Upload
nrsc
View
215
Download
0
Embed Size (px)
Citation preview
8/7/2019 Construction-sector_update-Oct-09
1/118
Edelweiss Value ScannerEdelweiss Value ScannerEdelweiss Value ScannerEdelweiss Value ScannerEdelweiss Value Scanner
1
8/7/2019 Construction-sector_update-Oct-09
2/118
1 Edelweiss Securities Limited
Executive Summary
Executive Summary
Indias road infrastructure woefully inadequate
As per the Global Competitiveness Report 2008-09, inadequate infrastructure is the
biggest stumbling block in Indias economic growth. While India has the second largest
road network in the world, the report ranks it at a dismal 87 th spot as far as quality
of roads is concerned, way below neighbours China, Pakistan, and Sri Lanka.
With the kind of multiplier effect that roads have on economic growth, a quantum
increase in investments in roads is paramount to achieve long-term growth targets.
Light at the end of the tunnel
The National Highway Development Programme (NHDP) is Indias flagship and the
worlds largest PPP road development programme. It had hit speed bumps in 2006-
08, primarily due to frequent changes in the regulatory framework and economic slowdown.
However, 2009 has come as a breath of fresh air; since December 2008, the National
Highway Authority of India (NHAI) has awarded (or is evaluating bids for) 24
projects worth INR 228 bn. NHAI has an ambitious target of awarding 23,000 km
of roads during the next two years. It expects to receive bids for 49 projects
spread over 5,074 km, worth INR 511 bn by 2009 end. The government has set an
ambitious target of building 20 km of road per day. Amidst all this, encouraging signs on
credit availability, interest rates and capital markets mean that achieving financial closure
(FC) on projects has become considerably easier compared to last year. This infuses us
with the confidence that the travails of the past three years are behind us and the project
award process is likely to be on the fast track.
Size of opportunity at central and state level-humungous
The chronic underinvestment in roads over the past 60 years has meant that huge
investment is required over the next couple of years to prop up the road infrastructure.At the national level, of the total 54,454 km under the NHDP (including the
NHDP Phase IV), 36,926 km of roads are still to be awarded. Overall, the NHAI
expects to spend about INR 3,315 bn on completion of the balance part of NHDP. This is
in addition to the huge opportunity available for road development at the state level with
states like Karnataka (INR 1,770 bn opportunity in 2009-15), Andhra Pradesh, and
Gujarat taking steps to improve road infrastructure.
Outlook: Good long-term opportunity
The governments seriousness towards road development is evident from the steps taken
in the past couple of months to make projects more commercially viable. The major
stumbling block now is getting the funding required for the ambitious plans announced-
both debt and equity. In our view, cracking the funding code is the key to
unlocking the PPP opportunity in the medium term. The sheer scale of government
plans means that there are likely to be ample opportunities for every player in the road
segment. We initiate coverage on IRB Infrastructure, the leader in the Indian road
BOT space, with a BUY recommendation. While past has been good, the future
promises to be better than ever for the company which has built up an impressive
portfolio of lucrative projects. With the focus of this report being on developers, we also
feature IVRCL (BUY), Nagarjuna (BUY), GMR (REDUCE), Reliance Infra (BUY),
Gammon (HOLD), Sadbhav Engineering (NOT RATED), Madhucon Projects (NOT
RATED), and Gayatri Projects (NOT RATED) in this report.
8/7/2019 Construction-sector_update-Oct-09
3/118
2 Edelweiss Securities Limited
Construction
Contents
At a glance ................................................................................................................. 3
Road infrastructure woefully inadequate ......................................................................... 4
Light at end of tunnel .................................................................................................. 6
Huge opportunity at centre and state levels .................................................................. 18
Time To Think About The Constraints ........................................................................... 26
Foreign Companies in NHDP: Changing Scenario ........................................................... 33
Annexure I: Frequent policy changes and their impact on project award .................... 35
Annexure II: Steps taken to attract more interest for NHDP projects ......................... 36
Annexure III: Work plan (for Aug-09 Jul 10) for ministry of roads .......................... 37
Annexure IV: National highway opportunity (phase wise) ......................................... 38
BOT Projects Snapshot ............................................................................................... 39
Companies
IRB Infrastructure ............................................................................................... 41
Gammon India .................................................................................................... 63
Gayatri Projects .................................................................................................. 71
GMR Infrastructure .............................................................................................. 77
IVRCL Infrastructure ............................................................................................ 83
Madhucon Projects .............................................................................................. 89
Nagarjuna Construction ....................................................................................... 95
Reliance Infrastructure ...................................................................................... 101
Sadbhav Engineering ......................................................................................... 107
8/7/2019 Construction-sector_update-Oct-09
4/118
8/7/2019 Construction-sector_update-Oct-09
5/118
4 Edelweiss Securities Limited
Construction
Road Infrastructure Woefully Inadequate
As per the Global Competitiveness Report 2008-09, inadequate infrastructure is the biggest
stumbling block in Indias economic growth. While India has the second largest road system
in the world at 3.3 mn km, the report ranks the country at a dismal 87 th position as far
as the quality of roads is concerned, way below neighbours China, Pakistan, and Sri
Lanka.
Table 1: India ranks w ay below in quality of roads
Country Ranking for quality of roads
France 1
Switzerland 2
USA 8
Malaysia 17
Japan 19
UK 24
South Africa 40
China 51
Sri Lanka 63
Pakistan 69
India 87
Source: World Economic Forum, Global Competitiveness Report 2008-09, Edelweiss research
The inadequacy issue becomes evident from the fact that the average distance covered on
roads by truck in India is less than 250 km per day compared to ~1,000 km per day in the
US. While the high volume of vehicles on Indian highways, various tax regimes, and frequent
check posts on state borders are also culprits, a major portion of the blame lies with the
inferior quality of roads.
Table 2: China versus I ndiaA case study in r oad quality and impl ementation success
China India
In 1988, China did not have an inch of expressway. The
original plan, considered ambitious at that time, was to build
upto 35,000 km of National Trunk Highway System (NTHS),
of which 70% was to be expressways, before 2020. The
NTHS was completed by the end of 2007, 13 years
ahead of the original plan.
Expressways in India with a length of 200 km form a
minuscule share of the overall road network; national
highways (NHs) and state highways (SHs) at 2% and 4%
respectively, do not fare much better. Also, while NHs
carry 40% o f the overall roadtraffic, only 14% of
them are 4/6/ 8 laned. SHs, of which only 0.6% are 4-
laned, are in a worse situation.
At the end of 2008, the Chinese national expressway
network stood at 60,300 km (of which 6,433 km was built in
2008). This makes it the world's second longest
expressway network, after the United States and roughly
equal to that of Canada, Germany, and France combined.
The NHDP has repeatedly suffered cost and time overruns
over its lifetime. NHDP Phase I and II, originally
intended to be completed by 2003 and 2004 ,
respectively, are still not completed and are likely to
miss their revised timelines too. The same is likely to betrue for Phase III and V.
The plan is to increase the total length of expressways to
65,000 km by 2010, 85,000 kilometers by 2020, 120,000
km by 2030, and 175,000 km by 2050. By 2010, the
Chinese expressway network will connect all provincial
capitals and cities with at least half-a-million population, as
well as some with population ranging between 200,000 and
500,000. The annual investment between 2010 and
2020 is projected at USD 12 bn.
Between 1951 and 2006, the vehicle population grew at a
CAGR of close to 11%; the freight and passenger traffic
carried by roads grew at a CAGR of 10%. On the other hand,
the total road length grew at a CAGR of 3.9% with the NH
segment increasing by a mere 2.2 %. Also, it is estimated
that 50% of state and district roads (forming 18% of
the overall road network) are of poor quality, causing
a loss of INR 60 bn per annum.
Source: Edelweiss research
Quality of Indian roads hasbeen judged poorercompared to neighbours like
China, Pakistan and SriLanka
China is much ahead ofIndia, both in terms ofquality as well asimplementation success inroad development
8/7/2019 Construction-sector_update-Oct-09
6/118
Edelweiss Securities Limited 5
Construction
While quality continues to be an issue, road transport has emerged as the dominant segment
in Indias transportation sector. The entire increase in the transportation sectors share in the
GDP between 1999-2000 and 2004-05 came from the road segment. During the past few
years, road transport has grown at a much higher rate compared to other competing modes
like inland waterways, railways, and airways.
All this makes it imperative for a quantum increase in road investments, which is also
necessary to achieve the countrys long-term growth targets. An INR 1 mn investment in
roads (at constant 1993 prices) helps 165 persons cross the poverty line. A World Bank study
has assessed that every rupee invested in the highways sector yields 7x returns in economic
value. With this kind of multiplier effect, it is high time for India to increase its investment in
improving its road network, both in terms of length and quality.
