39
 2014 Deepak Raj Kurrey APG10910313003 7/7/2014 Chhattisgarh State Power Generation Co. Ltd.

Chhattisgarh State Power Generation Company Limited

Embed Size (px)

DESCRIPTION

This is Chapter 1 of report on "Chhattisgarh State Electricity Board." assigned by Communication Skills Dept., APG Shimla University, Shimla, HP.It may contain some compilation error.

Citation preview

  • 2014

    Deepak Raj Kurrey

    APG10910313003

    7/7/2014

    Chhattisgarh State Power Generation Co. Ltd.

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 5

    Acknowledgement

    This is chapter 1 of the report on Chhattisgarh State Electricity

    Board. The data presented inside the report can be used for information

    and Industrial Report data.

    There may be Compilation Error.

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 6

    Introduction

    Chhattisgarh State Power Generation Co. Ltd. (CSPGCL) is the most important unit of the organization which gives the organization its identity. CSPGCL is the unit which generates electricity for CSEB. It became functional w.e.f. 01.01.2009. This company generates electricity which is further transmitted and distributed.

    The company generates electricity by the following Thermal Power Plant (TPP) Hydel Power Plant (HPP)

    The company has Thermal Power Plants and Hydel Power Plants which provides electricity by means of Coal and Water, the list is given below as on 11-10-2010

    Projects Units & Capacity

    Korba Thermal Power Station (East) 4x50MW 2x120MW Dr. Shyama Prasad Mukherjee Thermal Power Station

    2x250MW

    Hasdeo Thermal Power Station, Korba (West)

    4x120MW

    Korba West Extension Thermal Power Plant 1x500MW Bhoramdev Co-Generation Plant, Kawardha 1x6MW Mini-Mata Hasdeo Bango Hydel Power Station

    3x40MW

    Gangrel Hydel Power Station 4x2.5MW Sikasar Hydel Power Station 2x3.5MW Mini/ Micro Hydel Power Station, Korba (West)

    2x0.85MW

    Total Generation 2424.7MW

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 7

    The major of electricity generation is done by Thermal Power Plant (TPP), and Hydel Power Plant shares a small portion of it.

    One of the TPP is Korba West Extension (1x500MW), which has 4 turbine units to generate 480MW of electricity, but has found that it is generating 20MW more electricity than the actual plan and design. Here is a short technical overview of the plant.

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 8

    Hasdeo Thermal Power Plant 4x120MW, Korba (West)

    Thermal Power Plants generates electricity by the

    means of coal as its main energy generating fuel and water

    as a major driver and controller in electricity generation. We

    will little introduction of the power plants major

    machineries used in Hasdeo Thermal Power Plant.

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 9

    The Major organs of the TPP are as a follows

    Boiler

    Turbine

    Generator

    Water Treatment Plant

    Coal Handling Plant

    Ash Handling System

    Heavy Fuel Oil Handling System

    Compressed Air System

    Equipments Cooling System (Water)

    Diesel Generating Set

    Fire Fighting System

    Air Conditioning System

    Interlocking & Protection

    Here is a short briefing of all the above

    COAL HANDLING PLAN In a TPP, the initial process in

    the power generation is Coal Handling the overall

    processes carried out at a CHP in a coal based thermal power

    generating station or TPP is given in short here.

    Major Factors

    o Coal Companies

    o Transport

    o CHP Equipment Suppliers and Contractors

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 10

    Major Issues

    o Coal Quality

    o Coal Transportation

    o Coal Stock

    o Component Contractors

    Schematic cum Block Diagram of a CHP

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 11

    The basic layout of Coal Handling Plant is shown by block diagram. The coal is unloaded at various unloading station and transported by conveyors to crushing and screening plant via transfer house. After crushing required quantity of coal is transported to bunker via transfer house and remaining coal is stored in stockyard. This coal is reclaimed as per requirement. From the bunker the coal flows through coal mills to boiler furnace. The main aim of CHP to maintain level of coal in bunkers for smooth coal supply to boiler

    There are different streams for transporting of coal. For caring out preventive maintenance schedule one of the stream kept under shutdown. If at the same time breakdown occurs in a machine in other stream, which interrupt the coal supply to boilers. Due this loss of generation will occur.

    A plant, which supply of coal to boilers having capacity of 750 tons per hour failed to fulfill need will loss generation of 0.6 MU for one hour. This cost 1.20 Crore of Rupees.

    Technical Details

    CRUSHER HOUSE

    No. of Crusher Four (4) Nos.

    Type of Crusher Ring Hammer Type

    Capacity 1000 MTPH

    Max. Coal size at inlet 200 mm

    Motor Rating 750 KW

    Belt feeder Nos./capacity 4 Nos./1000 MTPH

    Vibrating feeder Nos./capacity 4 Nos./1000 MTPH

    Feeder size (MM) 7000 x 1600

    TRIPPER

    Total Number 6 Nos.

