46
Vermont AOT Bridge Maintenance and Preservation Conference July 1, 2008 George A. Christian, P.E. Inspection Data for Bridge Asset Management New York State Department of Transportation New York State DOT approach and Practice

Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

Embed Size (px)

Citation preview

Page 1: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

Vermont AOT

Bridge Maintenance and Preservation Conference

July 1, 2008

George A. Christian, P.E.

Inspection Data for Bridge Asset Management

New York StateDepartment of Transportation

New York State DOT approach and Practice

Page 2: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

OutlineBridge Management BackgroundNYS Bridge Evaluations

BackgroundBridge inspection ProgramInspection DataBridge Evaluation Programs

Bridge Asset Management StrategiesBridge Management analysis methods

Page 3: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

Asset Management

“Transportation Asset Management is a strategic and systematic process of operating, maintaining, upgrading and expanding physical assets effectively throughout their lifecycle. It

focuses on business and engineering practices for resource allocation and utilization, with the

objective of better decision-making based upon quality information and well-defined objectives.”

- AASHTO Subcommittee on Asset Management

Page 4: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

Bridge Management BackgroundTo manage bridges effectively we need the

following primary components:

Inventory definitionCurrent condition assessmentKnowledge of bridge vulnerabilities.Tracking of needs and projectsEconomic evaluation of potential actionsForecasting of deterioration and needsPhoto and document archive

Page 5: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

NYS Bridge Management System

Inventory Data Bridge Inspection Condition AssessmentVulnerabilitiesBridge Network Modeling Resource Allocation

Page 6: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

NY State Bridges

Owners: NYSDOT, Local Gov’ts, Authorities17,400 bridges carry public highways, 50,000+ spans

Page 7: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

NYS Bridge Ownership

(Local) 8587

(Other) 1187

(State)7632

Page 8: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

NYSDOT Bridge Evaluations

Program, in current format, developed in early 1980’s

Bridge Inspection (general and diving)Detailed Bridge Inventory -- BDMSLoad Capacity Evaluation (Rating, Posting)Bridge Safety Assurance (Vulnerabilities) Program

Bridge Inspection program is the primary data source for all evaluation functions

Page 9: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

NY’s bridge inspection programKey FeaturesClear mandateCentralized Responsibility and oversightFunding / Resource PriorityQuality ProvisionsCritical Findings ProcedureSafety CentricElement LevelData source for Bridge Mgmt.

Page 10: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

NYS Bridge Inspection Program

NYSDOT inspects State and Local owned highway bridges in New York StateInspection Team Leader must be a licensed Professional Engineer (P.E.)Biennial Inspection ProgramInterim Inspections9,500 NYSDOT inspections / year

Page 11: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

Element Level Inspections

Examine and evaluate all elements of the bridge (Visual, Tactile, Sounding)

Rate 47 elements22 common to all bridges25 on span by span basis

Document and photograph all “deficient” elements Measure and sketch deterioration and scour as necessary

Page 12: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

NYS Bridge Inspection Rating Scale

7 -- New condition, no deterioration6 --5 -- Minor deterioration and

functioning as designed 4 --3 --Serious deterioration or

not functioning as designed2 --1 -- Totally deteriorated or failed

condition

Def

icie

ntN

on-D

efic

ient

Good

Fair

Poor

Page 13: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

NYS Inspection Standards

Page 14: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

NYS Condition Rating

It is a rating calculated based on weighted inspection ratings of several components

Uses 13 different element ratingsWhen multiple rated elements exist, such as abutment backwalls, the calculation utilizes lowest rated elementIf C.R. < 5.00, the bridge is considered “Deficient”according to NYSDOT

C.R. is NYSDOT’s most widely used bridge condition performance indicator

Page 15: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

Uses of Inspection Data

Providing Data for Program PlanningUsed for developing capital program by using data with BMS softwareUsed to compute “Sufficiency Rating” (measure of the bridge’s ability to remain in service) to determine federal funding eligibility

Evaluation FunctionsInspection report used as a basis for structural integrity evaluations, load rating, and other functionsInspection report documentation as a reference

Page 16: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

Uses of Inspection Data

Scheduling Maintenance ActivitiesEmergency RepairsFlag RepairsCorrective MaintenancePreventative Maintenance

Satisfying Federal and State Reporting Requirements

Annual “Federal Tape”Annual NYS “Report of Bridge Management and Inspection Programs”

Page 17: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

Uses of Inspection Data

ForecastingElement deteriorationCondition rating trendsWork strategy forecasts

Cost estimatingCombine condition and inventory data

Page 18: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

Load Rating /Posting /Permit Reviews

State and Federal RequirementsNYSDOT Load Rating system

Bridge structural element databaseUse AASHTOWare® VIRTIS

Update data thru inspection program

Page 19: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

Bridge Safety Assurance Program (BSA)“Vulnerability Assessments”

Program of assessment of bridges’ vulnerability to structural failure due to their inherent characteristics or due to extreme eventsAssessments are made for individual failure modes

“Identify causes of failure beyond condition”(Why do Bridges Fail?)

Page 20: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

NYSDOT Bridge Failure Database

Page 21: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

NYSDOT Bridge Safety Assurance Program

Systematic evaluations of bridges based on failure modes.