8/7/2019 Construction-sector_update-Oct-09
7/118
6 Edelweiss Securities Limited
Construction
Light At End Of Tunnel
The National Highway Development Programme (NHDP), Indias flagship highway programme,
had hit speed bumps in 2006-08, first due to frequent changes in the regulatory framework
(p lease r e fe r A nnex u r e I ) and later due to an economic slowdown. The project award by
NHAI, which had touched new highs during 2005-06, progressively slowed down in the past
three years.
Chart 1: NHAI project award and implementation in various years
0
1,000
2,000
3,000
4,000
5,000
1999-00
2000-01
2001-02
2002-03
2003-04
2004-05
2005-06
2006-07
2007-08
2008-09
(km)
Project awarded Completed
Source: Government documents, Edelweiss research
The implementation of the new Model Concession Agreement (MCA) affected project awards
in 2006 and 2007. As against the original target of awarding projects spanning 10,641 km in
2008-09, the revised plan had envisaged NHAI awarding 60 BOT projects spread across
6,412 km. These projects worth ~INR 700 bn were to be awarded before March 2009.However, the imbroglio over the new pre qualification guidelines derailed the plans in H1CY08
and the economic slump and the liquidity crunch scuppered the dream in H2CY08. The NHAI
awarded eight projects spanning 643 km, worth INR 86 bn in FY09 under NHDP.
Table 3: NHDP targets and achievements in past two years
Target
(km)
Achievement
(%)
Target
(km)
Achievement
(%)
Completion 437 49 220 60
Tolling 1,869 55 2,003 61
Phase II Completion 2,013 55 2,522 61
Phase III Award of project 3,278 9 6,047 10
Phase V Contract 2,995 29 3,754 0
2007-08 2008-09
Phase I
NHDP Phase Category
Source: Government documents, Edelweiss research
What has changed?
With the NHDP suffering setbacks, the government took a series of steps to improve the
attractiveness of NHAI projects and address concerns of the road developer fraternity
(p lease r e fe r A nnex u r e I I ). The positive effect of these measures is trickling in now.
Regulatory issues andeconomic slump affectedproject award adversely
8/7/2019 Construction-sector_update-Oct-09
8/118
Edelweiss Securities Limited 7
Construction
Also, the liquidity crunch which had plagued the corporate world in the last quarter of 2008 is
now a thing of the past.
Chart 2: Net reverse repo position
(1,200)
(600)
0
600
1,200
1,800
Apr-08 Jun-08 Aug-08 Oct-08 Dec-08 Feb-09 Apr-09 Jun-09 Aug-09
(INRbn)
Net reverse repo
Source: Bloomberg, Edelweiss research
The Reserve Bank of India (RBI ) has taken various measures since September 2008,
which have resulted in augmentation of actual/potential liquidity of over INR 4,220
bn . In addition, the permanent reduction in the SLR by 1.0% of NDTL (net demand and time
liabilities) has made available liquid funds of INR 400 bn for credit expansion.
Table 4: RBI measures to boost liquidity
Sl. No. Measure Amount (INR bn)
1 CRR reduction 1,600
2 Unwinding/Buyback/De-sequestering of MSS securities 978
3 Term repo facility 6004 Increase in export credit refinance 255
5 Special refinance facility for SCBs (Non-RRBs) 385
6 Refinance facility for SIDBI/NHB/EXIM Bank 160
7 Liquidity facility for NBFCs through SPV 250
Total 4,228
Source: RBI, Edelweiss research
Another helping hand was lent by the cooling down of soaring interest rates, which had
adversely impacted project viability. RBI has cut the repo rate by 425bps and the reverse
repo rate by 275bps since September 2008, thus sending a strong signal to banks to reduce
interest rates. Reduction in the reverse repo rate was also a step towards discouraging banks
from parking their surplus funds with the central bank. This resulted in banks cutting their
lending rates with the prime lending rate of State Bank of India falling by 200bps since
September 2008.
Liquidity situation hasconsiderably improved ascompared to last year
8/7/2019 Construction-sector_update-Oct-09
9/118
8 Edelweiss Securities Limited
Construction
Chart 3: Reduction in interes t rates
3.0
5.3
7.6
9.9
12.2
14.5
Aug-08
Sep-08
Oct-08
Nov-08
Dec-08
Jan-09
Feb-09
Mar-09
Apr-09
May-09
Jun-09
Jul-09
Aug-09
(%)
SBI prime lending rate Repo rate
Source: RBI, Edelweiss research
The risk aversion of lenders to BOT projects (which are typically long term in nature) has also
decreased. Further, projects that are being awarded now will come up for financial closure
(FC) only towards the latter part of H2FY10 after completing various formalities. We expect
the situation on the FC front to improve by then.
And, last, business confidence has also recovered, with signs of a turnaround, rally in equity
markets across the globe, and a positive election outcome. The governments stated
objective of increased spending on infra projects (which was evident in the increased
allocation for various infra schemes in Budget 2009-10) has also come like a shot in the arm
for companies in the sector.
The effect is visible
Amidst all this, FY10 came as a breath of fresh air. Project award has resumed; since
December 2008, the NHAI has aw arded (or is evaluating bids for) 24 projects worth
INR 228 bn.
Interest rate reduction to
help BOT developers
8/7/2019 Construction-sector_update-Oct-09
10/118
Edelweiss Securities Limited 9
Construction
Table 5: Projects awarded/ bids under evaluation by NHAI
S. No. Project
Length
(km)
Total project
cost (INR bn)
VGF/ revenue
share Phase Developer
1 Vadakkancherry - Thrissur 30 6.2 VGF II KMC - CR18G Consortium
2 Pune Sholapur Pkg-I 110 11.1 VGF III Navinya Buildcon - Atlantia Spa
(JV)
3 Gujarat/Mh border - Surat -Hazira Port Section
133 15.1 VGF III Soma - Isolux Corsanconsortium
4 Pimpalgaon-Nashik Gonde 60 9.4 Revenue share III L&T - Ashoka Buildcon
consortium
5 MP/Mh Border-Dhule 97 8.4 Revenue share III HCC - John Laing - Sadbhav
Engg consortium
6 Cuddapah-Mydukur-Kurnool 189 15.9 VGF III KMC - IVRCL consortium
7 Elevated road from Chennai
Port-Maduravoyal
19 13.5 VGF VII Soma Enterprises
8 Kishangarh-Beawar 94 8.0 Revenue share III Soma - Isolux Corsan
consortium
9 Hyderabad-Vijayawada 181 17.4 Revenue share III GMR-Punj Lloyd consortium
10 Armur-Adloor-Yellareddy 60 4.9 VGF II Navyuga-KPCL consortium
11 Goa-Karnataka border to Panaji 65 4.7 VGF III IRB Infra
12 Amritsar-Pathankot 102 7.1 VGF III IRB Infra
13 Jaipur-Deoli 146 11.8 VGF III IRB Infra
14 Talegaon-Amravati 67 5.7 VGF III IRB Infra
15 Ghaziabad-Aligarh 126 11.4 VGF III PNC Infratech - SREI - Galfar
16 Kannur-Kuttipuram Pkg - I 83 13.7 VGF III KMC - CR18G Consortium
17 Kannur-Kuttipuram Pkg - II 82 13.1 VGF III KMC - CR18G Consortium
18 Pune Sholapur Pkg-II 110 8.4 VGF III IL&FS - ITNL
19 Hazaribagh-Ranchi 71 6.3 Annuity project III IL&FS - Punj Lloyd
20 MP/Mh border-Nagpur section 95 11.7 NA II Oriental Structural Engineers
21 Jaipur-Reengus 52 3.8 NA III Reliance Infra Source: NHAI, News reports, Edelweiss research
What the future holds in store?
NHAI has an ambitious target of awarding 23,000 km of roads in the next two years. This
involves inviting bids for projects spread over 13,000 km of roads in the next year
with an investment of ~ INR 1 tn.
Table 6: NHAI plan for next one year
NHDP phase No. of projects Length (km) Cost (INR bn)
Phase II 12 700 139
Phase III 96 8,825 602
Phase V 18 2,403 240
OMT projects 9 1,466 11
Total 135 13,394 993
Source: NHAI, Edelweiss research
Of the INR 982 bn required for the 126 projects under Phase II, III, and V, INR 546 bn is
expected to come from the private sector and the balance from the government.
Overall, a total investment of USD 70 bn is envisaged in the road sector in the next
three years. The private sector is expected to contribute USD 40 bn, of w hich USD
NHAI has ambitious plansfor project award in nextcouple of years
8/7/2019 Construction-sector_update-Oct-09
11/118
10 Edelweiss Securities Limited
Construction
10 bn is expected from foreign investors. Of this, USD 3-4 bn is expected in equity,
while for the balance, the government is looking at creating new debt instruments like
infrastructure bonds, securitising receivables, accessing the capital market, etc.
NHAI plans to seek bids for 71 projects spread over 7,987 km in the next two quarters worth
INR 616 bn.
