Construction-sector_update-Oct-09

  • Upload
    nrsc

  • View
    215

  • Download
    0

Embed Size (px)

Citation preview

  • 8/7/2019 Construction-sector_update-Oct-09

    1/118

    Edelweiss Value ScannerEdelweiss Value ScannerEdelweiss Value ScannerEdelweiss Value ScannerEdelweiss Value Scanner

    1

  • 8/7/2019 Construction-sector_update-Oct-09

    2/118

    1 Edelweiss Securities Limited

    Executive Summary

    Executive Summary

    Indias road infrastructure woefully inadequate

    As per the Global Competitiveness Report 2008-09, inadequate infrastructure is the

    biggest stumbling block in Indias economic growth. While India has the second largest

    road network in the world, the report ranks it at a dismal 87 th spot as far as quality

    of roads is concerned, way below neighbours China, Pakistan, and Sri Lanka.

    With the kind of multiplier effect that roads have on economic growth, a quantum

    increase in investments in roads is paramount to achieve long-term growth targets.

    Light at the end of the tunnel

    The National Highway Development Programme (NHDP) is Indias flagship and the

    worlds largest PPP road development programme. It had hit speed bumps in 2006-

    08, primarily due to frequent changes in the regulatory framework and economic slowdown.

    However, 2009 has come as a breath of fresh air; since December 2008, the National

    Highway Authority of India (NHAI) has awarded (or is evaluating bids for) 24

    projects worth INR 228 bn. NHAI has an ambitious target of awarding 23,000 km

    of roads during the next two years. It expects to receive bids for 49 projects

    spread over 5,074 km, worth INR 511 bn by 2009 end. The government has set an

    ambitious target of building 20 km of road per day. Amidst all this, encouraging signs on

    credit availability, interest rates and capital markets mean that achieving financial closure

    (FC) on projects has become considerably easier compared to last year. This infuses us

    with the confidence that the travails of the past three years are behind us and the project

    award process is likely to be on the fast track.

    Size of opportunity at central and state level-humungous

    The chronic underinvestment in roads over the past 60 years has meant that huge

    investment is required over the next couple of years to prop up the road infrastructure.At the national level, of the total 54,454 km under the NHDP (including the

    NHDP Phase IV), 36,926 km of roads are still to be awarded. Overall, the NHAI

    expects to spend about INR 3,315 bn on completion of the balance part of NHDP. This is

    in addition to the huge opportunity available for road development at the state level with

    states like Karnataka (INR 1,770 bn opportunity in 2009-15), Andhra Pradesh, and

    Gujarat taking steps to improve road infrastructure.

    Outlook: Good long-term opportunity

    The governments seriousness towards road development is evident from the steps taken

    in the past couple of months to make projects more commercially viable. The major

    stumbling block now is getting the funding required for the ambitious plans announced-

    both debt and equity. In our view, cracking the funding code is the key to

    unlocking the PPP opportunity in the medium term. The sheer scale of government

    plans means that there are likely to be ample opportunities for every player in the road

    segment. We initiate coverage on IRB Infrastructure, the leader in the Indian road

    BOT space, with a BUY recommendation. While past has been good, the future

    promises to be better than ever for the company which has built up an impressive

    portfolio of lucrative projects. With the focus of this report being on developers, we also

    feature IVRCL (BUY), Nagarjuna (BUY), GMR (REDUCE), Reliance Infra (BUY),

    Gammon (HOLD), Sadbhav Engineering (NOT RATED), Madhucon Projects (NOT

    RATED), and Gayatri Projects (NOT RATED) in this report.

  • 8/7/2019 Construction-sector_update-Oct-09

    3/118

    2 Edelweiss Securities Limited

    Construction

    Contents

    At a glance ................................................................................................................. 3

    Road infrastructure woefully inadequate ......................................................................... 4

    Light at end of tunnel .................................................................................................. 6

    Huge opportunity at centre and state levels .................................................................. 18

    Time To Think About The Constraints ........................................................................... 26

    Foreign Companies in NHDP: Changing Scenario ........................................................... 33

    Annexure I: Frequent policy changes and their impact on project award .................... 35

    Annexure II: Steps taken to attract more interest for NHDP projects ......................... 36

    Annexure III: Work plan (for Aug-09 Jul 10) for ministry of roads .......................... 37

    Annexure IV: National highway opportunity (phase wise) ......................................... 38

    BOT Projects Snapshot ............................................................................................... 39

    Companies

    IRB Infrastructure ............................................................................................... 41

    Gammon India .................................................................................................... 63

    Gayatri Projects .................................................................................................. 71

    GMR Infrastructure .............................................................................................. 77

    IVRCL Infrastructure ............................................................................................ 83

    Madhucon Projects .............................................................................................. 89

    Nagarjuna Construction ....................................................................................... 95

    Reliance Infrastructure ...................................................................................... 101

    Sadbhav Engineering ......................................................................................... 107

  • 8/7/2019 Construction-sector_update-Oct-09

    4/118

  • 8/7/2019 Construction-sector_update-Oct-09

    5/118

    4 Edelweiss Securities Limited

    Construction

    Road Infrastructure Woefully Inadequate

    As per the Global Competitiveness Report 2008-09, inadequate infrastructure is the biggest

    stumbling block in Indias economic growth. While India has the second largest road system

    in the world at 3.3 mn km, the report ranks the country at a dismal 87 th position as far

    as the quality of roads is concerned, way below neighbours China, Pakistan, and Sri

    Lanka.

    Table 1: India ranks w ay below in quality of roads

    Country Ranking for quality of roads

    France 1

    Switzerland 2

    USA 8

    Malaysia 17

    Japan 19

    UK 24

    South Africa 40

    China 51

    Sri Lanka 63

    Pakistan 69

    India 87

    Source: World Economic Forum, Global Competitiveness Report 2008-09, Edelweiss research

    The inadequacy issue becomes evident from the fact that the average distance covered on

    roads by truck in India is less than 250 km per day compared to ~1,000 km per day in the

    US. While the high volume of vehicles on Indian highways, various tax regimes, and frequent

    check posts on state borders are also culprits, a major portion of the blame lies with the

    inferior quality of roads.

    Table 2: China versus I ndiaA case study in r oad quality and impl ementation success

    China India

    In 1988, China did not have an inch of expressway. The

    original plan, considered ambitious at that time, was to build

    upto 35,000 km of National Trunk Highway System (NTHS),

    of which 70% was to be expressways, before 2020. The

    NTHS was completed by the end of 2007, 13 years

    ahead of the original plan.

    Expressways in India with a length of 200 km form a

    minuscule share of the overall road network; national

    highways (NHs) and state highways (SHs) at 2% and 4%

    respectively, do not fare much better. Also, while NHs

    carry 40% o f the overall roadtraffic, only 14% of

    them are 4/6/ 8 laned. SHs, of which only 0.6% are 4-

    laned, are in a worse situation.

    At the end of 2008, the Chinese national expressway

    network stood at 60,300 km (of which 6,433 km was built in

    2008). This makes it the world's second longest

    expressway network, after the United States and roughly

    equal to that of Canada, Germany, and France combined.

    The NHDP has repeatedly suffered cost and time overruns

    over its lifetime. NHDP Phase I and II, originally

    intended to be completed by 2003 and 2004 ,

    respectively, are still not completed and are likely to

    miss their revised timelines too. The same is likely to betrue for Phase III and V.

    The plan is to increase the total length of expressways to

    65,000 km by 2010, 85,000 kilometers by 2020, 120,000

    km by 2030, and 175,000 km by 2050. By 2010, the

    Chinese expressway network will connect all provincial

    capitals and cities with at least half-a-million population, as

    well as some with population ranging between 200,000 and

    500,000. The annual investment between 2010 and

    2020 is projected at USD 12 bn.

    Between 1951 and 2006, the vehicle population grew at a

    CAGR of close to 11%; the freight and passenger traffic

    carried by roads grew at a CAGR of 10%. On the other hand,

    the total road length grew at a CAGR of 3.9% with the NH

    segment increasing by a mere 2.2 %. Also, it is estimated

    that 50% of state and district roads (forming 18% of

    the overall road network) are of poor quality, causing

    a loss of INR 60 bn per annum.

    Source: Edelweiss research

    Quality of Indian roads hasbeen judged poorercompared to neighbours like

    China, Pakistan and SriLanka

    China is much ahead ofIndia, both in terms ofquality as well asimplementation success inroad development

  • 8/7/2019 Construction-sector_update-Oct-09

    6/118

    Edelweiss Securities Limited 5

    Construction

    While quality continues to be an issue, road transport has emerged as the dominant segment

    in Indias transportation sector. The entire increase in the transportation sectors share in the

    GDP between 1999-2000 and 2004-05 came from the road segment. During the past few

    years, road transport has grown at a much higher rate compared to other competing modes

    like inland waterways, railways, and airways.

    All this makes it imperative for a quantum increase in road investments, which is also

    necessary to achieve the countrys long-term growth targets. An INR 1 mn investment in

    roads (at constant 1993 prices) helps 165 persons cross the poverty line. A World Bank study

    has assessed that every rupee invested in the highways sector yields 7x returns in economic

    value. With this kind of multiplier effect, it is high time for India to increase its investment in

    improving its road network, both in terms of length and quality.