    Capacity of tripper conveyer 2000 MTPH (each).

    Travel of tripper 165 M.

    Travelling speed 0.3 M/sec.

    Belt speed 3.15 M/sec.

    Motor of tripper 2x5.5 kW

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 12

    SILOS

    Total Nos. 18 Nos.

    Cylindrical portion 9.2 M.

    Conical 3.485 M

    Hyperbolic 3.3 M

    Dia. (internal) 7.0 M (cylindrical)

    TRACK HOPPERS

    No. of Hopper One

    Max. Coal lump size 200 mm

    Paddle feeder capacity 100 MTPH

    CONVEYORS

    Conveyor capacity T/hr. 2000 MTPH

    Belt speed M/Sec. 2.8/3.15 M/Sec.

    Belt Width (Min) 1600 mm

    Boiler In this section, Crushed Coal coming from coal

    handling plant are burnt and water is converted into steam

    of certain pressure which is capable of rotating the turbine

    at 3000 rotation per minute and that is standard speed for

    electricity generation in Indian Standard. Detail of boiler

    used here:

    General Specification Manufacturer M/s BHEL (C.E. Design) Type Balanced Draft, Dry bottom, Single drum Controlled

    Circulation plus. Type of Firing - Oil Ignition Tilting Tangential Minimum load at which steam generator can be operated

    continuously with complete flame, stability without oil support (& MCR) 2 Adjacent, Mills at 50% capacity

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 13

    Minimum load at which the steam generator can be operated continuously with complete flame stability with oil support (% MCR) 20%

    Maximum load for which individual mill beyond which no oil support is required 50%

    Furnace Specification

    Type Controlled Circulation Wall Water Steam cooled Bottom Dry Draft Balanced Tube Arrangement Membrane Explosion/Implosion With stand capacity at 67% Yield point +/-660 mm/wc Residence time for fuel particles in the furnace 3 seconds Effective volume used to calculate the residence time (M3)

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 14

    - 14790 Height from furnace bottom ash hopper to furnace roof (M)

    - 62. 735 Depth (M) - 15.289 Width (M) - 18.034 Furnace projected area (M2) - 7610 Furnace volume (M3) - 14790

    Super Heaters

    LTSH pendant Panel 1

    Platen Horizontal Stage I Type Convection Radiant

    Stage II Stage III

    Radiant Platen (Drainable/Non- drainable) Non --- Non---- Pendant (Drainable/Non-drainable) Drainable ----------- Horizontal LTSH (--do--) Effective heating surface area (m2)/Modified

    5903/12500 1350/1660 1465/1730 Total circumferential heating surface area (m2)

    5703 ----------- ----------- Total Number of Tubes, Tube pitch (mm)

    708 444 408 Parallel to gas flow 101.6 54.00 63.5 Across gas flow 152.4 254.00 762

    Method of Joining long tube

    Total wt. of tubes (T)/modified

    Reheat Emergency temp. Control attemperator

    Type - Spray

    No. of stages of attemperator - One

    Position in the steam circuit - Cold reheats lines

    Specification of the Material - SA - 106 Gr - B

    Spray nozzle Material - SA- 213T & SS Tips

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 15

    Economizer

    Type - Non Steaming

    Water side effective heating - 7810 / 8903.4

    Surface area (M2)/ Modified

    Gas side effective heating/Modified - 10210/14204.4

    Surface area (M2)

    Gas flow path area (M2) - 128

    Design pressure of tubes Kg/Cm2 - 209.8

    OD of Tubes (MM) - 51.00

    Actual thickness tubes (MM) - 5.6

    Length of Tubes (MM) (approx.) - 2, 15,000/2, 45, 100

    Pitch (MM) - 101.6

    Total Wt. of Tubes (Kg.) - 4, 82, 200

    PRESSURES (STEAM & WATER)

    HP Heaters in

    Description Unit ----------------------- HP Heaters

    MCR 88.72% 70.84% 53.59% out

    MCR MCR MCR NCR

    Pressure

    Superheater Outlet kg/cm2 178 176.08 173.5 171.6 176.4

    LTSH Outlet kg/cm2 188.3 184.4 178.9 174.9 185.0

    Drum kg/cm2 193.4 188.4 181.6 176.4 189.3

    Economizer Inlet kg/cm2 197.2 191.9 184.6 179.1 192.9

    Reheater Outlet kg/cm2 43.46 41.05 32.93 24.99 46.60

    Reheater Inlet kg/cm2 45.85 43.20 34.66 26.31 49.00

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 16

    Pressure Drop

    Superheater System kg/cm2 15.4 12.3 8.1 4.80 12.9

    Reheater kg/cm2 2.39 2.15 1.73 1.32 2.40

    Economizer kg/cm2 1.60 1.30 0.80 0.50 1.4

    Excluding static head

    FUEL

    The fuel data on which the guarantees given are as follows:

    Description Unit

    Fuel Design Coal

    Proximate Analysis

    Fixed Carbon % 25.00

    Volatile Matter % 19.00

    Moisture % 12.00

    Ash % 44.00

    Grind ability Index HGI 58

    Higher Heating Value kcal/kg 3500

    Size of coal to mill mm 25

    Turbine In this section, the Heat energy is converted

    into Mechanical Energy (Rotational Energy). The water

    converted into steam is used to rotate the turbine which is

    coupled with a large Alternator.

