CPE 12016 IOM 1900(Draft1)Vacation Updated

  • Upload
    mhaise7

  • View
    224

  • Download
    1

Embed Size (px)

DESCRIPTION

Process

Citation preview

OPERATING PROCEDURES

Custom Process Equipment, LLC4727 NW Evangeline ThwyCarencro, LA 70520Tel 337-896-3815

Fax 337-896-3816

www.cpe-llc.comINSTALLATION AND OPERATIONS MANUAL

INCLUDEPICTURE "cid:[email protected]" \* MERGEFORMATINET

INSTALLATION, COMMISSIONING, AND OPERATING PROCEDURES

FOR

Khurmala Dome

Amine Contactor & Regeneration Section

Amine I, Gas Treatment Plant2013INDEX

SAFETY STATEMENT

BASIC COMPONENTS

SECTION I

INSTALLATION

SECTION II

OPERATION

SECTION III

START-UP & SHUTDOWN PROCEDURES

SECTION IV

MAINTENANCE

SECTION V

TROUBLESHOOTING

SECTION VI

DESIGN BASIS

SECTION VII

DocumentDoc. No.

P & ID12016-CPE-KAR AMINE #1- P&ID

Package GA DrawingsTROY to fill out

Cause & EffectTroy to fill out

Process Engineers Data BookCPE-12016-PED-1901

OPERATING PROCEDURESPRIVATE

******************************************************************************

WARNING - DANGER

EXPLOSIVE/HAZARDOUS GASES AND LIQUID******************************************************************************

Work being performed on this equipment may expose you to conditions, which can be hazardous and dangerous, as this equipment or area may contain explosive, flammable or toxic gasses or liquids. Keep all open flames at least 180 feet away.

This equipment must be serviced and operated by properly trained and qualified personnel only.

Do not clean, service, repair, or attempt to perform any work without relieving pressure and purging combustibles.

Check for unsafe conditions, and follow your company's safety practices any time work is performed on this equipment.

If you have any questions, contact CPE prior to performing any work on these units.

SECTION I

1.0BASIC COMPONENTS OF AN AMINE SWEETENING/REGENERATION SYSTEM1.1Contactor (646-V-0101) & Inlet Scrubber (646-S-0101). The contactor is a vertical tower with 20 2-pass BDH trays and the inlet scrubber is a two phase vertical separator with vertical vane pack. Please refer to drawings to see the contactor tower and inlet scrubber.

1.2Heat Exchangers. Rich/Lean Amine heat exchanger supplied is a plate and frame (646-E-0101). The Amine Thermosiphon Reboiler (646-E-0102) is a shell and tube type BEM T.E.M.A class C heat exchanger. The overhead reflux condenser (646-A-0101) and lean amine coolers (646-A-0102A/B) are all forced draft coil type exchangers.1.3Amine Booster, Amine Recirculation & Reflux Pumps (646-P-0102A/B, 646-P-0103A/B/C & 646-P-0101A/B respectively). The two by 100% capacity Booster pumps are electric motor driven centrifugal pumps, one in operation and one in standby. The three by 50% capacity amine recirculation pumps are variable speed electric motor driven positive displacement pumps, two in operation and one in standby. The two by 100% capacity reflux pumps are electric motor driven centrifugal pumps, one in operation and one in standby.1.4Still Column (646-V-0102). This column is a free standing unit with thermosiphon reboiler (646-E-0102) mounted directly to the vessels side wall. The column is randomly packed in two sections, top (3)/bottom (23) both sections have Nutter RingTM #1.5 packing and fluid distributors. See drawing for details. The towers sump serves as the amine surge volume. 1.5Reflux Accumulator (646-S-0103) & Reflux Condenser (646-A-0101). The condenser is forced draft with automatic temperature controlling louvers. The reflux accumulator is a vertical two phase separator with removable mist extractor.1.6Hot Oil System: Expansion Tank (646-T-0101), Hot Oil Circulation Pumps (646-P-0104A/B/C) & Direct Fired Heater (646-H-0101). This system supplies a continuous stream of hot oil (therminal 55) to the shell side of the still columns thermosiphon reboiler. This sub system is a self-contained heat media loop was provided by a third party and more information can be found in the hot oil systems installation and operating manual. 1.7Amine Flash Separator (646-S-0102). The amine flash separator is a three phase bucket and weir type separator used to remove a substantial portion of the acid gas liberated from pressure reduction taken by the amine solution during the regeneration process. This vessel also helps to separate and remove any liquid hydrocarbons which may have condensed from the natural gas flowing through the contactor. Excess liquid hydrocarbons carried over to the still column with the amine solution may lead to erratic column behavior, foaming, and premature fouling in the lean/rich amine exchanger, reboiler, and column internals with marked decreases in overall system efficiency. The levels are controlled by the bucket and weir heights in conjunction with displacer type level controls.

1.8Lean Amine Particulate Filter (646-S-0104). This is a cartridge type filter that removes solids from the amine.

1.9Lean Amine Carbon Filter (646-S-0105). This is a 10 % side streamed activated carbon filter which aids in the removal of organic contaminants and dissolved hydrocarbons from the amine.