  • 8/7/2019 Construction-sector_update-Oct-09

    7/118

    6 Edelweiss Securities Limited

    Construction

    Light At End Of Tunnel

    The National Highway Development Programme (NHDP), Indias flagship highway programme,

    had hit speed bumps in 2006-08, first due to frequent changes in the regulatory framework

    (p lease r e fe r A nnex u r e I ) and later due to an economic slowdown. The project award by

    NHAI, which had touched new highs during 2005-06, progressively slowed down in the past

    three years.

    Chart 1: NHAI project award and implementation in various years

    0

    1,000

    2,000

    3,000

    4,000

    5,000

    1999-00

    2000-01

    2001-02

    2002-03

    2003-04

    2004-05

    2005-06

    2006-07

    2007-08

    2008-09

    (km)

    Project awarded Completed

    Source: Government documents, Edelweiss research

    The implementation of the new Model Concession Agreement (MCA) affected project awards

    in 2006 and 2007. As against the original target of awarding projects spanning 10,641 km in

    2008-09, the revised plan had envisaged NHAI awarding 60 BOT projects spread across

    6,412 km. These projects worth ~INR 700 bn were to be awarded before March 2009.However, the imbroglio over the new pre qualification guidelines derailed the plans in H1CY08

    and the economic slump and the liquidity crunch scuppered the dream in H2CY08. The NHAI

    awarded eight projects spanning 643 km, worth INR 86 bn in FY09 under NHDP.

    Table 3: NHDP targets and achievements in past two years

    Target

    (km)

    Achievement

    (%)

    Target

    (km)

    Achievement

    (%)

    Completion 437 49 220 60

    Tolling 1,869 55 2,003 61

    Phase II Completion 2,013 55 2,522 61

    Phase III Award of project 3,278 9 6,047 10

    Phase V Contract 2,995 29 3,754 0

    2007-08 2008-09

    Phase I

    NHDP Phase Category

    Source: Government documents, Edelweiss research

    What has changed?

    With the NHDP suffering setbacks, the government took a series of steps to improve the

    attractiveness of NHAI projects and address concerns of the road developer fraternity

    (p lease r e fe r A nnex u r e I I ). The positive effect of these measures is trickling in now.

    Regulatory issues andeconomic slump affectedproject award adversely

  • 8/7/2019 Construction-sector_update-Oct-09

    8/118

    Edelweiss Securities Limited 7

    Construction

    Also, the liquidity crunch which had plagued the corporate world in the last quarter of 2008 is

    now a thing of the past.

    Chart 2: Net reverse repo position

    (1,200)

    (600)

    0

    600

    1,200

    1,800

    Apr-08 Jun-08 Aug-08 Oct-08 Dec-08 Feb-09 Apr-09 Jun-09 Aug-09

    (INRbn)

    Net reverse repo

    Source: Bloomberg, Edelweiss research

    The Reserve Bank of India (RBI ) has taken various measures since September 2008,

    which have resulted in augmentation of actual/potential liquidity of over INR 4,220

    bn . In addition, the permanent reduction in the SLR by 1.0% of NDTL (net demand and time

    liabilities) has made available liquid funds of INR 400 bn for credit expansion.

    Table 4: RBI measures to boost liquidity

    Sl. No. Measure Amount (INR bn)

    1 CRR reduction 1,600

    2 Unwinding/Buyback/De-sequestering of MSS securities 978

    3 Term repo facility 6004 Increase in export credit refinance 255

    5 Special refinance facility for SCBs (Non-RRBs) 385

    6 Refinance facility for SIDBI/NHB/EXIM Bank 160

    7 Liquidity facility for NBFCs through SPV 250

    Total 4,228

    Source: RBI, Edelweiss research

    Another helping hand was lent by the cooling down of soaring interest rates, which had

    adversely impacted project viability. RBI has cut the repo rate by 425bps and the reverse

    repo rate by 275bps since September 2008, thus sending a strong signal to banks to reduce

    interest rates. Reduction in the reverse repo rate was also a step towards discouraging banks

    from parking their surplus funds with the central bank. This resulted in banks cutting their

    lending rates with the prime lending rate of State Bank of India falling by 200bps since

    September 2008.

    Liquidity situation hasconsiderably improved ascompared to last year

  • 8/7/2019 Construction-sector_update-Oct-09

    9/118

    8 Edelweiss Securities Limited

    Construction

    Chart 3: Reduction in interes t rates

    3.0

    5.3

    7.6

    9.9

    12.2

    14.5

    Aug-08

    Sep-08

    Oct-08

    Nov-08

    Dec-08

    Jan-09

    Feb-09

    Mar-09

    Apr-09

    May-09

    Jun-09

    Jul-09

    Aug-09

    (%)

    SBI prime lending rate Repo rate

    Source: RBI, Edelweiss research

    The risk aversion of lenders to BOT projects (which are typically long term in nature) has also

    decreased. Further, projects that are being awarded now will come up for financial closure

    (FC) only towards the latter part of H2FY10 after completing various formalities. We expect

    the situation on the FC front to improve by then.

    And, last, business confidence has also recovered, with signs of a turnaround, rally in equity

    markets across the globe, and a positive election outcome. The governments stated

    objective of increased spending on infra projects (which was evident in the increased

    allocation for various infra schemes in Budget 2009-10) has also come like a shot in the arm

    for companies in the sector.

    The effect is visible

    Amidst all this, FY10 came as a breath of fresh air. Project award has resumed; since

    December 2008, the NHAI has aw arded (or is evaluating bids for) 24 projects worth

    INR 228 bn.

    Interest rate reduction to

    help BOT developers

  • 8/7/2019 Construction-sector_update-Oct-09

    10/118

    Edelweiss Securities Limited 9

    Construction

    Table 5: Projects awarded/ bids under evaluation by NHAI

    S. No. Project

    Length

    (km)

    Total project

    cost (INR bn)

    VGF/ revenue

    share Phase Developer

    1 Vadakkancherry - Thrissur 30 6.2 VGF II KMC - CR18G Consortium

    2 Pune Sholapur Pkg-I 110 11.1 VGF III Navinya Buildcon - Atlantia Spa

    (JV)

    3 Gujarat/Mh border - Surat -Hazira Port Section

    133 15.1 VGF III Soma - Isolux Corsanconsortium

    4 Pimpalgaon-Nashik Gonde 60 9.4 Revenue share III L&T - Ashoka Buildcon

    consortium

    5 MP/Mh Border-Dhule 97 8.4 Revenue share III HCC - John Laing - Sadbhav

    Engg consortium

    6 Cuddapah-Mydukur-Kurnool 189 15.9 VGF III KMC - IVRCL consortium

    7 Elevated road from Chennai

    Port-Maduravoyal

    19 13.5 VGF VII Soma Enterprises

    8 Kishangarh-Beawar 94 8.0 Revenue share III Soma - Isolux Corsan

    consortium

    9 Hyderabad-Vijayawada 181 17.4 Revenue share III GMR-Punj Lloyd consortium

    10 Armur-Adloor-Yellareddy 60 4.9 VGF II Navyuga-KPCL consortium

    11 Goa-Karnataka border to Panaji 65 4.7 VGF III IRB Infra

    12 Amritsar-Pathankot 102 7.1 VGF III IRB Infra

    13 Jaipur-Deoli 146 11.8 VGF III IRB Infra

    14 Talegaon-Amravati 67 5.7 VGF III IRB Infra

    15 Ghaziabad-Aligarh 126 11.4 VGF III PNC Infratech - SREI - Galfar

    16 Kannur-Kuttipuram Pkg - I 83 13.7 VGF III KMC - CR18G Consortium

    17 Kannur-Kuttipuram Pkg - II 82 13.1 VGF III KMC - CR18G Consortium

    18 Pune Sholapur Pkg-II 110 8.4 VGF III IL&FS - ITNL

    19 Hazaribagh-Ranchi 71 6.3 Annuity project III IL&FS - Punj Lloyd

    20 MP/Mh border-Nagpur section 95 11.7 NA II Oriental Structural Engineers

    21 Jaipur-Reengus 52 3.8 NA III Reliance Infra Source: NHAI, News reports, Edelweiss research

    What the future holds in store?

    NHAI has an ambitious target of awarding 23,000 km of roads in the next two years. This

    involves inviting bids for projects spread over 13,000 km of roads in the next year

    with an investment of ~ INR 1 tn.

    Table 6: NHAI plan for next one year

    NHDP phase No. of projects Length (km) Cost (INR bn)

    Phase II 12 700 139

    Phase III 96 8,825 602

    Phase V 18 2,403 240

    OMT projects 9 1,466 11

    Total 135 13,394 993

    Source: NHAI, Edelweiss research

    Of the INR 982 bn required for the 126 projects under Phase II, III, and V, INR 546 bn is

    expected to come from the private sector and the balance from the government.

    Overall, a total investment of USD 70 bn is envisaged in the road sector in the next

    three years. The private sector is expected to contribute USD 40 bn, of w hich USD

    NHAI has ambitious plansfor project award in nextcouple of years

  • 8/7/2019 Construction-sector_update-Oct-09

    11/118

    10 Edelweiss Securities Limited

    Construction

    10 bn is expected from foreign investors. Of this, USD 3-4 bn is expected in equity,

    while for the balance, the government is looking at creating new debt instruments like

    infrastructure bonds, securitising receivables, accessing the capital market, etc.

    NHAI plans to seek bids for 71 projects spread over 7,987 km in the next two quarters worth

    INR 616 bn.

