2004 COST DATA (Draft) Compiled By Engineering Estimates and Market Analysis Unit of the Agreements and Market Analysis Branch Jan. 28, 2005

cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

2004 COST DATA

(Draft)

Compiled By Engineering Estimates and Market Analysis Unit

of the

Agreements and Market Analysis Branch

Jan. 28, 2005

Page 2: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO COST DATA

FOREWORD

The Colorado Department of Transportation’s Engineering Estimates and Market Analysis (EEMA) Unit, of the Agreements

and Market Analysis Branch, publishes the Cost Data Book annually. A joint effort has been made between the Department’s

sections and the EEMA Unit to gather and record cost data for this publication.

The following data includes weighted average prices for items on highway construction projects that were bid during the 2002

calendar year. Caution should be used in applying these historical averages to specific projects. Allowances for varying

geographic, climatic, social, economic conditions and type of project should be made.

Changes and improvements are continually being made to update and increase the usefulness for future issues. Comments

and suggestions for improvements for users of this publication are welcome. A copy of this book is available on the CDOT web site.

Copies of this publication may be obtained

on hard copy, from:

Colorado Department of Transportation

Bid Plans, Room 117

4201 E. Arkansas Avenue

Denver, Colorado 80222

Phone: 303-757-9313

Page 3: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

2004 COST DATA

CONSTRUCTION

TABLE OF CONTENTS

LIST OF 2004 BID PROJECTS BRIDGE COST PER SQUARE FEET ITEM AVERAGE BID PRICES ITEM UNIT COSTS BY PROJECT Appendix A – 2004 Maintenance Type Projects

# OF PAGES

9

n/a

32

531

* released on the CDOT web-site

Page 4: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 1 2004 Cost Data PROJECTS BID FROM 01/01/04 THROUGH 12/31/04------------------------------------------------------------------------------------------------------------------------------------ BID CONTRACTOR/LETTING PROJECT NUMBER LOCATION DIST TERRAIN BIDS AWARDED BID INDEX------------------------------------------------------------------------------------------------------------------------------------04010802 ASPHALT SPECIALTIES CO., INC. 8 $1,586,248.25 90.46 STA 0062-015 US 6: WADSWORTH TO FEDERAL 6 U

04010805 A & S CONSTRUCTION CO. & AFFILIATED CO. 4 $1,463,025.85 97.95 STA 2911-001 SH 291 SALIDA NORTH 5 R

04010808 ASPHALT CONSTRUCTORS INC. 3 $1,261,139.90 128.86 STA 114A-009 S.H. 114, W OF COCHETOPA PASS 5 M

04010809 PENHALL COMPANY 6 $379,845.06 87.31 NH 5502-045 US550, DURANGO JOINT SEAL 5 M

04011502 LAFARGE WEST, INC 6 $2,671,609.00 107.86 IM 0704-203 I-70, GENOA-EAST, M.P. 374 - 1 P

04012901 ASPHALT SPECIALTIES CO., INC. 10 $2,131,812.90 83.09 STA 2854-097 US 285, LAFAYETTE TO DAHLIA 6 U

04012902 UNITED COMPANIES OF MESA COUNTY 4 $849,869.40 105.03 STA R300-120 R-3 SOUTHWEST CHIPSEAL 3 M

04012903 INTEGRATED ELECTRIC, INC. 8 $234,375.22 89.00 C 0342-040 US 34 IN WELD COUNTY 4 R

04012905 PREMIER PAVING, INC. 7 $1,022,091.35 78.71 STA 1211-058 SH 121 (WADS), 90TH TO 104TH 6 U

04012906 ASPHALT PAVING CO. 7 $2,083,604.60 77.84 STA 1211-059 SH 121 (WADS) - 6TH TO GRANDVI 6 U

04012907 ASPHALT PAVING CO. 4 $2,797,791.89 72.13 IM 0703-286 I-70, E & W OF IDAHO SPRINGS 1 M

04012908 LAWRENCE CONSTRUCTION CO. 6 $15,581,590.13 81.35 NH 0403-035 BERTHHOUD FALLS W. 2 MI. 1 M

04020502 D.G. HUSKIN CONSTRUCTION CO. 5 $2,480,778.27 85.14 STA 1604-008 US 160C, PRITCHETT TO US 287 2 P

04020503 COULSON EXCAVATING COMPANY 6 $851,494.65 93.97 STA 0341-050 US 34, JEFFERSON TO MONROE 4 U

04020504 AGGREGATE INDUSTRIES - WCR, INC. 8 $1,269,980.46 87.83 STA 0853-052 SANTA FE DR., FLORIDA TO I-25 6 U

04020507 MOUNTAIN CONSTRUCTORS, INC. 6 $65,134.00 82.97 C 001A-038 SH 1 & LARIMAR CO RD 54 4 R

04021201 ASPHALT SPECIALTIES CO., INC. 7 $1,112,323.90 95.16 STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 6 U

Page 5: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 2 2004 Cost Data PROJECTS BID FROM 01/01/04 THROUGH 12/31/04------------------------------------------------------------------------------------------------------------------------------------ BID CONTRACTOR/LETTING PROJECT NUMBER LOCATION DIST TERRAIN BIDS AWARDED BID INDEX------------------------------------------------------------------------------------------------------------------------------------04021204 CONCRETE WORKS OF COLORADO INC. 9 $1,831,904.50 85.89 STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 6 U

04021206 WARNING LITES & EQUIPMENT, INC. 3 $1,553,140.00 82.59 MC R300-118 R-3 PAVEMENT MARKINGS 3 M

04021207 CONCRETE WORKS OF COLORADO INC. 4 $1,122,928.60 113.89 STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 6 U

04021208 A & S CONSTRUCTION CO. & AFFILIATED CO. 5 $7,163,679.84 102.63 IM 0701-164 PARACHUTE EAST & WEST 3 M

04022601 D.G. HUSKIN CONSTRUCTION CO. 3 $2,153,005.84 103.67 STA 131A-031 SH 131, MP 13.6 TO MP 30.8 3 M

04022602 BRANNAN SAND AND GRAVEL COMPANY 8 $972,522.13 84.68 STA 391A-001 SH 391: SH 285 TO W. JEWELL AV 6 R

04022603 FOUR CORNERS MATERIALS 2 $860,821.65 114.39 STA 003A-001 SH 3, EAST OF DURANGO 5 M

04022604 HAMON CONTRACTORS, INC. 8 $6,773,273.49 84.46 IM 0252-359 CASTLE PINES INTERCHANGE 1 R

04022606 KIRKLAND CONSTRUCTION, RLLP 5 $2,205,576.20 91.31 STA 3501-010 SH 350 - BESHOUR JUNCTION 2 P

04022607 KIRKLAND CONSTRUCTION, RLLP 2 $1,388,976.00 103.03 STA 0241-042 US 24, N OF BUENA VISTA 5 M

04022608 DKS ENTERPRISES INC. 7 $265,549.00 116.36 C 074A-007 SH 74 @ BRYANT DR. 1 R

04022610 UNITED COMPANIES OF MESA COUNTY 6 $7,817,860.78 101.25 IM 0701-157 FRUITA TO CLIFTON 3 M

04022611 INTERSTATE HIGHWAY CONSTRUCTION 6 $3,218,889.89 90.14 STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 6 U

04030401 LAFARGE WEST, INC 6 $1,762,456.25 102.40 STA 014A-030 SH 14, WALDEN EAST 3 M

04030402 LAFARGE WEST, INC 4 $4,873,435.70 93.93 STA 0405-030 SH 40 & 385, CHEYENNE WELLS 1 P

04030403 D.G. HUSKIN CONSTRUCTION CO. 4 $3,660,904.93 113.06 NH 2872-016 US 287 - LAMAR 2 R

04030404 ASPHALT SPECIALTIES CO., INC. 6 $5,259,879.05 94.97 NH 0853-053 FT. LUPTON TO PLATTEVILLE 4 U

Page 6: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 3 2004 Cost Data PROJECTS BID FROM 01/01/04 THROUGH 12/31/04------------------------------------------------------------------------------------------------------------------------------------ BID CONTRACTOR/LETTING PROJECT NUMBER LOCATION DIST TERRAIN BIDS AWARDED BID INDEX------------------------------------------------------------------------------------------------------------------------------------04031102 ZAK DIRT, INC. 3 $649,049.49 129.30 SHE R400-164 R-4 SAFETY PROJECTS 4 R

04031103 UNITED RENTALS HIGHWAY TECHNOLOGIES CONTRACT REJ - NO REASON GIVEN MC R300-119 R-3 STENCIL PROJECT 3 M

04031104 A & S CONSTRUCTION CO. & AFFILIATED CO. 4 $1,543,440.90 100.28 STA 009A-023 SUMMIT COUNTY LINE NORTH 3 M

04031105 W.L. CONTRACTORS, INC. 5 $913,382.85 106.48 STA R600-189 R-6 SIGNAL PROJECTS 6 U

04031106 POWER ENGINEERS, INC. CONTRACT REJ - NO REASON GIVEN ITS SW00-264 I-70 WEST, FIBER OPTIC 00 M

04031802 CUSTOM LIGHTING SERVICES, LLC 1 $534,833.50 117.35 C R300-116 GRAND JUNCTION GUIDE SIGNS 3 U

04031804 DKS ENTERPRISES INC. 4 $399,310.00 88.48 SHE R300-113 DOWD BRIDGE, I-70 3 M

04031808 LAFARGE WEST, INC 2 $2,300,381.95 98.25 NH 0504-046 SH 50B - TROY TO SH 233 2 P

04031810 LAFARGE WEST, INC 7 $5,191,685.47 96.26 STA C470-026 SH83, Hilltop Rd. to Stroh Rd. 1 R

04031811 R.E. MONKS CONSTRUCTION COMPANY LLC 2 $10,221,497.65 102.25 STU M240-081 POWERS BLVD TO SH83, COLO. SP 2 R

04032503 ELAM CONSTRUCTION, INC. 3 $1,526,492.50 122.54 STA 0063-016 CLIFTON TO PALISADE 3 M

04032504 ELAM CONSTRUCTION, INC. 6 $2,698,614.40 103.84 STA 133A-028 SH 133, W OF PAONIA DAM 3 M

04040101 LAFARGE WEST, INC 6 $2,529,827.74 90.87 NH 2854-072 US 285: MORRISON RD TO KIPLING 6 R

04040102 LAFARGE WEST, INC 5 $4,582,362.55 100.34 NH 2873-134 US 287, VIRGINIA DALE N & S 4 R

04040104 UNITED RENTALS HIGHWAY TECHNOLOGIES 3 $420,475.00 107.51 MC R300-119 R-3 STENCIL REGIONWIDE 3 M

04040105 W.L. CONTRACTORS, INC. 3 $172,250.75 129.39 C R200-126 FY04 REGION 2 SIGNING 2 R

04040802 BRANNAN SAND AND GRAVEL COMPANY 9 $1,328,899.94 87.05 STU M055-016 COLFAX: PEORIA TO POTOMAC 6 U

Page 7: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 4 2004 Cost Data PROJECTS BID FROM 01/01/04 THROUGH 12/31/04------------------------------------------------------------------------------------------------------------------------------------ BID CONTRACTOR/LETTING PROJECT NUMBER LOCATION DIST TERRAIN BIDS AWARDED BID INDEX------------------------------------------------------------------------------------------------------------------------------------04040803 INTERFACE COMMUNICATIONS, COMPANY 7 $308,436.12 81.57 NH R600-220 C-470(4) & I-70(1) RAMP METERI 6 U

04040804 EVEN CONST INC. dba EVEN-PREISSER, INC. 3 $459,745.75 104.11 SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 2 U

04041501 KIRKLAND CONSTRUCTION, RLLP 4 $3,840,371.95 105.52 NH 0502-053 CIMARRON - WEST 3 M

04041504 LAFARGE WEST, INC 4 $2,093,057.95 88.88 NH 0505-039 US 50, EAST OF LAS ANIMAS 2 P

04041505 COULSON EXCAVATING COMPANY 4 $1,466,997.31 89.46 NH 2873-123 U.S. 287, IN LOVELAND NB & SB 4 R

04041506 AGGREGATE INDUSTRIES - WCR, INC. 5 $1,138,186.32 87.35 STA 2571-008 SH 257: US 34 TO MILLIKEN 4 R

04041508 ROCK & COMPANY 3 $297,950.00 86.12 STA 1191-020 SH 119 ROCKFALL MITIGATION, 29 4 M

04041509 M.A. CONCRETE CONSTRUCTION, INC. 3 $383,745.49 94.57 STA M555-023 I-70B & US 50, GRAND JCT. 3 U

04041510 INFRASOURCE UNDERGROUND SERVICES, INC. 3 $8,981,182.45 94.02 ITS SW00-264 I-70 WEST, FIBER OPTIC 00 M

04041511 LAFARGE WEST, INC 2 $1,773,238.40 98.45 STA 0853-051 US 85 BUS, 22ND - 5TH ST., GRE 4 R

04041512 LAWRENCE CONSTRUCTION CO. 7 $3,742,443.82 95.75 IM 0252-360 I-25 R.R. OVERPASS - CASTLE RO 1 R

04042203 KB CONSTRUCTION, INC 7 $886,074.14 112.54 STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 1 R

04042205 ADARAND CONSTRUCTORS, INC. 3 $3,271,336.16 122.95 IM 0253-188 I-25 MEDIAN SAFETY RAIL 4 R

04042206 SURFACE PREPARATION TECHNOLOGIES 3 $278,273.00 93.52 SHE 1601-052 R-5, CENTERLINE RUMBLE STRIPS 5 M

04042901 ASPHALT PAVING CO. 3 $876,645.35 77.71 NH 0741-015 - SMA Alt SH 74 EVERGREEN OVERLAY 1 M

04042902 ASPHALT SPECIALTIES CO., INC. 5 $2,495,000.00 96.91 SHE 052A-020 SH 52, I-25 TO US 287 4 R

04042904 TRICON KENT COMPANY 5 $1,342,079.19 98.08 NH 2852-010 US 285 & COUNTY RD. G 5 R

Page 8: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 5 2004 Cost Data PROJECTS BID FROM 01/01/04 THROUGH 12/31/04------------------------------------------------------------------------------------------------------------------------------------ BID CONTRACTOR/LETTING PROJECT NUMBER LOCATION DIST TERRAIN BIDS AWARDED BID INDEX------------------------------------------------------------------------------------------------------------------------------------04051301 NEW DESIGN CONSTRUCTION CO. 3 $434,048.22 101.84 NH 1602-101 SOUTH FORK JOINT SEAL 5 M

04051303 HAYWARD BAKER, INC. 1 $65,954.00 92.36 BR 0362-028 BRIDGE OVER KIOWA CREEK 1 R

04052001 KIRKLAND CONSTRUCTION, RLLP 3 $2,557,928.70 77.19 STA 165A-010 ON SH 165A FROM I-25 TO W/O RY 2 R

04052002 ELAM CONSTRUCTION, INC. 4 $3,131,076.40 99.22 STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 3 R

04052003 EVERIST MATERIALS, LLC 2 $455,674.34 84.05 STA 0092-017 2 MILES N. OF SILVERTHORNE 1 M

04052701 PENHALL COMPANY 4 $391,282.25 105.99 BR 0092-018 SH 9, SOUTH OF KREMMLING 3 M

04052702 HENKELS & McCOY, INC. 13 $414,822.63 86.79 AQC R600-215 SH 287, US 36 TO SH 128 6 U

04052703 A-1 CHIPSEAL COMPANY 2 $737,737.00 102.44 STA R400-170 EAST OF HUDSON, EAST 4 R

04060301 CONCRETE WORKS OF COLORADO INC. CONTRACT REJ - NO REASON GIVEN NH 0821-064 SH 82, GLENWOOD SPGS - ALT A 3 M

04060302 CONCRETE WORKS OF COLORADO INC. 2 $3,172,912.70 95.76 NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 3 M

04060303 CONCRETE WORKS OF COLORADO INC. CONTRACT REJ - NO REASON GIVEN NH 0821-064 SH 82, GLENWOOD SPGS - ALT C 3 M

04060304 SEMA CONSTRUCTION, INC. 6 $9,822,222.22 97.02 NH 0852-089 US 85, C-470 TO LOUVIER 1 R

04061001 ASPHALT PAVING CO. 4 $2,657,256.14 110.48 NH 0361-076 US 36 IN BOULDER COUNTY 4 R

04061002 53 CORPORATION, LLC 4 $461,759.40 90.59 CC R600-225 CHATFIELD STATE PARK 6 U

04061003 A-1 CHIPSEAL COMPANY 3 $1,047,777.00 113.17 STA R400-169 R-4 CHIP SEALS EAST 4 R

04061702 ASPHALT SPECIALTIES CO., INC. 4 $4,034,586.35 92.83 IM 0253-186 I-25, 120TH TO SH 7 6 R

04061703 MCATEE CONSTRUCTION CO. 5 $3,309,755.45 109.00 STA 0343-023 US 34, EAST OF AKRON 4 R

Page 9: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 6 2004 Cost Data PROJECTS BID FROM 01/01/04 THROUGH 12/31/04------------------------------------------------------------------------------------------------------------------------------------ BID CONTRACTOR/LETTING PROJECT NUMBER LOCATION DIST TERRAIN BIDS AWARDED BID INDEX------------------------------------------------------------------------------------------------------------------------------------04061704 XKE CONTRACTORS INC 4 $903,772.20 100.39 SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 2 U

04061705 INTEGRATED WATER SERVICES, INC. 3 $802,553.00 102.72 IM 0702-239 HANGING LAKES REST AREAS 3 M

04061706 ZAK DIRT, INC. 3 $570,579.19 124.89 STA R400-146 HOLYOKE AREA, STR. B-28-A & A- 4 P

04061708 DUCKELS CONSTRUCTION, INC. 7 $2,069,143.37 125.77 BR 0063-013 SH 6, PAWNEE CREEK STR. B-23-A 4 P

04061709 DKS ENTERPRISES INC. 9 $113,692.50 111.11 STA R400-168 R4 DILEMMA ZONE SAFETY PROJECT 4 P

04062402 BRANNAN SAND AND GRAVEL COMPANY 5 $3,183,834.35 109.30 IM 0761-185 I-76, LOCHBUIE TO HUDSON 4 P

04070101 KIRKLAND CONSTRUCTION, RLLP 7 $2,675,014.35 96.36 STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 3 M

04070104 SCHMIDT CONSTRUCTION COMPANY 4 $2,716,510.75 112.17 STA 086A-040 SH 86, ELBERT COUNTY 1 R

04070105 SEMA CONSTRUCTION, INC. 6 $13,055,555.00 111.41 IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 4 R

04071503 XKE CONTRACTORS INC 2 $156,568.50 105.03 SHE 105A-011 SH 105 NEAR SEDALIA 1 R

04071505 POWER ELECTRIC COMPANY 5 $179,288.23 123.74 SHE 0091-023 SH 9 VMS - FAIRPLAY TO FRISCO 1 M

04071506 EDWARD KRAEMER & SONS INC. 3 $2,080,457.61 157.80 BR 0061-073 US 6 OVER CLEAR CREEK AND ELK 1 M

04071507 AMERICAN CIVIL CONSTRUCTORS, INC. 3 $1,033,650.00 115.57 BR 0243-063 EAST OF LIMON 1 P

04072203 JALISCO INTERNATIONAL, INC. CONTRACT REJ - NO REASON GIVEN NH 0404-039 COLO. BLVD IN IDAHO SPRINGS 1 M

04072901 EDWARD KRAEMER & SONS INC. 4 $21,876,939.55 109.47 IMD 0252-364 I-25 OVER BROADWAY 6 U

04072903 A & S CONSTRUCTION CO. & AFFILIATED CO. 3 $923,043.00 102.76 STA R200-128 SH10, SH350 , SH160 MAINT. 2 P

04080502 BTE CONCRETE FORMWORK LLC 4 $1,349,754.00 137.38 IM 0701-168 RIFLE TO SILT SLAB REPAIR 3 M

Page 10: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 7 2004 Cost Data PROJECTS BID FROM 01/01/04 THROUGH 12/31/04------------------------------------------------------------------------------------------------------------------------------------ BID CONTRACTOR/LETTING PROJECT NUMBER LOCATION DIST TERRAIN BIDS AWARDED BID INDEX------------------------------------------------------------------------------------------------------------------------------------04080503 STURGEON ELECTRIC COMPANY, INC 2 $859,202.05 81.84 SHE 0253-184 I-25 NEAR LARKSPUR 1 R

04080505 POWER ELECTRIC COMPANY 5 $160,875.67 120.94 STA 2854-107 SH285 / CR43A IN PARK COUNTY 1 M

04080508 AMERICAN WEST CONSTRUCTION, LLC 4 $1,151,897.65 115.22 IM 0702-250 I-70 CULVERT REPAIRS (ALT. A) 1 M

04080508 AMERICAN WEST CONSTRUCTION, LLC CONTRACT REJ - NO REASON GIVEN IM 0702-250 I-70 CULVERT REPAIRS (ALT. B) 1 M

04081201 ROCKY MOUNTAIN MATERIALS & ASPHALT, INC. 3 $5,181,045.10 88.94 NH 0243-068 US 24, CONSTITUTION TO GARRETT 2 R

04081206 DUCKELS CONSTRUCTION, INC. 5 $5,191,229.81 109.63 STA 0091-016 PARK AVENUE IN BRECKENRIDGE 1 M

04081901 TLM CONSTRUCTORS, INC. 5 $1,265,770.60 113.37 C 060A-006 SH 60 & SH 257 IN MILLIKEN 4 R

04082601 KIEWIT WESTERN CO 3 $965,714.50 98.11 SHE 4701-105 C-470; BROADWAY TO I-25 6 R

04082602 CUSTOM LIGHTING SERVICES, LLC CONTRACT REJ - NO REASON GIVEN SHE 5502-047 SH550, DEER WARNING - MONTROSE 3 M

04091601 HAMON CONTRACTORS, INC. CONTRACT REJ - NO REASON GIVEN BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 7 6 U

04091602 W.L.H. CONSTRUCTION COMPANY 1 $722,496.00 99.55 STA 149A-021 SH 149 CRIBWALL 5 M

04091603 GONZALES CONSTRUCTION COMPANY, INC. CONTRACT REJ - NO REASON GIVEN BR C480-001 US160 & SH84 BRIDGE RAIL 5 M

04091605 NIELSONS SKANSKA, INC. 4 $6,265,091.20 101.25 NH 1602-100 GRANDVIEW 4TH LANE 5 R

04092301 FRONT RANGE BARRICADE 4 $148,321.00 112.43 SHE 0403-049 US 40, EAST OF CRAIG 3 R

04092302 KIEWIT WESTERN CO 4 $4,459,369.25 96.13 IM 0251-167 PINON REST AREAS ON I-25, MP 1 2 R

04100701 KIEWIT WESTERN CO 5 $493,166.50 82.38 SHE 105A-010 SH 105/FURROW RD 2 R

04100703 INTERFACE COMMUNICATIONS, COMPANY 6 $136,238.11 89.64 SHE 5502-047 SH550 AT MP 112.7, IN OURAY CO 3 M

Page 11: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 8 2004 Cost Data PROJECTS BID FROM 01/01/04 THROUGH 12/31/04------------------------------------------------------------------------------------------------------------------------------------ BID CONTRACTOR/LETTING PROJECT NUMBER LOCATION DIST TERRAIN BIDS AWARDED BID INDEX------------------------------------------------------------------------------------------------------------------------------------04100704 YENTER COMPANIES, INC. 2 $476,475.00 91.11 STA 0703-290 GEORGETOWN HILL ROCKFALL MITIG 1 R

04101402 YENTER COMPANIES, INC. CONTRACT REJ - NO REASON GIVEN SHE R400-172 R-4 SAFETY PROJECTS PHASE II 4 M

04101404 AMERICAN WEST CONSTRUCTION, LLC 2 $221,705.00 71.08 C 0702-253 I-70 CULVERT REPAIRS Ph II 1 M

04102101 NIELSONS SKANSKA, INC. 5 $1,349,521.15 73.31 C 1601-054 US 160 MONTOYA SLIDE #1 5 M

04102102 ARAPAHOE UTILITIES & INFRASTRUCTURE, INC 8 $712,644.60 96.35 BR 0361-064 DRAW W. OF LAST CHANCE 4 R

04102801 JALISCO INTERNATIONAL, INC. 6 $13,199,280.10 99.88 IM 0253-173 I-25 / 120TH BRIDGE REPLACEMEN 6 U

04111801 INTERSTATE HIGHWAY CONSTRUCTION 9 $478,213.90 109.51 NH 2873-137 US 287 IN BOULDER & LARIMER CO 4 R

04111802 HAMON CONTRACTORS, INC. 4 $6,326,718.25 96.72 BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 7 6 U

04111803 DKS ENTERPRISES INC. 5 $497,402.90 99.69 C R600-232 SH 285 AT VARIOUS LOCATIONS 6 R

04111804 SIMON CONTRACTORS 7 $2,296,134.01 93.81 IM 0705-074 I-70, WEST OF BURLINGTON 1 P

04113001 KIEWIT WESTERN CO 3 $681,775.00 112.74 ER 0702-255 I-70 GLENWOOD CANYON 3 M

04120201 NEW DESIGN CONSTRUCTION CO. 3 $889,723.60 103.88 MC R600-226 R-6, BRIDGE DECK REPAIR 6 R

04120202 KIEWIT WESTERN CO 3 $1,416,858.00 123.85 STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 1 P

04120902 BRANNAN SAND AND GRAVEL COMPANY 6 $753,539.95 98.54 STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 6 R

04122301 ASPHALT SPECIALTIES CO., INC. 5 $1,546,116.80 99.17 STA 0073-006 SH 7: 1ST AVENUE TO I-76 6 U

04122302 BRANNAN SAND AND GRAVEL COMPANY 5 $2,017,379.82 99.26 NH 0853-054 US 85 - 136TH TO WELD CTY ROAD 6 R

04122303 BRANNAN SAND AND GRAVEL COMPANY 4 $1,270,374.57 93.66 STA 1281-009 SH 128- US 287 TO MELODY 6 R

Page 12: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 9 2004 Cost Data PROJECTS BID FROM 01/01/04 THROUGH 12/31/04------------------------------------------------------------------------------------------------------------------------------------ BID CONTRACTOR/LETTING PROJECT NUMBER LOCATION DIST TERRAIN BIDS AWARDED BID INDEX------------------------------------------------------------------------------------------------------------------------------------04122304 PREMIER PAVING, INC. 6 $929,415.50 94.24 STA 391A-002 KIPLING: US 40 TO 38TH AVE. 6 R

04122308 A & S CONSTRUCTION CO. & AFFILIATED CO. 3 $2,163,997.50 99.52 NH 2854-104 SH 285 - KENOSHA PASS EAST 1 M

04122309 ROCK & COMPANY 4 $318,677.50 100.16 STA 145A-035 SH145 - OPHIR CRIBWALL FAILURE 5 M

04122310 KIEWIT WESTERN CO 3 $4,972,207.50 115.04 IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 1 M

04122311 A & S CONSTRUCTION CO. & AFFILIATED CO. 6 $4,147,132.30 105.61 NH 0502-055 DAWSON CREEK TO MONARCH PASS 5 M

04122312 A & S CONSTRUCTION CO. & AFFILIATED CO. 3 $1,887,632.20 110.31 NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALIDA 5 M

04122313 BRANNAN SAND AND GRAVEL COMPANY 6 $1,267,374.26 96.34 STA 0831-093 PARKER RD: PEORIA TO JEWELL AV 6 U

04122314 BRANNAN SAND AND GRAVEL COMPANY 4 $692,517.94 89.94 NH 0021-026 SH2 - 124TH TO BROMLEY LN 6 P

04122315 BRANNAN SAND AND GRAVEL COMPANY 5 $1,071,133.05 104.65 STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 6 U

04122316 NORAA CONCRETE CONSTRUCTION CORPORATION 6 $324,016.80 107.85 NH 0831-095 SH 83, LINCOLN AVE. - PARKER S 1 U

04122317 AGGREGATE INDUSTRIES - WCR, INC. 6 $869,601.10 116.11 NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC S 6 U

======= ================ ====== TOTALS 639 $325,537,920.91 98.59

Page 13: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 1 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

201-00000 Clearing and Grubbing 22 Lump Sum 648,764.34 29,489.29201-00001 Clearing and Grubbing 5 Acre 5,250.00 1,050.00202-00000 Removal of Structures and Obstructions 4 Lump Sum 108,923.13 27,230.78202-00001 Removal of Structure 233 Each 163,993.25 703.83

202-00002 Removal of Structure (Special) 23 Each 84,388.80 3,669.08202-00003 Removal of Structure (Special) 1 Lump Sum 18,000.00 18,000.00202-00009 Tree Trimming 1 Lump Sum 1,500.00 1,500.00202-00010 Removal of Tree 206 Each 55,923.17 271.47

202-00011 Tree Trimming 15 Each 4,824.75 321.65202-00015 Removal of Headwall 30 Each 15,474.64 515.82202-00019 Removal of Inlet 28 Each 25,806.00 921.64202-00020 Removal of Concrete Box Culvert 30 Each 49,420.00 1,647.33

202-00023 Removal of Embankment Protector Type 3 4 Each 1,115.00 278.75202-00024 Removal of Embankment Protector Type 5 5 Each 1,870.00 374.00202-00025 Removal of Ditch Lining 35 Lin Foot 245.00 7.00202-00026 Removal of Slope and Ditch Paving 419 Sq Yard 7,193.40 17.17

202-00027 Removal of Riprap 44 Sq Yard 517.44 11.76202-00030 Removal of Water Service 2 Each 3,625.00 1,812.50202-00033 Removal of Pipe 128 Each 108,502.83 847.68202-00035 Removal of Pipe 11,382 Lin Foot 123,602.98 10.86

202-00037 Removal of End Section 210 Each 28,932.67 137.77202-00040 Removal of Electrical Conduit 450 Lin Foot 1,125.00 2.50202-00070 Removal of Barricade 15 Each 1,350.00 90.00202-00080 Removal of Guard Post 54 Each 1,428.00 26.44

202-00090 Removal of Delineator 5,111 Each 28,641.30 5.60202-00100 Removal of Dome Channelizing Device 7 Each 1,400.00 200.00202-00150 Removal of Wall 2 Each 4,200.00 2,100.00202-00155 Removal of Wall 241 Lin Foot 29,990.48 124.44

202-00165 Removal of Wall 1 Lump Sum 15,275.00 15,275.00202-00170 Grinding And Texturing Concrete Pavement 38,812 Sq Yard 236,753.20 6.10202-00175 Removal of Concrete 2 Lump Sum 1,790.00 895.00202-00190 Removal of Concrete Median Cover Material 1,914 Sq Yard 7,335.00 3.83

202-00195 Removal of Median Cover 14,852 Sq Yard 45,564.07 3.07202-00200 Removal of Sidewalk 22,362 Sq Yard 171,863.91 7.69202-00201 Removal of Curb 106,251 Lin Foot 196,815.51 1.85202-00202 Removal of Gutter 1,456 Lin Foot 10,104.75 6.94

202-00203 Removal of Curb and Gutter 123,268 Lin Foot 449,535.08 3.65202-00204 Removal of Curb, Gutter and Sidewalk 1,723 Lin Foot 8,446.00 4.90

Page 14: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 2 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

202-00206 Removal of Concrete Curb Ramp 671 Sq Yard 11,811.54 17.60202-00210 Removal of Concrete Pavement 86,618 Sq Yard 633,420.62 7.31202-00212 Removal of Concrete Pavement 10 Sq Yard 510.00 51.00202-00215 Removal of Concrete Pavement (Planing) 16,350 Sq Yard 36,397.30 2.23

202-00220 Removal of Asphalt Mat 519,650 Sq Yard 1,439,192.12 2.77202-00226 Removal of Asphalt Mat (Special) 15 Sq Yard 107.40 7.16202-00240 Removal of Asphalt Mat (Planing) 4,858,548 Sq Yard 5,997,202.94 1.23202-00246 Removal of Asphalt Mat (Planing) (Special) 7,527 Sq Yard 46,028.50 6.12

202-00250 Removal of Pavement Marking 431,830 Sq Foot 323,742.27 0.75202-00400 Removal of Bridge 13 Each 2,556,616.18 196,662.78202-00410 Removal of Mat From Bridge 1,023 Sq Yard 4,092.00 4.00202-00425 Removal of Bridge Railing 8,619 Lin Foot 74,179.95 8.61

202-00450 Removal of Portions of Present Structure (Class 1) 334 Sq Yard 11,030.00 33.02202-00453 Removal of Portions of Present Structure (Class 2) 1,595 Sq Yard 235,526.00 147.67202-00454 Removal of Portions of Present Structure (Class 2A) 170 Sq Yard 22,872.32 134.54202-00456 Removal of Portions of Present Structure (Class 2B) 100 Sq Yard 12,600.00 126.00

202-00460 Removal of Portions of Present Structure (Class 3) 83 Sq Yard 33,915.00 408.61202-00462 Removal of Portions of Present Structure (Class 3A) 20 Sq Yard 7,600.00 380.00202-00495 Removal of Portions of Present Structure 15 Lump Sum 105,249.25 7,016.62202-00500 Removal of Portions of Present Structure 15 Each 386,774.04 25,784.94

202-00503 Removal of Portions of Present Structure 261 Sq Yard 94,516.50 362.13202-00504 Removal of Expansion Device 1,319 Lin Foot 65,816.90 49.90202-00520 Removal of Expansion Joint Material 625 Lin Foot 7,630.00 12.21202-00610 Removal of Railroad Track 50 Lin Foot 1,050.00 21.00

202-00700 Removal of Light Standard 186 Each 19,583.05 105.29202-00750 Removal of Luminaire 191 Each 5,970.00 31.26202-00805 Removal of Overhead Sign Structure 4 Each 7,256.00 1,814.00202-00806 Removal of Walkway 2,082 Lin Foot 18,738.00 9.00

202-00810 Removal of Ground Sign 1,578 Each 58,643.24 37.16202-00815 Removal of Sign (Special) 12 Each 900.00 75.00202-00821 Removal of Sign Panel 205 Each 5,631.37 27.47202-00825 Removal of Flashing Beacon 14 Each 2,443.20 174.51

202-00828 Removal of Traffic Signal Equipment 8 Lump Sum 36,443.99 4,555.50202-00830 Removal of Traffic Signal Face 16 Each 1,094.40 68.40202-00831 Removal of Traffic Signal Head 15 Each 1,376.12 91.74202-00840 Removal of Traffic Signal Pole 12 Each 5,450.00 454.17

202-00842 Removal of Mast Arm 4 Each 2,040.00 510.00202-00855 Removal of Traffic Signal Controller Cabinet 1 Each 400.00 400.00

Page 15: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 3 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

202-00895 Removal of Impact Attenuator 6 Each 3,050.00 508.33202-00900 Removal of Concrete Footing 102 Each 12,860.00 126.08202-00950 Removal of Concrete Foundation and Slab 4 Sq Yard 1,524.00 381.00202-01000 Removal of Fence 469,417 Lin Foot 199,391.23 0.42

202-01030 Removal of Road Closure Gate 4 Each 1,710.00 427.50202-01130 Removal of Guardrail Type 3 104,482 Lin Foot 287,046.47 2.75202-01140 Removal of Guardrail Type 4 20,083 Lin Foot 150,680.46 7.50202-01150 Removal of Guardrail Type 5 1,540 Lin Foot 3,773.00 2.45

202-01170 Removal of Guardrail Type 7 227 Lin Foot 1,243.20 5.48202-01300 Removal of End Anchorage 623 Each 84,886.94 136.26202-04001 Plug Culvert 58 Each 28,705.05 494.91202-04002 Clean Culvert 307 Each 149,438.33 486.77

202-04003 Clean Culvert (Special) 1 Each 500.00 500.00202-04005 Clean Valve Box 351 Each 44,157.15 125.80202-04100 Abandon Well 5 Each 1,930.00 386.00202-05008 Sawing Concrete (8 Inch) 1,203 Lin Foot 5,211.00 4.33

202-05026 Sawing Asphalt Material (6 Inch) 3,858 Lin Foot 5,599.00 1.45202-05100 Sandblasting Reinforcing Steel 8 Sq Yard 480.00 60.00202-05150 Sandblasting 98,735 Sq Foot 70,970.44 0.72202-06000 Removal of Detour 1 Lump Sum 5,000.00 5,000.00

202-06530 Clean Drain Pipe (Special) 6 Each 4,800.00 800.00202-07000 Obliterate Old Road 2 Lump Sum 3,000.00 1,500.00203-00000 Unclassified Excavation 22,116 Cubic Yard 262,520.55 11.87203-00010 Unclassified Excavation (Complete In Place) 1,626,070 Cubic Yard 7,778,845.60 4.78

203-00040 Unclassified Excavation (Special) 3,100 Cubic Yard 12,400.00 4.00203-00060 Embankment Material (Complete In Place) 1,800,255 Cubic Yard 7,410,485.02 4.12203-00061 Embankment Material (Complete In Place) 1,850 Ton 20,350.00 11.00203-00100 Muck Excavation 7,984 Cubic Yard 101,179.00 12.67

203-00210 Borrow (Complete In Place) 10,752 Cubic Yard 118,133.50 10.99203-00400 Rock Excavation 17,136 Cubic Yard 324,111.10 18.91203-00440 Rock Excavation (Special) 1,100 Cubic Yard 20,823.00 18.93203-00598 Rock Scaling 160 Hour 9,600.00 60.00

203-00700 Reclaim Pit 2 Each 1,000.00 500.00203-00850 Expanded Polystyrene Fill (Complete In Place) 6,250 Cubic Yard 450,000.00 72.00203-01100 Proof Rolling 858 Hour 72,229.20 84.18203-01140 Rolling 236 Hour 17,840.00 75.59

203-01500 Blading 4,354 Hour 446,996.15 102.66203-01510 Backhoe 1,145 Hour 125,917.93 109.97

Page 16: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 4 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

203-01515 Backhoe (Landscaping) 60 Hour 6,341.00 105.68203-01525 Backhoe (Special) 20 Hour 1,200.00 60.00203-01550 Dozing 758 Hour 90,707.34 119.67203-01551 Dozing (Heavy) 16 Hour 1,440.00 90.00

203-01555 Dozing (Landscaping) 52 Hour 4,716.00 90.69203-01582 Truck (Dump) 267 Hour 21,419.20 80.22203-01590 Front End Loader (Rubber Tire) 191 Hour 17,990.00 94.19203-01594 Combination Loader 890 Hour 80,631.12 90.60

203-01597 Potholing 3,838 Hour 454,921.56 118.53203-01620 Sweeping 50 Hour 3,000.00 60.00203-02060 Presplitting 300 Lin Foot 600.00 2.00203-02300 Rock Scaler 304 Hour 42,918.22 141.18

203-02310 Scaler Foreman 104 Hour 11,147.55 107.19203-02330 Laborer 724 Hour 30,049.84 41.51206-00000 Structure Excavation 163,338 Cubic Yard 1,304,109.76 7.98206-00050 Structure Backfill (Special) 61,982 Cubic Yard 384,135.00 6.20

206-00060 Structure Backfill (Special) (Flow-Fill) 224 Cubic Yard 14,770.00 65.94206-00065 Structure Backfill (Flow-Fill) 6,092 Cubic Yard 539,452.57 88.55206-00100 Structure Backfill (Class 1) 149,196 Cubic Yard 1,839,989.36 12.33206-00200 Structure Backfill (Class 2) 4,288 Cubic Yard 41,879.32 9.77

206-00360 Mechanical Reinforcement of Soil 117,645 Cubic Yard 2,894,394.33 24.60206-00505 Filter Material (Special) 4,619 Cubic Yard 103,073.91 22.32206-00510 Filter Material (Class A) 1,658 Cubic Yard 86,239.63 52.01206-00520 Filter Material (Class B) 327 Cubic Yard 10,631.74 32.51

206-00530 Filter Material (Class C) 23 Cubic Yard 736.00 32.00206-01000 Bed Course Material 874 Cubic Yard 17,979.45 20.57206-01750 Shoring 6 Lump Sum 169,696.65 28,282.78206-01781 Shoring (Area 1) 6 Lump Sum 196,180.00 32,696.67

206-01782 Shoring (Area 2) 3 Lump Sum 140,000.00 46,666.67206-01783 Shoring (Area 3) 2 Lump Sum 45,000.00 22,500.00206-01784 Shoring (Area 4) 1 Lump Sum 10,000.00 10,000.00206-01785 Shoring (Area 5) 1 Lump Sum 80,000.00 80,000.00

206-01786 Shoring (Area 6) 1 Lump Sum 20,000.00 20,000.00206-01787 Shoring (Area 7) 1 Lump Sum 25,000.00 25,000.00207-00205 Topsoil 184,328 Cubic Yard 1,127,999.86 6.12207-00210 Stockpile Topsoil 1,368 Cubic Yard 5,472.00 4.00

207-00305 Wetland Topsoil 1,638 Cubic Yard 20,753.20 12.67207-00310 Stockpile Wetland Topsoil 1,546 Cubic Yard 12,660.60 8.19

Page 17: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 5 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

208-00001 Silt Dike 500 Lin Foot 3,816.00 7.63208-00002 Erosion Log (12 Inch) 7,214 Lin Foot 32,557.50 4.51208-00004 Silt Berm 300 Lin Foot 1,620.00 5.40208-00005 Erosion Log 33,123 Lin Foot 163,170.09 4.93

208-00006 Erosion Log (Special) 37,756 Lin Foot 123,215.80 3.26208-00007 Erosion Log (8 Inch) 1,060 Lin Foot 4,216.00 3.98208-00010 Erosion Bales 346 Each 4,073.38 11.77208-00011 Erosion Bales (Weed Free) 4,965 Each 59,379.83 11.96

208-00020 Silt Fence 101,569 Lin Foot 163,676.87 1.61208-00030 Sediment Basin 4 Each 290,026.14 72,506.54208-00033 Sediment Trap 6 Each 23,599.84 3,933.31208-00040 Check Dam 20 Each 4,685.00 234.25

208-00045 Concrete Washout Structure 307 Each 172,809.87 562.90208-00050 Storm Drain Inlet Protection 1,007 Each 151,689.26 150.63208-00051 Storm Drain Inlet Protection 321 Lin Foot 8,949.00 27.88208-00055 Rigid Inlet Protection Device 40 Each 17,050.00 426.25

208-00060 Temporary Slope Drain 1,000 Lin Foot 18,491.70 18.49208-00070 Stabilized Construction Entrance 43 Each 46,262.84 1,075.88208-00100 Sediment Removal and Disposal 21 Lump Sum 46,577.25 2,217.96208-00110 Sediment Removal and Disposal 900 Cubic Yard 10,790.98 11.99

208-00200 Erosion Control Supervisor 35 Lump Sum 238,724.01 6,820.69208-00205 Erosion Control Supervisor 2,027 Hour 113,603.94 56.05208-00300 Temporary Berms 4,755 Lin Foot 4,755.00 1.00209-00000 Water 80 M Gallon 3,200.00 40.00

209-00100 Water (Landscaping) 15 M Gallon 4,267.78 284.52209-00200 Time-Released Water Product 400 Each 1,860.00 4.65209-00600 Dust Palliative (Magnesium Chloride) 78,821 Gallon 44,824.50 0.57210-00001 Reset Structure 18 Each 16,755.00 930.83

210-00010 Reset Mailbox Structure 15 Each 2,349.14 156.61210-00011 Reset Mailbox Structure (Type 1) 131 Each 17,276.00 131.88210-00012 Reset Mailbox Structure (Type 2) 20 Each 3,450.00 172.50210-00013 Reset Mailbox Structure (Type 3) 64 Each 21,592.00 337.38

210-00014 Reset Mailbox Structure (Type 4) 37 Each 16,290.00 440.27210-00015 Reset End Section 3 Each 2,200.00 733.33210-00030 Reset Water Service 1 Each 800.00 800.00210-00035 Reset Water Meter 12 Each 9,122.64 760.22

210-00050 Reset Fire Hydrant 13 Each 25,527.16 1,963.63210-00060 Reset Marker 8 Each 830.00 103.75

Page 18: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 6 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

210-00065 Reset Monument (Type 3A) 1 Each 560.00 560.00210-00090 Reset Delineator 957 Each 73,752.50 77.07210-00200 Reset Flagpole 1 Each 300.00 300.00210-00400 Reset Bridge Expansion Device 524 Lin Foot 29,873.70 57.01

210-00410 Modify Bridge Expansion Device 2 Each 23,004.10 11,502.05210-00425 Reset Bridge Railing 125 Lin Foot 1,562.50 12.50210-00440 Repair Curb 30 Lin Foot 1,380.00 46.00210-00473 Reset TV Cameras 4 Each 736.00 184.00

210-00750 Reset Light Standard 15 Each 15,350.00 1,023.33210-00760 Reset Luminaire 3 Each 481.00 160.33210-00805 Reset Overhead Sign Structure 2 Each 8,000.00 4,000.00210-00810 Reset Ground Sign 721 Each 82,744.87 114.76

210-00815 Reset Sign Panel 72 Each 8,804.17 122.28210-00820 Reset Variable Message Sign 1 Each 2,500.00 2,500.00210-00825 Reset Flashing Beacon 8 Each 9,440.00 1,180.00210-00830 Reset Traffic Signal Face 2 Each 530.00 265.00

210-00831 Reset Traffic Signal Head 6 Each 2,480.50 413.42210-00840 Reset Traffic Signal Pole 4 Each 6,564.00 1,641.00210-00848 Reset Traffic Signal Controller and Cabinet 5 Each 5,300.00 1,060.00210-00855 Reset Traffic Signal Controller Cabinet 3 Each 3,730.00 1,243.33

210-00858 Reset Pedestal Pole 3 Each 3,049.40 1,016.47210-00860 Reset Pedestrian Push Button 7 Each 532.40 76.06210-00865 Reset Pedestrian Signal Head 1 Each 250.00 250.00210-00866 Reset Fire Preemption Unit and Timer 2 Each 656.00 328.00

210-00867 Reset Fire Preemption Unit 2 Each 605.00 302.50210-00870 Reset Coordination Unit 3 Each 1,368.00 456.00210-00873 Reset Tone Decoder 3 Each 120.00 40.00210-00882 Reset Traffic Signal Vehicle Detector 1 Each 513.60 513.60

210-00890 Reset Intersection Detection System (Camera) 3 Each 3,675.00 1,225.00210-01000 Reset Fence 7,921 Lin Foot 19,773.60 2.50210-01011 Reset Gate 9 Each 1,435.00 159.44210-01050 Reset Chain Link Fence 4,325 Lin Foot 24,868.75 5.75

210-01130 Reset Guardrail Type 3 27,950 Lin Foot 237,797.15 8.51210-01140 Reset Guardrail Type 4 6,366 Lin Foot 55,635.00 8.74210-01200 Reset End Anchorage 19 Each 14,243.03 749.63210-01700 Reset Sprinkler Head 7 Each 364.00 52.00

210-02900 Relay Riprap 817 Cubic Yard 35,260.00 43.16210-03100 Replace Concrete Pavement 2,500 Sq Yard 218,750.00 87.50

Page 19: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 7 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

210-04000 Adjust Structure 16 Each 4,805.00 300.31210-04010 Adjust Manhole 1,290 Each 399,181.83 309.44210-04015 Modify Manhole 12 Each 15,379.19 1,281.60210-04020 Modify Inlet 71 Each 165,665.57 2,333.32

210-04025 Modify Structure 57 Each 34,852.00 611.44210-04030 Modify Guardrail 2,384 Lin Foot 36,456.00 15.29210-04050 Adjust Valve Box 1,151 Each 217,029.88 188.56210-04200 Adjust Guardrail 120,263 Lin Foot 449,329.75 3.74

211-00100 Drilling Hole 1,248 Lin Foot 16,224.00 13.00211-01111 Rock Reinforcement (Dowels) 2,000 Lin Foot 61,275.00 30.64211-01200 Rock Anchor 600 Lin Foot 25,200.00 42.00211-02116 Rock Dowel 6,570 Lin Foot 236,865.53 36.05

211-02270 Cement Grout 2,000 Cubic Foot 20,000.00 10.00212-00006 Seeding (Native) 837 Acre 324,859.07 388.12212-00010 Seeding (Lawn) 3 Pound 320.00 106.67212-00011 Seeding (Lawn) 0 Acre 609.75

212-00022 Seeding (Riparian) 2 Acre 6,600.00 3,300.00212-00028 Seeding (Wetlands) 1 Acre 11,288.90 11,288.90212-00047 Soil Preparation (Special) 417 Acre 596,503.70 1,430.46212-00048 Soil Preparation (Special) 4 Cubic Yard 120.00 30.00

212-00050 Sod 42,292 Sq Foot 27,026.05 0.64213-00000 Mulching 49 Acre 15,230.00 310.82213-00002 Mulching (Weed Free Hay) 559 Acre 208,796.80 373.52213-00003 Mulching (Weed Free) 142 Acre 55,972.19 394.17

213-00004 Mulching (Weed Free Straw) 66 Acre 37,098.50 562.10213-00005 Mulching (Decorative) 24,550 Cubic Foot 27,803.30 1.13213-00008 Mulching (Wood Chip) 4,750 Cubic Foot 9,500.00 2.00213-00061 Mulch Tackifier 147,734 Pound 236,162.71 1.60

213-00100 Soil Binder 144 Acre 47,512.50 329.95213-00300 Concrete Landscape Border 1,525 Lin Foot 24,400.00 16.00213-00462 Metal Landscape Border (3/16 X 5-1/2 Inch) 315 Lin Foot 1,638.00 5.20213-00700 Landscape Boulder 70 Each 8,100.00 115.71

213-00705 Landscape Boulder (Special) 9 Each 5,400.00 600.00214-00000 Landscape Maintenance 1 Lump Sum 21,000.00 21,000.00214-00201 Deciduous Tree (Tubeling) 50 Each 362.50 7.25214-00215 Deciduous Tree (1.5 Inch Caliper) 77 Each 16,974.45 220.45

214-00230 Deciduous Tree (3 Inch Caliper) 27 Each 13,675.00 506.48214-00310 Deciduous Shrub (1 Gallon Container) 139 Each 2,363.00 17.00

Page 20: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 8 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

214-00350 Deciduous Shrub (5 Gallon Container) 1,402 Each 51,599.95 36.80214-00401 Evergreen Tree (Tubeling) 50 Each 375.00 7.50214-00502 Evergreen Tree (2 Foot) (Ball and Burlap) 26 Each 4,641.56 178.52214-00504 Evergreen Tree (4 Foot) (Ball and Burlap) 73 Each 17,271.64 236.60

214-00506 Evergreen Tree (6 Foot) (Ball and Burlap) 114 Each 35,784.73 313.90214-00508 Evergreen Tree (8 Foot) (Ball and Burlap) 22 Each 6,820.00 310.00214-00610 Evergreen Shrub (1 Gallon Container) 80 Each 1,600.00 20.00214-00650 Evergreen Shrub (5 Gallon Container) 203 Each 7,105.00 35.00

214-00905 Perennials (2.25 Inch Pot) 5,050 Each 11,575.00 2.29214-00910 Perennials (1 Gallon Container) 355 Each 4,260.00 12.00214-01010 Brush Layer Cutting 3,610 Each 16,931.56 4.69214-01025 Dormant Log Cutting 10 Each 850.00 85.00

214-01030 Wattle 5 Each 1,125.00 225.00215-00000 Transplant Shrub 27 Each 3,449.25 127.75215-00001 Transplant Shrub 11 Sq Yard 330.00 30.00215-00060 Transplant Tree (3 to 6 Inch) 14 Each 7,000.00 500.00

215-00100 Transplant Tree (Over 6 Inch) 14 Each 8,800.00 628.57215-00500 Transplant Seedling 24 Each 384.00 16.00215-00600 Transplant Plug 2,200 Each 12,299.40 5.59216-00015 Soil Retention Blanket (Excelsior) 8,250 Sq Yard 11,580.00 1.40

216-00035 Soil Retention Blanket (Plastic) 58,700 Sq Yard 185,715.20 3.16216-00037 Soil Retention Blanket (Coconut) 12,375 Sq Yard 20,326.75 1.64216-00039 Soil Retention Blanket (Straw) 52,580 Sq Yard 59,993.00 1.14216-00041 Soil Retention Blanket (Straw/Coconut) 124,590 Sq Yard 155,268.02 1.25

217-00000 Herbicide Treatment 35,515 Sq Yard 6,041.10 0.17217-00020 Herbicide Treatment 220 Hour 27,079.76 123.09218-00000 Noxious Weed Management 1 Lump Sum 6,442.59 6,442.59250-00010 Environmental Health and Safety Management 10 Lump Sum 118,705.37 11,870.54

250-00050 Monitoring Technician 475 Hour 22,599.00 47.58250-00100 Environmental Health and Safety 3 Lump Sum 8,025.00 2,675.00250-00110 Health and Safety Officer 594 Hour 42,579.40 71.68250-00120 Material Sampling and Delivery 74 Each 31,232.82 422.07

250-00200 Material Handling (Stockpile) 160 Cubic Yard 3,100.00 19.38250-00210 Solid Waste Disposal 9,369 Cubic Yard 226,126.47 24.14250-00220 Hazardous Waste Disposal 29 Cubic Yard 4,578.99 157.90304-01000 Aggregate Base Course (Class 1) 54,923 Ton 588,300.60 10.71

304-01005 Aggregate Base Course (Class 1) 22,133 Cubic Yard 296,532.90 13.40304-02000 Aggregate Base Course (Class 2) 57,439 Ton 488,315.80 8.50

Page 21: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 9 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

304-03000 Aggregate Base Course (Class 3) 49,404 Ton 444,590.30 9.00304-05009 Aggregate Base Course (Class 5)(Special) 500 Ton 6,000.00 12.00304-06000 Aggregate Base Course (Class 6) 145,624 Ton 1,874,842.20 12.87304-06004 Aggregate Base Course (Class 6) 3,176 Sq Yard 18,036.70 5.68

304-06007 Aggregate Base Course (Class 6) 56,794 Cubic Yard 1,261,622.55 22.21304-06008 Aggregate Base Course (Class 6) (Special) 8,886 Cubic Yard 157,386.20 17.71304-06009 Aggregate Base Course (Class 6) (Special) 41,034 Ton 416,782.65 10.16304-07000 Aggregate Base Course (Class 7) 44,348 Ton 552,785.47 12.46

304-07009 Aggregate Base Course (Class 7) (Special) 18,257 Ton 352,006.00 19.28304-09000 Aggregate Base Course (Special) 14,985 Cubic Yard 312,583.24 20.86304-09014 Aggregate Base Course (Special) 72,808 Ton 1,008,912.34 13.86304-09055 Aggregate Base Course (Blotter Material) 25 Ton 1,375.00 55.00

306-01000 Reconditioning 129,664 Sq Yard 110,065.60 0.85307-00000 Hydrated Lime 3,458 Ton 345,800.00 100.00307-00212 Processing Lime Treated Subgrade (12 Inch) 40,331 Sq Yard 272,234.25 6.75310-00400 Process Asphalt Mat For Base Course 37,424 Sq Yard 48,651.20 1.30

310-00500 Full Depth Reclamation of Hot Mix Asph. Pavement 263,874 Sq Yard 540,559.30 2.05310-00600 Full Depth Reclam. of Hot Mix Asph. Pvmt over 8 Inche 89,396 Sq Yard 4,469.80 0.05403-00720 Hot Bituminous Pavement (Patching) (Asphalt) 31,937 Ton 2,712,243.65 84.92403-00721 Hot Bituminous Pavement (Patching) (Asphalt) 14,422 Sq Yard 297,128.76 20.60

403-00800 Emergency Pothole Repair 105 Ton 12,625.00 120.24403-01014 Hot Bituminous Pavement 10 Year Warranty 110,144 Sq Yard 750,080.64 6.81403-01020 Warranted Hot Bituminous Pavement System (10 Year) 110,144 Sq Yard 1,610,305.28 14.62403-02000 Hot Bituminous Pavement (Special) 11,677 Ton 455,403.00 39.00

403-09110 Stone Mastic Asphalt 77,372 Ton 3,617,246.60 46.75403-09111 Stone Mastic Asphalt 221,176 Sq Yard 707,763.20 3.20403-09121 Stone Mastic Asphalt (Fibers) (Asphalt) 67,182 Ton 2,941,754.32 43.79403-09126 Stone Mastic Asphalt (Asphalt) (Polymer Modified) 23,267 Ton 952,783.65 40.95

403-09500 Furnish Hot Bituminous Pavement 29,921 Ton 934,484.00 31.23403-32741 Hot Bituminous Pavement (Grading SG) (75) (PG 64-22) 4,883 Ton 180,671.00 37.00403-33701 Hot Bituminous Pavement (Grading S) (75) 19,694 Ton 655,916.55 33.31403-33721 Hot Bituminous Pavement (Grading S) (75) (PG 58-28) 138,234 Ton 4,335,904.05 31.37

403-33741 Hot Bituminous Pavement (Grading S) (75) (PG 64-22) 112,002 Ton 4,063,490.55 36.28403-33751 Hot Bituminous Pavement (Grading S) (75) (PG 64-28) 71,235 Ton 2,657,414.20 37.30403-33821 Hot Bituminous Pavement (Grading S) (100) (PG 58-28) 94,652 Ton 3,039,751.50 32.12403-33831 Hot Bituminous Pavement (Grading S) (100) (PG 58-34) 111,715 Ton 3,609,511.65 32.31

403-33841 Hot Bituminous Pavement (Grading S) (100) (PG 64-22) 275,282 Ton 8,770,210.85 31.86403-33851 Hot Bituminous Pavement (Grading S) (100) (PG 64-28) 79,956 Ton 2,807,804.10 35.12

Page 22: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 10 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

403-33871 Hot Bituminous Pavement (Grading S) (100) (PG 76-28) 251,404 Ton 8,824,649.97 35.10403-34701 Hot Bituminous Pavement (Grading SX) (75) 388,042 Ton 9,980,085.20 25.72403-34721 Hot Bituminous Pavement (Grading SX) (75) (PG 58-28) 69,553 Ton 2,668,089.58 38.36403-34731 Hot Bituminous Pavement (Grading SX) (75) (PG 58-34) 4,548 Ton 272,880.00 60.00

403-34741 Hot Bituminous Pavement (Grading SX) (75) (PG 64-22) 48,599 Ton 1,718,760.00 35.37403-34751 Hot Bituminous Pavement (Grading SX) (75) (PG 64-28) 94,768 Ton 3,709,802.00 39.15403-34801 Hot Bituminous Pavement (Grading SX) (100) 228,880 Ton 4,651,922.59 20.32403-34841 Hot Bituminous Pavement (Grading SX) (100) (PG 64-22) 109,810 Ton 4,265,598.90 38.85

403-34851 Hot Bituminous Pavement (Grading SX) (100) (PG 64-28) 96,168 Ton 3,851,767.25 40.05403-34871 Hot Bituminous Pavement (Grading SX) (100) (PG 76-28) 114,132 Ton 4,510,029.78 39.52403-35701 Hot Bituminous Pavement (Grading S-Fines) (75) 16,871 Ton 354,526.25 21.01405-00000 Heating and Scarifying Treatment 468,968 Sq Yard 719,090.50 1.53

405-00100 Heating and Remixing Treatment 866,580 Sq Yard 2,916,997.60 3.37405-00300 Heating and Repaving Treatment 180,678 Sq Yard 388,457.70 2.15406-09500 Cold Bituminous Pavement (Recycle) 1,042,776 Sq Yard 1,461,366.48 1.40408-01000 Hot Poured Joint and Crack Sealant 29 Ton 51,400.00 1,772.41

409-01010 Cover Coat Material (Type I) 6,434 Ton 234,908.00 36.51409-01015 Cover Coat Material (Type I) 586,291 Sq Yard 322,460.05 0.55409-02055 Cover Coat Material (Type II)(Special) 1,027,464 Sq Yard 925,625.94 0.90409-05000 Ultrathin Bonded Wearing Course 42,963 Sq Yard 249,185.40 5.80

411-03342 Asphalt Cement Performance Grade (PG 64-28) 9,315 Ton 2,364,037.99 253.79411-03345 Asphalt Cement Performance Grade (PG 76-28) 13,215 Ton 3,297,625.29 249.54411-03352 Asphalt Cement Performance Grade (PG 58-28) 9,602 Ton 1,810,046.85 188.51411-03354 Asphalt Cement Performance Grade (PG 64-22) 1,056 Ton 179,520.00 170.00

411-03355 Asphalt Cement Performance Grade (PG 58-34) 8,761 Ton 2,402,315.40 274.21411-10253 Emulsified Asphalt (CSS-1H) 104,302 Gallon 158,254.34 1.52411-10255 Emulsified Asphalt (Slow-Setting) 705,641 Gallon 709,126.86 1.00411-10261 Emulsified Asphalt (Rapid-Setting-2P)(Polymerized) 565,105 Gallon 480,339.25 0.85

411-10275 Emulsified Asphalt (HFMS-2P) (High Float) (Polymerize 217,684 Gallon 255,327.60 1.17411-10300 Emulsified Asphalt (Prime Coat) 35,661 Gallon 41,534.60 1.16411-10375 Emulsified Asphalt (HFRS-2P) (High Float) (Polymerize 234,517 Gallon 246,242.85 1.05411-21020 Liquid Asphaltic Material (MC-70) 14,069 Gallon 9,419.25 0.67

411-90010 Asphalt Rejuvenating Agent 116,759 Gallon 256,619.90 2.20411-90040 Recycling Agent 1,478,208 Gallon 1,972,954.00 1.33412-00000 Furnish Concrete Pavement 2,868 Cubic Yard 148,877.88 51.91412-00600 Concrete Pavement (6 Inch) 99,891 Sq Yard 1,695,815.05 16.98

412-00800 Concrete Pavement (8 Inch) 7,221 Sq Yard 367,008.00 50.83412-00801 Concrete Pavement (8 Inch) (Special) 5,236 Sq Yard 356,048.00 68.00

Page 23: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 11 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

412-00805 Concrete Pavement (8 Inch) (Fast Track) 202 Sq Yard 8,793.00 43.53412-00850 Concrete Pavement (8-1/2 Inch) 36,825 Sq Yard 1,046,464.24 28.42412-00870 Concrete Pavement (8-1/2 Inch) (Fast Track) 1,621 Sq Yard 77,808.00 48.00412-00900 Concrete Pavement (9 Inch) 2,805 Sq Yard 87,656.25 31.25

412-00950 Concrete Pavement (9-1/2 Inch) 223 Sq Yard 9,589.00 43.00412-00975 Concrete Pavement (9-3/4 Inch) 32,171 Sq Yard 1,447,679.70 45.00412-00976 Concrete Pavement (9-3/4) (Class E) 2,000 Sq Yard 6,000.00 3.00412-01000 Concrete Pavement (10 Inch) 47,206 Sq Yard 1,573,910.70 33.34

412-01001 Concrete Pavement (10 Inch) (Special) 1,986 Sq Yard 83,412.00 42.00412-01020 Concrete Pavement (10 Inch) (Fast Track) 3,126 Sq Yard 177,713.10 56.85412-01025 Concrete Pavement (10-1/4 Inch) 107,446 Sq Yard 2,968,732.98 27.63412-01050 Concrete Pavement (10-1/2 Inch) 14,750 Sq Yard 475,432.56 32.23

412-01100 Concrete Pavement (11 Inch) 545 Sq Yard 26,944.80 49.44412-01120 Concrete Pavement (11 Inch) (Fast Track) 3,294 Sq Yard 157,256.47 47.74412-01200 Concrete Pavement (12 Inch) 72,909 Sq Yard 2,139,879.15 29.35412-01250 Concrete Pavement (12-1/2 Inch) 12,344 Sq Yard 469,072.00 38.00

412-01350 Concrete Pavement (13-1/2 Inch) 5,558 Sq Yard 305,690.00 55.00412-05000 Partial Depth Repair of Concrete Pavement 1,292 Sq Foot 49,968.00 38.67412-14000 Sawing and Sealing Concrete Pavement Joints 402,381 Lin Foot 546,079.72 1.36412-15000 Routing and Sealing Concrete Pavement Cracks 14,524 Lin Foot 48,755.56 3.36

412-15050 Cross Stitching 308 Each 3,850.00 12.50420-00000 Geomembrane 2,500 Sq Yard 32,250.00 12.90420-00100 Geotextile (Erosion Control) (Class A) 11,639 Sq Yard 25,826.56 2.22420-00101 Geotextile (Erosion Control) (Class B) 1,645 Sq Yard 4,254.00 2.59

420-00110 Geotextile (Drainage) (Class A) 3,997 Sq Yard 6,709.50 1.68420-00130 Geotextile (Separator) (Class A) 1,273 Sq Yard 4,946.00 3.89420-00131 Geotextile (Separator) (Class B) 90,453 Sq Yard 46,856.50 0.52420-00200 Geotextile (Weed Barrier) 470 Sq Yard 662.70 1.41

420-00500 Geotextile (Paving) 1,480,339 Sq Yard 1,245,086.13 0.84420-00510 Geotextile (Crack Reduction) (High Density) 3,092 Sq Yard 45,580.00 14.74502-00100 Drilling Hole to Facilitate Pile Driving 803 Lin Foot 17,255.00 21.49502-00400 End Plate 72 Each 6,426.00 89.25

502-00460 Pile Tip 82 Each 7,530.00 91.83502-08375 Steel Pipe Piling (12-3/4 X 0.375 Inch) 7,359 Lin Foot 290,160.00 39.43502-11057 Steel Piling (HP 10x57) 137 Lin Foot 18,495.00 135.00502-11253 Steel Piling (HP 12x53) 954 Lin Foot 30,528.00 32.00

502-11274 Steel Piling (HP 12x74) 530 Lin Foot 23,320.00 44.00502-11489 Steel Piling (HP 14x89) 953 Lin Foot 38,120.00 40.00

Page 24: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 12 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

503-00018 Drilled Caisson (18 Inch) 34 Lin Foot 4,626.00 136.06503-00024 Drilled Caisson (24 Inch) 205 Lin Foot 10,313.00 50.31503-00030 Drilled Caisson (30 Inch) 1,923 Lin Foot 217,426.00 113.07503-00036 Drilled Caisson (36 Inch) 1,182 Lin Foot 155,210.52 131.31

503-00042 Drilled Caisson (42 Inch) 1,429 Lin Foot 209,017.00 146.27503-00048 Drilled Caisson (48 Inch) 1,223 Lin Foot 294,099.97 240.47503-00054 Drilled Caisson (54 Inch) 1,498 Lin Foot 489,210.00 326.58503-01060 Micropile (6 Inch) 2,025 Lin Foot 129,600.00 64.00

503-01120 Micropile (12 Inch) 6,000 Lin Foot 486,000.00 81.00504-03500 Retaining Wall (Design Build) 1,160 Sq Foot 365,400.00 315.00504-04410 Block Facing 173,236 Sq Foot 980,604.14 5.66504-04420 Precast Panel Facing 24,219 Sq Foot 622,467.00 25.70

504-06100 Ground Nailed Wall 32,153 Sq Foot 892,295.89 27.75504-06501 Permanent Tieback Anchor System 5,794 Sq Foot 150,304.47 25.94504-08100 Timber Retaining Wall 750 Sq Foot 25,350.00 33.80504-08255 Masonry Landscape Wall (Dry Stack) 1,692 Sq Foot 40,869.00 24.15

506-00000 Riprap 24 Cubic Yard 2,271.96 94.67506-00005 Riprap 2,000 Sq Yard 3,000.00 1.50506-00010 Riprap (Special) 1,058 Cubic Yard 44,232.00 41.81506-00030 Grouted Riprap 782 Cubic Yard 82,110.00 105.00

506-00105 Riprap (Gabions) (PVC Coated) 167 Cubic Yard 25,050.00 150.00506-00206 Riprap (6 Inch) 152 Cubic Yard 16,994.50 111.81506-00209 Riprap (9 Inch) 2,852 Cubic Yard 153,889.27 53.96506-00212 Riprap (12 Inch) 3,036 Cubic Yard 146,341.75 48.20

506-00218 Riprap (18 Inch) 558 Cubic Yard 42,035.31 75.33506-00224 Riprap (24 Inch) 641 Cubic Yard 28,002.84 43.69506-01020 Geogrid Reinforcement 42,523 Sq Yard 136,934.23 3.22506-01100 Concrete Block Revetment 138 Sq Yard 7,176.00 52.00

507-00000 Concrete Slope and Ditch Paving 61 Cubic Yard 19,711.75 323.14507-00100 Concrete Slope and Ditch Paving (Reinforced) 406 Cubic Yard 129,099.56 317.98507-00350 Grouted Riprap Slope and Ditch Paving 127 Cubic Yard 17,300.60 136.23507-00400 Bituminous Slope and Ditch Paving (Asphalt) 2,933 Ton 196,014.12 66.83

507-00550 Concrete Lined Ditch 30 Lin Foot 900.00 30.00508-00520 Insulation Material (2 Inch) 21,650 Sq Foot 48,311.98 2.23509-00000 Structural Steel 2,050,026 Pound 2,582,026.57 1.26509-00010 Structural Steel (Special) 9,800 Pound 20,090.00 2.05

510-00138 Structural Plate Pipe (138 Inch) 66 Lin Foot 56,496.00 856.00510-20100 Structural Plate Arch (Special) 79 Lin Foot 154,383.32 1,954.22

Page 25: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 13 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

512-00101 Bearing Device (Type I) 8 Each 6,400.00 800.00512-00102 Bearing Device (Type II) 64 Each 134,720.00 2,105.00512-00103 Bearing Device (Type III) 4 Each 20,000.00 5,000.00513-00600 Bridge Drain 4 Each 12,000.00 3,000.00

513-00690 Bridge Drain (Special) 29 Each 153,347.46 5,287.84514-00000 Pipe Railing 90 Lin Foot 6,660.00 74.00514-00100 Hand Rail 50 Lin Foot 600.00 12.00514-00200 Pedestrian Railing (Steel) 1,212 Lin Foot 147,974.00 122.09

514-00300 Traffic Railing (Steel) 250 Lin Foot 37,500.00 150.00514-01011 Bridge Rail (Steel) 1,022 Lin Foot 38,652.04 37.82514-01050 Hand and Bikeway Railing 103 Lin Foot 8,240.00 80.00515-00120 Waterproofing (Membrane) 49,237 Sq Yard 398,228.06 8.09

515-00400 Concrete Sealer 6,161 Sq Yard 38,848.03 6.31515-00410 Concrete Sealer (Calcium Nitrite) 907 Sq Yard 15,904.87 17.54517-00100 Waterproofing (Railroad) 909 Sq Yard 71,101.98 78.22518-00000 Bridge Compression Joint Sealer 265 Lin Foot 10,070.00 38.00

518-00010 Roadway Compression Joint Sealer 786 Lin Foot 4,523.00 5.75518-00100 Waterstop 45 Lin Foot 945.00 21.00518-00106 Waterstop (6 Inch) 365 Lin Foot 3,042.50 8.34518-01002 Bridge Expansion Device (0-2 Inch) 2,589 Lin Foot 273,737.10 105.73

518-01004 Bridge Expansion Device (0-4 Inch) 1,536 Lin Foot 226,676.00 147.58518-01006 Bridge Expansion Device (0-6 Inch) 292 Lin Foot 235,644.00 807.00518-01009 Bridge Expansion Device (0-9 Inch) 94 Lin Foot 81,200.00 863.83518-02100 Polymer Mortar End Dam 399 Cubic Foot 155,280.60 389.17

518-03000 Sawing and Sealing Bridge Joint 1,432 Lin Foot 11,768.00 8.22518-03100 Rapid Cure Silicone Joint Seal 270 Lin Foot 22,476.84 83.25519-01000 Epoxy Resin (Injection) 100 Lin Foot 1,000.00 10.00601-01000 Concrete Class B 1,957 Cubic Yard 715,037.42 365.37

601-01025 Concrete Class B (Miscellaneous) 272 Cubic Yard 97,920.00 360.00601-01040 Concrete Class B (Bridge) 74 Cubic Yard 25,790.25 348.52601-01050 Concrete Class B (Wall) 237 Cubic Yard 128,647.00 542.81601-03000 Concrete Class D 2,620 Cubic Yard 749,333.66 286.01

601-03030 Concrete Class D (Box Culvert) 2,239 Cubic Yard 654,488.78 292.31601-03040 Concrete Class D (Bridge) 21,452 Cubic Yard 7,186,067.08 334.98601-03041 Concrete Class D (Bridge) (Special) 386 Cubic Yard 274,064.10 710.01601-03050 Concrete Class D (Wall) 4,575 Cubic Yard 1,127,014.36 246.34

601-03540 Concrete Class DT (Deck Topping) 4 Cubic Yard 1,942.50 485.63601-04000 Concrete Class E 13 Cubic Yard 5,436.50 418.19

Page 26: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 14 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

601-05000 Concrete Class H 1,114 Cubic Yard 295,210.00 265.00601-05045 Concrete Class S40 216 Cubic Yard 76,813.92 355.62601-06100 Concrete (Patching) 8 Cubic Yard 3,750.00 468.75601-06150 Concrete (Patching) 4,936 Sq Foot 234,192.40 47.45

601-06400 Grout (Bridge)(Special) 1,292 Cubic Foot 142,520.66 110.31601-10055 Shotcrete Class I 25 Cubic Yard 11,800.00 472.00601-10075 Shotcrete (3 Inch Min Thick, 5000 psi Min Strength) 405 Sq Yard 94,365.00 233.00601-12084 Concrete Lining (84 Inch Conduit) 147 Lin Foot 11,760.00 80.00

601-40000 Masonry Veneer 44,635 Sq Foot 874,969.99 19.60601-40300 Structural Concrete Coating 13,366 Sq Yard 75,023.73 5.61601-40301 Structural Concrete Coating 142,279 Sq Foot 67,233.00 0.47601-40400 Structural Concrete Stain 2,027 Sq Yard 15,810.60 7.80

602-00000 Reinforcing Steel 984,918 Pound 700,471.08 0.71602-00020 Reinforcing Steel (Epoxy Coated) 6,807,794 Pound 5,753,209.50 0.85602-00030 Reinforcing (Fiber Reinforced Polymer)(Surface) 34 M Kip Foot 48,960.00 1,440.00603-00029 Prepare Culvert Pipe (30 Inch) 187 Lin Foot 1,870.00 10.00

603-00030 Culvert Lining (30 Inch) 187 Lin Foot 3,740.00 20.00603-00035 Prepare Culvert Pipe (36 Inch) 224 Lin Foot 7,168.00 32.00603-00036 Culvert Lining (36 Inch) 799 Lin Foot 143,820.00 180.00603-00048 Culvert Lining (48 Inch) 584 Lin Foot 370,840.00 635.00

603-00072 Culvert Lining (72 Inch) 482 Lin Foot 160,265.00 332.50603-00077 Prepare Culvert Pipe (78 Inch) 244 Lin Foot 8,540.00 35.00603-00078 Culvert Lining (78 Inch) 244 Lin Foot 122,000.00 500.00603-01120 12 Inch Reinforced Concrete Pipe 202 Lin Foot 10,340.00 51.19

603-01150 15 Inch Reinforced Concrete Pipe 874 Lin Foot 36,829.00 42.14603-01155 15 Inch Reinforced Concrete Pipe (Complete In Place) 150 Lin Foot 8,608.72 57.39603-01180 18 Inch Reinforced Concrete Pipe 8,549 Lin Foot 369,944.07 43.27603-01185 18 Inch Reinforced Concrete Pipe (Complete In Place) 1,930 Lin Foot 57,047.50 29.56

603-01240 24 Inch Reinforced Concrete Pipe 9,101 Lin Foot 547,849.40 60.20603-01245 24 Inch Reinforced Concrete Pipe (Complete In Place) 4,730 Lin Foot 168,541.13 35.63603-01300 30 Inch Reinforced Concrete Pipe 1,090 Lin Foot 79,663.00 73.09603-01305 30 Inch Reinforced Concrete Pipe (Complete In Place) 1,694 Lin Foot 60,330.60 35.61

603-01360 36 Inch Reinforced Concrete Pipe 2,285 Lin Foot 167,854.00 73.46603-01365 36 Inch Reinforced Concrete Pipe (Complete In Place) 1,918 Lin Foot 84,063.60 43.83603-01420 42 Inch Reinforced Concrete Pipe 330 Lin Foot 25,786.00 78.14603-01425 42 Inch Reinforced Concrete Pipe (Complete In Place) 1,342 Lin Foot 62,201.70 46.35

603-01480 48 Inch Reinforced Concrete Pipe 648 Lin Foot 64,800.00 100.00603-01485 48 Inch Reinforced Concrete Pipe (Complete In Place) 128 Lin Foot 12,800.00 100.00

Page 27: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 15 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

603-01540 54 Inch Reinforced Concrete Pipe 142 Lin Foot 18,184.00 128.06603-01600 60 Inch Reinforced Concrete Pipe 106 Lin Foot 17,781.28 167.75603-02185 23x14 Inch Reinforced Concrete Pipe (Complete In Plac 197 Lin Foot 10,835.00 55.00603-02240 30x19 Inch Reinforced Concrete Pipe Elliptical 347 Lin Foot 24,520.50 70.66

603-02245 30x19 Inch Reinforced Concrete Pipe Elliptical 107 Lin Foot 5,457.00 51.00603-02300 38x24 Inch Reinforced Concrete Pipe Elliptical 202 Lin Foot 17,847.00 88.35603-02360 45x29 Inch Reinforced Concrete Pipe Elliptical 87 Lin Foot 10,864.80 124.88603-02480 60x38 Inch Reinforced Concrete Pipe Elliptical 224 Lin Foot 27,760.00 123.93

603-02600 76x48 Inch Reinforced Concrete Pipe Elliptical 25 Lin Foot 5,750.00 230.00603-05012 12 Inch Reinforced Concrete End Section 2 Each 640.00 320.00603-05015 15 Inch Reinforced Concrete End Section 1 Each 470.00 470.00603-05018 18 Inch Reinforced Concrete End Section 37 Each 18,942.10 511.95

603-05024 24 Inch Reinforced Concrete End Section 116 Each 59,725.10 514.87603-05030 30 Inch Reinforced Concrete End Section 18 Each 14,940.00 830.00603-05036 36 Inch Reinforced Concrete End Section 63 Each 51,200.00 812.70603-05042 42 Inch Reinforced Concrete End Section 9 Each 10,652.87 1,183.65

603-05048 48 Inch Reinforced Concrete End Section 17 Each 16,420.00 965.88603-05054 54 Inch Reinforced Concrete End Section 3 Each 4,346.79 1,448.93603-05060 60 Inch Reinforced Concrete End Section 3 Each 4,461.31 1,487.10603-05124 30x19 Inch Reinforced Concrete End Section Elliptical 10 Each 5,045.00 504.50

603-05130 38x24 Inch Reinforced Concrete End Section Elliptical 2 Each 1,120.00 560.00603-05136 45x29 Inch Reinforced Concrete End Section Elliptical 4 Each 4,200.00 1,050.00603-05160 76x48 Inch Reinforced Concrete End Section Elliptical 2 Each 3,400.00 1,700.00603-07240 24 Inch Reinforced Concrete Pipe (Jacked) 293 Lin Foot 149,430.00 510.00

603-07360 36 Inch Reinforced Concrete Pipe (Jacked) 1,467 Lin Foot 837,400.00 570.82603-10120 12 Inch Corrugated Steel Pipe 299 Lin Foot 9,690.00 32.41603-10180 18 Inch Corrugated Steel Pipe 2,882 Lin Foot 140,613.10 48.79603-10240 24 Inch Corrugated Steel Pipe 5,656 Lin Foot 325,257.46 57.51

603-10300 30 Inch Corrugated Steel Pipe 2,588 Lin Foot 137,718.99 53.21603-10360 36 Inch Corrugated Steel Pipe 945 Lin Foot 96,736.40 102.37603-10420 42 Inch Corrugated Steel Pipe 256 Lin Foot 17,212.00 67.23603-10480 48 Inch Corrugated Steel Pipe 1,460 Lin Foot 108,559.36 74.36

603-10600 60 Inch Corrugated Steel Pipe 308 Lin Foot 61,600.00 200.00603-10720 72 Inch Corrugated Steel Pipe 30 Lin Foot 6,150.00 205.00603-10840 84 Inch Corrugated Steel Pipe 74 Lin Foot 11,470.00 155.00603-15021 21 Inch Equivalent Corrugated Steel Pipe Arch 27 Lin Foot 946.89 35.07

603-15030 30 Inch Equivalent Corrugated Steel Pipe Arch 273 Lin Foot 12,012.00 44.00603-15042 42 Inch Equivalent Corrugated Steel Pipe Arch 110 Lin Foot 13,200.00 120.00

Page 28: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 16 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

603-15072 72 Inch Equivalent Corrugated Steel Pipe Arch 48 Lin Foot 14,400.00 300.00603-30012 12 Inch Steel End Section 1 Each 140.00 140.00603-30015 15 Inch Steel End Section 4 Each 224.00 56.00603-30018 18 Inch Steel End Section 76 Each 24,725.00 325.33

603-30024 24 Inch Steel End Section 157 Each 51,722.80 329.44603-30030 30 Inch Steel End Section 55 Each 25,206.20 458.29603-30036 36 Inch Steel End Section 21 Each 13,708.20 652.77603-30042 42 Inch Steel End Section 2 Each 1,600.00 800.00

603-30048 48 Inch Steel End Section 7 Each 9,951.20 1,421.60603-31330 30 Inch Equivalent Arch Steel End Section 4 Each 1,640.00 410.00603-31342 42 Inch Equivalent Arch Steel End Section 1 Each 650.00 650.00603-33018 18 Inch Pipe Safety End Treatment 11 Each 5,860.00 532.73

603-33024 24 Inch Pipe Safety End Treatment 2 Each 960.00 480.00603-33036 36 Inch Pipe Safety End Treatment 2 Each 1,370.00 685.00603-33042 42 Inch Pipe Safety End Treatment 5 Each 4,075.00 815.00603-33048 48 Inch Pipe Safety End Treatment 4 Each 4,260.00 1,065.00

603-50002 2 Inch Plastic Pipe 38 Lin Foot 3,230.00 85.00603-50003 3 Inch Plastic Pipe 1,104 Lin Foot 66,240.00 60.00603-50004 4 Inch Plastic Pipe 372 Lin Foot 4,490.00 12.07603-50006 6 Inch Plastic Pipe 2,006 Lin Foot 60,180.00 30.00

603-50008 8 Inch Plastic Pipe 12 Lin Foot 1,080.00 90.00603-50012 12 Inch Plastic Pipe 3,200 Lin Foot 72,700.00 22.72603-50018 18 Inch Plastic Pipe 60 Lin Foot 4,200.00 70.00603-50024 24 Inch Plastic Pipe 648 Lin Foot 47,304.00 73.00

603-61120 12 Inch Flexible Pipe 727 Lin Foot 10,937.00 15.04603-61180 18 Inch Flexible Pipe 263 Lin Foot 6,235.00 23.71603-70303 3x3 Foot Concrete Box Culvert (Precast) 90 Lin Foot 18,090.00 201.00603-70604 6x4 Foot Concrete Box Culvert (Precast) 229 Lin Foot 61,830.00 270.00

603-70606 6x6 Foot Concrete Box Culvert (Precast) 126 Lin Foot 40,320.00 320.00603-70805 8x5 Foot Concrete Box Culvert (Precast) 86 Lin Foot 32,680.00 380.00603-70806 8x6 Foot Concrete Box Culvert (Precast) 43 Lin Foot 20,984.00 488.00603-82004 4 Inch Ductile Iron Pipe 12 Lin Foot 900.00 75.00

603-83012 12 Inch Sewer Pipe 126 Lin Foot 6,930.00 55.00604-00305 Inlet Type C (5 Foot) 58 Each 155,132.73 2,674.70604-00310 Inlet Type C (10 Foot) 13 Each 40,022.22 3,078.63604-00315 Inlet Type C (15 Foot) 5 Each 19,465.00 3,893.00

604-00320 Inlet Type C (20 Foot) 1 Each 5,000.00 5,000.00604-00350 Inlet Type C (Special) 6 Each 17,645.00 2,940.83

Page 29: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 17 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

604-00505 Inlet Type D (5 Foot) 15 Each 55,260.00 3,684.00604-00510 Inlet Type D (10 Foot) 15 Each 69,180.00 4,612.00604-00515 Inlet Type D (15 Foot) 5 Each 26,045.51 5,209.10604-00550 Inlet Type D (Special) 13 Each 68,700.00 5,284.62

604-13005 Inlet Type 13 (5 Foot) 12 Each 39,508.37 3,292.36604-13006 Inlet Type 13 (5 Foot) (Special) 19 Each 49,149.98 2,586.84604-13010 Inlet Type 13 (10 Foot) 2 Each 7,600.00 3,800.00604-13011 Inlet Type 13 (10 Foot) (Special) 2 Each 5,719.52 2,859.76

604-19000 Inlet Special 2 Each 7,300.00 3,650.00604-19010 Inlet Special (10 Foot) 2 Each 9,600.00 4,800.00604-19015 Inlet Special (15 Foot) 1 Each 8,615.25 8,615.25604-19105 Inlet Type R L 5 (5 Foot) 52 Each 177,490.00 3,413.27

604-19110 Inlet Type R L 5 (10 Foot) 40 Each 170,655.00 4,266.38604-19115 Inlet Type R L 5 (15 Foot) 2 Each 10,300.00 5,150.00604-19205 Inlet Type R L 10 (5 Foot) 10 Each 39,620.00 3,962.00604-19210 Inlet Type R L 10 (10 Foot) 6 Each 30,170.00 5,028.33

604-19215 Inlet Type R L 10 (15 Foot) 3 Each 18,700.00 6,233.33604-19305 Inlet Type R L 15 (5 Foot) 6 Each 30,940.00 5,156.67604-19310 Inlet Type R L 15 (10 Foot) 4 Each 22,200.00 5,550.00604-19315 Inlet Type R L 15 (15 Foot) 4 Each 29,965.00 7,491.25

604-19405 Inlet Type R Special (5 Foot) 16 Each 59,439.86 3,714.99604-19410 Inlet Type R Special (10 Foot) 18 Each 111,655.93 6,203.11604-19505 Inlet Type R L 20 (5 Foot) 1 Each 6,700.00 6,700.00604-20000 Outlet Structure 3 Each 19,200.00 6,400.00

604-25000 Vane Grate Inlet Special 2 Each 9,000.00 4,500.00604-25005 Vane Grate Inlet (5 Foot) 13 Each 33,100.36 2,546.18604-25006 Vane Grate Inlet Special (5 Foot) 3 Each 12,740.00 4,246.67604-25010 Vane Grate Inlet (10 Foot) 5 Each 14,728.02 2,945.60

604-26005 Vane Grate Inlet (Double) (5 Foot) 9 Each 38,133.89 4,237.10604-26010 Vane Grate Inlet (Double) (10 Foot) 4 Each 20,878.10 5,219.53604-30005 Manhole Slab Base (5 Foot) 18 Each 37,119.30 2,062.18604-30010 Manhole Slab Base (10 Foot) 47 Each 133,445.05 2,839.26

604-30015 Manhole Slab Base (15 Foot) 7 Each 29,091.51 4,155.93604-30020 Manhole Slab Base (20 Foot) 1 Each 3,650.00 3,650.00604-31010 Manhole Box Base (10 Foot) 2 Each 8,400.00 4,200.00604-31015 Manhole Box Base (15 Foot) 2 Each 10,400.00 5,200.00

604-39000 Manhole Special 3 Each 21,500.00 7,166.67604-39005 Manhole Special (5 Foot) 3 Each 5,760.00 1,920.00

Page 30: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 18 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

604-39010 Manhole Special (10 Foot) 3 Each 9,572.80 3,190.93604-39015 Manhole Special (15 Foot) 1 Each 5,600.00 5,600.00604-39020 Manhole Special (20 Foot) 1 Each 6,200.00 6,200.00604-39050 Manhole (Traffic Management System) 64 Each 171,700.00 2,682.81

604-50000 Inlet Grating and Frame (Median) 9 Each 2,565.00 285.00604-50060 Grating and Frame 10 Lin Foot 1,608.50 160.85604-50800 Sanitary Sewer Vault 1 Each 11,500.00 11,500.00604-56000 Slotted Vane Drain 80 Each 40,716.03 508.95

605-00020 2 Inch Perforated Pipe Underdrain 8,000 Lin Foot 107,112.80 13.39605-00040 4 Inch Perforated Pipe Underdrain 7,276 Lin Foot 72,001.80 9.90605-00060 6 Inch Perforated Pipe Underdrain 10,237 Lin Foot 248,308.57 24.26605-01020 2 Inch Horizontal Drain 3,000 Lin Foot 90,000.00 30.00

605-82100 Pipe Edge Drain 800 Lin Foot 4,800.00 6.00605-82306 6 Inch Drain Pipe 90 Lin Foot 2,700.00 30.00605-83560 6 Inch Pipe Underdrain 325 Lin Foot 7,150.00 22.00605-84000 Subsurface Drain Outlet 312 Lin Foot 8,548.62 27.40

605-84100 Subsurface Drain Outlet Structure 4 Each 1,500.00 375.00606-00301 Guardrail Type 3 (6-3 Post Spacing) 173,675 Lin Foot 2,461,165.34 14.17606-00305 Guardrail Type 3 (Special) 1,387 Lin Foot 49,931.44 36.00606-00700 Guardrail Type 7 1,157 Lin Foot 89,550.57 77.40

606-00701 Guardrail (Cable) 16,370 Lin Foot 206,753.10 12.63606-00705 Guardrail Type 7 (Special) 4,667 Lin Foot 173,069.20 37.08606-00710 Guardrail Type 7 (Style CA) 18,280 Lin Foot 684,758.89 37.46606-00720 Guardrail Type 7 (Style CC) 767 Lin Foot 44,486.00 58.00

606-00730 Guardrail Type 7 (Style CD) 5,847 Lin Foot 214,579.40 36.70606-00755 Concrete Glare Screen (Precast Type 7) 10,600 Lin Foot 318,000.00 30.00606-00800 Guardrail Type 7 (F-Shape Concrete Barrier) 12,040 Lin Foot 565,880.00 47.00606-00900 Guardrail (Special) 235 Lin Foot 64,400.00 274.04

606-01320 End Anchorage Type 3B 9 Each 8,200.00 911.11606-01340 End Anchorage Type 3D 124 Each 65,296.65 526.59606-01370 Transition Type 3G 284 Each 258,822.78 911.35606-01380 Transition Type 3H 69 Each 36,639.82 531.01

606-01385 Transition Type 3J 30 Each 19,081.30 636.04606-01390 End Anchorage Type 3K 40 Each 31,352.00 783.80606-01395 Transition Type 3L 31 Each 19,825.20 639.52606-01410 End Anchorage (Cable) 2 Each 6,520.00 3,260.00

606-01460 Median Terminal 14 Each 52,273.55 3,733.83606-02001 End Anchorage (Slotted Rail Terminal) 235 Each 317,960.97 1,353.03

Page 31: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 19 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

606-02003 End Anchorage (Nonflared) 201 Each 346,437.47 1,723.57606-02005 End Anchorage (Flared) 417 Each 555,500.79 1,332.14606-10200 Bridge Rail (Special) 135 Lin Foot 29,700.00 220.00606-10300 Bridge Rail Type 3 27 Lin Foot 1,944.00 72.00

606-10360 Bridge Rail Type 3R (Special) 280 Lin Foot 10,276.00 36.70606-10405 Bridge Rail Type 4 (Special) 40 Lin Foot 5,440.00 136.00606-10700 Bridge Rail Type 7 1,952 Lin Foot 138,138.20 70.77606-10705 Bridge Rail Type 7 (Special) 5,464 Lin Foot 523,167.15 95.75

606-10805 Bridge Rail Type 8 (Special) 7,795 Lin Foot 179,028.54 22.97606-11010 Bridge Rail Type 10R 7,628 Lin Foot 533,734.00 69.97606-11015 Bridge Rail Type 10R (Special) 1,319 Lin Foot 90,010.00 68.24606-11030 Bridge Rail Type 10M 3,857 Lin Foot 366,142.00 94.93

606-11032 Bridge Rail Type 10M (Special) 292 Lin Foot 38,116.54 130.54606-20000 Wire Rope Safety Fence 221,057 Lin Foot 3,004,728.31 13.59606-21000 Wire Rope End Anchorage 123 Each 246,925.00 2,007.52607-00000 Line Post 164 Each 16,000.75 97.57

607-00005 End Post 433 Each 54,348.44 125.52607-00010 Corner and Line Brace Post 898 Each 120,578.22 134.27607-00020 Corner and Line Brace Post (Special) 3 Each 525.00 175.00607-01000 Fence Barbed Wire with Metal Posts 369,101 Lin Foot 327,122.64 0.89

607-01050 Fence Wire With Metal Posts 902 Lin Foot 1,794.98 1.99607-01100 Fence Barbed Wire With Treated Wooden Posts 15,650 Lin Foot 32,159.40 2.05607-01110 Fence Barbed Wire With Treated Wooden Posts (Special) 8,016 Lin Foot 29,659.20 3.70607-11200 Fence Combination Wire With Metal Posts 45,254 Lin Foot 78,616.80 1.74

607-11300 Fence Combination Wire With Treated Wooden Posts 34,132 Lin Foot 83,589.60 2.45607-11350 Fence Deer 2,090 Lin Foot 17,466.13 8.36607-11525 Fence (Plastic) 54,161 Lin Foot 165,422.23 3.05607-11575 Rock Fall Fence 200 Lin Foot 70,000.00 350.00

607-11576 Temporary Rockfall Containment System 2 Lump Sum 17,000.00 8,500.00607-11580 Fence (Temporary) 7,589 Lin Foot 25,491.40 3.36607-11672 Fence Wood (Sound Barrier) (72 Inch) 440 Lin Foot 27,539.60 62.59607-11720 Fence Wood (Sound Barrier) (120 Inch) 450 Lin Foot 41,400.00 92.00

607-52900 Line Post (Chain Link) 65 Each 2,990.00 46.00607-52905 End Post (Chain Link) 26 Each 4,650.00 178.85607-52910 Corner and Line Brace Post (Chain Link) 34 Each 8,850.00 260.29607-53001 Fence Chain Link (PVC Coated) 1,813 Lin Foot 22,209.25 12.25

607-53137 Fence Chain Link (Special) (36 Inch) 1,856 Lin Foot 32,640.00 17.59607-53142 Fence Chain Link (42 Inch) 100 Lin Foot 4,000.00 40.00

Page 32: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 20 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

607-53148 Fence Chain Link (48 Inch) 100 Lin Foot 1,680.00 16.80607-53155 Fence Chain Link (Special)(54 Inch) 122 Lin Foot 11,712.00 96.00607-53161 Fence Chain Link (Special) (60 Inch) 6,119 Lin Foot 106,834.00 17.46607-53172 Fence Chain Link (72 Inch) 3,947 Lin Foot 29,717.00 7.53

607-53173 Fence Chain Link (Special) (72 Inch) 2,252 Lin Foot 31,528.00 14.00607-53178 Fence Chain Link (Spec) (78 In) 390 Lin Foot 12,090.00 31.00607-53191 Fence Chain Link (Special) (92 Inch) 435 Lin Foot 14,355.00 33.00607-53196 Fence Chain Link (96 Inch) 2,721 Lin Foot 42,175.50 15.50

607-53203 Fence Chain Link (Special)(102 Inch) 76 Lin Foot 5,700.00 75.00607-55030 Mesh Post 28 Each 56,800.00 2,028.57607-55100 Wire Mesh 76,800 Sq Foot 187,851.20 2.45607-55101 Cable Net 10,400 Sq Foot 171,350.00 16.48

607-60116 16 Foot Gate 8 Each 2,046.30 255.79607-60117 16 Foot Gate (Special) 5 Each 1,688.90 337.78607-60120 20 Foot Gate 5 Each 810.00 162.00607-60220 20 Foot Gate Single (Chain Link) 4 Each 2,800.00 700.00

607-60324 24 Foot Gate Twin 4 Each 3,175.00 793.75607-60620 Road Closure Gate 4 Each 46,100.00 11,525.00608-00000 Concrete Sidewalk 21,714 Sq Yard 548,859.64 25.28608-00003 Concrete Sidewalk (Fast Track) 240 Sq Yard 7,884.20 32.85

608-00005 Concrete Sidewalk (Special) 2,123 Sq Yard 130,272.50 61.36608-00006 Concrete Sidewalk (6 Inch) 5,542 Sq Yard 179,960.38 32.47608-00010 Concrete Curb Ramp 9,890 Sq Yard 758,289.29 76.67608-00011 Curb Ramp (Fast Track) 542 Sq Yard 32,956.36 60.81

608-00015 Truncated Domes 1,447 Sq Foot 24,410.51 16.87608-00051 Brick Pavers (Install Only) 834 Sq Foot 12,510.00 15.00608-01000 Bituminous Sidewalk 28 Ton 3,908.80 139.60608-01600 Aggregate Walkway 1,339 Sq Yard 8,964.07 6.69

608-10000 Sidewalk Drain 11 Lin Foot 1,579.00 143.55609-21010 Curb and Gutter Type 2 (Section I-B) 67,141 Lin Foot 590,276.42 8.79609-21011 Curb and Gutter Type 2 (Section I-M) 36,500 Lin Foot 261,003.74 7.15609-21020 Curb and Gutter Type 2 (Section II-B) 62,318 Lin Foot 787,386.05 12.63

609-21021 Curb and Gutter Type 2 (Section II-M) 23,409 Lin Foot 204,665.61 8.74609-21023 Curb and Gutter Type 2 (Section II-B) (Special) 1,907 Lin Foot 39,093.50 20.50609-21900 Curb and Gutter Type 2 Special 12,131 Lin Foot 303,275.00 25.00609-22022 Curb, Gutter and Sidewalk Type 2 (Section II-B) 4,331 Lin Foot 136,904.60 31.61

609-23000 Gutter (Special) 445 Lin Foot 13,257.00 29.79609-24002 Gutter Type 2 (2 Foot) 2,935 Lin Foot 28,065.00 9.56

Page 33: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 21 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

609-24004 Gutter Type 2 (4 Foot) 2,470 Lin Foot 37,084.00 15.01609-24006 Gutter Type 2 (6 Foot) 80 Lin Foot 1,920.00 24.00609-24008 Gutter Type 2 (8 Foot) 316 Lin Foot 12,125.45 38.37609-31010 Curb and Gutter Type 2 (Section I-B) (Fast Track) 522 Lin Foot 9,484.58 18.17

609-31020 Curb and Gutter Type 2 (Section II-B) (Fast Track) 633 Lin Foot 9,796.02 15.48609-31025 Curb and Gutter Type 2 (Section II-M) (Fast Track) 508 Lin Foot 12,476.48 24.56609-34006 Gutter Type 2 (6 Foot) (Fast Track) 112 Lin Foot 3,746.40 33.45609-40010 Curb Type 4 (Section B) 188 Lin Foot 1,908.20 10.15

609-40011 Curb Type 4 (Section M) 736 Lin Foot 7,382.00 10.03609-40130 Curb (Median) (Special) 2,394 Lin Foot 23,940.00 10.00609-60011 Curb Type 6 (Section M) 54,226 Lin Foot 236,670.83 4.36609-70040 Curb (Composite Material) 6,978 Lin Foot 54,428.40 7.80

609-71000 Curb (Special) 2,807 Lin Foot 35,291.90 12.57610-00010 Median Cover Material (Decorative) 27,352 Sq Foot 123,084.00 4.50610-00020 Median Cover Material (Patterned Concrete) 88,151 Sq Foot 382,163.69 4.34610-00024 Median Cover Material (4 Inch Patterned Concrete) 140,813 Sq Foot 612,994.15 4.35

610-00026 Median Cover Material (6 Inch Patterned Concrete) 25,751 Sq Foot 128,755.00 5.00610-00030 Median Cover Material (Concrete) 95,501 Sq Foot 288,277.32 3.02610-00040 Median Cover Material (Bituminous) 423 Ton 26,378.20 62.36610-00055 Median Cover Material (Stone) 9,000 Sq Foot 18,000.00 2.00

610-00060 Median Cover Material (Brick Pavers) 1 Sq Foot 30.00 30.00611-00024 24 Foot Cattle Guard 1 Each 10,000.00 10,000.00612-00001 Delineator (Type I) 8,813 Each 136,530.53 15.49612-00002 Delineator (Type II) 3,379 Each 51,006.06 15.10

612-00003 Delineator (Type III) 1,102 Each 20,080.08 18.22612-00010 Delineator (Special) 1,428 Each 108,420.00 75.92612-00021 Delineator (Type I) (Barrier) 103 Each 574.62 5.58612-00022 Delineator (Type II) (Barrier) 62 Each 985.88 15.90

612-00041 Delineator (Flexible) (Type I) 593 Each 12,423.90 20.95612-00042 Delineator (Flexible) (Type II) 360 Each 7,653.72 21.26612-00043 Delineator (Flexible) (Type III) 127 Each 2,845.00 22.40612-00260 Location Marker (Fiber Optic)(Dome) 25 Each 1,050.00 42.00

612-00270 Location Marker (Utility)(Flat Slat) 10 Each 380.00 38.00612-15000 Install Marker 364 Each 45,500.00 125.00613-00001 Directional Boring Conduit 1,200 Lin Foot 45,600.00 38.00613-00075 3/4 Inch Electrical Conduit 948 Lin Foot 9,108.54 9.61

613-00100 1 Inch Electrical Conduit 2,973 Lin Foot 28,243.50 9.50613-00125 1-1/4 Inch Electrical Conduit 120 Lin Foot 600.00 5.00

Page 34: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 22 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

613-00126 1-1/4 Inch Electrical Conduit (Jacked) 1,447 Lin Foot 78,065.65 53.95613-00127 1-1/4 Inch Electrical Conduit (Plastic)(Special) 6,119 Lin Foot 26,984.79 4.41613-00200 2 Inch Electrical Conduit 38,868 Lin Foot 416,960.73 10.73613-00201 2 Inch Electrical Conduit (Jacked) 71,338 Lin Foot 986,131.11 13.82

613-00300 3 Inch Electrical Conduit 10,186 Lin Foot 74,780.15 7.34613-00301 3 Inch Electrical Conduit (Jacked) 6,391 Lin Foot 119,542.98 18.70613-00400 4 Inch Electrical Conduit 4,002 Lin Foot 93,700.00 23.41613-00600 6 Inch Electrical Conduit 8,223 Lin Foot 333,092.76 40.51

613-00602 6 Inch Electrical Conduit (Install Only) 300 Lin Foot 1,890.00 6.30613-01100 1 Inch Electrical Conduit (Plastic) 4,155 Lin Foot 35,005.00 8.42613-01125 1-1/4 Inch Electrical Conduit (Plastic) 25,238 Lin Foot 8,375.86 0.33613-01150 1-1/2 Inch Electrical Conduit (Plastic) 1,220 Lin Foot 7,930.00 6.50

613-01200 2 Inch Electrical Conduit (Plastic) 183,357 Lin Foot 820,617.08 4.48613-01201 2 Inch Electrical Conduit (Plastic) (Special) 5,954 Lin Foot 74,425.00 12.50613-01250 2-1/2 Inch Electrical Conduit (Plastic) 1,020 Lin Foot 11,940.00 11.71613-01300 3 Inch Electrical Conduit (Plastic) 25,600 Lin Foot 242,145.64 9.46

613-01301 3 Inch Electrical Conduit (Plastic) (Special) 969 Lin Foot 14,535.00 15.00613-01400 4 Inch Electrical Conduit (Plastic) 5,276 Lin Foot 29,448.60 5.58613-01600 6 Inch Electrical Conduit (Plastic) 16,514 Lin Foot 79,455.72 4.81613-03500 Electrical Conduit (Plastic)(Multiduct)(Special) 233,291 Lin Foot 1,145,458.81 4.91

613-04000 Conduit (Install Only) 116 Lin Foot 3,235.70 27.89613-07000 Pull Box (Special) 150 Each 39,242.49 261.62613-07010 Pull Box (Surface Mounted) 60 Each 18,727.20 312.12613-07026 Pull Box (16"x24"x12") 10 Each 3,816.82 381.68

613-07033 Pull Box (24"x20"x12") 5 Each 825.00 165.00613-07034 Pull Box (24"x36"x18") 297 Each 185,023.92 622.98613-07038 Pull Box (36"x48"x18") 25 Each 20,094.04 803.76613-07050 Pull Box (13"x24"x18") Deep 7 Each 2,800.00 400.00

613-07199 Pull Box (Install Only) 19 Each 437.00 23.00613-10000 Wiring 32 Lump Sum 332,646.27 10,395.20613-16000 Luminaire (Special) 15 Each 24,128.42 1,608.56613-20100 Light Standard (Install Only) 93 Each 20,660.00 222.15

613-20200 Luminaire (Install Only) 154 Each 15,400.00 100.00613-20210 Luminaire (Special) (Install Only) 134 Each 34,036.00 254.00613-30005 Light Standard and Luminaire (Pedestrian) 8 Each 30,800.00 3,850.00613-30350 Light Standard Aluminum (35 Foot) 187 Each 224,400.00 1,200.00

613-30400 Light Standard Aluminum (40 Foot) 1 Each 2,400.00 2,400.00613-32300 Light Standard Steel (30 Foot) 1 Each 3,251.25 3,251.25

Page 35: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 23 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

613-32350 Light Standard Steel (35 Foot) 10 Each 18,100.00 1,810.00613-32352 Light Standard Steel (35 Foot) (2-Arm) 6 Each 13,260.00 2,210.00613-32400 Light Standard Steel (40 Foot) 84 Each 172,012.00 2,047.76613-34150 Light Standard Metal (15 Foot) 22 Each 22,000.00 1,000.00

613-34300 Light Standard Metal (30 Foot) 20 Each 41,132.10 2,056.61613-34400 Light Standard Metal (40 Foot) 64 Each 124,800.00 1,950.00613-35120 Light Standard Steel High Mast (120 Foot) 1 Each 44,900.00 44,900.00613-40000 Concrete Foundation Pad 179 Each 111,319.64 621.90

613-40010 Light Standard Foundation 303 Each 140,047.00 462.20613-40015 Light Standard Anchor 4 Each 1,800.00 450.00613-45000 High Mast Foundation 1 Each 8,368.00 8,368.00613-50000 Lowering Device 1 Each 7,985.00 7,985.00

613-50100 Lighting Control Center 4 Each 16,272.98 4,068.25613-50150 Secondary Service Pedestal 4 Each 9,155.52 2,288.88613-50200 Lighting System 1 Each 12,750.00 12,750.00613-50355 Power Transformer 5 Each 7,282.80 1,456.56

613-50410 Light Standard (Temporary) 57 Each 145,400.00 2,550.88613-70250 Luminaire High Pressure Sodium (250 Watt) 134 Each 60,553.34 451.89613-70251 Luminaire High Pressure Sodium (250 Watt) (Install On 12 Each 2,400.00 200.00613-70400 Luminaire High Pressure Sodium (400 Watt) 284 Each 80,878.00 284.78

613-70401 Luminaire High Pressure Sodium (400 Watt) (Install On 12 Each 1,740.00 145.00613-71000 Luminaire High Pressure Sodium (1000 Watt) 4 Each 3,832.00 958.00613-72150 Luminaire High Pressure Sodium (Wall Type) (150 Watt) 10 Each 29,720.00 2,972.00613-75100 Luminaire Metal Halide (100 Watt) 48 Each 41,136.00 857.00

613-75150 Luminaire Metal Halide (150 Watt) 22 Each 6,600.00 300.00613-75175 Luminaire Metal Halide (175 Watt) 24 Each 33,109.50 1,379.56613-75250 Luminaire Metal Halide (250 Watt) 96 Each 135,360.00 1,410.00613-75400 Luminaire Metal Halide (400 Watt) 34 Each 15,300.00 450.00

614-00011 Sign Panel (Class I) 6,527 Sq Foot 97,834.84 14.99614-00012 Sign Panel (Class II) 10,888 Sq Foot 172,484.55 15.84614-00013 Sign Panel (Class III) 8,949 Sq Foot 152,044.02 16.99614-00026 Sign Panel (Class I) (Install Only) 31 Each 1,558.00 50.26

614-00027 Sign Panel (Class II) (Install Only) 72 Sq Foot 223.20 3.10614-00028 Sign Panel (Class III) (Install Only) 3,942 Sq Foot 23,340.00 5.92614-00035 Sign Panel (Special) 10 Sq Foot 140.00 14.00614-00044 Timber Sign Post 4x4 Inch 155 Lin Foot 697.50 4.50

614-00200 Steel Sign Post (U-2) 357 Lin Foot 3,173.75 8.89614-00216 Steel Sign Post (2x2 Inch Tubing) 657 Lin Foot 7,843.00 11.94

Page 36: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 24 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

614-00218 Steel Sign Post (2.25x2.25 Inch Tubing) 102 Lin Foot 1,098.00 10.76614-00220 Steel Sign Post (2.5x2.5 Inch Tubing) 148 Lin Foot 1,964.44 13.27614-00357 Steel Sign Post (S 3x5.7) 14 Lin Foot 203.00 14.50614-00477 Steel Sign Post (S 4x7.7) 13 Lin Foot 227.50 17.50

614-00612 Steel Sign Post (W 6x12) 93 Lin Foot 2,139.00 23.00614-00615 Steel Sign Post (W 6x15) 335 Lin Foot 11,203.00 33.44614-00818 Steel Sign Post (W 8x18) 413 Lin Foot 11,609.00 28.11614-00821 Steel Sign Post (W 8x21) 270 Lin Foot 8,910.00 33.00

614-01022 Steel Sign Post (W 10x22) 191 Lin Foot 5,576.00 29.19614-01026 Steel Sign Post (W 10x26) 118 Lin Foot 4,248.00 36.00614-01226 Steel Sign Post (W 12x26) 243 Lin Foot 9,234.00 38.00614-01502 Steel Sign Support (2-Inch Round)(Post & Socket) 4,700 Lin Foot 53,750.36 11.44