2.0Lean Amine Polishing Filter (646-S-0106). This is a 10% side streamed fine particulate filter and removes fine particles which may carry over from the charcoal filter and/or accumulate in the amine solution over time. SECTION II

2.0INSTALLATION

The proper installation of the gas sweetening and amine regeneration system is imperative for successful operation. The equipment must be installed level.

2.1Installation Instructionsa)Remove all shipping braces, flange covers and protective guards. Inventory all parts.

b)Visually check the vessels, the couplings, nozzles, vessel shells and accessory items to see that none have been damaged during shipment. Report any damage as soon as possible.

c)Reinstall all components that were disassembled for shipment. Refer to Package GA Drawings for details as well as the packing list provided with shipment. Be sure that the still column contains pall ring saddles that may have been shipped loose. Check level and alignment of the vessels. If the contactors structured packing has been removed for shipment, it should be reinstalled. The filter elements must be installed in the lean amine stream downstream of the lean amine coolers and upstream of the amine circulation pumps. Ensure all pumps are properly lubricated. Please refer to Pumps section of this manual for more details on installation, operation and maintenance of these pumps.

d)Install ladders and walkway, which were removed using bolts and grating clips. Also install vessel accessories, and all piping items that were removed for shipment.

e)Check that all vessel accessories such as pressure gauges, gauge glasses, relief valves, etc., are installed in proper location. Refer to the drawings for nozzle locations, dimensions and general description. In addition, you may refer to vendor literature.

f)Check all instrument tubing for flattened areas or kinks. Repair or replace before start-up.

g)Purge all instrument lines and start admitting instrument air to the system. Check all instruments for proper operation and stroke all control valves and shutdown valves. Be sure that all control valves move freely and fail in the proper position.

h)Perform complete loop checks on all instruments and the entire safety logic. The loop check procedure is of critical importance and further steps of commissioning cannot proceed until this step is totally completed.

i) After completion of the "Loop Checks", a piping system hydro flushing is recommended. The initial flushing shall be carried out prior to leak testing. For austenitic steelwork flushing can be performed after pressure testing. Items of equipment that are sensitive to damage during hydro flushing, shall be removed, blocked off or isolated. Ball valves shall be flushed in fully open position. All piping systems shall be flushed using high pressure jet flushing equipment, such as rotating hose or rotating nozzle. Water velocity shall be a minimum of l0 m/s. On systems where high pressure jet flushing cannot be used due to complicated shapes and/or long runs HVWF may be used. The flushing medium shall in general be fresh water. When flushing stainless steel lines, the chloride ion content shall be less than 200ppm.

j)After completion of hydro flushing, a complete pressure (i.e., leak) test of all of the equipment should be performed. We suggest nitrogen should be used and all equipment should be brought to 95% of design pressure, slowly, checking all areas for leaks.

k)IMPORTANT: Refer to filter and pump sections of this manual for detailed installation and pre-commissioning checks which must be performed on these items.

l)Calibrate all instrumentation and set levels in accordance with alarm summaries.

m)Fill Procedure:

Before adding the amine solution or wash fluid, check all openings, man ways, gauge cocks, etc. in reboiler, pumps, filters, flash separator, contact tower air coolers, lean rich exchanger, still column, reflux pumps and reflux accumulator making sure they are secured by plugs or valves and are tight. Initial amine charge or wash fluid fill is to be put into the still column sump via the water makeup line. Have the operation management team prepare a valve close/open check list utilizing the as-installed and walked through P&ID during initial wash water fill before connecting the sour gas feed. 1. Check that drain valves are closed2. Open all control valve bypass lines3. Vent contact tower, flash separator, still column and/or reflux accumulator4. Check for acid gas leaking through vents

5. Bypass filters

6. Bypass main circulation pumps7. Close reflux accumulator level control valve and bypass The reflux accumulator should be filled separately and with make-up quality water8. Turn on power to electric panels: all alarms and shutdown signals should be operating correctly before continuing with the next steps.

9. Turn on amine fill pumps and slowly begin filling the system with the amine solution10. Closely monitor the level gauge in still column 646-V-??

11. Continue to fill the system until the set point level in still column *&&* is achieved12. Turn on one of the amine booster pumps13. Closely monitor level gauge (&*&) located the rich amine section of amine flash separator (646-V-???)

14. Continue filling the system and running the amine booster pump until the set point level of 646-LG-?? is achieved.

15. Turn off the booster pump and fill pump16. Check all liquid levels, the reflux accumulator and liquid hydrocarbon bucket in the amine flash separator are the only two levels that should visible through level gauges.

17. By pass the reflux accumulator control valve and fill the reflux accumulator via the top side 2 level gauge process connection of LG-??? 18. Slowly fill the reflux accumulator until the level set point is reached

19. Reconnect and tighten LG-??? to reflux accumulator 646-V-???

SECTION III3.0OPERATION3.1Definition

Sweetening is the process of removing acid gas from natural gas. This section is only included to discuss the removal of CO2 and H2S from natural gas by means of the tertiary amine methyldiethanolamine (MDEA)

The amine sweetening Unit supplied has been designed and fabricated to deliver a sweet gas composition in accordance with the design conditions and product specifications supplied by the customer. This section is intended to serve as a handbook and guide to assist with the initial start-up and normal operation of the unit. Not to replace the operating companies commissioning, decomisioning or operating procedures.

