73
Creating a project plan URBS 609 Project, Unit 3

Creating a project plan URBS 609 Project, Unit 3

Embed Size (px)

Citation preview

Page 1: Creating a project plan URBS 609 Project, Unit 3

Creating a project plan

URBS 609 Project, Unit 3

Page 2: Creating a project plan URBS 609 Project, Unit 3

This training module was crafted using PowerPoint by Microsoft Corporation. It has been packaged with PowerPoint Viewer, a standalone Microsoft product that allows a user to view this module without use of PowerPoint.

Urban and Regional Studies Institute 2

Left mouse-click or enter to go to next slideLeft mouse-click or enter to go to next slide Right mouse-click or backspace to go to previous Right mouse-click or backspace to go to previous slideslide ESC to exit this moduleESC to exit this module

This Unit of Instruction was crafted by Robert Hugg For Minnesota State University, Mankato Urban and Regional Studies Institute - 2004

Page 3: Creating a project plan URBS 609 Project, Unit 3

This module will provide: Introduction to laying out most commonly

used project fields, for easiest data entry Introduction to configuring MS Project in a

typical layout tools, displaying typically needed data

Step-by-step creation of a simple sample project

This module is constructed as the third of three blocks in a building block approach

Urban and Regional Studies Institute 3

Page 4: Creating a project plan URBS 609 Project, Unit 3

Be prepared before using MS Project Have the required building blocks defined

Identify a clear project goal Identify tasks, resources, requirements,

limitations Identify relationships between tasks

Constraints and Dependencies Identify a defined sequence for tasks

Like any tool, MS Project cannot define the goal of a project, the user must do that

Urban and Regional Studies Institute 4

Page 5: Creating a project plan URBS 609 Project, Unit 3

Start by adding the Project Guide and desired toolbars (refer to the previous unit for info)

Next, configure the WBS (Tasks Lists) fields to reflect the information desired

The default configuration contains 7 columns (fields) that show typical information Indicators, task name, duration Start, finish, predecessors, resource names

Column positions can be changed by dragging a column left or right (just like in MS Excel)

Urban and Regional Studies Institute 5

Customizing the Layout

Page 6: Creating a project plan URBS 609 Project, Unit 3

Right mouse click when in the task area to bring up a submenu

Urban and Regional Studies Institute 6

Select Insert Column

Customizing the Layout

Page 7: Creating a project plan URBS 609 Project, Unit 3

A dialogue box will appear providing a wide range of choices to add information… Scroll to “Cost” and select it

Urban and Regional Studies Institute 7

A cost column has been added

Customizing the Layout

Page 8: Creating a project plan URBS 609 Project, Unit 3

Repeat this process adding these columns Critical, % Complete, Total Slack

Urban and Regional Studies Institute 8

Customizing the Layout

Each column has hints, tips and detailed instructions that are accessible by rolling the mouse over the column header

Page 9: Creating a project plan URBS 609 Project, Unit 3

Drag and drop columns for layout according to personal preference…

Urban and Regional Studies Institute 9

Customizing the Layout

Page 10: Creating a project plan URBS 609 Project, Unit 3

Next, set customized display settings

Urban and Regional Studies Institute 10

Customizing the Display Settings

Tools Menu, Options… Use the tabs….

Page 11: Creating a project plan URBS 609 Project, Unit 3

For this project use the default settings on The schedule and calendar tabs The edit, view, and calculation tabs

It is best to use the default settings until a higher degree of comfort is achieved

Once customized, these settings can be set as default to reduce setup time

Urban and Regional Studies Institute 11

Customizing the Display Settings

Page 12: Creating a project plan URBS 609 Project, Unit 3

Open the PERT Entry Sheet

Use the same “Insert column” techniques to add the same columns…

Urban and Regional Studies Institute 12

Customizing the PERT Entry Sheet

Page 13: Creating a project plan URBS 609 Project, Unit 3

The result will be the PERT Entry Sheet plus the other columns from the task list

This is not required but saves work later…

Urban and Regional Studies Institute 13

Customizing the PERT Entry Sheet

Mouse-over help/hints and tips are available in all views

Page 14: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 14

Building a Sample ProjectBuilding a Sample Project

• Customize the display for best resultsCustomize the display for best results

• Use the default setting or add personal Use the default setting or add personal touchestouches

• Switch from Switch from PERT Entry SheetPERT Entry Sheet view to view to Gantt ViewGantt View

