23
Construction Cost Escalation…. 2006 AASHTO Subcommittee on Construction San Juan, Puerto Rico Kevin J. Dayton, P.E. State Construction Engineer Washington State DOT The Washington State Story

Construction Cost Escalation….sp.construction.transportation.org/Documents/...•1997 Associated Sand & Gravel acquired by ARC Material Corp (currently known as Rinker Materials)

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Construction Cost Escalation….sp.construction.transportation.org/Documents/...•1997 Associated Sand & Gravel acquired by ARC Material Corp (currently known as Rinker Materials)

Construction Cost Escalation….

2006 AASHTO Subcommittee on Construction San Juan, Puerto Rico

Kevin J. Dayton, P.E.State Construction Engineer

Washington State DOT

The Washington State Story

Page 2: Construction Cost Escalation….sp.construction.transportation.org/Documents/...•1997 Associated Sand & Gravel acquired by ARC Material Corp (currently known as Rinker Materials)

Price Escalation Versus Inflation

Page 3: Construction Cost Escalation….sp.construction.transportation.org/Documents/...•1997 Associated Sand & Gravel acquired by ARC Material Corp (currently known as Rinker Materials)

Cost Escalation – The Background

• Trends developed in 2002 and 2003

– Mostly steel price and availability

– Some concern over cement

• 2004 and 2005 showed marked increases in fuel

– Major driver for all of our items of work

– Hot Mix Asphalt (HMA) is estimated to be 36% dependent on petroleum products

– Cement continues to loom

• Late August 2005, Hurricane Katrina compounds the problem

– Reduction in Refinery Capacity

– Increase in work and demand for material, equipment and labor

• 2005 and 2006 continues to “fuel” the market

– Crude price run up, due in part to continued “geo-political” unrest

•• $50$50 $60 $70 barrel crude

• $2.00 $3.00 gallon diesel

– Unprecedented construction program – both private and public

Page 4: Construction Cost Escalation….sp.construction.transportation.org/Documents/...•1997 Associated Sand & Gravel acquired by ARC Material Corp (currently known as Rinker Materials)

Timing Is Everything…Why did WSDOT become so interested in cost escalation?

0

500

1,000

1,500

2,000

2,500

3,000

3,500

1999-01 2001-03 2003-05 2005-07 2007-09 2009-11 2011-13 2013-15

Mega Projects

TPA

Nickel

PEF

$1,205.3$1,273.6

$1,424.6

$2,693.1

$3,183.6$3,248.8

$2,596.2

$1,715.6

* This figure includes all Pre-Existing Funds

(state and federal), Nickel and TPA funds.

Includes Preservation and Improvement

Programs with two exceptions: expenditures

for the Tacoma Narrows Bridge and

expenditures in the Improvement Program

reimbursed by Sound Transit

Highway Construction Program*Dollars in Millions, 2006 Supplemental Budget

Page 5: Construction Cost Escalation….sp.construction.transportation.org/Documents/...•1997 Associated Sand & Gravel acquired by ARC Material Corp (currently known as Rinker Materials)

Development of Project Estimates

*CEVP has been widely recognized across the country as a major step forward in project cost estimating for large infrastructure projects.

More Variance(Project Development Risks)

Less Variance (Construction Risks)

Budget is refined as project development process unfolds

Costs change as market forces change

Costs change as project is defined

Project cost becomes “known”

$

Bid

amount

$

Final Cost

$

Early ProjectDefinition

Project Engineering, Permitting and Right-of-Way Ad Date Construction Award Date Operationally Complete

$

Legislative expectations set

Page 6: Construction Cost Escalation….sp.construction.transportation.org/Documents/...•1997 Associated Sand & Gravel acquired by ARC Material Corp (currently known as Rinker Materials)

Contracts Awarded

Page 7: Construction Cost Escalation….sp.construction.transportation.org/Documents/...•1997 Associated Sand & Gravel acquired by ARC Material Corp (currently known as Rinker Materials)

Costs of Construction Materials

The Construction Cost Index (CCI) helps WSDOT track market costs of a “basket” of common highway construction items that are strongly influenced by materials costs.

The following components

(weighted as shown) are

used to compute the CCI:• Concrete Pavement 3.2%• Crushed Surfacing 7.9%• Roadway Excavation 10.7%• Structural Concrete 17.4%• Steel Reinforcing Bar 5.4%• Structural Steel 6.9%

• Hot Mix Asphalt 48.5%

Data Source: Unit price

history from low bids on the above construction materials collected from WSDOT bid openings.

The eleven-year average growth rate of the CCI from 1990 through 2001 was 1.5% per year. Since 2001, the average growth rate has been 12% per year.