Table 7: NHAI plan for next two quarters
NHDP phase No. of projects Length (km) Cost (INR bn)
Phase II 9 447 122
Phase III 43 4,261 339
Phase V 12 1,833 137
Phase VII 1 22 7
OMT projects 6 1,424 11
Total 71 7,987 616
Source: NHAI, Edelweiss research
NHAI expects to receive bids for 49 projects spread over 5,074 km worth INR 511 bn by
2009 end. News reports suggest that response to some of these projects has beenenthusiastic with an average of 15 bidders expressing interest.
These projects include an INR 95 bn plan to enhance road connectivity in Jammu & Kashmir
by undertaking four laning of the Jammu-Srinagar national highway on BOT-annuity basis.
Ministry of Roads also emerging as a big aw ardee
In addition to the NHAI, the road ministry also has a large list of projects that it expects to
award on a PPP basis. It has chalked up a plan to aw ard 58 projects worth INR 188 bn
by July 2010 on BOT basis (please see Annexure III). These projects involve building
7,515 km roads in various states and largely relate to converting existing roads into two
lanes in various states. The ministry will award these projects either by itself or through
respective state governments.
It has also received clearance for two laning of the trans-Arunachal highway from Nechipu to
Hoj (311 km) and Potin to Pangin (407 km) estimated at INR 14.3 bn and INR 19.1 bn,
respectively, both on BOT annuity basis. This is part of the ministrys INR 134 bn plan of road
development in J&K and North-East, as per its 100-day agenda submitted to the Prime
Ministers Office.
News reports suggest that the World Bank has agreed to lend USD 3 bn to the
government to develop 5,937 km of highw ays. The proposed loan will cover 70% of the
project cost, while government will provide the balance. These roads have low traffic and are
not viable on PPP basis; these roads are likely to be constructed with full government funding.
These highways are not part of NHDP . The government has identified 6,376 km of roads
to be developed over the next few years with government funding, of which 5,937 km will bedeveloped using the World Bank fund.
News reports suggest that the Ministry has also approved 63 projects that will connect the
most populated cities in country to national highways. These projects stretched over 8,982
km will be taken up next year under NHDP phase IV.
Apart from NHAI, Ministry of
Roads also has largenumber of projects to beawarded
8/7/2019 Construction-sector_update-Oct-09
12/118
Edelweiss Securities Limited 11
Construction
New government, new deal for road projects
Keeping the sluggish progress on the road project award scenario in 2006-08 in mind,
the new government post election responded by appointing Mr. Kamal Nath (earlier the
Minister for Commerce and Industry) as the Minister for Road Transport & Highways
Ministry. He has announced an ambitious target of building 20 km of roads per day.
Many initiatives have been taken since then to speed up the progress in the roads space.
A summary of the same is given below:
The erstwhile Ministry of Shipping, Road Transport and Highways has been
bifurcated into separate departments under different ministersMinistry of Ports and
Shipping and Ministry of Roads and Surface Transport to ensure focused efforts on
development of both sectors.
NHAI has been asked to finalise a framework for better execution of projects; this
will include establishing a unity of command for proper delegation of power and
better internal communication within NHAI.
NHAI has decided to issue the letter of award (LoA) only after it has
acquired 80% of the land required for a project and notification for acquiring
the balance has been issued. The balance 20% will have to be handed before FC. Till
now, NHAI used to award the project after acquiring 50% of land. This is likely to
reduce delays due to land acquisition.
Budget 2009-10 has increased the allocation for NHAI by 23% to INR 85.8
bn compared to last years allocation of ~ INR 70 bn . The government has also
proposed an investment of INR 41.4 bn in 2009-10 for developing national highways,
besides those built by NHAI.
The 2009-10 budget has exempted highway developers from the 8% excise duty on
goods manufactured at work sites.
The budget has also allowed India Infrastructure Finance (IIFCL) to refinance 60%
of commercial bank loans for PPP projects. Also, IIFCL has been mandated to evolve
'takeout financing schemes with banks through which it will pick up infrastructure
loans from banks books.
The Prime Minister had set up a committee to suggest fast-track mechanisms to
improve inter-ministerial coordination for speeding up road projects. The
committees mandate was to examine ways to expedite award of projects, financing
road projects, restructuring of 4/6 laning projects based on traffic requirements and
those in backward areas and to make suggestions for making projects attractive for
banks and private investors. The committee has recently submitted its report to the
Prime Minister.
News reports suggest that the committee has recommended that government
should support NHAI in its borrowing programmes by offering sovereign guarantee.
This is likely to make it easier for NHAI to raise loans from international
organisations as well as lowering the rate of interest on its loans.
It has also recommended delegation of power to the road ministry on issues related
to MCA, RFQ, and RFP.
The government has approved the formation of an empowered group of ministers
(EGoM) to fast-track road projects. The EGoM will remove various policy bottlenecks
which do not require approval of the Cabinet or Cabinet Committee on Infrastructure
(CCI). The EGoM has the power to fine-tune regulations and change the bidding
norms for road projects if required.
Governments commitment toroad development shows inincreased allocation for roadprojects and other regulatoryreforms
8/7/2019 Construction-sector_update-Oct-09
13/118
12 Edelweiss Securities Limited
Construction
Proposed measures:
Along with the above mentioned initiatives, news reports suggest that several
measures are in the pipeline to achieve greater progress on road development front:
Proposal to amend the cross holding clause: The revised RFQ guidelines issued
by the Ministry of Finance in May 2009 had raised the earlier limit of 1% related to
conflict of interest to 5%. In essence, the new guidelines state that a bid will be
disqualified if an investor or its associate holds more than 5% (directly or indirectly)
in another company which is applying for the same project. The new RFQ guidelines
also state that this clause is not applicable for ownership by banks, insurance
companies, pension funds, and public financial companies.
Our interaction with ministry officials suggests that the government is considering a
proposal by way of which the conflict of interest margin may be raised
substantially from the current 5%. Government may also limit provisions of the
clause to direct holding. News reports suggest that the limit has been raised to
25%.
Our take: More than equity stake, management control should be the determining
factor. With most companies bidding in consortia, the 5% clause invariably crops up.
News reports suggest that INR 100 bn of investment in roads sector has been
blocked due to this rule. With the amount of investment that the government is
targeting in road projects, a fast resolution of this concern is necessary.
Proposal to amend the threshold technical capacityclause: The revised RFQ
guidelines had also doubled the threshold technical capacity required to bid for a
project. This means that to bid for a project of a certain total cost, the bidder
should have the experience of implementing projects at least twice that
cost in the preceding five years, i.e., to be eligible to bid for an INR 5 bn project,
he should have implemented projects worth INR 10 bn in the previous five years. As
per the old RFQ norms, the limit was set up at 100% of the project cost.
Many smaller developers opposed this saying that the revised norms will benefit
bigger developers and foreign companies and thus will leave smaller companies in adisadvantageous position. This will also limit competition as only a few developers
will be able to put in their bids.
Our interaction with ministry officials suggests that the government is considering a
proposal to roll back the change in regulations so that the old RFQ norms come into
place again.
Our take: Considering the large number of projects that the government is planning
to award, it needs to use the services of every developer available. A larger number
of developers will ensure better competition; more so considering the fact that most
projects awarded in the past eight-nine months have seen bids from only 2/3
bidders.
Proposal to amend the termination clause: This has been a major eyesore for
many developers. This clause states that in case the traffic on any BOT project
exceeds the design capacity for four years at a stretch, NHAI may terminate the
concession agreement unless the developer agrees to enhance the projects capacity.
For e.g., in case of a four-lane project, if the traffic exceeds the design
capacity for four consecutive years, NHAI may terminate the agreement
unless the developer agrees to enhance the roads capacity to six lanes.
Our interaction with ministry officials suggests that the government is considering a
proposal to amend this clause and introduce a more developer-friendly mechanism.
Our take: This clause created uncertainties regarding the eventual duration of the
concession period as well as cash flows from projects. With the upsides on traffic
Government looking to makeregulatory framework morefavourable for developers
Many steps being taken togenerate more developerinterest for roads
8/7/2019 Construction-sector_update-Oct-09
14/118
Edelweiss Securities Limited 13
Construction
capped (by linking it to concession period duration), developers were naturally not
enamored with this clause.
Proposal to provide an exit clause for the lead member: Currently, the lead
member in a consortium has to maintain 26% stake in the project SPV even after
completion of the project. News reports suggest that government is considering a
proposal to relax this clause so that developers can sell their stake and use thefunds for developing new projects.
Our take: As the project goes through different stages, different type of investors
would be interested in it. Once a project has been developed, the developer should
not be constrained in a major way to remain attached to the project. Allowing him to
sell stake and use the funds for new projects will be more beneficial. Once the
project is complete, more risk averse investors and pension funds will be willing to
come in. This will ease funding pains for the developer community.