A better understanding of the equipment and its application will provide greater operation efficiency and make solving operating problems easier. It is, therefore, the purpose of this manual to explain the design, construction and operating characteristics of the unit; however, it must be noted by the reader that no manual can foresee all possible situations due to the myriad combinations of pressure, temperature and operating conditions possible in operations. The reader is, therefore, advised that the services of a competent on-site technician during start-up and operation of the unit is essential to prudent safe operation.

3.2Effect of Contact Conditions1)Temperature there are practical limitations in using amine for acid gas absorption from the standpoint of both absorption efficiency and operational cost. The lower the temperature of contact, the greater the viscosity the amine solution will be. As the viscosity of the solution increases, the efficiency of contact decreases resulting in lower tray efficiencies. Additionally, the amine sweetening process involves both physical and chemical absorption and is driven primarily by chemical absorption. As the amine solution contacts the sour gas several chemical reactions take place, as in most controlled chemical reactions temperature is critical. The two primary reactions paths that take place are; Hydrogen sulfide reacts with the MDEA solution to form R2NHCH4+ plus HS- and is believed to take to take place instantaneously while Carbon dioxide reacts with the MDEA solution to form R2NCH4+ plus HCO3- and is generally considered to be the slower reaction since CO2 must form bicarbonate with the water in the solution before reacting with the tertiary amine. Both reactions are reversible and are in fact reversed in the still columns reboiler during the regeneration cycle. These reactions are exothermic and cause distinct temperature profiles across the contact tower. This profile reflects the rate of reactions and may prove to be a useful tool when determining pinch points, optimizing lean/rich approaches and advanced process trouble shooting techniques. The optimum lean amine solution temperature depends on ambient temperatures, inlet gas temperature and pressure, amine solution strength and lean amine loadings. As a rule of thumb the amine solution is generally held slightly above the inlet gas temperature 3-8 0C this helps to reduce foaming and liquid hydrocarbons condensing out the natural gas stream. Foaming in the contactor will lead to pronounced reductions in absorption efficiency and high amine losses which will carry over to the dehydration section of this gas process facility. Amine carry over will inadvertently effect the downstream dehydration process and should be mitigated prior to downstream contamination. On the other hand, if the lean amine solution temperature is excessively high, the higher vapor pressure of acid gases in the amine solution will lead to poor reaction kinetics and off spec product. Although this system is capable of meeting the sweet gas product specification under an assortment of varying set points and ambient temperatures it is advised that an experienced operating company or engineering firm be consulted for proper system optimization. 2)Pressure The contactors operating pressure is dependent on the available sour gas pressure and is directly related to the sour gas constituents partial pressure. The partial pressure of acid gas affects the rate at which it reacts with the amine solution. Generally the higher the partial pressure of acid gas the faster the reaction rate, however practical considerations such as down or upstream compressor stages and unit operations are generally the governing elements. 3)Amine Concentration The amine solution strength plays a significant role in the systems overall performance and limitations. This system was designed considering only a 50/50 solution of MDEA and water. Lower amine concentrations will generally lead to increased reboiler duty and higher rich/lean loadings. Although, slight adjustments to the amine solution strength can result in increased efficiency, leaner products, and lower corrosion rates it is suggested that this system be operated at its design solution strength and adjustment only be made by qualified experts. Note: the water used to dilute the amine solution to its proper strength must be free of contaminates and conform to the make-up water requirements provided in appendix #.3.3How Does the Process Work?All continuous and regenerative absorption processes have the same purpose, that is to remove contaminants from contaminated gas streams , producing a continuous gas stream with lower contaminants compositions, returning the sorbent through a regeneration cycle, removing the contaminant from the sorbent, leaving the lean sorbent to be pumped back to contact the gas and repeating the process.