Customizing Gantt Chart Display

Page 15: Creating a project plan URBS 609 Project, Unit 3

Invoke the Gantt Chart Wizard… Can only be accessed in Gantt and Tracking

Gantt views…

Urban and Regional Studies Institute 15

Building a Sample ProjectBuilding a Sample Project Customizing Gantt Chart Display

Page 16: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 16

Building a Sample ProjectBuilding a Sample Project

• Select Critical Path, this will automatically Select Critical Path, this will automatically calculate and display the critical pathcalculate and display the critical path

• Critical path is displayed in Critical path is displayed in REDRED

Customizing Gantt Chart Display

Page 17: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 17

Building a Sample Project Building a Sample Project

• Select the type of data to be displayed on Select the type of data to be displayed on the Gantt the Gantt

• For this project, select custom task For this project, select custom task informationinformation

Customizing Gantt Chart Display

Page 18: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 18

Building a Sample ProjectBuilding a Sample Project

• A Simple visual display provides easy A Simple visual display provides easy status reporting…status reporting…

Customizing Gantt Chart Display

Page 19: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 19

Building a Sample ProjectBuilding a Sample Project

• Showing dependencies between tasks is a Showing dependencies between tasks is a great way to pinpoint relationships and great way to pinpoint relationships and potential conflicts potential conflicts

Customizing Gantt Chart Display

Critical Link

Non-critical link

Page 20: Creating a project plan URBS 609 Project, Unit 3

This format will be applied to all projects until it is changed…

Urban and Regional Studies Institute 20

Building a Sample ProjectBuilding a Sample Project Customizing Gantt Chart Display

Page 21: Creating a project plan URBS 609 Project, Unit 3

Critical tasks and links are always displayed in RED

Non Critical tasks and links are displayed in blue, or another color the user prefers

Formats can be changed at any time during project planning or management but… Settle on a simple display that works best KISS (Keep It Simple Son)

Urban and Regional Studies Institute 21

Building a Sample ProjectBuilding a Sample ProjectAbout the Gantt Chart Display

Sample Gantt

Page 22: Creating a project plan URBS 609 Project, Unit 3

One task remains before entering data Set the project information

Urban and Regional Studies Institute 22

Building a Sample ProjectBuilding a Sample ProjectSetting the Project Information

OR

For the sample project, set the start date to

6/29/04

Page 23: Creating a project plan URBS 609 Project, Unit 3

Set working times by using the Task Wizard or accessing the menu For this project use the default settings in the

Wizard

Urban and Regional Studies Institute 23

Building a Sample ProjectBuilding a Sample ProjectSet Working Times

Page 24: Creating a project plan URBS 609 Project, Unit 3

Follow the steps in the wizard…

Urban and Regional Studies Institute 24

Building a Sample ProjectBuilding a Sample ProjectSet Working Times

Page 25: Creating a project plan URBS 609 Project, Unit 3

Tasks can be entered using the wizard, through the Gantt view task list or the PERT Entry sheet

Urban and Regional Studies Institute 25

Building a Sample ProjectBuilding a Sample ProjectEnter Tasks

Page 26: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 26

Building a Sample ProjectBuilding a Sample Project

• Entering data through the PERT Entry Entering data through the PERT Entry Sheet saves time…enter data only once for Sheet saves time…enter data only once for several usesseveral uses– Enter data before PERT analysis is conductedEnter data before PERT analysis is conducted– It will also populate the task dialogue boxes It will also populate the task dialogue boxes – It will also populate the Gantt Task ListIt will also populate the Gantt Task List

• To begin, enter the task names and To begin, enter the task names and durationsdurations– Enter Enter onlyonly Optimistic, pessimistic & expected Optimistic, pessimistic & expected

durationsdurations– PERT analysis will populate the PERT analysis will populate the duration duration fieldfield

Enter Tasks

Page 27: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 27

Building a Sample ProjectBuilding a Sample Project

• For this sample project enter these tasks:For this sample project enter these tasks:

Enter Tasks

TASK Optimistic Duration Expected Duration Pessimistic Duration

Foundation 1 week1 week 2 weeks2 weeks 3 weeks3 weeksFraming 2 weeks2 weeks 4 weeks4 weeks 7 weeks7 weeksRoof 1 week1 week 2 weeks2 weeks 3 weeks3 weeksElectrical 1 week1 week 2 weeks2 weeks 3 weeks3 weeksSheetrock 1 week1 week 3 weeks3 weeks 5 weeks5 weeksInterior Paint 1 week1 week 2 weeks2 weeks 4 weeks4 weeksExterior Paint 1 week1 week 2 weeks2 weeks 3 weeks3 weeksLandscaping 1 week1 week 2 weeks2 weeks 4 weeks4 weeks

