Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
1
Construction Cost Avoidance
2
Matthew J. Incinelli, PartnerCRI Orlando
Rob Broline, ManagerCRI Melbourne321-426-3026
3
Hard Bid
Characteristics: • Fixed price• Competitively bid• Basically requires complete plans• Low bidder generally chosen
Advantages: • Potential lower price• Comfort of competitive bid• Limited negotiations
Disadvantages: • Usually susceptible to many change orders• Motivation of contractor to cut costs (quality)• Must take qualified low bidder
(qualifications more general)• Generally not auditable• Increases chance of litigation
4
CM at Risk
Characteristics: • CM chosen based on qualifications proposal• Partnering environment• GMP/Fee negotiated• Audit at conclusion
Advantages: • Owner uses firm of their choice• Partnering arrangement• Costs audited at end• Plans don’t have to be complete to start• Quality less of a concern
Disadvantages: • Potential for higher price (not competitively bid)• Requires effective negotiations and historical data
5
Design Build
Characteristics: • CM/Architect team• Chosen based on qualifications proposal• Partnering environment• GMP/Fee negotiated• Audit at conclusion
Advantages: • Owner uses firm of their choice• Partnering arrangement• Plans can be less complete to start• Costs audited at end• Quicker from design to completion (fast track)
Disadvantages: • Less accountability from architect• Potential for higher price (not competitively bid)• Requires effective negotiations and historical data
6
Cost + Fee Contracts with a Guaranteed Maximum Price
What does the guaranteed maximum price represent?
Components of the guaranteed maximum price• Cost of the work:
• General conditions• General requirements• Subcontract/Owner direct purchases
7
Cost + Fee Contracts with a Guaranteed Maximum Price
Components of the guaranteed maximum price (cont.)
Insurances:•Payment and performance bond•General liability insurance•Subguard
Fee
Contingency:•Contractor•Owner contingency
8
5 Project Services
• Contract review
• Guaranteed Maximum Price review
• Periodic pay application review
• Interim date procedures
• Close out procedures
9
• Preventative
• Clarifies contract terms
• Industry best practices
• Residual value
• Accomplished prior to the contract being signed
• Should commence as soon as contract is drafted
Contract Review
10
• Identify and test problem areas on the front end
• Review of key rates (insurances, subguard, labor burden, etc.)
• Verification of key labor rates
• Similar benefits to contract review
• Commences at the time Guaranteed Maximum Price is submitted to the Owner by the Contractor
GMP Review
11
• Examine billing of key items
• Can be tailored to review high risk items the Owner identifies
• Ensures that the Construction Manager is properly documenting cost items
• Tests for advance billing
• Verify policies and procedures are in place and being followed
• Commenced upon receipt of monthly pay application from Contractor
Periodic Pay Application Review
12
• Identify cost savings early
• Early resolution of disputed items
• Speeds up the Project close out
• Examples of procedures
– Sample subcontractor files
– Sample labor and labor burden costs
– Examine billing of insurances, subguard
• Commences when certain milestones are achieved, usually when most of the major subcontractors have started their billing process
Interim Date Procedures
13
• Establishes the final project costs
• Verifies financial compliance to contractual terms
• Incorporates all previous findings and verifies compliance
• Provides assurance and third party independence to total project costs
Close Out Procedures
14
Commenced upon:• Substantial completion achieved• Final change order and pay application is
received (may be a draft)• When Owner still owes money
to the Contractor to ensure prompt cooperation
Close Out Procedures
15
I know my fiscal risk is mitigated because…1. I have a good attorney2. I have a guaranteed maximum price3. The Architect certifies payment4. I have a financial statement audit5. I have a robust payables process
Top 5 reasons used for not utilizing a construction auditor
16
Advantages to Independent Review
• Assurance
• Return
• Accountability
• Efficiency
• Affordability
17
• Lump sum– Must negotiate and verify!
– Discount to change to lump sum
• Cost of the work– Not preferred, why?
• Not-to-exceed– Preferred method; it has a ceiling and
savings come back to the Owner.
How do you contract for general conditions costs?
18
• Labor costs– Verify at time of submission– Discussions regarding escalation through project period
• Vehicles– Monthly rates– Number of vehicles– Time period of project
• General requirements– Trailer, office supplies, cell phones, etc.– Temporary facilities and utilities, clean up– Computer costs and software
• Labor burden
Important! Detailed listing of what is contained in the general conditions
19
• Advantages/disadvantages of:– Fixed rate
• Negotiate and verify!
– Not-to-exceed• Sets a ceiling
– Cost of work• Risk remains for high percentages (retirement, health, paid time off, etc.)• Only if the contract strictly defines components
• Proper components– What should be included in labor burden?
Labor Burden
20
• Protection– Who is protected?
• Rate– What is an average subcontractor
bond rate?
• Floor• Retentions/Losses
– Difficult to audit; better to set a reasonable rate in the contract.
Subguard / Subcontractor Bonds
21
• Rates– CM allocates the corporate
policy across all projects
• Limits– Contract sets limits; CM often
exceeds the coverages
• Self-insured vs. third party insurance– Difficult allocation: estimated losses, deductibles,
policy for large losses
Insurances
22
• Limits
• Tiered
Subcontractor Change Order Clauses
23
• Limits– Establish a percentage - original
CM fee % or flat rate for change orders
• Addition/Deductive change orders
Construction Manager Change Order Markup
24
• Approval/bidding– Owner should pre-approve prior to bids being
issued.– Risk is in getting responses from 3rd party bidders
• Cost plus– Self-performed can be done as
a mini guaranteed maximum price,with a pre-determined fee for overhead and profit
Self-Performed Work
25
• Limits– Determine acceptable limits
• Software• Overhead vs. Project costs
– Purchased vs. rental equipment
Construction Manager’s Internal Charges(vehicles, equipment, computers, etc.)
26
Questions?