    General Specification

    Manufacturer : KRAFTWERK UNION, WEST GERMANY Type : Three Cylinder, Reheat, Condensing Turbine Stages : HP 18 Nos. IP 14x2 Nos. LP 6x2 Nos. Nominal Rating : 500 MW Peak Loading : 536.7 MW

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 17

    Rated Speed : 3000 rpm Max/ Min Speed : 3090 / 2850 rpm Speed exclusion range 400 to 2850 rpm.

    Weight (in ton)

    HP IP LP

    a) Rotor : 11.6 21.8 84.6

    b) Cylinder Assembled : 80.0 32.5 86.0

    c) Main stop & control valve : 10

    d) Reheat stop & control valve : 17

    Moments of Inertia (kg/m2)

    a) Rotor of HP Cylinder : 713.0

    b) Rotor of IP Cylinder : 2145.6

    C) Rotor of LP Cylinder : 22981.0

    Shaft Lift pump

    a) Safety Valve Setting : 200/ 180 ata

    b) Pressure limiting valve setting : 180/ 140 ata

    c) Pump starts at a turbine speed of : 540 rpm

    TURBINE OIL PURIFIER SYSTEM

    Centrifuge.

    Max Capacity : 12500 Liters/hr.

    Rated capacity : 8100 liters /hr.

    Speed of bowl : 7605 R.P.M.

    Oil temp. inlet to electric heater : 550C(through regenerative heat

    exchanger)

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 18

    Oil temp. at outlet to electric heater : 650C

    Water temp. in the heater tank. : 90 0C

    GENERATOR In this section, Mechanical energy given to the turbine is converted into Electrical Energy. Here, Turbine rotates the Alternator at 3000 rpm. And electricity is generated of High Ampere. This is later stepped up to high voltage for Transmission using a step-up transformer.

    General Specification

    Make BHEL (KWU) Type THDF 115/59 Code IEC 34-1, VDE 0530 Cooling, stator winding Directly water cooled, Stator core , rotor

    Directly hydrogen cooled.

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 19

    RATING

    Apparent power 588 MVA Active Power 500 MW Power factor 0.85 (lag) Terminal voltage 21 kv permissible variation in + 58 % Voltage. Speed/ Frequency rpm/Hz 3000/50 Stator corrent 16200 Amps.

    Hydrogen pressure kg / cm2 4 Short Circuit Ratio 0.48 field current ( Calculated value) 4040 A Field Voltage 340V Class and type of Insulation MICALSTIC (Similar to class F) No. of terminals brought out 6

    Resistance in ohms at 20oC Stator winding between terminals u-x 0.001414

    v-y 0.0014 17

    w-z 0.001420

    Rotor winding F1- F 2 0.068293

    MAIN EXCITER

    Active Power 3780 KW Current 6300 A Voltage 600 V Speed 3000 rpm.

    Voltage Regulating System

    Type Thyristor 04-2

    Maximum output voltage 250 V

    Output current for field forcing 152 A

    Output current for rated Generator load 88A

    Auxiliary Voltages from three phase supply. 220 V

    Pilot exciter for thyristor sets 400 Hz.

    D. C. Voltage From station for contactors & drives 220V

    Power input continuously < O.1 KW

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 20

    Power input, short time < 1 kw

    DC Voltage from Station battery 2x24 for controls Max. 15 A Positive,

    and regulation Max. 6A negative

    Rated secondary voltage 120v

    Power input of Voltage transformer per phase 2 VA

    Rated secondary current 5 A

    Power input of current transformer per phase 6.5 VA (Plus losses in connecting lead)

    Accuracy of control Better than + - 0.5%

    Setting range of voltage point potentiometer +58 - 15% of nominal generator voltage.

    Setting range of drop compensation or compounding + 0-10% dependent on the and proportional to reactive current* setting of the potentiometer

    ------------------------------------------------------------------------------------------------

    * Direction of reactive current compensating depend on the phase relation which is determined by

    connection of CT's to TVR terminals.

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 21

    TORQUE, CRITICAL SPEEDS

    Maximum short circuit torque of stator at line to line single phase short circuit 1488 kpm

    Moment of inertia of generator shaft 10,000 kgm2 Critical speed (Calculated) nk1 14.4 S-1 (V-GEN)

    nk2 30. 1 S-1 (V-EXC)

    nk3 39.8 S-1 ( S-GEN)

    GENERATOR VOLUME AND FILLING QUANTITIES

    Generator volume (Gas Volume) 80 m3

    CO2 filling quantity *** 160 M3 (STP) *

    H2 filling quantity ** (to 4 bar) 520 M3 (STP) *

    * STP = Standard temperature and pressure. 00C and 1.013 bar to DIN 1343.