Now how does MDEA sweetening process work? First, refer to P&ID place proper as built # here. Wet sour gas flows vertically upwards into the absorber section of the contact tower where it is contacted counter currently across twenty trays with lean Methyl-Diethanol Amine (MDEA) Refer to vessel drawings for details of internals. Sweet gas leaves the top of the absorber tower through the outlet scrubber section while rich amine flows from the contactor tower to the regeneration package. The pressure of the amine solution is dramatically reduced via the contactors level control valve and flows into the flash separator prior to entering the lean/rich cross exchanger. Sour hydrocarbon vapors are released from the amine as the pressure is reduced in the flash separator and routed to incineration and/or flare. The vessel is equipped with sufficient retention time to separate and remove any light liquid phases that may develop, this light liquid phase collects in the separators bucket and is routed to skid edge where it is the operator responsibility to properly dispose of. Note: Both the vapors and light liquids will be rich with acid gas contaminants and must be disposed of in accordance to local or national regulations. The heavy liquid phase (amine solution) is routed to the lean/rich cross exchanger where it absorbs heat from the lean amine stream. The heat absorbed by the rich amine stream releases additional acid gasses from the solution and helps reduce the still columns reboiler duty. However, this acid gas breakout may lead to a complex two phase flow regime in the vertical piping between the rich/lean cross exchanger and still column. Several methods during the design of this system were used to predict and control this regime by proper process piping, however all such methods are inherently complex and lead only to close approximations. The object of this design was to minimize slugging to the still column which may disrupt the columns temperature profile and may lead to erratic behavior. It is the operator responsibility to analyze and mitigate any abnormal flow conditions which may result from operating this system outside of its design parameters, such abnormalities may include but not limited to: excess fouling on the lean or rich side of the exchanger due to improper maintenance, contaminated makeup water, excess amine degradation products due to improper reboiler startup and/or shutdown, etc. The rich amine solution enters the top of the still column between the upper and lower sections of random packing where it contacts the reflux stream flowing down the top section of packing and travels through the lower packing section as it contacts stripping vapors generated in the reboiler. Once the now semi-lean amine exits the lower section of packing it collects on a chimney tray and flows into the collection bucket of the once-through vertical thermosiphon reboiler there it enter the reboiler where it is partially vaporized and exits back into the column below the chimney tray and into the reboilers collection bucket spill over weir designed to maintain a constant liquid head feeding the thermosiphon reboiler. Remember when calculating an amine system reboilers required heat duty that it is the sum of the sensible heat energy needed to bring the bottoms liquid to its bubble point, the latent heat of vaporization energy associated for the desired boil-up ratio and the heat necessary to break the chemical bonds between the amine and acid gas. The now fully lean amine flows over this spill over weir and into the still columns sump, which also serves as the amines surge volume, during the steady state operation of the regeneration system the level in this towers sump will steadily decline as water is lost through the still columns overhead. This rate has been predicted for the design cases as depicted by the design basis of this system; however it is the operators duty to determine the actual amount needed as well as method of monitoring and adding makeup water to the system. This process should be tailored to conform to the operators standard practices. Lean Amine exits the column and enters the lean/rich cross exchanger where it supplies heat to the rich amine entering the still column as previously described. The lean amine then flows to the amine booster pumps which supply the necessary suction head pressure for the circulation pumps. After leaving the booster pump the lean amine passes through the lean amine air coolers then filtered the lean amine particulate and carbon filters. Upon leaving the filters the lean amines pressure is elevated to contactors operating pressure via the main circulation pumps and returned to the contactor to complete its regeneration process. 3.4Amine Degradation & ContaminationOne of the biggest problems connected with the operation of amine sweetening systems is amine contamination degradation. This contamination usually results in decreased performance, increased amine loss, and may result in damage to the equipment. The most common source of contamination is from slugs of heavy hydrocarbons, treating chemicals, saltwater, drilling mud and dirt. The solid particles that enter the amine are, in most cases, removed by the filter. Heavy hydrocarbons may cause foaming with the resultant loss of amine through carryover. This system includes an amine-hydrocarbon skimmer vessel. This is the three phase flash separator (646-S-0102) which skims the hydrocarbons off the amine. Amine degradation will usually occur in the reboiler and results in the formation of amine salts, which are toxic and corrosive. To limit the degradation of amine the reboiler of this system has been design with specific circulation rates and temperature of both the hot oil and amine. Operating outside of these ranges is not advised and may lead to excess degradation of the amine solution.3.5CorrosionThe sour gas processing service of this system is an inherently corrosive one. Several mitigating steps have been taken during the design of this system such as lean and rich amine loadings, selective control valve and line sizing to control velocity, excessive corrosion allowances where applicable, industry specific material selections and vessel coatings for specific regions of the process where acid gas may break out of the amine solution, as well as minimal dead legs in piping. However, it is ultimately the operators responsibility to properly monitor and mitigate corrosion problems through proper maintenance and operating procedures. The hot oil supply subsystem is also susceptible to accelerated corrosion rates if oxygen is allowed to contaminate the hot oil circulating in this subsystem. Please refer to the hot oil (therminal 55) suppliers literature for more information, and mitigating procedures.3.6 Alarm and Trip Setting

Instrument TagUnitsOperatingSet Point

Complete only after

as-piped and walked through P&ID completed

SECTION IV4.0START UP & SHUT DOWN PROCEDURESStart up and operation procedures depend on the particular application and type of equipment and auxiliaries supplied. However, there are certain generalities that usually apply which, with special procedures as pointed out, should permit operation with a minimum of difficulty.

Preliminary: operators should familiarize themselves with literature for all instruments and controls, and study any applicable flow sheets or drawings of the unit.

1.) Ensure that all Plant Check Out and Amine Unit Clean Out procedures have been carried out and included at a minimum plant controls logic, shutdown logic, electric systems, instrument air systems, purging and leak checks, emergency systems, and charging of all chemicals and lubricants. 2.) Block valves on sour process gas should be initially closed.

3.) Turn on power to electric panels: all alarms and shutdown signals must be operating correctly before continuing with the next steps.

4.) Turn on the hot oil subsystem following the startup procedure as given by the subsystems operations manual provided by the third party vendor.

5.) Pressurize the amine flash tank using blanket gas

6.) Turn on all condenser fans, reflux pumps, booster and circulation pumps.

7.) Allow time for the circulating hot oil to reach its set point temperature.

8.) Open the sour process gas inlet slowly to pressurize the contact tower and leave the sweet gas line valve closed; if applicable divert to incinerator or flare, keep the gas flow rate to no more than half the design flow rate. 9.) Check that the amine solution concentration.