Page 28: Creating a project plan URBS 609 Project, Unit 3

The PERT Entry Sheet Should look like this Notice all tasks begin and end on the same day

PERT Analysis has not been completed Notice all tasks appear to be critical…

Task Dependencies have not yet been identified

Urban and Regional Studies Institute 28

Building a Sample ProjectBuilding a Sample ProjectEnter Tasks

Page 29: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 29

Building a Sample ProjectBuilding a Sample Project

• Identify which tasks must finish before Identify which tasks must finish before others can begin – others can begin – a task dependencya task dependency– Foundation must finish before framing beginsFoundation must finish before framing begins– Highlight both tasks and click the link iconHighlight both tasks and click the link icon

Identify Task Dependencies

Page 30: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 30

Building a Sample ProjectBuilding a Sample Project

• By identifying 1 dependency the plan has By identifying 1 dependency the plan has changed…changed…– Start and end dates, critical task statusStart and end dates, critical task status– 1 predecessor has been set – task 1 precedes 1 predecessor has been set – task 1 precedes

tasks 2tasks 2

Identify Task Dependencies

Page 31: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 31

Building a Sample ProjectBuilding a Sample Project

• This can also be accomplished by using the This can also be accomplished by using the Task Information submenu (right mouse Task Information submenu (right mouse click)click)

Identify Task Dependencies

Page 32: Creating a project plan URBS 609 Project, Unit 3

Using this same technique, identify and set the other dependencies The roof is dependant on completion of the framing Electrical is dependant on completion of the framing Sheetrock is dependant on completion of the electrical Interior paint is dependant on completion of the sheetrock Exterior paint is dependant on completion of the framing Landscaping is dependant on completion of the exterior painting

Take a moment to think through the logic of these dependencies – this is a critical part of planning a project

Hint: highlight multiple tasks by using ctrl and clicking on link icon

Note: Tasks may be dependant on more than 1 other task

Urban and Regional Studies Institute 32

Building a Sample ProjectBuilding a Sample ProjectIdentify Task Dependencies

Page 33: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 33

Building a Sample ProjectBuilding a Sample Project

• Notice how much the plan has changed Notice how much the plan has changed and the PERT Analysis has not even been and the PERT Analysis has not even been completedcompleted– Critical tasks and dependencies have been Critical tasks and dependencies have been

identifiedidentified– Start and finish dates have been identifiedStart and finish dates have been identified

Identify Task Dependencies

Page 34: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 34

Building a Sample ProjectBuilding a Sample Project

• All task information has been All task information has been entered, it is time to complete the entered, it is time to complete the PERT AnalysisPERT Analysis

• Press the Calculate PERT iconPress the Calculate PERT icon

• Click “Yes” on option boxesClick “Yes” on option boxes– MS Project calculates dates and MS Project calculates dates and

durations…durations…

Completing the PERT Analysis

Page 35: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 35

Building a Sample ProjectBuilding a Sample Project

• Use these durations and critical Use these durations and critical task/path designations for the PERT task/path designations for the PERT Risk AnalysisRisk Analysis

Completing the PERT Analysis

Page 36: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 36

Building a Sample ProjectBuilding a Sample Project

• By navigating through the By navigating through the viewview menu, a menu, a variety of charts and graphs display the variety of charts and graphs display the planplan– Note: cost and resource info has not yet been Note: cost and resource info has not yet been

addedadded– The critical path has automatically been The critical path has automatically been

identified in identified in REDRED, as have the critical tasks, as have the critical tasks

• The Gantt charts and network diagram The Gantt charts and network diagram display the PERT Analysis data, not the display the PERT Analysis data, not the user provided estimatesuser provided estimates

• SaveSave the project and explore the views! the project and explore the views!

Explore the other views after the PERT Analysis is complete

Page 37: Creating a project plan URBS 609 Project, Unit 3

Gantt Chart view Notice the critical path in red?