614-01512 Steel Sign Support (2-Inch Round)(Post) 679 Lin Foot 4,270.00 6.29614-01522 Steel Sign Support (2-Inch Round)(Socket) 134 Each 4,624.30 34.51614-01552 Steel Sign Post (2.5 Inch Round) (Slipbase) 2,558 Lin Foot 56,126.60 21.94614-01554 Steel Sign Post (4 Inch Round) (Slipbase) 36 Lin Foot 1,684.80 46.80

614-01582 Steel Sign Support (2-1/2 Inch Round)(Post and Slipba 12,819 Lin Foot 307,731.27 24.01614-01585 Steel Sign Support (2-1/2 Inch Round Sch 80)(Post) 445 Lin Foot 8,199.44 18.43614-01588 Steel Sign Support (2-1/2 Inch Round Sch 80)(Slipbase 115 Each 12,649.05 109.99614-01736 Steel Sign Ground Stub base (36 Inch) 12 Each 2,580.00 215.00

614-03001 Concrete Footing (Type 1) 12 Each 5,280.00 440.00614-03002 Concrete Footing (Type 2) 22 Each 13,450.00 611.36614-03003 Concrete Footing (Type 3) 22 Each 12,340.00 560.91614-03004 Concrete Footing (Type 4) 14 Each 8,540.00 610.00

614-03005 Concrete Footing (Type 5) 8 Each 8,600.00 1,075.00614-03006 Concrete Footing (Type 6) 6 Each 5,760.00 960.00614-03007 Concrete Footing (Type 7) 10 Each 11,000.00 1,100.00614-07105 Modification of Sign Legend 4 Each 3,024.00 756.00

614-10123 Variable Message Sign (Install Only) 1 Each 9,525.00 9,525.00614-10125 Variable Message Sign (Ground Mounted) 1 Each 126,435.00 126,435.00614-10128 Blankout Sign (Fiber Optic) 2 Each 18,150.00 9,075.00614-10130 Illuminated Sign 6 Each 20,400.00 3,400.00

614-10147 Variable Message Sign LED (Overhead) 3 Each 438,339.16 146,113.05614-10148 Variable Message Sign LED (Speed Radar) 1 Each 97,606.20 97,606.20614-10150 12 Inch LED (Ball) 319 Each 39,370.80 123.42614-10151 12 Inch LED (Ball) (Green) 43 Each 6,331.75 147.25

614-10153 12 Inch LED (Ball) (Yellow) 43 Each 3,513.10 81.70614-10155 12 Inch LED (Arrow) 46 Each 4,677.50 101.68

Page 37: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 25 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

614-10156 12 Inch LED (Arrow) (Green) 17 Each 2,171.75 127.75614-10158 12 Inch LED (Arrow) (Yellow) 17 Each 1,499.40 88.20614-10160 Signal Head Backplates 81 Each 8,038.00 99.23614-21275 VMS Support (Ground Mounted) (12.75 Inch Diameter) 1 Each 13,519.51 13,519.51

614-32400 Monotube Overhead Sign Cantilever (24 Inch Diameter) 12 Each 298,536.58 24,878.05614-32900 Monotube Overhead Sign Cantilever (Install Only) 12 Each 36,000.00 3,000.00614-41275 Monotube Overhead Sign Bridge (12.75 Inch Diameter) 1 Each 26,062.00 26,062.00614-41400 Monotube Overhead Sign Bridge (14 Inch Diameter) 1 Each 29,377.00 29,377.00

614-41600 Monotube Overhead Sign Bridge (16 Inch Diameter) 2 Each 52,784.00 26,392.00614-42000 Monotube Overhead Sign Bridge (20 Inch Diameter) 3 Each 105,512.00 35,170.67614-42400 Monotube Overhead Sign Bridge (24 Inch Diameter) 1 Each 53,194.00 53,194.00614-70112 Traffic Signal Face (12) 15 Each 2,202.50 146.83

614-70117 Pedestrian Signal Face (16) 104 Each 46,853.70 450.52614-70216 Traffic Signal Face (8-8) 10 Each 3,941.10 394.11614-70328 Traffic Signal Face (12-8-8) 10 Each 5,033.60 503.36614-70336 Traffic Signal Face (12-12-12) 360 Each 261,487.19 726.35

614-70450 Traffic Signal Face (12-12-12-12)(Install Only) 2 Each 480.00 240.00614-70560 Traffic Signal Face (12-12-12-12-12) 80 Each 88,675.85 1,108.45614-72830 Communications Cabinet 7 Each 49,523.04 7,074.72614-72855 Traffic Signal Controller Cabinet 5 Each 66,500.00 13,300.00

614-72858 Pedestal Pole (3 Foot 6 Inch) 3 Each 1,694.20 564.73614-72860 Pedestrian Push Button 54 Each 5,091.95 94.30614-72864 Fire Preemption Unit 5 Each 10,700.00 2,140.00614-72866 Fire Preemption Unit and Timer 2 Each 12,603.30 6,301.65

614-72871 Loop Detector Wire (Prefab) Special 5,916 Lin Foot 32,291.70 5.46614-72872 Loop Detector (Micro Type) 67 Each 37,419.97 558.51614-72873 Loop Detector Wire Prefabricated (Install Only) 1,500 Lin Foot 9,450.00 6.30614-72875 Loop Detector Wire 91,352 Lin Foot 188,050.26 2.06

614-72878 Traffic Signal Vehicle Detector Amplifier (Loop Type) 26 Each 28,022.34 1,077.78614-72882 Traffic Signal Vehicle Detector (Micro Type) 27 Each 19,876.26 736.16614-72885 Traffic Signal Vehicle Detector (Special) 2 Each 10,000.00 5,000.00614-72886 Intersection Detection System (Camera) 88 Each 620,304.60 7,048.92

614-72887 Microwave Vehicle Radar Detector 1 Each 11,205.11 11,205.11614-72889 Traffic Signal Vehicle Detector (Micro Type) (Non-Inv 72 Each 47,557.00 660.51614-72891 Telephone Interconnect Wire 864 Lin Foot 1,536.00 1.78614-72895 Vehicle Detection System (Single Camera) 1 Each 7,100.00 7,100.00

614-72896 Intersection Detection System (Camera)(Install Only) 17 Each 10,837.00 637.47614-75216 Pedestrian Signal Face (16) (Install Only) 20 Each 1,955.00 97.75

Page 38: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 26 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

614-75332 Pedestrian Signal Face (16-16) (Install Only) 8 Each 1,680.00 210.00614-75336 Traffic Signal Face (12-12-12) (Install Only) 40 Each 5,895.00 147.38614-75560 Traffic Signal Face (12-12-12-12-12) (Install Only) 14 Each 2,690.00 192.14614-75848 Traffic Signal Controller and Cabinet (Install Only) 2 Each 5,865.00 2,932.50

614-75860 Pedestrian Push Button (Install Only) 28 Each 1,114.00 39.79614-75866 Fire Preemption Unit and Timer (Install Only) 4 Each 420.00 105.00614-75869 Furnish Fire Preempt Unit Emmitter (Furnish Only) 2 Each 2,200.00 1,100.00614-80000 Flashing Beacon 38 Each 66,327.17 1,745.45

614-80001 Flashing Beacon (Solar Powered) 4 Each 14,000.00 3,500.00614-80313 Barricade (Type 3 F-C) 2 Each 3,400.00 1,700.00614-80314 Barricade (Type 3 F-D) 2 Each 2,137.64 1,068.82614-80385 Rumble Strip 415,341 Lin Foot 78,586.24 0.19

614-80387 Rumble Strip (Grinding) 1,528,025 Lin Foot 220,810.83 0.14614-80391 Rumble Strip (Grinding)(Asphalt) 24,488 Lin Foot 12,244.00 0.50614-81000 Traffic Signal-Light Pole Steel 1 Each 1,230.00 1,230.00614-81010 Traffic Signal-Light Pole Steel (1 Mast Arm) 16 Each 356,105.20 22,256.58

614-81011 Traffic Signal-Light Pole Steel (1 Mast Arm) (Install 8 Each 4,692.00 586.50614-81020 Traffic Signal-Light Pole Steel (2 Mast Arm) 8 Each 305,035.00 38,129.38614-81125 Traffic Signal-Light Pole Steel (1-25 Foot Mast Arm) 3 Each 43,312.26 14,437.42614-81130 Traffic Signal-Light Pole Steel (1-30 Foot Mast Arm) 4 Each 41,799.48 10,449.87

614-81135 Traffic Signal-Light Pole Steel (1-35 Foot Mast Arm) 4 Each 55,756.36 13,939.09614-81140 Traffic Signal-Light Pole Steel (1-40 Foot Mast Arm) 4 Each 76,750.00 19,187.50614-81145 Traffic Signal-Light Pole Steel (1-45 Foot Mast Arm) 7 Each 129,451.00 18,493.00614-81150 Traffic Signal-Light Pole Steel (1-50 Foot Mast Arm) 4 Each 72,162.00 18,040.50

614-81155 Traffic Signal-Light Pole Steel (1-55 Foot Mast Arm) 8 Each 131,564.90 16,445.61614-81160 Traffic Signal Light Pole Steel (1-60 Mast Arm Foot) 2 Each 48,158.00 24,079.00614-81170 Traffic Signal-Light Pole Steel (1-70 Foot Mast Arm) 1 Each 38,000.00 38,000.00614-81175 Traffic Signal-Light Pole Steel (1-75 Foot Mast Arm) 1 Each 39,000.00 39,000.00

614-81240 Traffic Signal-Light Pole Steel (2-40 Foot Mast Arm) 1 Each 2,260.00 2,260.00614-81265 Traffic Signal-Light Pole Steel (2-65 Foot Mast Arm) 1 Each 14,300.00 14,300.00614-81302 Traffic Signal-Light Pole (2 Mast Arm) (Install Only) 2 Each 3,200.00 1,600.00614-82010 Traffic Signal Pole Steel (1 Mast Arm) 1 Each 24,300.00 24,300.00

614-84000 Traffic Signal Pedestal Pole Steel 7 Each 37,424.39 5,346.34614-84100 Traffic Signal Pedestal Pole Aluminum 18 Each 21,009.10 1,167.17614-84450 Traffic Signal Pedestal Pole Steel (Install Only) 5 Each 690.00 138.00614-84455 Traffic Signal Pedestal Pole (Install Only) 2 Each 2,200.00 1,100.00

614-85001 Impact Attenuator 2 Each 5,151.20 2,575.60614-85005 Impact Attenuator (Sand Filled Plastic Barrel) 11 Each 27,115.40 2,465.04

Page 39: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 27 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

614-85045 Truck with Mounted Attenuator and Flashing Arrow Pane 2 Each 13,859.28 6,929.64614-85115 Impact Attenuator (Quadguard) 9 Each 172,500.00 19,166.67614-85312 Traffic Signal Span Wire Pole (12 Inch) 1 Each 2,625.00 2,625.00614-85362 Traffic Signal-Light Span Wire Pole (12 Inch) 4 Each 19,242.00 4,810.50

614-85366 Traffic Signal-Light Span Wire Pole (16 Inch) 4 Each 28,783.00 7,195.75614-85520 Paint Traffic Signal Pole 1 Each 250.00 250.00614-86000 Traffic Signal Controller (Master) 1 Each 2,516.34 2,516.34614-86002 Spread Spectrum Radio 3 Each 8,814.00 2,938.00

614-86005 Telemetry (Master) 1 Lump Sum 450.00 450.00614-86105 Telemetry (Field) 9 Each 23,679.50 2,631.06614-86240 Traffic Signal Controller (Type 170) 10 Each 149,100.60 14,910.06614-86245 Controller (Type 170E) 9 Each 60,260.90 6,695.66

614-86246 Controller (Type 170E-HC11) 10 Each 125,105.65 12,510.57614-86247 Controller (Type 170E-HC11 W/W70SM Firmware) 2 Each 6,500.00 3,250.00614-86720 Mainline Weigh In Motion Sorter System 1 Lump Sum 250,695.82 250,695.82614-86732 Weigh In Motion Station (Type 2) 3 Each 201,000.00 67,000.00

614-86740 Weather Monitoring System 3 Lump Sum 99,783.18 33,261.06614-86755 Deicing System 1 Lump Sum 225,850.00 225,850.00614-86756 Anti-Icing System 1 Lump Sum 614,500.00 614,500.00614-86800 Uninterrupted Power Supply 1 Each 2,971.00 2,971.00

614-87010 Fiber Optic Cable (Single Mode) (12 Fiber) 6,770 Lin Foot 24,802.70 3.66614-87020 Optical Transceiver 77 Each 168,825.43 2,192.54614-87028 Video Optical Transceiver 11 Each 36,393.17 3,308.47614-87100 Automatic Traffic Recording Station 1 Each 4,460.00 4,460.00

614-87300 Traffic Management System Building 1 Each 60,863.40 60,863.40614-87318 Master Computer and Software 1 Lump Sum 49,304.56 49,304.56614-87320 Closed Circuit Television 6 Each 22,909.62 3,818.27614-87350 Test Fiber Optic Cable 2 Lump Sum 7,155.38 3,577.69

614-87406 Fiber Optic Cable (Single Mode) (6 Strands) 23,660 Lin Foot 92,274.00 3.90614-87424 Fiber Optic Cable (Single Mode) (24 Strands) 9,044 Lin Foot 35,878.15 3.97614-87448 Fiber Optic Cable (Single Mode) (48 Strands) 32,190 Lin Foot 35,087.10 1.09614-87496 Fiber Optic Cable (Single Mode) (96 Strands) 14,000 Lin Foot 31,500.00 2.25

614-87498 Fiber Optic Cable (Single Mode) (144 Strands) 295,380 Lin Foot 599,621.40 2.03614-87660 Video Enc/Dec 5 Each 28,428.90 5,685.78614-87670 Tier II Multiplexer 6 Each 518,036.22 86,339.37614-87680 Sonet Multiplexer 2 Each 373,145.82 186,572.91

614-87690 Ethernet Switch 1 Each 11,953.23 11,953.23614-87700 Ethernet Router 2 Each 38,489.80 19,244.90

Page 40: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 28 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

615-00030 Embankment Protector Type 3 76 Each 70,978.17 933.92615-00050 Embankment Protector Type 5 122 Each 23,117.00 189.48615-00150 Embankment Protector (Special) 30 Each 24,900.00 830.00616-00180 18 Inch Concrete Siphon Pipe 144 Lin Foot 14,400.00 100.00

616-00240 24 Inch Concrete Siphon Pipe 457 Lin Foot 31,076.00 68.00616-30018 18 Inch Trash Guard 2 Each 1,300.00 650.00616-30024 24 Inch Trash Guard 3 Each 1,200.00 400.00616-50048 6 Inch Valve and Valve Box 4 Each 3,770.00 942.50

617-00012 12 Inch Culvert Pipe 296 Lin Foot 8,450.40 28.55617-00015 15 Inch Culvert Pipe 1,959 Lin Foot 68,565.00 35.00617-00018 18 Inch Culvert Pipe 361 Lin Foot 16,638.00 46.09617-00024 24 Inch Culvert Pipe 2,399 Lin Foot 131,682.50 54.89

617-00036 36 Inch Culvert Pipe 518 Lin Foot 34,180.00 65.98617-00048 48 Inch Culvert Pipe 276 Lin Foot 24,840.00 90.00617-03000 Detour Culvert Pipe 1 Lump Sum 2,500.00 2,500.00617-03010 Detour Culvert Pipe 685 Lin Foot 34,240.00 49.99

618-00002 Prestressing Steel Wire or Strand 26,247 M Kip Foot 1,421,730.00 54.17618-00005 Prestressing Steel Bar 280 M Kip Foot 68,434.00 244.41618-00007 Grout (Strand)(Duct) 45 Cubic Foot 5,661.45 125.81618-00163 Prestressed Concrete I (BT63) 1,554 Lin Foot 217,560.00 140.00

618-00172 Prestressed Concrete I (BT72) 2,701 Lin Foot 324,120.00 120.00618-00184 Prestressed Concrete I (BT84) 1,435 Lin Foot 215,250.00 150.00618-01994 Prestressed Concrete Box (Depth 32" Through 48") 48,536 Sq Foot 1,914,944.40 39.45618-06034 Prestressed Concrete Slab (Depth 6" Through 13") 17,969 Sq Foot 722,533.49 40.21

618-10000 Precast Concrete U Girder (Pre-Tensioned) 12,626 Lin Foot 4,734,750.00 375.00619-06060 6 Inch Ductile Iron Pipe 6 Lin Foot 888.00 148.00619-10140 14 Inch Welded Steel Pipe 311 Lin Foot 27,990.00 90.00619-10665 66 Inch Welded Steel Pipe (Jacked) 196 Lin Foot 392,000.00 2,000.00

619-30160 2 Inch Galvanized Pipe 1,242 Lin Foot 10,991.70 8.85619-40060 3/4 Inch Copper Pipe 233 Lin Foot 18,640.00 80.00619-40080 1 Inch Copper Pipe 10 Lin Foot 47.10 4.71619-50060 3/4 Inch Plastic Pipe 1,370 Lin Foot 205.50 0.15

619-50080 1 Inch Plastic Pipe 2,690 Lin Foot 2,447.90 0.91619-50120 1-1/2 Inch Plastic Pipe 1,030 Lin Foot 1,246.30 1.21619-50160 2 Inch Plastic Pipe 1,212 Lin Foot 25,251.60 20.83619-50240 3 Inch Plastic Pipe 440 Lin Foot 2,860.00 6.50

619-50320 4 Inch Plastic Pipe 572 Lin Foot 7,687.20 13.44619-50480 6 Inch Plastic Pipe 440 Lin Foot 3,828.00 8.70

Page 41: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 29 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

619-51280 16 Inch Plastic Pipe 8 Lin Foot 616.00 77.00619-75016 2 Inch Gate Valve 2 Each 700.00 350.00620-00001 Field Office (Class 1) 21 Each 178,378.35 8,494.21620-00002 Field Office (Class 2) 57 Each 829,616.23 14,554.67

620-00005 Field Office (Special) 3 Each 242,000.00 80,666.67620-00011 Field Laboratory (Class 1) 14 Each 94,880.49 6,777.18620-00012 Field Laboratory (Class 2) 76 Each 826,762.30 10,878.45620-00015 Field Laboratory (State Furnished) 6 Each 14,300.00 2,383.33

620-00020 Sanitary Facility 153 Each 175,648.57 1,148.03621-00425 Detour 2 Lump Sum 337,000.00 168,500.00621-00450 Detour Pavement 50,765 Sq Yard 838,980.35 16.53622-00024 Entry Sign 2 Each 5,000.00 2,500.00

622-00100 Shade Shelter 20 Each 140,000.00 7,000.00622-00250 Bench 2 Each 6,400.00 3,200.00622-00270 Bollard 4 Each 2,200.00 550.00622-00300 Barbecue Grill 6 Each 2,400.00 400.00

622-00350 Trash Receptacle 20 Each 11,000.00 550.00622-00550 Wheel Stop (Concrete) 5 Each 310.00 62.00622-00600 Pump Pit 2 Each 50,000.00 25,000.00622-00700 Pump House 1 Each 58,400.00 58,400.00

622-00750 Sewage Lift Station 2 Each 60,000.00 30,000.00622-00800 Comfort Station 3 Each 1,441,540.62 480,513.54622-00825 Modify Building 1 Lump Sum 11,587.00 11,587.00622-00826 CeramicTile & Grout 750 Sq Foot 16,500.00 22.00

622-01000 Leaching Field 7,339 Sq Yard 293,560.00 40.00622-01550 Septic Tank (5500 Gal) 2 Each 40,000.00 20,000.00622-03270 Wastewater System 2 Lump Sum 593,718.00 296,859.00622-05506 Storage Tank (6000 Gal) 2 Each 44,000.00 22,000.00

622-11170 HVAC 2 Lump Sum 25,854.00 12,927.00622-11180 Building Plumbing Piping Systems 2 Lump Sum 82,260.00 41,130.00622-20080 Flagpole 4 Each 11,200.00 2,800.00623-00164 Drip Emitter 286 Each 286.00 1.00

623-00165 Emitter Valve Assembly 1 Each 70.00 70.00623-00186 3/4 Inch Flush Unit 9 Each 180.00 20.00623-00206 6 Inch Pop-Up Spray Sprinkler 48 Each 432.00 9.00623-00306 3/4 Inch Pop-Up Rotary Sprinkler 69 Each 1,104.00 16.00

623-01708 1 Inch Backflow Preventer 1 Each 900.00 900.00623-03108 1 Inch Automatic Control Valve 15 Each 1,500.00 100.00

Page 42: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 30 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

623-04000 Control Wire 24 Volt 3,180 Lin Foot 190.80 0.06623-04002 Power Source Wire 30 Lin Foot 52.50 1.75623-04008 1 Inch Quick-Coupler Valve 2 Each 190.00 95.00623-05016 2 Inch Gate Valve 1 Each 45.00 45.00

623-06900 Valve Box 12 Each 240.00 20.00623-08124 24 Station Automatic Controller 1 Each 2,500.00 2,500.00623-09900 Sprinkler System 1 Lump Sum 43,000.00 43,000.00624-14024 24 Inch Culvert Pipe (CR 4) 4,549 Lin Foot 197,947.92 43.51

624-14030 30 Inch Culvert Pipe (CR 4) 502 Lin Foot 32,486.43 64.71624-14036 36 Inch Culvert Pipe (CR 4) 125 Lin Foot 12,970.70 103.77624-14048 48 Inch Culvert Pipe (CR 4) 75 Lin Foot 13,389.11 178.52625-00000 Construction Surveying 83 Lump Sum 2,177,784.55 26,238.37

625-00001 Construction Surveying (Hourly) 755 Hour 87,863.99 116.38626-00000 Mobilization 136 Lump Sum 15,636,343.40 114,973.11626-01000 Public Information Services 52 Lump Sum 349,243.06 6,716.21627-00001 Pavement Marking Paint 13,156 Gallon 354,865.59 26.97

627-00002 Thermoplastic Pavement Marking 206,958 Sq Foot 307,489.05 1.49627-00003 Thermoplastic Pavement Marking (Inlaid) 54 Sq Foot 972.00 18.00627-00004 Epoxy Pavement Marking 9,535 Sq Foot 8,867.55 0.93627-00005 Epoxy Pavement Marking 90,778 Gallon 3,794,084.53 41.80

627-00011 Pavement Marking Paint (Waterborne) 2,460 Gallon 71,340.00 29.00627-00012 Pavement Marking Paint (Low VOC Solvent Base) 37,952 Gallon 968,175.18 25.51627-00025 4 Inch Pavement Marking Tape (Removable) 22,485 Lin Foot 72,941.10 3.24627-00030 Raised Pavement Marker (Temporary) 19,531 Each 19,531.00 1.00

627-00032 Raised Flexible Pavement Marker (Temporary) 8,474 Each 14,928.20 1.76627-00070 Preformed Thermoplastic Pavement Marking 1,182 Sq Foot 13,837.60 11.71627-00200 Warranted Epoxy Pavement Marking 132,900 Sq Foot 39,870.00 0.30627-00202 Epoxy Pavement Marking (2-Year Warranty) 132,900 Sq Foot 26,580.00 0.20

627-01000 Preformed Plastic Pavement Marking (Type A) 86,006 Sq Foot 719,954.90 8.37627-01003 Preformed Plastic Pavement Marking (Type A) (Inlaid) 31,929 Sq Foot 308,535.66 9.66627-02000 Preformed Plastic Pavement Marking (Type B) 3,016 Sq Foot 26,296.00 8.72627-02003 Preformed Plastic Pavement Marking (Type B) (Inlaid) 396 Sq Foot 5,940.00 15.00

627-03000 Preformed Plastic Pavement Marking (Type C) 11,614 Sq Foot 110,274.10 9.49627-03003 Preformed Plastic Pavement Marking (Type C) (Inlaid) 6,156 Sq Foot 60,067.40 9.76627-30205 Thermoplastic Pavement Marking (Word-Symbol) 50 Sq Foot 497.50 9.95627-30210 Thermoplastic Pavement Marking (Xwalk-Stopline) 1,386 Sq Foot 10,098.00 7.29

627-30305 Preformed Plastic Pavement Marking (60 Mil) (Word-Sym 942 Sq Foot 12,839.10 13.63627-30310 Preformed Plastic Pavement Marking (60 Mil) (Xwalk-St 5,060 Sq Foot 35,926.00 7.10

Page 43: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 31 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

627-30325 Preformed Plastic Pavement Marking (Type B) (Word-Sym 14,034 Sq Foot 177,113.52 12.62627-30330 Preformed Plastic Pavement Marking (Type B) (Xwalk-St 79,951 Sq Foot 631,934.43 7.90627-30405 Preformed Thermoplastic Pavement Marking (Word-Symbol 15,242 Sq Foot 158,311.51 10.39627-30406 Preformed Thermoplastic Pvmt Mkg (Word-Symbol)(Instal 900 Sq Foot 3,825.00 4.25

627-30410 Preformed Thermoplastic Pavement Marking (Xwalk-Stop 81,589 Sq Foot 640,567.86 7.85629-01001 Survey Monument (Type 1) 58 Each 10,070.45 173.63629-01002 Survey Monument (Type 2) 29 Each 11,020.67 380.02629-01003 Survey Monument (Type 3) 2 Each 810.00 405.00

629-01005 Survey Monument (Type 5) 35 Each 7,585.42 216.73629-01006 Survey Monument (Type 6) 1 Each 350.00 350.00629-01011 Survey Monument (Type 1A) 1 Each 155.00 155.00629-01021 Survey Monument (Type 2A) 3 Each 1,066.40 355.47

629-01031 Survey Monument (Type 3A) 30 Each 16,548.70 551.62629-01050 Monument Box 11 Each 3,100.45 281.86629-01110 Locate Monuments 83 Hour 8,943.80 107.76629-01210 Adjust Monument Box 54 Each 11,826.75 219.01

629-01300 Survey Monument (Temporary) 1 Each 160.00 160.00630-00000 Flagging 318,088 Hour 6,415,229.30 20.17630-00001 Pilot Car Operation 6,186 Hour 198,201.60 32.04630-00003 Uniformed Traffic Control 3,746 Hour 201,266.46 53.73

630-00004 Traffic Control Vehicle 20 Each 55,948.51 2,797.43630-00007 Traffic Control Inspection 6,139 Day 490,978.96 79.98630-00009 Traffic Control Vehicle (Truck) 5 Each 53,750.00 10,750.00630-00011 Courtesy Vehicle 150 Day 41,840.97 278.94

630-00012 Traffic Control Management 11,439 Day 4,691,653.97 410.15630-00015 Uniformed Traffic Control Coordination 3,396 Hour 75,409.50 22.21630-00020 Traffic Control Vehicle 5 Day 1,575.00 315.00630-00025 Traffic Control Vehicle 1,280 Hour 19,878.00 15.53

630-10005 Traffic Control 1 Lump Sum 7,300.00 7,300.00630-80001 Flashing Beacon (Portable) 139 Each 97,669.85 702.66630-80002 Flashing Beacon (Solar) 30 Each 16,185.08 539.50630-80305 Flagging Station Light 8 Each 9,547.71 1,193.46

630-80334 Barricade (Type 3 F-D) (Temporary) 2 Each 3,000.00 1,500.00630-80335 Barricade (Type 3 M-A) (Temporary) 139 Each 21,814.82 156.94630-80336 Barricade (Type 3 M-B) (Temporary) 182 Each 33,130.42 182.04630-80337 Barricade (Type 3 M-C) (Temporary) 119 Each 36,878.80 309.91

630-80338 Barricade (Type 3 M-D) (Temporary) 2 Each 38.00 19.00630-80341 Construction Traffic Sign (Panel Size A) 3,105 Each 178,430.60 57.47

Page 44: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

Colorado Department of Transporation 16:48 Thursday, January 27, 2005 32 2004 Cost Data

INDEX AND AVERAGE UNIT BID PRICES FOR 01/01/04 THROUGH 12/31/04

------------------------------------------------------------------------------------------------------------------------------------ITEM NUMBER ITEM TOTAL QUANTITY UNIT TOTAL COST AVERAGE PRICE------------------------------------------------------------------------------------------------------------------------------------

630-80342 Construction Traffic Sign (Panel Size B) 6,292 Each 486,430.39 77.31630-80343 Construction Traffic Sign (Panel Size C) 1,353 Each 119,499.52 88.32630-80344 Construction Traffic Sign (Special) 13,353 Sq Foot 222,047.47 16.63630-80350 Vertical Panel 175 Each 2,630.00 15.03

630-80351 Vertical Panel (Plastic) 35 Each 1,645.00 47.00630-80355 Portable Message Sign Panel 164 Each 896,713.16 5,467.76630-80356 Advance Warning Flashing or Sequencing Arrow Panel (A 10 Each 9,526.00 952.60630-80357 Advance Warning Flashing or Sequencing Arrow Panel (B 11 Each 11,442.00 1,040.18

630-80358 Advance Warning Flashing or Sequencing Arrow Panel (C 194 Each 266,722.76 1,374.86630-80359 Portable Message Sign Panel 4,647 Day 404,247.60 86.99630-80360 Drum Channelizing Device 15,289 Each 545,909.52 35.71630-80363 Drum Channelizing Device (With Light) (Flashing) 446 Each 24,150.48 54.15

630-80364 Drum Channelizing Device (With Light) (Steady Burn) 423 Each 20,170.00 47.68630-80365 Portable Message Sign Panel (State Furnished) 17 Each 6,615.00 389.12630-80367 Portable Traffic Speed Monitor 4 Each 10,500.00 2,625.00630-80370 Concrete Barrier (Temporary) 75,520 Lin Foot 1,333,641.40 17.66

630-80376 Guardrail Type 7 (Temporary) 13,558 Lin Foot 473,870.20 34.95630-80380 Traffic Cone 38,016 Each 368,135.91 9.68630-80384 Tubular Marker 1,685 Each 34,503.31 20.48630-80391 Channelizing Device (Fixed) 605 Each 41,720.00 68.96

630-80401 Delineator (Type I) (Temporary) 120 Each 3,120.00 26.00630-80403 Delineator (Type III) (Temporary) 54 Each 996.61 18.46630-80510 Mobile Pavement Marking Zone 18 Lump Sum 39,909.25 2,217.18630-80520 Mobile Pavement Marking Zone 104 Day 45,233.86 434.94

630-80560 Mobile Profilograph Operation Zone 8 Lump Sum 17,876.30 2,234.54630-85006 Impact Attenuator (Sand Filled Plastic Barrel) (Tempo 38 Each 62,005.20 1,631.72630-85010 Impact Attenuator (Temporary) 77 Each 328,806.54 4,270.21630-85040 Impact Attenuator (Truck Mounted Attenuator) (Tempora 12 Each 135,510.88 11,292.57

630-85115 Impact Attenuator (Quadguard) (Temporary) 2 Each 11,347.66 5,673.83630-86800 Traffic Signal (Temporary) 6 Lump Sum 163,757.67 27,292.95630-86820 Traffic Signal (Temporary)(State Furnished) 2 Each 300.00 150.00652-00000 Fire Protection Systems 1 Lump Sum 34,350.00 34,350.00

Page 45: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 1 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 201-00000 Clear and Grub LUMP SUM ===============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 1.00 800000.00 633792.17 250000.00STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 1.00 1000.00 12193.33 5500.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 50000.00 31662.50 30000.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1.00 15000.00 35187.85 12600.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1.00 25000.00 80250.00 40000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5.00 178200.00 156414.76 67620.00

NH 0502-053 CIMARRON - WEST 04/15/04 1.00 25000.00 46444.74 50000.00IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 1.00 6000.00 30955.76 13164.34NH 2852-010 US 285 & COUNTY RD. G 04/29/04 1.00 4000.00 18431.20 15000.00STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 1.00 10000.00 11841.00 10000.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 1.00 20000.00 17333.39 29000.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 50000.00 44431.43 50000.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 1.00 10000.00 8425.00 3200.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 1.00 2000.00 8271.43 17000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 8.00 15875.00 23941.76 23420.54

SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 1.00 5000.00 8800.00 7600.00STA 149A-021 SH 149 CRIBWALL 09/16/04 1.00 7800.00 8700.00 8700.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 9000.00 52000.00 20000.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 1.00 20000.00 35281.50 20000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4.00 10450.00 34129.64 14075.00

SHE 105A-010 SH 105/FURROW RD 10/07/04 1.00 25000.00 20604.94 15000.00C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 1.00 1000.00 7000.00 8000.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 1.00 25000.00 37760.00 5000.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 24000.00 38391.39 30000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4.00 18750.00 28711.89 14500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 21.00 54038.10 65922.03 30464.97

=============== 201-00001 Clear and Grub Acre ===================================================

STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 5.25 2000.00 1110.00 1000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5.25 2000.00 1110.00 1000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5.25 2000.00 1110.00 1000.00

Page 46: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 2 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00000 Rem Str and Obstructions LUMP SUM ===============================================

STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 1.00 5400.00 3558.83 3500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 5400.00 3558.83 3500.00

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 1.00 5000.00 22535.45 15423.13NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 10000.00 32886.97 75000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 7500.00 27313.07 45211.57

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 1.00 50000.00 25094.50 15000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 50000.00 25094.50 15000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 17600.00 20730.48 27230.78

=============== 202-00001 Rem Structure Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 1.00 600.00 557.30 230.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 1.00 1100.00 1527.11 1150.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 12.00 500.00 646.63 479.78STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 1.00 800.00 1065.55 725.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 2.00 800.00 586.57 600.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 1.00 700.00 605.50 800.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 1.00 1000.00 1017.66 524.00C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 2.00 3500.00 1800.00 1800.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1.00 650.00 16900.00 30000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 22.00 884.09 997.91 1999.38

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 2.00 700.00 520.83 255.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 14.00 600.00 288.81 255.32NH 2852-010 US 285 & COUNTY RD. G 04/29/04 1.00 1000.00 1493.79 485.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 25.00 600.00 371.90 500.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 4.00 1000.00 1029.54 1000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 46.00 647.83 419.51 458.03

Page 47: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 3 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00001 Rem Structure Each ===================================================

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 115.00 300.00 329.12 430.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 2500.00 1098.09 600.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1.00 500.00 1186.26 350.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 1.00 700.00 1200.00 1000.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 2.00 10000.00 12850.11 6500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 120.00 485.00 485.11 536.67

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 39.00 500.00 821.75 800.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 4.00 1000.00 533.40 450.00STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 1.00 1000.00 853.55 537.45 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 44.00 556.82 804.28 762.21 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 232.00 568.75 579.65 702.56

=============== 202-00002 Rem of Structure (Spec) Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 1.00 7500.00 3292.30 5578.80STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 1.00 6500.00 10960.00 6500.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 1.00 1000.00 956.73 610.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3.00 5000.00 5069.67 4229.60

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 9.00 25000.00 19525.00 6500.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 11.00 2000.00 2052.42 1200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 20.00 12350.00 9915.08 3585.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 23.00 11391.30 9025.11 3669.08

=============== 202-00003 Rem of Structure (Spec) LUMP SUM ===============================================

STA 0703-290 GEORGETOWN HILL ROCKFALL MITI 10/07/04 1.00 15000.00 43320.00 18000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 15000.00 43320.00 18000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 15000.00 43320.00 18000.00

Page 48: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 4 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00009 Tree Trimming LUMP SUM ===============================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 1.00 5000.00 3831.06 1500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 5000.00 3831.06 1500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 5000.00 3831.06 1500.00

=============== 202-00010 Rem Tree Each ===================================================

STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 1.00 250.00 332.02 230.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 7.00 200.00 453.08 300.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 7.00 450.00 289.68 310.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 15.00 320.00 379.65 300.00

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 5.00 250.00 339.10 196.86STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 1.00 250.00 566.67 100.00STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 3.00 300.00 333.33 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 9.00 266.67 350.16 153.81

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 78.00 275.00 277.57 300.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 1.00 700.00 563.53 383.87NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 10.00 150.00 478.75 400.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 22.00 400.00 278.29 350.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 111.00 292.34 292.54 319.67

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 71.00 200.00 249.68 205.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 71.00 200.00 249.68 205.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 206.00 261.41 287.63 271.47

=============== 202-00011 Tree Trimming Each ===================================================

STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 15.00 80.00 189.94 321.65 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 15.00 80.00 189.94 321.65 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 15.00 80.00 189.94 321.65

Page 49: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 5 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00015 Rem Headwall Each ===================================================

STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 2.00 400.00 935.00 1000.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 6.00 300.00 467.15 570.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 8.00 325.00 568.85 677.50

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 3.00 300.00 304.36 371.21NH 0502-053 CIMARRON - WEST 04/15/04 5.00 400.00 417.01 500.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 4.00 400.00 625.00 300.00IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 1.00 1000.00 1922.46 1842.21SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 3.00 700.00 682.69 430.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 2.00 300.00 459.29 250.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 18.00 455.56 577.35 469.21

NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 4.00 400.00 591.80 402.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4.00 400.00 591.80 402.20 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 30.00 413.33 576.33 515.82

=============== 202-00019 Rem Inlet Each ===================================================

STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 1.00 1000.00 1084.50 1256.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 1000.00 1084.50 1256.00

SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 2.00 270.00 650.00 300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 270.00 650.00 300.00

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 9.00 1000.00 698.86 350.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 9.00 1000.00 698.86 350.00

Page 50: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 6 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00019 Rem Inlet Each ===================================================

NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 16.00 250.00 1162.50 1300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 16.00 250.00 1162.50 1300.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 28.00 519.29 997.86 921.64

=============== 202-00020 Rem CBC Each ===================================================

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 28.00 2000.00 1469.33 750.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 28.00 2000.00 1469.33 750.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1.00 20000.00 20863.09 25000.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 1.00 5000.00 6705.15 3420.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 12500.00 16143.78 14210.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 30.00 2700.00 2215.49 1647.33

=============== 202-00023 Rem Emb Prot Ty 3 Each ===================================================

IM 0701-157 FRUITA TO CLIFTON 02/26/04 1.00 500.00 1208.33 200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 500.00 1208.33 200.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 3.00 200.00 540.90 305.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3.00 200.00 540.90 305.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 275.00 707.76 278.75

=============== 202-00024 Rem Emb Prot Ty 5 Each ===================================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 4.00 300.00 521.47 260.00

Page 51: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 7 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00024 Rem Emb Prot Ty 5 Each ===================================================C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 1.00 400.00 975.84 830.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 5.00 320.00 599.81 374.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5.00 320.00 599.81 374.00

=============== 202-00025 Rem Ditch Lining Lin Foot ===============================================

STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 35.00 6.00 10.42 7.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 35.00 6.00 10.42 7.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 35.00 6.00 10.42 7.00

=============== 202-00026 Rem S and D Pave Sq Yard ================================================

IM 0701-157 FRUITA TO CLIFTON 02/26/04 40.00 5.00 24.83 50.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 240.00 9.50 11.50 13.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 280.00 8.86 15.94 18.29

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 102.00 10.00 15.09 10.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 15.00 25.00 19.50 15.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 117.00 11.92 15.48 10.64

NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 21.80 40.00 42.33 38.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 21.80 40.00 42.33 38.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 418.80 11.33 18.01 17.18

=============== 202-00027 Rem Riprap Sq Yard ================================================

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 44.00 10.00 15.55 11.76 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 44.00 10.00 15.55 11.76 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 44.00 10.00 15.55 11.76

Page 52: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 8 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00030 Rem Water Service Each ===================================================

SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 1.00 300.00 1075.00 600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 300.00 1075.00 600.00

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 600.00 2243.93 3025.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 600.00 2243.93 3025.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 450.00 1659.47 1812.50

=============== 202-00033 Rem Pipe Each ===================================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 2.00 700.00 600.23 315.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 10.00 700.00 1635.70 1004.18STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 2.00 1500.00 900.00 1000.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 6.00 1000.00 2100.93 2370.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 20.00 870.00 1632.56 1344.59

NH 0502-053 CIMARRON - WEST 04/15/04 33.00 500.00 736.48 700.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 1.00 700.00 1132.80 840.00STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 1.00 2000.00 840.00 120.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 19.00 1200.00 1586.75 1300.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 5.00 655.00 1737.24 780.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 59.00 767.37 1130.53 892.54

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 28.00 535.00 657.86 700.00STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 3.00 1250.00 466.75 417.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 15.00 610.00 802.50 480.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 46.00 606.09 681.68 609.80

BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 3.00 600.00 705.63 300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3.00 600.00 705.63 300.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 128.00 721.52 1020.05 847.68

Page 53: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 9 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00035 Rem Pipe Lin Foot ===============================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 7.00 20.00 38.94 33.00STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 4.50 35.00 34.00 33.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 403.00 15.00 13.02 9.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 28.00 27.00 32.00 9.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 4.00 40.00 43.72 45.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 170.00 11.00 15.75 10.50STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 558.00 13.00 9.25 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,174.50 13.95 13.79 10.05

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 64.00 15.00 15.65 13.10STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 2,359.00 15.00 10.13 5.42STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 175.00 10.00 13.21 7.50SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 81.00 20.00 35.88 23.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 180.00 12.00 17.30 25.20SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 4.00 50.00 107.75 61.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2,863.00 14.70 11.14 7.54

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 4.00 42.00 67.25 99.00IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 849.00 15.00 11.34 8.50SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 77.00 20.00 31.25 12.50IMD 0252-364 I-25 OVER BROADWAY 07/29/04 3.00 40.00 158.67 100.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 345.00 14.00 20.75 14.50STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 829.00 12.00 22.76 10.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 200.00 15.00 19.15 13.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 741.00 16.00 10.57 16.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 3,048.00 14.50 16.08 12.02

SHE 105A-010 SH 105/FURROW RD 10/07/04 140.00 17.00 18.24 20.00C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 40.00 125.00 140.00 130.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 221.00 20.00 15.00 12.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 3,348.00 13.00 12.92 9.50BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 229.00 15.00 16.54 15.00STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 49.00 49.00 138.25 40.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 231.00 16.00 18.45 4.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4,258.00 15.23 14.97 11.47 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 11,343.50 14.77 13.75 10.48

Page 54: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 10 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00037 Rem of End Section Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 1.00 200.00 340.43 250.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 15.00 125.00 119.48 105.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 9.00 200.00 175.59 250.00NH 2872-016 US 287 - LAMAR 03/04/04 4.00 200.00 187.23 180.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 2.00 170.00 198.67 102.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 31.00 161.77 154.26 161.26

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 1.00 250.00 257.08 180.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 9.00 250.00 161.75 123.74STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 3.00 150.00 125.58 136.67SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 10.00 320.00 151.84 171.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 3.00 280.00 160.25 200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 26.00 268.85 157.62 154.37

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 146.00 100.00 158.23 120.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 3.00 200.00 204.57 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 149.00 102.01 159.01 119.60

C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 1.00 200.00 2750.00 1500.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 1.00 150.00 220.80 150.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 2.00 200.00 258.98 225.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4.00 187.50 578.39 525.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 210.00 133.12 162.81 137.77

=============== 202-00040 Rem Elec Conduit Lin Foot ===============================================

SHE R300-113 DOWD BRIDGE, I-70 03/18/04 450.00 1.00 6.40 2.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 450.00 1.00 6.40 2.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 450.00 1.00 6.40 2.50

Page 55: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 11 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00070 Rem Barricade Each ===================================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 15.00 230.00 65.00 90.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 15.00 230.00 65.00 90.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 15.00 230.00 65.00 90.00

=============== 202-00080 Rem Guard Post Each ===================================================

CC R600-225 CHATFIELD STATE PARK 06/10/04 53.00 40.00 21.75 26.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 53.00 40.00 21.75 26.00

STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 1.00 125.00 95.00 50.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 125.00 95.00 50.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 54.00 41.57 22.77 26.44

=============== 202-00090 Rem Delineator Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 35.00 10.00 11.57 10.00STA 2911-001 SH 291 SALIDA NORTH 01/08/04 147.00 7.00 5.78 7.00STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 355.00 5.00 7.17 5.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 5.00 10.00 10.18 12.28IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 42.00 8.00 6.16 1.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 196.00 6.00 6.70 2.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 34.00 5.00 10.00 6.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 20.00 8.00 12.00 6.00NH 2872-016 US 287 - LAMAR 03/04/04 136.00 6.00 9.40 4.00SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 50.00 8.50 6.67 10.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 332.00 5.00 5.58 4.80STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 75.00 7.00 2.78 2.55 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,427.00 5.94 6.83 4.77

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 287.00 7.00 3.85 1.55

Page 56: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 12 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00090 Rem Delineator Each ===================================================NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 900.00 5.00 6.85 1.00NH 0502-053 CIMARRON - WEST 04/15/04 78.00 6.00 5.17 5.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 163.00 5.00 7.40 2.60STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 150.00 5.00 6.73 8.32STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 6.00 9.00 16.33 33.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 70.00 20.00 24.05 47.90STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 28.00 8.00 8.32 3.50IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 50.00 3.00 7.12 9.35NH 2852-010 US 285 & COUNTY RD. G 04/29/04 12.00 7.00 9.88 11.40STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 60.00 10.00 8.69 11.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 200.00 9.00 5.62 4.10NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 16.00 8.00 2.63 2.60BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 16.00 15.00 6.79 2.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2,036.00 6.49 6.61 4.53

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 82.00 4.00 10.63 7.00STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 121.00 5.00 9.29 10.00SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 3.00 20.00 17.00 14.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 50.00 8.00 5.40 8.40STA 149A-021 SH 149 CRIBWALL 09/16/04 5.00 10.00 16.00 16.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 85.00 6.00 7.32 5.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 346.00 5.64 9.03 7.95

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 10.00 8.50 12.60 16.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 150.00 6.00 4.44 5.25STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 92.00 4.00 4.80 6.00STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 50.00 8.00 6.13 7.50NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 1,000.00 4.00 4.75 8.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,302.00 4.42 4.84 7.58 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5,111.00 5.75 6.51 5.60

=============== 202-00100 Rem of Dome Chan Device Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 7.00 1.00 102.96 200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 7.00 1.00 102.96 200.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 7.00 1.00 102.96 200.00

Page 57: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 13 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00150 Rem Wall Each ===================================================

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 600.00 1593.64 3000.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 990.00 1042.50 1200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 795.00 1348.69 2100.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 795.00 1348.69 2100.00

=============== 202-00155 Rem Wall Lin Foot ===============================================

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 94.00 40.00 24.44 21.92 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 94.00 40.00 24.44 21.92

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 147.00 30.00 120.06 190.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 147.00 30.00 120.06 190.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 241.00 33.90 63.64 124.44

=============== 202-00165 Rem Wall LUMP SUM ===============================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 15000.00 9950.75 15275.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 15000.00 9950.75 15275.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 15000.00 9950.75 15275.00

=============== 202-00170 Grinding And Texturing Conc Pvmt Sq Yard ================================================

STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 38,812.00 4.50 4.56 6.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 38,812.00 4.50 4.56 6.10 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 38,812.00 4.50 4.56 6.10

=============== 202-00175 Rem Concrete LUMP SUM ===============================================

STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1.00 1000.00 2385.78 690.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 1000.00 2385.78 690.00

Page 58: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 14 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00175 Rem Concrete LUMP SUM ===============================================

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 1.00 800.00 4440.00 1100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 800.00 4440.00 1100.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 900.00 3241.71 895.00

=============== 202-00190 Rem of Conc Median Cover Matl Sq Yard ================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 338.00 10.00 7.77 5.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 338.00 10.00 7.77 5.00

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 58.00 8.00 12.89 5.80NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1,144.00 5.00 7.83 3.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,202.00 5.14 8.01 3.42

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 374.00 5.00 5.62 4.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 374.00 5.00 5.62 4.10 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,914.00 5.97 7.42 3.83

=============== 202-00195 Rem of Median Cover Sq Yard ================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 8,102.00 5.00 5.78 1.30STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 3,792.00 6.00 4.17 5.66NH 2872-016 US 287 - LAMAR 03/04/04 132.00 8.00 16.25 12.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 9.00 12.00 20.02 19.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 51.00 6.00 22.12 9.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 12,086.00 5.36 5.55 2.83

BR 0243-063 EAST OF LIMON 07/15/04 1,410.00 6.00 4.37 3.00

Page 59: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 15 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00195 Rem of Median Cover Sq Yard ================================================IMD 0252-364 I-25 OVER BROADWAY 07/29/04 167.00 6.00 10.90 6.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,577.00 6.00 5.26 3.32

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1,045.00 7.00 6.46 4.10STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 80.00 10.00 15.07 16.10NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 64.00 12.50 18.46 8.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,189.00 7.50 7.60 5.12 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 14,852.00 5.60 5.66 3.07

=============== 202-00200 Rem Sidewalk Sq Yard ================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 57.00 12.00 16.67 5.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 680.00 4.00 11.48 6.50STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 960.00 6.00 10.73 10.70STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 1,389.00 5.00 6.76 3.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 250.00 12.00 17.69 15.50STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 672.00 4.00 12.53 8.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 1,448.00 6.00 8.70 6.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 390.00 6.00 14.69 10.23IM 0701-157 FRUITA TO CLIFTON 02/26/04 28.00 20.00 17.25 5.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 234.00 6.00 4.71 5.20STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 154.00 8.00 11.45 9.00NH 2872-016 US 287 - LAMAR 03/04/04 394.00 6.50 9.50 7.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 119.00 20.00 15.33 19.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 72.00 7.00 22.73 14.26 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 6,847.00 6.06 10.36 7.28

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 482.00 8.00 7.30 3.69SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 18.00 10.00 41.03 39.55STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 185.00 12.00 7.23 7.10STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 313.00 9.00 10.90 23.10NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 1,091.00 6.00 10.51 10.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 250.00 7.00 7.51 8.50NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 5.00 9.00 46.66 9.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 858.00 5.50 10.44 7.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3,202.00 6.91 9.33 9.61

Page 60: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 16 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00200 Rem Sidewalk Sq Yard ================================================

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 475.00 10.00 11.17 6.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 2,867.00 7.00 6.93 5.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 3,342.00 7.43 7.66 5.14

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 4,759.00 4.00 4.12 3.60STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 122.00 10.00 17.33 10.00STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 616.00 8.00 16.52 10.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 100.00 8.00 24.06 30.80STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 408.00 4.00 17.38 19.90STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 2,274.00 6.00 10.25 10.84STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 21.00 20.00 54.03 19.35NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 671.00 6.00 19.72 19.80 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 8,971.00 5.09 8.48 8.25 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 22,362.00 6.00 9.19 7.69

=============== 202-00201 Rem Curb Lin Foot ===============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 300.00 3.00 4.75 7.97STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 1,485.00 5.00 2.55 2.60STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 80.00 5.00 7.90 6.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 1,904.00 5.00 11.11 7.80STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1,908.00 3.00 3.75 5.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5,677.00 4.22 6.66 5.48

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 7,127.00 3.00 2.53 0.90STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 3,010.00 3.00 1.63 2.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 10,137.00 3.00 2.26 1.23

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 80,880.00 2.00 0.98 1.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 80,880.00 2.00 0.98 1.60

Page 61: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 17 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00201 Rem Curb Lin Foot ===============================================

C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 882.00 4.00 5.51 3.00STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 463.00 5.00 4.47 5.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 8,212.00 2.50 2.16 2.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 9,557.00 2.76 2.52 2.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 106,251.00 2.28 1.47 1.85

=============== 202-00202 Rem Gutter Lin Foot ===============================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 300.00 4.00 5.68 3.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 259.00 8.00 7.43 5.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 45.00 10.00 19.13 4.65STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 305.00 6.00 8.20 7.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 909.00 6.11 7.57 4.99

SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 153.00 7.00 9.88 7.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 153.00 7.00 9.88 7.50

STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 8.00 10.00 41.08 21.50NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 386.00 3.00 25.57 11.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 394.00 3.14 25.83 11.21 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,456.00 5.40 12.23 6.94

=============== 202-00203 Rem Curb and Gutter Lin Foot ===============================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 640.00 7.00 4.95 3.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 14,676.00 4.00 3.70 3.70STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 1,640.00 4.00 6.15 3.75STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 2,420.00 4.00 6.18 6.20

Page 62: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 18 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00203 Rem Curb and Gutter Lin Foot ===============================================STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 3,376.00 3.00 4.17 2.50STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 1,098.00 5.00 7.73 4.65STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 1,362.00 4.00 6.24 5.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 12,131.00 4.00 5.77 3.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 1,280.00 4.00 7.13 5.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 762.00 5.00 8.02 5.12STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 20.00 6.00 29.50 33.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 608.00 7.00 3.76 2.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 327.00 6.00 7.17 2.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 16,567.00 2.75 2.34 2.45NH 2872-016 US 287 - LAMAR 03/04/04 1,740.00 4.00 5.75 5.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 185.00 10.00 9.18 10.50STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 373.00 4.00 7.99 5.55STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 342.00 6.30 4.25 5.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 59,547.00 3.73 4.40 3.39

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 1,713.00 5.00 3.80 2.54SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 133.00 6.00 16.11 15.70STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 242.00 5.00 6.20 6.10STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 515.00 4.00 5.58 8.50STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 80.00 7.00 5.83 4.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 2,979.00 5.00 5.27 4.50NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 655.00 6.00 4.96 4.40NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 152.00 7.00 5.60 5.30SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 2,227.00 3.50 5.00 4.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 8,696.00 4.70 4.76 4.44

BR 0243-063 EAST OF LIMON 07/15/04 1,194.00 5.00 3.37 2.50NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 740.00 4.00 4.68 3.85STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1,863.00 3.00 7.06 4.20C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 119.00 4.00 5.53 5.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 2,052.00 3.00 5.15 2.30IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 3,807.00 5.00 5.25 5.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 9,775.00 4.11 5.46 3.89

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 7,146.00 3.50 3.17 3.75

Page 63: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 19 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00203 Rem Curb and Gutter Lin Foot ===============================================BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 10,078.00 2.50 3.42 2.50STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 340.00 7.00 10.67 7.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 490.00 5.00 7.35 6.45STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 948.00 4.00 6.54 6.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 250.00 6.00 8.18 8.51STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 1,540.00 4.00 7.91 4.85STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 210.00 5.00 9.38 7.65IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 40.00 10.00 16.33 35.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 522.00 4.00 9.00 10.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 2,984.00 5.00 6.35 3.48STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 1,174.00 5.00 7.60 3.75NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 18,020.00 2.90 6.47 3.75NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 1,508.00 4.00 10.28 5.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 45,250.00 3.30 5.65 3.78 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 123,268.00 3.67 4.86 3.65

=============== 202-00204 Rem C, G and Sidewalk Lin Foot ===============================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 70.00 7.00 10.69 10.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 162.00 6.00 20.33 11.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 232.00 6.30 14.64 10.70

STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 1,491.00 6.00 3.31 4.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,491.00 6.00 3.31 4.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,723.00 6.04 5.19 4.90

=============== 202-00206 Rem Conc Curb Ramp Sq Yard ================================================

NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 44.00 7.00 12.78 10.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 44.00 7.00 12.78 10.50

STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 168.00 10.00 18.00 12.00

Page 64: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 20 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00206 Rem Conc Curb Ramp Sq Yard ================================================STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 12.00 15.00 31.08 19.30STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 204.00 10.00 18.43 25.81STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 36.00 15.00 22.77 14.00STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 207.00 15.00 23.01 16.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 627.00 12.03 20.84 18.10 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 671.00 11.70 20.34 17.60

=============== 202-00210 Rem Conc Pavement Sq Yard ================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 11.00 20.00 43.57 9.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 53.00 20.00 16.37 15.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 59.00 25.00 240.22 198.00STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 515.00 8.00 8.33 4.50STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 447.00 15.00 13.39 10.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 1,596.00 10.00 18.50 15.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1,867.00 5.00 8.00 8.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 707.00 4.00 19.44 17.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5,255.00 7.94 14.10 13.38

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 345.00 10.00 12.41 4.51STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 3,328.00 12.00 10.33 10.15NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 13,780.00 3.00 4.14 3.20NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 80.00 3.00 23.23 28.40SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 219.00 2.70 13.88 13.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 17,752.00 4.82 5.01 4.77

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 47,651.00 1.50 3.68 4.75IM 0701-168 RIFLE TO SILT SLAB REPAIR 08/05/04 11,312.00 17.00 17.67 14.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 101.00 15.00 26.00 35.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 59,064.00 4.49 5.61 6.57

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 672.00 7.00 9.99 8.50

Page 65: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 21 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00210 Rem Conc Pavement Sq Yard ================================================NH 2873-137 US 287 IN BOULDER & LARIMER C 11/18/04 2,500.00 8.00 31.81 23.10STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 20.00 15.00 45.22 50.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 486.00 20.00 12.50 16.72NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 223.00 6.00 23.60 12.00NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 646.00 12.00 25.93 23.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4,547.00 9.64 26.73 19.83 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 86,618.00 5.04 7.57 7.31

=============== 202-00212 Rem Conc Pavement (Spec) Sq Yard ================================================

SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 10.00 3.00 39.50 51.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 10.00 3.00 39.50 51.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10.00 3.00 39.50 51.00

=============== 202-00215 Rem Conc Pvmt (Planing) Sq Yard ================================================

NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 15,082.00 3.00 2.24 1.85IM 0761-185 I-76, LOCHBUIE TO HUDSON 06/24/04 1,268.00 5.00 7.14 6.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 16,350.00 3.16 2.70 2.23 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 16,350.00 3.16 2.70 2.23

=============== 202-00220 Rem Asphalt Mat Sq Yard ================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 4,363.00 6.00 4.99 3.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 43,025.00 2.00 3.24 2.19STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 12,702.00 1.50 3.13 2.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 20.00 20.00 35.76 28.50C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 378.00 16.00 7.07 3.50STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 832.00 10.00 14.05 14.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 7,019.00 5.00 11.25 7.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 1,455.00 10.00 7.62 7.16STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 975.00 5.00 9.55 16.10IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 14,731.00 2.50 2.23 2.15STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 8,008.00 5.00 2.75 3.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 5.00 40.00 45.43 43.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 1,970.00 5.00 7.38 3.00

Page 66: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 22 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00220 Rem Asphalt Mat Sq Yard ================================================STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 10,379.00 3.75 3.09 3.26NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 8,227.00 2.50 7.64 4.80SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 632.00 10.00 9.50 5.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 92.50 10.00 23.12 27.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 1,282.00 5.00 3.25 2.50STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 2,028.00 5.00 8.72 4.25STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 23,884.00 1.50 1.33 1.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 142,007.50 2.86 4.28 2.92

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 50.00 10.00 21.30 10.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 4,946.00 8.00 6.92 5.45SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 2,141.00 3.00 5.43 4.30NH 0502-053 CIMARRON - WEST 04/15/04 600.00 6.00 7.97 8.00STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 250.00 20.00 19.33 12.00STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 2,634.00 6.00 5.72 5.41NH 2852-010 US 285 & COUNTY RD. G 04/29/04 3,476.00 3.00 3.61 2.20STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 13,571.00 3.00 2.67 1.50STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 5,645.00 3.00 2.25 2.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 33,798.00 4.25 5.91 5.50NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 48,487.00 3.00 2.57 1.70SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 1,626.00 2.80 5.81 6.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 117,224.00 3.69 3.66 3.22

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 27,446.00 1.50 2.28 3.30SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 250.00 15.00 23.50 21.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 14,988.00 3.00 3.28 3.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 31,564.00 1.00 1.55 1.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 28,704.00 2.00 4.62 2.50C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 4,690.00 2.50 5.08 3.50NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 38,382.00 3.00 1.54 1.25IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 17,505.00 3.00 2.78 2.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 163,529.00 2.19 2.74 2.10

SHE 105A-010 SH 105/FURROW RD 10/07/04 5,481.00 5.00 3.68 3.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 1,073.00 15.00 10.30 4.50BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 553.00 5.00 13.58 25.00

Page 67: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 23 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00220 Rem Asphalt Mat Sq Yard ================================================IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 71,856.00 1.50 2.73 3.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 9,670.00 4.00 2.18 1.75ER 0702-255 I-70 GLENWOOD CANYON 11/30/04 4,250.00 15.00 12.00 2.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 1,040.00 7.00 7.00 7.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 1,025.00 8.00 11.24 9.90NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 677.00 10.00 6.43 7.30STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 1,264.00 10.00 6.78 4.05 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 96,889.00 3.01 3.31 3.13 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 519,649.50 2.87 3.53 2.77

=============== 202-00226 Rem of Asph Mat (Special) Sq Yard ================================================

STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 15.00 35.00 16.54 7.16 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 15.00 35.00 16.54 7.16 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 15.00 35.00 16.54 7.16

=============== 202-00240 Rem Asphalt Mat (Planing) Sq Yard ================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 190,956.00 1.00 0.96 0.75STA 2911-001 SH 291 SALIDA NORTH 01/08/04 1,914.00 5.00 3.40 5.00IM 0704-203 I-70, GENOA-EAST, M.P. 374 - 01/15/04 285,120.00 1.00 1.15 1.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 102,367.00 1.50 1.38 1.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 126,414.00 1.00 0.87 0.85STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 266,952.00 0.50 0.74 0.50IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 266,304.00 2.50 0.96 0.81NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 81,664.00 1.50 1.17 1.97STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 319.00 10.00 26.19 13.95STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 94,241.00 1.25 1.14 1.10STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 119,952.00 1.00 0.88 0.80STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 71,680.00 1.00 1.18 1.20IM 0701-164 PARACHUTE EAST & WEST 02/12/04 32,970.00 1.50 2.55 2.80STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 2,712.00 2.80 5.35 3.79STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 91,408.00 1.25 1.21 1.00STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 2,368.00 1.50 3.55 2.50STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 1,000.00 3.00 6.35 3.25IM 0701-157 FRUITA TO CLIFTON 02/26/04 51,132.00 1.30 1.72 1.25STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 98,804.00 0.40 0.79 0.65STA 014A-030 SH 14, WALDEN EAST 03/04/04 4,283.00 3.00 3.43 4.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 10,229.00 5.00 1.67 1.00NH 2872-016 US 287 - LAMAR 03/04/04 202,292.00 0.85 1.62 1.38

Page 68: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 24 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00240 Rem Asphalt Mat (Planing) Sq Yard ================================================NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 134,722.00 1.00 1.03 0.95STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 4,811.00 3.25 3.51 2.90NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 184,029.00 1.00 1.05 1.20STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 12,964.00 2.50 3.55 5.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1,801.00 5.00 2.95 2.80STA 0063-016 CLIFTON TO PALISADE 03/25/04 20,431.00 1.00 2.77 2.40STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 4,933.00 1.30 3.64 4.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,468,772.00 1.18 1.13 1.05

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 227,520.00 1.00 0.83 0.64NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 8,500.00 1.50 3.31 2.25NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 3,123.00 4.00 3.94 3.50NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 63,254.00 1.00 1.49 1.55STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 5,116.00 2.00 2.80 2.30ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 7,710.00 15.00 39.08 85.83STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 82,489.00 1.40 1.56 1.30NH 0741-015 - SMA Alt SH 74 EVERGREEN OVERLAY 04/29/04 855.00 8.00 11.18 4.35SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 35,099.00 1.50 1.25 1.20STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 1,451.00 5.00 4.80 5.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 30,984.00 2.25 2.53 2.10STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 403.00 9.00 8.11 7.82NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 2,196.00 1.50 4.00 4.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 8,221.00 1.50 2.98 2.80NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 201,748.00 0.85 1.31 1.10IM 0253-186 I-25, 120TH TO SH 7 06/17/04 316,323.00 1.50 1.11 1.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 7,108.00 2.00 3.31 2.25BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 8,907.00 2.00 1.89 1.00IM 0761-185 I-76, LOCHBUIE TO HUDSON 06/24/04 1,268.00 3.00 5.78 5.45 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,012,275.00 1.38 1.45 1.76

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 360.00 6.00 14.83 10.00SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 284.00 12.00 18.00 18.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 2,268.00 5.00 4.63 4.07BR 0243-063 EAST OF LIMON 07/15/04 11,997.00 3.20 2.13 1.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 2,279.00 3.00 3.49 6.00SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 13,710.00 2.50 2.40 1.80NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 2,465.00 6.00 4.44 4.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 7,873.00 1.50 3.59 2.25C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 530.00 1.50 11.16 7.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 6,911.00 3.00 2.78 1.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 48,677.00 2.97 3.35 2.27

Page 69: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 25 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00240 Rem Asphalt Mat (Planing) Sq Yard ================================================

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 138.00 30.00 24.80 7.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 15,860.00 2.00 1.47 1.25BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 17,853.00 2.00 1.47 1.00IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 266,295.00 1.00 1.08 0.85MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 5,901.00 4.00 6.62 4.85STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 57,073.00 1.30 1.80 2.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 61,635.00 1.00 1.15 0.90STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 130,636.00 1.00 1.10 1.10NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 188,970.00 0.50 0.80 0.44STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 97,650.00 1.00 1.18 0.70STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 78,406.00 0.75 1.40 1.05NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 1,600.00 6.00 8.25 10.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 81,086.00 1.00 2.12 3.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 7,670.00 3.00 4.42 5.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 71,038.00 1.25 1.65 1.80STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 96,426.00 1.25 1.42 0.96NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 42,793.00 1.25 1.31 0.90STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 73,608.00 1.00 1.30 0.85NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 34,186.00 1.00 1.94 1.80 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,328,824.00 1.03 1.27 1.14 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4,858,548.00 1.20 1.23 1.23

=============== 202-00246 Rem Asphalt Mat (Planing)(Special) Sq Yard ================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 446.00 6.00 8.86 7.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 446.00 6.00 8.86 7.00

SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 412.00 5.00 7.93 8.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 2,364.00 5.00 5.70 3.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2,776.00 5.00 6.10 3.74

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 462.00 2.00 13.76 8.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 462.00 2.00 13.76 8.00

Page 70: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 26 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00246 Rem Asphalt Mat (Planing)(Special) Sq Yard ================================================

MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 3,843.00 6.00 8.17 7.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3,843.00 6.00 8.17 7.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 7,527.00 5.39 7.90 6.12

=============== 202-00250 Rem Pavement Marking Sq Foot ================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 3,518.00 1.50 1.05 1.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 12,917.00 1.50 1.19 0.95MC R300-118 R-3 PAVEMENT MARKINGS 02/12/04 132,900.00 0.25 0.37 0.30IM 0701-164 PARACHUTE EAST & WEST 02/12/04 1,000.00 2.00 1.64 2.20IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 13,220.00 0.85 0.84 0.80STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 40,000.00 1.00 0.68 0.67STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 2,500.00 1.50 1.20 0.75STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 2,583.00 2.00 2.11 2.25STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 4,500.00 0.80 1.36 1.80STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 32,241.00 0.95 0.95 1.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 245,379.00 0.63 0.69 0.58

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 500.00 2.00 1.27 0.80MC R300-119 R-3 STENCIL REGIONWIDE 04/01/04 37,300.00 1.50 0.50 0.50NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 1,650.00 1.75 2.32 2.10STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 1,030.00 3.00 2.50 2.10NH 2852-010 US 285 & COUNTY RD. G 04/29/04 550.00 1.60 3.15 1.60NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 10,357.00 2.00 0.98 1.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 20,000.00 1.50 0.90 0.85NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 600.00 2.00 1.63 1.30SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 2,347.00 1.50 1.51 1.35BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 4,000.00 1.00 1.29 1.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 78,334.00 1.57 0.91 0.81

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 1,000.00 1.40 1.14 1.20IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 35,000.00 1.25 0.88 0.85

Page 71: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 27 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00250 Rem Pavement Marking Sq Foot ================================================SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 150.00 2.50 2.80 2.60BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 1,000.00 3.00 1.77 1.51IMD 0252-364 I-25 OVER BROADWAY 07/29/04 2,000.00 1.00 2.09 2.02NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 40,598.00 1.30 0.86 0.79STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 100.00 2.00 3.38 3.75C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 4,890.00 1.25 1.24 1.25NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 10,000.00 1.00 1.78 1.75IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 1,357.00 1.70 1.53 2.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 96,095.00 1.27 1.03 1.00

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 6,023.00 0.80 1.77 1.60IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 3,000.00 1.50 1.77 2.10BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 900.00 2.00 1.29 1.25MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 2,000.00 2.00 1.80 2.15NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 99.00 3.00 2.98 2.13 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 12,022.00 1.28 1.75 1.79 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 431,830.00 0.96 0.85 0.75

=============== 202-00400 Rem Bridge Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 50000.00 48100.00 38000.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 1.00 20000.00 11075.00 11000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 35000.00 35758.33 24500.00

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 1.00 35000.00 49499.17 59194.18NH 2852-010 US 285 & COUNTY RD. G 04/29/04 1.00 5000.00 15384.20 10000.00BR 0092-018 SH 9, SOUTH OF KREMMLING 05/27/04 1.00 240000.00 280567.75 258922.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 2.00 15000.00 10890.33 8500.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 2.00 30000.00 28357.14 23500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 7.00 52857.14 55778.56 56016.60

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 1500000.00 1708043.53 1700000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 1500000.00 1708043.53 1700000.00

Page 72: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 28 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00400 Rem Bridge Each ===================================================

BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 1.00 20000.00 21674.38 15500.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1.00 180000.00 96129.00 100000.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 300000.00 340500.00 300000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3.00 166666.67 117342.72 138500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 13.00 187692.31 162592.45 196662.78

=============== 202-00410 Rem Mat From Br Sq Yard ================================================

STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 1,023.00 5.00 5.50 4.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,023.00 5.00 5.50 4.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,023.00 5.00 5.50 4.00

=============== 202-00425 Rem Bridge Railing Lin Foot ===============================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 534.00 6.00 10.74 11.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 106.00 15.00 15.44 21.00STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 389.00 10.00 11.01 6.25STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 1,270.00 7.00 8.59 8.60STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 40.00 40.00 69.28 26.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 187.00 7.00 12.33 12.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 326.00 10.00 16.63 22.50NH 2872-016 US 287 - LAMAR 03/04/04 95.00 15.00 27.75 38.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 2,856.00 8.00 3.65 3.30SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 154.00 10.00 23.00 20.50NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 512.00 9.00 8.50 7.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 6,469.00 8.37 8.05 8.01

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 250.00 10.00 6.14 4.95NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 274.00 7.00 14.13 14.50STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 575.00 10.00 6.44 6.60NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 94.00 7.00 13.30 12.60STA 0343-023 US 34, EAST OF AKRON 06/17/04 113.00 10.00 19.17 18.00

Page 73: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 29 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00425 Rem Bridge Railing Lin Foot ===============================================STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 60.00 11.00 32.67 32.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,366.00 9.24 9.99 10.35

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 174.00 9.00 42.82 12.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 174.00 9.00 42.82 12.00

IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 610.00 8.00 8.13 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 610.00 8.00 8.13 10.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8,619.00 8.50 8.98 8.61

=============== 202-00450 Rem Port Present Str (1) Sq Yard ================================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 4.00 500.00 220.08 365.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 500.00 220.08 365.00

SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 330.00 60.00 59.63 29.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 330.00 60.00 59.63 29.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 334.00 65.27 61.17 33.02

=============== 202-00453 Rem Port Present Str (2) Sq Yard ================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 10.00 150.00 198.69 490.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 10.00 150.00 198.69 490.00

IM 0253-186 I-25, 120TH TO SH 7 06/17/04 49.00 100.00 296.65 130.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 49.00 100.00 296.65 130.00

Page 74: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 30 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00453 Rem Port Present Str (2) Sq Yard ================================================

MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 1,536.00 150.00 183.33 146.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,536.00 150.00 183.33 146.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,595.00 148.46 188.18 147.67

=============== 202-00454 Rem Port Present Str (2A) Sq Yard ================================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 15.00 250.00 113.00 65.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 15.00 250.00 113.00 65.00

SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 100.00 90.00 96.21 72.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 100.00 90.00 96.21 72.00

BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 22.00 250.00 277.70 158.06 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 22.00 250.00 277.70 158.06

NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 33.00 100.00 245.83 340.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 33.00 100.00 245.83 340.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 170.00 126.76 147.92 134.54

=============== 202-00456 Rem Port Present Str (2B) Sq Yard ================================================

SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 100.00 100.00 120.46 126.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 100.00 100.00 120.46 126.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 100.00 100.00 120.46 126.00

Page 75: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 31 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00460 Rem Port Present Str (3) Sq Yard ================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 3.00 400.00 521.78 1200.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 3.00 600.00 516.99 415.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 6.00 500.00 520.41 807.50

IM 0253-186 I-25, 120TH TO SH 7 06/17/04 1.00 750.00 682.47 570.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 750.00 682.47 570.00

MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 76.00 300.00 556.67 375.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 76.00 300.00 556.67 375.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 83.00 319.88 552.95 408.61

=============== 202-00462 Rem Port Present Str (3A) Sq Yard ================================================

SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 20.00 200.00 290.84 380.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 20.00 200.00 290.84 380.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 20.00 200.00 290.84 380.00

=============== 202-00495 Rem Port Present Str LUMP SUM ===============================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 1.00 10000.00 4221.17 1900.00STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 1.00 7292.74 6350.00 5500.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 1.00 10000.00 8331.50 2000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3.00 9097.58 6206.05 3133.33

NH 0502-053 CIMARRON - WEST 04/15/04 1.00 10000.00 3823.55 2000.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 1.00 10000.00 4706.00 5000.00

Page 76: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 32 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00495 Rem Port Present Str LUMP SUM ===============================================NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 1.00 12000.00 15658.44 6315.20CC R600-225 CHATFIELD STATE PARK 06/10/04 1.00 3000.00 3400.00 2700.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 1.00 40000.00 39437.50 7750.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 5.00 15000.00 12990.85 4753.04

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 25000.00 26780.48 26000.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1.00 6000.00 11048.20 7000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 18666.67 20729.60 19666.67

IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 1.00 480.00 1648.57 1000.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 1.00 2000.00 1032.48 1929.90STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 1.00 2000.00 4479.26 4000.00STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 1.00 2000.00 7484.63 6154.15 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4.00 1620.00 3371.93 3271.01 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 14.00 10984.85 9491.26 7016.62

=============== 202-00500 Rem Port Present Str Each ===================================================

SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 4.00 1000.00 1290.30 1180.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 2.00 1200.00 1376.23 1000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 6.00 1066.67 1318.95 1120.00

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 1.00 3500.00 5181.25 5000.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 4.00 3000.00 88137.84 82013.51BR 0243-063 EAST OF LIMON 07/15/04 1.00 38000.00 33357.17 35000.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 3.00 2710.00 2461.38 4000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 9.00 6847.78 42878.68 42228.23 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 15.00 4535.33 21382.26 25784.94

=============== 202-00503 Rem Port Present Str Sq Yard ================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 200.00 250.00 229.19 155.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 200.00 250.00 229.19 155.00

Page 77: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 33 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00503 Rem Port Present Str Sq Yard ================================================

IM 0253-186 I-25, 120TH TO SH 7 06/17/04 16.00 160.00 385.81 230.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 16.00 160.00 385.81 230.00

NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 45.00 150.00 800.94 1329.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 45.00 150.00 800.94 1329.70 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 261.00 227.24 302.60 362.13

=============== 202-00504 Rem Exp Device Lin Foot ===============================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 499.30 60.00 22.92 5.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 207.00 100.00 125.65 150.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 706.30 71.72 72.50 47.50

NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 241.00 90.00 39.65 57.90 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 241.00 90.00 39.65 57.90

SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 174.00 40.00 228.88 57.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 174.00 40.00 228.88 57.75

IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 138.00 180.00 49.67 30.00STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 60.00 150.00 61.96 68.80 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 198.00 170.91 54.83 41.76 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,319.30 85.76 74.22 49.89

Page 78: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 34 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00520 Rem of Exp Joint Matl Lin Foot ===============================================

STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 265.00 20.00 34.27 22.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 265.00 20.00 34.27 22.00

IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 360.00 25.00 8.00 5.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 360.00 25.00 8.00 5.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 625.00 22.88 24.60 12.21

=============== 202-00610 Rem of RR Track Lin Foot ===============================================

SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 50.00 20.00 66.38 21.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 50.00 20.00 66.38 21.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 50.00 20.00 66.38 21.00

=============== 202-00700 Rem Light Standard Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 18.00 300.00 147.14 100.00NH 2872-016 US 287 - LAMAR 03/04/04 91.00 200.00 75.75 70.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 2.00 700.00 195.00 180.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 111.00 225.23 96.76 76.85

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 3.00 250.00 498.16 190.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3.00 250.00 498.16 190.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 65.00 80.00 108.32 110.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 7.00 250.00 484.27 476.15 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 72.00 96.53 139.28 145.60 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 186.00 175.81 123.25 105.29

Page 79: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 35 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00750 Rem Luminaire Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 20.00 100.00 40.13 30.00NH 2872-016 US 287 - LAMAR 03/04/04 12.00 100.00 56.25 50.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 32.00 100.00 43.85 37.50

C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 159.00 150.00 70.93 30.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 159.00 150.00 70.93 30.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 191.00 141.62 65.31 31.26

=============== 202-00805 Rem Overhead Sign Str Each ===================================================

C R200-126 FY04 REGION 2 SIGNING 04/01/04 2.00 3000.00 4487.05 1578.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 3000.00 4487.05 1578.00

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 3000.00 3550.00 2000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 3000.00 3550.00 2000.00

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 3300.00 2124.97 2100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 3300.00 2124.97 2100.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 3075.00 3544.44 1814.00

=============== 202-00806 Rem Walkway Lin Foot ===============================================

C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 2,082.00 10.00 15.70 9.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2,082.00 10.00 15.70 9.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,082.00 10.00 15.70 9.00

Page 80: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 36 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00810 Rem Ground Sign Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 2.00 75.00 57.89 60.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 47.00 50.00 27.48 20.40C 0342-040 US 34 IN WELD COUNTY 01/29/04 10.00 20.00 41.95 97.64STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 29.00 50.00 19.47 16.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 95.00 40.00 31.06 17.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 4.00 80.00 32.81 30.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 54.00 50.00 78.89 22.32STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 38.00 50.00 15.70 12.00STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 14.00 30.00 43.50 50.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 12.00 45.00 57.54 36.00C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 1.00 50.00 71.50 92.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 20.00 50.00 51.78 25.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 17.00 100.00 31.74 30.70IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 44.00 90.00 38.51 22.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 2.00 50.00 60.40 60.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 3.00 70.00 44.50 77.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 6.00 28.00 153.17 50.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 18.00 30.00 31.09 41.02NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 22.00 19.00 33.34 31.00C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 1.00 50.00 167.00 167.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 16.00 55.00 31.25 12.50STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 31.00 50.00 25.26 18.20STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 46.00 32.00 25.00 38.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 532.00 48.74 37.91 26.09

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 1.00 50.00 49.14 66.00NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 6.00 25.00 26.00 46.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 10.00 50.00 44.38 40.91NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 5.00 50.00 54.97 42.00SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 5.00 60.00 24.71 44.00NH 0502-053 CIMARRON - WEST 04/15/04 26.00 20.00 61.46 60.00STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 1.00 30.00 76.00 88.00STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 9.00 60.00 111.92 40.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 6.00 40.00 39.87 26.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 2.00 45.00 83.32 136.60STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 15.00 50.00 18.67 18.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 104.00 45.00 55.00 40.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 35.00 70.00 35.99 5.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 1.00 50.00 20.55 10.50CC R600-225 CHATFIELD STATE PARK 06/10/04 8.00 50.00 26.00 19.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 10.00 50.00 48.42 31.00STA 0343-023 US 34, EAST OF AKRON 06/17/04 1.00 40.00 33.80 55.00

Page 81: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 37 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00810 Rem Ground Sign Each ===================================================SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 11.00 50.00 68.88 13.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 256.00 47.23 51.09 34.74

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 23.00 35.00 38.86 60.00STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 36.00 40.00 32.31 26.00IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 389.00 20.00 23.62 26.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 1.00 150.00 67.51 100.65BR 0243-063 EAST OF LIMON 07/15/04 2.00 80.00 51.08 60.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 11.00 125.00 202.41 500.00STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 1.00 100.00 49.80 94.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 31.00 50.00 22.76 20.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 49.00 50.00 24.38 48.15C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 8.00 20.00 46.42 50.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 18.00 30.00 39.50 26.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 26.00 50.00 44.40 20.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 595.00 29.93 28.64 38.00

SHE 105A-010 SH 105/FURROW RD 10/07/04 3.00 100.00 89.26 50.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 52.00 60.00 31.46 21.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 16.00 75.00 48.91 45.00C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 12.00 100.00 1416.24 465.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 15.00 60.00 27.90 16.10NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 5.00 50.00 63.53 103.78STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 21.00 40.00 38.19 48.35STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 2.00 65.00 27.15 20.70STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 11.00 40.00 58.64 21.01NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 22.00 50.00 42.98 20.40STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 17.00 60.00 29.56 59.10NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 13.00 28.50 87.84 150.00NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 6.00 55.00 56.72 44.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 195.00 57.44 124.09 67.99 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,578.00 42.48 46.09 37.16

=============== 202-00815 Rem of Sign (Special) Each ===================================================

STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 12.00 350.00 351.52 75.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 12.00 350.00 351.52 75.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 12.00 350.00 351.52 75.00

Page 82: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 38 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00821 Rem Sign Panel Each ===================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 3.00 60.00 37.35 9.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 19.00 20.00 11.71 9.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 26.00 20.00 43.01 22.00STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 28.00 35.00 12.40 8.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 13.00 65.00 47.58 25.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 200.00 101.00 100.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 5.00 85.00 29.40 44.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 2.00 90.00 30.63 30.77 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 97.00 38.25 30.46 17.53

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 14.00 100.00 25.40 31.75NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 22.00 20.00 19.70 18.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 2.00 95.00 8.26 5.30IM 0253-186 I-25, 120TH TO SH 7 06/17/04 4.00 75.00 58.92 77.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 42.00 55.48 24.35 27.60

SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 1.00 100.00 68.50 70.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 2.00 50.00 19.40 49.22NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 10.00 476.00 32.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4.00 52.50 139.69 50.11

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 6.00 60.00 83.91 175.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 24.00 75.00 16.17 8.05STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 4.00 50.00 53.44 96.75STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 12.00 100.00 16.67 9.80STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 4.00 80.00 24.99 11.06NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 1.00 75.00 60.54 9.65STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 6.00 75.00 19.37 59.10NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 5.00 25.00 91.63 83.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 62.00 73.06 30.72 41.47 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 205.00 52.59 30.87 27.47

=============== 202-00825 Rem Flashing Beacon Each ===================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 2.00 200.00 160.21 200.00

Page 83: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 39 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00825 Rem Flashing Beacon Each ===================================================STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 2.00 250.00 207.50 195.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 225.00 168.09 197.50

STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 1.00 200.00 336.25 250.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 1.00 200.00 214.70 210.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 200.00 285.60 230.00

NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 8.00 200.00 105.63 149.15 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 8.00 200.00 105.63 149.15 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 14.00 207.14 153.77 174.51

=============== 202-00828 Rem Traf Sig Equipment LUMP SUM ===============================================

STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 1.00 10000.00 11470.47 8427.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 10000.00 11470.47 8427.00

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 1.00 4000.00 2815.30 2705.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 1.00 15000.00 10174.97 6346.44NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 6000.00 2162.80 2700.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3.00 8333.33 4328.97 3917.15

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 1.00 12000.00 5214.73 3172.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 10000.00 4036.34 3493.55NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 3000.00 2825.00 3200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 3.00 8333.33 3927.16 3288.52

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1.00 2500.00 6275.93 6400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 2500.00 6275.93 6400.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8.00 7812.50 5545.18 4555.50

Page 84: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 40 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00830 Rem Traf Sig Face Each ===================================================

NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 16.00 60.00 71.17 68.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 16.00 60.00 71.17 68.40 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 16.00 60.00 71.17 68.40

=============== 202-00831 Rem Traf Sig Head Each ===================================================

STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 2.00 90.00 173.09 102.56 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 90.00 173.09 102.56

STA R400-168 R4 DILEMMA ZONE SAFETY PROJEC 06/17/04 5.00 110.00 164.82 145.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 5.00 110.00 164.82 145.00

STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 8.00 115.00 56.50 55.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 8.00 115.00 56.50 55.75 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 15.00 110.00 116.25 91.74

=============== 202-00840 Rem Traf Sig Pole Each ===================================================

C 074A-007 SH 74 @ BRYANT DR. 02/26/04 6.00 450.00 841.48 350.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1.00 700.00 1069.97 675.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 7.00 485.71 874.13 396.43

SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 4.00 700.00 532.25 510.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 1.00 1000.00 1361.25 635.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 5.00 760.00 670.42 535.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 12.00 600.00 807.15 454.17

Page 85: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 41 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00842 Rem Mast Arm Each ===================================================

SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 4.00 350.00 532.25 510.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4.00 350.00 532.25 510.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 350.00 532.25 510.00

=============== 202-00855 Rem Traf Sig Control Cab Each ===================================================

C 074A-007 SH 74 @ BRYANT DR. 02/26/04 1.00 400.00 392.52 400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 400.00 392.52 400.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 400.00 392.52 400.00

=============== 202-00895 Rem of Impact Attenuator Each ===================================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 2.00 600.00 819.78 525.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 4.00 500.00 317.17 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 6.00 533.33 532.57 508.33 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6.00 533.33 532.57 508.33

=============== 202-00900 Rem Conc Footing Each ===================================================

NH 2872-016 US 287 - LAMAR 03/04/04 91.00 500.00 96.25 90.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 91.00 500.00 96.25 90.00

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 9.00 500.00 991.04 430.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 9.00 500.00 991.04 430.00

STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 2.00 400.00 566.67 400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 400.00 566.67 400.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 102.00 498.04 216.87 126.08

Page 86: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 42 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-00950 Rem Conc Found/Slab Sq Yard ================================================

C R200-126 FY04 REGION 2 SIGNING 04/01/04 4.00 300.00 522.00 381.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4.00 300.00 522.00 381.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 300.00 522.00 381.00

=============== 202-01000 Rem Fence Lin Foot ===============================================

STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 59,136.00 0.35 0.28 0.20STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 34.00 1.00 8.73 10.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 5,330.00 1.50 0.40 0.35STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1,873.00 1.00 1.15 0.80STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 15,132.00 0.50 0.50 0.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 81,505.00 0.47 0.35 0.28

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 3,992.00 2.00 4.33 4.58NH 0502-053 CIMARRON - WEST 04/15/04 31,716.00 0.35 0.58 0.50NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 24,038.00 0.25 0.54 0.30IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 4,620.00 1.20 0.57 0.55SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 863.00 1.00 1.71 1.70NH 2852-010 US 285 & COUNTY RD. G 04/29/04 7,666.00 0.70 1.07 0.80STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 200.00 3.00 4.59 7.07NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 7,872.00 0.60 0.84 0.35SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 67.00 2.00 8.28 4.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 81,034.00 0.52 1.02 0.69

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 26,099.00 0.40 0.38 0.40STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 30,284.00 0.40 0.30 0.20IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 172,150.00 0.25 0.27 0.26SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 1,400.00 1.80 1.33 0.65IMD 0252-364 I-25 OVER BROADWAY 07/29/04 4,035.00 2.00 2.23 2.15SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 76.00 4.00 18.00 25.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 46,276.00 0.35 0.31 0.22STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 135.00 2.50 4.10 4.49C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1,715.00 1.00 0.81 0.95NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 15,858.00 0.50 1.15 1.10

Page 87: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 43 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-01000 Rem Fence Lin Foot ===============================================IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 3,005.00 1.00 0.97 2.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 301,033.00 0.35 0.36 0.36

SHE 105A-010 SH 105/FURROW RD 10/07/04 2,475.00 1.20 0.90 1.00BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 1,684.00 4.00 1.16 1.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1,686.00 3.00 4.40 4.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 5,845.00 2.53 1.98 2.01 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 469,417.00 0.43 0.49 0.42

=============== 202-01030 Rem of Road Closure Gate Each ===================================================

STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 2.00 250.00 316.00 500.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 2.00 300.00 452.50 355.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 275.00 355.00 427.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 275.00 355.00 427.50

=============== 202-01130 Rem Gdrail Ty 3 Lin Foot ===============================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 300.00 3.00 3.23 3.50STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 98.00 4.00 7.98 5.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 1,152.00 3.00 2.50 2.50NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 1,797.00 2.50 3.15 3.07STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 2,705.00 3.00 2.03 1.90STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 212.50 4.00 4.03 3.80IM 0701-164 PARACHUTE EAST & WEST 02/12/04 50.00 3.00 5.38 3.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 13,231.00 2.50 2.13 1.50STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 833.50 3.00 2.71 2.56STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 1,138.00 2.50 3.38 2.15IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1,605.00 3.50 1.78 1.70STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 1,941.00 3.00 2.63 2.75IM 0701-157 FRUITA TO CLIFTON 02/26/04 575.00 4.00 2.92 3.00STA 014A-030 SH 14, WALDEN EAST 03/04/04 100.00 3.00 5.40 4.81STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 1,870.00 2.50 3.35 3.00NH 2872-016 US 287 - LAMAR 03/04/04 600.00 3.00 3.58 4.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 4,834.00 3.00 2.26 2.15SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 350.00 3.00 2.73 2.25

Page 88: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 44 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-01130 Rem Gdrail Ty 3 Lin Foot ===============================================STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 600.00 2.75 2.64 3.05NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 5,558.00 2.00 3.00 3.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 25.00 4.00 18.00 7.00STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 13,003.00 2.50 3.70 3.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 52,578.00 2.63 2.86 2.43

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 2,028.00 2.00 2.39 2.15NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 1,679.00 4.00 5.34 6.00NH 0502-053 CIMARRON - WEST 04/15/04 6,325.00 2.00 2.37 2.20NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 1,700.00 3.00 2.73 2.40STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 440.00 4.00 2.12 2.20IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 536.00 4.00 61.86 4.20STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 94.00 4.00 10.95 10.51IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 525.00 3.00 2.88 2.65SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 725.00 3.00 2.71 2.60STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 710.00 4.00 5.76 7.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 600.00 4.00 2.64 2.40NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 1,078.00 4.00 3.45 3.10CC R600-225 CHATFIELD STATE PARK 06/10/04 1,886.00 3.00 2.44 3.50IM 0253-186 I-25, 120TH TO SH 7 06/17/04 88.00 4.00 2.24 2.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 810.00 3.00 7.50 7.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 19,224.00 2.84 5.71 3.23

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 845.00 3.00 2.91 2.75IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 5,708.00 3.00 2.85 2.40BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 881.00 4.00 6.24 5.33BR 0243-063 EAST OF LIMON 07/15/04 400.00 2.50 5.18 7.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 150.00 4.00 4.11 3.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 710.00 4.00 3.46 2.51NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 3,688.00 2.50 4.50 2.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 12,382.00 2.98 3.50 2.68

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 2,419.00 3.00 2.68 2.25BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1,540.00 3.00 2.22 2.15C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 550.00 3.00 4.72 4.20IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 1,714.00 2.40 3.40 3.20

Page 89: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 45 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-01130 Rem Gdrail Ty 3 Lin Foot ===============================================STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 225.00 4.00 6.57 12.00NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 928.00 2.00 3.80 4.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 160.00 3.00 3.87 5.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 11,015.00 3.00 3.26 3.20NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 234.00 3.00 6.00 7.00STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 1,512.00 3.00 2.97 2.35 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 20,297.00 2.91 3.22 3.16 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 104,481.00 2.76 3.50 2.75

=============== 202-01140 Rem Gdrail Ty 4 Lin Foot ===============================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 60.00 20.00 43.83 70.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 722.00 5.00 7.33 5.15STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 32.00 10.00 6.67 10.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 225.00 12.00 5.09 5.17C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 140.00 15.00 64.00 64.00STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 225.00 10.00 6.56 9.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,404.00 8.68 8.78 14.52

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 275.00 7.00 17.68 20.00STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 150.00 15.00 13.55 13.49 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 425.00 9.82 17.05 17.70

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 915.00 10.00 7.75 10.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 78.00 8.00 25.93 6.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 993.00 9.84 9.17 9.74

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 706.00 16.00 7.92 1.60IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 3,576.00 7.50 8.51 9.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 313.00 10.00 8.88 5.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 30.00 15.00 8.60 21.45STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 476.00 10.00 9.36 10.00

Page 90: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 46 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-01140 Rem Gdrail Ty 4 Lin Foot ===============================================NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 120.00 14.00 9.35 4.80IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 12,040.00 9.00 9.25 6.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 17,261.00 9.07 8.93 6.55 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 20,083.00 9.09 9.13 7.50

=============== 202-01150 Rem Gdrail Ty 5 Lin Foot ===============================================

STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1,540.00 3.00 3.53 2.45 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,540.00 3.00 3.53 2.45 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,540.00 3.00 3.53 2.45

=============== 202-01170 Rem Gdrail Ty 7 Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 207.00 8.00 20.44 5.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 20.00 15.00 17.46 10.41 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 227.00 8.62 20.24 5.48 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 227.00 8.62 20.24 5.48

=============== 202-01300 Rem End Anchorage Each ===================================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 4.00 120.00 159.71 140.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 90.00 100.00 127.51 115.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 6.00 100.00 180.10 150.63STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 4.00 160.00 165.19 156.00IM 0701-164 PARACHUTE EAST & WEST 02/12/04 56.00 150.00 225.00 150.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 22.00 150.00 188.33 100.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 1.00 250.00 90.75 86.99STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 9.00 150.00 168.75 137.50IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 12.00 200.00 161.67 153.35STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 20.00 130.00 135.00 145.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 69.00 100.00 139.75 125.00STA 014A-030 SH 14, WALDEN EAST 03/04/04 2.00 150.00 237.17 200.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 12.00 130.00 156.25 130.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 4.00 150.00 142.88 110.00SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 2.00 150.00 191.67 155.00STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 4.00 250.00 155.00 165.00

Page 91: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 47 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-01300 Rem End Anchorage Each ===================================================NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 57.00 80.00 185.00 150.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 8.00 140.00 188.81 150.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 382.00 118.74 161.78 133.11

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 43.00 110.00 110.63 104.25NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 24.00 140.00 97.85 90.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 18.00 115.00 122.50 120.00STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 2.00 130.00 432.04 437.75IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 6.00 140.00 250.00 210.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 8.00 275.00 381.25 425.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 4.00 150.00 129.13 110.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 11.00 110.00 173.19 161.30IM 0253-186 I-25, 120TH TO SH 7 06/17/04 4.00 125.00 126.14 110.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 120.00 131.42 141.45 141.60

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 2.00 170.00 226.56 250.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 3.00 150.00 158.84 125.81BR 0243-063 EAST OF LIMON 07/15/04 8.00 165.00 165.73 201.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 200.00 184.81 160.50NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 9.00 150.00 206.25 185.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 23.00 159.13 189.86 187.43

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 14.00 140.00 143.99 150.00C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 4.00 128.00 260.81 230.00IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 14.00 130.00 177.86 168.00NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 36.00 180.00 184.67 4.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 2.00 200.00 778.00 130.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 24.00 200.00 188.33 220.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 4.00 150.00 403.33 420.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 98.00 169.10 193.46 129.96 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 623.00 130.60 163.57 136.26

=============== 202-04001 Plug Culvert Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 14.00 500.00 619.24 245.47 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 14.00 500.00 619.24 245.47

Page 92: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 48 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-04001 Plug Culvert Each ===================================================

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 1.00 500.00 1544.76 377.86NH 0502-053 CIMARRON - WEST 04/15/04 2.00 1500.00 507.39 800.00IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 1.00 500.00 628.95 424.65STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 2.00 500.00 355.06 250.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 2.00 300.00 1004.25 700.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 1.00 450.00 516.24 550.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 1.00 250.00 647.86 150.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 10.00 630.00 741.57 500.25

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 1.00 500.00 782.75 856.00IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 21.00 600.00 565.20 530.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 4.00 800.00 849.62 500.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 800.00 2165.08 300.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 4.00 500.00 307.50 220.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 31.00 616.13 615.26 489.23

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 3.00 600.00 2205.27 1700.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3.00 600.00 2205.27 1700.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 58.00 589.66 727.67 494.91

=============== 202-04002 Clean Culvert Each ===================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 9.00 900.00 587.83 360.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 6.00 1000.00 403.68 310.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 43.00 800.00 224.83 20.80IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 1.00 1000.00 5939.64 4200.00STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 9.00 800.00 996.00 1000.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 5.00 800.00 514.34 410.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 30.00 1000.00 210.52 305.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 40.00 1100.00 390.42 350.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 17.00 750.00 712.50 350.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 1.00 1000.00 580.62 614.94

Page 93: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 49 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-04002 Clean Culvert Each ===================================================STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 11.00 500.00 1700.00 1100.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 11.00 750.00 710.00 390.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 25.00 850.00 610.10 460.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1.00 1000.00 914.28 600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 209.00 882.54 457.69 380.14

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 9.00 500.00 535.05 614.48NH 0502-053 CIMARRON - WEST 04/15/04 8.00 1500.00 1050.00 800.00IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 7.00 700.00 1103.33 1760.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 5.00 800.00 1411.18 460.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 1.00 1000.00 920.00 400.00STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 4.00 1000.00 783.33 500.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 10.00 700.00 1735.16 860.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 10.00 750.00 887.88 357.40CC R600-225 CHATFIELD STATE PARK 06/10/04 1.00 750.00 1457.50 1400.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 1.00 950.00 1068.96 1600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 56.00 832.14 1053.24 787.93

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 16.00 1000.00 1650.00 200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 16.00 1000.00 1650.00 200.00

C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 1.00 2000.00 3250.00 4500.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 1.00 800.00 5230.00 150.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 5.00 1000.00 846.44 1000.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 4.00 750.00 1230.38 531.88IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 12.00 800.00 4820.00 800.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 3.00 750.00 917.26 429.05 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 26.00 871.15 2723.30 871.72 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 307.00 878.50 705.90 486.77

=============== 202-04003 Clean Culvert (Spec) Each ===================================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 1.00 30000.00 5275.38 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 30000.00 5275.38 500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 30000.00 5275.38 500.00

Page 94: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 50 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-04005 Clean Valve Box Each ===================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 51.00 100.00 94.66 115.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 5.00 150.00 148.57 185.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 28.00 75.00 113.16 100.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 27.00 100.00 115.39 155.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 5.00 100.00 112.39 90.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 40.00 110.00 88.18 100.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 27.00 150.00 108.75 160.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 8.00 110.00 97.82 102.54STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 2.00 200.00 135.74 271.41 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 193.00 108.19 101.49 123.88

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 4.00 100.00 147.34 101.04SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 7.00 110.00 145.00 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 11.00 106.36 146.32 100.38

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 6.00 110.00 134.29 80.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 4.00 120.00 127.87 115.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 33.00 150.00 85.91 149.95STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 25.00 220.00 90.65 100.00STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 6.00 130.00 122.94 150.35STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 2.00 200.00 103.12 187.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 27.00 140.00 82.53 154.65NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 1.00 200.00 195.23 160.90STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 17.00 130.00 87.53 134.35NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 26.00 150.00 147.42 110.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 147.00 155.51 102.68 130.24 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 351.00 127.95 103.08 125.80

=============== 202-04100 Abandon Well Each ===================================================

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 1500.00 1352.76 930.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 1500.00 1352.76 930.00

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 4.00 750.00 1232.17 250.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4.00 750.00 1232.17 250.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5.00 900.00 1265.06 386.00

Page 95: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 51 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-05008 Sawing Concrete (8 In) Lin Foot ===============================================

STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 935.00 3.00 4.46 5.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 935.00 3.00 4.46 5.00

NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 268.00 5.00 4.25 2.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 268.00 5.00 4.25 2.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,203.00 3.45 4.39 4.33

=============== 202-05026 Sawing Asphalt Mat (6 In) Lin Foot ===============================================

C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 820.00 2.50 2.23 0.95STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 1,256.00 2.00 1.50 1.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1,782.00 2.50 1.75 2.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3,858.00 2.34 1.80 1.45 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3,858.00 2.34 1.80 1.45

=============== 202-05100 Sandblasting Reinf Steel Sq Yard ================================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 8.00 20.00 36.93 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 8.00 20.00 36.93 60.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8.00 20.00 36.93 60.00

=============== 202-05150 Sandblasting Sq Foot ================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 7,848.00 0.60 0.58 0.55STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 28,000.00 0.45 0.42 0.41 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 35,848.00 0.48 0.47 0.44

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 35,000.00 0.50 0.52 0.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 35,000.00 0.50 0.52 0.50

Page 96: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 52 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 202-05150 Sandblasting Sq Foot ================================================

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 20,401.00 0.50 0.51 0.40BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 2,251.00 2.00 5.99 9.99 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 22,652.00 0.65 0.79 1.35

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 447.00 1.00 1.81 4.25BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1,080.00 1.00 2.05 2.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 3,708.00 1.00 0.86 0.80 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 5,235.00 1.00 1.12 1.34 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 98,735.00 0.55 0.59 0.72

=============== 202-06000 Rem Detour LUMP SUM ===============================================

NH 2852-010 US 285 & COUNTY RD. G 04/29/04 1.00 30000.00 22760.14 5000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 30000.00 22760.14 5000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 30000.00 22760.14 5000.00

=============== 202-06530 Clean Drain Pipe (Spec) Each ===================================================

BR 0362-028 BRIDGE OVER KIOWA CREEK 05/13/04 6.00 50.00 800.00 800.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 6.00 50.00 800.00 800.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6.00 50.00 800.00 800.00

=============== 202-07000 Oblit Old Road LUMP SUM ===============================================

STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 1.00 3000.00 5874.20 2000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 3000.00 5874.20 2000.00

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 1.00 10000.00 6623.96 1000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 10000.00 6623.96 1000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 6500.00 6195.53 1500.00

Page 97: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 53 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 203-00000 Uncl Excav Cubic Yard =============================================

STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 16,234.00 6.00 5.35 10.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 2,000.00 10.00 7.85 9.13 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 18,234.00 6.44 5.67 9.90

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 1,855.00 6.00 16.82 12.25IM 0253-186 I-25, 120TH TO SH 7 06/17/04 60.00 25.00 30.62 17.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,915.00 6.60 17.39 12.40

NH 2873-137 US 287 IN BOULDER & LARIMER C 11/18/04 1,667.00 13.00 17.80 30.40IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 300.00 50.00 97.67 25.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,967.00 18.64 22.32 29.58 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 22,116.00 7.54 8.57 11.87

=============== 203-00010 Uncl Excav (CIP) Cubic Yard =============================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 646.00 13.00 29.74 1.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 96,956.00 21.00 15.64 14.50STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 4,905.00 7.00 11.09 5.00C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 437.00 15.00 17.60 22.25STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 1,000.00 12.00 13.88 5.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 478.00 10.00 14.56 12.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 187.00 20.00 30.41 30.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 774,638.00 2.30 3.16 3.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 879,247.00 4.42 6.76 4.30

NH 0502-053 CIMARRON - WEST 04/15/04 129,201.00 5.50 5.13 5.15ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 5,094.00 150.00 75.35 130.95STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 28,010.00 6.00 8.73 5.25NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 3,172.00 6.00 10.19 8.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 318,843.00 3.00 2.87 2.95

Page 98: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 54 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 203-00010 Uncl Excav (CIP) Cubic Yard =============================================SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 1,532.00 11.00 14.13 7.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 485,852.00 5.42 4.06 5.06

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 101,518.00 5.50 5.17 4.50STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 16,879.00 18.00 15.04 14.50STA 149A-021 SH 149 CRIBWALL 09/16/04 3.00 8.00 207.00 207.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 103,491.00 4.00 7.99 5.15IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 13,074.00 5.00 8.57 4.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 234,965.00 5.71 6.90 5.51

SHE 105A-010 SH 105/FURROW RD 10/07/04 12,090.00 8.00 8.56 7.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 13,817.00 15.00 19.06 11.30STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 99.00 20.00 50.72 61.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 26,006.00 11.76 14.30 9.49 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,626,070.00 5.02 5.82 4.78

=============== 203-00040 Uncl Excav (Spec) Cubic Yard =============================================

CC R600-225 CHATFIELD STATE PARK 06/10/04 3,100.00 6.00 4.40 4.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3,100.00 6.00 4.40 4.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3,100.00 6.00 4.40 4.00

=============== 203-00060 Emb Matl (CIP) Cubic Yard =============================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 351.00 12.00 21.15 14.00STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 5,676.00 8.00 10.19 6.27IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 416,553.00 4.00 2.36 2.02STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 11,100.00 9.00 5.16 0.50IM 0701-157 FRUITA TO CLIFTON 02/26/04 6,667.00 9.00 13.01 13.00STA 014A-030 SH 14, WALDEN EAST 03/04/04 50.00 40.00 41.09 50.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 7,283.00 9.00 10.20 10.00NH 2872-016 US 287 - LAMAR 03/04/04 1,353.00 8.50 16.84 20.35

Page 99: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 55 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 203-00060 Emb Matl (CIP) Cubic Yard =============================================SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 36,531.00 4.00 7.33 6.50STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 10.00 10.00 34.82 26.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 1,280.00 10.00 12.00 12.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 38,910.00 6.00 7.53 5.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 525,764.00 4.46 3.17 2.90

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 56.10 12.00 14.70 10.05STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 13,327.00 8.00 8.77 6.12NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 10,949.00 9.00 11.46 7.50STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 290.00 6.00 22.16 22.00STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 6,807.00 14.00 17.33 16.00IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 36,914.00 8.00 4.50 4.76STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 1,204.00 15.00 25.43 24.20SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 7,162.00 7.00 12.78 8.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 18,188.00 9.00 10.05 6.60BR 0362-028 BRIDGE OVER KIOWA CREEK 05/13/04 5.00 30.00 350.00 350.00STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 17,591.00 14.00 8.63 6.50NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 210.00 24.00 29.93 29.30CC R600-225 CHATFIELD STATE PARK 06/10/04 11,622.00 6.00 6.09 4.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 4,055.00 8.00 11.07 9.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 6,333.00 7.00 9.77 7.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 134,713.10 9.12 8.19 6.79

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 29,323.00 5.50 9.07 7.70IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 771,735.00 3.75 4.97 3.60SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 450.00 20.00 27.00 24.00SHE 0091-023 SH 9 VMS - FAIRPLAY TO FRISCO 07/15/04 15.00 40.00 92.89 263.47BR 0243-063 EAST OF LIMON 07/15/04 3,386.00 10.00 16.25 18.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 21,138.00 9.00 7.73 7.00SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 150.00 25.00 35.15 37.30NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 164,181.00 3.00 3.97 3.75C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 6,140.00 8.00 13.69 14.50SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 1,695.00 50.00 29.00 24.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 8,576.00 10.00 10.75 10.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 8,098.00 7.00 9.38 11.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,014,887.00 4.00 5.17 4.09

BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 1,478.00 25.00 25.01 30.00

Page 100: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 56 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 203-00060 Emb Matl (CIP) Cubic Yard =============================================IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 106,942.00 6.00 4.68 6.00NH 2873-137 US 287 IN BOULDER & LARIMER C 11/18/04 1,250.00 12.00 26.20 25.50BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 14,533.00 8.00 8.08 6.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 611.00 20.00 16.67 18.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 72.60 20.00 26.42 15.00STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 4.00 35.00 180.30 22.35 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 124,890.60 6.60 5.67 6.54 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,800,254.70 4.70 4.69 4.12

=============== 203-00061 Emb Matl (CIP) Ton ====================================================

BR 0092-018 SH 9, SOUTH OF KREMMLING 05/27/04 1,850.00 8.00 10.43 11.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,850.00 8.00 10.43 11.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,850.00 8.00 10.43 11.00

=============== 203-00100 Muck Excav Cubic Yard =============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 1,000.00 5.00 19.52 10.04STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 190.00 20.00 22.83 21.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,190.00 7.39 20.05 11.79

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 978.00 10.00 10.54 6.05NH 0502-053 CIMARRON - WEST 04/15/04 1,000.00 10.00 10.14 10.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 10.00 13.00 28.28 12.40STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 300.00 15.00 15.12 21.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 500.00 6.00 31.59 45.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1,000.00 9.00 8.59 6.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3,788.00 9.61 11.21 13.55

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 1,000.00 10.00 8.84 8.35BR 0243-063 EAST OF LIMON 07/15/04 100.00 20.00 13.18 4.00IM 0701-168 RIFLE TO SILT SLAB REPAIR 08/05/04 1,000.00 10.00 14.32 17.00

Page 101: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 57 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 203-00100 Muck Excav Cubic Yard =============================================NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 100.00 15.00 18.10 10.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 306.00 8.00 11.69 10.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 500.00 13.00 13.75 12.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 3,006.00 10.79 12.15 11.91 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 7,984.00 9.73 13.06 12.67

=============== 203-00210 Borrow (CIP) Cubic Yard =============================================

STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 7,922.00 8.00 12.07 9.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 7,922.00 8.00 12.07 9.50

IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 2,830.00 10.00 26.72 15.15 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2,830.00 10.00 26.72 15.15 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10,752.00 8.53 15.16 10.99

=============== 203-00400 Rock Excav Cubic Yard =============================================

STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 14,822.00 12.00 8.06 7.55 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 14,822.00 12.00 8.06 7.55

STA 1191-020 SH 119 ROCKFALL MITIGATION, 2 04/15/04 7.00 25.00 540.00 100.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 2,282.00 100.00 76.38 90.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2,289.00 99.77 77.80 90.03

STA 0703-290 GEORGETOWN HILL ROCKFALL MITI 10/07/04 25.00 110.00 642.50 245.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 25.00 110.00 642.50 245.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 17,136.00 23.87 12.67 18.91

Page 102: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 58 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 203-00440 Rock Excav (Spec) Cubic Yard =============================================

STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 1,100.00 10.00 18.49 18.93 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,100.00 10.00 18.49 18.93 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,100.00 10.00 18.49 18.93

=============== 203-00598 Rock Scaling Hour ===================================================

