13
Firstname Surname, Affiliation/Company COMPRESSOR REBUNDLE TO INCREASE LNG PRODUCTION Antonio Pelagotti Baker Hughes, a GE company The economic crisis has impacted the development of new LNG plants in the recent years. A good opportunity to increase actual LNG production is to rebundle existing compressors. Some successful study has already been applied on some LNG plant in Middle East, Australia, West Africa where the machinery has been upgraded with limited impact on the plant layout. The rebundle projects starts with actual data analysis followed by an engineering study on various opportunities that ends with the recommendation on best solution. The compressor re bundle and upgrades can involve impeller selection for higher efficiency or operating range or include also casing for a large flow increase or higher pressure desired. The paper will discuss various opportunities including case studies of compressor rebundle.

COMPRESSOR REBUNDLE TO INCREASE LNG PRODUCTION …

  • Upload
    others

  • View
    12

  • Download
    0

Embed Size (px)

Citation preview

Page 1: COMPRESSOR REBUNDLE TO INCREASE LNG PRODUCTION …

Firstname Surname, Affiliation/Company

COMPRESSOR REBUNDLE TO INCREASE

LNG PRODUCTION

Antonio Pelagotti

Baker Hughes, a GE company

The economic crisis has impacted the development of new LNG plants in the recent years.

A good opportunity to increase actual LNG production is to rebundle existing compressors.

Some successful study has already been applied on some LNG plant in Middle East,

Australia, West Africa where the machinery has been upgraded with limited impact on the

plant layout.

The rebundle projects starts with actual data analysis followed by an engineering study on

various opportunities that ends with the recommendation on best solution.

The compressor re bundle and upgrades can involve impeller selection for higher efficiency

or operating range or include also casing for a large flow increase or higher pressure

desired.

The paper will discuss various opportunities including case studies of compressor rebundle.

Page 2: COMPRESSOR REBUNDLE TO INCREASE LNG PRODUCTION …

1 INTRODUCTION

Compressor rebundle can be required by Original Equipment Manufacturer (OEM) or by End User after looking to

the difference between actual compressor operation and the expected one. Plants are designed considering

multiple margin on process or equipment and this can sometime lead to an off-design operation.

OEM can leverage Remote Fleet Data, Customer data, assess the off-design operating condition and start a

conceptual study of possible upgrades

Figure 1 - Actual conditions may cause low efficiency or operability… Compressor re-bundle helps

optimize plant operation….

© 2019 Baker Hughes, a GE company, LLC - All rights reserved. Typical Compressor off-design operations are

• New process requirements… different Pressure, Gas composition, Flow, Temperatures.

• More power available from the driver

• Modifications to other equipment

• Design margins

Compressor upgrade is typically done by changing the internal (impeller and diaphragm) increasing the

performances and usually the efficiency, flow and/or head.

New aerodynamics state-of-art can increase efficiency up to 10% reducing power absorption and save energy. This

additional power can be used to increase head and flow maximizing the production keeping the same driver.

New internals can be designed to allow up to 50% more flow depending from compressor size.

Page 3: COMPRESSOR REBUNDLE TO INCREASE LNG PRODUCTION …

Compressor upgrades typically involve just the internal, in order to re-use the casing,without changing the external

process piping loop or foundation, but sometimes the upgrade can also replace the complete unit or sometimes the

complete train. The choice is made by looking at real operating conditions respect to the original curve. If the new

point falls well beyond the actual performance curves the modification suggested is the compressor replacement.

Re-Bundle/Re-wheeling Compressor Replacement Train Replacement

(matching plant layout) (same footprint) (same casing)

Figure 2 – Upgrade configuration

© 2019 Baker Hughes, a GE company, LLC - All rights reserved.

An example of debottleneck analysis is the compressor operated close to choke condition.

Figure 3 – Compressor operating condition and upgrade possibility

© 2019 Baker Hughes, a GE company, LLC - All rights reserved.

Altough the operating envelope is very large the compressor is operated at his maximum flow. What is typical in

this region typically is a drop in efficiency as it is close to the end of curve.

Page 4: COMPRESSOR REBUNDLE TO INCREASE LNG PRODUCTION …

The operating range can be recalibrated with a new stages selection recentering the average operating point at

efficiency peak.

With the new operating envelope the compressor will use more mass flow and will absorbe more power from the

gas turbine that should also be upgraded.