Proposal to vest ownership of roads with NHAI: The government is considering
a proposal to vest the ownership of roads with NHAI; it will then be leased out to
developers who will then raise loans against them. Currently, roads are not owned
by NHAI; it only allows developers to collect toll on them. Thus, developers cannot
use roads as collateral while borrowing from banks and other f inancial institutions.
Our take: While this will be a novel way to ease financing concerns, legal issues
(such as stamp duties and taxes to be paid) will have to looked into first.
Setting up of special land acquisition units: TheNHAI has decided to set up 150
special land acquisition units across various states to deal with land acquisition
problems. These units will be developed for each project in respective states; it is
proposed that they will comprise state government officials, who will carry out the
entire land acquisition process on behalf of NHAI. Currently, land acquisition
typically takes 24 months; NHAI plans to pare this time to 11 months.
To push the land acquisition process, responsibility has been fixed on project
directors, chief general managers (CGMs), and members of NHAI. Ten such units are
coming up in Rajasthan, 13 in Bihar, 25 in Uttar Pradesh, seven in Gujarat, 11 inOrissa, 13 in West Bengal, four in Jharkhand, 11 in Maharashtra and five in Assam.
Around 40 are already operational in Tamil Nadu and Karnataka and sanction has
been received for Goa. The NHAI has also started the process of setting up 10
regional centers to be headed by CGMs in Lucknow, Patna, Jammu & Kashmir,
Chennai, Guwahati, Delhi (Haryana & Punjab), Nagpur, Bangalore, and Kolkata.
Our take: Land acquisition is the biggest factor responsible for delays in project
implementation. As per a recent survey of major infrastructure projects facing
delays, land acquisition problems were responsible in 70% of cases. Also, news
reports suggest that NHAI was unable to acquire land in eight states in Q1FY10.
With NHAI now deciding to award LoA only after 80% of land acquisition is
completed, efforts on this front need to be increased to speed up execution.
Proposal to set up an expressway authority: The government intends to createa separate expressways authority, on the lines of NHAI, which will singularly
concentrate on construction of expressways across the country. Such a move is
likely to give an impetus to the construction of expressways in the country. The
government intends to take up construction of about 1,000 km of expressways in
four identified stretches under NHDP Phase VI. The proposed stretches are: Delhi-
Meerut (66 km), Vadodara-Mumbai (400 km), Kolkata-Dhanbad (277 km), and
Bangalore-Chennai (260 km).
News reports suggest that the governmentis also contemplating building a
network of expressways spanning 17,661 km by 2022 (end of the
Thirteenth Five Year Plan). A draft report has suggested that the expressways be
Government taking steps toensure administrative issueslike land acquisition are handled
efficiently
Government undertakingmeasures to improve viability ofroad projects
8/7/2019 Construction-sector_update-Oct-09
15/118
14 Edelweiss Securities Limited
Construction
built as per the following two schedules: (a) 2,665 km by 2012, 3,690 km by 2017,
and 6,031 km by 2022 on toll basis; or (b) 2,665 km by 2012 in the first phase and
9,721 km by 2017 in the second phase on toll basis. Along with either of the two
options above, the report has suggested building 5,275 km of roads on an annuity
basis till 2022.
Proposal to classify toll receipts as tangible assets: Currently, many banksclassify toll receipts as intangible assets which results in project loans to developers
being classified as unsecured loans. This attracts higher provisioning charges and
hence, the cost of loans for borrowers goes up. The government is studying a
proposal to classify toll receipts as tangible assets which will help developers
mobilise finance.
Proposal to seek foreign funds for road projects: The government recently
indicated that it is looking at sovereign wealth funds, private equity funds, and
pension funds to fund road building in India. The roads minister has already
undertaken road shows to meet investors to discuss which financing platforms would
be most effective. The government has earmarked USD 20 bn per year for road
building and expects foreign investors to fund half of this. The government aims to
reform policy and ease investment rules for infrastructure projects in an effort to
attract foreign capital.
Setting up a forum to address developer concerns: The government has
agreed to institutionalise a CII-Ministry of Roads-NHAI forum, as a mechanism to
address industry concerns. This forum will meet every month under the leadership
of secretary, Ministry of Roads, and report back to the minister on the progress
made on various issues.
Proposal to securitise cess and toll revenues: The government is considering a
proposal to securitise the cess that it levies on petrol and diesel and the toll it
collects from tolling bridges and bypasses on NHs (these two sources together
contributed INR 87 bn in FY09). This will help the government augment its resources
for road development.
Proposal to exempt SPVs from dividend distribution tax (DDT): News reports
suggest that the Roads Ministry is asking for an exemption from the dividend
distribution tax (DDT) for SPVs which are developing highways. Under the existing
income tax laws, both the SPVs and the holding company pay taxes when they
declare dividends. This is a major disincentive for developers. The ministrys
proposal is aimed at reducing the cascading tax effect.
Proposal to set up an independent regulator for highways to oversee all NHDP
phases. The regulator will examine problems faced in implementing NHDP projects
including land acquisition or disputes arising during the bidding process.
Proposal to make the toll collection process automated in projects executed through
the PPP mechanism. This is because it is felt that leakages under the manual system
of toll collection undermine the viability of road projects for government and
developers.
Proposal to set up an arbitration body for roads that will be an institutional set up to
deal with disputes between contractors and NHAI. As per Government estimates, as
much as INR 100 bn worth funds are stuck because of disputes between developers
and the NHAI.
Other measures that can be looked into:
Mix of annuity and toll: While currently, there are two clear models under the PPP
mechanismtoll and annuitythere is no model which encompasses the
Willingness on part ofGovernment to listen todeveloper concerns
8/7/2019 Construction-sector_update-Oct-09
16/118
Edelweiss Securities Limited 15
Construction
characteristics of both. Such a model may well emerge as a win-win proposition for
all stakeholders.
NHAI had some time ago proposed a new hybrid BOT model which combined the
characteristics of both the toll as well as annuity payment models. A draft MCA was
designed for this purpose and a communiqu was circulated among developers
seeking their feedback on the same.
Currently, under the BOT (annuity) model, no viability gap funding (VGF) is made
available to the developer and he has to bear the entire project cost. The project
cost/investment is recouped by the developer through annuity payments made by
NHAI after the construction is over, while the toll collected goes to the NHAI.
However, under the BOT (toll) model, the developer has to recover his investments
through toll collection. Depending upon the viability of the project, he may ask for a
viability gap funding (currently capped at 40% of the project cost) from the NHAI or
may agree to share revenues with the NHAI.
The hybrid model had proposed that in case the amount of VGF quoted by
the developer is more than 40% of the project cost, the funding
requirement in excess of 40% of the cost would be paid to the developer in
the form of annuity payments. Significantly, even while the incremental payment
would have been made by the government, the developer would have been allowed
to collect the toll through the concession period.
However, the government has rejected the hybrid model and has decided to go
along with the current annuity and toll models.
Our take: Our interaction with developers suggests that they were in favour of the
hybrid model. The new model would have reduced the financial risk for the
developer in case toll collection was not as per expectations since he would have
received an assured annuity payment from the government. Many projects in the
past couple of months could not be awarded as the VGF quoted by developers
exceeded the 40% cap. The new model would have made these projects viable and
increased the pace of project awards.
The government would also have had to pay only the incremental amount as annuity
under this model (against the earlier practice of paying the entire annuity amount
under the BOT-annuity model). This would have had the advantage of reducing
annuity payments significantly as well as transferring the commercial risk from NHAI
to the developer.
Another method that can be tried is to allow a project to run on the annuity mode till
the time the traffic on the project reaches such a level that it becomes viable under
the toll mode. This will lessen the burden of annuity payment that the government
has to bear.
Relook at the waterfall mechanism: Under the current waterfall mechanism
followed by NHAI, a project is first invited under the BOT-toll mode. In case of
inadequate response, the BOTannuity mode is used. In case even this fails, the
project is given on cash contract basis.
Our take: While theoretically, letting market forces determine the viability of a
project is the right way, the current method takes a long award time in case the
project is not viable under the PPP mode.
A faster way to award projects could be to assess the viability of awarding a contract
on the BOT-toll model before the tender is invited. In case a project is not
considered viable under the BOT-toll method, the annuity-based method could be
used directly without going through the bidding process.
Flexible approach needed tospur road development
Measures to fast track roadproject award and removeirritants in current processneed to be taken
8/7/2019 Construction-sector_update-Oct-09
17/118
16 Edelweiss Securities Limited
Construction
In a way, the government has already started working on this. It has decided that
project development mode will be decided as per the vehicular traffic on the road as
shown below:
Table 8: Project development mode
Vehucular traffic (in PCUs) Project development mode
> 15,000 BOT-toll10,000 - 15,000 BOT-annuity
< 10,000 EPC
Source: Edelweiss research
News reports suggest that the Government is considering a new policy under which
all road highway projects are to be earmarked from the beginning to one of three
processes of bidding, on the basis of its financial viability. NHAI has, under the new
policy, identified 6,831 km to be bid on toll, 1,143 km on annuity and 3,954 km on
EPC in FY10.
