00 min

Time for turning and un-loading : 2.00 min

Time for average 0.75 km return trip ( 0.75 x 60 / 15 ) : 3.00 min

Time for turning and spotting : 0.50 min

Total : 12.50 min

No.of tippers to match corrected cycle time of shovel ( 12.50 / 4.00 ) : 3.12 Nos

Output of tipper / hr with 50 min working / hr ( 50 x 3.70 / 12.50 ) : 14.80 cum

Output for 3 tippers per day ( 3 x 14.80 x 8 ) say : 355 cum

Further, assuming about 90 percent of excavation by deploying shovel and about 10 percent

excavation mainly for trimming of bed and sides to final profile by manual the daily output

will be : ( 355 / 0.9 ) say : 395 cum

Consider 395 cum excavation in soft rock requiring blasting for rate analysis.

2. Drilling and Blasting :

Depth of drilling per hole : 1.40 m

Effective depth of pull : 1.25 m

Grid spacing of holes for soft rock requiring blasting depends on the nature of soft rock at any

perticular location. For the purpose of rate analysis holes at average spacing of 1.5 times the

spacing considered for hard rock is assumed.

Grid spacing of holes : 1.50 x 2.00 m

Area of excavation for 395 cum ( 395 / 1.25 ) : 316 sqm

Nos. of holes for 316 sqm area 316 / ( 1.5 x 2.0 ) : 105 Nos.

Depth of drilling for 105 holes ( 105 x 1.4 ) say : 147.00 m

Add for secondary blasting LS : 3.00 m

Total depth of drilling : 150 m

Rate of drilling in soft rock per hour : 12 m

With 50 min / hour working rate of drilling ( 12 x 50 / 60 ) : 10 m

Time required for drilling with 2 jack hammers ( 150 / 2 / 10 ) : 7.50 hours

3. Requirement of materials :

Jack hammer drill rod : 150 m drilling

Quantity of Explosive ( Kelvex-220 ) at 0.2 kg / cum ( 395 x 0.2 ) : 79 kg

Explosive for secondary blasting LS : 1 kg

Ordinary detonators for secondary blasting 5 holes : 5 Nos.

Electric detonators at 1 per hole for main blast : 105 Nos.

Fuse coil : 175 Rm

4. Requirement of machinery :

Deploy 0.85 cum capacity shovel for 8 hours for digging and loading 240 cum.

13

Page 16: Data rates-Canal Works

CANAL AND ALLIED WORKS

Deploy 3 tippers 5 cum capacity for 8 hours for disposal of 240 cum.

Deploy 1 air compressor 8.5 cmm capacity for 7.5 hours.

Deploy 2 jack hammers for 7.5 hours for drilling.

5. Requirement of workforce ( other than machinery crew ) :

Output of 1 heavy & 1 light mazdoor assumed at 5 cum per day for trimming and disposal.

Deploy 2 crowbarman, 2 stone breaker, 8 heavy and 8 light mazdoors for 40 cum.

Deploy 1 blaster and 1 blasting helper for loading and blasting. Deploy 1 maistry for supervision.

6. Use rate of materials :

Cost of drill rod 1.5 m long @ `: 4395.00 / Each `: 4395.00

Life of drill rod for drilling in soft rock with reconditioning : 200 m

Use rate of drill rod per Rm drilling ( cost / life ) `: 21.98

Length of air hose for drilling for each jack hammer : 50 m

Cost of 25 mm dia air hose 50 m @ `: 200.00 / Rm `: 10000.00

Life of air hose : 800 hours

Use rate of 25 mm dia air hose per hr ( cost / life ) `: 12.50

RATE ANALYSIS UNIT : 395.00 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 Use rate of Jack hammer drill rod 1.5 m Rm 150.00 21.98 3296.25

Reconditioning charges @ 10 % 329.63

2 Use rate of 50 m air hose 2 Nos Hour 15.00 12.50 187.50

3 Explosive small dia ( Kelvex-220 ) kg 80.00 60.00 4800.00

4 Ordinary detonators Nos 5.00 7.00 35.00

5 Electric detonators Nos 105.00 12.00 1260.00

6 Fuse coil Rm 175.00 9.00 1575.00

7 Sundries LS 3.00 44.00 132.00

Total `: 11615.38

Add for small Tools and Plants @ 1% `: 116.15

Add for Contractor's Profit @ 10% `: 1161.54

Add for Contractor's Overheads @ 5% `: 580.77

Total cost of Materials : `: 13473.84

B. MACHINERY:

Sl No Unit Amount

in `:

1 Shovel 0.85 cum capacity Hour 8.00 1322.00 10576.00

Fuel / Energy charges Hour 8.00 832.00 6656.00

2 Tippers 5 cum capacity 3 Nos. Hour 24.00 309.00 7416.00

Fuel / Energy charges Hour 24.00 286.00 6864.00

3 Air compressor 8.5 cmm ( diesel ) Hour 7.50 223.00 1672.50

Fuel / Energy charges Hour 7.50 851.00 6382.50

4 Jack hammers 2 Nos. Hour 15.00 16.00 240.00

Fuel / Energy charges Hour 15.00 8.00 120.00

Total `: 39927.00

Add for small Tools and Plants @ 1% `: 399.27

Add for Contractor's Profit on DPOL / Energy @ 10% `: 2002.25

Add for Contractor's Overheads @ 5% `: 1996.35

Total hire charges of Machinery : `: 44324.87

Description

Rate

14

in `.

Rate

in `.

Perticulars

Quantity

Quantity

Page 17: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Shovel Hour 8.00 128.00 1024.00

2 Crew for Tipper Hour 24.00 95.00 2280.00

3 Crew for Air compressor Hour 7.50 121.00 907.50

4 Crew for Jack hammer Hour 15.00 188.00 2820.00

5 Maistry Day 1.00 241.23 241.23

6 Blaster Day 1.00 243.23 243.23

7 Helper blaster Day 1.00 239.73 239.73

8 Crowbarman Day 2.00 239.73 479.46

9 Stone breaker Day 2.00 241.73 483.46

10 Heavy mazdoor Day 8.00 238.73 1909.84

11 Light mazdoor Day 8.00 237.23 1897.84

Total `: 12526.29

Add for small Tools and Plants @ 1% `: 125.26

Add for Contractor's Profit @ 10% `: 1252.63

Add for hidden cost on Labour @ 15% `: 1878.94

Add for Contractor's Overheads @ 5% `: 626.31

Total cost of Labour : `: 16409.44

ABSTRACT:

A. Cost of Materials `: 13473.84

B. Hire charges of Machinery `: 44324.87

C. Cost of Labour `: 16409.44

TOTAL `: 74208.14

Add for other enabling works @ 1.00% `: 742.08

Total cost for 395.00 cum `: 74950.23

Rate per cum `:`:`:`: 189.75

Rate approved per cum `:`:`:`: 190.00

Note: For depth of cut exceeding 18 m from ground level increase the basic rate by 5 percent for the

quantity of excavation beyond 18 m depth.

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.6.1

ITEM: Excavation in hard rock of all toughness by blasting including boulders above 0.6 m dia.

( 0.113 cum ) for canals, cut-off trench of embankment, filter / catch water drains etc.,

minimising damage to side slopes of canal in water prism area by adopting any one or

combination of line drilling /pre-splitting /smooth blasting techniques and placing the excavated

rock neatly in approved dump area as directed including cost of all materials,machinery, labour,

levelling bed etc., complete with lead upto 1 km and depth of cut upto 18 m.

DATA:Excavation for canal in hard rock can be by using jack hammers or by using waggon drills or

by combination of both depending on the depth of cut, width of canal and side slope. In case of

waggon drill the rate of drilling will be faster and yeild per hole will be more due to wider spacing

of holes. For jack hammer drill the yeild per hole will be less due to closer spacing of holes.

As both the systems have advantages as well as disadvantages it is proposed to work out rates

using both the systems and include average rate in the Schedule of Rates.

Description

in `.

Quantity Rate

15

Page 18: Data rates-Canal Works

CANAL AND ALLIED WORKS

I. By using Jack hammers for drilling :

Assume 10.80 m width of canal at the bench level and 1.25 m average depth of cutting.

Assume side slopes of 0.25 horizontal to 1 vertical.

Generally, the length of canal bench to be excavated per blast shall not be more than 7 m to

avoid tight muck pile requiring higher digging time for shovel.

Sectional area of excavation ( 10.80 + 10.175 ) x 0.5 x 1.25 : 13.11 sqm

Consider 7 burden distance for excavation per blast.

Number of rows considered : 7 No.

Length of canal for 7 rows ( 7 x 1.00 ) : 7.00 m

Quantity of excavation for 7 m length ( 13.11 x 7.00 ) say : 92.00 cum

10.80 m

8.4 m

1 1.25 m

0.25

10.175 m

--

1.0 m

1.2 m

7.00 m

Free face

SKETCH SHOWING DRILLING & BLASTING PATTERN

1. Drilling and Blasting:

Consider drilling by Jack hammers and mucking by combination of Shovel and Tippers.

The burden ( distance of hole from free face of excavation ) is considered at 25 to 30 times dia

of hole and spacing of holes is considered at 1.20 to 1.25 times burden.

Burden distance for 32 mm dia jack hammer holes ( 0.032 x 30 ) say : 1.00 m

Spacing of holes ( 0.032 x 30 x 1.25 ) : 1.20 m

Grid spacing of holes for 32 mm dia jack hammer holes : 1.00 x 1.20 m

Depth of drilling per hole : 1.40 m

Effective depth of pull considering 10 % sub-drilling : 1.25 m

Rate of drilling by jack hammer in hard rock per hour : 8.00 m

Rate of drilling per hour with 50 min / hour working ( 8 x 50 / 60 ) say : 6.5 m

No.of holes in 7 rows @1.2 m interval staggered ( 4x8 + 3x9 + 16 ) : 75 Nos

Length of drilling for 75 holes @ 1.4 m per hole ( 75 x 1.4 ) : 105 m

Add drilling for secondary blasting for 5% quantity @ 0.6 m / cum say : 3 m

Total : 108.00 m

16

Page 19: Data rates-Canal Works

CANAL AND ALLIED WORKS

Time for drilling 108 m for 2 jack hammers ( 108 / 2 / 6.5 ) : 8.30 hours

Drilling and Blasting pattern :

Pattern of holes : Staggered

Hole initiation : Bottom

Initiation system : Ele detonators

Initiation pattern : All rows

2. Disposal of excavated rock :

Quantity of excavation ( in-situ ) : 92.00 cum

Capacity of shovel bucket : 0.85 cum

Capacity of shovel bucket under heaped condition : 1.00 cum

Capacity of tipper : 5.00 cum

Lead for disposal of excavated rock : Upto 1 km

Speed for loaded tipper under canal excavation condition : 15 km / hr

Speed for empty tipper under canal excavation condition : 15 km / hr

Turning and unloading time : 2.00 min

Shovel digging and loading cycle per bucket : 45 sec

In-situ qty / bucket for 40 % bulkage of hard rock ( 1 /1.40 ) : 0.71 cum

In-situ qty per load for 40 % bulkage of hard rock ( 5 /1.40 ) : 3.57 cum

Number of buckets per load ( 3.57 / 0.71 ) say : 5 buckets

Ideal cycle time for loading 5 buckets ( 5 x 45 / 60 ) : 3.75 min

The ideal cycle time for shovel requires spotting of a tipper within 3.75 minutes near the shovel.

However, in practice for dam or canal excavation the space available may not permit positioning

of tippers on either side of the shovel. Generally one tipper has to move after loading to position

next tipper for loading. Assuming one loading cycle extra, the corrected cycle time for shavel

will be ( 6 x 45 / 60 ) 4.50 min

Round trip cycle time for tipper:

Cycle time of shovel for digging & loading : 4.50 min

Time for (av ) 0.75 km haulage under load ( 0.75 x 60 / 15 ) : 3.00 min

Time for turning and un-loading : 2.00 min

Time for average 0.75 km return trip ( 0.75 x 60 / 15 ) : 3.00 min

Time for turning and spotting : 0.50 min

Total : 13.00 min

No.of tippers to match corrected cycle time of shovel ( 13.00 / 4.50) : 2.9 Nos

Output of tipper / hr with 50 min working / hr ( 50 x 3.57 / 13.00 ) : 13.73 cum

Deploy 0.9 cum shovel and 3 tippers for disposal of excavated rock.

Output of 1 shovel & 3 tippers per hour ( in-situ qty ) ( 13.73 x 2.9 ) : 39.80 cum

Out of the total blasted rock some residual muck at the bed needs to be removed by deploying

manual labour. Assume residual muck at bed at 0.10 cum / sqm of bed area.

Quantity of muck to be disposed by shovel ( 92 - 0.1 x 70 ) 85 cum

Time for disposal of 85 cum by shovel ( 85 / 39.80 ) : 2.2 hours

For levelling 85 cum muck in dump yard deploy 1 dozer for : 0.25 hour

Quantity of muck to be disposed by manual labour ( 92 - 85 ) 7 cum

3. Requirement of materials :

Jack hammer drill rod : 108 m drilling

Quantity of Explosive ( Kelvex-220 ) at 0.3 kg / cum ( 92 x 0.3 ) : 27.60 kg

Add for secondary blasting @ 0.2 kg / cum ( 92 x 0.05 x 0.2 ) : 0.90 kg

Total : 28.50 kg

Ordinary detonators for secondary blasting 8 holes of 0.6 m each : 8 Nos.

Electric detonators @ 1 per hole for main blast : 75 Nos

Detonating fuse coil : 120 Rm

17

Page 20: Data rates-Canal Works

CANAL AND ALLIED WORKS

4. Requirement of machinery :

Deploy 0.85 cum capacity shovel for 2.2 hours for digging and loading 85 cum.

Deploy 3 tippers 5 cum capacity for 2.2 hours for disposal of 85 cum.

Deploy 1 air compressor 8.5 cmm capacity for 8.5 hours.

Deploy 2 jack hammers for 8.5 hours for drilling.

Deploy 1 angle dozer for 0.25 hour for levelling muck in dump area.

5. Requirement of workforce ( other than machinery crew ) :

Deploy 1 Crowbarman, 1 Stone breaker for 1 day for levelling bed.

Deploy 2 heavy and 2 light mazdoors for disposal of 9 cum residual muck at bed level and for

other miscellaneous works.

Deploy 1 blaster and 1 blasting helper for loading and blasting.

Deploy 1 maistry.

6. Use rate of materials :

Cost of drill rod 1.5 m long @ `: 4395.00 / Each `: 4395.00

Life of drill rod for drilling in hard rock with reconditioning : 150 m

Use rate of drill rod per Rm drilling ( cost / life ) `: 29.30

Length of air hose for drilling for each jack hammer : 50 m

Cost of 25 mm dia 50 m air hose @ `: 200.00 / Rm `: 10000.00

Life of air hose : 800 hours

Use rate of 25 mm dia air hose per hour ( cost / life ) `: 12.50

RATE ANALYSIS UNIT : 92.00 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 Use rate of Jack hammer drill rod 1.5 m Rm 108.00 29.30 3164.40

Reconditioning charges @ 10 % 316.44

2 Use rate of 50 m air hose 2 Nos. Hour 17.00 12.50 212.50

3 Explosive small dia. (Kelvex-220 ) kg 28.50 60.00 1710.00

4 Ordinary detonators Nos 8.00 7.00 56.00

5 Electric detonators Nos 75.00 12.00 900.00

6 Fuse coil Rm 120.00 9.00 1080.00

7 Sundries LS 2.00 44.00 88.00

Total `: 7527.34

Add for small Tools and Plants @ 1% `: 75.27

Add for Contractor's Profit @ 10% `: 752.73

Add for Contractor's Overheads @ 5% `: 376.37

Total cost of Materials : `: 8731.71

B. MACHINERY:

Sl No Unit Amount

in `:

1 Shovel 0.85 cum capacity Hour 2.20 1322.00 2908.40

Fuel / energy charges Hour 2.20 832.00 1830.40

2 Angle dozer 90 hp Hour 0.25 1273.00 318.25

Fuel / Energy charges Hour 0.25 582.00 145.50

3 Tippers 5 cum capacity 3 Nos. Hour 6.60 309.00 2039.40

Fuel / Energy charges Hour 6.60 286.00 1887.60

Quantity

Perticulars

18

Description

in `.

in `.

Rate

RateQuantity

Page 21: Data rates-Canal Works

CANAL AND ALLIED WORKS

B. MACHINERY ( Contd ) :

Sl No Unit Amount

in `:

Contd

4 Air compressor 8.5 cmm ( diesel ) 1 Nos Hour 8.50 223.00 1895.50

Fuel / Energy charges Hour 8.50 851.00 7233.50

5 Jack hammers 2 Nos. Hour 17.00 16.00 272.00

Fuel / Energy charges Hour 17.00 8.00 136.00

Total `: 18666.55

Add for small Tools and Plants @ 1% `: 186.67

Add for Contractor's Profit on DPOL / Energy @ 10% `: 1123.30

Add for Contractor's Overheads @ 5% `: 933.33

Total hire charges of Machinery : `: 20909.84

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Shovel Hour 2.20 128.00 281.60

2 Crew for Dozer Hour 0.25 128.00 32.00

3 Crew for Tipper Hour 6.60 95.00 627.00

4 Crew for Air compressor Hour 8.50 121.00 1028.50

5 Crew for Jack hammer Hour 17.00 188.00 3196.00

6 Maistry Day 1.00 241.23 241.23

7 Blaster Day 1.00 243.23 243.23

8 Helper blaster Day 1.00 239.73 239.73

9 Crowbarman Day 1.00 239.73 239.73

10 Stone breaker Day 1.00 241.73 241.73

11 Heavy mazdoor Day 2.00 238.73 477.46

12 Light mazdoor Day 2.00 237.23 474.46

Total `: 7322.67

Add for small Tools and Plants @ 1% `: 73.23

Add for Contractor's Profit @ 10% `: 732.27

Add for hidden cost on Labour @ 15% `: 1098.40

Add for Contractor's Overheads @ 5% `: 366.13

Total cost of Labour : `: 9592.70

ABSTRACT:

A. Cost of Materials `: 8731.71

B. Hire charges of Machinery `: 20909.84

C. Cost of Labour `: 9592.70

TOTAL `: 39234.26

Add for other enabling works @ 1.00% `: 392.34

Total cost for 92.00 cum `: 39626.60

Rate per cum `:`:`:`: 430.72

II. By using waggon drills for drilling :

Assume 12.70 m width of excavation at bench level and 5.40 m depth of cutting in hard rock.

Assume side slopes of 0.25 horizontal to 1 vertical.

Rate

19

Description

in `.

QuantityDescription Rate

Quantity

in `.

Page 22: Data rates-Canal Works

CANAL AND ALLIED WORKS

1. Drilling and Blasting:

Consider drilling by Waggon drill and mucking by combination of Shovel and Tippers.

For good fragmentation to facilitate easy loading by 0.85 cum capacity shovel the bench height

to burden ratio shall be more than 3.

The burden ( distance of hole from free face of excavation ) is considered at 20 times diameter

of hole and spacing of holes is considered at 1.25 times burden.

Burden distance for 100 mm dia holes ( 0.10 x 20 ) : 2.00 m

Spacing of holes at 1.25 times burden ( 0.10 x 20 x 1.25 ) : 2.50 m

Grid spacing of holes for 100 mm dia Waggon drill holes : 2.00 x 2.50 m

Consider 3 burden distance for excavation per blast.

Depth of drilling per hole : 6.00 m

Effective depth of pull considering 10 % sub-drilling say : 5.40 m

Rate of drilling in hard rock per hour by Waggon drill : 12.00 m

Rate of drilling per hour with 50 min per hour working ( 12 x 50 / 60 ) : 10 m

12.70 m

1

5.40 m

0.25

10.00 m

12.70 m

1

5.40 m

0.25

2.0 m

2.5 m

6.00 m

Free face

SKETCH SHOWING DRILLING & BLASTING PATTERN

Sectional area of excavation ( 12.70+10.00 ) x 0.5 x 5.40 : 61.29 sqm

Length of canal for excavation ( 3 x 2.00 ) : 6.00 m

Quantity of excavation for 6.0 m length ( 61.29 x 6.00 ) : 368 cum

No. of blast holes in 3 rows ( 2 x 5 + 1 x 6 + 2 x 4 ) : 24 holes

20

Page 23: Data rates-Canal Works

CANAL AND ALLIED WORKS

Length of drilling for 24 holes ( 11 x 6 + 13 x 6.2 ) say : 147 m

Drilling for secondary blasting for 5% qty @ 0.6 m / cum : 11.00 m

No.of blast holes for secondary blasting @ 0.6 m / hole ( 11 / 0.6 ) : 18 holes

Consider 2 waggon drills for drilling holes.

Time for drilling 147 m for 2 Waggon drill @ 10 m / hour : 7.33 hours

Consider 368 cum hard rock excavation for rate analysis.

2. Disposal of excavated rock :

Capacity of shovel bucket : 0.85 cum

Capacity of shovel bucket under heaped condition : 1.00 cum

Capacity of tipper : 5.00 cum

Lead for disposal of excavated rock rock : Upto 1 km

Speed for loaded tipper under canal excavation condition : 15 km / hr

Speed for empty tipper under canal excavation condition : 15 km / hr

Turning and unloading time : 2.00 min

Shovel digging and loading cycle per bucket : 45 sec

In-situ qty / bucket for 40 % bulkage of hard rock ( 1 / 1.40 ) : 0.71 cum

In-situ qty per load for 40 % bulkage of hard rock ( 5 / 1.40 ) : 3.57 cum

Number of buckets per load ( 3.57 / 0.71 ) say : 5 buckets

Ideal cycle time for loading 5 buckets ( 5 x 45 / 60 ) : 3.75 min

The ideal cycle time for shovel requires spotting of a tipper within 3.75 minutes near the shovel.

However, in practice for dam or canal excavation the space available may not permit positioning

of tippers on either side of the shovel. Generally one tipper has to move after loading to position

next tipper for loading. Assuming one loading cycle extra, the corrected cycle time for shovel

will be ( 6 x 45 / 60 ) 4.50 min

Round trip cycle time for tipper:

Cycle time of shovel for digging & loading : 4.50 min

Time for (av ) 0.75 km haulage under load ( 0.75 x 60 / 15 ) : 3.00 min

Time for turning and un-loading : 2.00 min

Time for average 0.75 km return trip ( 0.75 x 60 / 15 ) : 3.00 min

Time for turning and spotting : 0.50 min

Total : 13.00 min

No.of tippers to match corrected cycle time of shovel (13.00 / 4.50) say : 2.9 Nos

Output of tipper / hr with 50 min working / hr ( 50 x 3.57 / 13.00 ) : 13.73 cum

Output of 2.7 tippers per hour ( 13.73 x 2.9 ) : 39.80 cum

Out of the total blasted rock some residual muck at the bed needs to be removed by deploying

manual labour. Assume residual muck at bed at 0.10 cum / sqm of bed area.

Quantity of muck to be disposed by shovel ( 368 - 0.1 x 60 ) : 362 cum

Time required for disposal of 362 cum ( 362 / 39.80 ) say : 9 hours

For levelling 362 cum muck in dump yard deploy 1 dozer for : 1.00 hour

Quantity of muck to be disposed by manual labour ( 368 - 362 ) : 6 cum

3. Requirement of materials :

100 mm dia TC bit : 147 m drilling

Extension rods with sleeve : 147 m drilling

Jack hammer drill rod : 11 m drilling

Quantity of Explosive @ 0.5 kg / cum for 368 cum : 184.00 kg

Consider 20 % high strength ANFO booster for priming ANFO. : 37.00 kg

Consider 80 % ANFO mixed with diesel oil for colunm. : 147.00 kg

Diesel oil @ 180 ml per kg of ANFO : 27.00 ltrs

Quantity of Explosive @ 0.2 kg / cum for secondary blast : 4 kg

Ordinary detonators for secondary blasting : 18 Nos.

21

Page 24: Data rates-Canal Works

CANAL AND ALLIED WORKS

Detonating cord for 24 holes in 3 rows : 210 Rm.

Detonating fuse coil for secondary blasting : 20 Rm

4. Requirement of machinery :

Deploy 0.85 cum capacity shovel for 9 hours for digging and loading 362 cum.

Deploy 3 tippers 5 cum capacity for 9 hours for disposal of 362 cum.

Deploy 2 air compressors 8.5 cmm capacity for 7.5 hours.

Deploy 2 waggon drills for 7.5 hours for drilling main blast holes.

Deploy 1 air compressor 8.5 cmm capacity for 1 hour.

Deploy 2 jack hammers for 1 hour for drilling secondary blast holes.

Deploy 1 angle dozer for 1 hour for levelling muck in dump area.

5. Requirement of workforce ( other than machinery crew ) :

Deploy 1 Crowbarman, 1 Stone breaker for 1 day for levelling bed.

Deploy 2 heavy and 2 light mazdoors for disposal of 9 cum residual muck at bed level.

Deploy 1 blaster and 1 blasting helper for loading and blasting.

Deploy 1 maistry.

6. Use rate of materials :

Cost of T.C bit 100 mm dia @ `: 12185.00 / Each `: 12185.00

Life of drill bit for drilling in hard rock : 80 m

Use rate of T.C bit per Rm drilling ( Cost / Life ) `: 152.31

Cost of extn rod with sleeve 4.5 m @ `: 4190.00 / Rm `: 18855.00

Life of extension rod : 1500 m

Use rate of extension rod per Rm drilling ( Cost / Life ) `: 12.57

Cost of 1.5 m drill rod @ `: 4395.00 / Each `: 4395.00

Life of drill rod for drilling in hard rock with reconditioning : 150 m

Use rate of drill rod per Rm drilling ( Cost / Life ) `: 29.30

Length of air hose for drilling for each jack hammer : 50 m

Cost of 50 m air hose 25 mm @ `: 200.00 / Rm `: 10000.00

Life of air hose : 800 hours

Use rate of air hose per hr ( Cost / Life ) `: 12.50

Cost of 50 m air hose 50 mm dia @ `: 270.00 / Rm `: 13500.00

Life of air hose : 800 hours

Use rate of air hose per hr ( Cost / Life ) `: 16.88

RATE ANALYSIS UNIT : 368.00 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 Use rate of T.C bit 100 mm dia Rm 147.00 152.31 22389.94

2 Use rate of Extension rod with sleeve Rm 147.00 12.57 1847.79

3 Use rate of Jack hammer drill rod 1.5 m Rm 11.00 29.30 322.30

Reconditioning charges @ 10 % 32.23

4 Use rate of air hose for waggon drill Hour 15.00 16.88 253.13

Use rate of 25 m air hose for JH 2 Nos Hour 2.00 12.50 25.00

5 High strength ANFO booster kg 37.00 65.00 2405.00

6 ANFO kg 147.00 52.00 7644.00

7 Diesel oil ltr 27.00 55.00 1485.00

8 Explosive small dia ( Kelvex-220 ) kg 4.00 60.00 240.00

Contd

Quantity Rate

22

Perticulars

in `.

Page 25: Data rates-Canal Works

CANAL AND ALLIED WORKS

A. MATERIALS ( Contd ) :

Sl No Unit Amount

in `:

Contd

9 Ordinary detonators Nos 18.00 7.00 126.00

10 D-cord Rm 210.00 9.00 1890.00

11 Detonating fuse coil Rm 20.00 9.00 180.00

12 Sundries LS 5.00 44.00 220.00

Total `: 39060.38

Add for small Tools and Plants @ 1% `: 390.60

Add for Contractor's Profit @ 10% `: 3906.04

Add for Contractor's Overheads @ 5% `: 1953.02

Total cost of Materials : `: 45310.04

B. MACHINERY:

Sl No Unit Amount

in `:

1 Tippers 5 cum capacity Hour 27.00 309.00 8343.00

Fuel / Energy charges Hour 27.00 286.00 7722.00

2 Shovel 0.85 cum capacity Hour 9.00 1322.00 11898.00

Fuel / Energy charges Hour 9.00 832.00 7488.00

3 Angle dozer Hour 1.00 1273.00 1273.00

Fuel / Energy charges Hour 1.00 582.00 582.00

4 Air compressor 8.5 cmm ( diesel ) Hour 16.00 223.00 3568.00

Fuel / Energy charges Hour 16.00 851.00 13616.00

5 Waggon drill Hour 15.00 239.00 3585.00

Fuel / Energy charges Hour 15.00 14.00 210.00

6 Jack hammer Hour 2.00 16.00 32.00

Fuel / Energy charges Hour 2.00 8.00 16.00

Total `: 58333.00

Add for small Tools and Plants @ 1% `: 583.33

Add for Contractor's Profit on DPOL / Energy @ 10% `: 2963.40

Add for Contractor's Overheads @ 5% `: 2916.65

Total hire charges of Machinery : `: 64796.38

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Tipper Hour 27.00 95.00 2565.00

2 Crew for Shovel Hour 9.00 128.00 1152.00

3 Crew for Dozer Hour 1.00 128.00 128.00

4 Crew for Air compressor Hour 16.00 121.00 1936.00

5 Crew for Waggon drill Hour 15.00 150.00 2250.00

6 Crew for Jack hammer Hour 2.00 188.00 376.00

7 Maistry Day 1.00 241.23 241.23

8 Blaster Day 1.00 243.23 243.23

9 Helper blaster Day 1.00 239.73 239.73

10 Crowbarman Day 1.00 239.73 239.73

11 Stone breaker Day 1.00 241.73 241.73

Contd

Description

23

RateQuantity

QuantityPerticulars

Description

in `.

Quantity

in `.

Rate

Rate

in `.

Page 26: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR ( Contd ) :

Sl No Unit Amount

in `:

Contd

12 Heavy mazdoor Day 2.00 238.73 477.46

13 Light mazdoor Day 2.00 237.23 474.46

Total `: 10564.57

Add for small Tools and Plants @ 1% `: 105.65

Add for Contractor's Profit @ 10% `: 1056.46

Add for hidden cost on Labour @ 15% `: 1584.69

Add for Contractor's Overheads @ 5% `: 528.23

Total cost of Labour : `: 13839.59

ABSTRACT:

A. Cost of Materials `: 45310.04

B. Hire charges of Machinery `: 64796.38

C. Cost of Labour `: 13839.59

TOTAL `: 123946.01

Add for other enabling works @ 1.00% `: 1239.46

Total cost for 368.00 cum `: 125185.47

Rate per cum `:`:`:`: 340.18

Assuming use of Jack hammers & Waggon drills in 50 : 50 ratio

Rate per cum `:`:`:`: 385.45

Rate approved per cum `:`:`:`: 385.00

Note: For depth of cut exceeding 18 m from ground level increase the basic rate by 5 percent for the

quantity of excavation beyond 18 m depth.

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.6.2

ITEM: Excavation in hard rock of all toughness including boulders above 0.6 m diameter(0.113 cum)

for canals, cut-off trench of embankments, filter / catch water drains and other appurtenent

structures by approved controlled blasting methods including control of vibrations by use

of delay detonators and control of fly-rocks by muffling arrangements and adopting only jack

hammers for drilling holes and minimising damage to side slopes of canal in water prism area

by adopting any one or combination of line drilling / pre-splitting / smooth blasting techniques

including cost of all materials, machinery, labour, placing excavated rock neatly in approved

dump area as directed etc., complete with lead upto 1 km and depth of cut upto 18 m.

DATA:Work requires:

- use of delay detonators to reduce ground vibrations.

- covering blasting area with chain link mesh or waste conveyor belts or waste tyres and sand

bags to prevent flying of rock fragments during blasting.

Drilling and Blasting pattern :

Pattern of holes : Staggered

Hole initiation : Bottom

Initiation system : Short delay detonators

Delay system : 25 ms interval

Initiation pattern : Straight line row by row

RateQuantity

24

in `.

Description

Page 27: Data rates-Canal Works

CANAL AND ALLIED WORKS

Assume 10.80 m width of canal at the bench level and 1.25 m average depth of cutting.

Assume side slopes of 0.25 horizontal to 1 vertical.

Generally, the length of canal bench to be excavated per blast shall not be more than 7 m to

avoid tight muck pile requiring higher digging time for shovel.

Sectional area of excavation ( 10.80 + 10.175 ) x 0.5 x 1.25 : 13.11 sqm

Consider 7 burden distance for excavation per blast.

Number of rows considered : 7 No.

Length of canal for 7 rows ( 7 x 1.00 ) : 7.00 m

Quantity of excavation for 7 m length ( 13.11 x 7.00 ) say : 92.00 cum

8.4 m

1 1.25 m

0.25

10.175 m

-- 1.2 m

All detonators in this row are 150 ms delay type

1 m All detonators in this row are 125 ms delay type

1

All detonators in this row are 100 ms delay type

All detonators in this row are 75 ms delay type

7.0 m

All detonators in this row are 50 ms delay type

All detonators in this row are 25 ms delay type

All detonators in this row are 0 ms delay type

Free face

SKETCH SHOWING DRILLING & BLASTING PATTERN

1. Drilling and Blasting:

Consider drilling by Jack hammers and mucking by combination of Shovel and Tippers.

The burden ( distance of hole from free face of excavation ) is considered at 25 to 30 times dia

of hole and spacing of holes is considered at 1.20 to 1.25 times burden.

Burden distance for 32 mm dia jack hammer holes ( 0.032 x 30 ) say : 1.00 m

Spacing of holes ( 0.032 x 30 x 1.25 ) : 1.20 m

Grid spacing of holes for 32 mm dia jack hammer holes : 1.00 x 1.20 m

Depth of drilling per hole : 1.40 m

Effective depth of pull considering 10 % sub-drilling : 1.25 m

Rate of drilling by jack hammer in hard rock per hour : 6.00 m

25

Page 28: Data rates-Canal Works

CANAL AND ALLIED WORKS

Rate of drilling per hour with 50 min / hour working ( 6 x 50 / 60 ) say : 5 m

No.of holes in 7 rows @ 1.2 m interval ( 4 x 8 + 3 x 9 + 16 ) : 75 Nos

Length of drilling for 75 holes @ 1.4 m per hole ( 75 x 1.4 ) : 105 m

Add drilling for secondary blasting for 5% quantity @ 0.6 m / cum say : 3 m

Total : 108.00 m

Time for drilling 108 m for 2 jack hammers ( 108 / 2 / 5 ) : 10.80 hours

2. Muffling arrangements:

For controlling flying of rock fragments during blasting consider covering the blasting area with

20 guage 50 x 50 mm chain link mesh and sand bags.

10 % extra area of wire mesh is considered for overlaps.

Area of chain link mesh for controlled blast area ( 12 x 8 x 1.1) say : 106 sqm

No.of 30 to 40 kg sand bags at 1 per hole ( 75 x 1 ) : 75 Nos

Add 20 % extra for edges : 15 Nos

Total number of sand bags to cover the blasting area : 90 Nos

3. Disposal of excavated rock :

Quantity of excavation ( in-situ ) : 92.00 cum

Capacity of shovel bucket : 0.85 cum

Capacity of shovel bucket under heaped condition : 1.00 cum

Capacity of tipper : 5.00 cum

Lead for disposal of excavated rock rock : Upto 1 km

Speed for loaded tipper under canal excavation condition : 15 km / hr

Speed for empty tipper under canal excavation condition : 15 km / hr

Turning and unloading time : 2.00 min

Shovel digging and loading cycle per bucket : 45 sec

In-situ qty / bucket for 40 % bulkage of hard rock ( 1 /1.40 ) : 0.71 cum

In-situ qty per load for 40 % bulkage of hard rock ( 5 /1.40 ) : 3.57 cum

Number of buckets per load ( 3.57 / 0.71 ) say : 5 buckets

Ideal cycle time for loading 5 buckets ( 5 x 45 / 60 ) : 3.75 min

The ideal cycle time for shovel requires spotting of a tipper within 3.75 minutes near the shovel.

However, in practice for dam or canal excavation the space available may not permit positioning

of tippers on either side of the shovel. Generally one tipper has to move after loading to position

next tipper for loading. Assuming one loading cycle extra, the corrected cycle time for shavel

will be ( 6 x 45 / 60 ) 4.50 min

Round trip cycle time for tipper:

Cycle time of shovel for digging & loading : 4.50 min

Time for (av ) 0.75 km haulage under load ( 0.75 x 60 / 15 ) : 3.00 min

Time for turning and un-loading : 2.00 min

Time for average 0.75 km return trip ( 0.75 x 60 / 15 ) : 3.00 min

Time for turning and spotting : 0.50 min

Total : 13.00 min

No.of tippers to match corrected cycle time of shovel ( 13.00 / 4.50) : 2.9 Nos

Output of tipper / hr with 50 min working / hr ( 50 x 3.57 / 13.00 ) : 13.73 cum

Deploy 0.9 cum shovel and 3 tippers for disposal of excavated rock.

Output of 1 shovel & 3 tippers per hour ( in-situ qty ) ( 13.73 x 2.9 ) : 39.80 cum

Out of the total blasted rock some residual muck at the bed needs to be removed by deploying

manual labour. Assume residual muck at bed at 0.10 cum / sqm of bed area.

Quantity of muck to be disposed by shovel ( 92 - 0.1 x 70 ) 85 cum

Time for disposal of 85 cum by shovel ( 85 / 39.80 ) : 2.2 hours

26

Page 29: Data rates-Canal Works

CANAL AND ALLIED WORKS

For levelling 85 cum muck in dump yard deploy 1 dozer for : 0.25 hour

Quantity of muck to be disposed by manual labour ( 92 - 85 ) 7 cum

4. Requirement of materials :

Jack hammer drill rod : 108 m drilling

Quantity of Explosive ( Kelvex-220 ) at 0.3 kg / cum ( 92 x 0.3 ) : 27.60 kg

Add for secondary blasting @ 0.2 kg / cum ( 92 x 0.05 x 0.2 ) : 0.90 kg

Total : 28.50 kg

Ordinary detonators for secondary blasting 8 holes of 0.6 m each : 8 Nos.

Electric short delay detonators @ 1 per hole for main blast : 75 Nos

Detonating fuse coil : 120 Rm

50 x 50 mm chain link wire mesh 119 sqm

Sand bags 0.025 cum 90 Nos

5. Requirement of machinery :

Deploy 0.85 cum capacity shovel for 2.2 hours for digging and loading 85 cum.

Deploy 3 tippers 5 cum capacity for 2.2 hours for disposal of 85 cum.

Deploy 1 air compressor 8.5 cmm capacity for 11 hours.

Deploy 2 jack hammers for 11 hours for drilling.

Deploy 1 angle dozer for 0.25 hour for levelling muck in dump area.

6. Requirement of workforce ( other than machinery crew ) :

Deploy 1 Crowbarman, 1 Stone breaker for 1 day for levelling bed.

Deploy 2 heavy and 2 light mazdoors for disposal of 9 cum residual muck at bed level and for

other miscellaneous works.

Deploy 1 blaster and 1 blasting helper for loading and blasting.

Deploy 1 maistry.

7. Use rate of materials :

Cost of drill rod 1.5 m long @ Rs:`: 4395.00 / Each `: 4395.00

Life of drill rod for drilling in hard rock with reconditioning : 150 m

Use rate of drill rod per Rm drilling ( cost / life ) `: 29.30

Length of air hose for drilling for each jack hammer : 50 m

Cost of 25 mm dia 50 m air hose @ `: 200.00 / Rm `: 10000.00

Life of air hose : 800 hours

Use rate of air hose per hr ( cost / life ) `: 12.50

Cost of wire mesh @ `: 220.00 / sqm `: 220.00

less salvage value at 10 % `: -22.00

Total `: 198.00

Add for replacement of damaged mesh @ 10 % `: 19.80

Total `: 217.80

Life of wire mesh with 25 % replacement each use : 3 uses

Use rate of wire mesh / use / sqm ( cost / life ) `: 72.60

Cost of empty cement bag per No. @ `: 3.00 / Each `: 3.00

Cost of sand / bag for 0.025 cum @ `: 615.00 / cum `: 15.38

Add for 1 km lead/loading/unloading charges for 0.015 cum `: 3.43

Filling charges @ 2 heavy mazdoors per 100 bags / day `: 4.77

Total cost per bag `: 26.58

Life of sand bag : 1 use

Use rate of sand bag / use / bag ( cost / life ) `: 26.58

27

Page 30: Data rates-Canal Works

CANAL AND ALLIED WORKS

RATE ANALYSIS UNIT : 92.00 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 Use rate of Jack hammer drill rod 1.5 m Rm 108.00 29.30 3164.40

Reconditioning charges @ 10 % 316.44

2 Use rate of 50 m air hose 2 Nos. Hour 22.00 12.50 275.00

3 Use rate of wire mesh sqm 106.00 72.60 7695.60

4 Use rate of sand bag Nos 90.00 26.58 2392.16

5 Explosive small dia. (Kelvex-220 ) kg 28.50 60.00 1710.00

6 Ordinary detonators Nos 8.00 7.00 56.00

7 Electric short delay detonators Nos 75.00 20.00 1500.00

8 Fuse coil Rm 120.00 9.00 1080.00

9 Sundries LS 2.00 44.00 88.00

Total `: 18277.60

Add for small Tools and Plants @ 1% `: 182.78

Add for Contractor's Profit @ 10% `: 1827.76

Add for Contractor's Overheads @ 5% `: 913.88

Total cost of Materials : `: 21202.02

B. MACHINERY:

Sl No Unit Amount

in `:

1 Shovel 0.85 cum capacity Hour 2.20 1322.00 2908.40

Fuel / Energy charges Hour 2.20 832.00 1830.40

2 Angle dozer 90 hp Hour 0.25 1273.00 318.25

Fuel / Energy charges Hour 0.25 582.00 145.50

3 Tippers 5 cum capacity 3 Nos. Hour 6.60 309.00 2039.40

Fuel / Energy charges Hour 6.60 286.00 1887.60

4 Air compressor 8.5 cmm ( diesel ) 1 No Hour 11.00 223.00 2453.00

Fuel / Energy charges Hour 11.00 851.00 9361.00

5 Jack hammers 2 Nos. Hour 22.00 16.00 352.00

Fuel / Energy charges Hour 22.00 8.00 176.00

Total `: 21471.55

Add for small Tools and Plants @ 1% `: 214.72

Add for Contractor's Profit on DPOL / Energy @ 10% `: 1340.05

Add for Contractor's Overheads @ 5% `: 1073.58

Total hire charges of Machinery : `: 24099.89

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Shovel Hour 2.20 128.00 281.60

2 Crew for Angle dozer Hour 0.25 128.00 32.00

3 Crew for Tipper Hour 6.60 95.00 627.00

4 Crew for Air compressor Hour 11.00 121.00 1331.00

5 Crew for Jack hammer Hour 22.00 188.00 4136.00

6 Maistry Day 1.00 241.23 241.23

7 Blaster Day 1.00 243.23 243.23

Contd

Description

in `.

Perticulars

Quantity

in `.

in `.

Rate

Rate

Rate

Quantity

QuantityDescription

28

Page 31: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR ( Contd ) :

Sl No Unit Amount

in `:

Contd

8 Helper blaster Day 1.00 239.73 239.73

9 Crowbarman Day 1.00 239.73 239.73

10 Stone breaker Day 1.00 241.73 241.73

11 Heavy mazdoor Day 2.00 238.73 477.46

12 Light mazdoor Day 2.00 237.23 474.46

Total `: 8565.17

Add for small Tools and Plants @ 1% `: 85.65

Add for Contractor's Profit @ 10% `: 856.52

Add for hidden cost on Labour @ 15% `: 1284.78

Add for Contractor's Overheads @ 5% `: 428.26

Total cost of Labour : `: 11220.37

ABSTRACT:

A. Cost of Materials `: 21202.02

B. Hire charges of Machinery `: 24099.89

C. Cost of Labour `: 11220.37

TOTAL `: 56522.29

Add for other enabling works @ 1.00% `: 565.22

Total cost for 92.00 cum `: 57087.51

Rate per cum `:`:`:`: 620.52

Rate approved per cum `:`:`:`: 621.00

Note: For depth of cut exceeding 18 m from ground level increase the basic rate by 5 percent for the

quantity of excavation beyond 18 m depth.

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.7

ITEM: Providing hearting embankment using selected impervious soil from approved borrow

areas in layers of 250 to 300 mm (before compaction) including cost of all materials, machinery,

labour, all other operations such as collection of soil, spreading soil in layer of specified

thickness, sorting out, breaking clods, levelling, sectioning edges / sides, watering, compacting

each layer to density control of not less than 95 percent or as stipulated using power

roller etc., complete with lead upto1 km and all lifts.

DATA:Capacity of shovel bucket : 0.50 cum

Capacity of shovel bucket under heaped condition : 0.58 cum

Capacity of tipper : 5.00 cum

Lead for conveyance of soil : Upto 1 km

Speed for loaded tipper under haul road condition : 20 km / hr

Speed for empty tipper under haul road condition : 25 km / hr

Turning and unloading time : 2.00 min

Shovel digging and loading cycle per bucket : 20 sec

1. Quantity of embankment :

In-situ qty / bucket for 15 % bulkage of soil ( 0.58 / 1.15 ) : 0.50 cum

In-situ quantity per load for 20 % bulkage of soil ( 5.0 / 1.2 ) : 4.00 cum

QuantityDescription

in `.

Rate

29

Page 32: Data rates-Canal Works

CANAL AND ALLIED WORKS

Number of buckets per load ( 4.00 / 0.50 ) say : 8 buckets

Cycle time for loading 8 buckets ( 8 x 20 / 60 ) say : 2.67 min

Round trip cycle time for tipper:

Ideal cycle time of shovel for digging & loading : 2.67 min

Time for 1km haulage under load ( 60 / 20 ) : 3.00 min

Time for turning and un-loading : 2.00 min

Time for 1 km return trip ( 60 / 25 ) : 2.40 min

Time for turning and spotting : 0.50 min

: 10.57 min

No.of tippers to match corrected cycle time of shovel (10.57 / 2.67) : 4 Nos

Output of tipper / hr with 50 min working / hr ( 50 x 4.00 / 10.57 ) : 18.92 cum

Output for 4 tippers per day ( 4 x 18.92 x 8 ) say : 605 cum

The in-situ dry density of soil in borrow area will be generally less than dry density of compacted

embankment. Therefore, the rolled embankment quantity will be slightly less than the borrow

area in-situ quantity. The extent of shrinkage in quantity depends on the degree of compaction.

For 95 % density control of embankment a shrinkage factor of 5 % may be assumed.

Quantity of embankment considering 5 %shrinkage ( 605 x 0.95 ) : 575 cum

Qty of soil for computing royalty charges @ 1.6 t / cum ( 575x1.6 ) : 920 tonnes

2. Stripping of borrow area :

Generally borrow area is stripped once in a week for 6 days requirement of soil.

Area to be stripped assuming 2.0 m depth of cut ( 605 x 6 / 2.0 ) : 1815 sqm

Depth of stripping : 0.25 m

Qty of stripping with 5 % extra area ( 1815 x 1.05 x 0.25 ) : 476 cum

Output of dozer per hr with 50 min / hr working for stripping : 100 cum

Time required for stripping 476 cum ( 476 / 100 ) : 4.76 hours

Consider 6 hours including time for levelling stripped siol / dozer shifting time.

Time required for stripping for one day embankment work 575 cum : 1.00 hour

3. Collection of soil for embankment :

Deploy one 0.50 cum capacity shovel for 8 hours for digging and loading soil.

Deploy 4 tippers of 5.00 cum capacity for 8 hours to convey soil to embankment area.

4. Spreading soil in 250 to 300 mm layer :

Quantity of loose soil to be spread ( 605 x 1.20 ) : 726 cum

Output of dozer for levelling per hour : 250 cum

Time required for levelling 726 cum ( 726 / 250 ) say : 3.00 hours

5. Watering :

Generally soil in the borrow area will be in moist condition. In the beginning of the season no

watering may be necessary and in summer months about 8 to 10 percent watering may be

needed to maintain the soil moisture within OMC plus or minus 3 percent limit. Assuming

seasonal average of 4 to 5 percent watering by weight, daily requirement of water for 575 cum

of embankment will be about 5 tanker loads of 8000 ltrs each. Deploy 8000 ltr capacity water

tanker for 5 hours daily for watering before rolling. Deploy 5 hp pump for 2.5 hours.