    Table 7: NHAI plan for next two quarters

    NHDP phase No. of projects Length (km) Cost (INR bn)

    Phase II 9 447 122

    Phase III 43 4,261 339

    Phase V 12 1,833 137

    Phase VII 1 22 7

    OMT projects 6 1,424 11

    Total 71 7,987 616

    Source: NHAI, Edelweiss research

    NHAI expects to receive bids for 49 projects spread over 5,074 km worth INR 511 bn by

    2009 end. News reports suggest that response to some of these projects has beenenthusiastic with an average of 15 bidders expressing interest.

    These projects include an INR 95 bn plan to enhance road connectivity in Jammu & Kashmir

    by undertaking four laning of the Jammu-Srinagar national highway on BOT-annuity basis.

    Ministry of Roads also emerging as a big aw ardee

    In addition to the NHAI, the road ministry also has a large list of projects that it expects to

    award on a PPP basis. It has chalked up a plan to aw ard 58 projects worth INR 188 bn

    by July 2010 on BOT basis (please see Annexure III). These projects involve building

    7,515 km roads in various states and largely relate to converting existing roads into two

    lanes in various states. The ministry will award these projects either by itself or through

    respective state governments.

    It has also received clearance for two laning of the trans-Arunachal highway from Nechipu to

    Hoj (311 km) and Potin to Pangin (407 km) estimated at INR 14.3 bn and INR 19.1 bn,

    respectively, both on BOT annuity basis. This is part of the ministrys INR 134 bn plan of road

    development in J&K and North-East, as per its 100-day agenda submitted to the Prime

    Ministers Office.

    News reports suggest that the World Bank has agreed to lend USD 3 bn to the

    government to develop 5,937 km of highw ays. The proposed loan will cover 70% of the

    project cost, while government will provide the balance. These roads have low traffic and are

    not viable on PPP basis; these roads are likely to be constructed with full government funding.

    These highways are not part of NHDP . The government has identified 6,376 km of roads

    to be developed over the next few years with government funding, of which 5,937 km will bedeveloped using the World Bank fund.

    News reports suggest that the Ministry has also approved 63 projects that will connect the

    most populated cities in country to national highways. These projects stretched over 8,982

    km will be taken up next year under NHDP phase IV.

    Apart from NHAI, Ministry of

    Roads also has largenumber of projects to beawarded

  • 8/7/2019 Construction-sector_update-Oct-09

    12/118

    Edelweiss Securities Limited 11

    Construction

    New government, new deal for road projects

    Keeping the sluggish progress on the road project award scenario in 2006-08 in mind,

    the new government post election responded by appointing Mr. Kamal Nath (earlier the

    Minister for Commerce and Industry) as the Minister for Road Transport & Highways

    Ministry. He has announced an ambitious target of building 20 km of roads per day.

    Many initiatives have been taken since then to speed up the progress in the roads space.

    A summary of the same is given below:

    The erstwhile Ministry of Shipping, Road Transport and Highways has been

    bifurcated into separate departments under different ministersMinistry of Ports and

    Shipping and Ministry of Roads and Surface Transport to ensure focused efforts on

    development of both sectors.

    NHAI has been asked to finalise a framework for better execution of projects; this

    will include establishing a unity of command for proper delegation of power and

    better internal communication within NHAI.

    NHAI has decided to issue the letter of award (LoA) only after it has

    acquired 80% of the land required for a project and notification for acquiring

    the balance has been issued. The balance 20% will have to be handed before FC. Till

    now, NHAI used to award the project after acquiring 50% of land. This is likely to

    reduce delays due to land acquisition.

    Budget 2009-10 has increased the allocation for NHAI by 23% to INR 85.8

    bn compared to last years allocation of ~ INR 70 bn . The government has also

    proposed an investment of INR 41.4 bn in 2009-10 for developing national highways,

    besides those built by NHAI.

    The 2009-10 budget has exempted highway developers from the 8% excise duty on

    goods manufactured at work sites.

    The budget has also allowed India Infrastructure Finance (IIFCL) to refinance 60%

    of commercial bank loans for PPP projects. Also, IIFCL has been mandated to evolve

    'takeout financing schemes with banks through which it will pick up infrastructure

    loans from banks books.

    The Prime Minister had set up a committee to suggest fast-track mechanisms to

    improve inter-ministerial coordination for speeding up road projects. The

    committees mandate was to examine ways to expedite award of projects, financing

    road projects, restructuring of 4/6 laning projects based on traffic requirements and

    those in backward areas and to make suggestions for making projects attractive for

    banks and private investors. The committee has recently submitted its report to the

    Prime Minister.

    News reports suggest that the committee has recommended that government

    should support NHAI in its borrowing programmes by offering sovereign guarantee.

    This is likely to make it easier for NHAI to raise loans from international

    organisations as well as lowering the rate of interest on its loans.

    It has also recommended delegation of power to the road ministry on issues related

    to MCA, RFQ, and RFP.

    The government has approved the formation of an empowered group of ministers

    (EGoM) to fast-track road projects. The EGoM will remove various policy bottlenecks

    which do not require approval of the Cabinet or Cabinet Committee on Infrastructure

    (CCI). The EGoM has the power to fine-tune regulations and change the bidding

    norms for road projects if required.

    Governments commitment toroad development shows inincreased allocation for roadprojects and other regulatoryreforms

  • 8/7/2019 Construction-sector_update-Oct-09

    13/118

    12 Edelweiss Securities Limited

    Construction

    Proposed measures:

    Along with the above mentioned initiatives, news reports suggest that several

    measures are in the pipeline to achieve greater progress on road development front:

    Proposal to amend the cross holding clause: The revised RFQ guidelines issued

    by the Ministry of Finance in May 2009 had raised the earlier limit of 1% related to

    conflict of interest to 5%. In essence, the new guidelines state that a bid will be

    disqualified if an investor or its associate holds more than 5% (directly or indirectly)

    in another company which is applying for the same project. The new RFQ guidelines

    also state that this clause is not applicable for ownership by banks, insurance

    companies, pension funds, and public financial companies.

    Our interaction with ministry officials suggests that the government is considering a

    proposal by way of which the conflict of interest margin may be raised

    substantially from the current 5%. Government may also limit provisions of the

    clause to direct holding. News reports suggest that the limit has been raised to

    25%.

    Our take: More than equity stake, management control should be the determining

    factor. With most companies bidding in consortia, the 5% clause invariably crops up.

    News reports suggest that INR 100 bn of investment in roads sector has been

    blocked due to this rule. With the amount of investment that the government is

    targeting in road projects, a fast resolution of this concern is necessary.

    Proposal to amend the threshold technical capacityclause: The revised RFQ

    guidelines had also doubled the threshold technical capacity required to bid for a

    project. This means that to bid for a project of a certain total cost, the bidder

    should have the experience of implementing projects at least twice that

    cost in the preceding five years, i.e., to be eligible to bid for an INR 5 bn project,

    he should have implemented projects worth INR 10 bn in the previous five years. As

    per the old RFQ norms, the limit was set up at 100% of the project cost.

    Many smaller developers opposed this saying that the revised norms will benefit

    bigger developers and foreign companies and thus will leave smaller companies in adisadvantageous position. This will also limit competition as only a few developers

    will be able to put in their bids.

    Our interaction with ministry officials suggests that the government is considering a

    proposal to roll back the change in regulations so that the old RFQ norms come into

    place again.

    Our take: Considering the large number of projects that the government is planning

    to award, it needs to use the services of every developer available. A larger number

    of developers will ensure better competition; more so considering the fact that most

    projects awarded in the past eight-nine months have seen bids from only 2/3

    bidders.

    Proposal to amend the termination clause: This has been a major eyesore for

    many developers. This clause states that in case the traffic on any BOT project

    exceeds the design capacity for four years at a stretch, NHAI may terminate the

    concession agreement unless the developer agrees to enhance the projects capacity.

    For e.g., in case of a four-lane project, if the traffic exceeds the design

    capacity for four consecutive years, NHAI may terminate the agreement

    unless the developer agrees to enhance the roads capacity to six lanes.

    Our interaction with ministry officials suggests that the government is considering a

    proposal to amend this clause and introduce a more developer-friendly mechanism.

    Our take: This clause created uncertainties regarding the eventual duration of the

    concession period as well as cash flows from projects. With the upsides on traffic

    Government looking to makeregulatory framework morefavourable for developers

    Many steps being taken togenerate more developerinterest for roads

  • 8/7/2019 Construction-sector_update-Oct-09

    14/118

    Edelweiss Securities Limited 13

    Construction

    capped (by linking it to concession period duration), developers were naturally not

    enamored with this clause.

    Proposal to provide an exit clause for the lead member: Currently, the lead

    member in a consortium has to maintain 26% stake in the project SPV even after

    completion of the project. News reports suggest that government is considering a

    proposal to relax this clause so that developers can sell their stake and use thefunds for developing new projects.

    Our take: As the project goes through different stages, different type of investors

    would be interested in it. Once a project has been developed, the developer should

    not be constrained in a major way to remain attached to the project. Allowing him to

    sell stake and use the funds for new projects will be more beneficial. Once the

    project is complete, more risk averse investors and pension funds will be willing to

    come in. This will ease funding pains for the developer community.