STA 1191-020 SH 119 ROCKFALL MITIGATION, 2 04/15/04 160.00 275.00 112.33 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 160.00 275.00 112.33 60.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 160.00 275.00 112.33 60.00

=============== 203-00700 Reclaim Pit Each ===================================================

STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 2.00 5000.00 7375.00 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 5000.00 7375.00 500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 5000.00 7375.00 500.00

=============== 203-00850 Polystyrene Fill (CIP) Cubic Yard =============================================

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 6,250.00 100.00 87.60 72.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 6,250.00 100.00 87.60 72.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6,250.00 100.00 87.60 72.00

=============== 203-01100 Proof Rolling Hour ===================================================

STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 10.00 100.00 79.00 86.99STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 50.00 75.00 60.50 54.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 20.00 90.00 77.07 41.43NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 25.00 70.00 93.06 110.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 5.00 100.00 118.96 85.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 110.00 80.00 81.94 68.85

Page 103: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 59 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 203-01100 Proof Rolling Hour ===================================================

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 10.00 90.00 90.74 84.67NH 0502-053 CIMARRON - WEST 04/15/04 100.00 60.00 70.83 75.00STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 25.00 75.00 78.33 75.00STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 10.00 80.00 82.00 80.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 40.00 80.00 83.68 120.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 10.00 80.00 75.60 85.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 200.00 90.00 70.00 40.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 20.00 100.00 118.81 100.00CC R600-225 CHATFIELD STATE PARK 06/10/04 5.00 100.00 111.25 100.00IM 0702-239 HANGING LAKES REST AREAS 06/17/04 10.00 90.00 141.50 211.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 10.00 70.00 88.29 80.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 440.00 81.08 80.97 68.37

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 30.00 115.00 107.52 100.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 12.00 80.00 86.03 65.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 100.00 90.00 107.25 160.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 142.00 94.44 104.98 139.30

SHE 105A-010 SH 105/FURROW RD 10/07/04 10.00 100.00 99.34 120.00BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 6.00 110.00 85.00 89.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 100.00 100.00 93.19 83.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 40.00 90.00 102.68 94.00NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 10.00 70.00 116.10 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 166.00 96.14 96.25 89.12 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 858.00 86.07 89.05 84.18

=============== 203-01140 Rolling Hour ===================================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 50.00 80.00 99.90 120.00IM 0701-164 PARACHUTE EAST & WEST 02/12/04 16.00 62.00 84.20 90.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 66.00 75.64 95.41 112.73

Page 104: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 60 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 203-01140 Rolling Hour ===================================================

NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 30.00 80.00 75.00 50.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 30.00 80.00 75.00 50.00

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 40.00 90.00 103.75 85.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 40.00 90.00 103.75 85.00

NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 50.00 75.00 81.67 60.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 50.00 100.00 65.00 50.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 100.00 87.50 76.11 55.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 236.00 83.65 86.38 75.59

=============== 203-01500 Blading Hour ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 20.00 100.00 130.99 100.00STA 2911-001 SH 291 SALIDA NORTH 01/08/04 50.00 90.00 105.36 120.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 60.00 90.00 122.24 129.50STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 150.00 80.00 90.00 90.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 8.00 110.00 118.49 125.00IM 0701-164 PARACHUTE EAST & WEST 02/12/04 32.00 90.00 96.00 90.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 50.00 90.00 95.00 80.00STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 100.00 80.00 98.00 96.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 10.00 105.00 103.33 120.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 100.00 90.00 100.00 90.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 40.00 120.00 98.50 85.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 50.00 100.00 104.05 51.28STA 014A-030 SH 14, WALDEN EAST 03/04/04 10.00 90.00 100.00 85.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 20.00 100.00 105.00 80.00NH 2872-016 US 287 - LAMAR 03/04/04 50.00 100.00 96.25 90.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 250.00 90.00 100.07 122.00STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 120.00 90.00 106.25 80.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 40.00 100.00 152.33 222.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 40.00 80.00 112.65 100.00

Page 105: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 61 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 203-01500 Blading Hour ===================================================STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 50.00 95.00 121.00 112.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 60.00 90.00 111.00 143.00STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 40.00 90.00 95.00 90.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,350.00 90.49 104.10 104.17

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 100.00 88.00 97.73 65.00NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 200.00 90.00 100.00 75.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 60.00 120.00 110.82 91.34NH 0502-053 CIMARRON - WEST 04/15/04 40.00 85.00 97.22 90.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 75.00 75.00 92.50 85.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 40.00 75.00 102.22 75.00STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 30.00 100.00 95.00 85.00STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 20.00 100.00 95.35 95.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 400.00 65.00 119.90 140.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 100.00 90.00 93.60 100.00STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 80.00 88.00 93.33 80.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 80.00 90.00 91.63 83.00BR 0092-018 SH 9, SOUTH OF KREMMLING 05/27/04 20.00 100.00 103.63 104.50NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 30.00 90.00 107.50 100.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 100.00 100.00 118.87 140.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 20.00 100.00 105.49 108.40CC R600-225 CHATFIELD STATE PARK 06/10/04 40.00 120.00 123.75 100.00STA 0343-023 US 34, EAST OF AKRON 06/17/04 80.00 100.00 110.60 83.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 50.00 75.00 98.33 80.00IM 0761-185 I-76, LOCHBUIE TO HUDSON 06/24/04 100.00 90.00 123.06 170.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,665.00 85.59 108.04 105.93

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 80.00 90.00 95.71 90.00STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 50.00 100.00 119.75 114.00IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 100.00 100.00 107.32 140.00SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 10.00 125.00 119.00 125.00BR 0243-063 EAST OF LIMON 07/15/04 20.00 100.00 120.84 125.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 50.00 120.00 111.62 112.02STA R200-128 SH10, SH350 , SH160 MAINT. 07/29/04 8.00 100.00 93.33 100.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 30.00 115.00 138.15 100.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 40.00 90.00 107.66 100.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 10.00 100.00 120.04 85.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 120.00 125.00 120.00 120.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 100.00 95.00 91.00 42.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 100.00 100.00 99.74 130.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 718.00 104.18 106.07 106.55

Page 106: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 62 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 203-01500 Blading Hour ===================================================

STA 0703-290 GEORGETOWN HILL ROCKFALL MITI 10/07/04 20.00 120.00 200.00 150.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 10.00 100.00 105.00 85.00BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 100.00 100.00 122.00 80.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 105.00 80.00 97.47 102.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 50.00 100.00 109.04 85.00C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 16.00 120.00 189.50 120.00STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 50.00 110.00 142.95 120.00STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 20.00 100.00 136.51 96.04IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 40.00 130.00 122.33 110.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 150.00 90.00 88.33 60.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 50.00 100.00 75.00 50.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 10.00 120.00 133.68 94.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 621.00 98.42 109.78 86.15 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4,354.00 92.01 106.81 102.66

=============== 203-01510 Backhoe Hour ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 12.00 100.00 115.51 100.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 330.00 90.00 142.46 118.34STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 50.00 80.00 73.00 60.00IM 0701-164 PARACHUTE EAST & WEST 02/12/04 48.00 90.00 87.00 90.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 10.00 100.00 113.14 150.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 100.00 80.00 95.00 80.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 100.00 120.00 127.50 135.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 650.00 92.65 123.83 108.57

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 40.00 100.00 92.94 95.43NH 2852-010 US 285 & COUNTY RD. G 04/29/04 8.00 100.00 107.00 150.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 15.00 70.00 68.00 62.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 25.00 90.00 77.50 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 88.00 92.05 89.59 84.63

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 50.00 100.00 117.92 86.56

Page 107: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 63 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 203-01510 Backhoe Hour ===================================================STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 24.00 90.00 137.22 130.00STA 149A-021 SH 149 CRIBWALL 09/16/04 10.00 130.00 102.00 102.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 16.00 120.00 118.50 50.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 40.00 100.00 100.36 150.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 140.00 102.71 116.81 109.06

C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 52.00 165.00 147.50 165.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 40.00 75.00 127.00 60.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 25.00 100.00 92.64 86.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 50.00 90.00 119.92 80.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 167.00 111.26 120.21 102.57 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,045.00 96.92 119.15 105.66

=============== 203-01515 Backhoe (Landscaping) Hour ===================================================

NH 0502-053 CIMARRON - WEST 04/15/04 50.00 105.00 87.50 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 50.00 105.00 87.50 100.00

NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 10.00 120.00 134.78 134.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 10.00 120.00 134.78 134.10 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 60.00 107.50 95.38 105.68

=============== 203-01525 Backhoe (Spec) Hour ===================================================

NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 20.00 130.00 91.67 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 20.00 130.00 91.67 60.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 20.00 130.00 91.67 60.00

=============== 203-01550 Dozing Hour ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 270.00 100.00 144.91 140.66

Page 108: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 64 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 203-01550 Dozing Hour ===================================================STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 10.00 100.00 133.12 95.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 50.00 100.00 147.50 175.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 330.00 100.00 144.60 144.48

NH 2852-010 US 285 & COUNTY RD. G 04/29/04 10.00 100.00 110.00 100.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 50.00 110.00 134.66 140.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 60.00 108.33 131.13 133.33

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 100.00 120.00 126.20 140.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 30.00 150.00 183.93 120.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 150.00 100.00 132.00 33.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 280.00 112.50 132.93 80.54

C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 16.00 180.00 125.00 120.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 40.00 80.00 154.00 120.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 56.00 108.57 150.00 120.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 726.00 106.17 139.54 117.01

=============== 203-01551 Dozing (Heavy) Hour ===================================================

STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 16.00 150.00 123.33 90.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 16.00 150.00 123.33 90.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 16.00 150.00 123.33 90.00

=============== 203-01555 Dozing (Landscaping) Hour ===================================================

STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 8.00 115.00 111.67 85.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 8.00 90.00 110.71 90.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 16.00 102.50 111.00 87.50

Page 109: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 65 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 203-01555 Dozing (Landscaping) Hour ===================================================

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 20.00 100.00 105.31 85.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 20.00 100.00 105.31 85.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 16.00 110.00 122.97 101.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 16.00 110.00 122.97 101.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 52.00 103.85 113.10 90.69

=============== 203-01582 Truck (Dump) Hour ===================================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 10.00 80.00 64.43 60.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 50.00 70.00 85.16 107.18IM 0701-164 PARACHUTE EAST & WEST 02/12/04 48.00 75.00 75.60 90.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 108.00 73.15 79.77 95.18

NH 0502-053 CIMARRON - WEST 04/15/04 30.00 60.00 75.34 60.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 15.00 60.00 74.25 84.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 50.00 75.00 82.50 80.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 95.00 67.89 77.66 74.32

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 24.00 50.00 74.65 70.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 24.00 50.00 74.65 70.00

NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 40.00 75.00 73.33 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 40.00 75.00 73.33 60.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 267.00 69.48 77.52 80.22

Page 110: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 66 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 203-01590 Front End Loader (Rubber) Hour ===================================================

IM 0701-164 PARACHUTE EAST & WEST 02/12/04 16.00 100.00 92.80 90.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 50.00 91.00 106.50 93.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 66.00 93.18 100.41 92.27

NH 0502-053 CIMARRON - WEST 04/15/04 20.00 100.00 111.68 100.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 25.00 100.00 100.00 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 45.00 100.00 107.19 100.00

C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 40.00 120.00 127.50 125.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 40.00 100.00 86.67 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 80.00 110.00 96.88 92.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 191.00 101.83 100.01 94.19

=============== 203-01594 Combination Loader Hour ===================================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 40.00 80.00 68.99 80.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 10.00 90.00 91.72 95.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 400.00 90.00 95.10 112.76STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 10.00 80.00 70.00 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 460.00 88.91 93.26 108.38

NH 2852-010 US 285 & COUNTY RD. G 04/29/04 10.00 100.00 77.00 65.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 10.00 100.00 77.00 65.00

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 30.00 100.00 140.89 100.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 24.00 90.00 101.38 90.00

Page 111: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 67 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 203-01594 Combination Loader Hour ===================================================STA 149A-021 SH 149 CRIBWALL 09/16/04 10.00 80.00 102.00 102.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 114.00 85.00 77.75 24.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 178.00 87.92 90.71 50.09

STA 0703-290 GEORGETOWN HILL ROCKFALL MITI 10/07/04 20.00 90.00 150.00 100.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 20.00 75.00 90.00 60.00STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 10.00 140.00 117.50 85.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 40.00 90.00 104.83 90.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 40.00 80.00 81.67 100.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 40.00 80.00 63.33 50.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 170.00 86.47 90.12 80.29 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 818.00 88.33 92.11 89.33

=============== 203-01597 Potholing Hour ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 40.00 160.00 166.62 160.00STA 2911-001 SH 291 SALIDA NORTH 01/08/04 20.00 130.00 125.88 100.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 40.00 100.00 154.01 160.00C 0342-040 US 34 IN WELD COUNTY 01/29/04 12.00 120.00 148.02 148.28STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 10.00 150.00 148.85 140.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 25.00 175.00 164.43 225.00STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 100.00 130.00 134.50 100.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 25.00 150.00 168.76 130.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 25.00 180.00 173.06 160.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 40.00 175.00 168.05 100.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 50.00 150.00 153.75 120.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 20.00 150.00 150.44 153.51STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 20.00 125.00 245.00 220.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 100.00 120.00 158.40 200.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 100.00 150.00 125.38 130.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 40.00 140.00 192.83 180.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 25.00 150.00 133.90 90.38NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 8.00 100.00 163.30 150.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 160.00 150.00 134.59 111.00C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 40.00 150.00 85.00 85.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 30.00 140.00 233.09 175.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 120.00 110.00 130.50 91.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 10.00 150.00 186.00 133.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,060.00 139.26 152.24 132.68

Page 112: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 68 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 203-01597 Potholing Hour ===================================================

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 10.00 150.00 168.83 115.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 60.00 150.00 200.11 175.00NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 200.00 130.00 114.69 28.40SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 40.00 120.00 157.90 89.70ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 700.00 150.00 159.92 86.50IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 40.00 100.00 191.62 207.12STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 20.00 140.00 125.66 150.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 40.00 140.00 154.00 175.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 100.00 150.00 134.25 134.00AQC R600-215 SH 287, US 36 TO SH 128 05/27/04 200.00 150.00 138.76 94.12NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 100.00 160.00 137.50 75.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 50.00 170.00 158.51 180.00CC R600-225 CHATFIELD STATE PARK 06/10/04 40.00 150.00 161.25 100.00IM 0702-239 HANGING LAKES REST AREAS 06/17/04 30.00 170.00 189.42 228.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 20.00 100.00 119.67 90.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,650.00 146.24 147.41 97.65

SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 10.00 170.00 200.00 200.00SHE 0091-023 SH 9 VMS - FAIRPLAY TO FRISCO 07/15/04 10.00 150.00 158.45 130.80IMD 0252-364 I-25 OVER BROADWAY 07/29/04 200.00 150.00 201.49 178.22STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 80.00 100.00 141.68 110.38NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 30.00 150.00 204.63 145.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 10.00 120.00 156.38 110.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 80.00 150.00 232.50 160.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 420.00 140.24 190.99 157.22

SHE 105A-010 SH 105/FURROW RD 10/07/04 10.00 180.00 215.00 200.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 8.00 150.00 250.00 250.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 270.00 120.00 152.45 95.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 100.00 190.00 191.23 182.00C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 25.00 172.00 150.79 130.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 20.00 150.00 182.81 160.85STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 10.00 150.00 168.75 180.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 25.00 150.00 120.83 109.66STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 20.00 150.00 218.30 161.20STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 20.00 150.00 179.65 40.40

Page 113: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 69 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 203-01597 Potholing Hour ===================================================STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 8.00 150.00 130.00 85.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 12.00 150.00 147.50 100.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 20.00 150.00 110.33 100.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 20.00 150.00 207.98 165.89NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 50.00 150.00 164.95 144.80STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 40.00 150.00 138.98 107.50NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 50.00 120.00 203.33 110.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 708.00 143.29 165.78 123.06 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3,838.00 143.11 155.98 118.53

=============== 203-01620 Sweeping Hour ===================================================

STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 10.00 100.00 76.67 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 10.00 100.00 76.67 60.00

NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 40.00 50.00 97.50 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 40.00 50.00 97.50 60.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 50.00 60.00 93.33 60.00

=============== 203-02060 Presplitting Lin Foot ===============================================

STA 0703-290 GEORGETOWN HILL ROCKFALL MITI 10/07/04 300.00 100.00 48.00 2.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 300.00 100.00 48.00 2.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 300.00 100.00 48.00 2.00

=============== 203-02300 Rock Scaler Hour ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 160.00 70.00 86.04 167.36 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 160.00 70.00 86.04 167.36

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 24.00 90.00 122.74 160.00

Page 114: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 70 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 203-02300 Rock Scaler Hour ===================================================STA 149A-021 SH 149 CRIBWALL 09/16/04 100.00 130.00 100.00 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 124.00 122.26 112.40 111.61

STA 0703-290 GEORGETOWN HILL ROCKFALL MITI 10/07/04 20.00 100.00 107.50 115.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 20.00 100.00 107.50 115.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 304.00 93.29 91.49 141.18

=============== 203-02310 Scaler Foreman Hour ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 80.00 80.00 91.52 109.34 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 80.00 80.00 91.52 109.34

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 24.00 80.00 106.26 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 24.00 80.00 106.26 100.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 104.00 80.00 94.47 107.19

=============== 203-02330 Laborer Hour ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 200.00 30.00 36.87 50.21IM 0701-164 PARACHUTE EAST & WEST 02/12/04 80.00 30.00 40.20 40.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 50.00 30.00 32.67 30.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 330.00 30.00 37.27 44.67

STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 10.00 35.00 37.50 40.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 100.00 30.00 42.50 35.00IM 0702-239 HANGING LAKES REST AREAS 06/17/04 50.00 30.00 52.31 79.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 160.00 30.31 45.76 49.06

Page 115: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 71 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 203-02330 Laborer Hour ===================================================

IM 0701-168 RIFLE TO SILT SLAB REPAIR 08/05/04 50.00 30.00 35.00 25.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 24.00 30.00 44.91 32.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 74.00 30.00 38.72 27.27

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 80.00 35.00 32.27 33.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 80.00 30.00 44.67 35.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 160.00 32.50 36.40 34.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 724.00 30.62 38.26 41.51

=============== 206-00000 Str Excav Cubic Yard =============================================

STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 8.00 15.00 46.51 72.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 43,654.00 18.00 20.93 16.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 5,108.00 6.00 3.37 3.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1,796.00 7.00 10.79 9.10STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 22,867.00 3.50 4.10 3.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 73,433.00 12.38 16.46 10.95

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 166.00 15.00 7.30 3.45SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 32.00 14.00 35.57 31.50NH 0502-053 CIMARRON - WEST 04/15/04 880.00 7.00 19.00 10.00IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 2,130.00 8.50 8.16 9.75SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 301.00 5.00 10.53 15.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 373.00 15.00 12.33 10.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 31,124.00 4.00 4.54 4.70CC R600-225 CHATFIELD STATE PARK 06/10/04 35.00 20.00 24.00 21.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 290.00 10.00 24.25 13.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 425.00 5.00 9.33 11.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 1,192.00 8.00 9.57 17.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 36,948.00 4.71 5.48 5.82

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 1,112.00 10.00 20.51 12.00

Page 116: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 72 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 206-00000 Str Excav Cubic Yard =============================================IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 2,458.00 4.00 8.74 11.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 92.00 18.00 60.82 87.53IMD 0252-364 I-25 OVER BROADWAY 07/29/04 21,258.00 6.00 5.22 5.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 1,068.00 10.00 7.62 10.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 3,808.00 18.00 15.59 6.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 155.00 10.00 11.78 10.50NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1,584.00 8.00 12.88 6.50IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 190.00 9.00 8.76 5.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 31,725.00 7.73 8.46 6.34

SHE 105A-010 SH 105/FURROW RD 10/07/04 49.00 19.00 22.11 14.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 18,812.00 5.00 5.16 3.75BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 2,289.00 5.00 7.15 4.50NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 55.00 20.00 34.00 20.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 27.00 20.00 40.33 50.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 21,232.00 5.09 5.41 3.96 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 163,338.00 8.80 10.67 7.98

=============== 206-00050 Str Bkfl (Spec) Cubic Yard =============================================

STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 8.00 20.00 49.56 79.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 61,843.00 8.00 16.96 6.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 131.00 15.00 103.00 95.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 61,982.00 8.02 17.08 6.20 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 61,982.00 8.02 17.08 6.20

=============== 206-00060 Str Bkfl (Spec) (Flow-Fill) Cubic Yard =============================================

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 150.00 75.00 95.61 59.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 150.00 75.00 95.61 59.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 74.00 80.00 71.12 80.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 74.00 80.00 71.12 80.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 224.00 76.65 87.52 65.94

Page 117: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 73 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 206-00065 Str Bkfl (Flow-Fill) Cubic Yard =============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 30.00 65.00 173.36 120.13STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 180.00 70.00 62.90 60.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 63.00 100.00 96.94 107.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 273.00 76.37 84.84 77.45

NH 0502-053 CIMARRON - WEST 04/15/04 508.00 75.00 97.73 100.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 705.50 100.00 76.24 60.20NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 100.00 75.00 100.00 100.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 186.00 80.00 123.75 68.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 112.00 50.00 70.00 65.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,611.50 84.78 88.18 76.45

BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 53.00 120.00 139.27 118.75BR 0243-063 EAST OF LIMON 07/15/04 302.00 80.00 119.55 130.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 160.00 65.00 81.23 91.65IM 0701-168 RIFLE TO SILT SLAB REPAIR 08/05/04 1,300.00 75.00 100.89 90.00STA 149A-021 SH 149 CRIBWALL 09/16/04 135.00 100.00 78.00 78.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1,815.00 70.00 86.00 85.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 3,765.00 74.10 93.84 90.84

C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 30.00 160.00 147.50 145.00STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 4.00 100.00 230.59 250.00STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 71.00 125.00 196.25 220.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 7.00 125.00 176.10 109.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 112.00 133.48 189.10 194.07 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5,761.50 78.35 93.23 88.19

=============== 206-00100 Str Bkfl (CL 1) Cubic Yard =============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 2,209.00 17.00 15.63 14.00

Page 118: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 74 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 206-00100 Str Bkfl (CL 1) Cubic Yard =============================================STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1,712.00 20.00 24.37 20.55STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 12,134.00 12.00 8.00 9.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 16,055.00 13.54 14.14 11.30

NH 0502-053 CIMARRON - WEST 04/15/04 284.00 25.00 45.07 25.00IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 1,589.00 15.00 21.56 23.84SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 315.00 15.00 22.74 22.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 42,262.00 12.00 10.29 7.50CC R600-225 CHATFIELD STATE PARK 06/10/04 75.00 30.00 41.75 37.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 700.00 18.00 31.86 21.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 45,225.00 12.33 11.39 8.54

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 5,040.00 15.00 23.17 21.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 24,396.00 12.00 14.10 12.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 680.00 22.00 29.50 15.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 4,367.00 23.00 22.86 25.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 125.00 12.50 30.70 32.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 750.00 30.00 17.75 17.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 35,358.00 14.36 17.44 15.12

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 51,694.00 13.00 15.86 14.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 864.00 20.00 23.12 16.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 52,558.00 13.12 15.94 14.03 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 149,196.00 13.22 14.55 12.33

=============== 206-00200 Str Bkfl (CL 2) Cubic Yard =============================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 18.00 25.00 83.58 60.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 26.00 13.00 23.92 14.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 44.00 17.91 39.26 32.82

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 79.90 10.00 13.23 6.85

Page 119: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 75 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 206-00200 Str Bkfl (CL 2) Cubic Yard =============================================NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 19.00 25.00 23.96 30.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 100.00 16.00 47.50 10.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 260.00 9.00 15.33 15.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 400.00 18.00 13.93 7.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 858.90 14.45 17.28 10.27

BR 0243-063 EAST OF LIMON 07/15/04 54.00 15.00 22.10 13.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1,756.00 22.00 13.94 6.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 365.00 15.00 17.00 26.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2,175.00 20.65 14.49 9.53

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1,210.00 10.00 14.01 9.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,210.00 10.00 14.01 9.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4,287.90 16.38 15.36 9.77

=============== 206-00360 Mechanical Reinforcement of Soil Cubic Yard =============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 40,409.00 15.00 19.96 24.85STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 9,448.00 12.50 16.25 16.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 49,857.00 14.53 19.69 23.27

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 25,097.00 9.00 20.60 23.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 700.00 12.00 22.93 57.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 25,797.00 9.08 20.67 23.94

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 3,295.00 12.00 16.61 28.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 21,304.00 6.00 27.29 35.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 3,784.00 19.00 26.67 22.00

Page 120: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 76 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 206-00360 Mechanical Reinforcement of Soil Cubic Yard =============================================NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 2,025.00 12.50 43.50 40.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 30,408.00 8.70 26.59 32.96

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 10,719.00 13.00 16.43 9.50BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 864.00 16.00 14.04 15.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 11,583.00 13.22 16.31 9.91 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 117,645.00 11.70 21.04 24.60

=============== 206-00505 Filter Matl (Spec) Cubic Yard =============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 4,619.00 25.00 29.90 22.32 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4,619.00 25.00 29.90 22.32 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4,619.00 25.00 29.90 22.32

=============== 206-00510 Filter Matl (CL A) Cubic Yard =============================================

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 7.00 60.00 59.34 38.09CC R600-225 CHATFIELD STATE PARK 06/10/04 20.00 50.00 40.00 30.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 27.00 52.59 48.52 32.10

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 35.00 20.00 94.73 100.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 175.00 28.00 32.72 30.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 808.00 40.00 37.75 44.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,018.00 37.25 39.05 43.52

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 613.00 38.00 88.60 67.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 613.00 38.00 88.60 67.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,658.00 37.78 59.51 52.01

Page 121: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 77 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 206-00520 Filter Matl (CL B) Cubic Yard =============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 213.00 48.00 34.47 28.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 213.00 48.00 34.47 28.70

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 44.00 40.00 48.65 39.06NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 70.00 50.00 30.02 40.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 114.00 46.14 37.90 39.64 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 327.00 47.35 35.50 32.51

=============== 206-00530 Filter Matl (CL C) Cubic Yard =============================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 23.00 40.00 50.92 32.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 23.00 40.00 50.92 32.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 23.00 40.00 50.92 32.00

=============== 206-01000 Bed Course Matl Cubic Yard =============================================

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 9.00 30.00 33.82 31.05NH 0502-053 CIMARRON - WEST 04/15/04 24.00 30.00 36.54 30.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 33.00 30.00 35.56 30.29

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 809.00 30.00 42.33 20.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 809.00 30.00 42.33 20.00

NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 32.00 19.00 40.00 25.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 32.00 19.00 40.00 25.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 874.00 29.60 42.04 20.57

Page 122: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 78 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 206-01750 Shoring LUMP SUM ===============================================

STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1.00 20000.00 67763.24 12600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 20000.00 67763.24 12600.00

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 1.00 15000.00 57447.66 18346.65NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 20000.00 191926.67 75000.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 1.00 5000.00 14125.00 11750.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 1.00 20000.00 33037.33 47000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4.00 15000.00 85465.28 38024.16

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1.00 19520.00 20228.09 5000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 19520.00 20228.09 5000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6.00 16586.67 69849.00 28282.78

=============== 206-01781 Shoring (A 1) LUMP SUM ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 5000.00 32637.50 12000.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1.00 20000.00 32650.00 35000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 12500.00 32640.00 23500.00

SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 1.00 2500.00 4687.32 2580.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 1.00 4000.00 25050.00 23600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 3250.00 16565.55 13090.00

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 20000.00 28938.69 55000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 20000.00 28938.69 55000.00

Page 123: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 79 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 206-01781 Shoring (A 1) LUMP SUM ===============================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1.00 25000.00 66816.67 68000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 25000.00 66816.67 68000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6.00 12750.00 32557.54 32696.67

=============== 206-01782 Shoring (A 2) LUMP SUM ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 5000.00 34687.50 12000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 5000.00 34687.50 12000.00

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 80000.00 42760.70 60000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 80000.00 42760.70 60000.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1.00 25000.00 61400.00 68000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 25000.00 61400.00 68000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 36666.67 45385.71 46666.67

=============== 206-01783 Shoring (A 3) LUMP SUM ===============================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 10000.00 8974.40 5000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 10000.00 8974.40 5000.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1.00 125000.00 22182.06 40000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 125000.00 22182.06 40000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 67500.00 16899.00 22500.00

Page 124: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 80 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 206-01784 Shoring (A 4) LUMP SUM ===============================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 35000.00 8378.85 10000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 35000.00 8378.85 10000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 35000.00 8378.85 10000.00

=============== 206-01785 Shoring (A 5) LUMP SUM ===============================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 10000.00 78383.01 80000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 10000.00 78383.01 80000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 10000.00 78383.01 80000.00

=============== 206-01786 Shoring (A 6) LUMP SUM ===============================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 10000.00 42244.29 20000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 10000.00 42244.29 20000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 10000.00 42244.29 20000.00

=============== 206-01787 Shoring (A 7) LUMP SUM ===============================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 35000.00 21513.69 25000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 35000.00 21513.69 25000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 35000.00 21513.69 25000.00

=============== 207-00205 Topsoil Cubic Yard =============================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 97.00 30.00 29.43 13.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 10.00 30.00 46.64 15.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 200.00 20.00 18.64 28.90NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 380.00 10.00 25.37 4.01STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 7,843.00 5.00 9.40 8.00STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 14.00 8.00 82.83 20.00

Page 125: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 81 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 207-00205 Topsoil Cubic Yard =============================================C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 123.00 10.00 31.81 22.25STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 28.00 30.00 42.05 49.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 20,074.00 6.00 2.50 2.55STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 3,500.00 8.00 9.61 8.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 1,000.00 10.00 10.68 7.86NH 2872-016 US 287 - LAMAR 03/04/04 4,006.00 7.00 16.18 17.23SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 6,933.00 5.00 5.37 4.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 62.00 20.00 47.53 121.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 450.00 13.00 11.00 8.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 44,959.00 3.50 2.80 2.90 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 89,679.00 4.88 5.05 4.47

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 1,286.00 15.00 20.88 30.10STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 1,936.00 15.00 10.53 6.99NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 8,444.00 8.50 12.03 11.00IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 2,600.00 8.00 3.61 3.23STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 54.00 20.00 50.63 34.02IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 900.00 10.00 28.83 16.50SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 3,300.00 7.00 4.18 5.40NH 2852-010 US 285 & COUNTY RD. G 04/29/04 1,156.00 20.00 15.19 7.90STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 8,410.00 6.00 8.05 8.00BR 0092-018 SH 9, SOUTH OF KREMMLING 05/27/04 400.00 17.00 27.38 49.50NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 14.50 8.00 82.50 50.00CC R600-225 CHATFIELD STATE PARK 06/10/04 1,342.00 15.00 6.88 7.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 7.00 10.00 82.00 58.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 29,849.50 9.21 10.09 9.88

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 6,955.00 8.00 5.11 5.00SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 135.00 20.00 10.25 7.50IMD 0252-364 I-25 OVER BROADWAY 07/29/04 807.00 16.00 15.95 15.00STA R200-128 SH10, SH350 , SH160 MAINT. 07/29/04 2,309.00 12.00 18.61 16.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 22,867.00 2.50 2.90 2.35STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 280.00 20.00 22.73 25.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1,368.00 6.00 9.55 5.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 10,439.00 6.00 14.33 10.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 4,870.00 6.00 7.96 6.85IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 1,703.00 9.00 8.63 8.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 51,733.00 5.36 7.19 5.87

SHE 105A-010 SH 105/FURROW RD 10/07/04 936.00 13.00 14.83 5.00

Page 126: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 82 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 207-00205 Topsoil Cubic Yard =============================================C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 490.00 24.00 21.00 8.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 9,500.00 6.00 7.94 9.50BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1,740.00 18.00 9.47 12.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 400.00 20.00 26.86 21.45 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 13,066.00 9.20 9.39 9.82 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 184,327.50 6.02 6.90 6.12

=============== 207-00210 Stockpile Topsoil Cubic Yard =============================================

C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1,368.00 3.00 5.91 4.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,368.00 3.00 5.91 4.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,368.00 3.00 5.91 4.00

=============== 207-00305 Wetland Topsoil Cubic Yard =============================================

NH 2852-010 US 285 & COUNTY RD. G 04/29/04 300.00 20.00 14.03 10.90STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 60.00 20.00 31.50 22.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 39.00 12.00 16.00 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 399.00 19.22 16.42 12.48

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 700.00 10.00 8.40 14.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 409.00 11.00 13.58 12.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,109.00 10.37 9.85 13.37

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 130.00 15.00 11.31 7.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 130.00 15.00 11.31 7.25 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,638.00 12.89 11.42 12.67

=============== 207-00310 Stockpile Wetland Topsoil Cubic Yard =============================================

NH 2852-010 US 285 & COUNTY RD. G 04/29/04 300.00 8.00 9.32 8.00

Page 127: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 83 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 207-00310 Stockpile Wetland Topsoil Cubic Yard =============================================STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 39.00 13.00 14.00 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 339.00 8.58 9.66 8.23

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 700.00 10.00 7.28 7.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 371.00 9.00 12.33 11.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,071.00 9.65 8.59 8.49

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 130.00 9.00 9.99 4.75NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 6.00 20.00 63.70 26.80 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 136.00 9.49 11.60 5.72 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,546.00 9.40 9.11 8.19

=============== 208-00001 Silt Dike Lin Foot ===============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 500.00 7.00 14.61 7.63 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 500.00 7.00 14.61 7.63 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 500.00 7.00 14.61 7.63

=============== 208-00002 Erosion Log (12 In) Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1,420.00 10.00 5.53 5.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 970.00 6.00 4.66 4.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,390.00 8.38 5.20 4.68

NH 2852-010 US 285 & COUNTY RD. G 04/29/04 400.00 6.00 5.40 5.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 400.00 6.00 5.40 5.00

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 100.00 5.00 7.00 7.50

Page 128: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 84 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 208-00002 Erosion Log (12 In) Lin Foot ===============================================NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 1,285.00 13.00 3.63 3.30STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 760.00 18.00 4.56 2.25C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 530.00 5.00 4.48 4.50NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 544.00 5.00 4.94 3.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 3,219.00 11.26 4.41 3.37

C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 325.00 8.50 7.00 6.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 230.00 6.00 6.08 6.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 555.00 7.46 6.53 6.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6,564.00 9.57 4.97 4.17

=============== 208-00004 Silt Berm Lin Foot ===============================================

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 300.00 5.00 5.59 5.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 300.00 5.00 5.59 5.40 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 300.00 5.00 5.59 5.40

=============== 208-00005 Erosion Log Lin Foot ===============================================

STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 100.00 6.00 9.12 17.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 490.00 7.00 11.87 13.21STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 120.00 8.00 10.70 7.40IM 0701-157 FRUITA TO CLIFTON 02/26/04 320.00 9.00 7.12 6.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 100.00 6.00 5.74 5.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 6,970.00 6.75 3.95 4.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 8,100.00 6.85 5.70 4.86

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 100.00 7.00 7.23 5.00STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 300.00 7.00 8.00 6.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 11,100.00 4.00 5.14 5.98IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 155.00 8.00 7.54 9.96STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 3,500.00 5.00 3.06 5.00

Page 129: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 85 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 208-00005 Erosion Log Lin Foot ===============================================NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 100.00 7.00 6.79 10.00CC R600-225 CHATFIELD STATE PARK 06/10/04 120.00 6.00 8.09 9.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 15,375.00 4.38 4.74 5.84

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 9,300.00 5.00 3.39 3.40STA 149A-021 SH 149 CRIBWALL 09/16/04 148.00 7.00 9.00 9.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 9,448.00 5.03 3.40 3.49

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 100.00 7.00 10.04 5.20NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 100.00 10.00 7.13 5.35 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 200.00 8.50 8.74 5.28 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 33,123.00 5.20 4.34 4.93

=============== 208-00006 Erosion Log (Special) Lin Foot ===============================================

NH 0502-053 CIMARRON - WEST 04/15/04 33,256.00 2.50 3.67 3.05BR 0092-018 SH 9, SOUTH OF KREMMLING 05/27/04 100.00 5.00 4.60 4.15NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 630.00 3.00 3.50 4.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 33,986.00 2.52 3.67 3.07

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 3,770.00 7.00 4.79 5.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 3,770.00 7.00 4.79 5.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 37,756.00 2.96 3.85 3.26

=============== 208-00007 Erosion Log (8 In) Lin Foot ===============================================

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 960.00 3.35 4.78 3.35 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 960.00 3.35 4.78 3.35

Page 130: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 86 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 208-00007 Erosion Log (8 In) Lin Foot ===============================================

NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 100.00 7.00 11.33 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 100.00 7.00 11.33 10.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,060.00 3.69 5.25 3.98

=============== 208-00010 Erosion Bales Each ===================================================

C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 2.00 15.00 16.96 9.75NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 151.00 15.00 11.35 11.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 153.00 15.00 11.43 10.98

STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 30.00 13.00 13.24 9.90STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 50.00 10.00 14.42 9.50STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 30.00 12.25 14.13 14.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 110.00 11.43 14.08 10.84

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 5.00 25.00 26.02 20.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 5.00 25.00 26.02 20.00

NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 48.00 11.00 14.01 13.56IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 30.00 15.00 18.67 15.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 78.00 12.54 15.28 14.11 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 346.00 13.46 13.11 11.77

=============== 208-00011 Erosion Bales (Weed Free) Each ===================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 25.00 15.00 13.63 12.00

Page 131: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 87 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 208-00011 Erosion Bales (Weed Free) Each ===================================================IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 12.00 20.00 26.57 25.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 20.00 15.00 30.63 17.64STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 75.00 14.00 12.20 10.50STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 24.00 15.00 16.49 10.30STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 7.00 14.00 14.41 9.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 50.00 13.00 14.41 15.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 50.00 15.00 10.31 9.21IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 156.00 14.00 11.51 10.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 50.00 13.00 13.33 8.43STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 18.00 14.00 16.06 11.25STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 181.00 15.00 13.23 7.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 668.00 14.41 13.36 10.25

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 168.00 12.00 9.35 9.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 50.00 13.00 12.65 8.18NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 50.00 15.00 12.65 8.40NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 27.00 11.00 11.13 12.50IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 36.00 12.00 15.63 17.50SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 81.00 11.00 14.20 16.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 423.00 12.00 11.62 11.00CC R600-225 CHATFIELD STATE PARK 06/10/04 40.00 15.00 10.65 9.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 25.00 12.00 14.57 12.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 147.00 15.00 12.31 12.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 25.00 13.00 15.33 11.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,072.00 12.63 11.84 11.15

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 99.00 15.00 14.63 17.00IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 2,123.00 11.00 10.10 11.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 70.00 20.00 18.84 15.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 30.00 12.00 16.70 12.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 45.00 14.00 10.00 10.00STA 149A-021 SH 149 CRIBWALL 09/16/04 29.00 18.00 50.00 50.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2,396.00 11.58 10.61 11.83

SHE 105A-010 SH 105/FURROW RD 10/07/04 25.00 14.00 18.54 15.00C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 100.00 18.00 19.00 22.00

Page 132: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 88 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 208-00011 Erosion Bales (Weed Free) Each ===================================================IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 54.00 16.00 13.01 13.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 300.00 11.00 10.60 11.00C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 50.00 20.00 12.28 10.70MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 50.00 20.00 29.33 18.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 50.00 12.00 14.41 12.35 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 629.00 14.17 13.64 13.72 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4,765.00 12.56 11.65 11.71

=============== 208-00020 Silt Fence Lin Foot ===============================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 260.00 3.00 1.77 1.10STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 1,400.00 1.50 0.98 0.85STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 2,440.00 1.00 1.17 1.20NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 10,200.00 2.00 3.23 3.91STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 500.00 2.00 1.55 1.10C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 745.00 2.50 1.50 1.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 650.00 2.00 1.23 1.10STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 1,640.00 2.00 1.61 1.50STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 500.00 1.60 1.89 2.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 810.00 2.00 1.29 1.23STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 1,000.00 2.00 3.20 3.40IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 2,196.00 1.50 1.28 1.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 1,000.00 2.00 1.08 0.97STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 1,200.00 1.50 1.67 1.25STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 2,750.00 2.00 1.82 1.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 6,750.00 1.40 1.20 1.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 34,041.00 1.75 2.00 2.03

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 5,239.00 1.50 1.16 0.97NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 500.00 2.00 1.76 1.21STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 30.00 2.00 5.94 3.12ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 200.00 4.00 8.81 5.20IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 900.00 2.00 1.94 2.21SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 100.00 2.00 1.53 2.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 1,400.00 3.00 2.56 1.50STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 500.00 2.50 1.90 1.50STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 200.00 3.00 3.90 4.64NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 50.00 1.60 10.00 10.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 515.00 1.75 1.74 1.50NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 100.00 3.00 1.81 1.80

Page 133: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 89 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 208-00020 Silt Fence Lin Foot ===============================================CC R600-225 CHATFIELD STATE PARK 06/10/04 2,550.00 2.00 1.33 1.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 2,550.00 1.50 1.36 1.10SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 615.00 1.40 1.74 1.50STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 160.00 1.50 1.92 1.50BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 300.00 1.50 2.67 3.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 15,909.00 1.86 1.54 1.36

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 40.00 3.50 3.43 3.95IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 9,272.00 1.50 1.09 1.50SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 200.00 3.50 3.13 3.25BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 220.00 3.00 8.60 19.80IMD 0252-364 I-25 OVER BROADWAY 07/29/04 2,360.00 1.75 2.59 1.50SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 110.00 3.00 6.85 3.20STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 725.00 2.50 2.03 1.50C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 95.00 1.50 2.27 2.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1,320.00 2.00 1.95 2.20IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 5,000.00 2.00 1.40 1.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 19,342.00 1.78 1.47 1.66

C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 1,020.00 1.20 1.25 1.40C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 1,000.00 2.50 3.26 2.30BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 200.00 3.00 3.03 2.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 16,630.00 1.00 1.35 1.05BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 3,997.00 1.50 1.15 1.00C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 1,000.00 1.50 2.32 1.50MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 500.00 2.00 3.00 6.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 50.00 5.00 5.67 3.00STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 2,490.00 1.60 1.79 1.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 2,190.00 2.00 1.64 1.49STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 500.00 1.50 1.84 1.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 1,000.00 1.50 1.78 2.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 30,577.00 1.32 1.52 1.27 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 99,869.00 1.64 1.68 1.62

=============== 208-00030 Sediment Basin Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 4.00 100000.00 88234.42 72506.53 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 100000.00 88234.42 72506.53 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 100000.00 88234.42 72506.53

Page 134: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 90 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 208-00033 Sediment Trap Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 5.00 400.00 2860.83 4419.97 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5.00 400.00 2860.83 4419.97

NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 1.00 500.00 1150.00 1500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 500.00 1150.00 1500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6.00 416.67 2753.90 3933.31

=============== 208-00040 Check Dam Each ===================================================

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 9.00 300.00 784.97 490.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 9.00 300.00 784.97 490.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 11.00 750.00 214.49 25.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 11.00 750.00 214.49 25.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 20.00 547.50 471.21 234.25

=============== 208-00045 Conc Washout Str Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 2.00 750.00 948.88 700.00STA 2911-001 SH 291 SALIDA NORTH 01/08/04 1.00 1000.00 1943.31 1400.00NH 5502-045 US550, DURANGO JOINT SEAL 01/08/04 1.00 1000.00 2412.50 3125.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 11.00 750.00 331.02 350.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 10.00 750.00 397.13 140.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 23.00 500.00 383.56 280.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 5.00 800.00 2944.38 5396.26STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 9.00 750.00 443.24 775.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 11.00 750.00 227.51 50.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 30.00 500.00 424.87 150.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 6.00 750.00 445.00 400.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 4.00 1000.00 245.44 153.51

Page 135: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 91 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 208-00045 Conc Washout Str Each ===================================================IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 1500.00 1110.59 600.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 5.00 700.00 378.33 360.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 2.00 1000.00 596.35 420.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 5.00 1000.00 535.34 228.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 2.00 1000.00 1378.86 110.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 4.00 400.00 415.00 300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 132.00 673.11 513.73 495.72

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 2.00 500.00 504.57 375.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 2.00 500.00 517.63 526.66NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 5.00 400.00 329.54 157.50ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 4.00 3000.00 1308.41 1200.00IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 1.00 2000.00 618.45 647.93STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 1.00 1300.00 764.37 350.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 3.00 800.00 619.88 460.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 1.00 500.00 809.40 900.00NH 1602-101 SOUTH FORK JOINT SEAL 05/13/04 1.00 2000.00 1616.67 850.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 1.00 1500.00 1142.00 2200.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 2.00 725.00 787.50 650.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 3.00 700.00 860.27 560.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 2.00 1250.00 613.93 368.40CC R600-225 CHATFIELD STATE PARK 06/10/04 1.00 1000.00 377.50 140.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 2.00 750.00 855.10 430.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 2.00 700.00 593.33 555.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 1.00 500.00 665.00 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 34.00 1063.24 665.68 589.58

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 1.00 1200.00 806.50 626.00IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1.00 1400.00 1467.20 580.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 2.00 1500.00 1390.59 750.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 4.00 720.00 749.14 500.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 3.00 850.00 1224.12 1500.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1.00 750.00 1136.80 600.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 4.00 1200.00 168.33 200.00STA 149A-021 SH 149 CRIBWALL 09/16/04 1.00 2000.00 1550.00 1550.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 3.00 750.00 1857.50 730.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 2.00 800.00 2465.80 800.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 22.00 1019.55 1226.21 724.82

C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 2.00 700.00 900.00 700.00

Page 136: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 92 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 208-00045 Conc Washout Str Each ===================================================C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 1.00 1500.00 1400.00 1500.00BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 1.00 1000.00 965.00 760.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 8.00 600.00 672.09 525.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 5.00 600.00 685.08 550.00C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 12.00 750.00 920.33 650.00MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 6.00 500.00 536.67 610.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 3.00 1000.00 811.68 480.10STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 7.00 700.00 501.39 310.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 5.00 500.00 742.69 438.45STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 9.00 600.00 437.56 481.25STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 5.00 500.00 624.96 1090.00STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 1.00 2000.00 1335.00 1000.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 1.00 1000.00 648.33 1000.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 1.00 1200.00 1367.00 1.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 30.00 500.00 437.53 495.18NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 1.00 750.00 671.45 750.80STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 10.00 600.00 664.10 806.20NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 2.00 450.00 668.75 350.00NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 5.00 500.00 715.27 900.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 115.00 620.43 623.91 595.85 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 303.00 722.05 596.70 560.89

=============== 208-00050 Storm Drain Inlet Protection Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 120.00 200.00 97.95 125.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 39.00 200.00 112.23 140.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 70.00 150.00 136.08 140.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 110.00 150.00 77.46 60.00STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 2.00 200.00 279.33 500.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 20.00 175.00 124.36 130.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 29.00 150.00 98.36 110.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 80.00 250.00 151.71 150.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 17.00 250.00 196.00 200.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 54.00 180.00 88.71 71.64IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 14.00 250.00 165.76 250.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 11.00 150.00 126.49 115.92STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 14.00 100.00 241.28 118.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 5.00 175.00 290.00 300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 585.00 185.38 115.38 121.10

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 34.00 150.00 85.57 32.40

Page 137: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 93 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 208-00050 Storm Drain Inlet Protection Each ===================================================STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 25.00 150.00 134.06 71.58STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 45.00 165.00 127.50 250.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 22.00 170.00 325.00 150.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 8.00 100.00 177.59 300.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 8.00 250.00 196.96 120.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 142.00 160.67 136.01 146.49

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 11.00 500.00 267.66 200.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 27.00 200.00 98.33 100.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 7.00 250.00 166.98 180.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 45.00 281.11 159.59 136.89

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 45.00 200.00 262.79 260.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 14.00 190.00 199.98 180.00MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 10.00 250.00 118.00 179.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 26.00 150.00 176.28 321.65STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 36.00 150.00 195.81 170.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 11.00 150.00 196.91 159.56STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 38.00 200.00 164.05 146.20STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 10.00 250.00 230.09 272.50STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 26.00 150.00 167.91 182.47STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 14.00 150.00 504.26 536.40NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 5.00 250.00 277.22 220.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 235.00 180.68 220.42 229.29 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,007.00 185.07 138.16 150.63

=============== 208-00051 Storm Drain Inlet Protection Lin Foot ===============================================

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 24.00 10.00 108.16 150.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 7.00 40.00 78.74 7.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 31.00 16.77 101.52 117.71

STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 50.00 8.00 11.33 10.00

Page 138: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 94 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 208-00051 Storm Drain Inlet Protection Lin Foot ===============================================NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 240.00 8.00 7.76 20.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 290.00 8.00 8.10 18.28 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 321.00 8.85 16.39 27.88

=============== 208-00055 Rigid Inlet Prot Device Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 9.00 500.00 451.92 500.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 17.00 380.00 355.00 450.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 26.00 421.54 420.83 467.31

NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 14.00 450.00 300.00 350.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 14.00 450.00 300.00 350.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 40.00 431.50 395.58 426.25

=============== 208-00060 Temporary Slope Drain Lin Foot ===============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 1,000.00 20.00 24.92 18.49 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,000.00 20.00 24.92 18.49 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,000.00 20.00 24.92 18.49

=============== 208-00070 Stabilized Construction Entrance Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 1.00 1000.00 1255.35 1100.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 1200.00 950.98 900.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 1.00 1000.00 1022.93 1000.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 2.00 1100.00 1578.88 1000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5.00 1080.00 1274.79 1000.00

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 2.00 1000.00 1200.00 500.00

Page 139: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 95 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 208-00070 Stabilized Construction Entrance Each ===================================================STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 2.00 1000.00 845.70 511.32STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 1.00 1000.00 823.90 400.00IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 1.00 1000.00 971.56 952.20SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 5.00 1000.00 1277.45 1100.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 2.00 1000.00 1066.61 740.00CC R600-225 CHATFIELD STATE PARK 06/10/04 2.00 1000.00 1185.00 1700.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 1.00 1000.00 1056.28 1200.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 5.00 952.00 1037.50 1650.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 21.00 988.57 1076.46 1104.99

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 1.00 1000.00 1023.25 1043.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 2.00 1200.00 1377.66 1250.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 2.00 1000.00 1224.82 1000.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1.00 1100.00 882.04 765.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 6.00 1083.33 1176.77 1051.33

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 5.00 1000.00 1296.40 1450.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 5.00 1000.00 864.23 800.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 1.00 1000.00 1066.67 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 11.00 1000.00 1120.32 1068.18 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 43.00 1015.35 1130.56 1075.88

=============== 208-00100 Sediment Removal and Disposal LUMP SUM ===============================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 1.00 1000.00 1565.66 1800.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 1.00 1500.00 1506.41 1700.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 1.00 1500.00 1904.73 2580.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 1.00 3000.00 4008.57 1500.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 4000.00 3784.34 1100.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1.00 2000.00 3050.78 1500.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1.00 2800.00 6500.00 5000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 7.00 2257.14 2837.05 2168.57

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 1.00 2000.00 1184.33 1533.95

Page 140: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 96 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 208-00100 Sediment Removal and Disposal LUMP SUM ===============================================STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 1.00 5000.00 844.77 834.30STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 1.00 1000.00 1253.52 2500.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 1.00 2900.00 2555.00 2075.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 1.00 2600.00 750.00 1000.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 5000.00 2867.41 4700.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 6.00 3083.33 1670.23 2107.21

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 1.00 4000.00 2953.50 5214.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 3500.00 10649.85 5000.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 1.00 4000.00 5525.80 3000.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 1.00 1600.00 1666.67 1000.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 3000.00 5550.00 1800.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 1.00 1000.00 1939.48 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 6.00 2850.00 4815.85 2752.33

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 1.00 1000.00 1148.00 240.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 3000.00 3498.74 2000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 2000.00 2192.77 1120.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 21.00 2638.10 2840.59 2217.96

=============== 208-00110 Sediment Removal and Disposal Cubic Yard =============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 700.00 8.50 16.43 10.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 700.00 8.50 16.43 10.50

STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 200.00 16.00 22.55 17.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 200.00 16.00 22.55 17.20 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 900.00 10.17 17.41 11.99

=============== 208-00200 Erosion Control Supervisor LUMP SUM ===============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 1.00 60000.00 11866.32 21497.92

Page 141: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 97 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 208-00200 Erosion Control Supervisor LUMP SUM ===============================================IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 5000.00 4524.61 7000.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 1.00 3000.00 3250.00 2000.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 1.00 4500.00 3216.67 3300.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1.00 3000.00 4541.08 3200.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1.00 4000.00 8200.00 8200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 6.00 13250.00 5693.40 7532.99

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 1.00 3500.00 1454.67 700.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 1.00 2500.00 2538.86 2924.73NH 0502-053 CIMARRON - WEST 04/15/04 1.00 10000.00 3294.42 4500.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 1.00 80000.00 97464.38 94062.00IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 1.00 5000.00 4332.57 3508.01SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 1.00 4000.00 5068.47 3400.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 1.00 3800.00 5110.80 1850.00STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 1.00 4250.00 3333.33 1000.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 1.00 9000.00 3500.00 5000.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 4000.00 4817.36 7200.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 1.00 3500.00 3125.00 2000.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 1.00 2500.00 3671.00 2600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 12.00 11004.17 8237.28 10728.73

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 1.00 7500.00 8028.57 5000.00STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 1.00 3000.00 3042.75 4171.00IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1.00 9000.00 8089.76 9400.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 4000.00 7269.16 7130.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 1.00 5000.00 4825.29 3000.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 6000.00 6526.79 4500.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 1.00 1500.00 1666.67 1000.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 5000.00 9450.00 5800.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 1.00 1000.00 3500.12 1000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 9.00 4666.67 6247.41 4555.67

C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 1.00 1000.00 472.50 450.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 1.00 4500.00 2460.00 900.00BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 1.00 3500.00 3005.38 3600.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1.00 6000.00 7028.28 3100.00

Page 142: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 98 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 208-00200 Erosion Control Supervisor LUMP SUM ===============================================BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 6000.00 6584.92 7500.00C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 1.00 1000.00 2146.27 3500.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 1.00 2000.00 2305.09 3330.35 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 7.00 3428.57 3698.50 3197.19 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 34.00 8163.24 6345.25 6980.12

=============== 208-00205 Erosion Control Supervisor Hour ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 40.00 60.00 63.01 75.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 139.00 60.00 170.29 50.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 70.00 50.00 57.68 39.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 110.00 60.00 55.36 58.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 33.00 50.00 63.61 77.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 48.00 50.00 57.19 76.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 180.00 60.00 160.99 40.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 120.00 55.00 47.75 35.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 100.00 55.00 53.95 41.12STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 100.00 60.00 52.40 50.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 50.00 55.00 50.88 63.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 990.00 57.11 100.39 49.41

NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 80.00 50.00 81.97 68.25STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 80.00 40.00 1901.50 46.00AQC R600-215 SH 287, US 36 TO SH 128 05/27/04 100.00 40.00 61.53 35.29CC R600-225 CHATFIELD STATE PARK 06/10/04 40.00 50.00 47.25 51.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 200.00 60.00 48.53 44.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 500.00 50.40 248.65 47.02

MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 50.00 50.00 48.33 45.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 75.00 60.00 67.93 97.55STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 20.00 60.00 76.87 70.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 50.00 60.00 78.49 89.46STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 60.00 50.00 67.20 97.80STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 75.00 60.00 57.20 54.50STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 86.00 60.00 65.48 100.64STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 41.00 60.00 87.07 88.15

Page 143: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 99 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 208-00205 Erosion Control Supervisor Hour ===================================================NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 80.00 60.00 57.92 44.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 537.00 57.95 65.62 76.69 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,027.00 55.68 127.96 56.05

=============== 208-00300 Temporary Berms Lin Foot ===============================================

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 4,755.00 0.65 1.88 1.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4,755.00 0.65 1.88 1.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4,755.00 0.65 1.88 1.00

=============== 209-00000 Water M Gallon ===============================================

NH 2872-016 US 287 - LAMAR 03/04/04 80.00 55.00 36.25 40.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 80.00 55.00 36.25 40.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 80.00 55.00 36.25 40.00

=============== 209-00100 Water (Landscaping) M Gallon ===============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 15.00 50.00 208.18 284.52 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 15.00 50.00 208.18 284.52 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 15.00 50.00 208.18 284.52

=============== 209-00200 Time-Released Water Product Each ===================================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 400.00 5.00 4.73 4.65 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 400.00 5.00 4.73 4.65 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 400.00 5.00 4.73 4.65

=============== 209-00600 Dust Palliative (Mg Cl) Gallon =================================================

STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 1,327.00 1.00 1.90 2.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,327.00 1.00 1.90 2.50

Page 144: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 100 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 209-00600 Dust Palliative (Mg Cl) Gallon =================================================

NH 0502-053 CIMARRON - WEST 04/15/04 18,000.00 0.55 0.54 0.50STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 15,000.00 0.65 0.99 0.64 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 33,000.00 0.60 0.74 0.56

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 31,294.00 0.60 0.47 0.50NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 13,200.00 0.90 1.44 0.55 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 44,494.00 0.69 0.66 0.51 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 78,821.00 0.66 0.70 0.57

=============== 210-00001 Res Structure Each ===================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 3.00 200.00 357.73 410.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 2.00 1200.00 622.33 550.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5.00 600.00 433.33 466.00

STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 6.00 400.00 2108.37 1200.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 4.00 437.50 1329.11 918.75STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 1.00 1200.00 1756.67 350.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 2.00 500.00 2718.15 1600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 13.00 488.46 1987.29 1109.62 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 18.00 519.44 1438.83 930.83

=============== 210-00010 Res Mailbox Str Each ===================================================

STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 3.00 250.00 221.90 215.38STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1.00 220.00 150.00 150.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 242.50 214.71 199.04

Page 145: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 101 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 210-00010 Res Mailbox Str Each ===================================================

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 6.00 200.00 131.42 49.00STA 0343-023 US 34, EAST OF AKRON 06/17/04 1.00 200.00 289.20 215.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 7.00 200.00 150.66 72.71

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 4.00 370.00 197.75 261.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4.00 370.00 197.75 261.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 15.00 256.67 177.08 156.61

=============== 210-00011 Res Mailbox Str (Ty 1) Each ===================================================

STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 4.00 200.00 213.60 103.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 5.00 150.00 222.16 280.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 19.00 200.00 185.66 89.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 28.00 191.07 194.70 125.45

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 8.00 150.00 160.00 126.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 8.00 150.00 151.84 156.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 12.00 235.00 142.25 133.00STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 11.00 200.00 106.67 105.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 3.00 210.00 95.21 78.90BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 1.00 150.00 122.86 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 43.00 190.70 138.18 124.27

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 9.00 170.00 161.63 287.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 13.00 150.00 177.75 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 22.00 158.18 171.15 176.50

STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 1.00 280.00 320.98 260.00

Page 146: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 102 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 210-00011 Res Mailbox Str (Ty 1) Each ===================================================NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 21.00 100.00 124.67 140.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 16.00 200.00 160.89 83.55 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 38.00 146.84 149.66 119.39 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 131.00 172.60 162.99 131.88

=============== 210-00012 Res Mailbox Str (Ty 2) Each ===================================================

STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 3.00 300.00 228.78 140.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3.00 300.00 228.78 140.00

SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 5.00 250.00 144.08 168.00STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 2.00 300.00 148.33 145.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 7.00 264.29 144.90 161.43

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 2.00 200.00 195.25 150.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 200.00 195.25 150.00

NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 8.00 230.00 171.67 200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 8.00 230.00 171.67 200.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 20.00 249.50 178.31 172.50

=============== 210-00013 Res Mailbox Str (Ty 3) Each ===================================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 5.00 250.00 413.50 440.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 25.00 300.00 375.20 400.00STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 2.00 260.00 350.00 500.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 1.00 350.00 388.80 430.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 2.00 400.00 320.42 200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 35.00 297.71 375.08 400.86

Page 147: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 103 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 210-00013 Res Mailbox Str (Ty 3) Each ===================================================

STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 1.00 350.00 230.00 225.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 3.00 320.00 203.92 205.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4.00 327.50 209.13 210.15

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 13.00 300.00 237.50 230.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 13.00 300.00 237.50 230.00

NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 11.00 300.00 301.65 320.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 1.00 300.00 291.60 211.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 12.00 300.00 300.56 310.95 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 64.00 300.47 329.66 337.38

=============== 210-00014 Res Mailbox Str (Ty 4) Each ===================================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 3.00 275.00 523.25 590.00STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 5.00 320.00 500.00 700.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 8.00 303.13 512.68 658.75

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 13.00 500.00 281.00 380.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 13.00 500.00 281.00 380.00

NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 16.00 600.00 350.08 380.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 16.00 600.00 350.08 380.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 37.00 500.68 349.96 440.27

Page 148: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 104 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 210-00015 Res End Section Each ===================================================

STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 1.00 400.00 543.00 200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 400.00 543.00 200.00

C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 1.00 1600.00 300.00 400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 1600.00 300.00 400.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 1000.00 473.57 300.00

=============== 210-00030 Res Water Service Each ===================================================

SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 1.00 400.00 2100.00 800.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 400.00 2100.00 800.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 400.00 2100.00 800.00

=============== 210-00035 Res Water Meter Each ===================================================

STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 9.00 1100.00 948.17 600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 9.00 1100.00 948.17 600.00

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 2.00 1500.00 624.81 511.32 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 1500.00 624.81 511.32

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1.00 1000.00 1826.19 2700.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 1000.00 1826.19 2700.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 12.00 1158.33 941.09 760.22

Page 149: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 105 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 210-00050 Res Fire Hydrant Each ===================================================

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 2.00 2000.00 1270.51 613.58STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 3.00 2000.00 2502.66 1500.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 1500.00 2201.03 1100.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 1.00 2180.00 2425.00 1000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 7.00 1954.29 2006.76 1118.17

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1.00 2000.00 4084.71 3400.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 2.00 3300.00 2550.11 3400.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 3.00 2000.00 1883.33 2500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 6.00 2433.33 2689.53 2950.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 13.00 2175.38 2224.87 1963.63

=============== 210-00060 Res Marker Each ===================================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 6.00 100.00 113.59 130.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 6.00 100.00 113.59 130.00

SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 2.00 80.00 50.00 25.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 80.00 50.00 25.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8.00 95.00 104.51 103.75

=============== 210-00065 Res Monument (Ty 3A) Each ===================================================

NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 1.00 420.00 469.98 560.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 420.00 469.98 560.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 420.00 469.98 560.00

=============== 210-00090 Res Delineator Each ===================================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 747.00 20.00 43.25 95.00

Page 150: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 106 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 210-00090 Res Delineator Each ===================================================IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 50.00 15.00 17.92 23.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 797.00 19.69 41.66 90.53

SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 160.00 20.00 20.33 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 160.00 20.00 20.33 10.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 957.00 19.74 38.09 77.07

=============== 210-00200 Reset Flagpole Each ===================================================

STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 1.00 500.00 533.33 300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 500.00 533.33 300.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 500.00 533.33 300.00

=============== 210-00400 Res Expan Device Lin Foot ===============================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 524.10 100.00 62.08 57.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 524.10 100.00 62.08 57.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 524.10 100.00 62.08 57.00

=============== 210-00410 Modify Bridge Expan Device Each ===================================================

STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 2.00 250.00 10524.47 11502.05 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 250.00 10524.47 11502.05 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 250.00 10524.47 11502.05

=============== 210-00425 Res Bridge Railing Lin Foot ===============================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 125.00 50.00 16.16 12.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 125.00 50.00 16.16 12.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 125.00 50.00 16.16 12.50

Page 151: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 107 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 210-00440 Repair Curb Lin Foot ===============================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 30.00 10.00 79.00 46.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 30.00 10.00 79.00 46.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 30.00 10.00 79.00 46.00

=============== 210-00473 Res TV Cameras Each ===================================================

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 4.00 750.00 278.33 184.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4.00 750.00 278.33 184.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 750.00 278.33 184.00

=============== 210-00750 Res Light Standard Each ===================================================

IM 0701-157 FRUITA TO CLIFTON 02/26/04 8.00 1200.00 406.50 325.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 8.00 1200.00 406.50 325.00

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 1000.00 1507.49 2000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 1000.00 1507.49 2000.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 5.00 2000.00 1923.86 2000.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 600.00 1711.12 750.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 6.00 1766.67 1898.83 1791.67 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 15.00 1413.33 1058.15 1023.33

=============== 210-00760 Res Luminaire Each ===================================================

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 500.00 243.34 41.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 500.00 243.34 41.00

Page 152: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 108 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 210-00760 Res Luminaire Each ===================================================

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 2.00 300.00 492.34 220.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 300.00 492.34 220.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 366.67 367.84 160.33

=============== 210-00805 Res Overhead Sign Str Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 2.00 6000.00 4339.19 4000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 6000.00 4339.19 4000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 6000.00 4339.19 4000.00

=============== 210-00810 Res Ground Sign Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 27.00 100.00 157.04 89.26STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 18.00 150.00 130.00 100.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 16.00 175.00 147.67 200.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 48.00 140.00 92.05 51.28STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 11.00 150.00 138.75 150.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 26.00 50.00 105.48 76.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 5.00 150.00 116.20 65.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 4.00 150.00 90.00 80.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 10.00 150.00 107.87 105.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 10.00 160.00 95.00 114.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 175.00 127.54 118.31 93.33

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 1.00 150.00 140.00 92.04SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 6.00 150.00 87.50 88.00NH 0502-053 CIMARRON - WEST 04/15/04 2.00 150.00 186.68 210.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 1.00 169.00 83.20 78.00STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 1.00 175.00 166.67 220.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 207.00 60.00 106.51 85.00STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 42.00 100.00 119.04 150.00IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 42.00 85.00 148.33 130.00

Page 153: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 109 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 210-00810 Res Ground Sign Each ===================================================SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 32.00 80.00 114.91 128.00STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 9.00 170.00 126.67 125.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 10.00 150.00 182.73 260.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 1.00 132.00 110.24 104.20SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 40.00 135.00 91.25 100.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 1.00 100.00 176.67 265.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 5.00 100.00 98.00 25.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 400.00 84.02 115.36 107.52

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 3.00 130.00 197.94 381.00BR 0243-063 EAST OF LIMON 07/15/04 3.00 170.00 135.46 110.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 4.00 200.00 175.65 250.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 2.00 130.00 162.57 240.75C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 26.00 100.00 186.60 250.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 48.00 140.00 106.00 131.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 18.00 132.00 192.63 160.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 104.00 131.31 150.59 179.06

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 6.00 70.00 152.79 55.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 8.00 180.00 163.24 185.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 4.00 950.00 188.33 150.00STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 3.00 100.00 154.39 180.55IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 1.00 150.00 298.33 170.00NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 20.00 100.00 109.92 83.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 42.00 193.10 134.52 113.85 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 721.00 107.76 122.47 114.76

=============== 210-00815 Res Sign Panel Each ===================================================

STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 2.00 60.00 78.96 42.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 3.00 60.00 116.36 78.00C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 1.00 150.00 145.33 144.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 4.00 400.00 411.26 600.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 2.00 155.00 215.67 110.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 4.00 50.00 115.52 80.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 2.00 140.00 66.32 15.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 18.00 157.78 196.71 190.72

Page 154: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 110 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 210-00815 Res Sign Panel Each ===================================================

C R200-126 FY04 REGION 2 SIGNING 04/01/04 6.00 80.00 833.85 514.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 1.00 119.00 139.52 104.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 7.00 85.57 682.91 455.43

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 140.00 282.00 400.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 7.00 200.00 35.23 70.62 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 8.00 192.50 60.54 111.79

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 5.00 75.00 60.97 11.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 13.00 75.00 70.04 58.76STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 18.00 100.00 18.55 17.20STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 1.00 100.00 120.55 16.35NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 1.00 200.00 94.91 9.65STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 1.00 200.00 42.31 134.35 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 39.00 93.59 49.63 33.05 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 72.00 119.85 139.14 122.28

=============== 210-00820 Res Var Mesg Sign Each ===================================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1.00 4500.00 2736.36 2500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 4500.00 2736.36 2500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 4500.00 2736.36 2500.00

=============== 210-00825 Res Flashing Beacon Each ===================================================

STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 1.00 1100.00 1708.00 2200.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 2.00 1200.00 649.04 610.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 3.00 1025.00 1020.00 940.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 6.00 1095.83 976.02 1040.00

Page 155: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 111 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 210-00825 Res Flashing Beacon Each ===================================================

NH 0502-053 CIMARRON - WEST 04/15/04 1.00 1200.00 2078.70 2000.00STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 1.00 1000.00 1271.93 1200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 1100.00 1565.30 1600.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8.00 1096.88 1166.67 1180.00

=============== 210-00830 Res Traf Sig Face Each ===================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 2.00 400.00 223.75 265.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 400.00 223.75 265.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 400.00 223.75 265.00

=============== 210-00831 Res Traf Sig Head Each ===================================================

STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 2.00 250.00 420.21 410.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 250.00 420.21 410.25

SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 4.00 110.00 333.75 415.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4.00 110.00 333.75 415.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6.00 156.67 370.80 413.42

=============== 210-00840 Res Traf Sig Pole Each ===================================================

STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 4.00 1000.00 1611.50 1641.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 1000.00 1611.50 1641.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 1000.00 1611.50 1641.00

=============== 210-00848 Res Traf Sig Control+Cab Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 1400.00 1374.53 1200.00

Page 156: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 112 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 210-00848 Res Traf Sig Control+Cab Each ===================================================STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 2.00 2500.00 1531.88 1050.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3.00 2133.33 1461.94 1100.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 2.00 1500.00 1049.65 1000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 1500.00 1049.65 1000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5.00 1880.00 1297.03 1060.00

=============== 210-00855 Res Traf Sig Control Cab Each ===================================================

IM 0253-186 I-25, 120TH TO SH 7 06/17/04 2.00 1500.00 1364.94 1240.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 1.00 1500.00 1062.50 1250.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3.00 1500.00 1264.13 1243.33 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 1500.00 1264.13 1243.33

=============== 210-00858 Res Pedestal Pole Each ===================================================

IM 0701-157 FRUITA TO CLIFTON 02/26/04 2.00 1000.00 1251.67 1300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 1000.00 1251.67 1300.00

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 1000.00 483.52 449.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 1000.00 483.52 449.40 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 1000.00 1025.74 1016.47

=============== 210-00860 Res Ped Push Button Each ===================================================

NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 6.00 100.00 82.74 57.90SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 1.00 100.00 130.00 185.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 7.00 100.00 89.49 76.06 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 7.00 100.00 89.49 76.06

Page 157: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 113 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 210-00865 Res Ped Sig Head Each ===================================================

SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 1.00 400.00 226.25 250.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 400.00 226.25 250.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 400.00 226.25 250.00

=============== 210-00866 Res Fire Preempt Unit+Timer Each ===================================================

STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 2.00 400.00 492.29 328.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 400.00 492.29 328.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 400.00 492.29 328.00

=============== 210-00867 Res Fire Preempt Unit Each ===================================================

C 074A-007 SH 74 @ BRYANT DR. 02/26/04 1.00 700.00 324.37 500.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1.00 600.00 249.72 105.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 650.00 287.05 302.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 650.00 287.05 302.50

=============== 210-00870 Res Coordination Unit Each ===================================================

STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 2.00 400.00 292.07 384.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 400.00 292.07 384.00

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 1.00 550.00 589.04 600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 550.00 589.04 600.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 450.00 360.60 456.00

=============== 210-00873 Res Tone Decoder Each ===================================================

STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 3.00 500.00 217.04 40.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3.00 500.00 217.04 40.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 500.00 217.04 40.00

Page 158: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 114 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 210-00882 Res Detector Each ===================================================

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 500.00 511.91 513.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 500.00 511.91 513.60 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 500.00 511.91 513.60

=============== 210-00890 Res Int Detect Sys (Camera) Each ===================================================

STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1.00 500.00 480.23 175.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 500.00 480.23 175.00

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 2.00 8000.00 1406.19 1750.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 8000.00 1406.19 1750.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 5500.00 907.59 1225.00

=============== 210-01000 Res Fence Lin Foot ===============================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 7,578.00 4.80 2.20 2.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 7,578.00 4.80 2.20 2.20

STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 120.00 6.00 14.42 9.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 100.00 5.00 3.86 3.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 123.00 460.00 14.75 14.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 343.00 168.51 12.08 9.04 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 7,921.00 11.89 3.21 2.50

=============== 210-01011 Res Gate Each ===================================================

STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1.00 200.00 518.31 180.00

Page 159: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 115 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 210-01011 Res Gate Each ===================================================STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1.00 150.00 315.00 320.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 175.00 473.13 250.00

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 6.00 150.00 234.29 120.00STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 1.00 200.00 393.75 215.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 7.00 157.14 248.15 133.57 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 9.00 161.11 284.97 159.44

=============== 210-01050 Res C L Fence Lin Foot ===============================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 4,325.00 8.00 5.99 5.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4,325.00 8.00 5.99 5.75 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4,325.00 8.00 5.99 5.75

=============== 210-01130 Res Gdrail Ty 3 Lin Foot ===============================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 8,059.00 4.00 10.02 9.70IM 0701-164 PARACHUTE EAST & WEST 02/12/04 1,695.00 18.00 10.50 13.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 103.50 5.50 11.30 13.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 425.00 7.50 14.36 18.75STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 530.00 9.00 17.77 16.60STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 225.00 7.00 10.40 9.40STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 2,188.00 7.00 8.33 9.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 13,225.50 6.67 10.32 10.68

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 8,727.00 3.00 4.31 4.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 226.00 7.00 9.41 10.30STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 225.00 13.00 19.77 24.78NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1,121.00 9.00 7.79 7.50NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 500.00 7.00 16.68 17.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 550.00 8.00 19.33 17.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 175.00 10.00 13.94 14.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 11,524.00 4.38 5.80 6.22

Page 160: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 116 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 210-01130 Res Gdrail Ty 3 Lin Foot ===============================================

C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 977.00 8.00 6.64 5.35STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 85.00 15.00 113.00 60.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 1,300.00 10.00 11.62 5.30NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 838.00 4.25 9.46 9.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3,200.00 8.02 11.57 7.79 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 27,949.50 5.88 8.35 8.51

=============== 210-01140 Res Gdrail Ty 4 Lin Foot ===============================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 20.00 25.00 51.62 90.00STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 300.00 10.00 10.05 17.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 320.00 10.94 11.81 21.56

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1,126.00 6.00 4.63 7.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,126.00 6.00 4.63 7.00

ER 0702-255 I-70 GLENWOOD CANYON 11/30/04 1,000.00 30.00 8.67 2.50STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 30.00 12.00 14.49 53.60IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 2,640.00 10.00 13.90 8.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 1,250.00 5.00 11.39 12.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4,920.00 12.81 12.05 8.30 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6,366.00 11.51 10.70 8.74

=============== 210-01200 Res End Anchorage Each ===================================================

STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 1.00 600.00 611.00 605.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 9.00 600.00 476.61 385.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 10.00 600.00 486.50 407.00

Page 161: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 117 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 210-01200 Res End Anchorage Each ===================================================

STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 1.00 4000.00 4968.33 3605.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 1.00 1400.00 2779.02 978.03NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 2.00 500.00 506.99 360.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 2.00 500.00 551.71 485.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 6.00 1233.33 1157.81 1045.51

NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 3.00 750.00 1220.83 1300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3.00 750.00 1220.83 1300.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 19.00 823.68 780.56 749.63

=============== 210-01700 Res Sprinkler Head Each ===================================================

STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 7.00 100.00 60.01 52.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 7.00 100.00 60.01 52.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 7.00 100.00 60.01 52.00

=============== 210-02900 Relay Riprap Cubic Yard =============================================

STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 12.00 30.00 53.15 27.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 12.00 30.00 53.15 27.50

CC R600-225 CHATFIELD STATE PARK 06/10/04 665.00 60.00 43.25 50.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 665.00 60.00 43.25 50.00

C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 140.00 10.00 39.30 12.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 140.00 10.00 39.30 12.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 817.00 50.99 42.69 43.16

Page 162: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 118 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 210-03100 Replace Conc Pvmt Sq Yard ================================================

NH 2873-137 US 287 IN BOULDER & LARIMER C 11/18/04 2,500.00 90.00 108.10 87.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2,500.00 90.00 108.10 87.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,500.00 90.00 108.10 87.50

=============== 210-04000 Adj Structure Each ===================================================

IM 0701-157 FRUITA TO CLIFTON 02/26/04 1.00 1000.00 720.83 535.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 1000.00 720.83 535.00

STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 14.00 800.00 215.99 155.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 14.00 800.00 215.99 155.00

STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 1.00 1000.00 2833.63 2100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 1000.00 2833.63 2100.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 16.00 825.00 363.85 300.31

=============== 210-04010 Adj Manhole Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 22.00 300.00 453.25 340.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 38.00 300.00 297.56 295.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 8.00 275.00 360.35 385.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 158.00 275.00 302.79 250.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 9.00 400.00 305.94 150.00STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 6.00 450.00 416.00 500.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 54.00 300.00 290.01 310.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 24.00 300.00 313.24 340.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 138.00 250.00 265.27 260.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 36.00 300.00 712.50 400.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 6.00 350.00 312.00 295.96STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 15.00 300.00 314.62 307.69

Page 163: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 119 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 210-04010 Adj Manhole Each ===================================================STA 014A-030 SH 14, WALDEN EAST 03/04/04 5.00 350.00 564.58 500.00NH 2872-016 US 287 - LAMAR 03/04/04 15.00 350.00 546.50 386.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 14.00 300.00 441.67 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 548.00 285.49 320.18 296.50

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 4.00 400.00 416.98 295.78NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 141.00 200.00 289.71 150.00STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 80.00 450.00 455.00 460.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 5.00 500.00 435.69 380.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 17.00 450.00 550.00 460.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 33.00 400.00 275.00 300.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 2.00 300.00 302.95 300.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 5.00 350.00 1171.25 385.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 287.00 318.82 362.47 283.20

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 21.00 350.00 461.38 600.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 300.00 2332.50 2000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 22.00 347.73 530.04 663.64

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 7.00 300.00 515.40 400.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 425.00 360.93 450.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 54.00 300.00 328.98 320.90STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 120.00 275.00 328.45 280.00STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 18.00 300.00 298.66 321.65STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 98.00 300.00 352.57 385.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 1.00 300.00 740.00 1200.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 60.00 300.00 275.16 330.98NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 8.00 300.00 344.68 333.70STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 54.00 300.00 319.11 285.85NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 12.00 250.00 400.38 330.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 433.00 291.97 330.74 325.23 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,290.00 296.14 331.97 309.44

=============== 210-04015 Modify Manhole Each ===================================================

STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 1.00 900.00 1117.83 750.00

Page 164: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 120 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 210-04015 Modify Manhole Each ===================================================STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 1.00 900.00 1614.03 2769.19 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 900.00 1365.93 1759.60

NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 1.00 1300.00 2250.00 1500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 1300.00 2250.00 1500.00

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 1200.00 1666.23 1900.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 7.00 825.00 2463.75 980.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 8.00 871.88 2364.06 1095.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1.00 1000.00 2015.28 1600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 1000.00 2015.28 1600.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 12.00 922.92 2089.09 1281.60

=============== 210-04020 Modify Inlet Each ===================================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 12.00 1500.00 839.67 520.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 4.00 1325.00 1283.89 2000.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 11.00 650.00 1850.98 1435.87NH 2872-016 US 287 - LAMAR 03/04/04 12.00 1200.00 5434.50 6038.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 39.00 1150.00 2393.86 2627.96

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 4.00 1500.00 1338.33 925.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 1.00 1350.00 2493.75 1875.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 5.00 1470.00 1503.39 1115.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 5.00 1500.00 2055.88 2500.00

Page 165: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 121 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 210-04020 Modify Inlet Each ===================================================IMD 0252-364 I-25 OVER BROADWAY 07/29/04 6.00 1500.00 2009.05 1900.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 4.00 3000.00 2950.00 3500.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 1500.00 2896.75 2300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 16.00 1875.00 2241.15 2512.50

STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 3.00 2000.00 1433.33 1800.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 7.00 1400.00 1983.33 1500.00NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 1.00 3100.00 1835.00 1500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 11.00 1718.18 1821.11 1581.82 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 71.00 1423.94 2222.39 2333.32

=============== 210-04025 Modify Structure Each ===================================================

SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 1.00 400.00 3600.00 1700.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 400.00 3600.00 1700.00

MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 56.00 400.00 287.33 592.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 56.00 400.00 287.33 592.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 57.00 400.00 364.37 611.44

=============== 210-04030 Modify Guardrail Lin Foot ===============================================

IM 0701-157 FRUITA TO CLIFTON 02/26/04 1,600.00 8.00 10.05 9.80STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 784.00 11.00 25.23 26.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,384.00 8.99 15.57 15.29 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,384.00 8.99 15.57 15.29

=============== 210-04050 Adj Valve Box Each ===================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 109.00 160.00 145.36 220.00

Page 166: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 122 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 210-04050 Adj Valve Box Each ===================================================STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 58.00 150.00 161.95 140.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 76.00 150.00 166.86 165.00STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 12.00 200.00 211.83 300.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 56.00 120.00 178.26 155.00C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 2.00 200.00 276.17 184.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 52.00 150.00 160.77 220.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 80.00 200.00 170.76 155.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 54.00 150.00 272.50 200.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 16.00 175.00 151.72 158.73STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 4.00 200.00 204.19 205.12STA 014A-030 SH 14, WALDEN EAST 03/04/04 4.00 200.00 289.06 250.00NH 2872-016 US 287 - LAMAR 03/04/04 21.00 170.00 296.25 255.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 4.00 150.00 129.00 198.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 26.00 300.00 325.00 375.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 574.00 166.08 174.57 195.44

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 4.00 200.00 172.62 158.61NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 77.00 190.00 182.28 85.00STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 65.00 420.00 405.00 385.00NH 0741-015 - SMA Alt SH 74 EVERGREEN OVERLAY 04/29/04 21.00 200.00 161.70 160.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 2.00 200.00 228.11 170.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 8.00 400.00 214.75 134.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 52.00 300.00 137.50 150.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 6.00 100.00 264.18 230.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 7.00 170.00 310.00 150.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 242.00 280.66 223.34 195.07

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 3.00 300.00 194.84 180.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 9.00 160.00 274.22 200.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1.00 200.00 258.32 180.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 13.00 195.38 252.04 193.85

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 6.00 200.00 247.87 250.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 19.00 180.00 223.33 150.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 66.00 160.00 128.13 119.80STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 52.00 200.00 145.83 170.00

Page 167: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 123 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 210-04050 Adj Valve Box Each ===================================================STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 12.00 150.00 144.28 172.10STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 4.00 190.00 213.55 180.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 9.00 300.00 390.00 700.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 54.00 160.00 130.93 123.57NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 2.00 200.00 199.58 188.30STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 46.00 160.00 188.41 140.15NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 52.00 125.00 223.32 220.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 322.00 166.89 168.36 171.17 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,151.00 190.73 179.17 188.56

=============== 210-04200 Adj Gdrail Lin Foot ===============================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 33,214.00 2.50 5.53 5.35IM 0701-164 PARACHUTE EAST & WEST 02/12/04 2,625.00 2.00 5.42 10.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 28,413.00 2.50 2.28 2.55STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 2,112.00 4.00 2.27 1.55STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 31,718.00 3.00 2.28 2.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 98,082.00 2.68 3.19 3.60

NH 0741-015 - SMA Alt SH 74 EVERGREEN OVERLAY 04/29/04 398.00 5.00 6.87 13.80SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 188.00 5.00 4.11 4.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 1,000.00 3.00 2.91 2.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,586.00 3.74 3.86 5.64

NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 7,689.00 3.00 5.07 4.70IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 12,906.00 3.00 4.08 4.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 20,595.00 3.00 4.45 4.26 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 120,263.00 2.75 3.33 3.74

=============== 211-00100 Drilling Hole Lin Foot ===============================================

BR 0362-028 BRIDGE OVER KIOWA CREEK 05/13/04 1,248.00 15.00 13.00 13.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,248.00 15.00 13.00 13.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,248.00 15.00 13.00 13.00

Page 168: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 124 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 211-01111 Rock Reinf (Dowels) Lin Foot ===============================================

STA 1191-020 SH 119 ROCKFALL MITIGATION, 2 04/15/04 1,450.00 45.00 47.83 19.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,450.00 45.00 47.83 19.50

STA 149A-021 SH 149 CRIBWALL 09/16/04 550.00 48.00 60.00 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 550.00 48.00 60.00 60.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,000.00 45.83 49.20 30.64

=============== 211-01200 Rock Anchor Lin Foot ===============================================

STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 600.00 48.00 111.25 42.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 600.00 48.00 111.25 42.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 600.00 48.00 111.25 42.00

=============== 211-02116 Rock Dowel Lin Foot ===============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 5,250.00 35.00 22.53 36.82 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5,250.00 35.00 22.53 36.82

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1,320.00 25.00 31.23 33.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,320.00 25.00 31.23 33.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6,570.00 32.99 24.04 36.05

=============== 211-02270 Cement Grout Cubic Foot =============================================

BR 0362-028 BRIDGE OVER KIOWA CREEK 05/13/04 2,000.00 15.00 10.00 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2,000.00 15.00 10.00 10.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,000.00 15.00 10.00 10.00

Page 169: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 125 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 212-00006 Seeding (Native) Acre ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 0.18 1000.00 2375.81 1800.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 0.01 2000.00 23932.30 28000.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 0.10 1000.00 3970.91 4675.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 30.73 800.00 410.62 329.15STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 14.60 450.00 359.00 300.00C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 0.30 50.00 1079.83 1092.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 0.05 3000.00 4304.41 5000.00STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 0.90 800.00 575.00 550.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 34.00 500.00 424.55 280.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 5.25 400.00 356.00 500.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 2.00 450.00 363.50 400.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 2.00 500.00 523.41 733.47STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 16.00 350.00 370.00 200.00NH 2872-016 US 287 - LAMAR 03/04/04 11.00 400.00 307.50 295.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 3.00 500.00 406.92 290.00SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 13.00 400.00 271.67 245.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 0.36 1000.00 2571.07 2395.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 0.75 1200.00 850.00 700.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 15.00 500.00 420.31 470.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 78.00 440.00 277.50 305.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 227.23 497.84 393.03 324.73

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 9.00 500.00 327.00 280.00NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 2.50 600.00 348.00 505.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 2.40 800.00 782.91 552.23NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 0.70 1000.00 1049.85 803.25NH 0502-053 CIMARRON - WEST 04/15/04 20.70 630.00 374.88 320.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 20.00 325.00 387.50 400.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 1.50 600.00 514.40 307.00STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 1.40 1000.00 523.33 1000.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 46.50 400.00 588.68 624.24IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 3.00 700.00 432.02 414.91STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 1.00 700.00 1000.79 1230.50IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 1.50 700.00 1573.33 935.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 6.00 500.00 285.99 275.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 5.00 600.00 455.62 342.10STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 16.00 900.00 298.00 297.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 7.00 300.00 455.25 460.00STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 2.00 1000.00 1074.00 888.00BR 0092-018 SH 9, SOUTH OF KREMMLING 05/27/04 1.50 750.00 1319.25 1045.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 22.90 400.00 282.54 210.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 0.40 500.00 784.61 763.90

Page 170: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 126 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 212-00006 Seeding (Native) Acre ===================================================CC R600-225 CHATFIELD STATE PARK 06/10/04 2.50 500.00 475.00 580.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 0.60 750.00 908.29 820.00IM 0702-239 HANGING LAKES REST AREAS 06/17/04 1.00 1500.00 3399.20 1675.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 1.30 700.00 691.67 705.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 2.50 550.00 425.93 346.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 178.90 521.97 454.88 448.57

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 30.80 525.00 272.21 220.00STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 10.00 390.00 389.69 391.00IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 252.00 325.00 348.99 350.00SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 0.30 1000.00 1320.00 1350.00SHE 0091-023 SH 9 VMS - FAIRPLAY TO FRISCO 07/15/04 0.20 2200.00 4921.65 4400.00BR 0243-063 EAST OF LIMON 07/15/04 1.50 600.00 710.36 500.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 650.00 612.46 330.00STA R200-128 SH10, SH350 , SH160 MAINT. 07/29/04 11.45 600.00 391.67 500.00SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 0.10 2000.00 3687.50 1575.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 42.00 350.00 325.66 325.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 4.00 900.00 1878.90 2140.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 2.00 500.00 469.70 475.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 19.40 500.00 440.00 420.00STA 149A-021 SH 149 CRIBWALL 09/16/04 1.00 700.00 900.00 900.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 13.50 450.00 363.75 385.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 12.00 500.00 731.81 700.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 401.25 381.57 371.97 381.16

SHE 105A-010 SH 105/FURROW RD 10/07/04 1.74 1000.00 801.29 800.00C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 1.00 650.00 2855.00 3800.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 2.00 1400.00 960.00 600.00BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 4.00 500.00 406.45 400.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 10.25 800.00 409.16 390.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 2.48 600.00 572.86 560.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 0.10 2500.00 1935.70 893.50IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 1.00 1500.00 840.00 1000.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 0.75 1000.00 888.45 528.80NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 0.80 1200.00 785.71 977.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 24.12 843.20 561.65 648.68 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 831.50 456.94 399.16 388.00

=============== 212-00010 Seeding (Lawn) Pound ==================================================

NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 3.20 37.00 200.00 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3.20 37.00 200.00 100.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.20 37.00 200.00 100.00

Page 171: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 127 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 212-00011 Seeding (Lawn) Acre ===================================================

SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 0.01 15000.00 14750.00 9000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 0.01 15000.00 14750.00 9000.00

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 0.45 1100.00 1099.78 1075.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 0.45 1100.00 1099.78 1075.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 0.46 1519.40 1511.64 1314.12

=============== 212-00022 Seeding (Riparian) Acre ===================================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 2.00 800.00 1880.00 3300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 800.00 1880.00 3300.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 800.00 1880.00 3300.00

=============== 212-00028 Seeding (Wetlands) Acre ===================================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1.00 1400.00 8000.00 11000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 1400.00 8000.00 11000.00

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 0.18 1900.00 3355.09 1605.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 0.18 1900.00 3355.09 1605.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.18 1476.27 6558.48 9566.86

=============== 212-00047 Soil Preparation (Spec) Acre ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 30.00 800.00 1376.49 1372.38STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 16.00 900.00 2887.50 1100.00

Page 172: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 128 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 212-00047 Soil Preparation (Spec) Acre ===================================================NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 3.00 2500.00 2708.57 2450.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 15.00 1400.00 2204.27 2200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 64.00 1045.31 1942.15 1548.77

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 2.50 1000.00 3216.00 2805.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 1.50 2500.00 3208.40 2965.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 13.90 1400.00 1375.18 1248.48NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 22.90 1900.00 2489.26 2000.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 0.40 850.00 3306.76 3210.20IM 0253-186 I-25, 120TH TO SH 7 06/17/04 0.50 1000.00 2768.38 2500.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 2.50 2800.00 2478.00 2126.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 44.20 1743.44 2351.61 1865.68

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 10.00 1280.00 2606.63 2790.00IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 252.00 400.00 1176.10 1200.00BR 0243-063 EAST OF LIMON 07/15/04 1.50 3000.00 3802.25 2150.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 1000.00 3055.07 3120.00SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 0.10 6000.00 4212.50 2625.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 13.00 1000.00 861.25 770.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 12.40 1500.00 3271.91 3200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 290.00 521.72 1275.20 1333.09

BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 4.00 900.00 2616.13 2300.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 9.25 1200.00 638.92 605.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 2.48 3100.00 3139.66 3060.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 0.10 10000.00 5634.88 2659.40NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 0.75 1000.00 3202.16 3083.65NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 0.80 2500.00 4193.75 4197.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 17.38 1503.91 1729.81 1629.56 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 415.58 773.37 1500.18 1435.35

=============== 212-00048 Soil Preparation (Spec) Cubic Yard =============================================

NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 4.00 40.00 209.17 30.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4.00 40.00 209.17 30.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 40.00 209.17 30.00

Page 173: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 129 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 212-00050 Sod Sq Foot ================================================

STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 2,317.00 1.00 1.11 0.65STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 500.00 2.00 0.80 1.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 20,500.00 0.40 0.45 0.44 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 23,317.00 0.49 0.52 0.47

SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 1,675.00 1.00 1.33 1.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,675.00 1.00 1.33 1.75

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 17,225.00 0.60 0.72 0.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 17,225.00 0.60 0.72 0.75

STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 75.00 2.00 5.33 2.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 75.00 2.00 5.33 2.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 42,292.00 0.56 0.61 0.64

=============== 213-00000 Mulching Acre ===================================================

STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 1.40 500.00 1150.00 1450.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.40 500.00 1150.00 1450.00

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 48.00 400.00 272.55 275.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 48.00 400.00 272.55 275.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 49.40 402.83 297.42 308.30

=============== 213-00002 Mulching (Weed Free Hay) Acre ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 0.18 1000.00 2777.48 1800.00

Page 174: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 130 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 213-00002 Mulching (Weed Free Hay) Acre ===================================================NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 30.73 750.00 782.44 825.66C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 0.30 1000.00 992.33 1092.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 0.05 3000.00 3720.47 5000.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 40.00 450.00 325.46 290.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 5.25 300.00 324.00 400.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 2.00 500.00 673.91 733.47STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 16.00 500.00 310.00 200.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 3.00 500.00 350.11 245.00SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 13.00 400.00 311.67 285.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 0.75 800.00 837.50 975.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 20.00 400.00 456.13 275.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 2.00 490.00 425.00 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 133.26 514.31 464.18 422.64

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 9.00 500.00 334.50 325.00NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 2.50 450.00 600.00 805.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 2.40 800.00 746.13 506.20STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 1.50 700.00 451.50 312.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 46.50 500.00 640.48 676.26IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 1.10 500.00 493.29 497.90STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 1.00 800.00 940.86 1096.75IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 1.50 700.00 1331.67 770.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 6.00 500.00 375.00 295.00STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 16.00 500.00 310.00 305.00STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 2.00 800.00 601.50 888.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 28.00 380.00 304.36 260.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 0.40 400.00 869.40 842.00CC R600-225 CHATFIELD STATE PARK 06/10/04 2.50 500.00 447.50 710.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 1.30 600.00 811.67 705.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 121.70 490.35 460.73 489.73

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 10.00 340.00 338.44 365.00IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 252.00 250.00 234.47 230.00SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 0.30 800.00 1200.00 1450.00SHE 0091-023 SH 9 VMS - FAIRPLAY TO FRISCO 07/15/04 0.20 2200.00 4921.65 4400.00BR 0243-063 EAST OF LIMON 07/15/04 1.50 500.00 909.83 900.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 650.00 707.46 710.00STA R200-128 SH10, SH350 , SH160 MAINT. 07/29/04 11.45 500.00 425.00 500.00SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 0.10 1600.00 3530.00 1260.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 5.18 450.00 813.96 909.50

Page 175: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 131 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 213-00002 Mulching (Weed Free Hay) Acre ===================================================IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 12.00 300.00 839.68 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 293.73 273.37 273.75 277.63

SHE 105A-010 SH 105/FURROW RD 10/07/04 0.74 1100.00 802.29 700.00C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 1.00 800.00 1762.50 2500.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 2.00 1100.00 1450.00 1500.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1.00 500.00 734.65 775.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 1.00 1000.00 883.33 1000.00NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 0.80 1250.00 740.17 977.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 6.54 965.44 1071.33 1311.16 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 555.23 386.91 364.59 371.10

=============== 213-00003 Mulching (Weed Free) Acre ===================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 0.01 2000.00 25026.00 33000.00STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 14.60 400.00 283.00 300.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 2.00 500.00 529.17 580.00NH 2872-016 US 287 - LAMAR 03/04/04 11.00 450.00 312.50 295.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 0.36 1000.00 2386.02 2150.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 34.00 330.00 370.00 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 61.97 377.44 365.59 433.90

NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 0.70 1000.00 978.43 803.25NH 0502-053 CIMARRON - WEST 04/15/04 20.70 500.00 437.50 435.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 20.00 325.00 390.00 325.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 0.60 1000.00 809.80 760.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 2.50 475.00 427.86 290.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 44.50 434.55 435.24 387.59

C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 2.00 450.00 532.10 550.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 19.40 500.00 355.00 320.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 21.40 495.33 380.97 341.50

Page 176: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 132 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 213-00003 Mulching (Weed Free) Acre ===================================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 9.25 500.00 326.81 310.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 2.93 600.00 429.96 420.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 0.10 2500.00 5100.32 1276.60NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 0.75 1000.00 626.80 402.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 13.03 566.62 390.38 347.46 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 140.90 430.88 395.79 397.25

=============== 213-00004 Mulching (Weed Free Straw) Acre ===================================================

STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 0.90 800.00 1725.00 1650.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 0.90 800.00 1725.00 1650.00

NH 2852-010 US 285 & COUNTY RD. G 04/29/04 5.00 500.00 543.48 684.20STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 7.00 600.00 424.75 403.00BR 0092-018 SH 9, SOUTH OF KREMMLING 05/27/04 1.50 700.00 1103.75 770.00IM 0702-239 HANGING LAKES REST AREAS 06/17/04 1.00 1400.00 1628.67 2179.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 14.50 631.03 596.59 660.41

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 30.80 350.00 440.16 450.00STA 149A-021 SH 149 CRIBWALL 09/16/04 1.00 700.00 1200.00 1200.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 13.75 400.00 719.00 650.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 45.55 372.78 499.42 526.84

BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 4.00 350.00 505.48 510.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4.00 350.00 505.48 510.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 64.95 434.95 522.35 571.19

Page 177: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 133 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 213-00005 Mulching (Decorative) Cubic Foot =============================================

STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 896.00 4.50 2.87 2.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 896.00 4.50 2.87 2.30

SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 8,354.00 4.50 1.05 1.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 8,354.00 4.50 1.05 1.25

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 15,300.00 2.00 2.09 1.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 15,300.00 2.00 2.09 1.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 24,550.00 2.94 1.78 1.13

=============== 213-00008 Mulching (Wood Chip) Cubic Foot =============================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 4,750.00 2.00 2.05 2.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4,750.00 2.00 2.05 2.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4,750.00 2.00 2.05 2.00

=============== 213-00061 Mulch Tackifier Pound ==================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 54.00 2.00 7.47 9.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 3.00 7.00 81.06 78.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 9,135.00 2.00 1.57 1.39STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 2,920.00 2.00 1.65 1.45STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 8.00 5.00 12.97 7.00STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 122.00 4.00 3.63 3.25IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 5,600.00 2.00 1.62 1.40STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 525.00 3.50 2.08 2.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 300.00 2.50 2.16 2.25STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 600.00 2.00 1.57 1.22STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 3,200.00 2.00 1.36 0.60NH 2872-016 US 287 - LAMAR 03/04/04 2,200.00 2.00 1.62 1.44

Page 178: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 134 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 213-00061 Mulch Tackifier Pound ==================================================NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 450.00 2.00 1.98 1.80SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 1,900.00 2.00 2.07 1.90STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 55.00 3.00 5.61 3.75NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 150.00 4.00 3.50 4.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 4,000.00 2.00 1.79 1.75STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 6,998.00 1.60 1.55 1.80 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 38,220.00 1.97 1.68 1.53

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 2,700.00 2.00 1.55 1.70NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 500.00 1.50 56.96 2.55STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 720.00 2.00 1.56 1.07NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 210.00 2.00 1.63 1.26NH 0502-053 CIMARRON - WEST 04/15/04 3,105.00 1.50 2.37 2.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 3,926.00 1.50 1.76 1.75STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 300.00 1.50 2.10 2.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 6,984.00 2.00 2.59 1.82IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 165.00 2.00 2.94 3.21STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 200.00 3.00 61.78 2.14IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 225.00 1.75 4.73 2.20SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 1,200.00 1.50 1.94 1.85NH 2852-010 US 285 & COUNTY RD. G 04/29/04 1,000.00 2.00 1.84 1.60STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 3,315.00 2.00 1.95 1.85STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 1,050.00 1.75 1.65 1.50STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 300.00 4.00 3.87 2.49BR 0092-018 SH 9, SOUTH OF KREMMLING 05/27/04 225.00 3.00 4.51 4.25NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 5,600.00 1.50 1.70 1.40NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 60.00 6.00 3.59 3.40CC R600-225 CHATFIELD STATE PARK 06/10/04 750.00 2.00 1.65 1.60IM 0253-186 I-25, 120TH TO SH 7 06/17/04 180.00 2.50 1.99 2.00IM 0702-239 HANGING LAKES REST AREAS 06/17/04 600.00 4.00 3.79 5.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 260.00 2.00 2.17 2.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 500.00 2.00 1.97 2.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 34,075.00 1.85 3.46 1.83

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 4,620.00 1.25 1.56 1.70STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 2,000.00 2.00 1.64 1.55IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 37,800.00 1.50 1.31 1.30SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 50.00 4.00 2.38 1.75SHE 0091-023 SH 9 VMS - FAIRPLAY TO FRISCO 07/15/04 30.00 3.25 8.80 14.67BR 0243-063 EAST OF LIMON 07/15/04 225.00 4.00 2.17 2.60

Page 179: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 135 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 213-00061 Mulch Tackifier Pound ==================================================IMD 0252-364 I-25 OVER BROADWAY 07/29/04 300.00 3.00 1.69 1.77STA R200-128 SH10, SH350 , SH160 MAINT. 07/29/04 2,290.00 2.50 2.48 3.00SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 20.00 5.00 8.13 5.25NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 9,600.00 1.80 1.37 1.30STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1,150.00 2.50 1.79 1.55C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 400.00 2.00 2.32 2.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 5,820.00 1.70 1.57 1.50STA 149A-021 SH 149 CRIBWALL 09/16/04 200.00 2.00 4.00 4.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 2,750.00 2.50 2.03 1.65IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 1,700.00 2.00 2.61 3.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 68,955.00 1.68 1.45 1.49

SHE 105A-010 SH 105/FURROW RD 10/07/04 74.00 5.00 5.36 5.00C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 150.00 1.50 8.75 14.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 600.00 3.75 2.14 1.70BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 800.00 2.00 1.90 2.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 2,775.00 2.00 1.49 1.45BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 879.00 1.50 1.24 1.20NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 30.00 4.00 8.74 6.91IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 350.00 4.00 3.55 2.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 150.00 2.00 2.59 2.25NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 160.00 2.60 3.94 3.16 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 5,968.00 2.27 1.90 2.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 147,218.00 1.82 1.95 1.60

=============== 213-00100 Soil Binder Acre ===================================================

STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 3.00 1000.00 369.43 210.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 2.00 325.00 690.00 1000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5.00 730.00 420.72 526.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 126.00 400.00 318.17 320.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 126.00 400.00 318.17 320.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 12.50 2500.00 357.52 365.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 12.50 2500.00 357.52 365.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 143.50 594.43 324.62 331.10

Page 180: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 136 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 213-00300 Conc Landscape Border Lin Foot ===============================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 1,525.00 7.00 13.65 16.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,525.00 7.00 13.65 16.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,525.00 7.00 13.65 16.00

=============== 213-00462 Landscape Border (3/16x5-1/2 In) Lin Foot ===============================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 315.00 5.50 5.33 5.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 315.00 5.50 5.33 5.20 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 315.00 5.50 5.33 5.20

=============== 213-00700 Landscape Boulder Each ===================================================

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 30.00 200.00 190.95 150.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 40.00 200.00 174.39 90.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 70.00 200.00 182.40 115.71 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 70.00 200.00 182.40 115.71

=============== 213-00705 Landscape Boulder (Special) Each ===================================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 9.00 350.00 834.62 600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 9.00 350.00 834.62 600.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 9.00 350.00 834.62 600.00

=============== 214-00000 Landscape Maintenance LUMP SUM ===============================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 1.00 10000.00 24178.74 21000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 10000.00 24178.74 21000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 10000.00 24178.74 21000.00

Page 181: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 137 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 214-00201 Deciduous Tree (Tubeling) Each ===================================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 50.00 15.00 14.54 7.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 50.00 15.00 14.54 7.25 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 50.00 15.00 14.54 7.25

=============== 214-00215 Deciduous Tree (1.5 In C) Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 52.00 250.00 203.14 211.99IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 10.00 260.00 300.78 250.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 62.00 251.61 223.07 218.12

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 15.00 250.00 258.11 230.05 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 15.00 250.00 258.11 230.05 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 77.00 251.30 228.70 220.45

=============== 214-00230 Deciduous Tree (3 In C) Each ===================================================

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 1.00 500.00 632.08 500.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 19.00 500.00 505.57 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 20.00 500.00 510.37 500.00

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 7.00 550.00 538.38 525.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 7.00 550.00 538.38 525.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 27.00 512.96 517.70 506.48

=============== 214-00310 Deciduous Shrub (1 Gal) Each ===================================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 139.00 17.00 26.43 17.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 139.00 17.00 26.43 17.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 139.00 17.00 26.43 17.00

Page 182: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 138 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 214-00350 Deciduous Shrub (5 Gal) Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 495.00 30.00 41.67 47.42 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 495.00 30.00 41.67 47.42

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 265.00 40.00 38.64 33.71IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 439.00 30.00 33.28 28.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 704.00 33.76 35.59 30.15

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 203.00 35.00 34.96 34.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 203.00 35.00 34.96 34.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,402.00 32.61 38.14 36.80

=============== 214-00401 Evergreen Tree (Tubeling) Each ===================================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 50.00 15.00 14.84 7.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 50.00 15.00 14.84 7.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 50.00 15.00 14.84 7.50

=============== 214-00502 Evergreen Tree (2 Ft)(B-B) Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 26.00 90.00 182.44 178.52 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 26.00 90.00 182.44 178.52 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 26.00 90.00 182.44 178.52

=============== 214-00504 Evergreen Tree (4 Ft)(B-B) Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 67.00 170.00 239.11 234.31 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 67.00 170.00 239.11 234.31

Page 183: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 139 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 214-00504 Evergreen Tree (4 Ft)(B-B) Each ===================================================

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 6.00 270.00 502.37 262.15 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 6.00 270.00 502.37 262.15 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 73.00 178.22 257.40 236.60

=============== 214-00506 Evergreen Tree (6 Ft)(B-B) Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 73.00 300.00 323.74 334.73 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 73.00 300.00 323.74 334.73

STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 3.00 400.00 350.00 300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3.00 400.00 350.00 300.00

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 4.00 350.00 424.97 342.40IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 14.00 370.00 240.91 220.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 18.00 365.56 289.34 247.20

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 20.00 300.00 306.84 300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 20.00 300.00 306.84 300.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 114.00 312.98 317.55 313.90

=============== 214-00508 Evergreen Tree (8 Ft)(B-B) Each ===================================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 22.00 380.00 320.06 310.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 22.00 380.00 320.06 310.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 22.00 380.00 320.06 310.00

Page 184: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 140 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 214-00610 Evergreen Shrub (1 Gal) Each ===================================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 80.00 20.00 30.45 20.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 80.00 20.00 30.45 20.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 80.00 20.00 30.45 20.00

=============== 214-00650 Evergreen Shrub (5 Gal) Each ===================================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 203.00 30.00 34.26 35.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 203.00 30.00 34.26 35.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 203.00 30.00 34.26 35.00

=============== 214-00905 Perennials (2.25 In Pot) Each ===================================================

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 4,000.00 2.00 2.43 2.40C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 50.00 2.25 3.47 2.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4,050.00 2.00 2.45 2.40

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1,000.00 3.00 2.02 1.85 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,000.00 3.00 2.02 1.85 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5,050.00 2.20 2.36 2.29

=============== 214-00910 Perennials (1 Gal) Each ===================================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 355.00 10.00 13.56 12.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 355.00 10.00 13.56 12.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 355.00 10.00 13.56 12.00

=============== 214-01010 Brush Layer Cutting Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 1,700.00 6.00 3.10 2.96

Page 185: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 141 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 214-01010 Brush Layer Cutting Each ===================================================IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 400.00 4.50 5.79 3.60STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 25.00 11.60 9.40 15.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,125.00 5.78 3.76 3.22

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1,000.00 6.00 6.08 7.76C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 20.00 3.00 14.98 18.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 100.00 4.00 8.50 11.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,120.00 5.77 6.41 8.23

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 300.00 4.00 3.22 2.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 50.00 13.00 6.03 4.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 350.00 5.29 3.44 2.36 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3,595.00 5.73 4.43 4.70

=============== 214-01025 Dormant Log Cutting Each ===================================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 10.00 72.00 78.00 85.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 10.00 72.00 78.00 85.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10.00 72.00 78.00 85.00

=============== 214-01030 Wattle Each ===================================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 5.00 110.00 167.50 225.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5.00 110.00 167.50 225.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5.00 110.00 167.50 225.00

=============== 215-00000 Transplant Shrub Each ===================================================

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 15.00 10.00 118.13 197.95

Page 186: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 142 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 215-00000 Transplant Shrub Each ===================================================IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 12.00 50.00 91.51 40.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 27.00 27.78 107.74 127.75 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 27.00 27.78 107.74 127.75

=============== 215-00001 Transplant Shrub Sq Yard ================================================

NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 11.00 50.00 103.33 30.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 11.00 50.00 103.33 30.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 11.00 50.00 103.33 30.00

=============== 215-00060 Transplant Tree (3-6 In) Each ===================================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 14.00 500.00 511.61 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 14.00 500.00 511.61 500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 14.00 500.00 511.61 500.00

=============== 215-00100 Transplant Tree (6+ In) Each ===================================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 8.00 400.00 851.34 650.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 8.00 400.00 851.34 650.00