6. Compaction :

Soil collected for embankment layer gets compacted to some extent during levelling.

Generally 8 to 10 passes of vibratory pad foot roller is adequate for achieving specified density

control of 95 percent.

Effective length of roller drum : 1.90 m

Speed of roller per hour : 4.0 km

Thickness of layer : 0.3 m

Number of roller passes to achieve specified density control : 9 Nos

30

Page 33: Data rates-Canal Works

CANAL AND ALLIED WORKS

Output of roller / hr with 50 min / hr working and 75 % effenciancy

( 1.9 x 4000 x 0.3 x 0.75 / 9 ) x 50 / 60 say : 160 cum

Time for rolling 726 cum loose soil in embankment layer ( 726/160) say : 4.5 hours

7. Sorting out / sectioning / labour for testing etc :

Assume 2 heavy and 2 light mazdoors.

RATE ANALYSIS UNIT : 575.00 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Add Royalty charges on 862.5 t soil @ `: 20.00 / tonne `: 17250.00

Total cost of Materials : `: 17250.00

B. MACHINERY:

Sl No Unit Amount

in `:

1 Angle dozer Hour 4.00 1273.00 5092.00

Fuel / Energy charges Hour 4.00 582.00 2328.00

2 Shovel 0.50 cum capacity Hour 8.00 799.00 6392.00

Fuel / Energy charges Hour 8.00 454.00 3632.00

3 Tippers 5.00 cum capacity 4 Nos. Hour 32.00 309.00 9888.00

Fuel / Energy charges Hour 32.00 286.00 9152.00

4 Pump 5 hp ( diesel ) Hour 2.50 7.00 17.50

Fuel / Energy charges Hour 2.50 76.00 190.00

5 Water tanker 8000 ltr Hour 5.00 306.00 1530.00

Fuel / Energy charges Hour 5.00 286.00 1430.00

6 Vibratory pad foot roller 8 tonne Hour 4.50 1246.00 5607.00

Fuel / Energy charges Hour 4.50 983.00 4423.50

7 Sundries LS 2.00 44.00 88.00

Total `: 49770.00

Add for small Tools and Plants @ 1% `: 497.70

Add for Contractor's Profit on DPOL / Energy @ 10% `: 2124.35

Add for Contractor's Overheads @ 5% `: 2488.50

Total hire charges of Machinery : `: 54880.55

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Dozer Hour 4.00 128.00 512.00

2 Crew for Shovel Hour 8.00 128.00 1024.00

3 Crew for Tipper Hour 32.00 95.00 3040.00

4 Crew for Pump Hour 2.50 60.00 150.00

5 Crew for Water tanker Hour 5.00 95.00 475.00

Contd

Description

Perticulars

Quantity

in `.

Description

Rate

Quantity

Rate

in `.

31

Quantity

Rate

in `.

Page 34: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR ( Contd ) :

Sl No Unit Amount

in `:

Contd

6 Crew for Roller Hour 4.50 151.00 679.50

7 Maistry Day 2.00 241.23 482.46

8 Heavy mazdoor Day 2.00 238.73 477.46

9 Light mazdoor Day 2.00 237.23 474.46

Total `: 7314.88

Add for small Tools and Plants @ 1% `: 73.15

Add for Contractor's Profit @ 10% `: 731.49

Add for hidden cost on Labour @ 15% `: 1097.23

Add for Contractor's Overheads @ 5% `: 365.74

Total cost of Labour : `: 9582.49

ABSTRACT:

A. Cost of Materials including royalty charges `: 17250.00

B. Hire charges of Machinery `: 54880.55

C. Cost of Labour `: 9582.49

TOTAL `: 81713.04

Add for other enabling works @ 1.00% `: 817.13

Total cost for 575.00 cum `: 82530.17

Rate per cum `:`:`:`: 143.53

Rate approved per cum `:`:`:`: 144.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.8

ITEM: Providing casing embankment using semi-pervious / pervious soil from approved borrow

areas in layers of 250 to 300 mm (before compaction) including cost of all materials, machinery,

labour, all other operations such as collection of soil, spreading soil in layer of specified

thickness, sorting-out, breaking clods, levelling, sectioning edges / sides, watering, compacting

each layer to density control of not less than 95 percent or as stipulated using power roller

etc., complete with lead upto 1 km and all lifts.

DATA:Capacity of shovel bucket : 0.50 cum

Capacity of shovel bucket under heaped condition : 0.58 cum

Capacity of tipper : 5.00 cum

Lead for conveyance of soil : Upto 1 km

Speed for loaded tipper under haul road condition : 20 km / hr

Speed for empty tipper under haul road condition : 25 km / hr

Turning and unloading time : 2.00 min

Shovel digging and loading cycle per bucket : 30 sec

1. Quantity of embankment :

In-situ qty per bucket for 15 % bulkage of soil ( 0.58 / 1.15 ) : 0.50 cum

In-situ quantity per load for 20 % bulkage of soil ( 5.0 / 1.2 ) say : 4.00 cum

Number of buckets per load ( 4.00 / 0.50 ) say : 8 buckets

Cycle time for loading 8 buckets ( 8 x 30 / 60 ) say : 4.00 min

Round trip cycle time for tipper:

Ideal cycle time of shovel for digging & loading : 4.00 min

Time for 1km haulage under load ( 60 / 20 ) : 3.00 min

Description Quantity

in `.

32

Rate

Page 35: Data rates-Canal Works

CANAL AND ALLIED WORKS

Time for turning and un-loading : 2.00 min

Time for 1 km return trip ( 60 / 25 ) : 2.40 min

Time for turning and spotting : 0.50 min

Total : 11.90 min

No.of tippers to match corrected cycle time of shovel (11.90 / 4.00) : 3 Nos

Output of tipper / hr with 50 min working / hr ( 50 x 4.00 / 11.90 ) : 16.80 cum

Output for 3 tippers per day ( 3 x 16.80 x 8 ) say : 403 cum

The in-situ dry density of soil in borrow area will be generally less than dry density of compacted

embankment. Therefore, the rolled embankment quantity will be slightly less than the borrow

area in-situ quantity. The extent of shrinkage in quantity depends on the degree of compaction.

For 95 % density control of embankment a shrinkage factor of 5 % may be assumed.

Quantity of embankment considering 5 % shrinkage ( 403 x 0.95 ) say : 385 cum

Qty of soil for computing royalty charges @ 1.6 t / cum ( 385x1.6 ) : 616 tonnes

2. Stripping of borrow area :

Generally borrow area is stripped once in a week for 6 days requirement of soil.

Area to be stripped assuming 2.0 m depth of cut ( 403 x 6 / 2.0 ) : 1209 sqm

Depth of stripping : 0.20 m

Quantity of stripping with 5 % extra area ( 1209 x 1.05 x 0.20 ) : 254 cum

Output of dozer per hr with 50 min / hr working for stripping : 70 cum

Time required for stripping 254 cum : 3.60 hours

Consider 4.5 hours including time for levelling stripped siol / dozer shifting time.

Requirement of dozer for one day work 403 cum say : 0.75 hours

3. Collection of soil for embankment :

Deploy one 0.50 cum capacity shovel for 8 hours for digging and loading soil.

Deploy 3 tippers of 5.00 cum capacity for 8 hours to convey soil to embankment area.

4. Spreading soil in 250 to 300 mm layer :

Quantity of loose soil to be spread ( 403 x 1.20 ) : 484 cum

Output of dozer for levelling per hour : 250 cum

Time required for levelling 484 cum say : 2.00 hours

5. Watering :

Generally soil in the borrow area will be in moist condition. In the beginning of the season no

watering be may necessary and in summer months about 8 to 10 percent watering may be

needed to maintain the soil moisture within OMC plus or minus 3 percent limit. Assuming

seasonal average of 4 to 5 percent watering by weight, daily requirement of water for 385 cum

of embankment will be about 4 tanker loads of 8000 ltrs each.

Deploy 8000 ltr capacity water tanker for 4 hours daily for watering before rolling.

Deploy 5 hp pump for 2 hours.

6. Compaction :

Soil collected for embankment layer gets compacted to some extent during levelling.

Generally 8 to 10 passes of vibratory pad foot roller is adequate for achieving specified density

control of 95 percent.

Effective length of roller drum : 1.90 m

Speed of roller per hour : 4.0 km

Thickness of layer : 0.3 m

Number of roller passes to achieve specified density control : 9 Nos

Output of roller / hr with 50 min / hr working and 75 % effenciancy

( 1.9 x 4000 x 0.3 x 0.75 / 9 ) x 50 / 60 say : 160 cum

Time for rolling 484 cum loose soil in embankment layer say : 3 hours

7. Sorting out / sectioning / labour for testing etc :

Assume 2 heavy and 2 light mazdoors.

33

Page 36: Data rates-Canal Works

CANAL AND ALLIED WORKS

RATE ANALYSIS UNIT : 385.00 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Add Royalty charges on 577.5 t soil @ `: 20.00 / tonne `: 11550.00

Total cost of Materials : `: 11550.00

B. MACHINERY:

Sl No Unit Amount

in `:

1 Angle dozer 90 hp Hour 2.75 1273.00 3500.75

Fuel / Energy charges Hour 2.75 582.00 1600.50

2 Shovel 0.50 cum capacity Hour 8.00 799.00 6392.00

Fuel / Energy charges Hour 8.00 454.00 3632.00

3 Tippers 5.00 cum capacity 3 Nos. Hour 24.00 309.00 7416.00

Fuel / Energy charges Hour 24.00 286.00 6864.00

4 Pump 5 hp ( diesel ) Hour 2.00 7.00 14.00

Fuel / Energy charges Hour 2.00 76.00 152.00

5 Water tanker 8000 ltr Hour 4.00 306.00 1224.00

Fuel / Energy charges Hour 4.00 286.00 1144.00

6 Vibratory pad foot roller 8 tonne Hour 3.00 1246.00 3738.00

Fuel / Energy charges Hour 3.00 983.00 2949.00

7 Sundries LS 2.00 44.00 88.00

Total `: 38714.25

Add for small Tools and Plants @ 1% `: 387.14

Add for Contractor's Profit on DPOL / Energy @ 10% `: 1642.95

Add for Contractor's Overheads @ 5% `: 1935.71

Total hire charges of Machinery : `: 42680.06

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Dozer Hour 2.75 128.00 352.00

2 Crew for Shovel Hour 8.00 128.00 1024.00

3 Crew for Tipper Hour 24.00 95.00 2280.00

4 Crew for Pump Hour 2.00 60.00 120.00

5 Crew for Water tanker Hour 4.00 95.00 380.00

6 Crew for Roller Hour 3.00 151.00 453.00

7 Maistry Day 2.00 241.23 482.46

8 Heavy mazdoor Day 2.00 238.73 477.46

9 Light mazdoor Day 2.00 237.23 474.46

Total `: 6043.38

Add for small Tools and Plants @ 1% `: 60.43

Contd

34

Description

in `.

Quantity

RateQuantity

in `.

Perticulars

RateDescription

in `.

RateQuantity

Page 37: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR ( Contd ) :

Sl No Unit Amount

in `:

Contd

Add for Contractor's Profit @ 10% `: 604.34

Add for hidden cost on Labour @ 15% `: 906.51

Add for Contractor's Overheads @ 5% `: 302.17

Total cost of Labour : `: 7916.83

ABSTRACT:

A. Cost of Materials including royalty charges `: 11550.00

B. Hire charges of Machinery `: 42680.06

C. Cost of Labour `: 7916.83

TOTAL `: 62146.88

Add for other enabling works @ 1.00% `: 621.47

Total cost for 385.00 cum `: 62768.35

Rate per cum `:`:`:`: 163.03

Rate approved per cum `:`:`:`: 163.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.9

ITEM: Providing hearting / casing embankment using homogeneous soil from approved borrow

areas in layers of 250 to 300 mm (before compaction) including cost of all materials, machinery,

labour, all other operations such as collection of soil, spreading soil in layer of specified

thickness, sorting-out, breaking clods, levelling, sectioning edges / sides, watering, compacting

each layer to density control of not less than 95 percent or as stipulated using power roller

etc., complete with lead upto 1 km and all lifts.

DATA:Capacity of shovel bucket : 0.50 cum

Capacity of shovel bucket under heaped condition : 0.58 cum

Capacity of tipper : 5.00 cum

Lead for conveyance of soil : Upto 1 km

Speed for loaded tipper under haul road condition : 20 km / hr

Speed for empty tipper under haul road condition : 25 km / hr

Turning and unloading time : 2.00 min

Shovel digging and loading cycle per bucket : 22 sec

1. Quantity of embankment :

In-situ qty / bucket for 15 % bulkage of soil ( 0.58 / 1.15 ) : 0.50 cum

In-situ quantity per load for 20 % bulkage of soil ( 5.0 / 1.2 ) : 4.00 cum

Number of buckets per load ( 4.00 / 0.50 ) say : 8 buckets

Cycle time for loading 8 buckets ( 8 x 22 / 60 ) say : 2.93 min

Round trip cycle time for tipper:

Ideal cycle time of shovel for digging & loading : 2.93 min

Time for 1km haulage under load ( 60 / 20 ) : 3.00 min

Time for turning and un-loading : 2.00 min

Time for 1 km return trip ( 60 / 25 ) : 2.40 min

Time for turning and spotting : 0.50 min

Total : 10.83 min

No.of tippers to match corrected cycle time of shovel (10.83 / 2.93) : 3.7 Nos

RateDescription Quantity

in `.

35

Page 38: Data rates-Canal Works

CANAL AND ALLIED WORKS

Output of tipper / hr with 50 min working / hr ( 50 x 4.00 / 10.83 ) : 18.47 cum

Output for 3.7 tippers per day ( 3.7 x 18.47 x 8 ) say : 547 cum

The in-situ dry density of soil in borrow area will be generally less than dry density of compacted

embankment. Therefore, the rolled embankment quantity will be slightly less than the borrow

area in-situ quantity. The extent of shrinkage in quantity depends on the degree of compaction.

For 95 % density control of embankment a shrinkage factor of 5 % may be assumed.

Quantity of embankment considering 5 % shrinkage ( 547 x 0.95 ) : 520 cum

Qty of soil for computing royalty charges @ 1.6 t / cum ( 520x1.6 ) : 832 tonnes

2. Stripping of borrow area :

Generally borrow area is stripped once in a week for 6 days requirement of soil.

Area to be stripped assuming 2.0 m depth of cut ( 547 x 6 / 2 ) : 1641 sqm

Depth of stripping : 0.25 m

Qty of stripping with 5 % extra area ( 1641 x 1.05 x 0.25 ) : 431 cum

Output of dozer per hr with 50 min / hr working for stripping : 100 cum

Time required for stripping 431 cum : 4.3 hours

Consider 5 hours including time for levelling stripped siol / dozer shifting time.

Requirement of dozer for one day embankment work 547 cum say : 0.80 hour

3. Collection of soil for embankment :

Deploy one 0.50 cum capacity shovel for 8 hours for digging and loading soil.

Deploy 4 tippers of 5.00 cum capacity for 8 hours to convey soil to embankment area.

4. Spreading soil in 250 to 300 mm layer :

Quantity of loose soil to be spread ( 547 x 1.20 ) : 656 cum

Output of dozer for levelling per hour : 250 cum

Time required for levelling 656 cum say : 2.60 hours

5. Watering :

Generally soil in the borrow area will be in moist condition. In the beginning of the season no

watering may be necessary and in summer months about 8 to 10 percent watering may be

needed to maintain the soil moisture within OMC plus or minus 3 percent limit. Assuming

seasonal average of 4 to 5 percent watering by weight, daily requirement of water for 520 cum

of embankment will be about 5 tanker loads of 8000 ltrs each. Deploy 8000 ltr capacity water

tanker for 5 hours daily for watering before rolling. Deploy 5 hp pump for 2.5 hours.

6. Compaction :

Soil collected for embankment layer gets compacted to some extent during levelling.

Generally 8 to 10 passes of vibratory pad foot roller is adequate for achieving specified density

control of 95 percent.

Effective length of roller drum : 1.90 m

Speed of roller per hour : 4.0 km

Thickness of layer : 0.3 m

Number of roller passes to achieve specified density control : 9 Nos

Output of roller / hr with 50 min / hr working and 75 % effenciancy

( 1.9 x 4000 x 0.3 x 0.75 / 9 ) x 50 / 60 say : 160 cum

Time for rolling 656 cum loose soil in embankment layer say : 4.1 hours

7. Sorting out / sectioning / labour for testing etc :

Assume 2 heavy and 2 light mazdoors.

36

Page 39: Data rates-Canal Works

CANAL AND ALLIED WORKS

RATE ANALYSIS UNIT : 520.00 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Add Royalty charges on 780 t soil @ `: 20.00 / tonne `: 15600.00

Total cost of Materials : `: 15600.00

B. MACHINERY:

Sl No Unit Amount

in `:

1 Angle dozer Hour 3.40 1273.00 4328.20

Fuel / Energy charges Hour 3.40 582.00 1978.80

2 Shovel 0.50 cum capacity Hour 8.00 799.00 6392.00

Fuel / Energy charges Hour 8.00 454.00 3632.00

3 Tippers 5.00 cum capacity 4 Nos. Hour 32.00 309.00 9888.00

Fuel / Energy charges Hour 32.00 286.00 9152.00

4 Pump 5 hp ( diesel ) Hour 2.50 7.00 17.50

Fuel / Energy charges Hour 2.50 76.00 190.00

5 Water tanker 8000 ltr Hour 5.00 306.00 1530.00

Fuel / Energy charges Hour 5.00 286.00 1430.00

6 Vibratory pad foot roller 8 tonne Hour 4.10 1246.00 5108.60

Fuel / Energy charges Hour 4.10 983.00 4030.30

7 Sundries LS 2.00 44.00 88.00

Total `: 47765.40

Add for small Tools and Plants @ 1% `: 477.65

Add for Contractor's Profit on DPOL / Energy @ 10% `: 2050.11

Add for Contractor's Overheads @ 5% `: 2388.27

Total hire charges of Machinery : `: 52681.43

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Dozer Hour 3.40 128.00 435.20

2 Crew for Shovel Hour 8.00 128.00 1024.00

3 Crew for Tipper Hour 32.00 95.00 3040.00

4 Crew for Pump Hour 2.50 60.00 150.00

5 Crew for Water tanker Hour 5.00 95.00 475.00

6 Crew for Roller Hour 4.10 151.00 619.10

7 Maistry Day 2.00 241.23 482.46

8 Heavy mazdoor Day 2.00 238.73 477.46

9 Light mazdoor Day 2.00 237.23 474.46

Total `: 7177.68

Add for small Tools and Plants @ 1% `: 71.78

Contd

Perticulars

Description

in `.

Quantity

37

Rate

Rate

in `.

in `.

Rate

QuantityDescription

Quantity

Page 40: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR ( Contd ) :

Sl No Unit Amount

in `:

Contd

Add for Contractor's Profit @ 10% `: 717.77

Add for hidden cost on Labour @ 15% `: 1076.65

Add for Contractor's Overheads @ 5% `: 358.88

Total cost of Labour : `: 9402.76

ABSTRACT:

A. Cost of Materials including royalty charges `: 15600.00

B. Hire charges of Machinery `: 52681.43

C. Cost of Labour `: 9402.76

TOTAL `: 77684.19

Add for other enabling works @ 1.00% `: 776.84

Total cost for 520.00 cum `: 78461.04

Rate per cum `:`:`:`: 150.89

Rate approved per cum `:`:`:`: 151.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.10

ITEM: Providing hearting embankment using impervious soil from approved dump areas in layers

of 250 to 300 mm (before compaction) including cost of all materials, machinery, labour, all

other operations such as collection of soil, spreading soil in layer of specified thickness,

sorting out, breaking clods, levelling, sectioning edges / sides, watering, compacting each layer

to density control of not less than 95 percent or as stipulated using power roller etc.,

complete with lead upto 1 km and all lifts.

DATA:Capacity of shovel bucket : 0.50 cum

Capacity of shovel bucket under heaped condition : 0.58 cum

Insitu qty / bucket for 10 % bulkage of soil in dump area : 0.53 cum

Capacity of tipper : 5.00 cum

Lead for conveyance of soil : Upto 1 km

Speed for loaded tipper under haul road condition : 20 km / hr

Speed for empty tipper under haul road condition : 25 km / hr

Turning and unloading time : 2.00 min

Digging of unsettled soil in dump area will be faster compared to borrow area in view of relatively

loose condition of soil. Assume a digging & loading cycle time at 80 % of borrow area.

Shovel digging and loading cycle per bucket ( 20 x 0.8 ) : 16 sec

1. Quantity of embankment :

In-situ quantity per load for 10 % bulkage of soil ( 5.0 / 1.1 ) say : 4.54 cum

Number of buckets per load ( 4.54 / 0.53 ) say : 8 buckets

Cycle time for loading 8 buckets ( 8 x 16 / 60 ) say : 2.13 min

Round trip cycle time for tipper:

Ideal cycle time of shovel for digging & loading : 2.13 min

Time for 1km haulage under load ( 60 / 20 ) : 3.00 min

Time for turning and un-loading : 2.00 min

Time for 1 km return trip ( 60 / 25 ) : 2.40 min

Time for turning and spotting : 0.50 min

Total : 10.03 min

RateDescription

38

in `.

Quantity

Page 41: Data rates-Canal Works

CANAL AND ALLIED WORKS

No.of tippers to match corrected cycle time of shovel (10.03 / 2.13) : 4.7 Nos

Output of tipper / hr with 50 min working / hr ( 50 x 4.54 / 10.03 ) : 22.60 cum

Output for 4.7 tippers per day ( 4.7 x 22.60 x 8 ) say : 850 cum

The output worked out above is the insitu quantity in dump area with 10 % bulkage factor.

The in-situ dry density of soil in borrow area will be generally less than dry density of compacted

embankment. Therefore, the rolled embankment quantity will be slightly less than the borrow

area in-situ quantity. The extent of shrinkage in quantity depends on the degree of compaction

of embankment. For 95 % density control of embankment a shrinkage factor of 5 % is assumed

for use of borrow area soil.

Further, as the insitu density of soil in dump area will be less compared to natural ground due

to bulkage of soil in dump area, for applying the shrinkage foctor it is necessary to convert the

insitu dump area quantity to equivalent borrow area quantity by applying bulkage factor.

Equivalent borrow area quantity for 10% bulkage ( 850 / 1.1 ) 773 cum

Qty of compacted embankment for 5 % shrinkage ( 773 x 0.95 ) : 734 cum

Qty of soil for computing royalty charges @ 1.6 t /cum ( 734 x 1.6 ) : 1175 tonnes

2. Stripping of borrow area :

Since soil is from dump area no stripping is involved.

3. Collection of soil for embankment :

Deploy one 0.50 cum capacity shovel for 8 hours for re-excavation and loading soil.

Deploy 5 tippers of 5.00 cum capacity for 8 hours to convey soil to embankment area.

4. Spreading soil in 250 to 300 mm layer :

Quantity of loose soil to be spread ( 850 x 1.10 ) : 935 cum

Output of dozer for levelling per hour : 250 cum

Time required for levelling 935 cum say : 4.00 hours

5. Watering :

Generally soil in the dump area will be in moist condition. In the beginning of the season no

watering may be necessary. However, in summer months as the loose soil looses moisture at

faster rate compared to borrow area about 10 to 12 % watering may be needed to maintain

the soil moisture within OMC plus or minus 3 percent limit. Assuming seasonal average of 5

to 6 percent watering by weight, daily requirement of water for 734 cum of embankment will be

about 8 tanker loads of 8000 ltrs each.

Deploy 8000 ltr capacity water tanker for 8 hours daily for watering before rolling.

Deploy 5 hp pump for 4 hours.

6. Compaction :

Soil collected for embankment layer gets compacted to some extent during levelling.

Generally 8 to 10 passes of vibratory pad foot roller is adequate for achieving specified density

control of 95 percent.

Effective length of roller drum : 1.90 m

Speed of roller per hour : 4.0 km

Thickness of layer : 0.3 m

Number of roller passes to achieve specified density control : 9 Nos

Output of roller / hr with 50 min / hr working and 75 % effenciancy

( 1.9 x 4000 x 0.3 x 0.75 / 9 ) x 50 / 60 say : 160 cum

Time for rolling 935 cum soil in embankment layer say : 6.00 hours

7. Sorting out / sectioning / labour for testing etc :

Assume 2 heavy and 2 light mazdoors.

39

Page 42: Data rates-Canal Works

CANAL AND ALLIED WORKS

RATE ANALYSIS UNIT : 734.00 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Add Royalty charges on 1101t soil @ `: 20.00 / tonne `: 22020.00

Total cost of Materials : `: 22020.00

B. MACHINERY:

Sl No Unit Amount

in `:

1 Angle dozer Hour 4.00 1273.00 5092.00

Fuel / Energy charges Hour 4.00 582.00 2328.00

2 Shovel 0.50 cum capacity Hour 8.00 799.00 6392.00

Fuel / Energy charges Hour 8.00 454.00 3632.00

3 Tippers 5.00 cum capacity 5 Nos. Hour 40.00 309.00 12360.00

Fuel / Energy charges Hour 40.00 286.00 11440.00

4 Pump 5 hp ( diesel ) Hour 4.00 7.00 28.00

Fuel / Energy charges Hour 4.00 76.00 304.00

5 Water tanker 8000 ltr Hour 8.00 306.00 2448.00

Fuel / Energy charges Hour 8.00 286.00 2288.00

6 Vibratory pad foot roller 8 tonne Hour 6.00 1246.00 7476.00

Fuel / Energy charges Hour 6.00 983.00 5898.00

7 Sundries LS 2.00 44.00 88.00

Total `: 59774.00

Add for small Tools and Plants @ 1% `: 597.74

Add for Contractor's Profit on DPOL / Energy @ 10% `: 2597.80

Add for Contractor's Overheads @ 5% `: 2988.70

Total hire charges of Machinery : `: 65958.24

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Dozer Hour 4.00 128.00 512.00

2 Crew for Shovel Hour 8.00 128.00 1024.00

3 Crew for Tipper Hour 40.00 95.00 3800.00

4 Crew for Pump Hour 4.00 60.00 240.00

5 Crew for Water tanker Hour 8.00 95.00 760.00

6 Crew for Roller Hour 6.00 151.00 906.00

7 Maistry Day 2.00 241.23 482.46

8 Heavy mazdoor Day 2.00 238.73 477.46

9 Light mazdoor Day 2.00 237.23 474.46

Total `: 8676.38

Add for small Tools and Plants @ 1% `: 86.76

Contd

Perticulars

Description

in `.

Description

Rate

Rate

Rate

in `.

in `.

Quantity

Quantity

Quantity

40

Page 43: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR ( Contd ) :

Sl No Unit Amount

in `:

Contd

Add for Contractor's Profit @ 10% `: 867.64

Add for hidden cost on Labour @ 15% `: 1301.46

Add for Contractor's Overheads @ 5% `: 433.82

Total cost of Labour : `: 11366.06

ABSTRACT:

A. Cost of Materials including royalty charges `: 22020.00

B. Hire charges of Machinery `: 65958.24

C. Cost of Labour `: 11366.06

TOTAL `: 99344.30

Add for other enabling works @ 1.00% `: 993.44

Total cost for 734.00 cum `: 100337.74

Rate per cum `:`:`:`: 136.70

Rate approved per cum `:`:`:`: 137.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.11

ITEM: Providing casing embankment using semi-pervious / pervious soil from approved dump

areas in layers of 250 to 300 mm (before compaction) including cost of all materials, machinery,

labour, all other operations such as collection of soil, spreading soil in layer of specified

thickness, sorting-out, breaking clods, levelling, sectioning edges / sides, watering, compacting

each layer to density control of not less than 95 percent or as stipulated using power roller

etc., complete with lead upto 1 km and all lifts.

DATA:Capacity of shovel bucket : 0.50 cum

Capacity of shovel bucket under heaped condition : 0.58 cum

Insitu quantity of soil per bucket considering 10 % bulkage : 0.53 cum

Capacity of tipper : 5.00 cum

Lead for conveyance of soil : Upto 1 km

Speed for loaded tipper under haul road condition : 20 km / hr

Speed for empty tipper under haul road condition : 25 km / hr

Turning and unloading time : 2.00 min

Digging of soil in dump area will be faster compared to borrow area in view of relatively loose

condition of soil. For semi-pervious / pervious soil in dump area the digging cycle can be slightly

more than the digging cycle of impervious soil in dump area. Assume a digging & loading cycle

time at 65 % of borrow area.

Shovel digging and loading cycle per bucket for soil in borrow area : 30 sec

Shovel digging and loading cycle/ bucket in dump area ( 30 x 0.65 ) : 20 sec

1. Quantity of embankment :

In-situ quantity per load for 10 % bulkage of soil ( 5.0 / 1.1 ) say : 4.53 cum

Number of buckets per load ( 4.53 / 0.53 ) say : 8 buckets

Cycle time for loading 8 buckets ( 8 x 20 / 60 ) say : 2.67 min

Round trip cycle time for tipper:

Ideal cycle time of shovel for digging & loading : 2.67 min

Time for 1km haulage under load ( 60 / 20 ) : 3.00 min

Time for turning and un-loading : 2.00 min

Description

in `.

41

Quantity Rate

Page 44: Data rates-Canal Works

CANAL AND ALLIED WORKS

Time for 1 km return trip ( 60 / 25 ) : 2.40 min

Time for turning and spotting : 0.50 min

Total : 10.57 min

No.of tippers to match corrected cycle time of shovel (10.57 / 2.67) : 4 Nos

Output of tipper / hr with 50 min working / hr ( 50 x 4.53 / 10.57 ) : 21.40 cum

Output for 4 tippers per day ( 4 x 21.40 x 8 ) say : 685 cum

The output worked out above is the insitu quantity in dump area with 10 % bulkage factor.

The in-situ dry density of soil in borrow area will be generally less than dry density of compacted

embankment. Therefore, the rolled embankment quantity will be slightly less than the borrow

area in-situ quantity. The extent of shrinkage in quantity depends on the degree of compaction

of embankment. For 95 % density control of embankment a shrinkage factor of 5 % is assumed

for use of borrow area soil.

Further, as the insitu density of soil in dump area will be less compared to natural ground due

to bulkage of soil in dump area, for applying the shrinkage foctor it is necessary to convert the

insitu dump area quantity to equivalent borrow area quantity by applying bulkage factor.

Equivalent borrow area quantity for 10% bulkage ( 685 / 1.1 ) 623 cum

Qty of compacted embankment for 5 % shrinkage ( 623 x 0.95 ) : 592 cum

Qty of soil for computing royalty charges @ 1.6 t /cum ( 592 x 1.6 ) : 947 tonnes

2. Stripping of borrow area :

Since the soil is from dump area no stripping is involved.

3. Collection of soil for embankment :

Deploy one 0.50 cum capacity shovel for 8 hours for re-excavation and loading soil.

Deploy 4 tippers of 5.00 cum capacity for 8 hours to convey soil to embankment area.

4. Spreading soil in 250 to 300 mm layer :

Quantity of loose soil to be spread ( 685 x 1.10 ) : 754 cum

Output of dozer for levelling per hour : 250 cum

Time required for levelling 754 cum say : 3.00 hours

5. Watering :

Generally soil in the dump area will be in moist condition. In the beginning of the season no

watering may be necessary. However, in summer months as the loose soil looses moisture at

faster rate compared to borrow area about 10 to 12 % watering may be needed to maintain

the soil moisture within OMC plus or minus 3 percent limit. Assuming seasonal average of 5

to 6 percent watering by weight, daily requirement of water for 592 cum of embankment will be

about 6 tanker loads of 8000 ltrs each.

Deploy 8000 ltr capacity water tanker for 6 hours daily for watering before rolling.

Deploy 5 hp pump for 3 hours.

6. Compaction :

Soil collected for embankment layer gets compacted to some extent during levelling.

Generally 8 to 10 passes of vibratory pad foot roller is adequate for achieving specified density

control of 95 percent.

Effective length of roller drum : 1.90 m

Speed of roller per hour : 4.0 km

Thickness of layer : 0.3 m

Number of roller passes to achieve specified density control : 9 Nos

Output of roller / hr with 50 min / hr working and 75 % effenciancy

( 1.9 x 4000 x 0.3 x 0.75 / 9 ) x 50 / 60 say : 160 cum

Time for rolling 754 cum soil in embankment layer say : 4.7 hours

7. Sorting out/ sectioning/ labour for testing etc :

Assume 2 heavy and 2 light mazdoors.

42

Page 45: Data rates-Canal Works

CANAL AND ALLIED WORKS

RATE ANALYSIS UNIT : 592.00 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Add Royalty charges on 888 t soil @ `: 20.00 / tonne `: 17760.00

Total cost of Materials : `: 17760.00

B. MACHINERY:

Sl No Unit Amount

in `:

1 Angle dozer 90 hp Hour 3.00 1273.00 3819.00

Fuel / Energy charges Hour 3.00 582.00 1746.00

2 Shovel 0.50 cum capacity Hour 8.00 799.00 6392.00

Fuel / Energy charges Hour 8.00 454.00 3632.00

3 Tippers 5.00 cum capacity 4 Nos. Hour 32.00 309.00 9888.00

Fuel / Energy charges Hour 32.00 286.00 9152.00

4 Pump 5 hp ( diesel ) Hour 3.00 7.00 21.00

Fuel / Energy charges Hour 3.00 76.00 228.00

5 Water tanker 8000 ltr Hour 6.00 306.00 1836.00

Fuel / Energy charges Hour 6.00 286.00 1716.00

6 Vibratory pad foot roller 8 tonne Hour 4.70 1246.00 5856.20

Fuel / Energy charges Hour 4.70 983.00 4620.10

7 Sundries LS 2.00 44.00 88.00

Total `: 48994.30

Add for small Tools and Plants @ 1% `: 489.94

Add for Contractor's Profit on DPOL / Energy @ 10% `: 2118.21

Add for Contractor's Overheads @ 5% `: 2449.72

Total hire charges of Machinery : `: 54052.17

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Dozer Hour 3.00 128.00 384.00

2 Crew for Shovel Hour 8.00 128.00 1024.00

3 Crew for Tipper Hour 32.00 95.00 3040.00

4 Crew for Pump Hour 3.00 60.00 180.00

5 Crew for Water tanker Hour 6.00 95.00 570.00

6 Crew for Roller Hour 4.70 151.00 709.70

7 Maistry Day 2.00 241.23 482.46

8 Heavy mazdoor Day 2.00 238.73 477.46

9 Light mazdoor Day 2.00 237.23 474.46

Total `: 7342.08

Add for small Tools and Plants @ 1% `: 73.42

Contd

Description

Quantity

Rate

Quantity

QuantityDescription

43

in `.

in `.

in `.

Perticulars

Rate

Rate

Page 46: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR ( Contd ) :

Sl No Unit Amount

in `:

Contd

Add for Contractor's Profit @ 10% `: 734.21

Add for hidden cost on Labour @ 15% `: 1101.31

Add for Contractor's Overheads @ 5% `: 367.10

Total cost of Labour : `: 9618.12

ABSTRACT:

A. Cost of Materials including royalty charges `: 17760.00

B. Hire charges of Machinery `: 54052.17

C. Cost of Labour `: 9618.12

TOTAL `: 81430.29

Add for other enabling works @ 1.00% `: 814.30

Total cost for 592.00 cum `: 82244.60

Rate per cum `:`:`:`: 138.93

Rate approved per cum `:`:`:`: 139.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.12

ITEM: Providing hearting embankment using impervious soil collected in embankment area in

heaps as part of disposal of excavated soil from canal in layers of 250 to 300 mm ( before

compaction ) including cost of all materials, machinery, labour, all other operations such as

spreading soil in layer of specified thickness , sorting-out, breaking clods, levelling, sectioning

edges /sides, watering, compacting each layer to density control of not less than 95 percent

or as stipulated using power roller etc., complete with lead upto 1 km for water.

DATA: Qty of soil collected in embankment area considered for rate analysis : 750 cum

Equivalent borrow area qty assuming 20 % bulkage ( 750 / 1.2 ) : 625 cum

The in-situ dry density of soil in borrow area will be generally less than dry density of compacted

embankment. Therefore, the rolled embankment quantity will be slightly less than the borrow

area in-situ quantity. The extent of shrinkage in quantity depends on the degree of compaction

of embankment. For 95 % density control of embankment a shrinkage factor of 5 % is assumed

for use of borrow area soil.

For use of excavated soil collected in embankment area equivalent borrow area quantity is to be

considered for applying the shrinkage factor.

Qty of embankment assuming 5% shrinkage ( 625 x 0.95 ) say : 595 cum

Qty of soil for computing royalty @ 1.6 t / cum ( 595 x 1.6 ) : 952 tonnes

1. Stripping of borrow area :

No stripping of top soil involved as useful soil from excavation is collected in embankment area.

2. Collection of soil for embankment :

Soil already collected in embankment area as part of disposal of soil from canal excavation.

3. Spreading soil in 250 to 300 mm layer :

Consider bulkage of 20 % in collection of soil and shrinkage factor of 5 % in compaction.

Quantity of loose soil to be spread : 750 cum

Output of dozer for levelling per hour : 250 cum

Time required for levelling 750 cum say : 3.00 hours

4. Watering :

Generally soil from canal excavation will be in moist condition.In the beginning of the season no

Description Rate

44

in `.

Quantity

Page 47: Data rates-Canal Works

CANAL AND ALLIED WORKS

watering may be necessary and in summer months about 8 to 10 percent watering may be

needed to maintain the soil moisture within OMC plus or minus 3 percent limit. Assuming

seasonal average of 4 to 5 percent watering by weight, daily requirement of water for 595 cum

of embankment will be about 5 tanker loads of 8000 ltrs each.

Deploy 8000 ltr capacity water tanker for 5 hours daily for watering before rolling.

Deploy 5 hp pump for 2.5 hours.

5. Compaction :

Soil collected for embankment layer gets compacted to some extent during levelling.

Generally 8 to 10 passes of vibratory pad foot roller is adequate for achieving specified density

control of 95 percent.

Effective length of roller drum : 1.90 m

Speed of roller per hour : 4.0 km

Thickness of layer : 0.3 m

Number of roller passes to achieve specified density control : 9 Nos

Output of roller / hr with 50 min / hr working and 75 % effenciancy

( 1.9 x 4000 x 0.3 x 0.75 / 9 ) x 50 / 60 say : 160 cum

Time for rolling 750 cum soil in embankment layer say : 4.7 hours

6. Sorting out / sectioning / labour for testing etc :

Assume 2 heavy and 2 light mazdoors.

RATE ANALYSIS UNIT : 595.00 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Add Royalty charges on 892.5 t soil @ `: 20.00 / tonne `: 17850.00

Total cost of Materials : `: 17850.00

B. MACHINERY:

Sl No Unit Amount

in `:

1 Angle dozer 90 hp Hour 3.00 1273.00 3819.00

Fuel / Energy charges Hour 3.00 582.00 1746.00

2 Pump 5 hp ( diesel ) Hour 2.50 7.00 17.50

Fuel / Energy charges Hour 2.50 76.00 190.00

3 Water tanker 8000 ltr Hour 5.00 306.00 1530.00

Fuel / Energy charges Hour 5.00 286.00 1430.00

4 Vibratory pad foot roller 8 tonne Hour 4.70 1246.00 5856.20

Fuel / Energy charges Hour 4.70 983.00 4620.10

5 Sundries LS 2.00 44.00 88.00

Total `: 19296.80

Add for small Tools and Plants @ 1% `: 192.97

Add for Contractor's Profit on DPOL / Energy @ 10% `: 807.41

Add for Contractor's Overheads @ 5% `: 964.84

Total hire charges of Machinery : `: 21262.02

Perticulars

Description

in `.

Quantity

45

Rate

in `.

Rate

Quantity

Page 48: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Dozer Hour 3.00 128.00 384.00

2 Crew for Pump Hour 2.50 60.00 150.00

3 Crew for Water tanker Hour 5.00 95.00 475.00

4 Crew for Roller Hour 4.70 151.00 709.70

5 Maistry Day 1.00 241.23 241.23

6 Heavy mazdoor Day 2.00 238.73 477.46

7 Light mazdoor Day 2.00 237.23 474.46

Total `: 2911.85

Add for small Tools and Plants @ 1% `: 29.12

Add for Contractor's Profit @ 10% `: 291.19

Add for hidden cost on Labour @ 15% `: 436.78

Add for Contractor's Overheads @ 5% `: 145.59

Total cost of Labour : `: 3814.52

ABSTRACT:

A. Cost of Materials including royalty charges `: 17850.00

B. Hire charges of Machinery `: 21262.02

C. Cost of Labour `: 3814.52

TOTAL `: 42926.54

Add for other enabling works @ 1.00% `: 429.27

Total cost for 595.00 cum `: 43355.81

Rate per cum `:`:`:`: 72.87

Rate approved per cum `:`:`:`: 73.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.13

ITEM: Providing casing embankment using semi-pervious / pervious soil collected in heaps

in embankment area as part of disposal of excavated soil from canal in layers of 250 to 300

mm ( before compaction ) including cost of all materials, machinery, labour, all other operations

such as spreading soil in layer of specified thickness, sorting-out, breaking clods, levelling,

sectioning edges / sides, watering, compacting each layer to density control of not less than

95 percent or as stipulated using power roller etc., complete with lead upto 1 km for water.

DATA: Qty of soil collected in embankment area considered for rate analysis : 750 cum

Equivalent borrow area qty assuming 20 % bulkage ( 750 / 1.2 ) : 625 cum

The in-situ dry density of soil in borrow area will be generally less than dry density of compacted

embankment. Therefore, the rolled embankment quantity will be slightly less than the borrow

area in-situ quantity. The extent of shrinkage in quantity depends on the degree of compaction

of embankment. For 95 % density control of embankment a shrinkage factor of 5 % is assumed

for use of borrow area soil.

For use of excavated soil collected in embankment area equivalent borrow area quantity is to be

considered for applying the shrinkage factor.

Qty of embankment assuming 5% shrinkage ( 625 x 0.95 ) say : 595 cum

Qty of soil for computing royalty same as in Item : 12 : 952 tonnes

1. Stripping of borrow area :

No stripping of top soil involved as useful soil from excavation is collected in embankment area.

Description

in `.

RateQuantity

46

Page 49: Data rates-Canal Works

CANAL AND ALLIED WORKS

2. Collection of soil for embankment :

Soil already collected in embankment area as part of disposal of soil from canal excavation.

from canal excavation.

3. Spreading soil in 250 to 300 mm layer :

Quantity of loose soil to be spread : 750 cum

Output of dozer cum shovel for levelling per hour : 250 cum

Time required for levelling 750 cum say : 3.00 hours

4. Watering :

Generally the soil from excavation will be in moist condition. In the beginning of the season no

watering may be necessary and in summer months about 8 to 10 percent watering may be

needed to maintain the soil moisture within OMC plus or minus 3 percent limit. Assuming

seasonal average of 4 to 5 percent watering by weight, daily requirement of water for 595 cum

of embankment will be about 5 tanker loads of 8000 ltrs each.

Deploy 8000 ltr capacity water tanker for 5 hours daily for watering before rolling.

Deploy 5 hp pump for 2.5 hours.

5. Compaction :

Soil collected for embankment layer gets compacted to some extent during levelling.

Generally 8 to 10 passes of vibratory pad foot roller is adequate for achieving specified density

control of 95 percent.

Effective length of roller drum : 1.90 m

Speed of roller per hour : 4.0 km

Thickness of layer : 0.3 m

Number of roller passes to achieve specified density control : 9 Nos

Output of roller / hr with 50 min / hr working and 75 % effenciancy

( 1.9 x 4000 x 0.3 x 0.75 / 9 ) x 50 / 60 say : 160 cum

Time for rolling 750 cum soil in embankment layer say : 4.7 hours

6. Sorting out / sectioning / labour for testing etc :

Assume 2 heavy and 2 light mazdoors.

RATE ANALYSIS UNIT : 595.00 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Add Royalty charges on 892.5 t soil @ `: 20.00 / tonne `: 17850.00

Total cost of Materials : `: 17850.00

B. MACHINERY:

Sl No Unit Amount

in `:

1 Angle dozer 90 hp Hour 3.00 1273.00 3819.00

Fuel / Energy charges Hour 3.00 582.00 1746.00

2 Pump 5 hp ( diesel ) Hour 2.50 7.00 17.50

Fuel / Energy charges Hour 2.50 76.00 190.00

Contd

Perticulars Rate

in `.

in `.

Description Rate

Quantity

Quantity

47

Page 50: Data rates-Canal Works

CANAL AND ALLIED WORKS

B. MACHINERY ( Contd ) :

Sl No Unit Amount

in `:

Contd

3 Water tanker 8000 ltr Hour 5.00 306.00 1530.00

Fuel / Energy charges Hour 5.00 286.00 1430.00

4 Vibratory pad foot roller 8 tonne Hour 4.70 1246.00 5856.20

Fuel / Energy charges Hour 4.70 983.00 4620.10

5 Sundries LS 2.00 44.00 88.00

Total `: 19296.80

Add for small Tools and Plants @ 1% `: 192.97

Add for Contractor's Profit on DPOL / Energy @ 10% `: 807.41

Add for Contractor's Overheads @ 5% `: 964.84

Total hire charges of Machinery : `: 21262.02

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Dozer Hour 3.00 128.00 384.00

2 Crew for Pump Hour 2.50 60.00 150.00

3 Crew for Water tanker Hour 5.00 95.00 475.00

4 Crew for Roller Hour 4.70 151.00 709.70

5 Maistry Day 1.00 241.23 241.23

6 Heavy mazdoor Day 2.00 238.73 477.46

7 Light mazdoor Day 2.00 237.23 474.46

Total `: 2911.85

Add for small Tools and Plants @ 1% `: 29.12

Add for Contractor's Profit @ 10% `: 291.19

Add for hidden cost on Labour @ 15% `: 436.78

Add for Contractor's Overheads @ 5% `: 145.59

Total cost of Labour : `: 3814.52

ABSTRACT:

A. Cost of Materials including royalty charges `: 17850.00

B. Hire charges of Machinery `: 21262.02

C. Cost of Labour `: 3814.52

TOTAL `: 42926.54

Add for other enabling works @ 1.00% `: 429.27

Total cost for 595.00 cum `: 43355.81

Rate per cum `:`:`:`: 72.87

Rate approved per cum `:`:`:`: 73.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.14

ITEM: Providing compacted embankment for field irrigation channels with gravely soil from

approved borrow area in layers of 100 to 150 mm thickness (before compaction) including cost

of all materials, machinery, labour, all other operations such as collection of soil, spreading

in layer of specified thickness, sorting-out, breaking clods, levelling, watering, compacting

as directed, dressing sides to required slope etc., complete with lead upto 50 m and all lifts.

48

in `.

Rate

Quantity RateDescription

in `.

Description Quantity

Page 51: Data rates-Canal Works

CANAL AND ALLIED WORKS

DATA:Output of 1 heavy & 1 light mazdoor assumed at 5 cum per day for excavation of gravely soil

and loading the same to either transport vehicle or dumping soil in channel embankment area.

Output of 1 heavy mazdoor assumed at 10 cum loose soil for spreading and levelling.

Assuming 4 percent watering ( about 60 ltr / cum ) and 5 trips per day:

Output of 1 bullock cart for watering : 30 cum / day

Assuming 2 km / hour speed and 25 passes per layer for rolling.