Updated cost estimates for projects: A major grouse that developers hold
against NHAI is that project cost estimates are woefully outdated and totally out of
sync with the current ground situation. A comparison of the estimated cost of someprojects as per NHAI and developers is pertinent in this respect:
Table 9: Variation between NHAI and developer cost estimates
Project
NHAI cost
estimate (INR bn) Developer
Developer cost
estimate (INR bn)
Variation
(%)
Talegaon-Amravati 5.7 IRB infra 8.5 50.6
Goa/KNT border - Panaji 4.7 IRB infra 8.4 77.4
MP/Maharashtra border - Dhule 8.4 HCC/John Laing/Sadbhav 14.2 69.5
Hyderabad-Vijaywada 17.4 GMR/Punj Lloyd 22.0 26.4
Source: Edelweiss research
While the government has taken measures to ensure that cost estimates are more
in tune with ground realities, a lot more needs to be done to reduce the variation.
Setting up a system of empanelled developers: The roads ministry has decided
to set up a system of empanelled developers by pre qualifying them for a period of
one year. This will be done by establishing their qualification strengths. We believe
such a step should be used for NHAI projects as well since it will streamline and
simplify the process of qualification of bidders as well as save time taken to arrive at
the bidding stage.
Our take: Government seriousness shows through even if target is
daunting: The target that the government has set for itselfbuilding 20 km of roads
per dayis definitely daunting, considering the fact that the current execution rate is
not even half of that. The NHAI chairman has said that achieving such a target will
take atleast 18 months. Even then, it will require a massive capacity enhancement
exercise at NHAI, developers, contractors, banks/financial institutions, and state
governments (responsible for land acquisition) to achieve the target.
The government has taken a plethora of steps in the past three-four months to
make the sector more commercially attractive. It recently said that all amendments
to the MCA will be completed by September 2009 end to attract investments. With
the government seriously showing its intent to address grievances of all
stakeholders involvedNHAI, developers, banks/financial institutions, among others-
and establishing a definite time frame to solve various issues, its commitment to
achieving a substantial jump in the pace of road development is evident.
Government committed to aquantum improvement incountrys road infrastructure
8/7/2019 Construction-sector_update-Oct-09
18/118
Edelweiss Securities Limited 17
Construction
Outlook: Future looks bright
The NHDP had run aground in the past three years, entangled in a maze of regulations
and unfavourable economic scenario. With both these irritants out of the way, we expect
a faster pace of project awards. With the government willing to look into the problems of
developers and taking steps to remove the roadblocks, things definitely look better than
a year ago. This makes us believe that the travails of the past three years are behind us
and we are well on the road to seeing some heightened activity on the project awards
scene. To conclude, it looks like there definitely is light at the end of the tunnel as far as
the road development space is concerned.
8/7/2019 Construction-sector_update-Oct-09
19/118
18 Edelweiss Securities Limited
Construction
Huge Opportunity At Centre And State Levels
Road projects have been at the forefront of the privatisation move in the Indian infra sector.
BOT road projects account for 81% of total PPP projects awarded in India, as far as number
of projects is concerned. This shows the rapid strides made as far as popularising the PPP
route in the road sector. The heartening thing is that the past has been good and the future
promises to be even better.
If there is one word to describe the opportunity in the Indian roads space, it is humongous.
While the expected investment in NHDP is INR 3,315 bn during 2006-17, it is not the only
place where the action is happening. The NHDP accounts for only 47% of the total road
sector investment in the Eleventh Five Year P lan. State roads, at 37% of the investment,
also form an important segment for any developer/contractor in the road space. Also, as far
as rural roads are concerned, the Eleventh Plan envisages spending over INR 400 bn on them
(investment on rural roads is sourced from the Prime Ministers Grameen Sadak Yojna,
(PMGSY) under the Bharat Nirman Programme). With the public sector contributing a
majority of funding for state roads and completely for rural roads, opportunities in these
segments are available more for contractors than developers.
We take a look at the upcoming road opportunity at the central level as well as the initiatives
taken by various state governments to foster road development. Our focus is on the PPP
opportunity at the central and state levels, since privatisation is the buzzword in the Indian
road sector today.
NHDP: Developing the countrys arterial network
NHDP, launched in 1998-99, has seen its scope getting enhanced from the two phases
envisaged initially to seven phases covering more than 54,000 km (p lease re fer
annex u r e I V fo r de ta i l s o f v a r i ous phases ).
Table 10: Various phases of NHDP
Phase Length (km) Date of approval Original approvedcost (INR bn)
Phase - I 7498 * Dec-00 303
Phase - II 6647 ** Dec-03 343
Phase - III A 4,815 Mar-05 330
Phase - III B 7,294 Apr-07 476
Phase - IV 20,000 Jul-08 *** 278
Phase - V 6,500 Oct-06 412
Phase - VI 1,000 Nov-06 167
Phase - VII 700 Dec-07 167
Total 54,454 2,476
Source: NHAI, Edelweiss research
Note: * Includes 5,846 km of GQ, 981 km of NSEW, 356 km of port connectivity, and 315 km of other roads** Includes 6,161 km of NSEW and 486 km of other NHs
*** 5,000 km were approved by CCEA in July 2008
While the NHDP started with awarding projects on cash contracting basis, the focus has
progressively shifted towards the PPP approach. The government in 2005 decided to
award all projects in NHDP Ph III-VII using the PPP approach. Since then, the BOT
approach has been the predominant mode of award. The status of BOT projects in NHDP
till date is summarised below:
Huge opportunity both atcentral and state level
NHDP Worlds largestPPP road developmentprogramme
8/7/2019 Construction-sector_update-Oct-09
20/118
Edelweiss Securities Limited 19
Construction
Chart 4: BOT toll projects in NHDP
77
26
5,677
1,171
456
87
0 1,000 2,000 3,000 4,000 5,000 6,000
Awarded
Completed
Cost (INR bn) Total length (km) No. of concessions
Source: NHAI, Edelweiss research
Chart 5: BOT annuity pro jects in NHDP
25
11
1,376
713
94
38
0 300 600 900 1,200 1,500
Awarded
Completed
Cost (INR bn) Total length (km) No. of concessions
Source: NHAI, Edelweiss research
Over the years, delays in implementation and restructuring in certain cases has meant
that the cost of NHDP has been revised upwards many times. The revised cost estimates
for various phases are as follows:
Table 11: Cost of NHDP phases (2006-17) (INR bn)
NHDP phase Modified cost estimates
Phase I and II (balance work) 684Phase III 1,143
Phase -IV 393
Phase -V 515
Phase -VI 229
Phase -VII 167
SARDP-NE, ICTT Cochin and others 184
Total 3,315
Source: NHAI, Edelweiss research
PPP approach gainingacceptance in NHDP
8/7/2019 Construction-sector_update-Oct-09
21/118
20 Edelweiss Securities Limited
Construction
As is evident, the NHDP involves an investment of INR 3,315 bn during 2006-17. The
expected funding for the same is shown below:
Chart 6: Funding sources of NHDP phases (2006-17) (I NR bn)
243
723
274
444
136
104
46
441
420
119
71
93
63
138
0 200 400 600 800 1,000 1,200 1,400
I and II (Balance work)
III
IV
V
VI
VII
SARDP-NE, ICTT Cochin & others
(INR bn)
Private Sector Public Sector
Source: NHAI, Edelweiss research
A significant portion of the opportunity still remains to be tapped. Substantial completion
has been achieved only on the initial two phases. The main focus currently is on
completing these two phases and to award project under Phases III and V.
Table12: Status of various NHDP phases
PhaseTotal
length (km)
Already
4-laned (km)
Under implementation
(km)
Balance for
award (km)Likely completion date
Phase I 7,498 7,227 265 6 Substantially completed
Phase II 6,647 3,451 2,444 752 Dec-10
Phase III 12,109 937 2,155 9,017 Dec-13
Phase IV 20,000 0 0 20,000 Dec-16
Phase V 6,500 131 899 5,470 Dec-13
Phase VI 1,000 0 0 1,000 Dec-16
Phase VII 700 0 19 681 Dec-15
Total 54,454 11,746 5,782 36,926
Source: NHAI, Edelweiss research
As can be seen above, of the total 54,454 km under the NHDP (including NHDP Phase IV
which will be implemented by Ministry of Roads), 36,926 km of roads are still to be
awarded. Of the seven phases, NHDP Phase IV and VI are yet to see any action on
ground while awarding under Phase VII has just begun. This means that there is a huge
opportunity waiting to be tapped by developers as far as NHDP is concerned.
