CSL TECHNOLOGIES (M) SDN BHD LRC TECH (M) SDN BHD
Ref. No. CS-P13 Revision No. 00
EQUIPMENT MAINTENANCE AND CALIBRATION PROCEDURE
Effective Date 01/11/2010 Page 1 of 5
This procedure is a “controlled” document and authorized for use. When printed from this share drive, this document is uncontrolled. Before using a printed copy of this document, ensure that it is the same as the latest version on share drive.
REVISION HISTORY
Rev No.
Effective Date Affected Page
Change Descriptions
Reviewed By
Approved By
00 01/11/2010 All New Issue Document Distribution Acknowledgement:
Dept. / Position
Business Development
Director
Admin Sales & Marketing
Design Production R&D
Acknowledgement
Date
Note: The details and the reason of change are documented in the Revision History state above and file at DCC.
CSL TECHNOLOGIES (M) SDN BHD LRC TECH (M) SDN BHD
Ref. No. CS-P02 Revision No. 00
EQUIPMENT MAINTENANCE AND CALIBRATION PROCEDURE
Effective Date 01/11/2010 Page 2 of 5
THIS IS AN UNCONTROLLED COPY OF A CONTROLLED DOCUMENT PRINTED
1.0 PURPOSE
To ensure that all measurement and test equipments which are used to determine and monitor product quality are periodically inspected, always ready for use and the measurement/test results they deliver are as accurate as required.
To ensure proper procedure for machine preventive maintenance and breakdown maintenance to reduce machine down time.
2.0 SCOPE
This procedure applies to all personnel who are involved in the handling, usage, storage, maintenance and calibration of machines and equipments.
3.0 DEFINITION
Measuring equipments: Inspection, measuring and test equipment
CSL TECHNOLOGIES (M) SDN BHD LRC TECH (M) SDN BHD
Ref. No. CS-P02 Revision No. 00
EQUIPMENT MAINTENANCE AND CALIBRATION PROCEDURE
Effective Date 01/11/2010 Page 3 of 5
THIS IS AN UNCONTROLLED COPY OF A CONTROLLED DOCUMENT PRINTED
4.0 PROCEDURE DETAILS 4.1 CALIBRATION
Process Flow Description Documents
/ Ref. Personnel
- Any purchase request for new measuring equipment shall obtain prior approval from Director. - Director shall verify to ensure the measuring equipment is suitable for use.
- Quotation
- Director
- Any new purchased measuring equipment shall be registered in the Equipment Calibration List. - Assign equipment number. - Determine that calibration or verification interval, calibrator (internal or external), measurement tolerance required. - For internal calibration, calibration instructions shall be prepared, and shall have traceable to international or national measurement standards.
- Equipment Calibration List (CS-F35)
- Production Manager
- The methods of handling, usage, maintenance and storage shall be determined in line with any applicable manufacturer’s recommendations:
• User shall check the measuring equipment working conditions before use.
• All measuring equipment shall be handled as per instructed by Production dept.
• Any malfunction or damage to the equipment used shall be reported to Director .
• After use, all measuring equipment shall be cleaned and stored in appropriate designated area to prevent misuse or loss.
- Ensure appropriate training is provided to equipment users to preserve the integrity of equipment for intended application, and no damage or loss of measurement precision.
- Operating Instruction
- User
- Recall measuring equipment for calibration when it is due.
- Equipment Calibration List (CS-F35)
- Production Manager
Update Equipment Calibration List
New measuring equipment
Determine handling, usage, maintenance & storage methods
YES
Prepare & monitor Calibration schedule
CSL TECHNOLOGIES (M) SDN BHD LRC TECH (M) SDN BHD
Ref. No. CS-P02 Revision No. 00
EQUIPMENT MAINTENANCE AND CALIBRATION PROCEDURE
Effective Date 01/11/2010 Page 4 of 5
THIS IS AN UNCONTROLLED COPY OF A CONTROLLED DOCUMENT PRINTED
Process Flow Description Documents / Ref.
Personnel
- For external calibration, arrange for proper packing and delivery to external calibrator. - External calibrator shall be a nationally accredited laboratory. - For internal calibration, calibration shall be conducted as per the defined calibration instructions by trained personnel. The calibration conditions shall be defined in the calibration instruction. - Generate internal calibration records accordingly.
- External Calibrator - Internal Calibration Instructions
- Production Manager
- Upon receipt of calibration report, internal or external, verify the results to determine the acceptability of the equipment against measurement tolerance required. - Paste calibration sticker upon acceptance. - For equipment that is not use for verifying product and process conformance to quality requirements, indicates with a “FOR INDICATION ONLY” label. - For equipment which calibration setting can be adjusted, shall be appropriately protected against accidental tempering of the setting (e.g. stored under lock-up, or sealed at the setting).
- Production Manager
- For acceptable calibrated equipment, release for use. - For unacceptable calibrated equipment, quarantine it and identify the remedy to either repair or replace the equipment.
- Production Manager
- To re-inspect the affected product measured using the ‘out of calibration’ equipment. - The inspection results shall be recorded. - Determine further action.
• Scrap • Buy new equipment • Use as it with correction factor
defined.
- Production Manager
Verify calibration results
Disposition after calibration
Out of calibration control
Send equipment for calibration
Continued from previous page
CSL TECHNOLOGIES (M) SDN BHD LRC TECH (M) SDN BHD
Ref. No. CS-P02 Revision No. 00
EQUIPMENT MAINTENANCE AND CALIBRATION PROCEDURE
Effective Date 01/11/2010 Page 5 of 5
THIS IS AN UNCONTROLLED COPY OF A CONTROLLED DOCUMENT PRINTED
4.2 PREVENTIVE MAINTENANCE
Process Flow Description Documents / Ref.
Personnel
- Maintain the Machine Maintenance List, update as necessary. - Prepare Preventive Maintenance Schedule for each machine. - The due for maintenance are refer to the manual book that be given by machine supplier.
- Machine Maintenance List (CS-F34)
- Production Supervisor
- Conduct Preventive Maintenance according to schedule. - Refer to the relevant machine Maintenance Plan.
- Machine Maintenance Record (CS-F33)
- Production Supervisor
- Clean the machine after use.
- User
4.3 BREAKDOWN MAINTENANCE
Process Flow Description Documents / Ref.
Personnel
- Inform Production Manager regarding the machine breakdown. - Production Manager shall arrange technician for breakdown maintenance.
- Production Manager
- Conduct problem shooting and repair the machine. - Record the maintenance results in the machine maintenance log book.
- Machine maintenance log book
- Production Supervisor
- In case of major breakdown that cannot be solved internally, Production Manager shall contact the relevant machine vendor for service. - File the vendor service records.
- Vendor service record
- Production Manager
Conduct Breakdown Maintenance
Machine Breakdown
Vendor Service
Conduct Preventive Maintenance
Preventive Maintenance
Schedule
Machine Cleanliness