Output of 1 bullock drawn roller with 70 percent efficiency

( 0.60 x 2000 x 0.15 x 0.70 / 25 ) x 8 x 50 / 60 say : 30 cum / day

Qty of soil for computing royalty at 1.6 t / cum ( 30 x 1.6 ) : 48 tonnes

RATE ANALYSIS UNIT : 30.00 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Add Royalty charges on 45 t soil @ Rs: 20.00 / tonne `: 900.00

Total cost of Materials : `: 900.00

B. MACHINERY:

Sl No Unit Amount

in `:

1 5 hp pump ( diesel ) Hour 0.25 7.00 1.75

Fuel / Energy charges Hour 0.25 76.00 19.00

Total `: 20.75

Add for small Tools and Plants @ 1% `: 0.21

Add for Contractor's Profit on DPOL / Energy @ 10% `: 1.90

Add for Contractor's Overheads @ 5% `: 1.04

Total hire charges of Machinery : `: 23.90

C. LABOUR:

Sl No Unit Amount

in `:

1 Operator pump Hour 0.25 60.00 15.00

2 Maistry Day 0.20 241.23 48.25

3 Heavy mazdoor for colletion of soil Day 6.00 238.73 1432.38

For spreading / levelling / sectioning Day 3.00 238.73 716.19

4 Cartman with Bullock cart for water Day 1.00 278.23 278.23

5 Bullock drawn roller for rolling Day 1.00 278.23 278.23

6 Light mazdoor for conveying soil Day 6.00 237.23 1423.38

Total `: 4191.66

Add for small Tools and Plants @ 1% `: 41.92

Add for Contractor's Profit @ 10% `: 419.17

Add for hidden cost on Labour @ 15% `: 628.75

Add for Contractor's Overheads @ 5% `: 209.58

Total cost of Labour : `: 5491.07

Description

Description

Quantity RatePerticulars

Rate

in `.

Quantity

Quantity

in `.

in `.

Rate

49

Page 52: Data rates-Canal Works

CANAL AND ALLIED WORKS

ABSTRACT:

A. Cost of Materials including royalty charges `: 900.00

B. Hire charges of Machinery `: 23.90

C. Cost of Labour `: 5491.07

TOTAL `: 6414.96

Add for other enabling works @ 1.00% `: 64.15

Total cost for 30.00 cum `: 6479.11

Rate per cum `:`:`:`: 215.97

Rate approved per cum `:`:`:`: 216.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.15

ITEM: Providing rubble and sand filling in layers of 250 to 300 mm including cost of all materials,

machinery, labour, watering, ramming etc., complete with lead upto 50 m and all lifts.

DATA:Consider 10 cum rubble and sand filling.

Consider 40 % voids in rubble filling.

1. Requirement of materials :

Rubble ( 10 x 1 x 1.02 ) 10.20 cum

Sand unscreened ( 10 x 0.4 x 1.02 ) 4.10 cum

2. Requirement of machinery :

No machinery proposed.

3. Requirement of work-force :

Heavy mazdoor for rubble filling 2 Nos.

Light mazdoor for packing sand and watering 2 Nos.

RATE ANALYSIS UNIT : 10.00 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 Rubble stones at quarry cum 10.20 400.00 4080.00

2 Sand ( unscreened ) at quarry cum 4.10 615.00 2521.50

Total `: 6601.50

Add for small Tools and Plants @ 1% `: 66.02

Add for Contractor's Profit @ 10% `: 660.15

Add for Contractor's Overheads @ 5% `: 330.08

Add Royalty charges on Rubble @ ( Included in material rate ) `: 0.00

Add Royalty charges on Sand @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 7657.74

B. MACHINERY:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

Perticulars

in `.

Description Rate

Rate

in `.

Quantity

Quantity

50

Page 53: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR:

Sl No Unit Amount

in `:

1 Heavy mazdoor Day 2.00 238.73 477.46

2 Light mazdoor Day 2.00 237.23 474.46

Total `: 951.92

Add for small Tools and Plants @ 1% `: 9.52

Add for Contractor's Profit @ 10% `: 95.19

Add for hidden cost on Labour @ 15% `: 142.79

Add for Contractor's Overheads @ 5% `: 47.60

Total cost of Labour : `: 1247.02

ABSTRACT:

A. Cost of Materials including royalty charges `: 7657.74

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 1247.02

TOTAL `: 8904.76

Add for other enabling works / watering charges @ 1.00% `: 89.05

Total cost for 10.00 cum `: 8993.80

Rate per cum `:`:`:`: 899.38

Rate approved per cum `:`:`:`: 899.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.16

ITEM: Providing rubble and murum filling in layers of 250 to 300 mm including cost of all materials,

machinery, labour, watering, ramming etc., complete with lead upto 50 m and all lifts.

DATA:Consider 10 cum rubble and murum filling for rate analysis.

1. Requirement of materials :

Rubble ( 10 x 1 x 1.02 ) 10.20 cum

Murum ( considering 40 % voids in rubble filling) ( 10 x 0.4 x 1.02 ) 4.10 cum

2. Requirement of machinery :

No machinery proposed.

3. Requirement of work-force :

Heavy mazdoor for rubble filling 2 Nos.

Light mazdoor for packing murum and watering 2 Nos.

RATE ANALYSIS UNIT : 10.00 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 Rubble stones at quarry cum 10.20 400.00 4080.00

2 Murum cum 4.10 140.00 574.00

Total `: 4654.00

Add for small Tools and Plants @ 1% `: 46.54

Add for Contractor's Profit @ 10% `: 465.40

Add for Contractor's Overheads @ 5% `: 232.70

Add Royalty charges on Rubble @ ( Included in material rate ) `: 0.00

Add Royalty charges on Murum @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 5398.64

Perticulars Quantity

51

Rate

Description

in `.

in `.

RateQuantity

Page 54: Data rates-Canal Works

CANAL AND ALLIED WORKS

B. MACHINERY:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Heavy mazdoor Day 2.00 238.73 477.46

2 Light mazdoor Day 2.00 237.23 474.46

Total `: 951.92

Add for small Tools and Plants @ 1% `: 9.52

Add for Contractor's Profit @ 10% `: 95.19

Add for hidden cost on Labour @ 15% `: 142.79

Add for Contractor's Overheads @ 5% `: 47.60

Total cost of Labour : `: 1247.02

ABSTRACT:

A. Cost of Materials including royalty charges `: 5398.64

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 1247.02

TOTAL `: 6645.66

Add for other enabling works @ 1.00% `: 66.46

Total cost for 10.00 cum `: 6712.11

Rate per cum `:`:`:`: 671.21

Rate approved per cum `:`:`:`: 671.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.17

ITEM: Providing and laying 250 mm thick sand blanket below embankment including cost of all

materials, machinery, labour, spreading to specified thickness etc., complete with lead upto

50 m and all lifts.

DATA:Consider 100 sqm sand blanket laying for rate analysis.

1. Requirement of materials :

Sand ( unscreened ) ( 100 x 0.25 x 1.02 ) 25.50 cum

2. Requirement of machinery :

No machinery proposed.

3. Requirement of work-force :

1 heavy mazdoor & 1 light mazdoor @ 10 cum / day for spreading collected sand.

Heavy mazdoor 2.5 Nos.

Light mazdoor 2.5 Nos.

Quantity

Description

52

in `.

Description

Rate

Rate

in `.

Quantity

Page 55: Data rates-Canal Works

CANAL AND ALLIED WORKS

RATE ANALYSIS UNIT : 100.00 sqm

A. MATERIALS:

Sl No Unit Amount

in `:

1 Sand ( unscreened ) cum 25.50 615.00 15682.5

0.00 0.00 0.00

Total `: 15682.50

Add for small Tools and Plants @ 1% `: 156.83

Add for Contractor's Profit @ 10% `: 1568.25

Add for Contractor's Overheads @ 5% `: 784.13

Add Royalty charges on Sand @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 18191.70

B. MACHINERY:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Heavy mazdoor Day 2.50 238.73 596.83

2 Light mazdoor Day 2.50 237.23 593.08

Total `: 1189.90

Add for small Tools and Plants @ 1% `: 11.90

Add for Contractor's Profit @ 10% `: 118.99

Add for hidden cost on Labour @ 15% `: 178.49

Add for Contractor's Overheads @ 5% `: 59.50

Total cost of Labour : `: 1558.77

ABSTRACT:

A. Cost of Materials including royalty charges `: 18191.70

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 1558.77

TOTAL `: 19750.47

Add for other enabling works @ 1.00% `: 197.50

Total cost for 100.00 sqm `: 19947.97

Rate per sqm `:`:`:`: 199.48

Rate approved per sqm `:`:`:`: 199.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.18

ITEM: Providing and constructing dry rubble rock-toe using rubble and stone chips from

approved source including cost of all materials, machinery, labour, hand packing rubble

53

Rate

Rate

QuantityPerticulars

Description

QuantityDescription

RateQuantity

in `.

in `.

in `.

Page 56: Data rates-Canal Works

CANAL AND ALLIED WORKS

and stone chips, finishing top and sides to required slopes etc., complete with lead upto 50 m

and all lifts.

DATA:Top width : NIL

Side slope upstream side : 1 (V) : 1 (H)

Side slope down stream side : 1 (V) : 1.5 (H)

Height : 1.00 m

Cross sectional area ( 0.00 + 2.50 ) x 1 / 2 : 1.25 sqm

1 1.5

1 1

Embankment 1.00 m

Consider 100 cum rock toe:

Length of rock toe for 100 cum ( 100 / 1.25 ) : 80 m

Surface finishing for D / S face ( 1.80 x 80 ) : 144 sqm

1. Requirement of materials :

Rubble ( 1.25 x 80 ) x 1.02 : 102.00 cum

Stone chips @ 15 % of rubble ( 102 x 0.15 ) : 15.30 cum

2. Requirement of machinery :

No machinery proposed.

3. Requirement of work-force :

Rock-toe material can be spread partly by dumping the material directly at spot and partly by

conveying manually. Consider 50 % by dumping and 50 % by manual conveying.

For conveying and laying :

Heavy mazdoor for rubble : 10 Nos.

Light mazdoor for chips : 2 Nos.

For packing and surface finishing.

Heavy mazdoor : 7 Nos.

Mason Class-II : 7 Nos.

Maistry : 1 No.

RATE ANALYSIS UNIT : 100.00 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 Rubble cum 102.00 400.00 40800.00

2 Stone chips cum 15.30 500.00 4080.00

3 Sundries LS 2.00 44.00 88.00

Total `: 44968.00

Add for small Tools and Plants @ 1% `: 449.68

Add for Contractor's Profit @ 10% `: 4496.80

Add for Contractor's Overheads @ 5% `: 2248.40

Add royalty charges for stones @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 52162.88

Perticulars Quantity

54

Rock-toe

Rate

SKETCH SHOWING DRY RUBBLE ROCK-TOE

( Filter details not shown )

in `.

Page 57: Data rates-Canal Works

CANAL AND ALLIED WORKS

B. MACHINERY:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Maistry Day 1.00 241.23 241.23

2 Mason Class-II Day 7.00 244.23 1709.61

3 Heavy mazdoor Day 17.00 238.73 4058.41

4 Light mazdoor Day 2.00 237.23 474.46

Total `: 6483.71

Add for small Tools and Plants @ 1% `: 64.84

Add for Contractor's Profit @ 10% `: 648.37

Add for hidden cost on Labour @ 15% `: 972.56

Add for Contractor's Overheads @ 5% `: 324.19

Total cost of Labour : `: 8493.66

ABSTRACT:

A. Cost of Materials including royalty charges `: 52162.88

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 8493.66

TOTAL `: 60656.54

Add for other enabling works @ 1.00% `: 606.57

Total cost for 100.00 cum `: 61263.11

Rate per cum `:`:`:`: 612.63

Rate approved per cum `:`:`:`: 613.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.19

ITEM: Providing and constructing longitudinal and cross graded filter drains using sand and

20 mm down approved clean, hard, graded aggregates satisfying specified filter creteria in layers

of specified thickness including cost of all materials, machinery, labour, laying to required

slopes, compaction etc., complete as per specifications and approved drawings with lead upto

50 m and all lifts.

DATA: Bottom width : 0.50 m

Side slopes : : 1( V ):1(H)

Depth : 0.50 m

Top width : 1.50 m

Cross sectional area ( 0.50 + 1.50 ) x 0.50 / 2 : 0.50 sqm

Thickness of sand layer : 150 mm

Thickness of 20 mm down CA layer : 200 mm

in `.

QuantityDescription Rate

in `.

Description Quantity Rate

55

Page 58: Data rates-Canal Works

CANAL AND ALLIED WORKS

15 cm

20 cm 20 mm down filter

1 15 cm Sand filter

1

0.5 m

Consider 100 cum filter drain:

Length of drain for 100 cum ( 100 / 0.50 ) : 200 m

Total quantity of filter materials with 2 % wastage ( 100 x 1.02 ) : 102 cum

1. Requirement of materials :

Quantity of 20 mm down filter aggregate with 2 % wastage

( 0.38 + 0.78 ) x 0.20 x 200 x 1.02 / 2 : 23.66 cum

20 mm down filter shall contain 75 % 20-10 mm & 25 % 10 mm down.

Quantity of filter sand with 2 % wastage ( 102.00 - 23.66 ) : 78.34 cum

2. Requirement of machinery :

No machinery proposed.

3. Requirement of work-force :

For conveying & laying sand ( 1 heavy & 1 light mazdoor 6 cum / day ).

Heavy mazdoor : 13 Nos.

Light mazdoor : 13 Nos.

For conveying & laying 20 mm down CA ( 1 heavy & 1 light 5 cum / day ).

Heavy mazdoor : 5 Nos.

Light mazdoor : 5 Nos.

Maistry : 1 No.

RATE ANALYSIS UNIT : 100.00 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 Sand ( unscreened ) cum 78.34 615.00 48179.10

2 Coarse aggregate 20-10 mm 75 % cum 17.75 950.00 16862.50

3 Coarse aggregate 10 mm down 25 % cum 5.91 1160.00 6855.60

Total `: 71897.20

Add for small Tools and Plants @ 1% `: 718.97

Add for Contractor's Profit @ 10% `: 7189.72

Add for Contractor's Overheads @ 5% `: 3594.86

Add royalty charges on Sand @ ( Included in material rate ) `: 0.00

Add royalty charges CA @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 83400.75

B. MACHINERY:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

Description Rate

in `.

in `.

Perticulars

SKETCH SHOWING DETAILS OF CROSS DRAIN

Quantity Rate

56

Quantity

Page 59: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR:

Sl No Unit Amount

in `:

1 Maistry Day 1.00 241.23 241.23

2 Heavy mazdoor Day 18.00 238.73 4297.14

3 Light mazdoor Day 18.00 237.23 4270.14

Total `: 8808.51

Add for small Tools and Plants @ 1% `: 88.09

Add for Contractor's Profit @ 10% `: 880.85

Add for hidden cost on Labour @ 15% `: 1321.28

Add for Contractor's Overheads @ 5% `: 440.43

Total cost of Labour : `: 11539.15

ABSTRACT:

A. Cost of Materials including royalty charges `: 83400.75

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 11539.15

TOTAL `: 94939.90

Add for other enabling works @ 1.00% `: 949.40

Total cost for 100.00 cum `: 95889.30

Rate per cum `:`:`:`: 958.89

Rate approved per cum `:`:`:`: 959.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.20

ITEM: Providing and constructing 500 mm thick vertical or inclined graded filter media consisting

of 150 mm thick sand layers and 200 mm thick 20 mm down coarse aggregate layer using

approved materials satisfying specified filter creteria including cost of all materials, machinery,

labour, laying to required slope, compaction etc., complete as per specifications and approved

drawings with lead upto 50 m and all lifts.

DATA:Total thickness of filter : 0.50 m

Thickness of sand layers ( 2 ) : 150 mm each

Thickness of 20 mm down CA layer : 200 mm

Consider 100 cum filter drain:

Area of drain for 100 cum ( 100 / 0.50 ) : 200 sqm

1. Requirement of materials :

Quantity of 20 mm down filter aggregate ( 200 x 1 x 0.20 x 1.02 ) : 40.80 cum

20 mm down filter shall contain 75 % 20-10 mm & 25 % 10 mm down

Quantity of filter sand ( 200 x 2 x 0.15 x 1.02 ) : 61.20 cum

2. Requirement of machinery :

No machinery proposed.

3. Requirement of work-force :

For conveying & laying sand ( 1 heavy & 1 light 6 cum / day ).

Heavy mazdoor : 10 Nos.

Light mazdoor : 10 Nos.

For conveying & laying 20 mm down CA ( 1 heavy & 1 light 5 cum / day ).

Heavy mazdoor : 8 Nos.

Light mazdoor : 8 Nos.

Maistry : 1 No.

in `.

Description Rate

57

Quantity

Page 60: Data rates-Canal Works

CANAL AND ALLIED WORKS

RATE ANALYSIS UNIT : 100.00 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 Sand ( unscreened ) cum 61.20 615.00 37638.00

2 Coarse aggregate 20-10 mm 75 % cum 30.60 950.00 29070.00

3 Coarse aggregate 10 mm down 25 % cum 10.20 1160.00 11832.00

Total `: 78540.00

Add for small Tools and Plants @ 1% `: 785.40

Add for Contractor's Profit @ 10% `: 7854.00

Add for Contractor's Overheads @ 5% `: 3927.00

Add royalty charges on Sand @ ( Included in material rate ) `: 0.00

Add royalty charges on CA @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 91106.40

B. MACHINERY:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Maistry Day 1.00 241.23 241.23

2 Heavy mazdoor Day 18.00 238.73 4297.14

3 Light mazdoor Day 18.00 237.23 4270.14

Total `: 8808.51

Add for small Tools and Plants @ 1% `: 88.09

Add for Contractor's Profit @ 10% `: 880.85

Add for hidden cost on Labour @ 15% `: 1321.28

Add for Contractor's Overheads @ 5% `: 440.43

Total cost of Labour : `: 11539.15

ABSTRACT:

A. Cost of Materials including royalty charges `: 91106.40

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 11539.15

TOTAL `: 102645.55

Add for other enabling works @ 1.00% `: 1026.46

Total cost for 100.00 cum `: 103672.00

Rate per cum `:`:`:`: 1036.72

Rate approved per cum `:`:`:`: 1037.00

in `.

Perticulars

Description Rate

Description

Rate

58

Quantity

RateQuantity

Quantity

in `.

in `.

Page 61: Data rates-Canal Works

CANAL AND ALLIED WORKS

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.21

ITEM: Providing and constructing graded filter media below and behind rock-toe consisting of

200 mm thick sand, 150 mm thick 20 mm down and 150 mm thick 40 mm down clean, hard,

graded coarse aggregate layers satisfying specified filter creteria behind rock-toe and 150 mm

thick sand, 200 mm thick 20 mm down and 650 mm thick 40 mm down clean, hard, graded

coarse aggregates layers satisfying speccified filter creiteria below rock-toe including cost of

all materials, machinery, labour, laying to specified thickness and slope, compaction etc.,

complete as per specifications and approved drawings with lead upto 50 m and all lifts.

DATA:Consider 80 m length of rock-toe for analysis.

1 1.5

1

Embankment

1.00 m

Cross drain

40 mm down filter

1.00 m 20 cm thick 20 mm filter

1 15 cm thick Sand filter

1. Quantity of filter behind rock-toe:

Sand unscreened ( 80 x 1.4 x 0.2 ) : 22.40 cum

20 mm down filter aggregate ( 80 x 1.4 x 0.15 ) : 16.80 cum

40 mm down filter aggregate ( 80 x 1.4 x 0.15 ) : 16.80 cum

Total : 56.00 cum

2. Quantity of filter below rock-toe:

Sand unscreened ( 0.5+0.8) x 0.15x 80 / 2 + ( 2 x 0.21x 0.85 x 80) : 36.37 cum

40 mm down filter aggregate ( 0.22+1.52 ) x 80 x 0.65 / 2 : 45.23 cum

40 mm filter shall contain 85 % 40-20 mm & 15 % 20-10 mm

20 mm down filter aggregate ( 0.5+2.5) x 80 x 0.5 - ( 36.37+ 45.23) : 38.40 cum

20 mm down filter shall contain 75 % 20-10 mm & 25 % 10 mm down

Total : 120.00 cum

Total quantity of filter ( 56.00 + 120.00 ) : 176.00 cum

Consider 176 cum filter for rate analysis.

3. Requirement of materials :

Sand unscreened ( 22.40 + 36.37 ) x 1.02 : 59.95 cum

40 - 20 mm filter aggregate ( 16.8 x 0.85 + 45.2 x 0.85 ) x 1.02 : 53.75 cum

20-10 mm filter aggregate

( 16.8 x 0.15 + 45.2 x 0.15 + 16.8 x 0.75 + 38.4 x 0.75 ) x 1.02 : 51.70 cum

10 mm below filter aggregate ( 16.8 x 0.25 + 38.4 x 0.25 ) x 1.02 : 14.10 cum

4. Requirement of machinery :

No machinery proposed.

5. Requirement of work-force :

For conveying & laying sand ( 1 heavy & 1 light mazdoor : 6 cum / day ).

Heavy mazdoor : 10 Nos.

Light mazdoor : 10 Nos.

1 0.5m

SKETCH SHOWING DETAILS OF FILTER BEHIND & BELOW ROCK-TOE

1

59

Rock-toe

Page 62: Data rates-Canal Works

CANAL AND ALLIED WORKS

For conveying & laying filter CA ( 1 heavy & 1 light mazdoor : 6 cum / day ).

Heavy mazdoor : 20 Nos.

Light mazdoor : 20 Nos.

Maistry : 1 No.

RATE ANALYSIS UNIT : 176.00 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 Sand ( unscreened ) cum 59.95 615.00 36869.25

2 Coarse aggregate 40-20 mm cum 53.75 740.00 39775.00

3 Coarse aggregate 20-10 mm cum 51.70 950.00 49115.00

4 Coarse aggregate 10 mm down cum 14.10 1160.00 16356.00

Total `: 142115.25

Add for small Tools and Plants @ 1% `: 1421.15

Add for Contractor's Profit @ 10% `: 14211.53

Add for Contractor's Overheads @ 5% `: 7105.76

Add royalty charges on Sand @ ( Included in material rate ) `: 0.00

Add royalty charges on CA @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 164853.69

B. MACHINERY:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Maistry Day 1.00 241.23 241.23

2 Heavy mazdoor Day 30.00 238.73 7161.90

3 Light mazdoor Day 30.00 237.23 7116.90

Total `: 14520.03

Add for small Tools and Plants @ 1% `: 145.20

Add for Contractor's Profit @ 10% `: 1452.00

Add for hidden cost on Labour @ 15% `: 2178.00

Add for Contractor's Overheads @ 5% `: 726.00

Total cost of Labour : `: 19021.24

ABSTRACT:

A. Cost of Materials including royalty charges `: 164853.69

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 19021.24

TOTAL `: 183874.93

60

Description

Perticulars

Rate

in `.

Description Rate

Quantity

Quantity Rate

in `.

in `.

Quantity

Page 63: Data rates-Canal Works

CANAL AND ALLIED WORKS

Add for other enabling works @ 1.00% `: 1838.75

Total cost for 176.00 cum `: 185713.68

Rate per cum `:`:`:`: 1055.19

Rate approved per cum `:`:`:`: 1055.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.22.1

ITEM: Providing and laying filter media for embankment consisting of 2 layers of poly-propeline

nonwoven filter fabric and 200 mm thick 20 mm down approved clean, hard, graded coarse

aggregate layer between filter fabric layers including cost of all materials, machinery, labour,

forming toe drain etc., complete with lead upto 50 m for aggregate and all leads for fabric

and all lifts.

22.a Using 200 gsm filter fabric.

DATA:Consider 100 sqm filter media laying.

200 gsm filter fabric is proposed in 2 layer with 20 cm thick 20 mm filter aggregate in between.

Filter fabric

20 mm down aggregate 20 cm th

CANAL

Hearting Casing

embankment embankment

Ground level

TYPICAL SKETCH SHOWING FILTER MEDIA USING FILTER FABRIC

1. Requirement of materials :

Filter fabric with 5 % for lapping and wastage ( 2 x 100 x 1.05 ) : 210.00 sqm

20 mm down aggregate with 2 % wastage ( 100 x 0.2 x 1.02 ) : 20.50 cum

20 mm down filter shall contain 75 % 20-10 mm & 25 % 10 mm down

2. Requirement of machinery :

No machinery proposed.

3. Requirement of work-force :

1 heavy mazdoor & 1 light mazdoor 6 cum / day.

Maistry 1 No.

Heavy mazdoor 3.5 Nos.

Light mazdoor 3.5 Nos.

RATE ANALYSIS UNIT : 100.00 sqm

A. MATERIALS:

Sl No Unit Amount

in `:

1 PP filter fabric 200 gsm sqm 210.00 220.00 46200.00

2 20 - 10 mm CA @ 75 % cum 15.40 950.00 14630.00

10 mm down CA @ 25 % cum 5.10 1160.00 5916.00

Total `: 66746.00

Add for small Tools and Plants @ 1% `: 667.46

Add for Contractor's Profit @ 10% `: 6674.60

Add for Contractor's Overheads @ 5% `: 3337.30

Add Royalty charges on CA @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 77425.36

Perticulars

61

RateQuantity

in `.

Page 64: Data rates-Canal Works

CANAL AND ALLIED WORKS

B. MACHINERY:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Maistry Day 1.00 241.23 241.23

2 Heavy mazdoor Day 3.50 238.73 835.56

3 Light mazdoor Day 3.50 237.23 830.31

Total `: 1907.09

Add for small Tools and Plants @ 1% `: 19.07

Add for Contractor's Profit @ 10% `: 190.71

Add for hidden cost on Labour @ 15% `: 286.06

Add for Contractor's Overheads @ 5% `: 95.35

Total cost of Labour : `: 2498.29

ABSTRACT:

A. Cost of Materials including royalty charges `: 77425.36

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 2498.29

TOTAL `: 79923.65

Add for other enabling works @ 1.00% `: 799.24

Total cost for 100.00 sqm `: 80722.88

Rate per sqm `:`:`:`: 807.23

Rate approved per sqm `:`:`:`: 807.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.22.2

ITEM: Providing and laying filter media for embankment consisting of 2 layers of poly-propeline

nonwoven filter fabric and 200 mm thick 20 mm down approved clean, hard, graded coarse

aggregate layer between filter fabric layers including cost of all materials, machinery, labour,

forming toe drain etc., complete with lead upto 50 m for aggregate and all leads for fabric

and all lifts.

22. b Using 250 gsm filter fabric.

DATA:Consider 100 sqm filter media laying.

1. Requirement of materials :

Filter fabric with 5 % for lapping and wastage ( 2 x 100 x 1.05 ) : 210.00 sqm

20 mm down aggregate with 2 % wastage ( 100 x 0.2 x 1.02 ) : 20.50 cum

20 mm down filter shall contain 75 % 20-10 mm & 25 % 10 mm down

2. Requirement of machinery :

No machinery proposed.

Description

Description Rate

Rate

Quantity

Quantity

62

in `.

in `.

Page 65: Data rates-Canal Works

CANAL AND ALLIED WORKS

3. Requirement of work-force :

1 heavy mazdoor & 1 light mazdoor 6 cum / day.

Maistry 1 No.

Heavy mazdoor 3.5 Nos.

Light mazdoor 3.5 Nos.

RATE ANALYSIS UNIT : 100.00 sqm

A. MATERIALS:

Sl No Unit Amount

in `:

1 PP filter fabric 250 gsm sqm 210.00 255.00 53550.00

2 20 - 10 mm CA @ 75 % cum 15.40 950.00 14630.00

10 mm down CA @ 25 % cum 5.10 1160.00 5916.00

Total `: 74096.00

Add for small Tools and Plants @ 1% `: 740.96

Add for Contractor's Profit @ 10% `: 7409.60

Add for Contractor's Overheads @ 5% `: 3704.80

Add Royalty charges on CA @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 85951.36

B. MACHINERY:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Maistry Day 1.00 241.23 241.23

2 Heavy mazdoor Day 3.50 238.73 835.56

3 Light mazdoor Day 3.50 237.23 830.31

Total `: 1907.09

Add for small Tools and Plants @ 1% `: 19.07

Add for Contractor's Profit @ 10% `: 190.71

Add for hidden cost on Labour @ 15% `: 286.06

Add for Contractor's Overheads @ 5% `: 95.35

Total cost of Labour : `: 2498.29

ABSTRACT:

A. Cost of Materials including royalty charges `: 85951.36

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 2498.29

TOTAL `: 88449.65

Perticulars

Quantity Rate

in `.

RateQuantity

RateDescription

in `.

in `.

Quantity

63

Description

Page 66: Data rates-Canal Works

CANAL AND ALLIED WORKS

Add for other enabling works @ 1.00% `: 884.50

Total cost for 100.00 sqm `: 89334.14

Rate per sqm `:`:`:`: 893.34

Rate approved per sqm `:`:`:`: 893.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.23

ITEM: Providing and constructing rockfill casing to canal embankment using graded stones and

spalls from approved source including cost of all materials, machinery, labour, spreading

stones and spalls in layers, hand packing, wedging, finishing surface to required slopes etc.,

complete with lead upto 50 m and all lifts.

DATA:Consider 100 cum rockfill casing to canal embankment.

Assume average 20 sqm surface finishing for 100 cum of rockfill.

1. Requirement of materials :

Quantity of rubble stones from quarry : 100.00 cum

Quantity of spalls from quarry @ 15 % : 15.00 cum

2. Requirement of machinery :

No machinery proposed.

3. Requirement of work-force :

Maistry 1 No.

For levelling and packing rock-fill :

Mason Cl- II 4 Nos.

Heavy mazdoor 4 Nos.

For surface finishing :

Mason Cl- II 2 Nos.

Heavy mazdoor 2 Nos.

Light mazdoor for supplying spalls and miscellaneous works. 2 Nos.

RATE ANALYSIS UNIT : 100.00 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 Rubble stones ( at quarry ) cum 100.00 400.00 40000.00

2 Stone chips / spalls ( at quarry ) cum 15.00 500.00 7500.00

Total `: 47500.00

Add for small Tools and Plants @ 1% `: 475.00

Add for Contractor's Profit @ 10% `: 4750.00

Add for Contractor's Overheads @ 5% `: 2375.00

Add Royalty charges on stones @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 55100.00

B. MACHINERY:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Contd

in `.

Rate

Quantity

Quantity

Rate

64

Perticulars

in `.

Description

Page 67: Data rates-Canal Works

CANAL AND ALLIED WORKS

B. MACHINERY ( Contd ) :

Sl No Unit Amount

in `:

Contd

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Maistry Day 1.00 241.23 241.23

2 Mason Cl- II Day 6.00 244.23 1465.38

3 Heavy mazdoor Day 6.00 238.73 1432.38

4 Light mazdoor Day 2.00 237.23 474.46

Total `: 3613.45

Add for small Tools and Plants @ 1% `: 36.13

Add for Contractor's Profit @ 10% `: 361.35

Add for hidden cost on Labour @ 15% `: 542.02

Add for Contractor's Overheads @ 5% `: 180.67

Total cost of Labour : `: 4733.62

ABSTRACT:

A. Cost of Materials including royalty charges `: 55100.00

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 4733.62

TOTAL `: 59833.62

Add for other enabling works @ 1.00% `: 598.34

Total cost for 100.00 cum `: 60431.96

Rate per cum `:`:`:`: 604.32

Rate approved per cum `:`:`:`: 604.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.24

ITEM: Providing and constructing rockfill casing to canal embankment using graded stones and

spalls available in dump yard including cost of all materials, machinery, labour, spreading

stones and spalls in layers, hand packing, wedging, finishing surface to required slopes etc.,

complete with lead upto 50 m and all lifts.

DATA:Consider 100 cum rockfill casing to canal embankment.

Assume average 20 sqm surface finishing for 100 cum of rockfill.

1. Requirement of materials :

Quantity of rubble stones from quarry : 100.00 cum

Quantity of spalls from quarry @ 15 % : 15.00 cum

2. Requirement of machinery :

No machinery proposed.

3. Requirement of work-force :

Maistry 1 No.

Description Rate

65

in `.

Quantity

Quantity Rate

in `.

Description

Page 68: Data rates-Canal Works

CANAL AND ALLIED WORKS

For sorting out materials in dump yard :

Crowbarman 2 Nos.

Heavy mazdoor 2 Nos.

For levelling and packing rock-fill :

Mason Cl- II 4 Nos.

Heavy mazdoor 4 Nos.

For surface finishing :

Mason Cl- II 2 Nos.

Heavy mazdoor 2 Nos.

Light mazdoor for supplying spalls and miscellaneous works. 2 Nos.

RATE ANALYSIS UNIT : 100.00 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 Rubble stones at dump yard cum 100.00 320.00 32000.00

2 Stone chips ( spalls ) at dump yard cum 15.00 385.00 5775.00

Total `: 37775.00

Add for small Tools and Plants @ 1% `: 377.75

Add for Contractor's Profit @ 10% `: 3777.50

Add for Contractor's Overheads @ 5% `: 1888.75

Add Royalty charges on stones @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 43819.00

B. MACHINERY:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Mason Cl- II Day 6.00 244.23 1465.38

2 Masistry Day 1.00 241.23 241.23

3 Crowbarman Day 2.00 239.73 479.46

4 Heavy mazdoor Day 8.00 238.73 1909.84

5 Light mazdoor Day 2.00 237.23 474.46

Total `: 4570.37

Add for small Tools and Plants @ 1% `: 45.70

Add for Contractor's Profit @ 10% `: 457.04

Add for hidden cost on Labour @ 15% `: 685.56

Add for Contractor's Overheads @ 5% `: 228.52

Total cost of Labour : `: 5987.18

QuantityPerticulars

Description

in `.

Quantity

Rate

Description Rate

66

Quantity

Rate

in `.

in `.

Page 69: Data rates-Canal Works

CANAL AND ALLIED WORKS

ABSTRACT:

A. Cost of Materials including royalty charges `: 43819.00

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 5987.18

TOTAL `: 49806.18

Add for other enabling works @ 1.00% `: 498.06

Total cost for 100.00 cum `: 50304.25

Rate per cum `:`:`:`: 503.04

Rate approved per cum `:`:`:`: 503.00

Note : Stones and spalls available in dump yard will be issued at specified issue rate in dump yard.

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.25

ITEM: Providing cohesive non-swelling (CNS) soil lining to canals using soil from approved borrow

area including cost of all materials, machinery, labour, spreading soil in layers of thickness

not more than 150 mm, breaking clods, watering, compacting to density control of not less

than 95 percent or as stipulated, dressing to required profile etc., complete with lead upto

1 km and all lifts.

DATA:Capacity of shovel bucket : 0.50 cum

Capacity of shovel bucket under heaped condition : 0.58 cum

Capacity of tipper : 5.00 cum

Lead for conveyance of soil : 1.00 km

Speed for loaded tipper under haul road condition : 20 km / hr

Speed for empty tipper under haul road condition : 25 km / hr

Turning and unloading time : 2.00 min

Shovel digging and loading cycle per bucket : 30 sec

1. Quantity of embankment :

In-situ qty / bucket for 15 % bulkage of soil ( 0.58 / 1.15 ) : 0.50 cum

In-situ quantity per load for 20 % bulkage of soil ( 5.0 / 1.2 ) say : 4.00 cum

Number of buckets per load ( 4.00 / 0.50 ) say : 8 buckets

Cycle time for loading 8 buckets ( 8 x 30 / 60 ) say : 4.00 min

Round trip cycle time for tipper:

Ideal cycle time of shovel for digging & loading : 4.00 min

Time for 1km haulage under load ( 60 / 20 ) : 3.00 min

Time for turning and un-loading : 2.00 min

Time for 1 km return trip ( 60 / 25 ) : 2.40 min

Time for turning and spotting : 0.50 min

Total : 11.90 min

No.of tippers to match corrected cycle time of shovel (11.90 / 4.00) : 3 Nos

Output of tipper / hr with 50 min working / hr ( 50 x 4.00 / 11.90 ) : 16.80 cum

Output for 3 tippers per day ( 3 x 16.80 x 8 ) say : 403 cum

The in-situ dry density of soil in borrow area will be generally less than dry density of compacted

embankment. Therefore, the rolled embankment quantity will be slightly less than the borrow

area in-situ quantity. The extent of shrinkage in quantity depends on the degree of compaction.

For 95 % density control of embankment a shrinkage factor of 5 % may be assumed.

Quantity of embankment considering 5 % shrinkage ( 403 x 0.95 ) say : 385 cum

Qty of soil for computing royalty charges @ 1.6 t / cum ( 385x1.6 ) : 616 tonnes

67

Page 70: Data rates-Canal Works

CANAL AND ALLIED WORKS

2. Stripping of borrow area :

Generally borrow area is stripped once in a week for 6 days requirement of soil.

Area to be stripped assuming 2.0 m depth of cut ( 403 x 6 / 2.0 ) : 1209 sqm

Depth of stripping : 0.20 m

Quantity of stripping with 5 % extra area ( 1209 x 1.05 x 0.20 ) : 254 cum

Output of dozer per hr with 50 min / hr working for stripping : 70 cum

Time required for stripping 254 cum : 3.60 hours

Consider 4.5 hours including time for levelling stripped siol / shifting time.

Requirement of dozer for one day work of 403 cum say : 0.75 hour

3. Collection of soil for embankment :

Deploy one 0.50 cum capacity shovel for 8 hours for digging and loading soil.

Deploy 3 tippers of 5.00 cum capacity for 8 hours to convey soil to embankment area.

4. Spreading soil in 150 mm layer :

In view of narrow width spreading soil by dozer may not be possible. Soil collected in heaps

along the edge of the canal can be pushed down by dozer and further spreading in layers of

specified thickness has to be by manual labour. Deploy dozer for 2 hours for pushing soil.

Output of heavy mazdoor for levelling per day : 20 cum

Quantity of loose soil to be spread ( 403 x 1.2 ) : 484 cum

As it may not be possible to take roller upto edges providing some roller margin is necessary.

Quantity of loose soil to be spread with 10 % extra for roller margin on canal side:

( 403 x 1.20 x 1.10 ) say : 530 cum

Consider 27 Heavy mazdoors for levelling 530 cum soil including extra soil laid for roller margin.

5. Watering :

Generally soil in the borrow area will be in moist condition. In the beginning of the season no

watering may be necessary and in summer months about 8 to 10 percent watering may be

needed to maintain soil moisture within OMC plus or minus 3 percent limit. Assuming seasonal

average of 5 % watering by weight, the daily requirement of water for 385 cum of embankment

will be about 4 tanker loads of 8000 ltrs each.

Deploy 8000 ltr capacity water tanker for 4 hours daily for watering before rolling.

Deploy 5 hp pump for 2 hours for pumping water to water tanker.

Consider 2 heavy mazdoors for spraying water.

6. Compaction :

Since dozer is not considered for spreading soil about 25 percent extra roller passes needed.

Generally about 10 passes of diesel road roller is adequate for achieving 95 percent density

control for 20 cm thick loose layer.

Effective length of roller drum : 1.50 m

Speed of roller per hour : 3.0 km

Thickness of layer : 0.15 m

Number of roller passes to achieve specified density control : 10 Nos

Output of roller / hr with 50 min /hr working and 75 % effenciancy

( 1.5 x 3000 x 0.15 x 0.75 / 10 ) x 50 / 60 say : 40 cum

Time for rolling 484 cum spread soil ( 484 / 40 ) say : 12 hours

7. Sorting out / sectioning etc :

Assume 2 heavy and 2 light mazdoors for sorting out.

No extra labour required for sectioning as trimming roller margin forms part of the soil collection

for bed lining.However 5 heavy mazdoors considered for finishing to required slopes.

68

Page 71: Data rates-Canal Works

CANAL AND ALLIED WORKS

RATE ANALYSIS UNIT : 385.00 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Add Royalty charges on 577.50 t soil @Rs: 20.00 / tonne `: 11550.00

Total cost of Materials : `: 11550.00

B. MACHINERY:

Sl No Unit Amount

in `:

1 Shovel 0.5 cum Hour 8.00 799.00 6392.00

Fuel / Energy charges Hour 8.00 454.00 3632.00

2 Angle dozer 90 hp Hour 2.75 1273.00 3500.75

Fuel / Energy charges Hour 2.75 582.00 1600.50

3 Tipper 5 cum Hour 24.00 309.00 7416.00

Fuel / Energy charges Hour 24.00 286.00 6864.00

4 Pump 5 hp ( diesel ) Hour 2.00 7.00 14.00

Fuel / Energy charges Hour 2.00 76.00 152.00

5 Water tanker 8000 ltr Hour 4.00 306.00 1224.00

Fuel / Energy charges Hour 4.00 286.00 1144.00

6 Diesel road roller 8-10 tonne Hour 12.00 252.00 3024.00

Fuel / Energy charges Hour 12.00 681.00 8172.00

7 Sundries LS 5.00 44.00 220.00

Total `: 43355.25

Add for small Tools and Plants @ 1% `: 433.55

Add for Contractor's Profit on DPOL / Energy @ 10% `: 2178.45

Add for Contractor's Overheads @ 5% `: 2167.76

Total hire charges of Machinery : `: 48135.02

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Shovel Hour 8.00 128.00 1024.00

2 Crew for Dozer Hour 2.75 128.00 352.00

3 Crew for Tipper Hour 24.00 95.00 2280.00

4 Crew for Pump Hour 2.00 60.00 120.00

5 Crew for Water tanker Hour 4.00 95.00 380.00

6 Crew for Road roller Hour 12.00 121.00 1452.00

7 Maistry Day 2.00 241.23 482.46

8 Heavy mazdoor Day 36.00 238.73 8594.28

9 Light mazdoor Day 2.00 237.23 474.46

Total `: 15159.20

Add for small Tools and Plants @ 1% `: 151.59

Contd

Description

69

Quantity

in `.

Description

Rate

Perticulars Rate

Quantity

in `.

Rate

in `.

Quantity

Page 72: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR ( Contd ):

Sl No Unit Amount

in `:

Contd

Add for Contractor's Profit @ 10% `: 1515.92

Add for hidden cost on Labour @ 15% `: 2273.88

Add for Contractor's Overheads @ 5% `: 757.96

Total cost of Labour : `: 19858.55

ABSTRACT:

A. Cost of Materials including royalty charges `: 11550.00

B. Hire charges of Machinery `: 48135.02

C. Cost of Labour `: 19858.55

TOTAL `: 79543.57

Add for other enabling works @ 1.00% `: 795.44

Total cost for 385.00 cum `: 80339.00

Rate per cum `:`:`:`: 208.67

Rate approved per cum `:`:`:`: 209.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.26

ITEM: Providing cohesive non-swelling ( CNS ) soil lining to canal using soil collected in heaps

along the edge of canal requiring CNS soil lining as part of the disposal of excavated soil from

canal excavation in CNS soil reach including cost of all machinery, labour, spreading in

layers of thickness not more than 150 mm, breaking clods,watering, compacting to density

control of not less than 95 percent or as stipulated, dressing to required profile etc.,complete

with lead upto upto 50 m and all lifts.

DATA:Daily progress of CNS lining assumed as in Item: 25. : 395 cum

1. Stripping of borrow area :

No stripping of borrow involved as the soil is from canal excavation.

2. Collection of soil for CNS lining :

It is assumed that cohesive non-swelling soil from canal excavation is conveyed and collected

along the edge of the canal reach requiring CNS soil lining and conveyance charges form part

of canal excavation.

Only local rehandling of soil to lining area is required.

3. Spreading soil in 150 mm layer :

For 395 cum finished lining 530 cum soil is to be spread including soil for roller margin.

Total quantity of soil to be laid for lining : 530 cum

Deploy dozer for about 2 hours for pushing soil to lining area.

Output of 1 heavy mazdoor for spreading soil : 20 cum / day

Deploy 27 heavy mazdoors.

4. Watering :

Generally the soil from excavation will be in moist condition. In the beginning of season no

watering may be necessary and in summer months about 8 to 10 percent watering may be

needed to maintain the soil moisture within OMC plus or minus 3 percent limit. However, for

any time gap between excavation and rehandling relatively more watering is needed. Assuming

seasonal average of 6 % watering by weight, requirement of water for 395 cum of embankment

will be about 5 tanker loads of 8000 ltrs each.

Deploy 8000 ltr capacity water tanker for 5 hours daily for watering before rolling.

70

in `.

Description Quantity Rate

Page 73: Data rates-Canal Works

CANAL AND ALLIED WORKS

Deploy 5 hp pump for 2.5 hours for pumping water to water tanker.

Deploy 2 heavy mazdoors for spraying water.

5. Compaction :

Since dozer is not considered for spreading soil about 25 percent extra roller passes needed.

Generally 10 passes of diesel road roller is adequate for achieving 95 percent density control for

15 cm thick loose layer.

Effective length of roller drum : 1.50 m

Speed of roller per hour : 3.0 km

Thickness of layer : 0.15 m

Number of roller passes to achieve specified density control : 10 Nos

Output of roller / hr with 50 min / hr working and 70 % job / management effenciancy

( 1.5 x 3000 x 0.15 x 0.70 / 10 ) x 50 / 60 say : 40 cum

Time for rolling 484 cum spread soil ( 484 / 40 ) say : 12 hours

6. Sorting out / sectioning etc :

Assume 2 heavy and 2 light mazdoors for sorting out.

No extra labour considered for sectioning as trimming roller margin forms part of soil collection

for bed lining.However for finishing the surface to required slopes etc deploy 5 heavy mazdoors.

RATE ANALYSIS UNIT : 395.00 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Add Royalty charges on592.5 t soil @ Rs: 20.00 / tonne `: 11850.00

Total cost of Materials : `: 11850.00

B. MACHINERY:

Sl No Unit Amount

in `:

1 Angle Dozer 90 hp Hour 2.00 1273.00 2546.00

Fuel / Energy charges Hour 2.00 582.00 1164.00

2 Pump 5 hp ( diesel ) Hour 2.50 7.00 17.50

Fuel / Energy charges Hour 2.50 76.00 190.00

3 Water tanker 8000 ltr Hour 5.00 306.00 1530.00

Fuel / Energy charges Hour 5.00 286.00 1430.00

4 Diesel road roller 8-10 tonne Hour 12.00 252.00 3024.00

Fuel / Energy charges Hour 12.00 681.00 8172.00

5 Sundries LS 5.00 44.00 220.00

Total `: 18293.50

Add for small Tools and Plants @ 1% `: 182.94

Add for Contractor's Profit on DPOL / Energy @ 10% `: 1117.60

Add for Contractor's Overheads @ 5% `: 914.68

Total hire charges of Machinery : `: 20508.71

Perticulars

Description

71

in `.

Quantity

in `.

Rate

RateQuantity

Page 74: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Dozer Hour 2.00 128.00 256.00

2 Crew for Pump Hour 2.50 60.00 150.00

3 Crew for Water tanker Hour 5.00 95.00 475.00

4 Crew for Road roller Hour 12.00 121.00 1452.00

5 Maistry Day 2.00 241.23 482.46

6 Heavy mazdoor

for spreading and levelling soil Day 29.00 238.73 6923.17

for sorting-out and watering Day 2.00 238.73 477.46

for sectioning and finishing Day 5.00 238.73 1193.65

7 Light mazdoor Day 2.00 237.23 474.46

Total `: 11884.20

Add for small Tools and Plants @ 1% `: 118.84

Add for Contractor's Profit @ 10% `: 1188.42

Add for hidden cost on Labour @ 15% `: 1782.63

Add for Contractor's Overheads @ 5% `: 594.21

Total cost of Labour : `: 15568.30

ABSTRACT:

A. Cost of Materials including royalty charges `: 11850.00

B. Hire charges of Machinery `: 20508.71

C. Cost of Labour `: 15568.30

TOTAL `: 47927.01

Add for other enabling works @ 1.00% `: 479.27

Total cost for 395.00 cum `: 48406.28

Rate per cum `:`:`:`: 122.55

Rate approved per cum `:`:`:`: 123.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.27

ITEM: Providing and fixing 200 x 200 x 750 mm size top surface neatly dressed canal bed level

stone including cost of all materials, labour, excavation, fixing in position to correct level etc.,

complete with lead upto 50 m and all lifts.

DATA:Consider 0.5 hour for excavation and fixing each stone with 50 min / hour working.

1 stone chiseller Cl- I for top surface dressing of 16 stones / day.

Consider fixing 32 canal bed level stones for rate analysis.

1. Requirement of materials :

Only labour charges involved for this item.

2. Requirement of machinery :

No machinery proposed.