PPP opportunity at state level: The undiscovered paradise
While NHDP hogs most of the spotlight, many states have been quietly and steadily
drawing up the roadmap for PPP projects in the road sector. In fact, the phenomena of
state PPP projects is old, with states like Rajasthan passing enabling resolution for
inviting private participation in roads way back in 1994. Other states like Gujarat had
started awarding PPP projects (like the Vadodara-Halol project which was completed in
2000) much before the turn of the century when NHDP projects picked pace.
NHDP entails huge fundingrequirements
PPP opportunity at state levelis probably bigger than NHDP
8/7/2019 Construction-sector_update-Oct-09
22/118
Edelweiss Securities Limited 21
Construction
The reason why the state PPP scene attracts relatively less attention than the NHDP is
because of the comparatively dispersed scene of action. Also, the level of activity differs
from state to state. While states like Maharashtra, Gujarat, and Rajasthan are active as
far as attracting private investments is concerned, there are many states which do not
have a PPP policy and a PPP cell even today. Also, the regulatory frameworks vary with
states having their own MCAs.
The level of investment at the state level till now is also low . Part of it can be
blamed on the slackness of states to take steps to set up the necessary
regulatory framework. Also, there have been apprehensions regarding the credit
worthiness of the involved state bodies (against NHAI, which is a AAA (Ind) rated
entity).
However, things seem to be changing now. State governments seem to have realized the
enormous potential of the private sector as far as developing the road network is
concerned. Also, increasing awareness about the positive impact of a robust
infrastructure network seems to be trickling in. All in all, we are set to see an enhanced
level of activity as far as the state PPP scene is concerned. We present the future
opportunity available in major states.
Karnataka: INR 1,770 bn opportunity
Karnataka has decided to develop a Core Road Network (CRN) spanning
66,000 km at an estimated cost of INR 1,770 bn under the PP P mode (BOT-
toll) over the next six years (2009-15). The CRN is to be developed in three
phases: (i) first phase involving the development of 10,000 km of state highways
(SHs) and major district roads (MDR) and 12,600 kms of village roads (VRs). The
estimated cost of developing state highways and MDR is INR 314 bn; (ii) second
phase with 40,000 km of roads to be developed at an estimated cost of INR 1,088
bn; and (iii) third phase comprising 16,000 km with an investment of INR 368 bn.
The CRN will connect the major IT centre of Bangalore with other IT hubs such as
Mysore, Hassan, Davangere, Hubli, Dharwad, and Mangalore to promote industrialand urban development besides integrating economically backward and remote
areas. It will be an all weather, smooth, speedy flowing road network with minimum
two lane carriageway including feeder roads and four-six lanes near urban
settlements.
The concession agreement initially developed for these roads had innovative
features like award of land pockets to developers to set up roadside amenities like
restaurants, which was to be an additional source of revenue for companies. It
proposed that developers would be eligible for one acre of wayside amenity land for
every 5 km of project road (SHs//MDR plus VRs). Land acquisition and development
was to be undertaken by developers. However, most of the developers that evinced
interest in the programme were uncomfortable with land acquisition. Upon their
requests, the government has now decided to acquire the land required for thedevelopment of these roads on its own.
Also, the state government has drawn up a plan for the overall development of
Bangalore with an outlay of INR 220 bn. The plan includes 12 major signal-free
corridors, three elevated corridors, strengthening of arterial and sub-arterial roads,
construction of 40 railway over and under bridges, etc.
Meanwhile, the much delayed Peripheral Ring Road in Bangalore is also expected to
see the light of the day. The state government has given the go-ahead for the first
phase of the project. It will be implemented by the Bangalore Development
Karnataka plans to spendINR 1,770 bn on roaddevelopment through PPPapproach in 20009-15
8/7/2019 Construction-sector_update-Oct-09
23/118
22 Edelweiss Securities Limited
Construction
Authority (BDA) in partnership with private companies. The road, once it fully
encircles the city, will be 116 km long and is expected to cost upwards of INR 30 bn.
Gujarat: The early mover
The Gujarat government has been active as far as PPP projects in the road sector
are concerned. It was the first state in India to have a law governing BOT
projects and such other arrangements along with private participation in
infrastructure projects. The state witnessed the completion of the Vadodara-Halol
and Ahmadabad-Mehsana toll projects in 2000 and 2003, respectively. The Gujarat
State Road Development Corporation (GSRDC) had last year signed a concession
agreement with Larsen and Toubro (L&T) for construction of three road corridors in
the state with a total length of 485 km and a project cost of INR 43 bn.
The state government has now plans to undertake improvement of roads with
private investment of about INR 90 bn. This involves developing 2,600 km of roads
with an investment of INR 30 bn on annuity basis and of 1,000 km of roads with an
investment of INR 60 bn on toll basis. The government has started with the projects
on annuity basis which would ensure a fixed stream of revenues for companies. Also,
the state government is assuring developers that 95% of the land will be made
available to them at the beginning of the project. This compares favourably with 50-
60% that most companies usually get in NHAI projects.
Also, the government has drawn up an ambitious plan for road development in the
state. The proposed investment is ~ INR 300 bn in 2010-12 and ~ INR 200
bn in 2012-17. PPP w ill be the major source of funding, contributing ~ INR
110 bn in 2010-12 and ~ INR 120 bn in 2012-17.
Andhra Pradesh: The programme approach
The state government has to its credit successful highway development programmes
such as the World Bank funded Andhra Pradesh State Highway Project (APSHP). The
government has already awarded 38 road projects on BOT basis worth INR 77 bn.
With the success of APSHP, the state government has now proposed a second
project, i.e., AP Road Sector Project (APRSP) for improvement and better
management of roads. The programme involves four laning of 1,252 km of roads
under the PPP basis; it also includes upgradation and improvement of 600 km of
roads and long-term performance based maintenance contract (LTPBMC) for 6,523
km of roads. Apart from this, there are 15 projects currently in the pipeline to be
awarded under the BOT model.
Madhya P radesh: The BOND-BOT approach
Madhya Pradesh (MP) has taken some innovative steps to foster the development of
the road network through the PPP route. It initiated the Bond-BOT scheme to
develop 2,000 km of state roads on BOT basis. The projects were aided by the state
government through a subsidy of INR 5 bn, which was raised by a bond issue underthe Madhya Pradesh Infrastructure Investment Fund Scheme. The projects
developed during the scheme included the likes of the 203 km Indore-Edalabad
project and the 247 km long Rewa-Amarkantak project.
MP was als o the first state to receive VGF from the central government. The
state has also been able to award BOT projects on a negative
grant/ revenue sharing basis, indicating the attractiveness of the stretches.
The state has completed projects spread over 1,532 km on BOT basis while projects
spanning 965 km on BOT basis are under development.
Gujarat ambitious roaddevelopment plans
8/7/2019 Construction-sector_update-Oct-09
24/118
8/7/2019 Construction-sector_update-Oct-09
25/118
24 Edelweiss Securities Limited
Construction
DBFOT model on an annuity basis. Land acquisition for phase I of the ORR from
Vandalur to Nemilichery has been completed. GMR Infrastructure recently won the
bid to develop this 29.65 km stretch at a cost of ~ INR 11 bn.
Apart from this, a road network development scheme for Chennai under the second
master plan has also been conceptualised. This plan, called the Chennai
Elevated Expressways, is to be developed at a cost of INR 130 bn. A total of
nine elevated corridors have been proposed in the medium term while 12 corridors
have been proposed in the long term. The overall project is to be completed by
2019-20.
Also, recently the state government stated that it proposes to develop and upgrade
12,000 km of road at an outlay of ~ INR 40 bn. While 5,500 km roads will be
widened, maintenance work will be carried out on 6,500 km roads. During the past
three years, the government had upgraded 3,270 km of major district and other
district roads into state highways.
Maharashtra: Leading the pack
Maharashtra is the leader as far as attracting private investment in road projects is
concerned. It formulated a policy in 1996 to finance road development projects
through private sector participation. A cabinet sub-committee has been formed to
take fast decisions related to infrastructure projects. The state has already
completed 16 major projects costing INR 54 bn. Further, 14 projects costing INR
108 bn are under development.
The state has ambitious plans regarding future projects. Upcoming projects include
the Worli-Nariman Point Sea Link, integrated road development programmes in
many cities, widening of various state highways on BOT basis, among others.
Punjab: Expressway all the way
The Punjab Industrial Development Board (PIDB) is the nodal body for infra
development in the state and is designated as the PPP cell for infrastructuredevelopment in Punjab. The state has already completed nine BOT projects in the
road sector.
The PIDB has an ambitious programme as far as future PPP projects are concerned.
Future projects include five ambitious expressw ays, viz., Mohali-Phagwara
Expressway (INR 25 bn), expressway around Mohali (INR 23 bn),
expressway for Amritsar Airport, Pathankot-Ajmer Expressway (INR 86 bn),
and expressway in Ropar along Sidhwan Canal up to Ludhiana. Other PPP
projects included two ring roads (the Amritsar ring road at a cost of INR 20 bn and
the Ludhiana ring road to be built at an estimated cost of INR 30 bn) apart from
various other road projects.
