CPMKL: 2010, Q1 GSTS Action Planning Cleanliness of Common Areas of Hotel
Key Priorities Root Causes Actions Action By Target
Completion
Date
Actual
Completi
on Date
Status Remarks
Public toilets repair and maintenance
(Public toilets at Lobby, Planters Inn, Lower Lobby, Mezzanine & Windows on KL)
Cleanliness of public toilet
No expertise and follow ups (no monitoring and working without deadline) to ensure defects being rectified.
Cleanliness of public toilets during meetings and functions is slacking due to poor planning to man the toilets resulting complaints.
Set up minimum stock of spare parts (with long lead time to obtain) and to maintain proper inventory. Stock keeping to be carried out by engineering clerk and supervised by Chief / Assistant Engineer
To highlight any challenges in daily operation meeting and weekly quality meeting.
To plan manning based on BEO and to have staff on standby during every break (tea break, lunch & evening tea break).
Cleanliness of public toilets will be constantly checked by PA Senior Supervisor and Executive Housekeeper
Anselm
Prakash
30th June
Immediate
2
CPMKL: 2010, Q1 GSTS Action Planning Cleanliness of Common Areas of Hotel
Key Priorities Root Causes Actions Action By Target
Completion
Date
Actual
Completi
on Date
Status Remarks
Cleanliness of public toilet
Present dustbins are ash bins and not suitable for public toilets causing littering in the toilet
To change present ash bin as they are not suitable to throw paper towels and other debris. To source for bin that come with top opening.
Prakash 30th June
3
CPMKL: 2010, Q1 GSTS Action Planning Cleanliness of Common Areas of Hotel
Key Priorities Root Causes Actions Action By Target
Completion
Date
Actual
Completi
on Date
Status Remarks
Cleanliness of guest lifts
Guest floor corridor carpet
Unpleasant smell resulted from busy operations hours (morning & evening) and during group check in
Poor supervision on monitoring guest floor corridor (level 6-28) carpet
To source and install proper air freshener dispenser in all guest lifts in order to eliminate bad smell.
To train supervisors on minimum standard based on SOP. Executive / Assistant Housekeeper to audit cleanliness daily.
Prakash
Prakash
Winnie
15th June
Immediate
4
CPMKL: 2010, Q1 GSTS Action Planning Cleanliness of Common Areas of Hotel
Key PrioritiesP Root Causes Actions Action By Target
Completio
n Date
Actual
Completi
on Date
Status Remarks
Appearance of hotel external compound
Lack of supervision on external landscape contractors
Periodic thorough cleaning cycle too long (6 months) resulting fungus and mildew build up along the driveway from entrance to lower lobby and main lobby including dirty driveway walls and edges.
To work with AML (landscape contractor) to clear dry plants and over grown trees at main entrance. To clean up the bushy area close to entrance car park. AML to cover gaps along the driveway planter by adding in more colorful plants. Weekly trimming of plants and daily clearing of dry leafs.
To review the current schedule of half yearly project cleaning to quarterly due to our tropical climate. Iincrease 2 man power to carry out this project as it will take approximately 10 days to complete the hotel compound.
Prakash/Mus
Mus
30th June
25th June