Urban and Regional Studies Institute 37

Building a Sample ProjectBuilding a Sample ProjectExplore the other views after the PERT Analysis is

complete

Page 38: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 38

Building a Sample ProjectBuilding a Sample Project

• Network DiagramNetwork Diagram

• Notice the Notice the Critical PathCritical Path in in RedRed? The ? The Critical Critical TasksTasks in in RedRed and non-critical tasks in and non-critical tasks in blueblue??– MS Project calculates dates and durations…MS Project calculates dates and durations…

Explore the other views after the PERT Analysis is complete

Page 39: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 39

Building a Sample ProjectBuilding a Sample Project

• Calendar viewCalendar view… an easy-to-read planning … an easy-to-read planning calendarcalendar

Explore the other views after the PERT Analysis is complete

(Extract of the calendar view)

Page 40: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 40

Building a Sample ProjectBuilding a Sample Project

• Other views include tracking, optimistic, Other views include tracking, optimistic, and pessimistic Gantt charts…(under and pessimistic Gantt charts…(under more more viewsviews tab) tab)– Note: do not reformat the pessimistic and Note: do not reformat the pessimistic and

optimistic Gantt views, the dates will be alteredoptimistic Gantt views, the dates will be altered

Explore the other views after the PERT Analysis is complete

Tracking Gantt

Page 41: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 41

Building a Sample ProjectBuilding a Sample ProjectExplore the other views after the PERT Analysis is

complete

Pessimistic Gantt

Optimistic Gantt

Page 42: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 42

Building a Sample ProjectBuilding a Sample Project

• Next, build a resource listNext, build a resource list– A list of people and equipment needed for the A list of people and equipment needed for the

projectproject– Use either the wizard or the resource sheet Use either the wizard or the resource sheet

viewview

Building a Resource List

Page 43: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 43

Building a Sample ProjectBuilding a Sample Project

• For this project use the following For this project use the following information:information:– PaintersPainters

• Ben Johnson, $10/hr, OT $15/hr Ben Johnson, $10/hr, OT $15/hr

• Amy Wilson, $17.50/hr, OT $25/hrAmy Wilson, $17.50/hr, OT $25/hr– LandscapersLandscapers

• Adam Stevens, $20/hr, OT $30/hrAdam Stevens, $20/hr, OT $30/hr

• Jill Morris, $25/hr, OT $35/hrJill Morris, $25/hr, OT $35/hr

• Contracted Equipment/workersContracted Equipment/workers– Concrete crew, $15/hr, OT $25/hrConcrete crew, $15/hr, OT $25/hr– Framers and Roofers crews, $10/hr, OT $20/hrFramers and Roofers crews, $10/hr, OT $20/hr– Electrician, $40/hr, OT $60/hrElectrician, $40/hr, OT $60/hr

Building a Resource List

Page 44: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 44

Building a Sample ProjectBuilding a Sample Project

• The resource sheet should look like this:The resource sheet should look like this:

Building a Resource List

Page 45: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 45

Building a Sample ProjectBuilding a Sample Project

• Assign resources to tasks by any of several Assign resources to tasks by any of several methods:methods:– In the In the Task Information boxTask Information box– In theIn the task list task list area (WBS)area (WBS)– In the PERT Entry SheetIn the PERT Entry Sheet– Through the WizardThrough the Wizard

Assigning Resources to the tasks

Page 46: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 46

Building a Sample ProjectBuilding a Sample Project

• For this project, 100% of the resource time For this project, 100% of the resource time is available, if it needs to be changed, do is available, if it needs to be changed, do so through the so through the resource sheetresource sheet view view

Assigning Resources to the tasks

Page 47: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 47

Building a Sample ProjectBuilding a Sample Project

• Assign tasks as follows:Assign tasks as follows:

Assigning Resources to the tasks

Page 48: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 48

Building a Sample ProjectBuilding a Sample Project

• As assignments are made, MS Project As assignments are made, MS Project calculates the costs…calculates the costs…

• All required entries and calculations are All required entries and calculations are done…save the project!done…save the project!

Assigning Resources to the tasks

Page 49: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 49

Building a Sample ProjectBuilding a Sample Project

• Checking the project statistics yields a Checking the project statistics yields a snapshot of costs and timessnapshot of costs and times

Check the Project Statistics

Page 50: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 50

Building a Sample ProjectBuilding a Sample Project

• Saving a project baseline allows a user to Saving a project baseline allows a user to track progress and compare project track progress and compare project expectationsexpectations– Compare estimates against actual durations, Compare estimates against actual durations,

costs etccosts etc

Saving a Project Baseline

Page 51: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 51

Building a Sample ProjectBuilding a Sample Project

• A User can save up to 11 baselines in MS A User can save up to 11 baselines in MS ProjectProject