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 6.00 600.00 613.69 600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 6.00 600.00 613.69 600.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 14.00 485.71 749.49 628.57

=============== 215-00500 Transplant Seedling Each ===================================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 24.00 12.00 18.33 16.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 24.00 12.00 18.33 16.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 24.00 12.00 18.33 16.00

Page 187: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 143 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 215-00600 Transplant Plug Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 1,150.00 4.00 3.38 3.35 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,150.00 4.00 3.38 3.35

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1,000.00 4.00 6.87 7.75NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 50.00 3.00 18.13 14.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,050.00 3.95 7.30 8.05 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,200.00 3.98 5.07 5.59

=============== 216-00015 Soil Reten Blanket (Excel) Sq Yard ================================================

NH 2852-010 US 285 & COUNTY RD. G 04/29/04 5,200.00 2.00 1.72 1.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 5,200.00 2.00 1.72 1.40

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 3,000.00 2.00 2.04 1.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 3,000.00 2.00 2.04 1.10

NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 50.00 5.00 13.65 20.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 50.00 5.00 13.65 20.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8,250.00 2.02 1.91 1.40

=============== 216-00035 Soil Reten Blanket (Plastic) Sq Yard ================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 10,000.00 5.00 7.02 6.42IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 12,817.00 5.00 4.16 3.70STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 465.00 8.00 7.33 12.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 27,813.00 5.10 1.05 1.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 51,095.00 5.08 4.20 2.89

Page 188: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 144 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 216-00035 Soil Reten Blanket (Plastic) Sq Yard ================================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 200.00 7.00 10.31 6.76NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 767.00 10.00 5.92 4.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 967.00 9.38 6.43 4.97

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 5,904.00 5.00 4.85 4.75STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 470.00 12.00 6.44 6.95 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 6,374.00 5.52 5.04 4.91

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 264.00 7.00 7.22 7.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 264.00 7.00 7.22 7.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 58,700.00 5.21 4.33 3.16

=============== 216-00037 Soil Reten Blanket (Coconut) Sq Yard ================================================

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 75.00 1.50 2.33 2.05CC R600-225 CHATFIELD STATE PARK 06/10/04 12,050.00 1.50 1.55 1.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 12,125.00 1.50 1.56 1.60

SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 150.00 4.00 4.00 4.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 150.00 4.00 4.00 4.00

NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 100.00 5.00 2.97 2.93 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 100.00 5.00 2.97 2.93 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 12,375.00 1.56 1.59 1.64

Page 189: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 145 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 216-00039 Soil Reten Blanket (Straw) Sq Yard ================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 670.00 2.00 2.18 2.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 15.00 3.00 19.22 5.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 6,066.00 2.00 1.25 1.20STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 44,562.00 1.20 1.05 1.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 51,313.00 1.31 1.16 1.12

C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 1,267.00 2.00 1.97 1.80 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,267.00 2.00 1.97 1.80 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 52,580.00 1.32 1.20 1.14

=============== 216-00041 Soil Reten Blanket (S/C) Sq Yard ================================================

STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 800.00 1.50 1.42 1.20IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 22,403.00 1.50 1.31 1.19STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 1,900.00 1.50 1.74 1.42STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 17,050.00 1.50 1.44 1.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 42,153.00 1.50 1.38 1.16

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 1,000.00 2.00 1.38 1.25NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 300.00 1.50 1.48 1.15IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 9,350.00 1.50 1.29 1.33NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 7,283.00 1.50 1.49 1.20NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 85.00 1.50 1.59 1.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 18,018.00 1.53 1.37 1.27

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 50.00 3.00 3.88 4.95IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 28,330.00 1.50 1.24 1.20SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 100.00 2.00 2.80 2.60IMD 0252-364 I-25 OVER BROADWAY 07/29/04 3,464.00 2.00 1.47 1.60NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 19,491.00 1.20 1.26 1.25

Page 190: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 146 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 216-00041 Soil Reten Blanket (S/C) Sq Yard ================================================SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 1,000.00 2.00 1.20 1.50IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 1,300.00 1.30 2.30 2.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 53,735.00 1.43 1.28 1.27

C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 400.00 1.60 2.15 2.50IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 8,496.00 1.50 1.36 1.30BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 638.00 1.50 1.34 1.30NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 150.00 3.00 3.16 2.15 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 9,684.00 1.53 1.39 1.36 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 123,590.00 1.48 1.34 1.24

=============== 217-00000 Herbicide Treatment Sq Yard ================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 8,500.00 0.20 0.26 0.10NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 3,000.00 0.25 0.26 0.22STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 9,700.00 1.00 0.10 0.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 21,200.00 0.57 0.23 0.12

CC R600-225 CHATFIELD STATE PARK 06/10/04 500.00 1.00 0.86 2.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 500.00 1.00 0.86 2.00

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 11,700.00 0.08 0.22 0.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 11,700.00 0.08 0.22 0.20

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 2,115.00 0.75 0.10 0.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2,115.00 0.75 0.10 0.10 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 35,515.00 0.43 0.23 0.17

Page 191: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 147 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 217-00020 Herbicide Treatment Hour ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 3.00 125.00 208.29 200.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 5.00 100.00 184.71 205.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 16.00 125.00 92.82 80.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 4.00 125.00 228.76 147.54STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 5.00 80.00 160.64 125.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 10.00 110.00 112.25 75.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 43.00 113.37 133.03 113.26

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 30.00 100.00 67.71 71.92NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 8.00 85.00 175.00 200.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 20.00 50.00 72.94 67.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 1.20 100.00 134.16 210.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 59.20 81.08 75.30 90.36

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 40.00 115.00 171.81 170.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 8.00 125.00 333.58 150.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 20.00 150.00 152.35 160.50C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 10.00 100.00 112.20 115.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 20.00 100.00 76.67 75.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 98.00 118.37 160.48 141.43

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 10.00 100.00 203.43 195.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 10.00 100.00 99.57 105.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 20.00 100.00 168.81 150.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 220.20 105.70 129.94 122.98

=============== 218-00000 Noxious Weed Management LUMP SUM ===============================================

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 1.00 3000.00 3302.51 6442.59 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 3000.00 3302.51 6442.59 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 3000.00 3302.51 6442.59

Page 192: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 148 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 250-00010 Envir Health/Safety Mngmt LUMP SUM ===============================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 1.00 4000.00 4813.00 4500.00STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 1.00 2500.00 4309.17 1000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 3250.00 4510.70 2750.00

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 1.00 6000.00 34987.18 94062.00IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 1.00 5000.00 2851.58 2766.08NH 2852-010 US 285 & COUNTY RD. G 04/29/04 1.00 3500.00 4818.00 6000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3.00 4833.33 9934.18 34276.03

BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 1.00 10000.00 4143.53 2516.29IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 5000.00 3162.56 2460.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 1500.00 4925.00 3000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 3.00 5500.00 4070.99 2658.76

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 4000.00 3714.18 2400.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 1.00 3500.00 2661.67 1.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 3750.00 3263.10 1200.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10.00 4500.00 6087.03 11870.54

=============== 250-00050 Monitoring Technician Hour ===================================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 10.00 80.00 71.73 75.00STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 32.00 41.00 69.17 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 42.00 50.29 69.61 63.57

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 40.00 80.00 75.69 39.40

Page 193: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 149 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 250-00050 Monitoring Technician Hour ===================================================NH 2852-010 US 285 & COUNTY RD. G 04/29/04 20.00 65.00 66.10 70.00BR 0092-018 SH 9, SOUTH OF KREMMLING 05/27/04 20.00 60.00 70.13 71.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 80.00 71.25 71.01 55.08

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 200.00 37.00 46.51 40.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 10.00 65.00 101.00 70.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 210.00 38.33 49.10 41.43

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 40.00 40.00 60.59 48.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 80.00 40.00 40.63 37.50STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 20.00 70.00 98.33 95.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 3.00 70.00 133.67 1.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 143.00 44.83 55.08 47.71 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 475.00 46.89 56.64 47.58

=============== 250-00100 Environmental Health and Safety LUMP SUM ===============================================

BR 0092-018 SH 9, SOUTH OF KREMMLING 05/27/04 1.00 5000.00 7025.00 5500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 5000.00 7025.00 5500.00

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 500.00 3643.75 875.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 500.00 3643.75 875.00

IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 1.00 2000.00 2569.14 1650.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 2000.00 2569.14 1650.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 2500.00 4043.93 2675.00

Page 194: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 150 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 250-00110 Health and Safety Officer Hour ===================================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 10.00 100.00 111.40 115.00STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 64.00 82.00 90.67 72.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 40.00 95.00 92.90 84.70STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 8.00 80.00 88.19 101.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 122.00 87.61 92.51 81.59

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 14.00 125.00 125.53 48.50IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 40.00 80.00 65.30 66.39NH 2852-010 US 285 & COUNTY RD. G 04/29/04 10.00 90.00 98.70 90.00BR 0092-018 SH 9, SOUTH OF KREMMLING 05/27/04 20.00 100.00 92.13 93.50NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 40.00 100.00 100.00 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 124.00 95.56 82.44 81.49

BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 20.00 110.00 76.24 60.39IMD 0252-364 I-25 OVER BROADWAY 07/29/04 200.00 70.00 58.38 60.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 10.00 70.00 144.75 105.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 230.00 73.48 63.41 61.99

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 40.00 80.00 77.82 80.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 40.00 75.00 72.12 60.00IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 20.00 100.00 78.29 58.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 15.00 110.00 110.00 100.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 3.00 90.00 150.33 1.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 118.00 85.76 79.93 70.03 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 594.00 83.43 78.62 71.68

=============== 250-00120 Material Sampling and Delivery Each ===================================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 2.00 200.00 182.90 180.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 8.00 200.00 82.65 74.03 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 10.00 200.00 93.78 95.22

Page 195: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 151 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 250-00120 Material Sampling and Delivery Each ===================================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 8.00 200.00 1149.81 2913.12IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 8.00 160.00 82.71 71.92NH 2852-010 US 285 & COUNTY RD. G 04/29/04 2.00 200.00 285.00 350.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 18.00 182.22 389.75 1365.57

BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 3.00 170.00 102.93 65.42IMD 0252-364 I-25 OVER BROADWAY 07/29/04 5.00 90.00 68.52 70.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 5.00 150.00 214.50 115.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 13.00 131.54 134.42 86.25

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 15.00 60.00 59.55 65.00IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 6.00 280.00 310.29 200.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 8.00 80.00 600.00 300.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 4.00 200.00 167.00 1.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 33.00 121.82 239.20 138.76 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 74.00 148.78 233.31 422.07

=============== 250-00200 Material Handling (Stockpile) Cubic Yard =============================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 75.00 20.00 16.06 12.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 75.00 20.00 16.06 12.00

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 80.00 25.00 18.31 15.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 5.00 25.00 163.33 200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 85.00 25.00 24.80 25.88 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 160.00 22.66 20.67 19.38

Page 196: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 152 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 250-00210 Solid Waste Disposal Cubic Yard =============================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 7.32 125.00 169.53 130.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 2.00 50.00 123.30 45.45 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 9.32 108.91 153.19 111.86

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 2.00 60.00 139.06 110.64NH 2852-010 US 285 & COUNTY RD. G 04/29/04 5.00 100.00 195.18 128.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 7.00 88.57 175.04 123.18

BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 1.00 400.00 316.39 261.69IMD 0252-364 I-25 OVER BROADWAY 07/29/04 100.00 20.00 40.24 50.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 200.00 250.00 99.75 37.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 9,000.00 20.00 24.21 23.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 9,301.00 24.99 26.03 23.62

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 40.00 40.00 48.34 100.00IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 1.00 250.00 337.71 50.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 1.00 200.00 521.67 500.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 10.00 130.00 130.00 1.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 52.00 64.42 77.82 87.69 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 9,369.32 25.34 26.62 24.13

=============== 250-00220 Hazardous Waste Disposal Cubic Yard =============================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 7.32 700.00 493.31 180.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 2.00 300.00 152.02 134.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 9.32 614.16 372.71 170.13

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 2.00 300.00 304.67 553.22

Page 197: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 153 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 250-00220 Hazardous Waste Disposal Cubic Yard =============================================NH 2852-010 US 285 & COUNTY RD. G 04/29/04 5.00 500.00 331.56 137.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 7.00 442.86 321.91 255.92

BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 1.00 700.00 354.56 301.95 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 700.00 354.56 301.95

IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 1.00 300.00 721.43 490.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 1.00 150.00 576.67 400.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 10.00 200.00 150.00 1.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 12.00 204.17 282.00 75.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 29.32 408.39 328.21 156.17

=============== 304-01000 ABC (CL 1) Ton ====================================================

IM 0701-157 FRUITA TO CLIFTON 02/26/04 3,736.00 12.00 14.27 12.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3,736.00 12.00 14.27 12.25

NH 0502-053 CIMARRON - WEST 04/15/04 46,376.00 9.00 11.35 10.35STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 4,811.00 15.00 14.33 13.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 51,187.00 9.56 11.57 10.60 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 54,923.00 9.73 11.84 10.71

=============== 304-01005 ABC (CL 1) Cubic Yard =============================================

STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 83.00 20.00 36.00 57.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 83.00 20.00 36.00 57.00

NH 2852-010 US 285 & COUNTY RD. G 04/29/04 5,559.00 10.00 18.54 16.30

Page 198: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 154 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 304-01005 ABC (CL 1) Cubic Yard =============================================STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 16,491.00 16.00 18.98 12.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 22,050.00 14.49 18.85 13.23 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 22,133.00 14.51 18.94 13.40

=============== 304-02000 ABC (CL 2) Ton ====================================================

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 54,553.00 8.00 11.68 8.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 54,553.00 8.00 11.68 8.20

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 2,886.00 15.00 20.24 14.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2,886.00 15.00 20.24 14.20 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 57,439.00 8.35 12.21 8.50

=============== 304-03000 ABC (CL 3) Ton ====================================================

STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 539.00 15.00 13.11 11.20NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 2,463.00 12.00 14.04 8.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3,002.00 12.54 13.75 8.98

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 46,402.00 10.00 8.49 9.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 46,402.00 10.00 8.49 9.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 49,404.00 10.15 8.61 9.00

=============== 304-05009 ABC (CL 5)(Spec) Ton ====================================================

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 500.00 20.00 15.30 12.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 500.00 20.00 15.30 12.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 500.00 20.00 15.30 12.00

Page 199: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 155 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 304-06000 ABC (CL 6) Ton ====================================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 3,166.00 15.00 14.35 11.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 1,754.00 12.00 15.63 12.25NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 6,902.00 15.00 14.03 9.30STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 2,256.00 15.00 12.90 11.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 4,274.00 16.00 15.50 17.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 3,124.00 12.00 18.38 16.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 21,476.00 14.52 14.73 12.48

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 1,102.00 14.00 26.57 17.70NH 0502-053 CIMARRON - WEST 04/15/04 16,394.00 11.00 13.43 10.85STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 689.00 15.00 14.80 17.00STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 558.00 20.00 17.33 16.00BR 0092-018 SH 9, SOUTH OF KREMMLING 05/27/04 85.00 25.00 23.75 11.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 63.00 13.00 34.88 28.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 145.00 20.00 18.33 22.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 1,528.00 15.00 19.39 14.55STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 614.00 15.00 28.00 20.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 21,178.00 12.05 14.97 12.20

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 13,579.00 12.00 12.17 12.00IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 26,800.00 12.00 13.81 16.25IMD 0252-364 I-25 OVER BROADWAY 07/29/04 7,518.00 13.00 15.01 10.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 8,561.00 13.00 18.64 14.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1,636.00 16.00 15.57 12.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 31,246.00 12.00 12.88 10.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 7,738.00 12.00 13.57 16.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 97,078.00 12.23 13.76 12.87

SHE 105A-010 SH 105/FURROW RD 10/07/04 1,810.00 18.00 17.39 20.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 381.00 25.00 24.00 19.50BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 547.00 25.00 28.85 28.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 3,008.00 14.00 12.73 12.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 146.00 15.00 23.94 27.65 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 5,892.00 16.99 17.83 16.82 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 145,624.00 12.74 14.20 12.87

Page 200: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 156 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 304-06004 ABC (CL 6) Sq Yard ================================================

STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 50.00 16.00 16.63 20.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 50.00 16.00 16.63 20.00

STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 3,126.00 5.00 5.63 5.45 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3,126.00 5.00 5.63 5.45 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3,176.00 5.17 5.97 5.68

=============== 304-06007 ABC (CL 6) Cubic Yard =============================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 44.00 20.00 38.97 30.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 11,713.00 20.00 26.45 26.47STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 2,215.00 20.00 24.65 22.00C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 164.00 35.00 43.97 32.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 981.00 27.00 26.03 25.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 6,974.00 20.00 19.80 19.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 1,816.00 20.00 20.20 18.32NH 2872-016 US 287 - LAMAR 03/04/04 1,954.00 23.00 21.00 20.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 1,423.00 20.00 21.50 25.00STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 41.00 35.00 44.33 62.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 27,325.00 20.58 24.07 23.16

STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 768.00 25.00 30.83 19.91SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 2,900.00 20.00 21.32 16.50NH 2852-010 US 285 & COUNTY RD. G 04/29/04 4,697.00 10.00 20.60 23.20STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 6,984.00 18.00 20.46 16.60NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 1,513.00 25.00 24.14 20.40CC R600-225 CHATFIELD STATE PARK 06/10/04 557.00 27.00 32.25 31.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 2,858.00 20.00 28.46 22.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 20,277.00 17.75 23.27 19.68

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 8,676.00 15.00 22.97 23.00

Page 201: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 157 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 304-06007 ABC (CL 6) Cubic Yard =============================================NH 2873-137 US 287 IN BOULDER & LARIMER C 11/18/04 417.00 20.00 47.12 46.50ER 0702-255 I-70 GLENWOOD CANYON 11/30/04 23.00 40.00 200.00 125.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 76.00 30.00 62.65 103.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 9,192.00 15.41 25.01 24.99 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 56,794.00 18.73 23.98 22.21

=============== 304-06008 ABC (CL 6) (Spec) Cubic Yard =============================================

SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 4,416.00 25.00 17.19 16.50IM 0253-186 I-25, 120TH TO SH 7 06/17/04 349.00 25.00 26.39 30.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4,765.00 25.00 17.74 17.49

NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 2,516.00 25.00 22.99 17.95NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 1,605.00 30.00 35.83 18.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4,121.00 26.95 26.55 17.97 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8,886.00 25.90 21.49 17.71

=============== 304-06009 ABC (CL 6) (Spec) Ton ====================================================

NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 16,065.00 8.00 11.73 10.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 16,065.00 8.00 11.73 10.30

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 13,539.00 8.00 10.90 7.25STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 2,454.00 12.00 13.99 12.30IM 0761-185 I-76, LOCHBUIE TO HUDSON 06/24/04 8,976.00 10.00 13.49 13.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 24,969.00 9.11 12.13 10.07 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 41,034.00 8.68 11.96 10.16

=============== 304-07000 ABC (CL 7) Ton ====================================================

IM 0704-203 I-70, GENOA-EAST, M.P. 374 - 01/15/04 1,384.00 11.00 17.38 13.50

Page 202: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 158 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 304-07000 ABC (CL 7) Ton ====================================================IM 0701-164 PARACHUTE EAST & WEST 02/12/04 6,940.00 11.00 13.37 13.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 7,600.04 10.00 13.17 11.75IM 0701-157 FRUITA TO CLIFTON 02/26/04 11,503.00 13.00 11.58 10.00STA 014A-030 SH 14, WALDEN EAST 03/04/04 6,411.00 10.00 13.33 15.00STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 3,322.00 12.00 10.31 11.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 2,041.00 13.00 15.85 12.00STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 5,147.00 11.00 17.12 16.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 44,348.04 11.37 13.34 12.46 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 44,348.04 11.37 13.34 12.46

=============== 304-07009 ABC (CL 7) (Spec) Ton ====================================================

STA 0343-023 US 34, EAST OF AKRON 06/17/04 3,424.00 12.00 9.35 7.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3,424.00 12.00 9.35 7.50

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 14,833.00 8.00 14.44 22.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 14,833.00 8.00 14.44 22.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 18,257.00 8.75 13.62 19.28

=============== 304-09000 ABC (Spec) Cubic Yard =============================================

STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 2,881.00 18.00 25.80 22.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,881.00 18.00 25.80 22.50

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 3,000.00 23.00 24.67 28.05NH 0741-015 - SMA Alt SH 74 EVERGREEN OVERLAY 04/29/04 174.00 30.00 29.73 30.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 179.00 20.00 26.95 15.10NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 3,930.00 13.00 13.48 12.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 7,283.00 17.70 21.92 19.12

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 4,082.00 18.00 26.32 21.62

Page 203: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 159 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 304-09000 ABC (Spec) Cubic Yard =============================================IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 45.00 30.00 79.74 65.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4,127.00 18.13 27.09 22.09

STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 694.00 28.50 35.00 25.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 694.00 28.50 35.00 25.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 14,985.00 18.38 24.54 20.86

=============== 304-09014 ABC (Spec) Ton ====================================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 3,496.00 12.00 15.22 13.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 747.00 15.00 15.45 18.50STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 2,452.00 18.00 13.55 13.50IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 17,018.00 12.00 9.58 10.04 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 23,713.00 12.71 10.31 11.10

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 872.72 18.00 13.46 8.52 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 872.72 18.00 13.46 8.52

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 29,847.00 12.00 14.32 15.65NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 8,822.00 13.00 12.13 11.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 38,669.00 12.23 13.82 14.70

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 200.00 35.00 24.05 24.25NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 8,767.00 13.00 24.33 18.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 586.00 14.00 25.83 12.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 9,553.00 13.52 24.37 17.76 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 72,807.72 12.63 13.90 13.86

Page 204: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 160 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 304-09055 ABC (Blotter) Ton ====================================================

STA R300-120 R-3 SOUTHWEST CHIPSEAL 01/29/04 25.00 25.00 40.00 55.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 25.00 25.00 40.00 55.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 25.00 25.00 40.00 55.00

=============== 306-01000 Reconditioning Sq Yard ================================================

STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 1,000.00 3.00 4.81 1.80STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 18,830.00 2.00 0.92 0.50STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 109,834.00 0.80 0.90 0.90 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 129,664.00 0.99 1.00 0.85 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 129,664.00 0.99 1.00 0.85

=============== 307-00000 Hydrated Lime Ton ====================================================

IM 0701-157 FRUITA TO CLIFTON 02/26/04 2,215.00 110.00 113.67 100.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 1,243.00 95.00 101.02 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3,458.00 104.61 110.22 100.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3,458.00 104.61 110.22 100.00

=============== 307-00212 Lime Tr Subgrade (12 In) Sq Yard ================================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 40,331.00 3.30 5.88 6.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 40,331.00 3.30 5.88 6.75 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 40,331.00 3.30 5.88 6.75

=============== 310-00400 Process Asphalt Mat For Base Course Sq Yard ================================================

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 37,424.00 1.50 1.64 1.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 37,424.00 1.50 1.64 1.30 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 37,424.00 1.50 1.64 1.30

Page 205: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 161 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 310-00500 Full Depth Reclam. of Hot Mix Asph. Pvmt Sq Yard ================================================

NH 0502-053 CIMARRON - WEST 04/15/04 41,887.00 1.20 1.65 2.40STA 0343-023 US 34, EAST OF AKRON 06/17/04 214,100.00 1.20 2.51 2.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 255,987.00 1.20 2.39 2.07

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 7,887.00 1.75 3.74 1.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 7,887.00 1.75 3.74 1.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 263,874.00 1.22 2.44 2.05

=============== 310-00600 Full Depth Reclam. Hot Mix Asph. Pvmt 8" Sq Yard ================================================

NH 0502-053 CIMARRON - WEST 04/15/04 89,396.00 0.20 0.30 0.05 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 89,396.00 0.20 0.30 0.05 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 89,396.00 0.20 0.30 0.05

=============== 403-00720 HBP (Patching) (Asph) Ton ====================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 60.00 100.00 105.05 85.00IM 0704-203 I-70, GENOA-EAST, M.P. 374 - 01/15/04 200.00 100.00 79.58 70.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 250.00 90.00 137.91 160.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 50.00 120.00 104.59 75.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 200.00 95.00 88.02 90.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 579.00 100.00 105.07 90.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 100.00 100.00 113.89 106.69STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 556.00 90.00 93.53 70.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 1,500.00 75.00 80.29 63.50C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 14.00 175.00 145.27 131.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 58.00 100.00 85.43 85.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 963.00 80.00 86.02 75.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 20.00 100.00 131.25 110.00IM 0701-164 PARACHUTE EAST & WEST 02/12/04 100.00 100.00 89.60 100.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 200.00 75.00 81.96 65.74C 074A-007 SH 74 @ BRYANT DR. 02/26/04 10.00 150.00 165.20 140.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 50.00 100.00 101.83 55.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 100.00 100.00 95.71 89.23

Page 206: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 162 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 403-00720 HBP (Patching) (Asph) Ton ====================================================STA 014A-030 SH 14, WALDEN EAST 03/04/04 100.00 125.00 100.00 95.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 200.00 80.00 99.50 68.00NH 2872-016 US 287 - LAMAR 03/04/04 200.00 100.00 97.50 100.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 677.00 100.00 76.95 60.00SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 87.00 100.00 115.33 100.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 24.60 100.00 112.70 111.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 200.00 80.00 120.00 120.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1,186.00 80.00 82.84 71.50STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 592.00 60.00 94.50 95.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 1,418.00 60.00 79.67 44.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 9,694.60 81.65 88.64 74.04

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 550.00 75.00 87.55 70.00NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 200.00 90.00 104.00 75.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 200.00 80.00 78.53 65.69NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 250.00 70.00 87.50 70.00NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 1,000.00 70.00 75.46 50.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 150.00 90.00 82.44 112.50STA 1191-020 SH 119 ROCKFALL MITIGATION, 2 04/15/04 21.00 175.00 216.67 200.00STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 4.00 200.00 120.00 128.00STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 2,137.00 70.00 76.50 85.00IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 100.00 80.00 126.70 116.87STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 75.00 90.00 149.37 185.83NH 0741-015 - SMA Alt SH 74 EVERGREEN OVERLAY 04/29/04 204.00 100.00 119.17 70.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 250.00 90.00 69.25 78.00BR 0362-028 BRIDGE OVER KIOWA CREEK 05/13/04 3.00 150.00 400.00 400.00STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 500.00 80.00 65.00 50.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 100.00 120.00 109.75 100.00STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 50.00 120.00 152.39 141.77STA R400-170 EAST OF HUDSON, EAST 05/27/04 50.00 115.00 72.50 70.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 105.00 80.00 99.08 82.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 78.00 100.00 101.67 93.40CC R600-225 CHATFIELD STATE PARK 06/10/04 267.00 90.00 64.25 64.00STA R400-169 R-4 CHIP SEALS EAST 06/10/04 70.00 100.00 133.33 100.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 250.00 100.00 95.61 85.00STA 0343-023 US 34, EAST OF AKRON 06/17/04 50.00 120.00 101.80 99.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 186.00 90.00 130.00 110.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 10.00 120.00 160.00 155.00IM 0761-185 I-76, LOCHBUIE TO HUDSON 06/24/04 300.00 70.00 100.90 79.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 7,160.00 79.52 87.86 77.60

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 266.00 100.00 108.57 100.00

Page 207: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 163 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 403-00720 HBP (Patching) (Asph) Ton ====================================================STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 100.00 100.00 121.00 69.00IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1,853.00 45.00 128.71 140.00SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 30.00 150.00 141.00 132.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 30.00 150.00 236.33 388.08SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 10.00 150.00 251.25 262.50NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 200.00 100.00 99.97 100.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 200.00 90.00 128.83 101.40C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 250.00 100.00 96.40 80.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 2,587.00 70.00 80.00 65.00STA 149A-021 SH 149 CRIBWALL 09/16/04 60.00 200.00 161.00 161.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 500.00 100.00 109.50 90.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 50.00 120.00 112.57 140.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 6,136.00 72.13 109.67 97.99

STA 0703-290 GEORGETOWN HILL ROCKFALL MITI 10/07/04 20.00 150.00 280.00 200.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 10.00 150.00 252.00 300.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 500.00 90.00 78.23 74.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 968.00 60.00 68.34 65.00C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 472.00 78.00 145.31 128.50IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 200.00 80.00 75.23 50.00ER 0702-255 I-70 GLENWOOD CANYON 11/30/04 350.00 220.00 326.33 200.00MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 100.00 120.00 97.67 118.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 250.00 85.00 106.67 120.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 250.00 80.00 96.19 82.15STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 341.00 90.00 111.54 90.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 100.00 100.00 91.64 107.40STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 500.00 75.00 92.94 81.00STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 250.00 80.00 95.20 86.40NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 512.00 130.00 116.67 80.00STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 10.00 180.00 519.00 250.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 1,190.00 110.00 119.00 125.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 228.00 100.00 101.00 80.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 257.00 90.00 98.37 90.23NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 100.00 100.00 84.41 82.65STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 268.00 80.00 95.12 94.20NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 50.00 100.00 124.70 85.00NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 2,009.00 80.00 75.33 75.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 8,935.00 93.03 98.48 93.51 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 31,925.60 82.53 94.85 84.89

=============== 403-00721 HBP (Patching) (Asph) Sq Yard ================================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 25.00 45.00 61.33 12.00

Page 208: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 164 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 403-00721 HBP (Patching) (Asph) Sq Yard ================================================STA 114A-009 S.H. 114, W OF COCHETOPA PASS 01/08/04 450.00 30.00 36.83 47.50STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 450.00 40.00 50.50 70.00STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 373.00 25.00 30.67 11.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,298.00 32.32 37.04 44.13

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 79.00 38.00 58.46 43.10NH 0502-053 CIMARRON - WEST 04/15/04 359.00 27.00 27.76 17.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 12,087.00 25.00 19.86 17.68NH 2852-010 US 285 & COUNTY RD. G 04/29/04 157.00 100.00 46.26 29.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 12,682.00 26.07 20.92 17.96

NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 100.00 50.00 54.67 25.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 342.00 70.00 31.33 28.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 442.00 65.48 39.94 27.32 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 14,422.00 27.84 23.25 20.60

=============== 403-00800 Emerg Pothole Rep Ton ====================================================

STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 50.00 140.00 122.10 110.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 50.00 140.00 122.10 110.00

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 50.00 150.00 112.65 125.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 50.00 150.00 112.65 125.00

STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 5.00 150.00 568.96 175.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 5.00 150.00 568.96 175.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 105.00 145.24 137.64 120.24

Page 209: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 165 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 403-01014 HBP 10 Yr Warranty Sq Yard ================================================

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 110,144.00 6.81 11.23 6.81 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 110,144.00 6.81 11.23 6.81 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 110,144.00 6.81 11.23 6.81

=============== 403-01020 Warranted HBP (10 Year) Sq Yard ================================================

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 110,144.00 19.00 13.14 14.62 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 110,144.00 19.00 13.14 14.62 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 110,144.00 19.00 13.14 14.62

=============== 403-02000 HBP (Spec) Ton ====================================================

IM 0701-164 PARACHUTE EAST & WEST 02/12/04 11,677.00 50.00 35.70 39.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 11,677.00 50.00 35.70 39.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 11,677.00 50.00 35.70 39.00

=============== 403-09110 SMA Ton ====================================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 28,581.00 53.00 48.36 44.55STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 14,737.00 33.00 52.04 45.25STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 9,830.00 42.00 52.75 52.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 53,148.00 45.42 50.32 46.21

NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 20,674.00 35.00 52.98 46.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 20,674.00 35.00 52.98 46.20

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 3,550.00 60.00 55.32 58.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 3,550.00 60.00 55.32 58.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 77,372.00 43.30 51.20 46.75

Page 210: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 166 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 403-09111 SMA Sq Yard ================================================

NH 0741-015 - SMA Alt SH 74 EVERGREEN OVERLAY 04/29/04 221,176.00 4.00 3.52 3.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 221,176.00 4.00 3.52 3.20 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 221,176.00 4.00 3.52 3.20

=============== 403-09121 SMA (Fibers) (Asph) Ton ====================================================

IM 0253-186 I-25, 120TH TO SH 7 06/17/04 34,588.00 42.00 49.39 40.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 34,588.00 42.00 49.39 40.00

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 2,526.00 50.00 51.25 49.80NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 30,068.00 48.00 48.66 47.64 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 32,594.00 48.15 48.82 47.81 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 67,182.00 44.99 49.09 43.79

=============== 403-09126 SMA (Asph) (P) Ton ====================================================

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 23,267.00 46.00 46.45 40.95 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 23,267.00 46.00 46.45 40.95 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 23,267.00 46.00 46.45 40.95

=============== 403-09500 Furnish HBP Ton ====================================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 3,000.00 20.00 30.36 34.00STA 114A-009 S.H. 114, W OF COCHETOPA PASS 01/08/04 3,524.00 45.00 57.67 48.00STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 3,954.00 45.00 48.50 50.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 500.00 37.00 35.30 28.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 15,943.00 20.00 24.58 24.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 26,921.00 27.26 32.42 32.15

NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 3,000.00 35.00 26.56 23.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3,000.00 35.00 26.56 23.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 29,921.00 28.04 31.35 31.23

Page 211: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 167 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 403-32741 HBP (Gr SG) (75) (PG 64-22) Ton ====================================================

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 4,883.00 50.00 36.97 37.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4,883.00 50.00 36.97 37.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4,883.00 50.00 36.97 37.00

=============== 403-33701 HBP (Gr S) (75) Ton ====================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 19,694.00 32.00 34.60 33.31 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 19,694.00 32.00 34.60 33.31 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 19,694.00 32.00 34.60 33.31

=============== 403-33721 HBP (Gr S) (75) (PG 58-28) Ton ====================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 7,320.00 40.00 30.61 27.51SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 104.00 100.00 74.33 77.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 7,424.00 40.84 30.84 28.20

STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 7,089.00 33.00 30.44 25.90SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 19,844.00 30.00 33.06 30.00STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 66,323.00 37.00 32.99 29.25STA 0343-023 US 34, EAST OF AKRON 06/17/04 34,200.00 34.00 39.21 35.50STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 773.00 40.00 80.00 75.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 1,856.00 40.00 51.14 50.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 130,085.00 34.99 35.54 31.39

SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 725.00 55.00 64.50 59.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 725.00 55.00 64.50 59.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 138,234.00 35.41 35.13 31.37

=============== 403-33741 HBP (Gr S) (75) (PG 64-22) Ton ====================================================

STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 55,467.00 39.00 33.02 32.65

Page 212: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 168 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 403-33741 HBP (Gr S) (75) (PG 64-22) Ton ====================================================C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 311.00 60.00 53.63 58.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 37,600.00 37.50 41.85 35.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 93,378.00 38.47 36.66 33.68

CC R600-225 CHATFIELD STATE PARK 06/10/04 2,518.00 44.00 39.25 41.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2,518.00 44.00 39.25 41.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1,051.00 40.00 61.64 51.00BR 0243-063 EAST OF LIMON 07/15/04 3,890.00 45.00 62.67 65.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 2,494.00 37.00 42.12 40.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 7,891.00 45.00 46.26 46.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 15,326.00 43.36 50.08 50.19

BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 780.00 55.00 57.93 59.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 780.00 55.00 57.93 59.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 112,002.00 39.37 38.47 36.28

=============== 403-33751 HBP (Gr S) (75) (PG 64-28) Ton ====================================================

STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 15,876.00 35.00 35.20 30.50SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 23,690.00 30.00 37.26 33.90STA 0343-023 US 34, EAST OF AKRON 06/17/04 30,314.00 37.00 44.47 41.80BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 1,355.00 43.00 77.71 76.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 71,235.00 34.34 40.92 37.30 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 71,235.00 34.34 40.92 37.30

=============== 403-33821 HBP (Gr S) (100) (PG 58-28) Ton ====================================================

STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 3,591.00 40.00 36.38 30.00

Page 213: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 169 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 403-33821 HBP (Gr S) (100) (PG 58-28) Ton ====================================================STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 42,788.00 32.00 34.45 30.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 43,540.00 35.00 34.00 34.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 89,919.00 33.77 34.45 31.94

NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 4,733.00 36.00 41.84 35.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4,733.00 36.00 41.84 35.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 94,652.00 33.88 34.78 32.12

=============== 403-33831 HBP (Gr S) (100) (PG 58-34) Ton ====================================================

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 111,715.00 31.00 37.46 32.31 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 111,715.00 31.00 37.46 32.31 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 111,715.00 31.00 37.46 32.31

=============== 403-33841 HBP (Gr S) (100) (PG 64-22) Ton ====================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 381.00 45.00 46.13 50.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 1,716.00 40.00 50.21 50.00NH 2872-016 US 287 - LAMAR 03/04/04 27,438.00 31.00 38.00 37.11NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 53,370.00 29.00 32.61 29.20STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 452.00 45.00 82.19 76.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 22,835.00 32.00 35.00 30.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 106,192.00 30.47 34.93 32.03

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 9,324.00 33.00 32.85 27.18NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 22,675.00 36.00 34.90 30.25NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 31,225.00 32.00 33.88 28.50STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 8,272.00 29.00 28.45 28.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 2,965.00 44.00 53.33 52.00IM 0761-185 I-76, LOCHBUIE TO HUDSON 06/24/04 24,908.00 32.00 35.32 35.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 99,369.00 33.11 34.60 31.16

Page 214: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 170 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 403-33841 HBP (Gr S) (100) (PG 64-22) Ton ====================================================

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 9,790.00 32.00 39.61 36.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 9,790.00 32.00 39.61 36.75

SHE 105A-010 SH 105/FURROW RD 10/07/04 2,495.00 42.00 46.26 43.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 48,744.00 28.00 32.20 31.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 8,111.00 33.00 34.18 33.05NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 207.00 60.00 59.41 58.65STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 374.00 50.00 51.40 37.95 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 59,931.00 29.51 33.08 31.92 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 275,282.00 31.27 34.44 31.86

=============== 403-33851 HBP (Gr S) (100) (PG 64-28) Ton ====================================================

STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 1,791.00 39.00 40.26 34.50NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 48,389.00 35.00 37.48 33.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 50,180.00 35.14 37.58 33.44

STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 9,528.00 34.00 33.88 34.85NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 20,248.00 35.00 38.84 39.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 29,776.00 34.68 37.90 37.94 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 79,956.00 34.97 37.66 35.12

=============== 403-33871 HBP (Gr S) (100) (PG 76-28) Ton ====================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 22,651.00 42.00 39.14 37.50STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 15,323.00 42.00 35.56 32.25STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 29,367.00 42.00 36.19 31.60STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 16,154.00 35.00 36.02 31.37

Page 215: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 171 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 403-33871 HBP (Gr S) (100) (PG 76-28) Ton ====================================================STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 14,514.00 33.00 36.25 36.30STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 8,683.00 35.00 36.03 33.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 13,135.00 36.00 35.39 31.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 1,582.00 40.00 50.11 49.23NH 2872-016 US 287 - LAMAR 03/04/04 23,751.00 36.00 42.26 43.53NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 23,381.00 35.00 39.10 36.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 168,541.00 37.89 37.40 35.34

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 23,442.00 28.00 35.48 32.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 8,364.00 55.00 42.43 41.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 38,278.00 33.00 38.77 32.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 70,084.00 33.95 37.95 33.07

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 5,604.00 45.00 44.57 50.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 5,604.00 45.00 44.57 50.00

NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 7,175.00 42.00 40.16 37.55 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 7,175.00 42.00 40.16 37.55 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 251,404.00 37.07 37.68 35.10

=============== 403-34701 HBP (Gr SX) (75) Ton ====================================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 14,584.00 25.00 25.57 20.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 24,558.00 34.00 33.90 33.08STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 37,158.02 24.00 27.39 26.88STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 6,696.00 28.00 31.50 28.00STA 014A-030 SH 14, WALDEN EAST 03/04/04 34,996.00 23.00 26.03 23.75STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 29,192.00 24.00 25.77 22.30STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 46,539.00 24.00 27.91 22.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 193,723.02 25.30 28.01 24.88

NH 0502-053 CIMARRON - WEST 04/15/04 24,315.00 23.00 27.93 24.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 24,315.00 23.00 27.93 24.00

Page 216: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 172 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 403-34701 HBP (Gr SX) (75) Ton ====================================================

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 15,963.00 25.00 27.99 25.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 10,635.00 36.00 39.34 36.20NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 44,490.00 25.00 29.30 21.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 71,088.00 26.65 30.43 24.61

IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 53,814.00 30.00 34.10 31.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 45,102.00 25.00 31.75 25.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 98,916.00 27.72 32.63 28.58 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 388,042.02 26.02 29.57 25.72

=============== 403-34721 HBP (Gr SX) (75) (PG 58-28) Ton ====================================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 6,022.00 42.00 37.71 36.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 6,022.00 42.00 37.71 36.50

STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 2,818.00 45.00 51.79 41.49STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 5,692.00 55.00 44.99 43.18 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 8,510.00 51.69 49.30 42.62

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 21,652.00 37.50 43.36 37.45 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 21,652.00 37.50 43.36 37.45

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 395.00 110.00 89.60 80.00NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 32,974.00 38.00 42.18 37.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 33,369.00 38.85 43.11 38.20 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 69,553.00 40.27 43.46 38.36

Page 217: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 173 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 403-34731 HBP (Gr SX) (75) (PG 58-34) Ton ====================================================

NH 2852-010 US 285 & COUNTY RD. G 04/29/04 4,548.00 55.00 62.40 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4,548.00 55.00 62.40 60.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4,548.00 55.00 62.40 60.00

=============== 403-34741 HBP (Gr SX) (75) (PG 64-22) Ton ====================================================

STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 32,348.00 34.00 39.15 33.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 32,348.00 34.00 39.15 33.00

IM 0253-186 I-25, 120TH TO SH 7 06/17/04 206.00 50.00 76.62 46.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 206.00 50.00 76.62 46.00

STA R200-128 SH10, SH350 , SH160 MAINT. 07/29/04 16,045.00 42.00 48.90 40.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 16,045.00 42.00 48.90 40.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 48,599.00 36.71 41.96 35.37

=============== 403-34751 HBP (Gr SX) (75) (PG 64-28) Ton ====================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 2,148.00 42.00 38.57 35.10STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 51,934.00 38.00 42.53 38.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 54,082.00 38.16 42.22 38.46

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 10,488.00 40.00 48.93 43.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 10,488.00 40.00 48.93 43.10

NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 30,198.00 37.00 45.13 39.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 30,198.00 37.00 45.13 39.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 94,768.00 37.99 43.75 39.15

Page 218: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 174 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 403-34801 HBP (Gr SX) (100) Ton ====================================================

IM 0701-164 PARACHUTE EAST & WEST 02/12/04 100,402.00 20.00 21.80 21.22IM 0701-157 FRUITA TO CLIFTON 02/26/04 106,305.00 20.00 23.00 18.65 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 206,707.00 20.00 22.47 19.90

STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 22,173.00 22.00 31.46 24.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 22,173.00 22.00 31.46 24.30 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 228,880.00 20.19 23.12 20.32

=============== 403-34841 HBP (Gr SX) (100) (PG 64-22) Ton ====================================================

IM 0704-203 I-70, GENOA-EAST, M.P. 374 - 01/15/04 55,809.00 33.00 41.06 37.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 55,809.00 33.00 41.06 37.50

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 1,059.00 45.00 82.80 80.60IM 0761-185 I-76, LOCHBUIE TO HUDSON 06/24/04 14,550.00 36.00 37.10 36.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 15,609.00 36.61 39.02 39.59

IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 38,392.00 42.00 40.83 40.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 38,392.00 42.00 40.83 40.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 109,810.00 36.66 40.74 38.85

=============== 403-34851 HBP (Gr SX) (100) (PG 64-28) Ton ====================================================

STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 30,057.00 33.00 39.08 36.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 30,057.00 33.00 39.08 36.25

Page 219: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 175 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 403-34851 HBP (Gr SX) (100) (PG 64-28) Ton ====================================================

NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 21,692.00 36.00 38.88 33.00IM 0761-185 I-76, LOCHBUIE TO HUDSON 06/24/04 33,296.00 34.00 41.42 41.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 54,988.00 34.79 40.55 38.30

STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 11,123.00 43.00 54.57 59.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 11,123.00 43.00 54.57 59.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 96,168.00 35.18 40.87 40.05

=============== 403-34871 HBP (Gr SX) (100) (PG 76-28) Ton ====================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 20,555.00 38.00 38.81 38.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 20,555.00 38.00 38.81 38.00

STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 1,135.00 65.00 55.63 54.90NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 251.70 42.00 90.00 80.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,386.70 60.83 60.06 59.46

BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 344.00 60.00 117.56 81.82SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 1,585.00 50.00 77.50 55.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,929.00 51.78 87.34 59.78

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 11,907.00 42.00 36.95 36.00MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 1,125.00 80.00 83.47 80.40STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 7,458.00 40.00 47.08 36.45

Page 220: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 176 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 403-34871 HBP (Gr SX) (100) (PG 76-28) Ton ====================================================STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 17,942.00 40.00 41.18 36.00STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 14,785.00 40.00 43.19 39.50STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 9,488.00 40.00 44.22 41.50STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 15,314.00 40.00 45.53 39.50STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 8,106.00 40.00 43.17 39.70NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 4,136.00 45.00 48.93 45.90 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 90,261.00 40.99 43.39 39.12 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 114,131.70 40.88 42.62 39.52

=============== 403-35701 HBP (Gr S-Fines) (75) Ton ====================================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 13,896.00 25.00 25.19 20.00STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 2,975.00 30.00 29.88 25.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 16,871.00 25.88 25.65 21.01 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 16,871.00 25.88 25.65 21.01

=============== 405-00000 Heating and Scarifying Sq Yard ================================================

NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 62,554.00 1.40 1.80 1.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 62,554.00 1.40 1.80 1.75

NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 135,934.00 1.60 1.63 1.50NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 270,480.00 1.40 1.51 1.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 406,414.00 1.47 1.54 1.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 468,968.00 1.46 1.58 1.53

=============== 405-00100 Heating and Remixing Treatment Sq Yard ================================================

STA 114A-009 S.H. 114, W OF COCHETOPA PASS 01/08/04 140,804.00 3.00 4.32 4.50IM 0701-164 PARACHUTE EAST & WEST 02/12/04 567,620.00 2.75 3.48 2.95STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 158,156.00 3.50 3.81 3.85 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 866,580.00 2.93 3.61 3.37 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 866,580.00 2.93 3.61 3.37

Page 221: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 177 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 405-00300 Heating and Repaving Treatment Sq Yard ================================================

STA 0063-016 CLIFTON TO PALISADE 03/25/04 180,678.00 1.35 2.22 2.15 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 180,678.00 1.35 2.22 2.15 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 180,678.00 1.35 2.22 2.15

=============== 406-09500 Cold Bitum Pvmt (Recycle) Sq Yard ================================================

IM 0701-157 FRUITA TO CLIFTON 02/26/04 670,236.00 1.10 1.68 1.43STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 372,540.00 1.45 1.62 1.35 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,042,776.00 1.23 1.66 1.40 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,042,776.00 1.23 1.66 1.40

=============== 408-01000 Hot Joint-Crack Sealant Ton ====================================================

STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 7.00 3000.00 2637.50 2000.00STA 014A-030 SH 14, WALDEN EAST 03/04/04 22.00 1700.00 1721.67 1700.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 29.00 2013.79 1881.94 1772.41 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 29.00 2013.79 1881.94 1772.41

=============== 409-01010 CC Matl (Ty I) Ton ====================================================

STA 114A-009 S.H. 114, W OF COCHETOPA PASS 01/08/04 2,464.00 30.00 41.33 47.00STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 3,970.00 35.00 28.50 30.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 6,434.00 33.09 34.69 36.51 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6,434.00 33.09 34.69 36.51

=============== 409-01015 CC Matl (Ty I) Sq Yard ================================================

STA R300-120 R-3 SOUTHWEST CHIPSEAL 01/29/04 586,291.00 0.60 0.66 0.55 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 586,291.00 0.60 0.66 0.55 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 586,291.00 0.60 0.66 0.55

Page 222: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 178 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 409-02055 CC Matl (Ty II)(Special) Sq Yard ================================================

STA R400-170 EAST OF HUDSON, EAST 05/27/04 446,558.00 0.70 0.93 0.85STA R400-169 R-4 CHIP SEALS EAST 06/10/04 580,906.00 0.70 1.01 0.94 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,027,464.00 0.70 0.98 0.90 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,027,464.00 0.70 0.98 0.90

=============== 409-05000 Ultrath Bond Wearing Course Sq Yard ================================================

STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 42,963.00 4.50 6.40 5.80 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 42,963.00 4.50 6.40 5.80 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 42,963.00 4.50 6.40 5.80

=============== 411-03342 Asph Cem (PG 64-28) Ton ====================================================

STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 1,494.40 250.00 260.06 250.18STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 2,192.00 245.00 266.89 260.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3,686.40 247.03 265.15 256.02

NH 0502-053 CIMARRON - WEST 04/15/04 613.00 240.00 274.34 265.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 631.00 260.00 278.88 260.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,244.00 250.14 276.64 262.46

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 428.00 275.00 272.50 263.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1,050.00 300.00 277.25 270.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,478.00 292.76 275.27 267.97

IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 2,907.00 270.00 274.50 240.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2,907.00 270.00 274.50 240.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 9,315.40 261.87 270.64 253.78

Page 223: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 179 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 411-03345 Asph Cem (PG 76-28) Ton ====================================================

IM 0701-164 PARACHUTE EAST & WEST 02/12/04 6,258.00 260.00 260.00 241.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 6,209.00 240.00 260.68 255.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 12,467.00 250.04 260.37 247.97

STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 71.01 350.00 346.33 329.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 677.00 270.00 288.88 270.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 748.01 277.59 293.07 275.60 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 13,215.01 251.60 261.71 249.54

=============== 411-03352 Asph Cem (PG 58-28) Ton ====================================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 1,694.00 165.00 191.41 185.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 1,182.00 180.00 199.62 209.76IM 0701-164 PARACHUTE EAST & WEST 02/12/04 354.00 165.00 187.80 180.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 846.71 180.00 174.39 168.17STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 582.00 200.00 203.50 170.00STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 629.00 150.00 182.08 179.00STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 694.00 165.00 190.13 195.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5,981.71 171.92 191.17 186.28

NH 0502-053 CIMARRON - WEST 04/15/04 894.00 170.00 187.95 185.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 894.00 170.00 187.95 185.00

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 563.00 200.00 207.42 210.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1,841.00 200.00 208.75 195.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2,404.00 200.00 208.29 198.51

IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 322.00 210.00 182.17 165.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 322.00 210.00 182.17 165.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 9,601.71 180.05 195.31 188.51

Page 224: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 180 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 411-03354 Asph Cem (PG 64-22) Ton ====================================================

IM 0701-157 FRUITA TO CLIFTON 02/26/04 64.00 190.00 175.71 170.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 992.00 190.00 176.67 170.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,056.00 190.00 176.56 170.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,056.00 190.00 176.56 170.00

=============== 411-03355 Asph Cem (PG 58-34) Ton ====================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 1,473.00 280.00 297.47 312.41STA 014A-030 SH 14, WALDEN EAST 03/04/04 2,100.00 260.00 256.80 250.00STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 1,182.00 260.00 251.26 250.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4,755.00 266.20 269.53 269.33

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 638.50 330.00 294.26 306.51 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 638.50 330.00 294.26 306.51

NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 3,367.00 250.00 276.36 275.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3,367.00 250.00 276.36 275.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8,760.50 264.62 273.91 274.22

=============== 411-10253 Emul Asph (CSS-1H) Gallon =================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 28,471.00 1.00 2.01 2.68NH 2872-016 US 287 - LAMAR 03/04/04 19,553.00 1.00 0.85 0.85 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 48,024.00 1.00 1.65 1.93

SHE 1601-052 R-5, CENTERLINE RUMBLE STRIPS 04/22/04 2,000.00 3.00 6.61 5.00

Page 225: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 181 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 411-10253 Emul Asph (CSS-1H) Gallon =================================================STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 100.00 1.50 1.33 1.07STA 0343-023 US 34, EAST OF AKRON 06/17/04 22,000.00 1.00 1.23 1.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 24,100.00 1.17 1.51 1.33

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 6,148.00 1.50 1.78 1.55 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 6,148.00 1.50 1.78 1.55

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 455.00 2.00 2.53 3.15STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 6,500.00 1.75 1.37 0.50IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 19,075.00 1.30 1.58 1.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 26,030.00 1.42 1.56 0.91 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 104,302.00 1.17 1.61 1.52

=============== 411-10255 Emul Asph (SS) Gallon =================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 9,727.00 1.00 0.99 0.20STA 2911-001 SH 291 SALIDA NORTH 01/08/04 13,115.00 1.00 1.55 1.00IM 0704-203 I-70, GENOA-EAST, M.P. 374 - 01/15/04 21,609.00 1.00 1.22 1.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 10,711.00 1.50 1.02 0.15STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 6,978.00 1.25 0.93 1.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 13,354.00 1.00 0.75 0.20IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 31,085.00 1.80 1.14 1.20STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 21,591.00 0.90 0.86 0.80STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 24,108.00 1.00 0.88 1.07STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 5,998.00 1.00 0.94 0.10STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 3,769.00 2.00 1.10 2.50IM 0701-164 PARACHUTE EAST & WEST 02/12/04 43,464.00 1.00 0.95 1.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 23,992.00 1.00 0.93 0.80STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 4,570.00 1.00 0.87 1.26STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 4,893.00 1.25 2.10 2.20IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 2,341.00 1.20 0.93 0.85STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 6,700.00 1.50 0.97 1.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 37,190.00 0.50 0.89 1.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 477.00 2.00 1.32 1.54STA 014A-030 SH 14, WALDEN EAST 03/04/04 13,709.00 1.00 0.94 1.25STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 43,426.00 1.00 0.93 1.25

Page 226: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 182 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 411-10255 Emul Asph (SS) Gallon =================================================STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 15,356.00 1.00 0.84 1.10STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 10.00 2.00 5.14 3.75NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 8,474.00 1.00 0.78 1.05STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 34,392.00 0.80 0.94 0.85STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 28,793.00 1.25 0.90 0.90 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 429,832.00 1.05 0.97 0.97

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 21,152.00 1.00 0.76 0.87STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 692.00 1.50 1.28 1.26NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 18,982.00 1.00 0.91 0.95STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 552.00 5.00 2.70 3.10STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 1,000.00 1.50 3.26 1.55NH 0741-015 - SMA Alt SH 74 EVERGREEN OVERLAY 04/29/04 10,010.00 1.00 1.27 1.40NH 2852-010 US 285 & COUNTY RD. G 04/29/04 1,936.00 1.00 2.37 1.60STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 28,384.00 1.00 0.92 0.90NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 5,567.00 1.25 1.12 1.00CC R600-225 CHATFIELD STATE PARK 06/10/04 1,304.00 2.00 1.00 1.10IM 0253-186 I-25, 120TH TO SH 7 06/17/04 31,634.00 0.90 0.77 0.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 121,213.00 1.02 0.94 0.80

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 3,119.00 1.00 1.69 1.25STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 15,633.00 1.60 0.95 1.30SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 240.00 3.00 1.63 1.25BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 30.00 5.00 8.06 2.52BR 0243-063 EAST OF LIMON 07/15/04 1,086.00 1.50 2.33 1.50IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1,804.00 2.00 1.30 1.00STA R200-128 SH10, SH350 , SH160 MAINT. 07/29/04 10,895.00 1.00 1.28 1.00SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 720.00 2.00 1.78 1.40NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 2,924.00 1.50 0.88 1.25NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 15,142.00 1.00 1.21 1.60IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 2,610.00 1.50 1.22 0.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 54,203.00 1.29 1.21 1.28

SHE 105A-010 SH 105/FURROW RD 10/07/04 1,193.00 2.00 1.32 0.50IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 12,616.00 1.00 1.05 1.05IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 13,887.00 0.93 1.29 1.10

Page 227: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 183 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 411-10255 Emul Asph (SS) Gallon =================================================MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 295.00 3.50 3.90 3.70STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 3,082.00 1.25 1.28 1.60NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 9,111.00 1.00 1.24 1.74STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 500.00 1.50 1.86 2.00STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 3,920.00 1.00 1.15 1.15NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 14,434.00 2.30 1.07 1.20NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 14,777.00 1.00 1.08 1.20NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 11,494.00 1.50 1.06 1.20STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 5,328.00 1.00 1.31 1.64NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 4,418.00 1.50 1.13 1.50STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 3,624.00 1.00 1.38 1.20NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 1,714.00 2.00 1.18 1.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 100,393.00 1.30 1.17 1.26 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 705,641.00 1.10 1.01 1.00

=============== 411-10261 Emul Asph (RS-2P) Gallon =================================================

STA R400-170 EAST OF HUDSON, EAST 05/27/04 245,607.00 0.86 0.88 0.85STA R400-169 R-4 CHIP SEALS EAST 06/10/04 319,498.00 0.85 0.98 0.85 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 565,105.00 0.85 0.95 0.85 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 565,105.00 0.85 0.95 0.85

=============== 411-10275 Emul Asph (HFMS-2P) Gallon =================================================

STA 114A-009 S.H. 114, W OF COCHETOPA PASS 01/08/04 72,160.00 1.50 1.42 1.32STA R300-120 R-3 SOUTHWEST CHIPSEAL 01/29/04 29,315.00 1.20 1.22 1.10STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 116,209.00 1.60 1.40 1.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 217,684.00 1.51 1.37 1.17 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 217,684.00 1.51 1.37 1.17

=============== 411-10300 Emul Asph (Prime Coat) Gallon =================================================

STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 3,214.00 1.60 1.50 1.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 2,930.00 1.50 1.21 1.15 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 6,144.00 1.55 1.27 1.07

Page 228: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 184 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 411-10300 Emul Asph (Prime Coat) Gallon =================================================

NH 0502-053 CIMARRON - WEST 04/15/04 26,414.00 0.75 1.51 1.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 26,414.00 0.75 1.51 1.10

NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 3,103.00 1.20 2.62 1.90 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3,103.00 1.20 2.62 1.90 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 35,661.00 0.93 1.59 1.16

=============== 411-10375 Emul Asph (HFRS-2P) Gallon =================================================

STA R300-120 R-3 SOUTHWEST CHIPSEAL 01/29/04 234,517.00 0.95 1.01 1.05 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 234,517.00 0.95 1.01 1.05 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 234,517.00 0.95 1.01 1.05

=============== 411-21020 Liq Asph Matl (MC-70) Gallon =================================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 9,803.00 2.00 1.25 0.05C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 295.00 5.00 2.67 2.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 10,098.00 2.09 1.31 0.11

NH 2852-010 US 285 & COUNTY RD. G 04/29/04 3,971.00 3.00 3.03 2.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3,971.00 3.00 3.03 2.10 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 14,069.00 2.35 1.87 0.67

=============== 411-90010 Asph Rejuvenating Agent Gallon =================================================

STA 114A-009 S.H. 114, W OF COCHETOPA PASS 01/08/04 7,036.00 1.50 3.13 2.90

Page 229: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 185 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 411-90010 Asph Rejuvenating Agent Gallon =================================================IM 0701-164 PARACHUTE EAST & WEST 02/12/04 56,762.00 1.10 1.37 2.20STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 9,267.00 1.50 1.43 1.50NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 6,532.00 1.00 2.20 2.30STA 0063-016 CLIFTON TO PALISADE 03/25/04 10,842.00 1.30 1.75 1.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 90,439.00 1.19 1.58 2.13

NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 16,312.00 2.00 2.35 2.45NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 10,008.00 1.50 2.34 2.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 26,320.00 1.81 2.35 2.43 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 116,759.00 1.33 1.75 2.20

=============== 411-90040 Recycling Agent Gallon =================================================

IM 0701-157 FRUITA TO CLIFTON 02/26/04 1,236,865.00 1.25 1.37 1.40STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 241,343.00 1.10 1.15 1.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,478,208.00 1.23 1.34 1.33 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,478,208.00 1.23 1.34 1.33

=============== 412-00000 Furn Conc Pvmt Cubic Yard =============================================

STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 2,868.00 50.00 58.15 51.91 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,868.00 50.00 58.15 51.91 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,868.00 50.00 58.15 51.91

=============== 412-00600 Conc Pvmt (6 In) Sq Yard ================================================

STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 427.00 30.00 35.40 31.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 97,575.00 16.00 17.86 16.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 98,002.00 16.06 17.93 16.56

STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 15.00 45.00 71.18 86.07

Page 230: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 186 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 412-00600 Conc Pvmt (6 In) Sq Yard ================================================STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 1,320.00 40.00 37.35 35.90NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 84.00 45.00 40.41 32.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 280.00 35.00 43.29 48.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,699.00 39.47 38.96 38.14

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 75.00 50.00 47.30 43.38C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 14.00 30.00 57.59 35.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 101.00 100.00 73.33 40.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 190.00 75.11 58.81 40.97 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 99,891.00 16.57 18.22 16.98

=============== 412-00800 Conc Pvmt (8 In) Sq Yard ================================================

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 600.00 22.00 53.33 35.00IM 0701-168 RIFLE TO SILT SLAB REPAIR 08/05/04 6,076.00 40.00 59.06 53.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 6,676.00 38.38 58.32 51.38

NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 545.00 40.00 61.32 44.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 545.00 40.00 61.32 44.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 7,221.00 38.50 58.64 50.83

=============== 412-00801 Conc Pvmt (8 In) (Spec) Sq Yard ================================================

IM 0701-168 RIFLE TO SILT SLAB REPAIR 08/05/04 5,236.00 40.00 71.52 68.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 5,236.00 40.00 71.52 68.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5,236.00 40.00 71.52 68.00

=============== 412-00805 Conc Pvmt (8 In) (Fast Track) Sq Yard ================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 87.00 100.00 55.93 40.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 87.00 100.00 55.93 40.00

Page 231: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 187 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 412-00805 Conc Pvmt (8 In) (Fast Track) Sq Yard ================================================

NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 115.00 100.00 74.55 46.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 115.00 100.00 74.55 46.20 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 202.00 100.00 64.17 43.53

=============== 412-00850 Conc Pvmt (8-1/2 In) Sq Yard ================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 36,074.00 25.00 30.66 28.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 36,074.00 25.00 30.66 28.00

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 265.00 60.00 59.93 52.16 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 265.00 60.00 59.93 52.16

STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 486.00 35.00 56.99 46.44 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 486.00 35.00 56.99 46.44 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 36,825.00 25.38 31.05 28.42

=============== 412-00870 Conc Pvmt (8-1/2 In) (Fast Track) Sq Yard ================================================

STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 1,621.00 60.00 67.25 48.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,621.00 60.00 67.25 48.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,621.00 60.00 67.25 48.00

=============== 412-00900 Conc Pvmt (9 In) Sq Yard ================================================

STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 2,805.00 38.00 35.30 31.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,805.00 38.00 35.30 31.25 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,805.00 38.00 35.30 31.25

Page 232: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 188 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 412-00950 Conc Pvmt (9-1/2 In) Sq Yard ================================================

NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 223.00 72.00 65.52 43.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 223.00 72.00 65.52 43.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 223.00 72.00 65.52 43.00

=============== 412-00975 Conc Pvmt (9-3/4 In) Sq Yard ================================================

NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 32,170.66 50.00 51.15 45.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 32,170.66 50.00 51.15 45.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 32,170.66 50.00 51.15 45.00

=============== 412-00976 Conc Pvmt (9-3/4 In) (Class E) Sq Yard ================================================

NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 2,000.00 25.00 6.00 3.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2,000.00 25.00 6.00 3.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,000.00 25.00 6.00 3.00

=============== 412-01000 Conc Pvmt (10 In) Sq Yard ================================================

NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 10,124.00 29.00 41.99 32.80STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 8,358.00 27.50 38.00 37.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 18,482.00 28.32 41.13 34.70

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 21,554.00 27.00 25.87 27.50C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 7,113.00 35.00 49.20 47.50IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 57.00 75.00 59.09 35.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 28,724.00 29.08 30.94 32.47 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 47,206.00 28.78 34.20 33.34

=============== 412-01001 Conc Pvmt (10 In) (Spec) Sq Yard ================================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1,986.00 50.00 46.59 42.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,986.00 50.00 46.59 42.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,986.00 50.00 46.59 42.00

Page 233: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 189 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 412-01020 Conc Pvmt (10 In) (Fast Track) Sq Yard ================================================

STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 3,126.00 67.00 57.83 56.85 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3,126.00 67.00 57.83 56.85 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3,126.00 67.00 57.83 56.85

=============== 412-01025 Conc Pvmt (10-1/4 In) Sq Yard ================================================

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 107,446.00 25.00 31.52 27.63 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 107,446.00 25.00 31.52 27.63 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 107,446.00 25.00 31.52 27.63

=============== 412-01050 Conc Pvmt (10-1/2 In) Sq Yard ================================================

STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 10,898.00 20.00 32.79 27.72 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 10,898.00 20.00 32.79 27.72

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 3,852.00 46.00 45.80 45.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3,852.00 46.00 45.80 45.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 14,750.00 26.79 35.27 32.23

=============== 412-01100 Conc Pvmt (11 In) Sq Yard ================================================

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 545.00 45.00 56.97 49.44 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 545.00 45.00 56.97 49.44 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 545.00 45.00 56.97 49.44

=============== 412-01120 Conc Pvmt (11 In) (Fast Track) Sq Yard ================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 75.00 80.00 75.15 60.00

Page 234: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 190 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 412-01120 Conc Pvmt (11 In) (Fast Track) Sq Yard ================================================STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 800.00 75.00 86.48 53.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 2,336.00 80.00 59.31 45.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3,211.00 78.75 65.30 47.34

STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 83.00 80.00 75.40 63.09 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 83.00 80.00 75.40 63.09 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3,294.00 78.79 65.48 47.74

=============== 412-01200 Conc Pvmt (12 In) Sq Yard ================================================

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 72,909.00 30.00 28.84 29.35 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 72,909.00 30.00 28.84 29.35 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 72,909.00 30.00 28.84 29.35

=============== 412-01250 Conc Pvmt (12-1/2 In) Sq Yard ================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 12,344.00 30.00 39.34 38.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 12,344.00 30.00 39.34 38.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 12,344.00 30.00 39.34 38.00

=============== 412-01350 Conc Pvmt (13-1/2 In) Sq Yard ================================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 5,558.00 42.00 51.88 55.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 5,558.00 42.00 51.88 55.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5,558.00 42.00 51.88 55.00

=============== 412-05000 Partial Depth Repair of Conc Pvmt Sq Foot ================================================

NH 5502-045 US550, DURANGO JOINT SEAL 01/08/04 1,100.00 70.00 56.17 36.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,100.00 70.00 56.17 36.00

Page 235: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 191 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 412-05000 Partial Depth Repair of Conc Pvmt Sq Foot ================================================

NH 1602-101 SOUTH FORK JOINT SEAL 05/13/04 192.00 100.00 68.67 54.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 192.00 100.00 68.67 54.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,292.00 74.46 57.17 38.67

=============== 412-14000 Sawing and Sealing Joints Lin Foot ===============================================

NH 5502-045 US550, DURANGO JOINT SEAL 01/08/04 180,164.00 1.60 1.67 1.39 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 180,164.00 1.60 1.67 1.39

NH 1602-101 SOUTH FORK JOINT SEAL 05/13/04 195,517.00 1.40 1.46 1.28NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 26,700.00 2.00 1.88 1.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 222,217.00 1.47 1.53 1.33 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 402,381.00 1.53 1.61 1.36

=============== 412-15000 Routing and Sealing Cracks Lin Foot ===============================================

NH 5502-045 US550, DURANGO JOINT SEAL 01/08/04 2,022.00 5.00 4.71 4.05 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,022.00 5.00 4.71 4.05

NH 1602-101 SOUTH FORK JOINT SEAL 05/13/04 12,002.00 2.75 3.78 3.23NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 500.00 4.00 3.93 3.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 12,502.00 2.80 3.78 3.24 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 14,524.00 3.11 4.01 3.36

=============== 412-15050 Cross Stitching Each ===================================================

NH 2873-137 US 287 IN BOULDER & LARIMER C 11/18/04 308.00 80.00 30.76 12.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 308.00 80.00 30.76 12.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 308.00 80.00 30.76 12.50

Page 236: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 192 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 420-00000 Geomembrane Sq Yard ================================================

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 2,500.00 20.00 15.38 12.90 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2,500.00 20.00 15.38 12.90 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,500.00 20.00 15.38 12.90

=============== 420-00100 Geotextile (Er Cont) (CL A) Sq Yard ================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 793.00 1.40 3.73 2.23STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 4,311.00 1.50 1.50 1.05STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1,662.00 1.10 1.60 1.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 6,766.00 1.39 1.79 1.32

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 262.00 4.00 3.64 4.14SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 144.00 2.00 27.66 7.80NH 2852-010 US 285 & COUNTY RD. G 04/29/04 740.00 2.00 2.72 3.35NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 328.00 2.00 3.24 3.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,474.00 2.36 5.23 4.00

BR 0243-063 EAST OF LIMON 07/15/04 40.00 5.00 6.96 4.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 49.00 3.00 7.84 5.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 2,100.00 2.00 3.58 3.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 330.00 2.00 2.68 1.85NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 250.00 3.50 2.90 2.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2,769.00 2.20 3.51 2.83

C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 206.00 5.00 6.00 4.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 3.00 3.00 46.12 32.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 209.00 4.97 7.68 4.40 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 11,218.00 1.78 2.68 2.11

Page 237: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 193 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 420-00101 Geotextile (Er Cont) (CL B) Sq Yard ================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 639.00 3.00 3.43 2.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 639.00 3.00 3.43 2.50

IM 0253-186 I-25, 120TH TO SH 7 06/17/04 224.00 3.00 3.07 2.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 224.00 3.00 3.07 2.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 481.00 2.00 3.21 3.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 96.00 3.00 4.28 2.50IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 145.00 4.00 9.43 2.30NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 60.00 10.00 3.10 3.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 782.00 3.11 3.99 2.82 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,645.00 3.05 3.62 2.59

=============== 420-00110 Geotextile (Drain) (CL A) Sq Yard ================================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 2,778.00 2.70 1.18 0.85 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,778.00 2.70 1.18 0.85

NH 0502-053 CIMARRON - WEST 04/15/04 97.00 3.00 5.15 5.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 97.00 3.00 5.15 5.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 584.00 2.50 3.94 3.80NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 284.00 2.00 5.25 4.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 254.00 3.00 3.03 2.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,122.00 2.49 4.04 3.44 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3,997.00 2.65 2.70 1.68

Page 238: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 194 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 420-00130 Geotextile (Separator) (CL A) Sq Yard ================================================

STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 373.00 2.00 2.12 2.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 373.00 2.00 2.12 2.00

STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 300.00 3.00 3.18 4.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 600.00 2.00 4.50 5.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 900.00 2.33 3.84 4.67 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,273.00 2.24 3.01 3.89

=============== 420-00131 Geotextile (Separator) (CL B) Sq Yard ================================================

SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 1,630.00 2.00 2.39 1.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,630.00 2.00 2.39 1.50

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 88,823.00 1.10 1.60 0.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 88,823.00 1.10 1.60 0.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 90,453.00 1.12 1.62 0.52

=============== 420-00200 Geotextile (Weed Barrier) Sq Yard ================================================

C 0342-040 US 34 IN WELD COUNTY 01/29/04 470.00 2.00 2.87 1.41 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 470.00 2.00 2.87 1.41 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 470.00 2.00 2.87 1.41

=============== 420-00500 Geotextile (Paving) Sq Yard ================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 1,764.00 2.00 3.07 1.30

Page 239: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 195 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 420-00500 Geotextile (Paving) Sq Yard ================================================STA 2911-001 SH 291 SALIDA NORTH 01/08/04 930.00 5.00 2.90 3.00IM 0704-203 I-70, GENOA-EAST, M.P. 374 - 01/15/04 537.00 3.00 3.53 2.50STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 102,601.00 1.00 0.90 0.65STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 266,952.00 1.00 0.85 0.65IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 12,415.00 3.00 1.34 0.75STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 319.00 3.00 11.00 20.50STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 91,239.00 0.80 0.79 0.53STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 71,680.00 1.00 1.05 1.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 1,200.00 3.00 7.50 5.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 748.00 1.75 7.50 3.50STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 122,555.00 0.80 0.92 0.50STA 0063-016 CLIFTON TO PALISADE 03/25/04 1,613.00 1.60 3.33 3.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 674,553.00 0.99 0.92 0.68

NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 455.00 3.00 10.50 1.00STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 51,184.00 1.50 1.24 1.24NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1,213.00 10.00 3.29 2.10IM 0253-186 I-25, 120TH TO SH 7 06/17/04 311,630.00 0.65 0.87 0.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 364,482.00 0.80 0.93 0.78

SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 400.00 4.00 3.55 1.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 400.00 4.00 3.55 1.70

IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 1,820.00 2.10 3.88 1.50STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 1,060.00 3.50 8.00 8.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 61,635.00 1.00 1.11 1.20STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 129,347.00 1.00 1.01 1.00STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 97,650.00 2.00 1.04 1.15STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 78,406.00 2.00 1.05 1.20STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 70,986.00 1.00 1.06 1.15 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 440,904.00 1.41 1.07 1.14 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,480,339.00 1.07 0.96 0.84

=============== 420-00510 Geotextile (Cr Reduc) (H D) Sq Yard ================================================

IM 0701-157 FRUITA TO CLIFTON 02/26/04 1,092.00 15.00 14.75 15.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,092.00 15.00 14.75 15.00

Page 240: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 196 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 420-00510 Geotextile (Cr Reduc) (H D) Sq Yard ================================================

NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 2,000.00 8.00 12.93 14.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2,000.00 8.00 12.93 14.60 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3,092.00 10.47 13.57 14.74

=============== 502-00100 Drill Hole Fac Pile Driving Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 625.00 38.00 9.80 9.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 70.00 100.00 38.50 62.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 695.00 44.24 10.58 14.34

SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 108.00 100.00 61.22 67.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 108.00 100.00 61.22 67.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 803.00 51.74 14.51 21.49

=============== 502-00400 End Plate Each ===================================================

BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 72.00 60.00 91.82 89.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 72.00 60.00 91.82 89.25 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 72.00 60.00 91.82 89.25

=============== 502-00460 Pile Tip Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 44.00 100.00 82.88 60.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 28.00 87.00 108.00 130.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 72.00 94.94 86.32 87.22

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 10.00 120.00 92.43 125.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 10.00 120.00 92.43 125.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 82.00 98.00 86.99 91.83

Page 241: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 197 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 502-08375 SP Pile (12-3/4x0.375 In) Lin Foot ===============================================

BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 4,555.00 23.00 39.14 36.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4,555.00 23.00 39.14 36.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 2,804.00 20.00 45.00 45.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2,804.00 20.00 45.00 45.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 7,359.00 21.86 41.17 39.43

=============== 502-11057 Steel Pile (HP 10x57) Lin Foot ===============================================

SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 137.00 70.00 127.50 135.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 137.00 70.00 127.50 135.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 137.00 70.00 127.50 135.00

=============== 502-11253 Steel Pile (HP 12x53) Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 954.00 25.00 31.88 32.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 954.00 25.00 31.88 32.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 954.00 25.00 31.88 32.00

=============== 502-11274 Steel Pile (HP 12x74) Lin Foot ===============================================

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 530.00 42.00 45.96 44.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 530.00 42.00 45.96 44.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 530.00 42.00 45.96 44.00

=============== 502-11489 Steel Pile (HP 14x89) Lin Foot ===============================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 953.00 25.50 42.50 40.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 953.00 25.50 42.50 40.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 953.00 25.50 42.50 40.00

Page 242: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 198 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 503-00018 Drilled Caisson (18 In) Lin Foot ===============================================

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 4.00 80.00 157.26 200.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 20.00 70.00 96.08 96.30NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 10.00 70.00 162.25 190.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 34.00 71.18 118.33 136.06 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 34.00 71.18 118.33 136.06

=============== 503-00024 Drilled Caisson (24 In) Lin Foot ===============================================

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 20.00 100.00 61.86 6.90 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 20.00 100.00 61.86 6.90

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 185.00 65.00 82.44 55.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 185.00 65.00 82.44 55.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 205.00 68.41 80.90 50.31

=============== 503-00030 Drilled Caisson (30 In) Lin Foot ===============================================

SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 13.00 150.00 69.50 88.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 13.00 150.00 69.50 88.00

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 707.00 120.00 164.93 180.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 707.00 120.00 164.93 180.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1,203.00 65.00 75.58 74.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,203.00 65.00 75.58 74.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,923.00 85.80 100.57 113.07

Page 243: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 199 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 503-00036 Drilled Caisson (36 In) Lin Foot ===============================================

C 0342-040 US 34 IN WELD COUNTY 01/29/04 68.00 218.00 168.33 85.89NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 58.00 200.00 142.53 142.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 266.00 150.00 164.12 115.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 19.00 220.00 161.26 135.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 45.00 200.00 200.00 200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 456.00 174.35 163.15 123.31

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 60.00 180.00 112.39 62.10ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 30.00 500.00 443.95 312.12IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 270.00 220.00 103.55 100.12SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 72.00 300.00 186.14 178.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 72.00 110.00 104.72 37.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 504.00 227.62 124.71 110.32

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 57.00 200.00 139.84 165.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 120.00 150.00 218.91 219.35C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 45.00 200.00 185.20 170.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 222.00 172.97 197.72 195.39 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,182.00 196.81 150.79 131.31

=============== 503-00042 Drilled Caisson (42 In) Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 140.00 220.00 239.22 180.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 19.00 200.00 417.43 206.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 34.00 250.00 242.50 235.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 193.00 223.32 257.33 192.25

C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 17.00 220.00 178.40 185.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 40.00 200.00 352.00 260.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 57.00 205.96 291.77 237.63

Page 244: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 200 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 503-00042 Drilled Caisson (42 In) Lin Foot ===============================================

SHE 5502-047 SH550 AT MP 112.7, IN OURAY C 10/07/04 30.00 300.00 510.57 393.10BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1,055.00 150.00 130.06 120.00C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 94.00 250.00 286.72 212.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,179.00 161.79 159.24 134.32 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,429.00 171.86 184.42 146.27

=============== 503-00048 Drilled Caisson (48 In) Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 41.00 280.00 292.31 160.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 42.00 200.00 456.55 224.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 21.00 250.00 187.67 156.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 42.00 210.00 235.72 195.00C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 201.00 200.00 294.00 294.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 84.00 275.00 280.00 260.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 431.00 225.64 308.50 251.43

C R200-126 FY04 REGION 2 SIGNING 04/01/04 109.00 200.00 407.17 392.00SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 84.00 220.00 157.36 71.30ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 62.00 800.00 652.83 436.97IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 244.00 300.00 176.10 156.77IM 0253-186 I-25, 120TH TO SH 7 06/17/04 31.50 250.00 220.82 210.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 530.50 322.25 239.64 227.48

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 21.00 200.00 346.69 347.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 21.00 200.00 346.69 347.75

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 73.50 150.00 226.27 258.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 21.00 200.00 206.07 190.00

Page 245: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 201 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 503-00048 Drilled Caisson (48 In) Lin Foot ===============================================C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 145.00 280.00 309.59 240.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 239.50 233.09 273.24 241.14 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,222.00 268.60 267.02 240.67

=============== 503-00054 Drilled Caisson (54 In) Lin Foot ===============================================

C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 100.00 300.00 372.00 372.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 21.00 300.00 360.00 320.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 121.00 300.00 368.45 362.98

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 939.00 250.00 356.62 370.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 939.00 250.00 356.62 370.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 392.00 250.00 188.11 225.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 46.00 225.00 220.96 210.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 438.00 247.37 190.49 223.42 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,498.00 253.27 291.40 326.58

=============== 503-01060 M pile (6 In) Lin Foot ===============================================

STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 2,025.00 74.00 87.25 64.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2,025.00 74.00 87.25 64.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,025.00 74.00 87.25 64.00

=============== 503-01120 M Pile (12 In) Lin Foot ===============================================

STA 149A-021 SH 149 CRIBWALL 09/16/04 6,000.00 85.00 81.00 81.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 6,000.00 85.00 81.00 81.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6,000.00 85.00 81.00 81.00

Page 246: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 202 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 504-03500 Retaining Wall(Design Build) Sq Foot ================================================

ER 0702-255 I-70 GLENWOOD CANYON 11/30/04 1,160.00 280.00 315.33 315.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,160.00 280.00 315.33 315.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,160.00 280.00 315.33 315.00

=============== 504-04410 Block Facing Sq Foot ================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 77,910.00 19.00 6.35 5.48 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 77,910.00 19.00 6.35 5.48

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 65,242.00 10.00 8.34 4.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 65,242.00 10.00 8.34 4.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 7,870.00 10.00 13.96 8.50STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 4,686.00 19.00 7.62 7.50NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 6,100.00 11.00 6.23 5.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 18,656.00 12.59 10.41 7.14

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 11,128.00 8.50 10.58 13.00STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 300.00 60.00 43.00 50.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 11,428.00 9.85 11.15 13.97 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 173,236.00 14.32 7.81 5.66

=============== 504-04420 Precast Panel Facing Sq Foot ================================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 13,965.00 17.00 12.00 13.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 13,965.00 17.00 12.00 13.00

Page 247: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 203 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 504-04420 Precast Panel Facing Sq Foot ================================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 10,254.00 15.00 30.70 43.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 10,254.00 15.00 30.70 43.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 24,219.00 16.15 23.12 25.70

=============== 504-06100 Ground Nailed Wall Sq Foot ================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 29,123.00 30.00 34.52 25.94 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 29,123.00 30.00 34.52 25.94

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 3,030.00 40.00 44.84 45.15 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 3,030.00 40.00 44.84 45.15 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 32,153.00 30.94 35.34 27.75

=============== 504-06501 Perm Tieback Anchor Sys Sq Foot ================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 5,794.00 97.00 49.37 25.94 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5,794.00 97.00 49.37 25.94 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5,794.00 97.00 49.37 25.94

=============== 504-08100 Timber Retaining Wall Sq Foot ================================================

STA 149A-021 SH 149 CRIBWALL 09/16/04 450.00 20.00 23.00 23.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 450.00 20.00 23.00 23.00

STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 300.00 40.00 42.00 50.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 300.00 40.00 42.00 50.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 750.00 28.00 36.82 33.80

Page 248: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 204 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 504-08255 Masonry Landscape Wall (Dry Stack) Sq Foot ================================================

STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 1,287.00 20.00 17.52 22.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,287.00 20.00 17.52 22.00

STA 149A-021 SH 149 CRIBWALL 09/16/04 405.00 25.00 31.00 31.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 405.00 25.00 31.00 31.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,692.00 21.20 18.10 24.15

=============== 506-00000 Riprap Cubic Yard =============================================

STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 3.50 100.00 340.00 330.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3.50 100.00 340.00 330.00

STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 19.50 70.00 67.81 57.28 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 19.50 70.00 67.81 57.28 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 23.00 74.57 81.09 98.78

=============== 506-00005 Riprap Sq Yard ================================================

STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 2,000.00 5.00 16.46 1.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,000.00 5.00 16.46 1.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,000.00 5.00 16.46 1.50

=============== 506-00010 Riprap (Special) Cubic Yard =============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 834.00 45.00 39.60 38.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 834.00 45.00 39.60 38.00

Page 249: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 205 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 506-00010 Riprap (Special) Cubic Yard =============================================

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 224.00 50.00 46.31 55.98 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 224.00 50.00 46.31 55.98 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,058.00 46.06 40.72 41.81

=============== 506-00030 Grouted Riprap Cubic Yard =============================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 782.00 100.00 98.00 105.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 782.00 100.00 98.00 105.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 782.00 100.00 98.00 105.00

=============== 506-00105 Riprap (Gabions) (PVC) Cubic Yard =============================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 167.00 90.00 145.00 150.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 167.00 90.00 145.00 150.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 167.00 90.00 145.00 150.00

=============== 506-00206 Riprap (6 In) Cubic Yard =============================================

C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 0.70 170.00 518.21 435.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 0.70 170.00 518.21 435.00

SHE 105A-010 SH 105/FURROW RD 10/07/04 18.00 100.00 80.93 75.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 15.00 65.00 254.00 160.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 8.00 70.00 96.71 105.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 41.00 81.34 145.43 111.95 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 41.70 82.83 152.63 117.37

Page 250: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 206 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 506-00209 Riprap (9 In) Cubic Yard =============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 129.00 50.00 50.43 50.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 20.00 60.00 110.00 100.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1,380.00 31.00 42.30 36.90STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 176.00 35.00 51.50 70.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,705.00 33.19 43.83 42.05

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 8.00 50.00 169.00 100.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 7.60 80.00 77.08 53.72STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 8.00 60.00 114.54 95.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 130.00 50.00 41.64 46.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 102.00 50.00 55.04 58.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 8.00 60.00 139.29 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 263.60 51.47 56.99 55.63

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 236.00 40.00 59.49 73.00SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 4.00 100.00 80.00 100.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 17.00 100.00 100.83 60.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 119.00 80.00 68.77 50.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 376.00 56.01 62.89 65.42

SHE 105A-010 SH 105/FURROW RD 10/07/04 53.00 80.00 72.51 75.00C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 100.00 110.00 135.00 120.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 194.00 60.00 43.54 65.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 50.00 60.00 56.23 45.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 397.00 75.26 59.13 77.67 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,741.60 44.17 48.87 51.72

=============== 506-00212 Riprap (12 In) Cubic Yard =============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 166.00 50.00 102.98 47.89

Page 251: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 207 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 506-00212 Riprap (12 In) Cubic Yard =============================================IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 125.00 55.00 48.77 52.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 12.00 50.00 115.00 110.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 2,060.00 30.00 35.50 40.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,363.00 32.83 49.18 41.54

NH 0502-053 CIMARRON - WEST 04/15/04 64.00 60.00 57.36 60.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 62.00 35.00 77.05 65.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 167.00 60.00 41.09 43.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 20.00 45.00 67.25 88.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 313.00 54.09 51.65 53.71

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 90.00 60.00 63.95 78.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 6.00 85.00 170.82 183.64STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 14.00 60.00 89.70 40.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 112.00 48.00 53.22 65.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 222.00 54.62 62.94 71.90

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 10.00 70.00 91.71 105.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 18.00 70.00 198.33 125.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 28.00 70.00 142.21 117.86 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,926.00 37.11 52.45 45.88

=============== 506-00218 Riprap (18 In) Cubic Yard =============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 15.00 55.00 111.98 47.89NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 50.00 32.00 60.00 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 65.00 37.31 84.62 57.20

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 10.50 80.00 84.31 50.76

Page 252: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 208 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 506-00218 Riprap (18 In) Cubic Yard =============================================IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 191.00 60.00 40.25 44.05 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 201.50 61.04 43.16 44.40

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 143.50 75.00 103.50 140.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 143.50 75.00 103.50 140.00

BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 67.00 60.00 66.46 39.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 20.00 50.00 76.65 110.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 50.00 60.00 83.59 64.35 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 137.00 58.54 71.89 58.62 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 547.00 61.26 65.15 74.56

=============== 506-00224 Riprap (24 In) Cubic Yard =============================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 519.00 27.00 34.00 40.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 519.00 27.00 34.00 40.00

CC R600-225 CHATFIELD STATE PARK 06/10/04 52.00 50.00 59.13 53.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 52.00 50.00 59.13 53.00

BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 12.00 100.00 149.63 100.07STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 44.00 65.00 117.04 40.00STA 149A-021 SH 149 CRIBWALL 09/16/04 14.00 40.00 109.00 109.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 70.00 66.00 120.97 64.10 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 641.00 33.12 52.94 43.69

=============== 506-01020 Geogrid Reinforce Sq Yard ================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 31,723.00 7.00 3.74 3.74 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 31,723.00 7.00 3.74 3.74

Page 253: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 209 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 506-01020 Geogrid Reinforce Sq Yard ================================================

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 10,800.00 5.00 2.28 1.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 10,800.00 5.00 2.28 1.70 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 42,523.00 6.49 3.47 3.22

=============== 506-01100 Conc Block Revetment Sq Yard ================================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 138.00 38.00 49.00 52.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 138.00 38.00 49.00 52.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 138.00 38.00 49.00 52.00

=============== 507-00000 Conc S and D Pave Cubic Yard =============================================

IM 0701-157 FRUITA TO CLIFTON 02/26/04 6.00 350.00 509.17 380.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 3.90 200.00 394.77 440.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 9.90 290.91 459.83 403.64

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 25.00 280.00 257.68 192.55STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 12.00 400.00 351.50 521.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 37.00 318.92 294.29 299.07

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 12.00 300.00 241.19 300.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 2.10 500.00 498.33 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 14.10 329.79 279.49 329.79 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 61.00 316.89 328.35 323.14

=============== 507-00100 Conc S and D Pave (Reinf) Cubic Yard =============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 121.00 300.00 307.87 335.00

Page 254: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 210 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 507-00100 Conc S and D Pave (Reinf) Cubic Yard =============================================STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 53.00 300.00 270.00 290.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 174.00 300.00 304.13 321.29

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 44.00 275.00 333.99 418.74SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 8.00 500.00 594.38 360.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 52.00 309.62 358.50 409.70

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1.00 350.00 629.91 570.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 18.00 300.00 626.25 615.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 19.00 302.63 626.53 612.63

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 132.00 250.00 263.39 250.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 29.00 250.00 332.00 250.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 161.00 250.00 272.16 250.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 406.00 281.53 310.22 317.98

=============== 507-00350 Gr Riprap S and D Pave Cubic Yard =============================================

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 7.00 300.00 292.86 290.00NH 0502-053 CIMARRON - WEST 04/15/04 98.00 150.00 130.04 125.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 22.00 120.00 118.66 137.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 127.00 153.07 134.18 136.23 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 127.00 153.07 134.18 136.23

=============== 507-00400 Bitum S and D Pave (Asph) Ton ====================================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 216.00 120.00 115.94 98.00C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 1.40 100.00 340.10 147.00

Page 255: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 211 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 507-00400 Bitum S and D Pave (Asph) Ton ====================================================IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 6.00 150.00 96.45 85.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 2.00 120.00 237.83 235.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 225.40 120.67 118.52 99.17

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 7.00 100.00 285.80 300.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 6.00 150.00 174.16 130.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 13.00 123.08 240.39 221.54

BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 12.00 200.00 348.37 373.11BR 0243-063 EAST OF LIMON 07/15/04 55.00 120.00 123.58 135.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 67.00 134.33 163.84 177.65

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 9.00 100.00 168.69 170.00C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 1.00 150.00 490.56 268.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 2,618.00 100.00 76.17 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2,628.00 100.02 76.61 60.46 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,933.40 102.49 80.52 66.82

=============== 507-00550 Concrete Lined Ditch Lin Foot ===============================================

STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 30.00 30.00 31.30 30.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 30.00 30.00 31.30 30.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 30.00 30.00 31.30 30.00

=============== 508-00520 Insulation Material (2 In) Sq Foot ================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 21,650.00 1.00 1.37 2.23 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 21,650.00 1.00 1.37 2.23 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 21,650.00 1.00 1.37 2.23

Page 256: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 212 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 509-00000 Str Steel Pound ==================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 8,642.00 1.50 2.09 1.78 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 8,642.00 1.50 2.09 1.78

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 1,861,451.00 1.12 1.16 1.12SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 18,950.00 2.50 2.11 2.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,880,401.00 1.13 1.17 1.13

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 768.00 10.00 2.62 3.10BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 3,022.00 5.50 9.83 16.68BR 0243-063 EAST OF LIMON 07/15/04 7,460.00 8.00 7.52 7.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 149,733.00 1.50 2.43 2.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 160,983.00 1.92 2.66 2.70 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,050,026.00 1.20 1.26 1.26

=============== 509-00010 Str Steel (Spec) Pound ==================================================

BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 9,800.00 6.00 2.47 2.05 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 9,800.00 6.00 2.47 2.05 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 9,800.00 6.00 2.47 2.05

=============== 510-00138 Str PP (138 In) Lin Foot ===============================================

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 66.00 500.00 943.06 856.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 66.00 500.00 943.06 856.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 66.00 500.00 943.06 856.00

=============== 510-20100 Str PA(Spec) Lin Foot ===============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 79.00 1500.00 1219.04 1954.22 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 79.00 1500.00 1219.04 1954.22 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 79.00 1500.00 1219.04 1954.22

Page 257: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 213 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 512-00101 Bearing Device (Type I) Each ===================================================

SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 8.00 400.00 726.25 800.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 8.00 400.00 726.25 800.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8.00 400.00 726.25 800.00

=============== 512-00102 Bearing Device (Type II) Each ===================================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 64.00 2800.00 2295.85 2105.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 64.00 2800.00 2295.85 2105.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 64.00 2800.00 2295.85 2105.00

=============== 512-00103 Bearing Device (Type III) Each ===================================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 4.00 6000.00 5597.86 5000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4.00 6000.00 5597.86 5000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 6000.00 5597.86 5000.00

=============== 513-00600 Bridge Drain Each ===================================================

BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 4.00 2500.00 4128.57 3000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4.00 2500.00 4128.57 3000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 2500.00 4128.57 3000.00

=============== 513-00690 Bridge Drain (Spec) Each ===================================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 2.00 2650.00 2500.00 2600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 2650.00 2500.00 2600.00

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 6.00 2250.00 11882.56 10907.91

Page 258: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 214 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 513-00690 Bridge Drain (Spec) Each ===================================================SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 4.00 2260.00 1918.75 2500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 10.00 2254.00 9133.92 7544.75

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 10.00 4500.00 3723.90 4070.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 10.00 4500.00 3723.90 4070.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 4.00 2000.00 4200.71 5000.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 3.00 13000.00 4484.78 4000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 7.00 6714.29 4295.40 4571.43 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 29.00 4132.41 6111.29 5287.84

=============== 514-00000 Pipe Railing Lin Foot ===============================================

STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 90.00 150.00 61.88 74.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 90.00 150.00 61.88 74.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 90.00 150.00 61.88 74.00

=============== 514-00100 Hand Rail Lin Foot ===============================================

STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 50.00 50.00 60.33 12.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 50.00 50.00 60.33 12.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 50.00 50.00 60.33 12.00

=============== 514-00200 Pedestrian Railing (Steel) Lin Foot ===============================================

C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 82.00 100.00 86.80 82.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 82.00 100.00 86.80 82.00

Page 259: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 215 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 514-00200 Pedestrian Railing (Steel) Lin Foot ===============================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1,130.00 150.00 133.70 125.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,130.00 150.00 133.70 125.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,212.00 146.62 131.03 122.09

=============== 514-00300 Traffic Railing (Steel) Lin Foot ===============================================

ER 0702-255 I-70 GLENWOOD CANYON 11/30/04 250.00 25.00 142.00 150.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 250.00 25.00 142.00 150.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 250.00 25.00 142.00 150.00

=============== 514-01011 Bridge Rail (Steel) Lin Foot ===============================================

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 1,022.00 40.00 37.66 37.82 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,022.00 40.00 37.66 37.82 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,022.00 40.00 37.66 37.82

=============== 514-01050 Hand and Bikeway Railing Lin Foot ===============================================

STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 103.00 50.00 76.67 80.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 103.00 50.00 76.67 80.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 103.00 50.00 76.67 80.00

=============== 515-00120 Waterproofing (Membrane) Sq Yard ================================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 890.00 13.00 13.83 14.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 446.00 10.00 12.55 11.30SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 206.00 15.00 13.00 11.50STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 2,013.00 7.25 7.50 8.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3,555.00 9.48 11.32 10.12

Page 260: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 216 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 515-00120 Waterproofing (Membrane) Sq Yard ================================================

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 572.00 10.00 26.40 25.50NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 467.00 10.00 16.63 15.50STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 186.00 10.00 14.24 11.15SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 412.00 9.00 12.46 8.50STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 118.00 13.00 33.00 20.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 948.00 9.00 9.30 7.30BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 2,342.00 10.00 8.52 7.85 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 5,045.00 9.80 11.75 10.91

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1,512.00 10.00 9.06 8.50BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 1,907.00 6.00 9.20 8.87BR 0243-063 EAST OF LIMON 07/15/04 671.00 10.00 9.95 9.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 21,517.00 7.00 7.52 7.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 557.00 12.00 10.73 15.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 26,164.00 7.28 7.87 7.44

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 4,337.00 8.00 7.85 7.50BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 4,898.00 8.00 6.92 6.69MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 3,843.00 9.00 9.42 8.25STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 915.00 7.00 11.67 10.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 412.00 10.00 9.98 12.00STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 68.00 25.00 32.13 19.35 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 14,473.00 8.34 8.23 7.77 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 49,237.00 8.01 8.71 8.09

=============== 515-00400 Concrete Sealer Sq Yard ================================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 4.00 8.00 128.59 200.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 3,225.00 4.00 4.70 3.50STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 112.00 6.00 14.00 16.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3,341.00 4.07 4.93 4.15

Page 261: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 217 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 515-00400 Concrete Sealer Sq Yard ================================================

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 544.00 8.00 8.44 3.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 544.00 8.00 8.44 3.60

BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 1,052.00 6.00 7.29 8.34BR 0243-063 EAST OF LIMON 07/15/04 295.00 10.00 8.26 10.00SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 2.00 40.00 83.00 112.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 384.00 4.00 6.63 12.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,733.00 6.28 7.27 9.55

NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 45.00 6.00 43.45 4.25NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 80.00 10.00 14.53 24.60IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 6.00 20.00 200.83 400.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 412.00 5.00 4.99 4.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 543.00 5.99 9.89 11.89 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6,161.00 5.21 5.97 6.31

=============== 515-00410 Concrete Sealer (Calcium Nitrite) Sq Yard ================================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 15.00 30.00 61.50 80.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 12.00 50.00 122.33 55.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 46.00 25.00 143.75 25.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 73.00 30.14 123.33 41.23

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 544.00 80.00 26.89 6.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 544.00 80.00 26.89 6.00

BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 93.00 40.00 50.30 49.59

Page 262: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 218 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 515-00410 Concrete Sealer (Calcium Nitrite) Sq Yard ================================================BR 0243-063 EAST OF LIMON 07/15/04 160.00 33.00 18.69 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 253.00 35.57 30.31 24.55

IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 4.00 50.00 266.67 500.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 33.00 50.00 44.50 43.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 37.00 50.00 57.20 92.41 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 907.00 62.37 35.09 17.54

=============== 517-00100 Waterproofing (Railroad) Sq Yard ================================================

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 909.00 45.00 84.69 78.22 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 909.00 45.00 84.69 78.22 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 909.00 45.00 84.69 78.22

=============== 518-00000 Brdg Compress Joint Sealer Lin Foot ===============================================

STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 265.00 40.00 51.21 38.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 265.00 40.00 51.21 38.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 265.00 40.00 51.21 38.00

=============== 518-00010 Rdwy Compress Joint Sealer Lin Foot ===============================================

STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 400.00 15.00 12.50 6.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 400.00 15.00 12.50 6.00

NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 386.00 6.00 7.15 5.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 386.00 6.00 7.15 5.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 786.00 10.58 9.34 5.75

Page 263: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 219 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 518-00100 Waterstop Lin Foot ===============================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 45.00 14.50 20.00 21.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 45.00 14.50 20.00 21.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 45.00 14.50 20.00 21.00

=============== 518-00106 Waterstop (6 In) Lin Foot ===============================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 345.00 10.00 7.17 8.50BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 20.00 10.00 21.13 5.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 365.00 10.00 7.68 8.34 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 365.00 10.00 7.68 8.34

=============== 518-01002 Br Expan Device (0-2 In) Lin Foot ===============================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 60.00 100.00 142.67 130.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 499.30 120.00 93.43 96.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 559.30 117.85 98.71 99.65

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 268.00 100.00 113.40 100.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 64.00 115.00 101.50 95.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 127.00 100.00 101.64 125.00NH 0741-015 - SMA Alt SH 74 EVERGREEN OVERLAY 04/29/04 193.00 100.00 112.63 105.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 60.00 100.00 127.51 110.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 241.00 75.00 130.53 105.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 953.00 94.69 115.80 105.98

BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 292.00 120.00 129.45 123.55SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 174.00 100.00 308.75 117.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 466.00 112.53 180.42 121.29

IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 379.40 105.00 101.43 91.00

Page 264: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 220 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 518-01002 Br Expan Device (0-2 In) Lin Foot ===============================================STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 94.00 110.00 116.67 100.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 138.00 150.00 133.33 120.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 611.40 115.93 106.65 98.93 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,589.70 107.92 116.74 105.70

=============== 518-01004 Br Expan Device (0-4 In) Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 202.00 120.00 117.51 110.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 216.00 80.00 88.50 89.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 418.00 99.33 111.39 99.15

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 152.00 125.00 124.15 120.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 588.00 160.00 153.54 200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 740.00 152.81 145.33 183.57

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 318.00 120.00 119.56 125.00STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 60.00 150.00 160.90 160.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 378.00 124.76 125.18 130.67 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,536.00 131.35 130.17 147.58

=============== 518-01006 Br Expan Device (0-6 In) Lin Foot ===============================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 292.00 525.00 573.56 807.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 292.00 525.00 573.56 807.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 292.00 525.00 573.56 807.00

=============== 518-01009 Br Expan Device (0-9 In) Lin Foot ===============================================

STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 14.00 700.00 1387.19 1800.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 14.00 700.00 1387.19 1800.00

Page 265: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 221 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 518-01009 Br Expan Device (0-9 In) Lin Foot ===============================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 80.00 900.00 791.19 700.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 80.00 900.00 791.19 700.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 94.00 870.21 959.57 863.83

=============== 518-02100 Polymer Mortar End Dam Cubic Foot =============================================

STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 354.00 300.00 293.01 315.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 354.00 300.00 293.01 315.00

BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 45.00 400.00 934.46 972.68 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 45.00 400.00 934.46 972.68 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 399.00 311.28 319.08 389.17

=============== 518-03000 Saw and Seal Br Joint Lin Foot ===============================================

IM 0701-157 FRUITA TO CLIFTON 02/26/04 814.00 10.00 9.38 5.00STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 180.00 15.00 20.75 18.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 78.00 10.00 18.67 11.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,072.00 10.84 11.15 7.62

IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 360.00 13.00 18.17 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 360.00 13.00 18.17 10.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,432.00 11.38 12.25 8.22

=============== 518-03100 Rapid Cure Silicone Jt Seal Lin Foot ===============================================

STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 193.00 30.00 63.66 75.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 193.00 30.00 63.66 75.00

Page 266: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 222 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 518-03100 Rapid Cure Silicone Jt Seal Lin Foot ===============================================

BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 77.00 85.00 101.80 103.92 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 77.00 85.00 101.80 103.92 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 270.00 45.69 68.13 83.25

=============== 519-01000 Epoxy Resin (Injection) Lin Foot ===============================================

BR 0243-063 EAST OF LIMON 07/15/04 100.00 30.00 114.89 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 100.00 30.00 114.89 10.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 100.00 30.00 114.89 10.00

=============== 601-01000 Conc CL B Cubic Yard =============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 395.00 500.00 450.69 504.12IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 22.00 350.00 520.59 550.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 55.00 400.00 557.56 420.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 88.80 350.00 434.45 555.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 560.80 460.56 461.40 505.72

NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 50.00 400.00 247.54 120.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 6.00 400.00 769.25 900.00STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 20.00 400.00 445.00 250.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 659.00 250.00 357.71 370.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 4.00 215.00 728.75 700.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 739.00 265.24 358.06 355.93

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 78.00 330.00 300.49 260.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 21.00 400.00 312.43 325.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 32.00 370.00 312.75 130.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 131.00 350.99 304.52 238.66

Page 267: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 223 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 601-01000 Conc CL B Cubic Yard =============================================

C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 3.00 600.00 2550.00 2500.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 440.00 180.00 279.00 215.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 21.00 450.00 266.29 260.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 2.00 500.00 754.85 536.10STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 60.00 350.00 320.25 475.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 526.00 213.78 289.69 260.71 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,956.80 313.12 371.39 365.41

=============== 601-01025 Conc CL B (Misc) Cubic Yard =============================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 272.00 350.00 275.00 360.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 272.00 350.00 275.00 360.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 272.00 350.00 275.00 360.00

=============== 601-01040 Conc CL B (Bridge) Cubic Yard =============================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 6.00 400.00 586.37 420.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 19.00 330.00 262.50 295.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 25.00 346.80 460.79 325.00

SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 32.00 230.00 552.00 375.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 32.00 230.00 552.00 375.00

STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 17.00 480.00 456.03 333.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 17.00 480.00 456.03 333.25 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 74.00 326.89 497.03 348.52

Page 268: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 224 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 601-01050 Conc CL B (Wall) Cubic Yard =============================================

STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 12.00 350.00 995.00 710.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 4.00 600.00 610.00 770.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 16.00 412.50 940.00 725.00

NH 0502-053 CIMARRON - WEST 04/15/04 11.30 400.00 525.31 450.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 26.00 500.00 416.10 430.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 37.30 469.71 440.63 436.06

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 138.00 350.00 413.34 459.60NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 46.12 500.00 785.00 810.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 184.12 387.57 506.43 547.37 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 237.42 402.16 517.55 541.85

=============== 601-03000 Conc CL D Cubic Yard =============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 2,430.00 550.00 427.29 268.74STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 14.00 450.00 945.75 745.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,444.00 549.43 429.27 271.47

STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 3.00 1000.00 738.00 674.34 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3.00 1000.00 738.00 674.34

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 172.87 400.00 383.56 485.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 172.87 400.00 383.56 485.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,619.87 540.08 427.15 286.02

Page 269: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 225 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 601-03030 Conc CL D (Box) Cubic Yard =============================================

IM 0701-157 FRUITA TO CLIFTON 02/26/04 7.50 600.00 728.33 640.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 7.20 550.00 485.50 370.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 14.70 575.51 600.04 507.76

NH 0502-053 CIMARRON - WEST 04/15/04 179.00 475.00 479.62 450.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 292.00 320.00 268.39 280.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 227.30 350.00 402.16 348.60CC R600-225 CHATFIELD STATE PARK 06/10/04 35.00 400.00 406.25 400.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 265.00 300.00 391.67 355.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 998.30 352.12 367.41 350.22

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 32.00 550.00 556.75 540.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 412.00 400.00 267.07 225.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 143.00 400.00 364.00 335.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 587.00 408.18 325.36 268.97

BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 599.00 300.00 283.79 210.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 40.00 500.00 548.30 343.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 639.00 312.52 292.34 218.34 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,239.00 356.98 328.97 292.31

=============== 601-03040 Conc CL D (Bridge) Cubic Yard =============================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 3.00 700.00 1320.19 2200.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 397.00 370.00 305.25 275.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 149.00 250.00 186.62 152.32NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 82.00 300.00 527.61 440.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 983.00 250.00 265.00 320.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,614.00 282.89 295.52 303.04

Page 270: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 226 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 601-03040 Conc CL D (Bridge) Cubic Yard =============================================

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 600.00 300.00 352.52 223.47NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 22.00 400.00 863.35 894.70SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 113.00 265.00 487.50 400.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 1,069.00 260.00 307.00 247.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,804.00 275.32 333.32 256.66

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 746.00 250.00 346.40 385.00BR 0243-063 EAST OF LIMON 07/15/04 290.00 420.00 601.67 420.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 10,826.00 300.00 345.89 335.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 382.00 400.00 399.83 385.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 12,244.00 302.92 352.37 341.62

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 2,122.00 250.00 224.43 230.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 3,650.00 400.00 386.66 425.00IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 1.20 775.00 3318.57 3640.00NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 17.00 600.00 438.33 440.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 5,790.20 345.69 312.25 354.25 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 21,452.20 310.64 334.76 334.98

=============== 601-03041 Conc CL D (Bridge) (Spec) Cubic Yard =============================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 2.00 1000.00 1375.51 570.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 1000.00 1375.51 570.00

SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 25.00 800.00 722.90 580.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 7.00 1000.00 739.97 600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 32.00 843.75 726.03 584.38

Page 271: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 227 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 601-03041 Conc CL D (Bridge) (Spec) Cubic Yard =============================================

BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 115.00 700.00 1162.05 1227.94 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 115.00 700.00 1162.05 1227.94

MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 221.00 600.00 623.33 445.00STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 8.00 1000.00 1401.93 1500.00STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 8.00 750.00 760.07 333.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 237.00 618.57 672.61 476.84 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 386.00 663.47 824.15 710.01

=============== 601-03050 Conc CL D (Wall) Cubic Yard =============================================

STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 470.50 300.00 344.25 320.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 470.50 300.00 344.25 320.00

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 391.00 400.00 282.28 279.96 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 391.00 400.00 282.28 279.96

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 40.00 300.00 318.91 300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 40.00 300.00 318.91 300.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 3,613.00 275.00 252.70 230.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 60.00 300.00 393.62 400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3,673.00 275.41 254.25 232.78 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4,574.50 288.80 267.89 246.37

Page 272: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 228 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 601-03540 Conc CL DT (Deck Topping) Cubic Yard =============================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 3.70 2000.00 1349.22 525.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3.70 2000.00 1349.22 525.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.70 2000.00 1349.22 525.00

=============== 601-04000 Conc CL E Cubic Yard =============================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 13.10 1000.00 949.22 415.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 13.10 1000.00 949.22 415.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 13.10 1000.00 949.22 415.00

=============== 601-05000 Conc CL H Cubic Yard =============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1,114.00 400.00 309.56 265.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,114.00 400.00 309.56 265.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,114.00 400.00 309.56 265.00

=============== 601-05045 Conc CL S40 Cubic Yard =============================================

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 216.00 350.00 377.97 355.62 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 216.00 350.00 377.97 355.62 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 216.00 350.00 377.97 355.62

