Upload
s-veeravel
View
214
Download
0
Embed Size (px)
Citation preview
8/13/2019 Cycletime Reduction
1/86
CYCLETIMEREDUCTION
8/13/2019 Cycletime Reduction
2/86
CYCLETIME REDUCTION
The Definition of Cycletime
There are two general definitions of Cycletime1. Time between beginning of production and completion of production.2. Time between the completion of the last product and completion ofthe next product.
While the scope of this Course covers BOTH areas, for purposes ofclarity, we will refer to definition 1 as leadtime and 2 as
cycletime.
Process1
Process2
Inspection Pack
Cycletime = Leadtime Cycletime
WIP WIP
8/13/2019 Cycletime Reduction
3/86
CYCLETIME REDUCTIONThe Definition of Cycletime
Process1
Process2
Inspection Pack
Leadtime
The leadtime starts the moment the piece parts are withdrawn fromStore and ends when the product is completed.The elements involved : waiting time, processing time, conversion orset-up time, transportation time and documentation time.To effectively reduce leadtime and cycletime, we would need toreduce/eliminate each of these elements.
Cycletime
WIP WIP
8/13/2019 Cycletime Reduction
4/86
CYCLETIME REDUCTION
The Definition of Cycletime
Cycletime = Available Production Time
Number of Products Produced
= Production Efficiency
Cycletime can be measured for the whole Production Line, for eachindividual Product or even Model.
8/13/2019 Cycletime Reduction
5/86
CYCLETIME REDUCTIONImportance of Cycletime
ReductionTechnology is constantly obsoleteTodays Product Lifecycles 3 12 monthsInventory is moneyRisk of inventory obsolescence highTodays Customers want- increased flexibility- low obsolescence riskThese goals can be achieved with reduced cycletime
A short cycletime is an organizations COMPETITIVE EDGE
8/13/2019 Cycletime Reduction
6/86
CYCLETIME REDUCTION
Theory of ConstraintsIn a Production line, identifythe bottleneck (D).Increase the bottleneck (D)
capacity. Bottleneck shifts toB.Increase the bottleneck (B)capacity.
To increase the effectivecapacity, focus on theconstraint (bottleneck) area.
Effective capacity
A DB C
Effective capacity
Effective capacity
8/13/2019 Cycletime Reduction
7/86
CYCLETIME REDUCTION
Theory of ConstraintsConstraints Product flowCycletime
To REDUCE Cycletime, production flow constraints
need to be eliminated or reduced.These constraints are :
Process1
Process2
Inspection Pack
WIP WIP
8/13/2019 Cycletime Reduction
8/86
CYCLETIME REDUCTION
Cycletime Analysis ToolsThree main tools used to analyze cycletime are:
1. Flow DiagramTo analyze the actual product flow.
2. Operations ChartTo analyze every production step and part used.
3. Process ChartTo study all the handling, inspection, operations, storageand delays as the product flows from raw materials tofinished goods.
8/13/2019 Cycletime Reduction
9/86
CYCLETIME REDUCTION
Cycletime Analysis ToolsThese tools are the macro analysis tools in that theyare used to analyze the overall operations.
Process1
Process2
Inspection Pack
WIP WIP
8/13/2019 Cycletime Reduction
10/86
CYCLETIME REDUCTIONCycletime Analysis Tools : Flow
DiagramWhat it is : A diagram that shows the path traveled bythe product as it flows through from Receiving toProduction to Shipping.
How to develop :1. Start with an existing or proposed scaled layout.2. Each step in the actual or proposed production flow is plotted
onto the layout, with arrows showing the direction of flow.
8/13/2019 Cycletime Reduction
11/86
Example : A current production layout.
Receiving
& IssuingStore
Shipping
Finished
GoodsStore
WI P
( K i t s )
Process1
WIP
Assembly Flow Inspection
WIP Awt.OQA
WIP Awt.Pack
Pack
OQA Room
Actual Product Flow
CYCLETIME REDUCTIONCycletime Analysis Tools : Flow
Diagram
8/13/2019 Cycletime Reduction
12/86
The Flow Diagram will be able to identify issues suchas :
Cross Traffic where flow lines cross
Backtracking where material flows backwardDistance product travelled.
CYCLETIME REDUCTIONCycletime Analysis Tools : Flow
Diagram
8/13/2019 Cycletime Reduction
13/86
Cross Traffic and Backtracking
Receiving
& IssuingStore
Shipping
Finished
GoodsStore
WI P
( K i t s )
Process1
WIP
Assembly Flow Inspection
WIP Awt.OQA
WIP Awt.Pack
Pack
OQA Room
Actual Product Flow
Backtracking
Cross Traffic
CYCLETIME REDUCTIONCycletime Analysis Tools : Flow
Diagram
8/13/2019 Cycletime Reduction
14/86
CYCLETIME REDUCTIONCycletime Analysis Tools : OperationsChart
What it is : A chart showingthe raw material,the purchased piece parts,
the fabrication/sub-assembly sequence,the assembly sequence,the equipment needs andthe time standards
to produce a finished product.