    ** Volume required with unit at stand still with the unit on turning gear, the volume will be higher.

    *** CO2 quantity kept on stock must always be sufficient for removal of the existing Hydrogen

    filling. All values are approximate.

    GENERATOR PROTECTIONS

    Generators are high quality machines for securing the best possible continuity of power supply. In addition to a suitable technical design and responsible mode of operation, provision has therefore been made for automatic protection facility the following protections have been provided in the 500 MW T. G.

    1. Generator Differential protection (87G) 2. Generator Low forward power protection ( 37G ) 3. Negative phase sequence protection (46G) 4. Pole slipping protection (98G) 5. Under frequency protection (81G) 6. L.B.B. Protection (50G) 7. Gen field failure protection (40G) 8. Stator Earth fault protection (64 G1 & 64G2) 9. Inter turn fault protection (95 G) 10. Over load protection (51G) 11. Over Voltage protection (59G) 12. Gen. Back up impedance protection (21G)

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 22

    Specification of Transformer

    Generator Transformer

    Manufacturer TOSHIBA

    Nos. of units 10 Nos. (1 0)

    Rating HV & LV (MVA) 200 MVA

    Rated Voltage, HV 420 KV

    Rated Voltage. LV 21 KV

    Rated current, HV 825 Amps

    Rated current, LV 9520 Amps

    No. of phases 1

    Frequency 50 Hz

    Type of cooling OF AF

    Connection symbol when formed a bank YD5

    Impedance at principal tap (75oC) 12.5%

    OFF CKT Tap Changer Tapping in 5 equal steps of 2.5% each

    provided on HV winding to give +5%

    to 5%

    Temperatures rises Variation of high voltage

    o Oil, by thermometer 50oC

    o Winding, by resistance 55oC

    CTI and WTI, auxiliary contacts settings

    o OTI Alarm 85oC

    Trip 90oC

    o WTI Alarm 105oC

    Trip 115oC

    Station Transformer

    Manufacturer HHE

    Nos. off 3

    Capacity 20/35/50 MVA

    Voltage Ratio 33/11.5/6.9 KV

    Vector group DY/nY/n

    Unit Auxiliary Transformer

    Manufacturer HHE

    Nos 6

    Capacity 20/25 KVA

    Voltage Ratio 21/6.9 KV

    Cooling ONAN/ONAF

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 23

    Percentage impedance 8.5%

    C.T. Transformer

    Manufacturer HHE

    Nos. 2

    Capacity 20/25KVA

    Voltage Ratio 33/6.9

    Vector group DY/n

    Percentage impedance 8.5%

    Cooling ONAN/ONAF

    Ash Water Transformer

    Nos. off 2

    Capacity 1250 KVA

    Voltage Ratio 11KV/433V

    Percentage impedance 0.06

    Station Service Transformer

    Make M/s. ASGM Gmbh

    Nos. off 6

    Capacity 1600 KVA

    Voltage Ratio 6.6 KV/0. 433 KV

    Vector group Dynl

    Percentage impedance 0.08 + 10%

    Unit Service Transformer

    Nos. off 6

    Capacity 1600 KVA

    Voltage Ratio 6.6 KV/433 V

    Vector Group DY 1

    Percentage impedance 0.08 + 10%

    TIE TRANSFORMER

    Manufacturer TOSHIBA

    Nos of units ONE

    Rating 55/75 MVA (30)

    Rated Voltage, HV 400 KV

    Rated Voltage. LV 34.5 KV

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 24

    Rated current. HV 1260 Amps

    Rated current, LV 108 Amps

    No. of phases 3

    Frequency 50 Hz

    Type of cooling ONAN/ONAF

    Connection symbol YND11

    Impedance at principle tap 11.74% @750C

    Fuel Oil Service Transformer

    Manufacturer M/s. Ingra

    Nos. off 2

    Capacity 1250 KVA

    Voltage Ratio 11/0. 433 KV

    Vector group DYnl

    Percentage impedance 6%

    WATER TREATMENT PLANT Water quality within powers is of critical importance in maintaining efficient operation and in limiting downtimes due to corrosion or maintenance. The major phases and stages where water quality is measured are discussed in this application note along with the parameters measured. Raw water contains organic matter, inorganic salts, bacteria which need to be

    removed before being fed to the boiler. It follows the three major steps for the purification of raw water

    Disinfection by Chlorination In this stage, microbiological organism is removed from the water before it is further purified or processed.

    Softening of Water In this stage, the hardness producing inorganic materials like Calcium and Magnesium are removed from the water. Because these substance can cause more consumption of fuel, caustic embrittlement of the boiler leading to blast of boiler. Here Lime soda process is followed where calcium is precipitated into

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 25

    carbonates and Magnesium into magnesium hydroxide. These are then settled and filtered.