Compressor rebundle may involve:

- New state of art impeller design…increase efficiency, enlarge operating range, reduce external diameter

- Diffusers … vaned or high diffuser ratio vaneless … increase efficiency

- Volute …. From constant to variable , including guided vanes… increase performances

- Side Streams … From constant to variable … increase performances

- Seals…clearance reduction…increase efficiency

- Gas Turbine Upgrade….more power

In case of compressor or train replacement a new casing can be provided to reduce external diameter, reduce

bearing span and/or increase design pressure.

2 Case Studies

2.1 AUSTRALIA LNG

The Australia LNG project was expected to become one of the fastest developed LNG projects.

In order to achieve such target the design is based on the previous train 4 and 5. The degree of “carbon-copy” was

maximized to capture scheduled and cost advantages.

The liquefaction unit uses the Propane pre-cooled/mixed refrigerant (C3/MR) technology with the following train

arrangement

GE Frame 7 + LPMR + MP/HPMR + Helper Motor

GE Frame 7+ PR + Helper Motor

Preferences was given to modification that improved performance but needed minimum or no changes to layout or

existing equipment dimensions

The train layout was unchanged and the LPMR compressor was replaced with a larger capacity one and the PR

compressor was designed brand new minimizing nozzle changes to keep piping layout.

The PR impellers were designed to minimize risk of lack of performances during the final test but chosen among

the latest developed impeller family to achieve state-of-art performances.

First impeller was characterized by high impeller inlet relative mach number and a dedicated model test was

foreseen to avoid any further surprise during full scale test.

Second, third and fourth impeller were chosen from another LNG project and scaled to fit new casing. The fifth is

the lower critical.

The risk of lack of performance during the string test was minimized by taking the approach of scaling from

previously proven impellers and verifying the new one with model test. Four out of five impeller were already

proven one year before acceptance test.

Final PR compressor features are:

- Long bearing span 5100mm

- Bearing Span / Shaft Diameter > 10.4

- High Logarithmic Decrement > 0.3

Page 5: COMPRESSOR REBUNDLE TO INCREASE LNG PRODUCTION …

- Highest High Mach Impeller w/ Inlet Mach No close to 1

- High Flow coefficient wheel larger than 0.14

- New casing design to allow High Max Allowable Desing Pressure (MAWP) greater than 30barG

- Large nozzles 52”,40”,36”,32”,32”

- High Flanges Gas Velocities> 35 m/s (> 40 m/s for alternate case)

- Largest Side Stream Ratio

Figure 4 – C3 compressor for Australia project

© 2019 Baker Hughes, a GE company, LLC - All rights reserved.

The trains are equipped with a low pressure axial MR compressor of AN200 type.

For the high flow rates requested for the Australia design, the an200 machine would require to operate at the limit

of its capability. It was decided to select for the Australia train the AN 250 type axial compressor which has a wider

operating range. AN additional advantage is that at the operating points the AN250 efficiency is 56% higher than

an200.

Figure 5 – Compressor operating condition and possible rebundle

© 2019 Baker Hughes, a GE company, LLC - All rights reserved.

Page 6: COMPRESSOR REBUNDLE TO INCREASE LNG PRODUCTION …

This gain in available power margin and the additional margin in the safe operating envelope have increased the

flexibility in the MR train operation.

The MPHP MR unit was unchanged.

All the three compressors were installed without impacting piping loop or plant foundation.

Australia LNG is in successful operation since many years.

2.2 Southeast Asia LNG

A plant in Southeast Asia is configured with as MS6001B that drives a Propane compressor with a steam turbine as

helper and a Mixed Refrigerant train with an MS7001EA as driver.

Customer asked for higher mass flow through the Propane compressor to increase LNG production without

changing the compressor casing

The Flow increase was about 20% in mass that led to a fast velocity at the flanges higher than 40 m/s and a

Impeller peripheral Mach greater than 1.25

Figure 6 – C3 train configuration

© 2019 Baker Hughes, a GE company, LLC - All rights reserved.