8/13/2019 Cycletime Reduction
15/86
CYCLETIME REDUCTIONCycletime Analysis Tools : OperationsChart
How to develop :1. Identify purchased vs. sub-assembled piece parts.2. Determine the operations required to fabricate each part and its sequence of
operations.
3. Determine the sequence of assembly for ALL piece parts.4. Identify the base part (raw PCB). This is the 1 st part that starts the assembly
process. Put that part on a horizontal line at the far right top of the page. On avertical line extending down from the right side of the horizontal line, place a circlefor each operation. Beginning with the first operation, list all operations down tothe last operation.
5.Place the 2
nd
part to the left of the 1st
part and the 3rd
part to the left of the 2nd
partetc. All of the fabrication steps are listed below the parts with a circle representingeach operation.
6. Draw a horizontal line from the bottom of the last operation of the 2 nd part to thepoint above the operation where it joins the 1 st part, and so on.
8/13/2019 Cycletime Reduction
16/86
Example :Base Part1st Part /
2nd Part3rd Part4 th Part
Sub-assemble 4 th Part to 3 rd Part
Assemble 1 st and 2 nd Parts andsub-assemble 3 rd and 4 th Parts
Operations tofabricate 4 th Part
Parts to be fabricatedPurchased Piece Part
CYCLETIME REDUCTIONCycletime Analysis Tools : OperationsChart
8/13/2019 Cycletime Reduction
17/86
How to develop : cont.7. Introduce all the purchased piece parts on horizontal lines above the assembly
operation circle where they are placed on the assembly.8. Put time standards, operation numbers, and operation descriptions next to and in
the circle.9. Sum total the hours per 1,000 units and place these total hours at the bottom right
under the last assembly or pack-out operation.
Example : PCB
05
10
Solder paste
Solder pasteprinting
Caps 0012 (4)
Res. 0120 (3)
SMDplacement
4002.5
250
4
Operation number
Operationdescription
Units per hour
Number ofhours to
complete 1,000units
6.5 hours
CYCLETIME REDUCTIONCycletime Analysis Tools : OperationsChart
8/13/2019 Cycletime Reduction
18/86
From the Operations Chart, the theoretical productleadtime can be determined.The difference between the actual leadtime and the
theoretical leadtime is the leadtime GAP.It is only through process and operations improvementthat the theoretical leadtime can be improved.
CYCLETIME REDUCTIONCycletime Analysis Tools : OperationsChart
8/13/2019 Cycletime Reduction
19/86
CYCLETIME REDUCTIONCycletime Analysis Tools : Process Chart
What it is : A chart that shows all the handling,inspection, operations, storage, and delays that occurto one part as it moves through the Production process.How to develop : Conventional symbols are used to describe theprocess steps.
Symbol Description Indicates Meaning
D
Circle
Square Arrow
Triangle
Big D
Operation
InspectionTransportation
Storage
Delay
Performing work on a part
Used for quality control workUsed when moving material
Used for long term storage
Used for short term storage
8/13/2019 Cycletime Reduction
20/86
Sample Process ChartingPROCESS CHART
PRESENT METHOD PROPOSED METHOD DATE : PAGE /
PART DESCRIPTION :
OPERATION DESCRIPTION :
SUMMARY PRESENT PROPOSED DIFFERENCE ANALYSIS : FLOW NO. TIME NO. TIME NO. TIME DIAGRAM
OPERATIONS WHY WHEN ATTACHED
TRANSPORT WHAT WHO
INSPECTIONS WHERE HOW
DELAYS
STORAGES STUDIED BY :
DIST. TRAVELED FT. FT. FT. STEP DETAILS OF PROCESS METHOD OPERATION TRANSPORT INSPECTION DELAY STORAGE DISTANCE QTY HRS/UNIT TIME CALCULATIONS
1
2
DD
D
1
2
3
4 5 6
7 8 9 10 11 12 13
CYCLETIME REDUCTIONCycletime Analysis Tools : Process Chart
8/13/2019 Cycletime Reduction
21/86
The main sections :1. Select either present method or proposed method, date and page.2. Describe the name of part and specifications if relevant.3. Record the limits of the study (example : from Receiving to FG).4. Record under the PRESENT column for study of current operations. To come
up with a new proposal, use the PROPOSED column. 5. For each step, the 5Ws and 1H are asked, starting with Why. Try to
Eliminate every step possible orCombine the steps orChange the sequence of operations to improve the product flow.
6. A Flow Diagram should be attached if available.7. Describe what happens in each step.8. Methods of transportation or storage are described (eg. by pallet).9. Symbols shade the appropriate symbol related to the step.
CYCLETIME REDUCTIONCycletime Analysis Tools : Process Chart
8/13/2019 Cycletime Reduction
22/86
The main sections :10. This is recorded when the transportation symbol is used. Specify unit of
measurement.11. Quantity refers to many things :
a. Operations Pieces per hourb. Transportation Number of pieces moved at a timec. Inspection Pieces per hour and/or frequency of inspectiond. Delays Number of pieces waitinge. Storage How many pieces per storage unit
12. Hours per unit time spent per piece at that step. Used only for operations,
transportation and inspection.13. Time calculations column provided to compute time spent.