    Dechlorination of Water It is the process of removing residual chlorine from disinfected wastewater prior to use it. Sulfur dioxide is most commonly used for dechlorination. This is done either by o Carbon bed which is not that much effective, or o Addition of bisulphate, later removed by Anion

    exchange process.

    Block Diagram of a Water Treatment Plant

    The water treatment plant here is established by Driplex Water Engineering.

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 26

    Technical Specification of the Plant as well as its auxiliaries

    Pre-treatment Plant

    Clarifier-cum-Flocculate:

    No. and type One (1)

    Rated effluent flow 3000m3/hr.

    Effluent Turbidity 20 NTU

    Retention Time at rated speed

    Floculation Zone 30 min.

    Classified Zone 2 hrs. 30 min

    O.D. at top 20.6

    Bridge revolving Speed 0.038

    Gravity Filter

    Nos. 2

    Flow rate per filter 300 M3/hr.

    Surface flow rate 4.845 M3/hr/m2

    Filter water reservoir and transfer pump:

    Reservoir Capacity 450 M3

    Nos. of pump 3 working+1

    Standby Capacity of pump 150 M3/hr.

    CHEMICAL DOSING SYSTEM

    Alum Dosing Pump

    Nos. of Tanks 3

    Capacity 8 Hrs. each to clarify

    Strength of solution 10%

    Alum Dosing System

    Type Positive displacement

    Control 0-100% automatically by pneumatic stroke positioned

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 27

    Nos. 2 each of 100% cap.

    Lime Slaking Tank

    Capacity 12 hrs. consumption of clarifiers at 10% strength.

    Nos. 2

    Lime Slurry Transfer Pump

    Nos. 2

    Capacity 4M3/hr.

    Lime Solution Preparation Tank

    Capacity 6 hrs. consumption of clarifier at 6% strength w/v

    strength of solution 6%

    Nos. 4.

    Lime Solution Dosing Pump

    Type positive displacement

    Control 0-100% automatically by pneumatic stroke positioned

    No. 2 each of 100% cap.

    Coagulant aid preparation Tank

    Nos. 2 each of 100% cap.

    Control 0-100% manually by micrometer dial.

    Type Positive displacement type.

    Chlorination System

    Nos. of chlorinators 4

    Capacity 10 Kg/hr

    Type of Injector Vacuum type

    Water Booster pumps 3 Nos. (2 w+1 s) Horizontal, centrifugal type

    DEMINERALIZATION PLANT

    GENERAL

    Nos. of stream 3

    Normal Flow through one stream 130m3/hr

    D.M. water storage tank 3 Nos. of 2000 m3 each

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 28

    ANION EXCHANGER

    No. off/stream 2

    Design flow rate 130 m3/hr.

    Shell lining 4.5 mm thick

    Shell Material IS - 226

    Size WBA 2100 x 4688, SBA 2100 x 5320

    Qty. WBA 4.4 m3 - IRA - 93 RE, SBA 5.17 m3-IRA-40 RC

    Regeneration NAOH

    MIXED BED UNITS

    No. off 3

    Design flow 130 m3/hr.

    Surface flow rate 40 m3/hr/m2

    Material IS-226 shell.

    Resin Cation + Anion 2 M3+ 2m3, IR-120 = MB + IR 402 MB

    REGENERATION SYSTEM

    Storage tanks Acid Alkali

    No. 4 4

    Size Dia & Length 3200 x 6766 mm 3200mm/6760 mm

    Capacity 50 M3 50 M3

    Lining RL-4.5 mm RL 4.5 mm

    Concentration of chemical 30% 48%

    UNLOADING PUMP

    Acid Alkali

    Nos. 2 2 Type Horizontal Horizontal

    Centrifugal Centrifugal

    Capacity 20 M3 20M3

    TDH MWC 10 10

    Neutralization System:

    No. of pits 2

    Capacity 450 M3

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 29

    Recirculation cum disposal pump :

    Nos. 2/pt (Total 4 nos.)

    Capacity 150 M3/hr/at 15 mwc

    Duty 3 hrs. every shift

    D.M. Tanks:

    No. 3

    Capacity 2000 M3 each

    Size 14 M x 14.M - Ht.

    Material MS I. S. - 226.

    Activated Carbon Filter :

    No per stream 1

    Design Flow rate 145 M3/hr.

    Design Surface flow rate 15 M3/hr/m2

    Filled Ht. 1200 MM

    Supporting Material Graded Gravel- 225 mm (Ht.)

    Material of shell IS 2002 Gr. II

    Internal painting epoxy.

    Cation Exchanger:

    No per stream 2

    Design Flow rate 130 M3/hr.