    Proposal to vest ownership of roads with NHAI: The government is considering

    a proposal to vest the ownership of roads with NHAI; it will then be leased out to

    developers who will then raise loans against them. Currently, roads are not owned

    by NHAI; it only allows developers to collect toll on them. Thus, developers cannot

    use roads as collateral while borrowing from banks and other f inancial institutions.

    Our take: While this will be a novel way to ease financing concerns, legal issues

    (such as stamp duties and taxes to be paid) will have to looked into first.

    Setting up of special land acquisition units: TheNHAI has decided to set up 150

    special land acquisition units across various states to deal with land acquisition

    problems. These units will be developed for each project in respective states; it is

    proposed that they will comprise state government officials, who will carry out the

    entire land acquisition process on behalf of NHAI. Currently, land acquisition

    typically takes 24 months; NHAI plans to pare this time to 11 months.

    To push the land acquisition process, responsibility has been fixed on project

    directors, chief general managers (CGMs), and members of NHAI. Ten such units are

    coming up in Rajasthan, 13 in Bihar, 25 in Uttar Pradesh, seven in Gujarat, 11 inOrissa, 13 in West Bengal, four in Jharkhand, 11 in Maharashtra and five in Assam.

    Around 40 are already operational in Tamil Nadu and Karnataka and sanction has

    been received for Goa. The NHAI has also started the process of setting up 10

    regional centers to be headed by CGMs in Lucknow, Patna, Jammu & Kashmir,

    Chennai, Guwahati, Delhi (Haryana & Punjab), Nagpur, Bangalore, and Kolkata.

    Our take: Land acquisition is the biggest factor responsible for delays in project

    implementation. As per a recent survey of major infrastructure projects facing

    delays, land acquisition problems were responsible in 70% of cases. Also, news

    reports suggest that NHAI was unable to acquire land in eight states in Q1FY10.

    With NHAI now deciding to award LoA only after 80% of land acquisition is

    completed, efforts on this front need to be increased to speed up execution.

    Proposal to set up an expressway authority: The government intends to createa separate expressways authority, on the lines of NHAI, which will singularly

    concentrate on construction of expressways across the country. Such a move is

    likely to give an impetus to the construction of expressways in the country. The

    government intends to take up construction of about 1,000 km of expressways in

    four identified stretches under NHDP Phase VI. The proposed stretches are: Delhi-

    Meerut (66 km), Vadodara-Mumbai (400 km), Kolkata-Dhanbad (277 km), and

    Bangalore-Chennai (260 km).

    News reports suggest that the governmentis also contemplating building a

    network of expressways spanning 17,661 km by 2022 (end of the

    Thirteenth Five Year Plan). A draft report has suggested that the expressways be

    Government taking steps toensure administrative issueslike land acquisition are handled

    efficiently

    Government undertakingmeasures to improve viability ofroad projects

  • 8/7/2019 Construction-sector_update-Oct-09

    15/118

    14 Edelweiss Securities Limited

    Construction

    built as per the following two schedules: (a) 2,665 km by 2012, 3,690 km by 2017,

    and 6,031 km by 2022 on toll basis; or (b) 2,665 km by 2012 in the first phase and

    9,721 km by 2017 in the second phase on toll basis. Along with either of the two

    options above, the report has suggested building 5,275 km of roads on an annuity

    basis till 2022.

    Proposal to classify toll receipts as tangible assets: Currently, many banksclassify toll receipts as intangible assets which results in project loans to developers

    being classified as unsecured loans. This attracts higher provisioning charges and

    hence, the cost of loans for borrowers goes up. The government is studying a

    proposal to classify toll receipts as tangible assets which will help developers

    mobilise finance.

    Proposal to seek foreign funds for road projects: The government recently

    indicated that it is looking at sovereign wealth funds, private equity funds, and

    pension funds to fund road building in India. The roads minister has already

    undertaken road shows to meet investors to discuss which financing platforms would

    be most effective. The government has earmarked USD 20 bn per year for road

    building and expects foreign investors to fund half of this. The government aims to

    reform policy and ease investment rules for infrastructure projects in an effort to

    attract foreign capital.

    Setting up a forum to address developer concerns: The government has

    agreed to institutionalise a CII-Ministry of Roads-NHAI forum, as a mechanism to

    address industry concerns. This forum will meet every month under the leadership

    of secretary, Ministry of Roads, and report back to the minister on the progress

    made on various issues.

    Proposal to securitise cess and toll revenues: The government is considering a

    proposal to securitise the cess that it levies on petrol and diesel and the toll it

    collects from tolling bridges and bypasses on NHs (these two sources together

    contributed INR 87 bn in FY09). This will help the government augment its resources

    for road development.

    Proposal to exempt SPVs from dividend distribution tax (DDT): News reports

    suggest that the Roads Ministry is asking for an exemption from the dividend

    distribution tax (DDT) for SPVs which are developing highways. Under the existing

    income tax laws, both the SPVs and the holding company pay taxes when they

    declare dividends. This is a major disincentive for developers. The ministrys

    proposal is aimed at reducing the cascading tax effect.

    Proposal to set up an independent regulator for highways to oversee all NHDP

    phases. The regulator will examine problems faced in implementing NHDP projects

    including land acquisition or disputes arising during the bidding process.

    Proposal to make the toll collection process automated in projects executed through

    the PPP mechanism. This is because it is felt that leakages under the manual system

    of toll collection undermine the viability of road projects for government and

    developers.

    Proposal to set up an arbitration body for roads that will be an institutional set up to

    deal with disputes between contractors and NHAI. As per Government estimates, as

    much as INR 100 bn worth funds are stuck because of disputes between developers

    and the NHAI.

    Other measures that can be looked into:

    Mix of annuity and toll: While currently, there are two clear models under the PPP

    mechanismtoll and annuitythere is no model which encompasses the

    Willingness on part ofGovernment to listen todeveloper concerns

  • 8/7/2019 Construction-sector_update-Oct-09

    16/118

    Edelweiss Securities Limited 15

    Construction

    characteristics of both. Such a model may well emerge as a win-win proposition for

    all stakeholders.

    NHAI had some time ago proposed a new hybrid BOT model which combined the

    characteristics of both the toll as well as annuity payment models. A draft MCA was

    designed for this purpose and a communiqu was circulated among developers

    seeking their feedback on the same.

    Currently, under the BOT (annuity) model, no viability gap funding (VGF) is made

    available to the developer and he has to bear the entire project cost. The project

    cost/investment is recouped by the developer through annuity payments made by

    NHAI after the construction is over, while the toll collected goes to the NHAI.

    However, under the BOT (toll) model, the developer has to recover his investments

    through toll collection. Depending upon the viability of the project, he may ask for a

    viability gap funding (currently capped at 40% of the project cost) from the NHAI or

    may agree to share revenues with the NHAI.

    The hybrid model had proposed that in case the amount of VGF quoted by

    the developer is more than 40% of the project cost, the funding

    requirement in excess of 40% of the cost would be paid to the developer in

    the form of annuity payments. Significantly, even while the incremental payment

    would have been made by the government, the developer would have been allowed

    to collect the toll through the concession period.

    However, the government has rejected the hybrid model and has decided to go

    along with the current annuity and toll models.

    Our take: Our interaction with developers suggests that they were in favour of the

    hybrid model. The new model would have reduced the financial risk for the

    developer in case toll collection was not as per expectations since he would have

    received an assured annuity payment from the government. Many projects in the

    past couple of months could not be awarded as the VGF quoted by developers

    exceeded the 40% cap. The new model would have made these projects viable and

    increased the pace of project awards.

    The government would also have had to pay only the incremental amount as annuity

    under this model (against the earlier practice of paying the entire annuity amount

    under the BOT-annuity model). This would have had the advantage of reducing

    annuity payments significantly as well as transferring the commercial risk from NHAI

    to the developer.

    Another method that can be tried is to allow a project to run on the annuity mode till

    the time the traffic on the project reaches such a level that it becomes viable under

    the toll mode. This will lessen the burden of annuity payment that the government

    has to bear.

    Relook at the waterfall mechanism: Under the current waterfall mechanism

    followed by NHAI, a project is first invited under the BOT-toll mode. In case of

    inadequate response, the BOTannuity mode is used. In case even this fails, the

    project is given on cash contract basis.

    Our take: While theoretically, letting market forces determine the viability of a

    project is the right way, the current method takes a long award time in case the

    project is not viable under the PPP mode.

    A faster way to award projects could be to assess the viability of awarding a contract

    on the BOT-toll model before the tender is invited. In case a project is not

    considered viable under the BOT-toll method, the annuity-based method could be

    used directly without going through the bidding process.

    Flexible approach needed tospur road development

    Measures to fast track roadproject award and removeirritants in current processneed to be taken

  • 8/7/2019 Construction-sector_update-Oct-09

    17/118

    16 Edelweiss Securities Limited

    Construction

    In a way, the government has already started working on this. It has decided that

    project development mode will be decided as per the vehicular traffic on the road as

    shown below:

    Table 8: Project development mode

    Vehucular traffic (in PCUs) Project development mode

    > 15,000 BOT-toll10,000 - 15,000 BOT-annuity

    < 10,000 EPC

    Source: Edelweiss research

    News reports suggest that the Government is considering a new policy under which

    all road highway projects are to be earmarked from the beginning to one of three

    processes of bidding, on the basis of its financial viability. NHAI has, under the new

    policy, identified 6,831 km to be bid on toll, 1,143 km on annuity and 3,954 km on

    EPC in FY10.