3. Requirement of workforce :

Maistry : 1 No.

Stone chiseller Cl- I : 2 Nos.

Heavy mazdoor : 2 Nos.

Description

72

Quantity Rate

in `.

Page 75: Data rates-Canal Works

CANAL AND ALLIED WORKS

RATE ANALYSIS UNIT : 32.00 Nos.

A. MATERIALS:

Sl No Unit Amount

in `:

1 Rough stone 200 x 200 x 750 mm Each 32.00 20.00 640.00

0.00 0.00 0.00

Total `: 640.00

Add for small Tools and Plants @ 1% `: 6.40

Add for Contractor's Profit @ 10% `: 64.00

Add for Contractor's Overheads @ 5% `: 32.00

Add for Royalty charges on stone @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 742.40

B. MACHINERY:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Maistry Day 1.00 241.23 241.23

2 Stone chiseller Cl- I Day 2.00 244.73 489.46

3 Heavy mazdoor Day 2.00 238.73 477.46

Total `: 1208.15

Add for small Tools and Plants @ 1% `: 12.08

Add for Contractor's Profit @ 10% `: 120.82

Add for hidden cost on Labour @ 15% `: 181.22

Add for Contractor's Overheads @ 5% `: 60.41

Total cost of Labour : `: 1582.68

ABSTRACT:

A. Cost of Materials including royalty charges `: 742.40

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 1582.68

TOTAL `: 2325.08

Add for other enabling works @ 1.00% `: 23.25

Total cost for 32.00 Nos. `: 2348.33

Rate per Each `:`:`:`: 73.39

Rate approved per Each `:`:`:`: 73.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.28

ITEM: Providing, fabricating and placing in position reinforcement steel for RCC works including

Perticulars

Rate

in `.

in `.

RateDescription

73

Description

RateQuantity

Quantity

Quantity

in `.

Page 76: Data rates-Canal Works

CANAL AND ALLIED WORKS

cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking,

lapping, welding wherever required, tying with 1.25 mm diameter soft annealed steel wire

etc., complete with initial lead upto 50 and all lifts.

DATA:Lap jointing considered assuming all reinforcement below 28 mm dia.

Quantity of binding wire per tonne : 10 kg

Wastage of steel : 2.5 percent

Consider fabrication and placing 1 tonne steel for rate analysis.

1. Requirement of materials :

Reinforcement steel with 2.5 % wastage ( 1 x 1.025 ) : 1.025 tonne

Binding wire 1.25 mm dia @ 10 kg / t ( 1 x 10 ) : 10 kg

2. Requirement of machinery :

No machinery required.

3. Requirement of workforce :

Cleaning and straightening : 2 Bar benders & 2 Heavy mazdoors

Marking, cutting, bending & stacking : 2 Bar benders & 4 Heavy mazdoors

Fixing & tying with binding wire : 2 Bar benders & 4 Heavy mazdoors

Checking / correcting & misc. : 1 Bar bender & 1 Heavy mazdoor

Maistry : 1 No.

RATE ANALYSIS UNIT : 1000.00 kg

A. MATERIALS:

Sl No Unit Amount

in `:

1 Rein.Steel with 2.5 % wastage kg 1025.00 48.48 49686.88

2 Binding wire 1.25 mm dia kg 10.00 60.00 600.00

3 Sundries ( chairs / spacers etc ) LS 5.00 44.00 220.00

Total `: 50506.88

Add for small Tools and Plants @ 1% `: 505.07

Add for Contractor's Profit @ 10% `: 5050.69

Add for Contractor's Overheads @ 5% `: 2525.34

Total cost of Materials : `: 58587.98

B. MACHINERY:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Bar bender Day 7.00 256.73 1797.11

2 Heavy mazdoor Day 11.00 238.73 2626.03

Total `: 4423.14

Contd

Rate

Perticulars Rate

in `.

RateDescription

Description

74

in `.

in `.

Quantity

Quantity

Quantity

Page 77: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR ( Contd ) :

Sl No Unit Amount

in `:

Contd

Add for small Tools and Plants @ 1% `: 44.23

Add for Contractor's Profit @ 10% `: 442.31

Add for hidden cost on Labour @ 15% `: 663.47

Add for Contractor's Overheads @ 5% `: 221.16

Total cost of Labour : `: 5794.31

ABSTRACT:

A. Cost of Materials `: 58587.98

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 5794.31

TOTAL `: 64382.29

Add for other enabling works @ 1.00% `: 643.82

Total cost for 1000.00 kg `: 65026.11

Rate per kg `:`:`:`: 65.03

Rate approved per kg `:`:`:`: 65.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.29.1

ITEM: Providing and laying 80 mm thick in-situ M-15 ( 28 days cube compressive strength not less

than 15 N / sqmm ) grade cement concrete using 20 mm down approved, clean, hard,

graded aggregates for canal lining deploying batching plant, transit mixer and vibratory

cylinder type mechanical paver including cost of all materials, machinery, labour, cleaning,

batching, mixing, placing in position, forming contraction joints, fixing PVC joint sealing strips,

finishing, curing, shifting of paver from one side to other side of canal etc., complete with lead

upto 1 km and all lifts. ( Cement content: 23.30 kg / sqm with use of super plasticiser )

DATA:Thickness of lining : 80 mm

Consider Cylinder type Mechanical paver with one side paving arrangement for CC lining.

Average output of mechanical paver / hour for 80 mm thick lining : 100 sqm

For 1 cum CC :- Coarse aggregates : 0.77 cum Blending ratio : 65 :35

Fine aggregate : 0.47 cum Cement content : 270 kg Super plasticizer : 0.8 ltr

Wastage : 1 % for cement and 2 % for coarse & fine aggregates.

Output of paver / hour with 50 min per hour working.( 100 x 50 / 60 ) say : 80 sqm

Qty of CC for paver / hr for 80 mm thickness ( 80 x 0.08 ) : 6.40 cum

Add extra qty for curvature at bed & side junction @ 6 % : 0.40 cum

Corrected qty of concrete for 80 sqm : 6.80 cum

Rated capacity of batching plant with 70 % efficiency for 6.80 cum / hour output:

( 6.80 x 60 / 50 / 0.7 ) : 11.65 cum / hr

Consider 15 cum per hour capacity Batching & mixing plant for concrete production.

Consider shifting & re-erection of Batching plant at 5 km interval.

Consider 2 cum capacity Transit mixers for conveying CC from BP to paver site.

Round trip cycle time for transit mixer :

Turning & spotting at BP : 2.00 min

Loading CC : 10.00 min

Conveying from BP to Paver site ( average ) : 5.00 min

Turning & spotting at Paver site : 2.00 min

in `.

RateDescription Quantity

75

Page 78: Data rates-Canal Works

CANAL AND ALLIED WORKS

Unloading concrete at paver site : 20.00 min

Return trip to BP ( average ) : 5.00 min

Total : 44.00 min

Output of transit mixer / hr with 50 min / hr working: ( 50 x 2 / 44 ) : 2.27 cum

Hourly requirement of concrete for 80 sqm / hour lining : 6.80 cum

No.of Transit mixers to match 6.80 cum / hr ( 6.8 / 2.27 ) say : 3 Nos.

Daily progress of lining @ 80 sqm / hour ( 8 x 80 ) : 640 sqm

Quantity of concrete for 640 sqm @ 6.80 cum / 80 sqm : 54.40 cum

Consider 640 sqm lining requiring 54.40 cum concrete for rate analysis.

1. Requirement of materials:

Cement for mix with 1 % wastage ( 54.40 x 270 x 1.01 ) : 14835 kg

Cement for incidentals @ 5 kg / cum ( 54.40 x 5 ) : 272 kg

Coarse aggregate 20-10 mm size ( 54.40 x 0.77 x 0.65 x 1.02 ) : 27.75 cum

Coarse aggregate 10-4.75 mm size ( 54.40 x 0.77 x 0.35 x 1.02 ) : 14.95 cum

Fine aggregate ( 54.40 x 0.47 x 1.02 ) : 26.10 cum

Super plasticiser ( 54.40 x 0.8 x 1.02 ) : 44.40 ltrs

PVC sealing strip in 4 m x 4 m grid @ 0.5 m / sqm ( 640 x 0.5 ) : 320 Rm

Curing compound @ 0.2 ltr / sqm ( 640 x 0.2 x 1.1 ) : 141 ltrs

2. Requirement of machinery :

Deploy 15 cum per hour capacity Batching & mixing plant for 8 hours for concrete production.

Deploy 3 Transit mixers for 8 hours for conveyance of CC from BP to Paver site.

Deploy 100 sqm / hour Mechanical paver for 8 hours for concrete lining.

Deploy about 50 KVA capacity DG set with all accessories for 9 hours at BP site.

Deploy about 30 KVA capacity DG set with all accessories for 9 hours at Paver site.

Deploy 0.5 cum capacity Shovel for 4 hours at BP site for pushing CA / FA from stock pile.

Deploy 2 Pumps 5 hp for 4 hour for water requirement at BP and Paver sites.

Deploy 1 Water tanker 8000 ltr capacity for 8 hour for water required at BP and Paver sites.

3. Formwork & scaffolding :

No formwork / scaffolding required for lining by paver.

4. Requirement of workforce ( other than machinery crew ) :

Mason Class I for finishing & fixing PVC strips : 2 Nos.

Mechanic : 2 Nos.

Fitter : 1 No.

Electrician : 2 Nos.

Maistry ( 1 at BP and 1 at Paver sites ) : 2 Nos.

Heavy mazdoor ( BP site for feeding cement to silo & misc. works ) : 10 Nos.

Heavy mazdoor ( Paver site ) : 10 Nos.

Light mazdoor ( Paver site ) : 5 Nos.

5. Use rate of materials :

Cost of paving cylinder @ `: 27800.00 / Each. `: 27800.00

Life of paving cylinder in sqm of lining : 40000

Use rate of paving cylinder / sqm ( cost / life ) `: 0.70

Add for repair charges at 25 % `: 0.17

Use rate of paving cylinder / sqm including repairs. `: 0.87

76

Page 79: Data rates-Canal Works

CANAL AND ALLIED WORKS

RATE ANALYSIS UNIT : 640.00 sqm

A. MATERIALS:

Sl No Unit Amount

in `:

1 Cement 43 Gr kg 14835.00 7.50 111262.50

Cement for incidentals @ 5 kg / cum kg 272.00 7.50 2040.00

2 Coarse aggregate 20-10 mm cum 27.75 950.00 26362.50

Coarse aggregate 10-4.75 mm cum 14.95 1160.00 17342.00

3 Fine aggregate ( screened ) cum 26.10 730.00 19053.00

4 Super plasticiser ltr 44.40 105.00 4662.00

5 PVC sealing strip Rm 320.00 45.00 14400.00

6 Curing compound ltr 141.00 134.00 18894.00

7 Use rate of paving cylinder sqm 640.00 0.87 556.00

8 Sundries LS 50.00 44.00 2200.00

Total `: 216772.00

Add for small Tools and Plants @ 1% `: 2167.72

Add for Contractor's Profit @ 10% `: 21677.20

Add for Contractor's Overheads @ 5% `: 10838.60

Add Royalty charges on CA @ ( Included in material rate ) `: 0.00

Add Royalty charges on FA @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 251455.52

B. MACHINERY:

Sl No Unit Amount

in `:

1 Batching plant 15 cum/hr rated capacity Hour 8.00 334.00 2672.00

Lubricants etc @ 5 % Hour 8.00 16.70 133.60

2 Transit mixer 3 Nos Hour 24.00 708.00 16992.00

Fuel / Energy charges Hour 24.00 832.00 19968.00

3 Mechanical paver Hour 8.00 311.00 2488.00

Lubricants etc @ 5 % Hour 8.00 15.55 124.40

4 DG set for batching plant 50 KVA Hour 9.00 104.00 936.00

Fuel / Energy charges Hour 9.00 908.00 8172.00

5 DG set for paver 30 KVA Hour 9.00 66.00 594.00

Fuel / Energy charges Hour 9.00 605.00 5445.00

6 Shovel 0.5 cum / Loader Hour 4.00 799.00 3196.00

Fuel / Energy charges Hour 4.00 454.00 1816.00

7 Water tanker Hour 8.00 306.00 2448.00

Fuel / Energy charges Hour 8.00 286.00 2288.00

8 Pump 5 hp(diesel) 2 Nos. 4 hrs each Hour 8.00 7.00 56.00

Fuel / Energy charges Hour 8.00 76.00 608.00

9 Sundries ( power line etc ) LS 50.00 44.00 2200.00

Total `: 70137.00

Add for small Tools and Plants @ 1% `: 701.37

Add for Contractor's Profit on DPOL / Energy @ 10% `: 4075.50

Add for Contractor's Overheads @ 5% `: 3506.85

Total hire charges of Machinery : `: 78420.72

Perticulars

Description

Quantity Rate

77

in `.

Quantity Rate

in `.

Page 80: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Batching plant Hour 8.00 181.00 1448.00

2 Crew for Transit mixer Hour 24.00 151.00 3624.00

3 Crew for Concrete paver Hour 8.00 241.00 1928.00

4 Crew for DG set Hour 18.00 75.00 1350.00

5 Crew for Shovel Hour 4.00 128.00 512.00

6 Crew for Water tanker Hour 8.00 95.00 760.00

7 Crew for Pump Hour 8.00 60.00 480.00

8 Mason Class I Day 2.00 256.73 513.46

9 Mechanic Day 2.00 254.73 509.46

10 Fitter Day 1.00 254.73 254.73

11 Electrician Day 2.00 241.23 482.46

12 Maistry Day 2.00 241.23 482.46

13 Heavy mazdoor ( BP site ) Day 10.00 238.73 2387.30

Heavy mazdoor ( Paver site ) Day 10.00 238.73 2387.30

14 Light mazdoor ( Paver site ) Day 5.00 237.23 1186.15

Total `: 18305.32

Add for small Tools and Plants @ 1% `: 183.05

Add for Contractor's Profit @ 10% `: 1830.53

Add for hidden cost on Labour @ 15% `: 2745.80

Add for Contractor's Overheads @ 5% `: 915.27

Total cost of Labour : `: 23979.97

ABSTRACT:

A. Cost of Materials including royalty charges `: 251455.52

B. Hire charges of Machinery `: 78420.72

C. Cost of Labour `: 23979.97

TOTAL `: 353856.21

Add for shifting & re-erection of BP @ 2.00% `: 7077.12

Add for LH / RH shifting & erection of Paver @ 0.50% `: 1769.28

Add for ledge cutting / erection of tracks etc @ 1.00% `: 3538.56

Add for other enabling works @ 1.00% `: 3538.56

Total cost for 640.00 sqm `: 369779.74

Rate per sqm `:`:`:`: 577.78

Rate approved per sqm `:`:`:`: 578.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.29.2

ITEM: Providing and laying 100 mm thick in-situ M-15 ( 28 days cube compressive strength not less

than 15 N / sqmm ) grade cement concrete using 20 mm down approved, clean, hard,

graded aggregates for canal lining deploying batching plant, transit mixer and vibratory

cylinder type mechanical paver including cost of all materials, machinery, labour, cleaning,

batching, mixing, placing in position, forming contraction joints, fixing PVC joint sealing strips,

finishing, curing, shifting of paver from one side to other side of canal etc., complete with lead

upto 1 km and all lifts. ( Cement content: 28.90 kg / sqm with use of super plasticiser )

DATA:Thickness of lining : 100 mm

Consider Cylinder type Mechanical paver with one side paving arrangement for CC lining.

in `.

78

QuantityDescription Rate

Page 81: Data rates-Canal Works

CANAL AND ALLIED WORKS

Average output of mechanical paver / hour for 100 mm thick lining : 80 sqm

For 1 cum CC :- Coarse aggregates : 0.77 cum Blending ratio : 65 :35

Fine aggregate : 0.47 cum Cement content : 270 kg Super plasticizer : 0.8 ltr

Wastage : 1 % for cement and 2 % for coarse & fine aggregates.

Output of paver / hour with 50 min per hour working ( 80 x 50 / 60 ) say : 65 sqm

Quantity of CC for paver / hour ( 65 x 0.10 ) : 6.50 cum

Add extra quantity for curvature at bed & side junction @ 5 % : 0.30 cum

Corrected qty of concrete for 65 sqm : 6.80 cum

Rated capacity of batching plant required with 70 % efficiency for 6.80 cum / hour output:

( 6.80 x 60 / 50 / 0.7 ) : 11.65 cum / hr

Consider 15 cum per hour capacity Batching & mixing plant for concrete production.

Consider shifting & re-erection of Batching plant at 5 km interval.

Consider 2 cum capacity Transit mixers for conveying CC from BP to paver site.

Round trip cycle time for transit mixer:

Turning & spotting at BP : 2.00 min

Loading CC : 10.00 min

Conveying from BP to Paver site ( average ) : 5.00 min

Turning & spotting at Paver site : 2.00 min

Unloading concrete at paver site : 20.00 min

Return trip to BP ( average ) : 5.00 min

Total : 44.00 min

Output of transit mixer / hr with 50 min / hr working: ( 50 x 2 / 44 ) : 2.27 cum

Hourly requirement of concrete for 65 sqm / hour lining : 6.80 cum

No. of Transit mixers to match 6.80 cum / hr ( 6.80 / 2.27 ) : 3 Nos.

Daily progress of lining @ 65 sqm / hour : 520 sqm

Quantity of concrete for 520 sqm @ 6.80 cum / 65 sqm : 54.40 cum

Consider 520 sqm lining requiring 54.40 cum concrete for rate analysis.

1. Requirement of materials:

Cement for mix with 1 % wastage ( 54.40 x 270 x 1.01 ) : 14835 kg

Cement for incidentals @ 5 kg / cum ( 54.40 x 5 ) : 272 kg

Coarse aggregate 20-10 mm size ( 54.40 x 0.77 x 0.65 x 1.02 ) : 27.75 cum

Coarse aggregate 10-4.75 mm size ( 54.40 x 0.77 x 0.35 x 1.02 ) : 14.95 cum

Fine aggregate ( 54.40 x 0.47 x 1.02 ) : 26.10 cum

Super plasticiser ( 54.40 x 0.8 x 1.02 ) : 44.40 ltrs

PVC sealing strip in 4 m x 4 m grid @ 0.5 m / sqm ( 520 x 0.5 ) : 260 Rm

Curing compound @ 0.2 ltr / sqm ( 520 x 0.2 x 1.1 ) : 115 ltrs

2. Requirement of machinery :

Deploy 15 cum per hour capacity Batching & mixing plant for 8 hours for concrete production.

Deploy 3 Transit mixers for for 8 hours for conveyance of CC from BP to Paver site.

Deploy 80 sqm / hour Mechanical paver for 8 hours for concrete lining.

Deploy about 50 KVA capacity DG set with all accessories for 9 hours at BP site.

Deploy about 30 KVA capacity DG set with all accessories for 9 hours at Paver site.

Deploy 0.5 cum capacity Shovel for 4 hours at BP site for pushing CA / FA from stock pile.

Deploy 2 Pumps 5 hp for 4 hour for water requirement at BP and Paver sites.

Deploy 1 Water tanker 8000 ltr capacity for 8 hour for water required at BP and Paver sites.

3. Formwork & scaffolding :

No formwork / scaffolding required for lining by paver.

4. Requirement of workforce ( other than machinery crew ) :

Mason Class I for finishing & fixing PVC strips : 2 Nos.

79

Page 82: Data rates-Canal Works

CANAL AND ALLIED WORKS

Mechanic : 2 Nos.

Fitter : 1 No.

Electrician : 2 Nos.

Maistry ( 1 at BP and 1 at Paver sites ) : 2 Nos.

Heavy mazdoor ( BP site for feeding cement to silo & misc. works ) : 10 Nos.

Heavy mazdoor ( Paver site ) : 10 Nos.

Light mazdoor ( Paver site ) : 5 Nos.

5. Use rate of materials :

Cost of paving cylinder @ `: 27800.00 / Each. `: 27800.00

Life of paving cylinder in sqm of lining : 40000

Use rate of paving cylinder / sqm ( cost / life ) `: 0.70

Add for repair charges at 25 % `: 0.17

Use rate of paving cylinder / sqm including repairs. `: 0.87

RATE ANALYSIS UNIT : 520.00 sqm

A. MATERIALS:

Sl No Unit Amount

in `:

1 Cement 43 Gr kg 14835.00 7.50 111262.50

Cement for incidentals @ 5 kg / cum kg 272.00 7.50 2040.00

2 Coarse aggregate 20-10 mm cum 27.75 950.00 26362.50

Coarse aggregate 10-4.75 mm cum 14.95 1160.00 17342.00

3 Fine aggregate ( screened ) cum 26.10 730.00 19053.00

4 Super plasticiser ltr 44.40 105.00 4662.00

5 PVC sealing strip Rm 260.00 45.00 11700.00

6 Curing compound ltr 115.00 134.00 15410.00

7 Use rate of paving cylinder sqm 520.00 0.87 451.75

8 Sundries LS 50.00 44.00 2200.00

Total `: 210483.75

Add for small Tools and Plants @ 1% `: 2104.84

Add for Contractor's Profit @ 10% `: 21048.38

Add for Contractor's Overheads @ 5% `: 10524.19

Add Royalty charges on CA @ ( Included in material rate ) `: 0.00

Add Royalty charges on FA @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 244161.15

B. MACHINERY:

Sl No Unit Amount

in `:

1 Batching plant 15 cum/hr rated capacity Hour 8.00 334.00 2672.00

Lubricants @ 5 % Hour 8.00 16.70 133.60

2 Transit mixer 3 Nos Hour 24.00 708.00 16992.00

Fuel / Energy charges Hour 24.00 832.00 19968.00

3 Mechanical paver Hour 8.00 311.00 2488.00

Lubricants @ 5 % Hour 8.00 15.55 124.40

4 DG set for batching plant 50 KVA Hour 9.00 104.00 936.00

Fuel / Energy charges Hour 9.00 908.00 8172.00

5 DG set for paver 30 KVA Hour 9.00 66.00 594.00

Fuel / Energy charges Hour 9.00 605.00 5445.00

Contd

Description

Perticulars

80

Quantity Rate

in `.

Rate

in `.

Quantity

Page 83: Data rates-Canal Works

CANAL AND ALLIED WORKS

B. MACHINERY ( Contd ) :

Sl No Unit Amount

in `:

Contd

6 Shovel 0.5 cum / Loader Hour 4.00 799.00 3196.00

Fuel / Energy charges Hour 4.00 454.00 1816.00

7 Water tanker Hour 8.00 306.00 2448.00

Fuel / Energy charges Hour 8.00 286.00 2288.00

8 Pump 5 hp (diesel ) 2 Nos 4 hr each Hour 8.00 7.00 56.00

Fuel / Energy charges Hour 8.00 76.00 608.00

9 Sundries ( power line etc ) LS 50.00 44.00 2200.00

Total `: 70137.00

Add for small Tools and Plants @ 1% `: 701.37

Add for Contractor's Profit on DPOL / Energy @ 10% `: 4075.50

Add for Contractor's Overheads @ 5% `: 3506.85

Total hire charges of Machinery : `: 78420.72

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Batching plant Hour 8.00 181.00 1448.00

2 Crew for Transit mixer Hour 24.00 151.00 3624.00

3 Crew for Concrete paver Hour 8.00 241.00 1928.00

4 Crew for DG set Hour 18.00 75.00 1350.00

5 Crew for Shovel Hour 4.00 128.00 512.00

6 Crew for Water tanker Hour 8.00 95.00 760.00

7 Crew for Pump Hour 8.00 60.00 480.00

8 Mason Class I Day 2.00 256.73 513.46

9 Mechanic Day 2.00 254.73 509.46

10 Fitter Day 1.00 254.73 254.73

11 Electrician Day 2.00 241.23 482.46

12 Maistry Day 2.00 241.23 482.46

13 Heavy mazdoor ( BP site ) Day 10.00 238.73 2387.30

Heavy mazdoor ( Paver site ) Day 10.00 238.73 2387.30

14 Light mazdoor ( Paver site ) Day 5.00 237.23 1186.15

Total `: 18305.32

Add for small Tools and Plants @ 1% `: 183.05

Add for Contractor's Profit @ 10% `: 1830.53

Add for hidden cost on Labour @ 15% `: 2745.80

Add for Contractor's Overheads @ 5% `: 915.27

Total cost of Labour : `: 23979.97

ABSTRACT:

A. Cost of Materials including royalty charges `: 244161.15

B. Hire charges of Machinery `: 78420.72

C. Cost of Labour `: 23979.97

TOTAL `: 346561.84

Add for shifting & erection of BP @ 2.00% `: 6931.24

Add for LH / RH shifting & erection of Paver @ 0.50% `: 1732.81

Add for ledge cutting / track laying etc @ 1.00% `: 3465.62

Description

in `.

QuantityDescription

Rate

in `.

Rate

81

Quantity

Page 84: Data rates-Canal Works

CANAL AND ALLIED WORKS

Add for other enabling works @ 1.00% `: 3465.62

Total cost for 520.00 sqm `: 362157.12

Rate per sqm `:`:`:`: 696.46

Rate approved per sqm `:`:`:`: 696.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.30.1

ITEM: Providing and laying 80 mm thick in-situ M-20 ( 28 days cube compressive strength not less

than 20 N / sqmm ) grade cement concrete using 20 mm down approved, clean, hard,

graded aggregates for canal lining deploying batching plant, transit mixer and vibratory

cylinder type mechanical paver including cost of all materials, machinery, labour, cleaning,

batching, mixing, placing in position, forming contraction joints, fixing PVC joint sealing strips,

finishing, curing, shifting of paver from one side to other side of canal etc., complete with lead

upto 1 km and all lifts. ( Cement content: 28.40 kg / sqm with use of super plasticiser )

DATA:Thickness of lining : 80 mm

Consider Cylinder type Mechanical paver with one side paving arrangement for CC lining.

Average output of mechanical paver / hour for 80 mm thick lining : 100 sqm

For 1 cum CC :- Coarse aggregates : 0.75 cum Blending ratio : 65 :35

Fine aggregate : 0.41 cum Cement content : 330 kg Super plasticizer : 1.00 ltr

Wastage : 1 % for cement and 2 % for coarse & fine aggregates.

Output of paver / hour with 50 min per hour working.( 100 x 50 / 60 ) say : 80 sqm

Qty of CC for paver / hr for 80 mm thickness ( 80 x 0.08 ) : 6.40 cum

Add extra qty for curvature at bed & side junction @ 6 % : 0.40 cum

Corrected qty of concrete for 100 sqm : 6.80 cum

Rated capacity of batching plant with 70 % efficiency for 6.80 cum / hour output:

( 6.80 x 60 / 50 / 0.7 ) : 11.65 cum / hr

Consider 15 cum per hour capacity Batching & mixing plant for concrete production.

Consider shifting & re-erection of Batching plant at 5 km interval.

Consider 2 cum capacity Transit mixers for conveying CC from BP to paver site.

Round trip cycle time for transit mixer :

Turning & spotting at BP : 2.00 min

Loading CC : 10.00 min

Conveying from BP to Paver site( average ) : 5.00 min

Turning & spotting at Paver site : 2.00 min

Unloading concrete at paver site : 20.00 min

Return trip to BP ( average ) : 5.00 min

Total : 44.00 min

Output of transit mixer / hr with 50 min / hr working: ( 50 x 2 / 44 ) : 2.27 cum

Hourly requirement of concrete for 80 sqm / hour lining : 6.80 cum

No.of Transit mixers to match 6.80 cum / hr ( 6.8 / 2.27 ) say : 3 Nos.

Daily progress of lining @ 80 sqm / hour : 640 sqm

Quantity of concrete for 640 sqm @ 6.80 cum / 80 sqm : 54.40 cum

Consider 640 sqm lining requiring 54.40 cum concrete for rate analysis.

1. Requirement of materials:

Cement for mix with 1 % wastage ( 54.40 x 330 x 1.01 ) : 18132 kg

Cement for incidentals @ 5 kg / cum ( 54.40 x 5 ) : 272 kg

Coarse aggregate 20-10 mm size ( 54.40 x 0.75 x 0.65 x 1.02 ) : 27.05 cum

Coarse aggregate 10-4.75 mm size ( 54.40 x 0.75 x 0.35 x 1.02 ) : 14.55 cum

Fine aggregate ( 54.40 x 0.41 x 1.02 ) : 22.75 cum

82

Page 85: Data rates-Canal Works

CANAL AND ALLIED WORKS

Super plasticiser ( 54.40 x 1.0 x 1.02 ) : 55.50 ltrs

PVC sealing strip in 4 m x 4 m grid @ 0.5 m / sqm ( 640 x 0.5 ) : 320 Rm

Curing compound @ 0.2 ltr / sqm ( 640 x 0.2 x 1.1 ) : 141 ltrs

2. Requirement of machinery :

Deploy 15 cum per hour capacity Batching & mixing plant for 8 hours for concrete production.

Deploy 3 Transit mixers for for 8 hours for conveyance of CC from BP to Paver site.

Deploy 100 sqm / hour Mechanical paver for 8 hours for concrete lining.

Deploy about 50 KVA capacity DG set with all accessories for 9 hours at BP site.

Deploy about 30 KVA capacity DG set with all accessories for 9 hours at Paver site.

Deploy 0.5 cum capacity Shovel for 4 hours at BP site for pushing CA / FA from stock pile.

Deploy 2 Pumps 5 hp for 4 hour for water requirement at BP and Paver sites.

Deploy 1 Water tanker 8000 ltr capacity for 8 hour for water required at BP and Paver sites.

3. Formwork & scaffolding :

No formwork / scaffolding required for lining by paver.

4. Requirement of workforce ( other than machinery crew ) :

Mason Class I for finishing & fixing PVC strips : 2 Nos.

Mechanic : 2 Nos.

Fitter : 1 No.

Electrician : 2 Nos.

Maistry ( 1 at BP and 1 at Paver sites ) : 2 Nos.

Heavy mazdoor ( BP site for feeding cement to silo & misc. works ) : 10 Nos.

Heavy mazdoor ( Paver site ) : 10 Nos.

Light mazdoor ( Paver site ) : 5 Nos.

5. Use rate of materials :

Cost of paving cylinder @ `: 27800.00 / Each. `: 27800.00

Life of paving cylinder in sqm of lining : 40000

Use rate of paving cylinder / sqm ( cost / life ) `: 0.70

Add for repair charges at 25 % `: 0.17

Use rate of paving cylinder / sqm including repairs. `: 0.87

RATE ANALYSIS UNIT : 640.00 sqm

A. MATERIALS:

Sl No Unit Amount

in `:

1 Cement 43 Gr kg 18132.00 7.50 135990.00

Cement for incidentals @ 5 kg / cum kg 272.00 7.50 2040.00

2 Coarse aggregate 20-10 mm cum 27.05 950.00 25697.50

Coarse aggregate 10-4.75 mm cum 14.55 1160.00 16878.00

3 Fine aggregate ( screened ) cum 22.75 730.00 16607.50

4 Super plasticiser ltr 55.50 105.00 5827.50

5 PVC sealing strip Rm 360.00 45.00 16200.00

6 Curing compound ltr 141.00 134.00 18894.00

7 Use rate of paving cylinder sqm 640.00 0.87 556.00

8 Sundries LS 50.00 44.00 2200.00

Total `: 240890.50

Add for small Tools and Plants @ 1% `: 2408.91

Add for Contractor's Profit @ 10% `: 24089.05

Add for Contractor's Overheads @ 5% `: 12044.53

Add Royalty charges on CA @ ( Included in material rate ) `: 0.00

Add Royalty charges on FA @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 279432.98

in `.

Perticulars

83

Quantity Rate

Page 86: Data rates-Canal Works

CANAL AND ALLIED WORKS

B. MACHINERY:

Sl No Unit Amount

in `:

1 Batching plant 15 cum/hr rated capacity Hour 8.00 334.00 2672.00

Lubricants etc @ 5 % Hour 8.00 16.70 133.60

2 Transit mixer 3 Nos Hour 24.00 708.00 16992.00

Fuel / Energy charges Hour 24.00 832.00 19968.00

3 Mechanical paver Hour 8.00 311.00 2488.00

Lubricants etc @ 5 % Hour 8.00 15.55 124.40

4 DG set for batching plant 50 KVA Hour 9.00 104.00 936.00

Fuel / Energy charges Hour 9.00 908.00 8172.00

5 DG set for paver 30 KVA Hour 9.00 66.00 594.00

Fuel / Energy charges Hour 9.00 605.00 5445.00

6 Shovel 0.5 cum / Loader Hour 4.00 799.00 3196.00

Fuel / Energy charges Hour 4.00 454.00 1816.00

7 Water tanker Hour 8.00 306.00 2448.00

Fuel / Energy charges Hour 8.00 286.00 2288.00

8 Pump 5 hp(diesel) 2 Nos. 4 hrs each Hour 8.00 7.00 56.00

Fuel / Energy charges Hour 8.00 76.00 608.00

9 Sundries ( power line etc ) LS 50.00 44.00 2200.00

Total `: 70137.00

Add for small Tools and Plants @ 1% `: 701.37

Add for Contractor's Profit on DPOL / Energy @ 10% `: 4075.50

Add for Contractor's Overheads @ 5% `: 3506.85

Total hire charges of Machinery : `: 78420.72

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Batching plant Hour 8.00 181.00 1448.00

2 Crew for Transit mixer Hour 24.00 151.00 3624.00

3 Crew for Concrete paver Hour 8.00 241.00 1928.00

4 Crew for DG set Hour 18.00 75.00 1350.00

5 Crew for Shovel Hour 4.00 128.00 512.00

6 Crew for Water tanker Hour 8.00 95.00 760.00

7 Crew for Pump Hour 8.00 60.00 480.00

8 Mason Class I Day 2.00 256.73 513.46

9 Mechanic Day 2.00 254.73 509.46

10 Fitter Day 1.00 254.73 254.73

11 Electrician Day 2.00 241.23 482.46

12 Maistry Day 2.00 241.23 482.46

13 Heavy mazdoor ( BP site ) Day 10.00 238.73 2387.30

Heavy mazdoor ( Paver site ) Day 10.00 238.73 2387.30

14 Light mazdoor ( Paver site ) Day 5.00 237.23 1186.15

Total `: 18305.32

Add for small Tools and Plants @ 1% `: 183.05

Add for Contractor's Profit @ 10% `: 1830.53

Add for hidden cost on Labour @ 15% `: 2745.80

Add for Contractor's Overheads @ 5% `: 915.27

Total cost of Labour : `: 23979.97

Description

RateDescription

Rate

in `.

84

in `.

Quantity

Quantity

Page 87: Data rates-Canal Works

CANAL AND ALLIED WORKS

ABSTRACT:

A. Cost of Materials including royalty charges `: 279432.98

B. Hire charges of Machinery `: 78420.72

C. Cost of Labour `: 23979.97

TOTAL `: 381833.67

Add for shifting & re-erection of BP @ 2.00% `: 7636.67

Add for LH / RH shifting & erection of Paver @ 0.50% `: 1909.17

Add for ledge cutting / erection of tracks etc @ 1.00% `: 3818.34

Add for other enabling works @ 1.00% `: 3818.34

Total cost for 640.00 sqm `: 399016.18

Rate per sqm `:`:`:`: 623.46

Rate approved per sqm `:`:`:`: 623.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.30.2

ITEM: Providing and laying 100 mm thick in-situ M-20 ( 28 days cube compressive strength not less

than 20 N / sqmm ) grade cement concrete using 20 mm down approved, clean, hard,

graded aggregates for canal lining deploying batching plant, transit mixer and vibratory

cylinder type mechanical paver including cost of all materials, machinery, labour, cleaning,

batching, mixing, placing in position, forming contraction joints, fixing PVC joint sealing strips,

finishing, curing, shifting of paver from one side to other side of canal etc., complete with lead

upto 1 km and all lifts. ( Cement content: 35.20 kg / sqm with use of super plasticiser )

DATA:Thickness of lining : 100 mm

Consider Cylinder type Mechanical paver with one side paving arrangement for CC lining.

Average output of mechanical paver / hour for 100 mm thick lining : 80 sqm

For 1 cum CC :- Coarse aggregates : 0.75 cum Blending ratio : 65 :35

Fine aggregate : 0.41 cum Cement content : 330 kg Super plasticizer : 1.0 ltr

Wastage : 1 % for cement and 2 % for coarse & fine aggregates.

Output of paver / hour with 50 min per hour working ( 80 x 50 / 60 ) say : 65 sqm

Quantity of CC for paver / hour ( 65 x 0.10 ) : 6.50 cum

Add extra quantity for curvature at bed & side junction @ 5 % : 0.30 cum

Corrected qty of concrete for 80 sqm : 6.80 cum

Rated capacity of batching plant required with 70 % efficiency for 6.80 cum / hour output:

( 6.80 x 60 / 50 / 0.7 ) : 11.65 cum / hr

Consider 15 cum per hour capacity Batching & mixing plant for concrete production.

Consider shifting & re-erection of Batching plant at 5 km interval.

Consider 2 cum capacity Transit mixers for conveying CC from BP to paver site.

Round trip cycle time for transit mixer:

Turning & spotting at BP : 2.00 min

Loading CC : 10.00 min

Conveying from BP to Paver site ( average ) : 5.00 min

Turning & spotting at Paver site : 2.00 min

Unloading concrete at paver site : 20.00 min

Return trip to BP ( average ) : 5.00 min

Total : 44.00 min

Output of transit mixer / hr with 50 min / hr working: ( 50 x 2 / 44 ) : 2.27 cum

Hourly requirement of concrete for 65 sqm / hour lining : 6.80 cum

No. of Transit mixers to match 6.80 cum / hr ( 6.80 / 2.27 ) : 3 Nos.

Daily progress of lining @ 65 sqm / hour : 520 sqm

85

Page 88: Data rates-Canal Works

CANAL AND ALLIED WORKS

Quantity of concrete for 520 sqm @ 6.80 cum / 65 sqm : 54.40 cum

Consider 520 sqm lining requiring 54.40 cum concrete for rate analysis.

1. Requirement of materials:

Cement for mix with 1 % wastage ( 54.40 x 330 x 1.01 ) : 18132 kg

Cement for incidentals @ 5 kg / cum ( 54.40 x 5 ) : 272 kg

Coarse aggregate 20-10 mm size ( 54.40 x 0.75 x 0.65 x 1.02 ) : 27.05 cum

Coarse aggregate 10-4.75 mm size ( 54.40 x 0.75 x 0.35 x 1.02 ) : 14.55 cum

Fine aggregate ( 54.40 x 0.41 x 1.02 ) : 22.75 cum

Super plasticiser ( 54.40 x 1.0 x 1.02 ) : 55.50 ltrs

PVC sealing strip in 4 m x 4 m grid @ 0.5 m / sqm ( 520 x 0.5 ) : 260 Rm

Curing compound @ 0.2 ltr / sqm ( 520 x 0.2 x 1.1 ) : 115 ltrs

2. Requirement of machinery :

Deploy 15 cum per hour capacity Batching & mixing plant for 8 hours for concrete production.

Deploy 3 Transit mixers for for 8 hours for conveyance of CC from BP to Paver site.

Deploy 80 sqm / hour Mechanical paver for 8 hours for concrete lining.

Deploy about 50 KVA capacity DG set with all accessories for 9 hours at BP site.

Deploy about 30 KVA capacity DG set with all accessories for 9 hours at Paver site.

Deploy 0.5 cum capacity Shovel for 4 hours at BP site for pushing CA / FA from stock pile.

Deploy 2 Pumps 5 hp for 4 hour for water requirement at BP and Paver sites.

Deploy 1 Water tanker 8000 ltr capacity for 8 hour for water required at BP and Paver sites.

3. Formwork & scaffolding :

No formwork / scaffolding required for lining by paver.

4. Requirement of workforce ( other than machinery crew ) :

Mason Class I for finishing & fixing PVC strips : 2 Nos.

Mechanic : 2 Nos.

Fitter : 1 No.

Electrician : 2 Nos.

Maistry ( 1 at BP and 1 at Paver sites ) : 2 Nos.

Heavy mazdoor ( BP site for feeding cement to silo & misc. works ) : 10 Nos.

Heavy mazdoor ( Paver site ) : 10 Nos.

Light mazdoor ( Paver site ) : 5 Nos.

5. Use rate of materials :

Cost of paving cylinder @ `: 27800.00 / Each. `: 27800.00

Life of paving cylinder in sqm of lining : 40000

Use rate of paving cylinder / sqm ( cost / life ) `: 0.70

Add for repair charges at 25 % `: 0.17

Use rate of paving cylinder / sqm including repairs. `: 0.87

RATE ANALYSIS UNIT : 520.00 sqm

A. MATERIALS:

Sl No Unit Amount

in `:

1 Cement 43 Gr kg 18132.00 7.50 135990.00

Cement for incidentals @ 5 kg / cum kg 272.00 7.50 2040.00

2 Coarse aggregate 20-10 mm cum 27.05 950.00 25697.50

Coarse aggregate 10-4.75 mm cum 14.55 1160.00 16878.00

3 Fine aggregate ( screened ) cum 22.75 730.00 16607.50

4 Super plasticiser ltr 55.50 105.00 5827.50

5 PVC sealing strip Rm 260.00 45.00 11700.00

Contd

Perticulars Rate

in `.

86

Quantity

Page 89: Data rates-Canal Works

CANAL AND ALLIED WORKS

A. MATERIALS ( Contd ) :

Sl No Unit Amount

in `:

Contd

6 Curing compound ltr 115.00 134.00 15410.00

7 Use rate of paving cylinder sqm 520.00 0.87 451.75

8 Sundries LS 50.00 44.00 2200.00

Total `: 232802.25

Add for small Tools and Plants @ 1% `: 2328.02

Add for Contractor's Profit @ 10% `: 23280.23

Add for Contractor's Overheads @ 5% `: 11640.11

Add Royalty charges on CA @ ( Included in material rate ) `: 0.00

Add Royalty charges on FA @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 270050.61

B. MACHINERY:

Sl No Unit Amount

in `:

1 Batching plant 15 cum/hr rated capacity Hour 8.00 334.00 2672.00

Lubricants @ 5 % Hour 8.00 16.70 133.60

2 Transit mixer 3 Nos Hour 24.00 708.00 16992.00

Fuel / Energy charges Hour 24.00 832.00 19968.00

3 Mechanical paver Hour 8.00 311.00 2488.00

Lubricants @ 5 % Hour 8.00 15.55 124.40

4 DG set for batching plant 50 KVA Hour 9.00 104.00 936.00

Fuel / Energy charges Hour 9.00 908.00 8172.00

5 DG set for paver 30 KVA Hour 9.00 66.00 594.00

Fuel / Energy charges Hour 9.00 605.00 5445.00

6 Shovel 0.5 cum / Loader Hour 4.00 799.00 3196.00

Fuel / Energy charges Hour 4.00 454.00 1816.00

7 Water tanker Hour 8.00 306.00 2448.00

Fuel / Energy charges Hour 8.00 286.00 2288.00

8 Pump 5 hp (diesel ) 2 Nos 4 hr each Hour 8.00 7.00 56.00

Fuel / Energy charges Hour 8.00 76.00 608.00

9 Sundries ( power line etc ) LS 50.00 44.00 2200.00

Total `: 70137.00

Add for small Tools and Plants @ 1% `: 701.37

Add for Contractor's Profit on DPOL / Energy @ 10% `: 4075.50

Add for Contractor's Overheads @ 5% `: 3506.85

Total hire charges of Machinery : `: 78420.72

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Batching plant Hour 8.00 181.00 1448.00

2 Crew for Transit mixer Hour 24.00 151.00 3624.00

3 Crew for Concrete paver Hour 8.00 241.00 1928.00

4 Crew for DG set Hour 18.00 75.00 1350.00

5 Crew for Shovel Hour 4.00 128.00 512.00

Contd

in `.

in `.

RateQuantity

Perticulars

87

Description

QuantityDescription

Quantity Rate

Rate

in `.

Page 90: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR ( Contd ) :

Sl No Unit Amount

in `:

Contd

6 Crew for Water tanker Hour 8.00 95.00 760.00

7 Crew for Pump Hour 8.00 60.00 480.00

8 Mason Class I Day 2.00 256.73 513.46

9 Mechanic Day 2.00 254.73 509.46

10 Fitter Day 1.00 254.73 254.73

11 Electrician Day 2.00 241.23 482.46

12 Maistry Day 2.00 241.23 482.46

13 Heavy mazdoor ( BP site ) Day 10.00 238.73 2387.30

Heavy mazdoor ( Paver site ) Day 10.00 238.73 2387.30

14 Light mazdoor ( Paver site ) Day 5.00 237.23 1186.15

Total `: 18305.32

Add for small Tools and Plants @ 1% `: 183.05

Add for Contractor's Profit @ 10% `: 1830.53

Add for hidden cost on Labour @ 15% `: 2745.80

Add for Contractor's Overheads @ 5% `: 915.27

Total cost of Labour : `: 23979.97

ABSTRACT:

A. Cost of Materials including royalty charges `: 270050.61

B. Hire charges of Machinery `: 78420.72

C. Cost of Labour `: 23979.97

TOTAL `: 372451.30

Add for shifting & erection of BP @ 2.00% `: 7449.03

Add for LH / RH shifting & erection of Paver @ 0.50% `: 1862.26

Add for ledge cutting / track laying etc @ 1.00% `: 3724.51

Add for other enabling works @ 1.00% `: 3724.51

Total cost for 520.00 sqm `: 389211.61

Rate per sqm `:`:`:`: 748.48

Rate approved per sqm `:`:`:`: 748.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.31

ITEM: Dismantling, shifting and re-erecting mechanical concrete paver and DG set with all

accessories across canal CD work or such other locations where dismantling, shifting,

re-erecting and aligning of paver is necessary for continuing further canal lining work including

cost of all materials, machinery, labour etc., complete with all leads and lifts.

DATA:Dismantling, shifting and re-erecting mechanical concrete paver is necessary at each CD work

location. As CD works will not be at any fixed interval separate rate is proposed for dismantling,

shifting and re-erection of paver. As per the information collected from equipment suppliers

1 day time is required for dismantling, shifting and re-erection of paver and DG set including

aligning and testing.

Deploy paver crew for 1 day.

Deploy heavy mazdoors 6 Nos for 1 day to assist paver crew.

Deploy tipper for 4 hours with fuel charges for 1 hour for shifting.

Quantity RateDescription

88

in `.

Page 91: Data rates-Canal Works

CANAL AND ALLIED WORKS

RATE ANALYSIS UNIT : 1.00 Shifting

A. MATERIALS:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total cost of Materials : `: 0.00

B. MACHINERY:

Sl No Unit Amount

in `:

1 Tipper Hour 4.00 309.00 1236.00

Fuel / Energy charges Hour 1.00 286.00 286.00

2 Sundries ( ropes / rails etc ) LS 1.00 44.00 44.00

Total `: 1566.00

Add for small Tools and Plants @ 1% `: 15.66

Add for Contractor's Profit on DPOL / Energy @ 10% `: 33.00

Add for Contractor's Overheads @ 5% `: 78.30

Total hire charges of Machinery : `: 1692.96

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Tipper Hour 4.00 95.00 380.00

2 Crew for Paver Hour 8.00 241.00 1928.00

3 Heavy mazdoor Day 6.00 238.73 1432.38

Total `: 3740.38

Add for small Tools and Plants @ 1% `: 37.40

Add for Contractor's Profit @ 10% `: 374.04

Add for hidden cost on Labour @ 15% `: 561.06

Add for Contractor's Overheads @ 5% `: 187.02

Total cost of Labour : `: 4899.90

ABSTRACT:

A. Cost of Materials `: 0.00

B. Hire charges of Machinery `: 1692.96

C. Cost of Labour `: 4899.90

TOTAL `: 6592.86

Add for other enabling works @ 1.00% `: 65.93

Total cost for 1.00 Shifting `: 6658.79

Rate per Shifting `:`:`:`: 6658.79

Rate approved per cum `:`:`:`: 6659.00

Note: The rate under this item shall not be considered for local shifting of paver from one side to other

side of canal. The cost of local shifting of paver is included in concrete lining rates under items

29.a, 29.b, 30.a and 30.b.