• Very useful for situations where:Very useful for situations where:– New tasks are addedNew tasks are added– The scope of the project changesThe scope of the project changes– Unexpected delays occurUnexpected delays occur– The project is crashedThe project is crashed– The project is relaxedThe project is relaxed

• Save each baseline as a new number using Save each baseline as a new number using the scroll down menu in the save baseline the scroll down menu in the save baseline areaarea

Saving a Project Baseline

Page 52: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 52

Building a Sample ProjectBuilding a Sample Project

• The project is functional and complete but The project is functional and complete but adding a few extra touches gives it adding a few extra touches gives it structurestructure

• Add a top level task that serves as a title Add a top level task that serves as a title and project overviewand project overview

Adding A Few Personalized Touches

•Indent all subsequent tasks

• Do not assign resources

• Marked critical

•But is Not critical for PERT Risk analysis purposes

Page 53: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 53

Building a Sample ProjectBuilding a Sample Project

• Add a milestone that serves as project Add a milestone that serves as project closureclosure

Adding A Few Personalized Touches

•Link to all other physical tasks

•Mark dependencies as FF (Finish to Finish) in Task Info Tab

• Do not assign resources

• Marked critical

•But is Not critical for PERT Risk analysis purposes

Page 54: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 54

Building a Sample ProjectBuilding a Sample Project

• Adjust Fonts for personal preferenceAdjust Fonts for personal preference

Adding A Few Personalized Touches

Page 55: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 55

Building a Sample ProjectBuilding a Sample Project

• Divide tasks into phasesDivide tasks into phases– Useful for large or complex projectsUseful for large or complex projects– Does not change project Does not change project

costs/duration/integritycosts/duration/integrity– Useful where functional use can be derived Useful where functional use can be derived

from completed tasks where project is from completed tasks where project is completed in phasescompleted in phases

Adding A Few Personalized Touches

Page 56: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 56

Building a Sample ProjectBuilding a Sample Project

• The result is a professional, highly visual The result is a professional, highly visual planplan

Adding A Few Personalized Touches

Page 57: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 57

Updating a Sample ProjectUpdating a Sample Project

• Updating a project is simple if a few basic Updating a project is simple if a few basic rules are rememberedrules are remembered– Update the % complete Update the % complete andand the date the work the date the work

is is donedone• Otherwise MS Project assumes the date the task is Otherwise MS Project assumes the date the task is

competed is the date the task was scheduled to be competed is the date the task was scheduled to be completedcompleted

– Enter a finish date Enter a finish date onlyonly when the task is when the task is finishedfinished

– Enter a % complete (when work is in progress Enter a % complete (when work is in progress but not complete) so MS Project can track and but not complete) so MS Project can track and forecast task and project completionforecast task and project completion

Updating a Project

Page 58: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 58

Building a Sample ProjectBuilding a Sample Project

• Updates can be made on Gantt view Updates can be made on Gantt view Task Task ListList (WBS) view or in the (WBS) view or in the Task Information Task Information TabTab

Assigning Resources to the tasks

Task Information Tab

Gantt view Task List

Page 59: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 59

Managing a Sample ProjectManaging a Sample Project

• Simple reports can help all concerned stay Simple reports can help all concerned stay in touch with a projectin touch with a project– Go to Go to ReportsReports on the View menu for a wide on the View menu for a wide

range of wizard driven reports – or create a range of wizard driven reports – or create a custom report!custom report!

Reports and graphs

Page 60: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 60

Managing a Sample ProjectManaging a Sample Project

• Budget overviews…Budget overviews…

Budget Reports

And budget reports that show under and over budget tasks and resources…

Page 61: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 61

Managing a Sample ProjectManaging a Sample ProjectCross tabs

Page 62: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 62

Managing a Sample ProjectManaging a Sample Project

• Projects can be crashed using MS ProjectProjects can be crashed using MS Project– Add extra resources to the resource list and Add extra resources to the resource list and

assign them to tasks to shorten project duration assign them to tasks to shorten project duration and/orand/or

– Assign existing resources overtime (OT) workAssign existing resources overtime (OT) work– To assign overtime, insert 2 new columns in the To assign overtime, insert 2 new columns in the

Task Usage View and add OT as appropriateTask Usage View and add OT as appropriate