10.) Circulate the amine solution until the still overhead condenser inlet temperature reaches its minimum operating temperature or set point.11.) Open the sweet gas valve and slowly increase the flow rate to its desired operating rate. While closely monitoring the sweet gas outlet composition. 12.) Switch to fully automatic mode. None of the safety shut downs should activate. ****NOTICE****

Amine Units are usually part of larger plants. Therefore the start-up and commissioning of the amine unit should be synchronized with other process and units within the entire gas treatment facility. The following precautions should also be made aware to operators and adhered to: A.) Make sure lean/rich cross exchanger, lean amine air cooler, filters and pump suction lines are flooded, bleeding air out of line should be done with extreme caution and appropriately vented as necessary. Use bypass valve if applicable.B.) Close all bypass valves (amine and hot oil where applicable) around the pumps and heat exchangers C.) CAUTION ensure that the reflux accumulator outlet is not restricted and operating properly. BACK PRESSURE COULD RESULT IN PROCESS FAILURE, EQUIPMENT DAMAGE AND PERSONAL INJURY. IRREGULAR PRESSURE CONTROL WILL LEAD TO ERATIC REBOILER BEHAVIOR AND A DIFFICULT TO CONTROL PROCESS.

D.) Check pumps and motors (where applicable) for proper oil level, alignment, condition of valves and seats, etc.E.) Adjust instrument air supply regulators to maintain proper supply pressure to shutdown and control valves.F.) Ensure all valves are in their proper location, drain valves are closed, relief valve isolations in accordance with the P&ID. Particularly ensure all lock open valves are locked open and all locked closed valves are locked closed.G.) If necessary to maintain minimum surge volume level and or appropriate amine solution strength, add make-up water. CAUTION SHOULD BE TAKEN, HOWEVER, THAT THE SURGE NOT BE FILLED TOO FULL. AMINE WILL EXPAND AS IT COMES UP TO THE OPERATING TEMPERATURE CAUSING THE SURGE VOLUME/STILL COLUMNS SUMP TO TRIP ON HIGH LEVEL. Once levels and temperatures are properly established, there is still room in the surge to accommodate absorber holdup and also provide for several days normal operating losses.H.) CAUTION THIS EQUIPMENT WILL HAVE HOT SURFACES. MOST ARE INSULATED BUT OPERATING PERSONNEL MUST EXERCISE CAUTION.I.) Several hours may be required to accumulate sufficient condensate for the oil level control to activate in the amine flash separator. DO NOT ALLOW AMINE TO SPILL INTO THE CONDENSATE BUCKET.

4.1Shutdown ProcedurePreliminary: check all temperatures, pressures, levels and flow rates. This information may save time returning the unit to operation.A.) Turn off gas to contactor 646-V-0101 if no bypass is in system

B.) Continue circulating amine while monitoring rich amine loading until it matches the lean amine loading.

C.) Remove heat source, by following the shut down procedures of the hot oil subsystem.D.) Disable makeup water supply and monitor the reflux flow rate until no reflux flow is observed.E.) Stop reflux pumps.F.) Turn off fans to reflux condenser.

G.) If draining is required allow the amine solution to circulate until the temperature entering the lean amine air cooler is approximately that of the exiting temperature. Otherwise circulate until the temperature entering the lean amine air cooler is under 100 0C. H.) Shut down the lean amine air cooler fans

I.) Turn off the circulation and booster pumps respectively.

J.) Bleed pressure off the absorber, if the system is to be down for any extended period of time. USE CAUTION AND VENT IN ACCORDANCE WITH PLANTS SOUR GAS VENTING PROCEDURES.K.) Turn off the blanket gas to the flash separator and bleed off the amine flash tank, if the system is to be down for any extended period of time. USE CAUTION AND VENT IN ACCORDANCE WITH PLANTS SOUR GAS VENTING PROCEDURES.

L.) Bleed pressure off the reflux accumulator, if the system is to be down for any extended period of time. USE CAUTION AND VENT IN ACCORDANCE WITH PLANTS SOUR GAS VENTING PROCEDURES.

M.) The Amine regeneration unit must be cooled down to ambient temperature by natural cooling before any draining of the system.

f)Standard maintenance procedures should apply to a unit being taken out of service for an extended period of time. The absorber and still column should be water-flushed with a caustic solution rinsed and drained. The pumps should be cleaned and plungers coated with a rust preventative. CAUTION ALWAYS DISCONNECT POWER SUPPLY PRIOR TO SERVICING ELECTRICAL EQUIPMENT. DO NOT ALLOW SMOKING OR OPEN FLAME AROUND GAS PROCESS EQUIPMENT.

4.2Operational Shutdown PhilosophyRefer To operational companys standard practices. SECTION V5.0MAINTENANCE

5.1Preventive Maintenance

The best control of operating problems is to have an effective maintenance program, not only for the equipment, but also for the chemical.

A thorough checkout of an amine sweetening unit should be made at least every 30-40 days to insure good operation.

Should a vessel require an internal inspection, a thorough purging is recommended.