    Updated cost estimates for projects: A major grouse that developers hold

    against NHAI is that project cost estimates are woefully outdated and totally out of

    sync with the current ground situation. A comparison of the estimated cost of someprojects as per NHAI and developers is pertinent in this respect:

    Table 9: Variation between NHAI and developer cost estimates

    Project

    NHAI cost

    estimate (INR bn) Developer

    Developer cost

    estimate (INR bn)

    Variation

    (%)

    Talegaon-Amravati 5.7 IRB infra 8.5 50.6

    Goa/KNT border - Panaji 4.7 IRB infra 8.4 77.4

    MP/Maharashtra border - Dhule 8.4 HCC/John Laing/Sadbhav 14.2 69.5

    Hyderabad-Vijaywada 17.4 GMR/Punj Lloyd 22.0 26.4

    Source: Edelweiss research

    While the government has taken measures to ensure that cost estimates are more

    in tune with ground realities, a lot more needs to be done to reduce the variation.

    Setting up a system of empanelled developers: The roads ministry has decided

    to set up a system of empanelled developers by pre qualifying them for a period of

    one year. This will be done by establishing their qualification strengths. We believe

    such a step should be used for NHAI projects as well since it will streamline and

    simplify the process of qualification of bidders as well as save time taken to arrive at

    the bidding stage.

    Our take: Government seriousness shows through even if target is

    daunting: The target that the government has set for itselfbuilding 20 km of roads

    per dayis definitely daunting, considering the fact that the current execution rate is

    not even half of that. The NHAI chairman has said that achieving such a target will

    take atleast 18 months. Even then, it will require a massive capacity enhancement

    exercise at NHAI, developers, contractors, banks/financial institutions, and state

    governments (responsible for land acquisition) to achieve the target.

    The government has taken a plethora of steps in the past three-four months to

    make the sector more commercially attractive. It recently said that all amendments

    to the MCA will be completed by September 2009 end to attract investments. With

    the government seriously showing its intent to address grievances of all

    stakeholders involvedNHAI, developers, banks/financial institutions, among others-

    and establishing a definite time frame to solve various issues, its commitment to

    achieving a substantial jump in the pace of road development is evident.

    Government committed to aquantum improvement incountrys road infrastructure

  • 8/7/2019 Construction-sector_update-Oct-09

    18/118

    Edelweiss Securities Limited 17

    Construction

    Outlook: Future looks bright

    The NHDP had run aground in the past three years, entangled in a maze of regulations

    and unfavourable economic scenario. With both these irritants out of the way, we expect

    a faster pace of project awards. With the government willing to look into the problems of

    developers and taking steps to remove the roadblocks, things definitely look better than

    a year ago. This makes us believe that the travails of the past three years are behind us

    and we are well on the road to seeing some heightened activity on the project awards

    scene. To conclude, it looks like there definitely is light at the end of the tunnel as far as

    the road development space is concerned.

  • 8/7/2019 Construction-sector_update-Oct-09

    19/118

    18 Edelweiss Securities Limited

    Construction

    Huge Opportunity At Centre And State Levels

    Road projects have been at the forefront of the privatisation move in the Indian infra sector.

    BOT road projects account for 81% of total PPP projects awarded in India, as far as number

    of projects is concerned. This shows the rapid strides made as far as popularising the PPP

    route in the road sector. The heartening thing is that the past has been good and the future

    promises to be even better.

    If there is one word to describe the opportunity in the Indian roads space, it is humongous.

    While the expected investment in NHDP is INR 3,315 bn during 2006-17, it is not the only

    place where the action is happening. The NHDP accounts for only 47% of the total road

    sector investment in the Eleventh Five Year P lan. State roads, at 37% of the investment,

    also form an important segment for any developer/contractor in the road space. Also, as far

    as rural roads are concerned, the Eleventh Plan envisages spending over INR 400 bn on them

    (investment on rural roads is sourced from the Prime Ministers Grameen Sadak Yojna,

    (PMGSY) under the Bharat Nirman Programme). With the public sector contributing a

    majority of funding for state roads and completely for rural roads, opportunities in these

    segments are available more for contractors than developers.

    We take a look at the upcoming road opportunity at the central level as well as the initiatives

    taken by various state governments to foster road development. Our focus is on the PPP

    opportunity at the central and state levels, since privatisation is the buzzword in the Indian

    road sector today.

    NHDP: Developing the countrys arterial network

    NHDP, launched in 1998-99, has seen its scope getting enhanced from the two phases

    envisaged initially to seven phases covering more than 54,000 km (p lease re fer

    annex u r e I V fo r de ta i l s o f v a r i ous phases ).

    Table 10: Various phases of NHDP

    Phase Length (km) Date of approval Original approvedcost (INR bn)

    Phase - I 7498 * Dec-00 303

    Phase - II 6647 ** Dec-03 343

    Phase - III A 4,815 Mar-05 330

    Phase - III B 7,294 Apr-07 476

    Phase - IV 20,000 Jul-08 *** 278

    Phase - V 6,500 Oct-06 412

    Phase - VI 1,000 Nov-06 167

    Phase - VII 700 Dec-07 167

    Total 54,454 2,476

    Source: NHAI, Edelweiss research

    Note: * Includes 5,846 km of GQ, 981 km of NSEW, 356 km of port connectivity, and 315 km of other roads** Includes 6,161 km of NSEW and 486 km of other NHs

    *** 5,000 km were approved by CCEA in July 2008

    While the NHDP started with awarding projects on cash contracting basis, the focus has

    progressively shifted towards the PPP approach. The government in 2005 decided to

    award all projects in NHDP Ph III-VII using the PPP approach. Since then, the BOT

    approach has been the predominant mode of award. The status of BOT projects in NHDP

    till date is summarised below:

    Huge opportunity both atcentral and state level

    NHDP Worlds largestPPP road developmentprogramme

  • 8/7/2019 Construction-sector_update-Oct-09

    20/118

    Edelweiss Securities Limited 19

    Construction

    Chart 4: BOT toll projects in NHDP

    77

    26

    5,677

    1,171

    456

    87

    0 1,000 2,000 3,000 4,000 5,000 6,000

    Awarded

    Completed

    Cost (INR bn) Total length (km) No. of concessions

    Source: NHAI, Edelweiss research

    Chart 5: BOT annuity pro jects in NHDP

    25

    11

    1,376

    713

    94

    38

    0 300 600 900 1,200 1,500

    Awarded

    Completed

    Cost (INR bn) Total length (km) No. of concessions

    Source: NHAI, Edelweiss research

    Over the years, delays in implementation and restructuring in certain cases has meant

    that the cost of NHDP has been revised upwards many times. The revised cost estimates

    for various phases are as follows:

    Table 11: Cost of NHDP phases (2006-17) (INR bn)

    NHDP phase Modified cost estimates

    Phase I and II (balance work) 684Phase III 1,143

    Phase -IV 393

    Phase -V 515

    Phase -VI 229

    Phase -VII 167

    SARDP-NE, ICTT Cochin and others 184

    Total 3,315

    Source: NHAI, Edelweiss research

    PPP approach gainingacceptance in NHDP

  • 8/7/2019 Construction-sector_update-Oct-09

    21/118

    20 Edelweiss Securities Limited

    Construction

    As is evident, the NHDP involves an investment of INR 3,315 bn during 2006-17. The

    expected funding for the same is shown below:

    Chart 6: Funding sources of NHDP phases (2006-17) (I NR bn)

    243

    723

    274

    444

    136

    104

    46

    441

    420

    119

    71

    93

    63

    138

    0 200 400 600 800 1,000 1,200 1,400

    I and II (Balance work)

    III

    IV

    V

    VI

    VII

    SARDP-NE, ICTT Cochin & others

    (INR bn)

    Private Sector Public Sector

    Source: NHAI, Edelweiss research

    A significant portion of the opportunity still remains to be tapped. Substantial completion

    has been achieved only on the initial two phases. The main focus currently is on

    completing these two phases and to award project under Phases III and V.

    Table12: Status of various NHDP phases

    PhaseTotal

    length (km)

    Already

    4-laned (km)

    Under implementation

    (km)

    Balance for

    award (km)Likely completion date

    Phase I 7,498 7,227 265 6 Substantially completed

    Phase II 6,647 3,451 2,444 752 Dec-10

    Phase III 12,109 937 2,155 9,017 Dec-13

    Phase IV 20,000 0 0 20,000 Dec-16

    Phase V 6,500 131 899 5,470 Dec-13

    Phase VI 1,000 0 0 1,000 Dec-16

    Phase VII 700 0 19 681 Dec-15

    Total 54,454 11,746 5,782 36,926

    Source: NHAI, Edelweiss research

    As can be seen above, of the total 54,454 km under the NHDP (including NHDP Phase IV

    which will be implemented by Ministry of Roads), 36,926 km of roads are still to be

    awarded. Of the seven phases, NHDP Phase IV and VI are yet to see any action on

    ground while awarding under Phase VII has just begun. This means that there is a huge

    opportunity waiting to be tapped by developers as far as NHDP is concerned.