Because of higher mass flow, the Gas turbine should deliver 4% more power and the steam turbine upgraded of

about 50% in power. The end user decided to rebundle to compressor to meet new operating condition

The main features of the installed compressor were:

• Old plenum aerodynamics…loss coefficient =2

• Old High Mach impellers geometry … reduced efficiency less than 0.8

• Tangential side streams

• Low diffusion ratios 1.4

• Constant section discharge volute loss coefficient =1.5

The new design has upgraded all the feature above (newly developed impeller, variable section volute, higher

diffuser ratio, radial side streams) increasing efficiency of about 4% with a final LNG production increased about

7%. The compressor was upgraded without new product but just using existing technology developed for more

recent project.

Page 7: COMPRESSOR REBUNDLE TO INCREASE LNG PRODUCTION …

Figure 7 - OLD vs NEW PR COMPRESSOR © 2019 Baker Hughes, a GE company, LLC - All rights reserved.

2.3 C3MR LNG project upgrade

One of the most common process used for LNG production is the C3 MR. there are at least seven trains with such

configuration.

The evolution of the train started from Australia with MS5002 as driver, then the MS7001 EA and the MS6001B

were introduced. This LNG liquefaction configuration is done by two trains: one with LPMR and MP/HP MR and the

other with C3 in single casing

Figure 8 – C3 operating condition and possible rebundle

© 2019 Baker Hughes, a GE company, LLC - All rights reserved.

Page 8: COMPRESSOR REBUNDLE TO INCREASE LNG PRODUCTION …

2.3.1 Propane Compressor

Looking to actual process data since 2007 it was noted that the compressor installed was mostly operated between

design and max flow, in a region were efficiency was not optimized. The average calculated efficiency was 75%.

The C3 compressor can be upgraded with state-of-art components increasing overall efficiency such as new

impeller. New diaphragm, suction and discharge volute.

Figure 9 – Flow coefficient variation and new rotor picture

© 2019 Baker Hughes, a GE company, LLC - All rights reserved.

Figure 10 - OLD vs NEW PR COMPRESSOR

© 2019 Baker Hughes, a GE company, LLC - All rights reserved.

The C3 could be upgraded by changing the internals and introducing more “modern” impeller (mixed flow) .

OEM had developed an high flow coefficient impeller family to increase efficiency and operating range at high flow

high Mach number. In Figure 9 it’s shown the effect of the introduction of this family on flow coefficient:

- Lower impeller diameter

Page 9: COMPRESSOR REBUNDLE TO INCREASE LNG PRODUCTION …

- Higher flow coefficient

- Higher diffuer ratio

Revamping the existing compressor using the referenced bundle design, allows an expected power saving of

6.4MW (about 9.3%) vs original design.

2.3.2 MP/HP Mixed refrigerant

Some trains in different countries are equipped with a compressor that takes care of MP/HP MR duties in a back to

back configuration. Typically, this compressor is on the same shaft line of the LPMR.

Historical data have been analyzed finding room for bundle optimization; the compressor is operated at high flow

for most part of the hours in a portion were efficiency is lower than operating at middle of the curve.

OEM has therefore re-design the bundle trying to keep same casing, introducing state-of-art impeller and

increasing efficiency by a new operating range more centered

Figure 11 – Compressor operating point and rebundle

© 2019 Baker Hughes, a GE company, LLC - All rights reserved.

The modification is impacting only the colored parts in figure 11 leaving unchanged head flanges (and also bearing

and dry gas seal) and casing (and flange’s position without need of piping realignment).

The new bundle is guaranteeing same flow with a better efficiency with an average power saving of about 4% for

one year.

2.3.3 Axial Compressor for Low Pressure Mixed Refrigerant.

Also the axial type LPMR compressor can be upgraded.

Page 10: COMPRESSOR REBUNDLE TO INCREASE LNG PRODUCTION …

Axial compressors are much more complex than centrifugal due to aeromechanics interaction between statoric and

rotoric blades. Axial compressor cannot be designed on custom needs but can only be scaled geometrically up and

down.

One way to slightly increase the flow of an axial compressor is to install and additional stage upstream without

changing the downstream ones.

The new stage must be deeply tested to assess correctly the mechanical behavior and blade frequencies with

wheel box test and ping test as a minimum.

The compressor volume flow can increase by 10-15% with minimum impact on the mechanical behavior and new

rotor can also be fitted inside the existing casing.

Figure 12 – LPMR Compressor upgrade

© 2019 Baker Hughes, a GE company, LLC - All rights reserved.