5.2Mechanical

5.2.1Pumps - Pump seals or O rings may need replacement or adjustment. Strainer screens should be cleaned and/or replaced. Consult the appropriate service bulletins for model specific maintenance instructions and procedures.5.2.2Filters The particulate and carbon filter elements should be replaced when the differential pressures across the filters are ?? psi (?? BAR) for carbon filters and ?? psi (?? BAR) for glycol filters. Filter elements can be purchased either directly from the vendor.5.2.3Temperature Controls - to insure that the fluid temperature in the reboiler is below the degradation temperature the controls must be in good working order.

5.2.4Level Controls and Control Valves - if not in good operating condition, can cause an upset in amine flow. Any valves and controls requiring lubrication should be properly lubricated at selected intervals to assure best performance. Maintenance and repair of valves and controls depends upon severity of service, e.g. mud, sand, etc.

5.2.5Safety Valves - safety valves require periodic inspection to assure the operator that the valves are not sticking and will provide safety relief. Pressure testing is the approved method.

5.2.6Overhead Condenser - Refer to instruction manual in final data books.

5.2.7Heat Exchangers:Tube Cleaning - Operating conditions sometimes result in an accumulation of dirt on the outside surface .This can be removed by directing compressed air, or a greaseless solvent followed by a water spray through the tubes in a direction opposite the normal flow. The inside of the tubes will require periodic inspection and cleaning as necessary.

Plug Leaks - Should tapered plugs develop leaks, additional tightening is normally all that is required. Thread dope may be used if tightening alone is not sufficient. If shoulder type plugs develop leaks, the gaskets should be replaced. TAPERED PLUGS THAT ARE REMOVED FOR TUBE INSPECTION OR CLEANING SHOULD BE REPLACED IN THE SAME HOLE.

Tube Leaks - Tube leaks can be of two types: (1) leaks in the tubewall itself (usually corrosion) and (2) leaks in the tube to tubesheet joint. In the first case, it is usually most practical to plug both ends of the tube with the resulting loss in heat transfer surface. When so many tubes have been plugged that performance is affected, retubing will be necessary. If leaks develop in the tube to tubesheet joints, re-rolling of the tube will be required. Care must be used in selection of the proper tube expander for the size and BWG of the tube being used. As with all rolled tube joints, over-rolling must be avoided.

General - If it is ever necessary to contact us for service or replacement parts, it is essential that the serial number or other identifying data be obtained from the metal nameplate attached to the exchangers. This is the only way to positively identify the correct parts that may be required.

5.3Process5.3.1Check amine in the surge volume of the still columns sump to always maintain a level in the gauge glass.

5.3.2Check filter cartridges. Filter cartridges should be replaced after three months of initial operation. The used cartridge elements should be visually inspected for accumulation of contaminants and debris. Upon analysis, a minimum replacement schedule should be determined. The carbon filters should be online whenever the unit is operating and offline during cartridge replacement.

5.3.3Take samples of amine and have these analyzed for contaminants (salts, hydrocarbons, etc.), pH, foaming tendency and color of amine, etc.

5.3.4Check levels, temperatures, pressures and flow rates regularly. This information will help diagnose problems and prevent shutdown.

5.3.5Check for leaks and repair as required.5.3.6the most important item in any preventive maintenance program is to "keep the system clean". When the amine is "dirty", the possibility of plugging the absorber is greater, the efficiency of dehydration is less, and glycol loss is enhanced.

5.4Periodic Shutdown and General Inspection

Every year or when required by operation, a shutdown and complete inspection of the unit is desirable. This should include but not be limited to:

5.4.1Cleaning of the reboiler. Remove any deposits.

5.4.2Clean the stripping column and clean or replace the packing if deemed necessary.

5.4.3Clean the amine contact tower.

5.4.4Clean all heat exchangers.

5.4.5Clean, inspect and repair all valves and controls. Replace damaged trim.

SECTION VI

6.0TROUBLESHOOTING

It is the responsibility of the operator in the field to quickly identify and if possible, eliminate an operating problem. A delay in correcting a malfunction can be very costly both in personnel safety and damage to equipment.

The most obvious indication of an amine sweetening systems malfunction is an off spec quality of the sweet gas or excessive amine losses. In the majority of cases this is brought about by insufficient amine circulation and/or high lean loadings. These two factors can be due to a variety or contributing causes as listed below.

In addition to mechanical causes, high product impurity may be found due to existing operating conditions for which the equipment was not designed. These conditions can sometimes be at least partially alleviated by both changes in process condition and mechanical operation.

6.1Common deviations, causes, consequences and actions are shown below:6.3.1FiltersDeviationCauseConsequenceAction

Low differential pressure across filter Torn element.Open bypass.Hydrocarbon Contamination.Foaming.

Filter material carry over.Confirm PLC and Field instruments agree.

Close bypass. Replace element.

High or continuously rising differential pressure Across filter Particle accumulation.

High liquid loadings.

Reduced Throughput. Hydrocarbon Contamination.

Foaming.Clean or replace dirty filters.

Sudden IncreaseLevel control failure.

Solid fouling.HC contamination.

Foaming.

Reduced throughput.

Clean or replace filter.

Mitigate level control failure

6.3.2Amine contactorDeviationCauseConsequenceAction

Low differential pressure across traysPossible tray damagePoor efficiency.