    PPP opportunity at state level: The undiscovered paradise

    While NHDP hogs most of the spotlight, many states have been quietly and steadily

    drawing up the roadmap for PPP projects in the road sector. In fact, the phenomena of

    state PPP projects is old, with states like Rajasthan passing enabling resolution for

    inviting private participation in roads way back in 1994. Other states like Gujarat had

    started awarding PPP projects (like the Vadodara-Halol project which was completed in

    2000) much before the turn of the century when NHDP projects picked pace.

    NHDP entails huge fundingrequirements

    PPP opportunity at state levelis probably bigger than NHDP

  • 8/7/2019 Construction-sector_update-Oct-09

    22/118

    Edelweiss Securities Limited 21

    Construction

    The reason why the state PPP scene attracts relatively less attention than the NHDP is

    because of the comparatively dispersed scene of action. Also, the level of activity differs

    from state to state. While states like Maharashtra, Gujarat, and Rajasthan are active as

    far as attracting private investments is concerned, there are many states which do not

    have a PPP policy and a PPP cell even today. Also, the regulatory frameworks vary with

    states having their own MCAs.

    The level of investment at the state level till now is also low . Part of it can be

    blamed on the slackness of states to take steps to set up the necessary

    regulatory framework. Also, there have been apprehensions regarding the credit

    worthiness of the involved state bodies (against NHAI, which is a AAA (Ind) rated

    entity).

    However, things seem to be changing now. State governments seem to have realized the

    enormous potential of the private sector as far as developing the road network is

    concerned. Also, increasing awareness about the positive impact of a robust

    infrastructure network seems to be trickling in. All in all, we are set to see an enhanced

    level of activity as far as the state PPP scene is concerned. We present the future

    opportunity available in major states.

    Karnataka: INR 1,770 bn opportunity

    Karnataka has decided to develop a Core Road Network (CRN) spanning

    66,000 km at an estimated cost of INR 1,770 bn under the PP P mode (BOT-

    toll) over the next six years (2009-15). The CRN is to be developed in three

    phases: (i) first phase involving the development of 10,000 km of state highways

    (SHs) and major district roads (MDR) and 12,600 kms of village roads (VRs). The

    estimated cost of developing state highways and MDR is INR 314 bn; (ii) second

    phase with 40,000 km of roads to be developed at an estimated cost of INR 1,088

    bn; and (iii) third phase comprising 16,000 km with an investment of INR 368 bn.

    The CRN will connect the major IT centre of Bangalore with other IT hubs such as

    Mysore, Hassan, Davangere, Hubli, Dharwad, and Mangalore to promote industrialand urban development besides integrating economically backward and remote

    areas. It will be an all weather, smooth, speedy flowing road network with minimum

    two lane carriageway including feeder roads and four-six lanes near urban

    settlements.

    The concession agreement initially developed for these roads had innovative

    features like award of land pockets to developers to set up roadside amenities like

    restaurants, which was to be an additional source of revenue for companies. It

    proposed that developers would be eligible for one acre of wayside amenity land for

    every 5 km of project road (SHs//MDR plus VRs). Land acquisition and development

    was to be undertaken by developers. However, most of the developers that evinced

    interest in the programme were uncomfortable with land acquisition. Upon their

    requests, the government has now decided to acquire the land required for thedevelopment of these roads on its own.

    Also, the state government has drawn up a plan for the overall development of

    Bangalore with an outlay of INR 220 bn. The plan includes 12 major signal-free

    corridors, three elevated corridors, strengthening of arterial and sub-arterial roads,

    construction of 40 railway over and under bridges, etc.

    Meanwhile, the much delayed Peripheral Ring Road in Bangalore is also expected to

    see the light of the day. The state government has given the go-ahead for the first

    phase of the project. It will be implemented by the Bangalore Development

    Karnataka plans to spendINR 1,770 bn on roaddevelopment through PPPapproach in 20009-15

  • 8/7/2019 Construction-sector_update-Oct-09

    23/118

    22 Edelweiss Securities Limited

    Construction

    Authority (BDA) in partnership with private companies. The road, once it fully

    encircles the city, will be 116 km long and is expected to cost upwards of INR 30 bn.

    Gujarat: The early mover

    The Gujarat government has been active as far as PPP projects in the road sector

    are concerned. It was the first state in India to have a law governing BOT

    projects and such other arrangements along with private participation in

    infrastructure projects. The state witnessed the completion of the Vadodara-Halol

    and Ahmadabad-Mehsana toll projects in 2000 and 2003, respectively. The Gujarat

    State Road Development Corporation (GSRDC) had last year signed a concession

    agreement with Larsen and Toubro (L&T) for construction of three road corridors in

    the state with a total length of 485 km and a project cost of INR 43 bn.

    The state government has now plans to undertake improvement of roads with

    private investment of about INR 90 bn. This involves developing 2,600 km of roads

    with an investment of INR 30 bn on annuity basis and of 1,000 km of roads with an

    investment of INR 60 bn on toll basis. The government has started with the projects

    on annuity basis which would ensure a fixed stream of revenues for companies. Also,

    the state government is assuring developers that 95% of the land will be made

    available to them at the beginning of the project. This compares favourably with 50-

    60% that most companies usually get in NHAI projects.

    Also, the government has drawn up an ambitious plan for road development in the

    state. The proposed investment is ~ INR 300 bn in 2010-12 and ~ INR 200

    bn in 2012-17. PPP w ill be the major source of funding, contributing ~ INR

    110 bn in 2010-12 and ~ INR 120 bn in 2012-17.

    Andhra Pradesh: The programme approach

    The state government has to its credit successful highway development programmes

    such as the World Bank funded Andhra Pradesh State Highway Project (APSHP). The

    government has already awarded 38 road projects on BOT basis worth INR 77 bn.

    With the success of APSHP, the state government has now proposed a second

    project, i.e., AP Road Sector Project (APRSP) for improvement and better

    management of roads. The programme involves four laning of 1,252 km of roads

    under the PPP basis; it also includes upgradation and improvement of 600 km of

    roads and long-term performance based maintenance contract (LTPBMC) for 6,523

    km of roads. Apart from this, there are 15 projects currently in the pipeline to be

    awarded under the BOT model.

    Madhya P radesh: The BOND-BOT approach

    Madhya Pradesh (MP) has taken some innovative steps to foster the development of

    the road network through the PPP route. It initiated the Bond-BOT scheme to

    develop 2,000 km of state roads on BOT basis. The projects were aided by the state

    government through a subsidy of INR 5 bn, which was raised by a bond issue underthe Madhya Pradesh Infrastructure Investment Fund Scheme. The projects

    developed during the scheme included the likes of the 203 km Indore-Edalabad

    project and the 247 km long Rewa-Amarkantak project.

    MP was als o the first state to receive VGF from the central government. The

    state has also been able to award BOT projects on a negative

    grant/ revenue sharing basis, indicating the attractiveness of the stretches.

    The state has completed projects spread over 1,532 km on BOT basis while projects

    spanning 965 km on BOT basis are under development.

    Gujarat ambitious roaddevelopment plans

  • 8/7/2019 Construction-sector_update-Oct-09

    24/118

  • 8/7/2019 Construction-sector_update-Oct-09

    25/118

    24 Edelweiss Securities Limited

    Construction

    DBFOT model on an annuity basis. Land acquisition for phase I of the ORR from

    Vandalur to Nemilichery has been completed. GMR Infrastructure recently won the

    bid to develop this 29.65 km stretch at a cost of ~ INR 11 bn.

    Apart from this, a road network development scheme for Chennai under the second

    master plan has also been conceptualised. This plan, called the Chennai

    Elevated Expressways, is to be developed at a cost of INR 130 bn. A total of

    nine elevated corridors have been proposed in the medium term while 12 corridors

    have been proposed in the long term. The overall project is to be completed by

    2019-20.

    Also, recently the state government stated that it proposes to develop and upgrade

    12,000 km of road at an outlay of ~ INR 40 bn. While 5,500 km roads will be

    widened, maintenance work will be carried out on 6,500 km roads. During the past

    three years, the government had upgraded 3,270 km of major district and other

    district roads into state highways.

    Maharashtra: Leading the pack

    Maharashtra is the leader as far as attracting private investment in road projects is

    concerned. It formulated a policy in 1996 to finance road development projects

    through private sector participation. A cabinet sub-committee has been formed to

    take fast decisions related to infrastructure projects. The state has already

    completed 16 major projects costing INR 54 bn. Further, 14 projects costing INR

    108 bn are under development.

    The state has ambitious plans regarding future projects. Upcoming projects include

    the Worli-Nariman Point Sea Link, integrated road development programmes in

    many cities, widening of various state highways on BOT basis, among others.

    Punjab: Expressway all the way

    The Punjab Industrial Development Board (PIDB) is the nodal body for infra

    development in the state and is designated as the PPP cell for infrastructuredevelopment in Punjab. The state has already completed nine BOT projects in the

    road sector.

    The PIDB has an ambitious programme as far as future PPP projects are concerned.

    Future projects include five ambitious expressw ays, viz., Mohali-Phagwara

    Expressway (INR 25 bn), expressway around Mohali (INR 23 bn),

    expressway for Amritsar Airport, Pathankot-Ajmer Expressway (INR 86 bn),

    and expressway in Ropar along Sidhwan Canal up to Ludhiana. Other PPP

    projects included two ring roads (the Amritsar ring road at a cost of INR 20 bn and

    the Ludhiana ring road to be built at an estimated cost of INR 30 bn) apart from

    various other road projects.