Haryana: Venturing out
The state government has approved the improvement of the Gurgaon-Faridabad
road, Ballabhgarh-Pali-Dhauj-Sohna road, Chandimandir-Jallah road, Bhuria-Khadri-
Deodha Nainawali road, and Yamunanagar-Ladwa-Karnal road on PPP basis. Of this,
the Gurgaon-Faridabad project has been already awarded to Reliance Infra. The
government is also planning a North-South and East-West corridor at an estimated
cost of INR 40 bn.
New entrants looking to catch upwith early movers
8/7/2019 Construction-sector_update-Oct-09
26/118
Edelweiss Securities Limited 25
Construction
Orissa: Taking first steps
Orissa has a road network of around 2.38 lakh km (including 3,100 km of NHs). The
state has embarked on an ambitious plan for improving road connectivity through
the PPP route.
Upcoming projects include the Capital Region Ring Road (INR 3 bn), Bhubaneswar-Paradeep Road (INR 5.6 bn), four Laning of Sambalpur-Rourkela Road (INR 12.7 bn),
Koira-Tensa-Lahunipara Road (INR 4 bn), among others.
Summary
The opportunity at the state level for the PPP route is abundant. The overall quantum
rivals that of the NHDP and is perhaps even bigger than it. However, the opportunity is
spread across a wide spectrum and the level of preparedness for PPP projects across
various states is also different. While some like Gujarat and Rajasthan are old hands at
the game, others like Orissa are in unchartered territory. The PPP framework and the
associated regulations also differ across states; this, along with the myriad agencies with
which companies will have to deal at the state level, is likely to ensure that there will be
misses along with hits on the way. However, it can be safely said that the state road PPP
scene is now ready for a quantum leap. Over the long term, it will ensure that there is noshortage of work for any participant in the infrastructure space.
8/7/2019 Construction-sector_update-Oct-09
27/118
26 Edelweiss Securities Limited
Construction
Time To Think About The Constraints
While no one doubts the huge opportunity in store, it is also prudent to keep the constraints
in mind. As far as the road development scene is concerned, the obvious constraints are:
1. Execution capability of contractors.
2. Amount of money the government (NHAI) can put in.
3. Debt funding from banks and other financial entities.
4. Capability of developers to provide the equity portion of funding.
We take a look at these factors involved:
1. Execution capability: A spending of INR 1 tn every year means that developers
alone will not be able to execute projects on their own; a significant chunk of the
work will have to be outsourced to third part contractors as well. But even then, a
look at the revenues earned by roads divisions of various contractors in FY09 reveals
that it appears unlikely that this much quantum of work can be handled.
Table 13: Order book/ execution ratio of various contractors
Company Order book/execution ratio (FY09 end)
IVRCL Infra 2.8
Nagarjuna Construction 2.6
Patel Engg 2.9
Simplex Infra 2.1
Gammon India 3.5
Hindustan Construction 4.9
Sadbhav Engg 4.6
Madhucon Projects 5.2
Gayatri Projects 5.7
Punj Lloyd 1.7
Source: Company, Edelweiss research
With the spurt in order awards in the past six months, most contractors currently
have a robust order book (>3x FY09 revenues). With the overall focus on
infrastructure development, there are going to be opportunities in other
infra segments as well. In this context, building 20 km of roads every day is
a tough task to achieve.
While the government has stated its intention to focus on capacity augmentation of
contractors, it is going to be a gradual progress rather than a fast one. The
government is also looking at getting the help of foreign players to achieve its
objective. While foreign players may be able to help in funding aspects and projectmanagement skills, it yet remains to be seen how many of them will be willing to get
their hands dirty doing the actual contracting work.
To conclude, even though projects awarded now will enter the execution stage after
only a year or so, we believe that execution is going to be an issue, atleast in
the medium term. The fact that many states are also becoming active as far as
road development is concerned is going to further test the execution abilities of
contractors.
Are there enough contractorsto build 7000 km of roadsevery year?
8/7/2019 Construction-sector_update-Oct-09
28/118
Edelweiss Securities Limited 27
Construction
2. Does the government have the money?: The proposed funding plan for NHDP
amounting to INR 1,735 bn in the Eleventh Five Year Plan is as follows:
Chart 7: Funding plan for NHDP in 11th plan
Cess21%
Externalassistance
2%
Borrowings byNHAI24%
Surplus fromuser fee
2%
Share of privatesector51%
Source: Working Group report on roads for the Eleventh Five Year Plan, Edelweiss research
As is evident, the private sector is expected to provide more than half of the funds
required. However, with the sluggish pace of project award in the first two years of
the plan, achieving this target is going to be an uphill task. Currently, it looks like
that the government may have to put more on the table than what was envisaged.
We take a look at various funding sources being utilised by NHAI over the
past few years:
Table 14: Funding sources utilised by NHAI (INR bn)
Borro- Budgetary Toll TotalYear Cess Grants Loans wings support collection
1999-00 10 5 0 7 0 0 22
2000-01 18 5 1 8 0 0 32
2001-02 21 9 1 56 0 0 87
2002-03 20 12 3 0 0 3 38
2003-04 20 12 3 0 0 4 38
2004-05 18 12 4 0 0 5 39
2005-06 33 24 5 13 7 8 90
2006-07 64 16 4 15 1 11 111
2007-08 65 18 4 20 3 14 125
2008-09 70 15 4 11 2 17 118
Total 340 127 29 129 12 61 699
External assistance
Source: Government documents, Edelweiss research
The amount collected from cess on diesel and petrol of INR 135 bn during the first
two years of the plan is more or less as per estimates. It goes into a non lapsable
fund to be used for highway development.
On the other hand, external assistance has reached INR 41 bn in the first two years
itself against projections of INR 45 bn over the plan period. This signifies the
emphasis being put by the government on road development.
Does the government haveenough money to back up itsambitious plans?
8/7/2019 Construction-sector_update-Oct-09
29/118
28 Edelweiss Securities Limited
Construction
As far as NHAI borrowings are concerned, there is still a lot of leeway left
with the agency: As against the planned figure of more than INR 400 bn of
borrowings, NHAI has borrowed only INR 31 bn in the past two years. There is
expected to be a sharp uptick in borrowings going ahead with the NHAI planning to
borrow INR 50 bn in FY10. News articles suggest, of this, INR 5 bn is proposed to be
raised from a multilateral agency and negotiations are going on with ADB for a USD
100 mn loan. The balance is proposed to be raised through tax-free bonds, which
are already available in the market. NHAI is also in talks with the World Bank to
restructure an earlier loan of USD 400 mn.
NHAI toll collection has also jumped to INR 17 bn this year. About 7,560 km of NHs
have been completed and are under tolling. However, 3,476 km of NHs are only
partially complete and hence are not under tolling. The toll collection could be
expected to jump further on completion of these projects.
Also, recent news reports suggest that the government is considering a move to
transfer a part of the INR 100 bn tax-free bonds raised by IIFCL to NHAI for
refinancing of road projects.
To summarise, the oft repeated statement from government that it will not allow
money to hinder road development is true to some extent. In the near term, it
seems that NHAI has adequate funds at its disposal to carry out its plans .
However, the picture over the medium term is muddled and will depend
upon several factors:
(i) How fast is the government able to remove bottlenecks and what will be the
success rate in awarding projects over the next two years.
(ii) How much will the government be able to support NHAI, constrained that it is
due to considerations about fiscal deficit.
(iii) How fast the economy recovers, for it will improve project viability by boosting
traffic and reduce dependence of developers on VGF (or conversely, how soon
will we see the return of developers willing to share revenues with Government).
3. Funding conundrum: Will the flood of liquidity translate into financial
closures: With no dearth of projects to choose from, liquidity situation improving,
and regulatory framework also turning favourable, the only stumbling block in
the way of a marked improvement in project awards, in our view, is funding .
Also, with increasing commoditization of the sector, the extent to which project
economics can be improved will increasingly depend upon innovative funding
structure along with design and execution capabilities.
In such a scenario, the extent of the companies participation in future BOT projects
(and the success of the overall PPP plan in roads) will depend upon the confidencewhich companies have in achieving FC on projects. Thus, cracking the funding
code is the key to unlocking the PPP opportunity, in our view.
There are two major questions which will determine the success of the Indian PPP
road projects in the medium term: (a) how much risk aversion from banks will the
BOT projects face, keeping in mind the worries on asset quality (toll revenues being
lower than estimates on some projects) and asset-liability mismatch (concession
period being increased for many projects); and (b) where will the required equity for
projects come from?
Can NHAI finances stand up tothe increased demand for
government funding?
Will funding emerge as thedeal-breaker?
8/7/2019 Construction-sector_update-Oct-09
30/118
Edelweiss Securities Limited 29
Construction
In order to get answers to these questions, we have interacted with banks,
financial institutions, private equity players as w ell as major developers in
the road BOT space. We present our analysis of the situation:
Banks turning sympathetic towards BOT projects .