Once all the sections are completed, return to complete the Summary.Use your Process Chart analyze and identify improvement opportunities.
CYCLETIME REDUCTIONCycletime Analysis Tools : Process Chart
8/13/2019 Cycletime Reduction
23/86
CYCLETIME REDUCTIONMethods of Analyzing Cycletime
Five main charts are used to micro analyzecycletime of operations :
Operations Analysis ChartOperator/Machine ChartGang ChartMulti-Machine Chart
Left/Right Hand Chart
8/13/2019 Cycletime Reduction
24/86
These charts are used to analyze and breakdown eachoperation into its separate micro elements.
Process1
Process2
Inspection Pack
WIP WIP
CYCLETIME REDUCTIONMethods of Analyzing Cycletime
8/13/2019 Cycletime Reduction
25/86
CYCLETIME REDUCTIONMethods of Analyzing Cycletime :Multi
Activity ChartWhat it is : It is a standard Chart Format used to createthe
Operations analysis chartOperator/machine chart
Gang chartMultimachine chartLeft-hand/right-hand chart
The chart is separated into 15 different sections.
8/13/2019 Cycletime Reduction
26/86
CYCLETIME REDUCTIONMethods of Analyzing Cycletime :Multi
Activity ChartMULTI ACTIVITY CHART
OPERATOR/MACHINE GANG MULTI MACHINELEFT HAND/RIGHT HAND OPERATIONS
OPERATION NO. PART NO. OPERATION DESCRIPTION :
DATE : TIME :
BY :
ACTIVITY TIME IN ACTIVITY SECONDS
TOTAL UTILIZATION : TOTAL UTILIZATION :
% UTILIZATION : % UTILIZATION :
TOTAL NORMAL TIME IN SECONDS PER UNIT :
+ % ALLOWANCE :
STANDARD TIME :
HOURS PER UNIT :
PIECES PER HOUR :
1
2 34 5
6
7
8 8
9 9
10 10
1112
1314
15
8/13/2019 Cycletime Reduction
27/86
CYCLETIME REDUCTIONMethods of Analyzing Cycletime :Multi
Activity ChartThe main sections :
1. Tick or cross the appropriate box on the chart being created.2. The operation number for the particular operation (if available).3. The product part number.4. The date of the study, include day, month and year.
5. The time the study started.6. Record the name of the person who is conducting the study.7. Operation described in clear terms.8. Activity will represent different things for different charts
1. Operations analysis use LEFT column only2. Operator/machine LEFT column for Operator, RIGHT for Machine3. Gang LEFT column for Operator 1, RIGHT for Operator 24. Multimachine 2 charts are taped next to each other. On the 1 st chart, LEFT
column for Operator, RIGHT for Machine 1. On the 2 nd chart, LEFT column forMachine 2, RIGHT column for Machine 3.
5. L-H/R-H LEFT column for Left Hand, RIGHT for Right Hand
8/13/2019 Cycletime Reduction
28/86
The main sections :9. These are the activity areas where the actual activities are recorded.10. Total Utilization is how much time this activity was working. Idle time is
NOT included.% Utilization is the total utilization divided by the total time of thatactivity.
11. Total normal time is how long it takes each activity to complete a cycleand includes both working time and idle time.
12. Allowances are the time added to normal time to make the timestandards realistic. These include personal time, fatigue and delays. A
ballpark figure of 10% is typically used.13. Standard time = normal time + allowances (in secs/unit).14. Hours per unit = standard time (secs/unit)/(3600 secs/hour)15. Pieces per hour = inverse of hours per unit = 1/(hours per unit)
CYCLETIME REDUCTIONMethods of Analyzing Cycletime :Multi
Activity Chart
8/13/2019 Cycletime Reduction
29/86
CYCLETIME REDUCTIONMethods of Analyzing CycletimePieces Per Hour Cycletime
Pieces Per Hour Cycletime
1 Hour
Cycletime
Cycletime
8/13/2019 Cycletime Reduction
30/86
CYCLETIME REDUCTIONMethods of Analyzing Cycletime :Operations
Analysis ChartWhat it is : A chart used to describe
a single activityusually one operator using tools 100% operator controlledExample : Packing operation.
MULTI ACTIVITY CHART OPERATOR/MACHINE GANG MULTI MACHINE
LEFT HAND/RIGHT HAND OPERATIONS
OPERATION NO. PART NO. OPERATION DESCRIPTION :
DATE : TIME :
BY :
ACTIVITY TIME IN ACTIVITY SECONDS
X100 AX250
Feb.26,05 0930Bruce Lee
Packing operation for shipment.
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
31/86
CYCLETIME REDUCTIONMethods of Analyzing CycletimeOperations Analysis Chart
SECONDS
This side is left blank
Activity ActivityFold carton box, insert kimcell.
Insert PCBA and pack into carton.Idle.
1047
These activities need to beanalyzed, for example :
Why 10 secs to preparebox? Can it be preparedahead of time?
Why idle time of 7 secs?How to eliminate this? Whatcan operator do if cannoteliminate?