    Design surface flow rate 35 M3/hr/M2

    Filled Ht. WAC-1.00 m, SAC 1.610 M

    Qty. of resin WAC -3.46 M3 m3-IRC-84RF, SAC 5.54 M3-IR-120 RF

    Regeneration by Hydrochloric Acid

    Shell size 2100 mm2 (wac)

    Material of shell IS -226 Rubber Lined.

    Degasser System:

    Nos. of 3

    Type Forced draft type

    Normal Flow rate 130 M3/hr

    Filled Material P.P.N.

    CO2 content in effluent 5 PPM (Max.)

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 30

    Shell material IS 226

    Rubber Lining 4.5 mm thick

    Size 2000 x 5575 ht (Degasser tower)

    Ash Handling Plant Ash is the residue left after the coal is incinerated. In Thermal Power Plants coal is generally used as fuel and hence the ash is produced as the byproduct of Combustion. Ash generated in power plant is about 30-40% of total coal consumption and hence the system is required to handle Ash for its proper utilization or disposal.

    Ash generated in the ESP which got carried out with the flue gas is generally called Fly ash. Around 80% is the value of fly ash generated. It also consists of Air pre heater ash & Economizer ash (it is about 2 % of the total ash content).

    Ash generated below furnace of the steam generator is called the bottom ash. Bottom ash (Bottom ash is 20% of the ash

    generated).

    Schematic Diagram of an Ash Handling Plant

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 31

    The ash handling system handles the ash by bottom ash handling system, coarse ash handling system, fly ash handling system, ash disposal system up to the ash disposal area and water recovery system from ash pond and Bottom ash overflow. Description is as follows:

    Bottom Ash Handling System Bottom ash resulting from the combustion of coal in the boiler shall fall into the over ground, refractory lined, water impounded, maintained level, double V-Section type/ W type steel- fabricated bottom ash hopper having a hold up volume to store bottom ash and economizer ash of maximum allowable condition with the rate specified. The slurry formed shall be transported to slurry sump through pipes.

    Coarse Ash (Economizer Ash) handling System Ash generated in Economizer hoppers shall be evacuated continuously through flushing boxes. Continuous generated Economizer slurry shall be fed by gravity into respective bottom ash hopper pipes with necessary slope.

    Air Pre Heater ash handling system Ash generated from APH hoppers shall be evacuated once in a shift by vacuum conveying system connected with the ESP hopper vacuum conveying system.

    Fly Ash Handling System Fly ash is considered to be collected in ESP Hoppers. Fly ash from ESP hoppers extracted by Vacuum Pumps up to Intermediate Surge Hopper cum Bag Filter for further Dry Conveying to fly ash silo. Under each surge hopper ash vessels shall be connected with Oil free screw compressor for conveying the fly ash from Intermediate Surge Hopper to silo. Total fly ash generated from each unit will be conveyed through streams operating simultaneously and in parallel.

    Ash Slurry Disposal System Bottom Ash slurry, Fly ash slurry and the Coarse Ash slurry shall be pumped from the common ash slurry sump up to the dyke area which is located at a distance from Slurry pump house.

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 32

    Technical Description of Ash Handling System

    HOPPER SPECIFICATION

    S. No. Description Units

    Provided

    per Boiler

    Ash Collection Rate per

    Boiler, Kg/Hr ( Max @

    100% BMCR)

    Holding

    Capacity in

    Hrs.

    1 Furnace bottom ash hopper 1 32800 Not less than

    2 hrs.

    2 Economizer 4 8190 8

    3 A. H. Hopper

    a) Primary

    b) Secondary

    4

    4

    2800

    5310

    8

    8

    4 E. P. Hopper

    1st Row

    2nd Row

    3rd Row

    4th Row

    5th Row

    6th Row

    16

    16

    16

    16

    16

    16

    103000

    17560

    6210

    2555

    1170

    570

    8

    8

    8

    8

    8

    8

    PUMPS SPECIFICATIONS

    L. P. Fly Ash water Pumps

    No. of Pumps : 4

    Location : Ash water pump house

    Capacity : 1100 M3/Hz

    Head : 65 MWC

    Suction : Submerged

    RPM : 1500

    H. P. Fly Ash Water Pump

    No. of Pumps : 3

    Suction : Submerged

    Capacity : 300 M3/Hr

    R.P.M. : 1500 rpm

    Head : 95 MWC

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 33

    Location : Ash water pump house

    Motor : 110 KW

    Seal Water Pump

    Units : 2

    Stand-by : 1 Unit

    Capacity : 100 M3/hr

    Head : 160 MWC

    Type : Centrifugal Pumps

    Location : Inside Ash Slurry Pump House

    R.P.M. : 3000 rpm

    Suction : Flooded

    Motor : 90 KW

    Fly Ash Slurry pump (Refer item for Bottom Ash Slurry Pump)

    No. of pumps Ten (10) size streams (each stream having two pumps in series)

    No. of Unit operation Three (3) streams working and two (2) stand by

    Type Horizontal single stage centrifugal with non-clog impeller

    Location Inside Ash Slurry pump house

    Capacity 1300 M3/Hr

    Head 40 MWC

    Motor 330 KW

    Heavy Fuel Oil Handling System This is the Heart of the boiler of the plant or we can say it is the heart of any fuel based power generation station around the globe. Fuel handling and storage problems can limit the efficiency of the entire boiler.