Construction Costs Indices Washington State

100

125

150

175

200

225

250

275

1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006

YTD

WSDOT CCI

These two data points have

been normalized in WSDOT

CCI to remove effect of spiking

structural steel prices in 2003

and 2004

Note: WSDOT 2006 Index is for Quarters 1 & 2

WSDOT Base 1990 = 110

WSDOT CCI

(Smoothed)

Page 8: Construction Cost Escalation….sp.construction.transportation.org/Documents/...•1997 Associated Sand & Gravel acquired by ARC Material Corp (currently known as Rinker Materials)

Construction Costs Indices Washington State

and Others

100

125

150

175

200

225

250

275

1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006

YTD

WSDOT CCI

FHWA

These two data points have

been normalized in WSDOT

CCI to remove effect of spiking

structural steel prices in 2003

and 2004

Note: WSDOT 2006 Index is for Quarters 1 & 2

FHWA 2006 Data not available

Sources: WSDOT Construction Office, FHWA

WSDOT Base 1990 = 110

FHWA Base 1987 = 100

WSDOT CCI

(Smoothed)

Costs of Construction Materials

The eleven-year average growth rate of the CCI from 1990 through 2001 was 1.5% per year. Since 2001, the average growth rate has been 12% per year.

The Construction Cost Index (CCI) helps WSDOT track market costs of a “basket” of common highway construction items that are strongly influenced by materials costs.

The following components

(weighted as shown) are

used to compute the CCI:• Concrete Pavement 3.2%• Crushed Surfacing 7.9%• Roadway Excavation 10.7%• Structural Concrete 17.4%• Steel Reinforcing Bar 5.4%• Structural Steel 6.9%

• Hot Mix Asphalt 48.5%

Data Source: Unit price

history from low bids on the above construction materials collected from WSDOT bid openings.

Page 9: Construction Cost Escalation….sp.construction.transportation.org/Documents/...•1997 Associated Sand & Gravel acquired by ARC Material Corp (currently known as Rinker Materials)

Construction Costs Indices Washington State

and Others

100

125

150

175

200

225

250

275

1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006

YTD

Other States Combined

WSDOT CCI

FHWA

These two data points have

been normalized in WSDOT

CCI to remove effect of spiking

structural steel prices in 2003

and 2004

Note: WSDOT 2006 Index is for Quarters 1 & 2

Other States 2006 Index based on California, Colorado and Oregon First Quarter Data

FHWA, South Dakota and Utah 2006 Data not available

Sources: WSDOT Construction Office, FHWA

WSDOT Base 1990 = 110

FHWA and Other States Base 1987 = 100

Other States: California, Colorado, Oregon,

South Dakota & Utah

WSDOT CCI

(Smoothed)

Costs of Construction Materials

The eleven-year average growth rate of the CCI from 1990 through 2001 was 1.5% per year. Since 2001, the average growth rate has been 12% per year.

The Construction Cost Index (CCI) helps WSDOT track market costs of a “basket” of common highway construction items that are strongly influenced by materials costs.

The following components

(weighted as shown) are

used to compute the CCI:• Concrete Pavement 3.2%• Crushed Surfacing 7.9%• Roadway Excavation 10.7%• Structural Concrete 17.4%• Steel Reinforcing Bar 5.4%• Structural Steel 6.9%

• Hot Mix Asphalt 48.5%

Data Source: Unit price

history from low bids on the above construction materials collected from WSDOT bid openings.

Page 10: Construction Cost Escalation….sp.construction.transportation.org/Documents/...•1997 Associated Sand & Gravel acquired by ARC Material Corp (currently known as Rinker Materials)

Prospects for Labor Costs

•Labor costs contribute roughly 40% to contract costs

•Potential labor shortages

•Contractors can face a “premium charge” just to attract a qualified workforce in a booming construction market

•Contract negotiations could see upward pressure on wages, healthcare and retirement

Page 11: Construction Cost Escalation….sp.construction.transportation.org/Documents/...•1997 Associated Sand & Gravel acquired by ARC Material Corp (currently known as Rinker Materials)

Consolidation of Bidders

Significant Acquisition and Consolidation Trends Affecting Pacific Northwest Market

•1980’s Fiorito Brothers no longer bids highway work

•1990’s Ledcor Industries no longer bids highway work

•1994 Wilder Construction Co. acquires Construction & Rigging

•1995 Progressive Contractors Inc. close in Washington

•1997 Associated Sand & Gravel acquired by ARC Material Corp (currently known as Rinker Materials)

•1998 Oldcastle Inc acquires M. A. Segale (currently known as ICON Materials)

•1998 Atkinson Construction becomes a wholly owned subsidiary of Clark Construction Group, LLC.