Various steps taken by the government to improve the viability of BOT projects havefound favour with banks. While a return of the 80:20 D/E structure for road BOT
projects is still far, banks are comfortable funding a 70:30 project structure (which
may go up to 75:25 in case the project is very lucrative).
Also, most banks do not have preferences regarding whether the project is a
NHAI/state project or the mode of project (toll/annuity). The paramount factor
determining lending decisions is viability of the project. As far as sectoral lending
caps are concerned, these can be changed internally in case a host of viable projects
are available in any particular sector.
Interest rates, on the other hand, present an interesting conundrum. The latter part
of the last year saw interest rates shooting up, making many projects unviable.
While rates have dropped significantly since then (currently at 11-12% level forproject finance proposals), most banks are of the view that we are near the end of
the interest rate cut cycle.
In fact post the budget, there have been apprehensions that the sheer size of
government borrowing will crowd out private players, driving interest rates higher by
the start of next year. This may well coincide with the time when majority of the
road BOT projects awarded this year are expected to come up for FC. How long will
developers get to enjoy a favourable interest rate environment has emerged as an
important point to ponder over.
.but, can they support long term funding r equirement
The problem with BOT project funding is not limited to tying up initial funds. Theirlong tenure creates headache of asset-liability mismatch for banks. Recognising this,
the government has been trying to take the help of IIFCL for this purpose.
In Budget 2009-10, the government has proposed release of long-term funds by
IIFCL for projects; IIFCL will also refinance 60% of bank loans for PPP in
critical sectors over 15- 18 months. It will provide refinance at 7.85%,
which banks can on-lend at 10.35%.
The World Bank has recently sanctioned a USD 1.2 bn loan to IIFCL. This loan is
designed to support IIFCLs role to catalyse private financing for PPP projects in
infrastructure and to stimulate the development of a long-term local currency debt
financing market.
The government has also mooted the idea of take-out financing which basically
involves securitising of infrastructure advances by primary financiers, especially
banks, in favour of long-term financial institutions. IIFCL recently indicated that
it has deployable funds of around INR 100 bn, a part of which has been
raised for 10-25 years. Thus, it is in a position to offer take-out financing.
However, it yet remains to be seen whether take-out financing will work. It has
been tried in the past too when SBI had tied up with IDFC, while IDBI had tied up
with LIC for take-out financing. But these arrangements could not work.
Banks shedding theirapprehension towards roadprojects
But do the banks have enoughlong term resources
8/7/2019 Construction-sector_update-Oct-09
31/118
30 Edelweiss Securities Limited
Construction
Anyways, IIFCLs overall exposure to the roads sector is low compared to the
requirements. For the roads sector, the quantum of IIFCLs disbursal in FY09
stood at INR 12.9 bn, which even though w as more than double the INR 5.8
bn achieved in previous year, is still on the lower side . Also, while IIFCL had
raised INR 100 bn earlier this year to refinance highways and port projects, it has
not received a single proposal till date for funding. The pace of project awards in the
time to come will determine whether IIFCL can achieve its target of lending INR 1 tn
over the next five years.
and, how much can they support
Even assuming that banks aided by IIFCL are willing to fund projects, the sheer
quantum of funds required means that doubts will continue to linger.
Chart 8: Banking sector exposure to roads and ports sector
0.0
6.0
12.0
18.0
24.0
30.0
0
100
200
300
400
500
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
(%)
(INRbn)
Roads/ports sector exposure As % of overall infra portfolio
Source: RBI, Edelweiss research
As shown in chart 8, total banking sector exposure to the roads and port
sector was ~INR 470 bn at FY09 end. The share of the roads/ports sector in the
overall infra portfolio of banks has been hovering around 17% for the past four
years.
We attempt a small exercise to ascertain the quantum of roads which can be funded
in the current scheme of things. The banking sector exposure to infrastructure at the
end of FY09 was ~ INR 2,700 bn.
Assumptions:
1. Banks credit to infra sector grows by 32% in FY10.
2. Roads/ports sector share in overall infra portfolio of banks is 17% in FY09; itrises to 20% in FY10 with increased thrust on the sector.
.and more importantly, howmuch can banks support roadprojects?
8/7/2019 Construction-sector_update-Oct-09
32/118
Edelweiss Securities Limited 31
Construction
Table 15: Incremental fund availability to roads sector
Particulars Funding
Banking sector exposure to infra at FY09 end (INR bn) A 2,700
Credit growth assumption for infra sector in FY10 (%) B 32
Banking sector exposure to infra at FY10 end (INR bn) C = A*(1+B) 3,564
Share of roads/ports sector in infra portfolio at FY09 end (%) D 17
Share of roads/ports sector assumed in infra portfolio at FY10 end (%) E 20
Incremental credit available for roads/ports sector in FY10 (INR bn) F = C*E-A*D 254
Assumed share of roads in incremental credit (%) G 75
Incremental credit available for roads in FY10 (INR bn) H = G*F 190
Assumed debt funding for a typical road project (%) I 70
Amount of road projects that can be funded (INR bn) J = H/I 272
Source: RBI, Edelweiss research
Table 15 shows that if the current scenario continues, only ~ INR 272 bn of
road projects will be able to get funding. This needs to be juxtaposed with
the ambitious plans of the central and state governments as far as the road
development scene is concerned.
The projects awarded on an EPC business will not face much problems; similarly,
annuity based projects are also likely to face comparatively less problems due to
absence of revenue risks. However, toll projects will pose a dilemma for banks due
to associated toll risks. In any case, bank funding to the sector will have to take a
quantum leap. In case the projects come up in a bunch, there is high probability that
some of them will face funding delays.
4. Equity commitment still the biggest worry and may emerge as the party
pooper: The bigger worry for BOT projects, in our view, is the equity commitment
required. With project sizes increasing and banks asking promoters to put in ahigher share of equity, the equity required for projects has increased substantially
when compared to projects awarded two-three years ago.
Coupled with this, the downtrend in equity markets (during the past one year) and
drying up of private equity options had soured the pitch. PE funds were reluctant to
invest as securitising toll fees and selling down to global pension funds as an option
had disappeared for some time. Compounding the problem was the fact that
the core contracting business (which anyways is a negative operating cash
flow business) for most companies had taken a hit last year due to increase
in commodity prices, interest rates, and slowdown in order intake, thus limiting the
parents ability to pump in money.
Many companies which had won projects in the 2005-07 period had hoped to sellstake in projects once they were complete and utilize the fund infusion to bid for
future projects. Even as these projects became operational/achieved completion, the
equity markets plunge poured cold water on such hopes.
As per the Economic Survey 2008-09, infrastructure companies raised less money
through public and rights issues in 2008-09 compared to the previous year. Public
share sales and rights issues fell from INR 870 bn in 2007-08 to INR 147 bn
in 2008-09.
Equity commitment fromdevelopers side may createroadblocks
8/7/2019 Construction-sector_update-Oct-09
33/118
32 Edelweiss Securities Limited
Construction
A ray of hope is, however, the signs of recovery in equity markets. Many companies
have announced fund raising plans. A summary of the fund raising plans of major
infra companies is given below:
Table 16: Fund raising by companies
Company
Fund raising by
companies (INRbn) Status
HCC 4.8 QIP completed
GVK 7.2 QIP completed
Punj Lloyd 6.7 QIP completed
Lanco 7.3 QIP completed
Nagarjuna Construction 3.7 QIP completed
Era Infra 3.0 Warrants allotted
Reliance Infra 39.8 Warrants allotted
Gammon Infrastructure 10.0 Shareholders's approval received
Sadbhav Engg 1.3 Shareholders's approval received
Unity Infraprojects 2.5 Shareholders's approval received
Gammon India 9.6 Board approval received Source: Edelweiss research
However, the amount of equity required for road projects is large. Assuming an
equity contribution of 30% for road projects, ~ INR 200-300 bn of funds will be
required for the equity commitment in upcoming road projects. Amidst such a
scenario, it surely is advantageous for companies with low leverage levels which are
in a better position to fulfill their equity commitment.
Possible options to help solve the funding cononundrum
Some of the options that can be tapped to ease funding pangs are:
1. Long-term loans provided on reimbursable basis by the government.
2. Multilateral funding institutions like the Asian Development Bank (ADB),
International Finance Corporation (IFC), and DEG, can lend a helping hand.
3. Currently, IIFCL can refinance only commercial banks. The facility can be extended
to NBFCs and other institutions lending to the infrastructure sector. Also, IIFCL can
finance only 20% of the project cost and 60% of debt has to be repaid in the first 10
years of the project. A removal of these restrictions will ensure that more projects
will achieve FC.
4. Currently, ECBs can be used only for refinancing old ECBs at better terms or for
undertaking capex. Allowing developers to access ECBs for repaying old rupee term
loans on operational projects will help repay high-cost funds a