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
32/86
CYCLETIME REDUCTIONMethods of Analyzing CycletimeOperations Analysis Chart
TOTAL UTILIZATION : TOTAL UTILIZATION :
% UTILIZATION : % UTILIZATION :
TOTAL NORMAL TIME IN SECONDS PER UNIT :
+ % ALLOWANCE :
STANDARD TIME :
HOURS PER UNIT :
PIECES PER HOUR :
14 secs67%
21 secs
10%
24 secs0.0067
150
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
33/86
CYCLETIME REDUCTIONMethods of Analyzing CycletimeOperator/Machine Chart
What it is : A chart that shows the activities andinter-relationship of the operator and themachine. The chart shows what each is doing
at any moment in time.Example : An operator running a marking machine.MULTI ACTIVITY CHART
OPERATOR/MACHINE GANG MULTI MACHINELEFT HAND/RIGHT HAND OPERATIONS
OPERATION NO. PART NO. OPERATION DESCRIPTION :
DATE : TIME :
BY :
ACTIVITY TIME IN ACTIVITY SECONDS
X
75 BY300Feb.26,05 1500
Jackie ChanInk marking EPROM.
Operator Ink Mark Machine
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
34/86
CYCLETIME REDUCTIONMethods of Analyzing CycletimeOperator/Machine Chart
SECONDSOperator Ink Mark Machine
Load EPROM. Idle.Mark unit.Idle.
57
Unload EPROM.45 Inspect EPROM. Idle.
579
The high percentage of idle timerepresents a waste of capacity.How to minimize?
Can the work sequence berearranged to utilize the idletime to do inspection?
Can the inspection beeliminated to reduce thecycletime?
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
35/86
CYCLETIME REDUCTIONMethods of Analyzing CycletimeOperator/Machine Chart
TOTAL UTILIZATION : TOTAL UTILIZATION :
% UTILIZATION : % UTILIZATION :
TOTAL NORMAL TIME IN SECONDS PER UNIT :
+ % ALLOWANCE :
STANDARD TIME :
HOURS PER UNIT :
PIECES PER HOUR :
14 secs 7 secs67% 33%
21 secs10%
24 secs0.0067
150
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
36/86
CYCLETIME REDUCTIONMethods of Analyzing CycletimeGang Chart
What it is : A chart to show the activities of two or morepeople when their activities intertwine. When more thantwo people are involved, tape two or more charts side byside.
Example : Solder joint touch-up and inspection.
MULTI ACTIVITY CHART OPERATOR/MACHINE GANG MULTI MACHINE
LEFT HAND/RIGHT HAND OPERATIONS
OPERATION NO. PART NO. OPERATION DESCRIPTION :
DATE : TIME :
BY :
ACTIVITY TIME IN ACTIVITY SECONDS
X
851700Feb.26, 05
LT800Solder joint touch-up and inspection.
Ali Bakar
Touch-up operator Inspection operator
8/13/2019 Cycletime Reduction
37/86
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
38/86
CYCLETIME REDUCTIONMethods of Analyzing CycletimeGang Chart
TOTAL UTILIZATION : TOTAL UTILIZATION :
% UTILIZATION : % UTILIZATION :
TOTAL NORMAL TIME IN SECONDS PER UNIT :
+ % ALLOWANCE :
STANDARD TIME :
HOURS PER UNIT :
PIECES PER HOUR :
26 secs
49%
27 secs
51%53 secs
10%
59 secs0.016
63
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
39/86
CYCLETIME REDUCTIONMethods of Analyzing CycletimeMulti-Machine Chart
What it is : A chart similar to the operator/machine chartexcept that additional charts are taped to the side of the1 st chart. On these additional charts, each additionalmachine takes up one column.
Example : 1 operator running 3 ink markers.
Operator Machine 1 Machine 2 Machine 3
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
40/86
CYCLETIME REDUCTIONMethods of Analyzing CycletimeLeft/Right Hand Chart
What it is : A chart that tracks the separate activities ofeach hand of an operator. Each hands activity isbroken down into detailed elements.
Example : Operator inserting PTH components into PCBA.
MULTI ACTIVITY CHART OPERATOR/MACHINE GANG MULTI MACHINE
LEFT HAND/RIGHT HAND OPERATIONS
OPERATION NO. PART NO. OPERATION DESCRIPTION :
DATE : TIME :
BY :
ACTIVITY TIME IN ACTIVITY SECONDS
X
65 AT540Feb.26, 05 1030
MuruPTH insertion into PCBA.
Left Hand Right Hand
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
41/86
CYCLETIME REDUCTIONMethods of Analyzing CycletimeLeft/Right Hand Chart
SECONDSLeft Hand Right HandPick-up PCBA. Pick-up component.
Align and insert component intoPCBA.
Idle (Holding PCBA).
Idle.Pass PCBA to next operation.
Idle.