The main advantage of a new row upstream are:

• +16% design flow (AN200 vs AN200+)

• +12% max flow (from 240k to 270k m3/h .. safety limits)

• IGV more closed on average for same operation … more conservative operation ... beneficial for

VSV life

• Higher efficiency for same operation (+3 efficiency points)

3 C3MR rebundle simulation

We can now apply all the above-mentioned modification to simulate possible advantages for power saving.

Figure 13 – C3MR Compressor train

© 2019 Baker Hughes, a GE company, LLC - All rights reserved.

LPMR ORIGINAL NEW HPMR ORIGINAL NEW

CC

VFD starter/helper

LPMR HPMR

GTCC

VFD starter/helper

GT

C3

Page 11: COMPRESSOR REBUNDLE TO INCREASE LNG PRODUCTION …

DataSheet DataSheet DataSheet DataSheet

POWER [kW]

POWER [kW]

POWER [kW] POWER [kW]

ORIGINAL 45,57 48,525 ORIGINAL 35,28 37,648

UPGRADED 44,864 47,339 UPGRADED 33,642 35,644

EXPECTED SAVING

-1.5% -2.4% EXPECTED SAVING

-4.6% -5.3%

MR TRAIN

ORIGINAL DataSheet

NEW DataSheet

PR ORIGINAL DataSheet

NEW DataSheet

POWER [kW]

POWER [kW]

POWER [kW] POWER [kW]

ORIGINAL 80,85 86,173 ORIGINAL 68,75 N.A.

UPGRADED 78,506 82,983 UPGRADED 62,309 66,040

EXPECTED SAVING

-2.9% -3.7% EXPECTED SAVING

-9.4% N.A.

Table 1 – C3MR power saving with compressor upgrades

4 Seals

Most of the compressors installed worldwide are using statoric seals at impeller in aluminum.

The clearance between stator and rotor is designed to avoid contact allowing a certain leakage coming back from

the impeller discharge. A contact will deform the seal permanently increasing the gap and reducing the compressor

efficiency.

New thermoplastic seals allow the contact between stator and rotor without deformation.

The clearance can be reduced to increase the stage and the overall compressor efficiency from 0.5 to 2 points

depending from flow coefficient.

Geometry is the same, so the thermoplastic seals can easily replace existing aluminum seals during compressor

maintenance.

Figure 14 – Thermoplastic seals

© 2019 Baker Hughes, a GE company, LLC - All rights reserved.

Standard material can reach 150°C maintaining mechanical properties, while to reach higher temperature (>180°C)

more expensive material must be selected.

5 Digital Outages

the Oil and Gas industry is entering in a new digital era. New technologies, tools and faster communication

technologies are now mature to be used during site operation.

These new technologies are including 3D scanning, Virtual Reality or Digital Tools.

Page 12: COMPRESSOR REBUNDLE TO INCREASE LNG PRODUCTION …

3D scan can be used to record the 3D layout of a plant to assess the position of the equipment and optimize the

sequences of activities during maintenance such as installation of lighter crane, EV circulation, parts handling.

The 3D scan can be also utilized to study new way of process piping removal and handling avoiding more intrusive

operation such as enclosure removal or gas turbine inlet handling.

Virtual Reality is more useful to help Field Engineer (FE) to prepare themselves to perform the outage minimizing

dangerous operation or unnecessary activities at site learning by simulation in a real environment.

Next to the virtual reality there are the video field procedure (VFP). Paper manuals are being more and more

dismissed to introduce electronic copies. In addition, short movies are created to show assembly and disassembly

procedure to help FE to work in a safer and productive way.

Field Engineer can also be equipped with state-of-art tools such as smart helmet or Bluetooth gage.

For the first, the field engineer is equipped with a portable Cam that can film what’s happening on the deck and

transmit to a dedicated technical office where another engineer can suggest actions from remote to optimize the

time of the outage.

Figure 15 – Virtual Outage

© 2019 Baker Hughes, a GE company, LLC - All rights reserved.

The Bluetooth gage is a modern tool capable of measuring optically the clearances and record them digitally

without the need of mechanical tools.

All the above technologies can improve the outage activities reducing time and cost, improving health, safety and

quality results

5 Conclusion

Compressor OEM are continuously evolving the equipment design; the evolution is in all areas such as

aerodynamics, mechanics and rotordynamics and is implemented during the design of new plant.

End users can access to these technologies to upgrade their equipment producing more LNG with same plant.

Compressor rebundle is including outages operation; new technologies can help end user to optimize the outages

reducing the time to do it, increasing LNG production.