    SOLID FUELS

    Solid fuels (including coal, wood, and solid waste) present some of the same handling difficulties. Problems occur unless a free-flowing, continuous supply of fuel that is properly sized for the specific type of combustion equipment is provided. The problems include sizing, shredding or pulverizing, consistency of moisture content, freezing or lumping, dusting, fires in storage due to

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 34

    spontaneous combustion, and fires in the feed or ash handling systems.

    Most problems can be minimized or eliminated through proper selection of fuel handling equipment. Specific types of equipment for handling, storage, and preparation depend on the characteristics of the solid fuel used.

    Because the proper equipment is not always available, fuel additives or aids have been used in the attempt to minimize problems. These additives include grinding aids, moisture improvers, dusting aids, freezing inhibitors, and catalysts to minimize combustibles in ash and fly ash handling systems.

    LIQUID FUELS

    Liquid fuels include waste oils, light oils, heavy oils, and other combustible liquids. Because of the problems of liquid residue disposal, an increasing variety of combustible liquids is being considered and tested. Figures 20-1 and 20-2 illustrate key components found in a typical liquid fuel handling system and fuel oil storage system, respectively.

    Problems encountered in the handling, storage, and preparation of liquid fuels include water contamination, sludge formation, resistance to flow, biological growths, instability, and corrosiveness. Generally, these conditions are manifested as excessive strainer plugging, poor flow, increased loading on the fuel pump, heater deposits, fuel line deposits, loss of storage space, burner tip deposits, burner fouling, leakage due to storage tank corrosion, poor atomization, and other combustion problems. Table 20-1 summarizes the nature and cause of problems associated with key liquid fuel handling system components.

    Compressed Air System Air compressors are used to supply process requirements, to operate pneumatic tools and equipment, and to meet instrumentation needs. Only 10-30% of energy reaches the point of end-use, and balance 70-

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 35

    90% of energy of the power of the prime mover being converted to unusable heat energy and to a lesser extent lost in form of friction, misuse and noise. Compressors are broadly classified as: Positive displacement compressor and Dynamic compressor.

    o Positive displacement compressors increase the pressure of the gas by reducing the volume. Positive displacement compressors are further classified as reciprocating and rotary compressors.

    o Dynamic compressors increase the air velocity, which is then converted to increased pressure at the outlet. Dynamic compressors are basically centrifugal compressors and are further classified as radial and axial flow types.

    COMPRESSED AIR SYSTEM

    Manufacturer : Kirloskar Pneumatic

    Model Number : T-BTD-BM

    Type of compressor : Horizontal Balanced Opposed

    Numbers : Eight Units

    Instrument Air : 4 Units.

    Plant Air : 4 Units

    Actual capacity of each compressor : 30.0 Nm3/min

    Discharge pressure Kg/cm2 gauge : 8.0

    Design ambient temperature : 50 deg C

    Design ambient pressure : 0.99753 Kg/cm2

    Design ambient humidity : 100%

    Exact capacity considering worst : 39.05(at45 deg.C&75%RH)

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 36

    EQUIPMENT COOLING SYSTEM Thermoelectric power plants boil water to create steam, which then spins turbines to generate electricity. The heat used to boil water can come from burning of a fuel, from nuclear reactions, or directly from the sun or geothermal heat sources underground. Once steam has passed through a turbine, it must be cooled back into water before it can be reused to produce more electricity. Colder water cools the steam more effectively and allows more efficient electricity generation.

    ECW Pumps (D.M. Water)

    Nos : 3 (1 standby)

    Flow : 2140 M3/hr

    Suction Head : 30 MWC

    Discharge Head : 50 MWC

    MOTOR Rating : 400 KW

    Speed : 985 RPM

    Plate Type Heat Exchanger

    Nos : 2 (1 standard)

    Fluid : Primary - Secondary

    : D.M. Water - Raw water

    In/Out let temp 0C : 44.5/38 - 35/40.92

    Flow rate (M3/hr) : 2140 - 2350

    Equipment Cooling Water Storage Tank

    Elevation : 24.0M

    Capacity : 60 M3 for unit No. 4, 50 M3 for unit 5 & 6

    Diesel Generator Set After a blackout (a near total loss of generation and load) takes place, efforts have to be taken to bring back the system to a normal state at

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 37

    the earliest. It may surprise you to know that this (black starting!) is not an easy task. Once a generator is tripped, restarting it requires a significant amount of power. Power is required for 2 types of activities:

    o Survival Power: For emergency lighting, battery chargers etc. Usually the requirement is 0.3% of the generator capacity.

    o Startup Power: For starting power plant auxiliaries (pumps etc.) Interestingly, nuclear and thermal units require approximately 8 % of the unit capacity for auxiliaries alone! Therefore, a 500 MW generator requires approximately 40 MW for running its auxiliaries.