Rate

in `.

Perticulars Rate

in `.

Description

Quantity

89

QuantityDescription

in `.

RateQuantity

Page 92: Data rates-Canal Works

CANAL AND ALLIED WORKS

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.32.1

ITEM: Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than

15 N /sq mm ) grade cement concrete using 20 mm down approved, clean, hard, graded

aggregates for side lining of canal including cost of all materials, machinery, labour,cleaning,

batching, mixing, formwork, supports, placing in position, levelling, vibrating, finishing junction

of bed and sides to required curveture, finishing side slopes, curing etc., complete with lead

upto 50 m and all lifts. ( Cement content : 270 kg / cum with use of super plasticiser )

DATA:For concrete lining of small canals locally fabricated manually operated paver can be considered.

By operating the screw jack the side shuttering can be positioned in place.

Consider laying of concrete in panels of 3 m length.

Length of shutter including 0.10 m overlap on previous lining 3.10 m

Assume 1.5 m bed width and 1.2 m depth of flow. Assume 0.30 m free board.

Assume side slopes of 1.5 horizontal to 1 vertical.

Sloped length of shuttering including 0.20 m free shutter at top and 0.30 m for curved portion and

overlap at bed will be ( 0.20 + 2.70 + 0.30 ) 3.20 m

Area of shutter plate on each side of canal ( 3.1 x 3.2 ) say : 10.00 sqm

Screw jack

Shutter plate

Side lining

Bracings

Hinged joints

Trolley

Bed lining

INDICATIVE ARRANGEMENT OF MANUAL PAVER

As the paver will be released soon after completing concreting upto top level of lining and moved

to next portion to be lined 200 uses can be considered as life of paver.

Further it is assumed that the shuttering of paver will be oiled after every 5 to 6 uses of the paver.

Considering this the quantity of shutter oil is assumed at 0.05 ltr / sqm.

Cost of manual paver :

Shuttering plate 4 mm thick ( 2 x 10 ) sqm @ 31.40 kg / sqm : 628.00 kg

Vertical and horizontal stiffeners 65 x 65 x 6 mm angles @ 1 m spacing

@ 5.8 kg / m ( 3.2 x 8 + 3 x 8 ) x 5.8 : 288.00 kg

Intermidiate stiffeners 40x40x5 mm angles 36 m @ 3.78 kg / m : 136.00 kg

Bracings ISMC100: 22 m @ 9.2 kg / m : 203.00 kg

Gusset plates for bracings 300 x 300 x 10 mm 6 Nos @ 78.5 kg / sqm : : 42.00 kg

Trolley frame ISMC200 : 7 m @ 22.1 kg / m : 155.00 kg

Top frame : 75.00 kg

Jack and jack supports : 125.00 kg

Wheels and supports : 150.00 kg

Miscellaneous and wastage : 50.00 kg

Total Wt : 1852.00 kg

say : 1850 kg

Cost of manual paver @ `: / tonne `: 244200.00

90

132000.00

Page 93: Data rates-Canal Works

CANAL AND ALLIED WORKS

For 1 cum CC :- Coarse aggregates : 0.77 cum Blending ratio : 65 :35

Fine aggregate : 0.47 cum Cement content : 270 kg Super plasticizer : 0.80 ltr

Wastage : 1 % for cement and 2 % for coarse & fine aggregates.

Consider laying concrete on both sides of the canal.

Therefore, deploy 2 concrete mixers ( diesel ) one on either side for lining.

Consider 300 / 200 ltr capacity mixer and 50 kg cement per mix for use of 20 mm down CA.

Equivalent volume batching using 0.3 x 0.3 x 0.3 m size boxes assumed for batching CA & FA.

Cycle time for batching / mixing / unloading 1 mix :

Batching 20-10 mm CA ( 0.093 cum ) : 4.00 min

Batching 10 mm below CA parellel activity : ---

Batching fine aggregate parellel activity : ---

Batching cement parellel activity : ---

Loading mixer drum & miscellaneous : 1.00 min

Mixing and unloading parellel activity : ---

Add for possible delays in any of the activity : 0.50 min

Total : 5.50 min

No. of mixes per day with 50 min / hr working ( 50 x 8 / 5.5 ) 73 mixes

Output of CC for 73 mixes ( 73 x 50 / 270 ) say : 13.50 cum

Daily output of 2 mixers ( one on either side of paver ) ( 2 x 13.50 ) say : 27.00 cum

For 20 mm down size coarse aggregate 150 mm thick lining is assumed.

Concrete lining area per paver length of 3 m : 18 sqm

Quantity of concrete per use of paver ( 18 x 0.15 ) : 2.70 cum

Add for curveture at junction of sides and bed @ 3 % say : 0.08 cum

Total quantity of concrete / paver length : 2.78 cum

No. of mixes by each mixer / paver length 2.78 / ( 2 x 50 / 270 ) 7.5 mixes

Consider concrete production and laying as parallel activities.

Cycle time of paver with 50 minutes / hour working :

Time required for laying concrete / paver length ( 7.5x 5.5x 60/ 50 ) say : 50.00 minutes

Time required for releasing and moving paver : 3.00 minutes

Time required for cleaning and resetting paver : 5.00 minutes

Total time for 1.85 cum concrete lining : 58.00 minutes

Number of paver cycles per day ( 8 x 60 / 58 ) say : 8 cycles

Daily progress based on cycle time of paver ( 8 x 2.78 ) say : 22.25 cum

Area of lining per use : 18.00 sqm

Area of lining for 12 uses of paver ( 18 x 8 ) : 144.00 sqm

For curing concrete use of curing compound is proposed.

10 percent extra curing compound considered for overlaps and wastage.

Water is required only for concrete mixing and washing. One tanker load ( 8000 ltrs) is adequate

for 2 days work. For 1 day work consider 5 hp pump for 0.25 hour & water tanker for 0.5 hour.

Consider 22.25 cum per day as progress of concreting for rate analysis.

1. Requirement of materials :

Cement for mix with 1 % wastage ( 22.25 x 270 x 1.01 ) : 6068 kg

Cement for incidentals @ 5 kg / cum ( 22.25 x 5 ) : 111 kg

Coarse aggregate 20-10 mm size ( 22.25 x 0.77 x 0.65 x 1.02 ) : 11.36 cum

Coarse aggregate 10-4.75 mm size ( 22.25 x 0.77 x 0.35 x 1.02 ) : 6.11 cum

Fine aggregate ( 22.25 x 0.47 x 1.02 ) : 10.67 cum

Super plasticiser ( 22.25 x 0.8 x 1.02 ) : 18.20 ltrs

Curing compound @ 0.2 ltr / sqm ( 144 x 0.2 x 1.1 ) : 31.70 ltrs

91

Page 94: Data rates-Canal Works

CANAL AND ALLIED WORKS

2. Requirement of machinery :

Deploy 300 / 200 ltr diesel concrete mixers 2 Nos. ( 1 on either side of paver ) for 8 hours.

Deploy 1 No. Manual paver for 8 hours for concrete lining.

Deploy 2 Nos. Needle vibraters for 8 hours for compacting concrete.

Deploy 1 Pump 5 hp for 0.25 hour for water requirement at paver site.

Deploy 1 Water tanker 8000 ltr capacity for 0.5 hour for water requirement at paver site.

3. Formwork & scaffolding :

No formwork / scaffolding required for lining by paver.

4. Requirement of work-force ( other than machinery crew ) :

Lining from both sides of canal using 2 mixers :

Mason Cl I : 2 Nos.

Heavy mazdoor:

For batching cement : 4 Nos.

For batching 20-10 mm size CA : 6 Nos.

For batching 10 mm below size CA : 4 Nos.

For batching FA : 6 Nos.

For remixing & filling mortar pans : 4 Nos.

For loading mortar pans : 4 Nos.

For unloading mortar pans and laying : 4 Nos.

For assisting Mason / Fitter, moving paver & spraying curing compound : 2 Nos.

Light mazdoor:

For conveying concrete @ 1 cum / day ( 8 x 50 x 2.78 / 50 ) : 22 Nos.

For cleaning & miscellaneous works : 2 Nos.

Fitter for handling the paver : 1 No.

Heavy mazdoors assisting mason also assist fitter for moving and re-positioning of paver.

5. Use rate of manual paver :

Cost of manual paver `: 244200.00

Add for repairs / replacements / catwalks etc., @ 25% `: 61050.00

Deduct salvage value @ 10 % ( - ) `: -24420.00

Total `: 280830.00

Consider useful life of paver at 150 uses.

Use rate of paver for av. 150 uses `: 280830 / 150 `: 1872.20

Shutter oil 0.05 ltr /sqm for 18 sqm @ `: 35.00 / ltr `: 31.50

Total `: 1903.70

Area of concreting allowing for overlaps / free shutter ( 3 x 3 x 2 ) : 18 sqm

Use rate of Manual Paver for concrete / use / sqm `:`:`:`: 105.76

( Excluding T & P / Profit / Overheads)

RATE ANALYSIS UNIT : 22.25 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 Cement for mix kg 6068.00 7.50 45510.00

Cement for incidentals @ 5 kg / cum kg 111.00 7.50 832.50

2 Coarse aggregate 20-10 mm cum 11.36 950.00 10792.00

Coarse aggregate 10 mm below cum 6.11 1160.00 7087.60

3 Fine aggregate cum 10.67 730.00 7789.10

Contd

Perticulars Quantity

92

Rate

in `.

Page 95: Data rates-Canal Works

CANAL AND ALLIED WORKS

A. MATERIALS ( Contd ) :

Sl No Unit Amount

in `:

Contd

4 Super Plasticizer ltr 18.20 105.00 1911.00

5 Curing compound ltr 31.70 134.00 4247.80

6 Use rate of manual paver sqm 144.00 105.76 15229.60

7 Sundries LS 20.00 44.00 880.00

Total `: 94279.60

Add for small Tools and Plants @ 1% `: 942.80

Add for Contractor's Profit @ 10% `: 9427.96

Add for Contractor's Overheads @ 5% `: 4713.98

Add Royalty charges on CA @ ( Included in material rate ) `: 0.00

Add Royalty charges on FA @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 109364.34

B. MACHINERY:

Sl No Unit Amount

in `:

1 Concrete mixer 300 / 200 ltr ( diesel ) Hour 16.00 46.00 736.00

Fuel / Energy charges Hour 16.00 76.00 1216.00

2 5 hp pump ( diesel ) Hour 0.25 7.00 1.75

Fuel / Energy charges Hour 0.25 76.00 19.00

3 Water tanker 8000 ltr Hour 0.50 306.00 153.00

Fuel / Energy charges Hour 0.50 286.00 143.00

4 Needle vibrator 40 mm dia ( petrol ) Hour 16.00 9.00 144.00

Fuel / Energy charges Hour 16.00 18.00 288.00

5 Sundries LS 15.00 44.00 660.00

Total `: 3360.75

Add for small Tools and Plants @ 1% `: 33.61

Add for Contractor's Profit on DPOL / Energy @ 10% `: 232.60

Add for Contractor's Overheads @ 5% `: 168.04

Total hire charges of Machinery : `: 3795.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Concrete mixer Hour 16.00 126.00 2016.00

2 Crew for Pump Hour 0.25 60.00 15.00

3 Crew for Water tanker Hour 0.50 95.00 47.50

4 Crew for Vibrator Hour 16.00 90.00 1440.00

5 Mason Class-I Day 2.00 256.73 513.46

6 Maistry Day 1.00 241.23 241.23

7 Fitter Day 1.00 254.73 254.73

8 Heavy mazdoor

for batching materials Day 20.00 238.73 4774.60

for loading mortar pans Day 8.00 238.73 1909.84

for laying and moving paver Day 6.00 238.73 1432.38

Contd

Description

Perticulars

Description

Rate

Quantity Rate

in `.

Quantity

Quantity

in `.

in `.

Rate

93

Page 96: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR ( Contd ) :

Sl No Unit Amount

in `:

Contd

9 Light mazdoor

for conveying concrete Day 22.00 237.23 5219.06

for cleaning / washing / curing Day 2.00 237.23 474.46

Total `: 18338.26

Add for small Tools and Plants @ 1% `: 183.38

Add for Contractor's Profit @ 10% `: 1833.83

Add for hidden cost on Labour @ 15% `: 2750.74

Add for Contractor's Overheads @ 5% `: 916.91

Total cost of Labour : `: 24023.12

ABSTRACT:

A. Cost of Materials inluding royalty charges `: 109364.34

B. Hire charges of Machinery `: 3795.00

C. Cost of Labour `: 24023.12

TOTAL `: 137182.45

Add for other enabling works @ 1.00% `: 1371.82

Total cost for 22.25 cum `: 138554.28

Rate per cum `:`:`:`: 6227.16

Rate approved per cum `:`:`:`: 6227.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.32.2

ITEM: Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than

20 N /sq mm ) grade cement concrete using 20 mm down approved, clean, hard, graded

aggregates for side lining of canal including cost of all materials, machinery, labour,cleaning,

batching, mixing, formwork, supports, placing in position, levelling, vibrating, finishing junction

of bed and sides to required curveture, finishing side slopes, curing etc., complete with lead

upto 50 m and all lifts. ( Cement content : 330 kg / cum with use of super plasticiser )

of super plasticiser )

DATA:For concrete lining of small canals locally fabricated manually operated paver can be considered.

By operating the screw jack the side shuttering can be positioned in place.

Consider laying of concrete in panels of 3 m length.

Length of shutter including 0.10 m overlap on previous lining 3.10 m

Assume 1.5 m bed width and 1.2 m depth of flow. Assume 0.30 m free board.

Assume side slopes of 1.5 horizontal to 1 vertical.

Sloped length of shuttering including 0.20 m free shutter at top and 0.30 m for curved portion and

overlap at bed will be ( 0.20 + 2.70 + 0.30 ) 3.20 m

Area of shutter plate on each side of canal ( 3.1 x 3.2 ) say : 10.00 sqm

As the paver will be released soon after completing concreting upto top level of lining and moved

to next portion to be lined 200 uses can be considered as life of paver.

Further it is assumed that the shuttering of paver will be oiled after every 5 to 6 uses of the paver.

Considering this the quantity of shutter oil is assumed at 0.05 ltr / sqm.

For 1 cum CC :- Coarse aggregates : 0.75 cum Blending ratio : 65 :35

Fine aggregate : 0.41 cum Cement content : 330 kg Super plasticizer : 1.00 ltr

Wastage : 1 % for cement and 2 % for coarse & fine aggregates.

in `.

QuantityDescription Rate

94

Page 97: Data rates-Canal Works

CANAL AND ALLIED WORKS

Consider laying concrete on both sides of the canal.

Therefore, deploy 2 concrete mixers ( diesel ) one on either side for lining.

Consider 300 / 200 ltr capacity mixer and 50 kg cement per mix for use of 20 mm down CA.

Equivalent volume batching using 0.3 x 0.3 x 0.3 m size boxes assumed for batching CA & FA.

Cycle time for batching / mixing / unloading 1 mix :

Batching 20-10 mm CA ( 0.074 cum ) : 4.00 min

Batching 10 mm below CA parellel activity : ---

Batching fine aggregate parellel activity : ---

Batching cement parellel activity : ---

Loading mixer drum & miscellaneous : 1.00 min

Mixing and unloading parellel activity : ---

Add for possible delays in any of the activity : 0.50 min

Total : 5.50 min

No. of mixes per day with 50 min / hr working ( 50 x 8 / 5.5 ) 73 mixes

Output of CC for 73 mixes ( 73 x 50 / 330 ) say : 11.00 cum

Daily output of 2 mixers ( one on either side of paver ) ( 2 x 11.00 ) say : 22.00 cum

For 20 mm down size coarse aggregate 150 mm thick lining is assumed.

Concrete lining area per paver length of 3 m : 18 sqm

Quantity of concrete per use of paver ( 18 x 0.15 ) : 2.70 cum

Add for curveture at junction of sides and bed @ 3 % say : 0.08 cum

Total quantity of concrete / paver length : 2.78 cum

No. of mixes by each mixer / paver length 2.78 / ( 2 x 50 / 330 ) 9 mixes

Consider concrete production and laying as parallel activities.

Cycle time of paver with 50 minutes / hour working :

Time required for laying concrete / paver length ( 9x 5.5x 60/ 50 ) say : 59.00 minutes

Time required for releasing and moving paver : 3.00 minutes

Time required for cleaning and resetting paver : 5.00 minutes

Total time for 1.85 cum concrete lining : 67.00 minutes

Number of paver cycles per day ( 8 x 60 / 67 ) say : 7 cycles

Daily progress based on cycle time of paver ( 7 x 2.78 ) say : 19.50 cum

Area of lining per use : 18.00 sqm

Area of lining for 12 uses of paver ( 18 x 7 ) : 126.00 sqm

For curing concrete use of curing compound is proposed.

10 percent extra curing compound considered for overlaps and wastage.

Water is required only for concrete mixing and washing. One tanker load ( 8000 ltrs) is adequate

for 2 days work. For 1 day work consider 5 hp pump for 0.25 hour & water tanker for 0.5 hour.

Consider 19.50 cum per day as progress of concreting for rate analysis.

1. Requirement of materials :

Cement for mix with 1 % wastage ( 19.5 x 330 x 1.01 ) : 6500 kg

Cement for incidentals @ 5 kg / cum ( 19.5 x 5 ) : 97 kg

Coarse aggregate 20-10 mm size range ( 19.5 x 0.75 x 0.65 x 1.02 ) : 9.70 cum

Coarse aggregate 10-4.75 mm size ( 19.5 x 0.75 x 0.35 x 1.02 ) : 5.22 cum

Fine aggregate ( 19.5 x 0.41 x 1.02 ) : 8.15 cum

Super plasticiser ( 19.5 x 1.0 x 1.02 ) : 19.90 ltrs

Curing compound @ 0.2 ltr / sqm ( 126 x 0.2 x 1.1 ) : 27.70 ltrs

2. Requirement of machinery :

Deploy 300 / 200 ltr diesel concrete mixers 2 Nos. ( 1 on either side of paver ) for 8 hours.

Deploy 1 No. Manual paver for 8 hours for concrete lining.

Deploy 2 Nos. Needle vibraters for 8 hours for compacting concrete.

Deploy 1 Pump 5 hp for 0.25 hour for water requirement at paver site.

95

Page 98: Data rates-Canal Works

CANAL AND ALLIED WORKS

Deploy 1 Water tanker 8000 ltr capacity for 0.5 hour for water requirement at paver site.

3. Formwork & scaffolding :

No formwork / scaffolding required for lining by paver.

4. Requirement of work-force ( other than machinery crew ) :

Lining from both sides of canal using 2 mixers :

Mason Cl I : 2 Nos.

Heavy mazdoor:

For batching cement : 4 Nos.

For batching 20-10 mm size CA : 6 Nos.

For batching 10 mm below size CA : 4 Nos.

For batching FA : 6 Nos.

For remixing & filling mortar pans : 4 Nos.

For loading mortar pans : 4 Nos.

For unloading mortar pans and laying : 4 Nos.

For assisting Mason / Fitter, moving paver & spraying curing compound : 2 Nos.

Light mazdoor:

For conveying concrete @ 1 cum / day ( 8 x 50 x 2.78 / 59 ) say : 20 Nos.

For cleaning & miscellaneous works : 2 Nos.

Fitter for handling the paver : 1 No.

Heavy mazdoors assisting mason also assist fitter for moving and re-positioning of paver.

5. Use rate of manual paver :

Cost of manual paver ( for details refer Item : 32 ) `: 244200.00

Add for repairs / replacements / catwalks etc., @ 25% `: 61050.00

Deduct salvage value @ 10 % ( - ) `: -24420.00

Total `: 280830.00

Consider useful life of paver at 150 uses.

Use rate of paver for av. 150 uses `: 280830 / 150 `: 1872.20

Shutter oil 0.05 ltr /sqm for 18 sqm @ `: 35.00 / ltr `: 31.50

Total `: 1903.70

Area of concreting allowing for overlaps / free shutter ( 3 x 3 x 2 ) : 18 sqm

Uae rate of Manual Paver for concrete / use / sqm `:`:`:`: 105.76

( Excluding T & P / Profit / Overheads)

RATE ANALYSIS UNIT : 19.50 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 Cement for mix kg 6500.00 7.50 48750.00

Cement for incidentals @ 5 kg / cum kg 97.00 7.50 727.50

2 Coarse aggregate 20-10 mm cum 9.70 950.00 9215.00

Coarse aggregate 10 mm below cum 5.22 1160.00 6055.20

3 Fine aggregate cum 8.15 730.00 5949.50

4 Super Plasticizer ltr 19.90 105.00 2089.50

5 Curing compound ltr 27.70 134.00 3711.80

6 Use rate of manual paver sqm 126.00 105.76 13325.90

7 Sundries LS 10.00 44.00 440.00

Total `: 90264.40

Add for small Tools and Plants @ 1% `: 902.64

Add for Contractor's Profit @ 10% `: 9026.44

Contd

in `.

Perticulars

96

RateQuantity

Page 99: Data rates-Canal Works

CANAL AND ALLIED WORKS

A. MATERIALS ( Contd ) :

Sl No Unit Amount

in `:

Contd

Add for Contractor's Overheads @ 5% `: 4513.22

Add Royalty charges on CA @ ( Included in material rate ) `: 0.00

Add Royalty charges on FA @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 104706.70

B. MACHINERY:

Sl No Unit Amount

in `:

1 Concrete mixer 300 / 200 ltr ( diesel ) Hour 16.00 46.00 736.00

Fuel / Energy charges Hour 16.00 76.00 1216.00

2 5 hp pump ( diesel ) Hour 0.25 7.00 1.75

Fuel / Energy charges Hour 0.25 76.00 19.00

3 Water tanker 8000 ltr Hour 0.50 306.00 153.00

Fuel / Energy charges Hour 0.50 286.00 143.00

4 Needle vibrator 40 mm dia ( petrol ) Hour 16.00 9.00 144.00

Fuel / Energy charges Hour 16.00 18.00 288.00

5 Sundries LS 5.00 44.00 220.00

Total `: 2920.75

Add for small Tools and Plants @ 1% `: 29.21

Add for Contractor's Profit on DPOL / Energy @ 10% `: 188.60

Add for Contractor's Overheads @ 5% `: 146.04

Total hire charges of Machinery : `: 3284.60

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Concrete mixer Hour 16.00 126.00 2016.00

2 Crew for Pump Hour 0.25 60.00 15.00

3 Crew for Water tanker Hour 0.50 95.00 47.50

4 Crew for Vibrator Hour 16.00 90.00 1440.00

5 Mason Class-I Day 2.00 256.73 513.46

6 Maistry Day 1.00 241.23 241.23

7 Fitter Day 1.00 254.73 254.73

8 Heavy mazdoor

for batching materials Day 20.00 238.73 4774.60

for loading mortar pans Day 8.00 238.73 1909.84

for laying and moving paver Day 6.00 238.73 1432.38

9 Light mazdoor

for conveying concrete Day 20.00 237.23 4744.60

for cleaning / washing Day 2.00 237.23 474.46

Total `: 17863.80

Add for small Tools and Plants @ 1% `: 178.64

Add for Contractor's Profit @ 10% `: 1786.38

Add for hidden cost on Labour @ 15% `: 2679.57

Add for Contractor's Overheads @ 5% `: 893.19

Total cost of Labour : `: 23401.58

Quantity

in `.

Description

Quantity

97

Quantity Rate

in `.

Description Rate

Perticulars Rate

in `.

Page 100: Data rates-Canal Works

CANAL AND ALLIED WORKS

ABSTRACT:

A. Cost of Materials inluding royalty charges `: 104706.70

B. Hire charges of Machinery `: 3284.60

C. Cost of Labour `: 23401.58

TOTAL `: 131392.88

Add for other enabling works @ 1.00% `: 1313.93

Total cost for 19.50 cum `: 132706.81

Rate per cum `:`:`:`: 6805.48

Rate approved per cum `:`:`:`: 6805.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.33

ITEM: Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than

15 N /sq mm ) grade cement concrete using 40 mm down approved, clean, hard, graded

aggregates for bed lining of canal including cost of all materials, machinery, labour, cleaning,

batching, mixing, formwork, placing in position, levelling, vibrating, finishing, curing etc.,complete

with lead upto 50 m and all lifts. (Cement content : 240 kg / cum with use of super plasticiser)

DATA:For 1 cum CC :- Coarse aggregates : 0.86 cum Blending ratio : 50 :30 : 20

Fine aggregate : 0.42 cum Cement content : 240 kg Super plasticizer : 0.72 ltr

Wastage : 1 % for cement and 2 % for coarse & fine aggregates.

Consider 300 / 200 ltr capacity mixer and 50 kg cement per mix for use of 40 mm down CA.

Equivalent volume batching using 0.3 x 0.3 x 0.3 m size boxes assumed for batching CA & FA.

Cycle time for batching / mixing / unloading 1 mix :

Batching 40-20 mm CA ( 0.094 cum ) : 4.00 min

Batching 20-10 mm & 10 mm below CA parellel activity : ---

Batching fine aggregate parellel activity : ---

Batching cement parellel activity : ---

Loading mixer drum & miscellaneous : 1.00 min

Mixing and unloading parellel activity : ---

Add for possible delays in any of the activity : 0.50 min

Total : 5.50 min

No. of mixes per day with 50 min / hr working ( 50 x 8 / 5.5 ) 73 mixes

Output of CC for 73 mixes ( 73 x 50 / 240 ) say : 15.20 cum

For 40 mm down size coarse aggregate 150 mm thick lining is assumed.

For curing concrete use of curing compound is proposed.

10 percent extra curing compound considered for overlaps and wastage.

Water is required only for concrete mixing and washing. One tanker load (8000 ltrs) is adequate

for 2 days work. For 1 day work consider 5 hp pump for 0.25 hour & water tanker for 0.5 hour.

Consider 15.20 cum per day as progress of concreting for rate analysis.

1. Requirement of materials :

Cement for mix with 1 % wastage ( 15.2 x 240 x 1.01 ) : 3685 kg

Cement for incidentals @ 5 kg / cum ( 15.2 x 5 ) : 76 kg

Coarse aggregate 40-20 mm size range ( 15.2 x 0.9 x 0.5 x 1.02 ) : 7.00 cum

Coarse aggregate 20-10 mm size range ( 15.2 x 0.9 x 0.3 x 1.02 ) : 4.20 cum

Coarse aggregate 10-4.75 mm size ( 15.2 x 0.9 x 0.2 x 1.02 ) : 2.80 cum

Fine aggregate ( 15.2 x 0.4 x 1.02 ) : 6.20 cum

Super plasticiser ( 15.2 x 0.72 x 1.02 ) : 11.20 ltrs

Curing compound @ 0.2 ltr / sqm ( 15.2 x 0.2 x 1.1/ 0.15 ) : 22.30 ltrs

98

Page 101: Data rates-Canal Works

CANAL AND ALLIED WORKS

2. Requirement of machinery :

Deploy 300 / 200 ltr diesel concrete mixer 1 No. for 8 hours.

Deploy 1 No. Needle vibraters for 8 hours for compacting concrete.

Deploy 1 Pump 5 hp for 0.25 hour for water requirement.

Deploy 1 Water tanker 8000 ltr capacity for 0.5 hour for water requirement.

3. Formwork & scaffolding :

No required for bed lining. Lump-sum provision is considered formwork.

4. Requirement of work-force ( other than machinery crew ) :

Mason Cl I : 1 No.

Heavy mazdoor:

For batching cement : 2 Nos.

For batching 40-20 CA : 3 Nos.

For batching 20-10 & 10-4.75 CA : 3 Nos.

For batching FA : 3 Nos.

For remixing & filling mortar pans : 2 Nos.

For loading mortar pans : 2 Nos.

For unloading mortar pans and laying : 2 Nos.

For assisting Mason / spraying curing compound : 1 No.

Light mazdoor:

For conveying concrete @ 1 cum / day say : 15 Nos.

For cleaning & miscellaneous works : 1 No.

RATE ANALYSIS UNIT : 15.20 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 Cement for mix kg 3685.00 7.50 27637.50

Cement for incidentals @ 5 kg / cum kg 76.00 7.50 570.00

2 Coarse aggregate 40-20 mm cum 7.00 740.00 5180.00

Coarse aggregate 20-10 mm cum 4.20 950.00 3990.00

Coarse aggregate 10 mm below cum 2.80 1160.00 3248.00

3 Fine aggregate cum 6.20 730.00 4526.00

4 Super Plasticizer ltr 11.20 105.00 1176.00

5 Curing compound ltr 22.30 134.00 2988.20

6 Sundries ( formwork / supports etc ) LS 3.00 44.00 132.00

Total `: 49447.70

Add for small Tools and Plants @ 1% `: 494.48

Add for Contractor's Profit @ 10% `: 4944.77

Add for Contractor's Overheads @ 5% `: 2472.39

Add Royalty charges on CA @ ( Included in material rate ) `: 0.00

Add Royalty charges on FA @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 57359.33

B. MACHINERY:

Sl No Unit Amount

in `:

1 Concrete mixer 300 / 200 ltr ( diesel ) Hour 8.00 46.00 368.00

Fuel / Energy charges Hour 8.00 76.00 608.00

Contd

Description

99

QuantityPerticulars Rate

in `.

in `.

RateQuantity

Page 102: Data rates-Canal Works

CANAL AND ALLIED WORKS

B. MACHINERY ( Contd ) :

Sl No Unit Amount

in `:

Contd

2 5 hp pump ( diesel ) Hour 0.25 7.00 1.75

Fuel / Energy charges Hour 0.25 76.00 19.00

3 Water tanker 8000 ltr Hour 0.50 306.00 153.00

Fuel / Energy charges Hour 0.50 286.00 143.00

4 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 9.00 72.00

Fuel / Energy charges Hour 8.00 18.00 144.00

Total `: 1508.75

Add for small Tools and Plants @ 1% `: 15.09

Add for Contractor's Profit on DPOL / Energy @ 10% `: 91.40

Add for Contractor's Overheads @ 5% `: 75.44

Total hire charges of Machinery : `: 1690.68

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Concrete mixer Hour 8.00 126.00 1008.00

2 Crew for Pump Hour 0.25 60.00 15.00

3 Crew for Water tanker Hour 0.50 95.00 47.50

4 Crew for Vibrator Hour 8.00 90.00 720.00

5 Mason Class-I Day 1.00 256.73 256.73

6 Maistry Day 1.00 241.23 241.23

7 Heavy mazdoor

for batching materials Day 13.00 238.73 3103.49

for loading mortar pans Day 2.00 238.73 477.46

for laying Day 3.00 238.73 716.19

8 Light mazdoor

for conveying concrete Day 15.00 237.23 3558.45

for cleaning / washing / curing Day 1.00 237.23 237.23

Total `: 10381.28

Add for small Tools and Plants @ 1% `: 103.81

Add for Contractor's Profit @ 10% `: 1038.13

Add for hidden cost on Labour @ 15% `: 1557.19

Add for Contractor's Overheads @ 5% `: 519.06

Total cost of Labour : `: 13599.48

ABSTRACT:

A. Cost of Materials inluding royalty charges `: 57359.33

B. Hire charges of Machinery `: 1690.68

C. Cost of Labour `: 13599.48

TOTAL `: 72649.48

Add for other enabling works @ 1.00% `: 726.49

Total cost for 15.20 cum `: 73375.98

Rate per cum `:`:`:`: 4827.37

Rate approved per cum `:`:`:`: 4827.00

Description Quantity

Description

in `.

Rate

100

Quantity

in `.

Rate

Page 103: Data rates-Canal Works

CANAL AND ALLIED WORKS

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.34

ITEM: Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than

15 N /sq mm ) grade cement concrete using 20 mm down approved, clean, hard, graded

aggregates for bed lining of canal including cost of all materials, machinery, labour, cleaning,

batching, mixing, formwork, placing in position, levelling, vibrating, finishing, curing etc.,complete

with lead upto 50 m and all lifts. (Cement content : 270 kg / cum with use of super plasticiser)

DATA:For 1 cum CC :- Coarse aggregates : 0.77 cum Blending ratio : 65 :35

Fine aggregate : 0.47 cum Cement content : 270 kg Super plasticizer : 0.80 ltr

Wastage : 1 % for cement and 2 % for coarse & fine aggregates.

Consider 300 / 200 ltr capacity mixer and 50 kg cement per mix for use of 20 mm down CA.

Equivalent volume batching using 0.3 x 0.3 x 0.3 m size boxes assumed for batching CA & FA.

Cycle time for batching / mixing / unloading 1 mix :

Batching 20-10 mm CA ( 0.093 cum ) : 4.00 min

Batching 10 mm below CA parellel activity : ---

Batching fine aggregate parellel activity : ---

Batching cement parellel activity : ---

Loading mixer drum & miscellaneous : 1.00 min

Mixing and unloading parellel activity : ---

Add for possible delays in any of the activity : 0.50 min

Total : 5.50 min

No. of mixes per day with 50 min / hr working ( 50 x 8 / 5.5 ) 73 mixes

Output of CC for 73 mixes ( 73 x 50 / 270 ) say : 13.50 cum

For 20 mm down size coarse aggregate 150 mm thick bed lining is assumed.

For curing concrete use of curing compound is proposed.

10 percent extra curing compound considered for overlaps and wastage.

Water is required only for concrete mixing and washing. One tanker load (8000 ltrs) is adequate

for 2 days work. For 1 day work consider 5 hp pump for 0.25 hour & water tanker for 0.5 hour.

Consider 13.50 cum per day as progress of concreting for rate analysis.

1. Requirement of materials :

Cement for mix with 1 % wastage ( 13.5 x 270 x 1.01 ) : 3682 kg

Cement for incidentals @ 5 kg / cum ( 13.5 x 5 ) : 67 kg

Coarse aggregate 20-10 mm size range ( 13.5 x 0.77 x 0.65 x 1.02 ) : 6.90 cum

Coarse aggregate 10-4.75 mm size ( 13.5 x 0.77 x 0.35 x 1.02 ) : 3.70 cum

Fine aggregate ( 13.5 x 0.47 x 1.02 ) : 6.47 cum

Super plasticiser ( 13.5 x 0.8 x 1.02 ) : 11.00 ltrs

Curing compound @ 0.2 ltr / sqm ( 13.5 x 0.2 x 1.1/ 0.15 ) : 19.80 ltrs

2. Requirement of machinery :

Deploy 300 / 200 ltr diesel concrete mixer 1 No. for 8 hours.

Deploy 1 No. Needle vibraters for 8 hours for compacting concrete.

Deploy 1 Pump 5 hp for 0.25 hour for water requirement.

Deploy 1 Water tanker 8000 ltr capacity for 0.5 hour for water requirement.

3. Formwork & scaffolding :

No formwork / scaffolding required for bed lining.

4. Requirement of work-force ( other than machinery crew ) :

Mason Cl I : 1 No.

101

Page 104: Data rates-Canal Works

CANAL AND ALLIED WORKS

Heavy mazdoor:

For batching cement : 2 Nos.

For batching 20-10 mm CA : 3 Nos.

For batching 10-4.75 mm CA : 2 Nos.

For batching FA : 3 Nos.

For remixing & filling mortar pans : 2 Nos.

For loading mortar pans : 2 Nos.

For unloading mortar pans and laying : 2 Nos.

For assisting Mason / spraying curing compound : 1 No.

Light mazdoor:

For conveying concrete @ 1 cum / day say : 14 Nos.

For cleaning & miscellaneous works : 1 No.

RATE ANALYSIS UNIT : 13.50 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 Cement for mix kg 3682.00 7.50 27615.00

Cement for incidentals @ 5 kg / cum kg 67.00 7.50 502.50

2 Coarse aggregate 20-10 mm cum 6.90 950.00 6555.00

Coarse aggregate 10 mm below cum 3.70 1160.00 4292.00

3 Fine aggregate cum 6.47 730.00 4723.10

4 Super Plasticizer ltr 11.00 105.00 1155.00

5 Curing compound ltr 19.80 134.00 2653.20

6 Sundries ( formwork / supports etc ) LS 3.00 44.00 132.00

Total `: 47627.80

Add for small Tools and Plants @ 1% `: 476.28

Add for Contractor's Profit @ 10% `: 4762.78

Add for Contractor's Overheads @ 5% `: 2381.39

Add Royalty charges on CA @ ( Included in material rate ) `: 0.00

Add Royalty charges on FA @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 55248.25

B. MACHINERY:

Sl No Unit Amount

in `:

1 Concrete mixer 300 / 200 ltr ( diesel ) Hour 8.00 46.00 368.00

Fuel / Energy charges Hour 8.00 76.00 608.00

2 5 hp pump ( diesel ) Hour 0.25 7.00 1.75

Fuel / Energy charges Hour 0.25 76.00 19.00

3 Water tanker 8000 ltr Hour 0.50 306.00 153.00

Fuel / Energy charges Hour 0.50 286.00 143.00

4 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 9.00 72.00

Fuel / Energy charges Hour 8.00 18.00 144.00

Total `: 1508.75

Add for small Tools and Plants @ 1% `: 15.09

Add for Contractor's Profit on DPOL / Energy @ 10% `: 91.40

Add for Contractor's Overheads @ 5% `: 75.44

Total hire charges of Machinery : `: 1690.68

QuantityDescription

QuantityPerticulars

in `.

in `.

Rate

Rate

102

Page 105: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Concrete mixer Hour 8.00 126.00 1008.00

2 Crew for Pump Hour 0.25 60.00 15.00

3 Crew for Water tanker Hour 0.50 95.00 47.50

4 Crew for Vibrator Hour 8.00 90.00 720.00

5 Mason Class-I Day 1.00 256.73 256.73

6 Maistry Day 1.00 241.23 241.23

7 Heavy mazdoor

for batching materials Day 12.00 238.73 2864.76

for loading mortar pans Day 2.00 238.73 477.46

for laying Day 3.00 238.73 716.19

8 Light mazdoor

for conveying concrete Day 14.00 237.23 3321.22

for cleaning / washing / curing Day 1.00 237.23 237.23

Total `: 9905.32

Add for small Tools and Plants @ 1% `: 99.05

Add for Contractor's Profit @ 10% `: 990.53

Add for hidden cost on Labour @ 15% `: 1485.80

Add for Contractor's Overheads @ 5% `: 495.27

Total cost of Labour : `: 12975.97

ABSTRACT:

A. Cost of Materials inluding royalty charges `: 55248.25

B. Hire charges of Machinery `: 1690.68

C. Cost of Labour `: 12975.97

TOTAL `: 69914.89

Add for other enabling works @ 1.00% `: 699.15

Total cost for 13.50 cum `: 70614.04

Rate per cum `:`:`:`: 5230.67

Rate approved per cum `:`:`:`: 5231.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.35

ITEM: Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than

20 N /sq mm ) grade cement concrete using 40 mm down approved, clean, hard, graded

aggregates for bed lining of canal including cost of all materials, machinery, labour, cleaning,

batching, mixing, formwork, placing in position, levelling, vibrating, finishing, curing etc.,complete

with lead upto 50 m and all lifts. (Cement content : 270 kg / cum with use of super plasticiser)

DATA:For 1 cum CC :- Coarse aggregates : 0.845 cum Blending ratio : 50 :30 : 20

Fine aggregate : 0.415 cum Cement content : 270 kg Super plasticizer : 0.8 ltr

Wastage : 1 % for cement and 2 % for coarse & fine aggregates.

Consider 300 / 200 ltr capacity mixer and 50 kg cement per mix for use of 40 mm down CA.

Equivalent volume batching using 0.3 x 0.3 x 0.3 m size boxes assumed for batching CA & FA.

Cycle time for batching / mixing / unloading 1 mix :

Batching 40-20 mm CA ( 0.078 cum ) : 4.00 min

Batching 20-10 mm & 10 mm below CA parellel activity : ---

Batching fine aggregate parellel activity : ---

Quantity

103

in `.

RateDescription

Page 106: Data rates-Canal Works

CANAL AND ALLIED WORKS

Batching cement parellel activity : ---

Loading mixer drum & miscellaneous : 1.00 min

Mixing and unloading parellel activity : ---

Add for possible delays in any of the activity : 0.50 min

Total : 5.50 min

No. of mixes per day with 50 min / hr working ( 50 x 8 / 5.5 ) 73 mixes

Output of CC for 73 mixes ( 73 x 50 / 270 ) say : 13.50 cum

For 40 mm down size coarse aggregate 150 mm thick lining is assumed.

For curing concrete use of curing compound is proposed with 10 % extra.

Water is required only for concrete mixing and washing. One tanker load ( 8000 ltrs) is adequate

for 2 days work. For 1 day work consider 5 hp pump for 0.25 hour & water tanker for 0.5 hour.

Consider 13.50 cum per day as progress of concreting for rate analysis.

1. Requirement of materials :

Cement for mix with 1 % wastage ( 13.5 x 270 x 1.01 ) : 3682 kg

Cement for incidentals @ 5 kg / cum ( 13.5 x 5 ) : 67 kg

Coarse aggregate 40-20 mm size range ( 13.5 x 0.845 x 0.5 x 1.02 ) : 5.81 cum

Coarse aggregate 20-10 mm size range ( 13.5 x 0.845 x 0.3 x 1.02 ) : 3.49 cum

Coarse aggregate 10-4.75 mm size ( 13.5 x 0.845 x 0.2 x 1.02 ) : 2.33 cum

Fine aggregate ( 13.5 x 0.415 x 1.02 ) : 5.71 cum

Super plasticiser ( 13.5 x 0.8 x 1.02 ) : 11.00 ltrs

Curing compound @ 0.2 ltr / sqm ( 13.5 x 0.2 x 1.1/ 0.15 ) : 19.80 ltrs

2. Requirement of machinery :

Deploy 300 / 200 ltr diesel concrete mixer 1 No. for 8 hours.

Deploy 1 No. Needle vibraters for 8 hours for compacting concrete.

Deploy 1 Pump 5 hp for 0.25 hour for water requirement.

Deploy 1 Water tanker 8000 ltr capacity for 0.5 hour for water requirement.

3. Formwork & scaffolding :

No formwork / scaffolding required for bed lining.

4. Requirement of work-force ( other than machinery crew ) :

Mason Cl I : 1 No.

Heavy mazdoor:

For batching cement : 2 Nos.

For batching 40-20 CA : 3 Nos.

For batching 20-10 & 10-4.75 CA : 3 Nos.

For batching FA : 3 Nos.

For remixing & filling mortar pans : 2 Nos.

For loading mortar pans : 2 Nos.

For unloading mortar pans and laying : 2 Nos.

For assisting Mason / spraying curing compound : 1 No.

Light mazdoor:

For conveying concrete @ 1 cum / day say : 14 Nos.

For cleaning & miscellaneous works : 1 No.

RATE ANALYSIS UNIT : 13.50 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 Cement for mix kg 3682.00 7.50 27615.00

Cement for incidentals @ 5 kg / cum kg 67.00 7.50 502.50

Contd

Perticulars Quantity

104

in `.

Rate

Page 107: Data rates-Canal Works

CANAL AND ALLIED WORKS

A. MATERIALS ( Contd ) :

Sl No Unit Amount

in `:

Contd

2 Coarse aggregate 40-20 mm cum 5.81 740.00 4299.40

Coarse aggregate 20-10 mm cum 3.49 950.00 3315.50

Coarse aggregate 10 mm below cum 2.33 1160.00 2702.80

3 Fine aggregate cum 5.71 730.00 4168.30

4 Super Plasticizer ltr 11.00 105.00 1155.00

5 Curing compound ltr 19.80 134.00 2653.20

6 Sundries ( formwork / supports etc ) LS 3.00 44.00 132.00

Total `: 46543.70

Add for small Tools and Plants @ 1% `: 465.44

Add for Contractor's Profit @ 10% `: 4654.37

Add for Contractor's Overheads @ 5% `: 2327.19

Add Royalty charges on CA @ ( Included in material rate ) `: 0.00

Add Royalty charges on FA @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 53990.69

B. MACHINERY:

Sl No Unit Amount

in `:

1 Concrete mixer 300 / 200 ltr ( diesel ) Hour 8.00 46.00 368.00

Fuel / Energy charges Hour 8.00 76.00 608.00

2 5 hp pump ( diesel ) Hour 0.25 7.00 1.75

Fuel / Energy charges Hour 0.25 76.00 19.00

3 Water tanker 8000 ltr Hour 0.50 306.00 153.00

Fuel / Energy charges Hour 0.50 286.00 143.00

4 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 9.00 72.00

Fuel / Energy charges Hour 8.00 18.00 144.00

Total `: 1508.75

Add for small Tools and Plants @ 1% `: 15.09

Add for Contractor's Profit on DPOL / Energy @ 10% `: 91.40

Add for Contractor's Overheads @ 5% `: 75.44

Total hire charges of Machinery : `: 1690.68

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Concrete mixer Hour 8.00 126.00 1008.00

2 Crew for Pump Hour 0.25 60.00 15.00

3 Crew for Water tanker Hour 0.50 95.00 47.50

4 Crew for Vibrator Hour 8.00 90.00 720.00

5 Mason Class-I Day 1.00 256.73 256.73

6 Maistry Day 1.00 241.23 241.23

7 Heavy mazdoor

for batching materials Day 13.00 238.73 3103.49

for loading mortar pans Day 2.00 238.73 477.46

for laying Day 3.00 238.73 716.19

Contd

Quantity

Description

Perticulars Quantity

Rate

Rate

Quantity

in `.

105

in `.

Rate

Description

in `.

Page 108: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR ( Contd ) :

Sl No Unit Amount

in `:

Contd

8 Light mazdoor

for conveying concrete Day 14.00 237.23 3321.22

for cleaning / washing Day 1.00 237.23 237.23

Total `: 10144.05

Add for small Tools and Plants @ 1% `: 101.44

Add for Contractor's Profit @ 10% `: 1014.41

Add for hidden cost on Labour @ 15% `: 1521.61

Add for Contractor's Overheads @ 5% `: 507.20

Total cost of Labour : `: 13288.71

ABSTRACT:

A. Cost of Materials inluding royalty charges `: 53990.69

B. Hire charges of Machinery `: 1690.68

C. Cost of Labour `: 13288.71

TOTAL `: 68970.07

Add for other enabling works @ 1.00% `: 689.70

Total cost for 13.50 cum `: 69659.77

Rate per cum `:`:`:`: 5159.98

Rate approved per cum `:`:`:`: 5160.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.36

ITEM: Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than

20 N /sq mm ) grade cement concrete using 20 mm down approved, clean, hard, graded

aggregates for bed lining of canal including cost of all materials, machinery, labour, cleaning,

batching, mixing, formwork, placing in position, levelling, vibrating, finishing, curing etc.,complete

with lead upto 50 m and all lifts. (Cement content : 330 kg / cum with use of super plasticiser)

DATA:For 1 cum CC :- Coarse aggregates : 0.75 cum Blending ratio : 65 :35

Fine aggregate : 0.41 cum Cement content : 330 kg Super plasticizer : 1.00 ltr

Wastage : 1 % for cement and 2 % for coarse & fine aggregates.

Consider 300 / 200 ltr capacity mixer and 50 kg cement per mix for use of 20 mm down CA.

Equivalent volume batching using 0.3 x 0.3 x 0.3 m size boxes assumed for batching CA & FA.

Cycle time for batching / mixing / unloading 1 mix :

Batching 20-10 mm CA ( 0.074 cum ) : 3.00 min

Batching 10 mm below CA parellel activity : ---

Batching fine aggregate parellel activity : ---

Batching cement parellel activity : ---

Loading mixer drum & miscellaneous : 1.00 min

Mixing and unloading parellel activity : ---

Add for possible delays in any of the activity : 0.50 min

Total : 4.50 min

No. of mixes per day with 50 min / hr working ( 50 x 8 / 4.5 ) 89 mixes

Output of CC for 89 mixes ( 89 x 50 / 330 ) say : 13.50 cum

For 20 mm down size coarse aggregate 150 mm thick lining is assumed.

For curing concrete use of curing compound is proposed.

Rate

106

Quantity

in `.

