Coca-Cola’s Atlanta Landfill Gas Cogeneration Project

Richard Crowther – Coca-Cola

1

Page 2: Coca-Cola’s Atlanta Landfill Gas Cogeneration Project · PDF file6 1. Project must deliver net economic savings versus the default energy source 2. Coca-Cola should retain full ownership

Coca-Cola’s Strategic Focus

Page 3: Coca-Cola’s Atlanta Landfill Gas Cogeneration Project · PDF file6 1. Project must deliver net economic savings versus the default energy source 2. Coca-Cola should retain full ownership

3

WATER STEWARDSHIP

SUSTAINABLE PACKAGING

ENERGY & CLIMATE

on Sus t a i nab i l i t y ?

focus Where does Coca -Co l a

Page 4: Coca-Cola’s Atlanta Landfill Gas Cogeneration Project · PDF file6 1. Project must deliver net economic savings versus the default energy source 2. Coca-Cola should retain full ownership

Al te rna t i ve Energy

P r o d u c t D e l i v e r y

F l e e t T r a n s p o r t a t i o n

P r o d u c t i o n E f f i c i e n c y

4 Key Areas for Energy & Climate

Page 5: Coca-Cola’s Atlanta Landfill Gas Cogeneration Project · PDF file6 1. Project must deliver net economic savings versus the default energy source 2. Coca-Cola should retain full ownership

5

Fuel Cells

Bio-Fuels

Solar Power

Cogeneration

Wind

Alternative energy sources considered

Page 6: Coca-Cola’s Atlanta Landfill Gas Cogeneration Project · PDF file6 1. Project must deliver net economic savings versus the default energy source 2. Coca-Cola should retain full ownership

6

1. Project must deliver net economic savings versus the default energy source

2. Coca-Cola should retain full ownership of all “Green” benefits generated

3. Suppliers must guarantee the long-term performance of the projects

4. All analysis must be realistic including tax treatment & inflation factors

6. We do not desire to be power exporters

7. We prefer PPAs style agreements

Our Requirements for Clean Energy Project Development

Page 7: Coca-Cola’s Atlanta Landfill Gas Cogeneration Project · PDF file6 1. Project must deliver net economic savings versus the default energy source 2. Coca-Cola should retain full ownership

Key Project Partners • Mas Energy

• Republic Services

• Atlanta Gas Light

• GE Jenbacher

• Veolia Energy N.A.

• Crowder Construction

6.525 MW combined heat & power plant using landfill gas

• Landfill gas processing

• 6.0 mile dedicated pipeline

• 3 Jenbacher J616 engines

• Heat recovery steam generators

• Steam turbine chiller

• Start-Up 3/2012, 15 months to build

Project Overview

Page 8: Coca-Cola’s Atlanta Landfill Gas Cogeneration Project · PDF file6 1. Project must deliver net economic savings versus the default energy source 2. Coca-Cola should retain full ownership

System Schematic

7 | Page

Appendix A

Cooling&Dehydra on

SiloxaneRemoval

PolishingBed

GasCompressor

2.175MWGen-set

2.175MWGen-set

2.175MWGen-set

HRSG

HRSG

HRSG

1065TonSteam-Driven

Chiller

LandfillGastoExis ngFlare

SiloxaneBedRegen&Destruc onFlare

SteamtoProcess,HVAC

ChilledWatertoProcess,HVAC

6.0mileDedicatedLFGpipelinetoTrigenera onPlant

11,400lb/hourof125psigsteam

ElectricitytoCoca-Cola&GaPower

Page 9: Coca-Cola’s Atlanta Landfill Gas Cogeneration Project · PDF file6 1. Project must deliver net economic savings versus the default energy source 2. Coca-Cola should retain full ownership

Q&A Richard Crowther