•1999 Oldcastle Inc acquires Inland Asphalt

•2000 Granite Construction acquires Wilder Construction Co.

•2001 Superior Asphalt acquires Morrill Asphalt

•2001 General Construction Company becomes an affiliate of Kiewit Construction

•2002 American Civil Constructors acquires Hurlen Construction

•2004 Wilder Construction Co. absorbs key One Way Construction personnel

Page 12: Construction Cost Escalation….sp.construction.transportation.org/Documents/...•1997 Associated Sand & Gravel acquired by ARC Material Corp (currently known as Rinker Materials)

Contractor Participation

Number of Construction Firms Prequalified for Bidding On, and

Winning WSDOT Construction Contracts

050

100150200250300350400450

429 360

2000 2001 2002 2003 2004 2005

Number of Bidders

2000 2001 2002 2003 2004 2005

Number Meeting Prequalification (no data

available before 2004)

Number Submitting One or More Bids to be

Prime Contractor

Number Winning an Award as Price Contractor

Number of Construction Firms Prequalified for Bidding On, and Winning WSDOT Construction Contracts

Number of Bidders

Page 13: Construction Cost Escalation….sp.construction.transportation.org/Documents/...•1997 Associated Sand & Gravel acquired by ARC Material Corp (currently known as Rinker Materials)

Specialty AreasSubcontracting and supply

Hot mix asphalt. Adequate competition in most of Western Washington but only one firm now supplying the majority of the Olympic Peninsula. Much of Eastern Washington sees little or no competition.

Roadway striping. Only three active private firms in Washington.

Shaft Drilling. Six firms now seeking work on WSDOT jobs, but only two have oscillator/rotator capability. WSDOT is encouraging a Utah firm to become active in WA.

Concrete pre-stressed structural elements. Suppliers in Tacoma, Spokane, Yakima and Pasco. Oregon and Canadian suppliers can compete, depending on haul costs.

Concrete post-tensioned structural elements. Currently only two firms doing this work. A third is trying to make entry.

Steel fabrication. Now limited to firms in Vancouver and Portland.

Deck Overlays – microsilica, latex, polyester. There are primarily two firms doing this type of work.

Page 14: Construction Cost Escalation….sp.construction.transportation.org/Documents/...•1997 Associated Sand & Gravel acquired by ARC Material Corp (currently known as Rinker Materials)

Average Number of Bidders

The average number of contractors bidding on WSDOT projects has decreased 11% in the first two quarters of 2006, from an average of 3.5 bidders in 2005 to an average of 3.1 bidders in the first two quarters of 2006.

Page 15: Construction Cost Escalation….sp.construction.transportation.org/Documents/...•1997 Associated Sand & Gravel acquired by ARC Material Corp (currently known as Rinker Materials)

Oil Prices Driving Costs Upward

Hot Mix Asphalt, Crude Oil & Diesel Fuel Indices

0

50

100

150

200

250

300

350

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2

2002 2003 2004 2005 2006

Crude OilUS Dept. of Energy,

Energy Information

Administration,

West Texas Intermediate

Hot Mix Asphalt

WSDOT

Diesel FuelUS Dept. of Energy,

Energy Information Administration

West Coast No. 2

BASE 2002 Q1 = 100

Page 16: Construction Cost Escalation….sp.construction.transportation.org/Documents/...•1997 Associated Sand & Gravel acquired by ARC Material Corp (currently known as Rinker Materials)

Communication

�Communication with Industry

�AGC, ADSC, WAPA

�Media opportunities

�Communication with Elected Officials

�Committee weekends

�Budget Hearings

�Communication with the Governor’s Office

�Through the Government Management and Accountability Program (GMAP)

�Governor’s Council of Economic Advisors

�Letter to House and Senate Leadership

Things that control us Things that we can (partially) control

Page 17: Construction Cost Escalation….sp.construction.transportation.org/Documents/...•1997 Associated Sand & Gravel acquired by ARC Material Corp (currently known as Rinker Materials)

Rising Construction Costs – Record National Media Coverage of Rising Highway Construction Costs and Impacts

“East Valley highwayexpansion threatened”

“Soaring materials costs hit projects”

“Construction costs slow transportation growth”

“VDOT: Rise in raw material prices to cost agency additional $180 million”

“Down the Road for I-5 Freeway”

“Construction costs on the rise”

“Road costs floor it in the fast lane”

“Price of asphalt proves crushing”

“Asphalt cost slows road work”

“Officials: Expect fewer projects”

“Construction costs rise with oil prices”

“Sticker shock hits construction projects”

“DOT postpones 24 projects”

“Paving plans hit pothole in rising price of asphalt”

“Road costs increase as petro soars”

“The road not taken”“Oil drives up asphalt tab”

“Construction costs restrict state road”

“WYDOT pleads for more dollars”

Page 18: Construction Cost Escalation….sp.construction.transportation.org/Documents/...•1997 Associated Sand & Gravel acquired by ARC Material Corp (currently known as Rinker Materials)

Things That Control Us

•Overall volume of public and private sector work seeking contractors.