Description

Page 109: Data rates-Canal Works

CANAL AND ALLIED WORKS

10 percent extra curing compound considered for overlaps and wastage.

Water is required only for concrete mixing and washing. One tanker load (8000 ltrs) is adequate

for 2 days work. For 1 day work consider 5 hp pump for 0.25 hour & water tanker for 0.5 hour.

Consider 13.50 cum per day as progress of concreting for rate analysis.

1. Requirement of materials :

Cement for mix with 1 % wastage ( 13.5 x 330 x 1.01 ) : 4500 kg

Cement for incidentals @ 5 kg / cum ( 13.5 x 5 ) : 67 kg

Coarse aggregate 20-10 mm size range ( 13.5 x 0.75 x 0.65 x 1.02 ) : 6.71 cum

Coarse aggregate 10-4.75 mm size ( 13.5 x 0.75 x 0.35 x 1.02 ) : 3.61 cum

Fine aggregate ( 13.5 x 0.41 x 1.02 ) : 5.65 cum

Super plasticiser ( 13.5 x 1.0 x 1.02 ) : 13.80 ltrs

Curing compound @ 0.2 ltr / sqm ( 13.5 x 0.2 x 1.1/ 0.15 ) : 19.80 ltrs

2. Requirement of machinery :

Deploy 300 / 200 ltr diesel concrete mixer 1 No. for 8 hours.

Deploy 1 No. Needle vibraters for 8 hours for compacting concrete.

Deploy 1 Pump 5 hp for 0.25 hour for water requirement.

Deploy 1 Water tanker 8000 ltr capacity for 0.5 hour for water requirement.

3. Formwork & scaffolding :

No formwork / scaffolding required for bed lining.

4. Requirement of work-force ( other than machinery crew ) :

Mason Cl I : 1 No.

Heavy mazdoor:

For batching cement : 2 Nos.

For batching 20-10 mm CA : 3 Nos.

For batching 10-4.75 mm CA : 2 Nos.

For batching FA : 3 Nos.

For remixing & filling mortar pans : 2 Nos.

For loading mortar pans : 2 Nos.

For unloading mortar pans and laying : 2 Nos.

For assisting Mason / spraying curing compound : 1 No.

Light mazdoor:

For conveying concrete @ 1 cum / day say : 14 Nos.

For cleaning & miscellaneous works : 1 No.

RATE ANALYSIS UNIT : 13.50 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 Cement for mix kg 4500.00 7.50 33750.00

Cement for incidentals @ 5 kg / cum kg 67.00 7.50 502.50

2 Coarse aggregate 20-10 mm cum 6.71 950.00 6374.50

Coarse aggregate 10 mm below cum 3.61 1160.00 4187.60

3 Fine aggregate cum 5.65 730.00 4124.50

4 Super Plasticizer ltr 13.80 105.00 1449.00

5 Curing compound ltr 19.80 134.00 2653.20

6 Sundries ( formwork / supports etc ) LS 3.00 44.00 132.00

Total `: 53173.30

Add for small Tools and Plants @ 1% `: 531.73

Add for Contractor's Profit @ 10% `: 5317.33

Contd

Perticulars Rate

107

Quantity

in `.

Page 110: Data rates-Canal Works

CANAL AND ALLIED WORKS

A. MATERIALS ( Contd ) :

Sl No Unit Amount

in `:

Contd

Add for Contractor's Overheads @ 5% `: 2658.67

Add Royalty charges on CA @ ( Included in material rate ) `: 0.00

Add Royalty charges on FA @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 61681.03

B. MACHINERY:

Sl No Unit Amount

in `:

1 Concrete mixer 300 / 200 ltr ( diesel ) Hour 8.00 46.00 368.00

Fuel / Energy charges Hour 8.00 76.00 608.00

2 5 hp pump ( diesel ) Hour 0.25 7.00 1.75

Fuel / Energy charges Hour 0.25 76.00 19.00

3 Water tanker 8000 ltr Hour 0.50 306.00 153.00

Fuel / Energy charges Hour 0.50 286.00 143.00

4 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 9.00 72.00

Fuel / Energy charges Hour 8.00 18.00 144.00

Total `: 1508.75

Add for small Tools and Plants @ 1% `: 15.09

Add for Contractor's Profit on DPOL / Energy @ 10% `: 91.40

Add for Contractor's Overheads @ 5% `: 75.44

Total hire charges of Machinery : `: 1690.68

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Concrete mixer Hour 8.00 126.00 1008.00

2 Crew for Pump Hour 0.25 60.00 15.00

3 Crew for Water tanker Hour 0.50 95.00 47.50

4 Crew for Vibrator Hour 8.00 90.00 720.00

5 Mason Class-I Day 1.00 256.73 256.73

6 Maistry Day 1.00 241.23 241.23

7 Heavy mazdoor

for batching materials Day 12.00 238.73 2864.76

for loading mortar pans Day 2.00 238.73 477.46

for laying Day 3.00 238.73 716.19

8 Light mazdoor

for conveying concrete Day 14.00 237.23 3321.22

for cleaning / washing / curing Day 1.00 237.23 237.23

Total `: 9905.32

Add for small Tools and Plants @ 1% `: 99.05

Add for Contractor's Profit @ 10% `: 990.53

Add for hidden cost on Labour @ 15% `: 1485.80

Add for Contractor's Overheads @ 5% `: 495.27

Total cost of Labour : `: 12975.97

in `.

Description

QuantityDescription

Perticulars Quantity Rate

in `.

in `.

Rate

Rate

Quantity

108

Page 111: Data rates-Canal Works

CANAL AND ALLIED WORKS

ABSTRACT:

A. Cost of Materials inluding royalty charges `: 61681.03

B. Hire charges of Machinery `: 1690.68

C. Cost of Labour `: 12975.97

TOTAL `: 76347.67

Add for other enabling works @ 1.00% `: 763.48

Total cost for 13.50 cum `: 77111.15

Rate per cum `:`:`:`: 5711.94

Rate approved per cum `:`:`:`: 5712.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.37

ITEM: Providing and fixing 50 mm dia and 125 mm long perforated GI pressure relief pipe

with one end closed with perforated GI plate and other end provided with alluminium lid

hinged to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete

with all leads and lifts.

DATA:Consider 10 Nos perforated 50 mm dia GI pipes 125 mm long each for rate analysis.

1. Requirement of materials :

GI pipe 50 mm dia 10 Nos ( 0.125 x 10 ) : 1.25 Rm

GI plate & Alluminium lid ( hinged ) ( 1 x 10 ) : 10 Nos.

2. Requirement of machinery :

No machinery proposed. Lump-sum provision considered for drilling holes in pipes.

3. Requirement of work-force :

Pipe fitter : 0.5 No.

Heavy mazdoor : 0.5 No.

RATE ANALYSIS UNIT : 10.00 Nos.

A. MATERIALS:

Sl No Unit Amount

in `:

1 GI pipe 50 mm dia 10 Nos Rm 1.25 280.00 350.00

2 GI plate & Alluminium lid ( hinged ) LS 10.00 44.00 440.00

Total `: 790.00

Add for small Tools and Plants @ 1% `: 7.90

Add for Contractor's Profit @ 10% `: 79.00

Add for Contractor's Overheads @ 5% `: 39.50

Total cost of Materials : `: 916.40

B. MACHINERY:

Sl No Unit Amount

in `:

1 Drilling 8 mm dia holes LS 2.00 44.00 88.00

0.00 0.00 0.00

Total `: 88.00

Add for small Tools and Plants @ 1% `: 0.88

Add for Contractor's Profit on DPOL / Energy @ 10% `: 8.80

Add for Contractor's Overheads @ 5% `: 4.40

Total hire charges of Machinery : `: 102.08

Perticulars

in `.

Quantity

in `.

Rate

Description Quantity Rate

109

Page 112: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR:

Sl No Unit Amount

in `:

1 Pipe fitter Day 0.50 249.23 124.62

2 Heavy mazdoor Day 0.50 238.73 119.37

Total `: 243.98

Add for small Tools and Plants @ 1% `: 2.44

Add for Contractor's Profit @ 10% `: 24.40

Add for hidden cost on Labour @ 15% `: 36.60

Add for Contractor's Overheads @ 5% `: 12.20

Total cost of Labour : `: 319.61

ABSTRACT:

A. Cost of Materials `: 916.40

B. Hire charges of Machinery `: 102.08

C. Cost of Labour `: 319.61

TOTAL `: 1338.09

Add for enabling works @ 1.00% `: 13.38

Total cost for 10.00 Nos. `: 1351.47

Rate per Each `:`:`:`: 135.15

Rate approved per Each `:`:`:`: 135.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.38

ITEM: Providing and fixing 50 mm dia and 225 mm long perforated GI pressure relief pipe

with one end closed with perforated GI plate and other end provided with alluminium lid

hinged to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete

with all leads and lifts.

DATA:Consider 10 Nos perforated 50 mm dia GI pipes 225 mm long each.

1. Requirement of materials :

GI pipe 50 mm dia 10 Nos ( 0.225 x 10 ) : 2.25 Rm

GI plate & Alluminium lid ( hinged ) ( 1 x 10 ) : 10 Nos.

2. Requirement of machinery :

No machinery proposed. Lump-sum provision considered for drilling holes in pipes.

3. Requirement of work-force :

Pipe fitter : 0.5 No.

Heavy mazdoor : 0.5 No.

RATE ANALYSIS UNIT : 10.00 Nos.

A. MATERIALS:

Sl No Unit Amount

in `:

1 GI pipe 50 mm dia 10 Nos Rm 2.25 280.00 630.00

2 GI plate & Alluminium lid ( hinged ) LS 10.00 44.00 440.00

Total `: 1070.00

Add for small Tools and Plants @ 1% `: 10.70

Add for Contractor's Profit @ 10% `: 107.00

Add for Contractor's Overheads @ 5% `: 53.50

Total cost of Materials : `: 1241.20

QuantityPerticulars

QuantityDescription Rate

110

in `.

in `.

Rate

Page 113: Data rates-Canal Works

CANAL AND ALLIED WORKS

B. MACHINERY:

Sl No Unit Amount

in `:

1 Drilling 8 mm dia holes LS 4.00 44.00 176.00

0.00 0.00 0.00

Total `: 176.00

Add for small Tools and Plants @ 1% `: 1.76

Add for Contractor's Profit on DPOL / Energy @ 10% `: 17.60

Add for Contractor's Overheads @ 5% `: 8.80

Total hire charges of Machinery : `: 204.16

C. LABOUR:

Sl No Unit Amount

in `:

1 Pipe fitter Day 0.50 249.23 124.62

2 Heavy mazdoor Day 0.50 238.73 119.37

Total `: 243.98

Add for small Tools and Plants @ 1% `: 2.44

Add for Contractor's Profit @ 10% `: 24.40

Add for hidden cost on Labour @ 15% `: 36.60

Add for Contractor's Overheads @ 5% `: 12.20

Total cost of Labour : `: 319.61

ABSTRACT:

A. Cost of Materials `: 1241.20

B. Hire charges of Machinery `: 204.16

C. Cost of Labour `: 319.61

TOTAL `: 1764.97

Add for enabling works @ 1.00% `: 17.65

Total cost for 10.00 Nos. `: 1782.62

Rate per Each `:`:`:`: 178.26

Rate approved per Each `:`:`:`: 178.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.39

ITEM: Providing and fixing 50 mm dia and 300 mm long perforated GI pressure relief pipe

with one end closed with perforated GI plate and other end provided with alluminium lid

hinged to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete

with all leads and lifts.

DATA:Consider 10 Nos perforated 50 mm dia GI pipes 300 mm long each.

1. Requirement of materials :

GI pipe 50 mm dia 10 Nos ( 0.3 x 10 ) : 3.00 Rm

GI plate & Alluminium lid ( hinged ) ( 1 x 10 ) : 10 Nos.

2. Requirement of machinery :

No machinery proposed. Lump-sum provision considered for drilling holes in pipes.

3. Requirement of work-force :

Pipe fitter : 0.5 No.

Heavy mazdoor : 0.5 No.

Description Quantity

Description Quantity

in `.

Rate

in `.

111

Rate

Page 114: Data rates-Canal Works

CANAL AND ALLIED WORKS

RATE ANALYSIS UNIT : 10.00 Nos.

A. MATERIALS:

Sl No Unit Amount

in `:

1 GI pipe 50 mm dia 10 Nos Rm 3.00 280.00 840.00

2 GI plate & Alluminium lid ( hinged ) LS 10.00 44.00 440.00

Total `: 1280.00

Add for small Tools and Plants @ 1% `: 12.80

Add for Contractor's Profit @ 10% `: 128.00

Add for Contractor's Overheads @ 5% `: 64.00

Total cost of Materials : `: 1484.80

B. MACHINERY:

Sl No Unit Amount

in `:

1 Drilling 8 mm dia holes LS 7.00 44.00 308.00

0.00 0.00 0.00

Total `: 308.00

Add for small Tools and Plants @ 1% `: 3.08

Add for Contractor's Profit on DPOL / Energy @ 10% `: 30.80

Add for Contractor's Overheads @ 5% `: 15.40

Total hire charges of Machinery : `: 357.28

C. LABOUR:

Sl No Unit Amount

in `:

1 Pipe fitter Day 0.50 249.23 124.62

2 Heavy mazdoor Day 0.50 238.73 119.37

Total `: 243.98

Add for small Tools and Plants @ 1% `: 2.44

Add for Contractor's Profit @ 10% `: 24.40

Add for hidden cost on Labour @ 15% `: 36.60

Add for Contractor's Overheads @ 5% `: 12.20

Total cost of Labour : `: 319.61

ABSTRACT:

A. Cost of Materials `: 1484.80

B. Hire charges of Machinery `: 357.28

C. Cost of Labour `: 319.61

TOTAL `: 2161.69

Add for enabling works @ 1.00% `: 21.62

Total cost for 10.00 Nos. `: 2183.31

Rate per Each `:`:`:`: 218.33

Rate approved per Each `:`:`:`: 218.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.40

ITEM: Providing and fixing 50 mm dia and 450 mm long perforated GI pressure relief pipe

with one end closed with perforated GI plate and other end provided with alluminium lid

Perticulars

Description

Description

112

Rate

in `.

Quantity

Quantity

in `.

in `.

Rate

RateQuantity

Page 115: Data rates-Canal Works

CANAL AND ALLIED WORKS

hinged to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete

with all leads and lifts.

DATA:Consider 10 Nos perforated 50 mm dia GI pipes 450 mm long each.

1. Requirement of materials :

GI pipe 50 mm dia 10 Nos ( 0.45 x 10 ) : 4.50 Rm

GI plate & Alluminium lid ( hinged ) ( 1 x 10 ) : 10 Nos.

2. Requirement of machinery :

No machinery proposed. Lump-sum provision considered for drilling holes in pipes.

3. Requirement of work-force :

Pipe fitter : 0.5 No.

Heavy mazdoor : 0.5 No.

RATE ANALYSIS UNIT : 10.00 Nos.

A. MATERIALS:

Sl No Unit Amount

in `:

1 GI pipe 50 mm dia 10 Nos Rm 4.50 280.00 1260.00

2 GI plate & Alluminium lid ( hinged ) LS 10.00 44.00 440.00

Total `: 1700.00

Add for small Tools and Plants @ 1% `: 17.00

Add for Contractor's Profit @ 10% `: 170.00

Add for Contractor's Overheads @ 5% `: 85.00

Total cost of Materials : `: 1972.00

B. MACHINERY:

Sl No Unit Amount

in `:

1 Drilling 8 mm dia holes LS 10.00 44.00 440.00

0.00 0.00 0.00

Total `: 440.00

Add for small Tools and Plants @ 1% `: 4.40

Add for Contractor's Profit on DPOL / Energy @ 10% `: 44.00

Add for Contractor's Overheads @ 5% `: 22.00

Total hire charges of Machinery : `: 510.40

C. LABOUR:

Sl No Unit Amount

in `:

1 Pipe fitter Day 0.50 249.23 124.62

2 Heavy mazdoor Day 0.50 238.73 119.37

Total `: 243.98

Add for small Tools and Plants @ 1% `: 2.44

Add for Contractor's Profit @ 10% `: 24.40

Add for hidden cost on Labour @ 15% `: 36.60

Add for Contractor's Overheads @ 5% `: 12.20

Total cost of Labour : `: 319.61

Perticulars

Description

Description

Rate

in `.

Rate

in `.

RateQuantity

113

Quantity

in `.

Quantity

Page 116: Data rates-Canal Works

CANAL AND ALLIED WORKS

ABSTRACT:

A. Cost of Materials `: 1972.00

B. Hire charges of Machinery `: 510.40

C. Cost of Labour `: 319.61

TOTAL `: 2802.01

Add for enabling works @ 1.00% `: 28.02

Total cost for 10.00 Nos. `: 2830.03

Rate per Each `:`:`:`: 283.00

Rate approved per Each `:`:`:`: 283.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.41

ITEM: Providing and fixing 50 mm dia and 750 mm long perforated GI pressure relief pipe

with one end closed with perforated GI plate and other end provided with alluminium lid

hinged to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete

with all leads and lifts.

DATA:Consider 10 Nos perforated 50 mm dia GI pipes 750 mm long each.

1. Requirement of materials :

GI pipe 50 mm dia 10 Nos ( 0.75 x 10 ) : 7.50 Rm

GI plate & Alluminium lid ( hinged ) ( 1 x 10 ) : 10 Nos.

2. Requirement of machinery :

No machinery proposed. Lump-sum provision considered for drilling holes in pipes.

3. Requirement of work-force :

Pipe fitter : 0.5 No.

Heavy mazdoor : 0.5 No.

RATE ANALYSIS UNIT : 10.00 Nos.

A. MATERIALS:

Sl No Unit Amount

in `:

1 GI pipe 50 mm dia Rm 7.50 280.00 2100.00

2 GI plate & Alluminium lid ( hinged ) LS 10.00 44.00 440.00

Total `: 2540.00

Add for small Tools and Plants @ 1% `: 25.40

Add for Contractor's Profit @ 10% `: 254.00

Add for Contractor's Overheads @ 5% `: 127.00

Total cost of Materials : `: 2946.40

B. MACHINERY:

Sl No Unit Amount

in `:

1 Drilling 8 mm dia holes LS 15.00 44.00 660.00

0.00 0.00 0.00

Total `: 660.00

Add for small Tools and Plants @ 1% `: 6.60

Add for Contractor's Profit on DPOL / Energy @ 10% `: 66.00

Add for Contractor's Overheads @ 5% `: 33.00

Total hire charges of Machinery : `: 765.60

Description

114

in `.

RateQuantityPerticulars

RateQuantity

in `.

Page 117: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR:

Sl No Unit Amount

in `:

1 Pipe fitter Day 0.50 249.23 124.62

2 Heavy mazdoor Day 0.50 238.73 119.37

Total `: 243.98

Add for small Tools and Plants @ 1% `: 2.44

Add for Contractor's Profit @ 10% `: 24.40

Add for hidden cost on Labour @ 15% `: 36.60

Add for Contractor's Overheads @ 5% `: 12.20

Total cost of Labour : `: 319.61

ABSTRACT:

A. Cost of Materials `: 2946.40

B. Hire charges of Machinery `: 765.60

C. Cost of Labour `: 319.61

TOTAL `: 4031.61

Add for enabling works @ 1.00% `: 40.32

Total cost for 10.00 Nos. `: 4071.93

Rate per Each `:`:`:`: 407.19

Rate approved per Each `:`:`:`: 407.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.42

ITEM: Drilling 1.00 m deep 32 mm dia pressure relief hole below pressure relief pipe for bed /

side lining of canal laid on rock including cost of all materials, machinery, labour etc.,

complete with all leads and lifts.

DATA:Consider 32 mm dia jack hammer dilling .

Rate of drilling assumed per hour : 5.00 Rm

Deploy 1 air compressor 8.5 cmm and 2 jack hammers for drilling.

Rate of progress for 1 m deep holes per hour with 2 jack hammers. : 10 holes

Time required for drilling 10 m ( 10 / ( 2 x 5 ) : 1 hour

Consider drilling 10 holes for rate analysis.

1. Requirement of materials :

Jack hammer drill rod ( 10 x 1 ) : 10 m drilling

2. Requirement of machinery :

Deploy 8.5 cmm Air compressor ( diesel ) for 1 hour.

Deploy 2 Nos. Jack hammers for 1 hour for drilling.

3. Requirement of work-force ( other than machinery crew ) :

No work-force required other than machinery crew.

4. Use rate of materials :

Cost of 1.5 m drill rod @ `: 4395.00 / Each `: 4395.00

Life of drill rod for drilling in hard rock with reconditioning : 150 Rm

Use rate of drill rod per Rm drilling ( cost / life ) `: 29.30

Cost of 25 mm dia air hose 50 m @ `: 200.00 / Rm `: 10000.00

Life of air hose : 800 hours

Description Quantity

115

Rate

in `.

Page 118: Data rates-Canal Works

CANAL AND ALLIED WORKS

Use rate of air hose per hour ( cost / life ) `: 12.50

Consider 10 holes of 1 m depth for analysis.

RATE ANALYSIS UNIT : 10.00 Nos.

A. MATERIALS:

Sl No Unit Amount

in `:

1 Use rate of drill rod 1.5 m long Rm 10.00 29.30 293.00

Reconditioning charges @ 10 % 29.30

2 Use rate of air hose 2 Nos. Hour 2.00 12.50 25.00

Total `: 347.30

Add for small Tools and Plants @ 1% `: 3.47

Add for Contractor's Profit @ 10% `: 34.73

Add for Contractor's Overheads @ 5% `: 17.37

Total cost of Materials : `: 402.87

B. MACHINERY:

Sl No Unit Amount

in `:

1 Air compressor 8.5 cmm diesel Hour 1.00 223.00 223.00

Fuel / Energy charges Hour 1.00 851.00 851.00

2 Jack hammer 2 Nos. Hour 2.00 16.00 32.00

Fuel / Energy charges Hour 2.00 8.00 16.00

Total `: 1122.00

Add for small Tools and Plants @ 1% `: 11.22

Add for Contractor's Profit on DPOL / Energy @ 10% `: 86.70

Add for Contractor's Overheads @ 5% `: 56.10

Total hire charges of Machinery : `: 1276.02

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Air compressor Hour 1.00 121.00 121.00

2 Crew for Jack hammer Hour 2.00 188.00 376.00

Total `: 497.00

Add for small Tools and Plants @ 1% `: 4.97

Add for Contractor's Profit @ 10% `: 49.70

Add for hidden cost on Labour @ 15% `: 74.55

Add for Contractor's Overheads @ 5% `: 24.85

Total cost of Labour : `: 651.07

ABSTRACT:

A. Cost of Materials `: 402.87

B. Hire charges of Machinery `: 1276.02

C. Cost of Labour `: 651.07

TOTAL `: 2329.96

Add for enabling works @ 1.00% `: 23.30

Total cost for 10.00 Nos. `: 2353.26

Rate per Each `:`:`:`: 235.33

Rate approved per Each `:`:`:`: 235.00

Description

Perticulars Rate

in `.

Rate

in `.

116

Description

Rate

Quantity

Quantity

Quantity

in `.

Page 119: Data rates-Canal Works

CANAL AND ALLIED WORKS

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.43

ITEM: Providing and forming 350 x 350 x 400 mm deep filter drain consisting of 75 mm thick

10 mm down coarse aggregate layer around pressure relief pipe and 75 mm thick sand

layer around coarse aggregate layer including cost of all materials, labour, excavation of pit

etc., complete with lead upto 50 m and all lifts.

DATA:Consider 10 Nos filter drains.

1. Requirement of materials :

10-4.75 mm filter (10 x 0.2 x 0.2 x 0.4 x 1.02 ) 0.16 cum

Sand filter ( 10 x 0.35 x 0.35 x 0.4 x 1.02 - 0.16 ) 0.34 cum

2. Requirement of machinery :

No machinery proposed.

3. Requirement of work-force :

Mason Cl- II : 0.1 No.

Heavy mazdoor : 0.1 No.

RATE ANALYSIS UNIT : 10.00 Nos.

A. MATERIALS:

Sl No Unit Amount

in `:

1 Coarse aggregate 10-4.75 mm cum 0.15 1160.00 174.00

2 Sand ( unscreened ) cum 0.35 615.00 215.25

Total `: 389.25

Add for small Tools and Plants @ 1% `: 3.89

Add for Contractor's Profit @ 10% `: 38.93

Add for Contractor's Overheads @ 5% `: 19.46

Add Royalty charges on CA @ ( Included in material rate ) `: 0.00

Add Royalty charges on FA @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 451.53

B. MACHINERY:

Sl No Unit Amount

in `:

1 Nil 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Mason Cl- II Day 0.10 244.23 24.42

2 Heavy mazdoor Day 0.10 238.73 23.87

Total `: 48.30

Contd

Description

117

Rate

in `.

Quantity

Description

Quantity

Quantity

Perticulars

Rate

in `.

Rate

in `.

Page 120: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR ( Contd ) :

Sl No Unit Amount

in `:

Contd

Add for small Tools and Plants @ 1% `: 0.48

Add for Contractor's Profit @ 10% `: 4.83

Add for hidden cost on Labour @ 15% `: 7.24

Add for Contractor's Overheads @ 5% `: 2.41

Total cost of Labour : `: 63.27

ABSTRACT:

A. Cost of Materials including royalty charges `: 451.53

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 63.27

TOTAL `: 514.80

Add for enabling works @ 1.00% `: 5.15

Total cost for 10.00 Nos. `: 519.95

Rate per Each `:`:`:`: 51.99

Rate approved per Each `:`:`:`: 52.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.44

ITEM: Fixing 25 to 40 mm thick Shahabad / Talikota / other similar stone slabs with pointing in

CM 1:3 proportion by volume for canal / field channel lining including cost of all materials

( except stone slabs ), labour, preparing surface, cutting slabs to required size, batching and

mixing mortar, packing mortar into joints and flush finishing joints neatly, curing etc.,complete

with lead upto 50 m and all lifts.

DATA:Consider 100 sqm slab lining in CM 1:3 proportion for rate analysis.

Quantity of CM 1:3 for pointing @ 0.002 cum / sqm ( 100 x 0.002 ) 0.20 cum

For 1 cum CM 1 : 3 mortar Cement : 460 kg Sand : 0.96 cum

Wastage of materials : 1 % for cement, 2 % for sand.

1. Requirement of materials :

Shahbad stone slabs ( 100 x 1.02 ) 102 sqm

Cement ( 0.2 x 460 x 1.01 ) 93 kg

Sand ( 0.2 x 0.96 x 1.02 ) 0.20 cum

2. Requirement of machinery :

No machinery proposed.

3. Requirement of work-force :

Maistry 1 No.

Mason Cl- II for preparing stone slabs for laying : 4 Nos.

Mason Cl- I for laying and jointing stone slabs : 4 Nos.

Heavy mazdoor for conveying stone slabs : 4 Nos.

Heavy mazdoor for assisting mason for laying stones : 4 Nos.

Heavy mazdoor for cement mortar mixing & conveying : 1 No.

Cartman with Double bullock cart for conveying water : 1 No.

Light mazdoor for curing : 1 No.

118

in `.

RateQuantityDescription

Page 121: Data rates-Canal Works

CANAL AND ALLIED WORKS

RATE ANALYSIS UNIT : 100.00 sqm

A. MATERIALS:

Sl No Unit Amount

in `:

1 Shahabad Stone slabs sqm 0.00 270.00 0.00

2 Cement 43 Gr kg 93.00 7.50 697.50

3 Sand ( screened ) cum 0.20 730.00 146.00

Total `: 843.50

Add for small Tools and Plants @ 1% `: 8.44

Add for Contractor's Profit @ 10% `: 84.35

Add for Contractor's Overheads @ 5% `: 42.18

Add Royalty charges on slabs @ ( Included in material rate ) `: 0.00

Add Royalty charges on sand @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 978.46

B. MACHINERY:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Maistry Day 1.00 241.23 241.23

2 Mason Class I Day 4.00 256.73 1026.92

3 Mason Class II Day 4.00 244.23 976.92

4 Heavy mazdoor Day 9.00 238.73 2148.57

5 Cartman with Bullock cart for water Day 1.00 278.23 278.23

6 Light mazdoor Day 1.00 237.23 237.23

Total `: 4909.10

Add for small Tools and Plants @ 1% `: 49.09

Add for Contractor's Profit @ 10% `: 490.91

Add for hidden cost on Labour @ 15% `: 736.37

Add for Contractor's Overheads @ 5% `: 245.46

Total cost of Labour : `: 6430.92

ABSTRACT:

A. Cost of Materials including royalty charges `: 978.46

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 6430.92

TOTAL `: 7409.38

Add for enabling works @ 1.00% `: 74.09

Total cost for 100.00 sqm `: 7483.47

Rate per sqm `:`:`:`: 74.83

Rate approved per sqm `:`:`:`: 75.00

Perticulars

in `.

Description

QuantityDescription

Rate

in `.

Rate

in `.

Quantity

119

RateQuantity

Page 122: Data rates-Canal Works

CANAL AND ALLIED WORKS

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.45

ITEM: Fixing PCC slabs of various sizes in CM 1 : 3 proportion by volume to side slopes of

canal including cost of all materials (excluding PCC slabs ), labour, preparing surface, packing

mortar into joints and flush finishing joints neatly, curing etc., complete with lead upto 50 m

and all lifts.

DATA:Consider 100 sqm slab lining in CM 1:3 proportion for rate analysis.

Consider 450 x 450 x 55 mm size lining slabs for working out mortar quantity.

Quantity of CM 1:3 for pointing @ 0.005 cum / sqm ( 100 x 0.005 ) 0.50 cum

For 1 cum CM 1 : 3 mortar Cement : 460 kg Sand : 0.96 cum

Wastage of materials : 1 % for cement and 2 % for sand.

1. Requirement of materials :

Cement ( 0.5 x 460 x 1.01 ) 233 kg

Sand ( 0.5 x 0.96 x 1.02 ) 0.50 cum

2. Requirement of machinery :

No machinery proposed.

3. Requirement of work-force :

Maistry 1 No.

Mason Cl- I for laying and jointing PCC slabs : 4 Nos.

Heavy mazdoor for conveying PCC slabs : 4 Nos.

Heavy mazdoor for assisting mason for laying slabs : 3 Nos.

Heavy mazdoor for cement mortar mixing & conveying : 1 No.

Cartman with Double bullock cart for conveying water : 1 No.

Light mazdoor for curing : 1 No.

RATE ANALYSIS UNIT : 100.00 sqm

A. MATERIALS:

Sl No Unit Amount

in `:

1 Cement 43 Gr kg 233.00 7.50 1747.50

2 Sand ( screened ) cum 0.50 730.00 365.00

Total `: 2112.50

Add for small Tools and Plants @ 1% `: 21.13

Add for Contractor's Profit @ 10% `: 211.25

Add for Contractor's Overheads @ 5% `: 105.63

Add Royalty charges on sand @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 2450.50

B. MACHINERY:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

Description

in `.

QuantityPerticulars Rate

in `.

RateQuantity

120

Page 123: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR:

Sl No Unit Amount

in `:

1 Maistry Day 1.00 241.23 241.23

2 Mason Class I Day 4.00 256.73 1026.92

3 Heavy mazdoor Day 8.00 238.73 1909.84

4 Cartman with Bullock cart for water Day 1.00 278.23 278.23

5 Light mazdoor Day 1.00 237.23 237.23

Total `: 3693.45

Add for small Tools and Plants @ 1% `: 36.93

Add for Contractor's Profit @ 10% `: 369.35

Add for hidden cost on Labour @ 15% `: 554.02

Add for Contractor's Overheads @ 5% `: 184.67

Total cost of Labour : `: 4838.42

ABSTRACT:

A. Cost of Materials including royalty charges `: 2450.50

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 4838.42

TOTAL `: 7288.92

Add for enabling works @ 1.00% `: 72.89

Total cost for 100.00 sqm `: 7361.81

Rate per sqm `:`:`:`: 73.62

Rate approved per sqm `:`:`:`: 74.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.46

ITEM: Fixing PCC lug slabs of various sizes in CM 1 : 3 proportion by volume for supporting

PCC slab lining including cost of all materials ( excluding PCC lug slabs ), labour, necessary

excavation, refilling, batching and mixing mortar, packing mortar into joints and flush finishing

joints neatly, curing etc., complete with lead upto 50 m and all lifts.

DATA:Consider 100 Rm lug slab fixing in CM 1:3 proportion.

Consider 450 x 150 x 30 mm size lug slabs for working out mortar quantity.

Quantity of CM 1:3 for pointing @ 0.0013 cum / Rm ( 100 x 0.0013 ) 0.13 cum

For 1 cum CM 1 : 3 mortar Cement : 460 kg Sand : 0.96 cum

Wastage of materials : 1 % for cement and 2 % for sand.

1. Requirement of materials :

Cement ( 0.13 x 460 x 1.01 ) 60 kg

Sand ( 0.13 x 0.96 x 1.02 ) 0.13 cum

2. Requirement of machinery :

No machinery proposed.

3. Requirement of work-force :

Maistry : 1 No.

Mason Cl- I for fixing and jointing PCC lug slabs : 1 No.

Mason Cl- II for assisting Mason Cl- I : 2 No.

Heavy mazdoor for conveying PCC lug slabs : 1 No.

Description Quantity

in `.

Rate

121

Page 124: Data rates-Canal Works

CANAL AND ALLIED WORKS

Heavy mazdoor for assisting mason for fixing PCC lug slabs : 2 Nos.

Heavy mazdoor for cement mortar mixing & conveying : 1 No.

Cartman with Double bullock cart for conveying water : 1 No.

Curing Light mazdoor : 1 No.

RATE ANALYSIS UNIT : 100.00 Rm

A. MATERIALS:

Sl No Unit Amount

in `:

1 Cement 43 Gr kg 60.00 7.50 450.00

2 Sand ( screened ) cum 0.13 730.00 94.90

Total `: 544.90

Add for small Tools and Plants @ 1% `: 5.45

Add for Contractor's Profit @ 10% `: 54.49

Add for Contractor's Overheads @ 5% `: 27.25

Add Royalty charges on sand @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 632.08

B. MACHINERY:

Sl No Unit Amount

in `:

1 NIL 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Maistry Day 1.00 241.23 241.23

2 Mason Class I Day 1.00 256.73 256.73

3 Mason Class II Day 2.00 244.23 488.46

4 Heavy mazdoor Day 4.00 238.73 954.92

5 Cartman with Bullock cart for water Day 1.00 278.23 278.23

6 Light mazdoor Day 1.00 237.23 237.23

Total `: 2456.80

Add for small Tools and Plants @ 1% `: 24.57

Add for Contractor's Profit @ 10% `: 245.68

Add for hidden cost on Labour @ 15% `: 368.52

Add for Contractor's Overheads @ 5% `: 122.84

Total cost of Labour : `: 3218.41

ABSTRACT:

A. Cost of Materials including royalty charges `: 632.08

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 3218.41

TOTAL `: 3850.49

122

RateQuantity

in `.

Description

Description

Rate

Rate

in `.

Perticulars

in `.

Quantity

Quantity

Page 125: Data rates-Canal Works

CANAL AND ALLIED WORKS

Add for enabling works @ 1.00% `: 38.50

Total cost for 100.00 Rm `: 3889.00

Rate per Rm `:`:`:`: 38.89

Rate approved per Rm `:`:`:`: 39.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.47

ITEM: Fixing 300 mm height pre-cast drop for field channel as directed including excavation and

bachfilling to the extent necessary etc., complete with all leads and lifts.

DATA:It is assumed that pre-cast drops will be supplied by the department at all drop locations.

1 Mason CL- II & 1 heavy mazdoor assumed for fixing 7 drops per day.

Consider fixing 7 pre-cast drops for rate analysis.

1. Requirement of materials :

Only labour charges involved for this item.

2. Requirement of machinery :

No machinery proposed.

3. Requirement of workforce :

Maistry : 1 No.

Mason Cl- II : 1 No.

Heavy mazdoor : 1 No.

RATE ANALYSIS UNIT : 7.00 Nos

A. MATERIALS:

Sl No Unit Amount

in `:

1 Nil 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total cost of Materials : `: 0.00

B. MACHINERY:

Sl No Unit Amount

in `:

1 Nil 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Maistry Day 1.00 241.23 241.23

Contd

Quantity

Description

Perticulars Quantity

in `.

Rate

Rate

123

Quantity

Description Rate

in `.

in `.

Page 126: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR ( Contd ) :

Sl No Unit Amount

in `:

Contd

2 Mason Cl- II Day 1.00 244.23 244.23

3 Heavy mazdoor Day 1.00 238.73 238.73

Total `: 724.19

Add for small Tools and Plants @ 1% `: 7.24

Add for Contractor's Profit @ 10% `: 72.42

Add for hidden cost on Labour @ 15% `: 108.63

Add for Contractor's Overheads @ 5% `: 36.21

Total cost of Labour : `: 948.69

ABSTRACT:

A. Cost of Materials `: 0.00

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 948.69

TOTAL `: 948.69

Add for enabling works @ 1.00% `: 9.49

Total cost for 7.00 Nos. `: 958.18

Rate per Each `:`:`:`: 136.88

Rate approved per Each `:`:`:`: 137.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.48.1

ITEM: Providing and fixing LDPE sheet for bed and sides of canal including cost of all materials,

labour, laying, joining as per specifications etc., complete with all leads and lifts.

48.a. Using 500 micron thick LDPE sheet.

DATA:Consider 250 sqm LDPE sheet 500 micron thick laying per day.

Consider 10 percent extra sheet for joints & wastage.

Hot bitumen Grade 85 / 25 and 80 / 100 in the ratio of 2 : 1 considered for joining sheets.

Consider 1 heavy mazdoor for assisting in laying work by supplier.

FSL

Concrete / Slab lining

CANAL

LDPE sheet

75 mm thick sand backing

( optional )

FSL

Concrete / Slab lining

CANAL

LDPE sheet

CNS lining ( optional )

TYPICAL SKETCH SHOWING LDPE SHEET FOR CANAL LINING

Description

in `.

RateQuantity

124

Page 127: Data rates-Canal Works

CANAL AND ALLIED WORKS

Consider 250 sqm LDPE sheet laying and jointing for rate analysis.

1. Requirement of materials :

LDPE sheet 500 micron thick ( 250 x 1.1 ) : 275 sqm

Bitumen 85/25 & 80/100 Gr @ 0.015 kg / sqm ( 250 x 0.015 x1.05 ) : 4 kg

2. Requirement of machinery :

No machinery proposed.

3. Requirement of workforce :

Laying and joining by supplier @ 10 % of sheet cost

Heavy mazdoor to assist supplier,s workforce : 1 No.

RATE ANALYSIS UNIT : 250.00 sqm

A. MATERIALS:

Sl No Unit Amount

in `:

1 LDPE sheet 500 micron thick sqm 275.00 110.00 30250.00

2 Bitumen 85 / 25 and 80 / 100 Gr kg 4.00 52.00 208.00

Total `: 30458.00

Add for small Tools and Plants @ 1% `: 304.58

Add for Contractor's Profit @ 10% `: 3045.80

Add for Contractor's Overheads @ 5% `: 1522.90

Total cost of Materials : `: 35331.28

B. MACHINERY:

Sl No Unit Amount

in `:

1 Nil 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Joining & laying @ 10 % of sheet cost sqm 250.00 11.00 2750.00

2 Heavy mazdoor Day 1.00 238.73 238.73

Total `: 2988.73

Add for small Tools and Plants @ 1% `: 29.89

Add for Contractor's Profit @ 10% `: 298.87

Add for hidden cost on Labour @ 15% `: 448.31

Add for Contractor's Overheads @ 5% `: 149.44

Total cost of Labour : `: 3915.24

ABSTRACT:

A. Cost of Materials including royalty charges `: 35331.28

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 3915.24

TOTAL `: 39246.52

Perticulars

Description Quantity

in `.

Description

Rate

Rate

in `.

Rate

in `.

Quantity

125

Quantity

Page 128: Data rates-Canal Works

CANAL AND ALLIED WORKS

Add for enabling works @ 1.00% `: 392.47

Total cost for 250.00 sqm `: 39638.98

Rate per sqm `:`:`:`: 158.56

Rate approved per sqm `:`:`:`: 159.00

Note : 1. If the surface on which the LDPE sheet is to be laid is too rough and undulating provide

average 75 mm thick unscreened sand backing to LDPE sheet.

2. For providing average 75 mm thick sand backing :

DATA:Quantity of sand ( unscreened ) ( 250 x 0.075 x 1.02 ) : 19.20 cum

1 heavy and 1 light mazdoor for laying 6 cum per day.

RATE ANALYSIS UNIT : 250.00 sqm

A. MATERIALS:

Sl No Unit Amount

in `:

1 Sand ( unscreened ) with 2 % wastage cum 19.20 615.00 11808.00

0.00 0.00 0.00

Total `: 11808.00

Add for small Tools and Plants @ 1% `: 118.08

Add for Contractor's Profit @ 10% `: 1180.80

Add for Contractor's Overheads @ 5% `: 590.40

Add Royalty charges on sand @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 13697.28

B. MACHINERY:

Sl No Unit Amount

in `:

1 Nil 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Heavy mazdoor Day 3.00 238.73 716.19

2 Light mazdoor Day 3.00 237.23 711.69

Total `: 1427.88

Add for small Tools and Plants @ 1% `: 14.28

Add for Contractor's Profit @ 10% `: 142.79

Add for hidden cost on Labour @ 15% `: 214.18

Add for Contractor's Overheads @ 5% `: 71.39

Total cost of Labour : `: 1870.52

in `.

Quantity Rate

Rate

in `.

in `.

Description

RateQuantity

126

Description

Quantity

Perticulars

Page 129: Data rates-Canal Works

CANAL AND ALLIED WORKS

ABSTRACT:

A. Cost of Materials including royalty charges `: 13697.28

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 1870.52

TOTAL `: 15567.80

Add for enabling works @ 1.00% `: 155.68

Total cost for 250.00 sqm `: 15723.48

Rate per sqm `:`:`:`: 63.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.48.2

ITEM: Providing and fixing LDPE sheet for bed and sides of canal including cost of all materials,

labour, laying, joining as per specifications etc., complete with all leads and lifts.

48.b. Using 750 micron thick LDPE sheet.

DATA:Consider 250 sqm LDPE sheet 750 micron thick laying per day.

Consider 10 percent extra sheet for joints & wastage.

Hot bitumen Grade 85 / 25 and 80 / 100 in the ratio of 2 : 1 considered for joining sheets.

Consider 1 heavy mazdoor for assisting in laying work by supplier.

Consider 250 sqm LDPE sheet laying and jointing for rate analysis.

1. Requirement of materials :

LDPE sheet 750 micron thick ( 250 x 1.1 ) : 275 sqm

Bitumen 85/25 & 80/100 Gr @ 0.015 kg / sqm ( 250 x 0.015 x1.05 ) : 4 kg

2. Requirement of machinery :

No machinery proposed.

3. Requirement of workforce :

Laying and joining by supplier @ 10 % of sheet cost

Heavy mazdoor to assist supplier,s workforce : 1 No.

RATE ANALYSIS UNIT : 250.00 sqm

A. MATERIALS:

Sl No Unit Amount

in `:

1 LDPE sheet 750 micron thick sqm 275.00 180.00 49500.00

2 Bitumen 85 / 25 and 80 / 100 Gr kg 4.00 52.00 208.00

Total `: 49708.00

Add for small Tools and Plants @ 1% `: 497.08

Add for Contractor's Profit @ 10% `: 4970.80

Add for Contractor's Overheads @ 5% `: 2485.40

Total cost of Materials : `: 57661.28

B. MACHINERY:

Sl No Unit Amount

in `:

1 Nil 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Contd

in `.

Rate

Description

Perticulars

in `.

127

Rate

Quantity

Quantity

Page 130: Data rates-Canal Works

CANAL AND ALLIED WORKS

B. MACHINERY ( Contd ) :

Sl No Unit Amount

in `:

Contd

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Joining & laying @ 10 % of sheet cost sqm 250.00 18.00 4500.00

2 Heavy mazdoor Day 1.00 238.73 238.73

Total `: 4738.73

Add for small Tools and Plants @ 1% `: 47.39

Add for Contractor's Profit @ 10% `: 473.87

Add for hidden cost on Labour @ 15% `: 710.81

Add for Contractor's Overheads @ 5% `: 236.94

Total cost of Labour : `: 6207.74

ABSTRACT:

A. Cost of Materials including royalty charges `: 57661.28

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 6207.74

TOTAL `: 63869.02

Add for enabling works @ 1.00% `: 638.69

Total cost for 250.00 sqm `: 64507.71

Rate per sqm `:`:`:`: 258.03

Rate approved per sqm `:`:`:`: 258.00

Note : 1. If the surface on which the LDPE sheet is to be laid is too rough and undulating provide

average 75 mm thick unscreened sand backing to LDPE sheet.

2. For providing average 75 mm thick sand backing add per sqm `: 63.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.48.3

ITEM: Providing and fixing LDPE sheet for bed and sides of canal including cost of all materials,

labour, laying, joining etc., complete with all leads and lifts.

48.c. Using 1000 micron thick LDPE sheet.

DATA:Consider 250 sqm LDPE sheet 1000 micron thick laying per day.

Consider 10 percent extra sheet for joints & wastage.

Hot bitumen Grade 85 / 25 and 80 / 100 in the ratio of 2 : 1 considered for joining sheets.

Consider 1 heavy mazdoor for assisting in laying work by supplier.

Consider 250 sqm LDPE sheet laying and jointing for rate analysis.

1. Requirement of materials :

LDPE sheet 1000 micron thick ( 250 x 1.1 ) : 275 sqm

Bitumen 85/25 & 80/100 Gr @ 0.015 kg / sqm ( 250 x 0.015 x1.05 ) : 4 kg

in `.

Rate

Quantity

Description

Rate

in `.

Description

128

Quantity

Page 131: Data rates-Canal Works

CANAL AND ALLIED WORKS

2. Requirement of machinery :

No machinery proposed.

3. Requirement of workforce :

Laying and joining by supplier @ 10 % of sheet cost

Heavy mazdoor to assist supplier,s workforce : 1 No.

RATE ANALYSIS UNIT : 250.00 sqm

A. MATERIALS:

Sl No Unit Amount

in `:

1 LDPE sheet 1000 micron thick sqm 275.00 215.00 59125.00

2 Bitumen 85 / 25 and 80 / 100 Gr kg 4.00 52.00 208.00

Total `: 59333.00

Add for small Tools and Plants @ 1% `: 593.33

Add for Contractor's Profit @ 10% `: 5933.30

Add for Contractor's Overheads @ 5% `: 2966.65

Total cost of Materials : `: 68826.28

B. MACHINERY:

Sl No Unit Amount

in `:

1 Nil 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Joining & laying @ 10 % of sheet cost sqm 250.00 21.50 5375.00

2 Heavy mazdoor Day 1.00 238.73 238.73

Total `: 5613.73

Add for small Tools and Plants @ 1% `: 56.14

Add for Contractor's Profit @ 10% `: 561.37

Add for hidden cost on Labour @ 15% `: 842.06

Add for Contractor's Overheads @ 5% `: 280.69

Total cost of Labour : `: 7353.99

ABSTRACT:

A. Cost of Materials including royalty charges `: 68826.28

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 7353.99

TOTAL `: 76180.27

Add for enabling works @ 1.00% `: 761.80

Total cost for 250.00 sqm `: 76942.07

Rate per sqm `:`:`:`: 307.77

Rate approved per sqm `:`:`:`: 308.00

Description

Rate

Description

Perticulars

Rate

Quantity

Quantity

129

in `.

Quantity

in `.

in `.

Rate

Page 132: Data rates-Canal Works

CANAL AND ALLIED WORKS

Note : 1. If the surface on which the LDPE sheet is to be laid is too rough and undulating provide

average 75 mm thick unscreened sand backing to LDPE sheet.

2. For providing average 75 mm thick sand backing add per sqm `: 63.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.49

ITEM: Providing and fixing 20 mm thick 100 mm depth tarfelt expansion joint filler board for

cement concrete lining of canal including cost of all materials, labour etc., complete with all

leads and lifts.