Off spec product.Mechanical repair.

Gradual differential pressure increasePossible fouling.Flooding.

Poor efficiency.

Capacity limit.

Off spec product.Cleanout.

Identify root cause.

Sudden differential pressure increaseFoaming.

Flooding.Poor efficiency.

Liquid carry over.

Plant upset.Reduce gas and/or liquid rates. Check relative inlet temperatures. Check for hydrocarbon contamination and feed gas liquid hydrocarbon entrainment.

Low gas flow rateUpstream process changeReduced amine demand.

Potential for poor mass transfer due to contactor trays weepingReduce amine flow. Supplement gas feed with clean or recycled gas.

High gas flow rateUpstream process changeIncreased amine demand. Possible jet flooding.Increase amine flow.

Low amine flow rateChange in supply pressure or pump control malfunctionPotential off spec product.Check pumps and inlet sour gas pressure

High amine flowChange in supply pressure or pump control malfunctionIncreased utility consumptionAdjust conditions check pump controls.

Amine contactor continuedDeviationCauseConsequenceAction

Low feed gas temperatureUpstream upset.

Change in ambient conditions.Reduced acid gas pickup.

Check instrument gauges. Monitor product spec for changes.

High feed gas temperatureUpstream upset.

Change in ambient conditions.Reduced acid gas pickup.

Check instrument gauges. Monitor product spec for changes.

Low lean amine temperatureUpstream upset.

Change in ambient conditions.Low rate of reaction due to higher solution viscosity. Off spec product.Reduce lean amine cooling by adjusting louvers (slowly while monitoring temp)

High lean amine temperatureUpstream upset.

Change in ambient conditions.Off spec product. Excessive moisture in treated gas. And potential for downstream condensation and corrosion/foulingIncrease lean amine cooling by adjusting louvers (slowly while monitoring temp) and/or fan control.

Low lean amine/feed gas temperature differentialUpstream upset.

Change in ambient conditions.Hydrocarbon condensation in contactor. Foaming. Emulsification. Increase lean amine cooling by adjusting louvers (slowly while monitoring temp) and/or fan control.

Low rich amine loadingOver circulation.High utility consumption.Reduce amine circulation rate.

High rich amine loadingUnder circulation.Off spec productIncrease amine circulation rate.

High H2S in treated gasFlooding.

Foaming.

High lean amine loading.

Low amine solution strength.

Low circulation rate. Excessive amine degradation. Poor contactor efficiency. Environmental non-compliance. Downstream corrosion.Adjust process conditions as warranted.

6.3.3Amine Flash Separator

DeviationCauseConsequenceAction

High pressure Malfunctioning pressure control valve. Excessive hydrocarbons in amine. Contactor foaming.Regenerator foaming. Excessive acid gas breakout in rich/lean amine cross exchanger. Correct contactor operation. Clean up amine.

Low pressureMalfunctioning pressure control valve.

Vessel vented to atmosphere or relief system. Blanket gas malfunction.Amine may not flow to still column. Environment contamination. Personal endangerment.Find and repair leak. Fix blanket gas and/or pressure control valve.

High flash gas rateExcessive hydrocarbon carry over from absorber. Foaming in still column.

Reduced acid gas absorption.Correct absorber operation.Clean up amine.

High hydrocarbon bucket levelMalfunctioning level control.Foaming in still column.

Reduced acid gas absorption.Fix level control.

High Amine bucket levelMalfunctioning level control.

Water leaking into the system. Excessive water makeup rates. Over filled systemAmine carry over into gas system. Diluted amine strength.Reduce makeup water rate.

Check amine strength.

Remove amine solution from system and correct solution strength

Low Amine bucket levelDehydrating amine. Low makeup water rate. High amine losses due to foaming in absorber or still column. Amine leakFlash gas carry over into amine still column.Correct amine solution strength. Find and repair leak. Correct absorber and/or still column operations.

6.3.4Lean/Rich Amine Cross Exchanger

DeviationCauseConsequenceAction

High rich side outlet temperatureHigh hot oil temperature and/or rate.

Flashing of acid gas in exchanger. Corrosion in exchangers and outlet piping.Check amine flows. Lower hot oil rate or temp. check for low lean loading.

Low rich side outlet temperatureExchanger foulingPoor still column performance. High lean loading. Increased hot oil demand.Check exchanger UA for design deviations and fouling. Check rich side differential pressure.

High rich or lean side differential pressure.Exchanger clogged or fouling.Poor still column performance. High lean loading. Increased hot oil demand.Clean exchanger.

6.3.5Amine Regeneration Still ColumnDeviationCauseConsequenceAction

Low pressureMalfunctioning pressure control. Loss of reboiler heat source. Upset in flare.Determine cause. Check panel agrees with instruments.

High or rising pressureDownstream upset. Failed pressure control. Flooded accumulator. Excessive reboiler duty. Condenser fouledDownstream unit shutdown. Unit shut down.Reduce reboiler duty. Raise reflux temperature. Shut down and clean overhead lines and condenser

Low differential pressure across packingPossible packing or distributor damagePoor efficiency.

Off spec product.Mechanical repair.

Gradual differential pressure increasePossible fouling.Flooding.

Poor efficiency.

Capacity limit.