5 5
12 12
413 9
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
42/86
CYCLETIME REDUCTIONMethods of Analyzing CycletimeLeft/Right Hand Chart
TOTAL UTILIZATION : TOTAL UTILIZATION :
% UTILIZATION : % UTILIZATION :
TOTAL NORMAL TIME IN SECONDS PER UNIT :
+ % ALLOWANCE :
STANDARD TIME :
HOURS PER UNIT :
PIECES PER HOUR :
5 secs17%
21 secs70%
30 secs10%
33 secs0.009109
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
43/86
CYCLETIME REDUCTIONMethods of Cycletime ReductionWork Station Design
Having a work station that is designed to ease the taskof the operator will help in maximizing work efficiency =reducing cycletime.
A well designed work station supports motion economy.
Process1
Process2
Inspection Pack
WIP WIP
8/13/2019 Cycletime Reduction
44/86
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
45/86
CYCLETIME REDUCTIONMethods of Cycletime ReductionWork Station Design
Some key considerations :Work table height should beconstant and ideally at elbow
height of the seated person.
Use chairs which can be
adjusted for height.Chairs should be comfortablewith back supports.
CYCLETIME REDUCTION
http://av.rds.yahoo.com/_ylt=A0Je5XNon7ZBkHsAC0RvCqMX;_ylu=X3oDMTBvMmFkM29rBHBndANhdl9pbWdfcmVzdWx0BHNlYwNzcg--/SIG=11ef9kgio/**http%3a//www.ergexperts.com/ergservices.htm8/13/2019 Cycletime Reduction
46/86
CYCLETIME REDUCTIONMethods of Cycletime ReductionWork Station Design
Some key considerations :Frequently used tools should belocated nearby the work station.Incorporate fixtures to replace thehuman hand for holding parts asmuch as possible.Locate reject bins or baskets closeto the work station to preventunnecessary movement by theoperator.Use chutes to take advantage ofgravity to move parts.
CYCLETIME REDUCTION
http://av.rds.yahoo.com/_ylt=A0Je5Wzdm7ZB2mAA_SJvCqMX;_ylu=X3oDMTBvMmFkM29rBHBndANhdl9pbWdfcmVzdWx0BHNlYwNzcg--/SIG=119dk5cr9/**http%3a//elpedregalsal.com/country.htm8/13/2019 Cycletime Reduction
47/86
CYCLETIME REDUCTIONMethods of Cycletime ReductionWork Station Design
Some key considerations : Align the work station to the product flow.
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
48/86
CYCLETIME REDUCTIONMethods of Cycletime ReductionMotion Economy
Economic motion minimizes processing time andhence contributes to cycletime reduction.This is strongly related to and supported by workstation design.
Process1
Process2
Inspection Pack
WIP WIP
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
49/86
CYCLETIME REDUCTIONMethods of Cycletime ReductionMotion Economy
Some key considerations :The hands should :
1. Operate as mirror images2. Start and stop motions at the
same time3. Move in opposite directions4. Be working at all times.
Use fixtures to replace handsholding parts where possible.Use foot operated controldevices where possible to freeup the hands.
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
50/86
CYCLETIME REDUCTIONMethods of Cycletime ReductionMotion Economy
Some key considerations :Use ballistic motions where possible :fast motions using one set of musclesand not trying to end the motion using
other muscles, example, throwing apart into a bin.Use controlled motions, i.e. whichrequire control at the end of the motion,only for activities needing safety or
quality considerations.Use curved continuous motions insteadof separate linear motions.
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
51/86
CYCLETIME REDUCTIONMethods of Cycletime ReductionLine Balancing
One technique which sees almost immediate impact in acycletime reduction exercise is line balancing. Bybalancing the production line, obvious line imbalances orbottlenecks can be removed. This increases the effectiveline capacity and reduces cycletime.Refer to section on Theory of Constraints.
Process1
Process2
Inspection Pack
WIP WIP
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
52/86
CYCLETIME REDUCTIONMethods of Cycletime ReductionRemoving NVA
Non-Value-Added activities are activities that do not addvalue to the product. They just add cost .Major NVA activities are inspection, product movementand waiting time. By removing or reducing theseactivities, the cycletime is reduced accordingly. Waitingtime is one of the major contributors to long cycletime .
Process1
Process2
Inspection Pack
WIP WIP
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
53/86
CYCLETIME REDUCTIONMethods of Cycletime ReductionRemoving NVA
While removing inspection needs to be justified with qualityimprovement, others such as eliminating a staging area(shown below), can be easily justified.
ISSUING STORE
ISSUING STORE
STAGING AREA
PRODUCTION LINE
PRODUCTION LINE
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
54/86
CYCLETIME REDUCTIONMethods of Cycletime ReductionRemoving NVA
Examples of elimination of handling and transportation.Improvement from A to D.
Double Handling
Transportation
Inventory on conveyor
No waiting
A
B
C
D
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
55/86
CYCLETIME REDUCTIONMethods of Cycletime ReductionQuick Set-ups
In handling multiple models, the process ofchanging from one model to the next is NVA. Itadds up to the product leadtime and hence,cycletime.Quick set-ups, therefore, reduce productcycletime.
Process1
Process2
Inspection Pack
WIP WIP
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
56/86
CYCLETIME REDUCTIONMethods of Cycletime ReductionQuick Set-ups
Internal setup : Setup activities done on the machine while themachine is down.