•Contractors’ access to key subcontractors and sources of construction material.

•Bonding and other capacity constraints affecting contractors’ appetite for work.

•Market trends in the construction industry towards consolidation and shrinkage of number of local firms.

•Contractors’ appetite for “risk” is inversely proportional to the volume of work available

Page 19: Construction Cost Escalation….sp.construction.transportation.org/Documents/...•1997 Associated Sand & Gravel acquired by ARC Material Corp (currently known as Rinker Materials)

Things That Control Us

•Typical estimating is based on trailing indicators (past bid history)

•Past results are not a guarantee of future performance

•There is no crystal ball

Page 20: Construction Cost Escalation….sp.construction.transportation.org/Documents/...•1997 Associated Sand & Gravel acquired by ARC Material Corp (currently known as Rinker Materials)

We Can Update Our Trailing IndicatorsWSDOT sends quarterly updates to its designers (shown below)

Hot Mix Asphalt: $57.89 per tonThe unit bid price increased by $2.93 from the average unit price of $54.96 per ton in the first quarter of 2006. The prices ranged from $43.41 to $750.00 per ton. The average unit bid price for Eastern Washington was $49. 32 and for Western Washington was $62.86.

Steel Reinforcing Bar: The unit bid price increased by $0.33 from the average unit price of $.90 per pound in the first quarter of 2006. The prices ranged from $0.85 to $2.15 per pound.

Structural Concrete: $480.56 per cubic yardThe unit bid price decreased by $99.35 from the average unit price of $579.91 per cubic yard in the first quarter of 2006. The prices ranged from $385.00 to $1,100.00 per cubic yard.

Steel Reinforcing Bar Unit Bid Price

$0.00

$0.25

$0.50

$0.75

$1.00

$1.25

1990 1992 1994 1996 1998 2000 2002 2004 2006

YTD

$ / LB

Hot Mix Asphalt Unit Bid Price

$20

$25

$30

$35

$40

$45

$50

$55

$60

1990 1992 1994 1996 1998 2000 2002 2004 2006

YTD

$ / TONStructural Concrete Unit Bid Price

$200

$250

$300

$350

$400

$450

$500

$550

$600

1990 1992 1994 1996 1998 2000 2002 2004 2006

YTD

$ / CY

Page 21: Construction Cost Escalation….sp.construction.transportation.org/Documents/...•1997 Associated Sand & Gravel acquired by ARC Material Corp (currently known as Rinker Materials)

Things that We Can (Partially) Control

Reduced cost through increased competitionCommunication

• Time bid advertisements to promote competitive appetite

• Communication of current and future contract opportunities; special outreach on unusual or difficult projects

• Call bidders

Contract structure

• Bundle/break up projects to attract bidders

• Give flexibility to contractors to encourage them to shop for the most economical materials values (“performance or end product specifications”)

• Flexible start date

Owner of choice

• Provide early payment provisions (“materials on hand”)

• Cost Reduction Incentive Proposals (CRIPs)

• Fair and efficient practices in contract administration

• Fair and efficient risk allocation in the contracting relationship

• Consistency in Specifications and a fair process for responding to questions and requests for clarification

Reduced cost through reduced scope

• Bid “additive alternates”

• Adjust a project scope to “buy-less”

• Cancel a project that inflation in materials costs has made too expensive.

The “Toolbox”

.

Page 22: Construction Cost Escalation….sp.construction.transportation.org/Documents/...•1997 Associated Sand & Gravel acquired by ARC Material Corp (currently known as Rinker Materials)

Questions??

http://www.wsdot.wa.gov/biz/construction

Page 23: Construction Cost Escalation….sp.construction.transportation.org/Documents/...•1997 Associated Sand & Gravel acquired by ARC Material Corp (currently known as Rinker Materials)

0

0.05

0.1

0.15

0.2

0.25

15

00

19

00

23

00

27

00

31

00

35

00

39

00

43

00

47

00

51

00

55

00

59

00

Total Project Cost (YOE $M)

Pro

ba

bilit

y

2006 CEVP 2005 CEVP As we begin to re-run CEVPs for a few large projects, we expect that our cost estimate ranges will extend to the right to reflect cost growth and uncertainty about that growth.*

* Other factors, such as a change in scope, may also contribute to a change in cost estimate ranges.

Cost Estimate Validation Process

50%

90%50%

90%