    Haryana: Venturing out

    The state government has approved the improvement of the Gurgaon-Faridabad

    road, Ballabhgarh-Pali-Dhauj-Sohna road, Chandimandir-Jallah road, Bhuria-Khadri-

    Deodha Nainawali road, and Yamunanagar-Ladwa-Karnal road on PPP basis. Of this,

    the Gurgaon-Faridabad project has been already awarded to Reliance Infra. The

    government is also planning a North-South and East-West corridor at an estimated

    cost of INR 40 bn.

    New entrants looking to catch upwith early movers

  • 8/7/2019 Construction-sector_update-Oct-09

    26/118

    Edelweiss Securities Limited 25

    Construction

    Orissa: Taking first steps

    Orissa has a road network of around 2.38 lakh km (including 3,100 km of NHs). The

    state has embarked on an ambitious plan for improving road connectivity through

    the PPP route.

    Upcoming projects include the Capital Region Ring Road (INR 3 bn), Bhubaneswar-Paradeep Road (INR 5.6 bn), four Laning of Sambalpur-Rourkela Road (INR 12.7 bn),

    Koira-Tensa-Lahunipara Road (INR 4 bn), among others.

    Summary

    The opportunity at the state level for the PPP route is abundant. The overall quantum

    rivals that of the NHDP and is perhaps even bigger than it. However, the opportunity is

    spread across a wide spectrum and the level of preparedness for PPP projects across

    various states is also different. While some like Gujarat and Rajasthan are old hands at

    the game, others like Orissa are in unchartered territory. The PPP framework and the

    associated regulations also differ across states; this, along with the myriad agencies with

    which companies will have to deal at the state level, is likely to ensure that there will be

    misses along with hits on the way. However, it can be safely said that the state road PPP

    scene is now ready for a quantum leap. Over the long term, it will ensure that there is noshortage of work for any participant in the infrastructure space.

  • 8/7/2019 Construction-sector_update-Oct-09

    27/118

    26 Edelweiss Securities Limited

    Construction

    Time To Think About The Constraints

    While no one doubts the huge opportunity in store, it is also prudent to keep the constraints

    in mind. As far as the road development scene is concerned, the obvious constraints are:

    1. Execution capability of contractors.

    2. Amount of money the government (NHAI) can put in.

    3. Debt funding from banks and other financial entities.

    4. Capability of developers to provide the equity portion of funding.

    We take a look at these factors involved:

    1. Execution capability: A spending of INR 1 tn every year means that developers

    alone will not be able to execute projects on their own; a significant chunk of the

    work will have to be outsourced to third part contractors as well. But even then, a

    look at the revenues earned by roads divisions of various contractors in FY09 reveals

    that it appears unlikely that this much quantum of work can be handled.

    Table 13: Order book/ execution ratio of various contractors

    Company Order book/execution ratio (FY09 end)

    IVRCL Infra 2.8

    Nagarjuna Construction 2.6

    Patel Engg 2.9

    Simplex Infra 2.1

    Gammon India 3.5

    Hindustan Construction 4.9

    Sadbhav Engg 4.6

    Madhucon Projects 5.2

    Gayatri Projects 5.7

    Punj Lloyd 1.7

    Source: Company, Edelweiss research

    With the spurt in order awards in the past six months, most contractors currently

    have a robust order book (>3x FY09 revenues). With the overall focus on

    infrastructure development, there are going to be opportunities in other

    infra segments as well. In this context, building 20 km of roads every day is

    a tough task to achieve.

    While the government has stated its intention to focus on capacity augmentation of

    contractors, it is going to be a gradual progress rather than a fast one. The

    government is also looking at getting the help of foreign players to achieve its

    objective. While foreign players may be able to help in funding aspects and projectmanagement skills, it yet remains to be seen how many of them will be willing to get

    their hands dirty doing the actual contracting work.

    To conclude, even though projects awarded now will enter the execution stage after

    only a year or so, we believe that execution is going to be an issue, atleast in

    the medium term. The fact that many states are also becoming active as far as

    road development is concerned is going to further test the execution abilities of

    contractors.

    Are there enough contractorsto build 7000 km of roadsevery year?

  • 8/7/2019 Construction-sector_update-Oct-09

    28/118

    Edelweiss Securities Limited 27

    Construction

    2. Does the government have the money?: The proposed funding plan for NHDP

    amounting to INR 1,735 bn in the Eleventh Five Year Plan is as follows:

    Chart 7: Funding plan for NHDP in 11th plan

    Cess21%

    Externalassistance

    2%

    Borrowings byNHAI24%

    Surplus fromuser fee

    2%

    Share of privatesector51%

    Source: Working Group report on roads for the Eleventh Five Year Plan, Edelweiss research

    As is evident, the private sector is expected to provide more than half of the funds

    required. However, with the sluggish pace of project award in the first two years of

    the plan, achieving this target is going to be an uphill task. Currently, it looks like

    that the government may have to put more on the table than what was envisaged.

    We take a look at various funding sources being utilised by NHAI over the

    past few years:

    Table 14: Funding sources utilised by NHAI (INR bn)

    Borro- Budgetary Toll TotalYear Cess Grants Loans wings support collection

    1999-00 10 5 0 7 0 0 22

    2000-01 18 5 1 8 0 0 32

    2001-02 21 9 1 56 0 0 87

    2002-03 20 12 3 0 0 3 38

    2003-04 20 12 3 0 0 4 38

    2004-05 18 12 4 0 0 5 39

    2005-06 33 24 5 13 7 8 90

    2006-07 64 16 4 15 1 11 111

    2007-08 65 18 4 20 3 14 125

    2008-09 70 15 4 11 2 17 118

    Total 340 127 29 129 12 61 699

    External assistance

    Source: Government documents, Edelweiss research

    The amount collected from cess on diesel and petrol of INR 135 bn during the first

    two years of the plan is more or less as per estimates. It goes into a non lapsable

    fund to be used for highway development.

    On the other hand, external assistance has reached INR 41 bn in the first two years

    itself against projections of INR 45 bn over the plan period. This signifies the

    emphasis being put by the government on road development.

    Does the government haveenough money to back up itsambitious plans?

  • 8/7/2019 Construction-sector_update-Oct-09

    29/118

    28 Edelweiss Securities Limited

    Construction

    As far as NHAI borrowings are concerned, there is still a lot of leeway left

    with the agency: As against the planned figure of more than INR 400 bn of

    borrowings, NHAI has borrowed only INR 31 bn in the past two years. There is

    expected to be a sharp uptick in borrowings going ahead with the NHAI planning to

    borrow INR 50 bn in FY10. News articles suggest, of this, INR 5 bn is proposed to be

    raised from a multilateral agency and negotiations are going on with ADB for a USD

    100 mn loan. The balance is proposed to be raised through tax-free bonds, which

    are already available in the market. NHAI is also in talks with the World Bank to

    restructure an earlier loan of USD 400 mn.

    NHAI toll collection has also jumped to INR 17 bn this year. About 7,560 km of NHs

    have been completed and are under tolling. However, 3,476 km of NHs are only

    partially complete and hence are not under tolling. The toll collection could be

    expected to jump further on completion of these projects.

    Also, recent news reports suggest that the government is considering a move to

    transfer a part of the INR 100 bn tax-free bonds raised by IIFCL to NHAI for

    refinancing of road projects.

    To summarise, the oft repeated statement from government that it will not allow

    money to hinder road development is true to some extent. In the near term, it

    seems that NHAI has adequate funds at its disposal to carry out its plans .

    However, the picture over the medium term is muddled and will depend

    upon several factors:

    (i) How fast is the government able to remove bottlenecks and what will be the

    success rate in awarding projects over the next two years.

    (ii) How much will the government be able to support NHAI, constrained that it is

    due to considerations about fiscal deficit.

    (iii) How fast the economy recovers, for it will improve project viability by boosting

    traffic and reduce dependence of developers on VGF (or conversely, how soon

    will we see the return of developers willing to share revenues with Government).

    3. Funding conundrum: Will the flood of liquidity translate into financial

    closures: With no dearth of projects to choose from, liquidity situation improving,

    and regulatory framework also turning favourable, the only stumbling block in

    the way of a marked improvement in project awards, in our view, is funding .

    Also, with increasing commoditization of the sector, the extent to which project

    economics can be improved will increasingly depend upon innovative funding

    structure along with design and execution capabilities.

    In such a scenario, the extent of the companies participation in future BOT projects

    (and the success of the overall PPP plan in roads) will depend upon the confidencewhich companies have in achieving FC on projects. Thus, cracking the funding

    code is the key to unlocking the PPP opportunity, in our view.

    There are two major questions which will determine the success of the Indian PPP

    road projects in the medium term: (a) how much risk aversion from banks will the

    BOT projects face, keeping in mind the worries on asset quality (toll revenues being

    lower than estimates on some projects) and asset-liability mismatch (concession

    period being increased for many projects); and (b) where will the required equity for

    projects come from?

    Can NHAI finances stand up tothe increased demand for

    government funding?

    Will funding emerge as thedeal-breaker?

  • 8/7/2019 Construction-sector_update-Oct-09

    30/118

    Edelweiss Securities Limited 29

    Construction

    In order to get answers to these questions, we have interacted with banks,

    financial institutions, private equity players as w ell as major developers in

    the road BOT space. We present our analysis of the situation:

    Banks turning sympathetic towards BOT projects .