Off spec product.Cleanout.

Identify root cause.

Sudden differential pressure increaseFoaming.

Flooding.Poor efficiency.

Liquid carry over.

Plant upset.Reduce gas and/or liquid rates. Check relative inlet temperatures. Check for hydrocarbon contamination and feed gas liquid hydrocarbon entrainment.

Gradual decline in rich amine flow Declining level in flash drum. Cross exchanger fouling/plugging. Open drains and leaksLoss of throughput and treating capability.Balance flows in and out of system. Check contactor for foaming and amine losses or operational upset. Check for maintenance activity. (filter change equipment drains) check reflux and makeup water rates.

Amine Regeneration Still Column Continued

DeviationCauseConsequence Action

Sudden loss of rich amine feedGas blow by in amine flash separator low level. Low pressure in amine flash separator. Lean rich amine cross exchanger plugged. Loss of circulation. Low amine inventoryFlash gas carry over to still column. Pump cavitation. Low level in still column sump. Excessive reboiler skin temperatures and amine degradation. Find and fix leak. Mitigate low level in flash drum. Add amine and/or make water and check solution strength. Mitigate circulation pumps problems. Check blanket gas train. Check for amine degradation and remove amine salts and reclaim amine if warranted. Check for liquid hydrocarbons carrying over into the still column and flashing in the cross exchanger.

Low level in still column sumpInsufficient make up water rate. Low amine inventory level. Amine leak. Amine carryover due to contactor flooding and/or foaming. Increased amine degradation products. Possible pump cavitation. High amine losses. Check makeup water rates and solution strength. Add amine solution to inventory. Correct contactor operation.

6.3.6Lean and Rich LoadingDeviationCause ConsequenceAction

High lean loadingInsufficient reboiler duty. Over circulating. Fouled exchangers. Off spec solution strength. Leaking cross exchanger. Caustic contamination. Off spec product. Excessive corrosion rates. Increase reboiler duty. Decrease circulation. Increase amine strength. Remove degradation products reclaim amine, if warranted. Clean fouled exchangers. Check sodium levels.

Low Lean LoadingExcessive reboiler duty. Under circulating, Off spec solution strength.Excessive utility usageLower reboiler duty. Increase circulation.

High rich loadingUnder circulating. Excessive feed gas rates. Feed gas composition change.High corrosion rates. High flash gas rates.Increase circulation. Check feed gas rate and composition.

Low rich loadingContactor flooding. Contactor loss of efficiency. High solution strength. Low feed gas rate. Feed gas composition change.Off spec product. Excessive utility consumption.Correct contactor operation. Check solution strength. Check feed gas rate and composition.

SECTION VII

7.0DESIGN BASIS

The design basis of the amine regeneration unit and contactor is as follows:

CompositionFeed GasUnit

Methane(Mole Fraction, Total)68.9%

Ethane(Mole Fraction, Total)9.55%

Propane(Mole Fraction, Total)5.6%

i-Butane(Mole Fraction, Total)1.38%

n-Butane(Mole Fraction, Total)2.33%

i-Pentane(Mole Fraction, Total)1.25%

n-Pentane(Mole Fraction, Total)0.491%

CO2(Mole Fraction, Total)3.51%

H2S(Mole Fraction, Total)5.6%

C6+(Mole Fraction, Total)0.87652%

PropertiesFeed GasUnit

Temperature140oF

Pressure378.5Psig

Mass Flow154262lb/h

Specific Gravity0.882

Water Content 238lbm/MMSCF

Water Dew Point 122oF

Equipment Specification InputsSimulation Design Case Output Requirements

DescriptionDesign SpecificationOperating-Case 1Design-Case 2

Reboiler Duty26.5 MMBTU/h24 MMBTU/h26.5 MMBTU/h

HEX Duty Lean/Rich Amine20.5 MMBTU/h18.7 MMBTU/h18.8 MMBTU/h

HEX Duty Lean Amine Return15 MMBTU/h13.76 MMBTU/h13.81 MMBTU/h

Stripping Column Reflux Condenser11.5 MMBTU/h8.04 MMBTU/h10.5 MMBTU/h

Circ. Pump Power Requirements150 hp141 hp141 hp

Circ. Pump Nominal Flowrate600 sgpm600 sgpm600 sgpm

Reflux Pump Power Requirements1 hp0.43 hp0.57 hp

Reflux Pump Nominal Flowrate32 sgpm14.8 sgpm19.4 sgpm

Booster Pump

Power Requirements30 hp25 hp25 hp

Booster Pump Nominal Flowrate600 sgpm600 sgpm600 sgpm

Abbreviation List:LT Level Transmitter

PT- Pressure Transmitter

TT Temperature Transmitter

PDZIT- Differential Pressure Transmitter

LAHH Level Alarm High HighLALL Level Alarm Low Low

LAH- Level Alarm High

LAL- Level Alarm Low

PAHH- Pressure Alarm High High

PALL Pressure Alarm Low Low

PAH- Pressure Alarm High

PAL Pressure Alarm Low

TAHH Temperature Alarm High High

TALL Temperature Alarm Low Low

TAH Temperature Alarm High

TAL Temperature Alarm Low

MDEA Methyl-Diethanol AminePAGE 2