Example : Changing over of tools, dies, jigs and materials whi lethe mach ine i s down .
External setup : Setup activities done before and after themachine is down and do not add to the machine downtime.
Example : Prepar ing in advanc e the necessary jigs, tools, thenext die and materials and removing the detached die and jigsaf ter the m achine i s u p .
Machine down Machine up
Internal setup change tool,die, materials
External setup prepare tool,die, materials
External setup remove
detached tool, die
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
57/86
CYCLETIME REDUCTIONMethods of Cycletime ReductionQuick Set-ups
Steps in Shortening Set-up Time
1. Separate the internal set-up tasks from the external set-up tasks
Example :Typical External Set-up Tasks Typical Internal Set-up Tasks
Preparation of dies, fixtures etc. Transfer of dies
Attachment and detachment Adjustment of location, height,
pressure, etc. Test run
2. Convert internal set-up to external set-up
Example : Preheating dies is a way of converting internalset-up to external set-up
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
58/86
CYCLETIME REDUCTIONMethods of Cycletime ReductionQuick Set-ups
3. Improve internal set-up
Example 1 : Reduce internal set-up by eliminating adjustment
StandardizedDie Height
Blocks
Locating Pin
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
59/86
CYCLETIME REDUCTIONMethods of Cycletime ReductionQuick Set-ups
88B
ColorcodingMachine
Address
Die storage area
(close to the point of use)
4. Improve external set-upReduce/eliminate time wasted searching for tools, dies and fixtures bydesignating areas by color coding shelves and assigning addresses for eachstorage area.
Reduce time wasted in transferring dies by storing frequently used dies closeto the machine.
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
60/86
Methods of Cycletime ReductionLot Size Reduction
Typically, the larger the lot size, the longer the waitingtime. Traditionally, large lot sizes were preferred due tohigh set-up times. However, with large lot sizes, WIPbuilds up and product cycletime lengthens.Reducing lot size reduces product cycletime.
Process1
Process2
Inspection Pack
WIP WIP
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
61/86
Methods of Cycletime ReductionLot Size Reduction
Example : Processing time 1 min./unit
A B C
A B C
A B C
A B C
A B C
A B C
Lot size : 3 Lot size : 1Time Time
0 min 0 min
3 min1 min
A B C
A B C
6 min
9 min
2 min
3 min
A B C4 min
A B C5 min
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
62/86
Methods of Cycletime ReductionParallel Processing
Parallel processing means processing 2 or moreoperations at the same time. In set-up time language, itmeans converting internal time to external time.Parallel processing, therefore, reduces set-up time.
Process1
Process2
Inspection Pack
WIP WIP
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
63/86
Methods of Cycletime ReductionParallel Processing
Example : Reducing internal set-up by using ParallelOperations
1 2 3 4 5 6 7machine stop machine start
Step No. OperationInternal /External
Required time(min) Performed by
1 Look for new die I 3 Operator2 Transfer new die I 10 Operator3 Remove used die I 2 Operator4 Attach new die I 2 Operator5 Transfer new material I 10 Operator6 Adjust I 20 Operator7 Transfer used die I 10 Operator
Before improvement (Total Internal Set-up Time : 57 Min)
Parallel Operations on a Press Machine
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
64/86
Methods of Cycletime ReductionParallel Processing
1 2 5 4 6a 7
machinestop
machinestart
Step No. Operation
Internal /
External
Required time
(min) Performed by1 Look for new die E 3 Assistant2 Transfer new die E 10 Assistant5 Transfer new material E 10 Assistant4 Attach new die * I 2 Assistant
6a Adjust ** I 7 Assistant3 Remove used die * I 2 Operator
6b Adjust ** I 8 Operator
After improvement (Total Internal Set-up Time : 10 Min)
3 6b
(Set-up assistant)
(Operator)
7 Transfer used die E 10 Assistant
Note : *, ** : conduct operations simultaneously
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
65/86
Methods of Cycletime ReductionWIP Reduction
Work In Progress (WIP) or inventory, when not beingprocessed, is accumulating cycletime. Therefore, toreduce cycletime, drive down WIP.
Process1
Process2
Inspection Pack
WIP WIP
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
66/86
Methods of Cycletime ReductionWIP Reduction
Raw material Finished productsto customers
Sea of inventory
Poor
scheduling
Machinebreakdown Quality
problems
Absenteeism
Long set-up times
Inventory Covers Problems
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
67/86
Methods of Cycletime ReductionWIP Reduction
The only justifiable WIP is that which isused to prevent a process from beinglinedown.For example, the WIP shown should onlyserve to prevent Process 2 from stoppingbecause of instability in Process 1 due to :
Machine downtimeLow yieldsQuality issuesBatch processing waiting time
However, as WIP represents waitinginventory and should be driven down.
Process1
Process2
WIP
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
68/86
Methods of Cycletime ReductionFIFO
FIFO stands for First In First Out. This is a flow sequence where thefirst product processed flows through and gets completed first, andso on.By implementing FIFO, no WIP gets bypassed and line issues areforced to be addressed, easing the subsequent product flow and
hence reducing cycletime.The only time FIFO should be bypassed is when there is anabnormal lot such as extremely low yield lot, quality question etc.