=============== 601-06100 Conc (Patching) Cubic Yard =============================================

IM 0701-168 RIFLE TO SILT SLAB REPAIR 08/05/04 7.50 1500.00 1570.08 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 7.50 1500.00 1570.08 500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 7.50 1500.00 1570.08 500.00

=============== 601-06150 Conc (Patching) Sq Foot ================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 1,800.00 31.00 33.03 28.00

Page 273: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 229 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 601-06150 Conc (Patching) Sq Foot ================================================STA 2911-001 SH 291 SALIDA NORTH 01/08/04 117.00 35.00 32.22 40.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 610.00 30.00 27.93 12.20NH 2872-016 US 287 - LAMAR 03/04/04 100.00 45.00 52.25 42.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 340.00 24.00 32.45 46.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,967.00 30.62 32.71 27.76

NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 300.00 40.00 35.00 22.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 10.00 150.00 211.83 130.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 144.00 40.00 122.16 52.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 454.00 42.42 68.12 33.89

ER 0702-255 I-70 GLENWOOD CANYON 11/30/04 600.00 90.00 220.67 200.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 405.00 32.00 73.13 2.66IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 60.00 60.00 68.33 85.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 300.00 30.00 11.44 8.70NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 150.10 40.00 62.88 51.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,515.10 56.47 94.67 90.06 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4,936.10 39.64 49.49 47.44

=============== 601-06400 Grout (Bridge)(Spec) Cubic Foot =============================================

BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 1,247.00 40.00 70.16 109.78 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,247.00 40.00 70.16 109.78

IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 45.00 50.00 156.67 125.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 45.00 50.00 156.67 125.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,292.00 40.35 73.18 110.31

=============== 601-10055 Shotcrete Class I Cubic Yard =============================================

STA 149A-021 SH 149 CRIBWALL 09/16/04 25.00 300.00 472.00 472.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 25.00 300.00 472.00 472.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 25.00 300.00 472.00 472.00

Page 274: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 230 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 601-10075 Shotcrete (3 In 5000 psi) Sq Yard ================================================

STA 1191-020 SH 119 ROCKFALL MITIGATION, 2 04/15/04 405.00 180.00 139.33 233.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 405.00 180.00 139.33 233.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 405.00 180.00 139.33 233.00

=============== 601-12084 Conc Lining (84 In Cond) Lin Foot ===============================================

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 147.00 230.00 136.00 80.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 147.00 230.00 136.00 80.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 147.00 230.00 136.00 80.00

=============== 601-40000 Masonry Veneer Sq Foot ================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 40,630.00 11.00 19.16 15.81 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 40,630.00 11.00 19.16 15.81

SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 220.00 23.00 61.38 68.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 220.00 23.00 61.38 68.00

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 3,785.00 32.00 60.58 57.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 3,785.00 32.00 60.58 57.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 44,635.00 12.84 22.27 19.60

=============== 601-40300 Struct Conc Coating Sq Yard ================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 4,752.00 5.00 6.88 4.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4,752.00 5.00 6.88 4.50

Page 275: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 231 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 601-40300 Struct Conc Coating Sq Yard ================================================

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 1,819.00 3.50 7.29 9.47SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 180.00 8.00 17.18 15.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,999.00 3.91 7.82 10.01

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 6,535.00 5.00 4.43 4.68NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 80.00 13.00 35.00 38.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 6,615.00 5.10 4.70 5.08 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 13,366.00 4.88 6.30 5.61

=============== 601-40301 Struct Conc Coating Sq Foot ================================================

STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 6,322.00 1.00 0.73 0.35 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 6,322.00 1.00 0.73 0.35

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 27,228.00 0.60 1.04 0.55 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 27,228.00 0.60 1.04 0.55

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 15,842.00 1.40 1.17 1.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 15,842.00 1.40 1.17 1.40

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 92,887.00 0.60 0.55 0.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 92,887.00 0.60 0.55 0.30 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 142,279.00 0.71 0.71 0.47

Page 276: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 232 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 601-40400 Struct Conc Stain Sq Yard ================================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 2,027.00 7.00 6.40 7.80 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,027.00 7.00 6.40 7.80 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,027.00 7.00 6.40 7.80

=============== 602-00000 Reinf Steel Pound ==================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 100.00 2.00 5.56 6.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 27,035.00 0.45 0.61 0.63IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 940.00 0.50 0.68 0.70IM 0701-157 FRUITA TO CLIFTON 02/26/04 1,550.00 1.25 1.47 0.70STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 440.00 1.00 3.34 3.05NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 1,170.00 1.00 1.43 0.50STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1,391.00 0.80 0.98 0.95STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 19,921.00 0.46 0.63 0.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 52,547.00 0.51 0.73 0.66

NH 0502-053 CIMARRON - WEST 04/15/04 24,958.00 0.55 0.90 0.85IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 71,318.00 0.45 0.69 0.71SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 74,886.00 0.80 0.78 0.55NH 2852-010 US 285 & COUNTY RD. G 04/29/04 30,039.00 0.60 1.04 0.81NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 70,892.00 0.65 0.78 0.70CC R600-225 CHATFIELD STATE PARK 06/10/04 4,250.00 0.75 0.96 1.30IM 0253-186 I-25, 120TH TO SH 7 06/17/04 1,000.00 1.00 1.33 1.60STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 60,418.00 0.52 0.89 0.80BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 46,660.00 0.70 0.79 0.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 384,421.00 0.62 0.80 0.72

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 8,428.00 1.00 0.94 1.25IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 6,281.00 1.25 0.80 0.85NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 47,260.00 0.90 0.79 0.80NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 3,073.80 1.00 1.63 1.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 65,042.80 0.95 0.86 0.87

C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 209.00 3.00 2.00 3.00

Page 277: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 233 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 602-00000 Reinf Steel Pound ==================================================C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 18,508.00 1.00 1.38 1.25BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 142,090.00 0.75 0.84 0.70IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 313,600.00 0.75 0.63 0.65BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 5,500.00 1.00 0.75 0.63MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 3,000.00 2.00 2.73 1.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 482,907.00 0.77 0.74 0.69 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 984,917.80 0.71 0.76 0.71

=============== 602-00020 Reinf Steel (Epoxy) Pound ==================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 444.00 2.00 3.35 1.30NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 425,035.00 0.47 0.70 0.70IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 266,945.00 0.56 0.73 0.78STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 33,120.00 0.60 0.67 0.74STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 1,088.00 1.10 2.58 2.10NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 12,970.00 0.60 0.88 0.55STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 73,881.00 0.70 0.88 0.50STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 140,340.00 0.60 0.72 0.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 953,823.00 0.54 0.73 0.71

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 61,213.00 0.55 0.83 0.84NH 2852-010 US 285 & COUNTY RD. G 04/29/04 14,710.00 0.65 1.25 1.03NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 3,659.00 1.00 0.99 1.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 7,975.00 1.00 1.45 1.10SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 27,335.00 0.90 1.02 1.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 5,205.00 0.60 1.07 0.90BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 140,830.00 0.75 0.91 0.83 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 260,927.00 0.72 0.93 0.87

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 148,706.00 0.60 0.88 0.86BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 15,510.00 1.10 1.44 1.25BR 0243-063 EAST OF LIMON 07/15/04 80,290.00 0.80 1.01 1.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 3,845,161.00 0.85 0.86 0.90NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 19,789.00 1.00 1.09 1.15STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 93,879.00 0.95 1.00 0.90C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 30,950.00 0.55 0.95 0.97 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4,234,285.00 0.84 0.87 0.90

Page 278: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 234 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 602-00020 Reinf Steel (Epoxy) Pound ==================================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 493,630.00 0.70 0.75 0.76BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 848,689.00 0.81 0.81 0.72IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 120.00 2.00 1.81 1.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 160.00 2.00 3.43 10.70STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 2,000.00 2.00 2.30 4.00NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 3,000.00 3.00 2.23 2.20NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 7,060.00 1.50 1.31 1.35STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 4,100.00 2.00 2.54 2.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,358,759.00 0.78 0.80 0.75 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6,807,794.00 0.78 0.83 0.85

=============== 602-00030 Reinf (FRP)(Surface) M Kip Foot =============================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 34.00 500.00 1468.93 1440.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 34.00 500.00 1468.93 1440.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 34.00 500.00 1468.93 1440.00

=============== 603-00029 Prep Culvert Pipe (30 In) Lin Foot ===============================================

IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 187.00 40.00 35.80 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 187.00 40.00 35.80 10.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 187.00 40.00 35.80 10.00

=============== 603-00030 Culvert Lining (30 In) Lin Foot ===============================================

IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 187.00 120.00 220.83 20.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 187.00 120.00 220.83 20.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 187.00 120.00 220.83 20.00

=============== 603-00072 Culvert Lining (72 In) Lin Foot ===============================================

C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 241.00 500.00 337.50 200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 241.00 500.00 337.50 200.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 241.00 500.00 337.50 200.00

Page 279: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 235 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-01120 12 In RCP Lin Foot ===============================================

IM 0701-157 FRUITA TO CLIFTON 02/26/04 12.00 80.00 74.50 70.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 12.00 80.00 74.50 70.00

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 190.00 40.00 44.30 50.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 190.00 40.00 44.30 50.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 202.00 42.38 46.43 51.19

=============== 603-01150 15 In RCP Lin Foot ===============================================

STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 148.00 70.00 57.56 55.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 701.00 30.00 28.91 39.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 849.00 36.97 32.44 41.79

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 25.00 60.00 41.47 54.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 25.00 60.00 41.47 54.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 874.00 37.63 32.72 42.14

=============== 603-01155 15 In RCP (CIP) Lin Foot ===============================================

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 16.00 30.00 99.75 27.17 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 16.00 30.00 99.75 27.17

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 134.00 40.00 82.24 61.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 134.00 40.00 82.24 61.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 150.00 38.93 85.95 57.39

Page 280: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 236 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-01180 18 In RCP Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 2,848.00 35.00 33.07 38.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1,534.00 28.00 27.00 34.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4,382.00 32.55 32.35 36.60

STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 1,387.00 28.00 48.22 50.61SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 22.00 40.00 104.78 67.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 858.00 55.00 63.00 57.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 272.00 40.00 30.64 41.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2,539.00 38.51 50.12 51.88

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 108.00 30.00 37.01 57.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 924.00 45.00 52.35 55.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,032.00 43.43 50.46 55.21

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 596.00 35.00 33.08 35.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 596.00 35.00 33.08 35.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8,549.00 35.81 39.82 43.27

=============== 603-01185 18 In RCP (CIP) Lin Foot ===============================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 317.00 38.00 37.50 19.00STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 173.00 40.00 59.49 35.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 490.00 38.71 43.89 24.65

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 610.00 35.00 33.59 21.31SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 55.00 40.00 75.75 48.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 665.00 35.41 35.21 23.52

Page 281: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 237 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-01185 18 In RCP (CIP) Lin Foot ===============================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 94.00 70.00 92.00 76.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 94.00 70.00 92.00 76.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 565.00 37.00 41.13 32.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 116.00 37.00 60.28 35.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 681.00 37.00 43.44 32.58 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,930.00 38.49 41.43 29.56

=============== 603-01240 24 In RCP Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 637.00 45.00 42.79 49.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 10.00 90.00 111.83 95.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 559.00 65.00 71.69 47.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 443.00 38.00 35.00 46.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,649.00 50.17 52.81 47.80

STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 2,110.00 35.00 48.43 40.24STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 2,486.00 90.00 85.41 90.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 363.00 50.00 36.41 40.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4,959.00 63.67 61.13 65.17

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1,767.00 35.00 44.24 59.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 68.00 60.00 115.32 130.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 76.00 60.00 48.13 49.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 288.00 55.00 56.63 58.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2,199.00 39.26 47.44 60.72

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 294.00 45.00 39.04 42.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 294.00 45.00 39.04 42.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 9,101.00 54.72 55.63 60.20

Page 282: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 238 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-01245 24 In RCP (CIP) Lin Foot ===============================================

SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 32.00 60.00 49.00 55.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 32.00 60.00 49.00 55.00

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 150.00 45.00 40.02 30.10STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 552.00 40.00 42.41 24.94STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 65.00 45.00 53.11 37.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 767.00 41.40 42.40 26.97

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 3,512.00 30.00 43.76 37.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 336.00 80.00 48.33 38.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 83.00 50.00 63.69 40.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3,931.00 34.70 44.26 37.16 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4,730.00 35.95 43.88 35.63

=============== 603-01300 30 In RCP Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 358.00 60.00 56.29 67.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 358.00 60.00 56.29 67.00

SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 86.00 60.00 115.27 67.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 181.00 55.00 113.89 41.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 267.00 56.61 114.28 49.37

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 173.00 55.00 56.20 58.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 166.00 70.00 146.49 150.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 339.00 62.35 96.32 103.05

Page 283: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 239 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-01300 30 In RCP Lin Foot ===============================================

SHE 105A-010 SH 105/FURROW RD 10/07/04 126.00 70.00 87.45 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 126.00 70.00 87.45 60.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,090.00 61.06 82.80 73.09

=============== 603-01305 30 In RCP (CIP) Lin Foot ===============================================

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 1,298.00 50.00 44.33 29.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,298.00 50.00 44.33 29.70

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 396.00 60.00 63.14 55.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 396.00 60.00 63.14 55.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,694.00 52.34 46.06 35.61

=============== 603-01360 36 In RCP Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 665.00 70.00 55.16 69.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 15.00 85.00 107.87 48.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 298.00 58.00 60.00 67.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 978.00 66.57 56.43 68.07

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1,082.00 57.00 73.11 74.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 51.00 90.00 97.52 175.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 152.00 75.00 68.75 70.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,285.00 60.44 73.50 77.54

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 22.00 80.00 76.53 75.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 22.00 80.00 76.53 75.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,285.00 63.25 65.98 73.46

Page 284: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 240 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-01365 36 In RCP (CIP) Lin Foot ===============================================

SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 40.00 80.00 71.00 90.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 40.00 80.00 71.00 90.00

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 1,436.00 60.00 52.34 35.10STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 100.00 75.00 94.40 75.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,536.00 60.98 53.30 37.70

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 331.00 70.00 79.56 65.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 331.00 70.00 79.56 65.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 11.00 60.00 122.53 95.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 11.00 60.00 122.53 95.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,918.00 62.92 55.57 43.83

=============== 603-01420 42 In RCP Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 72.00 90.00 72.48 83.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 223.00 69.00 69.00 70.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 295.00 74.13 70.96 73.17

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 35.00 115.00 98.43 120.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 35.00 115.00 98.43 120.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 330.00 78.46 75.64 78.14

=============== 603-01425 42 In RCP (CIP) Lin Foot ===============================================

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 1,342.00 80.00 84.34 46.35 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,342.00 80.00 84.34 46.35 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,342.00 80.00 84.34 46.35

Page 285: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 241 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-01480 48 In RCP Lin Foot ===============================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 413.00 85.00 86.50 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 413.00 85.00 86.50 100.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 235.00 88.00 98.80 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 235.00 88.00 98.80 100.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 648.00 86.09 94.26 100.00

=============== 603-01485 48 In RCP (CIP) Lin Foot ===============================================

SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 128.00 90.00 99.00 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 128.00 90.00 99.00 100.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 128.00 90.00 99.00 100.00

=============== 603-01540 54 In RCP Lin Foot ===============================================

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 80.00 100.00 119.54 118.80 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 80.00 100.00 119.54 118.80

SHE 105A-010 SH 105/FURROW RD 10/07/04 62.00 160.00 156.28 140.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 62.00 160.00 156.28 140.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 142.00 126.20 132.63 128.06

=============== 603-01600 60 In RCP Lin Foot ===============================================

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 58.00 140.00 170.18 174.16 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 58.00 140.00 170.18 174.16

Page 286: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 242 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-01600 60 In RCP Lin Foot ===============================================

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 48.00 129.00 137.79 160.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 48.00 129.00 137.79 160.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 106.00 135.02 156.74 167.75

=============== 603-02185 23x14 In RCP (CIP) Lin Foot ===============================================

SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 197.00 60.00 91.75 55.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 197.00 60.00 91.75 55.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 197.00 60.00 91.75 55.00

=============== 603-02240 30x19 In RCP Lin Foot ===============================================

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 47.00 70.00 136.70 101.50STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 12.00 100.00 143.82 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 59.00 76.10 138.50 101.19

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 230.00 70.00 86.17 63.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 230.00 70.00 86.17 63.00

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 58.00 70.00 66.40 70.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 58.00 70.00 66.40 70.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 347.00 71.04 90.12 70.66

=============== 603-02245 30x19 In RCP (CIP) Lin Foot ===============================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 107.00 65.00 60.78 51.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 107.00 65.00 60.78 51.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 107.00 65.00 60.78 51.00

Page 287: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 243 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-02300 38x24 In RCP Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 123.00 80.00 76.12 95.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 123.00 80.00 76.12 95.00

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 79.00 90.00 111.72 78.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 79.00 90.00 111.72 78.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 202.00 83.91 84.77 88.35

=============== 603-02360 45x29 In RCP Lin Foot ===============================================

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 32.00 80.00 155.41 167.65STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 55.00 90.00 85.88 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 87.00 86.32 103.87 124.88 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 87.00 86.32 103.87 124.88

=============== 603-02480 60x38 In RCP Lin Foot ===============================================

NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 208.00 100.00 142.50 115.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 208.00 100.00 142.50 115.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 16.00 85.00 217.50 240.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 16.00 85.00 217.50 240.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 224.00 98.93 156.56 123.93

=============== 603-02600 76x48 In RCP Lin Foot ===============================================

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 25.00 550.00 242.01 230.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 25.00 550.00 242.01 230.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 25.00 550.00 242.01 230.00

Page 288: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 244 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-05012 12 In RCES Each ===================================================

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 2.00 500.00 584.77 320.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 500.00 584.77 320.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 500.00 584.77 320.00

=============== 603-05015 15 In RCES Each ===================================================

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1.00 400.00 449.76 470.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 400.00 449.76 470.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 400.00 449.76 470.00

=============== 603-05018 18 In RCES Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 1.00 550.00 525.05 420.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 5.00 500.00 476.31 900.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 2.00 450.00 517.50 565.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 8.00 493.75 486.98 756.25

STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 1.00 400.00 606.53 387.80SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 2.00 500.00 345.67 360.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 700.00 459.77 490.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4.00 525.00 454.83 399.45

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 4.00 306.00 474.56 510.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 8.00 800.00 679.42 360.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 12.00 635.33 602.60 410.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 4.00 500.00 504.24 650.00

Page 289: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 245 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-05018 18 In RCES Each ===================================================BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 3.00 550.00 482.90 400.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 6.00 500.00 512.26 429.05 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 13.00 511.54 503.18 490.33 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 37.00 549.30 525.33 511.95

=============== 603-05024 24 In RCES Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 7.00 700.00 569.06 900.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 5.00 570.00 717.98 290.00SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 4.00 500.00 526.00 500.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 2.00 530.00 542.50 595.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 18.00 600.56 606.75 607.78

STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 4.00 500.00 663.56 418.70STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 40.00 450.00 553.13 420.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 44.00 454.55 569.57 419.88

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 43.00 365.00 513.69 540.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1.00 565.00 750.82 565.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 2.00 650.00 606.17 380.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 46.00 381.74 520.80 533.59

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 6.00 600.00 592.72 800.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 2.00 700.00 561.91 482.65 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 8.00 625.00 587.12 720.66 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 116.00 460.09 555.27 514.87

=============== 603-05030 30 In RCES Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 5.00 810.00 683.83 1200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5.00 810.00 683.83 1200.00

Page 290: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 246 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-05030 30 In RCES Each ===================================================

SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 2.00 600.00 816.74 520.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 600.00 816.74 520.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1.00 574.00 607.86 640.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 6.00 800.00 960.54 750.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 7.00 767.71 872.37 734.29

SHE 105A-010 SH 105/FURROW RD 10/07/04 4.00 1000.00 877.92 690.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4.00 1000.00 877.92 690.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 18.00 812.44 787.40 830.00

=============== 603-05036 36 In RCES Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 850.00 770.60 1000.00SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 1.00 800.00 781.67 750.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 2.00 750.00 907.50 1025.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 787.50 809.32 950.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 50.00 600.00 744.48 790.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 4.00 800.00 1117.21 800.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 950.00 1202.03 1200.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 2.00 900.00 984.57 725.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 57.00 630.70 772.49 795.61

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1.00 700.00 872.23 1400.00

Page 291: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 247 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-05036 36 In RCES Each ===================================================BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 750.00 759.15 650.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 725.00 827.00 1025.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 63.00 643.65 775.61 812.70

=============== 603-05042 42 In RCES Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 1100.00 868.22 1400.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 5.00 860.00 1050.00 1330.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 6.00 900.00 969.21 1341.67

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 1.00 750.00 1177.65 942.87 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 750.00 1177.65 942.87

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 2.00 1020.00 918.62 830.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 1020.00 918.62 830.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 9.00 910.00 1001.74 1183.65

=============== 603-05048 48 In RCES Each ===================================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 4.00 900.00 970.00 1050.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 900.00 970.00 1050.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 13.00 950.00 1088.24 940.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 13.00 950.00 1088.24 940.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 17.00 938.24 1077.24 965.88

=============== 603-05054 54 In RCES Each ===================================================

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 1.00 1500.00 1450.26 1546.79 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 1500.00 1450.26 1546.79

Page 292: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 248 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-05054 54 In RCES Each ===================================================

SHE 105A-010 SH 105/FURROW RD 10/07/04 2.00 1500.00 1782.95 1400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 1500.00 1782.95 1400.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 1500.00 1645.96 1448.93

=============== 603-05060 60 In RCES Each ===================================================

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 1.00 1800.00 1583.06 1661.31 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 1800.00 1583.06 1661.31

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 2.00 1500.00 1712.39 1400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 1500.00 1712.39 1400.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 1600.00 1664.74 1487.10

=============== 603-05124 30x19 In RCES Each ===================================================

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 2.00 600.00 809.99 600.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 1.00 615.00 801.38 600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3.00 605.00 806.54 600.00

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 6.00 700.00 775.26 420.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 6.00 700.00 775.26 420.00

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 750.00 692.54 725.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 750.00 692.54 725.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10.00 676.50 774.78 504.50

Page 293: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 249 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-05130 38x24 In RCES Each ===================================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 2.00 750.00 978.40 560.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 750.00 978.40 560.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 750.00 978.40 560.00

=============== 603-05136 45x29 In RCES Each ===================================================

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 2.00 1000.00 996.65 1060.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 2.00 1100.00 822.00 1040.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4.00 1050.00 887.50 1050.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 1050.00 887.50 1050.00

=============== 603-05160 76x48 In RCES Each ===================================================

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 2.00 6000.00 2160.64 1700.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 6000.00 2160.64 1700.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 6000.00 2160.64 1700.00

=============== 603-07240 24 In RCP (Jacked) Lin Foot ===============================================

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 293.00 425.00 375.05 510.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 293.00 425.00 375.05 510.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 293.00 425.00 375.05 510.00

=============== 603-07360 36 In RCP (Jacked) Lin Foot ===============================================

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 235.00 435.00 482.56 680.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 235.00 435.00 482.56 680.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1,232.00 400.00 565.61 550.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,232.00 400.00 565.61 550.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,467.00 405.61 552.30 570.82

Page 294: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 250 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-10120 12 In CSP Lin Foot ===============================================

IM 0701-157 FRUITA TO CLIFTON 02/26/04 14.00 80.00 59.67 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 14.00 80.00 59.67 60.00

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 135.00 35.00 30.30 25.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 150.00 35.00 27.22 36.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 285.00 35.00 28.68 31.05 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 299.00 37.11 30.40 32.41

=============== 603-10180 18 In CSP Lin Foot ===============================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 30.00 50.00 58.29 45.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 40.00 40.00 43.06 31.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 24.00 50.00 50.44 44.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 94.00 45.74 49.35 38.79

NH 0502-053 CIMARRON - WEST 04/15/04 80.00 50.00 47.30 56.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 40.00 50.00 38.66 45.00STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 24.00 50.00 66.33 43.00IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 420.00 28.00 49.33 60.50SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 156.00 40.00 94.28 41.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 36.00 36.00 50.02 50.10NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 152.00 40.00 35.43 40.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 908.00 35.88 54.96 51.76

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 130.00 50.00 51.65 56.85NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 620.00 70.00 43.56 42.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 24.00 50.00 61.92 40.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 7.50 120.00 153.33 90.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1,098.00 35.00 41.50 50.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,879.50 48.11 43.54 47.87 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,881.50 44.18 47.61 48.80

Page 295: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 251 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-10240 24 In CSP Lin Foot ===============================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 30.00 55.00 63.90 47.00STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 138.00 40.00 80.78 55.92IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 115.00 50.00 39.24 30.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 590.00 50.00 49.60 50.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 4.00 100.00 114.17 110.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 60.00 60.00 58.44 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 937.00 49.54 53.30 49.22

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 10.00 55.00 55.54 62.00NH 0502-053 CIMARRON - WEST 04/15/04 1,480.00 50.00 54.80 75.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 56.00 70.00 52.50 45.00IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 50.00 67.00 57.50 77.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 69.00 60.00 107.25 44.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 160.00 40.00 67.05 58.90STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 90.00 100.00 81.45 75.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 909.00 50.00 36.82 42.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2,824.00 51.99 50.03 62.10

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 130.00 65.00 63.18 69.35SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 52.00 90.00 74.00 44.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 894.00 80.00 50.07 46.00STA 149A-021 SH 149 CRIBWALL 09/16/04 5.00 65.00 334.00 334.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 781.00 62.00 55.50 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,862.00 71.64 54.37 54.22

NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 33.00 45.00 81.33 85.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 33.00 45.00 81.33 85.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5,656.00 58.01 52.07 57.51

=============== 603-10300 30 In CSP Lin Foot ===============================================

STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 27.00 50.00 81.87 60.37

Page 296: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 252 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-10300 30 In CSP Lin Foot ===============================================STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 40.00 55.00 65.40 60.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 28.00 80.00 82.71 78.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 95.00 60.95 75.98 65.41

NH 0502-053 CIMARRON - WEST 04/15/04 538.00 60.00 62.48 80.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 20.00 85.00 68.75 60.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 135.00 65.00 76.39 65.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1,690.00 35.00 40.91 42.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2,383.00 42.76 46.47 52.03

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 40.00 75.00 82.40 95.10SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 52.00 110.00 85.50 46.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 18.00 75.00 69.25 73.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 110.00 91.55 80.54 68.27 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,588.00 45.50 48.42 53.21

=============== 603-10360 36 In CSP Lin Foot ===============================================

STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 103.00 60.00 87.96 77.80 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 103.00 60.00 87.96 77.80

NH 0502-053 CIMARRON - WEST 04/15/04 350.00 75.00 71.56 90.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 75.00 70.00 53.99 50.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 425.00 74.12 67.29 82.94

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 263.00 100.00 71.70 51.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 16.00 85.00 97.50 85.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 279.00 99.14 73.64 52.95

Page 297: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 253 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-10360 36 In CSP Lin Foot ===============================================

C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 40.00 500.00 255.00 255.00STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 50.00 150.00 212.25 90.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 90.00 305.56 224.46 163.33 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 897.00 103.50 84.46 81.09

=============== 603-10420 42 In CSP Lin Foot ===============================================

NH 0502-053 CIMARRON - WEST 04/15/04 18.00 95.00 97.96 150.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 22.00 62.00 152.28 100.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 216.00 65.00 54.34 57.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 256.00 66.85 63.75 67.23 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 256.00 66.85 63.75 67.23

=============== 603-10480 48 In CSP Lin Foot ===============================================

STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 18.00 70.00 124.80 116.52STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 728.00 70.00 60.00 60.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 20.00 100.00 108.08 116.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 766.00 70.78 64.00 62.80

NH 0502-053 CIMARRON - WEST 04/15/04 262.00 66.00 91.45 125.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 342.00 75.00 57.47 56.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 604.00 71.10 68.96 85.93

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 90.00 100.00 96.50 95.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 90.00 100.00 96.50 95.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,460.00 72.71 68.10 74.36

Page 298: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 254 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-10600 60 In CSP Lin Foot ===============================================

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 308.00 110.00 148.25 200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 308.00 110.00 148.25 200.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 308.00 110.00 148.25 200.00

=============== 603-10720 72 In CSP Lin Foot ===============================================

STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 30.00 100.00 170.50 205.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 30.00 100.00 170.50 205.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 30.00 100.00 170.50 205.00

=============== 603-10840 84 In CSP Lin Foot ===============================================

NH 0502-053 CIMARRON - WEST 04/15/04 74.00 130.00 148.56 155.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 74.00 130.00 148.56 155.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 74.00 130.00 148.56 155.00

=============== 603-15021 21 In Equiv CSPA Lin Foot ===============================================

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 27.00 50.00 61.12 35.07 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 27.00 50.00 61.12 35.07 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 27.00 50.00 61.12 35.07

=============== 603-15030 30 In Equiv CSPA Lin Foot ===============================================

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 273.00 60.00 44.53 44.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 273.00 60.00 44.53 44.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 273.00 60.00 44.53 44.00

=============== 603-15042 42 In Equiv CSPA Lin Foot ===============================================

NH 0502-053 CIMARRON - WEST 04/15/04 110.00 130.00 95.19 120.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 110.00 130.00 95.19 120.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 110.00 130.00 95.19 120.00

Page 299: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 255 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-15072 72 In Equiv CSPA Lin Foot ===============================================

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 48.00 141.00 205.00 300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 48.00 141.00 205.00 300.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 48.00 141.00 205.00 300.00

=============== 603-30012 12 In SES Each ===================================================

IM 0701-157 FRUITA TO CLIFTON 02/26/04 1.00 180.00 196.33 140.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 180.00 196.33 140.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 180.00 196.33 140.00

=============== 603-30015 15 In SES Each ===================================================

BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 4.00 200.00 201.57 56.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4.00 200.00 201.57 56.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 200.00 201.57 56.00

=============== 603-30018 18 In SES Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 225.00 245.90 220.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 2.00 225.00 402.76 279.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 2.00 400.00 349.64 205.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5.00 295.00 340.31 237.60

NH 0502-053 CIMARRON - WEST 04/15/04 4.00 250.00 620.56 600.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 2.00 300.00 215.62 280.00IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 14.00 235.00 387.50 522.50SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 10.00 250.00 391.72 127.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 2.00 200.00 339.60 300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 32.00 243.44 401.11 379.53

Page 300: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 256 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-30018 18 In SES Each ===================================================

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 8.00 300.00 290.06 224.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 7.00 500.00 618.96 480.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 24.00 250.00 322.50 260.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 39.00 305.13 357.32 292.10 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 76.00 278.49 373.70 325.33

=============== 603-30024 24 In SES Each ===================================================

STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 16.00 250.00 340.26 280.80IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 2.00 275.00 313.63 265.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 12.00 350.00 367.00 350.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 1.00 250.00 260.83 235.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 5.00 350.00 379.18 285.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 36.00 298.61 350.74 302.30

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 1.00 310.00 363.83 210.00NH 0502-053 CIMARRON - WEST 04/15/04 38.00 300.00 411.65 300.00IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 2.00 270.00 456.67 645.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 10.00 265.00 447.24 160.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 4.00 250.00 429.00 325.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 11.00 300.00 313.42 320.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 66.00 290.91 397.07 292.73

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 12.00 350.00 330.94 260.00SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 1.00 500.00 325.00 450.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 12.00 700.00 640.92 520.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 29.00 300.00 415.00 390.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 54.00 403.70 434.40 391.11

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 1.00 350.00 458.00 400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 350.00 458.00 400.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 157.00 331.85 395.25 329.44

Page 301: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 257 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-30030 30 In SES Each ===================================================

STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 2.00 300.00 490.72 537.60STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 2.00 450.00 507.00 450.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 3.00 450.00 514.89 405.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 7.00 407.14 507.07 455.74

NH 0502-053 CIMARRON - WEST 04/15/04 10.00 350.00 608.01 650.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 34.00 310.00 403.55 400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 44.00 319.09 437.06 456.82

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 2.00 500.00 504.50 443.00SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 1.00 600.00 400.00 500.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 350.00 596.75 530.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4.00 487.50 515.93 479.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 55.00 342.55 450.36 458.29

=============== 603-30036 36 In SES Each ===================================================

STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 8.00 400.00 555.08 710.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 8.00 400.00 555.08 710.40

NH 0502-053 CIMARRON - WEST 04/15/04 7.00 500.00 558.16 550.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 350.00 531.95 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 8.00 481.25 553.53 543.75

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 3.00 900.00 957.21 725.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 2.00 500.00 750.00 750.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 5.00 740.00 859.70 735.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 21.00 511.90 611.41 652.77

Page 302: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 258 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-30042 42 In SES Each ===================================================

NH 0502-053 CIMARRON - WEST 04/15/04 1.00 600.00 802.37 800.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 400.00 884.85 800.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 500.00 851.85 800.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 500.00 851.85 800.00

=============== 603-30048 48 In SES Each ===================================================

STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 2.00 800.00 1215.12 1725.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 800.00 1215.12 1725.60

NH 0502-053 CIMARRON - WEST 04/15/04 5.00 650.00 1055.23 1300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 5.00 650.00 1055.23 1300.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 7.00 692.86 1108.52 1421.60

=============== 603-31330 30 In Equiv Arch SES Each ===================================================

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 4.00 350.00 459.91 410.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4.00 350.00 459.91 410.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 350.00 459.91 410.00

=============== 603-31342 42 In Equiv Arch SES Each ===================================================

NH 0502-053 CIMARRON - WEST 04/15/04 1.00 650.00 654.28 650.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 650.00 654.28 650.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 650.00 654.28 650.00

=============== 603-33018 18 In Pipe Safety End Treat Each ===================================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 2.00 650.00 372.50 455.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 650.00 372.50 455.00

Page 303: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 259 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-33018 18 In Pipe Safety End Treat Each ===================================================

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 9.00 800.00 1296.22 550.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 9.00 800.00 1296.22 550.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 11.00 772.73 1177.03 532.73

=============== 603-33024 24 In Pipe Safety End Treat Each ===================================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 2.00 1130.00 415.00 480.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 1130.00 415.00 480.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 1130.00 415.00 480.00

=============== 603-33036 36 In Pipe Safety End Treat Each ===================================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 2.00 2200.00 557.50 685.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 2200.00 557.50 685.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 2200.00 557.50 685.00

=============== 603-33042 42 In Pipe Safety End Treat Each ===================================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 5.00 4200.00 642.50 815.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5.00 4200.00 642.50 815.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5.00 4200.00 642.50 815.00

=============== 603-33048 48 In Pipe Safety End Treat Each ===================================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 4.00 9000.00 807.50 1065.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 9000.00 807.50 1065.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 9000.00 807.50 1065.00

Page 304: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 260 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-50002 2 In Plastic Pipe Lin Foot ===============================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 38.00 20.00 48.00 85.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 38.00 20.00 48.00 85.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 38.00 20.00 48.00 85.00

=============== 603-50003 3 In Plastic Pipe Lin Foot ===============================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 1,104.00 10.00 50.26 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,104.00 10.00 50.26 60.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,104.00 10.00 50.26 60.00

=============== 603-50004 4 In Plastic Pipe Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 350.00 16.00 12.85 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 350.00 16.00 12.85 10.00

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 22.00 11.00 53.51 45.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 22.00 11.00 53.51 45.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 372.00 15.70 14.08 12.07

=============== 603-50006 6 In Plastic Pipe Lin Foot ===============================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 2,006.00 20.00 24.99 30.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2,006.00 20.00 24.99 30.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,006.00 20.00 24.99 30.00

=============== 603-50008 8 In Plastic Pipe Lin Foot ===============================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 12.00 85.00 54.50 90.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 12.00 85.00 54.50 90.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 12.00 85.00 54.50 90.00

Page 305: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 261 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-50012 12 In Plastic Pipe Lin Foot ===============================================

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 3,100.00 30.00 20.54 22.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3,100.00 30.00 20.54 22.00

IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 100.00 30.00 97.08 45.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 100.00 30.00 97.08 45.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3,200.00 30.00 21.75 22.72

=============== 603-50018 18 In Plastic Pipe Lin Foot ===============================================

IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 60.00 60.00 85.17 70.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 60.00 60.00 85.17 70.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 60.00 60.00 85.17 70.00

=============== 603-50024 24 In Plastic Pipe Lin Foot ===============================================

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 648.00 120.00 76.80 73.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 648.00 120.00 76.80 73.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 648.00 120.00 76.80 73.00

=============== 603-61120 12 In Flexible Pipe Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 587.00 35.00 22.14 11.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 587.00 35.00 22.14 11.00

NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 140.00 40.00 29.00 32.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 140.00 40.00 29.00 32.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 727.00 35.96 23.18 15.04

Page 306: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 262 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-61180 18 In Flexible Pipe Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 258.00 50.00 28.20 20.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 258.00 50.00 28.20 20.00

SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 5.00 90.00 155.00 215.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 5.00 90.00 155.00 215.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 263.00 50.76 29.42 23.71

=============== 603-70303 3x3 Ft CBC (Precast) Lin Foot ===============================================

NH 2852-010 US 285 & COUNTY RD. G 04/29/04 90.00 275.00 234.60 201.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 90.00 275.00 234.60 201.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 90.00 275.00 234.60 201.00

=============== 603-70604 6x4 Ft CBC (Precast) Lin Foot ===============================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 229.00 280.00 255.00 270.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 229.00 280.00 255.00 270.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 229.00 280.00 255.00 270.00

=============== 603-70606 6x6 Ft CBC (Precast) Lin Foot ===============================================

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 126.00 500.00 300.85 320.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 126.00 500.00 300.85 320.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 126.00 500.00 300.85 320.00

=============== 603-70805 8x5 Ft CBC (Precast) Lin Foot ===============================================

STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 86.00 290.00 420.33 380.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 86.00 290.00 420.33 380.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 86.00 290.00 420.33 380.00

Page 307: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 263 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 603-70806 8x6 Ft CBC (Precast) Lin Foot ===============================================

NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 43.00 500.00 918.25 488.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 43.00 500.00 918.25 488.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 43.00 500.00 918.25 488.00

=============== 603-82004 4 In Duct Iron Pipe Lin Foot ===============================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 12.00 20.00 83.15 75.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 12.00 20.00 83.15 75.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 12.00 20.00 83.15 75.00

=============== 603-83012 12 In Sewer Pipe Lin Foot ===============================================

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 126.00 40.00 56.25 55.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 126.00 40.00 56.25 55.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 126.00 40.00 56.25 55.00

=============== 604-00305 Inlet Ty C (5 Ft) Each ===================================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 1.00 2400.00 2914.45 2600.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 1.00 2000.00 2701.46 2108.79STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 1.00 2200.00 2537.50 2475.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 2.00 2000.00 1945.77 1360.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 2.00 2500.00 2616.33 2000.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1.00 2200.00 1750.00 1700.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 8.00 2225.00 2356.43 1950.47

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 1.00 2000.00 2401.67 2100.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 1.00 2200.00 2090.44 2120.94STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 2.00 2000.00 2391.09 2134.00STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 2.00 2000.00 2120.00 2200.00

Page 308: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 264 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 604-00305 Inlet Ty C (5 Ft) Each ===================================================STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 1.00 2000.00 2269.50 1960.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 2.00 1600.00 2125.48 2400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 9.00 1933.33 2235.35 2183.22

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 15.00 2500.00 2001.77 2900.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 4.00 2500.00 3029.78 2770.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 6.00 3000.00 2540.51 2600.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 2.00 3000.00 2068.80 2400.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 1.00 3000.00 2733.33 2000.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 2300.00 2750.00 3300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 29.00 2648.28 2228.75 2768.28

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 1.00 3000.00 2820.00 3100.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 5.00 2000.00 2135.85 2000.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 1.00 4000.00 3208.33 4500.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 5.00 1900.00 4183.33 4400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 12.00 2208.33 3136.77 3300.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 58.00 2387.93 2452.07 2674.70

=============== 604-00310 Inlet Ty C (10 Ft) Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 2.00 2500.00 3063.94 2733.61STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1.00 2500.00 2692.50 2685.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3.00 2500.00 3010.87 2717.41

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 2500.00 2427.11 2900.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 2500.00 2427.11 2900.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 3.00 3000.00 3203.92 3400.00

Page 309: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 265 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 604-00310 Inlet Ty C (10 Ft) Each ===================================================IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 3250.00 3762.63 2770.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 2.00 3500.00 3439.78 3500.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 2500.00 3725.00 3800.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 7.00 3107.14 3383.12 3395.71

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 2.00 2500.00 2803.96 2600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 2500.00 2803.96 2600.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 13.00 2826.92 3103.47 3078.63

=============== 604-00315 Inlet Ty C (15 Ft) Each ===================================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1.00 3600.00 3482.50 3465.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 3600.00 3482.50 3465.00

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 4.00 4000.00 3220.17 4000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4.00 4000.00 3220.17 4000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5.00 3920.00 3240.35 3893.00

=============== 604-00320 Inlet Ty C (20 Ft) Each ===================================================

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 5000.00 3888.88 5000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 5000.00 3888.88 5000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 5000.00 3888.88 5000.00

=============== 604-00350 Inlet Ty C (Spec) Each ===================================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 2.00 3000.00 3396.95 3330.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 3000.00 3396.95 3330.00

Page 310: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 266 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 604-00350 Inlet Ty C (Spec) Each ===================================================

STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 1.00 2500.00 4976.31 2585.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 2500.00 4976.31 2585.00

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 3.00 4000.00 2993.88 2800.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 3.00 4000.00 2993.88 2800.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6.00 3416.67 3563.93 2940.83

=============== 604-00505 Inlet Ty D (5 Ft) Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 3000.00 2484.94 2000.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 1.00 2500.00 3094.15 3060.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 2750.00 2746.03 2530.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 4.00 2700.00 2583.39 3000.00STA 149A-021 SH 149 CRIBWALL 09/16/04 1.00 2800.00 5300.00 5300.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 1.00 3000.00 3305.84 3500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 6.00 2766.67 2776.72 3466.67

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 4.00 2400.00 3481.71 3600.00STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 1.00 3200.00 5156.00 5000.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 1.00 3750.00 6260.00 7000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 6.00 2758.33 4168.97 4400.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 14.00 2760.71 3385.90 3732.86

=============== 604-00510 Inlet Ty D (10 Ft) Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 4500.00 3855.14 4500.00

Page 311: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 267 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 604-00510 Inlet Ty D (10 Ft) Each ===================================================STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 4.00 3500.00 3322.50 3245.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5.00 3700.00 3588.82 3496.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 3.00 3500.00 3230.53 3600.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 3.00 4000.00 4512.32 5600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 6.00 3750.00 3657.79 4600.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 3.00 3500.00 4546.46 5200.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 1.00 4500.00 8255.67 8500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4.00 3750.00 5473.76 6025.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 15.00 3733.33 4291.82 4612.00

=============== 604-00515 Inlet Ty D (15 Ft) Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 6000.00 5048.24 5900.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 2.00 5250.00 3910.00 3720.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3.00 5500.00 4668.83 4446.67

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 1.00 5000.00 5804.03 7105.51 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 5000.00 5804.03 7105.51

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 500.00 5425.00 5600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 500.00 5425.00 5600.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5.00 4400.00 5145.83 5209.10

=============== 604-00550 Inlet Ty D (Spec) Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 2.00 8000.00 3797.65 3000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 8000.00 3797.65 3000.00

Page 312: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 268 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 604-00550 Inlet Ty D (Spec) Each ===================================================

NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 11.00 5000.00 5689.67 5700.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 11.00 5000.00 5689.67 5700.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 13.00 5461.54 5320.49 5284.62

=============== 604-13005 Inlet Ty 13 (5 Ft) Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 1.00 2500.00 2496.39 2008.37 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 2500.00 2496.39 2008.37

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 7.00 2500.00 2176.35 2900.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 7.00 2500.00 2176.35 2900.00

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 2.00 2860.00 3000.00 3300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 2860.00 3000.00 3300.00

NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 2.00 3000.00 4625.50 5300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 3000.00 4625.50 5300.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 12.00 2643.33 2733.69 3292.36

=============== 604-13006 Inlet Ty 13 (5 Ft) (Spec) Each ===================================================

STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 18.00 2200.00 3388.16 2486.11NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 3300.00 2718.48 4400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 19.00 2257.89 3357.72 2586.84 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 19.00 2257.89 3357.72 2586.84

Page 313: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 269 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 604-13010 Inlet Ty 13 (10 Ft) Each ===================================================

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 2.00 4500.00 2856.12 3800.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 4500.00 2856.12 3800.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 4500.00 2856.12 3800.00

=============== 604-13011 Inlet Ty 13 (10 Ft) (Spec) Each ===================================================

STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 2.00 4000.00 3848.10 2859.76 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 4000.00 3848.10 2859.76 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 4000.00 3848.10 2859.76

=============== 604-19000 Inlet Spec Each ===================================================

SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 2.00 4500.00 3512.50 3650.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 4500.00 3512.50 3650.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 4500.00 3512.50 3650.00

=============== 604-19010 Inlet Spec (10 Ft) Each ===================================================

SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 1.00 6700.00 5175.00 5500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 6700.00 5175.00 5500.00

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 4000.00 4976.81 4100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 4000.00 4976.81 4100.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 5350.00 5075.90 4800.00

=============== 604-19015 Inlet Spec (15 Ft) Each ===================================================

STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 1.00 5000.00 5952.54 8615.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 5000.00 5952.54 8615.25 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 5000.00 5952.54 8615.25

Page 314: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 270 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 604-19105 Inlet Ty R L5 (5 Ft) Each ===================================================

STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 2.00 2500.00 3295.83 3500.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 1.00 2500.00 4239.82 5280.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 5.00 3160.00 2875.00 2650.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 8.00 2912.50 3314.78 3191.25

STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 11.00 3500.00 3135.00 3460.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 8.00 2500.00 2768.55 3600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 19.00 3078.95 2943.81 3518.95

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 10.00 3300.00 3022.18 4000.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1.00 2500.00 2436.90 3300.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 2.00 2750.00 4025.00 4700.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 13.00 3153.85 3103.07 4053.85

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 4.00 2500.00 2922.27 2700.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 6.00 2500.00 3163.89 2400.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 2.00 3400.00 3400.00 3600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 12.00 2650.00 3082.74 2700.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 52.00 2973.08 3060.55 3413.27

=============== 604-19110 Inlet Ty R L5 (10 Ft) Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 1.00 3500.00 4288.66 3220.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1.00 4600.00 3147.50 2795.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 4050.00 4060.43 3007.50

STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 24.00 4000.00 4002.50 4560.00

Page 315: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 271 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 604-19110 Inlet Ty R L5 (10 Ft) Each ===================================================NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 8.00 4000.00 3248.77 4200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 32.00 4000.00 3751.26 4470.00

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 2.00 5000.00 3974.21 3900.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 5000.00 3974.21 3900.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1.00 3250.00 3627.05 3600.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 3.00 3500.00 4116.45 3400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4.00 3437.50 3953.32 3450.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 40.00 3996.25 3800.48 4266.38

=============== 604-19115 Inlet Ty R L5 (15 Ft) Each ===================================================

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 5500.00 4341.57 5000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 5500.00 4341.57 5000.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1.00 4500.00 5007.12 5300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 4500.00 5007.12 5300.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 5000.00 4674.34 5150.00

=============== 604-19205 Inlet Ty R L10 (5 Ft) Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 3.00 4500.00 4016.99 3800.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1.00 4200.00 3510.00 3520.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 4425.00 3977.99 3730.00

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 3800.00 3644.49 4500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 3800.00 3644.49 4500.00

Page 316: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 272 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 604-19205 Inlet Ty R L10 (5 Ft) Each ===================================================

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 3.00 4000.00 4294.95 4000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 3.00 4000.00 4294.95 4000.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 2.00 4200.00 3973.64 4100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 4200.00 3973.64 4100.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10.00 4190.00 4023.77 3962.00

=============== 604-19210 Inlet Ty R L10 (10 Ft) Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 2.00 5000.00 4788.70 4900.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 2.00 4360.00 4767.50 4835.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 4680.00 4784.46 4867.50

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 4500.00 4518.18 5200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 4500.00 4518.18 5200.00

STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 1.00 5000.00 5100.00 5500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 5000.00 5100.00 5500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6.00 4703.33 4762.01 5028.33

=============== 604-19215 Inlet Ty R L10 (15 Ft) Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 6850.00 6624.66 6900.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 6850.00 6624.66 6900.00

Page 317: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 273 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 604-19215 Inlet Ty R L10 (15 Ft) Each ===================================================

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 2.00 6000.00 5774.28 5900.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 6000.00 5774.28 5900.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 6283.33 6114.43 6233.33

=============== 604-19305 Inlet Ty R L15 (5 Ft) Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 3.00 5000.00 5170.21 5400.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1.00 5670.00 4970.00 4740.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 5167.50 5154.81 5235.00

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 5500.00 5517.71 5000.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 1.00 4400.00 5315.11 5000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 4950.00 5427.67 5000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6.00 5095.00 5224.97 5156.67

=============== 604-19310 Inlet Ty R L15 (10 Ft) Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 7000.00 6206.96 5600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 7000.00 6206.96 5600.00

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 6000.00 7092.89 5000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 6000.00 7092.89 5000.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1.00 5500.00 6321.25 7400.00

Page 318: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 274 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 604-19310 Inlet Ty R L15 (10 Ft) Each ===================================================BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 5000.00 6862.04 4200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 5250.00 6537.57 5800.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 5875.00 6543.29 5550.00

=============== 604-19315 Inlet Ty R L15 (15 Ft) Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 3.00 8500.00 8118.96 7300.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1.00 8600.00 8182.50 8065.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 8525.00 8123.84 7491.25 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 8525.00 8123.84 7491.25

=============== 604-19405 Inlet Ty R Spec (5 Ft) Each ===================================================

STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 1.00 3500.00 3790.24 2900.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 3500.00 3790.24 2900.00

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 6.00 3500.00 3198.15 3583.31STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 8.00 3000.00 3007.50 3930.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 14.00 3214.29 3127.21 3781.42

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 3500.00 4064.40 3600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 3500.00 4064.40 3600.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 16.00 3250.00 3228.12 3714.99

=============== 604-19410 Inlet Ty R Spec (10 Ft) Each ===================================================

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 17.00 4250.00 4554.81 6293.29STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 1.00 4200.00 4910.00 4670.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 18.00 4247.22 4563.86 6203.11 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 18.00 4247.22 4563.86 6203.11

Page 319: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 275 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 604-19505 Inlet Ty R L20 (5 Ft) Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 8500.00 7060.70 6700.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 8500.00 7060.70 6700.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 8500.00 7060.70 6700.00

=============== 604-20000 Outlet Structure Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 3.00 6000.00 7181.65 6400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3.00 6000.00 7181.65 6400.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 6000.00 7181.65 6400.00

=============== 604-25000 Vane Grate Inlet Spec Each ===================================================

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 2.00 2500.00 4335.20 4500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 2500.00 4335.20 4500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 2500.00 4335.20 4500.00

=============== 604-25005 Vane Grate Inlet (5 Ft) Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 9.00 2700.00 4224.17 2410.04STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 2.00 3350.00 2402.50 1905.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 11.00 2818.18 4098.54 2318.21

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 2.00 3200.00 3185.75 3800.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 3200.00 3185.75 3800.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 13.00 2876.92 3942.06 2546.18

=============== 604-25006 Vane Grate Inlet Spec (5 Ft) Each ===================================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 2.00 4000.00 4406.58 5170.00

Page 320: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 276 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 604-25006 Vane Grate Inlet Spec (5 Ft) Each ===================================================STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 3500.00 6220.69 2400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 3.00 3833.33 5104.32 4246.67 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 3833.33 5104.32 4246.67

=============== 604-25010 Vane Grate Inlet (10 Ft) Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 5.00 3300.00 4469.27 2945.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5.00 3300.00 4469.27 2945.60 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5.00 3300.00 4469.27 2945.60

=============== 604-26005 Vane Grate Inlet (D) (5 Ft) Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 3.00 3200.00 4881.05 2711.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3.00 3200.00 4881.05 2711.30

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 6.00 4200.00 4004.05 5000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 6.00 4200.00 4004.05 5000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 9.00 3866.67 4296.38 4237.10

=============== 604-26010 Vane Grate Inlet (D) (10 Ft) Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 2.00 4000.00 6423.17 4039.05 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 4000.00 6423.17 4039.05

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 2.00 4800.00 4969.45 6400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 4800.00 4969.45 6400.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 4400.00 5696.31 5219.52

Page 321: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 277 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 604-30005 MH Slab Base (5 Ft) Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 9.00 1900.00 2363.89 2008.37 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 9.00 1900.00 2363.89 2008.37

STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 2.00 2000.00 1978.48 1147.00STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 1.00 2000.00 2483.33 2700.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3.00 2000.00 2067.57 1664.67

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 2300.00 2039.22 2200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 2300.00 2039.22 2200.00

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 2.00 2000.00 3000.00 2700.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 3.00 2200.00 2151.31 2150.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 5.00 2120.00 2454.42 2370.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 18.00 2000.00 2324.22 2062.18

=============== 604-30010 MH Slab Base (10 Ft) Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 4.00 2800.00 2926.20 3057.18IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 3.00 2500.00 2714.21 2200.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1.00 3000.00 3270.67 2100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 8.00 2712.50 2877.54 2616.09

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 1.00 2500.00 2434.17 1800.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 4.00 2500.00 3377.94 3603.46STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 1.00 2500.00 2355.01 1452.49STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 19.00 2700.00 4505.00 2850.00

Page 322: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 278 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 604-30010 MH Slab Base (10 Ft) Each ===================================================NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 2500.00 2483.93 2200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 26.00 2646.15 3892.97 2846.78

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 3.00 3000.00 3487.57 2500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 3.00 3000.00 3487.57 2500.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 9.00 2500.00 2839.61 3100.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 4000.00 3616.75 3100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 10.00 2650.00 2893.20 3100.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 47.00 2680.85 3430.63 2839.26

=============== 604-30015 MH Slab Base (15 Ft) Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 3500.00 4267.52 3300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 3500.00 4267.52 3300.00

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 3.00 3000.00 4824.02 3997.17 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3.00 3000.00 4824.02 3997.17

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 3.00 3500.00 3741.19 4600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3.00 3500.00 3741.19 4600.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 7.00 3285.71 4372.27 4155.93

=============== 604-30020 MH Slab Base (20 Ft) Each ===================================================

STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1.00 5000.00 4831.68 3650.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 5000.00 4831.68 3650.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 5000.00 4831.68 3650.00

Page 323: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 279 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 604-31010 MH Box Base (10 Ft) Each ===================================================

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 2.00 4600.00 6546.62 4200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 4600.00 6546.62 4200.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 4600.00 6546.62 4200.00

=============== 604-31015 MH Box Base (15 Ft) Each ===================================================

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 6000.00 7922.44 5000.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 4000.00 6700.00 5400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 5000.00 7379.13 5200.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 5000.00 7379.13 5200.00

=============== 604-39000 MH Spec Each ===================================================

SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 2.00 5000.00 6487.50 8750.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 5000.00 6487.50 8750.00

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 1.00 7000.00 4148.20 4000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 7000.00 4148.20 4000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 5666.67 5707.73 7166.67

=============== 604-39005 MH Spec (5 Ft) Each ===================================================

STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 3.00 2000.00 3039.50 1920.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3.00 2000.00 3039.50 1920.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 2000.00 3039.50 1920.00

=============== 604-39010 MH Spec (10 Ft) Each ===================================================

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 1.00 5000.00 4380.53 3912.80

Page 324: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 280 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 604-39010 MH Spec (10 Ft) Each ===================================================STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 2.00 3000.00 4803.75 2830.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3.00 3666.67 4579.69 3190.93 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 3666.67 4579.69 3190.93

=============== 604-39015 MH Spec (15 Ft) Each ===================================================

STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 1.00 5500.00 7753.00 5600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 5500.00 7753.00 5600.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 5500.00 7753.00 5600.00

=============== 604-39020 MH Spec (20 Ft) Each ===================================================

STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 1.00 6000.00 9383.00 6200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 6000.00 9383.00 6200.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 6000.00 9383.00 6200.00

=============== 604-39050 MH (TMS) Each ===================================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 62.00 3000.00 2752.03 2650.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 62.00 3000.00 2752.03 2650.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 2.00 2000.00 3576.20 3700.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 2000.00 3576.20 3700.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 64.00 2968.75 2801.98 2682.81

=============== 604-50000 IG and F (Median) Each ===================================================

NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 9.00 1200.00 593.90 285.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 9.00 1200.00 593.90 285.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 9.00 1200.00 593.90 285.00

Page 325: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 281 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 604-50060 Grating and Frame Lin Foot ===============================================

STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 10.00 200.00 340.98 160.85 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 10.00 200.00 340.98 160.85 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10.00 200.00 340.98 160.85

=============== 604-50800 San Sewer Vault Each ===================================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 1.00 2000.00 10592.96 11500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 2000.00 10592.96 11500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 2000.00 10592.96 11500.00

=============== 604-56000 Slot Vane Drain Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 4.00 1800.00 2871.50 1629.01 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 1800.00 2871.50 1629.01

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 76.00 1800.00 719.69 450.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 76.00 1800.00 719.69 450.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 80.00 1800.00 827.28 508.95

=============== 605-00020 2 Inch PP Underdrain Lin Foot ===============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 8,000.00 30.00 14.40 13.39 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 8,000.00 30.00 14.40 13.39 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8,000.00 30.00 14.40 13.39

=============== 605-00040 4 In PP Underdrain Lin Foot ===============================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 5,154.00 4.00 21.70 9.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5,154.00 4.00 21.70 9.40

Page 326: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 282 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 605-00040 4 In PP Underdrain Lin Foot ===============================================

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 2,122.00 16.00 20.52 11.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2,122.00 16.00 20.52 11.10 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 7,276.00 7.50 21.10 9.90

=============== 605-00060 6 In PP Underdrain Lin Foot ===============================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 265.00 40.00 29.80 21.90NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 7,285.00 20.00 29.54 18.49 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 7,550.00 20.70 29.55 18.61

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 86.00 40.00 55.02 43.64 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 86.00 40.00 55.02 43.64

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 2,601.00 30.00 23.76 40.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2,601.00 30.00 23.76 40.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10,237.00 23.23 28.52 24.26

=============== 605-01020 2 In Hor Drain Lin Foot ===============================================

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 3,000.00 50.00 30.60 30.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3,000.00 50.00 30.60 30.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3,000.00 50.00 30.60 30.00

=============== 605-82100 Pipe Edge Drain Lin Foot ===============================================

STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 800.00 15.00 16.26 6.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 800.00 15.00 16.26 6.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 800.00 15.00 16.26 6.00

Page 327: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 283 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 605-82306 6 In Drain Pipe Lin Foot ===============================================

NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 90.00 30.00 20.13 30.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 90.00 30.00 20.13 30.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 90.00 30.00 20.13 30.00

=============== 605-83560 6 In Pipe Underdrain Lin Foot ===============================================

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 325.00 30.00 21.47 22.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 325.00 30.00 21.47 22.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 325.00 30.00 21.47 22.00

=============== 605-84000 Subsurface Drain Outlet Lin Foot ===============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 30.00 30.00 22.80 15.62 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 30.00 30.00 22.80 15.62

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 82.00 20.00 23.55 40.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 200.00 16.00 19.25 24.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 282.00 17.16 20.71 28.65 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 312.00 18.40 20.98 27.40

=============== 605-84100 Subsurface Drain Outlet Str Each ===================================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 4.00 540.00 472.50 375.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 540.00 472.50 375.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 540.00 472.50 375.00

=============== 606-00301 Gdrail Ty 3 (6-3) Lin Foot ===============================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 234.00 13.00 15.15 15.00

Page 328: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 284 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 606-00301 Gdrail Ty 3 (6-3) Lin Foot ===============================================STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 164.00 15.00 15.53 15.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 1,002.00 13.00 25.39 20.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 325.00 20.00 13.66 12.50STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 3,150.00 12.00 11.99 10.96STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 2,210.00 13.00 11.87 11.65STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 62.50 25.00 26.16 26.00IM 0701-164 PARACHUTE EAST & WEST 02/12/04 50.00 13.00 18.80 17.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 13,075.00 11.00 14.83 12.24STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 337.50 13.00 16.25 15.20STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 3,225.00 13.00 14.80 13.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 675.00 13.00 12.84 12.20STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 2,837.50 13.00 12.96 12.50IM 0701-157 FRUITA TO CLIFTON 02/26/04 688.00 13.00 14.01 12.80STA 014A-030 SH 14, WALDEN EAST 03/04/04 350.00 12.00 18.93 18.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 1,400.00 13.00 16.33 16.00NH 2872-016 US 287 - LAMAR 03/04/04 737.50 13.00 14.99 14.45NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 5,330.00 11.00 11.09 10.80SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 413.00 10.00 19.67 18.00STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 5,462.00 11.00 13.04 13.40C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 25.00 15.00 52.00 52.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 7,068.00 10.00 15.00 14.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 17,140.00 12.00 12.61 12.30STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 3,225.00 10.60 11.25 11.50STA 0063-016 CLIFTON TO PALISADE 03/25/04 338.00 13.00 22.00 21.00STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 10,045.00 10.00 14.23 16.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 79,569.00 11.43 13.52 13.18

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 1,443.75 12.00 14.90 14.50NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 9,293.25 10.00 15.97 15.00NH 0502-053 CIMARRON - WEST 04/15/04 4,875.00 11.00 13.29 13.50NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 5,550.00 12.00 13.94 13.40STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 1,100.00 11.00 17.76 17.85ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 203.00 30.00 38.99 25.20IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 136.00 30.00 22.08 25.28STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 94.00 15.00 26.64 22.40IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 2,225.00 11.00 13.93 12.60SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 1,125.00 12.00 17.30 16.50STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 807.50 30.00 26.91 26.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 4,350.00 13.00 14.71 14.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 607.00 14.00 18.07 18.00CC R600-225 CHATFIELD STATE PARK 06/10/04 2,050.00 13.00 14.50 15.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 2,739.00 12.00 14.12 13.60STA 0343-023 US 34, EAST OF AKRON 06/17/04 350.00 15.00 17.90 16.90STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 38.00 11.00 40.33 37.00

Page 329: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 285 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 606-00301 Gdrail Ty 3 (6-3) Lin Foot ===============================================BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 350.00 15.00 18.94 22.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 37,336.50 12.10 15.46 14.82

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 400.00 20.00 16.10 15.65IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 20,391.00 10.00 12.89 13.00SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 150.00 22.00 22.00 21.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 710.00 18.00 24.83 25.67BR 0243-063 EAST OF LIMON 07/15/04 850.00 15.00 16.83 17.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 600.00 17.00 17.44 17.60C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 850.00 12.00 17.38 17.00STA 149A-021 SH 149 CRIBWALL 09/16/04 240.00 13.00 21.00 21.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 4,377.00 12.00 16.55 14.80 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 28,568.00 11.09 13.81 14.07

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 4,570.00 12.00 14.45 14.25BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 3,426.00 13.00 14.21 13.85C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 2,523.00 13.00 16.60 14.20IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 3,250.00 16.00 17.91 16.50STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 125.00 15.00 19.94 25.00NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 1,058.00 16.00 17.30 16.90IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 75.00 20.00 15.70 15.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 11,590.00 12.00 17.03 17.50NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 402.00 13.00 20.87 22.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 80.00 25.00 31.08 35.30STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 1,100.00 13.00 17.85 16.55 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 28,199.00 12.95 16.53 16.20 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 173,672.50 11.76 14.50 14.17

=============== 606-00305 Gdrail Ty 3 (Spec) Lin Foot ===============================================

C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 75.00 32.00 42.00 42.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 75.00 32.00 42.00 42.00

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 1,050.00 20.00 39.56 38.00

Page 330: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 286 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 606-00305 Gdrail Ty 3 (Spec) Lin Foot ===============================================C R200-126 FY04 REGION 2 SIGNING 04/01/04 150.00 25.00 29.38 26.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 112.00 30.00 28.68 26.62 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,312.00 21.43 37.86 35.66 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,387.00 22.00 37.90 36.00

=============== 606-00700 Gdrail Ty 7 Lin Foot ===============================================

STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 20.00 50.00 73.62 71.05C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 160.00 55.00 118.00 118.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 400.00 80.00 43.15 32.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 580.00 72.07 48.22 57.07

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 150.00 45.00 34.33 42.00IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 327.00 60.00 58.57 76.91 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 477.00 55.28 51.73 65.93

ER 0702-255 I-70 GLENWOOD CANYON 11/30/04 100.00 200.00 140.33 250.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 100.00 200.00 140.33 250.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,157.00 76.21 54.13 77.40

=============== 606-00701 Gdrail (Cable) Lin Foot ===============================================

IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 16,370.00 8.00 13.53 12.63 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 16,370.00 8.00 13.53 12.63 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 16,370.00 8.00 13.53 12.63

=============== 606-00705 Gdrail Ty 7 (Spec) Lin Foot ===============================================

NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 124.00 100.00 72.50 85.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 124.00 100.00 72.50 85.00

Page 331: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 287 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 606-00705 Gdrail Ty 7 (Spec) Lin Foot ===============================================

NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 244.00 125.00 193.68 102.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 244.00 125.00 193.68 102.30

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 4,299.00 50.00 37.92 32.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4,299.00 50.00 37.92 32.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4,667.00 55.25 46.64 37.08

=============== 606-00710 Gdrail Ty 7 (Sty CA) Lin Foot ===============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 6,446.00 45.00 38.67 34.03STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 3,610.00 32.00 32.50 35.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 10,056.00 40.33 37.70 34.38

STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 220.00 68.00 101.75 54.00STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 13.00 110.00 213.38 222.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 233.00 70.34 104.95 63.37

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 380.00 55.00 66.85 80.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 380.00 55.00 66.85 80.00

STA 0703-290 GEORGETOWN HILL ROCKFALL MITI 10/07/04 350.00 40.00 56.00 52.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 5,352.00 38.00 35.52 34.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 853.00 45.00 40.81 45.00STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 416.00 35.00 37.95 55.00

Page 332: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 288 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 606-00710 Gdrail Ty 7 (Sty CA) Lin Foot ===============================================STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 640.00 30.00 67.18 50.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 7,611.00 38.04 38.86 38.61 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 18,280.00 40.07 39.53 37.46

=============== 606-00720 Gdrail Ty 7 (Sty CC) Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 767.00 30.00 54.49 58.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 767.00 30.00 54.49 58.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 767.00 30.00 54.49 58.00

=============== 606-00730 Gdrail Ty 7 (Sty CD) Lin Foot ===============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 3,082.00 40.00 40.88 43.29 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3,082.00 40.00 40.88 43.29

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 2,265.00 50.00 42.64 27.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2,265.00 50.00 42.64 27.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 500.00 32.00 49.01 40.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 500.00 32.00 49.01 40.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5,847.00 43.19 42.26 36.70

=============== 606-00755 Conc Glare Screen (Prec Ty 7) Lin Foot ===============================================

IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 10,600.00 8.00 30.67 30.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 10,600.00 8.00 30.67 30.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10,600.00 8.00 30.67 30.00

Page 333: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 289 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 606-00800 Gdrail Ty 7 (F-Sh Conc Barrier) Lin Foot ===============================================

IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 12,040.00 20.00 55.87 47.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 12,040.00 20.00 55.87 47.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 12,040.00 20.00 55.87 47.00

=============== 606-00900 Gdrail (Spec) Lin Foot ===============================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 60.00 150.00 170.98 65.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 60.00 150.00 170.98 65.00

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 75.00 125.00 170.50 140.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 75.00 125.00 170.50 140.00

ER 0702-255 I-70 GLENWOOD CANYON 11/30/04 100.00 280.00 258.67 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 100.00 280.00 258.67 500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 235.00 197.34 197.33 274.04

=============== 606-01320 End Anchor Ty 3B Each ===================================================

STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 5.00 500.00 790.00 600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5.00 500.00 790.00 600.00

NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 4.00 500.00 1199.33 1300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4.00 500.00 1199.33 1300.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 9.00 500.00 1041.90 911.11

Page 334: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 290 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 606-01340 End Anchor Ty 3D Each ===================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 2.00 500.00 461.79 420.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 3.00 500.00 490.15 430.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 1.00 600.00 504.67 520.00STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 1.00 500.00 819.50 539.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 2.00 450.00 439.24 420.50IM 0701-157 FRUITA TO CLIFTON 02/26/04 6.00 350.00 489.17 525.00C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 4.00 500.00 730.00 730.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 18.00 400.00 512.50 475.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 7.00 350.00 467.50 475.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 44.00 414.77 495.03 499.43

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 10.00 430.00 577.17 560.00C R200-126 FY04 REGION 2 SIGNING 04/01/04 1.00 500.00 840.08 738.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 3.00 400.00 515.91 470.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 5.00 450.00 581.09 534.00CC R600-225 CHATFIELD STATE PARK 06/10/04 5.00 450.00 545.00 600.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 4.00 500.00 513.74 480.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 28.00 446.43 563.34 547.79

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 23.00 475.00 509.54 480.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 2.00 400.00 552.66 550.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 5.00 500.00 862.50 875.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 30.00 474.17 554.12 550.50

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 5.00 400.00 505.45 475.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 5.00 500.00 479.77 467.65C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 7.00 450.00 678.23 535.00IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 2.00 500.00 733.57 700.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 1.00 500.00 766.67 450.00STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 2.00 450.00 670.36 580.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 22.00 456.82 605.09 521.30 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 124.00 443.75 550.49 526.59

Page 335: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 291 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 606-01370 Transition Ty 3G Each ===================================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 4.00 900.00 1135.45 1100.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 4.00 1000.00 1028.21 810.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 31.00 800.00 825.05 780.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 7.00 800.00 1183.95 1288.70STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 36.00 800.00 850.40 787.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 2.00 850.00 795.43 775.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 4.00 850.00 1083.33 750.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 8.00 800.00 718.85 690.79IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 850.00 876.23 837.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 4.00 900.00 800.00 750.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 8.00 800.00 925.00 900.00NH 2872-016 US 287 - LAMAR 03/04/04 4.00 800.00 987.50 950.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 10.00 900.00 858.76 820.00SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 8.00 850.00 1036.67 930.00STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 4.00 950.00 1112.50 1000.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 8.00 820.00 837.50 825.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 12.00 1000.00 932.71 875.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 10.00 800.00 805.00 810.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 165.00 839.45 894.42 841.98

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 10.00 800.00 997.50 975.00NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 8.00 850.00 971.30 900.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 12.00 800.00 995.00 1000.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 12.00 850.00 963.44 914.00IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 2.00 900.00 1109.96 1150.69STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 4.00 1500.00 1224.25 1140.00STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 1.00 1100.00 2700.00 2775.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 1000.00 959.52 880.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 4.00 850.00 1056.42 1021.10STA 0343-023 US 34, EAST OF AKRON 06/17/04 4.00 850.00 1001.00 960.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 2.00 900.00 1060.57 1244.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 60.00 885.00 1021.36 1014.11

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 4.00 950.00 1043.00 1027.00IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 8.00 1100.00 778.49 770.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 11.00 1100.00 1270.75 1006.52BR 0243-063 EAST OF LIMON 07/15/04 4.00 900.00 1065.28 1000.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 3.00 1200.00 1242.45 1270.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 30.00 1063.33 1027.50 971.66

Page 336: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 292 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 606-01370 Transition Ty 3G Each ===================================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 5.00 800.00 959.40 950.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 3.00 825.00 834.16 814.55C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 1.00 825.00 1196.01 963.00IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 6.00 920.00 1028.57 950.00NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 2.00 1200.00 1083.33 1150.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 4.00 1100.00 1140.00 850.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 4.00 1000.00 1283.63 1544.50STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 4.00 850.00 1203.05 1041.35 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 29.00 931.72 1068.19 1031.04 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 284.00 882.15 952.76 911.35

=============== 606-01380 Transition Ty 3H Each ===================================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 20.00 600.00 556.92 575.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 1.00 550.00 531.96 545.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 8.00 500.00 478.21 465.64NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 7.00 520.00 540.00 480.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 10.00 500.00 462.50 465.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 46.00 547.61 517.34 516.96

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 6.00 500.00 558.00 530.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 4.00 450.00 627.26 605.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 10.00 480.00 579.31 560.28

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1.00 500.00 497.99 470.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 500.00 497.99 470.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 4.00 500.00 583.81 575.00

Page 337: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 293 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 606-01380 Transition Ty 3H Each ===================================================BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 2.00 500.00 505.70 493.45NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 2.00 500.00 633.33 700.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 4.00 600.00 691.67 525.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 12.00 533.33 603.14 565.58 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 69.00 534.64 542.50 531.01

=============== 606-01385 Transition Ty 3J Each ===================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 1.00 800.00 635.88 430.00NH 2872-016 US 287 - LAMAR 03/04/04 1.00 900.00 737.50 550.00STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 1.00 750.00 835.00 940.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3.00 816.67 702.71 640.00

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 7.00 500.00 654.30 635.00NH 0502-053 CIMARRON - WEST 04/15/04 2.00 625.00 781.88 790.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 10.00 800.00 591.25 550.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 5.00 500.00 567.20 533.00STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 1.00 1000.00 2007.90 2031.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 25.00 650.00 645.47 648.85

C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 2.00 550.00 466.09 470.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 550.00 466.09 470.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 30.00 660.00 639.93 636.04

=============== 606-01390 End Anchor Ty 3K Each ===================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 1.00 700.00 827.44 780.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 5.00 750.00 748.80 680.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 2.00 750.00 708.33 600.00NH 2872-016 US 287 - LAMAR 03/04/04 1.00 1000.00 836.25 795.00STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 1.00 850.00 875.00 800.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 10.00 780.00 780.58 697.50

Page 338: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 294 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 606-01390 End Anchor Ty 3K Each ===================================================

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 7.00 700.00 861.38 720.00NH 0502-053 CIMARRON - WEST 04/15/04 2.00 700.00 809.75 820.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 10.00 800.00 795.00 800.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 9.00 700.00 830.84 806.00STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 1.00 1000.00 1385.63 1443.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 29.00 744.83 835.27 806.10

C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1.00 700.00 1002.97 1000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 700.00 1002.97 1000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 40.00 752.50 826.51 783.80

=============== 606-01395 Transition Ty 3L Each ===================================================

STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 1.00 400.00 427.40 425.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 2.00 300.00 658.33 275.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3.00 333.33 533.98 325.00

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 12.00 500.00 657.95 600.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 4.00 350.00 758.94 725.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 4.00 500.00 677.01 663.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 20.00 470.00 682.17 637.60

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 4.00 600.00 600.64 584.55STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 4.00 450.00 767.66 940.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 8.00 525.00 693.43 762.28 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 31.00 470.97 671.68 639.52

Page 339: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 295 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 606-01410 End Anchorage (Cable) Each ===================================================

IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 2.00 1500.00 3000.00 3260.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 1500.00 3000.00 3260.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 1500.00 3000.00 3260.00

=============== 606-01460 Median Terminal Each ===================================================

IM 0701-157 FRUITA TO CLIFTON 02/26/04 2.00 3200.00 3851.67 3785.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 2.00 3500.00 3493.57 3360.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 4.00 3500.00 4000.00 4000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 8.00 3425.00 3754.46 3786.25

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 2.00 3000.00 3482.50 3400.00IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 2.00 3200.00 4065.00 3750.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4.00 3100.00 3676.67 3575.00

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 3800.00 4237.92 4197.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 3800.00 4237.92 4197.00

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 3500.00 3565.53 3486.55 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 3500.00 3565.53 3486.55 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 14.00 3364.29 3758.89 3733.83

=============== 606-02001 End Anchor (SRT) Each ===================================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 24.00 1600.00 1494.18 2165.00STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 36.00 1500.00 1265.00 1215.00

Page 340: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 296 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 606-02001 End Anchor (SRT) Each ===================================================STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 1.00 1300.00 1271.09 1125.73NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 10.00 1300.00 1333.27 1270.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 61.00 1500.00 1290.64 1170.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 132.00 1501.52 1313.11 1370.42

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 31.00 1200.00 1862.00 1550.00C R200-126 FY04 REGION 2 SIGNING 04/01/04 1.00 1800.00 1840.08 1965.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 11.00 1200.00 1931.76 1235.00IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 2.00 1500.00 1421.30 1482.62SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 4.00 1300.00 2116.25 1200.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 8.00 1300.00 1349.48 1200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 57.00 1242.11 1812.84 1420.44

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 44.00 1200.00 1223.29 1200.00SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 2.00 1700.00 1775.00 1650.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 46.00 1221.74 1231.52 1219.57 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 235.00 1383.83 1402.31 1353.03

=============== 606-02003 End Anchor (Nonflared) Each ===================================================

STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 1.00 1800.00 1789.51 1850.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 3.00 1800.00 1693.72 1700.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 9.00 1700.00 1614.60 1520.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 4.00 1500.00 1997.07 2047.42STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 15.00 1650.00 1540.38 1480.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 4.00 1800.00 1799.45 1750.00IM 0701-164 PARACHUTE EAST & WEST 02/12/04 2.00 1700.00 1885.00 2000.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 12.00 1700.00 1750.00 1450.00STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 6.00 1600.00 2767.50 2835.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 2.00 1800.00 1855.34 1643.35STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 4.00 1700.00 1710.00 1750.00STA 014A-030 SH 14, WALDEN EAST 03/04/04 4.00 1600.00 1926.50 2000.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 8.00 1300.00 1671.25 1600.00NH 2872-016 US 287 - LAMAR 03/04/04 3.00 1500.00 1622.50 1590.00SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 1.00 1600.00 2010.00 1750.00C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 4.00 1750.00 2000.00 2000.00

Page 341: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 297 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 606-02003 End Anchor (Nonflared) Each ===================================================NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 22.00 1700.00 1612.50 1475.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 2.00 1840.00 1600.00 1600.00STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 1.00 1600.00 1825.00 1800.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 107.00 1652.62 1720.79 1677.44

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 14.00 1600.00 1589.17 1550.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 9.00 1600.00 1632.50 1600.00STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 2.00 1500.00 2366.34 2090.90SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 2.00 1600.00 1723.48 1650.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 2.00 2500.00 1992.00 1800.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 1.00 1750.00 1839.01 1793.70STA 0343-023 US 34, EAST OF AKRON 06/17/04 4.00 1700.00 2508.00 1690.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 2.00 1800.00 1827.71 2289.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 36.00 1670.83 1798.23 1675.38

BR 0243-063 EAST OF LIMON 07/15/04 4.00 1700.00 1844.82 1700.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 2.00 2000.00 2154.71 2180.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1.00 1600.00 2003.40 2000.00STA 149A-021 SH 149 CRIBWALL 09/16/04 2.00 1200.00 2600.00 2600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 9.00 1644.44 2031.10 2040.00

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 2.00 1800.00 1747.89 1707.50C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 10.00 1700.00 1997.70 1804.00NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 35.00 1700.00 1766.67 1800.00STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 2.00 1900.00 1996.92 1911.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 49.00 1712.24 1845.88 1801.58 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 201.00 1670.05 1774.08 1723.57

=============== 606-02005 End Anchor (Flared) Each ===================================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 4.00 1300.00 1576.25 1500.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 1.00 1500.00 1538.29 1280.00

Page 342: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 298 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 606-02005 End Anchor (Flared) Each ===================================================STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 1.00 1500.00 1320.63 1300.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 3.00 1300.00 1628.14 1723.85IM 0701-164 PARACHUTE EAST & WEST 02/12/04 54.00 1400.00 1511.00 1500.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 6.00 1500.00 1433.33 1200.00STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 2.00 1250.00 2422.50 3045.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 1500.00 1450.50 1261.25STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 22.00 1500.00 1370.00 1400.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 57.00 1100.00 1365.00 1300.00SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 6.00 1350.00 1498.33 1285.00STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 9.00 1700.00 1827.50 1310.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 9.00 1100.00 1215.00 1230.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 2.00 2000.00 1966.67 1700.00STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 110.00 1500.00 1370.00 1100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 287.00 1389.20 1416.21 1286.32

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 5.00 1350.00 1295.83 1200.00NH 0502-053 CIMARRON - WEST 04/15/04 10.00 1600.00 1353.69 1400.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 14.00 1500.00 1346.25 1300.00IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 3.00 1100.00 1338.33 1250.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 6.00 1650.00 1516.75 1400.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 8.00 1300.00 1267.51 1200.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 7.00 1200.00 1378.56 1347.70CC R600-225 CHATFIELD STATE PARK 06/10/04 5.00 1400.00 1378.75 1475.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 58.00 1426.72 1348.53 1323.43

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 4.00 1800.00 1492.38 1392.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 3.00 1800.00 1662.17 1358.80C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 3.00 1100.00 1501.32 1500.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 6.00 1400.00 1550.00 1500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 16.00 1518.75 1539.96 1446.53

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 6.00 1350.00 1442.14 1450.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 5.00 1300.00 1320.56 1287.75IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 14.00 1275.00 1575.00 1325.00NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 1.00 1500.00 1700.00 1700.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 1.00 1500.00 2016.67 1350.00

Page 343: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 299 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 606-02005 End Anchor (Flared) Each ===================================================NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 22.00 1400.00 1743.33 1600.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 4.00 1500.00 1665.00 1800.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 3.00 1300.00 2860.91 2428.65 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 56.00 1359.82 1671.71 1543.30 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 417.00 1395.44 1449.02 1332.14

=============== 606-10200 Brdg Rail (Spec) Lin Foot ===============================================

SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 135.00 200.00 273.75 220.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 135.00 200.00 273.75 220.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 135.00 200.00 273.75 220.00

=============== 606-10300 Brdg Rail Ty 3 Lin Foot ===============================================

STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 27.00 20.00 95.87 72.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 27.00 20.00 95.87 72.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 27.00 20.00 95.87 72.00

=============== 606-10360 Brdg Rail Ty 3R (Spec) Lin Foot ===============================================

NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 280.00 100.00 42.34 36.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 280.00 100.00 42.34 36.70 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 280.00 100.00 42.34 36.70

=============== 606-10405 Brdg Rail Ty 4 (Spec) Lin Foot ===============================================

STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 40.00 250.00 154.25 136.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 40.00 250.00 154.25 136.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 40.00 250.00 154.25 136.00

=============== 606-10700 Brdg Rail Ty 7 Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 636.00 50.00 70.47 53.00

Page 344: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 300 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 606-10700 Brdg Rail Ty 7 Lin Foot ===============================================STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 221.00 80.00 63.94 41.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 857.00 57.74 68.95 49.91

BR 0243-063 EAST OF LIMON 07/15/04 315.00 90.00 116.23 110.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 315.00 90.00 116.23 110.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 630.00 55.00 66.84 60.00NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 82.00 120.00 163.33 195.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 68.00 80.00 102.48 101.90 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 780.00 64.01 74.61 77.85 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,952.00 65.45 74.76 70.77

=============== 606-10705 Brdg Rail Ty 7 (Spec) Lin Foot ===============================================

STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 200.00 100.00 159.45 158.63 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 200.00 100.00 159.45 158.63

BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 915.00 110.00 178.69 98.61IMD 0252-364 I-25 OVER BROADWAY 07/29/04 3,412.00 50.00 82.43 91.50STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 937.00 80.00 89.99 95.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 5,264.00 65.77 96.65 93.36 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5,464.00 67.02 101.08 95.75

=============== 606-10805 Brdg Rail Ty 8 (Special) Lin Foot ===============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 7,795.00 120.00 28.49 22.97 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 7,795.00 120.00 28.49 22.97 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 7,795.00 120.00 28.49 22.97

Page 345: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 301 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 606-11010 Brdg Rail Ty 10R Lin Foot ===============================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 534.00 60.00 70.93 75.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 98.00 70.00 88.15 91.00STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 229.00 100.00 124.80 119.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 187.00 55.00 95.33 76.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 326.00 60.00 78.95 77.00NH 2872-016 US 287 - LAMAR 03/04/04 25.00 100.00 147.50 135.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 3,808.00 48.00 56.73 56.00SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 150.00 60.00 120.67 110.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 500.00 80.00 77.50 65.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5,857.00 55.65 64.87 65.08

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 278.00 75.00 76.98 70.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 274.00 110.00 142.16 170.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 609.00 75.00 84.89 82.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,161.00 83.26 94.25 99.89

IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 610.00 100.00 100.00 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 610.00 100.00 100.00 60.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 7,628.00 63.40 70.85 69.97

=============== 606-11015 Brdg Rail Ty 10R (Spec) Lin Foot ===============================================

STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 1,270.00 75.00 66.12 62.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,270.00 75.00 66.12 62.00

STA 0343-023 US 34, EAST OF AKRON 06/17/04 49.00 60.00 243.00 230.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 49.00 60.00 243.00 230.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,319.00 74.44 70.28 68.24

Page 346: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 302 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 606-11030 Brdg Rail Ty 10M Lin Foot ===============================================

NH 2872-016 US 287 - LAMAR 03/04/04 70.00 75.00 196.25 225.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 382.00 70.00 74.50 75.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 452.00 70.77 107.15 98.23

BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 500.00 75.00 102.36 109.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 500.00 75.00 102.36 109.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 724.00 80.00 89.63 98.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 724.00 80.00 89.63 98.00

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 2,181.00 90.00 99.23 90.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2,181.00 90.00 99.23 90.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3,857.00 83.93 97.95 94.93

=============== 606-11032 Brdg Rail Ty 10M (Spec) Lin Foot ===============================================

STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 202.00 81.60 151.15 155.77 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 202.00 81.60 151.15 155.77

NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 90.00 150.00 82.49 73.90 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 90.00 150.00 82.49 73.90 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 292.00 102.68 133.11 130.54

=============== 606-20000 Wire Rope Safety Fence Lin Foot ===============================================

IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 191,151.00 11.00 13.73 13.31 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 191,151.00 11.00 13.73 13.31

Page 347: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 303 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 606-20000 Wire Rope Safety Fence Lin Foot ===============================================

SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 23,837.00 15.00 15.50 15.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 23,837.00 15.00 15.50 15.50

IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 6,069.00 25.00 17.00 15.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 6,069.00 25.00 17.00 15.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 221,057.00 11.82 14.01 13.59

=============== 606-21000 Wire Rope End Anchorage Each ===================================================

IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 110.00 1180.00 2145.00 1950.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 110.00 1180.00 2145.00 1950.00

SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 8.00 2500.00 2200.00 2000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 8.00 2500.00 2200.00 2000.00

C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 1.00 2000.00 7809.92 8005.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 4.00 2500.00 2315.00 2105.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 5.00 2400.00 3931.15 3285.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 123.00 1315.45 2230.40 2007.52

=============== 607-00000 Line Post Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 14.00 40.00 609.35 607.20STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 150.00 36.00 49.00 50.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 164.00 36.34 171.58 97.57 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 164.00 36.34 171.58 97.57

Page 348: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 304 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 607-00005 End Post Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 12.00 100.00 361.18 356.71STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 41.00 100.00 87.00 90.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 4.00 120.00 90.53 86.05STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 2.00 110.00 128.50 123.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 19.00 122.00 115.00 120.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 78.00 106.64 146.55 138.98

NH 0502-053 CIMARRON - WEST 04/15/04 5.00 100.00 179.28 120.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 44.00 85.00 108.75 110.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 14.00 100.00 183.55 222.20STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 2.00 110.00 123.33 90.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 16.00 100.00 116.62 120.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 1.00 100.00 182.14 184.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 82.00 92.20 130.09 132.13

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 24.00 90.00 78.17 90.00STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 43.00 100.00 113.25 108.00IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 91.00 100.00 91.49 90.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 8.00 120.00 118.12 100.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 2.00 200.00 145.94 142.47C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 7.00 110.00 125.60 120.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 89.00 150.00 177.50 165.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 6.00 150.00 116.95 95.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 270.00 118.30 117.79 119.16

SHE 105A-010 SH 105/FURROW RD 10/07/04 2.00 150.00 221.39 200.00BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 1.00 100.00 177.75 99.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3.00 133.33 201.99 166.33 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 433.00 111.36 125.69 125.52

=============== 607-00010 Corner and Line Br Post Each ===================================================

STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 78.00 100.00 96.40 90.00

Page 349: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 305 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 607-00010 Corner and Line Br Post Each ===================================================IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 24.00 170.00 134.79 129.05STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 10.00 140.00 174.49 165.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 86.00 91.00 175.00 180.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 198.00 106.60 128.38 137.61

NH 0502-053 CIMARRON - WEST 04/15/04 51.00 120.00 276.59 165.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 29.00 95.00 121.25 115.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 16.00 150.00 194.44 237.10STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 8.00 150.00 135.00 100.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 16.00 150.00 164.23 170.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 1.00 150.00 215.71 212.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 121.00 124.17 202.20 159.30

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 80.00 125.00 107.97 125.00STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 49.00 150.00 139.13 140.00IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 272.00 90.00 102.82 100.00SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 7.00 200.00 240.00 205.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 60.00 160.00 124.77 125.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 200.00 213.71 220.42C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 2.00 140.00 178.37 180.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 84.00 150.00 204.75 195.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 12.00 150.00 131.65 120.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 567.00 119.42 120.54 125.92

SHE 105A-010 SH 105/FURROW RD 10/07/04 10.00 180.00 288.15 238.00BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 2.00 175.00 207.75 140.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 12.00 179.17 268.66 221.67 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 898.00 118.03 134.02 134.27

=============== 607-00020 Corner and Line Br Post (Spec) Each ===================================================

SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 3.00 400.00 182.33 175.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3.00 400.00 182.33 175.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 400.00 182.33 175.00

Page 350: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 306 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 607-01000 Fence BW MP Lin Foot ===============================================

STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 57,974.00 1.00 0.91 0.80IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 11,592.00 1.30 0.84 0.80STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1,871.00 1.00 1.74 1.35STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 23,350.00 1.00 1.10 1.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 94,787.00 1.04 0.94 0.88

NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 18,100.00 1.00 1.15 1.15IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 3,667.00 1.20 1.85 1.99SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 235.00 1.20 2.61 2.50NH 2852-010 US 285 & COUNTY RD. G 04/29/04 4,545.00 1.15 1.75 1.40STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 1,620.00 1.50 2.10 1.90BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 349.00 2.00 3.24 3.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 28,516.00 1.09 1.48 1.38

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 17,879.00 1.40 1.07 1.10IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 174,124.00 0.85 0.81 0.74SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 1,400.00 2.00 1.95 1.90NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 45,721.00 1.20 0.99 1.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 1,760.00 2.00 1.64 1.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 240,884.00 0.97 0.85 0.82

SHE 105A-010 SH 105/FURROW RD 10/07/04 3,230.00 2.00 1.55 1.10BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 1,684.00 1.50 2.11 1.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4,914.00 1.83 1.81 1.07 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 369,101.00 1.01 0.93 0.89

=============== 607-01050 Fence Wire MP Lin Foot ===============================================

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 902.00 1.25 2.15 1.99 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 902.00 1.25 2.15 1.99 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 902.00 1.25 2.15 1.99

Page 351: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 307 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 607-01100 Fence BW TWP Lin Foot ===============================================

BR 0092-018 SH 9, SOUTH OF KREMMLING 05/27/04 300.00 4.00 7.63 11.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 300.00 4.00 7.63 11.00

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 6,147.00 2.50 2.19 2.00STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 8,391.00 2.50 1.91 1.80C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 812.00 2.50 2.02 1.80 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 15,350.00 2.50 2.06 1.88 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 15,650.00 2.53 2.14 2.05

=============== 607-01110 Fence BW TWP (Spec) Lin Foot ===============================================

NH 0502-053 CIMARRON - WEST 04/15/04 8,016.00 3.25 3.33 3.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 8,016.00 3.25 3.33 3.70 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8,016.00 3.25 3.33 3.70

=============== 607-11200 Fence CW MP Lin Foot ===============================================

STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 1,162.00 2.60 1.51 1.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,162.00 2.60 1.51 1.25

NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 5,938.00 1.25 2.08 1.75NH 2852-010 US 285 & COUNTY RD. G 04/29/04 1,568.00 2.50 2.67 2.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 7,506.00 1.51 2.22 1.82

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 5,012.00 2.50 1.73 1.60C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 930.00 2.50 2.52 2.50

Page 352: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 308 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 607-11200 Fence CW MP Lin Foot ===============================================NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 28,909.00 1.50 1.81 1.70IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 1,735.00 2.00 3.27 2.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 36,586.00 1.69 1.89 1.74 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 45,254.00 1.68 1.94 1.74

=============== 607-11300 Fence CW TWP Lin Foot ===============================================

NH 0502-053 CIMARRON - WEST 04/15/04 6,104.00 3.00 2.25 3.00BR 0092-018 SH 9, SOUTH OF KREMMLING 05/27/04 350.00 16.00 8.25 11.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 7,834.00 3.00 2.69 2.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 14,288.00 3.32 2.65 2.76

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 19,509.00 3.00 2.36 2.20STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 335.00 10.00 4.44 3.80 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 19,844.00 3.12 2.39 2.23 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 34,132.00 3.20 2.48 2.45

=============== 607-11350 Fence Deer Lin Foot ===============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 2,090.00 12.00 12.11 8.36 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,090.00 12.00 12.11 8.36 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,090.00 12.00 12.11 8.36

=============== 607-11525 Fence (Plastic) Lin Foot ===============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 2,750.00 2.00 3.61 3.40STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 500.00 3.00 2.78 1.50IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1,000.00 2.00 2.38 2.15STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 1,000.00 3.00 2.93 1.71NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 200.00 3.00 3.30 3.20SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 1,000.00 2.00 2.03 2.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 400.00 3.00 6.15 12.50

Page 353: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 309 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 607-11525 Fence (Plastic) Lin Foot ===============================================STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 500.00 3.00 3.57 2.25STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 3,000.00 1.50 2.75 2.80 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 10,350.00 2.11 3.17 3.01

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 100.00 3.00 3.17 1.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 6,542.00 2.00 2.77 3.75IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 3,655.00 3.50 2.21 2.10STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 1,000.00 3.00 2.92 1.50STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 500.00 2.50 1.43 1.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 5,000.00 2.30 2.55 5.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 500.00 3.50 3.24 2.80NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 300.00 3.00 5.46 3.40STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 171.00 2.00 2.62 1.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 17,768.00 2.53 2.59 3.48

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 13,298.00 2.50 2.25 2.90SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 200.00 4.00 2.90 4.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1,000.00 2.25 4.05 3.89SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 110.00 4.00 3.50 3.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1,160.00 3.00 3.14 2.94C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 470.00 2.20 2.50 2.50NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1,320.00 2.00 2.24 2.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 17,558.00 2.50 2.39 2.90

C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 600.00 2.00 2.35 2.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 1,700.00 3.00 3.42 2.10IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 2,000.00 3.00 2.34 2.65BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1,805.00 3.00 2.92 2.20C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 200.00 4.00 3.67 3.25STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 400.00 2.00 3.33 3.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 300.00 4.00 4.77 7.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 80.00 10.00 8.88 8.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 7,085.00 3.01 2.96 2.63 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 52,761.00 2.50 2.67 3.08

Page 354: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 310 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 607-11575 Rock Fall Fence Lin Foot ===============================================

STA 0703-290 GEORGETOWN HILL ROCKFALL MITI 10/07/04 200.00 400.00 462.50 350.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 200.00 400.00 462.50 350.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 200.00 400.00 462.50 350.00

=============== 607-11576 Temp Rockfall Containment Sys LUMP SUM ===============================================

STA 1191-020 SH 119 ROCKFALL MITIGATION, 2 04/15/04 1.00 8000.00 14600.00 7000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 8000.00 14600.00 7000.00

STA 0703-290 GEORGETOWN HILL ROCKFALL MITI 10/07/04 1.00 15000.00 28892.00 10000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 15000.00 28892.00 10000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 11500.00 20316.80 8500.00

=============== 607-11580 Fence (Temp) Lin Foot ===============================================

STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 500.00 2.50 2.85 2.65STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 100.00 8.00 6.61 6.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 600.00 3.42 3.41 3.21

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 450.00 3.00 3.68 5.98NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 400.00 4.00 3.80 3.68NH 2852-010 US 285 & COUNTY RD. G 04/29/04 1,423.00 2.50 3.29 2.80CC R600-225 CHATFIELD STATE PARK 06/10/04 600.00 3.00 2.83 2.30STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 400.00 1.30 3.17 1.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3,273.00 2.70 3.39 3.09

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 3,016.00 3.00 4.08 4.00

Page 355: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 311 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 607-11580 Fence (Temp) Lin Foot ===============================================IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 200.00 3.00 2.56 1.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 3,216.00 3.00 3.99 3.84

MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 500.00 4.00 3.22 2.15 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 500.00 4.00 3.22 2.15 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 7,589.00 2.97 3.59 3.36

=============== 607-11672 Fence Wood (Sound) (72 In) Lin Foot ===============================================

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 440.00 40.00 74.82 62.59 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 440.00 40.00 74.82 62.59 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 440.00 40.00 74.82 62.59

=============== 607-11720 Fence Wood (Sound) (120 In) Lin Foot ===============================================

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 450.00 73.00 99.50 92.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 450.00 73.00 99.50 92.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 450.00 73.00 99.50 92.00

=============== 607-52900 Line Post (CL) Each ===================================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 65.00 55.00 50.82 46.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 65.00 55.00 50.82 46.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 65.00 55.00 50.82 46.00

=============== 607-52905 End Post (CL) Each ===================================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 4.00 83.00 202.50 205.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 83.00 202.50 205.00

Page 356: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 312 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 607-52905 End Post (CL) Each ===================================================

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 12.00 100.00 177.90 170.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 12.00 100.00 177.90 170.00

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 2.00 120.00 168.25 155.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 120.00 168.25 155.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 8.00 100.00 183.79 185.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 8.00 100.00 183.79 185.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 26.00 98.92 180.86 178.85

=============== 607-52910 Corner and Line Br Post (CL) Each ===================================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 23.00 120.00 295.00 300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 23.00 120.00 295.00 300.00

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 4.00 175.00 182.89 180.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4.00 175.00 182.89 180.00

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 170.00 195.00 180.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 170.00 195.00 180.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 6.00 120.00 187.21 175.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 6.00 120.00 187.21 175.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 34.00 127.94 231.63 260.29

Page 357: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 313 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 607-53001 Fence CL (PVC) Lin Foot ===============================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1,813.00 16.00 12.13 12.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,813.00 16.00 12.13 12.25 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,813.00 16.00 12.13 12.25

=============== 607-53137 Fence CL (Spec) (36 In) Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 576.00 20.00 17.49 18.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 576.00 20.00 17.49 18.00

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1,280.00 20.00 17.87 17.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,280.00 20.00 17.87 17.40 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,856.00 20.00 17.69 17.59

=============== 607-53142 Fence CL (42 In) Lin Foot ===============================================

NH 2872-016 US 287 - LAMAR 03/04/04 100.00 25.00 58.75 40.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 100.00 25.00 58.75 40.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 100.00 25.00 58.75 40.00

=============== 607-53148 Fence CL (48 In) Lin Foot ===============================================

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 100.00 8.00 19.08 16.80 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 100.00 8.00 19.08 16.80 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 100.00 8.00 19.08 16.80

=============== 607-53155 Fence CL (Spec)(54 In) Lin Foot ===============================================

SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 122.00 7.00 79.59 96.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 122.00 7.00 79.59 96.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 122.00 7.00 79.59 96.00

Page 358: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 314 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 607-53161 Fence CL (Spec) (60 In) Lin Foot ===============================================

STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 205.00 30.00 34.67 25.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 330.00 15.00 26.75 27.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 535.00 20.75 32.18 26.54

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 5,349.00 20.00 18.69 16.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 5,349.00 20.00 18.69 16.00

BR 0243-063 EAST OF LIMON 07/15/04 235.00 25.00 29.35 30.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 235.00 25.00 29.35 30.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6,119.00 20.26 19.71 17.46

=============== 607-53172 Fence CL (72 In) Lin Foot ===============================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 500.00 10.00 18.71 18.07 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 500.00 10.00 18.71 18.07

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 3,447.00 9.00 7.38 6.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3,447.00 9.00 7.38 6.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3,947.00 9.13 8.38 7.53

=============== 607-53173 Fence CL (Spec) (72 In) Lin Foot ===============================================

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 2,252.00 18.00 16.18 14.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2,252.00 18.00 16.18 14.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,252.00 18.00 16.18 14.00

Page 359: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 315 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 607-53178 Fence CL (Spec) (78 In) Lin Foot ===============================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 390.00 32.00 31.42 31.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 390.00 32.00 31.42 31.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 390.00 32.00 31.42 31.00

=============== 607-53191 Fence CL (Spec) (92 In) Lin Foot ===============================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 435.00 35.00 32.86 33.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 435.00 35.00 32.86 33.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 435.00 35.00 32.86 33.00

=============== 607-53196 Fence CL (96 In) Lin Foot ===============================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 2,721.00 11.50 15.25 15.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,721.00 11.50 15.25 15.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,721.00 11.50 15.25 15.50

=============== 607-53203 Fence CL (Spec)(102 In) Lin Foot ===============================================

SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 76.00 80.00 87.50 75.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 76.00 80.00 87.50 75.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 76.00 80.00 87.50 75.00

=============== 607-55030 Mesh Post Each ===================================================

STA 1191-020 SH 119 ROCKFALL MITIGATION, 2 04/15/04 16.00 650.00 1171.33 1300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 16.00 650.00 1171.33 1300.00

STA 0703-290 GEORGETOWN HILL ROCKFALL MITI 10/07/04 12.00 3000.00 4200.00 3000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 12.00 3000.00 4200.00 3000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 28.00 1657.14 2180.89 2028.57

Page 360: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 316 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 607-55100 Wire Mesh Sq Foot ================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 14,400.00 1.50 2.77 4.46 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 14,400.00 1.50 2.77 4.46

STA 1191-020 SH 119 ROCKFALL MITIGATION, 2 04/15/04 35,000.00 1.15 1.37 1.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 35,000.00 1.15 1.37 1.10

BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 14,400.00 3.00 1.97 2.01STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 4,700.00 3.00 6.62 7.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 19,100.00 3.00 3.61 3.24

STA 0703-290 GEORGETOWN HILL ROCKFALL MITI 10/07/04 8,300.00 4.00 3.65 2.80 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 8,300.00 4.00 3.65 2.80 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 76,800.00 1.98 2.49 2.45

=============== 607-55101 Cable Net Sq Foot ================================================

STA 1191-020 SH 119 ROCKFALL MITIGATION, 2 04/15/04 2,100.00 5.00 10.17 6.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2,100.00 5.00 10.17 6.50

STA 0703-290 GEORGETOWN HILL ROCKFALL MITI 10/07/04 8,300.00 20.00 19.25 19.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 8,300.00 20.00 19.25 19.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10,400.00 16.97 16.75 16.48

=============== 607-60116 16 Ft Gate Each ===================================================

NH 2852-010 US 285 & COUNTY RD. G 04/29/04 1.00 275.00 295.34 296.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 275.00 295.34 296.30

Page 361: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 317 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 607-60116 16 Ft Gate Each ===================================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 7.00 350.00 349.67 250.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 7.00 350.00 349.67 250.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8.00 340.63 341.44 255.79

=============== 607-60117 16 Ft Gate (Spec) Each ===================================================

NH 2852-010 US 285 & COUNTY RD. G 04/29/04 3.00 300.00 337.26 296.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3.00 300.00 337.26 296.30

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 2.00 250.00 360.79 400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 250.00 360.79 400.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5.00 280.00 348.62 337.78

=============== 607-60120 20 Ft Gate Each ===================================================

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 5.00 320.00 298.63 162.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 5.00 320.00 298.63 162.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5.00 320.00 298.63 162.00

=============== 607-60220 20 Ft Gate S (CL) Each ===================================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 4.00 900.00 837.65 700.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4.00 900.00 837.65 700.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 900.00 837.65 700.00

=============== 607-60324 24 Ft Gate Twin Each ===================================================

STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 1.00 350.00 665.00 500.00

Page 362: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 318 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 607-60324 24 Ft Gate Twin Each ===================================================CC R600-225 CHATFIELD STATE PARK 06/10/04 1.00 500.00 2625.00 1500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 425.00 1785.00 1000.00

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 1.00 400.00 576.50 645.00IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1.00 600.00 454.38 530.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 500.00 503.23 587.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 462.50 1031.02 793.75

=============== 607-60620 Road Closure Gate Each ===================================================

STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 2.00 8000.00 7099.60 8100.00NH 2872-016 US 287 - LAMAR 03/04/04 1.00 7500.00 22750.00 20000.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1.00 2850.00 9300.00 9900.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 6587.50 11287.25 11525.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 6587.50 11287.25 11525.00

=============== 608-00000 Conc Sidewalk Sq Yard ================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 67.00 35.00 33.50 47.00STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 1,179.00 24.00 23.21 23.50STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 152.00 35.00 37.33 32.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 1,120.00 30.00 27.63 20.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 891.00 24.00 26.59 30.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 20.00 40.00 82.10 55.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 8.00 70.00 45.00 40.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 37.00 35.00 63.50 65.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 93.00 32.00 53.61 56.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 12.00 40.00 54.18 28.35 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3,579.00 27.12 27.77 26.33

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 5,540.00 22.00 25.84 27.82SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 967.00 26.00 31.41 20.90

Page 363: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 319 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 608-00000 Conc Sidewalk Sq Yard ================================================STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 60.00 60.00 30.98 30.45NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 161.00 35.00 34.74 28.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 528.00 25.00 31.96 34.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 117.00 24.50 36.21 36.80SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 906.00 27.00 26.91 26.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 8,279.00 23.77 26.63 27.36

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 2,502.00 30.00 24.21 18.24IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 3,895.00 25.00 25.50 26.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 6,397.00 26.96 24.92 22.96

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1,505.00 25.00 23.10 17.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 165.00 32.00 99.67 30.00STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 476.00 25.00 39.39 31.15STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 1,204.00 25.00 33.30 27.09NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 109.00 25.00 41.18 30.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3,459.00 25.33 32.58 23.49 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 21,714.00 25.51 27.23 25.28

=============== 608-00003 Conc Sidewalk (Fast Track) Sq Yard ================================================

STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 229.00 50.00 40.39 32.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 229.00 50.00 40.39 32.75

STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 11.00 60.00 53.81 34.95 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 11.00 60.00 53.81 34.95 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 240.00 50.46 40.78 32.85

=============== 608-00005 Conc Sidewalk (Spec) Sq Yard ================================================

STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 477.00 36.00 31.25 32.00

Page 364: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 320 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 608-00005 Conc Sidewalk (Spec) Sq Yard ================================================NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 1,627.55 65.00 82.23 70.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2,104.55 58.43 63.39 61.39

STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 18.00 70.00 96.33 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 18.00 70.00 96.33 60.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,122.55 58.53 63.73 61.38

=============== 608-00006 Conc Sidewalk (6 In) Sq Yard ================================================

STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 540.00 32.00 36.48 38.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 810.00 32.00 37.37 37.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 234.00 30.00 28.83 29.07 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,584.00 31.70 35.96 36.17

STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 2,110.00 25.00 43.86 36.08 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2,110.00 25.00 43.86 36.08

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1,696.00 30.00 24.62 24.00STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 72.00 40.00 36.32 45.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 80.00 38.00 49.73 32.44 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,848.00 30.74 25.92 25.18 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5,542.00 28.83 36.15 32.47

=============== 608-00010 Conc Curb Ramp Sq Yard ================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 10.00 100.00 94.45 95.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 490.00 60.00 61.27 66.50STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 770.00 55.00 63.47 61.20

Page 365: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 321 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 608-00010 Conc Curb Ramp Sq Yard ================================================STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 105.10 55.00 81.08 48.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 250.00 100.00 72.21 80.50STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 608.00 55.00 70.40 56.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 648.00 60.00 79.42 70.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 119.00 50.00 117.23 54.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 20.00 70.00 163.68 160.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 22.00 135.00 132.50 90.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 276.00 65.00 86.56 115.54STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 146.00 70.00 86.25 70.00NH 2872-016 US 287 - LAMAR 03/04/04 394.00 50.00 105.50 117.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 75.00 75.00 111.71 123.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 80.00 60.00 92.82 107.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 71.00 50.00 125.00 160.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4,084.10 60.72 77.34 76.93

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 179.00 70.00 81.14 60.90SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 112.00 50.00 109.11 121.25STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 148.00 85.00 162.50 160.00STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 154.00 50.00 98.73 102.16STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 144.00 65.00 69.10 75.40NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 758.00 68.00 83.84 75.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 60.00 50.00 96.34 61.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 57.00 60.00 66.45 63.20SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 99.00 70.00 42.59 25.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,711.00 65.85 86.84 82.61

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 263.50 75.00 90.68 90.95C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 8.00 100.00 115.67 95.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 431.00 70.00 52.25 47.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 120.00 70.00 68.46 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 822.50 71.89 69.36 63.44

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 175.00 130.00 72.35 100.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 57.00 80.00 69.07 70.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 168.00 100.00 133.33 70.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 12.00 100.00 124.16 58.95

Page 366: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 322 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 608-00010 Conc Curb Ramp Sq Yard ================================================STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 476.00 65.00 62.15 75.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 77.00 65.00 99.07 72.34STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 304.00 60.00 99.50 72.00STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 36.00 100.00 139.12 109.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 300.00 80.00 114.67 120.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 1,070.00 70.00 78.34 69.84NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 597.00 75.00 93.00 65.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3,272.00 75.42 85.19 76.58 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 9,889.60 67.40 80.37 76.68

=============== 608-00011 Curb Ramp (Fast Track) Sq Yard ================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 45.00 60.00 79.66 93.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 214.00 75.00 64.69 56.29 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 259.00 72.39 67.81 62.67

STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 283.00 60.00 88.05 59.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 283.00 60.00 88.05 59.10 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 542.00 65.92 75.81 60.81