    Technical Specification

    Manufacturer

    Engine : Kirlosker Cummins

    Alternator & Exciter : NGEF

    Control panel : Control & Switchgear Co. Pvt. Ltd.

    Battery : Exide

    Charge : Logic stat

    Engine

    Rating at site condition : 750 KVA

    Engine type : KTA 3067 G

    RPM : 1500 rpm

    No. of Cylinders arrangement : 16 cylinder 600 Vee.

    Starting time : 30 Sec from Cold

    Governor : PSG Motorised

    Fuel Oil : HSD as per IS: 1460 grade

    Lube Oil : MIL IS2104 C

    Guaranteed fuel oil Consumption at 100% : 150 gms/BHP/hr

    Lub. oil consumption : 0.62 lit/hr

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 38

    Mech. Efficiency : 38%

    Total Weight : 6 Tons

    Alternator

    KW : 600

    KVA : 750

    PF : 0.8

    Stator Current : 1043 A

    Speed : 1500 rpm

    Fire Fighting System Fire is big threat and cause loss to human life and property. However, disasters due to fire normally remains localized to a particular installation until and unless tripping of the entire power plant causes disturbance in the transmission grid by way of over loading and leading to tripping of other power stations/ transmission lines connected with the grid. The most common cause of the fires is known to be electrical short circuits and fire triggered by the inflammable materials. The damages caused by the fire accidents generally take excessive time for restoration. Analysis of causes of fire incidents reveal that majority of the fires could perhaps be prevented and extent of damage minimized, if fire safety measures were strictly enforced. Early detection of fire and swiftness in fighting it can definitely turn major disaster to minor accidents. In power sector accidents taking place on account of human error or due to malfunctioning of any equipment are also causes of crisis situations. In this plant the following equipments are installed for fire-fighting

    Sprinkler System Jockey Pump Hydrant System with Booster Pump

    Air Condition System It is another method equipment cooling in the power station. The major function of air-condition is to optimize the temperature and control

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 39

    the humidity of the Major components as well as of its auxiliaries.

    Compressor

    Main Control Room Esp Control Room

    Maker Kirlosker Pheumatic Co. Kirlosker Pheumatic Co.

    No. off Six (6) Six (6)

    Model AC - 1670 AC - 470

    No. of Cylinders 16 4

    Type Reciprocating Reciprocating

    Refrigerant R-22 R-22

    Type of Cooling Air Cooling Air Cooling

    Condensing temp 20C 4.440C

    Operating RPM 1450. 1250 1000

    Capacity (TR) 136.96,117.19 25.86

    Drive KW at 500C 128.99,111.18 23.27

    Condenser

    No. off Six (6) Six (6) make Kirlosker Pneumatic Co. KirloskerPneumatic Co. Model 500-9, 500-8 250-70 Over all size OD 640X3419, 640x3114 340 x 2275(MM) Shell Thickness mm 8 6.35 Tube Mat. Copper Copper tube Size dia mm 19 19 Tube Thickness mm 1.41 1.41

    Interlocking & Protections

    Air PreHeater Interlocking FD Fan Interlocking ID Fan Interlocking PA Fan Interlocking Scanner Fan Logic Seal Air Fan Logic PUL Reviser CC Pump Protection

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 40

    MFT Conditions Boiler Flame Failure Protection Turbine Protection Generator Protection Earthling and Lightning Protection

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 41

    Introduction: The Hasdeo Bango Hydel Electric Project is situated at village Machadoli, Katghora, Korba at left bank of Hasdeo River. This Project is designed for multipurpose use. The Project was sanctioned by Planning Commission in March 1984. Hasdeo Bango Dam meets the water requirement of Aluminum Plant, SECL, NTPC, CSPGCL, Korba Town and other industrial units.

    Geographical Location: The Hasdeo Bango Hydro Electric Plant is situated at Hasdeo River, the geographical location is at Latitude 223613.69 N & Longitude 823549.95 E [Turbine Floor is at 302.44 Meters from MSL]

    Capacity: Three units of 40 MW each.

    Commissioning dates:

    Unit I - March 1994 Unit II - July 1994 Unit III - November 1994

  • Chapter 1: Chhattisgarh State Power Generation Co. Ltd.

    Communication Skills Report Page 42

    Salient Features:

    Project Cost: Project Cost of Bango Hydel Station was 105.39 Crores (Civil Works: 33.70 Crores, Electrical & Mechanical Works: 71.69 Crores)

    Power Evacuation: The Power is evacuated through 132 KV Korba East, Jamnipali, Manendragarh and Bishrampur feeders.

    Achievements: National Award with Gold Shield by Ministry of Power, Govt. of India in recognition of outstanding performance during the year of 2006-07.