Process1
Process2
Inspection Pack
WIP WIP
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
69/86
Methods of Cycletime ReductionKanbans
A Kanban is a card used in the Toyota Production System or JIT. Itis used to request or pull materials in a Pull Production System.In Malaysia, typically Kanban squares are used in the place ofKanban cards. By defining the Kanban quantity, WIP, productionflow and hence cycletime can be controlled.
Process1
Process2
Inspection Pack
WIP WIP
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
70/86
Methods of Cycletime ReductionKanbans
An in fo rmat ion sys tem tha t ha rmo nious ly con t ro l s theprodu c t ion o f the
necessary p rod uc t s in the
necessary qu ant i t ies at the
necessary t im e in
every p roc ess o f a f ac to ry and a l so amo ng c om panies
It u t i l izes a pul l sys tem that i s d ic ta ted by cus tom er orders
I t is a sub -sys tem tha t suppo r t s the Toyota Produc t ionSys tem or l ean m anufac tu r ing
What is the Kanban system?
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
71/86
Methods of Cycletime ReductionKanbans
PROCESS 1 PROCESS 2 FG CUSTOMERFG STOREWIPWIP
123
Cus tom er p laces o rderand FG Store ships FGavailable to Custo m er.
At the same t im e, aWi thdrawal Kanban i s
i s sued f rom FG Store toKanban loca t ion o f
Process 2 and WIP f romProcess 2 is pulled to
FG Store
Process 2 receives aProduc t ion Order ing
Kanban f rom i t sKanb an locat ion .
It s t a r ts p rodu c t ion
and a t the same t im eissu es a Withd rawalKanban to Kanban
loca t ion o f P rocess 1
Process 1 receives aProduc t ion Order ing
Kanban f rom i t sKanb an loc at ion.
It s t a rt s p ro duc t ion
and a t the same t im eissu es a Withdraw alKanban to Kanban
loc at ion of Raw Mat lStore
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
72/86
Methods of Cycletime ReductionLeveled Production
When there are two models to a product, say models Aand B. Typically, these models will be loaded as A,A,A,Athen B,B,B,B. In leveled production, the loading is
A,B,A,B,A,B,A,B.
The advantage of leveled production with regards tocycletime is huge if A and B are sold as a set.
Process1
Process2
Inspection Pack
WIP WIP
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
73/86
Methods of Cycletime ReductionLeveled Production
Example : Models A and B (a set) are processed through Processes1 and 2. Each take 1 minute to process for each process. Two setsare processed.
1 2
1 2
1 2
1 2
1 2
1 2
1 2
1 2 AB
A A
TimeTime
1 min 1 min
2 min2 min A A AB
3 min 3 min A AB B A
4 min 4 min
A
B B A A B A
Set completion : 4 min Set completion : 3 min
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
74/86
Methods of Cycletime ReductionEliminating Wastes
Wastes are elements in the Production area that addcost but not value. Eliminating these wastes will see thecycletime drop tremendously.
Process1
Process2
Inspection Pack
WIP WIP
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
75/86
Methods of Cycletime ReductionEliminating Wastes
Kiyo shi Suzaki refined waste classification into sevencategories :
Waste from overproduction Waste of waiting time Transportation waste Processing waste Inventory waste Waste of motion Waste from product defects
Henry Ford , If it doesnt add value, its waste .
CYCLETIME REDUCTION
http://rds.yahoo.com/S=96062857/K=product+defects/v=2/SID=e/l=II/R=1/SS=i/OID=3537c6685f8ab0dc/SIG=1hvqbmu5c/*-http%3A//images.search.yahoo.com/search/images/view?back=http%3A%2F%2Fimages.search.yahoo.com%2Fsearch%2Fimages%3Fp%3Dproduct%2Bdefects%26sm%3DYahoo%http://rds.yahoo.com/S=96062857/K=factory+workers/v=2/SID=e/l=II/R=40/SS=i/OID=c3b1981adad33700/SIG=1hsh5dtca/*-http%3A//images.search.yahoo.com/search/images/view?back=http%3A%2F%2Fimages.search.yahoo.com%2Fsearch%2Fimages%3Fp%3Dfactory%2Bworkers%26sm%3DYahoohttp://rds.yahoo.com/S=96062857/K=factory+workers/v=2/SID=e/l=II/R=12/SS=i/OID=887edcce87d6c9f0/SIG=1lhajqcni/*-http%3A//images.search.yahoo.com/search/images/view?back=http%3A%2F%2Fimages.search.yahoo.com%2Fsearch%2Fimages%3Fp%3Dfactory%2Bworkers%26sm%3DYahoohttp://rds.yahoo.com/S=96062857/K=factory+workers/v=2/SID=e/l=II/R=6/SS=i/OID=dc02920bf3a67cfa/SIG=1iulrvatq/*-http%3A//images.search.yahoo.com/search/images/view?back=http%3A%2F%2Fimages.search.yahoo.com%2Fsearch%2Fimages%3Fp%3Dfactory%2Bworkers%26sm%3DYahoo%http://rds.yahoo.com/S=96062857/K=factory+workers/v=2/SID=e/l=II/R=5/SS=i/OID=6091d59647c3b9be/SIG=1isdn0t22/*-http%3A//images.search.yahoo.com/search/images/view?back=http%3A%2F%2Fimages.search.yahoo.com%2Fsearch%2Fimages%3Fp%3Dfactory%2Bworkers%26sm%3DYahoo%http://rds.yahoo.com/S=96062857/K=floor+space/v=2/SID=e/l=II/R=48/SS=i/OID=cf32579f3de43434/SIG=1h5lam8dg/*-http%3A//images.search.yahoo.com/search/images/view?back=http%3A%2F%2Fimages.search.yahoo.com%2Fsearch%2Fimages%3Fp%3Dfloor%2Bspace%26sm%3DYahoo%2521%2B8/13/2019 Cycletime Reduction
76/86
Methods of Cycletime ReductionFlow Smoothing / Layout
Like water flowing through a pipe, a short and directproduction layout will tend to produce a smooth and fastproduction flow.Use a product-centric layout instead of a process-centriclayout to shorten product cycletime.