References

1. Mariani, A., “Enabling Technology for LNG industry”, LNG &GTL: World and Russian Prospects Conference, 2004.

Page 13: COMPRESSOR REBUNDLE TO INCREASE LNG PRODUCTION …

2. Bernocchi, A., Buoncristiano, S., Nuzzi, G., “Technology Evolution of LNG Main Refrigerant Turbocompressors”, APCI Owners’ Seminar VIII, 2003, Hershey, Pennsylvania.

3. Meher-Homji, C.B., Matthews, T., Pelagotti, A., Weyermann, H.P., “Gas Turbines and Turbocompressors for LNG service”, Proceedings of the 36th Turbomachinery Symposium, 2007, Houston, Texas, U.S.A.

4. Arnone, A., Bonaiuti, D., Boncinelli, P., Ermini, M., Milani, A., Baldassarre, L., Camatti, M., “CFD Applications to Industrial Centrifugal Compressor Design”, GT-2002-30393, ASME Turbo Expo 2002, Amsterdam, The Netherlands.

5. Bonaiuti, D., Arnone, A., Ermini, M., Baldassarre, L., “Analysis and Optimization of Transonic Centrifugal Impellers using the Design Of Experiments Technique”, Journal of Turbomachinery, Vol. 128, No.4, 2006. 6. Hohlweg, W., Blahovec, J., Wright, J., “Design Considerations for Centrifugal Compressors in Refrigerations Duty”, AIChE Spring National Meeting, 17th Annual Ethylene Producers’ Conference, 2005, Atlanta, GA, U.S.A.

7. Rotondo, P., Andreo, D., Falomi, S., Jorg, P., Lenzi, A., Hattenbach, T., Fioravanti, D., De Franciscis, S., “Combined Torsional and Electromechanical Analysis of an LNG Compression Train with Variable Speed Drive System”, Proceedings of the 38th Turbomachinery Symposium, 2009, Houston, Texas, U.S.A.

8. Ghizawi N.,Pelagotti A.,Grimaldi A.,Guenard D.,Giachi M. “Compressor Aerodynamic Design for LNG Applications” 3rd Gas Processing Symposium, 2012

9. Pelagotti A. Ermini M “Reliable Innovations on Compressors for LNG Value Chain” 11th Topical Conference on Gas Utilization – AiCHe 2011

10. Pelagotti, A., Toci, E., Nibbelke, R., Bowtell, G., “PLUTO LNG – LNG optimization using existing plant experience”, LNG16, 2010, Oran, Algeria.

11. Pelagotti A. Model Management- LNG Industry - Summer 2007

12. Hardin, James R., 2002, A New Approach to Predicting Centrifugal Compressor Sideload Pressure, @ IMECE2002- 39592, Proceedings of ASME International Mechanical Engineering Congress & Expo, 2002, New Orleans, USA.

13. Sorokes, J.M., Soulas, T., Koch, J.M., Gilarranz, J. L., 2009, Full- Scale. Aerodynamic And Rotordynamic Testing For Large Centrifugal Compressors, @ Proceedings of the Thirty Eighth Turbomachinery Symposium, Turbomachinery Laboratory, Texas A&M University, pp. 71-80.

14. Grimaldi, A., Tapinassi, L., Bernocchi, A., Biagi, F., Guénard, D., and Michelassi, V., 2007, “Impact of Inlet Swirl on High-Speed High-Flow Centrifugal Stage Performance”, ASME-IGTI Turbo-Expo, Paper GT2007-27202, Montreal QC.

15. Musardo,A.,Giovani G.,Pelella M.,Cipriani M., Patel V., Weatherwax M., CO2 Compression at World’s Largest Carbon Dioxide Injection Plant , Proceedings of the 41th Turbomachinery Symposium, 2007, Houston, Texas, U.S.A.

16. Pelagotti A, Baldassarre L., Meher-Homji, C.B., Masani K., FUTURE TRENDS IN LNG TURBOMACHINERY,LNG18, 2016, Perth, Australia

17. Pelagotti A., Mariotti G., Cortese C. GE Oil and Gas Turbo-Compressor Trains on First Floating LNG Plant LNG17 2013 Houston, U.S.A 18. Pelagotti A., Baldassarre L.. Latest Advances in LNG Compressors LNG17 2013 Houston, U.S.A