    Various steps taken by the government to improve the viability of BOT projects havefound favour with banks. While a return of the 80:20 D/E structure for road BOT

    projects is still far, banks are comfortable funding a 70:30 project structure (which

    may go up to 75:25 in case the project is very lucrative).

    Also, most banks do not have preferences regarding whether the project is a

    NHAI/state project or the mode of project (toll/annuity). The paramount factor

    determining lending decisions is viability of the project. As far as sectoral lending

    caps are concerned, these can be changed internally in case a host of viable projects

    are available in any particular sector.

    Interest rates, on the other hand, present an interesting conundrum. The latter part

    of the last year saw interest rates shooting up, making many projects unviable.

    While rates have dropped significantly since then (currently at 11-12% level forproject finance proposals), most banks are of the view that we are near the end of

    the interest rate cut cycle.

    In fact post the budget, there have been apprehensions that the sheer size of

    government borrowing will crowd out private players, driving interest rates higher by

    the start of next year. This may well coincide with the time when majority of the

    road BOT projects awarded this year are expected to come up for FC. How long will

    developers get to enjoy a favourable interest rate environment has emerged as an

    important point to ponder over.

    .but, can they support long term funding r equirement

    The problem with BOT project funding is not limited to tying up initial funds. Theirlong tenure creates headache of asset-liability mismatch for banks. Recognising this,

    the government has been trying to take the help of IIFCL for this purpose.

    In Budget 2009-10, the government has proposed release of long-term funds by

    IIFCL for projects; IIFCL will also refinance 60% of bank loans for PPP in

    critical sectors over 15- 18 months. It will provide refinance at 7.85%,

    which banks can on-lend at 10.35%.

    The World Bank has recently sanctioned a USD 1.2 bn loan to IIFCL. This loan is

    designed to support IIFCLs role to catalyse private financing for PPP projects in

    infrastructure and to stimulate the development of a long-term local currency debt

    financing market.

    The government has also mooted the idea of take-out financing which basically

    involves securitising of infrastructure advances by primary financiers, especially

    banks, in favour of long-term financial institutions. IIFCL recently indicated that

    it has deployable funds of around INR 100 bn, a part of which has been

    raised for 10-25 years. Thus, it is in a position to offer take-out financing.

    However, it yet remains to be seen whether take-out financing will work. It has

    been tried in the past too when SBI had tied up with IDFC, while IDBI had tied up

    with LIC for take-out financing. But these arrangements could not work.

    Banks shedding theirapprehension towards roadprojects

    But do the banks have enoughlong term resources

  • 8/7/2019 Construction-sector_update-Oct-09

    31/118

    30 Edelweiss Securities Limited

    Construction

    Anyways, IIFCLs overall exposure to the roads sector is low compared to the

    requirements. For the roads sector, the quantum of IIFCLs disbursal in FY09

    stood at INR 12.9 bn, which even though w as more than double the INR 5.8

    bn achieved in previous year, is still on the lower side . Also, while IIFCL had

    raised INR 100 bn earlier this year to refinance highways and port projects, it has

    not received a single proposal till date for funding. The pace of project awards in the

    time to come will determine whether IIFCL can achieve its target of lending INR 1 tn

    over the next five years.

    and, how much can they support

    Even assuming that banks aided by IIFCL are willing to fund projects, the sheer

    quantum of funds required means that doubts will continue to linger.

    Chart 8: Banking sector exposure to roads and ports sector

    0.0

    6.0

    12.0

    18.0

    24.0

    30.0

    0

    100

    200

    300

    400

    500

    1998

    1999

    2000

    2001

    2002

    2003

    2004

    2005

    2006

    2007

    2008

    2009

    (%)

    (INRbn)

    Roads/ports sector exposure As % of overall infra portfolio

    Source: RBI, Edelweiss research

    As shown in chart 8, total banking sector exposure to the roads and port

    sector was ~INR 470 bn at FY09 end. The share of the roads/ports sector in the

    overall infra portfolio of banks has been hovering around 17% for the past four

    years.

    We attempt a small exercise to ascertain the quantum of roads which can be funded

    in the current scheme of things. The banking sector exposure to infrastructure at the

    end of FY09 was ~ INR 2,700 bn.

    Assumptions:

    1. Banks credit to infra sector grows by 32% in FY10.

    2. Roads/ports sector share in overall infra portfolio of banks is 17% in FY09; itrises to 20% in FY10 with increased thrust on the sector.

    .and more importantly, howmuch can banks support roadprojects?

  • 8/7/2019 Construction-sector_update-Oct-09

    32/118

    Edelweiss Securities Limited 31

    Construction

    Table 15: Incremental fund availability to roads sector

    Particulars Funding

    Banking sector exposure to infra at FY09 end (INR bn) A 2,700

    Credit growth assumption for infra sector in FY10 (%) B 32

    Banking sector exposure to infra at FY10 end (INR bn) C = A*(1+B) 3,564

    Share of roads/ports sector in infra portfolio at FY09 end (%) D 17

    Share of roads/ports sector assumed in infra portfolio at FY10 end (%) E 20

    Incremental credit available for roads/ports sector in FY10 (INR bn) F = C*E-A*D 254

    Assumed share of roads in incremental credit (%) G 75

    Incremental credit available for roads in FY10 (INR bn) H = G*F 190

    Assumed debt funding for a typical road project (%) I 70

    Amount of road projects that can be funded (INR bn) J = H/I 272

    Source: RBI, Edelweiss research

    Table 15 shows that if the current scenario continues, only ~ INR 272 bn of

    road projects will be able to get funding. This needs to be juxtaposed with

    the ambitious plans of the central and state governments as far as the road

    development scene is concerned.

    The projects awarded on an EPC business will not face much problems; similarly,

    annuity based projects are also likely to face comparatively less problems due to

    absence of revenue risks. However, toll projects will pose a dilemma for banks due

    to associated toll risks. In any case, bank funding to the sector will have to take a

    quantum leap. In case the projects come up in a bunch, there is high probability that

    some of them will face funding delays.

    4. Equity commitment still the biggest worry and may emerge as the party

    pooper: The bigger worry for BOT projects, in our view, is the equity commitment

    required. With project sizes increasing and banks asking promoters to put in ahigher share of equity, the equity required for projects has increased substantially

    when compared to projects awarded two-three years ago.

    Coupled with this, the downtrend in equity markets (during the past one year) and

    drying up of private equity options had soured the pitch. PE funds were reluctant to

    invest as securitising toll fees and selling down to global pension funds as an option

    had disappeared for some time. Compounding the problem was the fact that

    the core contracting business (which anyways is a negative operating cash

    flow business) for most companies had taken a hit last year due to increase

    in commodity prices, interest rates, and slowdown in order intake, thus limiting the

    parents ability to pump in money.

    Many companies which had won projects in the 2005-07 period had hoped to sellstake in projects once they were complete and utilize the fund infusion to bid for

    future projects. Even as these projects became operational/achieved completion, the

    equity markets plunge poured cold water on such hopes.

    As per the Economic Survey 2008-09, infrastructure companies raised less money

    through public and rights issues in 2008-09 compared to the previous year. Public

    share sales and rights issues fell from INR 870 bn in 2007-08 to INR 147 bn

    in 2008-09.

    Equity commitment fromdevelopers side may createroadblocks

  • 8/7/2019 Construction-sector_update-Oct-09

    33/118

    32 Edelweiss Securities Limited

    Construction

    A ray of hope is, however, the signs of recovery in equity markets. Many companies

    have announced fund raising plans. A summary of the fund raising plans of major

    infra companies is given below:

    Table 16: Fund raising by companies

    Company

    Fund raising by

    companies (INRbn) Status

    HCC 4.8 QIP completed

    GVK 7.2 QIP completed

    Punj Lloyd 6.7 QIP completed

    Lanco 7.3 QIP completed

    Nagarjuna Construction 3.7 QIP completed

    Era Infra 3.0 Warrants allotted

    Reliance Infra 39.8 Warrants allotted

    Gammon Infrastructure 10.0 Shareholders's approval received

    Sadbhav Engg 1.3 Shareholders's approval received

    Unity Infraprojects 2.5 Shareholders's approval received

    Gammon India 9.6 Board approval received Source: Edelweiss research

    However, the amount of equity required for road projects is large. Assuming an

    equity contribution of 30% for road projects, ~ INR 200-300 bn of funds will be

    required for the equity commitment in upcoming road projects. Amidst such a

    scenario, it surely is advantageous for companies with low leverage levels which are

    in a better position to fulfill their equity commitment.

    Possible options to help solve the funding cononundrum

    Some of the options that can be tapped to ease funding pangs are:

    1. Long-term loans provided on reimbursable basis by the government.

    2. Multilateral funding institutions like the Asian Development Bank (ADB),

    International Finance Corporation (IFC), and DEG, can lend a helping hand.

    3. Currently, IIFCL can refinance only commercial banks. The facility can be extended

    to NBFCs and other institutions lending to the infrastructure sector. Also, IIFCL can

    finance only 20% of the project cost and 60% of debt has to be repaid in the first 10

    years of the project. A removal of these restrictions will ensure that more projects

    will achieve FC.

    4. Currently, ECBs can be used only for refinancing old ECBs at better terms or for

    undertaking capex. Allowing developers to access ECBs for repaying old rupee term

    loans on operational projects will help repay high-cost funds a