Process1 Process2 Inspection Pack
WIP WIP
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
77/86
Methods of Cycletime ReductionFlow Smoothing / Layout
Layout/flow guidelines :Product should flowtowards the shipment area.No backflow wherepossible.No cross flows.Do not use excess floorspace.
Keep area compact anddefined.Identify all inventory areasand kanbans.
S HI P ME NT
S HI P ME NT
S HI P ME NT
WALLED OFFFOR FUTUREEXPANSION
S HI P ME NT
S HI P ME NT
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
78/86
Methods of Cycletime Reduction5 S
A properly executed 5S environment can help reducecycletime.
A neat and properly defined work area means thattools and parts can be easily found. Searching time
and waiting time can be minimised or eliminatedresulting in reduced cycletime.
Process1 Process2 Inspection Pack
WIP WIP
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
79/86
CYCLETIME REDUCTIONCycletime Simulation
A cycletime simulation can reveal the theoreticalleadtime and cycletime for the product. This will be thetheoretical limit for the product cycletime.
1. Define the lot size, the processes and the UPH for each process.2. Compute the lot completion time for each process.3. List the Processes down the first column.4. List an Hour timeline across the top row.5. Plot the Lots as they move diagonally down from top left to bottom
right of the table.
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
80/86
CYCLETIME REDUCTIONCycletime Simulation
Lot Size : 3,000 Process Assembly Mark Test
UPH 1,200 2,000 1,500
Lot Completion Time 2.50 1.50 2.0
Lot Completion Time = Lot SizeUPH
1
2
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
81/86
CYCLETIME REDUCTIONCycletime Simulation
Timeline (hr)Process
Assembly
Mark
Test
1 2 3 4 5 6 7 8 9 10 11
Lot 1
Lot 1
Lot 1
Lot 2
Lot 2
Lot 2
Lot 3
Lot 3
Lot 3
Leadtime = 6hrsCycletime= 2.5hrs Cycletime
3
4
5
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
82/86
CYCLETIME REDUCTIONCycletime Metrics
Metrics related to cycletime are :Total leadtimeCycletimeProcess Cycle Efficiency (PCE)
Workstation Turnover Time (WTT)
Process1
Process2
Inspection Pack
Total Leadtime Cycletime
WIP WIP
PCE WTT
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
83/86
CYCLETIME REDUCTIONCycletime Metrics
Total LeadtimeUnit of measurement weeks/days/shifts/hours/minsTotal leadtime can be :
measured (from time piece parts are issued to receivingcompleted product at Finished Goods)computed from Littles Law :
Total Leadtime (time) =WIP (units)
Average Completion Rate
Effective Line Capacity(units/time)
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
84/86
CYCLETIME REDUCTIONCycletime Metrics
CycletimeUnit of measurement weeks/days/shifts/hours/mins
Although cycletime is defined as the time taken for the next product to be produced, the average cycletime is generally
computed as follows :
Cycletime (time/unit)= Available Production Time (time)
Number of Products Produced (unit)
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
85/86
CYCLETIME REDUCTIONCycletime Metrics
Process Cycle Efficiency (PCE)PCE indicates how efficiently the process is converting WIP intofinished products.PCE is a ratio.
Any process with low PCE will have large NVA activities andhence opportunities to for cycletime reduction.It is common to get PCEs of less than 10% before improvement. The Process Chart can be used to collect the required data forValue-Add Time.
PCE = Value-Add Time (time)
Total Leadtime (time)
CYCLETIME REDUCTION
8/13/2019 Cycletime Reduction
86/86
CYCLETIME REDUCTIONCycletime Metrics
Workstation Turnover Time (WTT)It is the time taken to set-up and perform one cycle ofwork at a specified workstation.Unit of measurement - hours/mins/secs.
WTT =Summation of (set-up time + process time) at the
workstation