DATA:Consider 100 m length of expansion joint.

1. Requirement of materials :

Tarfelt joint filler board with 2 % wastage ( 100 x 0.10 x 1.02 ) : 10.20 sqm

2. Requirement of machinery :

No machinery proposed.

3. Requirement of workforce :

Carpenter Cl- II : 1 No.

Heavy mazdoor to assist carpenter : 1 No.

RATE ANALYSIS UNIT : 100.00 Rm

A. MATERIALS:

Sl No Unit Amount

in `:

1 Tarfelt joint filler board 20 mm thick sqm 10.20 650.00 6630.00

0.00 0.00 0.00

Total `: 6630.00

Add for small Tools and Plants @ 1% `: 66.30

Add for Contractor's Profit @ 10% `: 663.00

Add for Contractor's Overheads @ 5% `: 331.50

Total cost of Materials : `: 7690.80

B. MACHINERY:

Sl No Unit Amount

in `:

1 Nil 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Carpenter Cl- II Day 1.00 244.23 244.23

2 Heavy mazdoor Day 1.00 238.73 238.73

Total `: 482.96

Contd

Rate

Rate

Perticulars

in `.

Quantity

Quantity

Rate

in `.

Description

130

Description

in `.

Quantity

Page 133: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR ( Contd ) :

Sl No Unit Amount

in `:

Contd

Add for small Tools and Plants @ 1% `: 4.83

Add for Contractor's Profit @ 10% `: 48.30

Add for hidden cost on Labour @ 15% `: 72.44

Add for Contractor's Overheads @ 5% `: 24.15

Total cost of Labour : `: 632.68

ABSTRACT:

A. Cost of Materials including royalty charges `: 7690.80

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 632.68

TOTAL `: 8323.48

Add for enabling works @ 1.00% `: 83.23

Total cost for 100.00 Rm `: 8406.71

Rate per Rm `:`:`:`: 84.07

Rate approved per Rm `:`:`:`: 84.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.50

ITEM: Providing and fixing 20 mm thick 150 mm depth tarfelt expansion joint filler board for

cement concrete lining of canal including cost of all materials, labour etc., complete with all

leads and lifts.

DATA:Consider 100 m length of expansion joint.

1. Requirement of materials :

Tarfelt joint filler board with 2 % wastage ( 100 x 0.15 x 1.02 ) : 15.30 sqm

2. Requirement of machinery :

No machinery proposed.

3. Requirement of workforce :

Carpenter Cl- II : 1 No.

Heavy mazdoor to assist carpenter : 1 No.

RATE ANALYSIS UNIT : 100.00 Rm

A. MATERIALS:

Sl No Unit Amount

in `:

1 Tarfelt joint filler board 20 mm thick sqm 15.30 650.00 9945.00

0.00 0.00 0.00

Total `: 9945.00

Add for small Tools and Plants @ 1% `: 99.45

Add for Contractor's Profit @ 10% `: 994.50

Add for Contractor's Overheads @ 5% `: 497.25

Total cost of Materials : `: 11536.20

in `.

in `.

Quantity

RateDescription

Rate

Quantity

131

Perticulars

Page 134: Data rates-Canal Works

CANAL AND ALLIED WORKS

B. MACHINERY:

Sl No Unit Amount

in `:

1 Nil 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Carpenter Cl- II Day 1.00 244.23 244.23

2 Heavy mazdoor Day 1.00 238.73 238.73

Total `: 482.96

Add for small Tools and Plants @ 1% `: 4.83

Add for Contractor's Profit @ 10% `: 48.30

Add for hidden cost on Labour @ 15% `: 72.44

Add for Contractor's Overheads @ 5% `: 24.15

Total cost of Labour : `: 632.68

ABSTRACT:

A. Cost of Materials including royalty charges `: 11536.20

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 632.68

TOTAL `: 12168.88

Add for enabling works @ 1.00% `: 121.69

Total cost for 100.00 Rm `: 12290.57

Rate per Rm `:`:`:`: 122.91

Rate approved per Rm `:`:`:`: 123.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.51

ITEM: Manucturing 550 x 550 x 55 mm size PCC lining slabs in M-15 (28 days cube compressive

strength not less than 15 N /sqmm ) grade cement concrete using 20 mm down approved,

clean, hard, graded aggregates including cost of all materials, machinery, labour, formwork,

batching, mixing, laying, compacting, finishing, curing etc.,complete with lead upto 50 m and

all lifts. ( Cement content : 270 kg / cum with use of super plasticiser )

DATA:For 1 cum CC :- Coarse aggregates : 0.80 cum Blending ratio : 65 : 35

Fine aggregate : 0.45 cum Cement content : 270 kg Super plasticizer : 0.80 ltr

Wastage : 1 % for cement and 2 % for coarse & fine aggregates.

Quantity of concrete for each slab ( 0.55 x 0.55 x 0.055 ) : 0.0167 cum

Number of slabs per cum of concrete : 60 Nos.

Consider 3 to 4 minutes for moulding one slab & 2 Masons working on moulding work.

Daily output of moulding for 2 Masons say : 250 slabs

Consider moulding of 225 lining slabs and 25 lug slabs daily as moulding of lug slabs saperately

results in high rate of under utilization of machinery and work force.

Description

RateDescription

in `.

Quantity

Quantity

Rate

132

in `.

Page 135: Data rates-Canal Works

CANAL AND ALLIED WORKS

Aportioning of machinery & wok force: For lining slabs : 90 percent

For lug slabs : 10 percent

Quantity of concrete for 225 lining slabs : 3.75 cum

Consider 3.75 cum concrete for 225 lining slabs for rate analysis.

1. Requirement of materials:

Cement for mix with 1 % wastage ( 3.75 x 270 x 1.01 ) : 1023 kg

Cement for incidental works @ 1 kg / slab ( 225 x 1 ) : 225 kg

Coarse aggregate 20-10 mm size range ( 3.75 x 0.8 x 0.65 x 1.02 ) : 2.00 cum

Coarse aggregate 10-4.75 mm size ( 3.75 x 0.8 x 0.35 x 1.02 ) : 1.05 cum

Fine aggregate ( 3.75 x 0.45 x 1.02 ) : 1.70 cum

Super plasticiser ( 3.75 x 0.80 x 1.02 ) : 3.00 ltr

2. Requirement of machinery :

For 225 lining slabs and 25 lug slabs :

Deploy 300 / 200 ltr capacity concrete mixer for 8 hours.

1 tanker load of water is considered adequate for 1 week slab production and curing work.

Consider 1 water tanker 8000 ltr for 1 hour & 1 pump 5 hp for 0.5 hour per week.

Deploy 1 Pump 5 hp for 0.1 hour for water required for concrete.

Deploy 1 Water tanker 8000 ltr capacity for 0.2 hour for water.

3. Formwork & scaffolding :

No formwork / scaffolding required. Use rate of mould considered.

4. Requirement of workforce ( other than machinery crew ) :

For 225 lining slabs and 25 lug slabs :

Maistry : 1 No.

Mason Cl-I : 2 Nos.

Heavy mazdoor for batching materials / laying CC : 3 Nos.

Heavy mazdoor for demoulding / oiling / laying : 2 Nos.

Heavy mazdoor for shifting slabs to curing pond : 1 No.

Heavy mazdoor for stacking after curing : 1 No.

Light mazdoor for cleaning & miscellaneous : 1 No.

5. Use rate of materials :

Consider steel moulds made of 40x40x4 mm angles

Quantity of steel per mould ( 0.55 x 4 x 2.4 x 1.025 ) say : 5.50 kg

Cost of steel angles @ `: 49.14 / kg `: 270.24

Cost of fabrication @ `: 16.00 / kg `: 88.00

Total `: 358.24

Less salvage value @ 15% ( - ) `: -53.74

Total `: 304.51

Number of uses ( considering moulds are released early ) say : 500 uses

Cost per use considering 500 uses ( 304.51 / 500 ) `: 0.61

Add for bolts & nuts / clamps etc. @ 15% `: 0.09

Add for shutter oil 0.1 ltr @ `: 35.00 / ltr `: 3.50

Total cost / use `: 4.20

RATE ANALYSIS UNIT : 225.00 Nos.

A. MATERIALS:

Sl No Unit Amount

in `:

1 Cement for mix kg 1023.00 7.50 7672.50

Cement for incidentals @ 1 kg / slab kg 225.00 7.50 1687.50

Contd

133

Perticulars

in `.

RateQuantity

Page 136: Data rates-Canal Works

CANAL AND ALLIED WORKS

A. MATERIALS ( Contd ) :

Sl No Unit Amount

in `:

Contd

2 Coarse aggregate 20-10 mm cum 2.00 950.00 1900.00

Coarse aggregate 10 mm below cum 1.05 1160.00 1218.00

3 Fine aggregate ( screened ) cum 1.70 730.00 1241.00

4 Super Plasticizer ltr 3.00 105.00 315.00

5 Use rate of moulds for 500 uses No. 225.00 4.20 945.08

Total `: 14979.08

Add for small Tools and Plants @ 1% `: 149.79

Add for Contractor's Profit @ 10% `: 1497.91

Add for Contractor's Overheads @ 5% `: 748.95

Add Royalty charges on CA @ ( Included in material rate ) `: 0.00

Add Royalty charges on FA @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 17375.74

B. MACHINERY:

Sl No Unit Amount

in `:

1 Concrete mixer 300 / 200 ltr ( diesel ) Hour 8.00 46.00 368.00

Fuel / Energy charges Hour 8.00 76.00 608.00

2 5 hp pump ( diesel ) Hour 0.10 7.00 0.70

Fuel / Energy charges Hour 0.10 76.00 7.60

3 Water tanker 8000 ltr Hour 0.20 306.00 61.20

Fuel / Energy charges Hour 0.20 286.00 57.20

Total `: 1102.70

Add for small Tools and Plants @ 1% `: 11.03

Add for Contractor's Profit on DPOL / Energy @ 10% `: 67.28

Add for Contractor's Overheads @ 5% `: 55.14

Total hire charges of Machinery : `: 1236.14

Aportioned hire charges of machinery @ 90 % for lining slabs : `: 1112.53

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Concrete mixer Hour 8.00 126.00 1008.00

2 Crew for Pump Hour 0.10 60.00 6.00

3 Crew for Water tanker Hour 0.20 95.00 19.00

4 Mason Class-I Day 2.00 256.73 513.46

5 Maistry Day 1.00 241.23 241.23

6 Heavy mazdoor

for batching materials / laying CC Day 3.00 238.73 716.19

for demoulding / oiling / laying Day 2.00 238.73 477.46

for shifting slabs to curing pond Day 1.00 238.73 238.73

for stacking after curing Day 1.00 238.73 238.73

7 Light mazdoor

for cleaning & miscellaneous Day 1.00 237.23 237.23

Total `: 3696.03

Contd

Perticulars Rate

Quantity

Quantity

Description

in `.

Description Rate

Quantity

Rate

in `.

134

in `.

Page 137: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR ( Contd ) :

Sl No Unit Amount

in `:

Contd

Add for small Tools and Plants @ 1% `: 36.96

Add for Contractor's Profit @ 10% `: 369.60

Add for hidden cost on Labour @ 15% `: 554.40

Add for Contractor's Overheads @ 5% `: 184.80

Total cost of Labour : `: 4841.80

Aportioned cost of labour @ 90 % for lining slabs : `: 4357.62

ABSTRACT:

A. Cost of Materials inluding royalty charges `: 17375.74

B. Hire charges of Machinery `: 1112.53

C. Cost of Labour `: 4357.62

TOTAL `: 22845.88

Add for enabling works @ 1.00% `: 228.46

Total cost for 225.00 Nos. `: 23074.34

Rate per Each `:`:`:`: 102.55

Rate approved per Each `:`:`:`: 103.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.52

ITEM: Manucturing 550 x 300 x 55 mm size PCC lug slabs in M-15 ( 28 days cube compressive

strength not less than 15 N /sqmm ) grade cement concrete using 20 mm down approved,

clean, hard, graded aggregates including cost of all materials, machinery, labour, formwork,

batching, mixing, laying, compacting, finishing, curing etc.,complete with lead upto 50 m and

all lifts. ( Cement content : 270 kg / cum with use of super plasticiser )

DATA:For 1 cum CC :- Coarse aggregates : 0.80 cum Blending ratio : 65 : 35

Fine aggregate : 0.45 cum Cement content : 270 kg Super plasticizer : 0.80 ltr

Wastage : 1 % for cement and 2 % for coarse & fine aggregates.

Quantity of concrete for each slab ( 0.55 x 0.30 x 0.055 ) : 0.009 cum

Number of slabs per cum of concrete : 111 Nos.

Consider 3 to 4 minutes for moulding one slab & 2 Masons working on moulding work.

Daily output of moulding for 2 Masons say : 250 slabs

Consider moulding of 225 lining slabs and 25 lug slabs daily as moulding of lug slabs saperately

results in high rate of under utilization of machinery and work force.

Aportioning of machinery & wok force: For lining slabs : 90 percent

For lug slabs : 10 percent

Quantity of concrete for 25 lug slabs : 0.225 cum

Consider 0.225 cum concrete for 25 lug slabs for rate analysis.

1. Requirement of materials:

Cement for mix with 1 % wastage ( 0.225 x 270 x 1.01 ) : 61.5 kg

Cement for incidental works @ 0.5 kg / slab ( 25 x 0.5 ) : 12.5 kg

Coarse aggregate 20-10 mm size range ( 0.225 x 0.8 x 0.65 x 1.02 ) : 0.12 cum

Coarse aggregate 10-4.75 mm size ( 0.225 x 0.8 x 0.35 x 1.02 ) : 0.06 cum

Fine aggregate ( 0.225 x 0.45 x 1.02 ) : 0.10 cum

Super plasticiser ( 0.225 x 0.80 x 1.02 ) : 0.2 ltr

Description

135

in `.

Quantity Rate

Page 138: Data rates-Canal Works

CANAL AND ALLIED WORKS

2. Requirement of machinery :

For 225 lining slabs and 25 lug slabs : ( same as in Item : 67 )

Deploy 300 / 200 ltr capacity concrete mixer for 8 hours.

Deploy 1 Pump 5 hp for 0.1 hour for water required for concrete.

Deploy 1 Water tanker 8000 ltr capacity for 0.2 hour for water.

3. Formwork & scaffolding :

No formwork / scaffolding required. Use rate of mould considered.

4. Requirement of workforce ( other than machinery crew ) :

For 225 lining slabs and 25 lug slabs :

Maistry : 1 No.

Mason Cl-I : 2 Nos.

Heavy mazdoor for batching materials / laying CC : 3 Nos.

Heavy mazdoor for demoulding / oiling / laying : 2 Nos.

Heavy mazdoor for shifting slabs to curing pond : 1 No.

Heavy mazdoor for stacking after curing : 1 No.

Light mazdoor for cleaning & miscellaneous : 1 No.

5. Use rate of materials :

Consider steel moulds made of 40 x 40 x 4 mm angles

Quantity of steel per mould (0.55x2+0.30x2) x 2.4x1.025 say : 4.25 kg

Cost of steel angles @ `: 49.14 / kg `: 208.82

Cost of fabrication @ `: 16.00 / kg `: 68.00

Total `: 276.82

Less salvage value @ 15% ( - ) `: -41.52

Total `: 235.30

Number of uses ( considering moulds are released early )

Cost per use considering 500 uses ( 235.30 / 500 ) `: 0.47

Add for bolts & nuts / clamps @ 15% `: 0.07

Add for shutter oil 0.06 ltr @ `: 35.00 / ltr `: 2.10

Total cost / use `: 2.64

RATE ANALYSIS UNIT : 25.00 Nos.

A. MATERIALS:

Sl No Unit Amount

in `:

1 Cement for mix kg 61.50 7.50 461.25

Cement for incidentals @ 0.5 kg / slab kg 12.50 7.50 93.75

2 Coarse aggregate 20-10 mm cum 0.12 950.00 114.00

Coarse aggregate 10 mm below cum 0.06 1160.00 69.60

3 Fine aggregate ( screened ) cum 0.10 730.00 73.00

4 Super Plasticizer ltr 0.20 105.00 21.00

5 Use rate of moulds for 500 uses No. 25.00 2.64 66.03

Total `: 898.63

Add for small Tools and Plants @ 1% `: 8.99

Add for Contractor's Profit @ 10% `: 89.86

Add for Contractor's Overheads @ 5% `: 44.93

Add Royalty charges on CA @ ( Included in material rate ) `: 0.00

Add Royalty charges on FA @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 1042.41

Perticulars Quantity Rate

136

in `.

Page 139: Data rates-Canal Works

CANAL AND ALLIED WORKS

B. MACHINERY:

Sl No Unit Amount

in `:

1 Concrete mixer 300 / 200 ltr ( diesel ) Hour 8.00 46.00 368.00

Fuel / Energy charges Hour 8.00 76.00 608.00

2 5 hp pump ( diesel ) Hour 0.10 7.00 0.70

Fuel / Energy charges Hour 0.10 76.00 7.60

3 Water tanker 8000 ltr Hour 0.20 306.00 61.20

Fuel / Energy charges Hour 0.20 286.00 57.20

Total `: 1102.70

Add for small Tools and Plants @ 1% `: 11.03

Add for Contractor's Profit on DPOL / Energy @ 10% `: 67.28

Add for Contractor's Overheads @ 5% `: 55.14

Total hire charges of Machinery : `: 1236.14

Aportioned hire charges of machinery @ 10 % for lug slabs : `: 123.61

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Concrete mixer Hour 8.00 126.00 1008.00

2 Crew for Pump Hour 0.10 60.00 6.00

3 Crew for Water tanker Hour 0.20 95.00 19.00

4 Mason Class-I Day 2.00 256.73 513.46

5 Maistry Day 1.00 241.23 241.23

6 Heavy mazdoor

for batching materials / laying CC Day 3.00 238.73 716.19

for demoulding / oiling / laying Day 2.00 238.73 477.46

for shifting slabs to curing pond Day 1.00 238.73 238.73

for stacking after curing Day 1.00 238.73 238.73

7 Light mazdoor

for cleaning & miscellaneous Day 1.00 237.23 237.23

Total `: 3696.03

Add for small Tools and Plants @ 1% `: 36.96

Add for Contractor's Profit @ 10% `: 369.60

Add for hidden cost on Labour @ 15% `: 554.40

Add for Contractor's Overheads @ 5% `: 184.80

Total cost of Labour : `: 4841.80

Aportioned cost of labour @ 10 % for lug slabs : `: 484.18

ABSTRACT:

A. Cost of Materials inluding royalty charges `: 1042.41

B. Hire charges of Machinery `: 123.61

C. Cost of Labour `: 484.18

TOTAL `: 1650.20

Add for enabling works @ 1.00% `: 16.50

Total cost for 25.00 Nos. `: 1666.71

Rate per Each `:`:`:`: 66.67

Rate approved per Each `:`:`:`: 67.00

Description Quantity

QuantityDescription

137

Rate

Rate

in `.

in `.

Page 140: Data rates-Canal Works

CANAL AND ALLIED WORKS

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.53

ITEM: Manucturing 450 x 300 x 30 mm size PCC lining slabs in M-15 (28 days cube compressive

strength not less than 15 N /sqmm ) grade cement concrete using 10 mm down approved,

clean, hard, graded aggregates including cost of all materials, machinery, labour, formwork,

batching, mixing, laying, compacting, finishing, curing etc.,complete with lead upto 50 m and

all lifts. ( Cement content : 360 kg / cum with use of super plasticiser )

DATA:For 1 cum CC :- Coarse aggregates : 0.68 cum Fine aggregate : 0.43 cum

Cement content : 360 kg Super plasticizer : 1.00 ltr

Wastage : 1 % for cement and 2 % for coarse & fine aggregates.

Quantity of concrete for each slab ( 0.45 x 0.30 x 0.03 ) : 0.004 cum

Number of slabs per cum of concrete : 247 Nos.

Consider 3 to 4 minutes for moulding one slab & 2 Masons working on moulding work.

Daily output of moulding for 2 Masons say : 250 slabs

Consider moulding of 225 lining slabs and 25 lug slabs daily as moulding of lug slabs saperately

results in high rate of under utilization of machinery and work force.

Aportioning of machinery & wok force: For lining slabs : 90 percent

For lug slabs : 10 percent

Quantity of concrete for 225 lining slabs : 0.90 cum

Consider 0.90 cum concrete for 225 lining slabs for rate analysis.

1. Requirement of materials:

Cement for mix with 1 % wastage ( 0.9 x 360 x 1.01 ) : 327 kg

Cement for incidental works @ 0.5 kg / slab ( 225 x 0.5 ) : 112.5 kg

Coarse aggregate 10-4.75 mm size ( 0.9 x 0.68 x 1.02 ) : 0.62 cum

Fine aggregate ( 0.9 x 0.43 x 1.02 ) : 0.40 cum

Super plasticiser ( 0.9 x 1.00 x 1.02 ) : 0.90 ltr

2. Requirement of machinery :

For 225 lining slabs and 25 lug slabs :

As daily requirement of concrete is very small deploy 45 / 30 hand mixer for 8 hours.

Deploy 1 Pump 5 hp for 0.1 hour for water required for concrete.

Deploy 1 Water tanker 8000 ltr capacity for 0.2 hour for water.

3. Formwork & scaffolding :

No formwork / scaffolding required. Use rate of mould considered.

4. Requirement of workforce ( other than machinery crew ) :

For 225 lining slabs and 25 lug slabs :

Maistry : 1 No.

Mason Cl-I : 2 Nos.

Heavy mazdoor for batching materials / laying CC : 2 Nos.

Heavy mazdoor for demoulding / oiling / laying : 2 Nos.

Heavy mazdoor for shifting slabs to curing pond : 1 No.

Heavy mazdoor for stacking after curing : 1 No.

Light mazdoor for cleaning & miscellaneous : 1 No.

5. Use rate of materials :

Consider steel moulds made of 30 x 30 x 4 mm angles

Quantity of steel per mould ( 0.45 x 2 + 0.3 x 2 ) x 1.8 x 1.025 say : 2.80 kg

Cost of steel angles @ `: 49.14 / kg `: 137.58

Cost of fabrication @ `: 16.00 / kg `: 44.80

Total `: 182.38

138

Page 141: Data rates-Canal Works

CANAL AND ALLIED WORKS

Less salvage value @ 15% ( - ) `: -27.36

Total `: 155.02

Number of uses ( considering moulds are released early )

Cost per use considering 500 uses ( 155.02 / 500 ) `: 0.31

Add for bolts & nuts / clamps @ 15% `: 0.05

Add for shutter oil 0.04 ltr @ `: 35.00 / ltr `: 1.40

Total cost / use `: 1.76

RATE ANALYSIS UNIT : 225.00 Nos.

A. MATERIALS:

Sl No Unit Amount

in `:

1 Cement for mix kg 327.00 7.50 2452.50

Cement for incidentals @ 0.5 kg / slab kg 112.50 7.50 843.75

2 Coarse aggregate 10 mm below cum 0.62 1160.00 719.20

3 Fine aggregate ( screened ) cum 0.40 730.00 292.00

4 Super Plasticizer ltr 0.90 105.00 94.50

5 Use rate of moulds for 250 uses No. 225.00 1.76 395.22

Total `: 4797.17

Add for small Tools and Plants @ 1% `: 47.97

Add for Contractor's Profit @ 10% `: 479.72

Add for Contractor's Overheads @ 5% `: 239.86

Add Royalty charges on CA @ ( Included in material rate ) `: 0.00

Add Royalty charges on FA @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 5564.72

B. MACHINERY:

Sl No Unit Amount

in `:

1 Hand mixer 45 / 30 ltr Hour 8.00 11.00 88.00

Fuel / Energy charges Hour 8.00 6.00 48.00

2 5 hp pump ( diesel ) Hour 0.10 7.00 0.70

Fuel / Energy charges Hour 0.10 76.00 7.60

3 Water tanker 8000 ltr Hour 0.20 306.00 61.20

Fuel / Energy charges Hour 0.20 286.00 57.20

Total `: 262.70

Add for small Tools and Plants @ 1% `: 2.63

Add for Contractor's Profit on DPOL / Energy @ 10% `: 11.28

Add for Contractor's Overheads @ 5% `: 13.14

Total hire charges of Machinery : `: 289.74

Aportioned hire charges of machinery @ 90 % for lining slab : `: 260.77

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Pump Hour 0.10 60.00 6.00

2 Crew for Water tanker Hour 0.20 95.00 19.00

3 Mason Class-I Day 2.00 256.73 513.46

4 Maistry Day 1.00 241.23 241.23

Contd

Description Quantity

Description

Perticulars Rate

in `.

in `.

in `.

RateQuantity

139

Quantity

Rate

Page 142: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR ( Contd ) :

Sl No Unit Amount

in `:

Contd

5 Heavy mazdoor

for batching / mixing / laying Day 2.00 238.73 477.46

for demoulding / cleaning / oiling Day 2.00 238.73 477.46

for shifting slabs to curing pond Day 1.00 238.73 238.73

for stacking after curing Day 1.00 238.73 238.73

6 Light mazdoor

for cleaning & miscellaneous Day 1.00 237.23 237.23

Total `: 2449.30

Add for small Tools and Plants @ 1% `: 24.49

Add for Contractor's Profit @ 10% `: 244.93

Add for hidden cost on Labour @ 15% `: 367.40

Add for Contractor's Overheads @ 5% `: 122.47

Total cost of Labour : `: 3208.58

Aportioned cost of labour @ 90 % for lining slabs : `: 2887.72

ABSTRACT:

A. Cost of Materials inluding royalty charges `: 5564.72

B. Hire charges of Machinery `: 260.77

C. Cost of Labour `: 2887.72

TOTAL `: 8713.21

Add for enabling works @ 1.00% `: 87.13

Total cost for 225.00 Nos. `: 8800.35

Rate per Each `:`:`:`: 39.11

Rate approved per Each `:`:`:`: 39.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.54

ITEM: Manucturing 450 x 150 x 30 mm size PCC lug slabs in M-15 ( 28 days cube compressive

strength not less than 15 N /sqmm ) grade cement concrete using 10 mm down approved,

clean, hard, graded aggregates including cost of all materials, machinery, labour, formwork,

batching, mixing, laying, compacting, finishing, curing etc.,complete with lead upto 50 m and

all lifts. ( Cement content : 360 kg / cum with use of super plasticiser )

DATA:For 1 cum CC :- Coarse aggregates : 0.68 cum Fine aggregate : 0.43 cum

Cement content : 360 kg Super plasticizer : 1.00 ltr

Wastage : 1 % for cement and 2 % for coarse & fine aggregates.

Quantity of concrete for each slab ( 0.45 x 0.15 x 0.03 ) : 0.002 cum

Number of slabs per cum of concrete : 494 Nos.

Consider 3 to 4 minutes for moulding one slab & 2 Masons working on moulding work.

Daily output of moulding for 2 Masons say : 250 slabs

Consider moulding of 225 lining slabs and 25 lug slabs daily as moulding of lug slabs saperately

results in high rate of under utilization of machinery and work force.

Aportioning of machinery & wok force: For lining slabs : 90 percent

For lug slabs : 10 percent

Quantity of concrete for 25 lug slabs : 0.05 cum

Consider 0.05 cum concrete for 25 lug slabs for rate analysis.

Description RateQuantity

in `.

140

Page 143: Data rates-Canal Works

CANAL AND ALLIED WORKS

1. Requirement of materials:

Cement for mix with 1 % wastage ( 0.05 x 360 x 1.01 ) : 18.2 kg

Cement for incidental works @ 0.3 kg / slab ( 25 x 0.3 ) : 7.5 kg

Coarse aggregate 10-4.75 mm size ( 0.05 x 0.68 x 1.02 ) : 0.035 cum

Fine aggregate ( 0.05 x 0.43 x 1.02 ) : 0.02 cum

Super plasticiser ( 0.05 x 1.00 x 1.02 ) : 0.05 ltr

2. Requirement of machinery :

For 225 lining slabs and 25 lug slabs : ( same as in Item :69 )

As daily requirement of concrete is very small deploy 45 / 30 hand mixer for 8 hours.

Deploy 1 Pump 5 hp for 0.1 hour for water required for concrete.

Deploy 1 Water tanker 8000 ltr capacity for 0.2 hour for water.

3. Formwork & scaffolding :

No formwork / scaffolding required. Use rate of mould considered.

4. Requirement of workforce ( other than machinery crew ) :

For 225 lining slabs and 25 lug slabs : ( same as in Item :69 )

Maistry : 1 No.

Mason Cl-I : 2 Nos.

Heavy mazdoor for batching materials / laying CC : 2 Nos.

Heavy mazdoor for demoulding / oiling / laying : 2 Nos.

Heavy mazdoor for shifting slabs to curing pond : 1 No.

Heavy mazdoor for stacking after curing : 1 No.

Light mazdoor for cleaning & miscellaneous : 1 No.

5. Use rate of materials :

Consider steel moulds made of 30 x 30 x 4 mm angles.

Quantity of steel per mould ( 0.45 x 2 + 0.15 x 2 ) x 1.8 x 1.025 say : 2.25 kg

Cost of steel angles @ `: 49.14 / kg `: 110.55

Cost of fabrication @ `: 16.00 / kg `: 36.00

Total `: 146.55

Less salvage value @ 15% ( - ) `: -21.98

Total `: 124.57

Number of uses ( considering moulds are released early )

Cost per use considering 500 uses ( 124.57 / 500 ) `: 0.25

Add for bolts & nuts / clamps @ 15% `: 0.04

Add for shutter oil 0.02 ltr @ `: 35.00 / ltr `: 0.70

Total cost / use `: 0.99

RATE ANALYSIS UNIT : 25.00 Nos.

A. MATERIALS:

Sl No Unit Amount

in `:

1 Cement for mix kg 18.20 7.50 136.50

Cement for incidentals @ 0.3 kg / slab kg 7.50 7.50 56.25

2 Coarse aggregate 10 mm below cum 0.035 1160.00 40.60

3 Fine aggregate ( screened ) cum 0.02 730.00 14.60

4 Super Plasticizer ltr 0.05 105.00 5.25

5 Use rate of moulds for 250 uses No. 25.00 0.99 24.66

Total `: 277.86

Contd

Perticulars Quantity

in `.

Rate

141

Page 144: Data rates-Canal Works

CANAL AND ALLIED WORKS

A. MATERIALS ( Contd ) :

Sl No Unit Amount

in `:

Contd

Add for small Tools and Plants @ 1% `: 2.78

Add for Contractor's Profit @ 10% `: 27.79

Add for Contractor's Overheads @ 5% `: 13.89

Add Royalty charges on CA @ ( Included in material rate ) `: 0.00

Add Royalty charges on FA @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 322.32

B. MACHINERY:

Sl No Unit Amount

in `:

1 Hand mixer 45 / 30 ltr Hour 8.00 11.00 88.00

Fuel / Energy charges Hour 8.00 6.00 48.00

2 5 hp pump ( diesel ) Hour 0.10 7.00 0.70

Fuel / Energy charges Hour 0.10 76.00 7.60

3 Water tanker 8000 ltr Hour 0.20 306.00 61.20

Fuel / Energy charges Hour 0.20 286.00 57.20

Total `: 262.70

Add for small Tools and Plants @ 1% `: 2.63

Add for Contractor's Profit on DPOL / Energy @ 10% `: 11.28

Add for Contractor's Overheads @ 5% `: 13.14

Total hire charges of Machinery : `: 289.74

Aportioned hire charges of machinery @ 10 % for lug slabs : `: 28.97

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Pump Hour 0.10 60.00 6.00

2 Crew for Water tanker Hour 0.20 95.00 19.00

3 Mason Class-I Day 2.00 256.73 513.46

4 Maistry Day 1.00 241.23 241.23

5 Heavy mazdoor

for batching / mixing / laying Day 2.00 238.73 477.46

for demoulding / cleaning / oiling Day 2.00 238.73 477.46

for shifting slabs to curing pond Day 1.00 238.73 238.73

for stacking after curing Day 1.00 238.73 238.73

6 Light mazdoor

for cleaning & miscellaneous Day 1.00 237.23 237.23

Total `: 2449.30

Add for small Tools and Plants @ 1% `: 24.49

Add for Contractor's Profit @ 10% `: 244.93

Add for hidden cost on Labour @ 15% `: 367.40

Add for Contractor's Overheads @ 5% `: 122.47

Total cost of Labour : `: 3208.58

Aportioned cost of labour @ 10 % for lug slabs : `: 320.86

Description

Description Quantity

Rate

in `.

in `.

RateQuantity

Rate

in `.

142

Perticulars Quantity

Page 145: Data rates-Canal Works

CANAL AND ALLIED WORKS

ABSTRACT:

A. Cost of Materials inluding royalty charges `: 322.32

B. Hire charges of Machinery `: 28.97

C. Cost of Labour `: 320.86

TOTAL `: 672.15

Add for enabling works @ 1.00% `: 6.72

Total cost for 25.00 Nos. `: 678.87

Rate per Each `:`:`:`: 27.15

Rate approved per Each `:`:`:`: 27.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.55

ITEM: Manucturing 400 x 400 x 30 mm size PCC lining slabs in M-15 (28 days cube compressive

strength not less than 15 N /sqmm ) grade cement concrete using 10 mm down approved,

clean, hard, graded aggregates including cost of all materials, machinery, labour, formwork,

batching, mixing, laying, compacting, finishing, curing etc.,complete with lead upto 50 m and

all lifts. ( Cement content : 360 kg / cum with use of super plasticiser )

DATA:For 1 cum CC :- Coarse aggregates : 0.68 cum Fine aggregate : 0.43 cum

Cement content : 360 kg Super plasticizer : 1.00 ltr

Wastage : 1 % for cement and 2 % for coarse & fine aggregates.

Quantity of concrete for each slab ( 0.40 x 0.40 x 0.03 ) : 0.0048 cum

Number of slabs per cum of concrete : 208 Nos.

Consider 3 to 4 minutes for moulding one slab & 2 Masons working on moulding work.

Daily output of moulding for 2 Masons say : 250 slabs

Consider moulding of 225 lining slabs and 25 lug slabs daily as moulding of lug slabs saperately

results in high rate of under utilization of machinery and work force.

Aportioning of machinery & wok force: For lining slabs : 90 percent

For lug slabs : 10 percent

Quantity of concrete for 225 lining slabs : 1.08 cum

Consider 1.08 cum concrete for 225 lining slabs for rate analysis.

1. Requirement of materials:

Cement for mix with 1 % wastage ( 1.08 x 360 x 1.01 ) : 393 kg

Cement for incidental works @ 0.5 kg / slab ( 225 x 0.5 ) : 112.5 kg

Coarse aggregate 10-4.75 mm size ( 1.08 x 0.68 x 1.02 ) : 0.75 cum

Fine aggregate ( 1.08 x 0.43 x 1.02 ) : 0.48 cum

Super plasticiser ( 1.08 x 1.00 x 1.02 ) : 1.10 ltr

2. Requirement of machinery :

For 225 lining slabs and 25 lug slabs :

As daily requirement of concrete is very small deploy 45 / 30 hand mixer for 8 hours.

Deploy 1 Pump 5 hp for 0.1 hour for water required for concrete.

Deploy 1 Water tanker 8000 ltr capacity for 0.2 hour for water.

3. Formwork & scaffolding :

No formwork / scaffolding required. Use rate of mould considered.

4. Requirement of workforce ( other than machinery crew ) :

For 225 lining slabs and 25 lug slabs :

Maistry : 1 No.

Mason Cl-I : 2 Nos.

Heavy mazdoor for batching materials / laying CC : 2 Nos.

Heavy mazdoor for demoulding / oiling / laying : 2 Nos.

143

Page 146: Data rates-Canal Works

CANAL AND ALLIED WORKS

Heavy mazdoor for shifting slabs to curing pond : 1 No.

Heavy mazdoor for stacking after curing : 1 No.

Light mazdoor for cleaning & miscellaneous : 1 No.

5. Use rate of materials :

Consider steel moulds made of 30 x 30 x 4 mm angles.

Quantity of steel per mould ( 0.4 x 4 ) x 1.8 x 1.025 say : 3.00 kg

Cost of steel angles @ `: 49.14 / kg `: 147.41

Cost of fabrication @ `: 16.00 / kg `: 48.00

Total `: 195.41

Less salvage value @ 15% ( - ) `: -29.31

Total `: 166.09

Number of uses ( considering moulds are released early )

Cost per use considering 500 uses ( 166.09 / 500 ) `: 0.33

Add for bolts & nuts / clamps @ 15% `: 0.05

Add for shutter oil 0.04 ltr @ `: 35.00 / ltr `: 1.40

Total cost / use `: 1.78

RATE ANALYSIS UNIT : 225.00 Nos.

A. MATERIALS:

Sl No Unit Amount

in `:

1 Cement for mix kg 393.00 7.50 2947.50

Cement for incidentals @ 0.5 kg / slab kg 112.50 7.50 843.75

2 Coarse aggregate 10 mm below cum 0.75 1160.00 870.00

3 Fine aggregate ( screened ) cum 0.48 730.00 350.40

4 Super Plasticizer ltr 1.10 105.00 115.50

5 Use rate of moulds for 250 uses No. 225.00 1.78 400.95

Total `: 5528.10

Add for small Tools and Plants @ 1% `: 55.28

Add for Contractor's Profit @ 10% `: 552.81

Add for Contractor's Overheads @ 5% `: 276.41

Add Royalty charges on CA @ ( Included in material rate ) `: 0.00

Add Royalty charges on FA @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 6412.60

B. MACHINERY:

Sl No Unit Amount

in `:

1 Hand mixer 45 / 30 ltr Hour 8.00 11.00 88.00

Fuel / Energy charges Hour 8.00 6.00 48.00

2 5 hp pump ( diesel ) Hour 0.10 7.00 0.70

Fuel / Energy charges Hour 0.10 76.00 7.60

3 Water tanker 8000 ltr Hour 0.20 306.00 61.20

Fuel / Energy charges Hour 0.20 286.00 57.20

Total `: 262.70

Add for small Tools and Plants @ 1% `: 2.63

Add for Contractor's Profit on DPOL / Energy @ 10% `: 11.28

Add for Contractor's Overheads @ 5% `: 13.14

Total hire charges of Machinery : `: 289.74

Aportioned hire charges of machinery @ 90 % for lining slab : `: 260.77

QuantityDescription

Perticulars Quantity Rate

in `.

144

in `.

Rate

Page 147: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Pump Hour 0.10 60.00 6.00

2 Crew for Water tanker Hour 0.20 95.00 19.00

3 Mason Class-I Day 2.00 256.73 513.46

4 Maistry Day 1.00 241.23 241.23

5 Heavy mazdoor

for batching / mixing / laying Day 2.00 238.73 477.46

for demoulding / cleaning / oiling Day 2.00 238.73 477.46

for shifting slabs to curing pond Day 1.00 238.73 238.73

for stacking after curing Day 1.00 238.73 238.73

6 Light mazdoor

for cleaning & miscellaneous Day 1.00 237.23 237.23

Total `: 2449.30

Add for small Tools and Plants @ 1% `: 24.49

Add for Contractor's Profit @ 10% `: 244.93

Add for hidden cost on Labour @ 15% `: 367.40

Add for Contractor's Overheads @ 5% `: 122.47

Total cost of Labour : `: 3208.58

Aportioned cost of labour @ 90 % for lining slabs : `: 2887.72

ABSTRACT:

A. Cost of Materials inluding royalty charges `: 6412.60

B. Hire charges of Machinery `: 260.77

C. Cost of Labour `: 2887.72

TOTAL `: 9561.09

Add for enabling works @ 1.00% `: 95.61

Total cost for 225.00 Nos. `: 9656.70

Rate per Each `:`:`:`: 42.92

Rate approved per Each `:`:`:`: 43.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.56

ITEM: Manucturing 400 x 150 x 30 mm size PCC lug slabs in M-15 ( 28 days cube compressive

strength not less than 15 N /sqmm ) grade cement concrete using 10 mm down approved,

clean, hard, graded aggregates including cost of all materials, machinery, labour, formwork,

batching, mixing, laying, compacting, finishing, curing etc.,complete with lead upto 50 m and

all lifts. ( Cement content : 360 kg / cum with use of super plasticiser )

DATA:For 1 cum CC :- Coarse aggregates : 0.68 cum Fine aggregate : 0.43 cum

Cement content : 360 kg Super plasticizer : 1.00 ltr

Wastage : 1 % for cement and 2 % for coarse & fine aggregates.

Quantity of concrete for each slab ( 0.40 x 0.15 x 0.03 ) : 0.0018 cum

Number of slabs per cum of concrete : 555 Nos.

Consider 3 to 4 minutes for moulding one slab & 2 Masons working on moulding work.

Daily output of moulding for 2 Masons say : 250 slabs

Consider moulding of 225 lining slabs and 25 lug slabs daily as moulding of lug slabs saperately

results in high rate of under utilization of machinery and work force.

145

Rate

in `.

Description Quantity

Page 148: Data rates-Canal Works

CANAL AND ALLIED WORKS

Aportioning of machinery & wok force: For lining slabs : 90 percent

For lug slabs : 10 percent

Quantity of concrete for 25 lug slabs : 0.045 cum

Consider 0.045 cum concrete for 25 lug slabs for rate analysis.

1. Requirement of materials:

Cement for mix with 1 % wastage ( 0.045 x 360 x 1.01 ) : 16.4 kg

Cement for incidental works @ 0.3 kg / slab ( 25 x 0.3 ) : 7.5 kg

Coarse aggregate 10-4.75 mm size ( 0.045 x 0.68 x 1.02 ) : 0.031 cum

Fine aggregate ( 0.045 x 0.43 x 1.02 ) : 0.02 cum

Super plasticiser ( 0.045 x 1.00 x 1.02 ) : 0.05 ltr

2. Requirement of machinery :

For 225 lining slabs and 25 lug slabs : ( same as in Item :71 )

As daily requirement of concrete is very small deploy 45 / 30 hand mixer for 8 hours.

Deploy 1 Pump 5 hp for 0.1 hour for water required for concrete.

Deploy 1 Water tanker 8000 ltr capacity for 0.2 hour for water.

3. Formwork & scaffolding :

No formwork / scaffolding required. Use rate of mould considered.

4. Requirement of workforce ( other than machinery crew ) :

For 225 lining slabs and 25 lug slabs : ( same as in Item :71 )

Maistry : 1 No.

Mason Cl-I : 2 Nos.

Heavy mazdoor for batching materials / laying CC : 2 Nos.

Heavy mazdoor for demoulding / oiling / laying : 2 Nos.

Heavy mazdoor for shifting slabs to curing pond : 1 No.

Heavy mazdoor for stacking after curing : 1 No.

Light mazdoor for cleaning & miscellaneous : 1 No.

5. Use rate of materials :

Consider steel moulds made of 30 x 30 x 4 mm angles

Quantity of steel per mould ( 0.4 x 2 + 0.15 x 2 ) x 1.8 x 1.025 say : 2.00 kg

Cost of steel angles @ `: 49.14 / kg `: 98.27

Cost of fabrication @ `: 16.00 / kg `: 32.00

Total `: 130.27

Less salvage value @ 15% ( - ) `: -19.54

Total `: 110.73

Number of uses ( considering moulds are released early )

Cost per use considering 500 uses ( 110.73 / 500 ) `: 0.22

Add for bolts & nuts / clamps @ 15% `: 0.03

Add for shutter oil 0.02 ltr @ `: 35.00 / ltr `: 0.70

Total cost / use `: 0.95

RATE ANALYSIS UNIT : 25.00 Nos.

A. MATERIALS:

Sl No Unit Amount

in `:

1 Cement for mix kg 16.40 7.50 123.00

Cement for incidentals @ 0.3 kg / slab kg 7.50 7.50 56.25

2 Coarse aggregate 10 mm below cum 0.031 1160.00 35.96

3 Fine aggregate ( screened ) cum 0.02 730.00 14.60

4 Super Plasticizer ltr 0.05 105.00 5.25

Contd

146

Perticulars Quantity Rate

in `.

Page 149: Data rates-Canal Works

CANAL AND ALLIED WORKS

A. MATERIALS ( Contd ) :

Sl No Unit Amount

in `:

Contd

5 Use rate of moulds for 250 uses No. 25.00 0.95 23.87

Total `: 258.93

Add for small Tools and Plants @ 1% `: 2.59

Add for Contractor's Profit @ 10% `: 25.89

Add for Contractor's Overheads @ 5% `: 12.95

Add Royalty charges on CA @ ( Included in material rate ) `: 0.00

Add Royalty charges on FA @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 300.36

B. MACHINERY:

Sl No Unit Amount

in `:

1 Hand mixer 45 / 30 ltr Hour 8.00 11.00 88.00

Fuel / Energy charges Hour 8.00 6.00 48.00

2 5 hp pump ( diesel ) Hour 0.10 7.00 0.70

Fuel / Energy charges Hour 0.10 76.00 7.60

3 Water tanker 8000 ltr Hour 0.20 306.00 61.20

Fuel / Energy charges Hour 0.20 286.00 57.20

Total `: 262.70

Add for small Tools and Plants @ 1% `: 2.63

Add for Contractor's Profit on DPOL/ Energy @ 10% `: 11.28

Add for Contractor's Overheads @ 5% `: 13.14

Total hire charges of Machinery : `: 289.74

Aportioned hire charges of machinery @ 10 % for lug slabs : `: 28.97

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Pump Hour 0.10 60.00 6.00

2 Crew for Water tanker Hour 0.20 95.00 19.00

3 Mason Class-I Day 2.00 256.73 513.46

4 Maistry Day 1.00 241.23 241.23

5 Heavy mazdoor

for batching / mixing / laying Day 2.00 238.73 477.46

for demoulding / cleaning / oiling Day 2.00 238.73 477.46

for shifting slabs to curing pond Day 1.00 238.73 238.73

for stacking after curing Day 1.00 238.73 238.73

6 Light mazdoor

for cleaning & miscellaneous Day 1.00 237.23 237.23

Total `: 2449.30

Add for small Tools and Plants @ 1% `: 24.49

Add for Contractor's Profit @ 10% `: 244.93

Add for hidden cost on Labour @ 15% `: 367.40

Add for Contractor's Overheads @ 5% `: 122.47

Total cost of Labour : `: 3208.58

`: 320.86

Perticulars Quantity

Rate

Rate

Quantity

Aportioned cost of labour @ 10 % for lug slabs :

Description

Description

in `.

147

in `.

in `.

Quantity

Rate

Page 150: Data rates-Canal Works

CANAL AND ALLIED WORKS

ABSTRACT:

A. Cost of Materials inluding royalty charges `: 300.36

B. Hire charges of Machinery `: 28.97

C. Cost of Labour `: 320.86

TOTAL `: 650.19

Add for enabling works @ 1.00% `: 6.50

Total cost for 25.00 Nos. `: 656.69

Rate per Each `:`:`:`: 26.27

Rate approved per Each `:`:`:`: 26.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.57

ITEM: Providing and constructing uncoursed rubble stone masonry in CM 1: 5 proportion by volume

for canal side lining using stones and stone chips from approved quarry including cost of

all materials, machinery,labour, batching and mixing mortar, packing mortar into joints, wedging

stone chips, forming weep holes at specified intervals, finishing, curing etc., complete with lead

upto 50 m and all lifts.

DATA:Consider 10 cum UCR masonry lining in CM 1:5 proportion for rate analysis.

thickness of UCR masonry lining assumed at 30 cm.

Through stones assumed at 1 per sqm.

Cement mortar content assumed at 40 percent.