=============== 608-00015 Truncated Domes Sq Foot ================================================

STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 281.00 25.00 14.87 9.21NH 2872-016 US 287 - LAMAR 03/04/04 776.00 20.00 12.25 12.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,057.00 21.33 13.35 11.63

NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 148.00 23.00 18.63 9.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 148.00 23.00 18.63 9.50

NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 128.00 20.00 60.67 55.00

Page 367: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 323 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 608-00015 Truncated Domes Sq Foot ================================================STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 114.00 25.00 34.64 32.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 242.00 22.36 45.12 44.28 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,447.00 21.67 18.20 16.87

=============== 608-00051 Inst Brick Pavers Sq Foot ================================================

NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 834.00 1.25 12.50 15.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 834.00 1.25 12.50 15.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 834.00 1.25 12.50 15.00

=============== 608-01000 Bitum Sidewalk Ton ====================================================

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 28.00 100.00 139.59 139.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 28.00 100.00 139.59 139.60 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 28.00 100.00 139.59 139.60

=============== 608-01600 Aggregate Walkway Sq Yard ================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 1,339.00 10.00 14.95 6.69 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,339.00 10.00 14.95 6.69 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,339.00 10.00 14.95 6.69

=============== 608-10000 Sidewalk Drain Lin Foot ===============================================

STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 10.00 120.00 143.32 130.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 1.00 150.00 612.96 279.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 11.00 122.73 174.63 143.55 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 11.00 122.73 174.63 143.55

=============== 609-21010 C and G Ty 2 I-B Lin Foot ===============================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 14,065.00 8.00 9.19 6.00

Page 368: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 324 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 609-21010 C and G Ty 2 I-B Lin Foot ===============================================C 0342-040 US 34 IN WELD COUNTY 01/29/04 600.00 15.00 31.56 23.38STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 216.00 12.00 14.51 11.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 3,334.00 11.00 7.34 9.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 50.00 20.00 22.92 29.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 2,740.00 10.00 9.25 9.80 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 21,005.00 9.01 9.56 7.57

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 246.00 13.00 15.95 15.75SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 497.00 12.00 15.37 17.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 344.00 13.00 10.63 14.70NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 370.00 11.00 14.15 11.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 154.00 12.00 17.82 22.10SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 155.00 10.00 12.63 11.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,766.00 11.95 14.42 15.04

BR 0243-063 EAST OF LIMON 07/15/04 1,086.00 12.00 16.05 10.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 6,404.00 15.00 8.91 6.53C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 412.00 9.00 15.31 18.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 4,843.00 12.00 14.55 16.20IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 8,885.00 10.00 12.70 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 21,630.00 12.01 11.95 10.51

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 3,845.00 9.00 7.35 9.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 617.00 12.00 9.93 12.00STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 240.00 12.00 17.74 13.60NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 18,020.00 6.60 15.00 7.30NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 18.00 20.00 22.40 22.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 22,740.00 7.22 13.62 7.79 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 67,141.00 9.45 11.45 8.79

=============== 609-21011 C and G Ty 2 I-M Lin Foot ===============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 132.00 12.00 23.14 21.03

Page 369: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 325 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 609-21011 C and G Ty 2 I-M Lin Foot ===============================================STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 10.00 22.00 94.00 88.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 6,263.00 7.00 6.19 6.50STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 4,269.00 10.70 5.75 6.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 10,674.00 8.56 6.43 6.56

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 21,209.00 9.00 9.28 7.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 21,209.00 9.00 9.28 7.00

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 168.00 12.00 19.42 15.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 168.00 12.00 19.42 15.00

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 4,449.00 10.00 8.20 9.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4,449.00 10.00 8.20 9.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 36,500.00 9.01 8.51 7.15

=============== 609-21020 C and G Ty 2 II-B Lin Foot ===============================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 1,167.00 13.00 16.23 8.70STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 617.00 15.00 13.88 10.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 1,640.00 15.00 16.15 16.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 2,420.00 13.00 16.99 17.60STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 668.00 15.00 15.41 10.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 1,098.00 15.00 17.29 14.95C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 166.00 15.00 18.30 11.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 634.00 14.00 16.96 11.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 1,206.00 15.00 20.44 16.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 3,816.00 12.00 9.65 11.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 20.00 25.00 41.51 38.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 155.00 17.50 20.58 15.00NH 2872-016 US 287 - LAMAR 03/04/04 940.00 10.00 40.25 46.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 211.00 20.00 24.51 31.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 108.00 18.00 21.88 21.00

Page 370: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 326 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 609-21020 C and G Ty 2 II-B Lin Foot ===============================================STA 0063-016 CLIFTON TO PALISADE 03/25/04 50.00 17.50 29.00 24.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 14,916.00 13.53 15.66 15.73

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 5,088.00 12.00 10.47 9.25SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 1,444.00 13.00 14.17 14.90STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 242.00 30.00 15.50 15.25STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 10,878.00 10.00 10.35 12.50NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 2,979.00 16.00 12.96 10.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 634.00 11.00 16.14 13.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 2,147.00 12.00 9.39 8.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 23,412.00 11.80 10.83 11.25

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 81.00 32.00 24.82 10.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 7,549.00 16.00 10.74 8.61C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 193.00 13.00 18.05 22.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 7,823.00 16.09 11.09 8.95

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 3,111.00 9.00 8.97 10.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 2,364.00 14.00 10.10 14.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 2,443.00 14.00 16.33 16.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 490.00 18.00 19.38 12.85STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 1,023.00 15.00 15.83 15.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 250.00 17.00 23.00 15.32STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 1,300.00 12.00 16.74 15.75STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 210.00 20.00 24.42 19.60NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 522.00 18.00 37.67 33.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 2,984.00 13.00 15.22 10.34NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 1,470.00 15.00 19.62 12.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 16,167.00 13.22 14.74 13.56 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 62,318.00 13.12 13.29 12.63

=============== 609-21021 C and G Ty 2 II-M Lin Foot ===============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 140.00 14.00 23.52 22.76

Page 371: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 327 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 609-21021 C and G Ty 2 II-M Lin Foot ===============================================IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 860.00 24.00 11.16 10.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 10,390.00 10.00 6.25 3.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 260.00 14.00 41.25 45.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 3,364.00 16.50 7.75 8.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 15,014.00 12.36 7.47 5.43

STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 4,390.00 11.00 16.99 17.80 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4,390.00 11.00 16.99 17.80

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 150.00 14.00 23.00 17.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 150.00 14.00 23.00 17.00

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 3,855.00 11.00 10.03 11.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3,855.00 11.00 10.03 11.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 23,409.00 11.89 10.19 8.74

=============== 609-21023 C and G Ty 2 II-B (Spec) Lin Foot ===============================================

STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 1,907.00 26.00 25.42 20.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,907.00 26.00 25.42 20.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,907.00 26.00 25.42 20.50

=============== 609-21900 C and G Ty 2 Special Lin Foot ===============================================

STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 12,131.00 35.00 29.99 25.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 12,131.00 35.00 29.99 25.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 12,131.00 35.00 29.99 25.00

Page 372: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 328 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 609-22022 CGS Ty 2 II-B Lin Foot ===============================================

STA 0063-016 CLIFTON TO PALISADE 03/25/04 67.00 50.00 48.33 45.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 67.00 50.00 48.33 45.00

STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 4,264.00 30.00 31.73 31.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4,264.00 30.00 31.73 31.40 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4,331.00 30.31 31.92 31.61

=============== 609-23000 Gutter (Special) Lin Foot ===============================================

NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 70.00 20.00 31.33 12.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 70.00 20.00 31.33 12.60

NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 375.00 30.00 69.85 33.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 375.00 30.00 69.85 33.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 445.00 28.43 65.59 29.79

=============== 609-24002 Gutter Ty 2 (2 Ft) Lin Foot ===============================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 2,825.00 18.00 7.16 9.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 110.00 21.00 15.77 24.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2,935.00 18.11 7.38 9.56 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,935.00 18.11 7.38 9.56

=============== 609-24004 Gutter Ty 2 (4 Ft) Lin Foot ===============================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 119.00 32.00 21.60 12.00

Page 373: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 329 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 609-24004 Gutter Ty 2 (4 Ft) Lin Foot ===============================================STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 85.00 20.00 21.94 19.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 204.00 27.00 21.72 15.17

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 2,266.00 20.00 20.59 15.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2,266.00 20.00 20.59 15.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,470.00 20.58 20.72 15.01

=============== 609-24006 Gutter Ty 2 (6 Ft) Lin Foot ===============================================

STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 80.00 40.00 36.75 24.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 80.00 40.00 36.75 24.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 80.00 40.00 36.75 24.00

=============== 609-24008 Gutter Ty 2 (8 Ft) Lin Foot ===============================================

STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 90.00 45.00 38.03 42.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 90.00 45.00 38.03 42.00

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 55.00 42.00 43.01 33.59SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 171.00 38.00 40.25 38.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 226.00 38.97 41.41 36.93 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 316.00 40.69 40.35 38.37

=============== 609-31010 C and G Ty 2 I-B (Fast Track) Lin Foot ===============================================

STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 242.00 35.00 19.84 21.49 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 242.00 35.00 19.84 21.49

Page 374: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 330 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 609-31010 C and G Ty 2 I-B (Fast Track) Lin Foot ===============================================

STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 280.00 20.00 16.18 15.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 280.00 20.00 16.18 15.30 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 522.00 26.95 18.30 18.17

=============== 609-31020 C and G Ty 2 II-B (Fast Track) Lin Foot ===============================================

STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 12.00 40.00 23.20 24.56 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 12.00 40.00 23.20 24.56

STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 621.00 20.00 18.95 15.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 621.00 20.00 18.95 15.30 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 633.00 20.38 19.08 15.48

=============== 609-31025 C and G Ty 2 II-M (Fast Track) Lin Foot ===============================================

STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 508.00 25.00 23.17 24.56 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 508.00 25.00 23.17 24.56 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 508.00 25.00 23.17 24.56

=============== 609-34006 Gutter Ty 2 (6 Ft) (Fast Track) Lin Foot ===============================================

STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 112.00 50.00 40.40 33.45 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 112.00 50.00 40.40 33.45 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 112.00 50.00 40.40 33.45

=============== 609-40010 Curb Ty 4 B Lin Foot ===============================================

STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 188.00 15.00 10.33 10.15 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 188.00 15.00 10.33 10.15 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 188.00 15.00 10.33 10.15

Page 375: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 331 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 609-40011 Curb Ty 4 M Lin Foot ===============================================

STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 516.00 20.00 8.00 4.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 516.00 20.00 8.00 4.50

NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 220.00 8.00 18.58 23.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 220.00 8.00 18.58 23.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 736.00 16.41 10.83 10.03

=============== 609-40130 Curb Median Special Lin Foot ===============================================

STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 2,394.00 12.00 11.76 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,394.00 12.00 11.76 10.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,394.00 12.00 11.76 10.00

=============== 609-60011 Curb Ty 6 M Lin Foot ===============================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 3,456.00 6.00 5.40 5.35NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 1,560.00 7.00 6.93 5.58STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 792.00 6.00 5.30 4.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 88.00 6.00 4.70 3.75IM 0701-157 FRUITA TO CLIFTON 02/26/04 200.00 12.00 12.50 5.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 1,399.00 5.00 5.57 5.50STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 80.00 10.00 30.25 11.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 919.00 7.00 6.14 5.50STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 440.00 6.90 4.48 5.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 8,934.00 6.34 6.15 5.36

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 7,905.00 6.00 3.76 2.75NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 7,227.00 5.50 4.52 4.25STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 3,010.00 5.50 3.78 2.50IM 0253-186 I-25, 120TH TO SH 7 06/17/04 400.00 6.00 5.22 4.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 18,542.00 5.72 4.06 3.32

Page 376: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 332 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 609-60011 Curb Ty 6 M Lin Foot ===============================================

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 21,276.00 6.00 1.93 3.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 310.00 10.00 14.32 13.88BR 0243-063 EAST OF LIMON 07/15/04 190.00 8.00 9.64 9.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 21,776.00 6.07 2.05 3.21

C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 882.00 7.00 11.53 13.50STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 463.00 6.00 7.74 8.00STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 160.00 15.00 46.00 65.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 3,401.00 5.00 6.83 9.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4,906.00 5.78 9.56 11.54 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 54,158.00 5.97 3.83 4.36

=============== 609-70040 Curb (Composite Material) Lin Foot ===============================================

NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 6,978.00 7.00 8.43 7.80 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 6,978.00 7.00 8.43 7.80 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6,978.00 7.00 8.43 7.80

=============== 609-71000 Curb (Special) Lin Foot ===============================================

STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 120.00 20.00 58.00 36.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 120.00 20.00 58.00 36.00

NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 129.00 15.00 25.09 21.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 129.00 15.00 25.09 21.10

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 523.00 15.00 26.98 26.00

Page 377: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 333 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 609-71000 Curb (Special) Lin Foot ===============================================NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 2,035.00 10.00 7.36 7.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2,558.00 11.02 10.23 11.04 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,807.00 11.59 11.87 12.57

=============== 610-00010 Median Cover Matl (Dec) Sq Foot ================================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 27,352.00 5.00 5.93 4.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 27,352.00 5.00 5.93 4.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 27,352.00 5.00 5.93 4.50

=============== 610-00020 Median Cover (Pattern Conc) Sq Foot ================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 609.00 8.00 10.85 11.10STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 36,587.00 4.50 3.22 2.08NH 2872-016 US 287 - LAMAR 03/04/04 2,880.00 15.00 12.88 10.50STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 6,336.00 5.00 5.08 3.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 46,412.00 5.27 4.01 2.88

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 2,325.00 7.50 6.68 7.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2,325.00 7.50 6.68 7.10

BR 0243-063 EAST OF LIMON 07/15/04 10,847.00 5.00 5.99 6.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 2,813.00 6.00 5.86 7.76NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 10,231.00 8.00 6.66 7.35 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 23,891.00 6.40 6.29 6.79

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 15,523.00 5.00 5.12 4.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 15,523.00 5.00 5.12 4.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 88,151.00 5.59 4.70 4.34

Page 378: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 334 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 610-00024 Median Cover (4 In Pattern Conc) Sq Foot ================================================

NH 2872-016 US 287 - LAMAR 03/04/04 28,663.00 4.50 5.91 5.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 28,663.00 4.50 5.91 5.30

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 69,522.00 5.00 3.99 3.40SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 2,872.00 6.00 5.71 5.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 72,394.00 5.04 4.04 3.48

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 241.00 6.00 10.95 6.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1,417.00 5.00 7.67 5.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,658.00 5.15 7.97 5.36

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 26,250.00 4.50 4.25 4.50STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 11,272.00 5.00 5.60 7.00NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 576.00 6.00 7.99 5.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 38,098.00 4.67 4.66 5.25 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 140,813.00 4.83 4.52 4.35

=============== 610-00026 Median Cover (6 In Pattern Conc) Sq Foot ================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 25,751.00 4.50 4.99 5.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 25,751.00 4.50 4.99 5.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 25,751.00 4.50 4.99 5.00

=============== 610-00030 Median Cover Matl (Conc) Sq Foot ================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 74,685.00 4.00 2.99 2.80

Page 379: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 335 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 610-00030 Median Cover Matl (Conc) Sq Foot ================================================C 0342-040 US 34 IN WELD COUNTY 01/29/04 3,905.00 3.50 3.01 3.26STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 4,708.00 3.00 6.10 6.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 6,410.00 4.00 2.30 2.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 89,708.00 3.93 3.09 2.97

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 1,517.00 7.00 3.67 2.86STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 141.00 7.00 6.20 6.10NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 309.00 5.00 6.65 4.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,967.00 6.69 3.96 3.30

NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 3,490.00 4.00 5.03 4.15STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 336.00 4.00 7.92 3.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3,826.00 4.00 5.28 4.09 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 95,501.00 3.99 3.15 3.02

=============== 610-00040 Median Cover Matl (Bitum) Ton ====================================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 283.00 60.00 54.22 53.00STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 140.00 100.00 96.07 81.28 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 423.00 73.24 68.07 62.36 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 423.00 73.24 68.07 62.36

=============== 610-00055 Median Cover Matl (Stone) Sq Foot ================================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 9,000.00 3.00 3.84 2.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 9,000.00 3.00 3.84 2.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 9,000.00 3.00 3.84 2.00

=============== 610-00060 Median Cover Matl (Brick) Sq Foot ================================================

STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 1.00 10.00 78.62 30.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 10.00 78.62 30.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 10.00 78.62 30.00

Page 380: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 336 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 611-00024 24 Ft Cattle Gd Each ===================================================

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 1.00 8000.00 9414.29 10000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 8000.00 9414.29 10000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 8000.00 9414.29 10000.00

=============== 612-00001 Delin (Ty I) Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 100.00 18.00 16.00 15.00STA 2911-001 SH 291 SALIDA NORTH 01/08/04 123.00 20.00 18.43 16.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 150.00 17.00 16.13 16.70NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 48.00 17.00 21.17 29.01STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 364.00 16.00 12.40 10.00C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 8.00 18.00 16.63 13.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 9.00 17.00 15.23 15.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 25.00 17.00 23.00 20.00STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 109.00 18.00 18.30 17.60IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 124.00 17.00 14.84 16.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 200.00 20.00 15.70 16.50IM 0701-157 FRUITA TO CLIFTON 02/26/04 30.00 15.00 15.67 15.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 175.00 17.00 12.50 12.31STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 20.00 17.00 21.63 17.50NH 2872-016 US 287 - LAMAR 03/04/04 50.00 15.00 18.75 10.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 334.00 14.00 14.28 11.00SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 70.00 12.00 14.67 13.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 231.00 15.00 11.50 11.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 276.00 16.00 13.58 10.50STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 354.00 14.60 11.50 13.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,800.00 16.19 14.44 13.22

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 215.00 15.00 13.28 14.25NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 1,048.00 15.00 12.95 14.25STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 9.00 18.00 21.61 20.45NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 50.00 16.00 14.82 13.65SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 6.00 16.00 17.93 27.30NH 0502-053 CIMARRON - WEST 04/15/04 123.00 13.00 15.18 19.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 311.00 11.00 15.03 18.10STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 98.00 15.00 15.39 14.55STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 20.00 15.00 19.89 18.90SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 240.00 14.00 12.96 15.30

Page 381: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 337 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 612-00001 Delin (Ty I) Each ===================================================NH 2852-010 US 285 & COUNTY RD. G 04/29/04 66.00 16.00 18.93 16.80STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 258.00 18.00 16.33 16.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 50.00 20.00 18.75 20.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 18.00 18.00 11.39 9.50CC R600-225 CHATFIELD STATE PARK 06/10/04 12.00 16.00 17.00 25.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 159.00 15.00 17.67 17.50STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 6.00 15.00 20.67 26.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2,689.00 14.82 14.27 15.66

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 126.00 14.00 18.26 16.00STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 192.00 15.00 13.56 13.60IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1,409.00 12.00 11.68 10.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 18.00 22.00 25.07 16.10BR 0243-063 EAST OF LIMON 07/15/04 50.00 18.00 18.80 24.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 177.00 18.00 14.66 17.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 32.00 20.00 13.39 14.98C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 12.00 13.00 15.57 15.00STA 149A-021 SH 149 CRIBWALL 09/16/04 5.00 17.00 77.00 77.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 150.00 16.00 17.45 18.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 28.00 18.00 15.70 12.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2,199.00 13.56 12.98 12.41

SHE 105A-010 SH 105/FURROW RD 10/07/04 36.00 21.00 15.35 12.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 10.00 22.00 22.40 17.00BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 2.00 16.00 26.60 20.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 68.00 16.00 15.16 10.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 60.00 18.00 15.07 17.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 17.00 18.00 17.33 12.00STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 25.00 16.00 14.81 18.25NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 800.00 22.00 27.00 32.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 65.00 16.00 18.49 9.65STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 17.00 18.00 14.51 13.95NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 25.00 18.00 20.75 25.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,125.00 20.69 22.95 26.75 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8,813.00 15.69 14.78 15.49

=============== 612-00002 Delin (Ty II) Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 42.00 20.00 16.51 15.00

Page 382: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 338 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 612-00002 Delin (Ty II) Each ===================================================STA 2911-001 SH 291 SALIDA NORTH 01/08/04 17.00 22.00 21.10 18.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 77.00 18.00 16.06 13.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 150.00 18.00 17.93 18.80NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 8.00 19.00 22.67 29.01C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 5.00 20.00 17.58 14.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 28.00 18.00 16.85 16.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 8.00 18.00 24.00 22.00STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 28.00 21.00 20.40 19.80IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 110.00 18.00 16.13 17.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 10.00 20.00 17.00 19.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 33.00 17.00 17.83 18.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 215.00 20.00 14.06 13.33NH 2872-016 US 287 - LAMAR 03/04/04 61.00 17.00 20.25 11.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 345.00 15.00 15.73 12.75STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 6.00 20.00 23.88 40.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 490.00 15.00 13.00 12.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 84.00 17.00 15.00 11.50STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 240.00 15.00 12.50 14.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,957.00 16.63 15.58 13.94

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 90.00 18.00 14.63 16.25NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 191.00 16.00 14.55 15.50NH 0502-053 CIMARRON - WEST 04/15/04 12.00 18.00 16.46 21.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 46.00 16.00 17.05 16.65STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 10.00 16.00 21.30 21.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 20.00 16.00 14.21 16.30NH 2852-010 US 285 & COUNTY RD. G 04/29/04 58.00 18.00 20.71 17.60STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 39.00 18.00 17.50 17.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 50.00 20.00 20.50 22.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 15.00 20.00 12.69 10.50IM 0253-186 I-25, 120TH TO SH 7 06/17/04 20.00 18.00 18.74 18.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 551.00 17.27 16.29 16.86

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 16.00 18.00 14.58 14.60IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 345.00 17.00 12.69 11.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 66.00 19.00 16.45 19.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 54.00 21.00 14.71 17.12C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 60.00 15.00 17.10 17.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 100.00 18.00 18.88 19.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 38.00 19.00 17.51 13.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 679.00 17.62 14.41 14.17

Page 383: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 339 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 612-00002 Delin (Ty II) Each ===================================================

SHE 105A-010 SH 105/FURROW RD 10/07/04 5.00 23.00 22.50 14.00BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 2.00 18.00 26.89 9.80BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 25.00 20.00 16.35 18.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 32.00 18.00 19.00 13.00STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 25.00 18.00 16.09 19.36NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 100.00 23.00 28.33 33.00NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 3.00 19.50 26.63 28.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 192.00 21.02 22.96 25.12 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3,379.00 17.18 15.75 15.10

=============== 612-00003 Delin (Ty III) Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 1.00 21.00 19.71 20.00STA 2911-001 SH 291 SALIDA NORTH 01/08/04 2.00 24.00 23.50 19.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 2.00 20.00 18.58 14.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 40.00 20.00 19.70 19.80NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 4.00 20.00 24.04 31.24STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 64.00 17.00 15.40 12.00C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 2.00 22.00 19.17 16.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 22.00 19.00 18.00 18.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 5.00 20.00 25.00 24.00STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 16.00 24.00 21.45 20.90IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 4.00 21.00 17.50 18.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 30.00 21.00 18.20 21.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 2.00 23.00 20.33 21.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 10.00 21.00 16.01 14.36NH 2872-016 US 287 - LAMAR 03/04/04 25.00 19.00 22.75 12.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 97.00 18.00 17.69 15.50SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 20.00 20.00 17.67 15.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 20.00 20.00 14.00 13.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 28.00 18.00 17.72 12.50STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 30.00 16.00 14.00 16.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 424.00 18.86 17.82 15.88

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 9.00 20.00 16.18 18.50NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 180.00 17.00 16.47 17.50

Page 384: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 340 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 612-00003 Delin (Ty III) Each ===================================================NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 6.00 14.00 17.50 19.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 12.00 17.00 19.12 18.70STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 5.00 17.00 25.34 23.10SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 25.00 18.00 16.16 17.30STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 52.00 20.00 18.50 18.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 12.00 25.00 24.00 26.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 6.00 22.00 13.73 11.60CC R600-225 CHATFIELD STATE PARK 06/10/04 2.00 20.00 19.63 29.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 8.00 20.00 20.06 19.50STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 4.00 20.00 24.67 29.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 321.00 18.12 17.34 18.23

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 13.00 20.00 15.85 15.65IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 70.00 21.00 13.65 12.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 6.00 25.00 29.89 21.14BR 0243-063 EAST OF LIMON 07/15/04 4.00 22.00 21.62 24.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 45.00 20.00 17.89 21.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 2.00 22.00 15.80 19.26C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 8.00 20.00 18.93 20.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 8.00 22.00 20.88 21.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 19.00 21.00 19.83 14.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 175.00 20.84 16.18 16.25

SHE 105A-010 SH 105/FURROW RD 10/07/04 8.00 25.00 21.21 16.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 2.00 18.00 23.40 19.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 15.00 21.00 18.13 20.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 43.00 20.00 20.00 14.00NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 100.00 24.00 29.33 34.00STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 2.00 20.00 557.38 16.50NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 10.00 20.00 21.08 11.80STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 2.00 20.00 16.09 16.15 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 182.00 22.48 31.85 25.56 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,102.00 19.56 19.11 18.22

=============== 612-00010 Delin (Spec) Each ===================================================

SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 2.00 50.00 23.50 22.00

Page 385: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 341 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 612-00010 Delin (Spec) Each ===================================================SHE 0403-049 US 40, EAST OF CRAIG 09/23/04 1,426.00 70.00 89.91 76.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,428.00 69.97 89.87 75.92 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,428.00 69.97 89.87 75.92

=============== 612-00021 Delin (Ty I) (Barrier) Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 103.00 12.00 17.93 5.58 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 103.00 12.00 17.93 5.58 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 103.00 12.00 17.93 5.58

=============== 612-00022 Delin (Ty II) (Barrier) Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 8.00 15.00 19.22 7.81 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 8.00 15.00 19.22 7.81

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 54.00 18.00 14.22 17.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 54.00 18.00 14.22 17.10 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 62.00 17.61 14.86 15.90

=============== 612-00041 Delin (Flex) (Ty I) Each ===================================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 140.00 28.00 26.73 26.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 31.00 26.00 25.30 24.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 3.00 30.00 37.17 50.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 174.00 27.68 26.54 26.06

STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 54.00 30.00 29.67 30.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 207.00 20.00 24.18 14.00

Page 386: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 342 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 612-00041 Delin (Flex) (Ty I) Each ===================================================STA 0343-023 US 34, EAST OF AKRON 06/17/04 144.00 25.00 22.20 21.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 7.00 25.00 24.53 16.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 412.00 23.14 23.94 18.59

SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 7.00 30.00 35.50 33.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 7.00 30.00 35.50 33.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 593.00 24.55 24.69 20.95

=============== 612-00042 Delin (Flex) (Ty II) Each ===================================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 80.00 30.00 27.33 27.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 37.00 27.00 27.41 26.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 117.00 29.05 27.37 26.68

STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 24.00 35.00 32.33 33.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 154.00 21.00 25.96 15.00STA 0343-023 US 34, EAST OF AKRON 06/17/04 60.00 27.00 24.50 21.50BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 2.00 27.00 25.34 17.36 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 240.00 23.95 25.97 18.44

SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 3.00 31.00 37.50 35.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 3.00 31.00 37.50 35.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 360.00 25.67 26.43 21.26

=============== 612-00043 Delin (Flex) (Ty III) Each ===================================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 40.00 35.00 28.58 29.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 7.00 28.00 28.13 28.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 47.00 33.96 28.47 28.85

Page 387: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 343 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 612-00043 Delin (Flex) (Ty III) Each ===================================================

STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 3.00 40.00 33.00 35.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 57.00 22.00 26.73 16.00STA 0343-023 US 34, EAST OF AKRON 06/17/04 10.00 30.00 25.20 22.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 6.00 28.00 26.29 18.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 76.00 24.24 26.64 17.70

SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 4.00 32.00 40.50 36.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4.00 32.00 40.50 36.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 127.00 28.08 27.39 22.40

=============== 612-00260 Loc Mark (Fib Opt)(Dome) Each ===================================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 25.00 400.00 53.17 42.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 25.00 400.00 53.17 42.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 25.00 400.00 53.17 42.00

=============== 612-00270 Loc Mark (Util)(Flat Slat) Each ===================================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 10.00 500.00 49.56 38.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 10.00 500.00 49.56 38.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10.00 500.00 49.56 38.00

=============== 612-15000 Inst Marker Each ===================================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 364.00 25.00 85.26 125.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 364.00 25.00 85.26 125.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 364.00 25.00 85.26 125.00

Page 388: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 344 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 613-00001 Direct Bor Cond Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1,200.00 10.00 39.18 38.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,200.00 10.00 39.18 38.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,200.00 10.00 39.18 38.00

=============== 613-00075 3/4 In Elec Cond Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 190.00 10.00 16.95 20.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 190.00 10.00 16.95 20.00

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 58.00 10.00 9.57 9.63 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 58.00 10.00 9.57 9.63

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 650.00 6.00 5.20 5.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 50.00 10.00 30.62 30.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 700.00 6.29 6.44 6.79 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 948.00 7.26 9.30 9.61

=============== 613-00100 1 In Elec Cond Lin Foot ===============================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 2,973.00 6.00 8.00 9.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2,973.00 6.00 8.00 9.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,973.00 6.00 8.00 9.50

=============== 613-00125 1-1/4 In Elec Cond Lin Foot ===============================================

C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 120.00 20.00 13.68 5.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 120.00 20.00 13.68 5.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 120.00 20.00 13.68 5.00

Page 389: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 345 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 613-00126 1-1/4 In Elec Cond (Jacked) Lin Foot ===============================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 1,447.00 70.00 59.69 53.95 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,447.00 70.00 59.69 53.95 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,447.00 70.00 59.69 53.95

=============== 613-00127 1-1/4 In Elec Cond (P)(Spec) Lin Foot ===============================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 6,119.00 8.00 11.24 4.41 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 6,119.00 8.00 11.24 4.41 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6,119.00 8.00 11.24 4.41

=============== 613-00200 2 In Elec Cond Lin Foot ===============================================

STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 170.00 10.00 13.30 17.75IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 2,000.00 12.00 8.46 7.80NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 165.00 10.00 14.25 9.48STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 100.00 10.00 16.74 19.10IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 304.00 11.00 5.96 5.00SHE R300-113 DOWD BRIDGE, I-70 03/18/04 1,500.00 6.00 14.85 13.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4,239.00 9.60 11.05 10.31

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 5,279.00 40.00 32.39 30.60SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 124.00 14.00 12.13 10.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 5,403.00 39.40 31.77 30.14

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 15,316.00 5.00 6.29 6.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 4,734.00 8.00 11.57 13.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1,161.00 12.00 11.93 11.77C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 410.00 9.00 6.66 8.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 495.00 10.00 10.98 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 22,116.00 6.20 7.47 7.93

Page 390: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 346 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 613-00200 2 In Elec Cond Lin Foot ===============================================

SHE 5502-047 SH550 AT MP 112.7, IN OURAY C 10/07/04 100.00 65.00 29.08 6.05IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 2,560.00 8.00 6.37 4.60BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 4,450.00 6.00 5.21 5.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 7,110.00 7.55 6.16 4.93 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 38,868.00 11.43 9.69 10.73

=============== 613-00201 2 In Elec Cond (Jacked) Lin Foot ===============================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 155.00 10.00 12.90 12.40C 0342-040 US 34 IN WELD COUNTY 01/29/04 530.00 15.00 12.35 6.80IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 200.00 20.00 46.75 65.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 322.00 15.00 9.11 8.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 100.00 20.00 20.26 16.50NH 2872-016 US 287 - LAMAR 03/04/04 60.00 15.00 56.25 50.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 60.00 17.00 14.04 11.70STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 1,050.00 12.00 10.08 11.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,477.00 14.07 13.85 15.45

NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 2,370.00 12.00 11.25 8.95SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 187.00 13.00 8.37 9.20ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 9,903.00 35.00 62.96 54.27SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 300.00 14.00 8.53 8.20AQC R600-215 SH 287, US 36 TO SH 128 05/27/04 28,540.00 6.00 9.50 8.56IM 0253-186 I-25, 120TH TO SH 7 06/17/04 200.00 15.00 13.58 13.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 170.00 15.00 16.50 15.00STA R400-168 R4 DILEMMA ZONE SAFETY PROJEC 06/17/04 215.00 10.00 18.48 12.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 41,885.00 13.38 13.38 19.46

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1,726.00 12.00 10.06 9.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,726.00 12.00 10.06 9.50

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 25,000.00 8.00 4.61 4.50

Page 391: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 347 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 613-00201 2 In Elec Cond (Jacked) Lin Foot ===============================================C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 250.00 15.00 15.97 16.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 25,250.00 8.07 4.71 4.61 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 71,338.00 11.49 11.15 13.82

=============== 613-00300 3 In Elec Cond Lin Foot ===============================================

STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 340.00 12.00 14.12 16.80NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 5,862.00 12.00 7.82 6.69IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1,824.00 14.50 8.30 6.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 8,026.00 12.57 8.25 6.96

SHE 0091-023 SH 9 VMS - FAIRPLAY TO FRISCO 07/15/04 1,100.00 10.00 12.64 7.21C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1,000.00 12.00 9.40 9.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2,100.00 10.95 11.10 8.06

NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 60.00 9.00 41.40 32.49 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 60.00 9.00 41.40 32.49 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10,186.00 12.21 8.88 7.34

=============== 613-00301 3 In Elec Cond (Jacked) Lin Foot ===============================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 165.00 12.00 19.66 19.70C 0342-040 US 34 IN WELD COUNTY 01/29/04 340.00 13.00 15.04 9.74STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 2,180.00 13.00 12.07 12.45 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,685.00 12.94 13.42 12.55

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 1,340.00 15.00 12.65 14.95ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 576.00 70.00 65.51 54.38

Page 392: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 348 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 613-00301 3 In Elec Cond (Jacked) Lin Foot ===============================================SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 300.00 15.00 9.04 8.70STA R400-168 R4 DILEMMA ZONE SAFETY PROJEC 06/17/04 1,190.00 13.00 26.95 19.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3,406.00 23.60 25.97 22.66

SHE 0091-023 SH 9 VMS - FAIRPLAY TO FRISCO 07/15/04 100.00 10.00 33.72 33.89STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 200.00 17.00 22.04 26.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 300.00 14.67 25.93 28.90 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6,391.00 18.70 20.45 18.70

=============== 613-00400 4 In Elec Cond Lin Foot ===============================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 3,367.00 12.00 24.88 25.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 635.00 30.00 15.48 15.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4,002.00 14.86 23.39 23.41 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4,002.00 14.86 23.39 23.41

=============== 613-00600 6 In Elec Cond Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1,312.00 18.00 23.92 16.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,312.00 18.00 23.92 16.00

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 6,911.00 65.00 43.76 45.16 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 6,911.00 65.00 43.76 45.16 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8,223.00 57.50 37.09 40.51

=============== 613-00602 Inst 6 In Elec Cond Lin Foot ===============================================

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 300.00 4.00 14.75 6.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 300.00 4.00 14.75 6.30 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 300.00 4.00 14.75 6.30

Page 393: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 349 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 613-01100 1 In Elec Cond (P) Lin Foot ===============================================

NH 2872-016 US 287 - LAMAR 03/04/04 850.00 4.00 4.63 4.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 850.00 4.00 4.63 4.00

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 3,155.00 7.00 7.85 9.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 150.00 7.00 21.60 21.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 3,305.00 7.00 8.62 9.56 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4,155.00 6.39 7.81 8.42

=============== 613-01125 1-1/4 In Elec Cond (P) Lin Foot ===============================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 24,594.00 1.00 0.62 0.19 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 24,594.00 1.00 0.62 0.19

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 644.00 5.00 5.86 5.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 644.00 5.00 5.86 5.75 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 25,238.00 1.10 0.88 0.33

=============== 613-01150 1-1/2 In Elec Cond (P) Lin Foot ===============================================

IM 0701-157 FRUITA TO CLIFTON 02/26/04 1,220.00 7.50 7.42 6.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,220.00 7.50 7.42 6.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,220.00 7.50 7.42 6.50

=============== 613-01200 2 In Elec Cond (P) Lin Foot ===============================================

C 0342-040 US 34 IN WELD COUNTY 01/29/04 1,620.00 9.00 7.69 4.52

Page 394: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 350 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 613-01200 2 In Elec Cond (P) Lin Foot ===============================================STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 1,696.00 8.00 7.42 7.70STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 1,000.00 8.00 7.12 7.22IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 10,565.00 7.00 4.88 5.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 200.00 8.00 10.32 11.50C 074A-007 SH 74 @ BRYANT DR. 02/26/04 1,000.00 10.00 10.14 7.50STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 1,544.00 8.00 8.48 6.15NH 2872-016 US 287 - LAMAR 03/04/04 27,700.00 6.00 5.74 5.63NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 1,130.00 8.00 9.12 8.70STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 1,845.00 7.00 7.01 5.75SHE R300-113 DOWD BRIDGE, I-70 03/18/04 500.00 8.00 9.59 8.20STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 50.00 5.00 12.23 11.25STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 46,502.00 4.70 2.33 2.35 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 95,352.00 5.72 5.09 4.09

NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 9,250.00 6.00 6.48 3.37SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 971.00 9.00 5.73 5.75ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 6,421.00 1.30 0.79 0.48SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 1,190.00 8.00 6.40 6.20STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 1,420.00 12.00 11.35 12.40AQC R600-215 SH 287, US 36 TO SH 128 05/27/04 120.00 15.00 16.32 8.97NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 2,840.00 8.00 11.15 12.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 300.00 10.00 10.54 7.50IM 0253-186 I-25, 120TH TO SH 7 06/17/04 400.00 7.00 8.18 7.70SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 870.00 10.00 8.69 7.75STA R400-168 R4 DILEMMA ZONE SAFETY PROJEC 06/17/04 5,870.00 6.50 8.14 7.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 29,652.00 5.95 6.86 5.26

BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 100.00 15.00 18.40 15.10IMD 0252-364 I-25 OVER BROADWAY 07/29/04 3,606.00 8.00 10.00 12.00STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 3,000.00 7.00 11.95 4.54NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 870.00 10.00 5.70 5.50STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 2,000.00 8.00 9.87 9.63NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1,000.00 11.00 9.63 9.50IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 8,185.00 6.50 5.57 5.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 18,761.00 7.48 8.39 7.08

SHE 5502-047 SH550 AT MP 112.7, IN OURAY C 10/07/04 1,000.00 9.00 15.91 5.79

Page 395: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 351 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 613-01200 2 In Elec Cond (P) Lin Foot ===============================================IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 32,956.00 5.00 3.24 2.80BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1,928.00 8.00 10.27 10.05C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 2,708.00 7.00 9.64 7.50NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 1,000.00 8.00 7.68 3.91 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 39,592.00 5.46 4.28 3.58 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 183,357.00 5.88 5.53 4.48

=============== 613-01201 2 In Elec Cond (P) (Spec) Lin Foot ===============================================

NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 5,954.00 10.00 11.65 12.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 5,954.00 10.00 11.65 12.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5,954.00 10.00 11.65 12.50

=============== 613-01250 2-1/2 In Elec Cond (P) Lin Foot ===============================================

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 900.00 12.00 11.13 11.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 900.00 12.00 11.13 11.00

NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 120.00 10.00 16.03 17.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 120.00 10.00 16.03 17.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,020.00 11.76 11.57 11.71

=============== 613-01300 3 In Elec Cond (P) Lin Foot ===============================================

C 0342-040 US 34 IN WELD COUNTY 01/29/04 650.00 11.00 9.43 4.52STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 1,413.00 9.00 8.99 9.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 6,376.00 12.00 6.30 6.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 1,550.00 15.00 13.98 14.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 208.00 12.00 18.28 14.36NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 970.00 10.00 10.35 9.60STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 30.00 14.00 18.88 14.85STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 50.00 10.00 17.12 15.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 11,247.00 11.80 8.30 7.92

Page 396: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 352 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 613-01300 3 In Elec Cond (P) Lin Foot ===============================================

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 774.00 10.00 7.14 7.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 420.00 10.00 7.45 7.10NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1,600.00 13.00 11.66 13.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2,794.00 11.72 10.28 10.45

BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 939.00 15.00 7.42 6.04BR 0243-063 EAST OF LIMON 07/15/04 320.00 17.00 10.25 9.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 250.00 10.00 18.37 18.30STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 150.00 12.00 13.03 8.72NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 1,220.00 8.00 9.68 9.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 6,910.00 11.50 11.93 11.77NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 600.00 13.00 14.28 11.80 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 10,389.00 11.63 11.72 10.96

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 900.00 12.00 5.16 4.50NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 270.00 13.00 21.27 22.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,170.00 12.23 7.26 8.54 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 25,600.00 11.74 9.50 9.46

=============== 613-01301 3 In Elec Cond (P) (Spec) Lin Foot ===============================================

NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 969.00 13.00 14.03 15.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 969.00 13.00 14.03 15.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 969.00 13.00 14.03 15.00

=============== 613-01400 4 In Elec Cond (P) Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 3,600.00 14.50 3.07 3.00

Page 397: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 353 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 613-01400 4 In Elec Cond (P) Lin Foot ===============================================STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 550.00 8.30 5.50 5.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4,150.00 13.68 3.16 3.33

STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 126.00 13.00 13.40 13.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 126.00 13.00 13.40 13.60

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1,000.00 13.00 13.99 13.91 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,000.00 13.00 13.99 13.91 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5,276.00 13.53 4.83 5.58

=============== 613-01600 6 In Elec Cond (P) Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1,200.00 20.00 6.15 6.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 15,000.00 10.00 4.48 4.55 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 16,200.00 10.74 4.88 4.66

BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 100.00 10.00 16.00 8.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 100.00 10.00 16.00 8.00

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 214.00 15.00 15.02 14.98 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 214.00 15.00 15.02 14.98 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 16,514.00 10.79 5.33 4.81

=============== 613-03500 Elec Cond (P)(Mult)(Spec) Lin Foot ===============================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 233,291.00 10.00 9.76 4.91 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 233,291.00 10.00 9.76 4.91 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 233,291.00 10.00 9.76 4.91

Page 398: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 354 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 613-04000 Inst Conduit Lin Foot ===============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 116.00 10.00 29.98 27.89 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 116.00 10.00 29.98 27.89 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 116.00 10.00 29.98 27.89

=============== 613-07000 Pull Box (Spec) Each ===================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 3.00 365.00 189.11 160.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 8.00 450.00 195.88 147.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 25.00 400.00 139.70 141.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 3.00 460.00 211.75 200.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 2.00 400.00 257.94 153.51STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 16.00 350.00 319.12 307.69SHE R300-113 DOWD BRIDGE, I-70 03/18/04 1.00 400.00 752.50 260.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 43.00 470.00 307.50 315.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 101.00 426.58 227.05 245.70

STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 9.00 400.00 208.66 206.95STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 7.00 330.00 220.55 165.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 7.00 350.00 259.49 312.45STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 3.00 600.00 318.93 295.71STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 13.00 350.00 310.11 327.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 2.00 300.00 469.20 321.80STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 8.00 365.00 317.32 430.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 49.00 372.04 276.83 294.42 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 150.00 408.77 244.75 261.62

=============== 613-07010 Pull Box (Surf Mtd) Each ===================================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 60.00 400.00 481.93 312.12 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 60.00 400.00 481.93 312.12 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 60.00 400.00 481.93 312.12

=============== 613-07026 Pull Box (16"x24"x12") Each ===================================================

IM 0701-157 FRUITA TO CLIFTON 02/26/04 8.00 265.00 427.17 435.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 8.00 265.00 427.17 435.00

Page 399: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 355 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 613-07026 Pull Box (16"x24"x12") Each ===================================================

SHE 5502-047 SH550 AT MP 112.7, IN OURAY C 10/07/04 2.00 500.00 869.82 168.41 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 500.00 869.82 168.41 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10.00 312.00 515.70 381.68

=============== 613-07033 Pull Box (24"x20"x12") Each ===================================================

STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 5.00 300.00 303.00 165.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5.00 300.00 303.00 165.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5.00 300.00 303.00 165.00

=============== 613-07034 Pull Box (24"x36"x18") Each ===================================================

STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1.00 1000.00 398.66 400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 1000.00 398.66 400.00

NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 9.00 800.00 589.21 438.58ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 222.00 550.00 640.13 657.00AQC R600-215 SH 287, US 36 TO SH 128 05/27/04 30.00 700.00 679.30 344.09NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 15.00 750.00 824.62 900.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 2.00 800.00 593.48 550.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 278.00 586.87 655.02 628.50

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 18.00 400.00 576.44 550.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 18.00 400.00 576.44 550.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 297.00 576.94 646.94 622.98

=============== 613-07038 Pull Box (36"x48"x18") Each ===================================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 11.00 700.00 982.31 1214.88

Page 400: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 356 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 613-07038 Pull Box (36"x48"x18") Each ===================================================AQC R600-215 SH 287, US 36 TO SH 128 05/27/04 14.00 1000.00 872.05 480.74 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 25.00 868.00 888.98 803.76 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 25.00 868.00 888.98 803.76

=============== 613-07050 Pull Box (13"x24"x18") Deep Each ===================================================

NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 7.00 560.00 345.69 400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 7.00 560.00 345.69 400.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 7.00 560.00 345.69 400.00

=============== 613-07199 Inst Pull Box Each ===================================================

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 19.00 150.00 113.66 23.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 19.00 150.00 113.66 23.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 19.00 150.00 113.66 23.00

=============== 613-10000 Wiring LUMP SUM ===============================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 1.00 6000.00 1381.39 820.00C 0342-040 US 34 IN WELD COUNTY 01/29/04 1.00 8000.00 7068.44 4496.35STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 1.00 2000.00 784.99 550.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 1.00 5000.00 1591.75 1450.49STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 1.00 5000.00 3498.40 500.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 40000.00 15032.31 8500.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 1.00 6000.00 2980.00 2500.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 1.00 10000.00 4679.75 3300.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 1.00 1000.00 3453.33 1650.00NH 2872-016 US 287 - LAMAR 03/04/04 1.00 20000.00 14165.50 6000.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 1.00 8500.00 3964.59 4500.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 1.00 10000.00 10719.61 12095.00SHE R300-113 DOWD BRIDGE, I-70 03/18/04 1.00 2000.00 9535.00 8215.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1.00 2000.00 1792.65 1250.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1.00 40000.00 61750.00 62000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 15.00 11033.33 6629.34 7855.12

NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 1.00 15000.00 12165.24 9014.00

Page 401: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 357 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 613-10000 Wiring LUMP SUM ===============================================SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 1.00 5500.00 6499.84 4140.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 1.00 10000.00 5109.38 4900.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 12000.00 5356.72 3400.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 1.00 15000.00 2150.00 1600.00STA R400-168 R4 DILEMMA ZONE SAFETY PROJEC 06/17/04 1.00 9000.00 27325.54 6500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 6.00 11083.33 12260.98 4925.67

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1.00 27000.00 26250.73 30300.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 20000.00 36402.42 42300.00STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 1.00 3000.00 7562.00 12193.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 8000.00 31209.34 28761.60C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1.00 4000.00 4134.60 4750.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 7000.00 11550.00 19000.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 1.00 25000.00 16059.23 15000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 7.00 13428.57 19032.75 21757.80

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1.00 60000.00 34382.37 29000.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 10000.00 588.17 575.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 1.00 2000.00 1570.06 1550.35NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 1.00 2000.00 2633.10 1835.48 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4.00 18500.00 11011.08 8240.21 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 32.00 12500.00 10499.76 10395.20

=============== 613-16000 Luminaire (Spec) Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 8.00 1000.00 2505.93 2400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 8.00 1000.00 2505.93 2400.00

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 7.00 1600.00 710.42 704.06 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 7.00 1600.00 710.42 704.06 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 15.00 1280.00 1871.15 1608.56

Page 402: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 358 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 613-20100 Inst Light Std Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 18.00 550.00 289.29 300.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 4.00 2500.00 521.00 265.00NH 2872-016 US 287 - LAMAR 03/04/04 71.00 500.00 240.00 200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 93.00 595.70 268.39 222.15 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 93.00 595.70 268.39 222.15

=============== 613-20200 Inst Lumin Each ===================================================

NH 2872-016 US 287 - LAMAR 03/04/04 154.00 100.00 105.00 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 154.00 100.00 105.00 100.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 154.00 100.00 105.00 100.00

=============== 613-20210 Inst Lumin (Spec) Each ===================================================

C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 134.00 400.00 564.43 254.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 134.00 400.00 564.43 254.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 134.00 400.00 564.43 254.00

=============== 613-30005 Light Std + Lumin (Pedest) Each ===================================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 8.00 2500.00 3886.02 3850.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 8.00 2500.00 3886.02 3850.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8.00 2500.00 3886.02 3850.00

=============== 613-30350 Light Std Alum (35 Ft) Each ===================================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 187.00 1630.00 1200.00 1200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 187.00 1630.00 1200.00 1200.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 187.00 1630.00 1200.00 1200.00

Page 403: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 359 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 613-30400 Light Std Alum (40 Ft) Each ===================================================

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 4000.00 2497.01 2400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 4000.00 2497.01 2400.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 4000.00 2497.01 2400.00

=============== 613-32300 Light Std Steel (30 Ft) Each ===================================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 1.00 3000.00 3690.71 3251.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 3000.00 3690.71 3251.25 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 3000.00 3690.71 3251.25

=============== 613-32350 Light Std Steel (35 Ft) Each ===================================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 10.00 2500.00 1845.01 1810.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 10.00 2500.00 1845.01 1810.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10.00 2500.00 1845.01 1810.00

=============== 613-32352 Light Std Steel (35 Ft) (2) Each ===================================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 6.00 2500.00 2253.30 2210.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 6.00 2500.00 2253.30 2210.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6.00 2500.00 2253.30 2210.00

=============== 613-32400 Light Std Steel (40 Ft) Each ===================================================

C 074A-007 SH 74 @ BRYANT DR. 02/26/04 1.00 2500.00 2572.63 2312.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 2500.00 2572.63 2312.00

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 34.00 3000.00 1178.82 1100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 34.00 3000.00 1178.82 1100.00

Page 404: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 360 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 613-32400 Light Std Steel (40 Ft) Each ===================================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 49.00 2000.00 2750.94 2700.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 49.00 2000.00 2750.94 2700.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 84.00 2410.71 2258.82 2047.76

=============== 613-34150 Light Std Metal (15 Ft) Each ===================================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 22.00 1500.00 1050.61 1000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 22.00 1500.00 1050.61 1000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 22.00 1500.00 1050.61 1000.00

=============== 613-34300 Light Std Metal (30 Ft) Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 5.00 1400.00 1848.35 1800.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5.00 1400.00 1848.35 1800.00

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 15.00 1800.00 2140.88 2142.14 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 15.00 1800.00 2140.88 2142.14 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 20.00 1700.00 2039.13 2056.61

=============== 613-34400 Light Std Metal (40 Ft) Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 16.00 1700.00 3126.63 3000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 16.00 1700.00 3126.63 3000.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 48.00 1500.00 1585.53 1600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 48.00 1500.00 1585.53 1600.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 64.00 1550.00 2059.71 1950.00

Page 405: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 361 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 613-35120 Light Std Steel Hi Mast (120 Ft) Each ===================================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 20000.00 48125.80 44900.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 20000.00 48125.80 44900.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 20000.00 48125.80 44900.00

=============== 613-40000 Conc Foundation Pad Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 39.00 750.00 636.08 600.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 8.00 650.00 817.50 775.00NH 2872-016 US 287 - LAMAR 03/04/04 71.00 600.00 737.50 700.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 118.00 652.97 694.33 672.03

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 1.00 600.00 1171.74 634.64NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 2.00 700.00 672.00 550.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3.00 666.67 771.95 578.21

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 48.00 650.00 528.70 510.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 800.00 586.25 315.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 49.00 653.06 529.49 506.02

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 9.00 600.00 622.64 610.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 9.00 600.00 622.64 610.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 179.00 650.56 644.12 621.90

=============== 613-40010 Light Std Foundation Each ===================================================

C 074A-007 SH 74 @ BRYANT DR. 02/26/04 1.00 800.00 1127.21 550.00

Page 406: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 362 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 613-40010 Light Std Foundation Each ===================================================STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 183.00 675.00 372.50 375.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 184.00 675.68 386.66 375.95

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 700.00 987.95 1255.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 15.00 700.00 798.06 791.80IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 56.00 1000.00 380.44 376.43 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 72.00 933.33 491.83 475.17

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 47.00 600.00 752.79 780.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 47.00 600.00 752.79 780.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 303.00 725.17 527.70 462.20

=============== 613-40015 Light Std Anchor Each ===================================================

STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 4.00 500.00 682.00 450.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 500.00 682.00 450.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 500.00 682.00 450.00

=============== 613-45000 Hi Mast Foundation Each ===================================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 12000.00 7250.31 8368.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 12000.00 7250.31 8368.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 12000.00 7250.31 8368.00

=============== 613-50000 Lowering Device Each ===================================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 2000.00 5043.49 7985.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 2000.00 5043.49 7985.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 2000.00 5043.49 7985.00

Page 407: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 363 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 613-50100 Lighting Ctrl Center Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 2.00 5500.00 4206.13 4000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 5500.00 4206.13 4000.00

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 4000.00 3971.03 3550.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 4000.00 4799.99 4722.98 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 4000.00 4431.56 4136.49 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 4750.00 4287.28 4068.25

=============== 613-50150 Secondary Serv Pedestal Each ===================================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 4.00 2800.00 2754.71 2288.88 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4.00 2800.00 2754.71 2288.88 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 2800.00 2754.71 2288.88

=============== 613-50200 Lighting System Each ===================================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 15000.00 8485.70 12750.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 15000.00 8485.70 12750.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 15000.00 8485.70 12750.00

=============== 613-50355 Power Transformer Each ===================================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 5.00 2000.00 1966.05 1456.56 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 5.00 2000.00 1966.05 1456.56 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5.00 2000.00 1966.05 1456.56

=============== 613-50410 Light Std (Temp) Each ===================================================

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 4.00 1700.00 2175.17 2200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4.00 1700.00 2175.17 2200.00

Page 408: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 364 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 613-50410 Light Std (Temp) Each ===================================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 40.00 1200.00 1700.26 1725.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 13.00 3500.00 5307.76 5200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 53.00 1764.15 2342.69 2577.36 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 57.00 1759.65 2329.97 2550.88

=============== 613-70250 Lumin HPS (250 W) Each ===================================================

C 0342-040 US 34 IN WELD COUNTY 01/29/04 4.00 400.00 449.69 683.44IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 36.00 1200.00 261.28 250.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 4.00 450.00 324.33 295.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 16.00 450.00 419.55 358.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 60.00 896.67 308.93 310.70

SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 4.00 500.00 354.79 340.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4.00 500.00 354.79 340.00

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 13.00 450.00 1442.69 1431.66 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 13.00 450.00 1442.69 1431.66

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 35.00 500.00 291.39 300.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 22.00 475.00 530.78 520.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 57.00 490.35 362.08 384.91 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 134.00 668.66 421.01 451.89

=============== 613-70251 Inst Lumin HPS (250 W) Each ===================================================

C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 12.00 200.00 538.15 200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 12.00 200.00 538.15 200.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 12.00 200.00 538.15 200.00

Page 409: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 365 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 613-70400 Lumin HPS (400 W) Each ===================================================

STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 4.00 500.00 429.00 365.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 6.00 400.00 380.21 300.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1.00 500.00 438.90 425.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 195.00 400.00 230.00 240.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 206.00 402.43 255.60 245.07

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 5.00 400.00 384.44 420.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 5.00 400.00 384.44 420.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 48.00 300.00 397.94 400.00STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 3.00 400.00 450.60 631.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 4.00 400.00 417.60 450.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 55.00 312.73 401.60 416.24

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 18.00 600.00 294.72 300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 18.00 600.00 294.72 300.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 284.00 397.54 315.65 284.78

=============== 613-70401 Inst Lumin HPS (400 W) Each ===================================================

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 8.00 200.00 110.66 115.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 8.00 200.00 110.66 115.00

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 4.00 200.00 256.25 205.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4.00 200.00 256.25 205.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 12.00 200.00 168.90 145.00

Page 410: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 366 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 613-71000 Lumin HPS (1000 W) Each ===================================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 4.00 2000.00 1772.80 958.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4.00 2000.00 1772.80 958.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 2000.00 1772.80 958.00

=============== 613-72150 Lumin HPS (WT) (150 W) Each ===================================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 8.00 300.00 3061.95 3300.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 2.00 900.00 1704.40 1660.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 10.00 420.00 2868.02 2972.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10.00 420.00 2868.02 2972.00

=============== 613-75100 Lumin Metal Halide (100 W) Each ===================================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 48.00 600.00 831.52 857.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 48.00 600.00 831.52 857.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 48.00 600.00 831.52 857.00

=============== 613-75150 Lumin Metal Halide (150 W) Each ===================================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 22.00 800.00 323.32 300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 22.00 800.00 323.32 300.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 22.00 800.00 323.32 300.00

=============== 613-75175 Lumin Metal Halide (175 W) Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 9.00 900.00 1243.78 1200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 9.00 900.00 1243.78 1200.00

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 15.00 1000.00 1495.44 1487.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 15.00 1000.00 1495.44 1487.30 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 24.00 962.50 1372.17 1379.56

Page 411: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 367 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 613-75250 Lumin Metal Halide (250 W) Each ===================================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 96.00 500.00 1149.99 1410.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 96.00 500.00 1149.99 1410.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 96.00 500.00 1149.99 1410.00

=============== 613-75400 Lumin Metal Halide (400 W) Each ===================================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 34.00 900.00 471.53 450.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 34.00 900.00 471.53 450.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 34.00 900.00 471.53 450.00

=============== 614-00011 Sign Panel (CL I) Sq Foot ================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 7.00 18.00 15.85 15.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 234.00 25.00 12.41 12.00C 0342-040 US 34 IN WELD COUNTY 01/29/04 31.00 11.00 17.53 24.27STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 179.00 15.00 11.87 18.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 637.00 13.00 13.56 13.50IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 18.62 20.00 15.44 13.55NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 127.00 15.00 15.43 17.85STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 193.00 18.00 13.27 11.35STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 81.40 13.00 16.35 17.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 13.00 17.00 14.03 12.40C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 13.00 16.00 18.90 18.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 94.00 15.00 15.32 15.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 60.00 15.00 18.00 20.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 43.00 17.00 13.47 15.35IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 276.00 15.00 14.40 12.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 90.00 18.00 20.65 14.50C 074A-007 SH 74 @ BRYANT DR. 02/26/04 93.00 18.00 17.69 17.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 12.00 14.00 16.58 16.50STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 31.00 15.00 14.55 14.36NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 94.50 11.00 14.31 15.50STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 137.00 12.00 20.01 20.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 177.00 18.00 14.48 11.40STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 473.00 16.00 11.75 12.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3,114.52 15.75 14.30 14.20

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 42.00 15.00 13.20 13.25

Page 412: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 368 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-00011 Sign Panel (CL I) Sq Foot ================================================NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 105.00 11.00 15.42 13.50STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 74.00 16.00 14.88 15.34SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 241.00 17.00 17.65 21.45NH 0502-053 CIMARRON - WEST 04/15/04 87.00 22.00 15.52 24.00NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 24.00 11.00 26.84 22.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 10.00 20.00 15.80 15.60STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 6.00 15.00 19.33 22.00STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 7.50 25.00 18.89 24.20SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 60.00 13.00 14.65 14.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 14.38 15.00 17.88 16.90STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 67.00 11.00 12.33 12.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 455.00 10.00 10.20 9.30NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 289.00 18.00 12.98 7.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 23.00 16.00 11.12 9.50CC R600-225 CHATFIELD STATE PARK 06/10/04 48.00 15.00 13.38 17.00STA 0343-023 US 34, EAST OF AKRON 06/17/04 12.50 15.00 14.74 13.50SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 8.00 25.00 48.83 12.80 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,573.38 14.42 13.75 13.23

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 123.00 13.00 12.46 12.00STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 94.00 17.00 11.37 10.70IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 96.00 20.00 9.97 9.00BR 0243-063 EAST OF LIMON 07/15/04 5.00 35.00 64.60 36.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 80.00 15.00 35.47 90.70STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 53.00 15.00 18.25 22.98NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 73.80 18.00 13.99 18.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 425.91 20.00 15.91 19.80C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 75.00 12.00 16.96 20.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 58.00 20.00 15.45 12.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,083.71 17.71 15.79 22.11

SHE 105A-010 SH 105/FURROW RD 10/07/04 40.00 21.00 14.35 13.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 132.00 15.00 11.72 10.50BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 100.30 18.00 12.33 11.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 15.00 16.00 17.67 13.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 158.00 15.00 11.61 9.10NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 5.00 16.00 16.45 20.94STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 73.00 15.00 14.24 13.95STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 28.00 19.00 12.34 9.70STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 48.00 15.00 12.63 11.06

Page 413: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 369 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-00011 Sign Panel (CL I) Sq Foot ================================================NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 33.00 20.00 14.73 9.55STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 67.00 18.00 13.04 14.50NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 55.00 15.00 18.02 18.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 754.30 16.38 13.00 11.73 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6,525.91 15.83 14.27 14.99

=============== 614-00012 Sign Panel (CL II) Sq Foot ================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 21.00 20.00 20.21 20.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 158.00 20.00 14.64 13.00C 0342-040 US 34 IN WELD COUNTY 01/29/04 148.40 14.00 19.80 28.12STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 168.00 16.00 13.27 20.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 207.00 16.00 16.69 15.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 360.00 18.00 17.73 20.08STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 249.00 19.00 15.00 13.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 142.00 19.00 17.54 14.45C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 16.00 21.00 21.14 20.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 120.00 18.00 17.44 16.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 99.00 19.00 15.78 17.40IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 580.00 18.00 16.25 14.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 25.00 20.00 18.10 17.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 162.00 18.00 18.13 20.51NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 126.75 15.00 16.70 17.60SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 70.00 12.00 21.00 25.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 146.00 20.00 17.07 13.25STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 789.00 17.00 13.75 14.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3,587.15 17.53 16.45 16.40

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 40.00 17.00 14.42 15.50STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 57.00 20.00 18.55 20.45NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 227.50 20.00 20.93 18.90NH 0502-053 CIMARRON - WEST 04/15/04 124.00 25.00 17.70 25.00STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 69.00 17.00 24.67 27.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 93.00 50.00 26.84 36.41STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 22.00 26.00 22.32 31.50SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 64.00 14.00 17.29 16.00STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 69.00 14.00 14.00 13.50STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 27.00 15.00 13.91 14.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 137.00 21.00 15.52 9.50NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 44.00 18.00 14.78 13.70

Page 414: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 370 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-00012 Sign Panel (CL II) Sq Foot ================================================IM 0253-186 I-25, 120TH TO SH 7 06/17/04 246.00 16.00 18.28 15.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 34.00 30.00 20.13 16.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,253.50 21.35 18.79 18.83

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 199.00 18.00 13.40 12.50IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 3,444.00 14.00 13.65 13.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 12.00 30.00 19.74 20.13STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 16.00 20.00 25.47 25.88NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 351.00 22.00 16.94 21.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 426.83 22.00 19.14 21.94C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 42.00 14.00 20.00 22.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 18.00 18.00 19.07 17.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4,508.83 15.64 14.37 14.61

SHE 105A-010 SH 105/FURROW RD 10/07/04 25.00 25.00 18.04 16.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 309.00 16.00 14.46 14.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 117.00 18.00 15.66 14.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 90.00 15.00 20.67 18.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 97.00 20.00 16.13 13.40NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 55.00 17.00 21.64 24.34STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 108.00 18.00 16.53 16.10STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 72.00 20.00 15.02 12.95STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 171.00 18.00 15.10 13.27NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 255.00 16.00 17.48 12.75STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 83.00 20.00 15.94 17.75NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 156.00 16.00 19.87 25.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,538.00 17.29 16.52 15.73 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10,887.48 17.15 15.84 15.84

=============== 614-00013 Sign Panel (CL III) Sq Foot ================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 138.00 20.00 20.03 22.32STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 35.00 25.00 17.00 14.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 35.00 24.00 21.29 15.50STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 215.00 20.00 19.16 18.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 8.00 25.00 18.06 19.44

Page 415: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 371 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-00013 Sign Panel (CL III) Sq Foot ================================================IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 709.00 22.00 17.83 15.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 200.00 21.00 21.49 20.50STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 38.00 18.00 20.96 16.10STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 332.00 22.00 16.50 18.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,710.00 21.50 18.75 17.23

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 1,209.00 18.00 16.38 17.30SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 79.00 18.00 19.32 17.00STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 18.00 18.00 16.33 16.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 32.00 19.00 17.95 19.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 273.00 25.00 18.95 12.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,611.00 19.21 16.96 16.41

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 4,921.00 18.00 17.36 17.00STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 100.00 22.00 24.40 16.11NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 73.00 24.00 20.12 25.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 5,094.00 18.16 17.49 17.10

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 516.00 20.00 18.98 17.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 18.00 25.00 20.88 16.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 534.00 20.17 19.04 16.97 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8,949.00 19.11 17.73 16.99

=============== 614-00026 Inst Sign Panel (CL I) Each ===================================================

STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 8.00 20.00 87.76 120.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 8.00 20.00 87.76 120.00

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 23.00 100.00 37.00 26.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 23.00 100.00 37.00 26.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 31.00 79.35 52.38 50.26

Page 416: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 372 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-00027 Inst Sign Panel (CL II) Sq Foot ================================================

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 72.00 20.00 3.46 3.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 72.00 20.00 3.46 3.10 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 72.00 20.00 3.46 3.10

=============== 614-00028 Inst Sign Panel (CL III) Sq Foot ================================================

C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 2,697.00 5.00 7.50 7.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,697.00 5.00 7.50 7.50

C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 1,245.00 7.00 7.74 2.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,245.00 7.00 7.74 2.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3,942.00 5.63 7.66 5.92

=============== 614-00035 Sign Panel (Spec) Sq Foot ================================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 10.00 40.00 31.04 14.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 10.00 40.00 31.04 14.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10.00 40.00 31.04 14.00

=============== 614-00044 Timber Sign Post (4x4 In) Lin Foot ===============================================

CC R600-225 CHATFIELD STATE PARK 06/10/04 155.00 14.00 7.38 4.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 155.00 14.00 7.38 4.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 155.00 14.00 7.38 4.50

=============== 614-00200 Steel Sign Post (U-2) Lin Foot ===============================================

NH 0502-053 CIMARRON - WEST 04/15/04 30.00 12.00 8.59 5.50

Page 417: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 373 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-00200 Steel Sign Post (U-2) Lin Foot ===============================================NH 2852-010 US 285 & COUNTY RD. G 04/29/04 75.00 11.00 7.50 8.10STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 91.00 15.00 9.33 9.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 196.00 13.01 8.32 8.12

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 30.00 15.00 6.57 11.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 100.00 12.00 10.99 11.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 130.00 12.69 9.17 11.00

STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 15.00 15.00 5.07 2.15STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 16.00 15.00 4.72 7.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 31.00 15.00 4.90 4.91 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 357.00 13.07 8.22 8.89

=============== 614-00216 Steel Sign Post (2x2 In T) Lin Foot ===============================================

STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 177.00 13.00 14.33 13.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 258.00 17.00 11.44 9.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 48.00 20.00 20.25 20.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 483.00 15.83 12.77 11.56

NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 52.00 15.00 16.61 20.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 52.00 15.00 16.61 20.00

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 122.00 13.00 12.14 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 122.00 13.00 12.14 10.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 657.00 15.24 12.89 11.94

Page 418: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 374 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-00218 Steel Sign Post (2.25x2.25 In T) Lin Foot ===============================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 42.00 15.00 16.64 9.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 42.00 15.00 16.64 9.00

NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 60.00 14.00 12.71 12.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 60.00 14.00 12.71 12.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 102.00 14.41 14.83 10.76

=============== 614-00220 Steel Sign Post (2.5x2.5 In T) Lin Foot ===============================================

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 119.00 22.00 12.39 12.27 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 119.00 22.00 12.39 12.27

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 29.00 28.00 12.26 17.39 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 29.00 28.00 12.26 17.39 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 148.00 23.18 12.38 13.27

=============== 614-00357 Steel Sign Post (S 3x5.7) Lin Foot ===============================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 14.00 30.00 19.70 14.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 14.00 30.00 19.70 14.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 14.00 30.00 19.70 14.50

=============== 614-00477 Steel Sign Post (S 4x7.7) Lin Foot ===============================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 13.00 32.00 25.75 17.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 13.00 32.00 25.75 17.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 13.00 32.00 25.75 17.50

Page 419: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 375 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-00612 Steel Sign Post (W 6x12) Lin Foot ===============================================

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 93.00 35.00 24.94 23.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 93.00 35.00 24.94 23.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 93.00 35.00 24.94 23.00

=============== 614-00615 Steel Sign Post (W 6x15) Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 166.00 36.00 42.56 40.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 166.00 36.00 42.56 40.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 169.00 40.00 28.71 27.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 169.00 40.00 28.71 27.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 335.00 38.02 36.56 33.44

=============== 614-00818 Steel Sign Post (W 8x18) Lin Foot ===============================================

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 46.00 40.00 33.44 21.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 46.00 40.00 33.44 21.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 367.00 45.00 31.25 29.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 367.00 45.00 31.25 29.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 413.00 44.44 31.50 28.11

=============== 614-00821 Steel Sign Post (W 8x21) Lin Foot ===============================================

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 270.00 45.00 34.59 33.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 270.00 45.00 34.59 33.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 270.00 45.00 34.59 33.00

Page 420: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 376 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-01022 Steel Sign Post (W 10x22) Lin Foot ===============================================

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 102.00 50.00 38.94 25.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 102.00 50.00 38.94 25.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 89.00 50.00 36.87 34.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 89.00 50.00 36.87 34.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 191.00 50.00 37.98 29.19

=============== 614-01026 Steel Sign Post (W 10x26) Lin Foot ===============================================

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 118.00 55.00 39.36 36.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 118.00 55.00 39.36 36.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 118.00 55.00 39.36 36.00

=============== 614-01226 Steel Sign Post (W 12x26) Lin Foot ===============================================

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 243.00 62.00 42.03 38.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 243.00 62.00 42.03 38.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 243.00 62.00 42.03 38.00

=============== 614-01502 Steel Sign Supp (2-In Rd)(Po&Sock) Lin Foot ===============================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 140.00 10.00 11.16 11.50NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 146.00 15.00 16.20 22.32STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 98.00 14.00 9.17 7.25C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 23.00 15.00 20.12 24.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 322.00 11.00 10.56 9.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 38.00 13.25 14.42 16.50STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 190.00 20.00 8.98 7.15 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 957.00 13.74 11.32 11.51

Page 421: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 377 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-01502 Steel Sign Supp (2-In Rd)(Po&Sock) Lin Foot ===============================================

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 96.00 10.00 16.24 11.50SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 190.00 13.00 12.64 18.85NH 0502-053 CIMARRON - WEST 04/15/04 135.00 13.00 14.08 20.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 48.00 14.00 18.26 17.68STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 584.00 12.50 11.40 11.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 12.00 15.00 11.21 9.70STA 0343-023 US 34, EAST OF AKRON 06/17/04 21.00 10.00 12.20 10.50SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 12.00 20.00 16.25 15.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,098.00 12.56 12.87 13.83

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 162.00 12.00 35.09 14.00IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1,704.00 15.00 9.55 9.50BR 0243-063 EAST OF LIMON 07/15/04 8.00 40.00 25.76 24.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 94.00 13.00 11.96 16.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 372.50 14.00 15.81 12.04NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 128.00 7.00 7.08 6.30IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 176.00 13.00 14.76 12.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2,644.50 14.16 12.54 10.42 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4,699.50 13.70 12.30 11.44

=============== 614-01512 Steel Sign Supp (2-In Rd)(Post) Lin Foot ===============================================

STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 50.00 20.00 10.34 10.50STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 139.00 10.00 10.30 10.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 302.00 9.00 8.66 2.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 491.00 10.40 9.15 5.50

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 188.00 5.00 8.31 8.35 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 188.00 5.00 8.31 8.35 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 679.00 8.91 8.96 6.29

Page 422: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 378 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-01522 Steel Sign Supp (2-In Rd)(Sock) Each ===================================================

STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 7.00 35.00 78.75 120.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 7.00 35.00 78.75 120.00

STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 40.00 40.00 50.24 31.50NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 28.00 70.00 19.11 9.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 68.00 52.35 38.57 22.24

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 19.00 100.00 37.43 41.70NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 40.00 100.00 55.00 37.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 59.00 100.00 49.34 38.51 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 134.00 72.43 43.72 34.51

=============== 614-01552 Steel Sign Post (2.5 In Rd) (Slip) Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 808.00 24.00 24.25 21.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 120.00 24.00 19.40 24.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 24.00 28.00 31.17 38.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 617.00 19.00 15.00 14.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,569.00 22.09 22.67 18.74

NH 0502-053 CIMARRON - WEST 04/15/04 133.00 35.00 21.05 22.00STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 68.00 32.00 31.33 36.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 72.00 25.00 33.75 35.80STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 87.00 25.00 25.58 25.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 247.00 24.00 25.05 25.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 607.00 27.57 26.08 26.86

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 264.50 40.00 25.15 28.00

Page 423: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 379 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-01552 Steel Sign Post (2.5 In Rd) (Slip) Lin Foot ===============================================NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 96.00 25.00 20.63 26.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 21.00 23.00 30.96 25.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 381.50 35.29 24.16 27.33 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,557.50 25.36 23.49 21.95

=============== 614-01554 Steel Sign Post (4 In Rd) (Slip) Lin Foot ===============================================

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 36.00 40.00 39.87 46.80 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 36.00 40.00 39.87 46.80 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 36.00 40.00 39.87 46.80

=============== 614-01582 Steel Sign Supp (2-1/2 In Rd)(Po&Slip) Lin Foot ===============================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 31.00 35.00 29.94 30.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 426.00 28.00 22.56 20.00C 0342-040 US 34 IN WELD COUNTY 01/29/04 119.00 24.00 29.39 37.38STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 325.00 28.00 21.65 23.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 946.00 25.00 24.69 27.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 48.00 32.00 22.06 25.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 473.00 30.00 31.81 39.05STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 270.00 30.00 22.55 18.50STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 149.00 25.00 24.44 22.70C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 14.00 45.00 30.89 28.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 76.00 30.00 25.32 20.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 188.50 30.00 24.17 26.35STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 615.00 25.00 24.48 23.59NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 202.00 26.00 24.70 26.00SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 55.00 25.00 31.00 35.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 39.00 25.00 29.54 21.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 180.00 10.00 22.20 18.80STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1,232.00 22.00 20.50 22.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5,388.50 25.35 24.51 25.02

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 38.00 26.00 22.88 24.75STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 16.00 30.00 28.75 35.79NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 60.00 40.00 34.81 31.50

Page 424: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 380 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-01582 Steel Sign Supp (2-1/2 In Rd)(Po&Slip) Lin Foot ===============================================STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 12.00 35.00 29.49 29.12ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 95.00 30.00 30.82 35.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 88.00 30.00 25.85 26.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 267.00 30.00 15.64 8.50NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 48.00 25.00 23.74 22.10IM 0253-186 I-25, 120TH TO SH 7 06/17/04 248.00 28.00 32.62 27.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 55.00 40.00 22.00 19.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 927.00 30.35 24.59 22.08

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 3,602.00 20.00 22.02 22.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 11.00 50.00 31.46 30.20STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 529.00 28.00 22.65 28.36C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 91.00 28.00 29.40 27.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4,233.00 21.25 22.23 22.92

SHE 105A-010 SH 105/FURROW RD 10/07/04 112.00 40.00 27.42 26.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 460.00 20.00 25.56 27.25BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 208.50 25.00 24.30 24.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 147.00 30.00 24.45 22.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 123.00 25.00 27.31 27.56STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 445.00 25.00 25.64 25.81STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 48.00 35.00 24.18 24.95STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 132.00 25.00 26.37 24.33NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 275.00 28.00 26.85 24.55STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 163.00 30.00 25.66 25.25NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 156.00 22.00 26.33 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2,269.50 25.78 25.80 24.41 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 12,818.00 24.43 23.93 24.01

=============== 614-01585 Steel Sign Supp (2-1/2 In Rd 80 )(Po) Lin Foot ===============================================

C 074A-007 SH 74 @ BRYANT DR. 02/26/04 12.00 20.00 21.48 17.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 12.00 20.00 21.48 17.00

STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 24.00 20.00 21.08 22.05 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 24.00 20.00 21.08 22.05

Page 425: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 381 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-01585 Steel Sign Supp (2-1/2 In Rd 80 )(Po) Lin Foot ===============================================

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 279.00 18.00 17.50 16.70STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 14.00 17.00 25.26 18.21 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 293.00 17.95 17.96 16.77

STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 116.00 15.00 18.67 22.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 116.00 15.00 18.67 22.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 445.00 17.35 18.55 18.43

=============== 614-01588 Steel Sign Supp (2-1/2 In Rd 80)(Slip) Each ===================================================

C 074A-007 SH 74 @ BRYANT DR. 02/26/04 1.00 30.00 183.55 214.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 4.00 50.00 206.25 215.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 5.00 50.00 149.08 130.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 10.00 48.00 169.01 172.40

STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 8.00 200.00 137.42 157.50NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 24.00 120.00 101.97 70.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 32.00 140.00 111.89 91.88

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 23.00 120.00 135.46 135.35STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 1.00 215.00 330.22 313.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 26.00 120.00 144.75 84.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 50.00 121.90 145.11 112.20

STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 10.00 80.00 110.00 140.00

Page 426: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 382 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-01588 Steel Sign Supp (2-1/2 In Rd 80)(Slip) Each ===================================================NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 13.00 100.00 150.50 75.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 23.00 91.30 139.25 103.26 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 115.00 114.39 134.72 109.99

=============== 614-01736 Steel Sign Ground Stub base (36 In) Each ===================================================

NH 0502-053 CIMARRON - WEST 04/15/04 12.00 50.00 185.87 215.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 12.00 50.00 185.87 215.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 12.00 50.00 185.87 215.00

=============== 614-03001 Conc Footing (Ty 1) Each ===================================================

IM 0701-157 FRUITA TO CLIFTON 02/26/04 4.00 800.00 673.50 650.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 800.00 673.50 650.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 6.00 600.00 411.59 360.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 2.00 655.00 2885.00 260.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 8.00 613.75 861.30 335.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 12.00 675.83 795.02 440.00

=============== 614-03002 Conc Footing (Ty 2) Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 10.00 750.00 698.46 825.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 10.00 750.00 698.46 825.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 10.00 800.00 459.46 420.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 10.00 800.00 459.46 420.00

Page 427: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 383 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-03002 Conc Footing (Ty 2) Each ===================================================

SHE 105A-010 SH 105/FURROW RD 10/07/04 2.00 700.00 580.88 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 700.00 580.88 500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 22.00 768.18 595.02 611.36

=============== 614-03003 Conc Footing (Ty 3) Each ===================================================

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 2.00 200.00 743.04 770.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 200.00 743.04 770.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 20.00 850.00 553.04 540.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 20.00 850.00 553.04 540.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 22.00 790.91 570.31 560.91

=============== 614-03004 Conc Footing (Ty 4) Each ===================================================

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 14.00 900.00 614.58 610.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 14.00 900.00 614.58 610.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 14.00 900.00 614.58 610.00

=============== 614-03005 Conc Footing (Ty 5) Each ===================================================

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 4.00 400.00 1048.08 1300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4.00 400.00 1048.08 1300.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 4.00 1250.00 839.56 850.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4.00 1250.00 839.56 850.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8.00 825.00 943.82 1075.00

Page 428: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 384 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-03006 Conc Footing (Ty 6) Each ===================================================

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 6.00 1500.00 921.73 960.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 6.00 1500.00 921.73 960.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6.00 1500.00 921.73 960.00

=============== 614-03007 Conc Footing (Ty 7) Each ===================================================

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 10.00 1600.00 1019.03 1100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 10.00 1600.00 1019.03 1100.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10.00 1600.00 1019.03 1100.00

=============== 614-07105 Mod Sign Legend Each ===================================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 4.00 725.00 774.24 756.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4.00 725.00 774.24 756.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 725.00 774.24 756.00

=============== 614-10123 Inst Var Mesg Sign Each ===================================================

C R200-126 FY04 REGION 2 SIGNING 04/01/04 1.00 4000.00 5742.84 9525.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 4000.00 5742.84 9525.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 4000.00 5742.84 9525.00

=============== 614-10125 Var Mesg Sign (Grnd Mtd) Each ===================================================

SHE 0091-023 SH 9 VMS - FAIRPLAY TO FRISCO 07/15/04 1.00 100000.00 137968.15 126435.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 100000.00 137968.15 126435.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 100000.00 137968.15 126435.00

=============== 614-10128 Blankout Sign (Fib Opt) Each ===================================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 2.00 12000.00 9054.87 9075.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 12000.00 9054.87 9075.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 12000.00 9054.87 9075.00

Page 429: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 385 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-10130 Illuminated Sign Each ===================================================

C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 6.00 2000.00 3357.60 3400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 6.00 2000.00 3357.60 3400.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6.00 2000.00 3357.60 3400.00

=============== 614-10147 VMS LED (Overhead) Each ===================================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 2.00 150000.00 162592.98 160169.58IM 0253-186 I-25, 120TH TO SH 7 06/17/04 1.00 100000.00 126040.88 118000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3.00 133333.33 147972.14 146113.05 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 133333.33 147972.14 146113.05

=============== 614-10148 VMS LED (Speed Radar) Each ===================================================

SHE 5502-047 SH550 AT MP 112.7, IN OURAY C 10/07/04 1.00 100800.00 102765.70 97606.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 100800.00 102765.70 97606.20 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 100800.00 102765.70 97606.20

=============== 614-10150 12 In LED (Ball) Each ===================================================

STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 37.00 170.00 134.51 120.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 112.00 180.00 136.26 118.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 80.00 170.00 138.27 143.59 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 229.00 174.89 136.59 127.26

STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 84.00 150.00 114.43 106.00STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 6.00 150.00 196.74 220.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 90.00 150.00 119.05 113.64 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 319.00 167.87 132.04 123.42

Page 430: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 386 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-10151 12 In LED (Ball) (Green) Each ===================================================

STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 43.00 150.00 172.81 147.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 43.00 150.00 172.81 147.25 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 43.00 150.00 172.81 147.25

=============== 614-10153 12 In LED (Ball) (Yellow) Each ===================================================

STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 43.00 150.00 90.93 81.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 43.00 150.00 90.93 81.70 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 43.00 150.00 90.93 81.70

=============== 614-10155 12 In LED (Arr) Each ===================================================

STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 4.00 150.00 119.57 110.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 8.00 150.00 148.67 110.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 12.00 150.00 138.97 110.00

STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 34.00 110.00 108.37 98.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 34.00 110.00 108.37 98.75 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 46.00 120.43 117.29 101.68

=============== 614-10156 12 In LED (Arr) (Green) Each ===================================================

STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 17.00 125.00 145.69 127.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 17.00 125.00 145.69 127.75 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 17.00 125.00 145.69 127.75

=============== 614-10158 12 In LED (Arr) (Yellow) Each ===================================================

STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 17.00 125.00 93.80 88.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 17.00 125.00 93.80 88.20 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 17.00 125.00 93.80 88.20

Page 431: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 387 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-10160 Sig Head B-Plates Each ===================================================

STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 14.00 200.00 121.80 125.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 30.00 180.00 99.64 106.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 44.00 186.36 106.69 112.05

STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 37.00 110.00 119.51 84.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 37.00 110.00 119.51 84.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 81.00 151.48 111.50 99.23

=============== 614-21275 VMS Support (Grnd Mtd) (12.75 In) Each ===================================================

SHE 5502-047 SH550 AT MP 112.7, IN OURAY C 10/07/04 1.00 15000.00 16165.42 13519.51 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 15000.00 16165.42 13519.51 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 15000.00 16165.42 13519.51

=============== 614-32400 Monotube Overhead Sign Cant (24 In Dia) Each ===================================================

C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 6.00 24000.00 22528.00 22528.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 6.00 24000.00 22528.00 22528.00

C R200-126 FY04 REGION 2 SIGNING 04/01/04 1.00 22000.00 28565.00 25668.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 2.00 30000.00 31386.99 28850.29IM 0253-186 I-25, 120TH TO SH 7 06/17/04 1.00 22000.00 30183.25 25200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4.00 26000.00 30365.38 27142.15

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1.00 25000.00 31233.58 29000.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 25000.00 25785.55 25800.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 25000.00 29054.37 27400.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 12.00 24833.33 28291.78 24878.05

Page 432: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 388 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-32900 Inst Monotube Overhead Sign Cant Each ===================================================

C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 12.00 2000.00 3812.11 3000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 12.00 2000.00 3812.11 3000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 12.00 2000.00 3812.11 3000.00

=============== 614-41275 Monotube Overhead Sign Brdg(12.75In Dia) Each ===================================================

C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 1.00 25000.00 26062.00 26062.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 25000.00 26062.00 26062.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 25000.00 26062.00 26062.00

=============== 614-41400 Monotube Overhead Sign Brdg (14 In Dia) Each ===================================================

C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 1.00 28000.00 29377.00 29377.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 28000.00 29377.00 29377.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 28000.00 29377.00 29377.00

=============== 614-41600 Monotube Overhead Sign Brdg (16 In Dia) Each ===================================================

C R200-126 FY04 REGION 2 SIGNING 04/01/04 2.00 25000.00 29589.73 26392.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 25000.00 29589.73 26392.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 25000.00 29589.73 26392.00

=============== 614-42000 Monotube Overhead Sign Brdg (20 In Dia) Each ===================================================

C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 1.00 36000.00 43052.00 43052.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 36000.00 43052.00 43052.00

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 36000.00 35856.20 20160.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 36000.00 35856.20 20160.00

Page 433: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 389 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-42000 Monotube Overhead Sign Brdg (20 In Dia) Each ===================================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 40000.00 42779.52 42300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 40000.00 42779.52 42300.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 37333.33 39732.76 35170.67

=============== 614-42400 Monotube Overhead Sign Brdg (24 In Dia) Each ===================================================

C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 1.00 38000.00 53194.00 53194.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 38000.00 53194.00 53194.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 38000.00 53194.00 53194.00

=============== 614-70112 Traf Sig Face (12) Each ===================================================

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 600.00 827.36 802.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 600.00 827.36 802.50

STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 14.00 120.00 120.00 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 14.00 120.00 120.00 100.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 15.00 152.00 195.25 146.83

=============== 614-70117 Ped Sig Face (16) Each ===================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 2.00 625.00 651.71 700.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 6.00 600.00 452.99 425.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 8.00 550.00 500.44 480.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 28.00 600.00 458.13 415.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1.00 800.00 571.00 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 45.00 596.67 483.33 442.44

Page 434: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 390 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-70117 Ped Sig Face (16) Each ===================================================

SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 8.00 600.00 451.32 433.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 8.00 600.00 482.82 430.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 16.00 600.00 468.50 431.50

STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 6.00 500.00 520.60 490.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 21.00 600.00 463.82 460.10C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 2.00 575.00 486.00 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 29.00 577.59 477.10 469.04

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 8.00 650.00 474.85 475.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 6.00 500.00 449.52 439.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 14.00 585.71 463.99 459.83 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 104.00 590.38 476.65 450.52

=============== 614-70216 Traf Sig Face (8-8) Each ===================================================

NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 10.00 450.00 419.76 394.11 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 10.00 450.00 419.76 394.11 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10.00 450.00 419.76 394.11

=============== 614-70328 Traf Sig Face (12-8-8) Each ===================================================

NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 10.00 600.00 559.10 503.36 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 10.00 600.00 559.10 503.36 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10.00 600.00 559.10 503.36

=============== 614-70336 Traf Sig Face (12-12-12) Each ===================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 5.00 900.00 833.68 860.00

Page 435: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 391 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-70336 Traf Sig Face (12-12-12) Each ===================================================C 0342-040 US 34 IN WELD COUNTY 01/29/04 18.00 800.00 777.28 913.72STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 1.00 900.00 830.97 836.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 17.00 800.00 681.16 576.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 2.00 800.00 697.06 615.37NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 19.00 850.00 734.78 690.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 50.00 900.00 680.30 687.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 7.00 800.00 754.27 700.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 20.00 775.00 785.00 900.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 139.00 843.53 727.46 740.76

NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 60.00 895.00 755.66 714.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 4.00 800.00 674.50 645.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 15.00 800.00 741.01 680.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 12.00 800.00 739.50 689.40STA R400-168 R4 DILEMMA ZONE SAFETY PROJEC 06/17/04 5.00 800.00 951.94 650.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 96.00 859.38 767.21 699.40

STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 9.00 650.00 739.02 672.11NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 12.00 1000.00 776.20 800.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 42.00 800.00 738.57 738.30C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 8.00 850.00 724.20 750.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 71.00 820.42 740.99 741.66

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 28.00 650.00 771.70 800.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 11.00 750.00 607.73 599.35STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 15.00 750.00 671.55 648.55 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 54.00 698.15 710.48 717.06 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 360.00 821.39 736.27 726.35

=============== 614-70450 Traf Sig Face (12-12-12-12)(Instal Only) Each ===================================================

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 2.00 500.00 308.75 240.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 500.00 308.75 240.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 500.00 308.75 240.00

Page 436: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 392 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-70560 Traf Sig Face (12-12-12-12-12) Each ===================================================

C 074A-007 SH 74 @ BRYANT DR. 02/26/04 4.00 1000.00 1077.32 950.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 4.00 1350.00 1216.48 1150.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 24.00 1300.00 1056.57 1180.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 4.00 1100.00 1150.07 950.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 5.00 1220.00 1175.00 1250.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 41.00 1246.34 1095.72 1140.73

NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 2.00 1350.00 1109.10 945.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 8.00 1350.00 1043.89 1000.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 4.00 1150.00 1167.56 1000.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 2.00 1200.00 1123.49 1032.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 16.00 1281.25 1095.47 997.19

STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 2.00 1100.00 1126.10 1018.50STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 9.00 1200.00 1214.84 1214.45C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 8.00 1350.00 1138.00 1100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 19.00 1252.63 1173.14 1145.63

STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 2.00 1100.00 1091.32 1067.90STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 2.00 1200.00 1063.30 1024.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4.00 1150.00 1077.31 1045.95 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 80.00 1250.00 1112.57 1108.45

=============== 614-72830 Communications Cabinet Each ===================================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 7.00 7000.00 7482.38 7074.72 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 7.00 7000.00 7482.38 7074.72 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 7.00 7000.00 7482.38 7074.72

Page 437: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 393 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-72855 Traf Sig Ctrl Cabinet Each ===================================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 3.00 14000.00 12050.00 12000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3.00 14000.00 12050.00 12000.00

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 1.00 13000.00 17387.17 17000.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1.00 14000.00 13352.60 13500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 13500.00 14865.56 15250.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5.00 13800.00 13658.89 13300.00

=============== 614-72858 Ped Pole (3.5 In) Each ===================================================

C 074A-007 SH 74 @ BRYANT DR. 02/26/04 1.00 1000.00 885.04 560.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 1000.00 885.04 560.00

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 2.00 1000.00 571.80 567.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 1000.00 571.80 567.10 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 1000.00 700.78 564.73

=============== 614-72860 Ped Push Button Each ===================================================

C 074A-007 SH 74 @ BRYANT DR. 02/26/04 6.00 120.00 121.81 140.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 7.00 135.00 93.78 104.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 2.00 120.00 89.39 75.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 15.00 127.00 105.17 114.53

SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 8.00 105.00 101.10 97.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 8.00 140.00 85.34 61.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 16.00 122.50 92.51 79.00

Page 438: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 394 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-72860 Ped Push Button Each ===================================================

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 21.00 130.00 91.73 90.95C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 2.00 120.00 98.40 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 23.00 129.13 92.31 91.74 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 54.00 126.57 96.55 94.30

=============== 614-72864 Fire Preempt Unit Each ===================================================

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 2500.00 6309.55 5100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 2500.00 6309.55 5100.00

C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 4.00 2000.00 1427.80 1400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4.00 2000.00 1427.80 1400.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5.00 2100.00 2554.36 2140.00

=============== 614-72866 Fire Preempt Unit + Timer Each ===================================================

C 0342-040 US 34 IN WELD COUNTY 01/29/04 1.00 5500.00 7954.24 6433.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 5500.00 7954.24 6433.30

SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 1.00 6000.00 6443.51 6170.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 6000.00 6443.51 6170.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 5750.00 7373.19 6301.65

=============== 614-72871 Loop Detect Wire (Prefab) Spec Lin Foot ===============================================

STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 5,130.00 6.50 4.91 3.69 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5,130.00 6.50 4.91 3.69

Page 439: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 395 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-72871 Loop Detect Wire (Prefab) Spec Lin Foot ===============================================

NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 786.00 10.00 16.47 17.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 786.00 10.00 16.47 17.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5,916.00 6.97 5.74 5.46

=============== 614-72872 Loop Detect (Micro Type) Each ===================================================

C 0342-040 US 34 IN WELD COUNTY 01/29/04 4.00 360.00 1035.05 1002.23STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 3.00 450.00 360.54 340.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 13.00 350.00 351.95 330.56 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 20.00 367.00 492.33 466.31

NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 8.00 350.00 373.78 315.00STA R400-168 R4 DILEMMA ZONE SAFETY PROJEC 06/17/04 30.00 500.00 864.48 700.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 38.00 468.42 812.48 618.95

NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 6.00 350.00 413.53 372.67STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 3.00 500.00 629.81 779.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 9.00 400.00 475.33 508.20 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 67.00 428.96 683.89 558.51

=============== 614-72873 Loop Detec Wire Prefab (Install Only) Lin Foot ===============================================

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1,500.00 2.50 6.95 6.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,500.00 2.50 6.95 6.30 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,500.00 2.50 6.95 6.30

=============== 614-72875 Loop Detect Wire Lin Foot ===============================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 8,040.00 3.00 2.21 1.80

Page 440: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 396 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-72875 Loop Detect Wire Lin Foot ===============================================STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 3,320.00 3.00 2.20 2.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 3,096.00 4.00 2.23 2.10STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 9,420.00 3.00 2.16 2.05STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 1,376.00 2.50 2.62 2.50STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 3,750.00 2.50 2.11 2.06STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 375.00 4.00 2.91 3.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 14,400.00 2.50 2.11 2.02STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 450.00 3.00 3.67 2.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 44,227.00 2.86 2.18 2.02

NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 7,400.00 2.50 2.74 2.35NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 5,280.00 2.50 2.30 1.90NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 1,160.00 2.50 2.61 2.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 13,840.00 2.50 2.61 2.17

STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 5,664.00 2.60 2.02 2.00STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 3,186.00 2.50 2.35 2.20NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 3,894.00 2.50 2.01 1.96STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 1,062.00 3.00 2.18 2.10STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 6,726.00 2.50 2.04 2.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 4,776.00 3.00 2.28 2.27NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 1,062.00 3.00 2.12 2.25STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 3,540.00 3.00 2.23 2.00NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 3,375.00 2.65 2.11 2.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 33,285.00 2.69 2.13 2.06 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 91,352.00 2.74 2.22 2.06

=============== 614-72878 Detect Amp (Loop) (4) Each ===================================================

NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 20.00 800.00 1106.58 978.54 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 20.00 800.00 1106.58 978.54

NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 4.00 750.00 1164.85 1414.26

Page 441: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 397 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-72878 Detect Amp (Loop) (4) Each ===================================================STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 2.00 850.00 1056.31 1397.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 6.00 783.33 1133.84 1408.59 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 26.00 796.15 1111.12 1077.78

=============== 614-72882 Detect (Micro) Each ===================================================

STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 16.00 400.00 416.71 410.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 16.00 400.00 416.71 410.25

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 5.00 450.00 1799.60 2100.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 6.00 400.00 580.34 468.71 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 11.00 422.73 1189.97 1210.21 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 27.00 409.26 714.12 736.16

=============== 614-72885 Detect (Spec) Each ===================================================

C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 2.00 3500.00 5384.60 5000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 3500.00 5384.60 5000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 3500.00 5384.60 5000.00

=============== 614-72886 Intersection Detect Sys (Camera) Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 4.00 6000.00 6381.69 6200.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 5.00 5500.00 5921.09 5400.00C 0342-040 US 34 IN WELD COUNTY 01/29/04 4.00 6000.00 5453.73 4600.90STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 4.00 6000.00 5112.00 5130.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 1.00 10000.00 30535.35 27520.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 6.00 5000.00 5419.67 5150.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 16.00 5500.00 5456.20 5280.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1.00 20000.00 5875.69 5300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 41.00 6036.59 6266.20 5827.40

Page 442: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 398 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-72886 Intersection Detect Sys (Camera) Each ===================================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 8.00 10000.00 11235.78 10268.75STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 18.00 5120.00 4959.50 4669.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 4.00 5500.00 5018.79 4810.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 10000.00 23146.18 23300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 31.00 6585.81 7993.65 6733.29

STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 1.00 12000.00 15876.20 15813.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 4.00 12000.00 20557.48 20009.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 4.00 5500.00 5520.00 5500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 9.00 9111.11 13354.02 13094.33

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 6.00 6000.00 5707.24 5800.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 1.00 24000.00 15566.67 20000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 7.00 8571.43 6465.66 7828.57 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 88.00 6746.14 7341.52 7048.92

=============== 614-72887 Detect (Microwave Veh) Each ===================================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 1.00 13000.00 12820.98 11205.11 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 13000.00 12820.98 11205.11 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 13000.00 12820.98 11205.11

=============== 614-72889 Detect (Micro) (Non-Invasive) Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 40.00 600.00 568.45 600.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 16.00 500.00 488.30 512.81STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 8.00 1300.00 1207.90 988.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 64.00 662.50 607.67 626.70

Page 443: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 399 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-72889 Detect (Micro) (Non-Invasive) Each ===================================================

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 4.00 1000.00 931.83 1110.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4.00 1000.00 931.83 1110.00

STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 4.00 550.00 807.00 752.01 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4.00 550.00 807.00 752.01 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 72.00 675.00 625.30 660.51

=============== 614-72891 Tele Intercon Wire Lin Foot ===============================================

NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 800.00 2.00 1.65 1.12 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 800.00 2.00 1.65 1.12

C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 64.00 2.00 8.00 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 64.00 2.00 8.00 10.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 864.00 2.00 1.99 1.78

=============== 614-72895 Vehicle Detect Sys (Single Camera) Each ===================================================

IM 0701-157 FRUITA TO CLIFTON 02/26/04 1.00 6000.00 7500.00 7100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 6000.00 7500.00 7100.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 6000.00 7500.00 7100.00

=============== 614-72896 Inst Intersect Detect Sys (Camera) Each ===================================================

NH 2872-016 US 287 - LAMAR 03/04/04 13.00 500.00 817.50 800.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 13.00 500.00 817.50 800.00

Page 444: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 400 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-72896 Inst Intersect Detect Sys (Camera) Each ===================================================

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 4.00 400.00 227.57 109.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4.00 400.00 227.57 109.25 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 17.00 476.47 706.89 637.47

=============== 614-75216 Inst Ped Sig Face (16) Each ===================================================

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 20.00 200.00 105.99 97.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 20.00 200.00 105.99 97.75 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 20.00 200.00 105.99 97.75

=============== 614-75332 Inst Ped Sig Face (16-16) Each ===================================================

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 8.00 120.00 237.50 210.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 8.00 120.00 237.50 210.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8.00 120.00 237.50 210.00

=============== 614-75336 Inst Traf Sig Face (12-12-12) Each ===================================================

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 30.00 150.00 123.19 126.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 30.00 150.00 123.19 126.50

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 10.00 200.00 257.50 210.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 10.00 200.00 257.50 210.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 40.00 162.50 164.51 147.38

=============== 614-75560 Inst Traf Sig Face (12-12-12-12-12) Each ===================================================

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 12.00 200.00 181.60 172.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 12.00 200.00 181.60 172.50

Page 445: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 401 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-75560 Inst Traf Sig Face (12-12-12-12-12) Each ===================================================

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 2.00 350.00 351.25 310.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 350.00 351.25 310.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 14.00 221.43 212.44 192.14

=============== 614-75848 Inst Traf Sig Ctrler + Cab Each ===================================================

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 2.00 1000.00 4341.19 2932.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 1000.00 4341.19 2932.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 1000.00 4341.19 2932.50

=============== 614-75860 Inst Ped Push Button Each ===================================================

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 20.00 50.00 38.19 34.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 20.00 50.00 38.19 34.50

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 8.00 50.00 102.00 53.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 8.00 50.00 102.00 53.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 28.00 50.00 60.39 39.79

=============== 614-75866 Inst Fire Preempt Unit + Timer Each ===================================================

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 4.00 670.00 478.75 105.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4.00 670.00 478.75 105.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 670.00 478.75 105.00

=============== 614-75869 Furn Fire Preempt Unit Emmitter Each ===================================================

C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 2.00 1000.00 1210.60 1100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 1000.00 1210.60 1100.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 1000.00 1210.60 1100.00

Page 446: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 402 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-80000 Flash Beacon Each ===================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 3.00 1600.00 1913.38 2240.00C 0342-040 US 34 IN WELD COUNTY 01/29/04 4.00 1500.00 1472.32 690.71NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 2.00 1500.00 3796.47 5578.80STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 2.00 1600.00 2062.88 2105.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 2.00 2000.00 1524.59 2000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 13.00 1615.38 1965.61 2219.26

NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 10.00 1200.00 1492.21 1349.32SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 2.00 2000.00 1568.58 1616.00STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 1.00 2000.00 2379.75 1900.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 1.00 1600.00 1597.74 1530.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 1.00 1800.00 2412.50 2250.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 15.00 1426.67 1610.47 1493.68

BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 1.00 2000.00 3150.60 2616.94STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 1.00 3500.00 2318.40 2973.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 2750.00 2630.48 2794.97

NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 8.00 1600.00 905.04 1185.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 8.00 1600.00 905.04 1185.20 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 38.00 1597.37 1679.64 1745.45

=============== 614-80001 Flash Beacon (Solar Pwred) Each ===================================================

C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 2.00 1200.00 3997.00 3500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 1200.00 3997.00 3500.00

SHE 105A-010 SH 105/FURROW RD 10/07/04 2.00 3000.00 4482.26 3500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 3000.00 4482.26 3500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 2100.00 4239.63 3500.00

Page 447: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 403 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-80313 Barricade (Ty 3 F-C) Each ===================================================

STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 2.00 1500.00 1493.75 1700.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 1500.00 1493.75 1700.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 1500.00 1493.75 1700.00

=============== 614-80314 Barricade (Ty 3 F-D) Each ===================================================

STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 1.00 1510.00 1193.33 1600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 1510.00 1193.33 1600.00

STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 1.00 750.00 2090.66 537.64 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 750.00 2090.66 537.64 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 1130.00 1706.09 1068.82

=============== 614-80385 Rumble Strip Lin Foot ===============================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 28,000.00 0.50 0.35 0.35 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 28,000.00 0.50 0.35 0.35

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 59,299.00 0.15 0.20 0.15NH 2852-010 US 285 & COUNTY RD. G 04/29/04 3,177.00 0.20 2.55 0.44 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 62,476.00 0.15 0.32 0.16

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 72,204.00 0.50 0.15 0.15 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 72,204.00 0.50 0.15 0.15

IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 149,683.00 0.18 0.11 0.11

Page 448: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 404 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-80385 Rumble Strip Lin Foot ===============================================NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 22,722.00 0.60 0.37 0.49IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 80,256.00 0.15 0.20 0.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 252,661.00 0.21 0.15 0.19 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 415,341.00 0.27 0.18 0.19

=============== 614-80387 Rumble Strip (Grind) Lin Foot ===============================================

IM 0701-164 PARACHUTE EAST & WEST 02/12/04 304,230.00 0.10 0.10 0.10IM 0701-157 FRUITA TO CLIFTON 02/26/04 317,480.00 0.13 0.10 0.09NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 52,821.00 0.15 0.17 0.15SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 182,160.00 0.15 0.14 0.11STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 10,440.00 0.66 0.38 0.25STA 0063-016 CLIFTON TO PALISADE 03/25/04 12,772.00 0.50 0.52 0.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 879,903.00 0.14 0.12 0.11

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 45,900.00 0.25 0.17 0.20ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 22,882.00 2.00 2.20 2.34SHE 1601-052 R-5, CENTERLINE RUMBLE STRIPS 04/22/04 409,340.00 0.14 0.15 0.10STA 0343-023 US 34, EAST OF AKRON 06/17/04 70,000.00 0.15 0.18 0.16IM 0761-185 I-76, LOCHBUIE TO HUDSON 06/24/04 100,000.00 0.10 0.10 0.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 648,122.00 0.21 0.20 0.19 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,528,025.00 0.17 0.15 0.14

=============== 614-80391 Rumble Strip (Grind)(Asphalt) Lin Foot ===============================================

NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 24,488.00 0.30 0.38 0.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 24,488.00 0.30 0.38 0.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 24,488.00 0.30 0.38 0.50

=============== 614-81000 Sig-Light Pole Steel Each ===================================================

NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 1.00 15000.00 4903.90 1230.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 15000.00 4903.90 1230.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 15000.00 4903.90 1230.00

Page 449: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 405 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-81010 Sig-Light Pole Steel (1) Each ===================================================

C 074A-007 SH 74 @ BRYANT DR. 02/26/04 1.00 10000.00 17512.48 16496.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 3.00 14000.00 15700.00 16000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 13000.00 16675.95 16124.00

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 4.00 11000.00 25633.28 23800.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4.00 11000.00 25633.28 23800.00

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 8.00 20000.00 24811.03 24551.15 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 8.00 20000.00 24811.03 24551.15 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 16.00 16000.00 23693.86 22256.58

=============== 614-81011 Inst Sig-Light Pole Steel (1) Each ===================================================

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 8.00 4000.00 1782.47 586.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 8.00 4000.00 1782.47 586.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8.00 4000.00 1782.47 586.50

=============== 614-81020 Sig-Light Pole Steel (2) Each ===================================================

C 074A-007 SH 74 @ BRYANT DR. 02/26/04 2.00 13000.00 34273.59 32312.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 3.00 15500.00 29950.00 30000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5.00 14500.00 32976.51 30924.80

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 35000.00 55549.57 54411.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 35000.00 55549.57 54411.00

Page 450: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 406 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-81020 Sig-Light Pole Steel (2) Each ===================================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 2.00 20000.00 46516.75 48000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 20000.00 46516.75 48000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8.00 18437.50 40418.35 38129.38

=============== 614-81125 Sig-Light Pole Steel (1-25 Ft) Each ===================================================

STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 2.00 9000.00 13513.02 14558.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 9000.00 13513.02 14558.00

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 1.00 13000.00 15400.22 14196.26 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 13000.00 15400.22 14196.26 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 10333.33 13948.53 14437.42

=============== 614-81130 Sig-Light Pole Steel (1-30 Ft) Each ===================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 1.00 10000.00 7355.41 2590.00C 0342-040 US 34 IN WELD COUNTY 01/29/04 1.00 9000.00 13690.05 13359.48STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 2.00 9000.00 12472.18 12925.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 9250.00 10992.73 10449.87 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 9250.00 10992.73 10449.87

=============== 614-81135 Sig-Light Pole Steel (1-35 Ft) Each ===================================================

C 0342-040 US 34 IN WELD COUNTY 01/29/04 1.00 10500.00 13848.59 13415.29 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 10500.00 13848.59 13415.29

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 1.00 14000.00 16039.46 14861.07

Page 451: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 407 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-81135 Sig-Light Pole Steel (1-35 Ft) Each ===================================================SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 2.00 15000.00 14337.78 13740.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3.00 14666.67 14730.48 14113.69 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 13625.00 14394.52 13939.09

=============== 614-81140 Sig-Light Pole Steel (1-40 Ft) Each ===================================================

STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 1.00 10000.00 13981.05 14550.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 10000.00 13981.05 14550.00

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 1.00 15000.00 19154.86 22600.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 2.00 15000.00 20791.40 19800.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 3.00 15000.00 20413.74 20733.33 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 13750.00 18626.88 19187.50

=============== 614-81145 Sig-Light Pole Steel (1-45 Ft) Each ===================================================

STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 4.00 11000.00 15953.31 17699.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 11000.00 15953.31 17699.00

SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 1.00 17500.00 16232.06 15555.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 17500.00 16232.06 15555.00

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 1.00 18000.00 19196.99 22700.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1.00 16700.00 21230.00 20400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 17350.00 20467.62 21550.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 7.00 13742.86 17089.92 18493.00

Page 452: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 408 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-81150 Sig-Light Pole Steel (1-50 Ft) Each ===================================================

STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 3.00 12000.00 16378.42 17254.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3.00 12000.00 16378.42 17254.00

C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1.00 19000.00 21375.40 20400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 19000.00 21375.40 20400.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 13750.00 17627.66 18040.50

=============== 614-81155 Sig-Light Pole Steel (1-55 Ft) Each ===================================================

C 0342-040 US 34 IN WELD COUNTY 01/29/04 2.00 13000.00 15545.19 15223.45NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 1.00 13000.00 16238.63 17700.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 2.00 14000.00 14755.20 14684.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1.00 15000.00 15597.55 14800.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 6.00 13666.67 15458.71 15385.82

SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 1.00 18000.00 16646.08 15950.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 18000.00 16646.08 15950.00

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 1.00 20000.00 20622.53 23300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 20000.00 20622.53 23300.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8.00 15000.00 15914.63 16445.61

=============== 614-81160 Sig-Light Pole Steel (1-60 Ft) Each ===================================================

STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 2.00 15000.00 22212.88 24079.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 15000.00 22212.88 24079.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 15000.00 22212.88 24079.00

Page 453: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 409 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-81170 Sig-Light Pole Steel (1-70 Ft) Each ===================================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1.00 20000.00 35844.88 38000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 20000.00 35844.88 38000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 20000.00 35844.88 38000.00

=============== 614-81175 Sig-Light Pole Steel (1-75 Ft) Each ===================================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1.00 23000.00 38099.81 39000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 23000.00 38099.81 39000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 23000.00 38099.81 39000.00

=============== 614-81240 Sig-Light Pole Steel (2-40 Ft) Each ===================================================

NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 1.00 18000.00 18340.62 2260.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 18000.00 18340.62 2260.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 18000.00 18340.62 2260.00

=============== 614-81265 Sig-Light Pole Steel (2-65 Ft) Each ===================================================

NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 1.00 21000.00 27578.03 14300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 21000.00 27578.03 14300.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 21000.00 27578.03 14300.00

=============== 614-81302 Inst Sig-Light Pole (2) Each ===================================================

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 2.00 2400.00 3150.00 1600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 2400.00 3150.00 1600.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 2400.00 3150.00 1600.00

=============== 614-82010 Sig Pole Steel (1) Each ===================================================

NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 1.00 10000.00 17026.62 24300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 10000.00 17026.62 24300.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 10000.00 17026.62 24300.00

Page 454: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 410 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-84000 Traf Sig Ped Pole Steel Each ===================================================

C 074A-007 SH 74 @ BRYANT DR. 02/26/04 1.00 1400.00 1425.67 940.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 1.00 1000.00 12663.31 31500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 1200.00 6612.27 16220.00

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 1.00 2500.00 2428.71 1716.66 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 2500.00 2428.71 1716.66

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 1.00 1500.00 1267.51 1300.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 3.00 1500.00 658.07 655.91 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4.00 1500.00 759.65 816.93 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 7.00 1557.14 3144.69 5346.34

=============== 614-84100 Traf Sig Ped Pole Alum Each ===================================================

NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 10.00 800.00 913.59 920.91 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 10.00 800.00 913.59 920.91

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 8.00 1000.00 1414.93 1475.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 8.00 1000.00 1414.93 1475.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 18.00 888.89 1117.53 1167.17

=============== 614-84450 Inst Traf Sig Ped Pole Steel Each ===================================================

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 5.00 700.00 279.63 138.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 5.00 700.00 279.63 138.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5.00 700.00 279.63 138.00

Page 455: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 411 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-84455 Inst Traf Sig Ped Pole Each ===================================================

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 2.00 500.00 1212.50 1100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 500.00 1212.50 1100.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 500.00 1212.50 1100.00

=============== 614-85001 Impact Atten Each ===================================================

NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 2.00 2000.00 7368.14 2575.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 2000.00 7368.14 2575.60 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 2000.00 7368.14 2575.60

=============== 614-85005 Impact Atten (Sand Fill) Each ===================================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 5.00 16000.00 3325.00 1550.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5.00 16000.00 3325.00 1550.00

NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 2.00 8000.00 8144.92 5682.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 8000.00 8144.92 5682.70

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 4.00 3000.00 4132.89 2000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4.00 3000.00 4132.89 2000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 11.00 9818.18 4839.28 2465.04

=============== 614-85045 Truck w/Mtd Atten & Flash Arrow Panel Each ===================================================

C 0342-040 US 34 IN WELD COUNTY 01/29/04 1.00 8250.00 8930.06 5579.28SHE R300-113 DOWD BRIDGE, I-70 03/18/04 1.00 5000.00 7202.50 8280.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 6625.00 8354.21 6929.64 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 6625.00 8354.21 6929.64

Page 456: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 412 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-85115 Impact Atten (Quadguard) Each ===================================================

SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 3.00 20000.00 13733.33 12500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3.00 20000.00 13733.33 12500.00

STA 0703-290 GEORGETOWN HILL ROCKFALL MITI 10/07/04 1.00 25000.00 15500.00 23000.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 3.00 25000.00 30381.83 28000.00STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 2.00 25000.00 18674.75 14000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 6.00 25000.00 25487.35 22500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 9.00 23333.33 22774.88 19166.67

=============== 614-85312 Span Wire Pole (12 In) Each ===================================================

SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 1.00 3500.00 3481.25 2625.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 3500.00 3481.25 2625.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 3500.00 3481.25 2625.00

=============== 614-85362 Sig-Light Span Wire Pole (12 In) Each ===================================================

STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 4.00 3000.00 5050.10 4810.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4.00 3000.00 5050.10 4810.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 3000.00 5050.10 4810.50

=============== 614-85366 Sig-Light Span Wire Pole (16 In) Each ===================================================

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 4.00 5000.00 7295.49 7195.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4.00 5000.00 7295.49 7195.75 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 5000.00 7295.49 7195.75

=============== 614-85520 Paint Traf Sig Pole Each ===================================================

C 074A-007 SH 74 @ BRYANT DR. 02/26/04 1.00 500.00 456.83 250.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 500.00 456.83 250.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 500.00 456.83 250.00

Page 457: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 413 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-86000 Traf Sig Ctrler (M) Each ===================================================

C 0342-040 US 34 IN WELD COUNTY 01/29/04 1.00 4200.00 3198.77 2516.34 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 4200.00 3198.77 2516.34 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 4200.00 3198.77 2516.34

=============== 614-86002 Spread Spectrum Radio Each ===================================================

NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 2.00 2200.00 2841.50 2657.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 2200.00 2841.50 2657.00

C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1.00 2275.00 3228.40 3500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 2275.00 3228.40 3500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 2225.00 2943.32 2938.00

=============== 614-86005 Telemetry (Master) LUMP SUM ===============================================

C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1.00 3000.00 384.20 450.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 3000.00 384.20 450.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 3000.00 384.20 450.00

=============== 614-86105 Telemetry (Field) Each ===================================================

C 0342-040 US 34 IN WELD COUNTY 01/29/04 1.00 2500.00 3008.23 2684.15NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 1.00 2550.00 6498.12 12600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 2525.00 4503.90 7642.08

NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 5.00 300.00 647.29 347.07

Page 458: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 414 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-86105 Telemetry (Field) Each ===================================================SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 1.00 2440.00 3300.54 3160.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 6.00 656.67 978.95 815.89

C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1.00 2200.00 3228.30 3500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 2200.00 3228.30 3500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 9.00 1243.33 2006.00 2631.06

=============== 614-86240 Ctrler (Ty 170) Each ===================================================

C 074A-007 SH 74 @ BRYANT DR. 02/26/04 1.00 10000.00 16275.08 15430.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 3.00 20000.00 2000.00 2000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 17500.00 9686.58 5357.50

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 10000.00 23571.29 19200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 10000.00 23571.29 19200.00

STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 1.00 16000.00 23402.80 20859.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 4.00 12000.00 23692.25 21902.90 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 5.00 12800.00 23634.36 21694.12 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10.00 14400.00 19504.82 14910.06

=============== 614-86245 Ctrler (Ty 170E) Each ===================================================

NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 5.00 7200.00 8357.85 7981.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 2.00 7500.00 7624.49 8187.95 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 7.00 7285.71 8250.53 8040.13

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 1.00 5000.00 6326.49 3350.00

Page 459: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 415 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-86245 Ctrler (Ty 170E) Each ===================================================NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 10000.00 5875.00 630.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 7500.00 6068.49 1990.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 9.00 7333.33 7932.32 6695.66

=============== 614-86246 Ctrler (Ty 170E-HC11) Each ===================================================

C 0342-040 US 34 IN WELD COUNTY 01/29/04 1.00 17500.00 14656.83 12582.65NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 2.00 17750.00 9175.47 5460.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 3.00 18500.00 13771.08 17051.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 6.00 18083.33 12397.90 12442.61

SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 1.00 18000.00 16707.78 16000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 18000.00 16707.78 16000.00

C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1.00 17000.00 1465.60 1450.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 17000.00 1465.60 1450.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 2.00 16000.00 16434.06 16500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 16000.00 16434.06 16500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10.00 17550.00 12666.70 12510.57

=============== 614-86247 Ctrler (Ty 170E-HC11 W/W70SM Firmware) Each ===================================================

SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 1.00 2400.00 3443.66 3300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 2400.00 3443.66 3300.00

C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1.00 5000.00 3165.40 3200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 5000.00 3165.40 3200.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 3700.00 3304.53 3250.00

Page 460: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 416 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-86720 ML WIM Sorter System LUMP SUM ===============================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 1.00 250000.00 269535.51 250695.82 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 250000.00 269535.51 250695.82 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 250000.00 269535.51 250695.82

=============== 614-86732 WIM Station (Type 2) Each ===================================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 2.00 50000.00 69200.00 69000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 50000.00 69200.00 69000.00

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 1.00 100000.00 61045.96 63000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 100000.00 61045.96 63000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 66666.67 65705.41 67000.00

=============== 614-86740 Weather Monitor System LUMP SUM ===============================================

SHE R300-113 DOWD BRIDGE, I-70 03/18/04 1.00 35000.00 39197.00 35300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 35000.00 39197.00 35300.00

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 1.00 19375.00 27134.40 25000.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 1.00 50000.00 44103.15 39483.18 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 34687.50 33497.68 32241.59 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 34791.67 35397.45 33261.06

=============== 614-86755 Deicing System LUMP SUM ===============================================

SHE R300-113 DOWD BRIDGE, I-70 03/18/04 1.00 290000.00 230443.00 225850.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 290000.00 230443.00 225850.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 290000.00 230443.00 225850.00

Page 461: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 417 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-86756 Anti-Icing Syst LUMP SUM ===============================================

SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 1.00 800000.00 530200.00 614500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 800000.00 530200.00 614500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 800000.00 530200.00 614500.00

=============== 614-86800 Uninterrupted Power Supply Each ===================================================

STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 1.00 5000.00 5064.19 2971.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 5000.00 5064.19 2971.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 5000.00 5064.19 2971.00

=============== 614-87010 Fiber Optic Cable (S Mode) (12 Fiber) Lin Foot ===============================================

NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 5,600.00 3.00 2.59 1.69AQC R600-215 SH 287, US 36 TO SH 128 05/27/04 1,170.00 5.00 5.81 13.11 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 6,770.00 3.35 3.49 3.66 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6,770.00 3.35 3.49 3.66

=============== 614-87020 Optic Transceiver Each ===================================================

NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 2.00 3000.00 1685.78 1077.32ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 61.00 2000.00 2245.43 2216.05AQC R600-215 SH 287, US 36 TO SH 128 05/27/04 14.00 3000.00 2854.11 2249.41 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 77.00 2207.79 2517.05 2192.54 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 77.00 2207.79 2517.05 2192.54

=============== 614-87028 Video Optic Transceiver Each ===================================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 11.00 2500.00 3174.56 3308.47 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 11.00 2500.00 3174.56 3308.47 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 11.00 2500.00 3174.56 3308.47

Page 462: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 418 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-87100 Auto Traf Rec Sta Each ===================================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 1.00 30000.00 8193.31 4460.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 30000.00 8193.31 4460.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 30000.00 8193.31 4460.00

=============== 614-87300 TMS Building Each ===================================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 1.00 70000.00 98877.87 60863.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 70000.00 98877.87 60863.40 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 70000.00 98877.87 60863.40

=============== 614-87318 Master Computer and Software LUMP SUM ===============================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 1.00 40000.00 48318.74 49304.56 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 40000.00 48318.74 49304.56 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 40000.00 48318.74 49304.56

=============== 614-87320 CCTV Each ===================================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 6.00 4000.00 4301.18 3818.27 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 6.00 4000.00 4301.18 3818.27 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6.00 4000.00 4301.18 3818.27

=============== 614-87350 Test Fiber Optic Cable LUMP SUM ===============================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 1.00 40000.00 34525.75 5243.62AQC R600-215 SH 287, US 36 TO SH 128 05/27/04 1.00 2500.00 3543.14 1911.76 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 21250.00 9352.38 3577.69 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 21250.00 9352.38 3577.69

Page 463: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 419 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-87406 Fiber Optic Cable (S Mode) (6 S) Lin Foot ===============================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 23,660.00 2.00 3.63 3.90 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 23,660.00 2.00 3.63 3.90 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 23,660.00 2.00 3.63 3.90

=============== 614-87424 Fiber Optic Cable (S Mode) (24 S) Lin Foot ===============================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 319.00 2.00 32.55 2.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 319.00 2.00 32.55 2.60

STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 5,725.00 8.00 4.68 4.55 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 5,725.00 8.00 4.68 4.55

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 3,000.00 3.00 2.97 3.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3,000.00 3.00 2.97 3.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 9,044.00 6.13 4.59 3.97

=============== 614-87448 Fiber Optic Cable (S Mode) (48 S) Lin Foot ===============================================

AQC R600-215 SH 287, US 36 TO SH 128 05/27/04 32,190.00 4.00 1.70 1.09 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 32,190.00 4.00 1.70 1.09 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 32,190.00 4.00 1.70 1.09

=============== 614-87496 Fiber Optic Cable (S Mode) (96 S) Lin Foot ===============================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 14,000.00 3.00 2.25 2.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 14,000.00 3.00 2.25 2.25 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 14,000.00 3.00 2.25 2.25

Page 464: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 420 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 614-87498 Fiber Optic Cable (S Mode) (144 S) Lin Foot ===============================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 295,380.00 2.00 2.11 2.03 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 295,380.00 2.00 2.11 2.03 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 295,380.00 2.00 2.11 2.03

=============== 614-87660 Video Encoder/Decoder Each ===================================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 5.00 6000.00 5909.39 5685.78 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 5.00 6000.00 5909.39 5685.78 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5.00 6000.00 5909.39 5685.78

=============== 614-87670 Tier II Multi Each ===================================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 6.00 60000.00 66802.46 86339.37 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 6.00 60000.00 66802.46 86339.37 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6.00 60000.00 66802.46 86339.37

=============== 614-87680 Sonet Multi Each ===================================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 2.00 70000.00 144020.50 186572.91 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 70000.00 144020.50 186572.91 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 70000.00 144020.50 186572.91

=============== 614-87690 Ethernet Switch Each ===================================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 1.00 3000.00 9306.29 11953.23 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 3000.00 9306.29 11953.23 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 3000.00 9306.29 11953.23

=============== 614-87700 Ethernet Router Each ===================================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 2.00 20000.00 19821.31 19244.90 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 20000.00 19821.31 19244.90 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 20000.00 19821.31 19244.90

Page 465: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 421 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 615-00030 Emb Prot Ty 3 Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 8.00 720.00 817.90 350.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 1.00 1200.00 2792.50 305.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 1.00 1400.00 1863.23 1230.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 10.00 836.00 1056.32 433.50

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 6.00 1000.00 935.00 500.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 6.00 1000.00 770.94 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 12.00 1000.00 852.97 500.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 38.00 1000.00 1330.93 1000.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 3.00 700.00 1919.80 1039.39 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 41.00 978.05 1353.30 1002.88

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 3.00 500.00 980.67 900.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 4.00 1500.00 1076.67 1500.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 5.00 730.00 1416.67 2000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 12.00 929.17 1217.87 1558.33 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 75.00 954.80 1213.07 935.38

=============== 615-00050 Emb Prot Ty 5 Each ===================================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 108.00 1000.00 738.04 100.00C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 1.00 1600.00 565.33 147.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 4.00 1060.00 470.00 680.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 113.00 1007.43 730.91 120.95

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 2.00 1250.00 1090.00 550.00

Page 466: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 422 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 615-00050 Emb Prot Ty 5 Each ===================================================IM 0253-186 I-25, 120TH TO SH 7 06/17/04 2.00 1500.00 1176.61 1100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4.00 1375.00 1124.64 825.00

BR 0243-063 EAST OF LIMON 07/15/04 1.00 1700.00 1144.26 1600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 1700.00 1144.26 1600.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 3.00 800.00 1201.49 1300.00C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 1.00 1200.00 1542.20 650.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4.00 900.00 1275.56 1137.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 122.00 1021.64 774.90 189.48

=============== 615-00150 Emb Prot (Spec) Each ===================================================

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 26.00 1800.00 715.82 650.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 26.00 1800.00 715.82 650.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 4.00 3500.00 2434.24 2000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4.00 3500.00 2434.24 2000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 30.00 2026.67 944.94 830.00

=============== 616-00180 18 In Conc Siphon Pipe Lin Foot ===============================================

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 144.00 68.00 72.25 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 144.00 68.00 72.25 100.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 144.00 68.00 72.25 100.00

=============== 616-00240 24 In Conc Siphon Pipe Lin Foot ===============================================

NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 457.00 55.00 87.22 68.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 457.00 55.00 87.22 68.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 457.00 55.00 87.22 68.00

Page 467: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 423 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 616-30018 18 In Trash Guard Each ===================================================

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 2.00 700.00 1475.00 650.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 700.00 1475.00 650.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 700.00 1475.00 650.00

=============== 616-30024 24 In Trash Guard Each ===================================================

NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 3.00 650.00 709.93 400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3.00 650.00 709.93 400.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 650.00 709.93 400.00

=============== 616-50048 6 In Valve and Box Each ===================================================

NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 3.00 700.00 834.80 790.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3.00 700.00 834.80 790.00

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 750.00 1112.50 1400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 750.00 1112.50 1400.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 712.50 885.29 942.50

=============== 617-00012 12 In Culvert Pipe Lin Foot ===============================================

BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 120.00 35.00 47.38 30.82 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 120.00 35.00 47.38 30.82 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 120.00 35.00 47.38 30.82

=============== 617-00015 15 In Culvert Pipe Lin Foot ===============================================

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1,959.00 24.00 30.36 35.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,959.00 24.00 30.36 35.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,959.00 24.00 30.36 35.00

Page 468: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 424 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 617-00018 18 In Culvert Pipe Lin Foot ===============================================

STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 43.00 60.00 49.82 38.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 43.00 60.00 49.82 38.00

BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 112.00 50.00 41.57 42.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 112.00 50.00 41.57 42.00

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 206.00 55.00 39.09 50.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 206.00 55.00 39.09 50.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 361.00 54.04 41.14 46.09

=============== 617-00024 24 In Culvert Pipe Lin Foot ===============================================

STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 2.50 60.00 79.00 77.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 170.00 40.00 58.43 48.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 172.50 40.29 58.51 48.42

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 2,206.00 25.00 51.99 55.00BR 0243-063 EAST OF LIMON 07/15/04 20.00 90.00 113.63 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2,226.00 25.58 52.22 55.40 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,398.50 26.64 52.67 54.90

=============== 617-00036 36 In Culvert Pipe Lin Foot ===============================================

BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 102.00 60.00 70.43 70.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 102.00 60.00 70.43 70.00

Page 469: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 425 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 617-00036 36 In Culvert Pipe Lin Foot ===============================================

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 416.00 60.00 64.87 65.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 416.00 60.00 64.87 65.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 518.00 60.00 65.97 65.98

=============== 617-00048 48 In Culvert Pipe Lin Foot ===============================================

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 276.00 90.00 88.40 90.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 276.00 90.00 88.40 90.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 276.00 90.00 88.40 90.00

=============== 617-03000 Detour Culvert Pipe LUMP SUM ===============================================

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 1.00 6000.00 8350.30 2500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 6000.00 8350.30 2500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 6000.00 8350.30 2500.00

=============== 617-03010 Detour Culvert Pipe Lin Foot ===============================================

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 490.00 50.00 48.01 46.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 195.00 60.00 71.71 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 685.00 52.85 55.53 49.99 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 685.00 52.85 55.53 49.99

=============== 618-00002 Prestress Steel W or S M Kip Foot =============================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 14,096.00 55.00 70.35 75.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 14,096.00 55.00 70.35 75.00

Page 470: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 426 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 618-00002 Prestress Steel W or S M Kip Foot =============================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 12,151.00 30.00 29.36 30.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 12,151.00 30.00 29.36 30.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 26,247.00 43.43 51.37 54.17

=============== 618-00005 Prestress Steel Bar M Kip Foot =============================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 269.00 310.00 279.23 236.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 11.00 350.00 2195.75 450.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 280.00 311.57 372.42 244.41 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 280.00 311.57 372.42 244.41

=============== 618-00007 Grout (Strand)(Duct) Cubic Foot =============================================

BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 45.00 100.00 180.75 125.81 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 45.00 100.00 180.75 125.81 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 45.00 100.00 180.75 125.81

=============== 618-00163 Prestress Conc I (BT63) Lin Foot ===============================================

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1,554.00 125.00 148.39 140.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,554.00 125.00 148.39 140.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,554.00 125.00 148.39 140.00

=============== 618-00172 Prestress Conc I (BT72) Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 2,701.00 130.00 133.53 120.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,701.00 130.00 133.53 120.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,701.00 130.00 133.53 120.00

Page 471: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 427 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 618-00184 Prestress Conc I (BT84) Lin Foot ===============================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1,435.00 130.00 145.00 150.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,435.00 130.00 145.00 150.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,435.00 130.00 145.00 150.00

=============== 618-01994 Prestress Conc Box (Depth 32" Thru 48") Sq Foot ================================================

BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 9,416.00 35.00 52.24 49.65 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 9,416.00 35.00 52.24 49.65

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 39,120.00 30.00 38.15 37.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 39,120.00 30.00 38.15 37.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 48,536.00 30.97 41.24 39.45

=============== 618-06034 Prestress Conc Slab (Depth 6" Thru 13") Sq Foot ================================================

BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 17,969.00 18.00 45.57 40.21 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 17,969.00 18.00 45.57 40.21 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 17,969.00 18.00 45.57 40.21

=============== 618-10000 Precast Conc U Girder (Pre-Ten) Lin Foot ===============================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 12,626.00 400.00 421.77 375.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 12,626.00 400.00 421.77 375.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 12,626.00 400.00 421.77 375.00

=============== 619-06060 6 In Duct Iron Pipe Lin Foot ===============================================

SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 6.00 80.00 149.50 148.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 6.00 80.00 149.50 148.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6.00 80.00 149.50 148.00

Page 472: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 428 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 619-10140 14 In Weld Steel Pipe Lin Foot ===============================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 311.00 40.00 88.26 90.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 311.00 40.00 88.26 90.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 311.00 40.00 88.26 90.00

=============== 619-10665 66 In Weld Steel Pipe (J) Lin Foot ===============================================

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 196.00 800.00 1600.00 2000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 196.00 800.00 1600.00 2000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 196.00 800.00 1600.00 2000.00

=============== 619-30160 2 In Galv Pipe Lin Foot ===============================================

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 1,242.00 10.00 8.78 8.85 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,242.00 10.00 8.78 8.85 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,242.00 10.00 8.78 8.85

=============== 619-40060 3/4 In Copper Pipe Lin Foot ===============================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 233.00 20.00 43.30 80.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 233.00 20.00 43.30 80.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 233.00 20.00 43.30 80.00

=============== 619-40080 1 In Copper Pipe Lin Foot ===============================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 10.00 30.00 34.18 4.71 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 10.00 30.00 34.18 4.71 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10.00 30.00 34.18 4.71

=============== 619-50060 3/4 In Plastic Pipe Lin Foot ===============================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1,370.00 2.00 1.36 0.15 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,370.00 2.00 1.36 0.15 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,370.00 2.00 1.36 0.15

Page 473: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 429 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 619-50080 1 In Plastic Pipe Lin Foot ===============================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 2,690.00 2.00 1.60 0.91 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2,690.00 2.00 1.60 0.91 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,690.00 2.00 1.60 0.91

=============== 619-50120 1-1/2 In Plastic Pipe Lin Foot ===============================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1,030.00 2.00 1.71 1.21 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,030.00 2.00 1.71 1.21 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,030.00 2.00 1.71 1.21

=============== 619-50160 2 In Plastic Pipe Lin Foot ===============================================

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 120.00 3.00 9.25 10.23 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 120.00 3.00 9.25 10.23

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 1,092.00 5.00 18.87 22.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,092.00 5.00 18.87 22.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,212.00 4.80 16.96 20.83

=============== 619-50240 3 In Plastic Pipe Lin Foot ===============================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 440.00 15.00 12.63 6.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 440.00 15.00 12.63 6.50 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 440.00 15.00 12.63 6.50

=============== 619-50320 4 In Plastic Pipe Lin Foot ===============================================

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 120.00 6.00 13.98 16.36 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 120.00 6.00 13.98 16.36

Page 474: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 430 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 619-50320 4 In Plastic Pipe Lin Foot ===============================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 302.00 13.00 21.39 12.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 302.00 13.00 21.39 12.00

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 150.00 8.00 5.91 14.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 150.00 8.00 5.91 14.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 572.00 10.22 15.40 13.44

=============== 619-50480 6 In Plastic Pipe Lin Foot ===============================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 440.00 18.00 18.90 8.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 440.00 18.00 18.90 8.70 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 440.00 18.00 18.90 8.70

=============== 619-51280 16 In Plastic Pipe Lin Foot ===============================================

SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 8.00 100.00 144.25 77.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 8.00 100.00 144.25 77.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8.00 100.00 144.25 77.00

=============== 619-75016 2 In Gate Valve Each ===================================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 2.00 200.00 339.22 350.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 200.00 339.22 350.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 200.00 339.22 350.00

=============== 620-00001 Field Office (CL 1) Each ===================================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 1.00 4500.00 7283.25 8000.00

Page 475: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 431 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 620-00001 Field Office (CL 1) Each ===================================================STA 114A-009 S.H. 114, W OF COCHETOPA PASS 01/08/04 1.00 5000.00 7666.67 5000.00IM 0704-203 I-70, GENOA-EAST, M.P. 374 - 01/15/04 1.00 8000.00 11916.67 7500.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 1.00 4000.00 14593.56 3200.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 1.00 10000.00 27583.33 20000.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 1.00 4000.00 6333.33 3000.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 1.00 7000.00 8700.00 6000.00STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 1.00 5000.00 6000.00 5000.00STA 014A-030 SH 14, WALDEN EAST 03/04/04 1.00 3000.00 7583.33 6000.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 1.00 8000.00 10625.00 8500.00STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 1.00 8000.00 8000.00 8000.00STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 1.00 3000.00 8683.33 7600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 12.00 5791.67 11390.86 7316.67

STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 1.00 8000.00 7500.00 8000.00STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 1.00 12000.00 4138.50 3027.00BR 0092-018 SH 9, SOUTH OF KREMMLING 05/27/04 1.00 5000.00 2875.00 2000.00IM 0702-239 HANGING LAKES REST AREAS 06/17/04 1.00 7500.00 7073.07 10178.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4.00 8125.00 5291.35 5801.25

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 1.00 8000.00 8400.00 10100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 8000.00 8400.00 10100.00

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 1.00 6000.00 8540.00 7000.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 1.00 5000.00 16664.64 20323.20NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 1.00 4000.00 7000.00 8000.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 1.00 5000.00 22487.54 21950.15 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4.00 5000.00 13939.61 14318.34 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 21.00 6190.48 10920.87 8494.21

=============== 620-00002 Field Office (CL 2) Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 1.00 10000.00 14240.86 9800.00

Page 476: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 432 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 620-00002 Field Office (CL 2) Each ===================================================STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 1.00 10000.00 17323.89 18000.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 1.00 7000.00 14051.16 16000.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 1.00 18000.00 15032.64 13000.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 1.00 15000.00 53183.33 40000.00STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 1.00 10000.00 9200.00 4000.00STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 1.00 4000.00 8533.33 5000.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 1.00 5000.00 10879.23 11760.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 1.00 12000.00 14155.78 15000.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 1.00 8000.00 12538.66 10000.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 1.00 12000.00 19500.00 10000.00IM 0701-164 PARACHUTE EAST & WEST 02/12/04 1.00 7000.00 13400.00 10000.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 1.00 7500.00 8988.42 8417.39IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 17500.00 27675.00 35000.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 1.00 7000.00 12833.33 15000.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 1.00 5000.00 13897.69 16000.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 1.00 12000.00 8484.68 4384.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1.00 10000.00 17555.01 7500.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 1.00 3000.00 9133.33 7400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 19.00 9473.68 16002.69 13487.44

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 1.00 12000.00 10613.33 7500.00NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 1.00 7000.00 10900.00 9000.00NH 0502-053 CIMARRON - WEST 04/15/04 1.00 15000.00 10373.20 10000.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 1.00 7000.00 11225.00 6900.00STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 1.00 5000.00 7503.43 7000.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 1.00 5000.00 14528.18 5630.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 1.00 5000.00 15040.00 8200.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 1.00 13000.00 10949.75 11500.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 1.00 5000.00 16000.00 12000.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 30000.00 27786.45 37500.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 1.00 15000.00 22154.65 10000.00STA 0343-023 US 34, EAST OF AKRON 06/17/04 1.00 4000.00 11240.00 8200.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 1.00 4000.00 9500.00 9500.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 1.00 5000.00 14857.14 12500.00IM 0761-185 I-76, LOCHBUIE TO HUDSON 06/24/04 1.00 10000.00 13653.03 17265.15 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 15.00 9466.67 13792.21 11513.01

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 1.00 12000.00 11642.86 10000.00IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1.00 12000.00 32166.89 49400.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 1.00 13000.00 19938.81 38262.64

Page 477: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 433 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 620-00002 Field Office (CL 2) Each ===================================================STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 10000.00 40474.08 26000.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1.00 7000.00 12850.40 9000.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 1.00 15000.00 21916.67 15000.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 15000.00 18450.00 14000.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 1.00 17000.00 22510.55 25000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 8.00 12625.00 22446.82 23332.83

STA 0703-290 GEORGETOWN HILL ROCKFALL MITI 10/07/04 1.00 5000.00 8750.00 2500.00BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 1.00 7000.00 10811.13 9000.00NH 2873-137 US 287 IN BOULDER & LARIMER C 11/18/04 1.00 3000.00 8377.44 5000.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 35000.00 44396.21 35000.00C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 1.00 9000.00 14538.19 10000.00IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 1.00 8500.00 9271.43 5400.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 1.00 7500.00 15849.20 27395.20STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 1.00 6000.00 20134.90 12000.00STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 1.00 7500.00 13928.91 18080.65STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 1.00 10000.00 19266.36 5695.00NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 1.00 9000.00 11666.67 7000.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 1.00 15000.00 16000.00 20000.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 1.00 7500.00 12125.00 10000.00STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 1.00 10000.00 21297.98 24726.20NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 1.00 5000.00 14220.65 22200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 15.00 9666.67 15306.44 14266.47 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 57.00 9964.91 16081.00 14554.67

=============== 620-00005 Field Office (Spec) Each ===================================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 40000.00 121221.14 130000.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 1.00 14000.00 19790.65 12000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 27000.00 77750.93 71000.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1.00 70000.00 89337.80 100000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 70000.00 89337.80 100000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 41333.33 83098.72 80666.67

Page 478: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 434 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 620-00011 Field Lab (CL 1) Each ===================================================

IM 0704-203 I-70, GENOA-EAST, M.P. 374 - 01/15/04 1.00 10000.00 8166.67 5000.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 1.00 4000.00 9423.11 3200.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 1.00 5000.00 9371.65 6000.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 1.00 8000.00 8869.90 12000.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 1.00 7000.00 8875.00 7500.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 1.00 10000.00 5323.74 2260.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 6.00 7333.33 8465.87 5993.33

STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 1.00 10000.00 7624.00 7000.00IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 1.00 11000.00 12233.33 10000.00STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 1.00 11000.00 3154.50 3159.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3.00 10666.67 8031.42 6719.67

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 1.00 9000.00 8650.00 10100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 9000.00 8650.00 10100.00

STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 1.00 6000.00 10489.98 7500.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 1.00 5000.00 8769.50 6047.49NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 1.00 12000.00 10000.00 7000.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 1.00 5000.00 12947.25 8114.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4.00 7000.00 10475.67 7165.37 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 14.00 8071.43 8896.16 6777.18

=============== 620-00012 Field Lab (CL 2) Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 1.00 10000.00 9442.31 6300.00STA 2911-001 SH 291 SALIDA NORTH 01/08/04 1.00 6000.00 8165.28 8000.00STA 114A-009 S.H. 114, W OF COCHETOPA PASS 01/08/04 1.00 6000.00 9833.33 7500.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 1.00 10000.00 12342.19 14000.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 1.00 10000.00 10730.81 5800.00

Page 479: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 435 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 620-00012 Field Lab (CL 2) Each ===================================================NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 1.00 8500.00 27950.00 30000.00STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 1.00 4000.00 7416.67 4500.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 1.00 5000.00 7489.38 7800.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 1.00 8000.00 11129.63 10000.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 1.00 10000.00 15125.00 10000.00IM 0701-164 PARACHUTE EAST & WEST 02/12/04 1.00 7000.00 12700.00 10000.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 1.00 5000.00 6000.00 3000.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 1.00 7500.00 6412.38 6959.06IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 13500.00 23200.00 30000.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 1.00 8000.00 9700.00 7500.00STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 1.00 5000.00 7250.00 7500.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 1.00 8500.00 12166.67 15000.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 1.00 9000.00 11016.67 10000.00STA 014A-030 SH 14, WALDEN EAST 03/04/04 1.00 3000.00 8033.33 6000.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 1.00 5000.00 11661.94 14000.00SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 1.00 2000.00 4298.00 8500.00STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 1.00 10000.00 8500.00 8000.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 1.00 10000.00 6250.00 4500.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1.00 10000.00 13821.47 5500.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 2.00 12000.00 13450.00 10000.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 1.00 3000.00 10666.67 8000.00STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 1.00 4000.00 8583.33 8500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 28.00 7571.43 11431.11 9887.82

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 1.00 12000.00 6983.33 5500.00NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 1.00 7000.00 10020.00 7100.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 1.00 5000.00 9395.28 8922.48NH 0502-053 CIMARRON - WEST 04/15/04 1.00 15000.00 11126.60 10000.00NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 1.00 8000.00 3920.81 4500.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 1.00 2000.00 5354.86 3200.00STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 1.00 4000.00 3987.50 4025.00IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 1.00 10000.00 21823.64 20469.02SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 1.00 5000.00 9056.27 6160.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 1.00 5000.00 15210.00 8050.00STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 1.00 13000.00 8000.00 8000.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 1.00 13000.00 11800.00 13000.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 22000.00 12725.05 16800.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 1.00 12000.00 9408.47 4182.50CC R600-225 CHATFIELD STATE PARK 06/10/04 1.00 6000.00 10025.00 13000.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 1.00 15000.00 16743.63 20000.00STA 0343-023 US 34, EAST OF AKRON 06/17/04 1.00 4000.00 8160.00 10100.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 1.00 4000.00 9500.00 9500.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 1.00 5000.00 16428.57 12500.00IM 0761-185 I-76, LOCHBUIE TO HUDSON 06/24/04 1.00 10000.00 11222.95 12514.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 20.00 8850.00 11116.15 9876.19

Page 480: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 436 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 620-00012 Field Lab (CL 2) Each ===================================================

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 1.00 15000.00 12071.43 10000.00IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1.00 12000.00 17108.00 19200.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 1.00 12000.00 9498.78 7942.55BR 0243-063 EAST OF LIMON 07/15/04 1.00 9000.00 14523.81 4000.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 30000.00 24883.39 20000.00STA R200-128 SH10, SH350 , SH160 MAINT. 07/29/04 1.00 13000.00 5666.67 6000.00IM 0701-168 RIFLE TO SILT SLAB REPAIR 08/05/04 1.00 7000.00 14260.00 7000.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 1.00 15000.00 15066.60 8000.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 8500.00 24766.38 18000.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1.00 7000.00 13014.40 11000.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 1.00 12000.00 9666.67 13000.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 15000.00 19250.00 15000.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 1.00 14000.00 18068.43 16000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 13.00 13038.46 15651.24 11934.04

BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 1.00 7000.00 12083.25 9800.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1.00 50000.00 26866.47 60000.00NH 2873-137 US 287 IN BOULDER & LARIMER C 11/18/04 1.00 3000.00 8586.56 5000.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 35000.00 23583.16 25000.00IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 1.00 9000.00 7257.14 5000.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 1.00 6400.00 11333.33 10000.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 1.00 7500.00 7156.56 8769.35STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 1.00 7500.00 12292.00 7168.00STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 1.00 10000.00 9974.76 5985.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 1.00 18000.00 12290.00 15000.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 1.00 10000.00 11375.00 10000.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 1.00 4000.00 7500.00 8000.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 1.00 7500.00 12837.32 7423.89STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 1.00 10000.00 11346.62 13490.70NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 1.00 5000.00 10296.37 6600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 15.00 12660.00 12065.70 13149.13 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 76.00 9847.37 12089.08 10878.45

=============== 620-00015 Field Lab (State Furn) Each ===================================================

IM 0704-203 I-70, GENOA-EAST, M.P. 374 - 01/15/04 1.00 6000.00 5100.00 4000.00

Page 481: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 437 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 620-00015 Field Lab (State Furn) Each ===================================================STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 1.00 5000.00 4040.00 1000.00STA 3501-010 SH 350 - BESHOUR JUNCTION . 1.00 3000.00 500.28 .STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 1.00 4000.00 6750.00 4000.00NH 2872-016 US 287 - LAMAR 03/04/04 1.00 3000.00 6375.00 2000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5.00 4200.00 4578.31 2750.00

NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 1.00 1100.00 4950.00 800.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 1100.00 4950.00 800.00

IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 1.00 3200.00 4728.57 2500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 3200.00 4728.57 2500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 7.00 3614.29 4652.97 2383.33

=============== 620-00020 Sanitary Facility Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 1.00 2000.00 784.60 760.00STA 2911-001 SH 291 SALIDA NORTH 01/08/04 1.00 600.00 1734.82 2000.00STA 114A-009 S.H. 114, W OF COCHETOPA PASS 01/08/04 1.00 1000.00 1716.67 2500.00NH 5502-045 US550, DURANGO JOINT SEAL 01/08/04 1.00 1000.00 1297.50 2500.00IM 0704-203 I-70, GENOA-EAST, M.P. 374 - 01/15/04 2.00 1100.00 1200.00 1000.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 1.00 1600.00 1238.87 920.00C 0342-040 US 34 IN WELD COUNTY 01/29/04 1.00 500.00 463.35 130.23STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 1.00 800.00 700.54 400.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 1.00 1000.00 855.29 800.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 1.00 1000.00 880.74 730.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 5.00 1500.00 2349.55 3347.28STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 1.00 1000.00 1400.00 1500.00STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 1.00 1500.00 1008.33 1000.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 1.00 800.00 785.20 775.00C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 1.00 500.00 193.50 216.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 1.00 1000.00 806.04 800.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 1.00 1000.00 807.03 1000.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 1.00 1500.00 1322.50 1000.00IM 0701-164 PARACHUTE EAST & WEST 02/12/04 1.00 1000.00 2530.00 2000.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 1.00 1000.00 1733.33 2000.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 1.00 1200.00 638.34 511.69

Page 482: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 438 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 620-00020 Sanitary Facility Each ===================================================STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 1.00 500.00 600.00 600.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 1800.00 2260.93 3000.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 1.00 1000.00 1540.00 1000.00STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 1.00 1000.00 1500.00 1000.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 1.00 1000.00 2333.33 1000.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 2.00 1000.00 745.00 1500.00STA 014A-030 SH 14, WALDEN EAST 03/04/04 1.00 1500.00 1350.00 2800.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 3.00 1000.00 1475.00 900.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 2.00 1000.00 1097.11 850.00STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 1.00 2000.00 1375.00 2000.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 1.00 1000.00 797.49 394.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 1.00 1000.00 950.00 1500.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1.00 1000.00 1217.15 1000.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 4.00 1060.00 1350.00 1700.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 1.00 1000.00 1293.33 1000.00STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 1.00 1000.00 1433.33 1500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 49.00 1117.14 1301.05 1454.56

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 2.00 1800.00 750.83 800.00NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 3.00 1000.00 1370.00 2000.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 2.00 600.00 792.92 511.32NH 0502-053 CIMARRON - WEST 04/15/04 1.00 1500.00 2285.00 1500.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 1.00 1500.00 1543.75 1500.00NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 1.00 1000.00 968.58 1000.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 1.00 500.00 1190.40 500.00STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 1.00 600.00 555.00 610.00STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 2.00 1000.00 707.07 500.00IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 1.00 1000.00 1066.67 1400.00NH 0741-015 - SMA Alt SH 74 EVERGREEN OVERLAY 04/29/04 1.00 1000.00 614.80 280.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 1.00 1500.00 2539.19 535.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 1.00 1000.00 2180.00 2500.00NH 1602-101 SOUTH FORK JOINT SEAL 05/13/04 1.00 1000.00 828.33 685.00BR 0362-028 BRIDGE OVER KIOWA CREEK 05/13/04 1.00 1500.00 480.00 480.00STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 1.00 1000.00 1733.33 1000.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 1.00 1000.00 1062.50 600.00STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 1.00 1000.00 537.50 550.00BR 0092-018 SH 9, SOUTH OF KREMMLING 05/27/04 1.00 1000.00 331.25 275.00STA R400-170 EAST OF HUDSON, EAST 05/27/04 1.00 1000.00 629.85 250.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 1.00 1500.00 2000.00 1000.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 1000.00 2085.48 2100.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 2.00 1500.00 856.93 397.80CC R600-225 CHATFIELD STATE PARK 06/10/04 1.00 1000.00 910.00 1000.00STA R400-169 R-4 CHIP SEALS EAST 06/10/04 2.00 1000.00 433.33 500.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 1.00 2000.00 1309.93 1200.00

Page 483: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 439 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 620-00020 Sanitary Facility Each ===================================================STA 0343-023 US 34, EAST OF AKRON 06/17/04 1.00 1500.00 1212.00 860.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 1.00 1500.00 1025.00 1200.00IM 0702-239 HANGING LAKES REST AREAS 06/17/04 13.00 1000.00 423.35 211.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 1.00 1000.00 1150.00 1200.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 1.00 1500.00 2211.43 4000.00IM 0761-185 I-76, LOCHBUIE TO HUDSON 06/24/04 2.00 1000.00 1285.45 1327.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 52.00 1113.46 1033.18 827.71

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 1.00 1650.00 1660.00 1500.00STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 2.00 1000.00 1369.25 1877.00IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1.00 1500.00 2299.27 2100.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 1.00 1500.00 1442.13 459.22BR 0243-063 EAST OF LIMON 07/15/04 1.00 1300.00 889.50 375.00STA R200-128 SH10, SH350 , SH160 MAINT. 07/29/04 1.00 1500.00 1666.67 2000.00IM 0701-168 RIFLE TO SILT SLAB REPAIR 08/05/04 1.00 1000.00 1155.00 900.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 2.00 1200.00 2072.21 2500.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 1500.00 2455.53 2880.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 2.00 500.00 878.60 750.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 2.00 800.00 1083.33 1000.00STA 149A-021 SH 149 CRIBWALL 09/16/04 1.00 1500.00 325.00 325.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 3.00 1500.00 1657.50 2000.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 2.00 1500.00 1988.53 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 21.00 1235.71 1574.45 1418.72

STA 0703-290 GEORGETOWN HILL ROCKFALL MITI 10/07/04 1.00 1000.00 625.00 500.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 1.00 2000.00 1140.00 650.00BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 1.00 1500.00 1420.75 2400.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 2.00 7500.00 2366.53 2100.00NH 2873-137 US 287 IN BOULDER & LARIMER C 11/18/04 1.00 500.00 908.22 500.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 3000.00 2582.86 1900.00C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 1.00 1000.00 1044.26 600.00IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 2.00 1050.00 1108.83 771.81MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 2.00 1200.00 673.33 820.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 2.00 1200.00 1133.33 400.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 1.00 1000.00 647.22 643.30STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 1.00 1000.00 721.91 400.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 1.00 1000.00 1086.38 531.88STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 1.00 1000.00 656.01 403.05STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 1.00 1000.00 789.22 1907.50NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 2.00 1500.00 1500.00 2000.00

Page 484: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 440 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 620-00020 Sanitary Facility Each ===================================================STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 1.00 1000.00 853.75 500.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 1.00 2000.00 1846.67 1500.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 1.00 1500.00 1872.50 2000.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 1.00 1000.00 2266.67 2000.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 2.00 1000.00 610.49 552.95NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 1.00 1000.00 826.01 429.05STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 1.00 1500.00 900.58 387.00NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 1.00 1100.00 563.83 300.00NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 1.00 1000.00 767.88 700.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 31.00 1645.16 1159.22 1017.46 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 153.00 1239.15 1222.10 1148.03

=============== 621-00425 Detour LUMP SUM ===============================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1.00 60000.00 149050.00 167000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 60000.00 149050.00 167000.00

BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 1.00 150000.00 180545.00 170000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 150000.00 180545.00 170000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 105000.00 174246.00 168500.00

=============== 621-00450 Detour Pvmt Sq Yard ================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 3,359.00 15.00 14.80 14.85 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3,359.00 15.00 14.80 14.85

NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 17,921.00 20.00 13.84 11.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 756.00 20.00 23.24 19.95 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 18,677.00 20.00 14.28 11.36

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 8,292.00 19.00 19.29 22.00

Page 485: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 441 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 621-00450 Detour Pvmt Sq Yard ================================================NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 7,185.00 17.00 20.29 17.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 893.00 18.00 18.91 11.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 16,370.00 18.07 19.55 19.21

SHE 105A-010 SH 105/FURROW RD 10/07/04 3,902.00 17.00 16.87 13.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 800.00 28.00 40.80 35.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 7,657.00 20.00 27.45 24.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 12,359.00 19.57 25.25 21.24 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 50,765.00 18.94 18.41 16.53

=============== 622-00024 Entry Sign Each ===================================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 2.00 2000.00 5918.95 2500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 2000.00 5918.95 2500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 2000.00 5918.95 2500.00

=============== 622-00100 Shade Shelter Each ===================================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 20.00 15000.00 6546.04 7000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 20.00 15000.00 6546.04 7000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 20.00 15000.00 6546.04 7000.00

=============== 622-00250 Bench Each ===================================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 2.00 1000.00 3410.93 3200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 1000.00 3410.93 3200.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 1000.00 3410.93 3200.00

=============== 622-00270 Bollard Each ===================================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 4.00 200.00 768.89 550.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4.00 200.00 768.89 550.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 200.00 768.89 550.00

Page 486: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 442 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 622-00300 BBQ Grill Each ===================================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 6.00 500.00 471.78 400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 6.00 500.00 471.78 400.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6.00 500.00 471.78 400.00

=============== 622-00350 Trash Receptacle Each ===================================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 20.00 750.00 578.42 550.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 20.00 750.00 578.42 550.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 20.00 750.00 578.42 550.00

=============== 622-00550 Wheel Stop (Conc) Each ===================================================

STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 5.00 50.00 79.09 62.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 5.00 50.00 79.09 62.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5.00 50.00 79.09 62.00

=============== 622-00600 Pump Pit Each ===================================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 2.00 50000.00 33846.12 25000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 50000.00 33846.12 25000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 50000.00 33846.12 25000.00

=============== 622-00700 Pump House Each ===================================================

SHE R300-113 DOWD BRIDGE, I-70 03/18/04 1.00 60000.00 68216.00 58400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 60000.00 68216.00 58400.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 60000.00 68216.00 58400.00

=============== 622-00750 Sewage Lift Station Each ===================================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 2.00 20000.00 36163.14 30000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 20000.00 36163.14 30000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 20000.00 36163.14 30000.00

Page 487: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 443 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 622-00800 Comfort Station Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 1.00 25000.00 29741.59 41540.62 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 25000.00 29741.59 41540.62

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 2.00 700000.00 757947.00 700000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 700000.00 757947.00 700000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 475000.00 445858.97 480513.54

=============== 622-00825 Mod Building LUMP SUM ===============================================

IM 0702-239 HANGING LAKES REST AREAS 06/17/04 1.00 15000.00 14195.67 11587.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 15000.00 14195.67 11587.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 15000.00 14195.67 11587.00

=============== 622-00826 Ceramic Tile & Grout Sq Foot ================================================

IM 0702-239 HANGING LAKES REST AREAS 06/17/04 750.00 12.00 29.58 22.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 750.00 12.00 29.58 22.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 750.00 12.00 29.58 22.00

=============== 622-01000 Leaching Field Sq Yard ================================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 7,339.00 37.00 37.60 40.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 7,339.00 37.00 37.60 40.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 7,339.00 37.00 37.60 40.00

=============== 622-01550 Septic Tank (5500 Gal) Each ===================================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 2.00 30000.00 23381.81 20000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 30000.00 23381.81 20000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 30000.00 23381.81 20000.00

Page 488: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 444 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 622-03270 Waste System LUMP SUM ===============================================

IM 0702-239 HANGING LAKES REST AREAS 06/17/04 1.00 217500.00 283054.26 296859.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 217500.00 283054.26 296859.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 217500.00 283054.26 296859.00

=============== 622-05506 Storage Tank (6000 Gal) Each ===================================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 2.00 25000.00 25426.06 22000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 25000.00 25426.06 22000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 25000.00 25426.06 22000.00

=============== 622-11170 HVA LUMP SUM ===============================================

IM 0702-239 HANGING LAKES REST AREAS 06/17/04 1.00 20000.00 12019.00 12927.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 20000.00 12019.00 12927.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 20000.00 12019.00 12927.00

=============== 622-11180 Bldg Plumbing Piping System LUMP SUM ===============================================

IM 0702-239 HANGING LAKES REST AREAS 06/17/04 1.00 94500.00 86956.43 41130.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 94500.00 86956.43 41130.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 94500.00 86956.43 41130.00

=============== 622-20080 Flagpole Each ===================================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 4.00 4000.00 3045.53 2800.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4.00 4000.00 3045.53 2800.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 4000.00 3045.53 2800.00

=============== 623-00164 Drip Emit Each ===================================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 286.00 2.50 3.81 1.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 286.00 2.50 3.81 1.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 286.00 2.50 3.81 1.00

Page 489: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 445 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 623-00165 Emit Valve Assembly Each ===================================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 100.00 74.85 70.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 100.00 74.85 70.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 100.00 74.85 70.00

=============== 623-00186 3/4 In Flush Unit Each ===================================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 9.00 25.00 21.86 20.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 9.00 25.00 21.86 20.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 9.00 25.00 21.86 20.00

=============== 623-00206 6 In Pop-Up Spray Spr Each ===================================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 48.00 13.00 13.77 9.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 48.00 13.00 13.77 9.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 48.00 13.00 13.77 9.00

=============== 623-00306 3/4 In Pop-Up Rotary Spr Each ===================================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 69.00 25.00 25.28 16.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 69.00 25.00 25.28 16.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 69.00 25.00 25.28 16.00

=============== 623-01708 1 Inch Backflow Preventer Each ===================================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 1000.00 892.66 900.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 1000.00 892.66 900.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 1000.00 892.66 900.00

=============== 623-03108 1 In Auto Ctrl Valve Each ===================================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 15.00 120.00 105.66 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 15.00 120.00 105.66 100.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 15.00 120.00 105.66 100.00

Page 490: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 446 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 623-04000 Ctrl Wire 24 Volt Lin Foot ===============================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 3,180.00 0.20 1.17 0.06 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3,180.00 0.20 1.17 0.06 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3,180.00 0.20 1.17 0.06

=============== 623-04002 Power Source Wire Lin Foot ===============================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 30.00 5.00 12.06 1.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 30.00 5.00 12.06 1.75 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 30.00 5.00 12.06 1.75

=============== 623-04008 1 In Quick-Coupler Each ===================================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 2.00 100.00 123.40 95.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 100.00 123.40 95.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 100.00 123.40 95.00

=============== 623-05016 2 In Gate Valve Each ===================================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 100.00 71.62 45.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 100.00 71.62 45.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 100.00 71.62 45.00

=============== 623-06900 Valve Box Each ===================================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 12.00 80.00 80.90 20.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 12.00 80.00 80.90 20.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 12.00 80.00 80.90 20.00

=============== 623-08124 24 Station Auto Ctrler Each ===================================================

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 2500.00 1684.23 2500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 2500.00 1684.23 2500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 2500.00 1684.23 2500.00

Page 491: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 447 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 623-09900 Sprinkler System LUMP SUM ===============================================

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 1.00 100000.00 46068.05 43000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 100000.00 46068.05 43000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 100000.00 46068.05 43000.00

=============== 624-14024 24 In Culvert Pipe (CR 4) Lin Foot ===============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 4,549.00 70.00 74.42 43.51 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4,549.00 70.00 74.42 43.51 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4,549.00 70.00 74.42 43.51

=============== 624-14030 30 In Culvert Pipe (CR 4) Lin Foot ===============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 502.00 80.00 93.45 64.71 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 502.00 80.00 93.45 64.71 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 502.00 80.00 93.45 64.71

=============== 624-14036 36 In Culvert Pipe (CR 4) Lin Foot ===============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 125.00 100.00 117.79 103.77 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 125.00 100.00 117.79 103.77 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 125.00 100.00 117.79 103.77

=============== 624-14048 48 In Culvert Pipe (CR 4) Lin Foot ===============================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 75.00 120.00 299.75 178.52 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 75.00 120.00 299.75 178.52 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 75.00 120.00 299.75 178.52

=============== 625-00000 Const Surveying LUMP SUM ===============================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 1.00 10000.00 10890.19 5700.00

Page 492: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 448 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 625-00000 Const Surveying LUMP SUM ===============================================STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 1.00 15000.00 14286.96 12000.00C 0342-040 US 34 IN WELD COUNTY 01/29/04 1.00 2500.00 2793.90 1914.33STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 1.00 10000.00 4997.85 2400.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 1.00 20000.00 10143.06 10500.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 1.00 350000.00 171459.38 156206.31STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 1.00 20000.00 14258.33 10000.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 1.00 7500.00 4602.90 3715.00C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 1.00 500.00 2432.50 2070.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 1.00 3000.00 8238.92 6200.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 1.00 15000.00 15498.78 10000.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 1.00 7500.00 6324.61 5331.87IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 80000.00 92975.00 90000.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 1.00 15000.00 44240.00 40000.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 1.00 3000.00 2448.57 2390.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 1.00 95000.00 26933.33 14000.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 1.00 30000.00 22464.90 25469.40STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 1.00 10000.00 24512.50 8050.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 1.00 60000.00 23040.16 16000.00SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 1.00 4500.00 16466.67 13900.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 1.00 4500.00 9230.48 9234.00C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 1.00 5000.00 5000.00 5000.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 1.00 25000.00 11000.00 14000.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1.00 50000.00 51340.96 30000.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1.00 130000.00 115850.00 110000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 25.00 38920.00 26643.23 24163.24

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 1.00 10000.00 6731.67 4500.00NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 1.00 40000.00 25750.00 26000.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 1.00 9000.00 22083.20 17023.78SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 1.00 7000.00 5856.62 7680.00NH 0502-053 CIMARRON - WEST 04/15/04 1.00 65000.00 67633.75 55000.00NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 1.00 15000.00 9390.94 7500.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 1.00 12000.00 10866.80 8000.00STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 1.00 5500.00 8000.00 6000.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 1.00 50000.00 147936.48 80845.00STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 1.00 10000.00 10920.00 11840.00IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 1.00 50000.00 28478.59 30980.13STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 1.00 15000.00 15624.29 13660.89SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 1.00 25000.00 39369.69 26000.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 1.00 20000.00 29200.00 25000.00STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 1.00 30000.00 21633.33 21000.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 1.00 75000.00 66825.00 99000.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 1.00 70000.00 21500.00 18000.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 60000.00 91903.85 64900.00

Page 493: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 449 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 625-00000 Const Surveying LUMP SUM ===============================================NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 1.00 20000.00 15622.16 10251.70CC R600-225 CHATFIELD STATE PARK 06/10/04 1.00 6000.00 11800.00 10000.00STA 0343-023 US 34, EAST OF AKRON 06/17/04 1.00 25000.00 15500.00 14000.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 1.00 10000.00 12050.00 8150.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 1.00 15000.00 15758.57 12810.00IM 0761-185 I-76, LOCHBUIE TO HUDSON 06/24/04 1.00 25000.00 8316.64 6083.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 24.00 27895.83 28747.43 24342.70

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 1.00 50000.00 88714.29 65000.00STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 1.00 25000.00 38345.00 39630.00IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1.00 150000.00 131428.53 95000.00SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 1.00 3000.00 4650.00 3600.00SHE 0091-023 SH 9 VMS - FAIRPLAY TO FRISCO 07/15/04 1.00 3000.00 1775.67 715.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 1.00 15000.00 26180.74 12078.20BR 0243-063 EAST OF LIMON 07/15/04 1.00 14000.00 17507.64 18000.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 75000.00 110099.44 137950.00IM 0701-168 RIFLE TO SILT SLAB REPAIR 08/05/04 1.00 6000.00 22250.00 40000.00SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 1.00 10000.00 5887.50 1775.00STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 1.00 3000.00 3472.60 1160.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 1.00 40000.00 76800.00 90400.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 50000.00 50699.90 34240.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1.00 9000.00 20391.80 23000.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 1.00 10000.00 12500.00 10000.00STA 149A-021 SH 149 CRIBWALL 09/16/04 1.00 5000.00 6700.00 6700.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 60000.00 135500.00 100000.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 1.00 35000.00 40184.45 40000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 18.00 31277.78 51478.95 39958.23

SHE 105A-010 SH 105/FURROW RD 10/07/04 1.00 25000.00 10817.02 12000.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 1.00 25000.00 21740.00 21000.00BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 1.00 15000.00 10517.63 14000.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1.00 120000.00 100252.09 75000.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 70000.00 60438.22 80000.00C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 1.00 5000.00 5248.57 3650.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 1.00 15000.00 15666.67 10000.00STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 1.00 7500.00 10202.80 13000.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 1.00 10000.00 6813.14 5850.69STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 1.00 6000.00 4886.81 5347.25STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 1.00 5000.00 4406.00 2000.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 1.00 20000.00 15366.67 10000.00

Page 494: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 450 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 625-00000 Const Surveying LUMP SUM ===============================================NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 1.00 15000.00 5500.00 5000.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 1.00 5000.00 6226.75 3207.00STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 1.00 5000.00 5635.82 5675.80NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 1.00 4000.00 4540.00 4500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 16.00 22031.25 19048.15 16889.42 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 83.00 30819.28 30106.04 26238.37

=============== 625-00001 Const Surveying (Hour) Hour ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 100.00 110.00 143.74 139.47 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 100.00 110.00 143.74 139.47

NH 2852-010 US 285 & COUNTY RD. G 04/29/04 15.00 120.00 139.16 115.80NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 40.00 200.00 149.43 130.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 120.00 120.00 103.75 80.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 175.00 138.29 120.88 94.50

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 100.00 125.00 126.13 120.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 40.00 100.00 115.30 107.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 100.00 120.00 146.25 110.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 240.00 118.75 132.01 113.67

STA 0703-290 GEORGETOWN HILL ROCKFALL MITI 10/07/04 80.00 150.00 135.00 150.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 40.00 110.00 122.00 90.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 100.00 125.00 123.74 125.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 20.00 150.00 125.00 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 240.00 132.92 125.60 125.42 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 755.00 126.62 129.81 116.38

=============== 626-00000 Mobilization LUMP SUM ===============================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 1.00 66000.00 72511.15 50000.00

Page 495: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 451 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 626-00000 Mobilization LUMP SUM ===============================================STA 2911-001 SH 291 SALIDA NORTH 01/08/04 1.00 66000.00 147201.27 100000.00STA 114A-009 S.H. 114, W OF COCHETOPA PASS 01/08/04 1.00 60000.00 120333.33 70000.00NH 5502-045 US550, DURANGO JOINT SEAL 01/08/04 1.00 25000.00 52289.50 29600.00IM 0704-203 I-70, GENOA-EAST, M.P. 374 - 01/15/04 1.00 100000.00 152357.67 71560.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 1.00 100000.00 92706.06 90000.00STA R300-120 R-3 SOUTHWEST CHIPSEAL 01/29/04 1.00 60000.00 90355.94 84855.00C 0342-040 US 34 IN WELD COUNTY 01/29/04 1.00 12000.00 8709.82 4841.32STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 1.00 50000.00 37180.63 6300.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 1.00 100000.00 86376.22 55000.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 1.00 180000.00 128390.37 65000.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 1.00 850000.00 1548542.64 1150000.00STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 1.00 130000.00 146488.60 83598.00STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 1.00 40000.00 89964.06 70000.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 1.00 30000.00 50132.66 20150.00C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 1.00 7000.00 7461.50 5069.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 1.00 36000.00 33747.47 30000.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 1.00 60000.00 74718.52 75000.00MC R300-118 R-3 PAVEMENT MARKINGS 02/12/04 1.00 20000.00 3166.67 7500.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 1.00 30000.00 129702.75 100000.00IM 0701-164 PARACHUTE EAST & WEST 02/12/04 1.00 320000.00 373091.20 273000.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 1.00 100000.00 165796.67 92390.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 1.00 30000.00 49393.71 32317.69STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 1.00 40000.00 84000.00 89000.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 500000.00 479331.23 546172.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 1.00 120000.00 148158.00 100000.00STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 1.00 100000.00 180000.00 150000.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 1.00 12000.00 10146.16 5368.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 1.00 450000.00 348340.08 280675.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 1.00 160000.00 124336.82 25000.00STA 014A-030 SH 14, WALDEN EAST 03/04/04 1.00 80000.00 135186.67 76330.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 1.00 260000.00 216099.00 120990.00NH 2872-016 US 287 - LAMAR 03/04/04 1.00 170000.00 256521.25 135260.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 1.00 300000.00 203866.60 62000.00SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 1.00 25000.00 66858.30 97574.89STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 1.00 80000.00 114768.75 134000.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 1.00 25000.00 40863.61 7831.00C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 1.00 15000.00 18000.00 18000.00SHE R300-113 DOWD BRIDGE, I-70 03/18/04 1.00 20000.00 24094.75 8600.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 1.00 125000.00 119705.00 59410.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1.00 250000.00 337704.56 100561.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1.00 500000.00 586618.15 265000.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 1.00 65000.00 165500.00 130000.00STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 1.00 125000.00 157935.33 200000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 44.00 133954.55 168839.48 117680.75

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 1.00 100000.00 71863.85 27600.00

Page 496: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 452 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 626-00000 Mobilization LUMP SUM ===============================================NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 1.00 215000.00 200320.00 58160.00MC R300-119 R-3 STENCIL REGIONWIDE 04/01/04 1.00 20000.00 11666.67 8000.00C R200-126 FY04 REGION 2 SIGNING 04/01/04 1.00 8000.00 13595.67 10765.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 1.00 40000.00 66390.13 36921.16NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 1.00 15000.00 16144.66 13841.00SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 1.00 20000.00 36575.74 42696.00NH 0502-053 CIMARRON - WEST 04/15/04 1.00 260000.00 308698.30 225000.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 1.00 130000.00 149244.50 64143.00NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 1.00 75000.00 53450.88 90000.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 1.00 85000.00 50908.99 31000.00STA 1191-020 SH 119 ROCKFALL MITIGATION, 2 04/15/04 1.00 25000.00 28833.33 20000.00STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 1.00 50000.00 62000.00 47000.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 1.00 200000.00 209145.17 155446.00STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 1.00 60000.00 71176.00 53652.00IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 1.00 150000.00 246842.94 110029.93STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 1.00 30000.00 51344.52 36094.00IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 1.00 120000.00 114566.67 57500.00SHE 1601-052 R-5, CENTERLINE RUMBLE STRIPS 04/22/04 1.00 40000.00 38666.67 52000.00NH 0741-015 - SMA Alt SH 74 EVERGREEN OVERLAY 04/29/04 1.00 50000.00 31059.10 12000.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 1.00 140000.00 95662.94 54503.30NH 2852-010 US 285 & COUNTY RD. G 04/29/04 1.00 170000.00 170870.64 160000.00NH 1602-101 SOUTH FORK JOINT SEAL 05/13/04 1.00 25000.00 48558.33 70000.00BR 0362-028 BRIDGE OVER KIOWA CREEK 05/13/04 1.00 10000.00 11000.00 11000.00STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 1.00 150000.00 115700.67 95000.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 1.00 150000.00 156086.25 108000.00STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 1.00 30000.00 42064.75 48000.00BR 0092-018 SH 9, SOUTH OF KREMMLING 05/27/04 1.00 30000.00 44498.25 33600.00AQC R600-215 SH 287, US 36 TO SH 128 05/27/04 1.00 15000.00 21030.23 15970.76STA R400-170 EAST OF HUDSON, EAST 05/27/04 1.00 25000.00 110000.00 25000.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 1.00 200000.00 432549.00 335000.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 300000.00 546694.72 667910.69NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 1.00 140000.00 221268.10 51578.70CC R600-225 CHATFIELD STATE PARK 06/10/04 1.00 30000.00 26664.50 32433.00STA R400-169 R-4 CHIP SEALS EAST 06/10/04 1.00 25000.00 112263.61 41331.06IM 0253-186 I-25, 120TH TO SH 7 06/17/04 1.00 100000.00 173131.31 20000.00STA 0343-023 US 34, EAST OF AKRON 06/17/04 1.00 150000.00 161729.80 80000.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 1.00 40000.00 84987.50 94950.00IM 0702-239 HANGING LAKES REST AREAS 06/17/04 1.00 60000.00 48236.33 39959.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 1.00 30000.00 51383.33 59150.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 1.00 110000.00 167814.00 147298.00STA R400-168 R4 DILEMMA ZONE SAFETY PROJEC 06/17/04 1.00 8000.00 10655.24 5000.00IM 0761-185 I-76, LOCHBUIE TO HUDSON 06/24/04 1.00 135000.00 198428.88 13194.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 43.00 87581.40 113852.31 78156.44

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 1.00 150000.00 244071.43 175000.00

Page 497: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 453 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 626-00000 Mobilization LUMP SUM ===============================================STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 1.00 100000.00 204005.75 195000.00IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1.00 750000.00 872266.62 970457.23SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 1.00 13000.00 25200.00 25000.00SHE 0091-023 SH 9 VMS - FAIRPLAY TO FRISCO 07/15/04 1.00 7000.00 12115.78 17894.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 1.00 80000.00 176107.28 91921.83BR 0243-063 EAST OF LIMON 07/15/04 1.00 50000.00 90833.33 97500.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 1200000.00 1304566.21 646067.50STA R200-128 SH10, SH350 , SH160 MAINT. 07/29/04 1.00 90000.00 143770.67 147000.00IM 0701-168 RIFLE TO SILT SLAB REPAIR 08/05/04 1.00 40000.00 135500.00 85000.00SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 1.00 30000.00 64772.50 30545.00STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 1.00 7000.00 11146.80 20164.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 1.00 250000.00 280784.42 240000.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 225000.00 585168.85 500000.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 1.00 80000.00 133719.73 48000.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 1.00 50000.00 63233.33 70000.00STA 149A-021 SH 149 CRIBWALL 09/16/04 1.00 60000.00 60000.00 60000.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 300000.00 598750.00 396000.00SHE 0403-049 US 40, EAST OF CRAIG 09/23/04 1.00 6000.00 15246.25 8800.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 1.00 250000.00 219590.00 290000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 20.00 186900.00 299579.49 205717.48

SHE 105A-010 SH 105/FURROW RD 10/07/04 1.00 30000.00 49899.38 36000.00SHE 5502-047 SH550 AT MP 112.7, IN OURAY C 10/07/04 1.00 10000.00 7376.90 5948.38STA 0703-290 GEORGETOWN HILL ROCKFALL MITI 10/07/04 1.00 20000.00 50000.00 35000.00C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 1.00 60000.00 33500.00 37000.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 1.00 170000.00 171500.00 90000.00BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 1.00 50000.00 103074.38 60000.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1.00 720000.00 809160.12 320000.00NH 2873-137 US 287 IN BOULDER & LARIMER C 11/18/04 1.00 25000.00 48582.11 6530.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 500000.00 501830.66 513583.00C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 1.00 26000.00 26238.59 15000.00IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 1.00 150000.00 163354.23 115500.00MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 1.00 70000.00 99130.00 97390.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 1.00 95000.00 185666.67 126000.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 1.00 30000.00 46644.23 26165.40STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 1.00 50000.00 81222.29 100000.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 1.00 60000.00 135091.15 42455.73STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 1.00 38000.00 55836.68 26346.73STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 1.00 40000.00 63812.21 27892.00NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 1.00 110000.00 174844.33 142000.00STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 1.00 20000.00 42000.00 35000.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 1.00 250000.00 315920.00 393000.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 1.00 250000.00 407983.18 270000.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 1.00 100000.00 234257.18 188000.00

Page 498: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 454 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 626-00000 Mobilization LUMP SUM ===============================================STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 1.00 50000.00 93731.83 29251.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 1.00 50000.00 60468.25 29373.00STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 1.00 30000.00 73652.54 23178.70NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 1.00 15000.00 42385.83 11700.00NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 1.00 30000.00 91814.00 76000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 28.00 108892.86 148231.97 102796.93 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 135.00 121829.63 163944.17 115046.99

=============== 626-01000 Public Info Services LUMP SUM ===============================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 1.00 3000.00 3826.16 3100.00NH 5502-045 US550, DURANGO JOINT SEAL 01/08/04 1.00 1000.00 4700.00 6250.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 1.00 5000.00 6353.20 2300.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 1.00 3000.00 3000.81 4300.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 1.00 5000.00 3597.22 500.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 1.00 4000.00 3182.23 600.00STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 1.00 2000.00 9166.67 13500.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 1.00 3000.00 2557.68 3100.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 1.00 4000.00 2726.83 3430.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 1.00 4000.00 6001.31 5000.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 1.00 3500.00 4876.25 6500.00IM 0701-164 PARACHUTE EAST & WEST 02/12/04 1.00 5000.00 8000.00 10000.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 1.00 4000.00 2208.56 2558.48STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 1.00 3000.00 2400.00 1800.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1.00 6500.00 6437.42 9000.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 1.00 2500.00 11538.33 5000.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 1.00 2500.00 5157.50 5000.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 1.00 10000.00 5860.56 3900.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 1.00 3000.00 5079.70 2231.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 1.00 5000.00 6421.93 2500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 20.00 3950.00 5185.90 4528.47

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 1.00 5000.00 2613.33 1000.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 1.00 3500.00 2825.32 2557.86NH 0502-053 CIMARRON - WEST 04/15/04 1.00 1000.00 3470.60 1000.00NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 1.00 6500.00 5195.64 10000.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 1.00 60000.00 76726.12 33500.00STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 1.00 2000.00 1515.00 2030.00STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 1.00 5000.00 5382.50 1800.00NH 0741-015 - SMA Alt SH 74 EVERGREEN OVERLAY 04/29/04 1.00 5000.00 5289.57 225.00

Page 499: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 455 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 626-01000 Public Info Services LUMP SUM ===============================================SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 1.00 2000.00 4782.69 3100.00NH 1602-101 SOUTH FORK JOINT SEAL 05/13/04 1.00 1000.00 2349.00 754.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 1.00 4000.00 6825.00 5300.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 1.00 100000.00 77500.00 110000.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 6500.00 12200.71 7200.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 1.00 3000.00 3820.48 3400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 14.00 14607.14 10714.10 12990.49

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1.00 30000.00 4587.67 7000.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 1.00 12000.00 5938.41 3966.59IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 10000.00 8092.87 3050.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 15000.00 11938.59 12000.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 12000.00 17250.00 4000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 5.00 15800.00 9382.07 6003.32

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 1.00 3000.00 2510.00 750.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1.00 10000.00 6307.18 4600.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 5000.00 4717.73 6500.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 1.00 2500.00 4666.67 1000.00STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 1.00 3000.00 4235.91 2400.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 1.00 3000.00 3798.93 2394.67STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 1.00 3000.00 3070.13 2935.53NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 1.00 6000.00 9833.33 5000.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 1.00 5000.00 14666.67 5000.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 1.00 3000.00 3463.52 2766.13NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 1.00 2000.00 2795.36 2681.45STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 1.00 2000.00 2914.91 3762.35NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 1.00 3000.00 4300.43 7000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 13.00 3884.62 4772.18 3599.24 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 52.00 7942.31 6695.66 6716.21

=============== 627-00001 Pvmt Mkg Paint Gallon =================================================

STA 114A-009 S.H. 114, W OF COCHETOPA PASS 01/08/04 400.00 40.00 36.00 33.00STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 40.00 75.00 56.79 52.00C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 6.00 300.00 95.79 92.00

Page 500: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 456 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 627-00001 Pvmt Mkg Paint Gallon =================================================IM 0701-164 PARACHUTE EAST & WEST 02/12/04 2,994.00 25.00 32.40 34.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 2,010.00 24.00 21.00 20.00STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 279.00 30.00 32.30 17.60STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 453.00 31.00 45.00 40.00STA 014A-030 SH 14, WALDEN EAST 03/04/04 2,060.00 22.00 22.29 20.50STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 430.00 34.00 29.00 29.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 8,672.00 26.09 27.75 27.16

STA 1191-020 SH 119 ROCKFALL MITIGATION, 2 04/15/04 8.00 300.00 232.67 58.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 91.00 40.00 52.66 49.39STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 13.00 65.00 61.95 60.90SHE 1601-052 R-5, CENTERLINE RUMBLE STRIPS 04/22/04 2,030.00 20.00 28.40 22.50NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 120.00 40.00 37.50 40.00STA 0343-023 US 34, EAST OF AKRON 06/17/04 998.00 30.00 26.90 27.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 25.00 70.00 79.71 42.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3,285.00 25.56 29.76 25.64

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1,100.00 25.00 27.45 27.00IM 0701-168 RIFLE TO SILT SLAB REPAIR 08/05/04 38.00 40.00 211.25 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,138.00 25.50 31.59 29.44

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 61.00 40.00 75.20 26.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 61.00 40.00 75.20 26.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 13,156.00 25.97 28.90 26.97

=============== 627-00002 Thermoplastic Pvmt Mkg Sq Foot ================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 32,079.00 1.50 1.36 1.25STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 13,237.00 1.75 1.55 1.50STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 18,262.00 2.00 1.63 1.55STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 46,992.00 1.50 1.29 1.25STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 12,135.00 1.60 1.50 1.44

Page 501: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 457 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 627-00002 Thermoplastic Pvmt Mkg Sq Foot ================================================STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 10,172.00 1.70 1.39 1.35STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 8,416.00 2.00 1.48 1.50STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 4,665.00 2.00 1.91 2.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 19,392.00 2.00 1.49 1.28NH 2872-016 US 287 - LAMAR 03/04/04 640.00 12.00 8.13 8.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 3,512.00 2.00 2.79 2.90 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 169,502.00 1.74 1.47 1.42

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 32,389.00 1.70 1.36 1.26NH 2852-010 US 285 & COUNTY RD. G 04/29/04 107.00 2.00 16.60 15.80 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 32,496.00 1.70 1.40 1.31

STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 4,960.00 2.00 3.04 4.98 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4,960.00 2.00 3.04 4.98 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 206,958.00 1.74 1.49 1.49

=============== 627-00003 Thermoplastic Pvmt Mkg (Inlaid) Sq Foot ================================================

C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 54.00 25.00 23.79 18.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 54.00 25.00 23.79 18.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 54.00 25.00 23.79 18.00

=============== 627-00004 Epoxy Pvmt Mkg Sq Foot ================================================

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 9,535.00 2.00 1.16 0.93 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 9,535.00 2.00 1.16 0.93 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 9,535.00 2.00 1.16 0.93

=============== 627-00005 Epoxy Pvmt Mkg Gallon =================================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 400.00 50.00 91.88 65.00

Page 502: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 458 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 627-00005 Epoxy Pvmt Mkg Gallon =================================================STA 114A-009 S.H. 114, W OF COCHETOPA PASS 01/08/04 540.00 45.00 64.70 61.10IM 0704-203 I-70, GENOA-EAST, M.P. 374 - 01/15/04 907.00 42.00 50.42 50.00STA R300-120 R-3 SOUTHWEST CHIPSEAL 01/29/04 1,892.00 42.00 52.81 55.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 500.00 70.00 50.03 50.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 3,853.00 35.00 51.59 49.37STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 845.00 60.00 50.70 50.00STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 20.00 42.00 103.58 105.00MC R300-118 R-3 PAVEMENT MARKINGS 02/12/04 47,654.00 31.00 31.42 30.00IM 0701-164 PARACHUTE EAST & WEST 02/12/04 1,504.00 50.00 49.40 51.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 1,005.00 45.00 53.33 45.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 204.00 60.00 50.20 48.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 416.00 60.00 58.60 58.00STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 581.00 45.00 62.50 65.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 1,316.00 42.00 49.00 48.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 191.00 50.00 45.02 44.61STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 1,111.00 60.00 47.00 48.00NH 2872-016 US 287 - LAMAR 03/04/04 314.00 30.00 63.75 55.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 625.00 50.00 45.72 41.50SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 613.00 60.00 63.67 60.00STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 668.00 60.00 53.75 52.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 268.00 80.00 62.50 60.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 300.00 80.00 54.24 50.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 502.00 75.00 48.50 49.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 527.00 70.00 50.33 49.00STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 1,017.00 60.00 49.33 48.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 67,773.00 36.51 39.77 36.32

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 1,307.00 50.00 48.85 46.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 33.00 60.00 81.65 81.81NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 20.00 75.00 183.78 157.50SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 32.00 90.00 81.23 80.50NH 0502-053 CIMARRON - WEST 04/15/04 208.00 70.00 57.38 65.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 568.00 50.00 45.75 50.00NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 353.00 50.00 53.13 51.50STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 215.00 60.00 57.85 57.00STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 28.00 60.00 112.00 155.00STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 78.00 60.00 59.93 58.85STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 50.00 100.00 59.01 50.47SHE 1601-052 R-5, CENTERLINE RUMBLE STRIPS 04/22/04 2,235.00 50.00 45.50 42.00NH 0741-015 - SMA Alt SH 74 EVERGREEN OVERLAY 04/29/04 550.00 65.00 53.97 56.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 422.00 40.00 50.68 46.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 61.00 80.00 79.06 68.40STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 896.00 70.00 54.83 54.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 267.00 45.00 52.25 44.00

Page 503: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 459 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 627-00005 Epoxy Pvmt Mkg Gallon =================================================STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 146.00 100.00 67.35 66.44STA R400-170 EAST OF HUDSON, EAST 05/27/04 1,260.00 45.00 46.50 43.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 30.00 60.00 122.50 150.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 419.00 80.00 51.10 47.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 504.00 55.00 56.34 84.20CC R600-225 CHATFIELD STATE PARK 06/10/04 65.00 100.00 68.25 85.00STA R400-169 R-4 CHIP SEALS EAST 06/10/04 1,856.00 40.00 46.67 45.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 1,961.00 45.00 45.75 42.25STA 0343-023 US 34, EAST OF AKRON 06/17/04 367.00 75.00 54.50 52.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 16.00 40.00 105.50 112.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 11.00 75.00 83.07 79.22BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 18.00 60.00 100.14 90.00IM 0761-185 I-76, LOCHBUIE TO HUDSON 06/24/04 540.00 50.00 49.53 54.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 14,516.00 52.42 50.59 49.31

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 159.00 60.00 62.01 60.00STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 223.00 100.00 50.77 53.85IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 195.00 47.10 65.12 64.00SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 20.00 140.00 72.50 70.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 20.00 100.00 110.41 100.65BR 0243-063 EAST OF LIMON 07/15/04 52.00 70.00 77.18 75.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 103.00 100.00 64.67 62.00STA R200-128 SH10, SH350 , SH160 MAINT. 07/29/04 538.00 70.00 76.50 73.00SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 20.00 90.00 95.63 47.25NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 399.00 55.00 61.43 62.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 80.00 60.00 64.43 62.86C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 52.00 80.00 88.68 90.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 820.00 42.00 76.50 68.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 66.00 100.00 353.95 460.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2,747.00 62.31 76.41 75.91

SHE 105A-010 SH 105/FURROW RD 10/07/04 32.00 140.00 159.22 210.00BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 18.00 125.00 170.13 140.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 131.00 65.00 77.25 82.00NH 2873-137 US 287 IN BOULDER & LARIMER C 11/18/04 9.00 100.00 381.75 562.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 75.50 80.00 100.53 98.00IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 680.00 49.00 63.09 64.90MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 14.00 120.00 128.33 150.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 120.00 52.00 61.33 59.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 89.00 65.00 88.33 134.00

Page 504: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 460 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 627-00005 Epoxy Pvmt Mkg Gallon =================================================STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 415.00 60.00 60.24 41.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 339.00 60.00 74.63 73.67STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 134.00 70.00 102.85 134.41STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 192.00 65.00 86.32 93.75NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 1,019.00 60.00 63.00 64.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 648.00 40.00 61.33 40.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 809.00 60.00 65.68 65.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 505.00 65.00 71.67 65.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 200.00 45.00 82.05 76.03NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 122.00 100.00 90.51 134.05STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 160.00 65.00 105.14 123.60NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 30.00 75.00 128.48 165.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 5,741.50 58.97 72.83 71.15 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 90,777.50 41.26 45.42 41.80

=============== 627-00011 Pvmt Mkg Paint (Waterborne) Gallon =================================================

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 2,460.00 30.00 44.00 29.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2,460.00 30.00 44.00 29.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2,460.00 30.00 44.00 29.00

=============== 627-00012 Pvmt Mkg Paint (Low VOC Solvent Base) Gallon =================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 1,083.00 35.00 25.31 38.00IM 0704-203 I-70, GENOA-EAST, M.P. 374 - 01/15/04 1,613.00 35.00 24.35 22.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 435.00 40.00 23.11 21.50STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 988.00 30.00 26.94 34.50STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 2,008.00 30.00 24.83 21.90IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 520.00 50.00 23.47 23.45NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 1,001.00 30.00 30.37 27.89STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 286.00 40.00 35.44 31.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 850.00 35.00 25.62 20.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 550.00 30.00 24.90 24.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 272.00 42.00 26.75 25.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 525.00 50.00 33.90 25.58IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 200.00 50.00 30.49 29.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 1,500.00 33.00 22.35 22.82STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 3,300.00 30.00 17.50 8.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 250.00 45.00 26.86 30.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 15,381.00 33.99 24.83 21.94

Page 505: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 461 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 627-00012 Pvmt Mkg Paint (Low VOC Solvent Base) Gallon =================================================

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 1,619.00 29.00 28.03 24.50STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 216.00 40.00 33.45 34.77IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 19.00 50.00 111.98 221.29STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 100.00 70.00 44.34 37.08NH 0741-015 - SMA Alt SH 74 EVERGREEN OVERLAY 04/29/04 1,150.00 35.00 23.45 23.45STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 146.00 55.00 36.30 46.34NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1,734.00 35.00 26.02 23.00CC R600-225 CHATFIELD STATE PARK 06/10/04 65.00 50.00 31.50 35.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 2,300.00 30.00 26.10 24.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 42.00 40.00 48.00 47.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 7,391.00 33.34 27.62 25.46

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 400.00 35.00 33.10 32.60SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 20.00 75.00 62.00 59.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 50.00 50.00 55.21 50.33BR 0243-063 EAST OF LIMON 07/15/04 20.00 60.00 85.83 80.00SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 20.00 80.00 56.00 40.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 407.00 31.00 34.27 34.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 260.00 30.00 50.81 52.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 108.00 35.00 57.60 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,285.00 35.02 42.44 41.23

SHE 105A-010 SH 105/FURROW RD 10/07/04 60.00 70.00 63.15 40.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1,829.00 27.00 33.56 36.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 720.00 35.00 50.78 49.50IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 700.00 30.00 39.34 35.38MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 54.00 100.00 86.00 160.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 100.00 40.00 45.00 40.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 408.00 40.00 36.98 16.10STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 1,724.00 30.00 41.22 36.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 1,476.00 30.00 21.51 16.22STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 636.00 35.00 43.28 16.10STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 848.00 30.00 28.18 16.35NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 1,705.00 27.00 33.00 30.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 1,419.00 40.00 30.43 30.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 1,000.00 32.00 39.27 16.59

Page 506: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 462 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 627-00012 Pvmt Mkg Paint (Low VOC Solvent Base) Gallon =================================================NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 488.00 40.00 49.08 19.30STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 688.00 40.00 27.42 16.10NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 40.00 40.00 57.03 22.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 13,895.00 32.58 35.28 28.04 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 37,952.00 33.38 29.17 25.51

=============== 627-00025 4 In Pvmt Mkg Tape (Rem) Lin Foot ===============================================

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 1,045.00 2.50 2.27 2.30ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 21,440.00 3.00 3.92 3.29 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 22,485.00 2.98 3.85 3.24 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 22,485.00 2.98 3.85 3.24

=============== 627-00030 Raised Pvmt Marker (Temp) Each ===================================================

STA R400-170 EAST OF HUDSON, EAST 05/27/04 7,895.00 4.00 1.00 1.00STA R400-169 R-4 CHIP SEALS EAST 06/10/04 11,636.00 3.50 1.08 1.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 19,531.00 3.70 1.06 1.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 19,531.00 3.70 1.06 1.00

=============== 627-00032 Raised Flex Pvmt Marker (Temp) Each ===================================================

STA 114A-009 S.H. 114, W OF COCHETOPA PASS 01/08/04 1,974.00 3.00 1.45 1.80STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 6,500.00 6.00 1.53 1.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 8,474.00 5.30 1.50 1.76 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8,474.00 5.30 1.50 1.76

=============== 627-00070 Preform Thermoplastic Pvmt Mkg Sq Foot ================================================

STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 270.00 10.00 11.40 14.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 482.00 12.00 13.20 11.00STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 366.00 15.00 10.20 11.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,118.00 12.50 11.89 11.72

Page 507: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 463 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 627-00070 Preform Thermoplastic Pvmt Mkg Sq Foot ================================================

NH 2852-010 US 285 & COUNTY RD. G 04/29/04 64.00 10.00 14.38 11.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 64.00 10.00 14.38 11.40 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,182.00 12.36 12.04 11.71

=============== 627-00200 War Epoxy Pvmt Mkg Sq Foot ================================================

MC R300-118 R-3 PAVEMENT MARKINGS 02/12/04 132,900.00 1.50 0.50 0.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 132,900.00 1.50 0.50 0.30 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 132,900.00 1.50 0.50 0.30

=============== 627-00202 Epoxy Pvmt Mkg (2-Yr War) Sq Foot ================================================

MC R300-118 R-3 PAVEMENT MARKINGS 02/12/04 132,900.00 1.00 0.70 0.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 132,900.00 1.00 0.70 0.20 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 132,900.00 1.00 0.70 0.20

=============== 627-01000 Preform Plastic Pvmt Mkg (Ty A) Sq Foot ================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 5,833.00 9.00 8.53 8.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 3,518.00 9.00 8.27 8.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 1,533.00 10.00 8.15 8.20STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 5,849.00 9.00 8.37 8.30STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 2,926.00 9.00 8.53 8.50STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 4,062.00 9.00 7.95 7.80STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 2,269.00 10.00 8.00 8.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 2,442.00 9.00 9.23 8.50STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 2,010.00 10.00 8.12 8.14NH 2872-016 US 287 - LAMAR 03/04/04 7,562.00 9.00 7.88 7.50NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 3,566.00 9.00 7.50 8.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 41,570.00 9.14 8.26 8.01

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 11,075.00 8.00 7.73 7.55

Page 508: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 464 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 627-01000 Preform Plastic Pvmt Mkg (Ty A) Sq Foot ================================================STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 1,081.00 9.00 9.05 8.13STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 810.00 11.00 10.94 9.31IM 0253-186 I-25, 120TH TO SH 7 06/17/04 10,682.00 8.00 8.42 8.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 23,648.00 8.15 8.14 7.84

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 2,176.00 9.00 9.74 10.25BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 909.00 9.00 8.51 8.25MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 276.00 11.00 12.33 13.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 1,324.00 9.00 9.40 9.65STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 1,550.00 9.00 9.77 8.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 3,166.00 9.00 9.89 9.57STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 2,396.00 9.00 9.34 9.65STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 2,112.00 9.00 9.09 9.80STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 4,459.00 8.50 9.17 9.95STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 1,536.00 9.00 10.20 10.20NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 884.00 9.00 10.14 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 20,788.00 8.92 9.52 9.70 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 86,006.00 8.81 8.51 8.37

=============== 627-01003 Preform Plastic Pvmt Mkg (Ty A) (Inlaid) Sq Foot ================================================

IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 6,200.00 10.00 8.04 8.34 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 6,200.00 10.00 8.04 8.34

NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 2,414.00 11.00 8.68 8.40STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 1,792.00 9.00 8.65 8.50NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 5,115.00 10.00 10.38 10.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 9,321.00 10.07 9.41 9.57

IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 7,568.00 10.00 11.95 9.42STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 1,400.00 9.30 14.17 13.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 7,440.00 12.00 11.31 10.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 16,408.00 10.85 11.88 10.22 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 31,929.00 10.45 10.68 9.66

Page 509: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 465 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 627-02000 Preform Plastic Pvmt Mkg (Ty B) Sq Foot ================================================

STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 2,896.00 14.00 8.50 8.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,896.00 14.00 8.50 8.50

NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 120.00 13.00 12.33 14.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 120.00 13.00 12.33 14.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3,016.00 13.96 8.92 8.72

=============== 627-02003 Preform Plastic Pvmt Mkg (Ty B) (Inlaid) Sq Foot ================================================

NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 396.00 12.00 12.00 15.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 396.00 12.00 12.00 15.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 396.00 12.00 12.00 15.00

=============== 627-03000 Preform Plastic Pvmt Mkg (Ty C) Sq Foot ================================================

STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 5,413.00 9.00 8.35 8.20STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 4,404.00 8.50 10.00 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 9,817.00 8.78 8.70 9.01

NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 670.00 10.00 11.42 9.45NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 550.00 9.00 9.79 9.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,220.00 9.55 10.90 9.52

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 447.00 10.00 13.37 20.50BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 130.00 10.00 8.51 8.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 577.00 10.00 12.58 17.74 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 11,614.00 8.92 9.24 9.49

Page 510: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 466 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 627-03003 Preform Plastic Pvmt Mkg (Ty C) (Inlaid) Sq Foot ================================================

STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 1,756.00 10.00 9.25 9.15NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 4,400.00 9.00 11.79 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 6,156.00 9.29 11.49 9.76 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6,156.00 9.29 11.49 9.76

=============== 627-30205 Thermoplastic Pvmt Mkg (WS) Sq Foot ================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 50.00 15.00 9.16 9.95 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 50.00 15.00 9.16 9.95 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 50.00 15.00 9.16 9.95

=============== 627-30210 Thermoplastic Pvmt Mkg (XS) Sq Foot ================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 1,320.00 7.00 7.25 6.95 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,320.00 7.00 7.25 6.95

NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 66.00 14.00 12.00 14.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 66.00 14.00 12.00 14.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,386.00 7.33 7.34 7.29

=============== 627-30305 Plastic Pvmt Mkg (60 Mil) (WS) Sq Foot ================================================

STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 214.00 15.00 11.54 13.05 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 214.00 15.00 11.54 13.05

SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 728.00 12.00 13.97 13.80 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 728.00 12.00 13.97 13.80 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 942.00 12.68 12.98 13.63

Page 511: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 467 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 627-30310 Plastic Pvmt Mkg (60 Mil) (XS) Sq Foot ================================================

STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 5,060.00 10.00 7.43 7.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5,060.00 10.00 7.43 7.10 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5,060.00 10.00 7.43 7.10

=============== 627-30325 Plastic Pvmt Mkg (Ty B) (WS) Sq Foot ================================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 402.00 15.00 11.70 11.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 2,921.00 13.00 10.84 10.50STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 252.00 15.00 11.82 11.35STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 396.00 14.00 11.59 11.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 295.00 16.00 13.50 15.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 138.00 13.00 14.17 10.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 145.00 15.00 13.06 15.35IM 0701-157 FRUITA TO CLIFTON 02/26/04 203.00 12.00 11.61 10.35STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 765.00 15.00 11.15 10.92STA 0063-016 CLIFTON TO PALISADE 03/25/04 744.00 14.00 12.33 11.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 6,261.00 13.79 11.34 11.02

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 335.00 11.00 12.20 11.20STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 978.00 14.00 15.69 16.45CC R600-225 CHATFIELD STATE PARK 06/10/04 27.00 17.00 16.63 18.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,340.00 13.31 14.21 15.18

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 290.00 18.00 12.76 12.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1,451.00 9.00 14.75 13.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,741.00 10.50 14.49 12.83

SHE 105A-010 SH 105/FURROW RD 10/07/04 99.00 16.00 14.69 20.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 428.00 14.00 18.63 26.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 69.00 15.00 12.43 12.20

Page 512: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 468 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 627-30325 Plastic Pvmt Mkg (Ty B) (WS) Sq Foot ================================================STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 186.00 13.00 13.58 15.00STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 1,466.00 12.00 13.37 8.00STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 944.00 12.00 17.71 15.05NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 917.00 13.00 15.17 15.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 214.00 12.00 14.06 15.48NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 149.00 20.00 15.40 16.10STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 220.00 13.00 16.43 15.05 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4,692.00 12.85 15.29 13.95 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 14,034.00 13.02 13.01 12.62

=============== 627-30330 Plastic Pvmt Mkg (Ty B) (XS) Sq Foot ================================================

STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 14,264.00 9.00 6.62 5.75STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 2,018.00 9.00 8.39 8.25STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 6,580.00 8.00 7.94 7.65STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 6,220.00 9.00 7.64 7.50STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 7,346.00 9.00 7.96 7.50STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 304.00 10.00 10.00 8.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 7,688.00 10.00 7.16 6.14IM 0701-157 FRUITA TO CLIFTON 02/26/04 252.00 8.00 10.08 8.50STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 2,732.00 9.00 7.23 7.13STA 0063-016 CLIFTON TO PALISADE 03/25/04 2,424.00 10.00 9.67 9.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 49,828.00 9.07 7.40 6.90

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 2,370.00 9.00 8.24 7.67SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 3,279.00 9.00 8.29 8.05STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 1,452.00 9.00 11.28 12.00CC R600-225 CHATFIELD STATE PARK 06/10/04 356.00 10.00 9.40 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 7,457.00 9.05 8.75 8.79

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 220.00 11.00 8.42 8.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 626.00 9.00 12.13 9.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 846.00 9.52 11.35 9.11

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1,720.00 10.00 9.87 10.50

Page 513: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 469 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 627-30330 Plastic Pvmt Mkg (Ty B) (XS) Sq Foot ================================================BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 504.00 10.00 9.21 9.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 3,204.00 9.00 9.41 9.65STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 2,512.00 9.00 10.65 8.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 1,200.00 9.00 9.70 9.57STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 2,160.00 10.00 9.54 10.75STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 2,690.00 9.00 9.60 9.80NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 1,124.00 9.00 10.83 11.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 800.00 9.00 10.19 11.80STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 1,980.00 9.00 9.88 9.65NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 3,926.00 8.00 10.51 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 21,820.00 9.02 9.96 9.85 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 79,951.00 9.06 8.13 7.90

=============== 627-30405 Preform Thermoplastic Pvmt Mkg (WS) Sq Foot ================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 308.00 10.00 12.53 8.00STA 2911-001 SH 291 SALIDA NORTH 01/08/04 267.50 16.00 12.15 15.00C 0342-040 US 34 IN WELD COUNTY 01/29/04 208.00 14.00 12.63 12.20NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 377.00 10.00 12.66 10.32STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 400.00 14.00 12.02 12.00NH 2872-016 US 287 - LAMAR 03/04/04 266.00 10.00 13.00 12.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 98.00 15.00 12.41 13.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,924.50 12.35 12.47 11.53

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 107.00 12.00 11.29 10.00MC R300-119 R-3 STENCIL REGIONWIDE 04/01/04 5,144.00 10.00 12.90 9.00NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 2,439.00 12.00 11.05 10.76STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 414.00 12.00 12.06 8.90STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 1,764.00 11.00 8.25 8.10STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 66.00 13.00 16.04 15.45SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 419.00 12.00 11.45 11.00STA R400-170 EAST OF HUDSON, EAST 05/27/04 406.00 11.00 12.00 12.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 277.00 15.00 12.51 11.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 644.00 12.00 15.27 14.70STA 0343-023 US 34, EAST OF AKRON 06/17/04 107.00 12.00 14.13 14.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 126.00 15.00 13.38 13.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 11,913.00 11.06 12.07 9.88

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 124.00 13.00 12.67 12.80

Page 514: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 470 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 627-30405 Preform Thermoplastic Pvmt Mkg (WS) Sq Foot ================================================STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 214.00 10.00 17.42 16.24STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 357.00 12.00 13.06 13.11C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 577.00 15.00 12.39 12.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,272.00 13.12 13.47 13.10

STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 132.00 12.50 14.17 13.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 132.00 12.50 14.17 13.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 15,241.50 11.41 12.31 10.39

=============== 627-30406 Inst Preform Thermoplastic Pvmt Mkg (WS) Sq Foot ================================================

MC R300-119 R-3 STENCIL REGIONWIDE 04/01/04 900.00 6.00 6.00 4.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 900.00 6.00 6.00 4.25 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 900.00 6.00 6.00 4.25

=============== 627-30410 Preform Thermoplastic Pvmt Mkg (XS) Sq Foot ================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 2,060.00 9.00 7.96 7.00STA 2911-001 SH 291 SALIDA NORTH 01/08/04 360.00 13.00 10.32 12.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 3,980.00 9.00 7.54 7.10C 0342-040 US 34 IN WELD COUNTY 01/29/04 194.00 10.00 12.16 12.20NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 72.00 10.00 9.70 8.09STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 949.00 11.00 9.19 9.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 260.00 8.00 11.54 14.20STA 014A-030 SH 14, WALDEN EAST 03/04/04 70.00 10.00 11.52 11.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 1,280.00 10.00 7.63 7.00NH 2872-016 US 287 - LAMAR 03/04/04 7,864.00 15.00 6.99 5.75NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 1,079.00 8.00 7.34 7.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 2,048.00 8.00 7.74 8.50STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 3,126.00 8.00 7.51 7.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 23,342.00 10.95 7.68 7.09

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 48.00 10.00 8.85 8.00

Page 515: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 471 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 627-30410 Preform Thermoplastic Pvmt Mkg (XS) Sq Foot ================================================MC R300-119 R-3 STENCIL REGIONWIDE 04/01/04 32,156.00 7.00 9.70 9.00NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 240.00 10.00 12.04 8.93NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 6,971.00 10.00 6.94 6.77STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 288.00 11.00 7.94 7.25STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 36.00 10.00 20.07 41.20STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 11,156.00 7.00 6.45 6.35STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 420.00 8.00 8.34 7.47SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 130.00 8.00 8.25 7.80STA R400-170 EAST OF HUDSON, EAST 05/27/04 148.00 10.00 7.75 7.50NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1,016.00 8.00 7.56 6.50NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 1,138.00 10.00 8.17 9.50STA 0343-023 US 34, EAST OF AKRON 06/17/04 100.00 12.00 10.04 10.85SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 188.00 10.00 9.46 8.50IM 0761-185 I-76, LOCHBUIE TO HUDSON 06/24/04 80.00 10.00 10.52 11.35 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 54,115.00 7.55 8.66 8.13

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 164.00 11.00 8.54 8.30STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 124.00 9.00 13.31 12.59STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 2,680.00 10.00 8.55 8.29C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 620.00 12.00 7.77 7.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 3,588.00 10.36 8.58 8.30

STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 544.00 8.20 10.50 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 544.00 8.20 10.50 10.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 81,589.00 8.65 8.24 7.85

=============== 629-01001 Survey Monument (Ty 1) Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 1.00 200.00 211.65 165.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 4.00 210.00 333.30 358.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5.00 208.00 298.54 319.40

NH 0502-053 CIMARRON - WEST 04/15/04 3.00 120.00 499.06 325.00

Page 516: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 472 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 629-01001 Survey Monument (Ty 1) Each ===================================================STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 3.00 210.00 266.67 300.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 2.00 200.00 264.68 51.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 8.00 173.75 350.45 247.13

BR 0243-063 EAST OF LIMON 07/15/04 3.00 200.00 104.78 95.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 3.00 250.00 115.30 107.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 6.00 225.00 111.36 101.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 30.00 50.00 156.29 155.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 2.00 150.00 158.11 150.00STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 7.00 200.00 171.96 134.35 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 39.00 82.05 158.81 151.04 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 58.00 120.34 188.35 173.63

=============== 629-01002 Survey Monument (Ty 2) Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 1.00 200.00 305.86 290.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 8.00 300.00 280.31 306.83 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 9.00 288.89 283.96 304.96

STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 6.00 500.00 390.50 500.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 2.00 400.00 656.25 325.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 8.00 475.00 456.94 456.25

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 6.00 250.00 559.69 355.00BR 0243-063 EAST OF LIMON 07/15/04 2.00 150.00 297.79 300.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 350.00 303.05 321.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 9.00 238.89 478.13 339.00

Page 517: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 473 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 629-01002 Survey Monument (Ty 2) Each ===================================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 3.00 100.00 452.73 525.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3.00 100.00 452.73 525.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 29.00 305.17 392.96 380.02

=============== 629-01003 Survey Monument (Ty 3) Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 1.00 200.00 424.01 460.00STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 1.00 600.00 459.50 350.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 400.00 439.22 405.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 400.00 439.22 405.00

=============== 629-01005 Survey Monument (Ty 5) Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 3.00 225.00 307.93 165.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 4.00 200.00 159.88 76.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 7.00 300.00 259.88 234.31STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 1.00 220.00 375.70 370.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 15.00 253.00 239.45 187.28

NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 5.00 150.00 375.00 350.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 5.00 150.00 375.00 350.00

BR 0243-063 EAST OF LIMON 07/15/04 1.00 150.00 311.35 346.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 2.00 200.00 84.70 64.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 3.00 183.33 137.00 158.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 5.00 125.00 349.62 375.00

Page 518: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 474 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 629-01005 Survey Monument (Ty 5) Each ===================================================STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 7.00 200.00 330.30 96.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 12.00 168.75 339.22 212.69 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 35.00 203.43 272.16 216.73

=============== 629-01006 Survey Monument (Ty 6) Each ===================================================

NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 1.00 136.00 375.00 350.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 136.00 375.00 350.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 136.00 375.00 350.00

=============== 629-01011 Survey Monument (Ty 1A) Each ===================================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1.00 215.00 281.69 155.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 215.00 281.69 155.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 215.00 281.69 155.00

=============== 629-01021 Survey Monument (Ty 2A) Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 1.00 200.00 342.60 330.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 2.00 300.00 399.70 368.20 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3.00 266.67 376.86 355.47 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3.00 266.67 376.86 355.47

=============== 629-01031 Survey Monument (Ty 3A) Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 1.00 500.00 504.20 500.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 3.00 450.00 435.54 380.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 8.00 500.00 691.67 400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 12.00 487.50 543.55 403.33

SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 1.00 500.00 452.68 510.00

Page 519: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 475 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 629-01031 Survey Monument (Ty 3A) Each ===================================================NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 6.00 400.00 311.29 200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 7.00 414.29 328.53 244.29

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 1.00 400.00 461.38 678.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 400.00 461.38 678.00

STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 3.00 450.00 843.03 1978.15STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 7.00 450.00 428.67 483.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 10.00 450.00 569.39 932.07 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 30.00 455.00 494.96 551.62

=============== 629-01050 Monument Box Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 1.00 100.00 211.24 100.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 3.00 300.00 351.95 360.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 250.00 322.32 295.00

NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 1.00 200.00 442.61 750.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 200.00 442.61 750.00

STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 3.00 250.00 245.89 228.90STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 3.00 300.00 187.75 161.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 6.00 275.00 219.46 195.08 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 11.00 259.09 283.48 281.86

=============== 629-01110 Locate Monuments Hour ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 8.00 90.00 225.84 120.00

Page 520: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 476 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 629-01110 Locate Monuments Hour ===================================================STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 8.00 100.00 140.18 122.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 8.00 100.00 137.26 125.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 3.00 100.00 156.30 105.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 48.00 150.00 98.57 98.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 75.00 130.93 125.40 106.07

STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 8.00 100.00 134.14 123.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 8.00 100.00 134.14 123.60 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 83.00 127.95 125.99 107.76

=============== 629-01210 Adjust Monument Box Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 1.00 180.00 221.35 150.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 4.00 200.00 184.32 102.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 26.00 200.00 233.16 230.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 2.00 160.00 274.44 225.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 4.00 200.00 225.43 225.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 2.00 160.00 303.23 300.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 1.00 335.00 315.84 255.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 40.00 198.88 233.67 218.58

NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 4.00 250.00 248.80 300.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 6.00 250.00 313.46 150.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 1.00 220.00 375.00 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 11.00 247.27 294.47 236.36

STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 3.00 200.00 199.39 161.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3.00 200.00 199.39 161.25 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 54.00 208.80 240.33 219.01

=============== 629-01300 Survey Monument (Temp) Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 1.00 60.00 118.68 160.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 60.00 118.68 160.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 60.00 118.68 160.00

Page 521: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 477 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-00000 Flagging Hour ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 1,200.00 22.00 20.54 20.00STA 2911-001 SH 291 SALIDA NORTH 01/08/04 2,300.00 20.00 18.17 19.00STA 114A-009 S.H. 114, W OF COCHETOPA PASS 01/08/04 1,440.00 22.00 20.42 19.25IM 0704-203 I-70, GENOA-EAST, M.P. 374 - 01/15/04 2,000.00 21.00 19.21 18.50STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 3,000.00 22.00 20.15 20.00STA R300-120 R-3 SOUTHWEST CHIPSEAL 01/29/04 850.00 20.00 17.13 21.00C 0342-040 US 34 IN WELD COUNTY 01/29/04 100.00 20.00 23.09 22.49STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 800.00 22.00 19.75 18.50STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 1,560.00 20.00 20.32 20.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 3,000.00 21.00 20.88 19.80NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 31,000.00 23.00 15.15 20.00STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 1,950.00 20.00 21.40 19.98STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 3,000.00 20.00 16.40 21.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 2,400.00 22.00 21.83 22.70C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 200.00 20.00 20.74 19.50STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 2,000.00 20.00 19.46 18.50STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 4,000.00 20.00 20.42 18.00MC R300-118 R-3 PAVEMENT MARKINGS 02/12/04 100.00 20.00 17.67 20.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 1,320.00 20.00 22.75 21.00IM 0701-164 PARACHUTE EAST & WEST 02/12/04 4,500.00 18.00 21.40 24.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 2,820.00 20.00 20.50 18.50STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 1,500.00 20.00 19.79 19.44STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 1,500.00 23.00 23.28 22.55IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 3,500.00 21.00 19.79 18.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 2,500.00 20.00 20.20 20.00STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 1,650.00 22.00 20.00 20.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 200.00 22.00 20.97 17.15IM 0701-157 FRUITA TO CLIFTON 02/26/04 8,000.00 17.00 18.67 18.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 1,500.00 20.00 19.98 18.90STA 014A-030 SH 14, WALDEN EAST 03/04/04 2,000.00 20.00 20.29 19.25STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 4,500.00 22.00 20.18 18.50NH 2872-016 US 287 - LAMAR 03/04/04 5,000.00 22.00 19.00 18.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 6,000.00 20.00 19.72 20.40SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 834.00 20.00 24.17 22.00STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 2,000.00 21.00 19.50 21.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 650.00 20.00 23.41 25.00C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 288.00 20.00 26.00 26.00SHE R300-113 DOWD BRIDGE, I-70 03/18/04 250.00 20.00 23.98 28.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 2,800.00 20.00 20.68 23.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 3,000.00 21.00 19.50 20.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 4,000.00 20.00 20.00 20.00STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 3,400.00 20.00 19.68 21.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 124,612.00 20.95 18.67 19.93

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 1,000.00 20.00 21.00 19.50

Page 522: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 478 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-00000 Flagging Hour ===================================================NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 4,000.00 18.00 21.22 21.00MC R300-119 R-3 STENCIL REGIONWIDE 04/01/04 480.00 20.00 26.67 40.00C R200-126 FY04 REGION 2 SIGNING 04/01/04 24.00 18.00 24.66 26.50STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 800.00 20.00 21.64 21.48NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 400.00 22.00 22.10 21.00SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 80.00 20.00 21.99 25.30NH 0502-053 CIMARRON - WEST 04/15/04 6,500.00 20.00 20.07 20.50NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 2,000.00 21.00 19.13 18.50NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 1,200.00 18.00 21.48 21.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 3,000.00 18.00 21.73 20.80STA 1191-020 SH 119 ROCKFALL MITIGATION, 2 04/15/04 1,152.00 21.00 23.67 21.00STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 350.00 22.00 23.17 23.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 230.00 28.00 28.62 26.01STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 10,000.00 18.00 19.15 19.30IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 2,500.00 22.00 18.53 19.92STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 3,600.00 20.00 20.70 21.00IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 300.00 20.00 22.00 22.00SHE 1601-052 R-5, CENTERLINE RUMBLE STRIPS 04/22/04 1,000.00 25.00 22.98 21.00NH 0741-015 - SMA Alt SH 74 EVERGREEN OVERLAY 04/29/04 770.00 22.00 18.60 16.70SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 3,800.00 20.00 20.25 19.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 3,600.00 22.00 18.95 17.40NH 1602-101 SOUTH FORK JOINT SEAL 05/13/04 1,800.00 23.00 22.75 20.00BR 0362-028 BRIDGE OVER KIOWA CREEK 05/13/04 160.00 22.00 25.00 25.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 5,000.00 20.00 20.18 19.70STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 1,000.00 23.00 19.98 20.00BR 0092-018 SH 9, SOUTH OF KREMMLING 05/27/04 900.00 24.00 20.53 14.50AQC R600-215 SH 287, US 36 TO SH 128 05/27/04 600.00 22.00 22.16 17.65STA R400-170 EAST OF HUDSON, EAST 05/27/04 800.00 20.00 22.50 19.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 8,000.00 21.00 19.00 20.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 4,000.00 23.00 20.69 19.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 700.00 19.00 22.24 22.10CC R600-225 CHATFIELD STATE PARK 06/10/04 340.00 20.00 20.25 20.00STA R400-169 R-4 CHIP SEALS EAST 06/10/04 1,450.00 19.00 17.33 19.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 3,000.00 20.00 21.68 21.00STA 0343-023 US 34, EAST OF AKRON 06/17/04 4,500.00 19.00 18.71 17.50SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 200.00 20.00 23.00 19.75STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 500.00 18.00 19.41 19.24BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 2,000.00 19.00 18.81 18.40IM 0761-185 I-76, LOCHBUIE TO HUDSON 06/24/04 2,500.00 20.00 22.81 24.35 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 84,236.00 20.15 20.35 19.91