Hydraulics Steel Details Overload Concrete Details Collision Earthquake

Evaluate statewide bridge population:Screen Assess Classify

Vuln. Classifications consider failure likelihood and consequence.Evaluation data needs collected during bridge inspections

Page 22: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

NYSDOT Bridge Safety Assurance

Vulnerability Assessment ProceduresAssessment ManualsRefined flowchart methods for screeningFollow up analysis for higher vulnerabilities Bridge Inventory database for screening and assessment updates

Page 23: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

NYSDOT Bridge Safety Assurance Program

Vulnerability Ratings (for each Failure Mode)

1. Safety Priority Action2. Safety Program Action3. Capital Program Action4. Inspection Program Action5. No Action

Page 24: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

BSA Safety Priority Action

Scour VulnerabilityMitigation

Scour RetrofitsFlood Warning Action PlanPost Flood Inspections

Page 25: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

BSA Capital Program Action

Retrofits: add primary redundancy

Page 26: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

NYSDOT Bridge Management Strategy

Goal OrientedDecentralized-but with central oversight Combined Capital and Maintenance programsLeast cost analysis for MR&R alternativesMaintenance /Operations First

Page 27: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

NYSDOT Bridge Goals

Eliminate Critical conditions:Low critical element ratingsHigh BSA vulnerabilities

Preservation:Reduce the overall number of deficient bridgesMaintain Interstate bridges in good conditionMaintain NHS bridges in at least fair condition

ServiceabilityReduce load restrictionsEliminate highway bridge clearance restrictions

Page 28: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

Performance Measures

Percentage of deficient bridgesStatewideInterstatesNHS

Number of bridges with critical elements rated less than 3 (serious deterioration)Serviceability by Hwy. classification

Number of bridges with load restrictionsNumber of bridges with clearance restrictions

Page 29: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

Maintenance / Operations FirstNYSDOT Bridge Maintenance

Corrective MaintenancePreventive (Cyclical) Maintenance$100 Million program

(out of $600 M state bridge program)In-house and contracted

Page 30: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

Bridge Maintenance

Corrective Maintenance

“Element Level” workElement inspection condition info.

ID work candidatesPerformance measure

Federal-aid (HBP) eligibleDelivery Initiatives

Job-order contracts

Page 31: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

Bridge Maintenance

Preventive (Cyclical) Maintenance

Washing (2 yr. cycle)Lubricate Bearings (4 yr.)Deck Sealing (4 yr.)Painting (12 yr.)Deck Overlay (12 yr.)Replace Deck Joints (as needed)

Federal-aid (HBP) eligible

Page 32: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

r

NYSDOT Bridge Preservation Status

4.4 $250K

$5K

4740 Fair Bridges

790 Poor

Treatment Costs / Bridge

Maintenance Candidates

Major Rehab or Replacement Candidates

2370 Good Bridges

5.8

$3.7M

Curve w/ Corrective Maintenance

Curve w/out Corrective Maintenance

Justification for Corrective Maintenance Program

Page 33: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

Local Projects

Included in Regional program updatesFed. Aid “pass-thru” projects (local let)DOT Oversight and Assistance

Local Projects Manual documents project development processStatewide Conference on Local Bridges

Information exchangeTraining

Page 34: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

Bridge Management Analysis Tools

Deterioration modelingNeeds assessment modelsCost assessmentForecasting BMS Software

Page 35: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

Deterioration ModelingElement Deterioration Curves

Page 36: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

Cost Modeling

Bridge unit cost dataReplacement cost estimating model

Based on historical dataBase area costsFeatures costs

Continuously updatedMaintenance and Rehab costs:

Inspection condition data determines work strategies—element combinationsAverage work strategy costs / s.f.

Page 37: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

Bridge Network AnalysisBridge Program Worksheet

Identifies program candidates for goal attainment using:

Condition (BDMS)InventoryElement and bridge inspection condition values

BSA vulnerabilities (BSA dB)Program Status (PSS)Deterioration module

Evaluates program updatesForecasts

Page 38: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

Bridge Network AnalysisBridge Needs Assessment Model (BNAM)

Forecasting-- Identifies present and future improvement needs for highway bridgesRegional bridge program development and evaluationStatewide bridge needs analysis and resource allocationUses Condition Rating as performance measureScenario analysis—treatment strategies, funding levels….

Page 39: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

Bridge Network AnalysisProgram Evaluation and Forecasts

State Highway Bridge Trend and Forecasts

26

27

28

29

30

31

32

33

34

35

36

1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016

Year

Perc

ent D

efic

ient

by

Num

ber

History Current Funding Needs Study Proposed Program

Page 40: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

Next StepsImprove on element level data for BMS purposes

condition state extentsImprove cost estimating modules

OptimizationQuantify life cycle costs

Preservation costsUser costs

Quantify benefits

Page 41: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

AASHTOWare® PONTISBMS Software

Licensed by most State DOT’s for over 15 years.Comprehensive BMS features

OptimizationPontis 5.2 (2009)

Software will feature a project focus with vastly improved project analysis capabilities.Multiple objective modeling framework.Incorporation of bridge risks.

Page 42: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

Pontis implementation IssuesElement level data

Uses AASHTO Core Element (CoRE) dataCollect CoRE data?Translate NYS to CoRE?Define new elements?

Program Optimization assumptionsOptimal means the least long term benefit / cost for each element stateMR&R benefits can be measured in two ways: future cost avoidance or change in element value (Bridge Health Index).

Page 43: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

Least Cost Optimization Results

Health Health IndexIndex

TimeTimeNear Term Long Term

Low

High

Unconstrained Curve

Page 44: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

Optimal Preservation

LongLongTerm Term CostCost

ConditionConditionPoor GoodLowow

High

Cost Minimization Point

Typical DOT Practices

Page 45: Data for Bridge Asset Mgmt Vermont - University of …transctr/pdf/Asset-Management.pdffor resource allocation and utilization, ... Annual NYS “Report of Bridge Management and Inspection

Summary:Bridge Inspection data →Asset management

Bridge inspection DataElement level conditionsNon-condition data (serviceability, vulnerabilities)Accessible Quality

Data supports program goals/ measuresMaintenance, Rehab, Replacement programsBridge safety