Wastage of materials : Cement : 1 % Sand & stones : 2 %

For 1 cum CM 1:5 prop Cement : 285 kg Sand : 1.00 cum

Area of masonry for 10 cum ( 10 / 0.3 ) 33.3 sqm

Quantity of mortar for 10 cum masonry ( 10 x 0.4 ) 4.00 cum

1. Requirement of materials :

Cement for 4 cum mortar ( 4 x 285 x 1.01 ) : 1152 kg

Sand for 4 cum mortar ( 4 x 1.00 x 1.02 ) : 4.10 cum

Uncoursed rubble stones ( 10 x 0.97 x 1.02 ) : 9.90 cum

Through stones @ 1 per sqm ( 33.3 x 1 x 1.02 ) : 34 Nos

Stone chips @ 15 % ( 10 x 0.15 x 1.02 ) : 1.55 cum

2. Requirement of machinery :

Deploy 5 hp diesel pump for 0.5 hour for water required for mortar mixing and curing.

Deploy 8000 ltr water tanker for 1 hour for water required for mortar mixing and curing.

3. Requirement of workforce ( other than machinery crew ) :

Maistry : 1 No.

Laying masonry Mason Cl I : 2 Nos.

Laying masonry Mason Cl II : 2 Nos

Conveying stones Heavy mazdoor : 2 Nos.

Conveying stones chips Light mazdoor : 1 No.

Cement mortar mixing & loading pans Heavy mazdoor : 1 No.

Conveying mortar Light mazdoor : 2 Nos.

Packing mortar Heavy mazdoor : 1 No.

Curing Light mazdoor : 1 No.

148

Page 151: Data rates-Canal Works

CANAL AND ALLIED WORKS

RATE ANALYSIS UNIT : 10.00 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 Cement 43 Gr kg 1152.00 7.50 8640.00

2 Sand ( screened ) cum 4.10 730.00 2993.00

3 Uncoursed rubble stones at quarry cum 9.90 400.00 3960.00

4 Through stones 200 x 200 x 300 mm Nos 34.00 16.00 544.00

5 Stone chips at quarry cum 1.55 500.00 775.00

Total `: 16912.00

Add for small Tools and Plants @ 1% `: 169.12

Add for Contractor's Profit @ 10% `: 1691.20

Add for Contractor's Overheads @ 5% `: 845.60

Add Royalty charges on stones @ ( Included in material rate ) `: 0.00

Add Royalty charges on sand @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 19617.92

B. MACHINERY:

Sl No Unit Amount

in `:

1 5 hp pump ( diesel ) Hour 0.50 7.00 3.50

Fuel / Energy charges Hour 0.50 76.00 38.00

2 Water tanker ( 8000 ltr ) Hour 1.00 306.00 306.00

Fuel / Energy charges Hour 1.00 286.00 286.00

Total `: 633.50

Add for small Tools and Plants @ 1% `: 6.34

Add for Contractor's Profit on DPOL / Energy @ 10% `: 32.40

Add for Contractor's Overheads @ 5% `: 31.68

Total hire charges of Machinery : `: 703.91

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Pump Hour 0.50 60.00 30.00

2 Crew for Water tanker Hour 1.00 95.00 95.00

3 Maistry Day 1.00 241.23 241.23

4 Mason Class I Day 2.00 256.73 513.46

5 Mason Class II Day 2.00 244.23 488.46

6 Heavy mazdoor Day 4.00 238.73 954.92

7 Light mazdoor Day 4.00 237.23 948.92

Total `: 3271.99

Add for small Tools and Plants @ 1% `: 32.72

Add for Contractor's Profit @ 10% `: 327.20

Add for hidden cost on Labour @ 15% `: 490.80

Add for Contractor's Overheads @ 5% `: 163.60

Total cost of Labour : `: 4286.31

149

Perticulars

Description

Description

in `.

in `.

Rate

in `.

Rate

Quantity

Quantity

Rate

Quantity

Page 152: Data rates-Canal Works

CANAL AND ALLIED WORKS

ABSTRACT:

A. Cost of Materials including royalty charges `: 19617.92

B. Hire charges of Machinery `: 703.91

C. Cost of Labour `: 4286.31

TOTAL `: 24608.14

Add for enabling works @ 1.00% `: 246.08

Total cost for 10.00 cum `: 24854.22

Rate per cum `:`:`:`: 2485.42

Rate approved per cum `:`:`:`: 2485.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.58

ITEM: Providing and constructing uncoursed rubble stone masonry in CM 1: 5 proportion by volume

for canal side lining using stones and stone chips from canal excavation including cost of

all materials, machinery,labour, batching and mixing mortar, packing mortar into joints, wedging

stone chips, forming weep holes at specified intervals, finishing, curing etc., complete with lead

upto 50 m and all lifts.

DATA:Consider 10 cum UCR masonry lining in CM 1:5 proportion for rate analysis.

thickness of UCR masonry lining assumed at 30 cm.

Through stones assumed at 1 per sqm.

Cement mortar content assumed at 40 percent.

Wastage of materials : Cement : 1 % Sand & stones : 2 %

For 1 cum CM 1:5 prop Cement : 285 kg Sand : 1.00 cum

Area of masonry for 10 cum ( 10 / 0.3 ) 33.3 sqm

Quantity of mortar for 10 cum masonry ( 10 x 0.4 ) 4.00 cum

1. Requirement of materials :

Cement for 4 cum mortar ( 4 x 285 x 1.01 ) : 1152 kg

Sand for 4 cum mortar ( 4 x 1.00 x 1.02 ) : 4.10 cum

Uncoursed rubble stones ( 10 x 0.97 x 1.02 ) : 9.90 cum

Through stones @ 1 per sqm ( 33.3 x 1 x 1.02 ) : 34 Nos

Stone chips @ 15 % ( 10 x 0.15 x 1.02 ) : 1.55 cum

2. Requirement of machinery :

Deploy 5 hp diesel pump for 0.5 hour for water required for mortar mixing and curing.

Deploy 8000 ltr water tanker for 1 hour for water required for mortar mixing and curing.

3. Requirement of workforce ( other than machinery crew ) :

Maistry : 1 No.

1 Crowman & 1 Heavy mazdoors for sorting out stones in dump yard.

Laying masonry Mason Cl I : 2 Nos.

Laying masonry Mason Cl II : 2 Nos

Conveying stones Heavy mazdoor : 2 Nos.

Conveying stones chips Light mazdoor : 1 No.

Cement mortar mixing & loading pans Heavy mazdoor : 1 No.

Conveying mortar Light mazdoor : 2 Nos.

Packing mortar Heavy mazdoor : 1 No.

Curing Light mazdoor : 1 No.

150

Page 153: Data rates-Canal Works

CANAL AND ALLIED WORKS

RATE ANALYSIS UNIT : 10.00 cum

A. MATERIALS:

Sl No Unit Amount

in `:

1 Cement 43 Gr kg 1152.00 7.50 8640.00

2 Sand ( screened ) cum 4.10 730.00 2993.00

3 Uncoursed rubble at dump yard cum 9.90 320.00 3168.00

4 Through stones 200 x 200 x 300 mm Nos 34.00 16.00 544.00

5 Stone chips at dump yard cum 1.55 385.00 596.75

Total `: 15941.75

Add for small Tools and Plants @ 1% `: 159.42

Add for Contractor's Profit @ 10% `: 1594.18

Add for Contractor's Overheads @ 5% `: 797.09

Add Royalty charges on stones @ ( Included in material rate ) `: 0.00

Add Royalty charges on sand @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 18492.43

B. MACHINERY:

Sl No Unit Amount

in `:

1 5 hp pump ( diesel ) Hour 0.50 7.00 3.50

Fuel / Energy charges Hour 0.50 76.00 38.00

2 Water tanker ( 8000 ltr ) Hour 1.00 306.00 306.00

Fuel / Energy charges Hour 1.00 286.00 286.00

Total `: 633.50

Add for small Tools and Plants @ 1% `: 6.34

Add for Contractor's Profit on DPOL / Energy @ 10% `: 32.40

Add for Contractor's Overheads @ 5% `: 31.68

Total hire charges of Machinery : `: 703.91

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Pump Hour 0.50 60.00 30.00

2 Crew for Water tanker Hour 1.00 95.00 95.00

3 Maistry Day 1.00 241.23 241.23

4 Mason Class I Day 2.00 256.73 513.46

5 Mason Class II Day 2.00 244.23 488.46

6 Crowbarman Day 1.00 239.73 239.73

7 Heavy mazdoor Day 5.00 238.73 1193.65

8 Light mazdoor Day 4.00 237.23 948.92

Total `: 3750.45

Add for small Tools and Plants @ 1% `: 37.50

Add for Contractor's Profit @ 10% `: 375.05

Add for hidden cost on Labour @ 15% `: 562.57

Add for Contractor's Overheads @ 5% `: 187.52

Total cost of Labour : `: 4913.09

ABSTRACT:

A. Cost of Materials including royalty charges `: 18492.43

Description

Description

QuantityPerticulars

Quantity

Rate

in `.

Rate

151

in `.

Quantity

in `.

Rate

Page 154: Data rates-Canal Works

CANAL AND ALLIED WORKS

B. Hire charges of Machinery `: 703.91

C. Cost of Labour `: 4913.09

TOTAL `: 24109.43

Add for enabling works @ 1.00% `: 241.09

Total cost for 10.00 cum `: 24350.52

Rate per cum `:`:`:`: 2435.05

Rate approved per cum `:`:`:`: 2435.00

Note : Stones / stone chips will be issued in dump area at specified issue rate.

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.59

ITEM: Providing and constructing 250 mm thick dry rubble stone pitching with pin headers at 2 per

sqm using stones and stone chips from approved source including cost of all materials, labour,

hand packing / wedging stone chips, finishing etc.,complete with lead upto 50 m and all lifts.

DATA:Consider 100 sqm dry rubble stone pitching for rate analysis.

Wastage of materials : Stones & chips : 2 %

1. Requirement of materials :

Uncoursed rubble stones ( 100 x 0.25 x 0.9 x 1.02 ) : 23.95 cum

Pin headers @ 2 per sqm ( 100 x 2 ) : 200 Nos

Stone chips @ 15 % ( 100 x 0.25 x 0.15 x 1.02 ) : 3.80 cum

2. Requirement of machinery :

No machinery proposed.

3. Requirement of workforce :

Maistry : 1 No.

Mason Cl II for laying pitching @ 50 sqm / day : 2 Nos

Heavy mazdoor for supplying stones and assisting mason : 4 Nos.

Light mazdoor for conveying stone chips : 1 No.

RATE ANALYSIS UNIT : 100.00 sqm

A. MATERIALS:

Sl No Unit Amount

in `:

1 Uncoursed rubble stones at quarry cum 23.95 400.00 9580.00

2 Pin header ( Through stone ) 300 mm Nos 200.00 16.00 3200.00

3 Stone chips at quarry cum 3.80 500.00 1900.00

Total `: 14680.00

Add for small Tools and Plants @ 1% `: 146.80

Add for Contractor's Profit @ 10% `: 1468.00

Add for Contractor's Overheads @ 5% `: 734.00

Add Royalty charges on stones @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 17028.80

B. MACHINERY:

Sl No Unit Amount

in `:

1 Nil 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Contd

Quantity

Description

Perticulars

Rate

in `.

Rate

in `.

Quantity

152

Page 155: Data rates-Canal Works

CANAL AND ALLIED WORKS

B. MACHINERY ( Contd ) :

Sl No Unit Amount

in `:

Contd

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Maistry Day 1.00 241.23 241.23

2 Mason Class II Day 2.00 244.23 488.46

3 Heavy mazdoor Day 4.00 238.73 954.92

4 Light mazdoor Day 1.00 237.23 237.23

Total `: 1921.84

Add for small Tools and Plants @ 1% `: 19.22

Add for Contractor's Profit @ 10% `: 192.18

Add for hidden cost on Labour @ 15% `: 288.28

Add for Contractor's Overheads @ 5% `: 96.09

Total cost of Labour : `: 2517.61

ABSTRACT:

A. Cost of Materials including royalty charges `: 17028.80

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 2517.61

TOTAL `: 19546.41

Add for enabling works @ 1.00% `: 195.46

Total cost for 100.00 sqm `: 19741.87

Rate per sqm `:`:`:`: 197.42

Rate approved per sqm `:`:`:`: 197.00

NOTE:If 150 mm thick murum bed is to be provided below pitching

DATA:Consider 100 sqm area of pitching:

Quantity of murum with 20 % bulkage ( 100 x 0.15 x 1.2 ) : 18 cum

Requirement of labour for spreading and tamping:

Consider 2 heavy and 2 light mazdoors.

RATE ANALYSIS UNIT : 100.00 sqm

A. MATERIALS:

Sl No Unit Amount

in `:

1 Murum cum 18.00 140.00 2520.00

0.00 0.00 0.00

Total `: 2520.00

Add for small Tools and Plants @ 1% `: 25.20

Add for Contractor's Profit @ 10% `: 252.00

Contd

Description

QuantityPerticulars

QuantityDescription

Rate

in `.

153

Rate

in `.

in `.

Rate

Quantity

Page 156: Data rates-Canal Works

CANAL AND ALLIED WORKS

A. MATERIALS ( Contd ) :

Sl No Unit Amount

in `:

Contd

Add for Contractor's Overheads @ 5% `: 126.00

Add Royalty charges on murum @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 2923.20

B. MACHINERY:

Sl No Unit Amount

in `:

1 Nil 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Heavy mazdoor Day 2.00 238.73 477.46

2 Light mazdoor Day 2.00 237.23 474.46

Total `: 951.92

Add for small Tools and Plants @ 1% `: 9.52

Add for Contractor's Profit @ 10% `: 95.19

Add for hidden cost on Labour @ 15% `: 142.79

Add for Contractor's Overheads @ 5% `: 47.60

Total cost of Labour : `: 1247.02

ABSTRACT:

A. Cost of Materials including royalty charges `: 2923.20

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 1247.02

TOTAL `: 4170.22

Add for enabling works @ 1.00% `: 41.70

Total cost for 100.00 sqm `: 4211.92

Add per sqm `:`:`:`: 42.00

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.60

ITEM: Providing and constructing 300 mm thick dry rubble stone pitching with pin headers at 2 per

sqm using stones and stone chips from approved source including cost of all materials, labour,

hand packing / wedging stone chips, finishing etc.,complete with lead upto 50 m and all lifts.

DATA:Consider 100 sqm dry rubble stone pitching for rate analysis.

Wastage of materials : stones & chips : 2 %

1. Requirement of materials :

Uncoursed rubble stones ( 100 x 0.3 x 0.9 x 1.02 ) : 27.50 cum

QuantityDescription

154

Perticulars

Description

Rate

in `.

Rate

in `.

Quantity

in `.

Rate

Quantity

Page 157: Data rates-Canal Works

CANAL AND ALLIED WORKS

Pin headers @ 2 per sqm ( 100 x 2 ) : 200 Nos

Stone chips @ 15 % ( 100 x 0.3 x 0.15 x 1.02 ) : 4.59 cum

2. Requirement of machinery :

No machinery proposed.

3. Requirement of workforce :

Maistry : 1 No.

Mason Cl II for laying pitching @ 50 sqm / day : 2 Nos

Heavy mazdoor for assisting mason : 5 Nos.

Light mazdoor for conveying stone chips : 1 No.

RATE ANALYSIS UNIT : 100.00 sqm

A. MATERIALS:

Sl No Unit Amount

in `:

1 Uncoursed rubble stones at quarry cum 27.50 400.00 11000.00

2 Pin header ( Through stone ) 300 mm Nos 200.00 16.00 3200.00

3 Stone chips at quarry cum 4.59 500.00 2295.00

Total `: 16495.00

Add for small Tools and Plants @ 1% `: 164.95

Add for Contractor's Profit @ 10% `: 1649.50

Add for Contractor's Overheads @ 5% `: 824.75

Add Royalty charges on stones @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 19134.20

B. MACHINERY:

Sl No Unit Amount

in `:

1 Nil 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Maistry Day 1.00 241.23 241.23

2 Mason Class II Day 2.00 244.23 488.46

3 Heavy mazdoor Day 5.00 238.73 1193.65

4 Light mazdoor Day 1.00 237.23 237.23

Total `: 2160.57

Add for small Tools and Plants @ 1% `: 21.61

Add for Contractor's Profit @ 10% `: 216.06

Add for hidden cost on Labour @ 15% `: 324.09

Add for Contractor's Overheads @ 5% `: 108.03

Total cost of Labour : `: 2830.35

Description

Description

Perticulars

in `.

Rate

Rate

in `.

Rate

in `.

Quantity

155

Quantity

Quantity

Page 158: Data rates-Canal Works

CANAL AND ALLIED WORKS

ABSTRACT:

A. Cost of Materials including royalty charges `: 19134.20

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 2830.35

TOTAL `: 21964.55

Add for enabling works @ 1.00% `: 219.65

Total cost for 100.00 sqm `: 22184.19

Rate per sqm `:`:`:`: 221.84

Rate approved per sqm `:`:`:`: 222.00

NOTE:If 150 mm thick murum bed is to be provided below pitching add `:`:`:`: 42.00

( As per rate analysis under item 59- Note )

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.61

ITEM: Providing and constructing 450 mm thick dry rubble stone pitching with pin headers at 2 per

sqm using stones and stone chips from approved source including cost of all materials, labour,

hand packing / wedging stone chips, finishing etc.,complete with lead upto 50 m and all lifts.

DATA:Consider 100 sqm dry rubble stone pitching for rate analysis.

Wastage of materials : Stones & chips : 2 %.

1. Requirement of materials :

Uncoursed rubble stones ( 100 x 0.45 x 0.9 x 1.02 ) : 41.30 cum

Pin headers @ 2 per sqm ( 100 x 2 ) : 200 Nos

Stone chips @ 15 % ( 100 x 0.45 x 0.15 x 1.02 ) : 6.88 cum

2. Requirement of machinery :

No machinery proposed.

3. Requirement of workforce :

Maistry : 1 No.

Mason Cl II for laying pitching @ 30 sqm / day : 3.5 Nos

Heavy mazdoor for assisting mason : 7 Nos.

Light mazdoor for conveying stone chips : 2 Nos.

RATE ANALYSIS UNIT : 100.00 sqm

A. MATERIALS:

Sl No Unit Amount

in `:

1 Uncoursed rubble stones at quarry cum 41.30 400.00 16520.00

2 Pin header ( Through stone ) 450 mm Nos 200.00 16.00 3200.00

3 Stone chips at quarry cum 6.88 500.00 3440.00

Total `: 23160.00

Add for small Tools and Plants @ 1% `: 231.60

Add for Contractor's Profit @ 10% `: 2316.00

Add for Contractor's Overheads @ 5% `: 1158.00

Add Royalty charges on stones @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 26865.60

Perticulars

in `.

Rate

156

Quantity

Page 159: Data rates-Canal Works

CANAL AND ALLIED WORKS

B. MACHINERY:

Sl No Unit Amount

in `:

1 Nil 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Maistry Day 1.00 241.23 241.23

2 Mason Class II Day 3.50 244.23 854.81

3 Heavy mazdoor Day 7.00 238.73 1671.11

4 Light mazdoor Day 2.00 237.23 474.46

Total `: 3241.61

Add for small Tools and Plants @ 1% `: 32.42

Add for Contractor's Profit @ 10% `: 324.16

Add for hidden cost on Labour @ 15% `: 486.24

Add for Contractor's Overheads @ 5% `: 162.08

Total cost of Labour : `: 4246.50

ABSTRACT:

A. Cost of Materials including royalty charges `: 26865.60

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 4246.50

TOTAL `: 31112.10

Add for enabling works @ 1.00% `: 311.12

Total cost for 100.00 sqm `: 31423.22

Rate per sqm `:`:`:`: 314.23

Rate approved per sqm `:`:`:`: 314.00

NOTE:If 150 mm thick murum bed is to be provided below pitching add `:`:`:`: 42.00

( As per rate analysis under item 59 - Note )

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.62

ITEM: Providing and constructing 300 mm thick rubble stone pitching set in CM 1: 5 proportion

by volume with pin headers at 2 per sqm in including cost of all materials from approved source,

labour, packing stone chips and mortar into joints, finishing, curing etc., complete with lead

upto 50 m and all lifts.

DATA:Consider 100 sqm rubble stone pitching in CM 1:5 proportion.

For 1 cum CM 1:5 prop Cement : 285 kg Sand : 1.00 cum

Cement mortar content assumed at 35 percent.

Quantity of mortar for 100 sqm pitching ( 100 x 0.3 x 0.35 ) 10.5 cum

Wastage of materials : Cement : 1 % Sand & stones : 2 %

Description

Description

in `.

Rate

Rate

in `.

Quantity

157

Quantity

Page 160: Data rates-Canal Works

CANAL AND ALLIED WORKS

1. Requirement of materials :

Uncoursed rubble stones ( 100 x 0.3 x 0.9 x 1.02 ) : 27.50 cum

Pin headers @ 2 per sqm ( 100 x 2 ) : 200 Nos

Stone chips @ 15 % ( 100 x 0.3 x 0.15 x 1.02 ) : 4.59 cum

Cement for 10.5 cum mortar ( 10.5 x 285 x 1.01 ) : 3023 kg

Sand for 10.5 cum mortar ( 10.5 x 1.00 x 1.02 ) : 10.70 cum

2. Requirement of machinery :

Deploy 5 hp diesel pump for 0.5 hour for water required for mortar mixing and curing.

Deploy 8000 ltr water tanker for 1 hour for water required for mortar mixing and curing.

3. Requirement of workforce ( other than machinery crew ) :

Maistry : 1 No.

Mason Cl II for laying pitching @ 25 sqm / day : 4 Nos

Heavy mazdoor for assisting mason : 4 Nos.

Heavy mazdoor for preparing cement mortar : 2 Nos

Heavy mazdoor for packing mortar : 2 Nos.

Light mazdoor for conveying stone chips : 1 No.

Light mazdoor for conveying mortar : 4 Nos

Light mazdoor for curing and miscellaneous works : 1 No.

RATE ANALYSIS UNIT : 100.00 sqm

A. MATERIALS:

Sl No Unit Amount

in `:

1 Uncoursed rubble stones at quarry cum 27.50 400.00 11000.00

2 Pin header ( Through stone ) 300 mm Nos 200.00 16.00 3200.00

3 Stone chips @ 15 % at quarry cum 4.60 500.00 2300.00

4 Cement kg 3023.00 7.50 22672.50

5 Sand ( screened ) cum 10.70 730.00 7811.00

Total `: 46983.50

Add for small Tools and Plants @ 1% `: 469.84

Add for Contractor's Profit @ 10% `: 4698.35

Add for Contractor's Overheads @ 5% `: 2349.18

Add Royalty charges on stones @ ( Included in material rate ) `: 0.00

Add Royalty charges on Sand @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 54500.86

B. MACHINERY:

Sl No Unit Amount

in `:

1 5 hp pump ( diesel ) Hour 0.50 7.00 3.50

Fuel / Energy charges Hour 0.50 76.00 38.00

2 Water tanker ( 8000 ltr ) Hour 1.00 306.00 306.00

Fuel / Energy charges Hour 1.00 286.00 286.00

Total `: 633.50

Add for small Tools and Plants @ 1% `: 6.34

Add for Contractor's Profit on DPOL / Energy @ 10% `: 32.40

Add for Contractor's Overheads @ 5% `: 31.68

Total hire charges of Machinery : `: 703.91

Description Quantity

158

Quantity

in `.

in `.

Rate

Rate

Perticulars

Page 161: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Pump Hour 2.00 60.00 120.00

2 Crew for Water tanker Hour 1.00 95.00 95.00

3 Maistry Day 1.00 241.23 241.23

4 Mason Class II Day 4.00 244.23 976.92

5 Heavy mazdoor Day 8.00 238.73 1909.84

6 Light mazdoor Day 6.00 237.23 1423.38

Total `: 4766.37

Add for small Tools and Plants @ 1% `: 47.66

Add for Contractor's Profit @ 10% `: 476.64

Add for hidden cost on Labour @ 15% `: 714.96

Add for Contractor's Overheads @ 5% `: 238.32

Total cost of Labour : `: 6243.94

ABSTRACT:

A. Cost of Materials including royalty charges `: 54500.86

B. Hire charges of Machinery `: 703.91

C. Cost of Labour `: 6243.94

TOTAL `: 61448.71

Add for enabling works @ 1.00% `: 614.49

Total cost for 100.00 sqm `: 62063.20

Rate per sqm `:`:`:`: 620.63

Rate approved per sqm `:`:`:`: 621.00

NOTE:If 150 mm thick murum bed is to be provided below pitching add `:`:`:`: 42.00

( As per rate analysis under item 59 - Note )

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.63

ITEM: Providing and constructing 300 mm thick dry size stone pitching using 200 to 250 mm size

stones with pin headers at 2 per sqm using stones and stone chips from approved source

including cost of all materials, labour, hand packing / wedging stone chips into joints finishing

etc., complete with lead upto 50 m and all lifts.

DATA:Consider 100 sqm dry size stone pitching for rate analysis.

Average 14.2 size stones considered per sqm pitching area.

1. Requirement of materials :

Size stones 200-250 mm height ( 100 x 14.2 x 0.9 x 1.02 ) : 1304 Nos.

Pin headers @ 2 per sqm ( 100 x 2 ) : 200 Nos

Stone chips @ 15 % ( 100 x 0.15 x 1.02 ) : 4.60 cum

2. Requirement of machinery :

No machinery proposed.

3. Requirement of labour :

Mason Cl II for laying pitching @ 50 sqm / day : 2 Nos

Heavy mazdoor for assisting mason : 4 Nos.

Light mazdoor for conveying stone chips : 1 No.

Light mazdoor for conveying stone chips : 1 No.

159

in `.

QuantityDescription Rate

Page 162: Data rates-Canal Works

CANAL AND ALLIED WORKS

RATE ANALYSIS UNIT : 100.00 sqm

A. MATERIALS:

Sl No Unit Amount

in `:

1 Size stones 200-250 mm height Nos 1304.00 11.00 14344.00

2 Pin header ( Through stone ) 300 mm Nos 200.00 16.00 3200.00

3 Stone chips cum 4.60 500.00 2300.00

Total `: 19844.00

Add for small Tools and Plants @ 1% `: 198.44

Add for Contractor's Profit @ 10% `: 1984.40

Add for Contractor's Overheads @ 5% `: 992.20

Add Royalty charges on stones @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 23019.04

B. MACHINERY:

Sl No Unit Amount

in `:

1 Nil 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Maistry Day 1.00 241.23 241.23

2 Mason Class II Day 2.00 244.23 488.46

3 Heavy mazdoor Day 4.00 238.73 954.92

4 Light mazdoor Day 2.00 237.23 474.46

Total `: 2159.07

Add for small Tools and Plants @ 1% `: 21.59

Add for Contractor's Profit @ 10% `: 215.91

Add for hidden cost on Labour @ 15% `: 323.86

Add for Contractor's Overheads @ 5% `: 107.95

Total cost of Labour : `: 2828.38

ABSTRACT:

A. Cost of Materials including royalty charges `: 23019.04

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 2828.38

TOTAL `: 25847.42

Add for enabling works @ 1.00% `: 258.47

Total cost for 100.00 sqm `: 26105.90

Rate per sqm `:`:`:`: 261.06

Rate approved per sqm `:`:`:`: 261.00

Description

Description

Perticulars Rate

in `.

in `.

in `.

Rate

RateQuantity

160

Quantity

Quantity

Page 163: Data rates-Canal Works

CANAL AND ALLIED WORKS

NOTE:If 150 mm thick murum bed is to be provided below pitching add `: 42.00

( As per rate analysis under item 59 - Note )

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.64

ITEM: Providing and constructing 450 mm thick dry size stone pitching using 200 to 250 mm size

stones with pin headers at 2 per sqm using stones and stone chips from approved source

including cost of all materials, labour, hand packing / wedging stone chips into joints finishing

etc., complete with lead upto 50 m and all lifts.

DATA:Consider 100 sqm dry size stone pitching for rate analysis.

Average 11.5 size stones considered per sqm pitching area.

1. Requirement of materials :

Size stones 250-300 mm height ( 100 x 11.5 x 0.9 x 1.02 ) : 1056 Nos.

Pin headers @ 2 per sqm ( 100 x 2 ) : 200 Nos

Stone chips @ 15 % ( 100 x 0.45 x 0.15 x 1.02 ) : 6.90 cum

2. Requirement of machinery :

No machinery proposed.

3. Requirement of labour :

Maistry 1 No.

Mason Cl II for laying pitching @ 30 sqm / day : 3.5 Nos

Heavy mazdoor for assisting masons : 7 Nos.

Light mazdoor for conveying stone chips : 2 Nos.

RATE ANALYSIS UNIT : 100.00 sqm

A. MATERIALS:

Sl No Unit Amount

in `:

1 Size stones 250-300 mm height Nos 1056.00 15.00 15840.00

2 Pin headers 450 mm Nos 200.00 22.00 4400.00

3 Stone chips cum 6.90 500.00 3450.00

Total `: 23690.00

Add for small Tools and Plants @ 1% `: 236.90

Add for Contractor's Profit @ 10% `: 2369.00

Add for Contractor's Overheads @ 5% `: 1184.50

Add Royalty charges on stones @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 27480.40

B. MACHINERY:

Sl No Unit Amount

in `:

1 Nil 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

Description

in `:

161

Perticulars Rate

Rate

in `:

Quantity

Quantity

Page 164: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR:

Sl No Unit Amount

in `:

1 Maistry Day 1.00 241.23 241.23

2 Mason Class II Day 3.50 244.23 854.81

3 Heavy mazdoor Day 7.00 238.73 1671.11

4 Light mazdoor Day 2.00 237.23 474.46

Total `: 3241.61

Add for small Tools and Plants @ 1% `: 32.42

Add for Contractor's Profit @ 10% `: 324.16

Add for hidden cost on Labour @ 15% `: 486.24

Add for Contractor's Overheads @ 5% `: 162.08

Total cost of Labour : `: 4246.50

ABSTRACT:

A. Cost of Materials including royalty charges `: 27480.40

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 4246.50

TOTAL `: 31726.90

Add for enabling works @ 1.00% `: 317.27

Total cost for 100.00 sqm `: 32044.17

Rate per sqm `:`:`:`: 320.44

Rate approved per sqm `:`:`:`: 320.00

NOTE:If 150 mm thick murum bed is to be provided below pitching add `:`:`:`: 42.00

( As per rate analysis under item 59 - Note )

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.65

ITEM: Providing and constructing 300 mm thick size stone pitching using 200 to 250 mm size

stones with pin headers at 2 per sqm set in CM 1 : 5 proportion by volume with pointing joints

in CM 1:3 proportion by volume including cost of all materials from approved source, labour,

packing stone chips and mortar into joints, finishing, curing etc.complete with lead upto 50 m

and all lifts.

DATA:Consider 100 sqm size stone pitching in CM 1:5 proportion for rate analysis.

Average 13.5 size stones considered per sqm pitching area allowing 20 mm mortar joints.

1. Requirement of materials :

Size stones 200-250 mm height ( 100 x 13.5 x 0.9 x 1.02 ) : 1240 Nos.

Pin headers( Through stones ) @ 2 per sqm ( 100 x 2 ) : 200 Nos

Stone chips @ 15 % with 2 % wastage ( 100 x 0.3 x 0.15 x 1.02 ) : 4.60 cum

Cement mortar 1 : 5 propn @ 30 % for packing ( 100 x 0.3 x 0.3 ) : 9.00 cum

For 1 cum CM 1:5 prop Cement : 285 kg Sand : 1.00 cum

Cement with 1 % wastage ( 9 x 285 x 1.01 ) : 2591 kg

Sand with 2 % wastage ( 9 x 1 x 1.02 ) : 9.20 cum

Cement mortar 1 : 3 propotion for pointing : 0.70 cum

For 1 cum CM 1 : 3 mortar Cement : 460 kg Sand : 0.96 cum

Cement with 1 % wastage ( 0.7 x 460 x 1.01 ) : 325 kg

Sand with 2 % wastage ( 0.7 x 0.96 x 1.02 ) : 0.70 cum

Description Rate

162

in `:

Quantity

Page 165: Data rates-Canal Works

CANAL AND ALLIED WORKS

2. Requirement of machinery :

Deploy 5 hp diesel pump for 0.5 hour for water required for mortar mixing and curing.

Deploy 8000 ltr water tanker for 1 hour for water required for mortar mixing and curing.

3. Requirement of labour :

Maistry 1 No.

Laying pitching Mason Cl II @ 25 sqm / day : 4 Nos

Cement mortar pointing Mason Cl-II 1 No.

Assisting mason Heavy mazdoor : 5 Nos.

Preparing CM 1 : 5 & 1:3 Heavy mazdoor : 2 Nos

Conveying stones chips Light mazdoor : 1 No.

Conveying CM Light mazdoor : 4 Nos

Curing Light mazdoor : 1 No.

RATE ANALYSIS UNIT : 100.00 sqm

A. MATERIALS:

Sl No Unit Amount

in `:

1 Size stones 200-250 mm height Nos 1240.00 11.00 13640.00

2 Pin headers 300 mm long Nos 200.00 16.00 3200.00

3 Stone chips @ 15 % at quarry cum 4.60 500.00 2300.00

4 Cement with 1 % wastage kg 2916.00 7.50 21870.00

5 Sand with 2 % wastage ( screened ) cum 9.90 730.00 7227.00

Total `: 48237.00

Add for small Tools and Plants @ 1% `: 482.37

Add for Contractor's Profit @ 10% `: 4823.70

Add for Contractor's Overheads @ 5% `: 2411.85

Add Royalty charges for Stones @ ( Included in material rate ) `: 0.00

Add Royalty charges for Sand @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 55954.92

B. MACHINERY:

Sl No Unit Amount

in `:

1 5 hp diesel pump Hour 0.50 7.00 3.50

Fuel / Energy charges Hour 0.50 76.00 38.00

2 Water tanker ( 8000 ltr ) Hour 1.00 306.00 306.00

Fuel / Energy charges Hour 1.00 286.00 286.00

Total `: 633.50

Add for small Tools and Plants @ 1% `: 6.34

Add for Contractor's Profit on DPOL / Energy @ 10% `: 32.40

Add for Contractor's Overheads @ 5% `: 31.68

Total hire charges of Machinery : `: 703.91

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Pump Hour 0.50 60.00 30.00

2 Crew for Water tanker Hour 1.00 95.00 95.00

3 Maistry Day 1.00 241.23 241.23

Contd

Description

Description

Perticulars

Quantity

Quantity

in `:

Rate

in `:

Rate

in `:

163

Rate

Quantity

Page 166: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR ( Contd ) :

Sl No Unit Amount

in `:

Contd

4 Mason Class II Day 5.00 244.23 1221.15

5 Heavy mazdoor Day 7.00 238.73 1671.11

6 Light mazdoor Day 6.00 237.23 1423.38

Total `: 4681.87

Add for small Tools and Plants @ 1% `: 46.82

Add for Contractor's Profit @ 10% `: 468.19

Add for hidden cost on Labour @ 15% `: 702.28

Add for Contractor's Overheads @ 5% `: 234.09

Total cost of Labour : `: 6133.25

ABSTRACT:

A. Cost of Materials including royalty charges `: 55954.92

B. Hire charges of Machinery `: 703.91

C. Cost of Labour `: 6133.25

TOTAL `: 62792.08

Add for enabling works @ 1.00% `: 627.92

Total cost for 100.00 sqm `: 63420.00

Rate per sqm `:`:`:`: 634.20

Rate approved per sqm `:`:`:`: 634.00

NOTE:If 150 mm thick murum bed is to be provided below pitching add `:`:`:`: 42.00

( As per rate analysis under item 59 - Note )

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.66

ITEM: Providing and constructing 450 mm thick size stone pitching using 200 to 250 mm size

stones with pin headers at 2 per sqm set in CM 1 : 5 proportion by volume with pointing joints

in CM 1:3 proportion by volume including cost of all materials from approved source, labour,

packing stone chips and mortar into joints, finishing, curing etc.complete with lead upto 50 m

and all lifts.

DATA:Consider 100 sqm size stone pitching in CM 1:5 proportion for rate analysis.

Average 11 size stones considered per sqm pitching area allowing 20 mortar joints.

1. Requirement of materials :

Size stones 250-300 mm height ( 100 x 11 x 0.9 x 1.02 ) : 1010 Nos.

Pin headers ( Through stone ) @ 2 per sqm ( 100 x 2 ) : 200 Nos

Stone chips @ 15 % ( 100 x 0.45 x 0.15 x 1.02 ) : 6.90 cum

Cement mortar 1 : 5 propotion @ 30 % : 13.50 cum

For 1 cum CM 1:5 prop Cement : 285 kg Sand : 1.00 cum

Cement with 1 % wastage ( 13.5 x 285 x 1.01 ) : 3886 kg

Sand with 2 % wastage ( 13.5 x 1 x 10.2 ) : 13.80 cum

Cement mortar 1 : 3 propotion for pointing : 0.40 cum

For 1 cum CM 1 : 3 mortar Cement : 460 kg Sand : 0.96 cum

Cement with 1 % wastage ( 0.4 x 460 x 1.01 ) : 186 kg

Sand with 2 % wastage ( 0.4 x 0.96 x 1.02 ) : 0.40 cum

Description Rate

164

in `:

Quantity

Page 167: Data rates-Canal Works

CANAL AND ALLIED WORKS

2. Requirement of machinery :

Deploy 5 hp diesel pump for 0.5 hour for water required for mortar mixing and curing.

Deploy 8000 ltr water tanker for 1 hour for water required for mortar mixing and curing.

3. Requirement of workforce :

Maistry 1 No.

Laying pitching Mason Cl II @ 15 sqm / day : 6 Nos

Cement mortar pointing Mason Cl-II 1 No.

Assisting mason Heavy mazdoor : 7 Nos.

Preparing CM 1 : 5 & CM 1:3 Heavy mazdoor : 3 Nos

Conveying stones chips Light mazdoor : 2 Nos

Conveying CM Light mazdoor : 4 Nos

Curing Light mazdoor : 1 No.

RATE ANALYSIS UNIT : 100.00 sqm

A. MATERIALS:

Sl No Unit Amount

in `:

1 Size stones 250-300 mm height Nos 1010.00 15.00 15150.00

2 Pin headers 450 mm Nos 200.00 22.00 4400.00

3 Stone chips @ 15 % at quarry cum 6.90 500.00 3450.00

4 Cement with 1 % wastage kg 4072.00 7.50 30540.00

5 Sand with 2 % wastage ( screened ) cum 14.20 730.00 10366.00

Total `: 63906.00

Add for small Tools and Plants @ 1% `: 639.06

Add for Contractor's Profit @ 10% `: 6390.60

Add for Contractor's Overheads @ 5% `: 3195.30

Add Royalty charges for Stones @ ( Included in material rate ) `: 0.00

Add Royalty charges for Sand @ ( Included in material rate ) `: 0.00

Total cost of Materials : `: 74130.96

B. MACHINERY:

Sl No Unit Amount

in `:

1 5 hp diesel pump Hour 0.50 7.00 3.50

Fuel / Energy charges Hour 0.50 76.00 38.00

2 Water tanker ( 8000 ltr ) Hour 1.00 306.00 306.00

Fuel / Energy charges Hour 1.00 286.00 286.00

Total `: 633.50

Add for small Tools and Plants @ 1% `: 6.34

Add for Contractor's Profit on DPOL / Energy @ 10% `: 32.40

Add for Contractor's Overheads @ 5% `: 31.68

Total hire charges of Machinery : `: 703.91

C. LABOUR:

Sl No Unit Amount

in `:

1 Crew for Pump Hour 0.50 60.00 30.00

2 Crew for Water tanker Hour 1.00 95.00 95.00

3 Maistry Day 1.00 241.23 241.23

Contd

Description

Perticulars

in `:

Rate

in `:

165

Quantity

Rate

in `:

RateQuantity

Quantity

Description

Page 168: Data rates-Canal Works

CANAL AND ALLIED WORKS

C. LABOUR ( Contd ) :

Sl No Unit Amount

in `:

Contd

4 Mason Class II Day 7.00 244.23 1709.61

5 Heavy mazdoor Day 10.00 238.73 2387.30

6 Light mazdoor Day 7.00 237.23 1660.61

Total `: 6123.75

Add for small Tools and Plants @ 1% `: 61.24

Add for Contractor's Profit @ 10% `: 612.38

Add for hidden cost on Labour @ 15% `: 918.56

Add for Contractor's Overheads @ 5% `: 306.19

Total cost of Labour : `: 8022.11

ABSTRACT:

A. Cost of Materials including royalty charges `: 74130.96

B. Hire charges of Machinery `: 703.91

C. Cost of Labour `: 8022.11

TOTAL `: 82856.98

Add for enabling works @ 1.00% `: 828.57

Total cost for 100.00 sqm `: 83685.55

Rate per sqm `:`:`:`: 836.86

Rate approved per sqm `:`:`:`: 837.00

NOTE:If 150 mm thick murum bed is to be provided below pitching add `:`:`:`: 42.00

( As per rate analysis under item 59 - Note )

SECTION: CANAL AND ALLIED WORKS. YEAR : 2014-15 ITEM No: WRD: 3.67

ITEM: Providing and laying 100 mm thick approved type grass turfing to side slopes of canal icluding

cost of all materials, labour, spraying watering for minimum 15 days etc.,complete with lead

50 m and all lifts.

DATA:Consider 100 sqm grass turfing area for rate analysis.

1. Requirement of materials :

Turfing sods : 100 sqm

Sand with 2 % wastage : 2 cum

2. Requirement of machinery :

No machinery proposed.

3. Requirement of workforce :

Preparation of surface and spreading sand:

Heavy mazdoors : 1 No.

Removing and loading sods:

Cartman with double bullock cart : 2 Nos.

Heavy mazdoors : 4 Nos.

Light mazdoors : : 4 Nos.

Unloading and laying sods:

Heavy mazdoors : 2 Nos.

in `:

Rate

166

Description Quantity

Page 169: Data rates-Canal Works

CANAL AND ALLIED WORKS

Light mazdoors : 2 Nos.

Watering for 15 days:

Light mazdoors : 1 No.

RATE ANALYSIS UNIT : 100.00 sqm

A. MATERIALS:

Sl No Unit Amount

in `:

1 Turfing sods sqm 100.00 25.00 2500.00

2 Sand ( unscreened ) cum 2.00 615.00 1230.00

Total `: 3730.00

Add for small Tools and Plants @ 1% `: 37.30

Add for Contractor's Profit @ 10% `: 373.00

Add for Contractor's Overheads @ 5% `: 186.50

Total cost of Materials : `: 4326.80

B. MACHINERY:

Sl No Unit Amount

in `:

1 Nil 0.00 0.00 0.00

0.00 0.00 0.00

Total `: 0.00

Add for small Tools and Plants @ 1% `: 0.00

Add for Contractor's Profit on DPOL / Energy @ 10% `: 0.00

Add for Contractor's Overheads @ 5% `: 0.00

Total hire charges of Machinery : `: 0.00

C. LABOUR:

Sl No Unit Amount

in `:

1 Maistry Day 0.10 241.23 24.12

2 Cartman with double bullock cart Day 2.00 278.23 556.46

3 Heavy mazdoor Day 7.00 238.73 1671.11

4 Light mazdoor Day 7.00 237.23 1660.61

Total `: 3912.30

Add for small Tools and Plants @ 1% `: 39.12

Add for Contractor's Profit @ 10% `: 391.23

Add for hidden cost on Labour @ 15% `: 586.85

Add for Contractor's Overheads @ 5% `: 195.62

Total cost of Labour : `: 5125.12

ABSTRACT:

A. Cost of Materials including royalty charges `: 4326.80

B. Hire charges of Machinery `: 0.00

C. Cost of Labour `: 5125.12

TOTAL `: 9451.92

Add for enabling works @ 1.00% `: 94.52

Total cost for 100.00 sqm `: 9546.44

Rate per sqm `:`:`:`: 95.46

Rate approved per sqm `:`:`:`: 95.00

Description

in `:

Quantity

RatePerticulars

Rate

in `:

Quantity

Description

167

in `:

Quantity Rate

Page 170: Data rates-Canal Works

CANAL AND ALLIED WORKS

Page 171: Data rates-Canal Works

CANAL AND ALLIED WORKS

FOR

ENABLING WORKS

DATA FOR PERCENTAGE PROVISIONS

ANNEXURES

168

Page 172: Data rates-Canal Works

CANAL AND ALLIED WORKS

SECTION: CANAL AND ALLIED WORKS. YEAR: 2014-15 Annexure-1

ITEM: Data for other enabling works as percentage of basic rate.

DATA:Stores / work shop / guarage / fuel depot / portable magazine / storage water tanks / water &

air supply lines / haul roads / transportation, erection and dismantling of plant and machinery /

sheds for machinery / ramp ways etc., are enabling works for canal and allied works.

In the data rate analysis provisions to be made for enabling works for canal lining work using

batching plant and mechanical paver including shifting from reach to reach are worked out

saperately and included in the data rate for respestive items.

This data rate is for other enabling works common to all items.

Assuming use of batching plant and mechanical paver for canal lining 10 to 20 km reach of

canal is considered necessary for arranging these plants. `:

1 Cement store 1 week qty 200 sqm @ `: 6600.00 / sqm `: 1320000.00

2 General store 100 sqm @ `: 7700.00 / sqm `: 770000.00

3 Work shop 25 sqm @ `: 7700.00 / sqm `: 192500.00

4 Guarage 100 sqm @ `: 5500.00 / sqm `: 550000.00

5 Sheds for machinery 100 sqm @ `: 5500.00 / sqm `: 550000.00

6 Fuel depot 25 sqm @ `: 6600.00 / sqm `: 165000.00

7 Water tanks 10 sqm ( 20000 ltr ) @ `: 4400.00 / sqm `: 44000.00

8 Water & air supply lines with fittings LS `: 22000.00

9 Field offices / ramp ways etc LS `: 110000.00

10 Local haul roads LS `: 220000.00

Total `: 3943500.00

Add interest for 1 year @ 11.00% `: 433785.00

Add for maintenance for 1 year @ 1.00% `: 39435.00

Less salvage value @ 50 % for ( 1 ) to ( 6 ) ( - ) `: -1773750.00

Less salvage value @ 75 % for ( 8 ) ( - ) `: -16500.00

( A ) Total `: 2626470.00

Transportation / Erection / Dismantling of plant & machinery:

Transportation, erection & dismantling costs are not considered for aggregate crushing and

processing system as market rates are considered for aggregates.

Capital cost of equipments :

1 Air compressors 8.5 cmm ( diesel ) 2 Nos `: 1752244

2 Shovel 0.85 cum 1 No `: 4943385

3 Shovel 0.5 cum 1 No `: 2988348

4 Dozer 1 No. `: 4061189

5 Tippers 10 Nos ( exclusive transportation not considered ) `: 0

6 Water tanker 1 No `: 929034

7 Vibratory pad foot roller 1 No `: 2737998

8 Jack hammers 4 Nos `: 204644

9 Pumps of various capacity LS `: 66000

10 Portable magazine / Misc equipments LS `: 66000

11 Batching plant 15 cum / hour `: 3498313

12 Mechanical paver `: 2057668

13 Diesel generating set 30 KVA `: 496171

14 Diesel generating set 50 KVA `: 780079

15 Work shop equipments / fuel pump / Misc LS `: 220000

Total `: 24801073

169

Page 173: Data rates-Canal Works

CANAL AND ALLIED WORKS

Enabling costs on machinery :

Transportation to site for ( 1 ) to ( 15 ) @ 1.50% `: 372016.10

Erection cost for ( 11 ) to ( 15 ) @ 6.00% `: 423133.86

Total `: 795149.96

Add interest for 1 years @ 11% `: 87466.50

Add dismantling cost for ( 11 ) to ( 15 ) @ 3.00% `: 211566.93

Add transportation from site for ( 1 ) to ( 15 ) 1.50% `: 372016.10

( B ) Total `: 1466199.48

Total cost of other enabling works ( A ) + ( B ) `:`:`:`: 4092669.48

Consider the above provisions for enabling works for 15 km reach of canal.

Assuming average cost of canal per km excluding CD works @ Rs:

Cost for 15 km reach of canal `: 330000000

Add for outlets and other miscellaneous works @ 20% `: 66000000

Total `: 396000000

Cost of other enabling works as percentage of total cost of canal

x 100 / : 1.03

say : 1.00

4092669.48 396000000

22000000

170