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 8,000.00 19.00 18.54 16.00STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 3,000.00 21.00 18.15 17.75IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 4,000.00 22.00 20.90 22.00

Page 523: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 479 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-00000 Flagging Hour ===================================================SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 300.00 25.00 21.50 21.00SHE 0091-023 SH 9 VMS - FAIRPLAY TO FRISCO 07/15/04 200.00 20.00 26.21 28.50BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 2,000.00 25.00 25.85 21.64BR 0243-063 EAST OF LIMON 07/15/04 300.00 20.00 21.20 22.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 12,000.00 20.00 18.79 19.29STA R200-128 SH10, SH350 , SH160 MAINT. 07/29/04 400.00 20.00 19.00 19.00IM 0701-168 RIFLE TO SILT SLAB REPAIR 08/05/04 2,100.00 18.00 22.65 21.00SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 500.00 20.00 24.65 23.80STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 200.00 20.00 23.80 19.72NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 1,600.00 23.00 20.94 21.50STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 6,800.00 23.00 20.52 20.22C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 2,500.00 19.00 21.50 21.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 960.00 20.00 19.83 17.00STA 149A-021 SH 149 CRIBWALL 09/16/04 600.00 21.00 25.00 25.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 10,500.00 19.00 21.71 21.00SHE 0403-049 US 40, EAST OF CRAIG 09/23/04 320.00 22.00 24.09 22.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 300.00 20.00 21.51 22.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 56,580.00 20.42 20.21 19.80

SHE 105A-010 SH 105/FURROW RD 10/07/04 400.00 23.00 20.36 18.00STA 0703-290 GEORGETOWN HILL ROCKFALL MITI 10/07/04 800.00 25.00 27.50 35.00C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 100.00 25.00 23.00 24.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 1,500.00 22.00 22.60 23.00BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 1,000.00 22.00 21.40 20.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 7,200.00 20.00 19.13 20.00NH 2873-137 US 287 IN BOULDER & LARIMER C 11/18/04 1,820.00 20.00 22.59 20.60BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 3,000.00 20.00 18.27 20.00C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 1,000.00 23.00 23.51 24.65IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 1,500.00 20.00 21.07 23.50MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 680.00 22.00 25.00 24.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 3,000.00 20.00 21.33 19.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 800.00 22.00 22.00 19.85STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 1,200.00 22.00 21.59 21.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 800.00 20.00 21.99 21.28STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 1,000.00 20.00 23.30 24.70STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 800.00 22.00 23.89 24.00NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 2,000.00 22.00 21.00 21.00STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 400.00 25.00 36.88 21.50IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 4,600.00 22.00 23.33 25.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 7,010.00 20.00 19.83 20.50NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 3,750.00 20.00 20.33 20.50STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 2,000.00 22.00 21.28 19.35NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 1,500.00 21.00 21.84 20.90STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 1,500.00 22.00 22.77 21.50

Page 524: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 480 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-00000 Flagging Hour ===================================================NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 1,000.00 20.00 22.59 24.00NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 1,300.00 22.00 22.12 22.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 51,660.00 20.91 21.15 21.48 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 317,088.00 20.64 19.71 20.15

=============== 630-00001 Pilot Car Operation Hour ===================================================

STA 114A-009 S.H. 114, W OF COCHETOPA PASS 01/08/04 408.00 31.00 35.07 35.20STA R300-120 R-3 SOUTHWEST CHIPSEAL 01/29/04 220.00 25.00 32.50 35.00STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 456.00 35.00 35.00 35.00STA 014A-030 SH 14, WALDEN EAST 03/04/04 250.00 35.00 37.00 32.00SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 150.00 35.00 38.50 33.00STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 450.00 25.00 30.50 31.00STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 500.00 28.00 33.33 40.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,434.00 30.14 33.91 34.89

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 1,000.00 35.00 23.45 20.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 1,000.00 35.00 31.16 31.20STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 1,000.00 30.00 32.75 32.00STA R400-170 EAST OF HUDSON, EAST 05/27/04 198.00 37.00 35.00 40.00STA R400-169 R-4 CHIP SEALS EAST 06/10/04 554.00 30.00 30.33 40.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3,752.00 33.03 29.16 30.19 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6,186.00 31.90 30.96 32.04

=============== 630-00003 Uniformed Traf Ctrl Hour ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 300.00 60.00 49.65 46.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 160.00 60.00 54.71 51.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 100.00 52.00 54.60 72.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 300.00 50.00 59.93 68.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 20.00 50.00 62.68 67.10STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 210.00 60.00 55.96 45.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 400.00 50.00 56.19 52.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 360.00 50.00 58.00 52.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 100.00 50.00 53.73 51.17C 074A-007 SH 74 @ BRYANT DR. 02/26/04 8.00 50.00 70.22 65.00

Page 525: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 481 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-00003 Uniformed Traf Ctrl Hour ===================================================STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 200.00 50.00 41.43 35.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 90.00 50.00 64.38 71.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,248.00 53.07 54.74 52.89

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 200.00 50.00 55.59 58.29IM 0253-186 I-25, 120TH TO SH 7 06/17/04 700.00 50.00 56.08 51.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 900.00 50.00 55.89 52.62

STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 110.00 60.00 59.78 58.95STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 64.00 55.00 49.62 46.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 64.00 55.00 63.17 69.14STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 160.00 55.00 66.23 65.40STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 100.00 55.00 63.85 60.82NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 100.00 55.00 48.35 46.10 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 598.00 55.92 60.36 58.54 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3,746.00 52.79 55.73 53.73

=============== 630-00004 Traf Ctrl Vehicle Each ===================================================

STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 1.00 2000.00 1563.54 1805.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 1.00 2500.00 2533.32 2600.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 2.00 3000.00 937.80 310.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 1.00 2000.00 3386.23 2000.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 1.00 3000.00 1305.43 1023.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 6.00 2583.33 1800.05 1341.40

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 1.00 1500.00 2110.29 1022.63IM 0253-186 I-25, 120TH TO SH 7 06/17/04 1.00 2500.00 5783.16 6600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 2000.00 3240.40 3811.32

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 2500.00 2019.34 1234.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 2500.00 2019.34 1234.00

Page 526: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 482 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-00004 Traf Ctrl Vehicle Each ===================================================

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 2.00 3000.00 3921.94 3100.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 5000.00 4480.76 4000.00MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 2.00 4500.00 5066.67 5000.00STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 1.00 2000.00 1197.73 830.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 1.00 2000.00 2078.42 5957.08STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 1.00 2000.00 3706.47 3225.86STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 2.00 2000.00 2192.02 4147.12NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 1.00 1000.00 555.33 536.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 11.00 2818.18 2983.05 3549.41 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 20.00 2650.00 2499.34 2797.43

=============== 630-00007 Traf Ctrl Inspection Day ====================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 22.00 120.00 77.23 62.00STA 2911-001 SH 291 SALIDA NORTH 01/08/04 20.00 100.00 76.55 90.00STA 114A-009 S.H. 114, W OF COCHETOPA PASS 01/08/04 20.00 100.00 96.00 88.00IM 0704-203 I-70, GENOA-EAST, M.P. 374 - 01/15/04 20.00 100.00 88.00 70.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 32.00 100.00 79.01 76.00STA R300-120 R-3 SOUTHWEST CHIPSEAL 01/29/04 12.00 200.00 133.75 195.00C 0342-040 US 34 IN WELD COUNTY 01/29/04 16.00 80.00 75.95 104.61STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 22.00 100.00 67.01 103.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 28.00 100.00 77.86 79.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 60.00 80.00 94.04 78.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 102.00 130.00 120.25 139.47STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 19.00 100.00 99.10 110.50STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 42.00 115.00 64.58 80.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 25.00 110.00 62.39 41.30STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 35.00 80.00 49.84 26.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 80.00 100.00 93.01 80.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 45.00 100.00 64.65 90.00IM 0701-164 PARACHUTE EAST & WEST 02/12/04 60.00 110.00 105.60 170.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 43.00 85.00 88.33 75.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 28.00 100.00 63.60 51.17STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 12.00 120.00 96.75 93.50IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 150.00 125.00 94.14 130.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 38.00 100.00 49.40 85.00STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 25.00 100.00 90.00 90.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 10.00 100.00 69.38 60.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 46.00 65.00 54.50 50.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 45.00 80.00 82.13 151.79

Page 527: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 483 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-00007 Traf Ctrl Inspection Day ====================================================STA 014A-030 SH 14, WALDEN EAST 03/04/04 18.00 150.00 42.00 29.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 50.00 100.00 63.75 50.00NH 2872-016 US 287 - LAMAR 03/04/04 54.00 110.00 71.25 65.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 60.00 70.00 78.26 61.00SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 24.00 70.00 98.67 72.00STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 26.00 100.00 55.50 32.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 40.00 100.00 53.77 56.00C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 16.00 70.00 58.00 58.00SHE R300-113 DOWD BRIDGE, I-70 03/18/04 10.00 90.00 59.40 51.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 25.00 80.00 45.00 30.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 36.00 100.00 89.23 50.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 210.00 88.00 92.00 93.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 18.00 100.00 80.00 70.00STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 25.00 100.00 54.50 95.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1,669.00 100.07 81.86 87.98

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 32.00 60.00 41.99 30.00NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 65.00 80.00 82.30 75.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 30.00 60.00 72.34 46.02NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 70.00 60.00 45.63 42.00SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 20.00 100.00 29.43 23.00NH 0502-053 CIMARRON - WEST 04/15/04 60.00 75.00 117.56 130.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 20.00 110.00 86.25 80.00NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 15.00 75.00 64.39 60.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 20.00 80.00 85.60 83.00STA 1191-020 SH 119 ROCKFALL MITIGATION, 2 04/15/04 36.00 90.00 23.00 21.00STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 10.00 100.00 70.67 60.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 128.00 150.00 154.88 104.04STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 50.00 50.00 51.63 50.75IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 180.00 125.00 68.26 55.32STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 40.00 100.00 85.50 52.50IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 70.00 55.00 41.33 44.00NH 0741-015 - SMA Alt SH 74 EVERGREEN OVERLAY 04/29/04 12.00 100.00 87.13 55.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 60.00 70.00 80.17 117.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 80.00 125.00 79.93 47.40STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 34.00 100.00 15.33 15.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 48.00 40.00 37.44 38.00STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 35.00 110.00 125.92 94.34BR 0092-018 SH 9, SOUTH OF KREMMLING 05/27/04 20.00 100.00 96.75 66.00AQC R600-215 SH 287, US 36 TO SH 128 05/27/04 8.00 60.00 88.17 117.65STA R400-170 EAST OF HUDSON, EAST 05/27/04 10.00 100.00 100.00 100.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 34.00 100.00 82.50 75.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 200.00 110.00 81.04 77.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 30.00 75.00 65.68 42.10

Page 528: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 484 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-00007 Traf Ctrl Inspection Day ====================================================CC R600-225 CHATFIELD STATE PARK 06/10/04 12.00 70.00 100.50 82.00STA R400-169 R-4 CHIP SEALS EAST 06/10/04 21.00 75.00 85.00 95.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 90.00 100.00 75.91 65.00STA 0343-023 US 34, EAST OF AKRON 06/17/04 35.00 80.00 76.40 75.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 60.00 40.00 27.75 55.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 83.00 80.00 110.84 107.51BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 275.00 75.00 77.69 82.00IM 0761-185 I-76, LOCHBUIE TO HUDSON 06/24/04 30.00 80.00 56.65 44.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2,023.00 90.37 75.65 70.22

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 45.00 100.00 145.06 165.00STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 120.00 100.00 51.00 42.00IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 140.00 75.00 86.78 93.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 48.00 200.00 138.84 125.81BR 0243-063 EAST OF LIMON 07/15/04 40.00 90.00 93.38 100.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 285.00 100.00 72.30 102.00STA R200-128 SH10, SH350 , SH160 MAINT. 07/29/04 8.00 100.00 70.00 85.00IM 0701-168 RIFLE TO SILT SLAB REPAIR 08/05/04 24.00 90.00 89.06 80.00SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 30.00 100.00 34.73 32.45STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 10.00 60.00 57.88 62.60NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 220.00 80.00 46.36 50.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 261.00 130.00 121.05 116.63C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 37.00 70.00 72.40 55.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 48.00 60.00 73.17 40.00STA 149A-021 SH 149 CRIBWALL 09/16/04 6.00 80.00 28.00 28.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 15.00 100.00 81.00 75.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 40.00 100.00 87.52 150.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1,377.00 100.39 86.96 88.22

SHE 105A-010 SH 105/FURROW RD 10/07/04 90.00 100.00 64.29 50.00STA 0703-290 GEORGETOWN HILL ROCKFALL MITI 10/07/04 10.00 140.00 125.00 100.00C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 16.00 100.00 120.00 120.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 15.00 100.00 68.60 55.00BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 60.00 125.00 87.20 65.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 125.00 100.00 94.42 108.00NH 2873-137 US 287 IN BOULDER & LARIMER C 11/18/04 15.00 80.00 90.45 66.80BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 150.00 100.00 89.82 50.00C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 35.00 120.00 95.76 55.00IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 25.00 84.00 30.14 50.00MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 20.00 120.00 155.00 135.00

Page 529: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 485 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-00007 Traf Ctrl Inspection Day ====================================================STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 35.00 80.00 106.67 100.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 50.00 100.00 57.48 53.60STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 20.00 80.00 80.97 72.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 20.00 80.00 72.26 31.91STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 20.00 100.00 89.90 80.60STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 60.00 100.00 63.40 65.40NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 17.00 120.00 42.67 27.00STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 8.00 80.00 163.00 100.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 35.00 150.00 128.33 100.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 45.00 75.00 113.33 115.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 25.00 100.00 100.00 110.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 15.00 100.00 91.50 94.00NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 50.00 100.00 77.53 75.10STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 32.00 100.00 76.04 80.60NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 24.00 84.00 69.67 61.50NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 25.00 75.00 81.63 83.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,042.00 100.57 83.70 74.66 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6,111.00 97.02 81.08 79.89

=============== 630-00009 Traf Ctrl Vehicle (Truck) Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 2.00 8500.00 3655.93 4600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 8500.00 3655.93 4600.00

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 14000.00 5728.20 16000.00MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 2.00 10000.00 15591.67 14275.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3.00 11333.33 11646.28 14850.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5.00 10200.00 6729.14 10750.00

=============== 630-00011 Courtesy Vehicle Day ====================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 150.00 850.00 641.49 278.94 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 150.00 850.00 641.49 278.94 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 150.00 850.00 641.49 278.94

Page 530: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 486 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-00012 Traf Ctrl Mgmt Day ====================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 80.00 350.00 380.10 390.00STA 2911-001 SH 291 SALIDA NORTH 01/08/04 45.00 425.00 397.16 420.00STA 114A-009 S.H. 114, W OF COCHETOPA PASS 01/08/04 40.00 360.00 445.00 440.00NH 5502-045 US550, DURANGO JOINT SEAL 01/08/04 49.00 400.00 523.83 575.00IM 0704-203 I-70, GENOA-EAST, M.P. 374 - 01/15/04 50.00 300.00 362.50 400.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 85.00 350.00 388.16 410.00STA R300-120 R-3 SOUTHWEST CHIPSEAL 01/29/04 30.00 350.00 252.50 305.00C 0342-040 US 34 IN WELD COUNTY 01/29/04 40.00 350.00 392.41 348.71STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 37.00 350.00 396.42 360.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 55.00 350.00 395.09 365.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 75.00 400.00 376.70 285.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 330.00 350.00 362.49 446.30STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 65.00 400.00 345.80 289.00STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 91.00 400.00 312.25 390.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 40.00 350.00 369.68 310.00C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 15.00 400.00 384.46 378.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 90.00 350.00 347.18 390.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 115.00 350.00 357.80 220.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 128.00 350.00 284.00 225.00IM 0701-164 PARACHUTE EAST & WEST 02/12/04 140.00 350.00 347.40 480.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 89.00 350.00 313.33 285.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 58.00 350.00 369.15 358.19STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 30.00 400.00 439.50 429.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 240.00 350.00 334.92 350.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 90.00 370.00 399.00 400.00STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 45.00 400.00 432.50 435.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 40.00 350.00 317.12 268.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 115.00 350.00 292.33 275.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 75.00 350.00 464.99 756.91STA 014A-030 SH 14, WALDEN EAST 03/04/04 45.00 325.00 415.83 405.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 110.00 350.00 370.00 380.00NH 2872-016 US 287 - LAMAR 03/04/04 110.00 300.00 383.75 365.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 135.00 350.00 372.56 380.00SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 60.00 350.00 384.33 325.00STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 60.00 350.00 330.00 420.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 120.00 350.00 363.64 358.00C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 58.00 350.00 462.00 462.00SHE R300-113 DOWD BRIDGE, I-70 03/18/04 30.00 400.00 425.50 436.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 60.00 400.00 535.00 750.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 133.00 350.00 354.91 300.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 120.00 350.00 460.00 460.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 45.00 400.00 340.00 320.00STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 65.00 400.00 386.67 300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3,533.00 357.06 365.71 383.62

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 120.00 350.00 384.83 385.00

Page 531: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 487 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-00012 Traf Ctrl Mgmt Day ====================================================NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 125.00 360.00 405.80 390.00MC R300-119 R-3 STENCIL REGIONWIDE 04/01/04 60.00 350.00 350.00 450.00C R200-126 FY04 REGION 2 SIGNING 04/01/04 20.00 350.00 387.25 472.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 75.00 350.00 352.53 260.77NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 90.00 350.00 396.81 346.50SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 50.00 380.00 399.82 460.00NH 0502-053 CIMARRON - WEST 04/15/04 120.00 285.00 341.25 330.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 50.00 300.00 342.50 320.00NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 50.00 350.00 406.95 410.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 60.00 360.00 413.40 390.00STA 1191-020 SH 119 ROCKFALL MITIGATION, 2 04/15/04 42.00 350.00 427.67 388.00STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 35.00 350.00 396.67 360.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 322.00 2000.00 1400.53 1248.48STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 80.00 395.00 387.83 380.65IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 200.00 350.00 369.78 387.25STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 75.00 400.00 404.29 362.25IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 120.00 317.00 404.17 412.50SHE 1601-052 R-5, CENTERLINE RUMBLE STRIPS 04/22/04 20.00 450.00 671.67 650.00NH 0741-015 - SMA Alt SH 74 EVERGREEN OVERLAY 04/29/04 22.00 450.00 390.23 370.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 105.00 350.00 369.35 370.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 150.00 400.00 381.09 363.20NH 1602-101 SOUTH FORK JOINT SEAL 05/13/04 45.00 400.00 457.33 415.00BR 0362-028 BRIDGE OVER KIOWA CREEK 05/13/04 10.00 400.00 500.00 500.00STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 80.00 350.00 775.00 925.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 120.00 350.00 326.25 330.00STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 25.00 450.00 423.68 427.36BR 0092-018 SH 9, SOUTH OF KREMMLING 05/27/04 45.00 375.00 352.50 270.00AQC R600-215 SH 287, US 36 TO SH 128 05/27/04 65.00 350.00 407.00 117.65STA R400-170 EAST OF HUDSON, EAST 05/27/04 25.00 375.00 325.00 400.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 170.00 385.00 400.00 380.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 200.00 360.00 401.17 360.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 66.00 325.00 391.50 394.70CC R600-225 CHATFIELD STATE PARK 06/10/04 35.00 350.00 372.50 300.00STA R400-169 R-4 CHIP SEALS EAST 06/10/04 42.00 350.00 333.33 400.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 165.00 350.00 369.51 400.00STA 0343-023 US 34, EAST OF AKRON 06/17/04 100.00 350.00 372.00 365.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 100.00 370.00 308.75 380.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 21.00 350.00 356.72 345.17BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 90.00 350.00 346.14 336.00IM 0761-185 I-76, LOCHBUIE TO HUDSON 06/24/04 56.00 350.00 413.28 436.90 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3,451.00 510.75 448.60 465.01

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 150.00 340.00 441.31 500.00STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 100.00 340.00 361.81 360.00

Page 532: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 488 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-00012 Traf Ctrl Mgmt Day ====================================================IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 245.00 325.00 409.56 410.00SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 25.00 420.00 406.00 412.00SHE 0091-023 SH 9 VMS - FAIRPLAY TO FRISCO 07/15/04 32.00 400.00 413.00 230.19BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 24.00 500.00 402.49 367.38BR 0243-063 EAST OF LIMON 07/15/04 30.00 380.00 411.84 425.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 720.00 325.00 280.94 370.00STA R200-128 SH10, SH350 , SH160 MAINT. 07/29/04 25.00 400.00 398.33 370.00IM 0701-168 RIFLE TO SILT SLAB REPAIR 08/05/04 49.00 375.00 380.63 350.00SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 60.00 400.00 459.88 459.75STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 30.00 350.00 395.19 254.93NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 200.00 400.00 323.08 335.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 170.00 350.00 383.08 379.85C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 93.00 350.00 372.00 400.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 120.00 350.00 391.67 350.00STA 149A-021 SH 149 CRIBWALL 09/16/04 30.00 400.00 472.00 472.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 220.00 400.00 331.25 385.00SHE 0403-049 US 40, EAST OF CRAIG 09/23/04 45.00 355.00 380.00 445.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 30.00 400.00 400.53 395.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2,398.00 354.56 357.54 383.75

SHE 105A-010 SH 105/FURROW RD 10/07/04 60.00 400.00 315.75 350.00STA 0703-290 GEORGETOWN HILL ROCKFALL MITI 10/07/04 25.00 450.00 435.00 470.00C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 40.00 450.00 575.00 600.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 50.00 420.00 548.00 500.00BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 60.00 425.00 370.80 290.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 300.00 350.00 395.40 350.00NH 2873-137 US 287 IN BOULDER & LARIMER C 11/18/04 45.00 370.00 418.64 370.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 300.00 365.00 363.00 370.00C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 90.00 340.00 458.58 482.00IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 45.00 370.00 445.00 400.00MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 60.00 450.00 444.00 412.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 70.00 380.00 395.00 385.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 60.00 350.00 392.43 364.55STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 50.00 350.00 417.97 390.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 50.00 350.00 418.75 329.77STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 50.00 350.00 439.29 462.15STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 65.00 350.00 442.90 436.00NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 32.00 500.00 388.33 415.00STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 20.00 400.00 646.75 400.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 80.00 370.00 518.33 360.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 85.00 425.00 419.17 395.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 60.00 400.00 426.67 420.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 50.00 350.00 391.13 331.77NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 70.00 350.00 428.24 412.95

Page 533: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 489 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-00012 Traf Ctrl Mgmt Day ====================================================STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 80.00 350.00 457.15 483.75NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 50.00 370.00 406.17 437.00NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 45.00 350.00 412.28 420.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,992.00 374.49 414.42 395.56 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 11,374.00 406.22 396.55 410.43

=============== 630-00015 Uniformed Traf Ctrl Coordination Hour ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 300.00 25.00 24.50 10.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 8.00 40.00 40.25 45.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 308.00 25.39 24.86 10.91

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 300.00 31.00 49.41 38.00NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 48.00 40.00 42.95 50.00IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 250.00 25.00 10.03 1.11NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 1,170.00 58.00 5.00 2.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,768.00 48.26 20.79 9.29

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 150.00 40.00 55.33 46.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 150.00 40.00 55.33 46.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 300.00 55.00 26.95 12.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 100.00 40.00 13.96 25.00MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 200.00 50.00 29.00 37.00STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 300.00 55.00 39.63 64.50STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 120.00 55.00 46.79 69.85NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 150.00 60.00 49.71 50.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,170.00 53.50 34.88 41.65 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3,396.00 47.63 28.18 22.21

=============== 630-00020 Traf Ctrl Vehicle Day ====================================================

NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 5.00 300.00 280.23 315.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 5.00 300.00 280.23 315.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 5.00 300.00 280.23 315.00

Page 534: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 490 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-00025 Traf Ctrl Vehicle Hour ===================================================

STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 360.00 32.00 18.38 16.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 200.00 26.00 19.17 25.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 560.00 29.86 18.73 19.21

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 300.00 26.00 12.80 11.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 300.00 26.00 12.80 11.00

STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 110.00 26.00 13.71 10.70STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 160.00 20.00 16.35 16.35NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 150.00 25.00 13.85 13.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 420.00 23.36 14.76 13.85 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,280.00 26.82 15.76 15.53

=============== 630-10005 Traf Ctrl LUMP SUM ===============================================

STA R400-168 R4 DILEMMA ZONE SAFETY PROJEC 06/17/04 1.00 10000.00 26768.53 7300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 10000.00 26768.53 7300.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 10000.00 26768.53 7300.00

=============== 630-80001 Flash Beacon (Port) Each ===================================================

NH 5502-045 US550, DURANGO JOINT SEAL 01/08/04 2.00 500.00 988.00 863.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 4.00 850.00 524.41 360.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 4.00 850.00 788.76 730.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 2.00 1000.00 1379.56 1562.06STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 4.00 800.00 665.00 500.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 2.00 750.00 1181.15 1550.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 8.00 1100.00 951.05 1200.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 6.00 300.00 1041.68 1805.10NH 2872-016 US 287 - LAMAR 03/04/04 5.00 800.00 68.75 50.00

Page 535: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 491 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80001 Flash Beacon (Port) Each ===================================================NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 4.00 850.00 666.50 510.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 4.00 800.00 933.95 725.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 45.00 793.33 828.34 887.35

NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 2.00 500.00 721.19 787.50SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 6.00 600.00 46.33 57.50NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 3.00 550.00 251.25 75.00IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 4.00 1000.00 636.65 442.57STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 2.00 500.00 777.50 525.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 2.00 500.00 1150.09 394.70NH 1602-101 SOUTH FORK JOINT SEAL 05/13/04 3.00 750.00 656.33 529.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 4.00 1000.00 645.63 360.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 4.00 1000.00 1094.94 500.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 2.00 800.00 281.75 475.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 32.00 753.13 623.09 366.62

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 4.00 600.00 467.00 313.00IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 8.00 900.00 760.26 620.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 4.00 1100.00 1371.59 1543.00SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 2.00 700.00 324.75 324.50NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 2.00 1000.00 498.71 450.00STA 149A-021 SH 149 CRIBWALL 09/16/04 2.00 500.00 81.00 81.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 22.00 836.36 764.82 640.68

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 4.00 1200.00 556.00 525.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 4.00 1000.00 1011.16 1500.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 6.00 1500.00 1059.69 1300.00STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 4.00 750.00 603.95 510.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 4.00 750.00 831.25 638.26STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 4.00 750.00 676.85 537.40STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 4.00 900.00 625.72 545.00STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 2.00 500.00 472.50 125.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 4.00 800.00 1035.00 850.00STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 4.00 850.00 778.85 859.95 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 40.00 950.00 782.70 797.81 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 139.00 835.97 764.60 702.66

Page 536: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 492 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80002 Flash Beacon (Solar) Each ===================================================

STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 8.00 400.00 431.25 525.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 8.00 400.00 431.25 525.00

STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 2.00 700.00 84.00 82.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 2.00 600.00 670.25 650.74BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 4.00 800.00 845.36 787.50IM 0761-185 I-76, LOCHBUIE TO HUDSON 06/24/04 4.00 700.00 537.48 442.40 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 12.00 716.67 649.08 532.09

IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 8.00 700.00 1169.15 500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 8.00 700.00 1169.15 500.00

BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 2.00 625.00 861.63 800.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 625.00 861.63 800.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 30.00 621.67 742.46 539.50

=============== 630-80305 Flagging Station Light Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 3.00 300.00 833.80 2200.00C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 2.00 300.00 810.00 810.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5.00 300.00 831.97 1644.00

IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 3.00 1500.00 748.94 442.57 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3.00 1500.00 748.94 442.57 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8.00 750.00 794.87 1193.46

Page 537: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 493 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80334 Barricade (3 F-D) (Temp) Each ===================================================

IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 2.00 800.00 886.96 1500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 800.00 886.96 1500.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 800.00 886.96 1500.00

=============== 630-80335 Barricade (3 M-A) (Temp) Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 4.00 250.00 540.87 374.90IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 18.00 250.00 227.03 250.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 2.00 250.00 191.97 204.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 2.00 200.00 203.50 125.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 26.00 246.15 261.99 256.06

NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 13.00 200.00 156.09 170.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 12.00 120.00 102.69 78.03STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 36.00 75.00 78.08 76.15IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 7.00 200.00 226.88 243.42STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 5.00 200.00 50.00 50.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 250.00 158.25 36.00CC R600-225 CHATFIELD STATE PARK 06/10/04 2.00 300.00 207.50 110.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 6.00 200.00 232.78 226.34 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 82.00 136.46 141.02 115.31

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 2.00 220.00 121.69 78.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 1.00 500.00 247.48 201.30BR 0243-063 EAST OF LIMON 07/15/04 9.00 300.00 267.79 200.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 4.00 175.00 339.61 514.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 4.00 250.00 175.62 123.05 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 20.00 267.00 241.79 235.28

BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 8.00 165.00 146.25 87.00

Page 538: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 494 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80335 Barricade (3 M-A) (Temp) Each ===================================================STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 3.00 150.00 148.33 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 11.00 160.91 146.51 90.55 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 139.00 177.70 193.49 156.94

=============== 630-80336 Barricade (3 M-B) (Temp) Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 6.00 200.00 239.18 100.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 4.00 250.00 226.82 200.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 4.00 275.00 572.37 490.93STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 8.00 270.00 214.00 220.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 10.00 200.00 277.00 260.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 2.00 250.00 138.42 102.35IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 2.00 350.00 324.41 500.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 10.00 175.00 159.63 45.75STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 4.00 250.00 230.00 160.00NH 2872-016 US 287 - LAMAR 03/04/04 12.00 250.00 71.25 55.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 5.00 235.00 76.50 77.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 67.00 232.61 219.92 165.24

NH 2852-010 US 285 & COUNTY RD. G 04/29/04 2.00 250.00 888.03 78.90STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 4.00 190.00 197.25 200.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 21.00 200.00 205.00 260.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 13.00 325.00 225.32 61.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 8.00 235.00 140.13 150.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 2.00 290.00 465.56 452.69BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 8.00 250.00 211.71 189.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 58.00 243.88 238.98 186.69

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 8.00 300.00 267.32 280.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 11.00 300.00 247.48 201.30IMD 0252-364 I-25 OVER BROADWAY 07/29/04 2.00 240.00 383.90 514.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 4.00 300.00 307.80 251.45C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 4.00 250.00 298.80 115.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 2.00 300.00 234.15 450.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 31.00 289.68 277.92 253.16

Page 539: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 495 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80336 Barricade (3 M-B) (Temp) Each ===================================================

MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 2.00 420.00 349.00 270.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 14.00 200.00 215.00 110.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 6.00 180.00 163.70 107.20NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 4.00 200.00 147.38 165.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 26.00 212.31 190.32 130.12 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 182.00 243.02 230.87 182.04

=============== 630-80337 Barricade (3 M-C) (Temp) Each ===================================================

STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 6.00 275.00 218.85 175.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 6.00 275.00 305.29 315.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 8.00 330.00 341.30 360.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 20.00 297.00 298.64 291.00

STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 30.00 200.00 206.50 203.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 4.00 500.00 399.97 300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 34.00 235.29 247.23 214.41

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 6.00 440.00 388.19 514.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 3.00 500.00 211.42 160.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 9.00 460.00 339.98 396.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 8.00 375.00 347.90 250.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 10.00 650.00 739.72 950.00STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 6.00 315.00 225.79 150.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 6.00 315.00 249.80 367.00STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 4.00 300.00 377.49 214.95STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 6.00 300.00 252.29 218.00

Page 540: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 496 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80337 Barricade (3 M-C) (Temp) Each ===================================================NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 10.00 400.00 223.63 214.50STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 6.00 300.00 271.48 215.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 56.00 394.29 343.58 360.80 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 119.00 337.48 316.57 309.91

=============== 630-80338 Barricade (3 M-D) (Temp) Each ===================================================

NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 2.00 500.00 259.50 19.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 500.00 259.50 19.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 500.00 259.50 19.00

=============== 630-80341 Const Traf Sign (A) Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 20.00 90.00 65.18 41.00STA 2911-001 SH 291 SALIDA NORTH 01/08/04 24.00 60.00 28.75 35.00STA 114A-009 S.H. 114, W OF COCHETOPA PASS 01/08/04 21.00 45.00 32.50 27.50NH 5502-045 US550, DURANGO JOINT SEAL 01/08/04 6.00 50.00 79.92 52.00IM 0704-203 I-70, GENOA-EAST, M.P. 374 - 01/15/04 2.00 75.00 59.42 30.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 32.00 65.00 57.94 72.00STA R300-120 R-3 SOUTHWEST CHIPSEAL 01/29/04 61.00 50.00 62.50 50.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 26.00 80.00 45.86 57.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 26.00 80.00 61.02 53.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 28.00 75.00 59.07 64.71STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 2.00 60.00 74.40 90.00STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 34.00 40.00 70.23 75.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 12.00 65.00 52.44 51.60STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 36.00 60.00 63.22 16.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 56.00 50.00 73.98 78.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 10.00 70.00 69.50 75.00IM 0701-164 PARACHUTE EAST & WEST 02/12/04 20.00 60.00 55.60 60.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 4.00 60.00 43.33 35.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 21.00 65.00 48.48 51.17STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 20.00 45.00 22.50 22.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 107.00 90.00 47.51 50.00STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 10.00 45.00 42.50 35.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 10.00 60.00 52.46 54.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 40.00 50.00 35.83 33.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 10.00 55.00 38.10 19.61STA 014A-030 SH 14, WALDEN EAST 03/04/04 4.00 60.00 32.83 30.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 24.00 70.00 77.50 40.00

Page 541: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 497 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80341 Const Traf Sign (A) Each ===================================================NH 2872-016 US 287 - LAMAR 03/04/04 33.00 90.00 40.00 20.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 1.00 60.00 78.88 102.00SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 4.00 60.00 93.33 92.00STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 57.00 40.00 39.00 14.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 15.00 70.00 45.97 62.00C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 11.00 60.00 81.00 81.00SHE R300-113 DOWD BRIDGE, I-70 03/18/04 6.00 50.00 46.56 40.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 24.00 60.00 20.00 20.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 8.00 60.00 82.27 75.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 44.00 55.00 67.50 69.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 8.00 50.00 51.00 43.00STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 47.00 60.00 32.67 47.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 924.00 62.68 53.56 47.65

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 7.00 50.00 47.78 30.00NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 1.00 60.00 32.15 25.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 16.00 50.00 46.79 51.13NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 4.00 55.00 1229.25 68.25SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 30.00 80.00 24.47 34.50NH 0502-053 CIMARRON - WEST 04/15/04 12.00 40.00 51.31 50.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 2.00 70.00 31.25 35.00NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 248.00 62.00 49.76 52.50STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 1.00 60.00 49.08 73.00STA 1191-020 SH 119 ROCKFALL MITIGATION, 2 04/15/04 32.00 80.00 91.00 83.00STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 3.00 60.00 52.33 55.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 13.00 50.00 40.99 41.62STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 92.00 75.00 73.03 71.05IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 86.00 70.00 41.84 38.73STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 2.00 50.00 52.89 50.00SHE 1601-052 R-5, CENTERLINE RUMBLE STRIPS 04/22/04 4.00 55.00 21.33 10.00NH 0741-015 - SMA Alt SH 74 EVERGREEN OVERLAY 04/29/04 4.00 70.00 67.57 65.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 44.00 60.00 55.62 42.10NH 1602-101 SOUTH FORK JOINT SEAL 05/13/04 6.00 35.00 29.67 11.00BR 0362-028 BRIDGE OVER KIOWA CREEK 05/13/04 2.00 90.00 50.00 50.00STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 14.00 60.00 8.33 8.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 20.00 50.00 42.75 44.00STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 2.00 65.00 47.54 11.08STA R400-170 EAST OF HUDSON, EAST 05/27/04 13.00 50.00 47.50 40.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 143.00 70.00 52.50 65.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 64.00 80.00 50.70 49.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 28.00 45.00 50.03 31.60CC R600-225 CHATFIELD STATE PARK 06/10/04 17.00 60.00 54.75 50.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 26.00 65.00 71.25 77.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 17.00 64.00 42.13 45.00

Page 542: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 498 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80341 Const Traf Sign (A) Each ===================================================STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 26.00 60.00 31.19 30.56BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 11.00 60.00 50.00 42.00IM 0761-185 I-76, LOCHBUIE TO HUDSON 06/24/04 8.00 65.00 48.65 44.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 998.00 65.51 58.25 51.95

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 15.00 50.00 53.30 44.00STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 14.00 70.00 39.44 31.25IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 80.00 75.00 73.28 52.00SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 2.00 65.00 36.00 42.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 4.00 100.00 46.77 25.16BR 0243-063 EAST OF LIMON 07/15/04 8.00 60.00 70.43 100.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 217.00 65.00 108.62 133.00STA R200-128 SH10, SH350 , SH160 MAINT. 07/29/04 10.00 70.00 11.67 15.00IM 0701-168 RIFLE TO SILT SLAB REPAIR 08/05/04 8.00 40.00 50.94 45.00SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 1.00 60.00 29.53 27.05STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 6.00 45.00 47.03 58.67NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 71.00 70.00 64.41 65.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 33.00 90.00 70.37 80.25C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 11.00 60.00 66.80 55.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 6.00 65.00 48.67 55.00STA 149A-021 SH 149 CRIBWALL 09/16/04 4.00 40.00 20.00 20.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 32.00 40.00 61.50 53.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 522.00 66.33 81.29 88.06

SHE 105A-010 SH 105/FURROW RD 10/07/04 6.00 75.00 69.33 20.00C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 11.00 60.00 62.50 60.00BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 17.00 65.00 61.88 49.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 80.00 60.00 45.69 53.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 54.00 60.00 51.27 35.00IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 6.00 52.00 20.86 40.00MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 20.00 75.00 69.00 81.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 10.00 50.00 93.33 70.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 30.00 60.00 56.47 53.60STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 50.00 60.00 56.40 51.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 24.00 60.00 65.58 40.42STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 26.00 60.00 56.06 53.75STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 30.00 65.00 55.94 54.50NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 4.00 60.00 47.67 40.00STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 4.00 45.00 60.00 13.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 32.00 65.00 46.00 55.00

Page 543: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 499 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80341 Const Traf Sign (A) Each ===================================================NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 38.00 50.00 42.33 55.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 22.00 50.00 39.36 33.18NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 108.00 60.00 66.84 64.35STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 64.00 60.00 70.93 75.25NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 4.00 55.00 55.53 61.50NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 10.00 55.00 67.67 66.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 650.00 59.86 56.50 55.27 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 3,094.00 63.62 59.70 57.46

=============== 630-80342 Const Traf Sign (B) Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 56.00 120.00 100.68 71.00STA 2911-001 SH 291 SALIDA NORTH 01/08/04 54.00 75.00 55.00 60.00STA 114A-009 S.H. 114, W OF COCHETOPA PASS 01/08/04 44.00 55.00 61.67 55.00NH 5502-045 US550, DURANGO JOINT SEAL 01/08/04 21.00 60.00 87.08 58.00IM 0704-203 I-70, GENOA-EAST, M.P. 374 - 01/15/04 38.00 80.00 78.92 50.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 26.00 100.00 84.18 110.00STA R300-120 R-3 SOUTHWEST CHIPSEAL 01/29/04 46.00 60.00 93.75 110.00C 0342-040 US 34 IN WELD COUNTY 01/29/04 56.00 80.00 68.28 58.12STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 34.00 90.00 78.81 67.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 34.00 90.00 93.71 78.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 54.00 90.00 72.11 52.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 107.00 95.00 112.63 145.05STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 32.00 100.00 104.00 95.00STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 24.00 80.00 100.33 110.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 41.00 75.00 64.44 51.60C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 15.00 85.00 21.08 2.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 74.00 70.00 90.67 51.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 74.00 110.00 109.42 115.00MC R300-118 R-3 PAVEMENT MARKINGS 02/12/04 8.00 90.00 18.33 25.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 67.00 110.00 89.75 115.00IM 0701-164 PARACHUTE EAST & WEST 02/12/04 120.00 80.00 69.60 85.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 86.00 90.00 43.33 35.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 40.00 80.00 86.54 102.34STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 43.00 50.00 34.00 33.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 77.00 120.00 110.89 160.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 22.00 90.00 41.40 95.00STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 36.00 50.00 62.50 55.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 20.00 80.00 83.03 86.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 104.00 60.00 36.67 33.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 116.00 60.00 80.66 33.95STA 014A-030 SH 14, WALDEN EAST 03/04/04 86.00 95.00 48.67 40.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 98.00 90.00 106.25 95.00NH 2872-016 US 287 - LAMAR 03/04/04 76.00 100.00 67.50 50.00

Page 544: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 500 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80342 Const Traf Sign (B) Each ===================================================NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 175.00 70.00 83.88 102.00SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 36.00 70.00 126.67 122.00STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 6.00 60.00 60.50 17.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 70.00 70.00 69.23 87.00C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 28.00 75.00 92.00 92.00SHE R300-113 DOWD BRIDGE, I-70 03/18/04 20.00 65.00 71.44 67.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 51.00 70.00 20.00 20.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 80.00 80.00 89.28 100.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 16.00 56.00 72.00 73.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 92.00 65.00 54.67 49.00STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 4.00 90.00 35.33 43.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,407.00 81.05 80.05 76.10

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 36.00 60.00 86.04 85.00NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 58.00 65.00 57.60 60.00MC R300-119 R-3 STENCIL REGIONWIDE 04/01/04 8.00 90.00 110.00 200.00C R200-126 FY04 REGION 2 SIGNING 04/01/04 14.00 80.00 52.44 114.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 26.00 60.00 75.40 71.58NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 45.00 55.00 82.78 73.50NH 0502-053 CIMARRON - WEST 04/15/04 36.00 45.00 64.19 60.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 48.00 80.00 48.75 45.00NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 12.00 70.00 78.26 105.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 56.00 65.00 89.86 105.00STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 12.00 80.00 60.33 66.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 82.00 180.00 146.71 156.06STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 183.00 100.00 103.25 101.50IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 41.00 100.00 106.53 94.05STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 34.00 60.00 67.00 63.00IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 28.00 47.00 84.17 82.50SHE 1601-052 R-5, CENTERLINE RUMBLE STRIPS 04/22/04 32.00 65.00 28.05 12.00NH 0741-015 - SMA Alt SH 74 EVERGREEN OVERLAY 04/29/04 68.00 80.00 74.23 65.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 52.00 60.00 96.49 102.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 22.00 70.00 68.02 52.60NH 1602-101 SOUTH FORK JOINT SEAL 05/13/04 32.00 45.00 53.00 21.00BR 0362-028 BRIDGE OVER KIOWA CREEK 05/13/04 14.00 100.00 50.00 50.00STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 40.00 90.00 5.67 5.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 88.00 55.00 46.00 44.00STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 14.00 90.00 76.72 22.19BR 0092-018 SH 9, SOUTH OF KREMMLING 05/27/04 11.00 115.00 60.75 55.00AQC R600-215 SH 287, US 36 TO SH 128 05/27/04 10.00 100.00 91.97 235.29STA R400-170 EAST OF HUDSON, EAST 05/27/04 36.00 45.00 57.50 60.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 68.00 90.00 70.00 90.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 90.00 140.00 82.45 59.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 56.00 45.00 80.55 63.20

Page 545: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 501 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80342 Const Traf Sign (B) Each ===================================================CC R600-225 CHATFIELD STATE PARK 06/10/04 2.00 60.00 83.75 98.00STA R400-169 R-4 CHIP SEALS EAST 06/10/04 36.00 45.00 106.67 60.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 50.00 80.00 101.25 77.00STA 0343-023 US 34, EAST OF AKRON 06/17/04 105.00 80.00 98.20 90.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 18.00 90.00 47.63 50.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 73.00 80.00 57.86 56.59BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 47.00 70.00 83.89 78.75IM 0761-185 I-76, LOCHBUIE TO HUDSON 06/24/04 72.00 75.00 56.65 44.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,755.00 81.68 78.91 74.94

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 34.00 60.00 72.31 65.00STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 46.00 80.00 45.93 41.70IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 74.00 85.00 88.54 67.00SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 24.00 90.00 43.00 46.00SHE 0091-023 SH 9 VMS - FAIRPLAY TO FRISCO 07/15/04 13.00 70.00 63.66 77.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 66.00 110.00 66.21 50.33BR 0243-063 EAST OF LIMON 07/15/04 9.00 120.00 114.67 150.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 75.00 120.00 174.62 257.00STA R200-128 SH10, SH350 , SH160 MAINT. 07/29/04 26.00 80.00 19.00 25.00IM 0701-168 RIFLE TO SILT SLAB REPAIR 08/05/04 42.00 55.00 57.13 50.00SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 17.00 65.00 29.53 27.05STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 24.00 50.00 46.85 29.75NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 31.00 90.00 76.61 70.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 71.00 100.00 109.71 107.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 24.00 70.00 98.60 100.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 34.00 80.00 62.33 80.00STA 149A-021 SH 149 CRIBWALL 09/16/04 22.00 55.00 27.00 27.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 149.00 60.00 60.25 42.00SHE 0403-049 US 40, EAST OF CRAIG 09/23/04 12.00 91.00 126.69 90.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 28.00 90.00 51.34 75.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 821.00 81.81 80.57 77.93

SHE 105A-010 SH 105/FURROW RD 10/07/04 20.00 115.00 122.38 50.00SHE 5502-047 SH550 AT MP 112.7, IN OURAY C 10/07/04 2.00 90.00 231.18 125.10STA 0703-290 GEORGETOWN HILL ROCKFALL MITI 10/07/04 48.00 100.00 65.00 55.00C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 36.00 70.00 73.50 72.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 34.00 60.00 57.40 26.00BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 24.00 80.00 90.38 69.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 110.00 90.00 102.75 156.00NH 2873-137 US 287 IN BOULDER & LARIMER C 11/18/04 35.00 80.00 66.51 66.80

Page 546: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 502 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80342 Const Traf Sign (B) Each ===================================================BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 44.00 130.00 98.47 100.00C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 20.00 60.00 70.36 100.00IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 40.00 71.00 23.50 40.00MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 31.00 150.00 113.67 111.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 74.00 70.00 101.67 90.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 36.00 75.00 93.03 107.20STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 52.00 80.00 81.19 77.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 44.00 80.00 84.61 71.27STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 49.00 80.00 71.13 64.50STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 36.00 105.00 72.57 65.40NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 48.00 80.00 55.00 40.00STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 20.00 60.00 65.25 14.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 68.00 100.00 77.67 90.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 76.00 75.00 62.50 75.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 86.00 60.00 52.00 70.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 38.00 60.00 60.17 44.24NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 72.00 100.00 89.20 85.80STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 54.00 75.00 103.26 129.00NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 44.00 75.00 82.33 100.00NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 32.00 75.00 101.25 100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,273.00 83.32 79.48 82.95 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6,256.00 81.79 79.71 77.41

=============== 630-80343 Const Traf Sign (C) Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 8.00 100.00 102.68 102.00STA 2911-001 SH 291 SALIDA NORTH 01/08/04 4.00 85.00 81.00 85.00STA 114A-009 S.H. 114, W OF COCHETOPA PASS 01/08/04 2.00 85.00 87.50 82.50NH 5502-045 US550, DURANGO JOINT SEAL 01/08/04 4.00 80.00 94.08 69.00IM 0704-203 I-70, GENOA-EAST, M.P. 374 - 01/15/04 28.00 85.00 100.67 80.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 12.00 70.00 100.16 110.00STA R300-120 R-3 SOUTHWEST CHIPSEAL 01/29/04 4.00 75.00 112.50 145.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 8.00 110.00 93.69 103.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 8.00 110.00 112.12 105.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 32.00 100.00 80.86 52.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 8.00 110.00 69.44 51.60STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 4.00 110.00 89.54 71.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 8.00 120.00 119.98 115.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 18.00 110.00 103.50 120.00IM 0701-164 PARACHUTE EAST & WEST 02/12/04 84.00 100.00 80.60 110.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 14.00 100.00 43.33 35.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 8.00 140.00 69.85 51.17STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 6.00 70.00 39.25 38.50IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 30.00 150.00 282.39 160.00

Page 547: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 503 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80343 Const Traf Sign (C) Each ===================================================STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 10.00 110.00 44.00 100.00STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 4.00 65.00 62.50 55.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 14.00 100.00 61.88 54.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 26.00 65.00 37.50 33.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 8.00 65.00 133.91 58.45STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 12.00 110.00 119.50 118.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 12.00 90.00 94.02 107.00SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 8.00 80.00 147.00 149.00STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 8.00 75.00 72.75 19.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 20.00 70.00 88.14 104.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 8.00 100.00 20.00 20.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 8.00 100.00 113.45 135.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 4.00 85.50 82.00 83.00STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 4.00 100.00 40.83 56.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 436.00 97.62 104.32 89.99

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 14.00 90.00 90.54 105.00NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 8.00 80.00 75.00 75.00C R200-126 FY04 REGION 2 SIGNING 04/01/04 5.00 88.00 70.77 152.00NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 8.00 55.00 88.93 73.50NH 0502-053 CIMARRON - WEST 04/15/04 4.00 60.00 85.71 80.00NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 8.00 80.00 83.64 105.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 8.00 80.00 106.50 105.00STA 1191-020 SH 119 ROCKFALL MITIGATION, 2 04/15/04 4.00 140.00 114.00 104.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 45.00 180.00 137.30 156.06IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 30.00 130.00 120.51 99.58STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 4.00 70.00 75.07 65.00IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 24.00 60.00 84.17 82.50SHE 1601-052 R-5, CENTERLINE RUMBLE STRIPS 04/22/04 8.00 75.00 32.00 15.00NH 0741-015 - SMA Alt SH 74 EVERGREEN OVERLAY 04/29/04 8.00 90.00 80.90 65.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 12.00 70.00 100.65 153.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 4.00 80.00 82.44 63.20NH 1602-101 SOUTH FORK JOINT SEAL 05/13/04 4.00 60.00 56.67 27.00BR 0362-028 BRIDGE OVER KIOWA CREEK 05/13/04 4.00 110.00 50.00 50.00STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 6.00 110.00 9.33 9.00STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 8.00 110.00 103.28 33.31BR 0092-018 SH 9, SOUTH OF KREMMLING 05/27/04 7.00 125.00 89.13 82.50NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 18.00 110.00 80.00 100.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 4.00 150.00 91.91 67.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 8.00 110.00 73.50 94.70IM 0253-186 I-25, 120TH TO SH 7 06/17/04 8.00 85.00 124.99 100.00STA 0343-023 US 34, EAST OF AKRON 06/17/04 8.00 100.00 128.00 125.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 11.00 100.00 59.50 60.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 8.00 100.00 85.63 84.88

Page 548: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 504 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80343 Const Traf Sign (C) Each ===================================================IM 0761-185 I-76, LOCHBUIE TO HUDSON 06/24/04 44.00 90.00 60.65 44.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 332.00 105.29 91.91 90.15

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 8.00 80.00 91.89 90.00STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 4.00 90.00 56.16 52.15IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 38.00 110.00 95.32 67.00SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 4.00 100.00 65.00 70.00SHE 0091-023 SH 9 VMS - FAIRPLAY TO FRISCO 07/15/04 6.00 100.00 52.74 77.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 12.00 120.00 67.54 50.33IMD 0252-364 I-25 OVER BROADWAY 07/29/04 15.00 130.00 193.62 308.00STA R200-128 SH10, SH350 , SH160 MAINT. 07/29/04 16.00 90.00 23.67 30.00IM 0701-168 RIFLE TO SILT SLAB REPAIR 08/05/04 40.00 80.00 71.94 65.00SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 12.00 90.00 137.60 135.20STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 12.00 75.00 56.22 76.58STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 16.00 110.00 149.87 160.50C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 8.00 85.00 129.70 105.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 8.00 85.00 71.33 80.00STA 149A-021 SH 149 CRIBWALL 09/16/04 4.00 65.00 27.00 27.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 24.00 80.00 64.00 42.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 20.00 110.00 67.85 95.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 247.00 95.91 89.35 89.58

STA 0703-290 GEORGETOWN HILL ROCKFALL MITI 10/07/04 24.00 120.00 77.50 55.00C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 26.00 80.00 84.50 84.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 24.00 100.00 115.41 150.00NH 2873-137 US 287 IN BOULDER & LARIMER C 11/18/04 4.00 95.00 98.66 66.80BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 11.00 130.00 92.22 75.00IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 28.00 90.00 22.29 40.00MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 8.00 150.00 157.00 132.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 19.00 90.00 106.67 100.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 8.00 110.00 63.54 48.25STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 8.00 80.00 82.19 77.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 24.00 80.00 86.95 82.97STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 8.00 80.00 75.44 53.75STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 8.00 60.00 63.44 54.50NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 4.00 100.00 65.00 40.00STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 4.00 75.00 69.50 15.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 26.00 120.00 91.67 110.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 14.00 85.00 65.00 75.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 8.00 70.00 58.33 75.00

Page 549: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 505 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80343 Const Traf Sign (C) Each ===================================================STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 8.00 65.00 78.15 71.88NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 8.00 120.00 111.31 107.25STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 8.00 110.00 101.91 134.35NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 24.00 100.00 85.98 100.00NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 8.00 90.00 112.05 110.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 312.00 96.83 80.45 85.41 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,327.00 99.03 93.66 88.88

=============== 630-80344 Const Traf Sign (Spec) Sq Foot ================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 119.00 20.00 18.78 26.00IM 0704-203 I-70, GENOA-EAST, M.P. 374 - 01/15/04 32.00 20.00 13.38 10.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 79.00 30.00 16.91 17.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 224.00 20.00 15.77 18.55STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 224.00 20.00 16.51 12.50IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 32.00 18.00 16.91 10.50NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 654.00 18.00 14.28 14.50STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 72.00 18.00 14.89 12.40STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 76.00 19.00 17.21 18.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 274.00 20.00 17.07 18.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 147.00 20.00 17.50 18.00IM 0701-164 PARACHUTE EAST & WEST 02/12/04 256.00 19.00 15.10 20.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 64.00 10.00 9.67 8.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 49.50 20.00 20.60 20.47IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 151.00 20.00 15.45 15.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 64.00 20.00 19.49 20.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 446.00 19.00 11.32 2.94STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 96.00 20.00 13.75 8.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 320.00 13.00 21.13 22.25STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 64.00 20.00 17.23 15.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 3,443.50 18.73 15.81 15.03

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 132.00 18.00 19.60 19.25STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 104.00 18.00 18.61 20.45NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 160.00 20.00 17.95 18.90ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 171.00 25.00 87.26 22.89IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 328.00 20.00 13.90 13.28STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 120.00 20.00 13.06 9.34NH 0741-015 - SMA Alt SH 74 EVERGREEN OVERLAY 04/29/04 32.00 20.00 19.68 18.75SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 80.00 17.00 18.62 16.00

Page 550: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 506 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80344 Const Traf Sign (Spec) Sq Foot ================================================STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 32.00 20.00 20.90 15.54NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 827.00 15.00 12.00 15.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 216.00 22.00 16.08 14.00CC R600-225 CHATFIELD STATE PARK 06/10/04 178.00 18.00 16.00 18.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 300.00 16.00 18.97 20.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 66.00 18.00 20.08 19.24 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2,746.00 18.09 19.00 16.52

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 400.00 20.00 17.16 20.00BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 209.00 25.00 25.29 23.15BR 0243-063 EAST OF LIMON 07/15/04 501.00 20.00 14.95 15.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1,715.00 15.00 18.65 25.00IM 0701-168 RIFLE TO SILT SLAB REPAIR 08/05/04 500.00 20.00 6.50 5.00STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 48.00 14.00 16.18 16.79NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 114.00 17.00 16.96 16.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 267.75 20.00 17.14 13.91SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 40.00 16.00 16.92 25.00STA 149A-021 SH 149 CRIBWALL 09/16/04 95.00 15.00 15.00 15.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 60.00 20.00 13.38 9.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 3,949.75 17.77 16.47 19.01

BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 20.00 20.00 14.35 8.80IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 368.00 20.00 13.99 13.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 846.00 15.00 13.30 13.00IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 144.00 19.00 13.43 15.00MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 82.60 25.00 23.33 20.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 448.00 14.50 19.67 18.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 144.00 18.00 19.26 21.45STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 140.00 19.00 27.59 13.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 120.00 19.00 15.40 14.89STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 240.00 16.00 18.10 20.40STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 144.00 20.00 20.84 20.70STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 95.00 15.00 10.88 10.50IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 4.00 20.00 21.87 20.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 36.00 15.00 19.86 16.59NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 112.00 20.00 15.60 15.00STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 224.00 18.00 17.56 15.05NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 45.00 20.00 16.57 16.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3,212.60 17.19 16.52 15.52 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 13,351.85 17.94 16.73 16.63

Page 551: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 507 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80350 Vert Panel Each ===================================================

STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 100.00 20.00 20.65 20.30STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 75.00 8.00 8.11 8.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 175.00 14.86 13.13 15.03 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 175.00 14.86 13.13 15.03

=============== 630-80351 Vert Panel (Plastic) Each ===================================================

C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 35.00 25.00 47.00 47.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 35.00 25.00 47.00 47.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 35.00 25.00 47.00 47.00

=============== 630-80355 Port Mesg Panel Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 8.00 8000.00 7620.46 5100.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 4.00 9000.00 6215.44 5600.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 4.00 8000.00 4057.79 4120.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 4.00 8000.00 4793.07 3700.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 2.00 25000.00 19804.18 18967.91STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 2.00 8000.00 4334.19 3100.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 4.00 9000.00 7754.73 5000.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 6.00 12000.00 8242.53 2500.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 2.00 4750.00 5392.59 3343.54STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 2.00 8500.00 5550.00 3200.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 2.00 3800.00 9046.42 7100.00SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 2.00 4000.00 3536.67 3100.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 2.00 10000.00 700.00 650.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 6.00 8000.00 8924.49 6250.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 4.00 8000.00 1550.00 1600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 54.00 8890.74 7128.78 4672.28

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 2.00 7000.00 12896.15 12531.75NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 2.00 5000.00 5151.06 5500.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 2.00 7000.00 9926.00 9360.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 5.00 22000.00 16950.99 15606.00

Page 552: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 508 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80355 Port Mesg Panel Each ===================================================STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 6.00 8500.00 8260.00 8120.00IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 4.00 10000.00 5729.21 5753.45SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 2.00 6000.00 9038.71 8000.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 2.00 10000.00 7962.10 4210.50STA R400-170 EAST OF HUDSON, EAST 05/27/04 4.00 7500.00 2750.00 3000.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 2.00 14000.00 11952.34 14100.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 2.00 7000.00 2459.30 1842.00STA R400-169 R-4 CHIP SEALS EAST 06/10/04 4.00 7500.00 3666.67 3000.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 4.00 750.00 10490.98 8200.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 4.00 10000.00 6052.86 5658.59IM 0761-185 I-76, LOCHBUIE TO HUDSON 06/24/04 2.00 7000.00 3822.41 2212.05 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 47.00 9148.94 8072.14 7334.27

STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 2.00 6500.00 1648.25 1043.00IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 2.00 14000.00 7795.00 8800.00BR 0243-063 EAST OF LIMON 07/15/04 3.00 9000.00 6311.02 5992.00SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 1.00 6000.00 2692.00 2704.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 2.00 8000.00 4398.69 4300.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 3.00 6500.00 9725.37 6420.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 2.00 7500.00 7333.33 5000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 15.00 8300.00 6641.07 5215.07

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 4.00 6000.00 8688.89 7500.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 4.00 10000.00 6660.07 5000.00C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 4.00 5000.00 5550.02 4415.00MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 2.00 10000.00 9266.67 10000.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 2.00 5000.00 6833.33 8000.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 4.00 5000.00 3624.26 750.55STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 4.00 4000.00 3777.63 4100.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 2.00 4000.00 5471.76 5318.82STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 4.00 7500.00 5065.46 3761.85STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 4.00 7000.00 4498.26 4360.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 2.00 10000.00 4858.33 3100.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 4.00 10000.00 3133.33 3200.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 2.00 4500.00 3655.40 1382.38NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 2.00 9000.00 3992.81 3861.25STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 4.00 5000.00 6902.83 6449.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 48.00 6729.17 5385.73 4614.03 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 164.00 8278.05 6818.53 5467.76

Page 553: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 509 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80356 Flash Arrow Panel (A Ty) Each ===================================================

IM 0701-157 FRUITA TO CLIFTON 02/26/04 4.00 750.00 714.00 550.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 2.00 1000.00 1847.78 2040.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 1.00 1000.00 678.67 486.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 7.00 857.14 1060.14 966.57

NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 1.00 1500.00 633.75 360.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1.00 1500.00 633.75 360.00

NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 2.00 1200.00 1300.00 1200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 1200.00 1300.00 1200.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 10.00 990.00 1054.70 952.60

=============== 630-80357 Flash Arrow Panel (B Ty) Each ===================================================

NH 5502-045 US550, DURANGO JOINT SEAL 01/08/04 2.00 1000.00 786.33 863.00STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 2.00 1500.00 1003.33 1000.00C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 2.00 900.00 693.00 693.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 6.00 1133.33 879.31 852.00

NH 1602-101 SOUTH FORK JOINT SEAL 05/13/04 2.00 1000.00 586.00 430.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 2.00 1400.00 2340.06 2600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 4.00 1200.00 1755.37 1515.00

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 1.00 1200.00 914.00 270.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 1200.00 914.00 270.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 11.00 1163.64 1204.67 1040.18

Page 554: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 510 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80358 Flash Arrow Panel (C Ty) Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 6.00 1500.00 1029.83 510.00IM 0704-203 I-70, GENOA-EAST, M.P. 374 - 01/15/04 2.00 1000.00 685.50 600.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 2.00 1000.00 1562.09 2100.00C 0342-040 US 34 IN WELD COUNTY 01/29/04 2.00 700.00 444.10 581.18STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 4.00 1300.00 906.13 1290.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 4.00 1300.00 1094.09 835.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 3.00 1100.00 1062.19 780.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 2.00 1000.00 3569.01 4463.04STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 2.00 1000.00 1016.74 515.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 2.00 1100.00 1178.29 1530.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 5.00 1600.00 1451.74 1700.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 2.00 1250.00 2400.00 2600.00IM 0701-164 PARACHUTE EAST & WEST 02/12/04 4.00 1000.00 1340.00 4000.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 2.00 1250.00 1028.30 716.38IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 3.00 1500.00 1657.68 3000.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 2.00 1000.00 625.21 536.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 2.00 800.00 1153.97 1023.83NH 2872-016 US 287 - LAMAR 03/04/04 2.00 1100.00 1300.00 1000.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 2.00 600.00 1233.75 862.00SHE R300-113 DOWD BRIDGE, I-70 03/18/04 1.00 1000.00 1035.00 840.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 2.00 1000.00 200.00 200.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 4.00 1000.00 1632.72 1150.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 1.00 860.00 930.00 950.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 61.00 1158.36 1261.27 1430.24

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 2.00 1000.00 1155.00 1550.00MC R300-119 R-3 STENCIL REGIONWIDE 04/01/04 1.00 900.00 1833.33 4000.00C R200-126 FY04 REGION 2 SIGNING 04/01/04 2.00 800.00 502.48 756.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 2.00 1000.00 755.65 715.85NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 2.00 750.00 804.88 630.00NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 2.00 1100.00 823.90 945.00STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 2.00 900.00 770.00 800.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 6.00 2500.00 2498.74 2288.88STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 2.00 1000.00 1032.50 1015.00IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 2.00 1200.00 2103.86 1549.01IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 2.00 1100.00 948.33 880.00NH 0741-015 - SMA Alt SH 74 EVERGREEN OVERLAY 04/29/04 2.00 1000.00 717.87 315.00AQC R600-215 SH 287, US 36 TO SH 128 05/27/04 2.00 1000.00 1526.21 2941.18NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 6.00 700.00 1000.00 1500.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 2.00 1000.00 580.68 421.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 4.00 750.00 1418.24 1000.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 2.00 600.00 958.21 892.50

Page 555: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 511 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80358 Flash Arrow Panel (C Ty) Each ===================================================IM 0761-185 I-76, LOCHBUIE TO HUDSON 06/24/04 3.00 1000.00 1090.60 553.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 46.00 1108.70 1241.78 1287.25

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 2.00 1500.00 2023.21 930.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 5.00 1100.00 3550.60 5144.00IM 0701-168 RIFLE TO SILT SLAB REPAIR 08/05/04 4.00 1000.00 378.13 350.00SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 1.00 800.00 545.38 540.75STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 2.00 600.00 390.00 464.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 2.00 2000.00 922.78 850.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 2.00 1200.00 1114.69 1326.80SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 2.00 1500.00 1583.33 1000.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 2.00 900.00 1950.00 1600.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 2.00 1000.00 950.40 1500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 24.00 1154.17 1588.96 1791.76

STA 0703-290 GEORGETOWN HILL ROCKFALL MITI 10/07/04 2.00 1700.00 575.00 400.00C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 2.00 900.00 740.00 480.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 4.00 1500.00 1532.57 575.00NH 2873-137 US 287 IN BOULDER & LARIMER C 11/18/04 2.00 1000.00 839.44 719.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 3.00 1500.00 3080.03 1500.00C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 2.00 1000.00 1240.95 1605.00IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 2.00 1250.00 685.71 500.00MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 4.00 1400.00 1121.67 700.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 3.00 1200.00 1100.00 1000.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 4.00 1000.00 1593.95 4288.70STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 4.00 900.00 1092.50 1200.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 4.00 900.00 589.93 744.64STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 4.00 1000.00 959.96 859.85STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 4.00 1000.00 1034.49 872.00NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 1.00 800.00 1600.00 2200.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 2.00 1000.00 1986.67 1300.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 2.00 1000.00 1308.33 1300.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 2.00 1000.00 1058.29 884.72NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 2.00 1500.00 1334.28 1287.10STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 4.00 1000.00 1437.07 1612.45NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 2.00 1000.00 1145.50 1500.00NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 2.00 750.00 1278.55 1200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 61.00 1113.11 1233.77 1237.09 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 192.00 1131.56 1281.21 1379.81

Page 556: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 512 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80359 Port Mesg Panel Day ====================================================

STA R300-120 R-3 SOUTHWEST CHIPSEAL 01/29/04 90.00 170.00 70.00 75.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 140.00 90.00 114.65 105.00STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 400.00 100.00 57.92 85.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 120.00 85.00 87.30 71.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 400.00 90.00 140.75 100.00IM 0701-164 PARACHUTE EAST & WEST 02/12/04 380.00 150.00 79.80 110.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 160.00 100.00 90.21 71.64IM 0701-157 FRUITA TO CLIFTON 02/26/04 200.00 100.00 66.67 65.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 30.00 150.00 159.33 150.00STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 60.00 115.00 123.75 160.00SHE R300-113 DOWD BRIDGE, I-70 03/18/04 10.00 100.00 336.75 307.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 45.00 100.00 92.00 81.00STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 140.00 130.00 67.33 79.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2,175.00 111.36 87.68 92.92

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 120.00 85.00 97.71 95.00C R200-126 FY04 REGION 2 SIGNING 04/01/04 12.00 200.00 172.48 158.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 10.00 85.00 146.78 138.06NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 20.00 120.00 138.80 136.50NH 0502-053 CIMARRON - WEST 04/15/04 400.00 125.00 77.50 80.00STA 1191-020 SH 119 ROCKFALL MITIGATION, 2 04/15/04 88.00 120.00 136.67 125.00STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 42.00 120.00 139.00 120.00NH 0741-015 - SMA Alt SH 74 EVERGREEN OVERLAY 04/29/04 24.00 200.00 94.90 80.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 180.00 80.00 81.75 82.00STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 20.00 200.00 148.13 138.75NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 392.00 200.00 70.00 60.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 1,308.00 139.95 91.73 82.89

BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 440.00 350.00 108.28 46.19IMD 0252-364 I-25 OVER BROADWAY 07/29/04 60.00 125.00 179.13 205.00IM 0701-168 RIFLE TO SILT SLAB REPAIR 08/05/04 130.00 110.00 94.25 80.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 24.00 105.00 139.80 175.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 654.00 272.66 114.41 72.21

STA 0703-290 GEORGETOWN HILL ROCKFALL MITI 10/07/04 60.00 160.00 85.00 70.00

Page 557: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 513 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80359 Port Mesg Panel Day ====================================================C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 40.00 90.00 80.00 60.00NH 2873-137 US 287 IN BOULDER & LARIMER C 11/18/04 50.00 115.00 79.57 71.90NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 10.00 150.00 666.67 400.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 200.00 120.00 98.33 110.00NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 100.00 100.00 79.51 58.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 460.00 118.37 95.27 91.29 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4,597.00 143.14 92.20 86.96

=============== 630-80360 Drum Channel Dev Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 200.00 45.00 43.32 31.00STA 2911-001 SH 291 SALIDA NORTH 01/08/04 150.00 50.00 38.70 40.00NH 5502-045 US550, DURANGO JOINT SEAL 01/08/04 100.00 30.00 24.00 29.00STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 500.00 40.00 37.80 23.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 200.00 50.00 29.09 51.50STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 200.00 50.00 40.62 42.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 75.00 50.00 52.50 52.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 500.00 45.00 60.54 72.52STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 100.00 45.00 25.90 25.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 100.00 50.00 24.61 20.65C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 36.00 60.00 10.58 2.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 60.00 50.00 39.02 36.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 300.00 40.00 43.46 42.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 100.00 50.00 48.00 42.00IM 0701-164 PARACHUTE EAST & WEST 02/12/04 100.00 45.00 57.80 75.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 20.00 40.00 43.33 35.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 50.00 60.00 36.65 30.70STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 200.00 25.00 18.30 17.60IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 95.00 50.00 46.26 65.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 60.00 35.00 25.80 30.00STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 50.00 30.00 40.00 30.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 100.00 50.00 34.38 33.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 500.00 24.00 34.17 33.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 100.00 50.00 107.02 9.60STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 200.00 40.00 52.50 70.00NH 2872-016 US 287 - LAMAR 03/04/04 136.00 45.00 41.50 30.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 150.00 40.00 40.71 25.50SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 20.00 50.00 65.67 70.00STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 4.00 50.00 65.00 30.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 200.00 50.00 35.51 37.00C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 56.00 40.00 40.00 40.00SHE R300-113 DOWD BRIDGE, I-70 03/18/04 30.00 50.00 31.91 35.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 20.00 50.00 16.50 13.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 300.00 40.00 56.77 45.00

Page 558: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 514 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80360 Drum Channel Dev Each ===================================================STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 140.00 35.00 40.50 41.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 50.00 40.00 45.00 38.00STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 20.00 40.00 30.00 34.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 5,222.00 41.52 42.50 39.97

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 200.00 45.00 40.42 40.50NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 50.00 40.00 36.10 40.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 300.00 50.00 36.35 30.68SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 110.00 50.00 27.30 23.00NH 0502-053 CIMARRON - WEST 04/15/04 250.00 32.00 45.00 45.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 163.00 40.00 29.88 20.00NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 16.00 40.00 34.04 31.50STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 16.00 40.00 42.94 36.40STA 1191-020 SH 119 ROCKFALL MITIGATION, 2 04/15/04 80.00 80.00 57.00 51.00STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 50.00 60.00 39.33 36.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 672.00 60.00 56.58 52.02IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 150.00 40.00 49.54 39.83STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 100.00 50.00 47.00 42.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 150.00 35.00 39.87 33.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 10.00 35.00 84.03 78.90NH 1602-101 SOUTH FORK JOINT SEAL 05/13/04 100.00 30.00 34.00 22.00STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 150.00 40.00 5.00 4.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 150.00 40.00 45.25 44.00BR 0092-018 SH 9, SOUTH OF KREMMLING 05/27/04 50.00 45.00 28.50 19.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 200.00 60.00 52.50 55.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 375.00 60.00 43.10 41.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 16.00 30.00 31.75 21.10CC R600-225 CHATFIELD STATE PARK 06/10/04 40.00 50.00 40.00 27.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 200.00 40.00 43.25 25.00STA 0343-023 US 34, EAST OF AKRON 06/17/04 50.00 40.00 42.70 40.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 50.00 40.00 50.50 50.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 4.00 35.00 37.74 36.22BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 150.00 35.00 35.00 33.50 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3,852.00 48.09 41.84 38.16

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 200.00 45.00 50.59 45.00STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 300.00 40.00 23.46 20.85IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 200.00 45.00 29.16 23.00SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 100.00 50.00 32.00 45.00SHE 0091-023 SH 9 VMS - FAIRPLAY TO FRISCO 07/15/04 10.00 50.00 24.95 16.50

Page 559: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 515 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80360 Drum Channel Dev Each ===================================================BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 100.00 80.00 29.75 20.13BR 0243-063 EAST OF LIMON 07/15/04 50.00 50.00 54.61 47.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 54.00 60.00 75.33 72.00IM 0701-168 RIFLE TO SILT SLAB REPAIR 08/05/04 324.00 40.00 27.94 25.00SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 50.00 50.00 29.03 27.05STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 40.00 30.00 26.72 6.10NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 300.00 50.00 23.09 22.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 150.00 50.00 47.04 53.50C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 100.00 35.00 31.66 25.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 100.00 50.00 46.00 35.00STA 149A-021 SH 149 CRIBWALL 09/16/04 80.00 30.00 7.00 7.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 400.00 40.00 27.75 13.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 100.00 50.00 33.84 30.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2,658.00 45.26 33.54 27.03

SHE 105A-010 SH 105/FURROW RD 10/07/04 100.00 50.00 35.07 28.00STA 0703-290 GEORGETOWN HILL ROCKFALL MITI 10/07/04 50.00 50.00 32.50 25.00C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 20.00 60.00 65.00 60.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 100.00 60.00 22.50 16.00BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 82.00 40.00 32.75 39.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 500.00 30.00 45.95 45.00NH 2873-137 US 287 IN BOULDER & LARIMER C 11/18/04 300.00 30.00 18.76 16.40BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 300.00 60.00 49.81 60.00C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 100.00 50.00 44.11 53.50STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 110.00 40.00 51.67 45.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 50.00 42.00 40.58 48.25STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 300.00 40.00 25.17 21.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 100.00 40.00 26.65 42.55STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 200.00 50.00 41.67 23.66STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 50.00 40.00 30.47 27.25NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 100.00 60.00 41.67 30.00STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 25.00 45.00 28.75 14.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 100.00 50.00 55.00 45.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 100.00 25.00 41.33 40.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 175.00 40.00 22.67 28.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 100.00 40.00 31.81 16.59NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 200.00 40.00 22.36 21.45STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 200.00 42.00 36.08 27.95NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 75.00 42.00 30.57 24.00NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 100.00 40.00 24.12 22.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 3,537.00 42.03 34.01 33.11 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 15,269.00 43.95 39.17 35.67

Page 560: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 516 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80363 Drum Channel Dev (Light) (F) Each ===================================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 4.00 75.00 57.00 60.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 10.00 60.00 79.60 83.68IM 0701-164 PARACHUTE EAST & WEST 02/12/04 25.00 70.00 68.80 105.00STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 8.00 40.00 22.50 22.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 10.00 60.00 29.00 45.00STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 10.00 35.00 62.50 55.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 10.00 45.00 33.67 33.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 20.00 60.00 50.60 41.00C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 6.00 50.00 52.00 52.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 2.00 70.00 18.00 16.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 5.00 45.00 51.67 45.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 110.00 56.68 54.06 59.97

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 4.00 55.00 38.70 45.00NH 0502-053 CIMARRON - WEST 04/15/04 9.00 50.00 67.07 70.00NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 4.00 50.00 37.26 31.50STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 4.00 55.00 48.94 52.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 30.00 50.00 61.53 86.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 4.00 60.00 91.24 84.20STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 10.00 60.00 11.50 11.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 10.00 45.00 45.25 44.00BR 0092-018 SH 9, SOUTH OF KREMMLING 05/27/04 4.00 60.00 63.13 43.50NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 20.00 75.00 69.00 68.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 25.00 90.00 62.17 61.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 4.00 40.00 29.00 26.30STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 4.00 40.00 67.55 65.64BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 6.00 50.00 89.25 89.25 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 138.00 61.52 59.36 62.12

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 10.00 70.00 110.01 55.00STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 20.00 60.00 35.70 31.30IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 50.00 55.00 50.63 47.00IM 0701-168 RIFLE TO SILT SLAB REPAIR 08/05/04 10.00 60.00 34.13 35.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 6.00 70.00 65.84 64.20STA 149A-021 SH 149 CRIBWALL 09/16/04 5.00 40.00 21.00 21.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 20.00 45.00 42.25 26.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 121.00 55.95 53.84 40.38

Page 561: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 517 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80363 Drum Channel Dev (Light) (F) Each ===================================================

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 10.00 75.00 34.30 32.00BR 0361-064 DRAW W. OF LAST CHANCE 10/21/04 2.00 50.00 62.50 79.00NH 2873-137 US 287 IN BOULDER & LARIMER C 11/18/04 2.00 50.00 88.79 25.70STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 6.00 60.00 75.00 50.00STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 3.00 60.00 37.25 15.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 20.00 70.00 64.33 60.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 4.00 40.00 73.50 85.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 20.00 50.00 50.67 70.00NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 10.00 50.00 38.77 28.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 77.00 59.09 53.77 53.17 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 446.00 58.40 55.54 54.15

=============== 630-80364 Drum Channel Dev (Light) (SB) Each ===================================================

NH 5502-045 US550, DURANGO JOINT SEAL 01/08/04 20.00 40.00 37.75 35.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 10.00 55.00 30.20 45.00IM 0701-157 FRUITA TO CLIFTON 02/26/04 25.00 40.00 33.83 33.00NH 2872-016 US 287 - LAMAR 03/04/04 25.00 50.00 42.00 30.00C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 20.00 60.00 64.00 64.00SHE R300-113 DOWD BRIDGE, I-70 03/18/04 30.00 65.00 40.34 40.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 50.00 50.00 74.41 47.00STA 0063-016 CLIFTON TO PALISADE 03/25/04 15.00 50.00 57.00 51.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 195.00 51.28 52.40 42.67

STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 20.00 80.00 46.33 41.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 10.00 45.00 45.25 44.00BR 0092-018 SH 9, SOUTH OF KREMMLING 05/27/04 10.00 50.00 70.75 49.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 40.00 63.75 53.00 43.75

IM 0701-168 RIFLE TO SILT SLAB REPAIR 08/05/04 68.00 65.00 39.31 35.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 20.00 50.00 42.50 26.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 88.00 61.59 40.04 32.95

Page 562: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 518 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80364 Drum Channel Dev (Light) (SB) Each ===================================================

MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 100.00 75.00 75.00 72.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 100.00 75.00 75.00 72.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 423.00 60.21 53.84 47.68

=============== 630-80365 Port Mesg Panel (State Furn) Each ===================================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 2.00 750.00 741.00 600.00STA 114A-009 S.H. 114, W OF COCHETOPA PASS 01/08/04 2.00 500.00 480.00 440.00NH 5502-045 US550, DURANGO JOINT SEAL 01/08/04 2.00 500.00 623.33 460.00STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 1.00 500.00 1412.50 525.00STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 2.00 800.00 725.00 450.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 9.00 622.22 687.91 491.67

NH 1602-101 SOUTH FORK JOINT SEAL 05/13/04 2.00 500.00 152.67 160.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 500.00 152.67 160.00

STA 149A-021 SH 149 CRIBWALL 09/16/04 2.00 500.00 675.00 675.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 500.00 675.00 675.00

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 2.00 450.00 712.00 110.00STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 2.00 500.00 975.00 150.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 4.00 475.00 828.89 130.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 17.00 558.82 675.84 389.12

=============== 630-80367 Port Traf Speed Monitor Each ===================================================

STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 2.00 4000.00 4262.50 1050.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 4000.00 4262.50 1050.00

Page 563: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 519 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80367 Port Traf Speed Monitor Each ===================================================

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 2.00 17000.00 6918.40 4200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 2.00 17000.00 6918.40 4200.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 4.00 10500.00 5856.04 2625.00

=============== 630-80370 Conc Barrier (Temp) Lin Foot ===============================================

STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 200.00 20.00 39.86 31.00NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 7,000.00 21.00 29.26 31.03STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 320.00 17.67 25.00 12.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 100.00 25.00 21.54 14.33STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 10,000.00 18.00 13.48 5.06STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 2,070.00 11.00 13.56 13.25NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 1,200.00 20.00 24.15 16.00C R300-116 GRAND JUNCTION GUIDE SIGNS 03/18/04 420.00 20.00 26.00 26.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 200.00 22.00 20.00 10.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 300.00 15.00 19.65 18.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 7,490.00 18.00 17.00 14.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 29,300.00 18.36 19.85 15.33

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 150.00 18.00 24.58 20.00NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 1,500.00 15.00 19.00 10.00STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 90.00 20.00 24.73 25.38SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 500.00 20.00 18.46 19.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 600.00 25.00 32.80 26.00BR 0092-018 SH 9, SOUTH OF KREMMLING 05/27/04 100.00 25.00 24.63 37.50NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 6,900.00 17.00 23.71 27.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 690.00 16.00 27.36 15.80SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 130.00 25.00 23.00 19.00STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 460.00 20.00 24.70 27.10BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 2,200.00 15.00 25.37 29.60 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 13,320.00 17.14 23.94 24.50

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 1,400.00 20.00 26.06 37.00

Page 564: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 520 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80370 Conc Barrier (Temp) Lin Foot ===============================================IMD 0252-364 I-25 OVER BROADWAY 07/29/04 3,200.00 16.00 10.15 7.67NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 4,400.00 20.00 20.91 20.50STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1,000.00 21.00 21.07 20.00NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 2,000.00 17.00 53.75 38.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 12,000.00 18.52 24.48 21.88

SHE 105A-010 SH 105/FURROW RD 10/07/04 1,850.00 19.00 15.11 8.00C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 200.00 66.00 25.50 25.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 15,000.00 15.00 16.48 12.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 3,000.00 15.00 10.85 15.00IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 150.00 25.00 37.46 20.00MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 200.00 55.00 65.67 74.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 20,400.00 16.33 16.26 12.87 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 75,020.00 17.62 20.18 17.34

=============== 630-80376 Gdrail Ty 7 (Temp) Lin Foot ===============================================

STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 3,210.00 20.00 59.50 39.00IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 4,908.00 18.00 18.65 18.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 8,118.00 18.79 24.39 26.30

ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 500.00 25.00 65.07 144.62IM 0252-360 I-25 R.R. OVERPASS - CASTLE R 04/15/04 140.00 25.00 27.35 30.33 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 640.00 25.00 50.16 119.62

IM 0701-168 RIFLE TO SILT SLAB REPAIR 08/05/04 3,000.00 17.00 44.26 48.00C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 100.00 18.00 30.09 25.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 3,100.00 17.03 43.69 47.26

C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 1,070.00 40.00 42.20 16.00

Page 565: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 521 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80376 Gdrail Ty 7 (Temp) Lin Foot ===============================================IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 630.00 40.00 33.75 32.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1,700.00 40.00 38.70 21.93 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 13,558.00 21.34 30.63 34.95

=============== 630-80380 Traffic Cone Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 600.00 13.00 10.83 12.00STA 2911-001 SH 291 SALIDA NORTH 01/08/04 175.00 10.00 6.95 7.00STA 114A-009 S.H. 114, W OF COCHETOPA PASS 01/08/04 300.00 10.00 6.00 6.00NH 5502-045 US550, DURANGO JOINT SEAL 01/08/04 200.00 12.00 11.50 11.00IM 0704-203 I-70, GENOA-EAST, M.P. 374 - 01/15/04 400.00 9.00 10.29 7.50STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 300.00 12.00 10.11 8.00STA R300-120 R-3 SOUTHWEST CHIPSEAL 01/29/04 150.00 10.00 9.13 11.00C 0342-040 US 34 IN WELD COUNTY 01/29/04 200.00 10.00 10.09 9.30STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 500.00 12.00 9.15 8.75STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 500.00 12.00 11.97 15.00IM 0703-286 I-70, E & W OF IDAHO SPRINGS 01/29/04 500.00 14.00 10.32 5.25NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 350.00 14.00 13.13 15.62STA 1604-008 US 160C, PRITCHETT TO US 287 02/05/04 200.00 10.00 12.50 11.00STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 100.00 13.00 11.03 12.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 600.00 10.00 10.62 10.35C 001A-038 SH 1 & LARIMAR CO RD 54 02/05/04 50.00 15.00 4.17 2.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 400.00 10.00 8.48 4.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 500.00 10.00 13.63 16.50STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 600.00 10.00 13.63 19.00IM 0701-164 PARACHUTE EAST & WEST 02/12/04 1,000.00 10.00 9.90 15.00STA 131A-031 SH 131, MP 13.6 TO MP 30.8 02/26/04 300.00 8.00 8.50 7.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 400.00 12.00 9.66 8.19STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 400.00 12.00 4.70 4.40IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 581.00 12.00 10.96 10.00STA 3501-010 SH 350 - BESHOUR JUNCTION 02/26/04 140.00 10.00 5.80 8.00STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 200.00 10.00 12.00 12.00C 074A-007 SH 74 @ BRYANT DR. 02/26/04 300.00 10.00 10.93 10.75IM 0701-157 FRUITA TO CLIFTON 02/26/04 500.00 7.00 7.00 7.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 600.00 9.00 11.64 2.81STA 014A-030 SH 14, WALDEN EAST 03/04/04 300.00 10.00 6.58 5.00STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 500.00 12.00 8.75 8.00NH 2872-016 US 287 - LAMAR 03/04/04 250.00 15.00 9.25 7.00NH 0853-053 FT. LUPTON TO PLATTEVILLE 03/04/04 200.00 10.00 10.88 12.50SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 300.00 10.00 15.92 14.25STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 150.00 10.00 12.00 10.00STA R600-189 R-6 SIGNAL PROJECTS 03/11/04 300.00 10.00 8.20 11.15SHE R300-113 DOWD BRIDGE, I-70 03/18/04 50.00 10.00 9.16 15.00NH 0504-046 SH 50B - TROY TO SH 233 03/18/04 300.00 10.00 9.00 8.00

Page 566: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 522 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80380 Traffic Cone Each ===================================================STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 300.00 10.00 10.40 12.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 200.00 8.00 2.05 2.10STA 0063-016 CLIFTON TO PALISADE 03/25/04 300.00 9.00 9.67 9.00STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 150.00 12.00 8.33 8.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 14,346.00 10.72 10.26 9.90

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 600.00 10.00 9.47 6.10NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 200.00 10.00 8.10 6.00MC R300-119 R-3 STENCIL REGIONWIDE 04/01/04 100.00 10.00 20.00 25.00C R200-126 FY04 REGION 2 SIGNING 04/01/04 75.00 8.00 8.68 7.65STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 300.00 10.00 12.40 12.27NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 400.00 12.00 10.82 10.50SHE M086-041 SH50B @ TROY AVE & WILLS BLVD 04/08/04 150.00 10.00 4.82 1.15NH 0502-053 CIMARRON - WEST 04/15/04 50.00 8.00 11.27 10.00NH 0505-039 US 50, EAST OF LAS ANIMAS 04/15/04 200.00 12.00 8.88 7.00NH 2873-123 U.S. 287, IN LOVELAND NB & SB 04/15/04 200.00 7.00 9.91 9.50STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 200.00 10.00 10.96 10.40STA 1191-020 SH 119 ROCKFALL MITIGATION, 2 04/15/04 100.00 12.00 11.33 10.00STA M555-023 I-70B & US 50, GRAND JCT. 04/15/04 50.00 13.00 15.33 16.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 960.00 10.00 11.38 10.40STA 0853-051 US 85 BUS, 22ND - 5TH ST., GR 04/15/04 400.00 10.00 10.33 10.15STA 0091-021 SH 9 - FAIRPLAY DRAINAGE 04/22/04 200.00 10.00 12.44 12.60IM 0253-188 I-25 MEDIAN SAFETY RAIL 04/22/04 800.00 6.00 7.25 6.50SHE 1601-052 R-5, CENTERLINE RUMBLE STRIPS 04/22/04 500.00 10.00 3.93 2.50NH 0741-015 - SMA Alt SH 74 EVERGREEN OVERLAY 04/29/04 150.00 10.00 18.13 15.00SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 100.00 10.00 11.80 16.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 30.00 10.00 9.41 5.30NH 1602-101 SOUTH FORK JOINT SEAL 05/13/04 250.00 7.00 9.83 7.50BR 0362-028 BRIDGE OVER KIOWA CREEK 05/13/04 50.00 15.00 10.00 10.00STA 165A-010 ON SH 165A FROM I-25 TO W/O R 05/20/04 300.00 12.00 2.33 1.00STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 300.00 10.00 10.88 11.00STA 0092-017 2 MILES N. OF SILVERTHORNE 05/20/04 400.00 13.00 12.43 9.11BR 0092-018 SH 9, SOUTH OF KREMMLING 05/27/04 50.00 20.00 6.00 4.00AQC R600-215 SH 287, US 36 TO SH 128 05/27/04 200.00 12.00 12.34 14.12STA R400-170 EAST OF HUDSON, EAST 05/27/04 300.00 11.00 10.00 10.00NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 75.00 15.00 10.00 12.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 200.00 16.00 10.41 10.00NH 0361-076 US 36 IN BOULDER COUNTY 06/10/04 300.00 10.00 11.34 11.60CC R600-225 CHATFIELD STATE PARK 06/10/04 300.00 10.00 9.50 6.00STA R400-169 R-4 CHIP SEALS EAST 06/10/04 600.00 11.00 5.00 5.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 300.00 10.00 11.67 10.00STA 0343-023 US 34, EAST OF AKRON 06/17/04 250.00 12.00 11.55 11.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 30.00 10.00 156.43 12.50STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 50.00 10.00 5.55 5.66

Page 567: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 523 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80380 Traffic Cone Each ===================================================BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 200.00 7.00 8.74 8.40IM 0761-185 I-76, LOCHBUIE TO HUDSON 06/24/04 500.00 7.00 10.29 7.75 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 10,420.00 10.06 10.38 8.59

STA 0131-041 SH 13, SOUTH OF MEEKER, M.P. 07/01/04 100.00 10.00 7.94 6.00STA 086A-040 SH 86, ELBERT COUNTY 07/01/04 100.00 10.00 9.44 8.35IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 500.00 10.00 11.86 10.00SHE 105A-011 SH 105 NEAR SEDALIA 07/15/04 50.00 13.00 10.00 12.00SHE 0091-023 SH 9 VMS - FAIRPLAY TO FRISCO 07/15/04 100.00 10.00 9.16 7.70BR 0061-073 US 6 OVER CLEAR CREEK AND EL 07/15/04 60.00 20.00 11.04 10.07BR 0243-063 EAST OF LIMON 07/15/04 200.00 10.00 12.09 12.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 930.00 11.00 14.78 14.40STA R200-128 SH10, SH350 , SH160 MAINT. 07/29/04 150.00 10.00 8.00 8.00IM 0701-168 RIFLE TO SILT SLAB REPAIR 08/05/04 50.00 10.00 6.50 5.00SHE 0253-184 I-25 NEAR LARKSPUR 08/05/04 150.00 10.00 7.51 5.41STA 2854-107 SH285 / CR43A IN PARK COUNTY 08/05/04 300.00 8.00 9.04 4.64NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 200.00 10.00 4.64 4.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 450.00 15.00 12.01 11.77C 060A-006 SH 60 & SH 257 IN MILLIKEN 08/19/04 250.00 10.00 11.86 11.00SHE 4701-105 C-470; BROADWAY TO I-25 08/26/04 300.00 15.00 10.67 11.00STA 149A-021 SH 149 CRIBWALL 09/16/04 50.00 7.00 1.40 1.40NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 500.00 10.00 8.80 3.20SHE 0403-049 US 40, EAST OF CRAIG 09/23/04 200.00 10.00 11.93 15.00IM 0251-167 PINON REST AREAS ON I-25, MP 09/23/04 150.00 12.00 9.51 10.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4,790.00 11.04 11.07 9.64

SHE 105A-010 SH 105/FURROW RD 10/07/04 100.00 15.00 8.03 12.00SHE 5502-047 SH550 AT MP 112.7, IN OURAY C 10/07/04 50.00 10.00 20.42 7.78STA 0703-290 GEORGETOWN HILL ROCKFALL MITI 10/07/04 200.00 15.00 8.38 6.75C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 60.00 12.00 6.50 6.00C 1601-054 US 160 MONTOYA SLIDE #1 10/21/04 50.00 12.00 6.52 1.10IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 600.00 10.00 13.61 11.00NH 2873-137 US 287 IN BOULDER & LARIMER C 11/18/04 150.00 9.00 8.74 6.20BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 200.00 12.00 14.67 15.00C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 175.00 12.00 10.98 8.75IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 500.00 10.00 5.36 9.00MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 150.00 12.00 14.67 15.00STA 0243-069 SH 24 IN LIMON, I AVE EAST TO 12/02/04 300.00 9.30 13.00 15.00STA 095A-006 SHERIDAN BLVD. - US 6 TO 25TH 12/09/04 500.00 12.00 10.24 10.70STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 500.00 12.00 7.00 7.00

Page 568: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 524 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80380 Traffic Cone Each ===================================================NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 300.00 10.00 9.84 13.83STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 400.00 10.00 12.19 10.75STA 391A-002 KIPLING: US 40 TO 38TH AVE. 12/23/04 650.00 12.00 10.62 10.90NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 400.00 10.00 8.33 10.00STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 25.00 15.00 12.13 8.00IM 0703-287 I-70, BAKERVILLE EAST OVERLAY 12/23/04 500.00 14.00 13.50 15.00NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 200.00 8.00 11.58 12.00NH 0502-056 - ALT B US 50 PONCHA SPRINGS TO SALID 12/23/04 250.00 10.00 9.33 12.00STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 600.00 12.00 9.22 9.95NH 0021-026 SH2 - 124TH TO BROMLEY LN 12/23/04 400.00 10.00 9.10 8.60STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 500.00 12.00 13.85 12.90NH 0831-095 SH 83, LINCOLN AVE. - PARKER 12/23/04 200.00 10.00 10.19 8.00NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 300.00 12.00 8.60 8.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 8,260.00 11.24 10.28 10.65 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 37,816.00 10.69 10.38 9.67

=============== 630-80384 Tubular Marker Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 405.00 16.00 29.48 25.66STA 0341-050 US 34, JEFFERSON TO MONROE 02/05/04 300.00 20.00 30.43 32.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 705.00 17.70 29.89 28.36

NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 180.00 25.00 23.50 22.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 180.00 25.00 23.50 22.00

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 300.00 25.00 16.57 18.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 300.00 25.00 16.57 18.00

NH 2873-137 US 287 IN BOULDER & LARIMER C 11/18/04 500.00 28.00 13.26 10.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 500.00 28.00 13.26 10.30 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1,685.00 22.84 20.61 20.48

Page 569: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 525 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80391 Channel Dev (Fixed) Each ===================================================

STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 300.00 55.00 58.00 84.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 300.00 55.00 58.00 84.00

NH 0821-064 SH 82, GLENWOOD SPGS - ALT B 06/03/04 180.00 56.00 47.00 64.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 180.00 56.00 47.00 64.00

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 125.00 50.00 37.10 40.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 125.00 50.00 37.10 40.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 605.00 54.26 51.00 68.96

=============== 630-80401 Delin (Ty I) (Temp) Each ===================================================

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 120.00 20.00 22.65 26.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 120.00 20.00 22.65 26.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 120.00 20.00 22.65 26.00

=============== 630-80403 Delin (Ty III) (Temp) Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 50.00 40.00 21.52 17.85 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 50.00 40.00 21.52 17.85

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 4.00 25.00 25.90 26.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 4.00 25.00 25.90 26.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 54.00 38.89 21.84 18.46

Page 570: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 526 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80510 Mobile Pvmt Mkg Zone LUMP SUM ===============================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 1.00 2000.00 2034.50 5000.00STA 114A-009 S.H. 114, W OF COCHETOPA PASS 01/08/04 1.00 2500.00 2166.67 1000.00STA R300-120 R-3 SOUTHWEST CHIPSEAL 01/29/04 1.00 1000.00 3625.00 4500.00MC R300-118 R-3 PAVEMENT MARKINGS 02/12/04 1.00 15000.00 3166.67 7500.00STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 1.00 1000.00 750.00 900.00STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 1.00 2000.00 3000.00 2000.00STA 014A-030 SH 14, WALDEN EAST 03/04/04 1.00 2000.00 2363.33 2500.00SHE R400-164 R-4 SAFETY PROJECTS 03/11/04 1.00 5000.00 1140.00 1100.00STA 009A-023 SUMMIT COUNTY LINE NORTH 03/11/04 1.00 1000.00 1656.25 1100.00STA 133A-028 SH 133, W OF PAONIA DAM 03/25/04 1.00 1500.00 2141.67 2200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 10.00 3300.00 2249.00 2780.00

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 1.00 3000.00 2740.00 2500.00STA 2571-008 SH 257: US 34 TO MILLIKEN 04/15/04 1.00 3000.00 1544.00 260.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 1.00 3000.00 1223.26 526.30STA R400-170 EAST OF HUDSON, EAST 05/27/04 1.00 1100.00 894.88 789.75IM 0761-185 I-76, LOCHBUIE TO HUDSON 06/24/04 1.00 5000.00 3784.83 4424.15 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 5.00 3020.00 2193.19 1700.04

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 4000.00 1425.00 1100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 4000.00 1425.00 1100.00

IM 0705-074 I-70, WEST OF BURLINGTON 11/18/04 1.00 8000.00 2429.86 509.05NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 1.00 5000.00 1771.67 2000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 6500.00 2126.08 1254.53 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 18.00 3616.67 2168.45 2217.18

=============== 630-80520 Mobile Pvmt Mkg Zone Day ====================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 10.00 500.00 265.34 160.00

Page 571: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 527 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80520 Mobile Pvmt Mkg Zone Day ====================================================STA 2854-097 US 285, LAFAYETTE TO DAHLIA 01/29/04 10.00 500.00 596.67 580.00STA 1211-058 SH 121 (WADS), 90TH TO 104TH 01/29/04 2.00 600.00 660.84 515.00STA 1211-059 SH 121 (WADS) - 6TH TO GRANDV 01/29/04 5.00 500.00 502.38 525.00STA 0853-052 SANTA FE DR., FLORIDA TO I-25 02/05/04 6.00 300.00 443.88 465.00STA 1211-057 SH 121; BELLEVIEW TO HAMPDEN 02/12/04 5.00 400.00 430.53 460.00STA 0404-040 COLFAX AVE -SHERIDAN - E/O OF 02/12/04 2.00 400.00 721.71 350.00STA 0881-013 SH 88, ALAMEDA TO LOUISIANA 02/12/04 6.00 300.00 468.75 500.00STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 10.00 300.00 649.69 767.54 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 56.00 412.50 507.65 491.44

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 6.00 300.00 139.03 110.00STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 2.00 400.00 645.25 869.24IM 0253-186 I-25, 120TH TO SH 7 06/17/04 12.00 300.00 494.98 460.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 20.00 310.00 395.87 395.92

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 6.00 500.00 936.64 1050.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 3.00 400.00 337.98 106.38STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 2.00 300.00 450.60 537.40STA 0831-093 PARKER RD: PEORIA TO JEWELL A 12/23/04 6.00 500.00 945.10 110.59STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 5.00 500.00 178.24 107.50NH 0404-041 SH 40 (COLFAX AVE.) - QUEBEC 12/23/04 6.00 500.00 238.88 150.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 28.00 475.00 573.54 349.82 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 104.00 409.62 506.03 434.94

=============== 630-80560 Mobile Profilograph Oper Zone LUMP SUM ===============================================

STA 2911-001 SH 291 SALIDA NORTH 01/08/04 1.00 2000.00 4442.06 5000.00STA 114A-009 S.H. 114, W OF COCHETOPA PASS 01/08/04 1.00 2500.00 3333.33 2500.00STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 1.00 1000.00 575.00 550.00STA 0241-042 US 24, N OF BUENA VISTA 02/26/04 1.00 2000.00 4500.00 5000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 4.00 1875.00 3447.11 3262.50

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 1.00 1800.00 2783.33 1000.00

Page 572: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 528 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-80560 Mobile Profilograph Oper Zone LUMP SUM ===============================================NH 2852-010 US 285 & COUNTY RD. G 04/29/04 1.00 3000.00 1220.26 526.30 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 2400.00 2072.85 763.15

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 1.00 5000.00 1400.00 1300.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 5000.00 1400.00 1300.00

NH 0502-055 DAWSON CREEK TO MONARCH PASS 12/23/04 1.00 5000.00 5616.67 2000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 1.00 5000.00 5616.67 2000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 8.00 2787.50 3125.61 2234.54

=============== 630-85006 Impact Atten (Sand Fill) (Temp) Each ===================================================

STA 003A-001 SH 3, EAST OF DURANGO 02/26/04 8.00 1000.00 1107.50 715.00STU M240-081 POWERS BLVD TO SH83, COLO. S 03/18/04 4.00 1110.00 1550.00 1600.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 12.00 1036.67 1255.00 1010.00

NH 2854-072 US 285: MORRISON RD TO KIPLIN 04/01/04 2.00 3000.00 4038.33 3000.00NH 2852-010 US 285 & COUNTY RD. G 04/29/04 2.00 2000.00 2860.52 1052.60STA 006A-035 SH 6, W OF GRAND JCT - FRUITA 05/20/04 4.00 2750.00 1762.50 1650.00SHE 096A-036 SH96, PUEBLO, ACERO - ORMAN 06/17/04 2.00 1800.00 1693.75 1500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 10.00 2460.00 2582.94 1770.52

NH 1602-100 GRANDVIEW 4TH LANE 09/16/04 6.00 1000.00 2407.50 530.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 6.00 1000.00 2407.50 530.00

BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 6.00 3000.00 4336.97 3000.00

Page 573: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 529 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-85006 Impact Atten (Sand Fill) (Temp) Each ===================================================STA 0073-006 SH 7: 1ST AVENUE TO I-76 12/23/04 2.00 4000.00 4355.68 3100.00NH 2854-104 SH 285 - KENOSHA PASS EAST 12/23/04 2.00 3400.00 2266.67 2400.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 10.00 3280.00 4031.10 2900.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 38.00 1995.79 2745.96 1631.72

=============== 630-85010 Impact Atten (Temp) Each ===================================================

NH 0403-035 BERTHHOUD FALLS W. 2 MI. 01/29/04 4.00 3000.00 5159.41 13389.11STA 391A-001 SH 391: SH 285 TO W. JEWELL A 02/26/04 4.00 1500.00 2761.90 3070.18IM 0252-359 CASTLE PINES INTERCHANGE 02/26/04 5.00 4500.00 4150.13 7500.00STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 8.00 4000.00 4717.34 906.65STA 0405-030 SH 40 & 385, CHEYENNE WELLS 03/04/04 2.00 5000.00 5050.00 2000.00STA C470-026 SH83, Hilltop Rd. to Stroh Rd 03/18/04 2.00 5000.00 4743.85 3200.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 25.00 3700.00 4285.89 4839.61

NH 2873-134 US 287, VIRGINIA DALE N & S 04/01/04 2.00 12000.00 5576.90 2500.00ITS SW00-264 I-70 WEST, FIBER OPTIC 04/15/04 3.00 3500.00 7430.48 3615.39SHE 052A-020 SH 52, I-25 TO US 287 04/29/04 2.00 7000.00 4001.98 3850.00NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 13.00 6500.00 3465.83 1800.00BR 0063-013 SH 6, PAWNEE CREEK STR. B-23- 06/17/04 2.00 4000.00 6685.71 3000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 22.00 6409.09 4352.05 2406.64

IM 0761-183 FT. MORGAN TO BRUSH (PHASE I) 07/01/04 4.00 5000.00 6735.48 5200.00IMD 0252-364 I-25 OVER BROADWAY 07/29/04 3.00 7500.00 14727.58 7390.00NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 4.00 5000.00 1247.50 1100.00STA 0091-016 PARK AVENUE IN BRECKENRIDGE 08/12/04 1.00 4500.00 5554.56 8500.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 12.00 5583.33 7191.04 4655.83

SHE 105A-010 SH 105/FURROW RD 10/07/04 2.00 6000.00 2782.94 4000.00C 0702-253 I-70 CULVERT REPAIRS Ph II 10/14/04 1.00 6500.00 4100.00 4200.00IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 12.00 4000.00 5778.83 5800.00C R600-232 SH 285 AT VARIOUS LOCATIONS 11/18/04 2.00 5000.00 6777.27 5350.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 17.00 4500.00 5530.62 5441.18 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 76.00 4960.53 4928.71 4240.88

Page 574: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 530 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-85040 Impact Atten (T-M-A) (Temp) Each ===================================================

STA 0062-015 US 6: WADSWORTH TO FEDERAL 01/08/04 2.00 5000.00 9848.30 6150.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 2.00 5000.00 9848.30 6150.00

NH R600-220 C-470(4) & I-70(1) RAMP METER 04/08/04 1.00 5000.00 2431.52 2100.00IM 0253-186 I-25, 120TH TO SH 7 06/17/04 2.00 8000.00 25563.91 13000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 3.00 7000.00 14768.79 9366.67

MC R600-226 R-6, BRIDGE DECK REPAIR 12/02/04 2.00 10000.00 12816.67 17000.00NH 0853-054 US 85 - 136TH TO WELD CTY ROA 12/23/04 2.00 8500.00 23516.77 7446.34STA 1281-009 SH 128- US 287 TO MELODY 12/23/04 2.00 8500.00 21505.44 19346.75STA 095A-007 SHERIDAN BLVD: I-76 TO 68TH 12/23/04 1.00 9000.00 21259.46 7524.70 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 7.00 9000.00 20358.91 13587.27 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 12.00 7833.33 16158.55 11292.57

=============== 630-85115 Impact Atten (Quadguard) (Temp) Each ===================================================

STA R400-146 HOLYOKE AREA, STR. B-28-A & A 06/17/04 2.00 14000.00 5391.28 5673.83 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 14000.00 5391.28 5673.83 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 14000.00 5391.28 5673.83

=============== 630-86800 Traffic Signal (Temp) LUMP SUM ===============================================

STA 0831-089 SH 83, ARAPAHOE TO ORCHARD 02/26/04 1.00 20000.00 12665.83 8205.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FIRST QUARTER 1.00 20000.00 12665.83 8205.00

STU M055-016 COLFAX: PEORIA TO POTOMAC 04/08/04 1.00 3000.00 16172.52 20452.67

Page 575: cost data 2004 english cover · projects bid from 01/01/04 through 12/31/04-----bid contractor/ letting project number location dist terrain bids awarded bid index-----04010802 asphalt

COLORADO DEPARTMENT OF TRANSPORTATION 12:05 Friday, January 28, 2005 531 ITEM UNIT COSTS BY PROJECTS -- 2004 COST DATA------------------------------------------------------------------------------------------------------------------------------------ ITEM NUMBER/ ITEM DESCRIPTION/ UNIT/PROJECT NUMBER PROJECT LOCATION DATE LET QUANTITY ENGR. EST. AVERAGE BID AWARDED BID------------------------------------------------------------------------------------------------------------------------------------

=============== 630-86800 Traffic Signal (Temp) LUMP SUM ===============================================NH 0852-089 US 85, C-470 TO LOUVIER 06/03/04 1.00 32000.00 21407.75 29100.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE SECOND QUARTER 2.00 17500.00 18266.61 24776.34

NH 0243-068 US 24, CONSTITUTION TO GARRET 08/12/04 1.00 25000.00 14315.79 14000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 25000.00 14315.79 14000.00

IM 0253-173 I-25 / 120TH BRIDGE REPLACEME 10/28/04 1.00 25000.00 53811.84 56000.00BR 0021 024 SH 2, FLYOVER BRIDGE, N OF I 11/18/04 1.00 50000.00 36996.04 36000.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 37500.00 47085.52 46000.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 6.00 25833.33 25405.79 27292.95

=============== 630-86820 Traffic signal(Temp.)(State Furnished) Each ===================================================

STA 145A-035 SH145 - OPHIR CRIBWALL FAILUR 12/23/04 2.00 2500.00 725.00 150.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE FOURTH QUARTER 2.00 2500.00 725.00 150.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 2.00 2500.00 725.00 150.00

=============== 652-00000 Fire Protection Syst LUMP SUM ===============================================

IMD 0252-364 I-25 OVER BROADWAY 07/29/04 1.00 50000.00 47280.12 34350.00 -------------- --------------- --------------- --------------- WEIGHTED AVERAGE FOR THE THIRD QUARTER 1.00 50000.00 47280.12 34350.00 ============== =============== =============== =============== WEIGHTED AVERAGE FOR THE YEAR 1.00 50000.00 47280.12 34350.00