Crashing a Project

Page 63: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 63

Managing a Sample ProjectManaging a Sample Project

• Projects can be crashed using MS ProjectProjects can be crashed using MS Project– Crash projects with caution – it is a disruptive Crash projects with caution – it is a disruptive

actionaction

• Do a Do a what ifwhat if crashing exercise and save crashing exercise and save the baseline separately, keeping the the baseline separately, keeping the original project intact – allows exploration original project intact – allows exploration without riskwithout risk– Compute crash savings and costs – how much Compute crash savings and costs – how much

time will be saved and how many extra $ it will time will be saved and how many extra $ it will costcost• Refer to early instruction units for these techniques Refer to early instruction units for these techniques oror

• Examine variances between baseline in MS ProjectExamine variances between baseline in MS Project

Crashing a Project

Page 64: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 64

Managing a Sample ProjectManaging a Sample Project

• Project will update the costs and changed Project will update the costs and changed durations accordinglydurations accordingly

• Remember – effort required to complete a Remember – effort required to complete a task/project remains fixed, only duration task/project remains fixed, only duration changeschanges

• Save the baseline of a crashed project to Save the baseline of a crashed project to compare against original estimates and compare against original estimates and expectationsexpectations

• Be sure to check critical tasks status; non-Be sure to check critical tasks status; non-critical tasks may become critical after critical tasks may become critical after crashingcrashing

Crashing a Project

Page 65: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 65

Managing a Sample ProjectManaging a Sample Project

• MS Project does not MS Project does not – Compute probability of on-time completionCompute probability of on-time completion

• Do this using the Excel PERT CalculatorDo this using the Excel PERT Calculator– Refer to previous instruction for this techniqueRefer to previous instruction for this technique

What MS Project does not do

For this project, there is a 39.64% probability of completing the project within 13 weeks (the PERT likely duration)…

Page 66: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 66

Managing a Sample ProjectManaging a Sample ProjectWhat MS Project does not do

… a 90.54% probability of completing the project within 15 weeks…

INCLUDE ONLY CRITICAL TASKS IN PERT RISK ANALYSIS

Page 67: Creating a project plan URBS 609 Project, Unit 3

Urban and Regional Studies Institute 67

Managing a Sample ProjectManaging a Sample ProjectWhat MS Project does not do

…but only a 3.30% probability of completing the project within 11 weeks.

INCLUDE ONLY CRITICAL TASKS IN PERT RISK ANALYSIS

Page 68: Creating a project plan URBS 609 Project, Unit 3

A strong tool that saves time Makes tracking project status easy Makes communicating project status easy Be prepared before beginning Use the program resources for assistance

Wizards, guides and help function Save the project data often (in 2 places)

Urban and Regional Studies Institute 68

MS ProjectMS ProjectReview and Final Thoughts

Page 69: Creating a project plan URBS 609 Project, Unit 3

KISS (Keep It Simple Son) Stay in touch with the project If the plan doesn’t seem right it probably

isn’t – track down suspected discrepancies

Practice makes perfect MS Project get easier to use with practice Start with default settings and then

customize

Urban and Regional Studies Institute 69

MS ProjectMS ProjectReview and Final Thoughts

Page 70: Creating a project plan URBS 609 Project, Unit 3

MS Project automatically Identifies Critical tasks & the Critical Path

(in RED) Computes Late/Early start and finish dates Computes Total Slack (A.K.A Total Float)

Critical tasks will always have ZERO Total Slack Effort to complete a task is fixed

Duration changes by adding or subtracting resources; more resources = less duration

Urban and Regional Studies Institute 70

MS ProjectMS ProjectReview and Final Thoughts

Page 71: Creating a project plan URBS 609 Project, Unit 3

Even the best plan is still an estimate A plan is only as good as the data it uses

Bad estimates = bad plans Risk Analysis must be computed separately

Construct and use an Excel-based PERT Risk Calculator MS Project is just a tool, the manager owns the

project and is responsible for its health Communicate status frequently and clearly

Urban and Regional Studies Institute 71

MS ProjectMS ProjectReview and Final Thoughts

Page 72: Creating a project plan URBS 609 Project, Unit 3

Dr. Anthony Filipovitch MS Project, by Microsoft Corporation MS Excel, by Microsoft Corporation PM Body of Knowledge (PMBOK),

Philadelphia: PMI, 2000

Urban and Regional Studies Institute 72

Page 73: Creating a project plan URBS 609 Project, Unit 3

You have completed

URBS 609 Project Unit 3

Please proceed to

URBS 609

Project Management Assignment

Urban and Regional Studies Institute 73

This Unit of Instruction was crafted by Robert Hugg For Minnesota State University, Mankato Urban and Regional Studies Institute - 2004